1 March 2017 Technical Explanatory Note on Sediment Basin Design prepared by Grant Witheridge Catchments & Creeks Pty Ltd ABN The Mechanics Of Sediment Basin Operation 1. Introduction This report provides an overview of the hydraulics of construction site sediment basins. The aim of the report is to explain, in simple terms, the fluid mechanics that determines how sediment basins are sized and operated, and to outline the design philosophy behind the new IECA Australasia sediment basin design guidelines (Appendix B) released in Sediment basins can be classified using various naming systems. In the past these classification systems have been based on either the type of soil/sediment that the basins are designed to treat (e.g. Type C, D & F), the drainage conditions within the basin (e.g. wet & dry basins), or the hydraulic conditions that exist during the normal operation of the basin (e.g. continuous flow & plug flow basins). Continuous flow operation means the basin continuously decants water while in operation. In these basins, the contained water is allowed to decant from the basin as soon as the flows reach the basin s outlet structure, even if the water has not reached the desired level of treatment. Continuous flow basins can operate as either free-draining basins, which are titled dry basins, or as non free-draining basins, which are usually titled wet basins. Plug flow operation means the basin is designed to prevent discharge during the initial treatment phase of the basin, or while the basin is filling to a predetermined volume. The operation of these basins normally occurs in three phases: (i) inflow, (ii) settlement and (iii) decent; however, these phases can overlap. It is important to note that once a plug flow basin reaches its full volume, it then begins to operate as a continuous flow basin; however, the basin will not freely drain to an empty condition once the inflow stops. Instead, the basin will usually drain back to its designated full condition, after which the basin may or may not need to be manually drained to its designated empty condition. In the new IECA guidelines, sediment basins are classified as Type A, B, C & D basins. This classification breaks away from the traditional soil-based classification of Type C for coarse grained soils, Type D for dispersive soils, and Type F for fine grained soils; and instead adopts a simple alphabetic classification that retains the title and function of both the Type C and D basins. The operation of Type F basins was considered to be so similar to Type D basins that the term was discontinued. 2. Terminology The terminology used to describe the various components of a sediment basin can be controversial because the mechanics of these basins overlaps several fields of science and engineering each profession having its own preferred terminology. The mechanics of construction site sediment basins also shares a lot of similarities with the fluid mechanics of wastewater treatment systems, which can also incorporate continuous and plug flow systems. Catchments and Creeks Pty Ltd Mechanics of Sediment Basin Operation Page 1.

2 The terminology adopted within this paper is not wholly consistent with that used in Auckland, New Zealand or the USA to describe the sediment basins or by the wastewater industry to describe settling ponds. Figure 1 identifies some of the terms used within this paper. Figure 1 Adopted terminology for sediment basins 3. The mechanics of continuous flow sediment basins The mechanics of continuous-flow sediment basins is the most basic of all sediment basins. These basins operate with a continuous flow of water passing through a settling pond that has been sized to achieve sufficient residence time to allow the settlement of a specified particle size. It is generally not sufficient for the sediment particles to only partially settle before they reach the decent end of the basin; instead, it is usually necessary for the particles to fully settle to the floor of the basin so that they can adhere to the rest of the settled sediment. It is only through this action that the settled sediment can resist the shear forces resulting from the clear supernatant flowing above the sediment. In its most basic form, a continuous flow basin is only suitable for the treatment of waters containing sediment particles that exhibit good settling properties. In order for a clayey sediment to have good settling properties, most of the clay particles need to be bound into small aggregates or peds. If the soil is unstable in water, or has been heavily disturbed by mechanical equipment, then there is a greater risk that the individual clay particles will break free of these natural peds and stay suspended as the flow passes through the sediment basin. It is for the above reasons that continuous flow sediment basins are only considered suitable for the treatment of good-settling, coarse-grained soils (i.e. soils that are both non-dispersive, and have minimal fines). Consequently, these sediment basins have traditionally been termed Type C basins ( C for coarse grained soils). In order to improve the ability of Type C basins to capture fine sediment particles, either a geotextile or aggregate filter can be incorporated into the basin s outlet structure (usually a riser pipe ). In theory this means that the finer sediment particles do not need to fully settle to the floor of the basin before the fluid reaching the outlet; however, it is generally recognised that neither a geotextile or aggregate filter is sufficient to capture and retain most of the clay-sized particles. Consequently, Type C sediment basins have rarely performed well on Australian construction sites given the fine and dispersive nature of many Australian soils. Further improvements can be made to the performance of these basins through the integration of a floating, skimmer-type decent system, which aims to decent the cleanest water from the upper surface of the settling pond. Figure 2 demonstrates the operation of continuous-flow sediment basins. Catchments and Creeks Pty Ltd Mechanics of Sediment Basin Operation Page 2.

3 Figure 2 Typical stages of operation for a continuous-flow sediment basin The sizing of continuous-flow sediment basins is based on the idealised settlement characteristics of sediment particles passing uniformly through a rectangular basin (i.e. uniform, non-turbulent flow conditions exist throughout the basin). 4. The mechanics of plug flow sediment basins The mechanics of a plug-flow sediment basin is based on a staged approach to water treatment. The first stage is the capturing of the inflow, the second stage is the settlement of the retained fluid, and the final stage is the decanting of the clear supernatant leaving behind the settled sediment. There are, however, two modes of operation for most plug-flow basins. The first mode of operation is when the volume of storm runoff entering the basin is less than the available basin volume, which relates to the case described above. This means the basin will not overflow during the basin s operation. Figure 3 demonstrates the basic operation of a plug-flow sediment basin during the first mode of operation (i.e. no uncontrolled overtopping). Figure 3 Typical stages of operation for a non-overtopped, plug-flow sediment basin Catchments and Creeks Pty Ltd Mechanics of Sediment Basin Operation Page 3.

4 The second mode of operation is when the volume of runoff entering the basin is greater than the available basin volume. This means the basin reaches its full capacity and overflows begin to occur during the filling and/or settling stages of its operation. During this mode of operation the basin s performance mimics that of a continuous-flow sediment basin. Entering this second mode of operation does not necessarily mean that the basin has failed, or that the overflow will necessarily fail to meet the desired water quality standard, but it is normal for the water quality to slowly decline as this mode of operation continues. Plug-flow basins can be designed solely for the first mode of operation, in which case the size of the basin is based on a specified volume of runoff, which is normally based on a probable storm frequency (e.g. Type D basins). Alternatively, plug-flow basins can be designed for both modes of operation, in which case the basin is sized for a specified volume, as well as a specified minimum settling pond surface area (e.g. the new Type A basins). Plug-flow basins have traditionally been used to treat waters that either contain significant quantities of fine-grained sediment, or significant quantities of dispersive clays. 5. The mechanics of Type A sediment basins In 2016, IECA Australasia introduced a new sediment basin design, the Type A basin, which was based on the high efficiency sediment basins developed in Auckland, New Zealand. Key requirements of the Auckland basin design include: On earthwork sites with slopes less than 10% and less than 200 m in length, the sediment basin has an equivalent volume of 2% of the contributing catchment (i.e. 200 m 3 for each ha of contributing catchment). On sites with slopes greater than 10% and/or 200 m in length, the sediment basin has an equivalent volume of 3% of the contributing catchment (i.e. 300 m 3 for each ha of contributing catchment). Sediment clean-out is required when the volume of retained sediment reaches 20% of the basin s design volume. Thus the sediment storage volume is taken as 20% of the pond volume, and this sediment storage volume is included within the specified basin volume of m 3 per hectare of contributing catchment. A dead storage volume of 30% of the total settling pond volume is to be allocated. This is the non-decant volume located below the low-flow decent system. This volume is retained to help dissipate inflow energy during the initial filling of the basin. Typically this volume consists of the lower 0.4 to 0.8 m of the pond, and includes the nominated sediment storage volume of 20% of the total settling pond volume. The recommended decant rate is 3 litres/second/ha of contributing catchment. If two floating decant arms are required, the lower arm must decant throughout the full live storage depth, and the upper arm should only operate through the upper 50% of the live storage depth. If three decant arms are used, then the operating range of each arm should be: 100% of live storage, 67% and 33%. The length to width ratio of the settling pond is no less than 3:1 and no greater than 5:1. The settling pond depth (including the designated sediment storage zone) may be 1 to 2 metres, but no deeper than 2 m. Ideally, drainage catchments should be limited to a maximum of 5 ha per basin. As previously discussed, the terminology adopted throughout this paper is not wholly consistent with that used in Auckland. For the purposes of clarity, Figure 4 demonstrates some of the terms used in Auckland in relation to the above dot points. Catchments and Creeks Pty Ltd Mechanics of Sediment Basin Operation Page 4.

5 Figure 4 Terminology as used for the Auckland sediment basins Developing a design procedure for the new Type A basins involved establishing a mathematical relationship between the sizing of sediment basins in Auckland, and the key hydrological parameters associated with the operation of these basins in Auckland. This meant that these basins could now be sized appropriately for various climatic regions in Australia. The mechanics of a Type A sediment basin is described below and shown in Figure 5. Figure 5 Typical stages of operation for a Type A sediment basin First mode of operation basin operation without overflow: The settling pond begins to fill while the water level remains below the elevation of the primary overflow spillway. During this stage it is critical for the inflow to be uniformly distributed across the width of the basin, and for the inflow to have low levels of turbulence, thus allowing for optimum particle settlement. If the starting water level is at the designated empty condition, then the floating, low-flow decent system begins to decant water almost immediately after the water first enters the basin. Catchments and Creeks Pty Ltd Mechanics of Sediment Basin Operation Page 5.

6 Technical note 1: Even though a floating skimmer pipe collects water from the upper surface of the settling pond, it is important to note that this does not mean that only surface water will be drawn towards the outlet. Supernatant will flow towards this decent pipe from a full range of depths, meaning that water can be drawn up towards the skimmer pipe from a metre or more below the water surface. Selective withdrawal is a particular type of decanting. It is a process where water is selectively withdrawn from a specific layer or elevation within a stratified fluid. Large lakes and water supply dams can contain several stratified layers of water, each with a different water temperature and/or density. However, fluid stratification is a condition that only occurs in certain circumstances within sediment basins. This means that the majority of the water flowing towards a skimmer pipe will come from the full depth of the clear supernatant, with a small quantity of water possibly being extracted from within the settling floc blanket. If the water level in the settling pond continues to rise, then eventually more of the low-flow skimmer pipes will be engaged (depending on the design of the low-flow outlet structure). Depending on the design of the riser pipe outlet, it is possible that the crest of the riser pipe will act as a medium flow spillway (Figure 2b). In the Auckland system, this riser pipe consists of a 150 mm diameter pipe, and its crest is set 300 mm below the primary spillway crest. This design means that the crest of the riser pipe operates as another component of the low-flow decant system. In Australian, this riser pipe typically has a larger diameter, and it may not always be appropriate for the crest of the riser pipe to be set 300 mm below the spillway. Second mode of operation basin operates with a degree of overflow: If the water level in the settling pond exceeds the elevation of the spillway crest, then water will discharge freely over the spillway. Again it is important to note that similar to the low-flow skimmer pipes, the spillway will not just skim clear supernatant from the top of the settling pond, but instead, water can be drawn towards the spillway from a wide range of depths. Because the basin s total decent (low-flow pipes plus spillway) has now increased, the interface between the suspended sediment and the clear supernatant will move closer towards the basin s outlet (see Figure 5c). If the basin s decent continues to be high, then eventually the suspended sediment will reach the skimmer pipes and the overflow spillway, and the basin will reach a condition of water quality failure. Third mode of operation inflows cease and the basin is de-watered: Once inflows to the basin cease, the basin will rapidly drain to the elevation of the spillway crest, then slowly drain to the lowest decent setting of the floating decant pipes. If, at the point when the basin stops spilling over the spillway, the quality of the decant water from the skimmer pipes does not meet the required water quality (typically 50 mg/l or the equivalent NTU), then the low-flow decent system can be shut-off to allow the sediment basin time to achieve optimum supernatant water quality. When a suitable supernatant water quality is achieved, the basin is allowed to de-water to its designated empty condition, which is usually set at the lowest travel point of the lowest skimmer pipe. It is noted that circumstances can exist where the basin s operating conditions will require the basin to be de-watered immediately, even if the supernatant water quality fails to meet the desired standard. Such conditions may exist in the event of an imminent storm that is expected to refill the basin. Catchments and Creeks Pty Ltd Mechanics of Sediment Basin Operation Page 6.

7 5.1 Numerical analysis of the Auckland basin performance The following is a summary of the mathematical analysis of the Auckland basins that was developed during the recent IECA review. Initially an investigation was conducted into the continuous flow mode of operation (i.e. a full basin with inflow = outflow = 3 litres/second/ha). Then an investigation was conducted into the plug flow operation of the basin (i.e. when a storm does not cause the basin to overflow). If it is assumed that: the Auckland basins allow the full settlement (to the basin floor) of the critical particle size; and the shortest residence time occurs when the basin is full, but not overflowing, and the inflow rate equals the low-flow skimmer pipe decant rate of 3 litres/second/ha; and the basin s hydraulic properties can be represented by a continuous flow process; then: using Stakes Law it was determined that the Auckland basins were sized for an equivalent mm particle size. It is noted that for a traditional Type C sediment basin, the critical particle size is typically 0.02 mm, which is four times the size of the equivalent particle size attributed to the Auckland basins. This could partially explain the increased efficiency of the Auckland sediment basins. The next step was to analyse the volume of the Auckland basin to see if a relationship could be developed that could link the basin volume to a particular storm event. It is noted that the total volume of a sediment basin (V B ) is made up of the settling volume (V S ) plus the nominated sediment storage volume (V SS ), which is that part of the basin s volume that is made available for storage of the settled sediment. This means the sediment storage volume cannot be considered an effective part of the basin s settling volume. The Auckland design process nominates 20% sediment storage volume, which is included within the nominated total volume of 300 m 3 per hectare. Therefore, the effective settling volume (V S ) is only 80% of 300 m 3, which is 240 m 3 per hectare. A simplified Excel-based analysis of the Auckland basins indicated that the specified settling volume of 240 m 3 per hectare is likely to provide non-overtopping operating conditions for a storm frequency of between 1 and 1.5 years. This means that during a 1 in 1 year storm, the basin is likely to fill, but not overtop; and that the desired discharge water quality is likely to be maintained throughout the basin s operation during such a storm. The key outcomes from the Auckland sediment basin analysis can be summaries as: the performance of the Auckland basins is related to both the basin s settling volume (V S ) and the basin s surface area (A S ). the basins appear to have sufficient volume to cater for most 1 in 1 year to 1 in 1.5 year storms without overtopping with respect to the basin s surface area and low-flow decent rate, the effective critical particle size for a continuous flow operation is mm, which is much finer than traditionally used in Australian sediment basins. 5.2 Key design variables that need to be managed for Type A basins In order to optimise the design of a Type A basin it is necessary to identify the key design variables, the limits and constrains of these variables, and the influence these variables have on the design of the basin. A summary of the key variable is presented in Table 1. Catchments and Creeks Pty Ltd Mechanics of Sediment Basin Operation Page 7.

8 Table 1 Summary of key design variable Variable Typical value Range Influence of variable on basin design Design storm 1 in 1 year 1 to 5 yr ARI Increasing the design storm severity increases the required basin volume Catchment area Desirable < 5 ha per basin Length:width ratio 3:1 2:1 to 10:1 Important when overtopping occurs Total pond volume The total pond volume (V T ) = settling volume (V S ) + lower storage (V L ) Settling zone depth 1.5 m 0.6 to 3.0 m Minimum depth of 0.6 metres Lower storage volume (dead storage, V L ) Sediment storage volume (V SS ) 40% of settling zone volume, (V S ) 30% of settling zone volume Low-flow decent rate 0.3 to 0.9 (L/s/ha) N/A Includes the sediment storage zone Minimum V L = V SS + 10% (V S ) Approximately 30% of total volume N/A Minimum V SS = 30% (V S ) Approximately 20% of total volume Increasing the low-flow decent rate can reduce the required basin volume Critical particle size 0.01 mm to 0.02 Only critical when the settling zone depth is greater than the critical value, which causes the minimum pond area (A S ) to become critical Water temperature Depends on local conditions Based on the coldest wet month Maximum allowable supernatant velocity 1.5 cm/s 1.0 to 2.0 cm/s Depends on whether the sediment floc is suspended or fully settled (i) Settling volume (V S ) The settling volume directly impacts on the settling pond surface area; however, if the settling pond depth exceeds its optimum value, then the surface area of the settling pond will be governed by the minimum pond surface area requirement. The settling volume can be altered by modifying the following variables: the low-flow decent rate, either by modifying the flow rate per decent arm, or increasing the number of decent arms the nominated design storm frequency (e.g. 1 yr, 2 yr or 5 yr ARI). (ii) Lower storage (V L ) The required lower storage volume directly impacts on the total basin volume. The lower storage volume incorporates the sediment storage zone, plus a volume above the settled sediment that is normally retained between storms, but this water can be used on the site for such things as dust control and plant watering if desired. If this upper layer of the lower storage volume is not retained between storms, then the basin will be able to receive a certain volume of inflow before the basin s floating decant system begins to discharge flows. If this upper layer of the lower storage volume is retained between storms (i.e. not used for dust control, etc.), then this clear supernatant liquor will be the first water decanted from the basin at the start of the next storm. The absence of this retained supernatant will likely mean that turbulence from the initial inflows will cause the re-suspension of previously settled sediment, meaning that the initial discharge from the basin may exceed the desired water Catchments and Creeks Pty Ltd Mechanics of Sediment Basin Operation Page 8.

9 turbidity. This is an issue that will need to be monitored once the use of these basins becomes more widely spread. The lower storage volume can be altered by modifying the requirements for the sediment storage volume. (iii) Sediment storage volume (V SS ) The required sediment storage volume directly impacts on the total basin volume. Increasing the allowable sediment storage volume will increase the allocated lower storage volume. Increasing the allowable sediment storage volume can possibly decrease the frequency of basin maintenance (i.e. reduce the frequency of de-silting operations). (iv) Low-flow decent rate The low-flow decent rate impacts on the required settling volume, and therefore the total volume of the settling pond. The allowable low-flow decent rate may be influenced by: the maximum allowable supernatant scour velocity that could cause settled sediment to be drawn up towards the decent pipes; and the knowledge that increasing the low-flow decent rate will increase the minimum required surface area of the settling pond; especially when it is considered that it is desirable to avoid those circumstances where the settling pond surface area is governed by the minimum surface area requirement. (v) Width of the emergency overflow spillway The width of the emergency spillway can directly influence the risk of settled sediment being drawn up and dragged over the spillway by friction forces (scour) caused by the contraction of the supernatant flow as it approaches the spillway. The design limits resulting from this hydraulic issue are not currently fully understood. Consequently, this is an issue that will require further monitoring. As discussed above, as surface waters move towards the spillway, the width of the flow must contract from the width of the basin to the width of the spillway. This contraction of flow causes a direct increase in flow velocity, which technically increases the risk of these surface water disturbing the settled sediment below. However, the saving grace is that this contraction of flow normally occurs over an inclined batter leading to the spillway crest. It is therefore possible that the upper surface of the settled sediment blanket is located well away from the crest of the spillway (due to the both the depth of the blanket and the inclined face of the earth batter leading up to the spillway). This means that disturbance to the sediment blanket may not occur. This is an aspect of sediment basin fluid mechanics that is not well understood, and only field testing will identify if scour of the settled sediment blanket will become a problem. (vi) Design storm frequency The design storm frequency directly impacts on the required settling pond volume and the settling pond surface area. Increasing the severity of the design storm will improve the expected long-term water quality outcomes, but will significantly increase the cost of the basin s construction. (vii) Critical particle size Selection of the critical particle size directly impacts on the minimum settling pond surface area requirement, but may not necessarily alter the required basin volume. Decreasing the critical particle size will likely improve the expected long-term water quality outcomes, but Catchments and Creeks Pty Ltd Mechanics of Sediment Basin Operation Page 9.

10 may increase the cost of the basin s construction depending on the nominated basin depth. (viii) Settling pond water temperature The temperature of the settling pond water is usually governed by the air temperature during storm events. The nominated water temperature is usually set as the air temperature during the wet season; however, this rule may not apply as temperatures approach zero. Reducing the water temperature reduces the settling velocity of sediment particles, resulting in an increase in the required settling pond surface area. 5.3 The optimum settling pond depth and its importance to Type A basin design The sizing of a Type A basin is governed by the requirements for both a minimum settling volume (V S ), and a minimum settling zone surface area (A S ). Under normal circumstances, a basin designer should try to optimise the basin s dimensions such that both the pond volume and surface area are minimised. For a given low-flow decant rate (Q A ), there is an optimum settling zone depth (D S ) that will allow the minimum settling volume and minimum settling zone surface area requirements to be achieved concurrently. Conversely, for a given settling zone depth, there is an optimum low-flow decant rate that will also allow both of these design requirements to be achieved concurrently. If site conditions place restrictions on the total depth of the sediment basin (D T ), then this will directly impact upon the maximum allowable depth of the settling zone (D S ); however, the relationship between the settling zone depth and the total pond depth is complex, and depends on a number of factors. 5.4 Determination of basin sizing equations that could be utilised across Australia The original design aim of the Type A basin was to replicate the performance of the Auckland basins. A simplified Excel flow model was used to analyse the performance of the Auckland basins as they are operated in Auckland. The Excel model incorporated the several assumptions are discussed below. Adopting these assumptions means that the real life outcomes of these Type A basins cannot be guaranteed. Ultimately the performance of Type A basin will be determined from in-situ testing and design optimisation. The assumptions incorporated into the Excel model include: Rainfall is uniform over the drainage catchment, and is uniform throughout the storm s duration. The drainage catchment is approximately rectangular such that the rate of increase in inflow into the basin is steady from time 0 to its peak discharge at time TB, which is equal to the time of concentration of the catchment (i.e. the point in time when all of the catchment is contributing flow into the basin). The inflow hydrograph can be represented by a simple trapezoidal time discharge profile (Figure 6) with a constant rise in discharge to the peak, a constant peak inflow that is maintained for a sufficient period to allow the inflow of the storms runoff volume, and then a linear decline in the inflow rate until a zero inflow is reached at time TE. Catchments and Creeks Pty Ltd Mechanics of Sediment Basin Operation Page 10.

11 Figure 6 Adopted basin inflow hydrograph The storm duration (T) is assumes to be equal to the time of concentration for the catchment (T C ); thus the peak discharge can be estimated using the Rational Method, Q PEAK = C*I*A. The total volume of the inflow hydrograph is equal to the total rainfall depth (I*T) times the catchment area (A) times the volumetric runoff coefficient (C V ); thus V = (C V *I*T*A). The volumetric runoff coefficient (C V ) was estimated by developing a best fit equation for a clayey soil (soil Group D in Table B7 of IECA (2008)). Low-flow begins to discharge from the basin as soon as flows enter the basin (i.e. there is no initial filling of the basin). This means the analysis will theoretically under-estimate the required storage volume. It is noted that this Excel-based analysis did not take into account the volume of the retained supernatant (i.e the dead water storage minus the nominated sediment storage volume, which was taken as 25% of the settling zone volume). This means the total volume of the sediment basin will be effectively 15% of the settling volume larger that that determined within this analysis. However, it is also noted that the existence of this additional volume will not alter the performance of the basin with respect to the Excel analysis. The sizing of Type A basin is based on satisfying the following three-point test: (i) a minimum settling pond volume, V S (ii) a minimum settling pond surface area, A S (iii) a maximum supernatant flow velocity to prevent disturbance of the settled sediment floc. (i) Minimum settling volume, V S : The minimum settling volume is determined from the following equation: where: V S = minimum settling volume [m 3 ] V S = K. A (I X yr, 24 hr) 1.8 (Eqn. 1) K = equation coefficient that varies with the design event (X) and the chosen low-flow decent rate (Q A ) refer to Table 2 A = area of the drainage catchment connected to the sediment basin [ha] I X yr, 24 hr = the average rainfall intensity for an X-year, 24-hour storm [mm/hr] X = the nominated design event (ARI) expressed in years Catchments and Creeks Pty Ltd Mechanics of Sediment Basin Operation Page 11.

12 Table 2 Type A basin sizing equation coefficient K Low-flow decent rate Q A Coefficient K for specific design events L/s/ha m 3 /s/ha 1 year 2 year 5 year (ii) Minimum surface area requirement, A S : The basin s settling zone must satisfy a minimum surface area (A S ) measured at the midelevation of the basin s settling zone. A S = K A Q L (Eqn. 2) where: A S = minimum mean-depth pond surface area [m 2 ] Q L = the maximum low-flow decent rate prior to flows overtopping the emergency spillway [m 3 /s] = Q A *A Q A = the low-flow decent rate per hectare of contributing catchment [m 3 /s/ha] A = area of the drainage catchment connected to the basin [ha] K A = equation coefficient for a Type A basin (refer to Table 3) K A = (18.μ) / (g.(s-1).d 2 ) (Eqn. 3) where: μ = kinematic viscosity of the water at a given temperature [m 2 /s] g = acceleration due to gravity [m/s 2 ] s = specific gravity of critical sediment particle (assume: s = 2.65 for clay soils) d = diameter of critical sediment particle (default: d = 0.01 mm) [m] Table 3 Equation coefficient (K A ) for 0.01 mm particle size with specific gravity of 2.65 Recommended water temperature ( C) Equation coefficient, K A 14,520 12,670 11, The nominated critical particle size (d p = 0.01 mm) should be treated only as a design variable, not an performance standard. Consequently it should not be assumed that the basin will only be capable of capturing particles larger than 0.01 mm. This design variable is used simply because it allows the incorporation of important design variables such as water temperature, water viscosity, and residence time. (iii) Maximum supernatant velocity, V Surface : It is important to ensure that the maximum clear water (supernatant) velocity above the settled sediment floc (V Surface ) does not exceed a velocity that will cause disturbance to the settled sediment. From the field testing performed on the decanting of wastewater treatment plants (Witheridge & Wilkinson, 1989), the allowable supernatant velocity is currently assumed to be 1.5 cm/s. Field testing of Type A sediment basin may lead to a modification of this allowable supernatant velocity. Catchments and Creeks Pty Ltd Mechanics of Sediment Basin Operation Page 12.

13 6. The mechanics of Type B sediment basins The design of Type B basins is based on a modification of the Type A basin design. The basic operation of a Type B sediment basin is shown in Figure 7. Figure 7 Typical stages of operation for a Type B sediment basin Two design options have been prepared, and the choice between these two options depends on the expected floc settling characteristics. The first design option, Option 1B, is based on setting a minimum settling pond surface area (A S ) and depth (D S ) such that the settled sediment has sufficient time to settle to the floor of the basin, which means the sediment floc is able to form a slightly compacted sediment blanket. It is assumed that allowing the sediment to fully settle the basin floor will increase the resistance of the sediment blanket to the effects of scour caused by the decanting of the supernatant. The second design option, Option 2B, is based on providing sufficient time to allow the sediment floc to settle at least 600 mm. This design option results in a basin with a greater depth, but smaller surface area, than design Option 1B. Both design options assume that the layout of the sediment basin has incorporated the same hydraulic efficient characteristics as a Type A basin, including: energy dissipation / mixing forebay automatic dosing with flocculant or coagulant inflows passing over a level spreader rectangular settling pond with no deadwater zones. The minimum dimensions of a Type B basin must be based on concurrently satisfying the minimum average surface area (A S ), the minimum settling zone depth (D S ) or depth to the settled floc (D F ), and the maximum allowable supernatant velocity (v S ) requirements. Unlike a Type C basin, the sizing of the settling pond surface area (A S ) does not incorporate a hydraulic efficiency correction factor (H e ). This is because of the required hydraulic efficient design characteristics listed above ensures that inflows into the settling pond are evenlydistributed and have low-turbulence, thus H e = 1.0. If laboratory testing of the sediment-flocculant partnership indicates a poor sediment settlement rate, such as less than 100 mm in 15 minutes, then the minimum depth of the settling zone (D S ) is governed by the minimum recommended depth of 0.5 m, which increases the volume of the settling zone compared to those basins that utilise a more effective flocculant. Type B basins do not incorporate a low-flow decant system, consequently the overflow spillway functions as the sole point of discharge from the basin. In order to reduce the risk of the re- Catchments and Creeks Pty Ltd Mechanics of Sediment Basin Operation Page 13.

14 suspension of settled or still-settling sediment, the overflow spillway on a Type B basin should be given the maximum practical width. Ideally the maximum allowable supernatant (clear liquor) velocity upstream of the overflow spillway should be 1.5 cm/s (0.015 m/s) during the basin s design storm (i.e. Q = 0.5 Q1); however, this may not always be practical for Type B basins. In such cases, designers should take all reasonable measures to achieve a spillway crest width just less than the top width of the settling zone. The nominated settling zone depth for an Option 2B design needs to be within the range of 0.6 to 2.0 m. The greater the nominated depth, the smaller the required surface area of the basin, but the volume of the settling zone (V S ), and consequently the total basin volume, will essentially remain unchanged. The minimum recommended settling zone depth for an Option 2B design is 0.6 m, which is an increase from the 0.5 m used in Option 1B. This is because the sediment floc in an Option 2B basin is considered to be still settling as it approaches the overflow spillway; whereas in design Option 1B the sediment floc is assumed to have fully settled, and thus more resistant to disturbance. 7. The mechanics of Type C sediment basins The mechanics of a Type C sediment basin is based on the properties of a traditional settling pond. These basins operate with a continuous flow of water passing through the settling pond, which has been sized to allow the full settlement (to the bottom of the nominated settling zone) of a specified particle size. The minimum average surface area of the settling zone (A S ) is based on the following equation. A S = K S H e Q (Eqn. 4) where: A S = average surface area of settling zone = V S /D S [m 2 ] K S = sediment settlement coefficient = the inverse of the settling velocity of the critical particle size H e = hydraulic efficiency correction factor Q = design discharge = 0.5 Q1 [m 3 /s] Q1 = peak discharge for the critical storm duration 1 in 1 year ARI event V S = volume of the settling zone [m 3 ] D S = depth of the settling zone [m] The basic operation of a Type C sediment basin is shown in Figure 8. Figure 8 Typical stages of operation for a Type C sediment basin with riser pipe Catchments and Creeks Pty Ltd Mechanics of Sediment Basin Operation Page 14.

15 Type-C sediment basins typically adopt a design discharge of 0.5 times the peak 1 in 1 year ARI discharge (Q1), and a critical particle size of d = 0.02 mm ( m). The hydraulic efficiency correction factor (H e ) depends on flow conditions entering the settling pond, and the shape of the basin. The minimum recommended depth of the settling zone (D S ) is 0.6 m. The desirable minimum length to width ratio at the mid-elevation of the settling zone is 3:1. The use of internal baffles may be required in order to prevent short-circuiting if the length-to-width ratio is less than three. The development of Equation 4 is based on a rectangular settling pond with uniform inflow (Q), width (W), depth (D) and length (L). The hydraulic analysis of such a settling pond provides the following outcomes: the average forward velocity: V H = Q/(D.W) the travel time across the basin: t H = L/(VH) thus, t H = (L.D.W)/Q = Volume/Discharge in other words, t H = retention time The assumption of uniform flow means a hydraulic efficiency correction factor (H e ) of unity is adopted. The falling velocity of a sediment particle depends on: particle size, shape and relative density water temperature (a factor of viscosity) assumed to be based on temperature of rainfall water motion (turbulence and up-flow caused by mass settlement of sediment particles) electro-magnetic forces (not considered in the Stokes Law equation). Stokes Law (Equation 5) is typically adopted for the determination of the particle settling velocity. V p = (g.(s-1).d 2 )/(18.μ) = 1/K S (Eqn. 5) where: V p = particle falling velocity [m/s] s = specific gravity of particle g = acceleration due to gravity [m/s 2 ] d = particle diameter [m] μ = kinematic viscosity of the water at a given temperature [m 2 /s] If the settling pond is sized such that the critical particle size settles to the bed (t p ) just before reaching the end of the basin, then: t H = t p or t H = (L.D.W.)/Q = D/V p thus Surface area (A S ) = L.W = Q/V p So for a soil with critical particle size of 0.02 mm, and specific gravity of 2.6, and with a basin water temperature of 13º C, then V p = m/s, and K S = 3400, thus: A S = Q/ = 3400(Q) = K S (Q) (Eqn. 6) where: A s = surface area of sediment basin at the base of the settling zone Q = design storm peak flow rate; typically Q = 0.5 Q1 Catchments and Creeks Pty Ltd Mechanics of Sediment Basin Operation Page 15.

16 Q1 = peak discharge from the 1 in 1 year ARI design storm If near-uniform flow conditions do not occur throughout the basin, then the required surface area (A S ) is determined from Equation 7, which is the same as Equation 4. General design equation: A S = K S H e Q (Eqn. 7) 8. The mechanics of Type D sediment basins Type D sediment basins operate as plug-flow settling tanks as demonstrated in Figure 9. Figure 9 Typical stages of operation for a Type D sediment basin The minimum volume of the upper settling zone is defined by Equation 8. V S = 10. R(Y%,5-day). C V. A (Eqn. 8) where: V S = volume of the settling zone [m 3 ] R(Y%,5-day) = Y%, 5-day rainfall depth [mm] C V = volumetric runoff coefficient A = effective catchment surface area connected to the basin [ha] The minimum recommended depth of the settling zone is 0.6 m, or L/200 for basins longer than 120 m (where L = effective basin length). It is recommended that settling zone depths greater than 1 m should be avoided if the particle settlement velocity is expected to be slow. The desirable minimum length to width ratio of 3:1 is also recommended for Type D basins. The length to width ratio is important for Type D basins because they operate as continuous-flow settling ponds (i.e. similar to Type C basins) once the flow begins to discharge over the emergency spillway. Type D basins are typically designed for a maximum 5-day cycle that being the filling, treatment and discharge of the basin occurs within a maximum 5-day period. In some tropical regions this may not be practical, and either a shorter or longer time frame may be required. The use of a shorter time period usually requires the application of fast acting flocculants that usually require a much higher degree of environmental management compared to the use of gypsum. The use of a longer time period will require the construction of a significantly larger basin. Unlike permanent stormwater treatment ponds and wetlands, Type D basins are not designed to allow high flows to bypass the basin. Even when the basin is full, sediment-laden stormwater runoff should continue to be directed through the basin. This allows the continued settlement of coarse-grained particles contained in the flow. Such basin management practices may cause Catchments and Creeks Pty Ltd Mechanics of Sediment Basin Operation Page 16.

17 some re-suspension and discharge of previously settled fine sediments during heavy storms, but the task of trapping the anticipated large volume of sand and coarse silts washed from a construction site is considered more important. In effect, Type D basins are designed to produce high quality outflows during the more frequent lighter storms (i.e. storms less than the 1 in 1 year ARI storm), but to also allow the continued trapping of coarse sediments during the less frequent heavy storms (i.e. storms equal to, or greater than, the 1 in 1 year ARI storm). The volumetric runoff coefficient (C V ) is not the same as the discharge runoff coefficient (C) used in the Rational Method to calculate peak runoff discharges. A volumetric runoff coefficient of 1.0 is typically applied to impervious surface areas, including open soil surfaces that have been compacted by construction traffic. Grant M Witheridge Director RPEQ 3591 March, 2017 Catchments and Creeks Pty Ltd Mechanics of Sediment Basin Operation Page 17.

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area.

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area. Sediment Trench SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils [1] Performance of

More information

APPENDIX B REVISION JUNE 2018

APPENDIX B REVISION JUNE 2018 APPENDIX B REVISION JUNE 2018 This revision of Appendix B of IECA (2008) is the finalised version of the draft release in December 2016 following industry consultation. IECA acknowledges the financial

More information

Instream Sediment Control Systems

Instream Sediment Control Systems Instream Sediment Control Systems INSTREAM PRACTICES Photo 1 Photo 2 Modular sediment The information contained within this series of fact sheets deals only with the design of temporary instream sediment

More information

Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils Type 3 System Instream Works Dispersive Soils

Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils Type 3 System Instream Works Dispersive Soils Sediment Basins SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils Type 3 System Instream Works Dispersive Soils Symbol Photo 1 Type A basin Photo

More information

Coarse Sediment Traps

Coarse Sediment Traps Coarse Sediment Traps SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils [2] Type 3 System Supplementary Trap Dispersive Soils [1] Though primarily

More information

Rock & Aggregate Drop Inlet Protection

Rock & Aggregate Drop Inlet Protection Rock & Aggregate Drop Inlet Protection SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System Supplementary Trap Dispersive Soils

More information

Sediment Control Practices. John Mathews Ohio Dept. of Natural Resources, Division of Soil and Water Resources

Sediment Control Practices. John Mathews Ohio Dept. of Natural Resources, Division of Soil and Water Resources Sediment Control Practices John Mathews Ohio Dept. of Natural Resources, Division of Soil and Water Resources Practices Treat the Largest Soil Particles Sand Sand Silt Clay Treated Untreated Settleable

More information

APPENDIX G APPENDIX G SEDIMENT CONTAINMENT SYSTEM DESIGN RATIONALE

APPENDIX G APPENDIX G SEDIMENT CONTAINMENT SYSTEM DESIGN RATIONALE APPENDIX G SEDIMENT CONTAINMENT SYSTEM DESIGN RATIONALE March 18, 2003 This page left blank intentionally. March 18, 2003 G-2 FIGURES Page # Figure G.1 Estimated Runoff from Precipitation Over Different

More information

Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils

Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils Sediment Weirs SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils [1] Type 3 classification

More information

Construction Exits Rock pads

Construction Exits Rock pads Construction Exits Rock pads SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow [1] Clayey Soils Type 3 System Supplementary Trap Dispersive Soils [1] Minor

More information

U-Shaped Sediment Traps

U-Shaped Sediment Traps U-Shaped Sediment Traps SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils [1] Type 3 System Supplementary Trap Dispersive Soils [1] Generally

More information

Stormwater Outlet Sediment Traps

Stormwater Outlet Sediment Traps Stormwater Outlet Traps SEDIMENT CONTROL TECHNIQUES Photo 1 Excavated sediment trap just prior to scheduled clean-out (note energy dissipater at end of pipe) Photo 2 A supplementary straw bale barrier

More information

Sediment Weirs (Instream)

Sediment Weirs (Instream) Sediment Weirs (Instream) INSTREAM PRACTICES Flow Control No Channel Flow Dry Channels Erosion Control Low Channel Flows Shallow Water Sediment Control High Channel Flows [1] Deep Water [1] Sediment weirs

More information

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1]

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] Rock Linings DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1] The design of permanent installations

More information

Chutes Part 5: Rock linings

Chutes Part 5: Rock linings Chutes Part 5: Rock linings DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent [2] [1] Chutes

More information

Rock Sizing for Batter Chutes

Rock Sizing for Batter Chutes Rock Sizing for Batter Chutes STORMWATER MANAGEMENT PRACTICES Photo 1 Rock-lined batter chute Photo 2 Rock-lined batter chute 1. Introduction In the stormwater industry a chute is a steep drainage channel,

More information

Rock Sizing for Small Dam Spillways

Rock Sizing for Small Dam Spillways Rock Sizing for Small Dam Spillways STORMWATER MANAGEMENT PRACTICES Photo 1 Rock-lined spillway on a construction site sediment basin Photo 2 Rock-lined spillway on a small farm dam 1. Introduction A chute

More information

B805 TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES - OPSS 805

B805 TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES - OPSS 805 B805 MEASURES - OPSS 805 805.1 GENERAL Construction activities frequently remove protective cover and expose soil to accelerated rates of erosion. Sediments generated thereby can be conveyed via runoff

More information

Rock Sizing for Multi-Pipe & Culvert Outlets

Rock Sizing for Multi-Pipe & Culvert Outlets Rock Sizing for Multi-Pipe & Culvert Outlets STORMWATER AND WATERWAY MANAGEMENT PRACTICES Photo 1 Rock pad outlet structure at end of a duel stormwater pipe outlet Photo 2 Rock pad outlet structure at

More information

Rock Sizing for Waterway & Gully Chutes

Rock Sizing for Waterway & Gully Chutes Rock Sizing for Waterway & Gully Chutes WATERWAY MANAGEMENT PRACTICES Photo 1 Rock-lined waterway chute Photo 2 Rock-lined gully chute 1. Introduction A waterway chute is a stabilised section of channel

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

Standards for Soil Erosion and Sediment Control in New Jersey May 2012

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SEDIMENT BASIN Definition A barrier, dam, excavated pit, or dugout constructed across a waterway or at other suitable locations to intercept and retain sediment. Basins created by construction

More information

TPDES: Soil, Erosion and Sedimentation Methods

TPDES: Soil, Erosion and Sedimentation Methods SAWS TPDES: Soil, Erosion and Sedimentation Methods Philip Handley Supervisor-Resource Protection & Compliance August 25, 2014 TPDES: Soil, Erosion and Sedimentation Methods Soil Common term: Dirt Common

More information

Stormwater Inlet Sediment Traps

Stormwater Inlet Sediment Traps Stormwater Inlet Sediment Traps SEDIMENT CONTROL TECHNIQUES Photo 1 Kerb inlet Photo 2 Field (drop) inlet Table 1 provides the recommended default classification of various sediment control systems suitable

More information

Sediment Trap. A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff through a stabilized spillway.

Sediment Trap. A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff through a stabilized spillway. Sediment Trap SC-15 Source: Caltrans Construction Site Best Management Practices Manual, 2003. Description A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff

More information

Construction Exits Vibration grids

Construction Exits Vibration grids Construction Exits Vibration grids SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils [1] Type 3 System Supplementary Trap Dispersive Soils [1]

More information

B-1. Attachment B-1. Evaluation of AdH Model Simplifications in Conowingo Reservoir Sediment Transport Modeling

B-1. Attachment B-1. Evaluation of AdH Model Simplifications in Conowingo Reservoir Sediment Transport Modeling Attachment B-1 Evaluation of AdH Model Simplifications in Conowingo Reservoir Sediment Transport Modeling 1 October 2012 Lower Susquehanna River Watershed Assessment Evaluation of AdH Model Simplifications

More information

Gully Erosion Part 1 GULLY EROSION AND ITS CAUSES. Introduction. The mechanics of gully erosion

Gully Erosion Part 1 GULLY EROSION AND ITS CAUSES. Introduction. The mechanics of gully erosion Gully Erosion Part 1 GULLY EROSION AND ITS CAUSES Gully erosion A complex of processes whereby the removal of soil is characterised by incised channels in the landscape. NSW Soil Conservation Service,

More information

HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR (c)(1)(i) (xii)

HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR (c)(1)(i) (xii) HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR 257.73(c)(1)(i) (xii) (i) Site Name and Ownership Information: Site Name: E.C. Gaston Steam Plant Site Location:

More information

Sedimentation. Several factors affect the separation of settleable solids from water. Some of the more common types of factors to consider are:

Sedimentation. Several factors affect the separation of settleable solids from water. Some of the more common types of factors to consider are: Sedimentation Sedimentation, or clarification, is the process of letting suspended material settle by gravity. Suspended material may be particles, such as clay or silts, originally present in the source

More information

Storm Sewer Design [2]

Storm Sewer Design [2] Class 5 [1] Storm Sewer Design 9. Check Q < Qf and Vmax > vf > Vmin. Vmin is normally specified to avoid sedimentation. This will normally be 1.0 m/s at pipe full condition. (BS EN 752 suggests that for

More information

WELCOME Lake Wabukayne OPEN HOUSE

WELCOME Lake Wabukayne OPEN HOUSE WELCOME Lake Wabukayne Sediment Removal Project OPEN HOUSE We are here to: Update you, the community, on recent developments and activities at Lake Wabukayne Present the preferred alternative and receive

More information

Stone Outlet Sediment Trap

Stone Outlet Sediment Trap 3.12 Sediment Control Description: A stone outlet sediment trap is a small detention area formed by placing a stone embankment with an integral stone filter outlet across a drainage swale for the purpose

More information

Chemical coagulants and flocculants

Chemical coagulants and flocculants Chemical coagulants and flocculants SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils [1] Type 2 System Concentrated Flow Clayey Soils Type 3 System Instream Works Dispersive Soils [1] Chemical

More information

EROSION CONTROL NARRATIVE

EROSION CONTROL NARRATIVE EROSION CONTROL NARRATIVE Erosion and sediment control has been designed for the Willow Bend Phase I Subdivision according to UDFCD and the City of Thornton criteria, in order to minimize erosion and sediment

More information

WQ Outlet Design Single Orifice Orifice diameter = 24. Perforated riser/orifice Plate Outlet area per perforation row = 4

WQ Outlet Design Single Orifice Orifice diameter = 24. Perforated riser/orifice Plate Outlet area per perforation row = 4 These calculations should be used when designing the outlet structures for extended wet and dry detention basins (Sections 4. 7 and 4.8). The water quality outlet size and the trash rack design will vary

More information

Sediment Trap. At multiple locations within the project site where sediment control is needed.

Sediment Trap. At multiple locations within the project site where sediment control is needed. Sediment Trap SE-3 Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control

More information

Hydraulics Prof. Dr. Arup Kumar Sarma Department of Civil Engineering Indian Institute of Technology, Guwahati

Hydraulics Prof. Dr. Arup Kumar Sarma Department of Civil Engineering Indian Institute of Technology, Guwahati Hydraulics Prof. Dr. Arup Kumar Sarma Department of Civil Engineering Indian Institute of Technology, Guwahati Module No. # 04 Gradually Varied Flow Lecture No. # 07 Rapidly Varied Flow: Hydraulic Jump

More information

Tarbela Dam in Pakistan. Case study of reservoir sedimentation

Tarbela Dam in Pakistan. Case study of reservoir sedimentation Tarbela Dam in Pakistan. HR Wallingford, Wallingford, UK Published in the proceedings of River Flow 2012, 5-7 September 2012 Abstract Reservoir sedimentation is a main concern in the Tarbela reservoir

More information

Module 15 : Grit Chamber. Lecture 19 : Grit Chamber

Module 15 : Grit Chamber. Lecture 19 : Grit Chamber Module 15 : Grit Chamber Lecture 19 : Grit Chamber 15. GRIT CHAMBER Grit chamber is the second unit operation used in primary treatment of wastewater and it is intended to remove suspended inorganic particles

More information

15. GRIT CHAMBER 15.1 Horizontal Velocity in Flow Though Grit Chamber

15. GRIT CHAMBER 15.1 Horizontal Velocity in Flow Though Grit Chamber 15. GRIT CHAMBER Grit chamber is the second unit operation used in primary treatment of wastewater and it is intended to remove suspended inorganic particles such as sandy and gritty matter from the wastewater.

More information

APPENDIX B DESIGN CRITERIA FOR TEMPORARY WATER QUALITY BMPS USED DURING CONSTRUCTION

APPENDIX B DESIGN CRITERIA FOR TEMPORARY WATER QUALITY BMPS USED DURING CONSTRUCTION APPENDIX B DESIGN CRITERIA FOR TEMPORARY WATER QUALITY BMPS USED DURING CONSTRUCTION This Appendix presents design criteria and example calculations for the following temporary water quality BMPs for use

More information

Suitable Applications Sediment traps should be considered for use:

Suitable Applications Sediment traps should be considered for use: Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective

More information

Materials. Use materials meeting the following.

Materials. Use materials meeting the following. 208.01 Section 208. SOIL EROSION AND SEDIMENTATION CONTROL 208.01 Description. Install and maintain erosion and sedimentation controls to minimize soil erosion and to control sedimentation from affecting

More information

Module 15 : Grit Chamber. Lecture 19 : Grit Chamber

Module 15 : Grit Chamber. Lecture 19 : Grit Chamber 1 P age Module 15 : Grit Chamber Lecture 19 : Grit Chamber 2 P age Grit chamber is the second unit operation used in primary treatment of wastewater and it is intended to remove suspended inorganic particles

More information

Porous Weirs for Flood Mitigation

Porous Weirs for Flood Mitigation University of Southern Queensland Faculty of Engineering and Surveying Porous Weirs for Flood Mitigation A dissertation submitted by Mr Joseph Ian Saunders in fulfilment of the requirements of Courses

More information

Sediment Capture in Pervious Concrete Pavement tsystems: Effects on Hydrological Performance and Suspended Solids

Sediment Capture in Pervious Concrete Pavement tsystems: Effects on Hydrological Performance and Suspended Solids Concrete Sustainability Conference April 14 th 2010, Tempe, AZ Sediment Capture in Pervious Concrete Pavement tsystems: Effects on Hydrological l Performance and Suspended Solids Discharge Luis A. Mata,

More information

Erosion and Sediment Control Measures 2.7 Silt Fences

Erosion and Sediment Control Measures 2.7 Silt Fences Erosion and Sediment Control Measures Silt fences are designed to intercept sheet flow sediment laden stormwater run-off and filter out both the larger and smaller particles of sediment. Silt fences and

More information

EXAMPLES (SEDIMENT TRANSPORT) AUTUMN 2018

EXAMPLES (SEDIMENT TRANSPORT) AUTUMN 2018 EXAMPLES (SEDIMENT TRANSPORT) AUTUMN 2018 Q1. Using Cheng s formula estimate the settling velocity of a sand particle of diameter 1 mm in: (a) air; (b) water. Q2. Find the critical Shields parameter diameter

More information

Orica Australia Pty Ltd Ammonium Nitrate Facility Upgrade

Orica Australia Pty Ltd Ammonium Nitrate Facility Upgrade Orica Australia Pty Ltd Ammonium Nitrate Facility Upgrade January 2010 Revision 0 Contents 1. Introduction 1 1.1 Purpose 1 1.2 Objectives 1 1.3 Relevant Environmental Legislation, Guidelines and Policies

More information

Instream Erosion Control General

Instream Erosion Control General Instream Erosion Control General EROSION CONTROL TECHNIQUES Revegetation Temperate Climates Short-Term Non Vegetation Wet Tropics Long-Term Weed Control [1] Semi-Arid Zones Permanent [1] Weed control attributes

More information

Strategies for managing sediment in dams. Iwona Conlan Consultant to IKMP, MRCS

Strategies for managing sediment in dams. Iwona Conlan Consultant to IKMP, MRCS Strategies for managing sediment in dams Iwona Conlan Consultant to IKMP, MRCS 1 Sediment trapping by dams Active storage capacity Dead storage coarse material (bed load) Fine materials (suspension) Francis

More information

Use of Rock in Stormwater Engineering. Version 3, July 2017

Use of Rock in Stormwater Engineering. Version 3, July 2017 Version 3, 2017 Use of Rock in Stormwater Engineering Version 3, July 2017 Prepared by: Published by: Diagrams by: Photos by: Grant Witheridge, Catchments and Creeks Pty Ltd Catchments and Creeks Pty Ltd

More information

Continuing Education Course #101 Drainage Design with WinTR-55

Continuing Education Course #101 Drainage Design with WinTR-55 1 of 5 Continuing Education Course #101 Drainage Design with WinTR-55 1. WinTR-55 uses the Kinematic Wave method for calculating storm runoff rates and volumes. 2. According to the Velocity Method, the

More information

ENGINEERING HYDROLOGY

ENGINEERING HYDROLOGY ENGINEERING HYDROLOGY Prof. Rajesh Bhagat Asst. Professor Civil Engineering Department Yeshwantrao Chavan College Of Engineering Nagpur B. E. (Civil Engg.) M. Tech. (Enviro. Engg.) GCOE, Amravati VNIT,

More information

1.060 Engineering Mechanics II Spring Problem Set 8

1.060 Engineering Mechanics II Spring Problem Set 8 1.060 Engineering Mechanics II Spring 2006 Due on Monday, May 1st Problem Set 8 Important note: Please start a new sheet of paper for each problem in the problem set. Write the names of the group members

More information

UNDERSTANDING RE-SUSPENSION RATES

UNDERSTANDING RE-SUSPENSION RATES TECHNICAL PAPER CST-07-002 This paper is one of a series of technical papers that explain the principles involved in the physics and chemistry of water quality design. This is public domain information.

More information

Technical Memorandum

Technical Memorandum 2855 Telegraph Avenue, Suite 4, Berkeley, CA 9475, Phone (51) 848-898, Fax (51) 848-8398 Technical Memorandum Date: September 6, 27 To: Mr. Michael Bowen, Project Manager From: Yantao Cui, Ph.D., Hydraulic

More information

Advanced /Surface Hydrology Dr. Jagadish Torlapati Fall 2017 MODULE 2 - ROUTING METHODS

Advanced /Surface Hydrology Dr. Jagadish Torlapati Fall 2017 MODULE 2 - ROUTING METHODS Routing MODULE - ROUTING METHODS Routing is the process of find the distribution of flow rate and depth in space and time along a river or storm sewer. Routing is also called Flow routing or flood routing.

More information

SEDIMENTATION INTRODUCTION

SEDIMENTATION INTRODUCTION SEDIMENTATION INTRODUCTION Sedimentation is removal of particulate materials suspended in water by quiescent settling due to gravity Commonly used unit operation in water and wastewater treatment plants

More information

Instructor : Dr. Jehad Hamad. Chapter (7)

Instructor : Dr. Jehad Hamad. Chapter (7) Instructor : Dr. Jehad Hamad Chapter (7) 2017-2016 Soil Properties Physical Properties Mechanical Properties Gradation and Structure Compressibility Soil-Water Relationships Shear Strength Bearing Capacity

More information

Rock Sizing for Drainage Channels

Rock Sizing for Drainage Channels Rock Sizing for Drainage Channels STORMWATER MANAGEMENT PRACTICES Photo 1 Rock-lined drainage channel Photo 2 Rock-lined catch drain (during construction phase) 1. Introduction Rock size is primarily dependent

More information

In-channel coarse sediment trap Best Management Practice

In-channel coarse sediment trap Best Management Practice In-channel coarse sediment trap Best Management Practice By Henry R. Hudson July 2002 Environmental Management Associates Ltd., Christchurch Complexity Environmental Value Cost Low Moderate High Low Moderate

More information

Open Channel Flow Part 2. Ch 10 Young, notes, handouts

Open Channel Flow Part 2. Ch 10 Young, notes, handouts Open Channel Flow Part 2 Ch 10 Young, notes, handouts Uniform Channel Flow Many situations have a good approximation d(v,y,q)/dx=0 Uniform flow Look at extended Bernoulli equation Friction slope exactly

More information

CASE STUDY SOLIS, SWITZERLAND

CASE STUDY SOLIS, SWITZERLAND SEDIMENT MANAGEMENT CASE STUDY SOLIS, SWITZERLAND Key project features Name: Solis Country: Switzerland Category: bypass channel/tunnel Reservoir volume (original): 4.1 Mm 3 Installed capacity: 64 MW Date

More information

New design rainfalls. Janice Green, Project Director IFD Revision Project, Bureau of Meteorology

New design rainfalls. Janice Green, Project Director IFD Revision Project, Bureau of Meteorology New design rainfalls Janice Green, Project Director IFD Revision Project, Bureau of Meteorology Design Rainfalls Design Rainfalls Severe weather thresholds Flood forecasting assessing probability of rainfalls

More information

APPENDIX B WORKSHEETS & EXHIBITS

APPENDIX B WORKSHEETS & EXHIBITS APPENDIX B WORKSHEETS & EXHIBITS A worksheet provides the designer a representation of a measure that allows for input of specific design criteria. The plan designer will be required to assess field conditions

More information

THE NEED FOR AN ADDITIONAL SPILLWAY AT THE SANFORD DAM BOILING SPRING LAKES, NC. Presentation for The Brunswick County Commissioners April 20, 2015

THE NEED FOR AN ADDITIONAL SPILLWAY AT THE SANFORD DAM BOILING SPRING LAKES, NC. Presentation for The Brunswick County Commissioners April 20, 2015 THE NEED FOR AN ADDITIONAL SPILLWAY AT THE SANFORD DAM BOILING SPRING LAKES, NC Presentation for The Brunswick County Commissioners April 20, 2015 The Sanford Dam Earth Dam constructed in 1961 Drainage

More information

Attachment B to Technical Memorandum No.2. Operations Plan of Ross Valley Detention Basins

Attachment B to Technical Memorandum No.2. Operations Plan of Ross Valley Detention Basins Attachment B to Technical Memorandum No.2 Operations Plan of Ross Valley Detention Basins Operations Plan of Ross Valley Detention Basins Stetson Engineers Inc. January 26, 2011 1.0 Introduction Achieving

More information

CONCEPTS Conservational Channel Evolution and Pollutant Transport System

CONCEPTS Conservational Channel Evolution and Pollutant Transport System CONCEPTS Conservational Channel Evolution and Pollutant Transport System Eddy J. Langendoen Watershed Physical Processes Research Unit National Sedimentation Laboratory USDA Agricultural Research Service

More information

CPESC Syllabus Australasia

CPESC Syllabus Australasia CPESC Syllabus Australasia 2 August 2012 PREAMBLE The purpose of this document is to provide details related to competency areas, performance objectives or syllabus relevant to the Certified Professionals

More information

PONDNET.WK1 - Flow and Phosphorus Routing in Pond Networks

PONDNET.WK1 - Flow and Phosphorus Routing in Pond Networks PONDNET.WK1 - Flow and Phosphorus Routing in Pond Networks Version 2.1 - March 1989 William W. Walker, Jr. Ph.D., Environmental Engineer 1127 Lowell Road, Concord, Massachusetts 01742 508-369-8061 PONDNET.WK1

More information

Sand Storage Dams Performance, cost-efficiency, working principles and constraints

Sand Storage Dams Performance, cost-efficiency, working principles and constraints Copyright by Josep de Trincheria Copyright by Josep de Trincheria Copyright by Josep de Trincheria Copyright by Josep de Trincheria Sand Storage Dams Performance, cost-efficiency, working principles and

More information

5. Which surface soil type has the slowest permeability rate and is most likely to produce flooding? A) pebbles B) sand C) silt D) clay A) B) C) D)

5. Which surface soil type has the slowest permeability rate and is most likely to produce flooding? A) pebbles B) sand C) silt D) clay A) B) C) D) 1. During a heavy rainstorm, soil samples A and B both became saturated with water. However, 10 minutes after the storm ended, the soils appeared as shown below. Which statement best explains the observed

More information

Appendix 15 Computational Methodology

Appendix 15 Computational Methodology Appendix 15 Computational Methodology Introduction This Appendix describes the process used by the risk team to determine the final loss exceedence values in the risk analysis. The process involved the

More information

9. Flood Routing. chapter Two

9. Flood Routing. chapter Two 9. Flood Routing Flow routing is a mathematical procedure for predicting the changing magnitude, speed, and shape of a flood wave as a function of time at one or more points along a watercourse (waterway

More information

Continuing Education Associated with Maintaining CPESC and CESSWI Certification

Continuing Education Associated with Maintaining CPESC and CESSWI Certification Continuing Education Associated with Maintaining CPESC and CESSWI Certification Module 2: Stormwater Management Principles for Earth Disturbing Activities Sponsors: ODOTs Local Technical Assistance Program

More information

Erosion Surface Water. moving, transporting, and depositing sediment.

Erosion Surface Water. moving, transporting, and depositing sediment. + Erosion Surface Water moving, transporting, and depositing sediment. + Surface Water 2 Water from rainfall can hit Earth s surface and do a number of things: Slowly soak into the ground: Infiltration

More information

SST3005 Fundamentals of Soil Science LAB 5 LABORATORY DETERMINATION OF SOIL TEXTURE: MECHANICAL ANALYSIS

SST3005 Fundamentals of Soil Science LAB 5 LABORATORY DETERMINATION OF SOIL TEXTURE: MECHANICAL ANALYSIS LAB 5 LABORATORY DETERMINATION OF SOIL TEXTURE: MECHANICAL ANALYSIS Learning outcomes The student is able to: 1. Separate soil particles : sand, silt and clay 2. determine the soil texture class using

More information

FEEDLOT DESIGN AND CONSTRUCTION. 11. Sediment removal systems. AUTHORS: Peter Watts and Orla Keane

FEEDLOT DESIGN AND CONSTRUCTION. 11. Sediment removal systems. AUTHORS: Peter Watts and Orla Keane 11. Sediment removal systems AUTHORS: Peter Watts and Orla Keane Introduction Sedimentation systems are constructed to capture and detain rainfall runoff, allowing any entrained sediment to settle out

More information

Independent Environmental Audit Erosion and Sediment Control

Independent Environmental Audit Erosion and Sediment Control Independent Environmental Audit Erosion and Sediment Control Commencement of YOUNG TO BETHUNGRA LOOPING PIPELINE JUNE 2016 suite 1, 39 fitzmaurice st (po box 5464) wagga wagga nsw 2650 australia t (02)

More information

Streams. Water. Hydrologic Cycle. Geol 104: Streams

Streams. Water. Hydrologic Cycle. Geol 104: Streams Streams Why study streams? Running water is the most important geologic agent in erosion, transportation and deposition of sediments. Water The unique physical and chemical properties of water make it

More information

Chapter 7 Mudflow Analysis

Chapter 7 Mudflow Analysis Chapter 7 Mudflow Analysis 7.0 Introduction This chapter provides information on the potential and magnitude of mud floods and mudflows that may develop in Aspen due to rainfall events, snowmelt, or rain

More information

U.S. Army Corps of Engineers Detroit District. Sediment Trap Assessment Saginaw River, Michigan

U.S. Army Corps of Engineers Detroit District. Sediment Trap Assessment Saginaw River, Michigan U.S. Army Corps of Engineers Detroit District December 2001 December 2001 This report has been prepared for USACE, Detroit District by: W.F. BAIRD & ASSOCIATES LTD. 2981 YARMOUTH GREENWAY MADISON, WISCONSIN

More information

STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1. DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT

STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1. DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1 DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT Prepared by: PAULUS, SOKOLOWSKI & SARTOR STORMWATER MANAGEMENT 1. Methodology

More information

HOTEL KANATA 160 HEARST WAY KANATA, ONTARIO SERVICING REPORT. Prepared for: David Johnston Architect. Prepared By:

HOTEL KANATA 160 HEARST WAY KANATA, ONTARIO SERVICING REPORT. Prepared for: David Johnston Architect. Prepared By: HOTEL KANATA 160 HEARST WAY KANATA, ONTARIO SERVICING REPORT Prepared for: David Johnston Architect Prepared By: BaseTech Consulting Inc. 309 Roywood Crescent Newmarket, Ontario L3Y 1A6 BCI Project No.

More information

Soil Erosion and Sediment Control. Basic Principles and Practices

Soil Erosion and Sediment Control. Basic Principles and Practices Soil Erosion and Sediment Control Basic Principles and Practices Acknowledgements The following document was created by Healthy Land and Water with some material sourced from Brisbane City Council, and

More information

Mass Wasting. Revisit: Erosion, Transportation, and Deposition

Mass Wasting. Revisit: Erosion, Transportation, and Deposition Mass Wasting Revisit: Erosion, Transportation, and Deposition While landslides are a normal part of erosion and surface processes, they can be very destructive to life and property! - Mass wasting: downslope

More information

SILT FENCE EFFECTIVENESS

SILT FENCE EFFECTIVENESS SILT FENCE EFFECTIVENESS Michelle G. Holloway, Department of Earth Sciences, University of South Alabama, Mobile, AL 36688. E-mail: MLG@jaguar1.usouthal.edu. Sediment is the number one pollutant in Dog

More information

APPENDIX A: EROSION & SEDIMENT CONTROL FORMS

APPENDIX A: EROSION & SEDIMENT CONTROL FORMS APPENDIX A: EROSION & SEDIMENT CONTROL FORMS Croy Engineering # 1580.08 EROSION & SEDIMENT CONTROL FORMS Appendix-1 This page intentionally left blank. Croy Engineering # 1580.08 EROSION & SEDIMENT CONTROL

More information

L-17 Coagulation and Flocculation Part-I. Environmental Engineering-I

L-17 Coagulation and Flocculation Part-I. Environmental Engineering-I L-17 Coagulation and Flocculation Part-I Environmental Engineering-I Content Part-I Coagulation, Types of Coagulant, Part-II dosing, rapid mixing, Flocculation-design parameters. Purpose The primary purpose

More information

CIE4491 Lecture. Hydraulic design

CIE4491 Lecture. Hydraulic design CIE4491 Lecture. Hydraulic design Marie-claire ten Veldhuis 19-9-013 Delft University of Technology Challenge the future Hydraulic design of urban stormwater systems Focus on sewer pipes Pressurized and

More information

Project Description. Project Options. End Analysis On... Apr 26, :00:00. Rainfall Details

Project Description. Project Options. End Analysis On... Apr 26, :00:00. Rainfall Details Project Description File Name... 323 - Att Pond 3 East PIPES ONLY.SPF Project Options Flow Units... Elevation Type... Hydrology Method... EPA SWMM Infiltration Method... Link Routing Method... Enable Overflow

More information

Selected Site BMPs: Why s the Water Muddy? John C. Hayes, Ph.D., P. E. Biosystems Engineering Clemson University

Selected Site BMPs: Why s the Water Muddy? John C. Hayes, Ph.D., P. E. Biosystems Engineering Clemson University Selected Site BMPs: Why s the Water Muddy? John C. Hayes, Ph.D., P. E. Biosystems Engineering Clemson University The BMP worked fine until last week when it rained! Turbidity Best Management Practices

More information

Stage Discharge Tabulation for Only Orifice Flow

Stage Discharge Tabulation for Only Orifice Flow Stage Discharge Tabulation for Only Orifice Flow DEPTH STAGE DISCHARGE (meters) (feet) (meters) (feet) (m 3 /s) (ft 3 /s) 0 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 2.00 0.7 1.3 2.0 2.6 3.3 3.9 4.6

More information

12 SWAT USER S MANUAL, VERSION 98.1

12 SWAT USER S MANUAL, VERSION 98.1 12 SWAT USER S MANUAL, VERSION 98.1 CANOPY STORAGE. Canopy storage is the water intercepted by vegetative surfaces (the canopy) where it is held and made available for evaporation. When using the curve

More information

PRIMARY TREATMENT NATURE

PRIMARY TREATMENT NATURE PRIMARY TREATMENT NATURE Physical and chemical processes. Physical: sedimentation based in density differences Chemical: coagulation and flocculation, ph adjustment, precipitation (formation of insoluble

More information

THINK FLUID DYNAMIX CFD Simulation of Clarifiers. THINK Fluid Dynamix

THINK FLUID DYNAMIX CFD Simulation of Clarifiers. THINK Fluid Dynamix THINK FLUID DYNAMIX CFD Simulation of Clarifiers Provided by: THINK Fluid Dynamix Am Pestalozziring 21 D-91058 Erlangen (Germany) Tel. +49 (0)9131 69098-00 http://www.think-fd.com CFD ENGINEERING & CONSULTING

More information

ARTICLE 5 (PART 2) DETENTION VOLUME EXAMPLE PROBLEMS

ARTICLE 5 (PART 2) DETENTION VOLUME EXAMPLE PROBLEMS ARTICLE 5 (PART 2) DETENTION VOLUME EXAMPLE PROBLEMS Example 5.7 Simple (Detention Nomograph) Example 5.8 Offsite and Unrestricted Areas (HEC-HMS) Example 5.9 Ponds in Series w/ Tailwater (HEC-HMS) Example

More information

CASE STUDY BINGA, PHILIPPINES

CASE STUDY BINGA, PHILIPPINES SEDIMENT MANAGEMENT CASE STUDY BINGA, PHILIPPINES Key project features Name: Binga Country: Philippines Category: modify operating rule (focus or redistribute sediment); adaptive strategies Reservoir volume

More information