Travel Demand Model Report City of Peterborough Comprehensive Transportation Plan Update Supporting Document

Size: px
Start display at page:

Download "Travel Demand Model Report City of Peterborough Comprehensive Transportation Plan Update Supporting Document"

Transcription

1 Travel Demand Model Report City of Peterborough Comprehensive Transportation Plan Update Supporting Document Prepared for: City of Peterborough and Morrison Hershfield June 2012 Paradigm Transportation Solutions Limited 43 Forest Road Cambridge ON N1S 3B4

2

3 PROJECT SUMMARY PROJECT NAME:... CITY OF PETERBOROUGH COMPREHENSIVE TRANSPORTATION PLAN UPDATE SUPPORTING DOCUMENT TRAVEL DEMAND MODEL REPORT CLIENT:... MORRISON HERSHFIELD LIMITED 2440 DON REID DRIVE OTTAWA ON K1H 1E1 CLIENT PROJECT MANAGER:... BASSAM G. HAMWI, M.ENG., P.ENG.. PRINCIPAL & MANAGER TRANSPORTATION PLANNING PH: FAX: CONSULTANT:... PARADIGM TRANSPORTATION SOLUTIONS LIMITED 43 FOREST ROAD CAMBRIDGE ON N1S 3B4 PH: FAX: CONSULTANT PROJECT MANAGER... JAMES MALLETT, M.A.SC., P.ENG., PTOE REPORT DATE:... JUNE 2012 PROJECT NUMBER:

4

5 EXECUTIVE SUMMARY Paradigm Transportation Solutions Limited has prepared this Transportation Demand Modelling Report on behalf of Morrison Hershfield and the City of Peterborough. Paradigm Transportation solutions was part of the project team headed by Morrison Hershfield that was commissioned by the City of Peterborough to provide and update to the City s 2002 Transportation Master Plan. This report provides an overall review of the current model, its identified limitations, presents a comprehensive plan for addressing these shortcomings. In doing so, the inherent assumptions, procedures and processes used in this update are included. In addition, the report provides information with respect to the model network performance in the planning horizon years establish for the study (2006, 2021 and 2031) Paradigm Transportation Solutions Limited Page i

6

7 CONTENTS 1.0 EXISTING MODEL FRAMEWORK BACKGROUND STUDY GOALS AND OBJECTIVES ESSENTIAL / HIGH PRIORITY DESIRABLE / MEDIUM PRIORITY POTENTIAL FOR FUTURE EXPANSION / LOW PRIORITY MODEL OVERVIEW ASSESSMENT KNOWN ISSUES AND CONSTRAINTS ACTION ITEMS FOR UPDATE MODELLING FRAMEWORK TRIP GENERATION TRIP DISTRIBUTION AND MODE SPLIT TRIP ASSIGNMENT MODELLED SPEEDS MODEL FRAMEWORK ENHANCEMENTS DATA SOURCES TRAFFIC ANALYSIS ZONE RESOLUTION MODEL NETWORK RESOLUTION CENTROID CONNECTORS NETWORK ATTRIBUTES PHYSICAL ATTRIBUTES (LENGTH, LANES, AND POSTED SPEED) FUNCTIONAL CLASSIFICATION AND PLANNING CAPACITY LINK DELAY ESTIMATES MODELLING PROCESS TRANSPORTATION DEMAND MODELLING TRANSPORTATION MODEL OVERVIEW LAND USE DATA SOURCES LIMITATIONS AND ASSUMPTIONS TAZ FRAMEWORK TRIP GENERATION DATA SOURCES METHODOLOGY COMPARISON TO 2002 MODEL TRIP GENERATION RATE COMPARISON CALIBRATION SUMMARY TRIP DISTRIBUTION AND MODE SPLIT DATA SOURCES METHODOLOGY GRAVITY MODEL CALIBRATION MODE SPLIT AND AUTO OCCUPANCY EXTERNAL PASSENGER VEHICLE TRAFFIC DATA SOURCES METHODOLOGY Paradigm Transportation Solutions Limited Page i

8 8.0 MODEL SPEEDS AND VDF EQUATIONS DATA SOURCES METHODOLOGY VDF DEVELOPMENT VDF CALIBRATION AND VALIDATION COMPARISON TO EXISTING VDF FUNCTIONS EXISTING VDF CALIBRATION CONCLUSION ADOPTED VDF ENHANCEMENTS RESULTS ASSIGNMENT METHODOLOGY VALIDATION SYSTEM-WIDE VEHICLE MILES OF TRAVEL (VMT) SYSTEM-WIDE TRAFFIC VOLUMES CORRIDOR VOLUMES LINK-SPECIFIC CALIBRATION MODEL VALIDATION CONCLUSION AND FUTURE ENHANCEMENTS VALIDATION CONCLUSION FUTURE MODEL ENHANCEMENTS TEMPORAL MODELS SPECIAL GENERATORS EXTERNAL TRAVEL DEMANDS BASE YEAR (2006) CONDITIONS DEFICIENCY DEFINITION BASE YEAR (2006) NETWORK PERFORMANCE BASE YEAR (2006) NETWORK LINK DEFICIENCIES LAND USE FORECASTS BACKGROUND POPULATION AND EMPLOYMENT PROJECTIONS FORECAST CONDITIONS TRAVEL DEMAND INCREASES INTERNAL-BASED TRAVEL DEMANDS... ERROR! BOOKMARK NOT DEFINED EXTERNAL TRAVEL DEMANDS TOTAL TRAVEL DEMANDS... ERROR! BOOKMARK NOT DEFINED COMMITTED ROAD NETWORK IMPROVEMENTS... ERROR! BOOKMARK NOT DEFINED FUTURE (2031) NETWORK PERFORMANCE FUTURE (2031) NETWORK PERFORMANCE... ERROR! BOOKMARK NOT DEFINED PERFORMANCE TRENDS Arterial and Collector Performance Trends APPENDICES Appendix A Population and Employment Growth Projections Appendix B Travel Demand Matrices Paradigm Transportation Solutions Limited Page ii

9 FIGURES FIGURE 1.1: CURRENT MODEL LIMITS... 2 FIGURE 2.1: TRAFFIC ANALYSIS ZONES... 9 FIGURE 2.2: MODEL NETWORK FIGURE 2.3: CENTROID CONNECTOR EXAMPLE (DOWNTOWN PETERBOROUGH) FIGURE 3.1: CITY OF PETERBOROUGH MODELLING PROCEDURE Figure 5.1: 2002 Model PM Peak Hour Auto Trip Generation Equations FIGURE 5.2: 2002 MODEL AUTO TRIP GENERATION EQUATIONS VS TTS OBSERVED TRIPS FIGURE 5.3: 2002 MODEL AUTO TRIP GENERATION EQUATIONS VS TTS FIGURE 5.4: COMPARATIVE DIFFERENCES FEBRUARY 2009 AND AUGUST 2009 DATA FIGURE 5.5: 2006 REVISED TRIP GENERATION EQUATIONS VS TTS OBSERVED TRIPS FIGURE 5.6: TOTAL PREDICTED TRIPS VS. TOTAL OBSERVED TRIPS (2006) FIGURE 5.7: TOTAL PREDICTED TRIPS VS. TOTAL OBSERVED TRIPS (PRODUCTIONS AND ATTRACTIONS) FIGURE 5.8: PM PEAK HOUR AUTO TRIP CALIBRATION HBW PRODUCTIONS PREDICTED VS. OBSERVED FIGURE 5.9: PM PEAK HOUR AUTO TRIP CALIBRATION HBW ATTRACTIONS PREDICTED VS. OBSERVED FIGURE 5.10: PM PEAK HOUR AUTO TRIP CALIBRATION HBO PRODUCTIONS PREDICTED VS. OBSERVED FIGURE 5.11: PM PEAK HOUR AUTO TRIP CALIBRATION HBO ATTRACTIONS PREDICTED VS. OBSERVED FIGURE 5.12: PM PEAK HOUR AUTO TRIP CALIBRATION NHB PRODUCTIONS PREDICTED VS. OBSERVED FIGURE 5.13: PM PEAK HOUR AUTO TRIP CALIBRATION NHB ATTRACTIONS PREDICTED VS. OBSERVED FIGURE 6.1: SAMPLE TRAVEL IMPEDANCE FUNCTION FIGURE 8.1: TRAVEL TIME SECTIONS STUDIED FIGURE 8.2: OBSERVED SPEED VS. V/C RATIO FIGURE 8.3: OBSERVED AVERAGE TRAVEL SPEED VS. V/C AND EXISTING VDF FUNCTIONS FIGURE 8.4: OBSERVED AVERAGE TRAVEL SPEED VS. V/C AND VDF FUNCTIONS FIGURE 9.1: PM PEAK HOUR AUTO TRIP CALIBRATION PREDICTED VS. OBSERVED FIGURE 9.2: MAXIMUM ALLOWABLE DEVIATION ACROSS SCREENLINES FIGURE 9.3: SCREENLINES FIGURE 9.4: NORTH-SOUTH SCREENLINE CALIBRATION VOLUMES (PM PEAK HOUR) FIGURE 9.5: EAST-WEST SCREENLINE CALIBRATION FIGURE 11.1: BASE YEAR PERFORMANCE MEASURES FIGURE PM PEAK HOUR NETWORK LOS FIGURE 12.1: SUPER ANALYSIS ZONE (SAZ) STRUCTURE FIGURE 12.2: PROJECTED GROWTH IN POPULATION AND EMPLOYMENT (2006 TO 2031) FIGURE 12.3: RELATIVE GROWTH IN POPULATION AND EMPLOYMENT (2006 TO 2031) FIGURE 12.4: STUDY AREA POPULATION AND EMPLOYMENT TRENDS FIGURE 13.1: 2006 PM PEAK HOUR INTERNAL TRAVEL DEMANDS FIGURE 13.2: 2021 PM PEAK HOUR INTERNAL TRAVEL DEMANDS FIGURE 13.3: 2031 PM PEAK HOUR INTERNAL TRAVEL DEMANDS FIGURE 13.4: 2021 PERFORMANCE MEASURES FIGURE 13.5: 2021 PM PEAK HOUR NETWORK LOS FIGURE 13.6: 2031 PERFORMANCE MEASURES FIGURE 13.7: 2031 PM PEAK HOUR NETWORK LOS FIGURE 13.8: VKMT AND VHT GROWTH TRENDS FIGURE 13.9: ARTERIAL AND COLLECTOR SYSTEM FIGURE 13.10: ARTERIAL AND COLLECTOR PERFORMANCE (VKMT) FIGURE 13.11: ARTERIAL AND COLLECTOR PERFORMANCE (VHT) Paradigm Transportation Solutions Limited Page i

10 TABLES TABLE 2.1: PLANNING CAPACITIES TABLE 2.2: PLANNING CAPACITY ADJUSTMENTS MADE DURING CALIBRATION PROCESS TABLE 2.3: BPR VARIABLES TABLE 6.1: TRIP DISTRIBUTION CALIBRATION TABLE 6.2: MODE SHARE AND AUTO OCCUPANCY TABLE 8.1: AVERAGE LOADED SPEEDS VS. AVERAGE PEAK SPEED WITHIN FUNCTIONAL CLASSIFICATIONS TABLE 11.1: PLANNING CAPACITIES TABLE 11.2: LEVEL-OF-SERVICE AND V/C RELATIONSHIP TABLE 13.1: TOTAL TRAVEL DEMAND INCREASES TABLE 13.2: NETWORK ASSUMPTIONS WITHIN GROWTH AREAS Paradigm Transportation Solutions Limited Page ii

11 1.0 EXISTING MODEL FRAMEWORK 1.1 Background The City of Peterborough (COP) has maintained and continues to refine a transportation planning model which has been used to forecast future travel conditions along the City of Peterborough Roadway System. The model has undergone several revisions since its development in the mid-1980's. In 2003, a City of Peterborough model was developed using TransCAD software based on 1996 weekday PM peak hour conditions. Two horizon years (2011 and 2021) were developed for this model using land use forecasts provided by the City's Planning Department and officially endorsed by City of Peterborough Council. Since the study completion in 2002, the original TransCAD model has undergone revisions and updates. The first revision involved changes to the base assumptions as well as refinement of the modeling procedures in the West-Side corridor Analysis Review in The model remained an automobile-based model. As a result of work performed by the County of Peterborough, refinements were made and the TransCAD model was revised to incorporate additional information related to the County of Peterborough. Finally, the model has been adjusted to reflect the most recent land use forecast prepared by the City s Planning Department. Following this latest revision, travel demand scenarios were developed for 2011, 2021 and Traffic volumes were assigned to the horizon year networks and the resultant traffic volume forecasts were used to determine the travel demands on the Peterborough road network. The City's model has two key components: a supply component (road network) representing the characteristics of all of the significant roadways in the area and a demand component (trip matrix) representing the typical weekday PM peak hour traffic volume that flows through the network. The core area of the model update will be within the boundaries of the model area which extends into the County of Peterborough. However, significant transportation links to other municipalities (external links) are an important part of City's transportation infrastructure. The existing City of Peterborough model coverage shown in Figure 1.1 covers the entire City of Peterborough and includes area municipalities such as Lakefield and Bridgenorth. These municipalities vary from the populated centres with urban intensive features, to the Townships of Ottonabee and South Monaghan with a more rural & pastoral area setting. Tourism, industry and farming, as well as all the natural resources including mineral resources and environmental resources, make up Peterborough's economic diversity. 1.2 Study Goals and Objectives The primary goal of this study is to update the City of Peterborough model such that it can assist in variety of municipal decision making processes. These decision making processes were grouped into three categories based on their level of priority. The three categories are: Essential; Desirable; and Potential for Future Expansion. Paradigm Transportation Solutions Limited Page 1

12 Figure 1.1: Current Model Limits City of Peterborough Limit City of Peterborough Model Update Figure 1.1 Paradigm Model Limits Paradigm Transportation Solutions Limited Page 2

13 1.2.1 Essential / High Priority The ongoing work in Peterborough requires a suitably rigorous travel demand forecasting model that is capable of providing forecasts to be used in the following types of studies: Long Range Transportation Plans - For estimating major corridor deficiencies and- travel demand needs for new major facilities; Land Use and Growth Management Plans - Far evaluating transportation impacts of major changes in future land use and development; Area Municipal Transportation Plans - For determining municipal long range transportation plans; and Transportation Corridor studies - For evaluating alternative solutions within the identified corridor and also for providing sufficient output to aid in design of preferred alternative Desirable / Medium Priority In addition to the above minimum requirement, the ability to provide transportation planning input into the following types of studies is viewed as highly desirable: Traffic lmpact Assessments - For evaluating the impacts of proposed development on existing transportation facilities and services, for identifying improvements to transportation facilities and accommodating travel demands associated with development proposals; Travel Demand Management Strategies - For evaluating alternative methods of reducing or accommodating future travel demands within specified sub areas in Peterborough; Traffic Operational Plans - For evaluating traffic impacts and alternative traffic improvements in sub areas of Peterborough; and Setting of Development Charges - For identifying major improvements required to City of Peterborough road network and for assessing percentage increase in travel demand related to new development in the City and adjacent local municipalities Potential for Future Expansion / Low Priority Consideration to developing modules that could provide information with regard to the following should be given: Transit Plans - For identifying need for services between municipalities and within Peterborough and for providing ridership data for preliminary design of transit services; Air Quality Improvement Strategies - For estimating air quality impacts associated with alternative development and transportation plans and for monitoring changes in traffic and related impacts on air quality; and Emergency Response Planning - For planning alternative routing of traffic in instances where major roads or river crossings may be closed. Paradigm Transportation Solutions Limited Page 3

14 1.3 Model Overview Assessment The City of Peterborough model has undergone a number of transformations/updates since it was first developed. The current model can be likened to a photocopy of a photocopy. That is to say, that with each change/evolution of the modelling framework, some integrity has been lost at each step along the way. Indeed the model has evolved from a rigorous four-step transportation planning model to essentially an assignment tool. Based on this, it is clear that a fresh start approach is required in terms of the modelling framework as the current model does not adequately meet the requirements outlined above. 1.4 Known Issues and Constraints The City of Peterborough model was originally designed to prepare long range transportation plans for the Peterborough area utilizing travel demand forecasts to identify major transportation requirements over a 20-year horizon period. The City identified the following key issues and constraints: Traffic Assignment - Intersection delay is ignored in the current City of Peterborough model. Most traffic assignment procedures assume that delay occurs on the links rather than at the intersections. This is a reasonable assumption for highways and freeways but not for road corridors with extensive signalized intersections. There are a number of signalized intersections within the City of Peterborough model that involve highly complex movements and signal systems. These have been highly simplified in the current model. The current traffic assignment process does not modify control systems in an attempt to reach equilibrium. The use of sophisticated traffic signal systems, freeway ramp metering or enhanced network traffic control is not easily analyzed with conventional traffic assignment procedures. In the past transportation planning model networks were populated with road attribute data manually. This information can now be managed electronically with the added GIS component. Commercial Vehicle Travel - The City of Peterborough Count Program includes collection of detailed vehicle classification data which to date has not been fully utilized in the current City of Peterborough model. The project explored the need to more accurately and reasonably model commercial vehicle travel. Extent of Road Network - The current model assumes that all trips begin and end at a single point in a zone (the centroids) and occurs only on the links included in the model network. Not all roads/streets have been included in the current network nor have all possible trip origins and destinations been included. The current zone/network system is an oversimplification of reality and excludes some travel most notably shorter trips. Over-simplified Roadway Capacities - Determining the capacity of roadways requires a complex process of calculations that consider many factors. Travel forecasts in the City of Peterborough model have been oversimplified. For example, capacity is based only on the number of lanes of a roadway and its type (freeway or arterial). Emphasis on Peak Hour Travel - As mentioned above, forecasts are done for the PM peak hour on a typical weekday. A forecast for the peak hour of the day does not provide any information on what is happening the other 23 hours of the day, in particular during the AM peak hour and the mid-day conditions. A measure of the duration of congestion beyond the peak hour such as "peak spreading" is not determined. Further, travel forecasts are made for an 'average weekday'. Variation in Paradigm Transportation Solutions Limited Page 4

15 travel by time of year (summer vs. typical) or day of the week (weekday vs. weekend) was not currently considered. 1.5 Action Items for Update Based on the model review and the Terms of Reference for the study, the following key elements have been identified as requiring action in this update Modelling Framework The current City of Peterborough model has a number of fundamental features that needed to be reviewed in the project including the Traffic Analysis Zones (TAZ) and network resolution. These are the fundamental building blocks of the model. A well-designed TAZ system and comprehensive network structure (including centroid connectors) can greatly assist in providing reliable and meaningful forecasts. The TOR expressed concern with the current zone system and the state of the network including the coverage of the network and the network link characteristics. Based on the geographical size of City of Peterborough and the level of resolution necessary, it was determined that the TAZ s and network required a critical review and update. There were a number of important items that needed to be given consideration in this review: Longitudinal conformity - It is essential that any new TAZ system that is developed be able to be linked geographically back through the current zone system to provide the City with the ability to monitor changes in travel patterns and demands over time as well as to utilize previous land use and travel demand data. Road Network Complexity - There is an adage in transportation planning that states Travel knows no boundaries. This notion is important when considering the roadway network to be included in the model. In many ways the network that is developed should focus on the demands of the system rather than any self-imposed jurisdictional filter. That is, there may be local roads that are playing an important function and should be included. Similarly, there may be a series of local roads that feed together to load the City of Peterborough road network and should be included as a system rather than being represented by a centroid connector. Road Network Use - Understanding the nature of the road system and how it is used is very important in terms of providing an accurate traffic assignment. As with the above, traffic does not necessarily adhere to an assumed functional classification. For example, there may be links in the network that are classed as local in Official Plans that are performing a major collector function. Also it is important to understand that all arterials are not created equal and the model network needs to reflect this. Roadway Planning Capacity - Coupled with the above is the determination of roadway capacity. The TOR noted that there is perhaps an over-simplified view toward capacity in the current framework. While that may be accurate and should be thoroughly reviewed, there are also important features in the modelling framework such as the Volume-Delay Functions (VDF) and intersection delays that are very important in determining the true capacity of a corridor. In many cases, it is the intersections which govern the throughput of a corridor and it is incumbent upon the modelling framework to accurately reflect these to the maximum extent possible. Paradigm Transportation Solutions Limited Page 5

16 1.5.2 Trip Generation The absence of Trip Generation rates and equations in the current model severely limit the ability of the tool to produce accurate long-term forecasts of demand. The current tool relies on the 1996 Transportation Tomorrow Survey Demand matrices that have been Fratar-balanced into the horizon years. This approach has a number of limitations including: Low Sample - The demand matrix is based on roughly a 4.5% sample and has a significant number of no-observation cells. The Fratar technique cannot create demand; rather it simply factors demand where it exists in the base table. This is reasonable for short-term planning horizons where travel patterns are not likely to change much. It cannot reflect long-term changes in demand resulting from new development patterns, where no demand was observed in the base year without an artificial intervention. Fixed Demand Patterns - This technique is not responsive to reflect the changes in travel demand that might occur as result of infrastructure improvements. For example, the impact of a new arterial link, or improvements to the Highway 115, or other Highways that reduce travel times and therefore make commuting to the GTA from the area a shorter time trip, cannot be reflected by a Fratar-based model. There are other issues that have been identified with travel demand in the TOR that need be given consideration in the model update: Commercial Vehicle Travel: A significant amount of commercial travel demand relies on the Provincial Highway system through Peterborough area. In addition, there are a number of agricultural and industrial developments which generate commercial vehicle travel. Methods of estimating commercial travel demand needs to be considered in the update. Temporal Variation: Understanding time-varying demand is fundamental to understanding how the transportation system is utilized. The role that the transportation planning model can have in this regard needs to be reviewed. Many agencies are now carrying forward both AM peak hour and PM peak hour trip generation functions to attempt to capture the unique issues associated with each peak hour. The current model prepares PM peak hour forecasts which tends to be the highest hour of demand for the majority of the system but may be less accurate in areas of high industrial employment (which tend to have AM peak hour based issues) and high tourist activity (which tend to have Saturday peak hour issues). Tourism: The ability of the current model to accurately reflect peak travel demands in high tourist areas is an area of concern for the transportation planning in the area. The model update must review and consider means to determine whether the modelling tool is the appropriate method in forecasting this demand and secondly how it could get incorporated into the modelling structure Trip Distribution and Mode Split The current model does not employ any gravity-model based trip distribution methods as it relies on the Fratar technique to forecast future demand. Development of trip distribution functions will be required for a full four-step transportation planning model. The TOR also highlights the need to consider the role of mode split in the modelling framework. There are a number of issues that could potentially arise depending upon the approach ultimately undertaken. It is Paradigm Transportation Solutions Limited Page 6

17 recognized that there are specific areas which rely on public transport to provide effective transportation services. The degree to which this will play a role in the ultimate development of the model will need to be addressed in this effort Trip Assignment The current model framework relies on the traditional link-based approach to traffic assignment. This approach uses parameters related to the ratio of volume to capacity to assign delay to the link. This has a number of limitations; the most significant of which is that it ignores the impacts of intersections on capacity and consequently it is difficult to accurately model areas such as downtown Peterborough. The model update considered new and improved methods of estimating delay. This included a detailed review of the VDF functions available in the model. The model update also addresses the issues of advanced assignment techniques which give consideration to intersection delays and turn penalties Modelled Speeds At a project steering committee meeting of January 14, 2010 it was identified by that without confirmed and validated model speed estimation, the full evaluation of some of the parameters proposed for the evaluation of the alternatives could not be included in the benefit-cost analysis proposed for the evaluation of alternatives. At the meeting, it was identified that overall the model speed estimation that resulted from the calibration process to date had shown to well-represent typical conditions in Peterborough based on experience in developing models elsewhere. Despite these findings, the following issues were nonetheless identified: it was felt that the model VDF functions that were currently being used potentially underestimated the impacts of congestion in Peterborough, in particular for instances of high V/C ratios; the VDF functions currently in use within the model and previously used in the development of the 2002 TMP and West Side Analysis were not supportable in that they had not been validated for use in the Peterborough context; there was a desire to be able to forecast link speeds with a reasonable degree of precision to linkspecific segments; and there was a general lack of objective, observed speed data against which the VDF function and areaspecific, and link specific speeds could be tested and validated. It was agreed that in order to provide enhanced assessments of the relationship between speed and congestion in the context of the Peterborough network, it would be necessary to undertake a comprehensive data collection effort couple with detailed analyses of the average and free speed conditions. Paradigm Transportation Solutions Limited Page 7

18 2.0 MODEL FRAMEWORK ENHANCEMENTS This section documents the work undertaken to update the current modelling framework given the goals and objectives identified above, along with the identified issues and constraints. 2.1 Data Sources Within the modelling framework a number of data sources and methods were used in this update: City of Peterborough GIS database City of Peterborough maintains a single-line representation of the entire road network within the City. This is maintained within a Geographic Information System and is tied to a number of information sources which are important to transportation planning; Traffic Count Data The City of Peterborough conducts a comprehensive annual traffic counting program. The data are mapped to the road sections and intersections within the City of GIS structure and include automatic traffic recorder counts, intersection turning movement counts and classification counts; and County of Peterborough Model In cooperation with the City of Peterborough, the County of Peterborough provided its model network files to the project to ensure that the most recent changes completed in its TMP update were reflected in the City s work. 2.2 Traffic Analysis Zone Resolution The existing Traffic Analysis Zone System (TAZ) has been found in practice at City of Peterborough to be too coarse in many cases to provide reliable forecasts at the municipal level. Notable issues with the current TAZ structure included: TAZ boundaries were found to span barriers. While in most cases, these areas were undeveloped and would not generate travel demand, it did not provide adequate flexibility for changes over the long term. Indeed identification of areas that produce little or no trips is as important as those that are high generators; and Known growth areas were typically found to have large zones which would not be capable of reflecting potential future development scenarios without the development of a sub-area model. A comprehensive review of the TAZ framework was undertaken and the structure was modified accordingly. Figure 2.1 illustrates the refined TAZ structure that resulted from this effort. 2.3 Model Network Resolution The development of the TAZ structure described above was in part created through the addition of new roadways to the modelling framework. A thorough review of the entire City of Peterborough roadway infrastructure was undertaken. The City of Peterborough GIS formed that basis on which the model would be constructed. The model framework was developed as the locus of: Paradigm Transportation Solutions Limited Page 8

19 Figure 2.1: Traffic Analysis Zones City of Peterborough Model Update Figure 2.1 Paradigm Traffic Analysis Zones Paradigm Transportation Solutions Limited Page 9

20 All County of Peterborough roads; All City of Peterborough arterial roads; All City of Peterborough collector roads; All important local streets such as those that are effectively performing a function of collector roads; All known future new roads; and Potential roadway patterns in new growth areas. Outside of City of Peterborough, with co-operation from the County of Peterborough the model network was incorporated in its entirety. This provides an important potential policy variable for the City and allows the City to test important provincial policy directives with respect to the impact of new potential transportation corridors on the City of Peterborough road network. For example, the Highway 7 corridor route has been incorporated into the modelling framework to provide the City with information on the potential diversion to the corridor to or from City of Peterborough roads. Figure 2.2 illustrates the refined network structure that resulted from this effort. 2.4 Centroid Connectors As a direct result of the development of the TAZ structure, additional centroid connectors were added to the modeling framework. Coincident with this work, a review of the centroid connectors was undertaken. The following process and generalized rules were applied to the placement of centroid connectors: Centroid connectors should reflect the local road system wherever possible; No centroid connector should be directly connected into an intersection, unless it is representing a local road; In urban areas, centroid connectors should reflect access to and from major parking facilities; The number of centroid connectors should be limited to four for any particular zone, with one or two being preferred. Figure 2.3 provides an example of the assignment of centroid connectors in downtown Peterborough. Paradigm Transportation Solutions Limited Page 10

21 Figure 2.2: Model Network City of Peterborough Model Update Figure 2.2 Paradigm Model Network Paradigm Transportation Solutions Limited Page 11

22 Figure 2.3: Centroid Connector Example (Downtown Peterborough) City of Peterborough Model Update Figure 2.3 Paradigm Centroid Connector Example Downtown Peterborough Paradigm Transportation Solutions Limited Page 12

23 2.5 Network Attributes There are a number of roadway network attributes that are contained in the network file. These have been updated to reflect the nature of the modelling desired within the City. Important attributes include: Link Length the length of the link expressed in kilometres; Direction of Travel a flag used by the model to assist in assignment with 0 representing two-way flow, -1 and 1 representing one-way flow depending on the direction of the link s insertion into the network; Street Name as it appears in the City or County GIS Functional Classification the assigned functional classification (see 2.6.3); Alpha alpha variable in the BPR VDF formulation; Beta - beta variable in the BPR VDF formulation; Posted Speed legal posted speed on the link; User Assigned Free Flow Speed user-defined variable per direction (AB and BA) used to influence assignment; Free Flow Travel Time calculated travel time on link per direction (AB and BA) based on the User Assigned Free Flow Speed used to influence assignment; Number of Lanes number of lanes per direction (AB and BA) in the link; User Assigned Per Lane Capacity - user-defined variable per lane per direction (AB and BA) used to influence assignment; Capacity - calculated variable per direction (AB and BA) used to influence assignment; Existing PM peak hour traffic volumes per direction (AB and BA) as observed in the field Physical Attributes (Length, lanes, and posted speed) The number of travel lanes and posted speed data were obtained directly from the City and County GIS along with the direction of travel. Note one-way links are assigned values of 1 or -1 to indicate one-way travel with respect to the network topology. Link length is automatically calculated within TransCAD based on the Euclidean distance between the endpoints of each line segment. The network is based on the UTM NAD 83 projection contained in the City GIS Functional Classification and Planning Capacity Functional classification in transportation modeling is used to identify not only the intended function of a particular road, but also the actual function. It is important to realize that not arterial roads perform equally and in some cases, it is arguable that collector roads are performing minor arterial function. A thorough review of the network was performed by City staff to assign major and minor function to each of the arterial and collector links within the model framework. Paradigm Transportation Solutions Limited Page 13

24 The planning capacities assigned to each model link are based on the functional classification assigned to each link, along with the area type designation. Table 2.1 summarizes the generalized planning capacities assigned in the City of Peterborough Model. TABLE 2.1: PLANNING CAPACITIES Functional Classification Grade Peterborough WALTS WUTS SEMCOG Region of Waterloo Region of Niagara Region of Ottawa- Carleton Brantford St.Thomas London Freeway Freeway Ramps Fwy. To Arterial n/a Fwy. To Fwy Highway Rural Arterial High Medium Low 600 n/a n/a n/a 650 n/a 600 n/a n/a Collector High Medium n/a n/a Local n/a n/a n/a The entries in the table highlight the intended role of each class of facility within the various area types. For example a two-lane major arterial could carry up to 800 vehicles per lane per hour (e.g. Downtown Peterborough), while in areas such as Downtown Peterborough arterial facilities would only be expected to carry 700 vehicles per lane per hour. The generalized planning capacities noted above were modified during the model calibration process. Table 2.2 summarizes notable changes made during the calibration process along with the rationale for the change. TABLE 2.2: PLANNING CAPACITY ADJUSTMENTS MADE DURING CALIBRATION PROCESS Based Link Adjusted Link No. Street From/to Comment / Explanation Capacity Capacity 1 Parkhill Rd. West Brealey Drive to Wallis Drive 1600 veh/hr 700 veh/hr 2 Parkhill Road West Monaghan Road to Fairbairn Street 1400 veh/hr 1600 veh/hr 3 Monaghan Road McDonnel Street to Parkhill Road 1400 veh/hr 700 veh/hr This section of Parkhill is a two lane rural cross-section equivalent to the road segment west of Brealey. This section of Parkhill immediately east of Monaghan Road over the bridge operates the same as the link to the west. This section of Monaghan Road is striped as and operates as a two-lane facility. It has pavement of a four lane facility but doesn t operate as such. 4 Charlotte Street Monaghan Road to George Street 1400 veh/hr 700veh/hr This section of Charlotte Street operates as a wide two lane road. 5 Sherbrooke Street Glenforest Boulevard to Wallis Drive 800 veh/hr 1600 veh/hr 6 Sherbrooke Street Wallis Drive to Monaghan Road 1600 veh/hr 1400 veh/hr 7 Sherbrooke Street Monaghan Road to George Street 1400 veh/hr 700 veh/hr 8 Hunter Street Alymer Street to George Street 1200 veh/hr 600 veh/hr 9 Hunter Street East George Street to Rogers Street 1400 veh/hr 700 veh/hr 10 Chemong Road Parkhill Road to Sunset Boulevard 1600 veh/hr 1200 veh/hr 11 Chemong Road Towerhill Road to Milroy Drive 800 veh/hr 1600 veh/hr This section of Sherbrooke Street is a four lane arterial with few side street and driveway conflicts. This section of Sherbrooke is four lane but has numerous side street and direct residential driveway interfaces. This section of Sherbrooke Street operates as a wide two lane road. This section of Hunter Street is a two lane facility with on-street parking. This section of Hunter Street is a wide two lane facility with onstreet parking both sides of the road. This section of Chemong Road is base 4 lane however there are no turning lanes, lane geometry is narrow and significant number of uncontrolled commercial accesses. This section of Chemong Road is a four lane arterial with turning lanes at intersections. Paradigm Transportation Solutions Limited Page 14

25 2.5.3 Link Delay Estimates The link performance function is a mathematical representation of the relationship between flow (i.e. traffic volumes and travel cost (i.e. travel time) on any given link in the network. In the case of the City of Peterborough model link delay calculations are based on the BPR formulation. where: t: congested link travel time t f : link free-flow travel time v: link volume c: link planning capacity : calibration parameter : calibration parameter t t f 1 v / c (Equation 1) The BPR formulation is the default link performance function provided in TransCAD. In the case of Peterborough, the and parameters are assigned by functional classification. The default values are 0.15 and 4.00 respectively. To refine the calibration parameters, it was necessary to collect speed and travel time data across the Peterborough network, so that travel speeds could be verified by functional classification and by corridor. In order to calibrate and refine the VDF functions, a comprehensive dataset of traffic operating speeds are required for each functional classification and through a range of V/C values. It was important that data were collected on links that are experiencing as broad a range as possible to ensure that the VDF functions replicate the delay and speed conditions that are occurring on these links. In order that the V/C values could accurately be represented, the measured volumes on the links were used. Overall, data were collected on about 169 km of roadways. To ensure statistical reliability, three days of sampling was undertaken. To improve sampling efficiency, to provide a full range of V/C conditions and to respect timing and budgetary constraints, sampling was undertaken during the AM and PM peak periods. Section 8.0 of the report details the process undertaken to calibrate the VDF functions. Based on the result, the following suggested changes to the modelling framework were made: in general the link free speeds, be set to the average observed speed by functional class grouping (Arterial, Collector, Local), subject to calibration adjustments; and the BPR formulation be implemented such that the alpha constant reflects the function classification under consideration and the exponent on the V/C term remain at 4. Table 2.3 contains the values as assigned by functional classification. The importance of the BPR values is to create congestion on lower class facilities sooner, so that short-cutting is reduced. The shape of the functions creates delay on the lower class roads sooner than for the higher class roads, thus encouraging the assignment of traffic to the higher class facilities wherever possible. Paradigm Transportation Solutions Limited Page 15

26 TABLE 2.3: BPR VARIABLES Class Alpha Beta Freeway/Expressway Arterial Highway (Rural Regional Road) Major Arterial Minor Arterial Major Collector Minor Collector Local Paradigm Transportation Solutions Limited Page 16

27 3.0 MODELLING PROCESS 3.1 Transportation Demand Modelling Transportation demand modelling has a history dating back to the late 1960 s, when the standard fourstage procedure (trip generation, trip distribution, mode split and assignment) was first introduced. These models were initially developed to assist municipalities in dealing with rapid automobile growth and the planning of new roadway infrastructure. In later years, the planning of transit systems became more important, which resulted in advances in transit modelling techniques. The last 40 years has seen much progress, but the basic inputs and outputs have not changed significantly. In general, the model inputs consist of: land use data allocated according to a set of traffic zones; and network data that describe all the physical characteristics of the road links and transit routes that connect these zones. The model outputs include estimates of travel volumes and travel times for: all origin/destination pairs by mode; and each link on the road and transit network. These outputs are used for many transportation-related activities including: strategic planning; transportation demand management analysis; highway and transit project evaluation; traffic and revenue studies; transit route planning and local site impact analysis. Despite the complex mathematical equations employed by the model, they represent a simplification of human travel behaviour. Many of the data inputs as well as the formulas used to estimate travel represent average conditions or behaviour, and cannot hope to replicate the real world in all its detail. Therefore, while the model produces remarkably accurate estimates of travel over the system in general, and reasonable comparisons with observed counts on many individual road and transit links, in some cases there will remain significant variations between observed and estimated values. To some extent, the model accuracy can be improved by introducing site-specific trip generation rates and enhanced traffic zone and network detail. For instance actual traffic attracted to a particular zone may be higher than estimated because the specific type of retail in that zone attracts more trips per foot than the average square foot of retail space. When detailed forecasts are required, a sub-area model can be developed for a specific area or municipality, using the City of model as a starting point. This step will result in improved model accuracy within the sub-area, such that the model outputs can be directly input to other software used for specific applications, such as the design and signal timing of intersections. 3.2 Transportation Model Overview The City of Peterborough transportation model is comprised of three main components: a traffic zone system and associated land use data; a base network; and a four-stage transportation modelling procedure. Paradigm Transportation Solutions Limited Page 17

28 City of Peterborough has been divided into a system of Traffic Analysis Zones (Figure 2.1). The zone size varies according to population and employment densities and geographical features and barriers. The updated TAZ boundaries are coincident with the Traffic Analysis Zones used the previous Transportation Master Plan and thus are a subset of the TAZ s and can be aggregated to compare longitudinal data over time. These boundaries also attempt to adhere to the federal government s census tracts and to municipal boundaries wherever possible. It must be noted that census boundaries are adjusted over time and may in time not remain consistent with these boundaries. Detailed demographic information has been developed for current and future years for each traffic zone. Also included in the zone system are external zones located at entry points to the Peterborough area to account for traffic entering, leaving or passing through the area. The second component is a digital base network that covers City of Peterborough (Figure 2.2). The auto network is comprised of all freeway, arterial and collector facilities within City of Peterborough and County of Peterborough (model the model area). Within the highly urbanized parts of City of Peterborough important local roads are also included. Each auto link contains information on the number of lanes, posted speed limit, and capacity. The digital auto network consists of approximately 1,847 nodes (intersections) and 2,419 links (road segments). The third component is the transportation modelling procedure that predicts the number of auto vehicle trips during the PM peak hour. This procedure is represented schematically in Figure 3.1. This diagram contains three types of boxes, which differentiate between policy input variables, sub-model algorithms and model outputs. The directional arrows indicate the flow of the modelling procedure through a series of sub-models, which are referenced according to the sections in this report. The boxes shaded in yellow represent major sub-models in the transportation demand estimation process, where this is described in more detail in the following sections: Trip Production and Attraction: estimate the number of person trips in each traffic zone for each trip purpose, based upon the population and employment demographics; Mode Split: estimates the mode of choice for a trip for each origin/destination (e.g. walk/bike, transit or auto) by using the relative share of Auto trips compared to Non-Auto trips; Trip Distribution: estimate the trip interchanges, of the number of person trips between zones, based upon trip impedance; Traffic Assignment: based upon the final trip matrices from the mode split stage, this step estimates route choice on the road network. Paradigm Transportation Solutions Limited Page 18

29 Figure 3.1: City of Peterborough Modelling Procedure Land Use Data Trip Production Trip Attraction HBW Prod HBO Prod NHB Prod HBW Attr HBO Attr NHB Attr Trip Balancing Auto Impedance Trip Distribution Total Trips Home-Based Work Home-Based Other Non Home-Based Vehicle Assignment Mode Split Auto Mode Share Auto Person Trips Total Vehicle Trips Auto Trips Auto Occupancy External Auto Trips City of Peterborough Model Update Figure 3.1 Paradigm Peterborough Modelling Procedure Paradigm Transportation Solutions Limited Page 19

30 4.0 LAND USE As outlined above, land use information is one of the primary inputs to the modelling process. It is used to create the projected amount of travel demand produced and attracted to any particular area within the City of Peterborough. This section of the report provides an overview of the demographic information used in this study. 4.1 Data Sources Data used in this update were provided by City of Peterborough Planning staff at the TAZ level and were obtained from the following sources: 2001 Census Canada Data The primary source of demographic (population and employment data) for this study was that which was available from the 2001 Census Canada database. Data provided to the City was made available at the Dissemination Area (DA) level and through GIS allocation procedures were used by planning staff to allocate to the TAZ structure. 4.2 Limitations and Assumptions The population data used in the modelling process is widely considered to be the most reliable source of information available as it is based on a virtually 100% sample. It should be noted that there are known issues with Census Data including: Under-reporting: Experience across Canada has shown that under-reporting of population and employment data does occur. In particular, work at-home, nomadic (no regular place of work or work in several locations) and student population data are affected. It addition, it should be noted that the Statistics Canada employment data is based on a 20% sample as only 1 in 5 households receive the long form census survey which requires detailed employment locations Data Suppression: Statistics Canada applies data suppression policies when the values for population or employment fall below a specified minimum threshold. In the sparsely occupied areas of Peterborough, this can affect the overall distribution of residents and jobs. 4.3 TAZ Framework In the scope of work identified for the project, a refinement of the TAZ structure to provide more refined assignments had been identified as a key deliverable. This process (Section 2.2 and Section 2.3) was seen as important to the overall improvement of the model. At the outset of the project, City of Peterborough Planning staff indicated that provision of population and employment data at any level more discrete than the TAZ structure would not be possible, therefore limiting the ability to provide a more discrete structure. Paradigm Transportation Solutions Limited Page 20

31 5.0 TRIP GENERATION As outlined above, the trip generation modules (productions and attractions) are the first modelling processes. They make use of the land use information to create the projected amount of travel demand produced and attracted to any particular area within the City of Peterborough. This section of the report provides an overview of the trip generation modules contained in the City of Peterborough model. 5.1 Data Sources The trip generation relationships are based on the following data sources: Transportation Tomorrow Survey This information is collected each census year and is based on a telephone survey of residents within the Greater Golden Horseshoe (GGH) area. It provides the City with a 24-hour database of travel patterns for all travel modes and four primary trip purposes; and Demographic Data The population and employment data produced by City of Peterborough staff provide the necessary independent variables for determining the trip generation relationships. In this case the independent variables included total population, total primary employment, total manufacturing employment, total institutional employment and total other employment 5.2 Methodology The trip generation sub-model determines the number of trips produced and attracted by each traffic zone. Separate production and attraction equations were developed for three typical PM peak hour trip purposes: Home-Based Work (HBW) Home-Based Other (HBO) Non Home-Based (NHB) These trip purposes are an aggregation of detailed trip purposes (e.g. work to home, work to dropping off passenger, work to shop) that exhibit common trip characteristics. These trip purposes have similar demographic generators, trip lengths and mode biases. The first step in developing trip generation rates and equations was to test the overall rigour of the data contained in the TTS database. The daily trips per capita were calculated based on the observed trips and the demographic information. Overall the person-trips per capita were estimated to be in the order of 2.5 person-trips per capita and about 6.5 trips per household. When compared to data collected across North America these values were found to be in the order of 8 to 10 person trips per household on a daily basis and 3-4 trips per person during the peak hour. This indicates that the TTS data experiences underreporting of trips in the order of 20-35% compared to experience across North America. Previous documentation in Peterborough indicated that the Data Management Group (DMG) at the University of Toronto who collected this information, has recognized the under-reporting of trips as an issue with the data as far back as Reports prepared for the 1996 survey data and suggest that non-home-based- Work travel was under-reported by 27% to 41% in 1996 which is significant. Another known issue with the TTS data is the temporal distribution of trips. Significant values of the trip making are coded to the quarter-hours. Therefore, determination of a single peak hour is highly sensitive to Paradigm Transportation Solutions Limited Page 21

32 whether a particular 15-minute is included. A common technique to avoid this concern is to use the PM peak period (i.e. 3:00 PM to 6:00 PM) and then apply a peak hour factor to obtain the peak hour data. For the City of Peterborough model, to avoid these two particular issues, the peak period was extended to include all trips coded between 3:44 PM to 5:16 PM. Overall this resulted in 0.30 person trips during the PM peak hour which is consistent with experience elsewhere across North America. Having established that there was sufficient overall trip-making contained in the database, linear regression techniques were used to test the relationship of various independent variables and combinations for each trip purpose. Several combinations of the independent variables, along with geographical stratification (i.e. urban, vs. rural) were assessed to determine which combination of independent variable(s) and geographical stratification provided the most statistically reliable model Comparison to 2002 Model In the 2002 Transportation Master Plan, trip generation functions were developed to produce PM peak hour Auto Driver trips. These were based on the 2001 TTS data. The first step in model calibration was to test these functions against the 2006 TTS data to determine if the functions were still relevant, or in need of an update. Figure 5.1 depicts the PM Peak hour Auto trip Demand production and attraction functions used in the 2002 study for each of the three trip purposes. The demographic data provided by the City in mid-february 2009 were then fed into the trip generation module to produce the estimated trips produced and attracted to each Superzone. The trip generation results were then compared to the data collected in the 2006 TTS. (Figure 5.2) Overall the predicted productions were within 4% of the observed values, while the predicted attractions were within 9%. In each case, there predicted values were underestimated. The industry-accepted measure of the Goodness of Fit of the observed versus the modelled trips is the Coefficient of Determination (R 2 ). The FHWA s Model Validation and Reasonableness Checking Manual 1 (MVRCM) identifies that the Coefficient of Determination (R 2 ) should be greater than In the case of the Peterborough model, the Coefficient of Determination (R 2 ) was calculated to be 0.91 for the overall productions and 0.81 for the overall attractions, indicating a good degree of correlation between the predicted and the observed trips. (Figure 5.3) Based on the reviews of the preliminary results that were provided, it was felt by the project team that additional effort to gain increased precision in the model would be a prudent course of action. As such, additional effort was expended on updating the trip generation functions within the model. The results follow Trip Generation Rate Comparison Using the same process that was followed in the 2002 TMP, automobile trip generation functions were developed for each trip type using the 2006 Transportation Tomorrow Survey Data and the revised demographic data provided by the City in mid-august (Figure 5.4) This process led to improved 1 Model Validation and Reasonableness Checking Manual, FHWA, Barton-Aschman Associates Inc. and Cambridge Systematics Inc., City Staff updated/refined the 2006 base year population and employment data between February 2009 and August 2009 to reflect the City s the Growth Plan Policy initiative which was running contemporaneously with the study at the time. Paradigm Transportation Solutions Limited Page 22

33 overall precision with respect to the Trip Generation Functions. (Figure 5.5) process are discussed below: The results of this Paradigm Transportation Solutions Limited Page 23

34 Figure 5.1: 2002 Model Auto PM Peak Hour Trip Generation Equations HBO Attractions HBO Attractions Population Trips = *Population R-squared = 0.76 HBO Productions HBO Productions Figure Model PM Peak Hour Auto Trip Generation Equations HBW Attractions Paradigm NHB Attractions Employment Trips = *Employment R-squared = 0.63 NHB Attractions Population Trips = *Population R-squared = 0.88 HBW Productions HBW Productions HBW Attractions Employment Trips = *Employment R-squared = 0.87 NHB Productions Employment Population Trips = *Population R-squared = 0.69 Trips = *Employment R-squared = 0.89 NHB Productions City of Peterborough Model Update Paradigm Transportation Solutions Limited Page 24

35 Figure 5.2: 2002 Model Auto Trip Generation Equations vs TTS Observed Trips NHB Model 1, 2 HBW HBO Production Attraction Production Attraction Production Attraction SAZ Pop'n Emp't Pred. Obs. Pred. Obs. Pred. Obs. Pred. Obs. Pred. Obs. Pred. Obs Total Population Estimates for SAZ 1-14 from City of Peterborough staff, from TTS 2 Employment Estimates for SAZ 1-14 from City of Peterborough staff, from 2002 Master Plan with adjustments Figure Auto Trip Generation Equations vs TTS Observed Trips City of Peterborough Transportation Master Plan Paradigm Paradigm Transportation Solutions Limited Page 25

36 Figure 5.3: 2002 Model Auto Trip Generation Equations vs TTS Productions Attractions Coefficient of Determination (R 2 ) = 0.91 Coefficient of Determination (R 2 ) = 0.81 Figure Auto Trip Generation Equations vs TTS City of Peterborough Transportation Master Plan Paradigm Paradigm Transportation Solutions Limited Page 26

37 Figure 5.4: Comparative Differences February 2009 and August 2009 Data SAZ Feb Data Aug Data Absolute Difference Percent Difference Pop'n Emp't Pop'n Emp't Pop'n Emp't Pop'n Emp't % -2.1% % -2.4% % -1.5% % -1.8% % -2.0% % -1.8% % -1.8% % -1.9% % -1.7% % -3.5% % -2.9% % -2.5% % 0.0% % -3.0% % 44.8% % 44.7% % 158.0% % 471.2% % 31.0% Total % 4.1% Figure 5.4 Comparative Differences February 2009 and August 2009 data City of Peterborough Transportation Master Plan Paradigm Paradigm Transportation Solutions Limited Page 27

38 Figure 5.5: 2006 Revised Trip Generation Equations vs Observed TTS SAZ Model Production HBW Attraction HBO Production Attraction NHB Production Attraction Pop'n Emp't Pred. Obs. Diff. Pred. Obs. Diff Pred. Obs. Diff. Pred. Obs. Diff Pred. Obs. Diff. Pred. Obs. Diff Total City of Peterborough Transportation Master Plan Paradigm Figure Revised Auto Trip Generation Equations vs TTS Observed Trips Paradigm Transportation Solutions Limited Page 28

39 Overall Fit Overall the predicted productions were within 0% of the observed values, while the predicted attractions were within 0%. The Coefficient of Determination (R 2 ) overall was calculated to be (Figure 5.6) For the trip productions, the value was calculated to be 0.91 for the overall productions and 0.97 for the overall attractions, indicating a very high degree of correlation between the predicted and the observed trips. (Figure 5.7) Home Based Work (HBW) A number of model constructs were tested to determine of the good-of-fit measures previous observed could be improved. The HBW productions were determined to be statistically related to both population and employment. The following equations were developed: HBW (productions) = (Employment) (Population) HBW (attractions) = (Population) (Employment) Scattergram plots of the predicted versus observed values for the productions (Figure 5.8) and attractions (Figure 5.9) were prepared. The purpose of the exercised was to identify the closeness to the line X=Y that the data fell to identify the overall goodness of fit and identify any outliers. The graphics indicate a high degree of correlation between the predicted and observed values. The Coefficient of Determination for the productions was 0.94, while for the attractions it was HBO A number of model constructs were tested to determine of the good-of-fit measures previous observed could be improved. The HBO productions were determined to be statistically related to both population and employment. The following equations were developed: HBO (productions) = (Employment) (Population) HBO (attractions) = (Population) (Employment) Scattergram plots of the predicted versus observed values for the productions (Figure 5.10) and attractions (Figure 5.11) were prepared. The purpose of the exercised was to identify the closeness to the line X=Y that the data fell to identify the overall goodness of fit and identify any outliers. The graphics indicate a high degree of correlation between the predicted and observed values. The Coefficient of Determination for the productions was 0.89, while for the attractions it was NHB A number of model constructs were tested to determine of the good-of-fit measures previous observed could be improved. The NHB productions were determined to be statistically related to both population and employment. The following equations were developed: NHB (productions) = (Employment) (Population) NHB (attractions) = (Population) (Employment) Scattergram plots of the predicted versus observed values for the productions (Figure 5.12) and attractions (Figure 5.13) were prepared. The purpose of the exercised was to identify the closeness to the line X=Y that the data fell to identify the overall goodness of fit and identify any outliers. The graphics indicate a high degree of correlation between the predicted and observed values. The Coefficient of Determination for the productions was 0.69, while for the attractions it was Paradigm Transportation Solutions Limited Page 29

40 Figure 5.6: Total Predicted Trips vs. Total Observed Trips (2006) 8000 Coefficient of Determination (R 2 ) = Figure 5.6 City of Peterborough Transportation Master Plan Total Predicted Trips vs. Total Observed Trips (2006) Paradigm Paradigm Transportation Solutions Limited Page 30

41 Figure 5.7: Total Predicted Trips vs. Total Observed Trips (Productions and Attractions) Productions Attractions Coefficient of Determination (R 2 ) = 0.91 Coefficient of Determination (R 2 ) = 0.97 City of Peterborough Transportation Master Plan Paradigm Figure 5.7 Total Predicted Trips vs. Total Observed Trips Productions and Attractions Paradigm Transportation Solutions Limited Page 31

42 Figure 5.8: PM Peak Hour Auto Trip Calibration HBW Productions Predicted vs. Observed Coefficient of Determination (R 2 ) = Figure 5.8 PM Peak Hour Auto Trip Calibration HBW Productions Predicted vs. Observed City of Peterborough Transportation Master Plan Paradigm Paradigm Transportation Solutions Limited Page 32

43 Figure 5.9: PM Peak Hour Auto Trip Calibration HBW Attractions Predicted vs. Observed Coefficient of Determination (R 2 ) = Figure 5.9 PM Peak Hour Auto Trip Calibration HBW Attractions Predicted vs. Observed City of Peterborough Transportation Master Plan Paradigm Paradigm Transportation Solutions Limited Page 33

44 Figure 5.10: PM Peak Hour Auto Trip Calibration HBO Productions Predicted vs. Observed Coefficient of Determination (R 2 ) = Figure 5.10 PM Peak Hour Auto Trip Calibration HBO Productions Predicted vs. Observed City of Peterborough Transportation Master Plan Paradigm Paradigm Transportation Solutions Limited Page 34

45 Figure 5.11: PM Peak Hour Auto Trip Calibration HBO Attractions Predicted vs. Observed Coefficient of Determination (R 2 ) = Figure 5.11 PM Peak Hour Auto Trip Calibration HBO Attractions Predicted vs. Observed City of Peterborough Transportation Master Plan Paradigm Paradigm Transportation Solutions Limited Page 35

46 Figure 5.12: PM Peak Hour Auto Trip Calibration NHB Productions Predicted vs. Observed 1600 Coefficient of Determination (R 2 ) = City of Peterborough Transportation Master Plan Paradigm Figure 5.12 PM Peak Hour Auto Trip Calibration NHB Productions Predicted vs. Observed Paradigm Transportation Solutions Limited Page 36

47 Figure 5.13: PM Peak Hour Auto Trip Calibration NHB Attractions Predicted vs. Observed 1600 Coefficient of Determination (R 2 ) = City of Peterborough Transportation Master Plan Paradigm Figure 5.13 PM Peak Hour Auto Trip Calibration NHB Attractions Predicted vs. Observed Paradigm Transportation Solutions Limited Page 37

48 5.3 Trip Generation Calibration Summary The trip generation equations were generally overall found to have the highest reliability on the attraction side. The HBO attraction equation had an R 2 value of 0.96 and while the HBW attraction equation had an R 2 value of NHB trips were generally found to have poor fits to the independent variables. The total amount of trips predicted on the attraction side was found to be virtually replicating the observed trips. Therefore, trip balancing to the attraction side was determined to provide the best results. Paradigm Transportation Solutions Limited Page 38

49 6.0 TRIP DISTRIBUTION AND MODE SPLIT As outlined above, the trip distribution module is used to allocate trips between all origins and destinations. They are generally based on a gravity model formulation, which is based on Sir Isaac Newton s Law of Universal Gravitation. The fundamental nature of the equation indicates that the relative attractiveness of any two zones is directly proportional to the population and employment in each zone and inversely proportional to the travel time separating them. This section of the report provides an overview of the trip distribution modules contained in the City of Peterborough model. 6.1 Data Sources The trip distribution relationships are based on the following data sources: Transportation Tomorrow Survey This information is collected each census year and is based on a telephone survey of residents within the Greater Golden Horseshoe (GGH) area. It provides the City with a 24-hour database of travel patterns for all travel modes and four primary trip purposes. 6.2 Methodology The most common method of distributing trips between any two given TAZ s used in transportation planning is the gravity model. The essence of the model is that the relative attractiveness of any two given TAZ s is directly proportional to the cross product of a measure of the propensity to create trips and inversely proportional to an impedance function. This is based on Sir Isaac Newton s Law of Universal Gravitation: Within the Peterborough modelling process, the trip distribution module estimates the number of person trips travelling between OD pairs for each trip purpose (HBW, HBO, NHB). The trip distribution models are developed for internal trip-making and do not include trips that originate or are destined to areas outside the City of Peterborough. A separate external trip matrix has is added to the final internal auto matrix prior to assignment. (see Section 7.0) Internal trip distribution is a multi-step process that starts with the calculation of travel impedances (or travel time in this case) between OD pairs. The impedance matrices are then used to calculate friction factors, which describe the propensity to travel between different locations. Friction factors are calculated for each trip purpose as they exhibit different trip length characteristics. A balancing algorithm is used to implement the gravity models and convert the trip production and attraction vectors into full OD matrices. Travel impedance is based on the travel time (including link delay and intersection delay) between any given two zones. Auto impedances were developed for each trip purpose for the City of Peterborough model. These impedances were then used to calibrate gravity models for each trip purpose. Gravity models are used to distribute the production and attraction vectors between OD pairs. The friction factors take the form of a negative exponential equation. The functions are calibrated to the Trip Length Distribution (TLD) curves for each trip purpose. As these values become less negative, the average trip lengths increase as illustrated in Figure 6.1. Paradigm Transportation Solutions Limited Page 39

50 Figure 6.1: Example of Gravity Model Travel Impedance Function Fij Factor Combined Travel Impedance (min) Figure 6.1 City of Peterborough Transportation Master Plan Sample Travel Impedance Function Paradigm Paradigm Transportation Solutions Limited Page 40

51 Individual trip purpose matrices are then computed using the two-dimensional, or doubly constrained balancing procedures in TransCAD. Inputs to the gravity models include the balanced production and attraction vectors and the friction matrices. Each trip purpose is subject to the same iterative balancing process. The results of this sub-model are four trip purpose matrices that describe the travel between all origins and destinations. 6.3 Gravity Model Calibration Calibrating the gravity model consists of evaluating the parameters of the impedance function (or the values in the friction factor table) so that the gravity model reproduces, as closely as possible, the base year productions and/or attractions and the base year trip length distribution. TransCAD provides a procedure that calibrates a friction factor lookup table, a K-Factor matrix, and exponential, inverse power, and gamma impedance functions. Regardless of the model being calibrated, the calibration procedure requires: a base year P-A matrix; a base year impedance matrix; and a zone layer All of the calibration procedures use the base year P-A matrix and the impedance matrix to generate the Observed Trip Length Distribution (OTLD), and the aim is to calibrate the model such that this OTLD is reproduced as closely as possible. Table 6.1 shows the average calibrated trip lengths using the trip distribution parameters and friction factors developed for City of Peterborough. The calibrated parameters by purpose are: HBW HBO NHB The entries in the table indicate that the functions are able to replicate the average trip lengths to within about 1.16% or about 15 seconds for HBW trips and to within 1/100 th of a minute for the other two trip types. TABLE 6.1: TRIP DISTRIBUTION CALIBRATION Trip Type Observed Average Travel Time (min) Predicted Average Travel Time (min) Difference (%) Home Based Work (HBW) % Home Based Other (HBO) % Non Home Based (NHB) % Paradigm Transportation Solutions Limited Page 41

52 Another measure of the accuracy of the distribution model is to compare the trip length frequency distributions of the estimated person trips from the model to the observed person trips from the household survey. The coincidence ratio is one such measure. The coincidence ratio is the ratio in common between two distributions as a percentage of the total area of those distributions. In general, the coincidence ratio measures the percent of the area that coincides between the two curves. This ratio for each trip purpose should be at least 60 percent. For Peterborough, all purposes exceed the 60 percent target. 6.4 Mode Split and Auto Occupancy Given the dominance and ubiquitous use of the auto share in City of Peterborough, the development of a mode split model was not deemed to be worthwhile and was outside the TOR for the study. Therefore, the resulting person trip demands were then converted to vehicle trips through the application of global auto person trip share and auto occupancy factors which were calculated from the TTS database. (Table 6.2) TABLE 6.2: MODE SHARE AND AUTO OCCUPANCY Purpose % Auto Persons Auto - Occupancy HBW 94.9% 1.03 HBO 91.7% 1.24 NHB 98.1% 1.14 Paradigm Transportation Solutions Limited Page 42

53 7.0 EXTERNAL PASSENGER VEHICLE TRAFFIC Passenger travel demand to, from and through Peterborough area is an important component of the traffic flows on the City of Peterborough road system. These data were collected from a number of sources and as illustrated in Figure 3.3 were added to the internally generated travel demands to complete the passenger travel demand matrices. 7.1 Data Sources Transportation Tomorrow Survey Data Travel demand to and from the west of Peterborough was supplemented with the O-D information available in the TTS database. 7.2 Methodology The above data sources provided the combined Internal-to-External (I-X), External-to-Internal (X-I) and External-to-External (X-X) travel demand portions of the travel matrices. These demands were subsequently added to the Internal-to-Internal (I-I) travel demands from the trip distribution and model split modules to complete the auto demand matrices. These data sources were used in the following manner: the TTS data were processed so that the origin-destination location information was consistent with the updated TAZs and both were imported into TransCAD matrices. Paradigm Transportation Solutions Limited Page 43

54 8.0 MODEL SPEEDS AND VDF EQUATIONS Through the modelling process enhancements to the Volume-Delay Functions and Model Speed estimation were made. These are described below. 8.1 Data Sources In order to calibrate and refine the VDF functions, a comprehensive dataset of traffic operating speeds was required for each functional classification and through a range of V/C values. It was important that data were collected on links that are experiencing as broad a range as possible to ensure that the VDF functions replicate the delay and speed conditions that are occurring on these links. In order that the V/C values were accurately represented, the measured volumes on the links were used. Figure 8.1 illustrates the location of 2008/2009 ATR data that was provided by the City of Peterborough. In addition, the red links illustrate the links measured for overall travel time (which included delay experienced at intersections) and mid-block operating speeds (a measure of free-flow speed). Overall, data were collected on about 169 km of roadways which was down as follows: Freeway Ramp Freeway Arterial Collector Local Private 1.9 km 13.5 km 89.3 km 48.8 km 14.3 km 1.0 km Given that there was an assumed average operating speed of about 40 km /h and that some deadheading was required to accomplish efficient routing of the network, it required about 4.5 hours to complete the sample the entire proposed network. To ensure statistical reliability, three days of sampling was undertaken. To improve sampling efficiency, to provide a full range of V/C conditions and to respect timing and budgetary constraints, sampling was undertaken during the AM and PM peak periods. 8.2 Methodology The data collected were used in a two-fold purpose. Firstly, the average travel speed which gives consideration to delay experienced at intersections was plotted against the V/C ratio measured for the section and used in the model. The link-based BPR functions were reviewed against these plots to determine if the BPR function is indeed the most applicable given the observed shapes of the delay curves. Where necessary, further assessment of BPR, Conical, Logit-Based, Acelik and generalized cost functions were conducted to determine if the shape of the observed volume-delay relationship better followed other curves. Following this assessment, the VDF functions were re-calibrated to the observed data to a statistically-valid degree. In addition to the above, the observed mid-block (undelayed) operating speeds were used as a surrogate for the free flow speeds (desired undelayed travelling speed) that are desired on the links. This method improved the overall estimates of delay using the refined VDF functions and contemporaneously refines the network assignment. Subsequently, for each roadway segment, the average loaded travel speed (one that Paradigm Transportation Solutions Limited Page 44

55 gives consideration to the delays experienced at intersections) were then compared to the calculated V/C ratio and plotted against the VDF functions that have been used in the model development. The average loaded speed by functional class from above was used as the starting speed for each functional class. Paradigm Transportation Solutions Limited Page 45

56 Figure 8.1: Travel Time Sections Studied Legend ATR Traffic Data Collected in 2008/09 Proposed Travel Time and Travel Speed Measurement Location City of Peterborough Model Update Figure 8.1 Paradigm Travel Time Sections Studied Paradigm Transportation Solutions Limited Page 46

57 8.3 VDF Development Figure 8.2 illustrates the scattergram of the overall average loaded speeds compared to the V/C ratio calculated for the roadway segment. Note that the V/C ratios are calculated based on the respective hourly volume that was provided for each of the 2009 ATR locations provided. That is, if the speed sample was measured at 2:30 PM, the volume data associated to 2:30 PM were used to calculate the V/C ratios. The assumed capacity for the link under question was extracted for the model. The information presented in Figure 8.2 shows that there is generally a wide variation in the average travel speed that is occurring on the links across all V/C values. However, there was a general trend of decreasing average speed with increasing V/C. The trend line shown on the graph generally indicates that the average travel speed reduces by about 0.7 km/h for each 0.1 change in V/C. 8.4 VDF Calibration and Validation The data collected for each roadway segment were reduced to extract the average travel time (including delays at intersections) and the average peak mid-block speed. Table 8.1 summarizes these two measures by functional classification. The entries in Table 8.1 show that: The overall average travel speed was 43.5 km/h, while the average peak speed was more than 53 km/h, or about 22% (10 km/h) higher; The average travel speed generally reflected the pattern of decreasing overall average speed with decreasing functional classification; and The average loaded speeds were generally lower than those suggested by the current model calibration. TABLE 8.1: AVERAGE LOADED SPEEDS VS. AVERAGE PEAK SPEED WITHIN FUNCTIONAL CLASSIFICATIONS Functional Class Average Average Travel Speed Peak Speed Freeway Average Highway Average High Capacity Arterial Average Medium Capacity Arterial Average Low capacity Arterial Average High Capacity Collector Average Low Capacity Collector Average Local Average Grand Average Paradigm Transportation Solutions Limited Page 47

58 Figure 8.2: Observed Speed vs. V/C Ratio Average Loaded Speed (km/h) y = x R² = V/C Ratio City of Peterborough Model Update Figure 8.2 Paradigm Observed Speed vs. V/C Ratio Paradigm Transportation Solutions Limited Page 48

59 8.4.1 Comparison to Existing VDF Functions The above data were then re-evaluated to determine the average loaded travel speed compared to the V/C ratio and plotted against the VDF functions that have been used in the model development. Figure 8.3 illustrates the average loaded speeds compared to the V/C ratio calculated for the roadway segment. The calculated average loaded speed by functional class from above was used as the starting speed for each functional class. The following observations are noted: the shape of the VDF function generally follows the observed average loaded speed pattern albeit it appears to be slightly flatter; and it appears that the effect of congestion begins to affect average loaded travel speed by a V/C of about Existing VDF Calibration Conclusion Based on the foregoing, it is concluded that: the average speeds within the current model are higher than those observed, indicating that global reductions in the free speeds are warranted; the existing model VDF functions generally well-represent the observed Speed-Delay relationships; potential improvements to the VDF function include improving the sensitivity to V/C to begin closer to a V/C of 0.3 and flattening of the VDF curve Adopted VDF Enhancements Based on the foregoing, the following are suggested changes to the modelling framework: in general the link free speeds, be set to the average observed speed by functional class grouping (Arterial, Collector, Local), subject to calibration adjustments; and the BPR formulation be implemented such that the alpha constant reflects the function classification under consideration and the exponent on the V/C term remain at 4. (Figure 8.4). 8.5 Results In the redevelopment of the Volume-Delay Functions, data were collected with respect to the average loaded travel speed. This information was used to refine the VDF equations within the model. The resultant model loaded speeds compare as follows: Overall the average loaded speed is within 9% of the observed average mid-block speed; For arterial roads, the average loaded speeds are within 12-15% of the observed average mid-block speeds; and For collector roads, the average loaded speeds are within 12-20% of the observed average mid-block speeds. Paradigm Transportation Solutions Limited Page 49

60 Figure 8.3: Observed Average Travel Speed vs. V/C and Existing VDF Functions Loaded Speed (km/h) High Capacity Arterial Medium Capacity Arterial Low Capacity Arterial High Capacity Collector Low Capacity Collector Local Observed Arterial Observed Collector V/C Ratio City of Peterborough Model Update Figure 8.3 Paradigm Observed Average Travel Speed vs. V/C and Existing VDF Functions Paradigm Transportation Solutions Limited Page 50

61 Figure 8.4: Observed Average Travel Speed vs. V/C and Adopted VDF Functions Loaded Speed (km/h) High Capacity Arterial Medium Capacity Arterial Low Capacity Arterial High Capacity Collector Low Capacity Collector Local Observed Arterial Observed Collector V/C Ratio City of Peterborough TMP Figure 8.4 Paradigm Observed Average Travel Speed vs. V/C and VDF Functions Paradigm Transportation Solutions Limited Page 51

62 9.0 ASSIGNMENT The final step in the modelling process is to assign the assembled auto vehicle demands to the roadway networks. The following describes this process. 9.1 Methodology The vehicle assignment sub-model determines the actual path taken by the vehicle trips. The main inputs to this step are the auto trip matrices and the road network. The following are traffic assignment methods encountered in transportation planning practice, all of which are available in TransCAD: All-or-Nothing Assignment (AON) - Under All-or-Nothing Assignment, all traffic flows between O-D pairs are assigned to the shortest paths connecting the origins and destinations. This model is unrealistic in that only one path between every O-D pair is used, even if there is another path with the same or nearly the same travel time or cost. Also, traffic on links is assigned without considering whether or not there is adequate capacity or heavy congestion; travel time is a fixed input and does not vary depending on the congestion on a link. Stochastic Assignment The assignment method distributes trips between O-D pairs among multiple alternative paths that connect the O-D pairs. The proportion of trips that is assigned to a particular path equals the choice probability for that path, which is calculated by a Logit route choice model. This method does not assign trips to all the alternative paths, but only to paths containing links that are considered "reasonable." A reasonable link is one that takes the traveler farther away from the origin and/or closer to the destination. The link travel time in this method is a fixed input and is not dependent on link volume. Consequently, the method is not an equilibrium method. Incremental Assignment - Incremental Assignment is a process in which fractions of traffic volumes are assigned in steps. In each step, a fixed proportion of total demand is assigned, based on All-or-Nothing Assignment. After each step, link travel times are recalculated based on link volumes. When there are many increments used, the flows may resemble an equilibrium assignment; however, this method does not yield an equilibrium solution. Consequently, there will be inconsistencies between link volumes and travel times that can lead to errors in evaluation measures. Also, Incremental Assignment is influenced by the order in which volumes for O-D pairs are assigned, raising the possibility of additional bias in the results. Capacity Restraint - Capacity Restraint attempts to approximate an equilibrium solution by iterating between all-or-nothing traffic loadings and recalculating link travel times based on a congestion function that reflects link capacity. Unfortunately, this method does not converge and can flip-flop back and forth in the loadings on some links. The capacity restraint method as implemented in some software packages attempts to lessen this problem by smoothing the travel times and by averaging the flows over a set of the last iterations. This method does not converge to an equilibrium solution and has the additional problem that the results are highly dependent on the specific number of iterations run. Performing one more or one less iteration usually changes the results substantially. User Equilibrium (UE) - User Equilibrium uses an iterative process to achieve a convergent solution, in which no travelers can improve their travel times by shifting routes. In each iteration network link flows are computed, which incorporate link capacity restraint effects and flow-dependent travel times. Stochastic User Equilibrium (SUE) - Stochastic User Equilibrium is a generalization of user equilibrium that assumes travelers do not have perfect information concerning network attributes and/or they Paradigm Transportation Solutions Limited Page 52

63 perceive travel costs in different ways. SUE assignments produce more realistic results than the deterministic UE model, because SUE permits use of less attractive as well as the most-attractive routes. Less-attractive routes will have lower utilization, but will not have zero flow as they do under UE. System Optimum Assignment (SO) - System Optimum Assignment computes an assignment that minimizes total travel time on the network. Under SO Assignment, no users can change routes without increasing their total travel time on the system, although it is possible that travelers could reduce their own travel times. This method can be thought of as a model in which congestion is minimized when travelers are told which routes to use. Based on experience in developing hundreds of models across North America, the User Equilibrium process models across has been found to provide the most reliable means of assigning trips. This step is implemented in TransCAD using the built-in assignment procedure User Equilibrium Assignment. This method is an iterative process. The first iteration loads trips on the shortest path between origin and destination and travel times are calculated based on the link volume delay functions. The next iteration reassigns a percentage of the trips to a second optimal path and so on until the network is in a state of equilibrium (usually requiring iterations). Outputs from this stage include: origin/destination travel times, link travel times, link speeds and link volumes for autos. 9.2 Validation When validating the model s assignment, reliance was placed on the FHWA s Model Validation and Reasonableness Checking Manual 3 (MVRCM) to provide guidance with respect to the acceptable precision of the assignment modules within the planning model. Accordingly, assignment validation targets were set on three increasingly detailed levels of precision: System-wide (VMT and Volumes); Corridor Volumes (Screenlines); and Link Specific Volumes System-Wide Vehicle Miles of Travel (VMT) When evaluating the accuracy of the assignment, the first check was observed versus modelled Vehicle Miles of Travel (VMT). VMT is the product of the link volume and the link distance, summed over the desired geographic area and facility types. The observed VMT is a product of a comprehensive traffic count program. Since not every link in the network was counted for the validation year, estimates of observed VMT were developed. In the case of the Peterborough model, the primary source of observed VMT is the traffic count database maintained by City staff. It is important to note that these data have been used as provided to the project team. No attempts have been made to rationalize the count data between stations along arterials, or to normalize the data into a consistent weekday PM peak hour (e.g. Thursday PM peak hour in October). 3 Model Validation and Reasonableness Checking Manual, FHWA, Barton-Aschman Associates Inc. and Cambridge Systematics Inc., Paradigm Transportation Solutions Limited Page 53

64 It is important to note that a cursory review of the data has indicated that within individual count locations there is significant variation in the traffic counts within the data. In some cases this variations was observed to be as much as 30%. This variation can affect the assessment of the calibration, particularly at the screenline and link level. Further, data provided by City staff represented a sampling of about 250 locations within the City. According to the MVRCM, the modelled VMT should be within 5% of the observed VKMT on a network level. The observed traffic count data is insufficient to provide an overall assessment of the VKMT as the counts only cover about 9% of the estimated VKMT in the network. Nonetheless to assess the model s performance comparisons were made where observed data were available. The MVRCM also suggests that VKMT breakdown for populations such as Peterborough is typically as follows: Freeway/Expressway 33-38%; Major Arterial 27-33%; Minor Arterial 18-22%; and Collectors 8-12%. In the case of the Peterborough model, the VMT breakdown in the count data provided does not follow this distribution. It should be noted however, that these are based on that travel patterns in American cities where they have a more developed freeway network for commuter traffic. Peterborough also has an overall lower density than many similar size populations in the US. Overall the modelled VKMT for the all functional classes is within 1.5% of the observed VKMT. More specifically, the modelled VKMT for the arterial functional classes which comprise 73% of the model network is within 2.2% of the observed VKMT. Medium capacity arterials which comprise 62% of the model network are calibrated within 0.5% of the observed VKMT System-Wide Traffic Volumes Consistent with the MVRCM, the next level of validation of the highway assignment is the comparison of observed versus estimated traffic volume on the highway network. As noted above, the observed count data were derived from the traffic count data provided by the City. As indicated in the MVRCM, traffic volumes were validated at the system-wide level by first comparing the overall assignment performance The first level of validation was to compare observed versus estimated volumes for all links with counts. To compare the system-wide assignment performance, a scattergram of the counts versus the assigned volumes was prepared. The degree to which the scattergram follows a 45-degree line (i.e. observed = estimated) is a measure of the ability of the model to replicate the observed volumes. Figure 9.1 indicates that in the case of the Peterborough model, the observed and predicted volumes generally follow a 45-degree line. The industry-accepted measure of the Goodness of Fit of the observed versus the modelled volumes is the Coefficient of Determination (R 2 ). The MVRCM identifies that the Coefficient of Determination (R 2 ) should be greater than In the case of the Peterborough model, the Coefficient of Determination (R 2 ) was Paradigm Transportation Solutions Limited Page 54

65 calculated to be 0.89, which exceeds this value indicating a strong degree of correlation between the modelled volumes and the observed traffic counts. Paradigm Transportation Solutions Limited Page 55

66 Figure 9.1: Scattergram Plot of Observed vs. Predicted Directional Volumes (PM Peak Hour) R 2 = Modelled Observed Figure 9.1 PM Peak Hour Auto Trip Calibration Predicted vs. Observed City of Peterborough Transportation Master Plan Paradigm Paradigm Transportation Solutions Limited Page 56

67 Another important industry-accepted measure of the Goodness of Fit of the modelled volumes compare to the observed traffic volumes is the Root Mean Square Error (RMSE). This value is calculated as follows: The MVRCM does not provide strict guidelines with respect to the % RMSE values, though it is generally accepted that % RMSE values for models should be in the order of 35%. Referring to assignment results the % RMSE for the entire network is calculated at 30% which is consistent with these targets. In terms of absolute volumes, the average loading compared to the average count indicated that volumes were predicted within 9-38 vehicles per direction (varies by direction) on high capacity arterial sections which is excellent, vehicles per direction (varies by direction) on medium capacity arterial sections which is very good and within vehicles per direction (varies by direction) on low capacity arterial sections, which is also very good. Accuracy on the high capacity collectors was acceptable with the average error being vehicles per direction (varies by direction) on and excellent on low capacity collectors with the average error being vehicles per direction (varies by direction). On average across all functional classifications, the volumes were predicted within vehicles per direction (varies by direction), which is very good. Therefore, based on the requirements outlined above, the system-wide calibration met FHWA and industrystandard requirements both in terms of VMT and traffic volumes Corridor Volumes Having satisfied the overall system-wide calibration targets, the next level of investigation carried out was at screenlines. Typically, screenlines run across the model from edge to edge with sub-groupings referred to as cut lines. In the case of Peterborough, a combination of screenlines and cutlines were used. The MVRCM provides guidance with respect to ADT volumes across screenlines and the maximum allowable deviation permitted. Figure 9.2 illustrates that lower volume screenlines have a higher allowable deviation (> 50%) than do higher volume screenlines (20%). Various agencies have established differing degrees of precision with respect to screenline assignments. For example, the State of Michigan uses 10% at screenlines for its statewide model. In the case of Peterborough, the MVRCM method targets which are based on the volume at the screen line were used to determine the acceptability of the assignment using the PM peak hour volumes rather than the ADT volumes and assuming the same relationship applies to the peak hour values. For Peterborough, seven screenlines were developed to verify the model assignment. Figure 9.3 illustrates the three screenlines used to verify north-south flows through the City (100, 300 and 500) and east-west through various sections of the City (200, 400, 600, 800 and 1000). Figure 9.4 illustrates the screenline calibration across the screenlines running east-west across the City which monitor the north-south flows. Overall the screenline located north of Parkhill Road (Screenline 100) was calibrated within 7-10% of the of the observed traffic volumes which is very good. All links meet the maximum allowable deviation criteria, except University Road southbound. Ackison Road and University Road experience among the highest deviations. Within this screenline, there appears to be overassignment on George Street. Paradigm Transportation Solutions Limited Page 57

68 Figure 9.2: Maximum Allowable Deviation Across Screenlines Source: NCHRP 255 p.41 (cited in FHWA, Calibration and Adjustment of System Planning Models, Dec. 1990) Figure 9.2 City of Peterborough Transportation Master Plan Maximum Allowable Deviation Across Screenlines Paradigm Paradigm Transportation Solutions Limited Page 58

69 Figure 9.3: Screenlines Figure 9.3 Screenlines City of Peterborough Transportation Master Plan Paradigm Paradigm Transportation Solutions Limited Page 59

APPENDIX IV MODELLING

APPENDIX IV MODELLING APPENDIX IV MODELLING Kingston Transportation Master Plan Final Report, July 2004 Appendix IV: Modelling i TABLE OF CONTENTS Page 1.0 INTRODUCTION... 1 2.0 OBJECTIVE... 1 3.0 URBAN TRANSPORTATION MODELLING

More information

3.0 ANALYSIS OF FUTURE TRANSPORTATION NEEDS

3.0 ANALYSIS OF FUTURE TRANSPORTATION NEEDS 3.0 ANALYSIS OF FUTURE TRANSPORTATION NEEDS In order to better determine future roadway expansion and connectivity needs, future population growth and land development patterns were analyzed as part of

More information

Appendixx C Travel Demand Model Development and Forecasting Lubbock Outer Route Study June 2014

Appendixx C Travel Demand Model Development and Forecasting Lubbock Outer Route Study June 2014 Appendix C Travel Demand Model Development and Forecasting Lubbock Outer Route Study June 2014 CONTENTS List of Figures-... 3 List of Tables... 4 Introduction... 1 Application of the Lubbock Travel Demand

More information

TRAVEL DEMAND MODEL. Chapter 6

TRAVEL DEMAND MODEL. Chapter 6 Chapter 6 TRAVEL DEMAND MODEL As a component of the Teller County Transportation Plan development, a computerized travel demand model was developed. The model was utilized for development of the Transportation

More information

2015 Grand Forks East Grand Forks TDM

2015 Grand Forks East Grand Forks TDM GRAND FORKS EAST GRAND FORKS 2015 TRAVEL DEMAND MODEL UPDATE DRAFT REPORT To the Grand Forks East Grand Forks MPO October 2017 Diomo Motuba, PhD & Muhammad Asif Khan (PhD Candidate) Advanced Traffic Analysis

More information

Appendix B. Durham Region Travel Demand Model Calibration

Appendix B. Durham Region Travel Demand Model Calibration Appendix B Durham Region Travel Demand Model Calibration AECOM 300 Water Street 905 668 9363 tel Whitby, ON, Canada L1N 9J2 905 668 0221 fax www.aecom.com To Ron Albright, Municipality of Clarington Page

More information

6 th Line Municipal Class Environmental Assessment

6 th Line Municipal Class Environmental Assessment 6 th Line Municipal Class Environmental Assessment County Road 27 to St John s Road Town of Innisfil, ON September 6, 2016 APPENDIX L: TRAVEL DEMAND FORECASTING MEMORANDUM Accessible formats are available

More information

Technical Memorandum #2 Future Conditions

Technical Memorandum #2 Future Conditions Technical Memorandum #2 Future Conditions To: Dan Farnsworth Transportation Planner Fargo-Moorhead Metro Council of Governments From: Rick Gunderson, PE Josh Hinds PE, PTOE Houston Engineering, Inc. Subject:

More information

Changes in the Spatial Distribution of Mobile Source Emissions due to the Interactions between Land-use and Regional Transportation Systems

Changes in the Spatial Distribution of Mobile Source Emissions due to the Interactions between Land-use and Regional Transportation Systems Changes in the Spatial Distribution of Mobile Source Emissions due to the Interactions between Land-use and Regional Transportation Systems A Framework for Analysis Urban Transportation Center University

More information

APPENDIX G Halton Region Transportation Model

APPENDIX G Halton Region Transportation Model APPENDIX G Halton Region Transportation Model Halton Region Transportation Master Plan Working Paper No. 1 - Legislative Context Working Paper No. 2 - Active Transportation Halton Transportation Model

More information

III. FORECASTED GROWTH

III. FORECASTED GROWTH III. FORECASTED GROWTH In order to properly identify potential improvement projects that will be required for the transportation system in Milliken, it is important to first understand the nature and volume

More information

2014 Certification Review Regional Data & Modeling

2014 Certification Review Regional Data & Modeling 2014 Certification Review Regional Data & Modeling July 22, 2014 Regional Data Census Program Coordination PAG works with and for member agencies to ensure full participation in all Census Bureau programs

More information

Appendix C Final Methods and Assumptions for Forecasting Traffic Volumes

Appendix C Final Methods and Assumptions for Forecasting Traffic Volumes Fairview Ave. and Main St. Improvements and Local Streets Plan Appendices Ada County Highway District Appendix C Final Methods and Assumptions for Forecasting Traffic Volumes January 3, 207 Appendices

More information

Metrolinx Transit Accessibility/Connectivity Toolkit

Metrolinx Transit Accessibility/Connectivity Toolkit Metrolinx Transit Accessibility/Connectivity Toolkit Christopher Livett, MSc Transportation Planning Analyst Research and Planning Analytics Tweet about this presentation #TransitGIS OUTLINE 1. Who is

More information

APPENDIX I: Traffic Forecasting Model and Assumptions

APPENDIX I: Traffic Forecasting Model and Assumptions APPENDIX I: Traffic Forecasting Model and Assumptions Appendix I reports on the assumptions and traffic model specifications that were developed to support the Reaffirmation of the 2040 Long Range Plan.

More information

Date: March 31, 2014 PATE; fyril 2.3,2 >H

Date: March 31, 2014 PATE; fyril 2.3,2 >H aj BRAMPTON fifs Rower City XH-l-f r.t "»* City Council The Corporation of the City of Brampton SRAMPTON CITY COUNCIL Date: March 31, 2014 PATE; fyril 2.3,2 >H File: POO GR VisWhtoJed ^t'th-meeh'^a Subject:

More information

StanCOG Transportation Model Program. General Summary

StanCOG Transportation Model Program. General Summary StanCOG Transportation Model Program Adopted By the StanCOG Policy Board March 17, 2010 What are Transportation Models? General Summary Transportation Models are technical planning and decision support

More information

Douglas County/Carson City Travel Demand Model

Douglas County/Carson City Travel Demand Model Douglas County/Carson City Travel Demand Model FINAL REPORT Nevada Department of Transportation Douglas County Prepared by Parsons May 2007 May 2007 CONTENTS 1. INTRODUCTION... 1 2. DEMOGRAPHIC INFORMATION...

More information

Palmerston North Area Traffic Model

Palmerston North Area Traffic Model Palmerston North Area Traffic Model Presentation to IPWEA 7 November 2014 PNATM Presentation Overview Model Scope and type Data collected The model Forecasting inputs Applications PNCC Aims and Objectives

More information

Expanding the GSATS Model Area into

Expanding the GSATS Model Area into Appendix A Expanding the GSATS Model Area into North Carolina Jluy, 2011 Table of Contents LONG-RANGE TRANSPORTATION PLAN UPDATE 1. Introduction... 1 1.1 Background... 1 1.2 Existing Northern Extent of

More information

COUNCIL POLICY MANUAL

COUNCIL POLICY MANUAL COUNCIL POLICY MANUAL SECTION: PUBLIC WORKS SUBJECT: SNOW & ICE CONTROL POLICY 2012/2013 GOAL: Pages: 1 of 10 Approval Date: Dec. 3, 2012 Res. # 1001/2012 To annually identify the winter maintenance costs

More information

Data Collection. Lecture Notes in Transportation Systems Engineering. Prof. Tom V. Mathew. 1 Overview 1

Data Collection. Lecture Notes in Transportation Systems Engineering. Prof. Tom V. Mathew. 1 Overview 1 Data Collection Lecture Notes in Transportation Systems Engineering Prof. Tom V. Mathew Contents 1 Overview 1 2 Survey design 2 2.1 Information needed................................. 2 2.2 Study area.....................................

More information

HORIZON 2030: Land Use & Transportation November 2005

HORIZON 2030: Land Use & Transportation November 2005 PROJECTS Land Use An important component of the Horizon transportation planning process involved reviewing the area s comprehensive land use plans to ensure consistency between them and the longrange transportation

More information

CIV3703 Transport Engineering. Module 2 Transport Modelling

CIV3703 Transport Engineering. Module 2 Transport Modelling CIV3703 Transport Engineering Module Transport Modelling Objectives Upon successful completion of this module you should be able to: carry out trip generation calculations using linear regression and category

More information

Market Street PDP. Nassau County, Florida. Transportation Impact Analysis. VHB/Vanasse Hangen Brustlin, Inc. Nassau County Growth Management

Market Street PDP. Nassau County, Florida. Transportation Impact Analysis. VHB/Vanasse Hangen Brustlin, Inc. Nassau County Growth Management Transportation Impact Analysis Market Street PDP Nassau County, Florida Submitted to Nassau County Growth Management Prepared for TerraPointe Services, Inc. Prepared by VHB/Vanasse Hangen Brustlin, Inc.

More information

SBCAG Travel Model Upgrade Project 3rd Model TAC Meeting. Jim Lam, Stewart Berry, Srini Sundaram, Caliper Corporation December.

SBCAG Travel Model Upgrade Project 3rd Model TAC Meeting. Jim Lam, Stewart Berry, Srini Sundaram, Caliper Corporation December. SBCAG Travel Model Upgrade Project 3rd Model TAC Meeting Jim Lam, Stewart Berry, Srini Sundaram, Caliper Corporation December. 7, 2011 1 Outline Model TAZs Highway and Transit Networks Land Use Database

More information

BROOKINGS May

BROOKINGS May Appendix 1. Technical Methodology This study combines detailed data on transit systems, demographics, and employment to determine the accessibility of jobs via transit within and across the country s 100

More information

Updating the Urban Boundary and Functional Classification of New Jersey Roadways using 2010 Census data

Updating the Urban Boundary and Functional Classification of New Jersey Roadways using 2010 Census data Updating the Urban Boundary and Functional Classification of New Jersey Roadways using 2010 Census data By: Glenn Locke, GISP, PMP 1 GIS-T May, 2013 Presentation Overview Purpose of Project Methodology

More information

Typical information required from the data collection can be grouped into four categories, enumerated as below.

Typical information required from the data collection can be grouped into four categories, enumerated as below. Chapter 6 Data Collection 6.1 Overview The four-stage modeling, an important tool for forecasting future demand and performance of a transportation system, was developed for evaluating large-scale infrastructure

More information

NATHAN HALE HIGH SCHOOL PARKING AND TRAFFIC ANALYSIS. Table of Contents

NATHAN HALE HIGH SCHOOL PARKING AND TRAFFIC ANALYSIS. Table of Contents Parking and Traffic Analysis Seattle, WA Prepared for: URS Corporation 1501 4th Avenue, Suite 1400 Seattle, WA 98101-1616 Prepared by: Mirai Transportation Planning & Engineering 11410 NE 122nd Way, Suite

More information

WOODRUFF ROAD CORRIDOR ORIGIN-DESTINATION ANALYSIS

WOODRUFF ROAD CORRIDOR ORIGIN-DESTINATION ANALYSIS 2018 WOODRUFF ROAD CORRIDOR ORIGIN-DESTINATION ANALYSIS Introduction Woodruff Road is the main road to and through the commercial area in Greenville, South Carolina. Businesses along the corridor have

More information

Traffic Demand Forecast

Traffic Demand Forecast Chapter 5 Traffic Demand Forecast One of the important objectives of traffic demand forecast in a transportation master plan study is to examine the concepts and policies in proposed plans by numerically

More information

Encapsulating Urban Traffic Rhythms into Road Networks

Encapsulating Urban Traffic Rhythms into Road Networks Encapsulating Urban Traffic Rhythms into Road Networks Junjie Wang +, Dong Wei +, Kun He, Hang Gong, Pu Wang * School of Traffic and Transportation Engineering, Central South University, Changsha, Hunan,

More information

Appendix B. Traffic Analysis Report

Appendix B. Traffic Analysis Report Appendix B Traffic Analysis Report Report No. 14369/TR/WN02 August 2007 SALLINS BYPASS BYPASS OPTIONEERING ANALYSIS - TRAFFIC REPORT Kildare County Council Áras Chill Dara, Devoy Park, Naas, Co Kildare

More information

Appendix B. Land Use and Traffic Modeling Documentation

Appendix B. Land Use and Traffic Modeling Documentation Appendix B Land Use and Traffic Modeling Documentation Technical Memorandum Planning Level Traffic for Northridge Sub-Area Study Office of Statewide Planning and Research Modeling & Forecasting Section

More information

Visitor Flows Model for Queensland a new approach

Visitor Flows Model for Queensland a new approach Visitor Flows Model for Queensland a new approach Jason. van Paassen 1, Mark. Olsen 2 1 Parsons Brinckerhoff Australia Pty Ltd, Brisbane, QLD, Australia 2 Tourism Queensland, Brisbane, QLD, Australia 1

More information

Trip Generation Model Development for Albany

Trip Generation Model Development for Albany Trip Generation Model Development for Albany Hui (Clare) Yu Department for Planning and Infrastructure Email: hui.yu@dpi.wa.gov.au and Peter Lawrence Department for Planning and Infrastructure Email: lawrence.peter@dpi.wa.gov.au

More information

Mapping Accessibility Over Time

Mapping Accessibility Over Time Journal of Maps, 2006, 76-87 Mapping Accessibility Over Time AHMED EL-GENEIDY and DAVID LEVINSON University of Minnesota, 500 Pillsbury Drive S.E., Minneapolis, MN 55455, USA; geneidy@umn.edu (Received

More information

I. M. Schoeman North West University, South Africa. Abstract

I. M. Schoeman North West University, South Africa. Abstract Urban Transport XX 607 Land use and transportation integration within the greater area of the North West University (Potchefstroom Campus), South Africa: problems, prospects and solutions I. M. Schoeman

More information

Prepared for: San Diego Association Of Governments 401 B Street, Suite 800 San Diego, California 92101

Prepared for: San Diego Association Of Governments 401 B Street, Suite 800 San Diego, California 92101 Activity-Based Travel Model Validation for 2012 Using Series 13 Data: Coordinated Travel Regional Activity Based Modeling Platform (CT-RAMP) for San Diego County Prepared for: San Diego Association Of

More information

OREGON POPULATION FORECAST PROGRAM

OREGON POPULATION FORECAST PROGRAM OREGON POPULATION FORECAST PROGRAM PROGRAM OVERVIEW BACKGROUND Beginning in 1973 with the passage of Senate Bill (SB) 100, Oregon s growth management system has relied on population forecasts as the primary

More information

A Method for Mapping Settlement Area Boundaries in the Greater Golden Horseshoe

A Method for Mapping Settlement Area Boundaries in the Greater Golden Horseshoe A Method for Mapping Settlement Area Boundaries in the Greater Golden Horseshoe Purpose This paper describes a method for mapping and measuring the lands designated for growth and urban expansion in the

More information

Regional Performance Measures

Regional Performance Measures G Performance Measures Regional Performance Measures Introduction This appendix highlights the performance of the MTP/SCS for 2035. The performance of the Revenue Constrained network also is compared to

More information

March 31, diversity. density. 4 D Model Development. submitted to: design. submitted by: destination

March 31, diversity. density. 4 D Model Development. submitted to: design. submitted by: destination March 31, 2010 diversity density 4 D Model Development submitted to: design submitted by: destination 4 D Model Development Team SANDAG: Mike Calandra Rick Curry Rob Rundle Parsons Brinckerhoff: Bill Davidson

More information

Regional Performance Measures

Regional Performance Measures G Performance Measures Regional Performance Measures Introduction This appendix highlights the performance of the MTP/SCS for 2035. The performance of the Revenue Constrained network also is compared to

More information

FHWA Peer Exchange Meeting on Transportation Systems Management during Inclement Weather

FHWA Peer Exchange Meeting on Transportation Systems Management during Inclement Weather Travel Demand Modeling & Simulation at GBNRTC Matt Grabau Kimberly Smith Mike Davis Why Model? Travel modeling is a tool for transportation planners and policy makers, to observe impacts of a transportation

More information

Developing and Validating Regional Travel Forecasting Models with CTPP Data: MAG Experience

Developing and Validating Regional Travel Forecasting Models with CTPP Data: MAG Experience CTPP Webinar and Discussion Thursday, July 17, 1-3pm EDT Developing and Validating Regional Travel Forecasting Models with CTPP Data: MAG Experience Kyunghwi Jeon, MAG Petya Maneva, MAG Vladimir Livshits,

More information

APPENDIX C-6 - TRAFFIC MODELING REPORT, SRF CONSULTING GROUP

APPENDIX C-6 - TRAFFIC MODELING REPORT, SRF CONSULTING GROUP APPENDIX C-6 - TRAFFIC MODELING REPORT, SRF CONSULTING GROUP Scott County 2030 Comprehensive Plan Update Appendix C Scott County Traffic Model Final Report and Documentation March 2008 Prepared for: Scott

More information

Forecasts for the Reston/Dulles Rail Corridor and Route 28 Corridor 2010 to 2050

Forecasts for the Reston/Dulles Rail Corridor and Route 28 Corridor 2010 to 2050 George Mason University Center for Regional Analysis Forecasts for the Reston/Dulles Rail Corridor and Route 28 Corridor 21 to 25 Prepared for the Fairfax County Department of Planning and Zoning Lisa

More information

transportation research in policy making for addressing mobility problems, infrastructure and functionality issues in urban areas. This study explored

transportation research in policy making for addressing mobility problems, infrastructure and functionality issues in urban areas. This study explored ABSTRACT: Demand supply system are the three core clusters of transportation research in policy making for addressing mobility problems, infrastructure and functionality issues in urban areas. This study

More information

5.1 Introduction. 5.2 Data Collection

5.1 Introduction. 5.2 Data Collection Chapter 5 Traffic Analysis 5.1 Introduction This chapter of the EIS assesses the traffic impacts of the proposed N5 Westport to Turlough Road Project (the proposed scheme). The proposed scheme will provide

More information

Neighborhood Locations and Amenities

Neighborhood Locations and Amenities University of Maryland School of Architecture, Planning and Preservation Fall, 2014 Neighborhood Locations and Amenities Authors: Cole Greene Jacob Johnson Maha Tariq Under the Supervision of: Dr. Chao

More information

An Integrated Approach to Statewide Travel Modeling Applications in Delaware

An Integrated Approach to Statewide Travel Modeling Applications in Delaware TRB 88 th Annual Meeting Washington, D.C. January 14 th, 29 An Integrated Approach to Statewide Travel Modeling Applications in Delaware The Context: Challenges for Today s Modelers: Personnel: Vacant

More information

Cipra D. Revised Submittal 1

Cipra D. Revised Submittal 1 Cipra D. Revised Submittal 1 Enhancing MPO Travel Models with Statewide Model Inputs: An Application from Wisconsin David Cipra, PhD * Wisconsin Department of Transportation PO Box 7913 Madison, Wisconsin

More information

City of Hermosa Beach Beach Access and Parking Study. Submitted by. 600 Wilshire Blvd., Suite 1050 Los Angeles, CA

City of Hermosa Beach Beach Access and Parking Study. Submitted by. 600 Wilshire Blvd., Suite 1050 Los Angeles, CA City of Hermosa Beach Beach Access and Parking Study Submitted by 600 Wilshire Blvd., Suite 1050 Los Angeles, CA 90017 213.261.3050 January 2015 TABLE OF CONTENTS Introduction to the Beach Access and Parking

More information

Appendix B.1 EMME Model Calibration Memo

Appendix B.1 EMME Model Calibration Memo Appendix B.1 EMME Model Calibration Memo itrans 144 Front Street West, Suite 655 Toronto, ON M5J 2L7 Tel: (416) 847-0005 Fax: (905) 882-1557 www.hdrinc.com www.itransconsulting.com File: 2.0 Memorandum

More information

Regional Snapshot Series: Transportation and Transit. Commuting and Places of Work in the Fraser Valley Regional District

Regional Snapshot Series: Transportation and Transit. Commuting and Places of Work in the Fraser Valley Regional District Regional Snapshot Series: Transportation and Transit Commuting and Places of Work in the Fraser Valley Regional District TABLE OF CONTENTS Complete Communities Daily Trips Live/Work Ratio Commuting Local

More information

Figure 8.2a Variation of suburban character, transit access and pedestrian accessibility by TAZ label in the study area

Figure 8.2a Variation of suburban character, transit access and pedestrian accessibility by TAZ label in the study area Figure 8.2a Variation of suburban character, transit access and pedestrian accessibility by TAZ label in the study area Figure 8.2b Variation of suburban character, commercial residential balance and mix

More information

Traffic Impact Study

Traffic Impact Study Traffic Impact Study Statham DRI One University Parkway Prepared for: Barrow County Prepared by: October 2012 Table of Contents Executive Summary i Section 1. Introduction 1 Project Description 1 Methodology

More information

Trip Distribution Modeling Milos N. Mladenovic Assistant Professor Department of Built Environment

Trip Distribution Modeling Milos N. Mladenovic Assistant Professor Department of Built Environment Trip Distribution Modeling Milos N. Mladenovic Assistant Professor Department of Built Environment 25.04.2017 Course Outline Forecasting overview and data management Trip generation modeling Trip distribution

More information

COMBINATION OF MACROSCOPIC AND MICROSCOPIC TRANSPORT SIMULATION MODELS: USE CASE IN CYPRUS

COMBINATION OF MACROSCOPIC AND MICROSCOPIC TRANSPORT SIMULATION MODELS: USE CASE IN CYPRUS International Journal for Traffic and Transport Engineering, 2014, 4(2): 220-233 DOI: http://dx.doi.org/10.7708/ijtte.2014.4(2).08 UDC: 656:519.87(564.3) COMBINATION OF MACROSCOPIC AND MICROSCOPIC TRANSPORT

More information

WEBER ROAD RESIDENTIAL DEVELOPMENT Single Family Residential Project

WEBER ROAD RESIDENTIAL DEVELOPMENT Single Family Residential Project WEBER ROAD RESIDENTIAL DEVELOPMENT Single Family Residential Project WEBER ROAD RESIDENTIAL DEVELOPMENT TRAFFIC IMPACT STUDY TABLE OF CONTENTS 1.0 Executive Summary Page 2.0 Introduction 2.1 DEVELOPMENT

More information

Project Appraisal Guidelines

Project Appraisal Guidelines Project Appraisal Guidelines Unit 16.2 Expansion Factors for Short Period Traffic Counts August 2012 Project Appraisal Guidelines Unit 16.2 Expansion Factors for Short Period Traffic Counts Version Date

More information

Date: June 19, 2013 Meeting Date: July 5, Consideration of the City of Vancouver s Regional Context Statement

Date: June 19, 2013 Meeting Date: July 5, Consideration of the City of Vancouver s Regional Context Statement Section E 1.5 To: From: Regional Planning and Agriculture Committee Lee-Ann Garnett, Senior Regional Planner Planning, Policy and Environment Department Date: June 19, 2013 Meeting Date: July 5, 2013 Subject:

More information

Study Overview. the nassau hub study. The Nassau Hub

Study Overview. the nassau hub study. The Nassau Hub Livable Communities through Sustainable Transportation the nassau hub study AlternativeS analysis / environmental impact statement The Nassau Hub Study Overview Nassau County has initiated the preparation

More information

Attachment 3. Updating UBC s Regional Context Statement. University of British Columbia CONSIDERATION MEMORANDUM OF CONSULTATION INPUT

Attachment 3. Updating UBC s Regional Context Statement. University of British Columbia CONSIDERATION MEMORANDUM OF CONSULTATION INPUT Attachment 3 University of British Columbia Updating UBC s Regional Context Statement CONSIDERATION MEMORANDUM OF CONSULTATION INPUT Campus and Community Planning February 24, 2014 1 CONSIDERATION MEMORANDUM

More information

Economic Activity Economic A ctivity

Economic Activity Economic A ctivity 5 Economic Economic Activity Activity ECONOMIC ACTIVITY 5.1 EMPLOYMENT... 5-7 5.1.1 OBJECTIVE... 5-7 5.1.2 POLICIES... 5-7 5.2 PROTECTING THE AREA OF EMPLOYMENT... 5-9 5.2.1 OBJECTIVE... 5-9 5.2.2 POLICIES...

More information

3. THE TRANSPORTATION AND TRANSIT MASTER PLAN

3. THE TRANSPORTATION AND TRANSIT MASTER PLAN The Master Plan Report Page 3-1 3. THE TRANSPORTATION AND TRANSIT MASTER PLAN 3.1 The Strategy Through the technical and consultation processes "A Balanced Road and Transit System" has been defined as

More information

Growth Management: Analysis of Comments Received and Responses Comments received as of October 16, 2017

Growth Management: Analysis of Comments Received and Responses Comments received as of October 16, 2017 Growth Management: Analysis of Comments Received and s Comments received as of October 16, Comments informing the Region of Peel s growth management work have been summarized with responses below. These

More information

GIS Analysis of Crenshaw/LAX Line

GIS Analysis of Crenshaw/LAX Line PDD 631 Geographic Information Systems for Public Policy, Planning & Development GIS Analysis of Crenshaw/LAX Line Biying Zhao 6679361256 Professor Barry Waite and Bonnie Shrewsbury May 12 th, 2015 Introduction

More information

Snow and Ice Control POLICY NO. P-01/2015. CITY OF AIRDRIE Snow and Ice Control Policy

Snow and Ice Control POLICY NO. P-01/2015. CITY OF AIRDRIE Snow and Ice Control Policy Page 1 CITY OF AIRDRIE Snow and Ice Control Effective Date: Approved By: Approved On: March 17, 2015 City Council March 16, 2015 Revision Date: Resolution #: ------ PURPOSE: The City of Airdrie is responsible

More information

A Hybrid Approach for Determining Traffic Demand in Large Development Areas

A Hybrid Approach for Determining Traffic Demand in Large Development Areas A Hybrid Approach for Determining Traffic Demand in Large Development Areas Xudong Chai Department of Civil, Construction, and Environmental Engineering Iowa State University 394 Town Engineering Ames,

More information

STAFF REPORT. MEETING DATE: July 3, 2008 AGENDA ITEM: 7

STAFF REPORT. MEETING DATE: July 3, 2008 AGENDA ITEM: 7 STAFF REPORT SUBJECT: Travel Models MEETING DATE: July 3, 2008 AGENDA ITEM: 7 RECOMMENDATION: Receive information on status of travel model development in Santa Barbara County and review factors to achieve

More information

The effects of impact fees on urban form and congestion in Florida

The effects of impact fees on urban form and congestion in Florida The effects of impact fees on urban form and congestion in Florida Principal Investigators: Andres G. Blanco Ruth Steiner Presenters: Hyungchul Chung Jeongseob Kim Urban and Regional Planning Contents

More information

California Urban Infill Trip Generation Study. Jim Daisa, P.E.

California Urban Infill Trip Generation Study. Jim Daisa, P.E. California Urban Infill Trip Generation Study Jim Daisa, P.E. What We Did in the Study Develop trip generation rates for land uses in urban areas of California Establish a California urban land use trip

More information

Final City of Colusa STREETS & ROADWAYS MASTER PLAN. October J Street Suite 390 Sacramento, CA 95814

Final City of Colusa STREETS & ROADWAYS MASTER PLAN. October J Street Suite 390 Sacramento, CA 95814 Final City of Colusa STREETS & ROADWAYS MASTER PLAN October 2009 660 J Street Suite 390 Sacramento, CA 95814 TABLE OF CONTENTS I. INTRODUCTION... 1 Report Organization...1 II. ANALYSIS METHODOLOGY... 2

More information

2040 MTP and CTP Socioeconomic Data

2040 MTP and CTP Socioeconomic Data SE Data 6-1 24 MTP and CTP Socioeconomic Data Purpose of Socioeconomic Data The socioeconomic data (SE Data) shows the location of the population and employment, median household income and other demographic

More information

GIS in Community & Regional Planning

GIS in Community & Regional Planning GIS in Community & Regional Planning The The role role of of GIS GIS in in Re-writing the the Zoning Bylaw for for the the City City of of Vernon LandInfo Technologies Presentation Overview The GIS Initiative

More information

Tier 2 Final Environmental Assessment I-66 Transportation Technical Report. Appendix E. Travel Demand Forecasting Model Validation Memorandum

Tier 2 Final Environmental Assessment I-66 Transportation Technical Report. Appendix E. Travel Demand Forecasting Model Validation Memorandum Tier 2 Final Environmental Assessment I-66 Transportation Technical Report Appendix E Travel Demand Forecasting Model Validation Memorandum FINAL AUGUST 216 MEMORANDUM To: Robert Josef, VDOT Northern Virginia

More information

محاضرة رقم 4. UTransportation Planning. U1. Trip Distribution

محاضرة رقم 4. UTransportation Planning. U1. Trip Distribution UTransportation Planning U1. Trip Distribution Trip distribution is the second step in the four-step modeling process. It is intended to address the question of how many of the trips generated in the trip

More information

Taming the Modeling Monster

Taming the Modeling Monster Taming the Modeling Monster Starring: Ellen Greenberg Scott McCarey Jim Charlier Audience Poll, part 1 Elected Officials Board Members Public Staff Consultants Journalists Other Audience Poll, part 2 Modeling

More information

Appendix C: City of Mississauga Transportation Strategy Update

Appendix C: City of Mississauga Transportation Strategy Update Appendix C: City of Mississauga Transportation Strategy Update Transportation Strategy Update Transportation and Works Department Agenda - Objectives - What has changed? - Forecasted trends and issues

More information

Table 3-1 Gallatin County Population and Employment Trends ( )

Table 3-1 Gallatin County Population and Employment Trends ( ) 3.1 INTRODUCTION The method and process used to predict growth in the Bozeman area up to the year 030 is contained in this chapter of the Transportation Plan. By using population, employment and other

More information

PROPOSED PROJECT. Section PROJECT DESCRIPTION

PROPOSED PROJECT. Section PROJECT DESCRIPTION 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 1.1 PROJECT DESCRIPTION This Environmental Assessment describes the proposed improvements

More information

April 10, Mr. Curt Van De Walle, City Manager City of Castle Hills 209 Lemonwood Drive Castle Hills, Texas 78213

April 10, Mr. Curt Van De Walle, City Manager City of Castle Hills 209 Lemonwood Drive Castle Hills, Texas 78213 Mr. Curt Van De Walle, City Manager City of Castle Hills 209 Lemonwood Drive Castle Hills, Texas 78213 Subject: Revised Castle Hills BASIS Charter School Traffic Impact Analysis Review City of Castle Hills,

More information

MPOs SB 375 LAFCOs SCAG Practices/Experiences And Future Collaborations with LAFCOs

MPOs SB 375 LAFCOs SCAG Practices/Experiences And Future Collaborations with LAFCOs Connecting LAFCOs and COGs for Mutual Benefits MPOs SB 375 LAFCOs SCAG Practices/Experiences And Future Collaborations with LAFCOs Frank Wen, Manager Research & Analysis Land Use & Environmental Planning

More information

Regional Transit Development Plan Strategic Corridors Analysis. Employment Access and Commuting Patterns Analysis. (Draft)

Regional Transit Development Plan Strategic Corridors Analysis. Employment Access and Commuting Patterns Analysis. (Draft) Regional Transit Development Plan Strategic Corridors Analysis Employment Access and Commuting Patterns Analysis (Draft) April 2010 Contents 1.0 INTRODUCTION... 4 1.1 Overview and Data Sources... 4 1.2

More information

Local Area Key Issues Paper No. 13: Southern Hinterland townships growth opportunities

Local Area Key Issues Paper No. 13: Southern Hinterland townships growth opportunities Draft Sunshine Coast Planning Scheme Review of Submissions Local Area Key Issues Paper No. 13: Southern Hinterland townships growth opportunities Key Issue: Growth opportunities for Southern Hinterland

More information

Parking Regulations Dundas Street West, from Bathurst Street to Dovercourt Road

Parking Regulations Dundas Street West, from Bathurst Street to Dovercourt Road STAFF REPORT ACTION REQUIRED Parking Regulations Dundas Street West, from Bathurst Street to Dovercourt Road Date: October 28, 2008 To: From: Toronto and East York Community Council Director, Transportation

More information

South Western Region Travel Time Monitoring Program Congestion Management Process Spring 2008 Report

South Western Region Travel Time Monitoring Program Congestion Management Process Spring 2008 Report South Western Region Travel Monitoring Program Congestion Management Process Spring 2008 Report Prepared by: South Western Regional Planning Agency 888 Washington Boulevard Stamford, CT 06901 Telephone:

More information

Transit Time Shed Analyzing Accessibility to Employment and Services

Transit Time Shed Analyzing Accessibility to Employment and Services Transit Time Shed Analyzing Accessibility to Employment and Services presented by Ammar Naji, Liz Thompson and Abdulnaser Arafat Shimberg Center for Housing Studies at the University of Florida www.shimberg.ufl.edu

More information

TRAFFIC IMPACT STUDY. Platte Canyon Villas Arapahoe County, Colorado (Arapahoe County Case Number: Z16-001) For

TRAFFIC IMPACT STUDY. Platte Canyon Villas Arapahoe County, Colorado (Arapahoe County Case Number: Z16-001) For TRAFFIC IMPACT STUDY For Platte Canyon Villas Arapahoe County, Colorado (Arapahoe County Case Number: Z16-001) February 2015 Revised: August 2015 April 2016 July 2016 September 2016 Prepared for: KB Home

More information

CVS Derwood. Local Area Transportation Review

CVS Derwood. Local Area Transportation Review CVS Derwood Montgomery County, Maryland May 27, 2016 Local Area Transportation Review Prepared for: JC Bar Properties, Inc. Steve Fleming, PE 415 Fallowfield Road, Suite 301 Camp Hill, Pennsylvania 17011

More information

Environmental Analysis, Chapter 4 Consequences, and Mitigation

Environmental Analysis, Chapter 4 Consequences, and Mitigation Environmental Analysis, Chapter 4 4.17 Environmental Justice This section summarizes the potential impacts described in Chapter 3, Transportation Impacts and Mitigation, and other sections of Chapter 4,

More information

Transportation Statistical Data Development Report OKALOOSA-WALTON OUTLOOK 2035 LONG RANGE TRANSPORTATION PLAN

Transportation Statistical Data Development Report OKALOOSA-WALTON OUTLOOK 2035 LONG RANGE TRANSPORTATION PLAN Transportation Statistical Data Development Report OKALOOSA-WALTON OUTLOOK 2035 LONG RANGE TRANSPORTATION PLAN Prepared for the Okaloosa-Walton Transportation Planning Organization and The Florida Department

More information

GIS ANALYSIS METHODOLOGY

GIS ANALYSIS METHODOLOGY GIS ANALYSIS METHODOLOGY No longer the exclusive domain of cartographers, computer-assisted drawing technicians, mainframes, and workstations, geographic information system (GIS) mapping has migrated to

More information

King City URA 6D Concept Plan

King City URA 6D Concept Plan King City URA 6D Concept Plan King City s Evolution Among the fastest growing cities 2000 Census 1,949 2010 Census 3,111 60% increase 2016 Census estimate 3,817 23% increase Average annual rate 4.3% Surpassing

More information

City of Saginaw Right of Way Division Snow and Ice Removal Policy January 18, 2016

City of Saginaw Right of Way Division Snow and Ice Removal Policy January 18, 2016 Snow and Ice Removal Policy January 18, 2016 It is the policy of the to provide snowplowing and ice removal services in order to: Provide safe traveling conditions for motorists and pedestrians Assist

More information

MANAGING TRANSPORTATION & LAND USE INTERACTIONS (PL-58)

MANAGING TRANSPORTATION & LAND USE INTERACTIONS (PL-58) MANAGING TRANSPORTATION & LAND USE INTERACTIONS (PL-58) COURSE OUTLINE DAY ONE 1:30 2:00 p.m. MODULE 1: History and Context Understand history and foundation for transportation and land use planning today

More information

Forecasts from the Strategy Planning Model

Forecasts from the Strategy Planning Model Forecasts from the Strategy Planning Model Appendix A A12.1 As reported in Chapter 4, we used the Greater Manchester Strategy Planning Model (SPM) to test our long-term transport strategy. A12.2 The origins

More information