Critchfield Rd / SR-129
|
|
- Poppy Gilmore
- 5 years ago
- Views:
Transcription
1 NOVEMBER 27, 2017 Critchfield Rd / SR-129 Intersection Safety Study Alternatives Report
2
3 CRITCHFIELD INTERSECTION SAFETY STUDY Contents Introduction...1 Purpose...2 Existing Conditions...2 Proposed Alternatives...2 Alternative 1 - HAWK Pedestrian Crossing...3 Alternative 2 - Roundabout...4 Alternative 3 Pedestrian/Bicycle Tunnel...5 Alternative 4 Signalized Intersection...7 Alternative 5 Pedestrian/Bicycle Bridge...7 Alternative 6 Do Nothing...9 Public Involvement...9 Summary List of Attachments Appendix A Intersection Traffic Counts Appendix B Intersection Crash Data Appendix C Alternative Figures Appendix D Alternative Cost Estimates Critchfield Intersection Safety Study
4 CRITCHFIELD INTERSECTION SAFETY STUDY Introduction In a joint effort, the Lewis-Clark Valley Metropolitan Planning Organization (LCVMPO) and Asotin County have identified the need to conduct a safety study at the intersection of Critchfield Road and State Route 129. This intersection is located on the primary route between the Cities of Clarkston and Asotin. The intersection is a 3-leg intersection, with a pedestrian path running parallel to SR-129 and the river. The pedestrian path is currently maintained by Asotin County, and is frequently used by pedestrians and cyclists alike from the City of Clarkston, WA to the City of Asotin, WA. Figure 1 below shows the layout of the intersection, including the pedestrian path and adjacent Snake River. To Clarkston Unofficial Parking N Existing Drainage Pipes Snake River To Asotin At-Grade Path Crossing & Guard Rail Opening Figure 1: Critchfield Rd. & SR-129 Intersection The pedestrian path generally runs about 10 feet in elevation below SR-129, and comes up to roadway grade for pedestrian access from SR-129 south of Critchfield Road as seen in Figure 1. On the pathway just north of the intersection, two large drainage pipes daylight onto the path that conveys stormwater from the basin above Critchfield Road into the River. Currently, there is no crosswalk across SR-129 to access the opening in the guardrail. There is also a gravel lot on the north side of Critchfield Road that is Critchfield Intersection Safety Study 1
5 CRITCHFIELD INTERSECTION SAFETY STUDY used as an unofficial parking lot for pedestrians and cyclists which is owned by the Washington State Department of Transportation. Purpose Pedestrians traveling from Critchfield Road to the pathway do not always use the dedicated opening in the guardrail, and are commonly seen stepping over the guardrail to access the path. This crossing method is not safe, especially considering that SR-129 has a posted speed limit of 55 miles per hour. The purpose of this intersection safety study was to evaluate the traffic conditions at the intersection and provide recommendations for safer pedestrian and bicycle travel around Critchfield Road and across SR- 129 to access the trail. Existing Conditions To analyze the existing conditions for the intersection, traffic counts were taken during the week at two separate time periods: AM Peak Hour (7:00 AM 10:00 AM), and PM Peak Hour (3:00 PM 6:00 PM) during the weekday. Table 1 shows a summary of the intersection counts, including peak times and peak volumes for the analysis periods. Detailed traffic counts for each analysis period can be found in Appendix A. Table 1: Intersection Count Summary Time Period Peak Time Peak Volume (veh./hr.) 7:00 AM 10:00 AM 7:15 AM 831 3:00 PM 6:00 PM 4:45 PM 821 In addition to traffic counts, crash data was also reviewed in the vicinity of the intersection. According to Washington State Department of Transportation (WSDOT) records, there have been 14 collisions on SR-129 from January 1, 2014 to December 31, While there has been a fair amount of crashes on SR-129, most of these crashes are attributed to striking deer, rocks, or other objects. Of the 14 crashes that have occurred, only one resulted in a possible injury with no serious injuries or fatalities. According to the crash data available, there are no serious safety issues for vehicles near this intersection. Detailed crash data can also be found in Appendix B. Proposed Alternatives There were six possible alternatives that were proposed as a solution to pedestrian and bicycle travel across SR-129 at Critchfield Road (in no particular ranking or order): Alternative 1: High-Intensity Activated Crosswalk (HAWK) Pedestrian Crossing Alternative 2: Roundabout with pedestrian crosswalks Alternative 3: Pedestrian/Bicycle Tunnel Alternative 4: Signalized Intersection with pedestrian crosswalks Alternative 5: Pedestrian/Bicycle Bridge Alternative 6: Do Nothing Each of the proposed alternatives have advantages and disadvantages in terms of cost, ease of implementation, as well as impact to traffic that are identified in this study. Critchfield Intersection Safety Study 2
6 CRITCHFIELD INTERSECTION SAFETY STUDY Alternative 1 - HAWK Pedestrian Crossing The High-Intensity Activated CrossWalK (HAWK) is a small signal and crosswalk system that is activated by pedestrians. It operates similar to a normal traffic intersection once activated by a user. Flashing beacons alert oncoming traffic of the presence of a pedestrian. These types of crossings are typically used when an intersection does not warrant a traffic signal installation. The HAWK crossing would include small concrete pedestrian islands and curbing to provide pedestrian protection from traffic passing through. The crossing would likely function the most efficiently placed at the location of the at-grade path crossing and guardrail opening. Additional curb and asphalt path would also be installed on the side of SR-129 opposite from the existing pedestrian path on the river to provide a safe pedestrian route to Critchfield Road. Figure 2 on the left shows the general proposed layout for Alternative 1, including a detail for a typical HAWK crossing. Full size figures for the alternatives can be found in Appendix C. The planning level cost estimate for this alternative including mobilization, contingency, WSDOT oversight, Engineering, and inspection is approximately $404,000, which is the least expensive alternative for the intersection (aside from Alternative 6: Do Nothing). Detailed cost estimates can be found in Appendix D. Figure 2: Alternative 1 - HAWK Pedestrian Crossing Table 2 on the following page shows a summary of the advantages and disadvantages of this alternative. Critchfield Intersection Safety Study 3
7 CRITCHFIELD INTERSECTION SAFETY STUDY Table 2: Alternative 1 Advantages and Disadvantages HAWK Pedestrian Crossing Summary Minimal Intersection Impact Advantages Relatively Low Cost Less effective on high speed roads Driver unfamiliarity with light cycle Disadvantages Less efficient than typical intersection Additional Maintenance by WSDOT As seen by the summary table above, HAWK pedestrian crossings are typically less effective on high speed roads such as SR-129, which has a speed limit of 55 miles per hour. Due to the light cycle that is initiated by pedestrians (flashing yellow, solid yellow, solid red, flashing red light phases), there is a certain amount of driver unfamiliarity that can make the intersection operate less efficiently. After additional analysis and discussion with WSDOT, the HAWK crossing does not meet a warrant for implementation in this specific application. As such, this improvement is not a feasible alternative. Alternative 2 - Roundabout This alternative would include changing the existing intersection layout into a roundabout. To accommodate the existing layout, the proposed roundabout would be a two-lane, three-leg roundabout to minimize impact to traffic on SR A truck apron would also allow for larger trucks and vehicles to travel through the roundabout safely. The proposed layout for Alternative 2 can be seen in Figure 3 on the following page. Full size figures for the alternatives can be found in Appendix C. The planning level cost estimate including mobilization, contingency, WSDOT oversight, Engineering, and inspection for this alternative is approximately $975,000. Detailed cost estimates can be found in Appendix D. The roundabout would include sidewalk to connect the at-grade pedestrian path crossing and guardrail opening to the roundabout, with connecting crosswalks and pedestrian islands for safe travel across the intersection. Due to the proximity of Clemans Road to the intersection, it would not likely be able to be incorporated into the roundabout safely. Figure 3: Alternative 2 - Roundabout Critchfield Intersection Safety Study 4
8 CRITCHFIELD INTERSECTION SAFETY STUDY The installation of a roundabout would likely close off Clemans Road from Critchfield Road, meaning traffic would have to use an alternate route for access to SR-129. Table 3 below summarizes the advantages and disadvantages for this alternative. Table 3: Alternative 2 Advantages and Disadvantages Roundabout Intersection Summary Minimal traffic impact Advantages Traffic calming Minimal impact to WSDOT Maintenance Large intersection impact High costs and intersection impact Disadvantages Less efficient for high speed roads Impact to utilities in the area Closes off Clemans Road from Critchfield Road As seen in the summary table, the disadvantages generally outweigh the identified advantages for implementing this alternative at the intersection. Another challenge of implementing this alternative are the existing drainage culverts that currently run under SR-129. Drainage from the basin above towards Critchfield Road would require redirection or redesign of facilities to adequately convey stormwater. Alternative 3 Pedestrian/Bicycle Tunnel This alternative would include the installation a pedestrian/bicycle tunnel crossing below SR-129 just to the north of Critchfield Road, connecting to the unofficial gravel parking lot. To accommodate for pedestrian and bicycle traffic, the tunnel would be 14 feet wide and 12 feet high (from tunnel floor to ceiling). This alternative would allow the intersection layout to remain the same. Figure 4 shows the proposed layout of the alternative. Full size figures for the alternatives can be found in Appendix C. Critchfield Intersection Safety Study 5
9 CRITCHFIELD INTERSECTION SAFETY STUDY The pedestrian tunnel would include additional asphalt pathway for safe pedestrian and bicycle travel, as well as a small portion of guardrail to keep southbound traffic turning onto Critchfield Road isolated from the pedestrians. While this alternative would allow the layout of the intersection to remain the same, a large extent of SR-129 would require demolition, regrading, and new asphalt and striping to allow clearance for the pedestrian tunnel. The planning level cost estimate including mobilization, contingency, WSDOT oversight, Engineering, and inspection for this alternative is approximately $1,066,000. Detailed cost estimates can be found in Appendix D. Table 4 on the following page shows a summary of the advantages and disadvantages of the proposed alternative. Figure 4: Alternative 3 - Pedestrian/Bicycle Tunnel Table 4: Alternative 3 Advantages and Disadvantages Pedestrian/Bicycle Tunnel Intersection Summary Does not impede traffic flow Advantages Pedestrian safety High costs and intersection impact Pedestrian reluctance Disadvantages Difficult to monitor Water levels could encroach into tunnel during extreme wet weather events Critchfield Intersection Safety Study 6
10 CRITCHFIELD INTERSECTION SAFETY STUDY Alternative 4 Signalized Intersection This alternative would include the installation of a signalized intersection system. Normal intersection cycles would allow for routine pedestrian walk cycles. This alternative would allow the intersection layout to remain the same. Figure 5 to the left shows the proposed layout of the alternative. Full size figures for the alternatives can be found in Appendix C. Analysis results for the intersection indicated that that the criteria for a signal warrant were not met, so this alternative was ruled out as a possibility for the intersection. As such, no costs were evaluated for this alternative. Figure 5: Alternative 4 - Signalized Intersection Alternative 5 Pedestrian/Bicycle Bridge This alternative would include the installation a pedestrian/bicycle bridge crossing above SR-129 just to the north of Critchfield Road, connecting to the unofficial gravel parking lot on one end, and the at-grade path crossing on the other end. To accommodate for pedestrian and bicycle traffic, the tunnel would be 14 feet wide and 17.5 feet above the roadway (from road surface to bottom of bridge). This alternative would allow the intersection layout to remain the same. Critchfield Intersection Safety Study 7
11 CRITCHFIELD INTERSECTION SAFETY STUDY Figure 6 shows the proposed layout of the alternative. Full size figures for the alternatives can be found in Appendix C. The pedestrian bridge is proposed to be constructed from reinforced concrete, utilizing concrete pillars, ramps, and landings to comply with the Americans with Disabilities Act (ADA) standards. The bridge will also have aluminum handrails and safety accessories, such as a metal safety cage to prevent any falls from the bridge. There are currently a number of power poles and powerlines in the area that would also need to be relocated to allow for proper clearances and pedestrian safety. The planning level cost estimate for this alternative including mobilization, contingency, WSDOT oversight, Engineering, and inspection is approximately $1,428,000, making it the most expensive alternative. Detailed cost estimates can be found in Appendix D. Table 5 on the following page summarizes the advantages and disadvantages for the alternative. Figure 6: Alternative 5 - Pedestrian/Bicycle Bridge Table 5: Alternative 5 Advantages and Disadvantages Pedestrian/Bicycle Tunnel Intersection Summary Minimal existing intersection impact Advantages Does not impede traffic flow Pedestrian safety High cost Disadvantages Pedestrian reluctance (height) Impact to existing powerline layout Critchfield Intersection Safety Study 8
12 CRITCHFIELD INTERSECTION SAFETY STUDY Alternative 6 Do Nothing This alternative would consist of leaving the intersection as-is, with any pedestrians navigating across the roadway as necessary. There are no costs associated with this alternative, and there would be improvements to the safety of the intersection as a whole. Public Involvement An open house was held on October 16, 2017 with the goal of obtaining public input on the proposed alternatives. 40 people attended the meeting and provided valuable insight to the existing traffic as well as feedback on the proposed alternatives. Of the 40 people that signed-in, 38 people provided written or responses to the survey that was provided. The survey asked attendees which alternative they liked best, which one they liked the least, and if they used this crossing near Critchfield Road to get to the pedestrian path. The comments were summarized as seen in Figure 7 and Figure 8 below. MOST LIKED ALTERNATIVES LEAST LIKED ALTERNATIVES 13% 15% 1 HAWK Signal 2 Roundabout 3 Ped/Bike Tunnel 8% 47% 1 HAWK 2 Roundabout 3 Ped/Bike Tunnel 35% 4 Ped/Bike Bridge 5 Do Nothing 16% 4 Ped/Bike Bridge 5 No Response 35% 16% 12% 3% Figure 7: Most Liked Alternatives Figure 8: Least Liked Alternative 50% of people who commented use the intersection as a pedestrian/bicyclist 29% do not use the intersection as a pedestrian/bicyclist 21% did not respond Figure 9: Attendee Intersection Use As seen by the figures on the previous page, the majority of the attendees of the public open house liked the HAWK pedestrian signal the most, followed by a tie for the roundabout and the pedestrian/bike tunnel, the Do Nothing option, and the pedestrian/bike bridge last. Many of the comments during the public meeting were in favor of adding advanced warning signage of the pedestrian crossing so vehicles Critchfield Intersection Safety Study 9
13 CRITCHFIELD INTERSECTION SAFETY STUDY were more aware of pedestrians on the roadway, which could also be done independently from the HAWK system. On the opposite side of the spectrum, the least liked option (after no response ) was the roundabout, followed by the HAWK signal, the pedestrian/bike bridge, and the pedestrian/bike tunnel last. Drawing from both the most and least liked surveys, there is clearly some controversy surrounding the opinion of the HAWK signal and the roundabout. Both alternatives rank highly as most and least liked options which illustrates this fact. Judging from the most and least liked figures, the alternative that was relatively well liked as in addition to low ranking (in terms of least favorite) was the pedestrian/bicycle tunnel. In addition to collecting opinions on most and least liked alternatives, comments were also collected asking people what was important to them pertaining to the future of the intersection and the pedestrian path. Figure 10 summarizes the topics of the comments received. Trail Safety Connection / General Safety Slow Traffic at Intersection Don't Impede/Stop Traffic COMMENTS ABOUT THE INTERSECTION BY CATEGORY Concerned about Cost Don't cut off Clemans Retain Parking Lot 6 Maintain Aesthetics/Wildlife Area 8 14 Reduce motorized and nonmotorized interaction Focus on Future Growth Other - Thank you, flooding, no response Figure 10: Intersection Comment Summary Critchfield Intersection Safety Study 10
14 CRITCHFIELD INTERSECTION SAFETY STUDY The top 3 comments related to concerns for trail safety and general pedestrian safety, slowing traffic at the intersection, and to avoid impeding or stopping traffic through the intersection. To evaluate the alternatives in regard to these concerns, the following table was created: Table 6: Comment Evaluation Table Comment Evaluation Table Comment HAWK Roundabout Ped Tunnel Ped Bridge Trail Safety Connection/General Safety X X Slow Traffic at Intersection X X Do not impede or stop traffic X X Cost Concerns (costs too high) X Do not cut off Clemans Road X X X X Retain Parking lot X X X Maintain aesthetics/wildlife X X X Reduce motorized and non-motorized interaction X X Focus on future growth X X X Comments addressed (out of 9) As seen in Table 6, the pedestrian tunnel and pedestrian bridge both addressed the highest amount of the public concerns collected by the surveys. The HAWK signal addressed 5 of the 9 comments, but it will not technically reduce interaction with motorized vehicles or increase safety as much as some of the other options. In addition to these items, the HAWK crossing does not meet a warrant for pedestrian volumes across the highway, ruling this alternative out as a feasible option. The roundabout could only completely address 3 of the 9 comments. Summary Based on the data collected from the public involvement, it appears that the alternative that provides a safe pedestrian crossing and addresses the most of the public s comments is either the pedestrian/bicycle bridge or the pedestrian tunnel. Both of these options address 7 out of the 9 commonly mentioned concerns from the public about the safety of the intersection. Following discussions with WSDOT, it was generally agreed that these two alternatives would be the most preferred alternatives to implement across SR-129. Critchfield Intersection Safety Study 11
15 CRITCHFIELD INTERSECTION SAFETY STUDY Appendix A Intersection Traffic Counts
16 AC-06 Justin Baker Report Title 3 File Name: Temp Site Code: Location: Cars and Peds Study Date: 01/17/2017 SR129 Southbound Time Peds Right Thru Left Critchfield Rd Westbound Peds Right Thru Left SR129 Northbound Peds Right Thru Left Critchfield Rd Eastbound Peds Right Thru Left 07: : : : : : : : : : : : Int Grand % % AM Pk Hr AM Pk Vol AM PHF :15 07: : :15 07:15-07:15 07:15-07:15-07:15 07: COUNTpro ing Movement Report: Page 1 of 8 CountingCars.com
17 AC-06 Justin Baker Report Title 3 File Name: Temp Site Code: Location: Trucks and Bikes Study Date: 01/17/2017 SR129 Southbound Time Bikes Right Thru Left Critchfield Rd Westbound Bikes Right Thru Left SR129 Northbound Bikes Right Thru Left Critchfield Rd Eastbound Bikes Right Thru Left 07: : : : : : : : : : : : Int Grand % % AM Pk Hr AM Pk Vol AM PHF : : : : : COUNTpro ing Movement Report: Page 2 of 8 CountingCars.com
18 AC-06 Justin Baker Report Title 3 File Name: Temp Site Code: Location: All Vehicles Study Date: 01/17/2017 SR129 Southbound Time Right Thru Left Critchfield Rd Westbound Right Thru Left SR129 Northbound Right Thru Left Critchfield Rd Eastbound Right Thru Left 07: : : : : : : : : : : : Grand % NaN NaN NaN NaN % % Trucks Int AM Pk Hr AM Pk Vol 07:15 07: : :15 07:15-07:15 07:15-07:15-07:15 07: COUNTpro ing Movement Report: Page 3 of 8 CountingCars.com
19 AM PHF SR129 Southbound Time Right Thru Left Critchfield Rd Westbound Right Thru Left SR129 Northbound Right Thru Left Critchfield Rd Eastbound Right Thru Left Int COUNTpro ing Movement Report: Page 4 of 8 CountingCars.com
20 AC-06 Justin Baker Report Title 3 File Name: Temp Site Code: Location: All Vehicles Study Date: 01/17/2017 SR129 In = 958 Out = Right Thru Left Critchfield Rd Out = 400 In = Right Thru Left Volumes 07:00 to 10:00 Volume = 1709 Right Thru Left In = 0 Out = 0 Critchfield Rd Left Thru Right In = 544 Out = 721 SR129 COUNTpro ing Movement Report: Page 5 of 8 CountingCars.com
21 AC-06 Justin Baker Report Title 3 File Name: Temp Site Code: Location: All Vehicles Study Date: 01/17/2017 SR Right Thru Left - - Right Critchfield Rd Left Thru AM Peak Hour Statistics AM Peak Hour Begins: 07:15 AM Peak Hour Volume: 831 AM Peak Hour Factor: Thru Left - - Critchfield Rd 63 Right - Left Thru Right SR129 COUNTpro ing Movement Report: Page 6 of 8 CountingCars.com
22 AC-06 Justin Baker Report Title 3 File Name: Temp Site Code: Location: Cars Study Date: 01/17/2017 2,000 Vehicles 1,800 1,600 1,400 1,200 1, :15 07:30 07:45 08:00 08:15 08:30 08:45 09:00 09:15 09:30 09:45 10:00 Time COUNTpro ing Movement Report: Page 7 of 8 CountingCars.com
23 AC-06 Justin Baker Report Title 3 File Name: Temp Site Code: Location: Trucks Study Date: 01/17/ Vehicles :15 07:30 07:45 08:00 08:15 08:30 08:45 09:00 09:15 09:30 09:45 10:00 Time COUNTpro ing Movement Report: Page 8 of 8 CountingCars.com
24 LCVMPO - LCSC Count Project Report Title 2 Report Title 3 File Name: AC-06 (3-6) Site Code: Location: Cars and Peds Study Date: 05/25/2016 SR-129 Southbound Time Peds Right Thru Left None Westbound Peds Right Thru Left SR-129 Northbound Peds Right Thru Left Critchfield St. Eastbound Peds Right Thru Left 15: : : : : : : : : : : : : Int Grand % % PM Pk Hr :45 16: : :45 16:45-16:45 16:45 16:45 16:45-16:45 16:45 COUNTpro ing Movement Report: Page 1 of 10 CountingCars.com
25 PM Pk Vol PM PHF SR-129 Southbound Time Peds Right Thru Left None Westbound Peds Right Thru Left SR-129 Northbound Peds Right Thru Left Critchfield St. Eastbound Peds Right Thru Left Int COUNTpro ing Movement Report: Page 2 of 10 CountingCars.com
26 LCVMPO - LCSC Count Project Report Title 2 Report Title 3 File Name: AC-06 (3-6) Site Code: Location: Trucks and Bikes Study Date: 05/25/2016 SR-129 Southbound Time Bikes Right Thru Left None Westbound Bikes Right Thru Left SR-129 Northbound Bikes Right Thru Left Critchfield St. Eastbound Bikes Right Thru Left 15: : : : : : : : : : : : : Int Grand % % PM Pk Hr :00 15: : :00 15:00-15:00 15:00-15:00-15:00 15:00 COUNTpro ing Movement Report: Page 3 of 10 CountingCars.com
27 PM Pk Vol PM PHF SR-129 Southbound Time Bikes Right Thru Left None Westbound Bikes Right Thru Left SR-129 Northbound Bikes Right Thru Left Critchfield St. Eastbound Bikes Right Thru Left Int COUNTpro ing Movement Report: Page 4 of 10 CountingCars.com
28 LCVMPO - LCSC Count Project Report Title 2 Report Title 3 File Name: AC-06 (3-6) Site Code: Location: All Vehicles Study Date: 05/25/2016 SR-129 Southbound Time Right Thru Left COUNTpro ing Movement Report: Page 5 of 10 None Westbound Right Thru Left SR-129 Northbound Right Thru Left Critchfield St. Eastbound Right Thru Left 15: : : : : : : : : : : : : Grand % NaN NaN NaN NaN % % Trucks PM Pk Hr 16:45 16: : :45 16:45-16:45 16:45 16:45 16:45-16:45 16:45 Int CountingCars.com
29 PM Pk Vol PM PHF SR-129 Southbound Time Right Thru Left None Westbound Right Thru Left SR-129 Northbound Right Thru Left Critchfield St. Eastbound Right Thru Left Int COUNTpro ing Movement Report: Page 6 of 10 CountingCars.com
30 LCVMPO - LCSC Count Project Report Title 2 Report Title 3 File Name: AC-06 (3-6) Site Code: Location: All Vehicles Study Date: 05/25/2016 SR-129 In = 815 Out = Right Thru Left Critchfield St. Out = 304 In = Right Thru Left Volumes 15:00 to 18:15 Volume = 2044 Right Thru Left In = 1 Out = 0 None Left Thru Right In = 758 Out = 690 SR-129 COUNTpro ing Movement Report: Page 7 of 10 CountingCars.com
31 LCVMPO - LCSC Count Project Report Title 2 Report Title 3 File Name: AC-06 (3-6) Site Code: Location: All Vehicles Study Date: 05/25/2016 SR Right Thru Left - - Right Critchfield St Left Thru PM Peak Hour Statistics PM Peak Hour Begins: 16:45 PM Peak Hour Volume: 821 PM Peak Hour Factor: Thru Left - - None 28 Right - Left Thru Right SR-129 COUNTpro ing Movement Report: Page 8 of 10 CountingCars.com
32 LCVMPO - LCSC Count Project Report Title 2 Report Title 3 File Name: AC-06 (3-6) Site Code: Location: Cars Study Date: 05/25/2016 4,000 Vehicles 3,600 3,200 2,800 2,400 2,000 1,600 1, :00 03:15 03:30 03:45 04:00 04:15 04:30 04:45 05:00 05:15 05:30 05:45 06:00 06:15 Time COUNTpro ing Movement Report: Page 9 of 10 CountingCars.com
33 LCVMPO - LCSC Count Project Report Title 2 Report Title 3 File Name: AC-06 (3-6) Site Code: Location: Trucks Study Date: 05/25/ Vehicles :00 03:15 03:30 03:45 04:00 04:15 04:30 04:45 05:00 05:15 05:30 05:45 06:00 06:15 Time COUNTpro ing Movement Report: Page 10 of 10 CountingCars.com
34 HCS7 Two-Way Stop-Control Report General Information Site Information Analyst sjl Intersection SR-129 & Critchfield Rd Agency/Co. Keller Associates Jurisdiction Asotin County Date Performed 2/15/2017 East/West Street Critchfield Road Analysis Year 2017 North/South Street SR-129 Time Analyzed AM Peak Hour Peak Hour Factor 0.73 Intersection Orientation North-South Analysis Time Period (hrs) 0.25 Project Description Lanes Exisiting Conditions (1/17/2017 counts) Major Street: North-South Vehicle Volumes and Adjustments oach Eastbound Westbound Northbound Southbound Movement U L T R U L T R U L T R U L T R Priority U U Number of Lanes Configuration LR L T T R Volume, V (veh/h) Percent Heavy Vehicles (%) Proportion Time Blocked Percent Grade (%) 0 Right Channelized No No No No Median Type/Storage Critical and Follow-up Headways Undivided Base Critical Headway (sec) Critical Headway (sec) Base Follow-Up Headway (sec) Follow-Up Headway (sec) Delay, Queue Length, and Level of Service Flow Rate, v (veh/h) Capacity, c (veh/h) v/c Ratio % Queue Length, Q₉₅ (veh) Control Delay (s/veh) Level of Service, LOS D A oach Delay (s/veh) oach LOS D Copyright 2017 University of Florida. All Rights Reserved. HCS7 TWSC Version 7.1 Generated: 2/15/2017 2:33:54 PM SR-129 Critchfield_2017 AM Peak.xtw
35 HCS7 Two-Way Stop-Control Report General Information Site Information Analyst sjl Intersection SR-129 & Critchfield Rd Agency/Co. Keller Associates Jurisdiction Asotin County Date Performed 2/17/2017 East/West Street Critchfield Road Analysis Year 2017 North/South Street SR-129 Time Analyzed PM Peak Hour Peak Hour Factor 0.98 Intersection Orientation North-South Analysis Time Period (hrs) 0.25 Project Description Exisiting Conditions (5/25/2016 counts + 1%) Lanes Vehicle Volumes and Adjustments Major Street: North-South oach Eastbound Westbound Northbound Southbound Movement U L T R U L T R U L T R U L T R Priority U U Number of Lanes Configuration LR L T T R Volume, V (veh/h) Percent Heavy Vehicles (%) Proportion Time Blocked Percent Grade (%) 0 Right Channelized No No No No Median Type/Storage Critical and Follow-up Headways Undivided Base Critical Headway (sec) Critical Headway (sec) Base Follow-Up Headway (sec) Follow-Up Headway (sec) Delay, Queue Length, and Level of Service Flow Rate, v (veh/h) Capacity, c (veh/h) v/c Ratio % Queue Length, Q₉₅ (veh) Control Delay (s/veh) Level of Service, LOS B A oach Delay (s/veh) oach LOS B Copyright 2017 University of Florida. All Rights Reserved. HCS7 TWSC Version 7.1 Generated: 2/17/2017 1:47:47 PM SR-129 Critchfield_2017 PM Peak.xtw
36 CRITCHFIELD INTERSECTION SAFETY STUDY Appendix B Intersection Crash Data Critchfield Intersection Safety Study
37 . Accidents_AsotinCounty SEVERITY! (! (! Property Damage Only Personal Injury Fatality 7/29/2010 ADT= 2021 Cr d iel hf itc Rd 12/30/ /23/2011! 08/19/2003! 9/30/ /24/2007 (! 12/26/2006 ADT= /27/2007 Cl em a ns R d! M as te rs Dr 12/02/2001! 12/28/2001! SR 12 9!
38
39 CRITCHFIELD INTERSECTION SAFETY STUDY Appendix C Alternative Figures Critchfield Intersection Safety Study
40
41
42
43
44
45 CRITCHFIELD INTERSECTION SAFETY STUDY Appendix D Alternative Cost Estimates Critchfield Intersection Safety Study
46 Project: Critchfield Study Engineer: Scott Linja, EI Client: LCVMPO 733 5th Street, Suite A Clarkston, Washington Printed: November 27, 2017 Phone: Fax: ENGINEER'S OPINION OF PROBABLE CONSTRUCTION COST ALTERNATIVE 1 - HAWK PEDESTRIAN CROSSING QUANTITY UNITS UNIT PRICE COST SITEWORK Excavation 500 CY $ $ 10,000 Guardrail Removal 100 LF $ 3.50 $ 1,000 Pathway Base Material (3/4 Aggregate) 50 TON $ $ 1,000 New Guardrail 100 LF $ $ 3,000 New Guardrail End Flares (Type 1) 2 EA $ 2, $ 5,000 Asphalt Pathway 30 TON $ $ 8,000 Asphalt Pavement Markings 1 LS $ 1, $ 1,000 Erosion Control 1 LS $ 2, $ 2,000 Traffic Control 1 LS $ 5, $ 5,000 HAWK PEDESTRIAN SIGNAL Hawk Pedestrian Signal 1 LS $ 150, $ 150,000 Lighting 1 LS $ 30, $ 30,000 SUBTOTAL = $ 216,000 Mobilization 10% $ 22,000 Contingency (Estimating & Construction) 15% $ 36,000 WSDOT Oversight & Plan Review 3% $ 9,000 Engineering 20% $ 55,000 Construction Engineering & Inspection 20% $ 66,000 ALTERNATIVE 1 PRELIMINARY COST = $ 404,000 The opinion of most probable cost herein is based on our perception of current conditions at the project location. This estimate reflects our opinion of probable costs at this time and is subject to change as the project design matures. Keller Associates has no control over variances in the cost of labor, materials, equipment, services provided by others, contractor s methods of determining prices, competitive bidding or market conditions, practices or bidding strategies. Keller Associates cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not vary from the costs presented herein. Concept Alternative Estimates.xlsx Page 3
47 Project: Critchfield Study Engineer: Scott Linja, EI Client: LCVMPO 733 5th Street, Suite A Clarkston, Washington Printed: November 27, 2017 Phone: Fax: ENGINEER'S OPINION OF PROBABLE CONSTRUCTION COST ALTERNATIVE 2 - ROUNDABOUT QUANTITY UNITS UNIT PRICE COST SITEWORK Sawcut and Asphalt Removal 4000 SY $ 3.00 $ 12,000 Excavation 4000 CY $ $ 80,000 Guardrail Removal 700 LF $ 3.50 $ 3,000 Roadway Base Material (3/4 Aggregate) 3500 TON $ $ 70,000 New Guardrail 700 LF $ $ 18,000 New Guardrail End Flares (Type 1) 3 EA $ 2, $ 8,000 Asphalt Pavement 1200 TON $ $ 96,000 Asphalt Pavement Markings 1 LS $ 5, $ 5,000 Concrete Sidewalk and Islands 1000 SY $ $ 50,000 Concrete Curb and Gutter 1750 LF $ $ 39,000 Erosion Control 1 LS $ 6, $ 6,000 Lighting 9 EA $ 7, $ 68,000 Traffic Control 1 LS $ 8, $ 8,000 SUBTOTAL = $ 463,000 Mobilization 10% $ 47,000 Contingency (Estimating & Construction) 30% $ 153,000 WSDOT Oversight & Plan Review 3% $ 20,000 Engineering 20% $ 133,000 Construction Engineering & Inspection 20% $ 159,000 ALTERNATIVE 2 PRELIMINARY COST = $ 975,000 The opinion of most probable cost herein is based on our perception of current conditions at the project location. This estimate reflects our opinion of probable costs at this time and is subject to change as the project design matures. Keller Associates has no control over variances in the cost of labor, materials, equipment, services provided by others, contractor s methods of determining prices, competitive bidding or market conditions, practices or bidding strategies. Keller Associates cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not vary from the costs presented herein. Concept Alternative Estimates.xlsx Page 4
48 Project: Critchfield Study Engineer: Scott Linja, EI Client: LCVMPO 733 5th Street, Suite A Clarkston, Washington Printed: November 27, 2017 Phone: Fax: ENGINEER'S OPINION OF PROBABLE CONSTRUCTION COST ALTERNATIVE 3 - PEDESTRIAN TUNNEL QUANTITY UNITS UNIT PRICE COST SITEWORK Sawcut and Asphalt Removal 3800 SY $ 3.00 $ 12,000 Excavation 2200 CY $ $ 44,000 Guardrail Removal 800 LF $ 3.50 $ 3,000 Roadway Base Material (3/4 Aggregate) 3300 TON $ $ 66,000 New Guardrail 870 LF $ $ 22,000 New Guardrail End Flares (Type 1) 4 EA $ 2, $ 10,000 Asphalt Pavement 620 TON $ $ 62,000 Asphalt Pavement Markings 1 LS $ 2, $ 2,000 Erosion Control 1 LS $ 3, $ 3,000 Traffic Control 1 LS $ 10, $ 10,000 PEDESTRIAN TUNNEL Masonry Wing Walls 900 SF $ $ 45,000 Concrete Tunnel Floor Slab 30 CY $ 1, $ 36,000 Concrete Tunnel Walls 75 CY $ 1, $ 90,000 Concrete Tunnel Ceiling 60 CY $ 1, $ 72,000 Lighting 1 LS $ 30, $ 30,000 SUBTOTAL = $ 507,000 Mobilization 10% $ 51,000 Contingency (Estimating & Construction) 30% $ 167,000 WSDOT Oversight & Plan Review 3% $ 22,000 Engineering 20% $ 145,000 Construction Engineering & Inspection 20% $ 174,000 ALTERNATIVE 3 PRELIMINARY COST = $ 1,066,000 The opinion of most probable cost herein is based on our perception of current conditions at the project location. This estimate reflects our opinion of probable costs at this time and is subject to change as the project design matures. Keller Associates has no control over variances in the cost of labor, materials, equipment, services provided by others, contractor s methods of determining prices, competitive bidding or market conditions, practices or bidding strategies. Keller Associates cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not vary from the costs presented herein. Concept Alternative Estimates.xlsx Page 2
49 Project: Critchfield Study Engineer: Scott Linja, EI Client: LCVMPO 733 5th Street, Suite A Clarkston, Washington Printed: November 27, 2017 Phone: Fax: ENGINEER'S OPINION OF PROBABLE CONSTRUCTION COST ALTERNATIVE 5 - PEDESTRIAN BRIDGE QUANTITY UNITS UNIT PRICE COST SITEWORK Rock Removal & General Excavation 500 CY $ $ 10,000 Asphalt (Pathway Repair) 35 TONS $ $ 9,000 New Guardrail 180 LF $ $ 5,000 New Guardrail End Flares (Type 1) 2 EA $ 2, $ 5,000 Erosion Control 1 LS $ 3, $ 3,000 Traffic Control 1 LS $ 5, $ 5,000 PEDESTRIAN BRIDGE Concrete Columns 38 CY $ 1, $ 46,000 Concrete Ramps & Landings 100 CY $ 1, $ 120,000 Steel Pedestrian Bridge 980 SF $ $ 294,000 Handrailing 800 LF $ $ 140,000 Lighting 1 LS $ 30, $ 30,000 Power Line Relocation 1 LS $ 12, $ 12,000 SUBTOTAL = $ 679,000 Mobilization 10% $ 68,000 Contingency (Estimating & Construction) 30% $ 224,000 WSDOT Oversight & Plan Review 3% $ 30,000 Engineering 20% $ 194,000 Construction Engineering & Inspection 20% $ 233,000 ALTERNATIVE 5 PRELIMINARY COST = $ 1,428,000 The opinion of most probable cost herein is based on our perception of current conditions at the project location. This estimate reflects our opinion of probable costs at this time and is subject to change as the project design matures. Keller Associates has no control over variances in the cost of labor, materials, equipment, services provided by others, contractor s methods of determining prices, competitive bidding or market conditions, practices or bidding strategies. Keller Associates cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not vary from the costs presented herein. Concept Alternative Estimates.xlsx Page 4
JEP John E. Jack Pflum, P.E. Consulting Engineering 7541 Hosbrook Road, Cincinnati, OH Telephone:
JEP John E. Jack Pflum, P.E. Consulting Engineering 7541 Hosbrook Road, Cincinnati, OH 45243 Email: jackpflum1@gmail.com Telephone: 513.919.7814 MEMORANDUM REPORT Traffic Impact Analysis Proposed Soccer
More informationWEBER ROAD RESIDENTIAL DEVELOPMENT Single Family Residential Project
WEBER ROAD RESIDENTIAL DEVELOPMENT Single Family Residential Project WEBER ROAD RESIDENTIAL DEVELOPMENT TRAFFIC IMPACT STUDY TABLE OF CONTENTS 1.0 Executive Summary Page 2.0 Introduction 2.1 DEVELOPMENT
More informationThe Highline Development Traffic Impact Study
The Highline Development Traffic Impact Study Columbia Falls, Montana Prepared For: TD&H Engineering 450 Corporate Drive, Suite 101 Kalispell, MT 59901 June, 2018 130 South Howie Street Helena, Montana
More informationTRAFFIC IMPACT STUDY MANUFACTURING COMPANY
TRAFFIC IMPACT STUDY For MANUFACTURING COMPANY Prepared For: Airway Heights, WA Prepared By: SUNBURST ENGINEERING, P. S. 4310 S. Ball Dr. Veradale, WA 99037 April, 2013 TRAFFIC IMP ACT STUDY Manufacturing
More informationMEMORANDUM. The study area of the analysis was discussed with City staff and includes the following intersections:
MEMORANDUM DATE: JULY 6, 2012 TO: FROM: RE: CC: MELANIE KNIGHT BRAD BYVELDS/ JENNIFER LUONG 1050 SOMERSET STREET PRELIMINARY TRAFFIC ANALYSIS OUR FILE NO. 111152 NEIL MALHOTRA The purpose of this memo
More informationAddendum No: 1 THE FOLLOWING IS BEING ISSUED AS ADDENDUM NO. 1 PLEASE REVIEW THE FOLLOWING PAGES. Firm: Address
CITY OF WACO Purchasing Services Post Office Box 2570 Waco, Texas 76702-2570 254 / 750-6640 Fax: 254 / 750-8063 www.waco-texas.com Date: 11/6/17 RFB No: 2017-066 Commodity: Sidewalk Improvement Plans Closing
More informationApril 10, Mr. Curt Van De Walle, City Manager City of Castle Hills 209 Lemonwood Drive Castle Hills, Texas 78213
Mr. Curt Van De Walle, City Manager City of Castle Hills 209 Lemonwood Drive Castle Hills, Texas 78213 Subject: Revised Castle Hills BASIS Charter School Traffic Impact Analysis Review City of Castle Hills,
More informationTRAFFIC ALERT FOR WEEK OF February 4 8, 2008
TRAFFIC ALERT FOR WEEK OF February 4 8, 2008 Highway work zones in the Staunton District The following is a list of highway work that might affect traffic in the Staunton transportation district during
More informationTRAFFIC IMPACT STUDY. Platte Canyon Villas Arapahoe County, Colorado (Arapahoe County Case Number: Z16-001) For
TRAFFIC IMPACT STUDY For Platte Canyon Villas Arapahoe County, Colorado (Arapahoe County Case Number: Z16-001) February 2015 Revised: August 2015 April 2016 July 2016 September 2016 Prepared for: KB Home
More informationTRAFFIC IMPACT STUDY
TRAFFIC IMPACT STUDY TERRE HAUTE CONVENTION CENTER WABASH AVENUE & 9 TH STREET TERRE HAUTE, INDIANA PREPARED FOR 8365 Keystone Crossing, Suite 201 Indianapolis, IN 46240 Phone: (317) 202-0864 Fax: (317)
More informationCE351 Transportation Systems: Planning and Design
CE351 Transportation Systems: Planning and Design TOPIC: Level of Service (LOS) at Traffic Signals 1 Course Outline Introduction to Transportation Highway Users and their Performance Geometric Design Pavement
More informationMarket Street PDP. Nassau County, Florida. Transportation Impact Analysis. VHB/Vanasse Hangen Brustlin, Inc. Nassau County Growth Management
Transportation Impact Analysis Market Street PDP Nassau County, Florida Submitted to Nassau County Growth Management Prepared for TerraPointe Services, Inc. Prepared by VHB/Vanasse Hangen Brustlin, Inc.
More information10701 TRAFFIC CONTROL 1.00 LUMP SUM $4, $4, $ $4, $4, %
ACCOUNT NO. 10154-403-172 ACCOUNT NO. 10154-403-174 ACCOUNT NO. 11712-84-174-84600 ACCOUNT NO. 10154-403-172 10701 TRAFFIC CONTROL 1.00 LUMP SUM $4,000.00 $4,000.00 0.00 $0.00 1.00 $4,000.00 1.00 $4,000.00
More informationSignalized Intersections
Signalized Intersections Kelly Pitera October 23, 2009 Topics to be Covered Introduction/Definitions D/D/1 Queueing Phasing and Timing Plan Level of Service (LOS) Signal Optimization Conflicting Operational
More informationCVS Derwood. Local Area Transportation Review
CVS Derwood Montgomery County, Maryland May 27, 2016 Local Area Transportation Review Prepared for: JC Bar Properties, Inc. Steve Fleming, PE 415 Fallowfield Road, Suite 301 Camp Hill, Pennsylvania 17011
More informationTRANSPORTATION IMPACT STUDY WHEELER STREET CLOSURE
TRANSPORTATION IMPACT STUDY WHEELER STREET CLOSURE Village of Greene, Chenango County, New York Prepared for: VILLAGE OF GREENE 49 Genesee Street Greene, NY 13778 Prepared by: LARSON DESIGN GROUP 1000
More informationTraffic Impact Study
Traffic Impact Study Statham DRI One University Parkway Prepared for: Barrow County Prepared by: October 2012 Table of Contents Executive Summary i Section 1. Introduction 1 Project Description 1 Methodology
More informationCity of Saginaw Right of Way Division Snow and Ice Removal Policy January 18, 2016
Snow and Ice Removal Policy January 18, 2016 It is the policy of the to provide snowplowing and ice removal services in order to: Provide safe traveling conditions for motorists and pedestrians Assist
More informationAirline Road: is a two lane residential roadway adjacent to the west side of the proposed school site with a speed limit of 30 mph.
HIGHLAND PARK ISD TRAFFIC IMPACT STUDY REPORT FOR PROPOSED HPISD ELEMENTARY SCHOOL SITE ON NORTHWEST HIGHWAY BETWEEN AIRLINE ROAD AND DURHAM IN THE CITY OF DALLAS, TEXAS PURPOSE OF STUDY The purpose of
More informationTRANSPORTATION AND TRAFFIC ANALYSIS REPORT
Square One Drive Extension Municipal Class Environmental Assessment Environmental Study Report Appendix B Transportation and Traffic Analysis Report TRANSPORTATION AND TRAFFIC ANALYSIS REPORT FINAL DRAFT
More informationFINAL Traffic Report for the Proposed Golden Valley Road and Newhall Ranch Road Projects in the City of Santa Clarita, California May 5, 2005
FINAL Traffic Report for the Proposed Golden Valley Road and Newhall Ranch Road Projects in the City of Santa Clarita, California May 5, 2005 Prepared For: EDAW, Inc. 1420 Kettner Boulevard, Suite 620
More informationAnnual Collision Report
2016 Annual Collision Report Contents The Annual Collision Report is a summary of statistics associated with traffic collisions that occurred in the City of Winnipeg. This information is provided by Manitoba
More informationMunicipal Act, 2001 Loi de 2001 sur les municipalités
Municipal Act, 2001 Loi de 2001 sur les municipalités ONTARIO REGULATION 239/02 MINIMUM MAINTENANCE STANDARDS FOR MUNICIPAL HIGHWAYS Consolidation Period: From January 25, 2013 to the e-laws currency date.
More informationFIG. A1 TODDY THOMAS SCHOOL - NORTH SAFE ROUTES TO SCHOOL CONCEPTUAL LAYOUT CITY OF FORTUNA TODDY THOMAS SCHOOL - NORTH GENERAL NOTES KEYNOTES
GENERAL NOTES. NEW & RELOCATED ROADWAY SIGNS NOT SHOWN FOR CLARITY BUT, ARE INCLUDING IN CONCEPTUAL DESIGN COST ESTIMATE. KEYNOTES E X I S T I N G D E V E L O P M E N T. NEW 5' WIDE CONCRETE SIDEWALK.
More information20217 CLEAR STONE TON $14.20 $5, $ $ $ %
ACCOUNT NO: 10332-84-174-84300: 54250(91223) ACCOUNT NO: 10529-403-172: 54440 (91226) ACCOUNT NO: 10463-51-130: 54250 (91223) ACCOUNT NO: 10332-84-174-84300: 54250 (91223) 20217 CLEAR STONE 375.00 TON
More informationCommittee Meeting November 6, 2018
Committee Meeting November 6, 2018 Agenda Where we are in the process Land Use Plan Transportation Element Housing & Neighborhoods Elements Next Steps Schedule November 6: Plan Elements December: Plan
More information1.0 INTRODUCTION AND SUMMARY...
TABLE OF CONTENTS 1.0 INTRODUCTION AND SUMMARY... 1 1.1 Purpose and Study Objective... 1 1.2 Executive Summary... 1 2.0 ROADWAY CONDITIONS... 5 2.1 Granville Parkway (South Intersection)... 8 2.2 Tuscany
More informationTravel Demand Management Plan
Travel Demand Management Plan Tryg s & Apartment Building 8 West Lake Street Minneapolis, MN AUTHORIZED PROPERTY REPRESENTATIVE: By Dated: Mr. Johnny Carlson Trammell Crow Chicago Development, Inc. 5 South
More informationSUBJECT: SUMMARY OF FINDINGS. October 29, Mr. Carter Redish Carter Group Architects, Inc S. El Camino Real, Suite F San Clemente, CA 92672
October 29, 2018 Mr. Carter Redish Carter Group Architects, Inc. 1810 S. El Camino Real, Suite F San Clemente, CA 92672 SUBJECT: CANYON STEEL FOCUSED TRAFFIC IMPACT ANALYSIS Dear Mr. Carter Redish: Urban
More informationROAD SAFETY AUDIT. VFW Parkway at Spring Street at Bridge Street (Route 109) City of Boston. November 13, Prepared For: MassDOT Highway Division
ROAD SAFETY AUDIT VFW Parkway at Spring Street at Bridge Street (Route 109) City of Boston November 13, 2015 Prepared For: MassDOT Highway Division Prepared By: Nitsch Engineering 2 Center Plaza, Suite
More informationNATHAN HALE HIGH SCHOOL PARKING AND TRAFFIC ANALYSIS. Table of Contents
Parking and Traffic Analysis Seattle, WA Prepared for: URS Corporation 1501 4th Avenue, Suite 1400 Seattle, WA 98101-1616 Prepared by: Mirai Transportation Planning & Engineering 11410 NE 122nd Way, Suite
More informationDOLLAR GENERAL PROJECT FOCUSED TRAFFIC ANALYSIS (REVISED) May 20, 2015
DOLLAR GENERAL PROJECT FOCUSED TRAFFIC ANALYSIS (REVISED) May 20, 2015 May 20, 2015 Mr. Dan Biswas, VP of Development CJS DEVELOPMENT II, LLC 5111 North Scottsdale Road, Suite 200 Scottsdale, CA 85250
More informationBrandywine Road Speed Study FINAL REPORT
Brandywine Road Speed Study FINAL REPORT City of Albuquerque Brandywine Road Speed Study Final Report Albuquerque, New Mexico City of Albuquerque May, 2016 Brandywine Road Speed Study Final Report City
More informationSubject: Desert Palisades Specific Plan - Tram Way Access Sight Distance
Endo Engineering Traffic Engineering Air Quality Studies Noise Assessments July 13, 2015 Mr. Ed Freeman Pinnacle View, LLC P.O. Box 1754 Lake Oswego, OR 97035-0579 Subject: Desert Palisades Specific Plan
More informationSHORT NIGHTTIME WATER SHUTDOWN TO OCCUR IN EARLY HOURS OF MAY 29
Thank you for your interest in the Center City Connector Streetcar. In this weekly update, you ll find information about ongoing construction for the 1st phase of utility work in Pioneer Square. UPDATES
More informationChapter 3 Snow & Ice Training Program Annual Review Checklist Wing Plow Operational Guidelines
Chapter 3 Snow & Ice Training Program Annual Review Checklist Wing Plow Operational Guidelines Snow & Ice Training Program WSDOT employees are our most important resource and providing a safe environment
More information20217 CLEAR STONE TON $14.20 $5, $ $ $ %
ACCOUNT NO: 10332-84-174-84300: 54250(91223) ACCOUNT NO: 10529-403-172: 54440 (91226) ACCOUNT NO: 10463-51-130: 54250 (91223) ACCOUNT NO: 10332-84-174-84300: 54250 (91223) 20217 CLEAR STONE 375.00 TON
More informationTOWN OF GRAND FALLS WINDSOR
TOWN OF GRAND FALLS WINDSOR DEPARTMENT OF ENGINEERING AND WORKS FREQUENTLY ASKED QUESTIONS FOR WINTER OPERATIONS... What streets are the first to be plowed & salted/sanded? The roads crews are each assigned
More informationCity of Brainerd, Minnesota Snowplowing Policy
City of Brainerd, Minnesota Snowplowing Policy 1. Introduction The city of Brainerd, Minnesota, finds that it is in the best interest of the residents of the city to assume basic responsibility for control
More informationConstruction Exits Vibration grids
Construction Exits Vibration grids SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils [1] Type 3 System Supplementary Trap Dispersive Soils [1]
More informationMADISON, WI STONE HOUSE DEVELOPMENT 1000 E. WASHINGTON AVENUE REDEVELOPMENT TRANSPORTATION STUDY DECEMBER 14, 2015
MADISON, WI STONE HOUSE DEVELOPMENT 1000 E. WASHINGTON AVENUE REDEVELOPMENT TRANSPORTATION STUDY DECEMBER 14, 2015 TABLE OF CONTENTS... 3 Proposed Development... 3 Methodology... 3 Phase 1 Development...
More informationCHAPTER 3. CAPACITY OF SIGNALIZED INTERSECTIONS
CHAPTER 3. CAPACITY OF SIGNALIZED INTERSECTIONS 1. Overview In this chapter we explore the models on which the HCM capacity analysis method for signalized intersections are based. While the method has
More informationSNOW REMOVAL - REQUEST FOR PROPOSAL. Snow Removal/Clearing and Sanding/Salting for Winter Fundy Ocean Research Center for Energy
Fundy Ocean Research Center for Energy SNOW REMOVAL - REQUEST FOR PROPOSAL Snow Removal/Clearing and Sanding/Salting for Winter 2016-17 Sites 1. FORCE Sub-Station Driveway (portion of Old Black Rock Road),
More informationSample Snow Services Proposal Alle Rorie 7157 E Kemper Rd Cincinnati, OH Phone: (800)
Sample Snow Services Proposal Alle Rorie 7157 E Kemper Rd Cincinnati, OH 45249 Phone: (800) 280-5153 Email: goisales@gisdynamics.com Service Address Corporate America Jim Smith 1 Corporate Way Cincinnati,
More informationTable of Contents Introduction... 4 Study Area... 5
Table of Contents Introduction... 4 Study Area... 5 Streets and s... 5 Traffic Volumes... 8 Recent and Anticipated Development... 10 Crash Analysis... 10 Projected Traffic Volumes... 11 Trip Generation...
More informationAppendix I: Traffic Study
City of Fontana Sierra Lakes Commerce Center Draft EIR Appendix I: Traffic Study FirstCarbon Solutions H:\Client (PN JN)\0144\01440050\EIR\1 ADEIR\01440050 Sec99 99 Appendix Dividers.doc THIS PAGE INTENTIONALLY
More informationLIC SR INTERCHANGE OPERATIONS STUDY
LIC SR 16 18.20 - INTERCHANGE OPERATIONS STUDY Project Summary Location SR 16 & W. Church St. Interchange Newark, Ohio Licking County PID 99478 Study Sponsor ODOT District 5 Proposed Work Add Left Turn
More information12"CMP DIA. ELEV. PVC CI DI CMP VCP RCP RCAP LRCP LCPP STA. LA LB BM-2 ROW PI POT LF TH PVC
PLANS FOR X-REFS: FILE PATH: Z:\WEST BRANCH 3682 MAIN STREET SIDEWALK IMPROVEMENTS - PHASE 3\DRAWINGS\_PRODUCTION DRAWINGS\TITLE & INDEX PLOTTED: Thursday, May 26, 216 4:7:42 PM MAIN STREET SIDEWALK PHASE
More informationFranklin County Engineer's Office - Highway Design Dublin Road And Fishinger Road Improvements Rebid Bid Tabulation
2/20/2015 Page 1 of 16 Strawser Paving Co., Inc. Double Z Construction Co Decker Construction Company Shelly & Sands, Inc. 1595 Frank Road 2550 Harrison Road 3040 McKinley Avenue P.O.Box 2469 Columbus,
More informationPLAZA MEXICO RESIDENCES
PLAZA MEXICO RESIDENCES TRAFFIC STUDY PREPARED FOR: 3000 E. IMPERIAL, LLC. 6940 Beach Boulevard, D-501 Buena Park, California 90621 PREPARED BY: OCTOBER 5, 2017 translutions the transportatio n solutions
More informationBruce Freeman Rail Trail
Functional Design Report Bruce Freeman Rail Trail Station Road to Concord Town Line Sudbury, Massachusetts PREPARED FOR Town of Sudbury Planning and Community Development 287 Old Sudbury Road Sudbury,
More informationActive Traffic & Safety Management System for Interstate 77 in Virginia. Chris McDonald, PE VDOT Southwest Regional Operations Director
Active Traffic & Safety Management System for Interstate 77 in Virginia Chris McDonald, PE VDOT Southwest Regional Operations Director Interstate 77 at Fancy Gap Mountain Mile markers 0-15 Built in late
More informationAppendix C Traffic Study
Final Environmental Impact Statement Appendix C Traffic Study Schofield Generating Station Project, Hawaii October 2015 C-1 Final Environmental Impact Statement This page intentionally left blank. Schofield
More informationMEMORANDUM (DRAFT) DRAFT
117 Commercial St. NE, Suite 310 Salem, OR 97301 503.391.8773 www.dksassociates.com MEMORANDUM (DRAFT) DATE: February 15, 2017 TO: FROM: SUBJECT: Alex Dupey, MIG Scott Mansur, PE, PTOE; Garth Appanaitis,
More informationSubmittal/Approval Letter
Submittal/Approval Letter To: Patrick Muench, P.E. Date: May 1, 2017 Turnpike Design Engineer Financial Project ID: 436517-1-52-01 & 436517-3-52-01 New Construction ( ) RRR ( ) Federal Aid : Not Applicable
More informationSpeed Limit Review. Montague Road, West End. Prepared for Brisbane City Council CEB06842 CEB06842
Speed Limit Review Montague Road, West End CEB06842 CEB06842 Prepared for Brisbane City Council 2 November 2016 Speed Limit Review Montague Road, West End Document Information Prepared for Brisbane City
More informationMonroe County: Key West and Lower Keys
FDOT PROJECT UPDATES June 15-21, 2015 Monroe County: Key West and Lower Keys Monroe County projects website: www.fdotmonroe.com Opt Out: If you no longer wish to receive these weekly notifications, please
More information1 h. Page 1 of 12 FINAL EXAM FORMULAS. Stopping Sight Distance. (2 ) N st U Where N=sample size s=standard deviation t=z value for confidence level
Page 1 of 12 FINAL EXAM FORMULAS Stopping Sight Distance 2 2 V V d 1.47Vt 1.075 i f a 2 2 Vi Vf d 1.47Vt 30( f 0.01 G) Where d = distance (ft) V = speed (mph) t = time (sec) a=deceleration rate (ft/sec
More informationGIS ANALYSIS METHODOLOGY
GIS ANALYSIS METHODOLOGY No longer the exclusive domain of cartographers, computer-assisted drawing technicians, mainframes, and workstations, geographic information system (GIS) mapping has migrated to
More informationThe Urbana Free Library Parking and Transportation Study
CHAMPAIGN COUNTY REGIONAL PLANNING COMMISSION The Urbana Free Library Parking and Transportation Study Final Report 7/18/2013 Champaign Urbana Urbanized Area Transportation Study (CUUATS) TABLE OF CONTENTS
More informationThe Sunland Park flyover ramp is set to close the week of March 19 until early summer
March 2, 2018 The Sunland Park flyover ramp is set to close the week of March 19 until early summer GO 10 is targeting the week of March 19 to close the Sunland Park Drive flyover entrance ramp to I 10
More informationPer your request and authorization, we have prepared this traffic evaluation for the above referenced project.
Memorandum To: From: Re: Marc Stout, P.E. City Engineer, City of Roseville Chris Gregerson, P.E., T.E. Matt Weir, P.E., T.E., PTOE Douglas Boulevard Coffee Kiosk Traffic Evaluation Roseville, California
More informationAppendix C Benchmarking Cost Estimates
REPORT Appendix C Benchmarking Cost Estimates C-1 Table C-1 Permits, Notifications & Location Services Notes: Costs associated with delays in construction have not been included in this estimate OneCall
More information1. PROJECT BACKGROUND. July 18, Alberta Infrastructure & Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8
July 18, 2005 Alberta Infrastructure & Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 Mr. Alain Momedi, P.Eng. Project Engineer Dear Mr. Momedi: H11:04 km 11.1 Erosion along
More informationPW 001 SNOW REMOVAL AND SANDING FOR ROADWAYS AND SIDEWALKS October 6, 2014 (#223-14) Original October 19, 2015; October 15, 2018 Public Works
Policy Statement: The Village of Kitscoty will provide snow and ice control on municipal streets and sidewalks according to determined priorities. Purpose: To provide direction and information to employees
More informationCUSTER COUNTY SNOW REMOVAL PROCEDURES
CUSER COUNY SNOW REMOVAL PROCEDURES Prioritization of Plow Routes County-maintained roads are plowed based upon the following prioritization criteria: 1. Arterial Roadways and School Bus routes: Arterial
More informationYORK REGION DISTRICT SCHOOL BOARD. Procedure #NP464.0, Snow/Ice Clearance and Removal
YORK REGION DISTRICT SCHOOL BOARD Procedure #NP464.0, Snow/Ice Clearance and Removal Application The Snow/Ice Clearance and Removal procedure addresses the practices to be followed with regards to the
More informationDesign Priciples of Traffic Signal
Design Priciples of Traffic Signal Lecture Notes in Transportation Systems Engineering Prof. Tom V. Mathew Contents 1 Overview 1 2 Definitions and notations 2 3 Phase design 3 3.1 Two phase signals.................................
More informationFY 2010 Continuing i Planning Program Product Report. Local Transportation and Traffic Data. Wood-Washington-Wirt Interstate Planning Commission
FY 2010 Continuing i Planning Program Product Report Local Transportation and Traffic Data Travel Time and Delay Data for Belpre and Marietta, Ohio Wood-Washington-Wirt Interstate Planning Commission CONTINUING
More informationTraffic Impact Analysis. for the STARBUCKS STORE. Located at 9900 BALBOA BOULEVARD. Submitted to CITY OF LOS ANGELES. January 2017.
Traffic Impact Analysis for the STARBUCKS STORE Located at 9900 BALBOA BOULEVARD Submitted to CITY OF LOS ANGELES January 2017 Submitted By January 5, 2017 Ken A. Aitchison, P.E. Transportation Engineering
More information6711 LEE HIGHWAY TRAFFIC IMPACT STUDY ARLINGTON, VIRGINIA
6711 TRAFFIC IMPACT STUDY ARLINGTON, VIRGINIA Prepared for: NVR, Inc. Prepared by: Wells + Associates, Inc. Michael J. Workosky, PTP, TOPS, TSOS John J. Andrus William L. Zeid, PE 703.917.6620 May 4, 2017
More informationChecklist: Deposing the Driver in an Auto Accident
Checklist: Deposing the Driver in an Auto Accident 1. PERSONAL BACKGROUND All names ever used Present and past residences for 10 years If the deponent has rented a residence, get the name and address of
More informationCITY OF NEW LONDON WINTER ROAD & SIDEWALK MAINTENANCE POLICY
CITY OF NEW LONDON WINTER ROAD & SIDEWALK MAINTENANCE POLICY GENERAL The purpose of this policy is to set up acceptable procedures and policies for the winter maintenance of public areas in the City of
More informationA Study of Red Light Cameras in Kansas City, MO
A Study of Red Light s in Kansas City, MO Prepared by the Special Operations Division Executive Summary This paper will analyze the crash data for the 29 red light cameras located in 17 intersections in
More informationI-95/I-85 INTERCHANGE ROADWAY SAFETY ASSESSMENT
FINAL REPORT I-95/I-85 INTERCHANGE ROADWAY SAFETY ASSESSMENT Prepared for: Prepared by: 117306012.B MARCH 2013 Final Report March 2013 I-95/I-85 Interchange ROADWAY SAFETY ASSESSMENT Prepared for: Prepared
More informationCITY OF BEAVER DAM SNOW & ICE REMOVAL POLICY
CITY OF BEAVER DAM SNOW & ICE REMOVAL POLICY Revised January, 2016 Approved by Operations Committee: February 1, 2016 This snow and ice removal policy guides Public Works personnel with deicing, plowing,
More informationNew Jersey Department of Transportation DATE : 04/10/12 PAGE : TABULATION OF BIDS
PAGE : 421-1 CONTRACT TIME : 12/15/12 COMPLETION DATE CONTRACT DESCRIPTION : PROJECT(S) : 100% STATE MAINTENANCE ROADWAY REPAIR CONTRACT CENTRAL, CONTRACT NO. C204, DP 11421 ROUTES US 1 NB & SB, 18 NB
More informationVIRGINIA S I-77 VARIABLE SPEED LIMIT SYSTEM FOR LOW VISIBILITY CONDITIONS
VIRGINIA S I-77 VARIABLE SPEED LIMIT SYSTEM FOR LOW VISIBILITY CONDITIONS Christopher D. McDonald, PE, PTOE Regional Operations Director, Southwest Region NRITS and ITS Arizona Annual Conference October
More informationRoundabout Level of Service
Roundabout Level of Service Rahmi Akçelik Director Akcelik & Associates Pty Ltd email: rahmi.akcelik@sidrasolutions.com web: www.sidrasolutions.com 8 January 2009 Contents 1. Introduction... 1 2. Fundamental
More informationCITY OF EAST PEORIA SNOW AND ICE CONTROL PROGRAM INTRODUCTION
CITY OF EAST PEORIA SNOW AND ICE CONTROL PROGRAM INTRODUCTION The responsibility for providing snow and ice control on East Peoria s 240 lane miles of streets and alleys rests with the Street Divisions
More informationTown of Windsor. Department of Public Works
Town of Windsor Department of Public Works 860.285.1855 TOWN OF WINDSOR PUBLIC WORKS SNOW REMOVAL PLAN In Windsor, as throughout the New England states, winter can bring a variety of weather conditions
More informationPolicy Title: Snow Removal & Ice Control Policy #: PW
Village of Fruitvale Corporate Policy Manual Policy Title: Snow Removal & Ice Control Policy #: PW-2012-01 Section: PUBLIC WORKS Initially Approved: 2012 06 04 Last Reviewed: 2013 05 06 Council Approval:
More informationSNOW CONTROL OPERATIONS
SNOW CONTROL OPERATIONS PUBLIC WORKS TEAM STREET MAINTENANCE DIVISION SNOW CONTROL OPERATIONS Standard Operating Procedures for Snow Removal Operations. 1. Plowing operations will be initiated when snow
More informationFARM 1065 PORTION 1, ATLANTIS TRAFFIC IMPACT ASSESSMENT
FARM 1065 PORTION 1, ATLANTIS TRAFFIC IMPACT ASSESSMENT February 2018 FIRST ISSUE Prepared by: JG AFRIKA (PTY) LTD Branch: Cape Town PO Box 38561 Postal code: 7430 Telephone: 021 530 1800 Email: wink@
More informationAugust 10, 2007 File:
August 10, 2007 File: 15-85-72 Alberta Infrastructure and Transportation Room 301, Provincial Building 9621-96 Avenue Peace River, AB T8S 1T4 Attention: Mr. Ed Szmata PEACE REGION (PEACE HIGH LEVEL AREA)
More informationTRAFFIC STUDY FOR THE GAFFEY POOL PROJECT LOS ANGELES, CALIFORNIA CITY OF LOS ANGELES, BUREAU OF ENGINEERING OCTOBER 2013 PREPARED FOR PREPARED BY
TRAFFIC STUDY FOR THE GAFFEY POOL PROJECT LOS ANGELES, CALIFORNIA OCTOBER 2013 PREPARED FOR CITY OF LOS ANGELES, BUREAU OF ENGINEERING PREPARED BY DRAFT TRAFFIC STUDY FOR THE GAFFEY POOL PROJECT October
More informationMonitoring Scour Critical Bridges During Floods For Local Bridge Owners. Presented by
Monitoring Scour Critical Bridges During Floods For Local Bridge Owners Presented by SAFETY FIRST DO NOT ENDANGER YOURSELF OR OTHERS WHILE MONITORING BRIDGES DO NOT ENTER FLOOD WATERS FLOOD WATERS INCLUDE
More informationParking Regulations Dundas Street West, from Bathurst Street to Dovercourt Road
STAFF REPORT ACTION REQUIRED Parking Regulations Dundas Street West, from Bathurst Street to Dovercourt Road Date: October 28, 2008 To: From: Toronto and East York Community Council Director, Transportation
More information401 PLANTMIX BITUMINOUS PAVEMENTS GENERAL Rev. June 10, 2004 401.03.16 SURFACING MISCELLANEOUS AREAS: Surfacing of road approaches and connections, street intersection areas, frontage roads, island areas,
More informationSnow Removal Policy WARREN COUNTY ENGINEER S OFFICE (WCEO) WARREN COUNTY HIGHWAY DEPARTMENT. October 16, 2014
Snow Removal Policy WARREN COUNTY ENGINEER S OFFICE (WCEO) October 16, 2014 Presented by: Neil F. Tunison, Warren County Engineer Snow Removal Policy OPERATIONS SAFETY WARREN COUNTY ENGINEER S OFFICE (WCEO)
More informationAppendix C Final Methods and Assumptions for Forecasting Traffic Volumes
Fairview Ave. and Main St. Improvements and Local Streets Plan Appendices Ada County Highway District Appendix C Final Methods and Assumptions for Forecasting Traffic Volumes January 3, 207 Appendices
More informationFocused Traffic Analysis for the One Lincoln Park Project
September 15, 2015 Mr. Bill Johnson Coldwell Banker 511 Sir Francis Drake Boulevard Greenbrae, CA 94904 Focused Traffic Analysis for the One Lincoln Park Project Dear Mr. Johnson; As requested, W-Trans
More informationCLAREMONT MASTER PLAN 2017: LAND USE COMMUNITY INPUT
Planning and Development Department 14 North Street Claremont, New Hampshire 03743 Ph: (603) 542-7008 Fax: (603) 542-7033 Email: cityplanner@claremontnh.com www.claremontnh.com CLAREMONT MASTER PLAN 2017:
More informationVehicle Motion Equations:
1 Vehicle Motion Equations: v = at + v (2.2.4) x x = v2 2 v 2a (2.2.6) v 2 = v 2 + 2a(x x ) (2.2.6) x = 1 2 at2 + v t + x (2.2.7) D b = x cos α (2.2.10) x = vt D b = v 2 v 2 2g(f G) (2.2.14) e + f s =
More informationNew Jersey Department of Transportation Extreme Weather Asset Management Pilot Study
New Jersey Department of Transportation Extreme Weather Asset Management Pilot Study Overview Prepared for: June 26, 2018 Introduction Overview of Pilot Study New Jersey s Climate New Jersey s Transportation
More informationFlood Scenario Worksheet
Flood Scenario Worksheet Scenario adapted from: http://www.epa.gov/watersecurity/tools/trainingcd/simple/source/scenario-8/ssc8-0.pdf Simple Tabletop Exercise, Interdependency Natural Disaster Scenario,
More informationHSIP FUNDING APPLICATION
Page 1 Lucas County - Sylvania Ave at Centennial Rd DATE 5/1/2013 Project Information: COUNTY Lucas County LOCATION TYPE PROJECT SERVICE LIFE 20 years SEGMENT INFORMATION ROUTE BEGIN SLM END SLM PRESENT
More informationMunicipality of Grey Highlands Policy
Municipality of Grey Highlands Policy Policy Name: Maintenance Standards Plan for Municipal Roadways Policy Number: A09-T-02 Department: Transportation & Environmental Services Authority: Director of Transportation
More information2014 Data Collection Project ITE Western District
2014 Data Collection Project ITE Western District Project Completed By: Oregon State University OSU ITE Student Chapter 101 Kearney Hall Corvallis, OR 97331 Student Coordinator: Sarah McCrea (OSU ITE Student
More informationS.170 th Street Micro-Simulation Seattle-Tacoma International Airport Port of Seattle/Aviation Planning
Seattle-acoma International Airport Port of Seattle/Aviation Planning Port of Seattle PO OF SEAE Aviation Planning Airport Operations January 24, 2013 Summary he Port is planning to relocate the cell phone
More information