1 Public Disclosure Authorized AFRICA Ethiopia Environment & Natural Resources Global Practice IBRD/IDA Specific Investment Loan FY 2014 Seq No: 4 ARCHIVED on 03-Dec-2015 ISR21446 Implementing Agencies: Ministry of Agriculture Public Disclosure Authorized Key Dates Key Project Dates Bank Approval Date:22-Nov-2013 Planned Mid Term Review Date:20-Jun-2016 Original Closing Date:07-Apr-2019 Project Development Objectives Effectiveness Date:07-Apr-2014 Actual Mid-Term Review Date:-- Revised Closing Date:07-Apr-2019 Public Disclosure Authorized Project Development Objective (from Project Appraisal Document) The Project's Development and Global Environment Objective is to reduce land degradation and improve land productivity in selected watersheds in targeted regions in Ethiopia. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Sustainable Land Management Project (P133410) Global Environmental Objective (from Project Appraisal Document) The Project's Development and Global Environment Objective is to reduce land degradation and improve land productivity in selected watersheds in targeted regions in Ethiopia. Public Disclosure Authorized Has the Global Environmental Objective been changed since Board Approval of the Project Objective? No Components Name Component 1: Integrated Watershed and Landscape Management:(Cost $73.98 M) Component 2: Institutional Strengthening, Capacity Development and Knowledge Generation and Management:(Cost $16.98 M) Component 3: Rural Land Administration, Certification and Land Use:(Cost $12.20 M) Page 1 of 13

2 Component 4: Project Management:(Cost $4.45 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Progress towards achievement of GEO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions The team commends the strong commitment and leadership of the Government of Ethiopia (GoE) to its long-term SLM Program, which the Bank team views as a flagship that demonstrates Ethiopia s leadership globally on resilient landscapes, as well as the high level of regional and local mobilization, action and ownership of SLMP-2 and associated projects. For this reason, Government commitment rating has been upgraded to Highly Satisfactory given the leading role SLMP plays as the flagship for the country s NRM agenda, which is reflected in the name change of the implementing agency to the Ministry of Agriculture and Natural Resources (MoANR). Some aspects of project implementation, however, should live up to this high level of ownership and visibility, corresponding to the extensive anecdotal evidence of massive success on the ground in transforming landscapes and livelihoods. As of Oct 31, 2015, nearly a third of the funding of SLMP-2 has been disbursed and was slightly above the original target, and this amount has risen dramatically since then as of November 13th. According to the interim financial report (IFR) for the quarter ended July 7, 2015, the cumulative budget utilization is 55 percent, indicating improvement from 36 percent noted in January On-the-ground implementation of project activities started in April Various physical, biological and agronomic land management practices were implemented in selected micro-watersheds of all project watersheds/woredas in the six regions. Some progress was also noted with regard to the on the issuance of the second-level certificates to the individual land/parcels. In addition, different capacity building activities mainly extensive trainings focusing on different topics/thematic areas (watershed management, land administration and certification, safeguard, procurement, financial management, etc) were given to the project staff working at federal, regional and woreda levels including Development Agents (DAs) working in respective micro-watersheds. Moreover, farmers training, awareness raising and farmers field days and knowledge exchange visits were conducted at community level in all selected micro-watersheds of project woredas. Overall, progress has been modest for component 1 (Integrated Watershed and Landscape Management) and component 3 (Rural Land Administration, Certification and Use) to date. It should be noted however that there were delays in the start-up of the planned activities and that the initial project implementation period more or less overlapped with the rainy season which went through October this past year. This can partly explain the lag in achievements. Another key aspect that caused delays is the preparation and approval of the consolidated Annual Work Plan and Budget (AWPB). The task team discussed options with the national and regional PSUs and development partners (DPs) for on time delivery of the AWPB, as each year the AWPB is delivered late resulting in disbursement delays by a quarter on averages and corresponding delays in project execution on the ground. In this regard, agreement reached to resolve this issue by synchronizing the AWPB timeline with the overall Government of Ethiopia (GoE) work planning and budgeting process. Accordingly, the AWPB process should generally start in October as stated in the PIM. For the next AWPB, the draft regional AWPBs should start to be assembled now and into January and, over the following months, refined and aggregated so that the nationwide AWPB can be approved by MoANR and then the WB in May-June for budget release in July at the same time as other Government programs. With regard to the Monitoring and evaluation, the task team appreciates the recent progress made by the Ministry of Agriculture and Natural Resources (MoANR) in improving SLMP s programmatic long-term M&E system. In this regard, the MoANR has developed and approved the program-wide harmonized M&E framework and implementation manual including standardized reporting templates earlier this year. However, there are still problems with data collection, consistency, reporting and aggregation issues at all levels. The other critical issue is the delay in the finalization and implementation of Climate Smart Agriculture (CSA) field manual. The Zero Draft CSA field manual developed by PSU/MoANR through a highly participatory process. In addition, the development of the harmonized national Small-Scale Irrigation (SSI) planning, design and implementation guideline has also been delayed mainly due to the delay in the procurement process of hiring a consultant. The Bank team is closely following up on the finalization of both the CSA and harmonized SSI manuals and provides regular intensive technical and advisory support to the PSU. Page 2 of 13

3 Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Moderate Moderate Macroeconomic -- Low Low Sector Strategies and Policies -- Moderate Moderate Technical Design of Project or Program -- Moderate Moderate Institutional Capacity for Implementation and Sustainability -- Substantial Substantial Fiduciary -- Substantial Substantial Environment and Social -- Moderate Moderate Stakeholders -- Substantial Substantial Other Overall -- Substantial Substantial Results Project Development Objective Indicators PHINDPDOTBL 1. Total incremental land area brought under sustainable and climate-smart/resilient land management practices (Hectare(Ha), Custom) Value Page 3 of 13

4 Reported cumulatively. This ISR is using achievement numbers from the national PSU Project Implementation Status Report from SLMP-2 (July 2014-June 2015) sent to the WB in August The target value for December is 600,000 Ha and actual achievement at end June is only at 55% (330,310 Ha) of that with 6 months to go. PHINDPDOTBL 2. Total area of restored or reforested/afforested on both individual and communal land (Hectare(Ha), Custom) Value According to the results framework, data for this indicator is expected after the second year. This indicator continues to lack a target (not in PAD), which will be set when the baseline study is conducted (starting end 2015). Selection of the consulting firm for the baseline survey has been finalized and the contract awarded. The firm will start working end PHINDPDOTBL 3. Increase in the amount of biomass in the intervention areas (Ton/Ha) (Hectare(Ha), Custom) Value According to the results framework, progress data for this indicator is expected at mid-term and at the end of project evaluation. This indicator continues to lack a target (not in PAD), which will be set when the baseline study is conducted (starting end 2015). Selection of the consulting firm for the baseline survey has been finalized and the contract awarded. The firm will start working end The firm will examine the applicability of using Ex-Act as measuring method for Biomass/Carbon. Overall Monitoring & Evaluation (M&E) and reporting: The task team placed a strong emphasis on M&E given the strategic importance of: (i) monitoring to assess progress and draw lessons to support quality implementation and scaling up; (ii) reporting for continued and scaled up financing for resilient landscapes throughout the country; and (iii) the past recognition that M&E implementation has been unsatisfactory. To address the above challenges, the task team added value by recommending a series of near-term and medium-term actions as detailed in the October 2015 Aide Memoire and agreed with MoANR. At the same time, the task team recognized the recent progress made by MoANR in improving SLMP s programmatic long-term M&E system, as evidenced by: (i) the development and approval of the program-wide harmonized M&E framework and implementation manual and standardized reporting templates earlier this year; (ii) rolling out of associated training by GIZ and MoANR; and (iii) M&E staffing in place. In addition, a series of recent communication or knowledge products (three films and a new case study) has helped raise the profile and achievements of SLMP but there remains a serious need to provide the accompanying quantitative evidence. This ISR is using achievement numbers from the national PSU Project Implementation Status Report from SLMP-2 (July 2014-June 2015) sent to Page 4 of 13

5 PHINDGEOTBL PHINDGEOTBL the WB in August The methods used to aggregate these numbers from the six regions has not been sufficiently documented or explained by the client. Overall, the results framework for SLMP-2 shows modest progress in terms of tangible achievements. However, in particular in the third component some progress was noted for the number of targeted communal lands issued with geo-referenced map-based land certificates (Rural Land Administration, Certification and Use). There has also been positive progress with regard to the training activities both for key service providers and land users in component two (Capacity Development, Knowledge Generation and Management). These numbers are now also gender disaggregated. Overall progress has been modest for component 1 (Integrated Watershed and Landscape Management) to date. It should be noted however that there were delays in the start-up of this program and that the initial project implementation period more or less overlapped with the rainy season which went through October this past year. This can partly explain the lag in achievements. Another key aspect that caused delays is the timing of the planning process. Furthermore, the October 2015 visits made in selected watersheds/woredas confirmed good progress on the ground and also noted problems with data collection, data consistency in reporting and data aggregation issues. Also, some indicators can only be measured once baseline data becomes available. Going forward a concentrated effort is required to ensure timely, consistent and accurate data collection and a number of action points have been included in this Aide-Memoire to that effect. The October 2015 mission noted that the domestic firm hired by the MoANR to carry out the baseline survey did not participate in the mission, which was an opportunity lost. Global Environmental Objective Indicators 2. Total area of restored or reforested/afforested on both individual and communal land (Hectare(Ha), Custom) Value Same as indicator 1 in PDO. 3. Increase in the amount of biomass in the intervention areas (Ton/ha) (Hectare(Ha), Custom Supplement) Value Overall For indicator 3 above, it is the same as indicator 3 in PDO. Intermediate Results Indicators Page 5 of 13

6 1. Land users (households) adopting at least three additional sustainable and climate-smart/resilient land management practices on individual lands disaggregated by gender (Percentage, Custom) Value Data for this indicator is due December 2015 according to the results framework. According to the current watershed plans, households are now adopting at least one practice, but within the context of the new watershed plans, next data collection will include households adopting at least three practices. Not reported on (July 7, 2015). Reporting due December Total land area in hectares (individual and communal) brought under a catchment management system as a result of the project (Hectare(Ha), Custom) Value No new data. This indicator will be reported on annually after the second project year as per the results framework. 3. Amount of carbon accumulation in 10 selected watersheds below and above ground as a result of the project (Tones/year, Custom) Value This indicator continues to lack a target (not in PAD), which will be set when the baseline study is conducted (starting end 2015). Selection of the consulting firm for the baseline survey has been finalized and the contract awarded. The firm will start working end Formal reporting on this indicator is expected after the fourth year of project implementation given the long latency for terrestrial carbon accumulation, interim reports will be provided in the meantime. Page 6 of 13

7 4. Increase in per cent of households adopting and applying backyard livestock management practice in the targeted watersheds (Percentage, Custom) Value According to the results framework, data is expected after the second year of project implementation. 5. New technologies (sustainable and climate smart/resilient practices) applied on a large scale in the project intervention areas (Number, Custom) Value "Large scale" implies at least a 10% adoption rate by households. Reporting on this indicator is not due until December Direct project beneficiaries (Number, Core) Value The direct beneficiaries of the project are 234,598 of which 36% are female beneficiaries (84,455). Page 7 of 13

8 Female beneficiaries (Percentage, Core Supplement) Value Number of land users (small holder farmers disaggregated by gender) trained in (a) planning and implementation of techniques of sustainable and climate-smart/resilient land management practices; ( (Number, Custom) Value The Client disaggregated the number by gender. Overall 32% of people trained are female. Number of land users (small holder farmers disaggregated by gender) trained in planning and implementation of techniques of sustainable and climate-smart/resilient land management practices (Number, Custom Breakdown) Value Number of land users (small holder farmers disaggregated by gender) trained in entrepreneurship, business development/management (Number, Custom Breakdown) Value Page 8 of 13

9 Number of land users (small holder farmers disaggregated by gender) trained in land rights and registration awareness (Number, Custom Breakdown) Value Number of woredas with well-equipped information centers on sustainable and climate-smart/resilient land management practices as a result of the project (Number, Custom) Value Reporting due in December Number of SLM related strategies developed or improved (Number, Custom) Value Identification of best SLM practices and updating of participatory watershed guidelines are underway and the Climate-Smart Agriculture field manual will is yet to be finalized. The indicator will be reported by the client in December 2015 according to the approved result framework. 10. Key service providers (disaggregated by gender) trained in (a) community-based watershed mgt; (b) cadastral surveying, rural land administration, certification and land use planning; (c) M&E (Number, Custom) Value Page 9 of 13

10 The client disaggregated the number by gender. Overall 19% of people trained are female. Key service providers (disaggregated by gender) trained in community-based watershed management (Number, Custom Breakdown) Value Key service providers (disaggregated by gender) trained in cadastral surveying, rural land administration, certification and land use planning (Number, Custom Breakdown) Value Key service providers (disaggregated by gender) trained in M&E and financial planning/management and procurement and other cross-cutting issues (Number, Custom Breakdown) Value Page 10 of 13

11 11. Total number (and area) of targeted communal lands issued with geo-referenced map- base land certificates. (Hectare(Ha), Custom) Value The total number of parcels of communal land issued with 2nd level certificate as of March, 2015 is 510 and as of end June, 2015 is 1,841. The amount in terms of Ha was not provided by the client due to a change in the government's procedures for acquiring maps (only EMA can provide mapping services), and is due to be reported in December Total number (and area) of targeted communal lands issued with geo-referenced map- base land certificates. (Number of Certificates) (Number, Custom Supplement) Value Number of individual land parcels covered with geo-referenced maps (Number, Custom) Value The October 2015 mission notes inconsistency in the way the PSU is reporting the data regarding 2nd level certification in its progress report. One problem is the way the intermediate-level indicator #12 is formulated. However, this indicator was originally intended to report on 2nd level certificates issued for individual holdings and not merely individual holdings covered by maps as it currently reads. 85,053 is the number of 2nd level certificates not maps. The number of individual holdings covered by maps is actually 196,754 according to the PSU progress report dated August This issue will have to be rectified through the restructuring. Page 11 of 13

12 13. Number of households in the intervention areas issued with geo-referenced map-base certificates disaggregated by gender (Number, Custom) Value The October 2015 mission noted there is an error in the PSU progress report page 16: 21,263 is the number of households (not individual holdings) with 2nd level certificates (Annex 1 of the PSU M&E report has it correctly reported, other sections do not). In February, the issuance of second-level certificates for individual parcels was 34,253 and is now up to 85, Local level participatory land use plans prepared and implemented at kebele level within the project intervention areas (Number, Custom) Value Overall Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P IDA Effective USD % P TF Effective USD % P TF Effective USD % P TF Effective USD % Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P IDA Effective 22-Nov Dec Apr Apr Apr-2019 Page 12 of 13

13 P TF Effective 10-Dec Dec Apr Dec Dec-2018 P TF Effective 10-Dec Dec Apr Apr Apr-2019 P TF Effective 10-Dec Dec Apr Apr Apr-2019 Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) P Sustainable Land Management Project Page 13 of 13

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report Public Disclosure Authorized AFRICA Ethiopia Environment & Natural Resources Global Practice IBRD/IDA Specific Investment Loan FY 2014 Seq No: 6 ARCHIVED on 10-Nov-2016 ISR24795 Implementing Agencies:

More information

Public Disclosure Copy. Implementation Status & Results Report Emergency Agricultural Livelihoods and Climate Resilience Project (P166328)

Public Disclosure Copy. Implementation Status & Results Report Emergency Agricultural Livelihoods and Climate Resilience Project (P166328) Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Dominica Agriculture Global Practice IBRD/IDA Investment Project Financing FY 2018 Seq No: 1 ARCHIVED on 18-Jul-2018 ISR33480 Implementing Agencies:

More information

The World Bank Zambia Water Resources Development Project (P114949)

The World Bank Zambia Water Resources Development Project (P114949) Public Disclosure Authorized AFRICA Zambia Water Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 8 ARCHIVED on 13-Jan-2018 ISR28939 Implementing Agencies: Republic of Zambia, Ministry

More information

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report Public Disclosure Authorized AFRICA Mozambique Environment & Natural Resources Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 4 ARCHIVED on 22-Jun-2016 ISR23891 Implementing Agencies:

More information

The World Bank Second Irrigation and Drainage Improvement Project (P086592)

The World Bank Second Irrigation and Drainage Improvement Project (P086592) Public Disclosure Authorized EUROPE AND CENTRAL ASIA Kazakhstan Water Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 9 ARCHIVED on 16-Dec-2017 ISR30851 Implementing Agencies: Ministry

More information

Public Disclosure Copy

Public Disclosure Copy EUROPE AND CENTRAL ASIA Uzbekistan Water Global Practice IBRD/IDA Investment Project Financing FY 2017 Seq No: 2 ARCHIVED on 12-Jan-2018 ISR30728 Implementing Agencies: Ministry of Agriculture and Water

More information

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report Public Disclosure Authorized Public Disclosure Copy AFRICA Chad Agriculture Global Practice IBRD/IDA Emergency Recovery Loan FY 2012 Seq No: 10 ARCHIVED on 25-Apr-2017 ISR27559 Implementing Agencies: Public

More information

The World Bank. Key Dates. Project Development Objectives. Components. Implementation Status & Results Report. Key Project Dates

The World Bank. Key Dates. Project Development Objectives. Components. Implementation Status & Results Report. Key Project Dates AFRICA Africa Environment Global Practice IBRD/IDA Adaptable Program Loan FY 2009 Seq No: 9 ARCHIVED on 22-Nov-2014 ISR16750 Implementing Agencies: Lake Victoria Basin Commission Key Dates Key Project

More information

The World Bank Zambia Water Resources Development Project (P114949)

The World Bank Zambia Water Resources Development Project (P114949) Public Disclosure Authorized AFRICA Zambia Water Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 9 ARCHIVED on 25-Jun-2018 ISR32561 Implementing Agencies: Republic of Zambia, Ministry

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Guinea Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 3 ARCHIVED on 01-Nov-2017 ISR30006 Implementing

More information

The World Bank. Key Dates. Project Development Objectives. Components. Implementation Status & Results Report. Key Project Dates

The World Bank. Key Dates. Project Development Objectives. Components. Implementation Status & Results Report. Key Project Dates Public Disclosure Copy AFRICA Africa Environment & Natural Resources Global Practice IBRD/IDA Adaptable Program Loan FY 2009 Seq No: 11 ARCHIVED on 18-Dec-2015 ISR21679 Implementing Agencies: Ministry

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Togo Agriculture Global Practice IBRD/IDA Specific Investment Loan FY 2011 Seq No: 9 ARCHIVED on 28-Jul-2015 ISR20315 Implementing Agencies: General Secretariat of Ministry

More information

The World Bank Cities and Climate Change (P123201)

The World Bank Cities and Climate Change (P123201) Public Disclosure Authorized AFRICA Mozambique Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Investment Project Financing FY 2012 Seq No: 13 ARCHIVED on 17-May-2018 ISR31517

More information

The World Bank Integrated Forest Ecosystem Management (P151102)

The World Bank Integrated Forest Ecosystem Management (P151102) Public Disclosure Authorized EUROPE AND CENTRAL ASIA Kyrgyz Republic Environment & Natural Resources Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 3 ARCHIVED on 08-May-2017 ISR27969

More information

Cities and Climate Change (P123201)

Cities and Climate Change (P123201) Public Disclosure Authorized AFRICA Mozambique Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Investment Project Financing FY 2012 Seq No: 14 ARCHIVED on 04-Nov-2018 ISR33750

More information

The World Bank Mali Reconstruction and Economic Recovery (P144442)

The World Bank Mali Reconstruction and Economic Recovery (P144442) Public Disclosure Authorized AFRICA Mali Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Emergency Recovery Loan FY 2014 Seq No: 7 ARCHIVED on 30-Jun-2017 ISR28723 Implementing

More information

The World Bank Uganda Energy for Rural Transformation III (P133312)

The World Bank Uganda Energy for Rural Transformation III (P133312) Public Disclosure Authorized AFRICA Uganda Energy & Extractives Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 4 ARCHIVED on 19-Jul-2017 ISR28421 Implementing Agencies: Ministry

More information

The World Bank Ecuador - Sustainable Family Farming Modernization Project (P151963)

The World Bank Ecuador - Sustainable Family Farming Modernization Project (P151963) Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Ecuador Agriculture Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 5 ARCHIVED on 17-Nov-2017 ISR30151 Implementing Agencies:

More information

NATURAL RESOURCES MANAGEMENT IN A CHANGING CLIMATE IN MALI (P145799)

NATURAL RESOURCES MANAGEMENT IN A CHANGING CLIMATE IN MALI (P145799) Public Disclosure Authorized AFRICA Mali Environment & Natural Resources Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 5 ARCHIVED on 10-Jun-2016 ISR21867 Implementing Agencies:

More information

Public Disclosure Copy. AFCC2/RI-The Eastern Electricity Highway Project under the First Phase of the Eastern Africa Power

Public Disclosure Copy. AFCC2/RI-The Eastern Electricity Highway Project under the First Phase of the Eastern Africa Power Public Disclosure Authorized AFCC2/RI-The Eastern Electricity Highway Project under the First Phase of the Eastern Africa Power Integration AFRICA Africa Energy & Extractives Global Practice IBRD/IDA Investment

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Togo Agriculture Global Practice IBRD/IDA Specific Investment Loan FY 2011 Seq No: 10 ARCHIVED on 16-Jan-2016 ISR22410 Implementing Agencies: General Secretariat of

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Belize Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 8 ARCHIVED on 18-Jun-2018

More information

The World Bank. Key Dates. Project Development Objectives. Components. Overall Ratings. Public Disclosure Authorized

The World Bank. Key Dates. Project Development Objectives. Components. Overall Ratings. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Copy AFRICA South Sudan Urban Development Global Practice IBRD/IDA Specific Investment Loan FY 2013 Seq No: 4 ARCHIVED on 11-Feb-2015 ISR18127 Implementing

More information

The World Bank Sri Lanka Agriculture Sector Modernization Project (P156019)

The World Bank Sri Lanka Agriculture Sector Modernization Project (P156019) Public Disclosure Authorized SOUTH ASIA Sri Lanka Agriculture Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 4 ARCHIVED on 09-Jan-2018 ISR31203 Implementing Agencies: Ministry of

More information

The World Bank Indonesia National Slum Upgrading Project (P154782)

The World Bank Indonesia National Slum Upgrading Project (P154782) Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Investment Project Financing FY 2017 Seq No: 4 ARCHIVED on 04-Apr-2018

More information

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report Public Disclosure Authorized AFRICA Uganda Energy & Extractives Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 1 ARCHIVED on 16-Nov-2015 ISR21261 Implementing Agencies: Ministry

More information

Zambia - Mining and Environmental Remediation and Improvement Project (P154683)

Zambia - Mining and Environmental Remediation and Improvement Project (P154683) AFRICA Zambia Environment & Natural Resources Global Practice IBRD/IDA Investment Project Financing FY 2017 Seq No: 4 ARCHIVED on 26-Nov-2018 ISR34605 Implementing Agencies: Ministry of Mines and Mineral

More information

The World Bank Sri Lanka Agriculture Sector Modernization Project (P156019)

The World Bank Sri Lanka Agriculture Sector Modernization Project (P156019) Public Disclosure Authorized SOUTH ASIA Sri Lanka Agriculture Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 3 ARCHIVED on 10-Sep-2017 ISR29482 Implementing Agencies: Ministry of

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized EAST ASIA AND PACIFIC Mongolia Finance & Markets Global Practice IBRD/IDA Investment Project Financing FY 2017 Seq No: 3 ARCHIVED on 18-Dec-2017 ISR30626 Implementing Agencies:

More information

Sierra Leone Energy Access Project - Sierra Leone Infrastructure Development Fund (P126180)

Sierra Leone Energy Access Project - Sierra Leone Infrastructure Development Fund (P126180) Public Disclosure Authorized AFRICA Sierra Leone Energy & Extractives Global Practice Recipient Executed Activities Specific Investment Loan FY 2013 Seq No: 5 ARCHIVED on 15-Apr-2016 ISR23021 Implementing

More information

The World Bank Bangladesh Modern Food Storage Facilities Project (P120583)

The World Bank Bangladesh Modern Food Storage Facilities Project (P120583) SOUTH ASIA Bangladesh Agriculture Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 5 ARCHIVED on 22-Apr-2016 ISR23210 Implementing Agencies: Directorate General, Ministry of Food Key

More information

The World Bank Ethiopia: National Quality Infrastructure Development Project (P160279)

The World Bank Ethiopia: National Quality Infrastructure Development Project (P160279) Public Disclosure Authorized AFRICA Ethiopia Trade & Competitiveness Global Practice IBRD/IDA Investment Project Financing FY 2017 Seq No: 1 ARCHIVED on 22-Jun-2017 ISR28689 Implementing Agencies: Ministry

More information

The World Bank Third Northern Uganda Social Action Fund (NUSAF 3) (P149965)

The World Bank Third Northern Uganda Social Action Fund (NUSAF 3) (P149965) Public Disclosure Authorized AFRICA Uganda Social Protection & Labor Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 5 ARCHIVED on 29-Jan-2018 ISR31243 Implementing Agencies: The

More information

Public Disclosure Copy. First Part of the Second Phase of the Niger Basin Water Resources Development and Sustainable

Public Disclosure Copy. First Part of the Second Phase of the Niger Basin Water Resources Development and Sustainable Public Disclosure Authorized First Part of the Second Phase of the Niger Basin Water Resources Development and Sustainable Ecosystems AFRICA Western Africa Water Global Practice IBRD/IDA Investment Project

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Nigeria Agriculture Global Practice IBRD/IDA Investment Project Financing FY 2017 Seq No: 1 ARCHIVED on 30-Jun-2017 ISR28944 Implementing Agencies: Federal Ministry

More information

Public Disclosure Copy. Implementation Status & Results Report Tanzania: Resilient Natural Resource Management for Tourism and Growth (P150523)

Public Disclosure Copy. Implementation Status & Results Report Tanzania: Resilient Natural Resource Management for Tourism and Growth (P150523) Public Disclosure Authorized AFRICA Tanzania Environment & Natural Resources Global Practice IBRD/IDA Investment Project Financing FY 2018 Seq No: 1 ARCHIVED on 05-Dec-2017 ISR30455 Implementing Agencies:

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized EAST ASIA AND PACIFIC Vietnam Environment & Natural Resources Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 1 ARCHIVED on 03-Nov-2016 ISR25240 Implementing

More information

The World Bank Earthquake Housing Reconstruction Project (P155969)

The World Bank Earthquake Housing Reconstruction Project (P155969) Public Disclosure Authorized SOUTH ASIA Nepal Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 1 ARCHIVED on 18-Nov-2015 ISR20331

More information

The World Bank Indonesia: Geothermal Energy Upstream Development Project (P155047)

The World Bank Indonesia: Geothermal Energy Upstream Development Project (P155047) EAST ASIA AND PACIFIC Indonesia Energy & Extractives Global Practice Recipient Executed Activities Investment Project Financing FY 2017 Seq No: 3 ARCHIVED on 20-Jan-2018 ISR30972 Implementing Agencies:

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Mali Energy & Extractives Global Practice IBRD/IDA Specific Investment Loan FY 2009 Seq No: 11 ARCHIVED on 10-Feb-2016 ISR22432 Implementing Agencies: Eenrgie du Mali

More information

The World Bank Mali Reconstruction and Economic Recovery (P144442)

The World Bank Mali Reconstruction and Economic Recovery (P144442) Public Disclosure Authorized AFRICA Mali Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 8 ARCHIVED on 19-Dec-2017 ISR30326 Implementing

More information

The World Bank Health System Performance Reinforcement Project (P156679)

The World Bank Health System Performance Reinforcement Project (P156679) Public Disclosure Authorized AFRICA Cameroon Health, Nutrition & Population Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 3 ARCHIVED on 14-Apr-2017 ISR27518 Implementing Agencies:

More information

The World Bank Livestock Sector Development Support Project (P159476)

The World Bank Livestock Sector Development Support Project (P159476) Public Disclosure Authorized AFRICA Burkina Faso Agriculture Global Practice IBRD/IDA Investment Project Financing FY 2018 Seq No: 2 ARCHIVED on 04-May-2018 ISR32278 Implementing Agencies: Ministry of

More information

Key Dates. Global Development Objectives. Components. Overall Ratings. Implementation Status and Key Decisions

Key Dates. Global Development Objectives. Components. Overall Ratings. Implementation Status and Key Decisions Public Disclosure Authorized AFRICA Western Africa Water Global Practice Global Environment Project Investment Project Financing FY 2015 Seq No: 4 ARCHIVED on 06-Nov-2017 ISR29485 Implementing Agencies:

More information

The World Bank Bangladesh Weather and Climate Services Regional Project (P150220)

The World Bank Bangladesh Weather and Climate Services Regional Project (P150220) Public Disclosure Authorized SOUTH ASIA Bangladesh Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 3 ARCHIVED on 01-Dec-2017 ISR30351

More information

The World Bank Ethiopia: Transport Systems Improvement Project (TRANSIP) (P151819)

The World Bank Ethiopia: Transport Systems Improvement Project (TRANSIP) (P151819) Public Disclosure Authorized AFRICA Ethiopia Transport & Digital Development Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 4 ARCHIVED on 25-May-2018 ISR32324 Implementing Agencies:

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized EUROPE AND CENTRAL ASIA Albania Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Investment Project Financing FY 2017 Seq No: 2 ARCHIVED on 16-Aug-2017

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized EAST ASIA AND PACIFIC Myanmar Energy & Extractives Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 5 ARCHIVED on 18-Jan-2018 ISR29499 Implementing Agencies:

More information

The World Bank Biodiversity Conservation and Rural Livelihoods Improvement (P088520)

The World Bank Biodiversity Conservation and Rural Livelihoods Improvement (P088520) Public Disclosure Authorized SOUTH ASIA India Environment & Natural Resources Global Practice IBRD/IDA Investment Project Financing FY 2011 Seq No: 14 ARCHIVED on 07-Dec-2017 ISR30690 Implementing Agencies:

More information

The World Bank Cusco Regional Development (P117318)

The World Bank Cusco Regional Development (P117318) LATIN AMERICA AND CARIBBEAN Peru Urban Development Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 3 ARCHIVED on 27-Jan-2015 ISR16645 Implementing Agencies: Cusco Regional Government

More information

Ecuador - Sustainable Family Farming Modernization Project (P151963)

Ecuador - Sustainable Family Farming Modernization Project (P151963) Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Ecuador Agriculture Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 7 ARCHIVED on 19-Nov-2018 ISR34313 Implementing Agencies:

More information

development plans that promote sustainable land and natural resources management and productive investments at commune level.

development plans that promote sustainable land and natural resources management and productive investments at commune level. Public Disclosure Authorized AFRICA Burkina Faso Agriculture Global Practice IBRD/IDA Adaptable Program Loan FY 2013 Seq No: 6 ARCHIVED on 24-Jun-2016 ISR24201 Implementing Agencies: National Coordination

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Belize Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 7 ARCHIVED on 19-Dec-2017

More information

Urban Water Supply Project (P156739)

Urban Water Supply Project (P156739) AFRICA Cote d'ivoire Water Global Practice IBRD/IDA Investment Project Financing FY 2017 Seq No: 4 ARCHIVED on 04-Oct-2018 ISR33891 Implementing Agencies: Republic of Cote d'ivoire, Cellule de Coordination

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Mali Global Practice IBRD/IDA Specific Investment Loan FY 2009 Seq No: 10 ARCHIVED on 29-Jun-2015 ISR20110 Implementing Agencies: Eenrgie du Mali (EDM-SA) Public Disclosure

More information

Public Disclosure Copy. Implementation Status & Results Report Ghana FIP - Enhancing Natural Forest and Agroforest Landscapes Project (P148183)

Public Disclosure Copy. Implementation Status & Results Report Ghana FIP - Enhancing Natural Forest and Agroforest Landscapes Project (P148183) Public Disclosure Authorized AFRICA Ghana Environment & Natural Resources Global Practice Recipient Executed Activities Investment Project Financing FY 2015 Seq No: 6 ARCHIVED on 19-Dec-2017 ISR30434 Implementing

More information

Public Disclosure Copy. Implementation Status & Results Report Small Town Water Supply and Urban Septage Management Project (P156738)

Public Disclosure Copy. Implementation Status & Results Report Small Town Water Supply and Urban Septage Management Project (P156738) Public Disclosure Authorized AFRICA Benin Water Global Practice IBRD/IDA Investment Project Financing FY 2017 Seq No: 2 ARCHIVED on 04-Dec-2017 ISR30468 Implementing Agencies: The Republic of Benin, Agence

More information

Public Disclosure Copy. Implementation Status & Results Report AGRICULTURAL COMPETITIVENESS IMPROVEMENT PROJECT (P122812)

Public Disclosure Copy. Implementation Status & Results Report AGRICULTURAL COMPETITIVENESS IMPROVEMENT PROJECT (P122812) Public Disclosure Authorized EUROPE AND CENTRAL ASIA Azerbaijan Agriculture and Rural Development Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 3 ARCHIVED on 10-Apr-2015 ISR18747

More information

EC Ibarra Transport Infrastructure Improvement Project (P147280)

EC Ibarra Transport Infrastructure Improvement Project (P147280) LATIN AMERICA AND CARIBBEAN Ecuador Transport Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 6 ARCHIVED on 04-Feb-2019 ISR35827 Implementing Agencies: Municipality of Ibarra, Municipality

More information

Public Disclosure Copy. Implementation Status & Results Report DJ-Rural Community Development and Water Mobilization Project (PRODERMO) (P117355)

Public Disclosure Copy. Implementation Status & Results Report DJ-Rural Community Development and Water Mobilization Project (PRODERMO) (P117355) Public Disclosure Authorized MIDDLE EAST AND NORTH AFRICA Djibouti Agriculture Global Practice IBRD/IDA Investment Project Financing FY 2011 Seq No: 13 ARCHIVED on 17-Jan-2018 ISR31070 Implementing Agencies:

More information

The World Bank Third Northern Uganda Social Action Fund (NUSAF 3) (P149965)

The World Bank Third Northern Uganda Social Action Fund (NUSAF 3) (P149965) Public Disclosure Authorized AFRICA Uganda Social Protection & Labor Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 2 ARCHIVED on 08-Apr-2016 ISR23131 Implementing Agencies: Office

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Brazil Agriculture Global Practice IBRD/IDA Investment Project Financing FY 2010 Seq No: 15 ARCHIVED on 29-Dec-2017 ISR30320 Implementing Agencies:

More information

The World Bank Dam Operational Improvement and Safety (P096532)

The World Bank Dam Operational Improvement and Safety (P096532) Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Water Global Practice IBRD/IDA Specific Investment Loan FY 2009 Seq No: 14 ARCHIVED on 17-Jun-2017 ISR27994 Implementing Agencies: Republic

More information

The World Bank EGYPT-Farm-level Irrigation Modernization (P117745)

The World Bank EGYPT-Farm-level Irrigation Modernization (P117745) Public Disclosure Authorized MIDDLE EAST AND NORTH AFRICA Egypt, Arab Republic of Water Global Practice IBRD/IDA Specific Investment Loan FY 2011 Seq No: 15 ARCHIVED on 24-Jul-2017 ISR28917 Implementing

More information

Public Disclosure Copy. Implementation Status & Results Report KH - Livelihood Enhancement and Association of the Poor Project (LEAP) (P153591)

Public Disclosure Copy. Implementation Status & Results Report KH - Livelihood Enhancement and Association of the Poor Project (LEAP) (P153591) Public Disclosure Authorized EAST ASIA AND PACIFIC Cambodia Agriculture Global Practice IBRD/IDA Investment Project Financing FY 2017 Seq No: 1 ARCHIVED on 17-Jun-2017 ISR28362 Implementing Agencies: Ministry

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized SOUTH ASIA Nepal Agriculture Global Practice IBRD/IDA Investment Project Financing FY 2008 Seq No: 22 ARCHIVED on 27-Apr-2018 ISR32244 Implementing Agencies: Poverty Alleviation

More information

Public Disclosure Copy

Public Disclosure Copy EUROPE AND CENTRAL ASIA Bulgaria Water Global Practice IBRD/IDA Specific Investment Loan FY 2010 Seq No: 14 ARCHIVED on 07-Feb-2016 ISR22610 Implementing Agencies: Ministry of Regional Development and

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized SOUTH ASIA India Water Global Practice IBRD/IDA Specific Investment Loan FY 2011 Seq No: 11 ARCHIVED on 17-Mar-2016 ISR21556 Implementing Agencies: National Mission for Clean

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized SOUTH ASIA Bangladesh Finance, Competitiveness and Innovation Global Practice IBRD/IDA Investment Project Financing FY 2017 Seq No: 2 ARCHIVED on 21-Mar-2018 ISR31666 Implementing

More information

The World Bank Health System Strengthening and Support Project (P152799)

The World Bank Health System Strengthening and Support Project (P152799) Public Disclosure Authorized EUROPE AND CENTRAL ASIA Turkey Health, Nutrition & Population Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 3 ARCHIVED on 23-Dec-2016 ISR25849 Implementing

More information

The World Bank Georgia National Innovation Ecosystem (GENIE) Project (P152441)

The World Bank Georgia National Innovation Ecosystem (GENIE) Project (P152441) Public Disclosure Authorized EUROPE AND CENTRAL ASIA Georgia Trade & Competitiveness Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 1 ARCHIVED on 28-Jun-2016 ISR24271 Implementing

More information

The World Bank India: Bihar Integrated Social Protection Strengthening Project (P118826)

The World Bank India: Bihar Integrated Social Protection Strengthening Project (P118826) Public Disclosure Authorized SOUTH ASIA India Social Protection & Labor Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 5 ARCHIVED on 13-May-2016 ISR23158 Implementing Agencies: Rural

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Haiti Social, Urban, Rural and Resilience Global Practice Global Practice Recipient Executed Activities Emergency Recovery Loan FY 2011 Seq No:

More information

The World Bank Ethiopia Geothermal Sector Development Project (P133613)

The World Bank Ethiopia Geothermal Sector Development Project (P133613) Public Disclosure Authorized AFRICA Ethiopia Energy & Extractives Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 8 ARCHIVED on 13-Mar-2018 ISR31676 Implementing Agencies: Ethiopian

More information

The World Bank Caribbean Regional Communications Infrastructure Program (P114963)

The World Bank Caribbean Regional Communications Infrastructure Program (P114963) Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Caribbean Transport & ICT Global Practice IBRD/IDA Adaptable Program Loan FY 2012 Seq No: 9 ARCHIVED on 25-Jan-2017 ISR26209 Implementing Agencies:

More information

Climate Adaptation and Mitigation Program for Aral Sea Basin CAMP4ASB (P151363)

Climate Adaptation and Mitigation Program for Aral Sea Basin CAMP4ASB (P151363) EUROPE AND CENTRAL ASIA Central Asia Environment & Natural Resources Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 6 ARCHIVED on 19-Dec-2018 ISR35024 Implementing Agencies: Ministry

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Guinea Water Global Practice IBRD/IDA Investment Project Financing FY 2017 Seq No: 2 ARCHIVED on 14-Apr-2018 ISR31899 Implementing Agencies: Ministry of Energy and Hydraulics

More information

Public Disclosure Copy. Implementation Status & Results Report Somali Core Economic Institutions and Opportunities Program (SCORE) (P152241)

Public Disclosure Copy. Implementation Status & Results Report Somali Core Economic Institutions and Opportunities Program (SCORE) (P152241) Public Disclosure Authorized AFRICA Somalia Trade & Competitiveness Global Practice Recipient Executed Activities Investment Project Financing FY 2016 Seq No: 2 ARCHIVED on 29-Nov-2016 ISR25649 Implementing

More information

Public Disclosure Copy. Implementation Status & Results Report UGANDA North Eastern Road-corridor Asset Management Project (NERAMP) (P125590)

Public Disclosure Copy. Implementation Status & Results Report UGANDA North Eastern Road-corridor Asset Management Project (NERAMP) (P125590) Public Disclosure Authorized AFRICA Uganda Transport & ICT Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 6 ARCHIVED on 18-Dec-2017 ISR30767 Implementing Agencies: REPUBLIC OF UGANDA,

More information

Sri Lanka Strategic Cities Development Project (P130548)

Sri Lanka Strategic Cities Development Project (P130548) SOUTH ASIA Sri Lanka Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 10 ARCHIVED on 21-Dec-2018 ISR35436 Implementing Agencies:

More information

PAMSIMAS Support Trust Fund (P116236)

PAMSIMAS Support Trust Fund (P116236) Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Water Global Practice Recipient Executed Activities Specific Investment Loan FY 2010 Seq No: 8 ARCHIVED on 17-Dec-2015 ISR22003 Implementing

More information

The World Bank Second Irrigation and Drainage Improvement Project (P086592)

The World Bank Second Irrigation and Drainage Improvement Project (P086592) Public Disclosure Authorized EUROPE AND CENTRAL ASIA Kazakhstan Water Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 8 ARCHIVED on 07-Jun-2017 ISR28508 Implementing Agencies: Ministry

More information

The World Bank Bangladesh Modern Food Storage Facilities Project (P120583)

The World Bank Bangladesh Modern Food Storage Facilities Project (P120583) Public Disclosure Authorized SOUTH ASIA Bangladesh Agriculture Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 8 ARCHIVED on 10-Nov-2017 ISR28544 Implementing Agencies: Government

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Argentina Environment & Natural Resources Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 4 ARCHIVED on 29-Jun-2017 ISR28581

More information

The World Bank CG Rep. LISUNGI Safety Nets System Project (P145263)

The World Bank CG Rep. LISUNGI Safety Nets System Project (P145263) Public Disclosure Authorized AFRICA Congo, Republic of Social Protection & Labor Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 7 ARCHIVED on 04-Dec-2017 ISR30246 Implementing Agencies:

More information

Rio de Janeiro Strengthening Public Sector Management Technical Assistance Project (P127245)

Rio de Janeiro Strengthening Public Sector Management Technical Assistance Project (P127245) Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Brazil Macroeconomics, Trade and Investment Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 8 ARCHIVED on 18-Jan-2018 ISR29371

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Rwanda Energy & Extractives Global Practice Recipient Executed Activities Investment Project Financing FY 2017 Seq No: 3 ARCHIVED on 07-May-2018 ISR32125 Implementing

More information

Public Disclosure Copy. Implementation Status & Results Report Girls Education and Womens Empowerment and Livelihood Project (P151451)

Public Disclosure Copy. Implementation Status & Results Report Girls Education and Womens Empowerment and Livelihood Project (P151451) Public Disclosure Authorized AFRICA Zambia Social Protection & Labor Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 1 ARCHIVED on 04-Sep-2015 ISR20625 Implementing Agencies: Ministry

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Argentina Environment & Natural Resources Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 3 ARCHIVED on 12-Dec-2016 ISR24148

More information

The World Bank. Increased Access to Modern Energy (P110075) Key Dates. Project Development Objectives. Components. Public Disclosure Authorized

The World Bank. Increased Access to Modern Energy (P110075) Key Dates. Project Development Objectives. Components. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Copy AFRICA Benin Energy & Extractives Global Practice IBRD/IDA Specific Investment Loan FY 2009 Seq No: 12 ARCHIVED on 18-Jan-2017 ISR25167 Implementing

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized SOUTH ASIA India Water Global Practice IBRD/IDA Specific Investment Loan FY 2011 Seq No: 13 ARCHIVED on 20-Mar-2017 ISR27142 Implementing Agencies: Public Disclosure Authorized

More information

The World Bank BF-Youth Employment & Skills Development (P130735)

The World Bank BF-Youth Employment & Skills Development (P130735) Public Disclosure Authorized AFRICA Burkina Faso Social Protection & Labor Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 8 ARCHIVED on 08-Jan-2018 ISR30015 Implementing Agencies:

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized MIDDLE EAST AND NORTH AFRICA Iraq Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 2 ARCHIVED on 27-May-2016

More information

The World Bank Transport Connectivity and Asset Management Project (P132833)

The World Bank Transport Connectivity and Asset Management Project (P132833) Public Disclosure Authorized SOUTH ASIA Sri Lanka Transport & Digital Development Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 4 ARCHIVED on 23-Mar-2018 ISR30586 Implementing Agencies:

More information

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report Public Disclosure Authorized AFRICA Nigeria Environment Global Practice IBRD/IDA Specific Investment Loan FY 2012 Seq No: 5 ARCHIVED on 04-Jun-2015 ISR17367 Implementing Agencies: Public Disclosure Authorized

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Brazil Water Global Practice IBRD/IDA Specific Investment Loan FY 2012 Seq No: 11 ARCHIVED on 30-Jun-2017 ISR28569 Implementing Agencies: SEMARH,

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized SOUTH ASIA Afghanistan Agriculture Global Practice Recipient Executed Activities Specific Investment Loan FY 2013 Seq No: 9 ARCHIVED on 16-Jun-2017 ISR28632 Implementing Agencies:

More information

The World Bank Emergency 2007 Cyclone Recovery and Restoration Project (P111272)

The World Bank Emergency 2007 Cyclone Recovery and Restoration Project (P111272) Public Disclosure Authorized SOUTH ASIA Bangladesh Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Emergency Recovery Loan FY 2009 Seq No: 17 ARCHIVED on 19-Jun-2017 ISR27863

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized SOUTH ASIA Bangladesh Trade & Competitiveness Global Practice IBRD/IDA Investment Project Financing FY 2017 Seq No: 1 ARCHIVED on 13-Oct-2017 ISR29718 Implementing Agencies:

More information

Public Disclosure Copy. Implementation Status & Results Report Strengthening Institutional Capacity for Government Effectiveness Project (P149176)

Public Disclosure Copy. Implementation Status & Results Report Strengthening Institutional Capacity for Government Effectiveness Project (P149176) Public Disclosure Authorized AFRICA Burundi Governance Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 4 ARCHIVED on 10-Jul-2017 ISR28718 Implementing Agencies: Government of Burundi,

More information