Appendix B.1 EMME Model Calibration Memo

Size: px
Start display at page:

Download "Appendix B.1 EMME Model Calibration Memo"

Transcription

1 Appendix B.1 EMME Model Calibration Memo

2 itrans 144 Front Street West, Suite 655 Toronto, ON M5J 2L7 Tel: (416) Fax: (905) File: 2.0 Memorandum To: Mohan Philip City of Hamilton Cc: From: Steve Keen Date: February 21, 2012 Re: ROPA9 TMP Review Summary of Modelling Work This memo details the calibration work and development of forecasts for the base and alternative 2031 scenarios in the ROPA9 study area. 1. MODEL ASSUMPTIONS AND ADJUSTMENTS The model used for the ROPA9 TMP study was the Hamilton 2010 LRT Model provided by the City on November 10, After completing our review, we identified a series of changes that needed to be made to the networks to represent the existing situation and planned future developments appropriately. These changes (all of which have been saved as EMME macros using the Network Editor tool) are as follows: 1 of 25 C:\Users\nbaudais\Desktop\ROPA Modelling summary Memo rev-1.docx

3 Table 1: Network Changes Network Modification Add missing second eastbound lane to Red Hill Valley Pkwy west of Stone Church Add Second Road West Add two additional centroids between Second Road and Upper Centennial and redistribute land use Add Whitedeer Road Code collectors at capacity and 2 lanes Code Highland and Upper Mount Albion at 50 km/h (not 60) Code local roads at consistent 500 capacity and 2 lanes (multiple changes, many were 4 lanes) Code Mud St lane capacity at consistent 1000 (without fluctuations from 700 to 1800 in existing coding) Code Upper Centennial lane capacity at 1200 Extend Glover Rd to Dickenson and Twenty Road to Glover Move wrongly located centroid from east of Upper Centennial to west of Fletcher (zone 2615) and connect it to Trinity Church and Fletcher Reconfigure centroid connectors to approximate local roads Reduce Gatestone to 40 km/h in school zone Remove direct centroid connector to Mud Street from zone 2658 Remove direct centroid connectors to Rymal from zones to south Add centroid between First Road and Upper Centennial Add centroid for Trinity West development and redistribute land use Add collector road between Fletcher and Upper Centennial south of Rymal Add extension of Second Road West south of Rymal to collector Add Trinity West Collector Add two additional centroids south of Rymal and redistribute land use Close Upper Mount Albion south of Trinity West Collector Code Rymal at 60 km/h through study area Reduce 8 lane components of Dartnall Road, Rymal Road and Upper Centennial to 4 lanes Scenarios Future Future Future Future Future Future Future Future Future In addition, the following revisions were made to future year land use: Multiply demand to zone 2648 (North Glanbrook Industrial Park) by 5 (2021) and by 6 (2031) to approximate actual forecast demand based on growth plans; Disaggregate demand allocated to model zones to additional zones south of Rymal, west of the Karst lands and north of Highland/west of Upper Centennial, for new developments in the ROPA, Trinity West and Felker developments, respectively. The revised road networks for 2011 and 2031 are shown in Exhibit 1 and Exhibit 2, below. February 21, of 25

4 Exhibit 1: 2011 road network and number of lanes February 21, of 25

5 Exhibit 2: 2031 road network and number of lanes 2. MODEL CALIBRATION The model was calibrated to a 2011 base year by using 2011 (or early 2012) count data on key links in and around the ROPA 9 study area. After running the model, a post-process consisting of assigning count volumes to link extra attributes and using these in the EMME demand adjustment process was used to redistribute and reassign flows in order that they more accurately represented the observed conditions. Links leading to the following intersections were selected for calibration: Stone Church and Red Hill Valley Parkway Stone Church and Upper Mount Albion Highland and First Highland and Second Gatestone and Second Rymal and Dartnall Rymal and Pritchard Rymal and Trinity Church Rymal and Upper Mount Albion Rymal and Fletcher Rymal and Second Rymal and Centennial February 21, of 25

6 In calibration, we used the GEH statistic as an evaluation measure. The formulation of the GEH equation, which balances both absolute and relative difference, is depicted below, where M represents modelled volume and C represents count volume. Out of the 74 count locations used in calibration, 61%, or 45, had a GEH of 5 or less; 89%, or 66, had a GEH of 10 or less; and 96%, or 71, had a GEH of 12 or less. This represents a high level of calibration accuracy. In addition, we considered screenlines north and south of Rymal and east of Second Road, formed by adding together parallel links. As is shown below, the modelled volumes closely approximate count volumes, with the exception of traffic east of Second Road, where westbound modelled volumes are 21% lower than observed totals because of low modelled demand on Highland Road; however, the GEH value is still acceptably low. Table 2: Model Calibration DIR COUNT MODEL Absdiff Reldiff GEH North of Rymal (UMA to Second) NB % 8 North of Rymal (UMA to Second) SB % 7 South of Rymal (East of Glover to Centennial) NB 989 1, % 1 South of Rymal (East of Glover to Centennial) SB % 1 East of Second (Highland to Rymal) EB % 1 East of Second (Highland to Rymal) WB 1, % 7 To calibrate future scenarios, a mask derived from the difference between the adjusted and original demand matrices was applied to adjust the future year demand matrices. This was not applied for zones that experienced high demographic growth between 2008 and 2011, as in those cases the difference between modelled and observed base year volumes was taken to be due to growth rather than lack of calibration AND 2031 BASE FORECASTS The base scenario with calibration adjustments made shows the following volumes and volume/capacity ratios for the 2011 and 2031 time horizons. Of particular note, Exhibit 6 shows a number of east-west (E-W) links (Mud Street, Rymal Road and Dickenson Road) that are over capacity in the westbound direction. This is not necessarily an E-W problem, but possibly north-south traffic that has to travel westbound to access the planned Trinity Church Arterial Road (TCAR). Alternatives that included improved E-W access to the TCAR were developed to test their potential to alleviate these problem areas identified in the base case. February 21, of 25

7 Exhibit 3: 2011 Base Scenario Volumes February 21, of 25

8 Exhibit 4: 2011 Base Scenario V/C Ratios February 21, of 25

9 Exhibit 5: 2031 Base Scenario Volumes February 21, of 25

10 Exhibit 6: 2031 Base Scenario V/C Ratios February 21, of 25

11 4. ALTERNATIVES The alternatives to the base run of the ROPA 2031 horizon model feature the following variations from the base scenario. For each alternative, all other aspects of the network remain the same as the base. The first three alternatives were developed to examine if the E-W problems revealed in the base case scenario could be alleviated. Alternative 1 (Scenario 20313) Extend the collector road, south of Rymal Road (within ROPA9 development), further west of Trinity Church Road to Trinity Church Arterial Corridor; Alternative 2 (Scenario 20314) Extend Trinity Church Arterial Corridor south to Golf Club Road, increase capacity of Golf Club Road to 700/lane from Regional Road 56 to the Trinity Church Arterial Corridor; Alternative 3 (Scenario 20315) Extend Twenty Road east to existing Trinity Church Road; The next four alternatives were developed to understand the impacts of closing (or not) Second Road West. These results will be used in a more detailed analysis separate from this memo. Alternative 4 (Scenario 20316) Close Second Road West to through traffic north of Gatestone Drive (Upper Mount Albion remains closed); Alternative 5 (Scenario 20317) Maintain Upper Mount Albion Road open (Second Road West remains open); Alternative 6 (Scenario 20318) Extend Gatestone Drive southwards in a straight line to intersect with Rymal Road; Alternative 7 (Scenario 20319) Close Second Road West between Gatestone Drive and Rymal Road. The differences in volume (alternative - original) are discussed below. Green links are those that were present in the original but not the alternative, while yellow links are those present in the alternative but not the original (where a single link overlays a split link, this is also shown in green). Volumes that are different by more than 100 are shown for the first three alternatives, while differences of more than 50 (due to a wider range of diversion options or smaller initial volumes) are shown for the subsequent four. Where a link is split by the addition of an intersection, the differences (positive and negative) reflect the entire volume on the link, as the original link is considered to have been replaced by the new split two, so the overall impact can be seen by subtracting the negative value displayed from the positive value. February 21, of 25

12 Alternative 1: 2031 Volume Differences This alternative examines the effect of extending the collector road south of Rymal Road to meet the future TCAR. It shows a relief of 284 vehicles westbound approaching the TCAR, with no impact on Mud Street. The v/c ratios on the next page show v/c ratios of close to 1.0 on Rymal Road, the extended collector road and Dickenson Road; although more balanced than in the base network. February 21, of 25

13 Alternative 1: 2031 V/C Ratios February 21, of 25

14 Alternative 2: 2031 Volume Differences This alternative models the impact of extending the TCAR southwards to meet Golf Club Road in order to provide relief to Rymal Road. It provides no relief to Mud Street and a relief to Rymal Road of only 124 vehicles per hour and would require an upgrading of Golf Club Road. February 21, of 25

15 Alternative 2: 2031 V/C Ratios February 21, of 25

16 Alternative 3: 2031 Volume Differences This alternative models the impact of extending the Twenty Road eastwards to meet Trinity Church Road thereby providing a connection from Trinity Church Road to the TCAR. This option provides no relief to Mud Street and a relief to Rymal Road of 326 vehicles per hour (the most of the three options tested) and would require an upgrading of Twenty Road. February 21, of 25

17 Alternative 3: 2031 V/C Ratios February 21, of 25

18 Alternative 4: 2031 Volume Differences Alternative 4 tests the option of closing Second Road West north of Gatestone Drive. This shows a diversion of approximately 360 northbound and 188 southbound vehicles from Second Road W. and increases traffic on Gatestone Drive by approximately 200 vehicles NB and 160 vehicles SB. A minor diversion onto Upper Centennial is also shown. February 21, of 25

19 Alternative 4: 2031 V/C Ratios February 21, of 25

20 Alternative 5: 2031 Volume Differences This alternative tests the option of keeping Upper Mt. Albion Road open (it was previously recommended to remain open as part of the previous ROPA 9 Master Plan). The results show that a demand of 642 vehicles would be generated on the opened Upper Mt. Albion Road. February 21, of 25

21 Alternative 5: 2031 V/C Ratios February 21, of 25

22 Alternative 6: 2031 Volume Differences Alternative 6 examines the impact of extend Gatestone Drive to meet Rymal Road, this potentially relieving Second Road West. The result shows a relief of 170 vehicles on the lower part of Second Road West and an increase of 221 vehicles on the extended Gatestone Drive. Relief on the upper part of Second Road West is shown to be insignificant. February 21, of 25

23 Alternative 6: 2031 V/C Ratios February 21, of 25

24 Alternative 7: 2031 Volume Differences Alternative 7 tests the option of closing Second Road West between Rymal Road and Gatestone Drive. This shows a reduction in traffic on the lower part of Second Road West of 366 NB vehicles and reduction of 121 of Gatestone Drive. There is an insignificant reduction NB on the upper part of Second Road West, presumably because some of the current demand on Second Road West originates from the Gatestone Drive area. February 21, of 25

25 Alternative 7: 2031 V/C Ratios February 21, of 25

26 5. SUMMARY OF ALTERNATIVES FORECASTS The most notable forecast changes in traffic volumes of implementing each of the alternatives are summarized in Table 3, while the locations where congestion is reduced or increases across the 100% v/c ratio point are summarized in Table 4. Table 3: Summary of alternatives Alternative Traffic increases (amount) Traffic reductions (amount) 1 New east-west collector (700) Twenty Road E. (100) 2 Golf Club Road. (200) TC Arterial (north of Golf Club) (500) 3 Twenty Road E. (600) TC Road (south of Twenty) (100) 4 Gatestone Drive (200) Highland Road W. (east of Second) (100) Trinity Church Road (100) TC Arterial (south of Rymal) (300) Rymal Road E. (east of TC Road) (300) TC Arterial (north of Twenty) (200) TC Road (north of Golf Club) (200) Trinity Church Arterial (300) TC Road (north of Twenty) (200) Rymal Road (east of TC Arterial) (300) Second Road W. (400) Rymal Road E. (east of Second) (100) Highland Road W. (west of Second) (100) Rymal Road E. (west of UMA) (300) TC Arterial (north of Rymal) (300) Gatestone Dr/Second Road W. (100) 5 Upper Mount Albion Road (600) Trinity West Collector (200) Rymal Road E. (east of UMA) (200) 6 Gatestone Drive Rymal connection (200) Second Road W. (south of Gatestone) (200) 7 Rymal Road E. (east of Second) (100) Whitedeer Road (200) (Volumes are to the nearest 100) Table 4: Summary of congestion changes Rymal Road E. (east of Second) (200) Second Road W. (400) Gatestone Drive (100) Alternative Impact v/c goes over 1.00 Impact v/c goes below New east-west collector Mud Street W. (east of TC Arterial) 2 Golf Club Road Twenty Road E. (west of TC Arterial) Rymal Road E. (east of TC Road) Mud Street W. (east of TC Arterial) Dickenson Road E. (west of TCR) 3 Twenty Road E. extension Mud Street W. (east of TC Arterial) Dickenson Road E. (west of TCR) 4 - Mud Street W. (east of TC Arterial) 5 - Mud Street W. (east of TC Arterial) The results of this analysis is one input into a subsequent more comprehensive evaluation of alternatives. February 21, of 25

6 th Line Municipal Class Environmental Assessment

6 th Line Municipal Class Environmental Assessment 6 th Line Municipal Class Environmental Assessment County Road 27 to St John s Road Town of Innisfil, ON September 6, 2016 APPENDIX L: TRAVEL DEMAND FORECASTING MEMORANDUM Accessible formats are available

More information

APPENDIX IV MODELLING

APPENDIX IV MODELLING APPENDIX IV MODELLING Kingston Transportation Master Plan Final Report, July 2004 Appendix IV: Modelling i TABLE OF CONTENTS Page 1.0 INTRODUCTION... 1 2.0 OBJECTIVE... 1 3.0 URBAN TRANSPORTATION MODELLING

More information

Appendix B. Durham Region Travel Demand Model Calibration

Appendix B. Durham Region Travel Demand Model Calibration Appendix B Durham Region Travel Demand Model Calibration AECOM 300 Water Street 905 668 9363 tel Whitby, ON, Canada L1N 9J2 905 668 0221 fax www.aecom.com To Ron Albright, Municipality of Clarington Page

More information

FINAL Traffic Report for the Proposed Golden Valley Road and Newhall Ranch Road Projects in the City of Santa Clarita, California May 5, 2005

FINAL Traffic Report for the Proposed Golden Valley Road and Newhall Ranch Road Projects in the City of Santa Clarita, California May 5, 2005 FINAL Traffic Report for the Proposed Golden Valley Road and Newhall Ranch Road Projects in the City of Santa Clarita, California May 5, 2005 Prepared For: EDAW, Inc. 1420 Kettner Boulevard, Suite 620

More information

APPENDIX G Halton Region Transportation Model

APPENDIX G Halton Region Transportation Model APPENDIX G Halton Region Transportation Model Halton Region Transportation Master Plan Working Paper No. 1 - Legislative Context Working Paper No. 2 - Active Transportation Halton Transportation Model

More information

Signalized Intersections

Signalized Intersections Signalized Intersections Kelly Pitera October 23, 2009 Topics to be Covered Introduction/Definitions D/D/1 Queueing Phasing and Timing Plan Level of Service (LOS) Signal Optimization Conflicting Operational

More information

TRANSPORTATION AND TRAFFIC ANALYSIS REPORT

TRANSPORTATION AND TRAFFIC ANALYSIS REPORT Square One Drive Extension Municipal Class Environmental Assessment Environmental Study Report Appendix B Transportation and Traffic Analysis Report TRANSPORTATION AND TRAFFIC ANALYSIS REPORT FINAL DRAFT

More information

WEBER ROAD RESIDENTIAL DEVELOPMENT Single Family Residential Project

WEBER ROAD RESIDENTIAL DEVELOPMENT Single Family Residential Project WEBER ROAD RESIDENTIAL DEVELOPMENT Single Family Residential Project WEBER ROAD RESIDENTIAL DEVELOPMENT TRAFFIC IMPACT STUDY TABLE OF CONTENTS 1.0 Executive Summary Page 2.0 Introduction 2.1 DEVELOPMENT

More information

Appendixx C Travel Demand Model Development and Forecasting Lubbock Outer Route Study June 2014

Appendixx C Travel Demand Model Development and Forecasting Lubbock Outer Route Study June 2014 Appendix C Travel Demand Model Development and Forecasting Lubbock Outer Route Study June 2014 CONTENTS List of Figures-... 3 List of Tables... 4 Introduction... 1 Application of the Lubbock Travel Demand

More information

3. THE TRANSPORTATION AND TRANSIT MASTER PLAN

3. THE TRANSPORTATION AND TRANSIT MASTER PLAN The Master Plan Report Page 3-1 3. THE TRANSPORTATION AND TRANSIT MASTER PLAN 3.1 The Strategy Through the technical and consultation processes "A Balanced Road and Transit System" has been defined as

More information

III. FORECASTED GROWTH

III. FORECASTED GROWTH III. FORECASTED GROWTH In order to properly identify potential improvement projects that will be required for the transportation system in Milliken, it is important to first understand the nature and volume

More information

FINAL REPORT. City of Toronto. Contract Project No: B

FINAL REPORT. City of Toronto. Contract Project No: B City of Toronto SAFETY IMPACTS AND REGULATIONS OF ELECTRONIC STATIC ROADSIDE ADVERTISING SIGNS TECHNICAL MEMORANDUM #2B BEFORE/AFTER COLLISION ANALYSIS AT MID-BLOCK LOCATIONS FINAL REPORT 3027 Harvester

More information

TRAFFIC IMPACT STUDY. Platte Canyon Villas Arapahoe County, Colorado (Arapahoe County Case Number: Z16-001) For

TRAFFIC IMPACT STUDY. Platte Canyon Villas Arapahoe County, Colorado (Arapahoe County Case Number: Z16-001) For TRAFFIC IMPACT STUDY For Platte Canyon Villas Arapahoe County, Colorado (Arapahoe County Case Number: Z16-001) February 2015 Revised: August 2015 April 2016 July 2016 September 2016 Prepared for: KB Home

More information

Table of Contents Introduction... 4 Study Area... 5

Table of Contents Introduction... 4 Study Area... 5 Table of Contents Introduction... 4 Study Area... 5 Streets and s... 5 Traffic Volumes... 8 Recent and Anticipated Development... 10 Crash Analysis... 10 Projected Traffic Volumes... 11 Trip Generation...

More information

Appendix B. Traffic Analysis Report

Appendix B. Traffic Analysis Report Appendix B Traffic Analysis Report Report No. 14369/TR/WN02 August 2007 SALLINS BYPASS BYPASS OPTIONEERING ANALYSIS - TRAFFIC REPORT Kildare County Council Áras Chill Dara, Devoy Park, Naas, Co Kildare

More information

Tier 2 Final Environmental Assessment I-66 Transportation Technical Report. Appendix E. Travel Demand Forecasting Model Validation Memorandum

Tier 2 Final Environmental Assessment I-66 Transportation Technical Report. Appendix E. Travel Demand Forecasting Model Validation Memorandum Tier 2 Final Environmental Assessment I-66 Transportation Technical Report Appendix E Travel Demand Forecasting Model Validation Memorandum FINAL AUGUST 216 MEMORANDUM To: Robert Josef, VDOT Northern Virginia

More information

3.0 ANALYSIS OF FUTURE TRANSPORTATION NEEDS

3.0 ANALYSIS OF FUTURE TRANSPORTATION NEEDS 3.0 ANALYSIS OF FUTURE TRANSPORTATION NEEDS In order to better determine future roadway expansion and connectivity needs, future population growth and land development patterns were analyzed as part of

More information

JEP John E. Jack Pflum, P.E. Consulting Engineering 7541 Hosbrook Road, Cincinnati, OH Telephone:

JEP John E. Jack Pflum, P.E. Consulting Engineering 7541 Hosbrook Road, Cincinnati, OH Telephone: JEP John E. Jack Pflum, P.E. Consulting Engineering 7541 Hosbrook Road, Cincinnati, OH 45243 Email: jackpflum1@gmail.com Telephone: 513.919.7814 MEMORANDUM REPORT Traffic Impact Analysis Proposed Soccer

More information

Prepared for: San Diego Association Of Governments 401 B Street, Suite 800 San Diego, California 92101

Prepared for: San Diego Association Of Governments 401 B Street, Suite 800 San Diego, California 92101 Activity-Based Travel Model Validation for 2012 Using Series 13 Data: Coordinated Travel Regional Activity Based Modeling Platform (CT-RAMP) for San Diego County Prepared for: San Diego Association Of

More information

WOODRUFF ROAD CORRIDOR ORIGIN-DESTINATION ANALYSIS

WOODRUFF ROAD CORRIDOR ORIGIN-DESTINATION ANALYSIS 2018 WOODRUFF ROAD CORRIDOR ORIGIN-DESTINATION ANALYSIS Introduction Woodruff Road is the main road to and through the commercial area in Greenville, South Carolina. Businesses along the corridor have

More information

APPENDIX I: Traffic Forecasting Model and Assumptions

APPENDIX I: Traffic Forecasting Model and Assumptions APPENDIX I: Traffic Forecasting Model and Assumptions Appendix I reports on the assumptions and traffic model specifications that were developed to support the Reaffirmation of the 2040 Long Range Plan.

More information

Market Street PDP. Nassau County, Florida. Transportation Impact Analysis. VHB/Vanasse Hangen Brustlin, Inc. Nassau County Growth Management

Market Street PDP. Nassau County, Florida. Transportation Impact Analysis. VHB/Vanasse Hangen Brustlin, Inc. Nassau County Growth Management Transportation Impact Analysis Market Street PDP Nassau County, Florida Submitted to Nassau County Growth Management Prepared for TerraPointe Services, Inc. Prepared by VHB/Vanasse Hangen Brustlin, Inc.

More information

Expanding the GSATS Model Area into

Expanding the GSATS Model Area into Appendix A Expanding the GSATS Model Area into North Carolina Jluy, 2011 Table of Contents LONG-RANGE TRANSPORTATION PLAN UPDATE 1. Introduction... 1 1.1 Background... 1 1.2 Existing Northern Extent of

More information

Appendix B. Land Use and Traffic Modeling Documentation

Appendix B. Land Use and Traffic Modeling Documentation Appendix B Land Use and Traffic Modeling Documentation Technical Memorandum Planning Level Traffic for Northridge Sub-Area Study Office of Statewide Planning and Research Modeling & Forecasting Section

More information

VHD Daily Totals. Population 14.5% change. VMT Daily Totals Suffolk 24-hour VMT. 49.3% change. 14.4% change VMT

VHD Daily Totals. Population 14.5% change. VMT Daily Totals Suffolk 24-hour VMT. 49.3% change. 14.4% change VMT 6.9 Suffolk 6-54 VMT Population and Travel Characteristics Population 14.5% change 2014 1,529,202 VHD Daily Totals 2014 251,060 49.3% change 2040 1,788,175 2040 374,850 VMT Daily Totals 2014 39,731,990

More information

FARM 1065 PORTION 1, ATLANTIS TRAFFIC IMPACT ASSESSMENT

FARM 1065 PORTION 1, ATLANTIS TRAFFIC IMPACT ASSESSMENT FARM 1065 PORTION 1, ATLANTIS TRAFFIC IMPACT ASSESSMENT February 2018 FIRST ISSUE Prepared by: JG AFRIKA (PTY) LTD Branch: Cape Town PO Box 38561 Postal code: 7430 Telephone: 021 530 1800 Email: wink@

More information

Prepared for. 3D/International, Inc West Loop South, Suite 400 Houston, Texas November 2006

Prepared for. 3D/International, Inc West Loop South, Suite 400 Houston, Texas November 2006 DRAFT TRAFFIC IMPACT STUDY FOR PHASED DEVELOPMENT OF TAMU CC Prepared for 3D/International, Inc. 1900 West Loop South, Suite 400 Houston, Texas 77027 November 2006 Interim Review Only Document Incomplete:

More information

Traffic Impact Analysis. for the STARBUCKS STORE. Located at 9900 BALBOA BOULEVARD. Submitted to CITY OF LOS ANGELES. January 2017.

Traffic Impact Analysis. for the STARBUCKS STORE. Located at 9900 BALBOA BOULEVARD. Submitted to CITY OF LOS ANGELES. January 2017. Traffic Impact Analysis for the STARBUCKS STORE Located at 9900 BALBOA BOULEVARD Submitted to CITY OF LOS ANGELES January 2017 Submitted By January 5, 2017 Ken A. Aitchison, P.E. Transportation Engineering

More information

US 169/I-70 North Loop Planning & Environmental Linkages Study

US 169/I-70 North Loop Planning & Environmental Linkages Study US 169/I-70 North Loop Planning & Environmental Linkages Study VISSIM Calibration Document Draft April 13, 2018 Page i Table of Contents 1. Overview... 1 2. Data Types... 2 3. Model Parameter Adjustments...

More information

Traffic Impact Study

Traffic Impact Study Traffic Impact Study Statham DRI One University Parkway Prepared for: Barrow County Prepared by: October 2012 Table of Contents Executive Summary i Section 1. Introduction 1 Project Description 1 Methodology

More information

MEMORANDUM. The study area of the analysis was discussed with City staff and includes the following intersections:

MEMORANDUM. The study area of the analysis was discussed with City staff and includes the following intersections: MEMORANDUM DATE: JULY 6, 2012 TO: FROM: RE: CC: MELANIE KNIGHT BRAD BYVELDS/ JENNIFER LUONG 1050 SOMERSET STREET PRELIMINARY TRAFFIC ANALYSIS OUR FILE NO. 111152 NEIL MALHOTRA The purpose of this memo

More information

S.170 th Street Micro-Simulation Seattle-Tacoma International Airport Port of Seattle/Aviation Planning

S.170 th Street Micro-Simulation Seattle-Tacoma International Airport Port of Seattle/Aviation Planning Seattle-acoma International Airport Port of Seattle/Aviation Planning Port of Seattle PO OF SEAE Aviation Planning Airport Operations January 24, 2013 Summary he Port is planning to relocate the cell phone

More information

Appendix C Final Methods and Assumptions for Forecasting Traffic Volumes

Appendix C Final Methods and Assumptions for Forecasting Traffic Volumes Fairview Ave. and Main St. Improvements and Local Streets Plan Appendices Ada County Highway District Appendix C Final Methods and Assumptions for Forecasting Traffic Volumes January 3, 207 Appendices

More information

Parking Regulations Dundas Street West, from Bathurst Street to Dovercourt Road

Parking Regulations Dundas Street West, from Bathurst Street to Dovercourt Road STAFF REPORT ACTION REQUIRED Parking Regulations Dundas Street West, from Bathurst Street to Dovercourt Road Date: October 28, 2008 To: From: Toronto and East York Community Council Director, Transportation

More information

MnDOT Method for Calculating Measures of Effectiveness (MOE) From CORSIM Model Output

MnDOT Method for Calculating Measures of Effectiveness (MOE) From CORSIM Model Output MnDOT Method for Calculating Measures of Effectiveness (MOE) From CORSIM Model Output Rev. April 29, 2005 MnDOT Method for Calculating Measures of Effectiveness (MOE) From CORSIM Model Output Table of

More information

TRAFFIC FORECAST METHODOLOGY

TRAFFIC FORECAST METHODOLOGY CHAPTER 5 TRAFFIC FORECAST METHODOLOGY Introduction Need for County-Level Traffic Forecasting 2030 HC-TSP Model Methodology Model Calibration Future Traffic Forecasts Hennepin County Transportation Systems

More information

Travel Demand Model Report City of Peterborough Comprehensive Transportation Plan Update Supporting Document

Travel Demand Model Report City of Peterborough Comprehensive Transportation Plan Update Supporting Document Travel Demand Model Report City of Peterborough Comprehensive Transportation Plan Update Supporting Document Prepared for: City of Peterborough and Morrison Hershfield June 2012 Paradigm Transportation

More information

TRANSPORTATION IMPACT STUDY WHEELER STREET CLOSURE

TRANSPORTATION IMPACT STUDY WHEELER STREET CLOSURE TRANSPORTATION IMPACT STUDY WHEELER STREET CLOSURE Village of Greene, Chenango County, New York Prepared for: VILLAGE OF GREENE 49 Genesee Street Greene, NY 13778 Prepared by: LARSON DESIGN GROUP 1000

More information

Project Level Traffic Forecast Report Business 40 Reconstruction Study Forsyth County

Project Level Traffic Forecast Report Business 40 Reconstruction Study Forsyth County Project Level Traffic Forecast Report Business 40 Reconstruction Study Forsyth County TIP No. U-2827 B WBS # 34872.1.1 June 2013 Prepared for North Carolina Department of Transportation Prepared by Project

More information

Taming the Modeling Monster

Taming the Modeling Monster Taming the Modeling Monster Starring: Ellen Greenberg Scott McCarey Jim Charlier Audience Poll, part 1 Elected Officials Board Members Public Staff Consultants Journalists Other Audience Poll, part 2 Modeling

More information

April 10, Mr. Curt Van De Walle, City Manager City of Castle Hills 209 Lemonwood Drive Castle Hills, Texas 78213

April 10, Mr. Curt Van De Walle, City Manager City of Castle Hills 209 Lemonwood Drive Castle Hills, Texas 78213 Mr. Curt Van De Walle, City Manager City of Castle Hills 209 Lemonwood Drive Castle Hills, Texas 78213 Subject: Revised Castle Hills BASIS Charter School Traffic Impact Analysis Review City of Castle Hills,

More information

South East Growth Corridor - VITM project

South East Growth Corridor - VITM project Growth Areas Authority 20 Jan 2012 South East Growth Corridor - VITM project Final Report South East Growth Corridor - VITM project Final Report Prepared for Growth Areas Authority Prepared by AECOM Australia

More information

The Highline Development Traffic Impact Study

The Highline Development Traffic Impact Study The Highline Development Traffic Impact Study Columbia Falls, Montana Prepared For: TD&H Engineering 450 Corporate Drive, Suite 101 Kalispell, MT 59901 June, 2018 130 South Howie Street Helena, Montana

More information

A Study of Red Light Cameras in Kansas City, MO

A Study of Red Light Cameras in Kansas City, MO A Study of Red Light s in Kansas City, MO Prepared by the Special Operations Division Executive Summary This paper will analyze the crash data for the 29 red light cameras located in 17 intersections in

More information

CVS Derwood. Local Area Transportation Review

CVS Derwood. Local Area Transportation Review CVS Derwood Montgomery County, Maryland May 27, 2016 Local Area Transportation Review Prepared for: JC Bar Properties, Inc. Steve Fleming, PE 415 Fallowfield Road, Suite 301 Camp Hill, Pennsylvania 17011

More information

Focused Traffic Analysis for the One Lincoln Park Project

Focused Traffic Analysis for the One Lincoln Park Project September 15, 2015 Mr. Bill Johnson Coldwell Banker 511 Sir Francis Drake Boulevard Greenbrae, CA 94904 Focused Traffic Analysis for the One Lincoln Park Project Dear Mr. Johnson; As requested, W-Trans

More information

570 Hazeldean Road, Ottawa, ON Transportation Brief Mattamy Homes. Prepared By: Stantec Consulting Ltd. Project Number:

570 Hazeldean Road, Ottawa, ON Transportation Brief Mattamy Homes. Prepared By: Stantec Consulting Ltd. Project Number: 570 Hazeldean Road, Ottawa, ON Transportation Brief Mattamy Homes Prepared By: Stantec Consulting Ltd. Project Number: 163600871 March 2013 570 HAZELDEAN ROAD, OTTAWA, ON TRANSPORTATION BRIEF MARCH 2013

More information

Final City of Colusa STREETS & ROADWAYS MASTER PLAN. October J Street Suite 390 Sacramento, CA 95814

Final City of Colusa STREETS & ROADWAYS MASTER PLAN. October J Street Suite 390 Sacramento, CA 95814 Final City of Colusa STREETS & ROADWAYS MASTER PLAN October 2009 660 J Street Suite 390 Sacramento, CA 95814 TABLE OF CONTENTS I. INTRODUCTION... 1 Report Organization...1 II. ANALYSIS METHODOLOGY... 2

More information

Appendix C Traffic Study

Appendix C Traffic Study Final Environmental Impact Statement Appendix C Traffic Study Schofield Generating Station Project, Hawaii October 2015 C-1 Final Environmental Impact Statement This page intentionally left blank. Schofield

More information

CONTINUING PLANNING PROGRAM LOCAL TRANSPORTATION AND TRAFFIC DATA PRODUCT REPORT [OH Corridors]

CONTINUING PLANNING PROGRAM LOCAL TRANSPORTATION AND TRAFFIC DATA PRODUCT REPORT [OH Corridors] CONTINUING PLANNING PROGRAM LOCAL TRANSPORTATION AND TRAFFIC DATA PRODUCT REPORT [OH Corridors] Travel Time and Delay Analysis for Belpre (OH) and Marietta (OH) Fiscal Year 2009 Report WOOD WASHINGTON

More information

I-10 East at Redd closes for 24 hours this Sunday, Feb 11. Then, I-10 West at Resler closes for 27 hours on Feb 25

I-10 East at Redd closes for 24 hours this Sunday, Feb 11. Then, I-10 West at Resler closes for 27 hours on Feb 25 NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov February 9, 2018 I-10 East at Redd closes for 24 hours this Sunday, Feb 11

More information

Greater Toronto Area Cordon Count Summary Analysis of Traffic Trends 1985 to 2011

Greater Toronto Area Cordon Count Summary Analysis of Traffic Trends 1985 to 2011 Greater Toronto Area Cordon Count Summary Analysis of Traffic Trends 1985 to 2011 Prepared by: Data Management Group Department of Civil Engineering University of Toronto Telephone: (416) 978-3916 Table

More information

Brandywine Road Speed Study FINAL REPORT

Brandywine Road Speed Study FINAL REPORT Brandywine Road Speed Study FINAL REPORT City of Albuquerque Brandywine Road Speed Study Final Report Albuquerque, New Mexico City of Albuquerque May, 2016 Brandywine Road Speed Study Final Report City

More information

2014 Data Collection Project ITE Western District

2014 Data Collection Project ITE Western District 2014 Data Collection Project ITE Western District Project Completed By: Oregon State University OSU ITE Student Chapter 101 Kearney Hall Corvallis, OR 97331 Student Coordinator: Sarah McCrea (OSU ITE Student

More information

CHAPTER 3. CAPACITY OF SIGNALIZED INTERSECTIONS

CHAPTER 3. CAPACITY OF SIGNALIZED INTERSECTIONS CHAPTER 3. CAPACITY OF SIGNALIZED INTERSECTIONS 1. Overview In this chapter we explore the models on which the HCM capacity analysis method for signalized intersections are based. While the method has

More information

FY 2010 Continuing i Planning Program Product Report. Local Transportation and Traffic Data. Wood-Washington-Wirt Interstate Planning Commission

FY 2010 Continuing i Planning Program Product Report. Local Transportation and Traffic Data. Wood-Washington-Wirt Interstate Planning Commission FY 2010 Continuing i Planning Program Product Report Local Transportation and Traffic Data Travel Time and Delay Data for Belpre and Marietta, Ohio Wood-Washington-Wirt Interstate Planning Commission CONTINUING

More information

TRAFFIC IMPACT STUDY

TRAFFIC IMPACT STUDY TRAFFIC IMPACT STUDY TERRE HAUTE CONVENTION CENTER WABASH AVENUE & 9 TH STREET TERRE HAUTE, INDIANA PREPARED FOR 8365 Keystone Crossing, Suite 201 Indianapolis, IN 46240 Phone: (317) 202-0864 Fax: (317)

More information

Table 3-1 Gallatin County Population and Employment Trends ( )

Table 3-1 Gallatin County Population and Employment Trends ( ) 3.1 INTRODUCTION The method and process used to predict growth in the Bozeman area up to the year 030 is contained in this chapter of the Transportation Plan. By using population, employment and other

More information

Appendix I: Traffic Study

Appendix I: Traffic Study City of Fontana Sierra Lakes Commerce Center Draft EIR Appendix I: Traffic Study FirstCarbon Solutions H:\Client (PN JN)\0144\01440050\EIR\1 ADEIR\01440050 Sec99 99 Appendix Dividers.doc THIS PAGE INTENTIONALLY

More information

TRAFFIC IMPACT STUDY MANUFACTURING COMPANY

TRAFFIC IMPACT STUDY MANUFACTURING COMPANY TRAFFIC IMPACT STUDY For MANUFACTURING COMPANY Prepared For: Airway Heights, WA Prepared By: SUNBURST ENGINEERING, P. S. 4310 S. Ball Dr. Veradale, WA 99037 April, 2013 TRAFFIC IMP ACT STUDY Manufacturing

More information

Palmerston North Area Traffic Model

Palmerston North Area Traffic Model Palmerston North Area Traffic Model Presentation to IPWEA 7 November 2014 PNATM Presentation Overview Model Scope and type Data collected The model Forecasting inputs Applications PNCC Aims and Objectives

More information

OVERVIEW OF A SIMULATION STUDY OF THE HIGHWAY 401 FTMS

OVERVIEW OF A SIMULATION STUDY OF THE HIGHWAY 401 FTMS OVERVIEW OF A SIMULATION STUDY OF THE HIGHWAY 401 FTMS HELLINGA, Bruce 1, BAKER, Mark 1, VAN AERDE, Michel 1, AULTMAN-HALL, Lisa 1, and MASTERS, Philip 2 1 Transportation Systems Research Group Queen's

More information

NATHAN HALE HIGH SCHOOL PARKING AND TRAFFIC ANALYSIS. Table of Contents

NATHAN HALE HIGH SCHOOL PARKING AND TRAFFIC ANALYSIS. Table of Contents Parking and Traffic Analysis Seattle, WA Prepared for: URS Corporation 1501 4th Avenue, Suite 1400 Seattle, WA 98101-1616 Prepared by: Mirai Transportation Planning & Engineering 11410 NE 122nd Way, Suite

More information

The Sunland Park flyover ramp is set to close the week of March 19 until early summer

The Sunland Park flyover ramp is set to close the week of March 19 until early summer March 2, 2018 The Sunland Park flyover ramp is set to close the week of March 19 until early summer GO 10 is targeting the week of March 19 to close the Sunland Park Drive flyover entrance ramp to I 10

More information

CIV3703 Transport Engineering. Module 2 Transport Modelling

CIV3703 Transport Engineering. Module 2 Transport Modelling CIV3703 Transport Engineering Module Transport Modelling Objectives Upon successful completion of this module you should be able to: carry out trip generation calculations using linear regression and category

More information

COMBINATION OF MACROSCOPIC AND MICROSCOPIC TRANSPORT SIMULATION MODELS: USE CASE IN CYPRUS

COMBINATION OF MACROSCOPIC AND MICROSCOPIC TRANSPORT SIMULATION MODELS: USE CASE IN CYPRUS International Journal for Traffic and Transport Engineering, 2014, 4(2): 220-233 DOI: http://dx.doi.org/10.7708/ijtte.2014.4(2).08 UDC: 656:519.87(564.3) COMBINATION OF MACROSCOPIC AND MICROSCOPIC TRANSPORT

More information

Date: March 31, 2014 PATE; fyril 2.3,2 >H

Date: March 31, 2014 PATE; fyril 2.3,2 >H aj BRAMPTON fifs Rower City XH-l-f r.t "»* City Council The Corporation of the City of Brampton SRAMPTON CITY COUNCIL Date: March 31, 2014 PATE; fyril 2.3,2 >H File: POO GR VisWhtoJed ^t'th-meeh'^a Subject:

More information

HALFF 16196? TRAFFIC MANAGEMENT PLAN. Richardson ISD Aikin Elementary School Dallas, Texas North Bowser Road Richardson, Texas 75081

HALFF 16196? TRAFFIC MANAGEMENT PLAN. Richardson ISD Aikin Elementary School Dallas, Texas North Bowser Road Richardson, Texas 75081 30280 16196? TRAFFIC MANAGEMENT PLAN Exhibit 572B Aikin Elementary School Planned Development District No. 572 Approved City Plan Commission October20, 2016 July 12, 2016 Prepared for HALFF AVO 31586 PHO1

More information

5.1 Introduction. 5.2 Data Collection

5.1 Introduction. 5.2 Data Collection Chapter 5 Traffic Analysis 5.1 Introduction This chapter of the EIS assesses the traffic impacts of the proposed N5 Westport to Turlough Road Project (the proposed scheme). The proposed scheme will provide

More information

I. M. Schoeman North West University, South Africa. Abstract

I. M. Schoeman North West University, South Africa. Abstract Urban Transport XX 607 Land use and transportation integration within the greater area of the North West University (Potchefstroom Campus), South Africa: problems, prospects and solutions I. M. Schoeman

More information

Future Forecasts Meeting Agenda

Future Forecasts Meeting Agenda Future Forecasts Meeting Agenda US 192 Feasibility Study Date: January 10, 2012 Project #: 9891.07 At: Viera Governmental Center, Building A, Natural Resources Large Conference Room 10:00 12:00 PM 1. Introductions

More information

TRAFFIC STUDY FOR THE GAFFEY POOL PROJECT LOS ANGELES, CALIFORNIA CITY OF LOS ANGELES, BUREAU OF ENGINEERING OCTOBER 2013 PREPARED FOR PREPARED BY

TRAFFIC STUDY FOR THE GAFFEY POOL PROJECT LOS ANGELES, CALIFORNIA CITY OF LOS ANGELES, BUREAU OF ENGINEERING OCTOBER 2013 PREPARED FOR PREPARED BY TRAFFIC STUDY FOR THE GAFFEY POOL PROJECT LOS ANGELES, CALIFORNIA OCTOBER 2013 PREPARED FOR CITY OF LOS ANGELES, BUREAU OF ENGINEERING PREPARED BY DRAFT TRAFFIC STUDY FOR THE GAFFEY POOL PROJECT October

More information

Albion Falls -Virtual Field Trip-

Albion Falls -Virtual Field Trip- Albion Falls -Virtual Field Trip- School of GEOGRAPHY & GEOLOGY Carolyn Eyles & Susan Vajoczki Prepared by Liz Kenny and Zachary Windus From McMaster University turn right onto Main Street West towards

More information

1.0 INTRODUCTION AND SUMMARY...

1.0 INTRODUCTION AND SUMMARY... TABLE OF CONTENTS 1.0 INTRODUCTION AND SUMMARY... 1 1.1 Purpose and Study Objective... 1 1.2 Executive Summary... 1 2.0 ROADWAY CONDITIONS... 5 2.1 Granville Parkway (South Intersection)... 8 2.2 Tuscany

More information

TRAFFIC ALERT FOR WEEK OF February 4 8, 2008

TRAFFIC ALERT FOR WEEK OF February 4 8, 2008 TRAFFIC ALERT FOR WEEK OF February 4 8, 2008 Highway work zones in the Staunton District The following is a list of highway work that might affect traffic in the Staunton transportation district during

More information

Traffic Demand Forecast

Traffic Demand Forecast Chapter 5 Traffic Demand Forecast One of the important objectives of traffic demand forecast in a transportation master plan study is to examine the concepts and policies in proposed plans by numerically

More information

Roadway Traffic Noise Feasibility Assessment. Conservancy Subdivision. Ottawa, Ontario

Roadway Traffic Noise Feasibility Assessment. Conservancy Subdivision. Ottawa, Ontario Conservancy Subdivision Ottawa, Ontario REPORT: GWE17 151 Traffic Noise Prepared For: Andrew Finnson Barrhaven Conservancy East Inc. Ottawa, Ontario Prepared By: Joshua Foster, P.Eng., Principal Omar Daher,

More information

Accessing and Using Indiana Traffic Data

Accessing and Using Indiana Traffic Data Accessing and Using Indiana Traffic Data Purdue Road School March 6, 2013 Presented by: Gregory Katter, PE Asset Planning Indiana Traffic Data 1. Overview of Traffic Data Collection Program 2. Accessing

More information

DOLLAR GENERAL PROJECT FOCUSED TRAFFIC ANALYSIS (REVISED) May 20, 2015

DOLLAR GENERAL PROJECT FOCUSED TRAFFIC ANALYSIS (REVISED) May 20, 2015 DOLLAR GENERAL PROJECT FOCUSED TRAFFIC ANALYSIS (REVISED) May 20, 2015 May 20, 2015 Mr. Dan Biswas, VP of Development CJS DEVELOPMENT II, LLC 5111 North Scottsdale Road, Suite 200 Scottsdale, CA 85250

More information

TRAVEL DEMAND MODEL. Chapter 6

TRAVEL DEMAND MODEL. Chapter 6 Chapter 6 TRAVEL DEMAND MODEL As a component of the Teller County Transportation Plan development, a computerized travel demand model was developed. The model was utilized for development of the Transportation

More information

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP)

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP) NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP) Project Overview Briefing Packet September 2015 RECOMMENDED ALTERNATIVES Environmental Impact Statement (EIS) Project Divided into 3 Segments Segment 1:

More information

Metro Emergency Security Operations Center (ESOC) 410 Center Street City of Los Angeles

Metro Emergency Security Operations Center (ESOC) 410 Center Street City of Los Angeles Metro Emergency Security Operations Center (ESOC) 410 Center Street City of Los Angeles Traffic Study August 31, 2015 AECOM 515 South Flower Street, 4 th Floor Los Angeles, CA 90071 Job Number: 60323255

More information

TRAFFIC IMPACT STUDY FOR SOUTH BAY SALT POND RESTORATION PROJECT PHASE 2

TRAFFIC IMPACT STUDY FOR SOUTH BAY SALT POND RESTORATION PROJECT PHASE 2 APPENDIX G TRAFFIC IMPACT STUDY FOR SOUTH BAY SALT POND RESTORATION PROJECT PHASE 2 South Bay Salt Pond Restoration Project Phase II May 2015 Draft Environmental Impact Statement/Report Traffic Impact

More information

PLAZA MEXICO RESIDENCES

PLAZA MEXICO RESIDENCES PLAZA MEXICO RESIDENCES TRAFFIC STUDY PREPARED FOR: 3000 E. IMPERIAL, LLC. 6940 Beach Boulevard, D-501 Buena Park, California 90621 PREPARED BY: OCTOBER 5, 2017 translutions the transportatio n solutions

More information

January 12, Mr. Ryan Granger TMGB Wilson, LLC 2221 Health Drive SW, Suite 2200 Wyoming, Michigan 49519

January 12, Mr. Ryan Granger TMGB Wilson, LLC 2221 Health Drive SW, Suite 2200 Wyoming, Michigan 49519 January 12, 2018 Mr. Ryan Granger TMGB Wilson, LLC 2221 Health Drive SW, Suite 2200 Wyoming, Michigan 49519 Re: Proposed Reserve at Rivertown Mixed-Use Development Updated Trip Generation and Site Driveway

More information

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP)

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP) NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP) Planning for a Mega Project in a Metropolitan Area TxDOT Short Course October 13, 2015 RECOMMENDED ALTERNATIVES Environmental Impact Statement (EIS) Project

More information

South Western Region Travel Time Monitoring Program Congestion Management Process Spring 2008 Report

South Western Region Travel Time Monitoring Program Congestion Management Process Spring 2008 Report South Western Region Travel Monitoring Program Congestion Management Process Spring 2008 Report Prepared by: South Western Regional Planning Agency 888 Washington Boulevard Stamford, CT 06901 Telephone:

More information

Travel Demand Management Plan

Travel Demand Management Plan Travel Demand Management Plan Tryg s & Apartment Building 8 West Lake Street Minneapolis, MN AUTHORIZED PROPERTY REPRESENTATIVE: By Dated: Mr. Johnny Carlson Trammell Crow Chicago Development, Inc. 5 South

More information

CHAPTER 2. CAPACITY OF TWO-WAY STOP-CONTROLLED INTERSECTIONS

CHAPTER 2. CAPACITY OF TWO-WAY STOP-CONTROLLED INTERSECTIONS CHAPTER 2. CAPACITY OF TWO-WAY STOP-CONTROLLED INTERSECTIONS 1. Overview In this chapter we will explore the models on which the HCM capacity analysis method for two-way stop-controlled (TWSC) intersections

More information

Growth Management: Analysis of Comments Received and Responses Comments received as of October 16, 2017

Growth Management: Analysis of Comments Received and Responses Comments received as of October 16, 2017 Growth Management: Analysis of Comments Received and s Comments received as of October 16, Comments informing the Region of Peel s growth management work have been summarized with responses below. These

More information

Speed Limit Review. Montague Road, West End. Prepared for Brisbane City Council CEB06842 CEB06842

Speed Limit Review. Montague Road, West End. Prepared for Brisbane City Council CEB06842 CEB06842 Speed Limit Review Montague Road, West End CEB06842 CEB06842 Prepared for Brisbane City Council 2 November 2016 Speed Limit Review Montague Road, West End Document Information Prepared for Brisbane City

More information

North Carolina s First Quadrant Left: History and Lessons Learned

North Carolina s First Quadrant Left: History and Lessons Learned North Carolina s First Quadrant Left: History and Lessons Learned Michael P. Reese, P.E. (Corresponding Author) Congestion Management Section Project Engineer North Carolina Department of Transportation

More information

MADISON, WI STONE HOUSE DEVELOPMENT 1000 E. WASHINGTON AVENUE REDEVELOPMENT TRANSPORTATION STUDY DECEMBER 14, 2015

MADISON, WI STONE HOUSE DEVELOPMENT 1000 E. WASHINGTON AVENUE REDEVELOPMENT TRANSPORTATION STUDY DECEMBER 14, 2015 MADISON, WI STONE HOUSE DEVELOPMENT 1000 E. WASHINGTON AVENUE REDEVELOPMENT TRANSPORTATION STUDY DECEMBER 14, 2015 TABLE OF CONTENTS... 3 Proposed Development... 3 Methodology... 3 Phase 1 Development...

More information

North Carolina s First Quadrant Left: History and Lessons Learned

North Carolina s First Quadrant Left: History and Lessons Learned 0 0 0 North Carolina s First Quadrant Left: History and Lessons Learned Michael P. Reese, P.E. (Corresponding Author) Congestion Management Section Project Engineer North Carolina Department of Transportation

More information

Time Space Diagrams for Thirteen Shock Waves

Time Space Diagrams for Thirteen Shock Waves Time Space Diagrams for Thirteen Shock Waves Benjamin Coifman Institute of Transportation Studies 19 McLaughlin Hall University of California Berkeley, CA 9472 zephyr@eecs.berkeley.edu http://www.cs.berkeley.edu/~zephyr

More information

Perth County Road Fatal Head-on Collision - A Common and Dangerous Issue

Perth County Road Fatal Head-on Collision - A Common and Dangerous Issue Perth County Road Fatal Head-on Collision - A Common and Dangerous Issue Posting Date: 25-Aug-2016 Figure 1: View looking east long "Speeders Alley" - a more appropriate name for the long, straight and

More information

Data Collection. Lecture Notes in Transportation Systems Engineering. Prof. Tom V. Mathew. 1 Overview 1

Data Collection. Lecture Notes in Transportation Systems Engineering. Prof. Tom V. Mathew. 1 Overview 1 Data Collection Lecture Notes in Transportation Systems Engineering Prof. Tom V. Mathew Contents 1 Overview 1 2 Survey design 2 2.1 Information needed................................. 2 2.2 Study area.....................................

More information

KAISER SOUTH NORTHERN VIRGINIA HUB TRAFFIC IMPACT STUDY PRINCE WILLIAM COUNTY, VIRGINIA TABLE OF CONTENTS. Section 2 BACKGROUND INFORMATION 12

KAISER SOUTH NORTHERN VIRGINIA HUB TRAFFIC IMPACT STUDY PRINCE WILLIAM COUNTY, VIRGINIA TABLE OF CONTENTS. Section 2 BACKGROUND INFORMATION 12 KAISER SOUTH NORTHERN VIRGINIA HUB TRAFFIC IMPACT STUDY PRINCE WILLIAM COUNTY, VIRGINIA TABLE OF CONTENTS Page EXECUTIVE SUMMARY 1 Purpose of Report and Study Objectives... 1 Site Location and Study Area...

More information

Subject: Desert Palisades Specific Plan - Tram Way Access Sight Distance

Subject: Desert Palisades Specific Plan - Tram Way Access Sight Distance Endo Engineering Traffic Engineering Air Quality Studies Noise Assessments July 13, 2015 Mr. Ed Freeman Pinnacle View, LLC P.O. Box 1754 Lake Oswego, OR 97035-0579 Subject: Desert Palisades Specific Plan

More information

ADAPTIVE SIGNAL CONTROL IV

ADAPTIVE SIGNAL CONTROL IV ADAPTIVE SIGNAL CONTROL IV Evaluation of the Adaptive Traffic Control System in Park City, Utah Dr. Peter T. Martin Associate Professor Aleksandar Stevanovic Research Associate Ivana Vladisavljevic Research

More information