Appendix D. Hydrology and Hydraulics

Size: px
Start display at page:

Download "Appendix D. Hydrology and Hydraulics"

Transcription

1 Appendix D Hydrology and Hydraulics

2 TECHNICAL MEMORANDUM Date: February 13, 2014 Document No.: To: Paul Bergstrom Company: Rare Element Resources From: Micah Richey cc: Tammy Rauen and Roman Popielak RE: BEAR LODGE PROJECT, BULL HILL MINE PRE-FEASIBILITY HYDROLOGY AND HYDRAULICS, REVISION E 1.0 INTRODUCTION Rare Element Resources (RER) is proposing a new open-pit mine for rare earth materials north of Sundance, Wyoming referred to as the Bear Lodge Project, Bull Hill Mine. This memorandum describes pre-feasibility level hydrology and hydraulics calculations for the site. The calculations were performed in order to develop the framework for an initial stormwater management plan for the site, encompassing possible stormwater diversions, runoff collection channels, haul road culverts, and sedimentation ponds. 2.0 METHODOLOGY 2.1 Hydrology Calculations Peak stormwater flow rates contributing to, or otherwise impacting the proposed facilities at the Bear Lodge Project were estimated for the 100-year frequency, 6-hour duration storm event in accordance with the Wyoming Department of Environmental Quality, Land Quality Division s Guidelines (WDEQ). Using the site topography provided by RER, basins were delineated for the Mineable Pit, Waste Rock Facility (WRF), Haul Roads, and Plant Site (see Figure 1). The time of concentration for each basin was then estimated using TR-55 methodology (NRCS, 1986). Curve numbers for the site were assigned using TR- 55 methodology (NRCS, 1986) in conjunction with soil survey information (NRCS, 2011). The 100-year frequency, 6-hour duration, and 10-year frequency, 24-hour duration storm depths were estimated for the site from the NOAA Atlas 2 (NOAA, 1973). Hydrologic modeling was then performed using the Hydrologic Engineering Center s Hydrologic Modeling System (HEC-HMS) (USACE 2010) to calculate runoff volumes and peak flow rates. 2.2 Preliminary Sediment Pond Sizing In accordance with the Wyoming Department of Environmental Quality Water Quality Rules and Regulations, Chapter 11, Section 31, the sediment ponds are sized to accommodate runoff from the 10- year frequency, 24-hour duration event, which was modeled using HEC-HMS (Wyoming DEQ 2012). Additionally, the ponds are sized to accommodate the expected sediment. In accordance with Michigan Department of Environmental Quality guidelines, the sediment pond are sized, at a minimum, to contain I:\11\82323\0100\0122 TM\Feb14\ TM PreFeasibilityHydrologyHydraulicsRevE 13FEB14.docx Golder Associates Inc. 44 Union Boulevard, Suite 300 Lakewood, CO USA Tel: (303) Fax: (303) Golder Associates: Operations in Africa, Asia, Australasia, Europe, North America and South America Golder, Golder Associates and the GA globe design are trademarks of Golder Associates Corporation

3 Paul Bergstrom February 13, 2014 Rare Element Resources the volume of sediment equal to one inch of runoff from the entire catchment area, or 3,630 ft3/acre of sediment (Michigan DEQ 2012). In addition to storage for environmental flows from the pit and Basin Pt-N, the Pit Pond is also sized to accommodate pit dewatering flows of 500 gallons per minute (gpm). The pond water and sediment capacity is estimated using an assumed retention time (2 days) and settling velocity parameters based on particle size. 2.3 Channel and Culvert Hydraulics Channel sizing calculations were performed with an open channel flow spreadsheet using Manning s equation. Riprap sizing was performed using U.S. Army Corps of Engineers methodology (USACE, 1994). Culvert crossings were modeled using HY8 culvert analysis software (FHWA 2011). 3.0 ASSUMPTIONS Runoff from the top of the WRF travels down the 1-percent slope to the north and south then cascades perpendicular to the slopes, and is collected in a perimeter channel at the toe of the facility Haul Road culvert crossings were located based on the proposed road alignments and topography supplied by RER All calculations assume the following facility conditions: Full build out of the Pit and WRF The WRF is in a closed condition with 50-percent of the area reclaimed The Low Grade Ore (LGO) stockpile has been processed and either been sent to the Upton facility or added to the footprint of the WRF All runoff from the plant site is collected for discharge to a sedimentation pond Time of concentration for both the Plant Site and the Mineable Pit are assumed to be 10 minutes Channel lining criteria: Design Flow Velocity (ft/s) Channel Lining Material <5 Grass 5 15 Riprap >15 Concrete, Articulated Concrete Block Curve Numbers Used in hydrology calculations (NRCS,1986, Web Soil Survey): Description of Soil & Land Cover Woods-Grass Combination, HSG B, Fair Cover SCS Curve Number Applicable Site Areas Undisturbed or Reclaimed areas Newly Graded Areas, HSG B Disturbed Areas, Pit, Unreclaimed WRF, and Plant pad I:\11\82323\0100\0122 TM\Feb14\ TM PreFeasibilityHydrologyHydraulicsRevE 13FEB14.docx

4 Paul Bergstrom February 13, 2014 Rare Element Resources Storm Depths (NOAA, 1973): Storm Event 2-year 24-hour 10-year 24-hour 100-year 6-hour Storm Depth (in) Applications Tc Calculations Sedimentation Pond Volumes Conveyance Channel, Riprap, and Culvert Sizing Storm event temporal distribution Dimensionless design mass curve (Tyrell & Hasfurther 1983) Type II storm distribution Manning s n Coefficients: Manning s n Description Stability Capacity Grass Riprap Mountain Stream Corrugated Metal Pipe (CMP) Haul Road Culverts: Culverts are assumed to be corrugated steel with Manning s n = Length, available headwater depth, headwall configuration, downstream channel geometry, and slope are assumed or estimated from available topography Channel Assumptions: Slopes for flow routing and channel sizing calculations are the average slope across the entire reach 3H:1V side slopes Minimum freeboard is 1 ft 4.0 CALCULATIONS Basin area-weighted curve number calculations are presented in Table 1. Time of concentration calculations are presented as Table 2. The HEC-HMS model parameters are included as Attachment A and calculated 100-year frequency, 6-hour duration and 10-year frequency, 24-hour duration peak flows are included as Tables 3 and 3a respectively. Preliminary channel sizing calculations are presented in Table 4. Preliminary riprap sizing calculations are presented in Tables 5 and 5a. HY-8 Culvert sizing model output is included as Attachment B. Pit dewatering pond sizing calculations are included as Attachment C. 5.0 CONCLUSIONS AND DISCUSSION Channel dimensions and revetment have been designed based on available topography and preliminary facility designs. Dimensions and revetment requirements may change as the designs become more detailed. I:\11\82323\0100\0122 TM\Feb14\ TM PreFeasibilityHydrologyHydraulicsRevE 13FEB14.docx

5 Paul Bergstrom February 13, 2014 Rare Element Resources Proposed Stormwater Management Arrangement A berm around the upgradient side of the Mineable Pit highwall (PIT DIV N. and PIT DIV S.) prevents surface water flows from running into the Mineable Reserve pit during the design storm event and diverts the stormwater north and east into the existing drainages. Perimeter channels (as assumed) carry stormwater flows along the north and west side of the WRF to a proposed sediment trapping pond on the north side of the WRF (Pond 1 on Figure 1). Perimeter channel (as assumed) carry stormwater flows along the north and east side of the WRF to a proposed sediment trapping pond on the northeast corner of the WRF (Pond 2 on Figure 1). Perimeter channels (as assumed) carry stormwater flows along the south side of the WRF to a proposed sediment trapping pond on the southeast corner of the WRF (Pond 3 on Figure 1). Parallel diversion channels along the south and west sides of the WRF will divert the undisturbed upper reaches of Beaver Creek along the toe of the WRF and terminate into an upper tributary of Beaver Creek. Perimeter channels along the north and south sides of the Plant Site Pad (labeled PD-N and PD-S, respectively) convey flow to a sediment trapping pond on the east side of the Plant Site Pad. The following table provides a summary of the proposed diversion channels: Reach ID 100-yr/6-hr Peak Flow (cfs) Length Slope (ft/ft) Side Slope (_H:1V) Left Right Bottom Width Depth Freeboard WRF WRF 2a WRF 2b WRF WRF DIV W PIT DIV S PIT DIV N PIT DIV N BC DIV U BC DIV L PD-N PD-S Preliminary Sedimentation Pond Sizing The required volumes for each of the sediment trapping ponds are presented in the table below. The volumes are representative of storage to accommodate runoff from the 10-year 24-hour event and sediment storage. The Pit Pond also includes storage for water and sediment as a result of 500 gpm pit dewatering (calculations presented in Appendix C). The ponds and any associated embankments will be protected by outlet works and overflow spillways to be provided as part of detailed designs. The overflow spillways will likely be designed to flow over the face of the embankment in a controlled manner in a I:\11\82323\0100\0122 TM\Feb14\ TM PreFeasibilityHydrologyHydraulicsRevE 13FEB14.docx

6 Paul Bergstrom February 13, 2014 Rare Element Resources reinforced section. The ponds will require periodic maintenance and cleanout to ensure proper functioning. The required freeboard storage of one foot is not included in these numbers. Sediment Pond Catchment Area (ac) 10-Year Event Volume (ac-ft) 1 Sediment Storage Volume (ac-ft) 2 Total Pond Volume (ac-ft) 3 Waste Rock Facility Pond Pond Pond Pit Pond Environmental Flows Pit Dewatering PUG Plant PUG Plant Pond Notes: 1. In accordance with the Wyoming Department of Environmental Quality Water Quality Rules and Regulations, Chapter 11, Section 31, the sediment ponds are sized to accommodate the 10-year 24-hour runoff event. The design storm event was modeled using the Hydrologic Engineering Center's HEC-HMS program. Additionally, the ponds must be sized to accommodate the expected sediment storage. 2. The annual volume of sediment generated was assumed to be equal to one inch of runoff from the entire catchment area. This corresponds to 3,630 ft³/acre. 3. Total pond volume represents a neatline volume and does not include the required freeboard. 5.3 Haul Road Culvert Sizing Estimated culvert sizes are summarized in the table below. Culvert Designation (See Figure 1) Design Flow (cfs) Culvert Size (in.) Length No. of Barrels D D I:\11\82323\0100\0122 TM\Feb14\ TM PreFeasibilityHydrologyHydraulicsRevE 13FEB14.docx

7 Paul Bergstrom February 13, 2014 Rare Element Resources REFERENCES Association of State Dam Safety Officials (ASDSO) (2000): n. pag. Online. Internet. 20 January Available: HEC-HMS Hydrologic Modeling System [computer software] August 2010 US Army Corps of Engineers Version 3.5 Natural Resource Conservation Service (NRCS) Urban hydrology for small watersheds, 2nd edition (USSCS Technical Release Number 55). Washington D.C.: United States Department of Agriculture. Soil Survey Staff, Natural Resources Conservation Service, United States Department of Agriculture. Web Soil Survey. Available online at Accessed January 20, Tyrell, Patrick T. and Hasfurther, Victor R. Design Rainfall Distributions for the State of Wyoming. Department of Civil Engineering, College of Engineering, University of Wyoming. August U.S. Army Corps of Engineers (USACE) Hydraulic Design of Flood Control Channels. Engineer Manual Department of the Army. Washington D.C.: United States Government Printing Office. U.S. Federal Highway Administration (FHWA) HY8 Culverts Version FHWA Culvert Analysis. Washington, DC: FHA Office of Technology Applications. U.S. National Oceanic and Atmospheric Administration (NOAA) Precipitation Frequency Atlas of the Western US, Atlas No. 2, volume II Wyoming. Silver Spring MD: US Department of Commerce. Wyoming Department of Environmental Quality, Land Quality Division (WDEQ): Chapter 11, Section 31. Available: I:\11\82323\0100\0122 TM\Feb14\ TM PreFeasibilityHydrologyHydraulicsRevE 13FEB14.docx

8 TABLES

9 TABLE 1 SUBBASIN SUMMARY TABLE RARE ELEMENT RESOURCES BEAR LODGE MINE PRE-FEASIBILITY STUDY Date: 2/13/14 Project Number: By: MBR Chkd: SR Design Storm 100 -Year Reccurence Interval Apprvd: REK 2-Year, 24-Hour 100-Year, 24-Hour Depth (inches) Depth (inches) Storm Distribution II Subbasin ID Subbasin Area (ft 2 ) Subbasin Area (acres) Subbasin Area (sq mile) CN = 65 CN = 86 Woods-Grass Combo HSG B Fair Cover (acres) Newly Graded Areas HSG B (acres) Composite SCS Curve No. S = CN Unit Runoff Q (in) Runoff Volume (ac-ft) Runoff Volume (ft 3 ) Pt S 2,560, CN = ,252 Pt E 1,388, CN = ,710 Pt NE 1,911, CN = ,769 Pt N 961, CN = ,650 WRF 1 4,551, CN = ,258 WRF 2 6,262, CN = ,805 WRF 3 9,221, CN = ,436,976 BC 1 13,822, CN = ,036 BC 2 6,455, CN = ,472 Pd N 7,416, CN = ,955 Pd S 3,653, CN = ,729 HR 1 3,870, CN = ,954 HR 2 2,328, CN = ,276 WT 1 3,434, CN = ,423 PLNT 1,964, CN = ,188 Pit I 9,889, CN = ,541,008 J:\11JOBS\ Bear Lodge Mine\Surface Water\H&H calculations\bear Lodge H&H v4.11rev E.xlsm Page 1 of 1 Golder Associates 2/13/2014

10 TABLE 2 BASIN TIME OF CONCENTRATION CALCULATIONS RARE ELEMENT RESOURCES BEAR LODGE MINE PRE-FEASIBILITY STUDY Project Number: Date: 2/13/14 By: MBR Chkd: SR Apprvd: REK Subbasin ID Subbasin Area (sq mile) Composite Curve Number Total Lag (0.6*Tc) (min) Total Travel Time (min) Type of Flow Length Slope (ft/ft) Flow Segment 1 Flow Segment 2 Typical Hydraulic Roughness Condition (1) Radius (Channel Only) Travel Time (min) Type of Flow Length Slope (ft/ft) Roughness Condition (1) Typical Hydraulic Radius (Channel Only) Pt S Sheet H Range 4.4 Shallow U Unpaved 0.7 Pt E Sheet H Range 4.8 Shallow U Unpaved 2.8 Pt NE Sheet H Range 5.2 Shallow U Unpaved 2.2 Pt N Sheet H Range 5.5 Shallow U Unpaved 0.6 WRF Sheet A Smooth 2.4 Shallow U Unpaved 6.3 WRF Sheet A Smooth 2.4 Shallow U Unpaved 4.1 WRF Sheet A Smooth 2.4 Shallow U Unpaved 6.3 BC Sheet H Range 6.2 Shallow U Unpaved 2.3 BC Sheet H Range 5.4 Shallow U Unpaved 2.7 Pd N Sheet H Range 6.9 Shallow U Unpaved 3.8 Pd S Sheet H Range 6.0 Shallow U Unpaved 5.0 HR Sheet H Range 5.7 Shallow U Unpaved 1.4 HR Sheet H Range 5.7 Shallow U Unpaved 1.5 WT Sheet H Range 5.8 Shallow U Unpaved 0.8 Notes: (1) Refer to Attachment A for Roughness Condition descriptions and Tc Coeffiecients. (2) PLNT and Pit I Subbasins times of concentration assumed to be 10 min Travel Time (min) J:\11JOBS\ Bear Lodge Mine\Surface Water\H&H calculations\bear Lodge H&H v4.11rev E.xlsm Page 1 of 2 Golder Associates 2/13/2014

11 TABLE 2 BASIN TIME OF CONCENTRATION CALCULATIONS RARE ELEMENT RESOURCES BEAR LODGE MINE PRE-FEASIBILITY ST Project Number: Date: 2/13/14 By: MBR Chkd: SR Apprvd: REK Subbasin ID Subbasin Area (sq mile) Composite Curve Number Pt S Pt E Pt NE Pt N WRF WRF WRF BC BC Pd N Pd S HR HR WT Type of Flow Length Slope (ft/ft) Flow Segment 3 Flow Segment 4 Typical Hydraulic Roughness Condition (1) Radius (Channel Only) Travel Time (min) Type of Flow Length Slope (ft/ft) Roughness Condition (1) Typical Hydraulic Radius (Channel Only) Channel R Riprap Channel Z Mtn. Stream Channel R Riprap Channel E Earth-lined Shallow U Unpaved 0.4 Channel R Riprap Shallow U Unpaved 2.6 Channel R Riprap Shallow U Unpaved 0.4 Channel R Riprap Channel Z Mtn. Stream Channel R Riprap Channel Z Mtn. Stream Channel R Riprap Channel Z Mtn. Stream Channel R Riprap Channel Z Mtn. Stream Channel Z Mtn. Stream Channel Z Mtn. Stream Channel Z Mtn. Stream Channel R Riprap Channel Z Mtn. Stream Channel R Riprap Notes: (1) Refer to Attachment A for Roughness Condition descriptions and Tc Coeffiecients. (2) PLNT, Pit I, and Pit II Subbasins times of concentration assumed to be 10 min Travel Time (min) J:\11JOBS\ Bear Lodge Mine\Surface Water\H&H calculations\bear Lodge H&H v4.11rev E.xlsm Page 2 of 2 Golder Associates 2/13/2014

12 TABLE 3 FLOW RESULTS FROM HEC-HMS RARE ELEMENT RESOURCES BEAR LODGE MINE PRE-FEASIBILITY STUDY Project Number: Date: 2/13/14 By: MBR Chkd: SR Apprvd: REK HEC-HMS Basin Model: Bear Lodge Rev E HEC-HMS Met. Model: 100-year 6-hour HEC-HMS Control Specs: 36-hour 5-min HEC-HMS filepath: J:\11JOBS\ Bear Lodge Mine\Surface Water\H&H calculations\hec-hms\bearlodge_pre_feas_reve Drainage Peak Total Hydrologic Area Discharge Time of Volume Element (sq mile) (cfs) Peak (ac-ft) BC Jun2525, 01: Pt-S Jun2525, 01:00 3 R_Pt-E Jun2525, 01:00 3 Pt NE Jun2525, 01: Pt E Jun2525, 01: Junction-Pt Jun2525, 01: R_BC Jun2525, 01: J_BC Jun2525, 01: R_BC Jun2525, 01: BC Jun2525, 01: J_BC Jun2525, 01:00 31 Sink-BC Jun2525, 01:00 31 Pit I Jun2525, 00: Pt N Jun2525, 00: Sink-Pit Jun2525, 00: Pd-N Jun2525, 01: Pd-S Jun2525, 01: Sink Jun2525, 01: WT Jun2525, 01: R_WT Jun2525, 01: HR Jun2525, 01: R_HR Jun2525, 01: HR Jun2525, 01: Sink Jun2525, 01: WRF Jun2525, 00: Pond Jun2525, 00: WRF Jun2525, 00: Pond Jun2525, 00: PLNT Jun2525, 00:55 7 Sink Jun2525, 00:55 7 WRF Jun2525, 01:00 33 Pond Jun2525, 01:00 33 Page 1 of 1 Golder Associates J:\11JOBS\ Bear Lodge Mine\Surface Water\H&H calculations\bear Lodge H&H v4.11rev E.xlsm 2/13/2014

13 TABLE 3A 10-year 24-hour FLOW RESULTS FROM HEC-HMS RARE ELEMENT RESOURCES BEAR LODGE MINE PRE-FEASIBILITY STUDY Project Number: Date: 2/13/14 By: MBR Chkd: SR Apprvd: REK HEC-HMS Basin Model: Bear Lodge Rev D HEC-HMS Met. Model: 10-year 24-hour HEC-HMS Control Specs: 36-hour 5-min HEC-HMS filepath: J:\11JOBS\ Bear Lodge Mine\Surface Water\H&H calculations\hec-hms\bearlodge_pre_feas_revd Drainage Peak Total Hydrologic Area Discharge Time of Volume Element (sq mile) (cfs) Peak (ac-ft) BC Jun2525, 01: Pt-S Jun2525, 01: R_Pt-E Jun2525, 01: Pt NE Jun2525, 01: Pt E Jun2525, 01: Junction-Pt Jun2525, 01: R_BC Jun2525, 01: J_BC Jun2525, 01:05 19 R_BC Jun2525, 01:05 19 BC Jun2525, 01: J_BC Jun2525, 01: Sink-BC Jun2525, 01: Pit I Jun2525, 00: Pt N Jun2525, 00: Sink-Pit Jun2525, 00: Pd-N Jun2525, 01: Pd-S Jun2525, 01: Sink Jun2525, 01: WT Jun2525, 01: R_WT Jun2525, 01: HR Jun2525, 01: R_HR Jun2525, 01: HR Jun2525, 01: Sink Jun2525, 01: WRF Jun2525, 00: Pond Jun2525, 00: WRF Jun2525, 00: Pond Jun2525, 00: PLNT Jun2525, 00: Sink Jun2525, 00: WRF Jun2525, 01: Pond Jun2525, 01: Page 1 of 1 Golder Associates J:\11JOBS\ Bear Lodge Mine\Surface Water\H&H calculations\bear Lodge H&H v4.11rev E.xlsm 2/13/2014

14 Table 4 Channel Hydraulic Calculations RARE ELEMENT RESOURCES Date: 12/6/13 BEAR LODGE MINE PRE-FEASIBILITY STUDY By: AMS PROJECT NO.: Chkd: MBR Apprvd: RP Channel Design Geometry Channel Roughness Parameters Hydraulic Calculations Channel Evaluations Q100 from HEC-HMS (cfs) HEC HMS Element ID for Q Approximate Channel Length Bed Slope (ft/ft) Left Side Slope (H:1V) Right Side Slope (H:1V) Bottom Width Minimum Channel Depth Design Channel Reach Designation Lining WRF WRF R Riprap WRF 2a WRF R Riprap WRF 2b WRF R Riprap WRF WRF R Riprap WRF DIV W 36.6 Pt NE R Riprap PIT DIV S 48.5 Pt-S R Riprap PIT DIV N WT R Riprap PIT DIV N R_HR R Riprap BC DIV U J_BC R Riprap BC DIV L J_BC R Riprap PD-N PD-N R Riprap PD-S 70.4 PD-S R Riprap < 1/2 Vel. Head indicates that the remaining freeboard is less than 1/2 the velocity head (V 2 /2g) suggesting water may splash out. Warning: VxD>9 indicates that the velocity times the depth is greater than 9 ft 2 /sec, which is undesirable and may be un Unstable V indicates that calculated velocity exceeds the recommended maximum for the lining material. Unstable T indicates that calculated shear stress exceeds the recommended maximum for the lining material. Mannings 'n' for Capacity (Depth Calculation) Mannings 'n' for Stability (Velocity Calculation) Maximum Velocity (ft/sec) Maximum Normal Flow Depth Froude Number Normal Depth Shear Stress (lb/ft 2 ) Stream Power (W/m 2 ) Top Width of Flow Top Width of Channel Available Freeboard J:\11JOBS\ Bear Lodge Mine\Surface Water\H&H calculations\bear Lodge H&H v4.11rev D v2.xlsm Page 7 of 7 Golder Associates 1/14/2014

15 Table 5a U.S. Corps of Engineers (mild) Method Riprap Size Calculation Riprap Channel Evaluation Date: 12/6/13 Bear Lodge Mine By: AMS PROJECT NO.: Chkd: MBR Apprvd: RP Reach Designation Design Flow Q (cfs) Normal Flow Depth d Depth Averaged Velocity V (ft/s) Velocity Distribution Coefficient C V Channel Side Slopes Correction K 1 Calculated Particle Size D 30 Riprap Size D 50 (in) Recommended Riprap D 50 (inches) BC DIV U BC DIV L USACE Paper EM , 6/30/94 D = S USACE Method Riprap Calculations for Mild Riprap (Bed Slopes <2%) γ C C C d w 30 f s V T γ s γ w K1gd Inputs below as determined in EM , 6/30/ S f : Minimum safety factor of 1.1 for moderate debris impact 0.3 C s : Value of 0.30 for angular rock 165 γs: Density of solids (pcf) 2.2 Cg: Gradation Coefficient (D 85 /D 15 ) 2.0 T: Riprap Thickness (x D 50 ) C T : Correction for thickness > 1.5 * D 50 Note: A C V of 1.25 should be used downstream of concrete channels due to the difference in velocity profiles Riprap D50 determined as recommended in EM , 6/30/94 V 2.5 D 1 3 D = D D15 Page 1 of 2 Golder Associates J:\11JOBS\ Bear Lodge Mine\Surface Water\H&H calculations\bear Lodge Riprap Rev D.xlsm 1/14/2014

16 Table 5 U.S. Corps of Engineers (Steep) Method Riprap Size Calculation Riprap Channel Evaluation Date: 12/6/13 Bear Lodge Mine By: AMS PROJECT NO.: Chkd: MBR Apprvd: RP Reach Designation Design Flow Q (cfs) USACE Method Riprap Calculations for Steep Riprap (Bed Slopes >2% but <20%) Normal Flow Depth d Unit Flow (ft 2 /sec) Flow Concentration Factor Calculated Particle Size D 30 Riprap Size D 50 (inches) Recommended Riprap D 50 (inches) WRF WRF 2a WRF 2b WRF WRF DIV W PIT DIV S PIT DIV N PIT DIV N PD-N PD-S * Reach HR-U is consumed by the Reserve Pit USACE Paper EM , 6/30/ S q D 30 = 1 3 g Inputs below as determined in EM , 6/30/ Cg: Gradation Coefficient (D 85 /D 15 ) Riprap D50 determined as recommended in EM , 6/30/94 D 1 3 D = D D Flow Concentration Factor (1.25 from USACE steep riprap method) Page 2 of 2 Golder Associates J:\11JOBS\ Bear Lodge Mine\Surface Water\H&H calculations\bear Lodge Riprap Rev D.xlsm 1/14/2014

17 FIGURE

18 LEGEND Pd N WRF S WRF 1 Pt NE NOTES RARE ELEMENT RESOURCES BEAR LODGE PROJECT, BULL HILL MINE CROOK COUNTY, WYOMING PRE-FEASABILITY WATERSHED MANAGEMENT PLAN FIGURE 1

19 ATTACHMENT A HEC-HMS MODEL PARAMETERS

20 Attachment A HEC-HMS Screen Captures and Inputs HEC-HMS Basin Model Schematic (Mineable Scenario) Subbasin Sub Basin Area Area (mi 2 ) Subbasin Loss SCS Curve Number Initial Abstraction Curve (in) Number Impervious (%) Subbasin Lag Time (hr) %Time %Rainfall BC BC BC Pt-S Pt-S 65 0 Pt-S Pt NE Pt NE 65 0 Pt NE Pt E Pt E 65 0 Pt E BC BC BC Pit I Pit I 86 0 Pit I Pt N Pt N 65 0 Pt N Pd-N Pd-N 66 0 Pd-N Pd-S Pd-S 65 0 Pd-S WT WT WT HR HR HR HR HR HR WRF WRF WRF WRF WRF WRF PLNT PLNT 86 0 PLNT WRF WRF WRF Length Routing Kinematic Wave Channel Slope (ft/ft) Manning's n subreaches Shape Diameter Width Transform SCS Unit Hydrograph Side Slope (xh:1v) Reach R_Pt-E Trapezoid R_BC Trapezoid 10 3 R_BC Trapezoid 10 3 R_WT Trapezoid 10 5 R_HR Trapezoid 50 9 Dimensionless S-Graph J:\11JOBS\ Bear Lodge Mine\Surface Water\H&H calculations\bear Lodge H&H v4.11rev E.xlsm Page 1 of 1 Golder Associates, Inc. 2/13/2014

21 ATTACHMENT B HY8 CULVERT SIZING OUTPUT

22 December 2013 Attachment B HY-8 Culvert Analysis Culvert D1 Inputs j:\11jobs\ bear lodge mine\surface water\h&h calculations\hy8\attachment b hy-8 rev d.docx

23 December 2013 Attachment B HY-8 Culvert Analysis Culvert D1 Outputs j:\11jobs\ bear lodge mine\surface water\h&h calculations\hy8\attachment b hy-8 rev d.docx

24 December 2013 Attachment B HY-8 Culvert Analysis Culvert D1 Outputs j:\11jobs\ bear lodge mine\surface water\h&h calculations\hy8\attachment b hy-8 rev d.docx

25 December 2013 Attachment B HY-8 Culvert Analysis Culvert D1 Outputs j:\11jobs\ bear lodge mine\surface water\h&h calculations\hy8\attachment b hy-8 rev d.docx

26 December 2013 Attachment B HY-8 Culvert Analysis Culvert D2 Inputs j:\11jobs\ bear lodge mine\surface water\h&h calculations\hy8\attachment b hy-8 rev d.docx

27 December 2013 Attachment B HY-8 Culvert Analysis Culvert D2 Outputs j:\11jobs\ bear lodge mine\surface water\h&h calculations\hy8\attachment b hy-8 rev d.docx

28 December 2013 Attachment B HY-8 Culvert Analysis Culvert D2 Outputs j:\11jobs\ bear lodge mine\surface water\h&h calculations\hy8\attachment b hy-8 rev d.docx

29 December 2013 Attachment B HY-8 Culvert Analysis Culvert D2 Outputs j:\11jobs\ bear lodge mine\surface water\h&h calculations\hy8\attachment b hy-8 rev d.docx

30 ATTACHMENT C PIT DEWATERING SEDIMENT POND SIZING

31 February Table C1: Sediment Pond Sizing Summary Catchment Area (ac) 10-Year Event Volume (ac-ft) 1 Sediment Storage Volume (ac-ft) 2 Total Pond Volume (ac-ft) 3 Sediment Pond Waste Rock Facility Pond Pond Pond Pit Pond Environmental Flows Pit Dewatering PUG Plant PUG Plant Pond Notes: 1. In accordance with the Wyoming Department of Environmental Quality Water Quality Rules and Regulations, Chapter 11, Section 31, the sediment ponds are sized to accommodate the 10-year 24- hour runoff event. The design storm event was modeled using the Hydrologic Engineering Center's HEC-HMS program. Additionally, the ponds must be sized to accommodate the expected sediment 2. The annual volume of sediment generated was assumed to be equal to one inch of runoff from the entire catchment area. This corresponds to 3,630 ft 3 /acre. 3. Total pond volume represents a neatline volume and does not include the required freeboard. J:\11JOBS\ Bear Lodge Mine\Surface Water\H&H calculations\bear Lodge H&H v4.11rev E.xlsm

32 December 2013 Attachment C Settling Velocity Calculations Calculation of the settling velocity u of a single particle: natural sediment or spherical Janwillem Rouweler; HAS University of Applied Sciences; N input cel: yellow calculation cel: blue INPUT: Acceleration of gravity g = 9.81 m/s 2 usually g = 9.81 m/s 2 Density of particle ρ PARTICLE = ρ P = 1100 kg/m3 Diameter of particle d = meter (Be Aware: 1 mm = m) Assume Fine sand Density of fluid ρ FLUID = ρ F = 1000 kg/m3 usually water ρ F = 1000 kg/m 3 Viscosity of fluid η FLUID = η F = Pa s usually water η F = Pa s "Dimensionless particle diameter d * "= Natural particles (Song Zhiyao): Settling velocity u = m/s Re = ρ F *u*d/η F = 5.76E ft/s Spherical particles (Guo): Settling velocity u = m/s Re = ρ F *u*d/η F = 7.57E ft/s V S = 0.01 ft/s Settling velocity for the design particle size chosen Q = 1.11 cfs 500 gpm Discharge rate measured in cubic feet per second A S = 177 sq. ft. Minimum surface are for trapping soil particles of a certain size J:\11JOBS\ Bear Lodge Mine\Surface Water\November 2013\Pit Dewatering Pond\SedBasin_1.xls

33 December 2013 Attachment C Pond Sizing Calculations Influent Parameters m 3 /day Flow gpd gpm 500 Influent TSS mg/l 1500 Effluent TSS mg/l 35 Sedimentation Basin Mass of Sludge without Anaerobic Decomposition kg/yr 1,457,391 Ratio of Fixed Solids to VSS Volatile Solids kg/yr - Fixed Solids kg/yr 1,457,391 Volatile Solids Reduction % 0% Sludge Accumulation years 1 VSS decomposition years 1 yr 1 kg/yr - Total SS yr 1 yr 1 1,457,391 Total Solid yr 1 kg 1,457,391 Detention Time days 2 m 3 5,451 Volume gallons 1,440,000 ac-ft 4.4 Lagoon Depth m 1.00 m 2 5,451 Surface Area ft2 58,653 Mass of Accumulated Sludge / Area kg/m Density of Sludge kg/m Average Compaction % 15% Sludge Bank Depth m 1.68 m 2.68 Total Lagoon Depth ft 8.80 Length to width ratio 3.0 ft Length m ft Width m 42.6 Laminar Velocity ft/s Laminar Velocity Contingency Adjusted Laminar Velocity ft/s Settling Velocity ft/s Settling Velocity - Adjusted Laminar Velocity ft/s Water Storage ac-ft 4.4 Sediment Storage ac-ft 7.4 Total Required Storage ac-ft 11.8 J:\11JOBS\ Bear Lodge Mine\Surface Water\November 2013\Pit Dewatering Pond\SedBasin_1.xls

APPENDIX B HYDROLOGY

APPENDIX B HYDROLOGY APPENDIX B HYDROLOGY TABLE OF CONTENTS 1.0 INTRODUCTION... 1 2.0 PROBABLE MAXIMUM PRECIPITATION (PMP)... 1 3.0 DESIGN FLOW CALCULATION... 1 4.0 DIVERSION CHANNEL SIZING... 2 5.0 REFERENCES... 4 LIST OF

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

Section 4: Model Development and Application

Section 4: Model Development and Application Section 4: Model Development and Application The hydrologic model for the Wissahickon Act 167 study was built using GIS layers of land use, hydrologic soil groups, terrain and orthophotography. Within

More information

Continuing Education Course #101 Drainage Design with WinTR-55

Continuing Education Course #101 Drainage Design with WinTR-55 1 of 5 Continuing Education Course #101 Drainage Design with WinTR-55 1. WinTR-55 uses the Kinematic Wave method for calculating storm runoff rates and volumes. 2. According to the Velocity Method, the

More information

STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1. DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT

STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1. DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1 DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT Prepared by: PAULUS, SOKOLOWSKI & SARTOR STORMWATER MANAGEMENT 1. Methodology

More information

APPENDIX B DESIGN CRITERIA FOR TEMPORARY WATER QUALITY BMPS USED DURING CONSTRUCTION

APPENDIX B DESIGN CRITERIA FOR TEMPORARY WATER QUALITY BMPS USED DURING CONSTRUCTION APPENDIX B DESIGN CRITERIA FOR TEMPORARY WATER QUALITY BMPS USED DURING CONSTRUCTION This Appendix presents design criteria and example calculations for the following temporary water quality BMPs for use

More information

Chapter 10 - Sacramento Method Examples

Chapter 10 - Sacramento Method Examples Chapter 10 Sacramento Method Examples Introduction Overview This chapter presents two example problems to demonstrate the use of the Sacramento method. These example problems use the SACPRE and HEC-1 computer

More information

Hydrology and Hydraulics Design Report. Background Summary

Hydrology and Hydraulics Design Report. Background Summary To: National Park Services Montezuma Castle National Monument Richard Goepfrich, Facility Manager From: Multicultural Technical Engineers Date: Tuesday - February 13, 2018 Subject: 30% Hydrology and Hydraulics

More information

PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0

PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0 PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0 LYCOMING COUNTY S.R.15, SECTION C41 FINAL HYDROLOGIC AND HYDRAULIC REPORT STEAM VALLEY RUN STREAM RELOCATION DATE: June, 2006 REVISED:

More information

Coal Combustion Residuals Unit Inflow Design Flood Control System Plan

Coal Combustion Residuals Unit Inflow Design Flood Control System Plan Coal Combustion Residuals Unit Inflow Design Flood Control System Plan Virginia Electric and Power Company Chesterfield Power Station Upper (East) Pond Chesterfield County, Virginia GAI Project Number:

More information

Submitted to: St. Johns River Power Park New Berlin Road Jacksonville, FL 32226

Submitted to: St. Johns River Power Park New Berlin Road Jacksonville, FL 32226 RUN-ON/RUN-OFF CONTROL SYSTEM PLAN RUN-ON AND RUN-OFF CONTROL SYSTEM PLAN St. Johns River Power Park Byproduct Storage Area B Phase I Development Submitted to: St. Johns River Power Park 11201 New Berlin

More information

1.0 INSPECTION ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER PROJECT, CARMACKS, YUKON. Dear Mr. West-Sells,

1.0 INSPECTION ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER PROJECT, CARMACKS, YUKON. Dear Mr. West-Sells, Doc. No. 162 Rev. 0 Mr. Paul West-Sells President & Chief Operating Officer Western Copper Corporation 2060-1111 West Georgia Street Vancouver, BC V6E 4M3 ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER

More information

Rock Sizing for Batter Chutes

Rock Sizing for Batter Chutes Rock Sizing for Batter Chutes STORMWATER MANAGEMENT PRACTICES Photo 1 Rock-lined batter chute Photo 2 Rock-lined batter chute 1. Introduction In the stormwater industry a chute is a steep drainage channel,

More information

ARTICLE 5 (PART 2) DETENTION VOLUME EXAMPLE PROBLEMS

ARTICLE 5 (PART 2) DETENTION VOLUME EXAMPLE PROBLEMS ARTICLE 5 (PART 2) DETENTION VOLUME EXAMPLE PROBLEMS Example 5.7 Simple (Detention Nomograph) Example 5.8 Offsite and Unrestricted Areas (HEC-HMS) Example 5.9 Ponds in Series w/ Tailwater (HEC-HMS) Example

More information

Objectives: After completing this assignment, you should be able to:

Objectives: After completing this assignment, you should be able to: Data Analysis Assignment #1 Evaluating the effects of watershed land use on storm runoff Assignment due: 21 February 2013, 5 pm Objectives: After completing this assignment, you should be able to: 1) Calculate

More information

INTRODUCTION TO HYDROLOGIC MODELING USING HEC-HMS

INTRODUCTION TO HYDROLOGIC MODELING USING HEC-HMS INTRODUCTION TO HYDROLOGIC MODELING USING HEC-HMS By Thomas T. Burke, Jr., PhD, PE Luke J. Sherry, PE, CFM Christopher B. Burke Engineering, Ltd. October 8, 2014 1 SEMINAR OUTLINE Overview of hydrologic

More information

Stage Discharge Tabulation for Only Orifice Flow

Stage Discharge Tabulation for Only Orifice Flow Stage Discharge Tabulation for Only Orifice Flow DEPTH STAGE DISCHARGE (meters) (feet) (meters) (feet) (m 3 /s) (ft 3 /s) 0 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 2.00 0.7 1.3 2.0 2.6 3.3 3.9 4.6

More information

Continuing Education Associated with Maintaining CPESC and CESSWI Certification

Continuing Education Associated with Maintaining CPESC and CESSWI Certification Continuing Education Associated with Maintaining CPESC and CESSWI Certification Module 2: Stormwater Management Principles for Earth Disturbing Activities Sponsors: ODOTs Local Technical Assistance Program

More information

Rock Sizing for Small Dam Spillways

Rock Sizing for Small Dam Spillways Rock Sizing for Small Dam Spillways STORMWATER MANAGEMENT PRACTICES Photo 1 Rock-lined spillway on a construction site sediment basin Photo 2 Rock-lined spillway on a small farm dam 1. Introduction A chute

More information

Pressure Head: Pressure head is the height of a column of water that would exert a unit pressure equal to the pressure of the water.

Pressure Head: Pressure head is the height of a column of water that would exert a unit pressure equal to the pressure of the water. Design Manual Chapter - Stormwater D - Storm Sewer Design D- Storm Sewer Sizing A. Introduction The purpose of this section is to outline the basic hydraulic principles in order to determine the storm

More information

Stormwater Guidelines and Case Studies. CAHILL ASSOCIATES Environmental Consultants West Chester, PA (610)

Stormwater Guidelines and Case Studies. CAHILL ASSOCIATES Environmental Consultants West Chester, PA (610) Stormwater Guidelines and Case Studies CAHILL ASSOCIATES Environmental Consultants West Chester, PA (610) 696-4150 www.thcahill.com Goals and Challenges for Manual State Stormwater Policy More Widespread

More information

Stormwater Capacity Analysis for Westover Branch Watershed

Stormwater Capacity Analysis for Westover Branch Watershed Stormwater Capacity Analysis for Westover Branch Watershed Pimmit Run Little Pimmit Run, Mainstem Stohman's Run Gulf Branch Pimmit Run Tributary Little Pimmit Run, W. Branch Little Pimmit Run, E. Branch

More information

APPENDIX G APPENDIX G SEDIMENT CONTAINMENT SYSTEM DESIGN RATIONALE

APPENDIX G APPENDIX G SEDIMENT CONTAINMENT SYSTEM DESIGN RATIONALE APPENDIX G SEDIMENT CONTAINMENT SYSTEM DESIGN RATIONALE March 18, 2003 This page left blank intentionally. March 18, 2003 G-2 FIGURES Page # Figure G.1 Estimated Runoff from Precipitation Over Different

More information

Module 5: Channel and Slope Protection Example Assignments

Module 5: Channel and Slope Protection Example Assignments Module 5: Channel and Slope Protection Example Assignments A) Example Project Assignment on Slope and Swale Design North America Green Software Example (Erosion Control Materials Design Software) The following

More information

Bushkill Creek 3 rd Street Dam Removal Analysis

Bushkill Creek 3 rd Street Dam Removal Analysis Bushkill Creek 3 rd Street Dam Removal Analysis HEC HMS Runoff and Routing Model Stephen Beavan, Melanie DeFazio, David Gold, Peter Mara and Dan Moran CE 421: Hydrology Fall 2010 December 15, 2010 Contents

More information

UPPER COSUMNES RIVER FLOOD MAPPING

UPPER COSUMNES RIVER FLOOD MAPPING UPPER COSUMNES RIVER FLOOD MAPPING DRAFT BASIC DATA NARRATIVE FLOOD INSURANCE STUDY SACRAMENTO COUTY, CALIFORNIA Community No. 060262 November 2008 Prepared By: CIVIL ENGINEERING SOLUTIONS, INC. 1325 Howe

More information

Standards for Soil Erosion and Sediment Control in New Jersey May 2012

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SEDIMENT BASIN Definition A barrier, dam, excavated pit, or dugout constructed across a waterway or at other suitable locations to intercept and retain sediment. Basins created by construction

More information

Notes: Space for as many as two segments per flow type can be used for each worksheet. Include a map, schematic, or description of flow segments.

Notes: Space for as many as two segments per flow type can be used for each worksheet. Include a map, schematic, or description of flow segments. Worksheet 3: Time of Concentration (Tc) or travel time (Tt) Project By Date Location Checked Date Check one: Present Developed Check one: Tc Tt through subarea Notes: Space for as many as two segments

More information

CITY OF CAPE CORAL STORMWATER MASTER PLAN PHASE II - PART 1 BASINS 4, 10, & 14 SUB-BASIN DRAINAGE IMPROVEMENTS HYDRAULIC ANALYSIS SUMMARY

CITY OF CAPE CORAL STORMWATER MASTER PLAN PHASE II - PART 1 BASINS 4, 10, & 14 SUB-BASIN DRAINAGE IMPROVEMENTS HYDRAULIC ANALYSIS SUMMARY CITY OF CAPE CORAL STORMWATER MASTER PLAN PHASE II - PART 1 BASINS 4, 10, & 14 SUB-BASIN DRAINAGE IMPROVEMENTS HYDRAULIC ANALYSIS SUMMARY Cape Coral, FL Prepared for: The City of Cape Coral Public Works

More information

A GIS-based Approach to Watershed Analysis in Texas Author: Allison Guettner

A GIS-based Approach to Watershed Analysis in Texas Author: Allison Guettner Texas A&M University Zachry Department of Civil Engineering CVEN 658 Civil Engineering Applications of GIS Instructor: Dr. Francisco Olivera A GIS-based Approach to Watershed Analysis in Texas Author:

More information

Drainage Analysis. Appendix F

Drainage Analysis. Appendix F Drainage Analysis Appendix F Golden View Drive Elizabeth Street LMORE CREEK Ricky Road Rabbit Creek Road LITTLE RABBIT CREEK East 156th Avenue MOA Project #10-026 Golden View Drive Intersection

More information

TPDES: Soil, Erosion and Sedimentation Methods

TPDES: Soil, Erosion and Sedimentation Methods SAWS TPDES: Soil, Erosion and Sedimentation Methods Philip Handley Supervisor-Resource Protection & Compliance August 25, 2014 TPDES: Soil, Erosion and Sedimentation Methods Soil Common term: Dirt Common

More information

Stone Outlet Sediment Trap

Stone Outlet Sediment Trap 3.12 Sediment Control Description: A stone outlet sediment trap is a small detention area formed by placing a stone embankment with an integral stone filter outlet across a drainage swale for the purpose

More information

******************* Project Description ******************* File Name... NAAF Stormwater Improvement Project 11_21_2014.SPF

******************* Project Description ******************* File Name... NAAF Stormwater Improvement Project 11_21_2014.SPF Autodesk Storm and Sanitary Analysis 2014 - Version 8.1.62 (Build 1) ----------------- *** Project Description *** File Name... NAAF Stormwater Improvement Project 11_21_2014.SPF Analysis Options Flow

More information

Technical Memorandum. To: From: Copies: Date: 10/19/2017. Subject: Project No.: Greg Laird, Courtney Moore. Kevin Pilgrim and Travis Stroth

Technical Memorandum. To: From: Copies: Date: 10/19/2017. Subject: Project No.: Greg Laird, Courtney Moore. Kevin Pilgrim and Travis Stroth Technical Memorandum To: From: Greg Laird, Courtney Moore Kevin Pilgrim and Travis Stroth 5777 Central Avenue Suite 228 Boulder, CO 80301 www.otak.com Copies: [Electronic submittal] Date: 10/19/2017 Subject:

More information

DRAINAGE REPORT FOR THORNTON SELF STORAGE THORNTON, COLORADO

DRAINAGE REPORT FOR THORNTON SELF STORAGE THORNTON, COLORADO DRAINAGE REPORT FOR THORNTON SELF STORAGE THORNTON, COLORADO Prepared by: Bowman Consulting 603 Park Point Dr. Suite 100 Golden, CO 80401 (303)-801-2900 June 29, 2015 Revised August 14, 2015 CERTIFICATE

More information

APPENDIX B WORKSHEETS & EXHIBITS

APPENDIX B WORKSHEETS & EXHIBITS APPENDIX B WORKSHEETS & EXHIBITS A worksheet provides the designer a representation of a measure that allows for input of specific design criteria. The plan designer will be required to assess field conditions

More information

Rucker Pond. Background

Rucker Pond. Background Rucker Pond Background The Rucker Basin consists of two subbasins (East and West) that drain to a single area known as Rucker Pond. Both subbasins have the same hydraulic parameters, but have different

More information

BRANDON LAKES AVENUE PRE AND POST CONDITIONS DRAINAGE REPORT

BRANDON LAKES AVENUE PRE AND POST CONDITIONS DRAINAGE REPORT BRANDON LAKES AVENUE PRE AND POST CONDITIONS DRAINAGE REPORT Hillsborough County Public Works County Center, 22nd Floor 601 E. Kennedy Blvd. Tampa, FL 33602 BRANDON LAKES AVENUE DRAINAGE IMPROVEMENTS Capital

More information

Chapter 7 Mudflow Analysis

Chapter 7 Mudflow Analysis Chapter 7 Mudflow Analysis 7.0 Introduction This chapter provides information on the potential and magnitude of mud floods and mudflows that may develop in Aspen due to rainfall events, snowmelt, or rain

More information

Rock & Aggregate Drop Inlet Protection

Rock & Aggregate Drop Inlet Protection Rock & Aggregate Drop Inlet Protection SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System Supplementary Trap Dispersive Soils

More information

CASE STUDIES. Introduction

CASE STUDIES. Introduction Introduction The City of Winston-Salem faces the challenge of maintaining public infrastructure (e.g., water and sewer lines, storm drains, roads, culverts and bridges) while minimizing the potential impacts

More information

Sediment Trap. At multiple locations within the project site where sediment control is needed.

Sediment Trap. At multiple locations within the project site where sediment control is needed. Sediment Trap SE-3 Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control

More information

City of Thornton Attn: Tim Semones Development Engineeering 9500 Civic Center Dr. Thornton, CO 80229

City of Thornton Attn: Tim Semones Development Engineeering 9500 Civic Center Dr. Thornton, CO 80229 Development Engineering Land Surveying Construction Administration District Services October 20, 2017 City of Thornton Attn: Tim Semones Development Engineeering 9500 Civic Center Dr. Thornton, CO 80229

More information

HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR (c)(1)(i) (xii)

HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR (c)(1)(i) (xii) HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR 257.73(c)(1)(i) (xii) (i) Site Name and Ownership Information: Site Name: E.C. Gaston Steam Plant Site Location:

More information

Suitable Applications Sediment traps should be considered for use:

Suitable Applications Sediment traps should be considered for use: Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective

More information

STORMWATER MANAGEMENT COMPUTATIONS. Mount Prospect

STORMWATER MANAGEMENT COMPUTATIONS. Mount Prospect STORMWATER MANAGEMENT COMPUTATIONS Mount Prospect MHG PROJECT No. 2011.173.11 November 6, 2014 Prepared for: Piney Meetinghouse Investments c/o Mr. Dennis Fling 14801 Clopper Road Boyds, MD 20841 (301)

More information

Design Storms for Hydrologic Analysis

Design Storms for Hydrologic Analysis Design Storms for Hydrologic Analysis Course Description This course is designed to fulfill two hours of continuing education credit for Professional Engineers. Its objective is to provide students with

More information

Technical Memorandum No

Technical Memorandum No Pajaro River Watershed Study in association with Technical Memorandum No. 1.2.10 Task: Evaluation of Four Watershed Conditions - Sediment To: PRWFPA Staff Working Group Prepared by: Gregory Morris and

More information

Chapter 7 Mudflow Analysis

Chapter 7 Mudflow Analysis Chapter 7 Mudflow Analysis 7.0 Introduction This chapter provides information on the potential and magnitude of mud floods and mudflows that may develop in Aspen due to rainfall events, snowmelt, or rain

More information

The effectiveness of the Natural Resource Conservation Service (NRCS) and Huff rainfall distribution methods for use in detention basin design

The effectiveness of the Natural Resource Conservation Service (NRCS) and Huff rainfall distribution methods for use in detention basin design Scholars' Mine Masters Theses Student Theses and Dissertations Spring 2010 The effectiveness of the Natural Resource Conservation Service (NRCS) and Huff rainfall distribution methods for use in detention

More information

EROSION CONTROL NARRATIVE

EROSION CONTROL NARRATIVE EROSION CONTROL NARRATIVE Erosion and sediment control has been designed for the Willow Bend Phase I Subdivision according to UDFCD and the City of Thornton criteria, in order to minimize erosion and sediment

More information

Materials. Use materials meeting the following.

Materials. Use materials meeting the following. 208.01 Section 208. SOIL EROSION AND SEDIMENTATION CONTROL 208.01 Description. Install and maintain erosion and sedimentation controls to minimize soil erosion and to control sedimentation from affecting

More information

Open Channel Flow Part 2. Ch 10 Young, notes, handouts

Open Channel Flow Part 2. Ch 10 Young, notes, handouts Open Channel Flow Part 2 Ch 10 Young, notes, handouts Uniform Channel Flow Many situations have a good approximation d(v,y,q)/dx=0 Uniform flow Look at extended Bernoulli equation Friction slope exactly

More information

LOCATED IN INDIAN RIVER COUNTY PREPARED FOR S.J.R.W.M.D. AND F.W.C.D. DECEMBER, 2003 Updated 2007 Updated May 2014 PREPARED BY

LOCATED IN INDIAN RIVER COUNTY PREPARED FOR S.J.R.W.M.D. AND F.W.C.D. DECEMBER, 2003 Updated 2007 Updated May 2014 PREPARED BY FELLSMERE WATER CONTROL DISTRICT EAST MASTER DRAINAGE PLAN AND STORMWATER HYDROLOGIC ANALYSIS OF THE GRAVITY DRAINAGE SYSTEM LOCATED BETWEEN THE EAST BOUNDARY, LATERAL U, THE MAIN CANAL, AND DITCH 24 LOCATED

More information

This site will utilize an infiltration berm to manage the two-year/24-hour volume increase.

This site will utilize an infiltration berm to manage the two-year/24-hour volume increase. Gates TETRA TECH, INC. By: RH Date: 1/30/2017 Subject: Gates Road Checked By: JB Date: 2/1/2017 PCSM Design and Evaluation PURPOSE: The purpose of these calculations is to design a Post-Construction Stormwater

More information

Hydrology Study Report

Hydrology Study Report Hafeez Consulting www.hafeezconsulting.com Civil/ Structural Engineering, Design & Construction 1451 S. Hacienda St. Anaheim CA 92804 (714) 225-4565 Fax (714)917-2977 engineer@hafeezconsulting.com Hydrology

More information

STORMWATER REPORT FRITO LAY SUBDIVISION NO. 3

STORMWATER REPORT FRITO LAY SUBDIVISION NO. 3 STORMWATER REPORT FRITO LAY SUBDIVISION NO. 3 May 2018 STORMWATER REPORT I. Subdivision Data a. The parcel is adjacent to the existing Frito Lay property in Topeka; and the subject plat application encompasses

More information

Report for Area Drainage Studies for 1320 MW (2x660 MW) THERMAL POWER PROJECT AT MIRZAPUR, U.P.

Report for Area Drainage Studies for 1320 MW (2x660 MW) THERMAL POWER PROJECT AT MIRZAPUR, U.P. Report for Area Drainage Studies for 1320 MW (2x660 MW) THERMAL POWER PROJECT AT MIRZAPUR, U.P. 1. Introduction M/s Welspun Energy Uttar Pradesh Ltd. (WEUPL) is putting up 1320 MW (2 x 660 MW) coal fired

More information

ISSN Vol.03,Issue.10 May-2014, Pages:

ISSN Vol.03,Issue.10 May-2014, Pages: www.semargroup.org, www.ijsetr.com ISSN 2319-8885 Vol.03,Issue.10 May-2014, Pages:2187-2191 YIN YIN HTWE 1, AYE AYE THANT 2 1 Dept of Civil Engineering, Mandalay Technological University, Mandalay, Myanmar,

More information

INTRODUCTION TO HEC-HMS

INTRODUCTION TO HEC-HMS INTRODUCTION TO HEC-HMS Hydrologic Engineering Center- Hydrologic Modeling System US Army Corps of Engineers Hydrologic Engineering Center HEC-HMS Uses Schematics Enter properties: watershed, rivers (reaches),

More information

Mr. Michael Malone CPS Energy 145 Navarro Street San Antonio, Texas Project No

Mr. Michael Malone CPS Energy 145 Navarro Street San Antonio, Texas Project No January 17, 2018 Mr. Michael Malone 145 Navarro Street San Antonio, Texas 78205 Project No. 0337367 Environmental Resources Management CityCentre Four 840 West Sam Houston Pkwy N. Suite 600 Houston, Texas

More information

This site will utilize an infiltration berm to manage the two-year/24-hour volume increase.

This site will utilize an infiltration berm to manage the two-year/24-hour volume increase. Gates TETRA TECH, INC. By: RH Date: 11/11/2016 Subject: Gates Road Checked By: JB Date: 11/13/2016 PCSM Design and Evaluation PURPOSE: The purpose of these calculations is to design a Post-Construction

More information

Rock Sizing for Waterway & Gully Chutes

Rock Sizing for Waterway & Gully Chutes Rock Sizing for Waterway & Gully Chutes WATERWAY MANAGEMENT PRACTICES Photo 1 Rock-lined waterway chute Photo 2 Rock-lined gully chute 1. Introduction A waterway chute is a stabilised section of channel

More information

Drainage Study for Civic Center Way

Drainage Study for Civic Center Way Drainage Study for 23401 Civic Center Way P.C.C.E. INC. CIVIL ENGINEERING AND DESIGN Drainage Study for 23401 Civic Center Way WHOLE FOODS AT THE PARK Prepared by: P.C.C.E. INC STEPHEN R. SMITH, P.E. 23801

More information

UTILITY REPORT FOR THORNTON SELF STORAGE THORNTON, COLORADO

UTILITY REPORT FOR THORNTON SELF STORAGE THORNTON, COLORADO UTILITY REPORT FOR THORNTON SELF STORAGE THORNTON, COLORADO Prepared by: Bowman Consulting 63 Park Point Dr. Suite 1 Golden, CO 841 (33)-81-29 June 29, 215 Revised August 14, 215 Revised September 3, 215

More information

Sediment Trap. A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff through a stabilized spillway.

Sediment Trap. A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff through a stabilized spillway. Sediment Trap SC-15 Source: Caltrans Construction Site Best Management Practices Manual, 2003. Description A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff

More information

Sediment Control Practices. John Mathews Ohio Dept. of Natural Resources, Division of Soil and Water Resources

Sediment Control Practices. John Mathews Ohio Dept. of Natural Resources, Division of Soil and Water Resources Sediment Control Practices John Mathews Ohio Dept. of Natural Resources, Division of Soil and Water Resources Practices Treat the Largest Soil Particles Sand Sand Silt Clay Treated Untreated Settleable

More information

THE NEED FOR AN ADDITIONAL SPILLWAY AT THE SANFORD DAM BOILING SPRING LAKES, NC. Presentation for The Brunswick County Commissioners April 20, 2015

THE NEED FOR AN ADDITIONAL SPILLWAY AT THE SANFORD DAM BOILING SPRING LAKES, NC. Presentation for The Brunswick County Commissioners April 20, 2015 THE NEED FOR AN ADDITIONAL SPILLWAY AT THE SANFORD DAM BOILING SPRING LAKES, NC Presentation for The Brunswick County Commissioners April 20, 2015 The Sanford Dam Earth Dam constructed in 1961 Drainage

More information

Case Study 2: Twenty-mile Creek Rock Fords

Case Study 2: Twenty-mile Creek Rock Fords Case Study : Twenty-mile Creek Rock Fords Location Crossing Description Washington. Okanagan National Forest. Methow Valley Ranger District. Chewuch river basin, East Chewuch Road. The Twenty-mile Creek

More information

5. ROADSIDE AND MEDIAN CHANNELS

5. ROADSIDE AND MEDIAN CHANNELS 5. ROADSIDE AND MEDIAN CHANNELS Roadside and median channels are open-channel systems which collect and convey stormwater from the pavement surface, roadside, and median areas. These channels may outlet

More information

Homework 10. Logan Dry Canyon Detention Basin Design Case Study Date: 4/14/14 Due: 4/25/14

Homework 10. Logan Dry Canyon Detention Basin Design Case Study Date: 4/14/14 Due: 4/25/14 Homework 10. Logan Dry Canyon Detention Basin Design Case Study Date: 4/14/14 Due: 4/25/14 Section 1: Case Study Introduction This case study serves as an integrative problem based learning exercise. In

More information

Chapter 5 CALIBRATION AND VERIFICATION

Chapter 5 CALIBRATION AND VERIFICATION Chapter 5 CALIBRATION AND VERIFICATION This chapter contains the calibration procedure and data used for the LSC existing conditions model. The goal of the calibration effort was to develop a hydraulic

More information

Appendix E Guidance for Shallow Flooding Analyses and Mapping

Appendix E Guidance for Shallow Flooding Analyses and Mapping Appendix E Guidance for Shallow Flooding Analyses and Mapping E.1 Introduction Different types of shallow flooding commonly occur throughout the United States. Types of flows that result in shallow flooding

More information

3301 East 120 th Avenue Assited Living & Memory Care

3301 East 120 th Avenue Assited Living & Memory Care UTILITY REPORT FOR 3301 East 120 th Avenue Assited Living & Memory Care 1 st Submittal January 23, 2016 2 nd Submittal March 04, 2016 Prepared for: 3301 E. 120 th Ave, LLC. 8200 E. Maplewood Ave., Suite

More information

DRAINAGE REPORT. Ministry of Transportation and Infrastructure. Highway 7 Four Laning Silverdale Avenue to Nelson Street 100% Detailed Design

DRAINAGE REPORT. Ministry of Transportation and Infrastructure. Highway 7 Four Laning Silverdale Avenue to Nelson Street 100% Detailed Design DRAINAGE REPORT Ministry of Transportation and Infrastructure Highway 7 Four Laning Silverdale Avenue to Nelson Street 100% Detailed Design December 14, 2017 Reviewed by: Amanda Rust, P. Eng. Senior Drainage

More information

STABILIZATION OF THE H&CT RAILWAY STONE DAM WALTER E. SKIPWITH, PE, JOYCE CRUM, AIA AND JOHN BAUMGARTNER, PE. Introduction.

STABILIZATION OF THE H&CT RAILWAY STONE DAM WALTER E. SKIPWITH, PE, JOYCE CRUM, AIA AND JOHN BAUMGARTNER, PE. Introduction. STABILIZATION OF THE H&CT RAILWAY STONE DAM WALTER E. SKIPWITH, PE, JOYCE CRUM, AIA AND JOHN BAUMGARTNER, PE I. A. Introduction General The Old Stone Dam is located in the upper reach of Cottonwood Creek

More information

Preliminary Hydraulic Report

Preliminary Hydraulic Report Tarrant County, Texas Preliminary Hydraulic Report Prepared for: Texas Department of Transportation Fort Worth District Prepared by: AECOM Corporation Scott C. Williams, P.E. No. 101334, Date 2009 This

More information

Workshop: Build a Basic HEC-HMS Model from Scratch

Workshop: Build a Basic HEC-HMS Model from Scratch Workshop: Build a Basic HEC-HMS Model from Scratch This workshop is designed to help new users of HEC-HMS learn how to apply the software. Not all the capabilities in HEC-HMS are demonstrated in the workshop

More information

APPENDIX B DRAINAGE REPORT

APPENDIX B DRAINAGE REPORT APPENDIX B DRAINAGE REPORT B-1 South Lamar Blvd. Transportation Corridor Study Drainage Report Prepared for: City of Austin and HDR, Inc. Prepared by: and Services, Inc. Final 07-09-2015 Michael C. Meriwether,

More information

9. PROBABLE MAXIMUM PRECIPITATION AND PROBABLE MAXIMUM FLOOD

9. PROBABLE MAXIMUM PRECIPITATION AND PROBABLE MAXIMUM FLOOD 9. PROBABLE MAXIMUM PRECIPITATION AND PROBABLE MAXIMUM FLOOD 9.1. Introduction Due to the size of Watana Dam and the economic importance of the Project to the Railbelt, the Probable Maximum Flood (PMF)

More information

Open Channel Flow I - The Manning Equation and Uniform Flow COURSE CONTENT

Open Channel Flow I - The Manning Equation and Uniform Flow COURSE CONTENT Open Channel Flow I - The Manning Equation and Uniform Flow Harlan H. Bengtson, PhD, P.E. COURSE CONTENT 1. Introduction Flow of a liquid may take place either as open channel flow or pressure flow. Pressure

More information

STORMWATER MANAGEMENT REPORT

STORMWATER MANAGEMENT REPORT STORMWATER MANAGEMENT REPORT THE FAIRWAYS AT EDGEWOOD LOTS 5 & 6, BLOCK 1201 TOWNSHIP OF RIVER VALE BERGEN COUNTY, NEW JERSEY PREPARED BY: DAPHNE A. GALVIN PROFESSIONAL ENGINEER LICENSE NO. 24GE03434900

More information

APPENDIX E GREATER SPRINGFIELD RELIABILTIY PROJECT DRAINAGE ANALYSIS FOR THE NEWGATE/PHELPS ROAD AND THE HATCHETT HILL ROAD AREAS

APPENDIX E GREATER SPRINGFIELD RELIABILTIY PROJECT DRAINAGE ANALYSIS FOR THE NEWGATE/PHELPS ROAD AND THE HATCHETT HILL ROAD AREAS APPENDIX E GREATER SPRINGFIELD RELIABILTIY PROJECT DRAINAGE ANALYSIS FOR THE NEWGATE/PHELPS ROAD AND THE HATCHETT HILL ROAD AREAS New England East-West Solution (NEEWS) Greater Springfield Reliability

More information

PRELIMINARY CULVERT ANALYSIS REPORT FOR CULVERT NO. 008-C OREGON AVENUE OVER PINEHURST CREEK

PRELIMINARY CULVERT ANALYSIS REPORT FOR CULVERT NO. 008-C OREGON AVENUE OVER PINEHURST CREEK PRELIMINARY CULVERT ANALYSIS REPORT FOR CULVERT NO. 008-C OREGON AVENUE OVER PINEHURST CREEK Prepared for The District of Columbia Department of Transportation Washington, D.C. Prepared by Parsons Transportation

More information

B805 TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES - OPSS 805

B805 TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES - OPSS 805 B805 MEASURES - OPSS 805 805.1 GENERAL Construction activities frequently remove protective cover and expose soil to accelerated rates of erosion. Sediments generated thereby can be conveyed via runoff

More information

Modeling Great Britain s Flood Defenses. Flood Defense in Great Britain. By Dr. Yizhong Qu

Modeling Great Britain s Flood Defenses. Flood Defense in Great Britain. By Dr. Yizhong Qu Modeling Great Britain s Flood Defenses AIRCurrents Editor s note: AIR launched its Inland Flood Model for Great Britain in December 2008. The hazard module captures the physical processes of rainfall-runoff

More information

George Mason University Department of Civil, Environmental and Infrastructure Engineering

George Mason University Department of Civil, Environmental and Infrastructure Engineering George Mason University Department of Civil, Environmental and Infrastructure Engineering Dr. Celso Ferreira Prepared by Lora Baumgartner December 2015 Revised by Brian Ross July 2016 Exercise Topic: Getting

More information

D. MATHEMATICAL MODEL AND SIMULATION

D. MATHEMATICAL MODEL AND SIMULATION D. MATHEMATICAL MODEL AND SIMULATION D - i TABLE OF CONTENTS D.1 Objective of Model Development... D - 1 D.2 Selection of Software... D - 1 D.3 General Steps of Simulation by MOUSE... D - 1 D.4 Cases of

More information

University of the Virgin Islands Conceptual Stormwater Management Plan Coral Bay Watershed Final Letter Report (May 2005)

University of the Virgin Islands Conceptual Stormwater Management Plan Coral Bay Watershed Final Letter Report (May 2005) Final Letter Report (May 2005) Background The Coral Bay watershed, shown in Figure 1, is located in the southeastern portion of the island of St. John, U.S. Virgin Islands (USVI) and consists of approximately

More information

Open Channel Flow K Subramanya Solution Manual

Open Channel Flow K Subramanya Solution Manual We have made it easy for you to find a PDF Ebooks without any digging. And by having access to our ebooks online or by storing it on your computer, you have convenient answers with open channel flow k

More information

Technical Memorandum. City of Salem, Stormwater Management Design Standards. Project No:

Technical Memorandum. City of Salem, Stormwater Management Design Standards. Project No: Technical Memorandum 6500 SW Macadam Avenue, Suite 200 Portland, Oregon, 97239 Tel: 503-244-7005 Fax: 503-244-9095 Prepared for: Project Title: City of Salem, Oregon City of Salem, Stormwater Management

More information

Template for Sediment and Erosion Control Plan General Instructions. Section Instructions

Template for Sediment and Erosion Control Plan General Instructions. Section Instructions Template for Sediment and Erosion Control Plan General Instructions Introduction: Soil erosion and sediment deposition from farmlands can contribute to degraded surface water quality. Sediment delivery

More information

StreamStats: Delivering Streamflow Information to the Public. By Kernell Ries

StreamStats: Delivering Streamflow Information to the Public. By Kernell Ries StreamStats: Delivering Streamflow Information to the Public By Kernell Ries U.S. Department of the Interior U.S. Geological Survey MD-DE-DC District 410-238-4317 kries@usgs.gov StreamStats Web Application

More information

STRUCTURAL STABILITY ASSESSMENT

STRUCTURAL STABILITY ASSESSMENT STRUCTURAL STABILITY ASSESSMENT CFR 257.73(d) Bottom Ash Pond Complex Cardinal Plant Brilliant, Ohio October, 2016 Prepared for: Cardinal Operating Company Cardinal Plant Brilliant, Ohio Prepared by: Geotechnical

More information

CONCEPTS Conservational Channel Evolution and Pollutant Transport System

CONCEPTS Conservational Channel Evolution and Pollutant Transport System CONCEPTS Conservational Channel Evolution and Pollutant Transport System Eddy J. Langendoen Watershed Physical Processes Research Unit National Sedimentation Laboratory USDA Agricultural Research Service

More information

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area.

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area. Sediment Trench SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils [1] Performance of

More information

Selected Site BMPs: Why s the Water Muddy? John C. Hayes, Ph.D., P. E. Biosystems Engineering Clemson University

Selected Site BMPs: Why s the Water Muddy? John C. Hayes, Ph.D., P. E. Biosystems Engineering Clemson University Selected Site BMPs: Why s the Water Muddy? John C. Hayes, Ph.D., P. E. Biosystems Engineering Clemson University The BMP worked fine until last week when it rained! Turbidity Best Management Practices

More information

Drivable Grass Report for Hydraulic Performance Testing

Drivable Grass Report for Hydraulic Performance Testing Drivable Grass Report for Hydraulic Performance Testing Prepared for Soil Retention Products, Inc. Prepared by Michael D. Turner Amanda L. Cox Christopher I. Thornton March 2011 Colorado State University

More information

J.H. Campbell Generating Facility Pond A - Location Restriction Certification Report

J.H. Campbell Generating Facility Pond A - Location Restriction Certification Report J.H. Campbell Generating Facility Pond A - Location Restriction Certification Report Pursuant to: 40 CFR 257.60 40 CFR 257.61 40 CFR 257.62 40 CFR 257.63 40 CFR 257.64 Submitted to: Consumers Energy Company

More information