1 Project Description File Name Att Pond 3 East PIPES ONLY.SPF Project Options Flow Units... Elevation Type... Hydrology Method... EPA SWMM Infiltration Method... Link Routing Method... Enable Overflow Ponding at Nodes... Skip Steady State Analysis Time Periods... Analysis Options CMS Elevation EPA SWMM SCS Curve Number Hydrodynamic YES NO Start Analysis On... Apr 25, :00:00 End Analysis On... Apr 26, :00:00 Start Reporting On... Apr 25, :00:00 Antecedent Dry Days... 0 days Runoff (Dry Weather) Time Step :00:10 days hh:mm:ss Runoff (Wet Weather) Time Step :00:10 days hh:mm:ss Reporting Time Step :00:10 days hh:mm:ss Routing Time Step seconds Rainfall Details SN Rain Gage Data Data Source Rainfall Rain State County Return Rainfall Rainfall ID Source ID Type Units Period Depth Distribution (years) (mm) 1 Time Series 50yr RI Cumulative mm None None South Africa 24-hr, Type 2 Page 1 of 7
2 Subbasin Hydrology Subbasin : Post-Attenuation Area (ha) Impervious Area (%) Conductivity (mm/hr) Drying Time (days) Average Slope (%) Equivalent Width (m) Impervious Area Manning's Roughness Pervious Area Manning's Roughness Curb & Gutter Length (m) Rain Gage ID Wellington Composite Curve Number Area Soil Curve Soil/Surface Description (ha) Group Number Paved roads with curbs & sewers 3.06 C % grass cover, Fair C Urban commercial, 85% imp 6.65 C Composite Area & Weighted CN Subbasin Runoff Results Total Rainfall (mm) Total Runon (mm) Total Evaporation (mm) Total Infiltration (mm) Total Runoff (mm) Peak Runoff (cms) Time of Concentration (days hh:mm:ss) :45:24 Page 2 of 7
3 Subbasin : Post-Development Area (ha) Impervious Area (%) Conductivity (mm/hr) Drying Time (days) Average Slope (%) Equivalent Width (m) Impervious Area Manning's Roughness Pervious Area Manning's Roughness Curb & Gutter Length (m) Rain Gage ID Wellington Composite Curve Number Area Soil Curve Soil/Surface Description (ha) Group Number Urban commercial, 85% imp 6.65 C Paved roads with curbs & sewers 3.06 C % grass cover, Fair C Composite Area & Weighted CN Subbasin Runoff Results Total Rainfall (mm) Total Runon (mm) Total Evaporation (mm) Total Infiltration (mm) Total Runoff (mm) Peak Runoff (cms) Time of Concentration (days hh:mm:ss) :45:24 Page 3 of 7
4 Subbasin : Pre-Development Area (ha) Impervious Area (%) Weighted Curve Number Conductivity (mm/hr) Drying Time (days) Average Slope (%) Equivalent Width (m) Impervious Area Manning's Roughness Pervious Area Manning's Roughness Curb & Gutter Length (m) Rain Gage ID Wellington Composite Curve Number Area Soil Curve Soil/Surface Description (ha) Group Number 50-75% grass cover, Fair C Composite Area & Weighted CN Subbasin Runoff Results Total Rainfall (mm) Total Runon (mm) Total Evaporation (mm) Total Infiltration (mm) Total Runoff (mm) Peak Runoff (cms) Weighted Curve Number Time of Concentration (days hh:mm:ss) :30:55 Page 4 of 7
5 Storage Nodes Storage Node : Attenuation Chamber Invert Elevation (m) Max (Rim) Elevation (m) Max (Rim) Offset (m) Initial Water Elevation (m) Initial Water Depth (m) Ponded Area (m²) Evaporation Loss Storage Area Volume Curves Storage Curve : POND Stage Storage Storage Area Volume (m) (m²) (m³) Page 5 of 7
6 Page 6 of 7
7 Storage Node : Attenuation Chamber (continued) Outflow Weirs SN Element Weir Flap Crest Crest Length Weir Total Discharge ID Type Gate Elevation Offset Height Coefficient (m) (m) (m) (m) 1 Overflow Weir Rectangular No Outflow Orifices SN Element Orifice Orifice Flap Circular Rectangular Rectangular Orifice Orifice ID Type Shape Gate Orifice Orifice Orifice Invert Coefficient Diameter Height Width Elevation (mm) (mm) (mm) (m) 1 25yr Orifice Side CIRCULAR No yr Orifice Side CIRCULAR No Output Summary Results Peak Inflow (cms) Peak Lateral Inflow (cms) Peak Outflow (cms) Peak Exfiltration Flow Rate (cmm) Max HGL Elevation Attained (m) Max HGL Depth Attained (m) Average HGL Elevation Attained (m) Average HGL Depth Attained (m) Time of Max HGL Occurrence (days hh:mm) :30 Total Exfiltration Volume (1000-m³) Total Flooded Volume (ha-mm)... 0 Total Time Flooded (min)... 0 Total Retention Time (sec) Page 7 of 7
******************* Project Description ******************* File Name... NAAF Stormwater Improvement Project 11_21_2014.SPF
Autodesk Storm and Sanitary Analysis 2014 - Version 8.1.62 (Build 1) ----------------- *** Project Description *** File Name... NAAF Stormwater Improvement Project 11_21_2014.SPF Analysis Options Flow
More informationSTORMWATER DESIGN CALCULATIONS
STORMWATER DESIGN CALCULATIONS REF : C7011-2390 AT 19a-23 MEMORIAL AVENUE BLACKWALL FOR MR KERR Contents 1.0 Detention System Requirements 1.1 Storage-Area calcs. 1.2 Data Files for Pre & Post Developed
More informationWATER MANAGEMENT REPORT FOR PAGE ESTATES
WATER MANAGEMENT REPORT FOR PAGE ESTATES SLB Consulting of SW Florida, LLC PO Box 2826 Bonita Springs, FL. 34133 Phone: 239-948-9566 sandra@slbconsult.com C.O.A. # 25395 September 1, 2014 Sandra L. Bottcher
More informationCity of Columbia BMP Manual. Detailed Unified Sizing Criteria Example Wet Pond Design
City of Columbia BMP Manual Detailed Unified Sizing Criteria Example Wet Pond Design April 17, 2013 Wet Pond Example: Unified Sizing Criteria Methodology Base Data Location: Rome, GA Site Drainage Area
More informationContinuing Education Course #101 Drainage Design with WinTR-55
1 of 5 Continuing Education Course #101 Drainage Design with WinTR-55 1. WinTR-55 uses the Kinematic Wave method for calculating storm runoff rates and volumes. 2. According to the Velocity Method, the
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.
More informationStormwater Guidelines and Case Studies. CAHILL ASSOCIATES Environmental Consultants West Chester, PA (610)
Stormwater Guidelines and Case Studies CAHILL ASSOCIATES Environmental Consultants West Chester, PA (610) 696-4150 www.thcahill.com Goals and Challenges for Manual State Stormwater Policy More Widespread
More informationStage Discharge Tabulation for Only Orifice Flow
Stage Discharge Tabulation for Only Orifice Flow DEPTH STAGE DISCHARGE (meters) (feet) (meters) (feet) (m 3 /s) (ft 3 /s) 0 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 2.00 0.7 1.3 2.0 2.6 3.3 3.9 4.6
More informationINTRODUCTION TO HYDROLOGIC MODELING USING HEC-HMS
INTRODUCTION TO HYDROLOGIC MODELING USING HEC-HMS By Thomas T. Burke, Jr., PhD, PE Luke J. Sherry, PE, CFM Christopher B. Burke Engineering, Ltd. October 8, 2014 1 SEMINAR OUTLINE Overview of hydrologic
More informationCIE4491 Lecture. Hydraulic design
CIE4491 Lecture. Hydraulic design Marie-claire ten Veldhuis 19-9-013 Delft University of Technology Challenge the future Hydraulic design of urban stormwater systems Focus on sewer pipes Pressurized and
More informationCITY OF CAPE CORAL STORMWATER MASTER PLAN PHASE II - PART 1 BASINS 4, 10, & 14 SUB-BASIN DRAINAGE IMPROVEMENTS HYDRAULIC ANALYSIS SUMMARY
CITY OF CAPE CORAL STORMWATER MASTER PLAN PHASE II - PART 1 BASINS 4, 10, & 14 SUB-BASIN DRAINAGE IMPROVEMENTS HYDRAULIC ANALYSIS SUMMARY Cape Coral, FL Prepared for: The City of Cape Coral Public Works
More informationUNIVERSITY OF BOLTON. ENGINEERING, SPORTS and SCIENCES BSC CIVIL ENGINEERING SEMESTER 1 EXAMINATION 2014/2015 WATER ENGINEERING MODULE NO: BLT3023
[TW59] UNIVERSITY OF BOLTON ENGINEERING, SPORTS and SCIENCES BSC CIVIL ENGINEERING SEMESTER 1 EXAMINATION 014/015 WATER ENGINEERING MODULE NO: BLT303 Date: Tuesday, 0 January 015 Time: 10.00-1.00 INSTRUCTIONS
More informationAPPENDIX B DRAINAGE REPORT
APPENDIX B DRAINAGE REPORT B-1 South Lamar Blvd. Transportation Corridor Study Drainage Report Prepared for: City of Austin and HDR, Inc. Prepared by: and Services, Inc. Final 07-09-2015 Michael C. Meriwether,
More informationSection 3.0 Existing Systems Hydrology and Hydraulics
Section 3.0 Existing Systems Hydrology and Hydraulics This chapter summarizes the results and methodology of MACTEC s evaluation of the existing drainage systems and lakes for the City of Maitland, Florida.
More informationAdvanced /Surface Hydrology Dr. Jagadish Torlapati Fall 2017 MODULE 2 - ROUTING METHODS
Routing MODULE - ROUTING METHODS Routing is the process of find the distribution of flow rate and depth in space and time along a river or storm sewer. Routing is also called Flow routing or flood routing.
More informationDEPARTMENT OF CIVIL AND ENVIRONMENTAL ENGINEERING Urban Drainage: Hydraulics. Solutions to problem sheet 2: Flows in open channels
DEPRTMENT OF CIVIL ND ENVIRONMENTL ENGINEERING Urban Drainage: Hydraulics Solutions to problem sheet 2: Flows in open channels 1. rectangular channel of 1 m width carries water at a rate 0.1 m 3 /s. Plot
More informationFinal Drainage Report
Final Drainage Report Expo Rail Operations and Maintenance Facility Santa Monica, California Prepared for: Exposition Metro Line Construction Authority Prepared by: W2 Design, Inc. 50 S. De Lacey Avenue
More informationDetermination of Urban Runoff Using ILLUDAS and GIS
Texas A&M University Department of Civil Engineering Instructor: Dr. Francisco Olivera CVEN689 Applications of GIS to Civil Engineering Determination of Urban Runoff Using ILLUDAS and GIS Tae Jin Kim 03.
More informationThe effectiveness of the Natural Resource Conservation Service (NRCS) and Huff rainfall distribution methods for use in detention basin design
Scholars' Mine Masters Theses Student Theses and Dissertations Spring 2010 The effectiveness of the Natural Resource Conservation Service (NRCS) and Huff rainfall distribution methods for use in detention
More informationARTICLE 5 (PART 2) DETENTION VOLUME EXAMPLE PROBLEMS
ARTICLE 5 (PART 2) DETENTION VOLUME EXAMPLE PROBLEMS Example 5.7 Simple (Detention Nomograph) Example 5.8 Offsite and Unrestricted Areas (HEC-HMS) Example 5.9 Ponds in Series w/ Tailwater (HEC-HMS) Example
More informationDRAINAGE REPORT. Ministry of Transportation and Infrastructure. Highway 7 Four Laning Silverdale Avenue to Nelson Street 100% Detailed Design
DRAINAGE REPORT Ministry of Transportation and Infrastructure Highway 7 Four Laning Silverdale Avenue to Nelson Street 100% Detailed Design December 14, 2017 Reviewed by: Amanda Rust, P. Eng. Senior Drainage
More informationEROSION CONTROL NARRATIVE
EROSION CONTROL NARRATIVE Erosion and sediment control has been designed for the Willow Bend Phase I Subdivision according to UDFCD and the City of Thornton criteria, in order to minimize erosion and sediment
More informationHow to integrate wetland processes in river basin modeling? A West African case study
How to integrate wetland processes in river basin modeling? A West African case study stefan.liersch@pik-potsdam.de fred.hattermann@pik-potsdam.de June 2011 Outline Why is an inundation module required?
More informationWorkshop: Build a Basic HEC-HMS Model from Scratch
Workshop: Build a Basic HEC-HMS Model from Scratch This workshop is designed to help new users of HEC-HMS learn how to apply the software. Not all the capabilities in HEC-HMS are demonstrated in the workshop
More informationD. MATHEMATICAL MODEL AND SIMULATION
D. MATHEMATICAL MODEL AND SIMULATION D - i TABLE OF CONTENTS D.1 Objective of Model Development... D - 1 D.2 Selection of Software... D - 1 D.3 General Steps of Simulation by MOUSE... D - 1 D.4 Cases of
More informationSTREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1. DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT
STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1 DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT Prepared by: PAULUS, SOKOLOWSKI & SARTOR STORMWATER MANAGEMENT 1. Methodology
More informationRucker Pond. Background
Rucker Pond Background The Rucker Basin consists of two subbasins (East and West) that drain to a single area known as Rucker Pond. Both subbasins have the same hydraulic parameters, but have different
More informationBRANDON LAKES AVENUE PRE AND POST CONDITIONS DRAINAGE REPORT
BRANDON LAKES AVENUE PRE AND POST CONDITIONS DRAINAGE REPORT Hillsborough County Public Works County Center, 22nd Floor 601 E. Kennedy Blvd. Tampa, FL 33602 BRANDON LAKES AVENUE DRAINAGE IMPROVEMENTS Capital
More informationCaledon Villas Corporation
Caledon Villas Corporation Functional Servicing Report Caledon Villas Residential Subdivision Town of Caledon Project No. L11-557 April 2014 Caledon Villas Corporation Town of Caledon Caledon Villas Residential
More informationWal-mart Store # Ft. Walton Beach, FL NE Corner of Eglin Parkway/S.R. 85 and South Street STORMWATER REPORT. February 2017
Wal-mart Store #6746-00 Ft. Walton Beach, FL NE Corner of Eglin Parkway/S.R. 85 and South Street STORMWATER REPORT February 2017 CPH Project No. W13900 1031-C W. 23rd Street Panama City, FL 32405 Phone
More informationSeptember 6, City of Thornton 9500 Civic Center Drive Thornton, CO (303) RE: Maverik Thornton, CO - Drainage Report
September 6, 2016 City of Thornton 9500 Civic Center Drive Thornton, CO 80229 (303) 538-7295 RE: Maverik Thornton, CO - Drainage Report As per your request, we are submitting to you the drainage report
More informationStormwater Capacity Analysis for Westover Branch Watershed
Stormwater Capacity Analysis for Westover Branch Watershed Pimmit Run Little Pimmit Run, Mainstem Stohman's Run Gulf Branch Pimmit Run Tributary Little Pimmit Run, W. Branch Little Pimmit Run, E. Branch
More informationChapter 10 - Sacramento Method Examples
Chapter 10 Sacramento Method Examples Introduction Overview This chapter presents two example problems to demonstrate the use of the Sacramento method. These example problems use the SACPRE and HEC-1 computer
More informationDrainage Analysis. Appendix F
Drainage Analysis Appendix F Golden View Drive Elizabeth Street LMORE CREEK Ricky Road Rabbit Creek Road LITTLE RABBIT CREEK East 156th Avenue MOA Project #10-026 Golden View Drive Intersection
More informationSection 4: Model Development and Application
Section 4: Model Development and Application The hydrologic model for the Wissahickon Act 167 study was built using GIS layers of land use, hydrologic soil groups, terrain and orthophotography. Within
More informationVolume 1, Chapter 4 Rainfall
Volume 1, Chapter 4 Rainfall Users Guidance: If a UDFCD Section number in this chapter is skipped: It was adopted as is; please refer to that Section in the corresponding UDFCD Manual, Volume, Chapter
More informationDRAINAGE CALCULATIONS
DRAINAGE CALCULATIONS NW 8 th Street and NW 8 th Terrace Roadway and Drainage Improvements City of Miami Project B-30745 And NW 14 th Court Roadway and Drainage Improvements City of Miami Project B-30746
More informationUrban Hydrology for Small Watersheds
United States Department of Agriculture Natural Resources Conservation Service Conservation Engineering Division Urban Hydrology for Small Watersheds TR-55 Technical Release 55 June 1986 To show bookmarks
More informationSubmitted to: St. Johns River Power Park New Berlin Road Jacksonville, FL 32226
RUN-ON/RUN-OFF CONTROL SYSTEM PLAN RUN-ON AND RUN-OFF CONTROL SYSTEM PLAN St. Johns River Power Park Byproduct Storage Area B Phase I Development Submitted to: St. Johns River Power Park 11201 New Berlin
More informationTable 1 - Infiltration Rates
Stantec Consulting Ltd. 100-300 Hagey Boulevard, Waterloo ON N2L 0A4 November 14, 2017 File: 161413228/10 Attention: Mr. Michael Witmer, BES, MPA, MCIP, RPP City of Guelph 1 Carden Street Guelph ON N1H
More informationInterconnected Channel and Pond Routing Model (ICPR) 2002 Streamline Technologies, Inc. Page 1 of 5
==== Basins ============================================================================== Name: 1A Node: Swale 1 Status: Onsite : Type: SCS Unit Hydrograph CN Unit Hydrograph: Uh256 Peaking Factor: 256.0
More informationSediment Capture in Pervious Concrete Pavement tsystems: Effects on Hydrological Performance and Suspended Solids
Concrete Sustainability Conference April 14 th 2010, Tempe, AZ Sediment Capture in Pervious Concrete Pavement tsystems: Effects on Hydrological l Performance and Suspended Solids Discharge Luis A. Mata,
More informationPONDNET.WK1 - Flow and Phosphorus Routing in Pond Networks
PONDNET.WK1 - Flow and Phosphorus Routing in Pond Networks Version 2.1 - March 1989 William W. Walker, Jr. Ph.D., Environmental Engineer 1127 Lowell Road, Concord, Massachusetts 01742 508-369-8061 PONDNET.WK1
More informationDRAINAGE REPORT FOR THORNTON SELF STORAGE THORNTON, COLORADO
DRAINAGE REPORT FOR THORNTON SELF STORAGE THORNTON, COLORADO Prepared by: Bowman Consulting 603 Park Point Dr. Suite 100 Golden, CO 80401 (303)-801-2900 June 29, 2015 Revised August 14, 2015 CERTIFICATE
More information12 SWAT USER S MANUAL, VERSION 98.1
12 SWAT USER S MANUAL, VERSION 98.1 CANOPY STORAGE. Canopy storage is the water intercepted by vegetative surfaces (the canopy) where it is held and made available for evaporation. When using the curve
More informationA HYDROLOGIC STUDY OF THE EFFECTS OF URBAN DEVELOPMENT ON STORM RUNOFF: A CASE STUDY IN QUEENS, NY ABSTRACT
154 A HYDROLOGC STUDY OF THE EFFECTS OF URBAN DEVELOPMENT ON STORM RUNOFF: A CASE STUDY N QUEENS, NY Monica Tsang-Rakovan, Kevin J. Phillips, Khalid Bajwa, John Ferrelli, Fanning, Phillips and Molnar Fanning,
More informationLOCATED IN INDIAN RIVER COUNTY PREPARED FOR S.J.R.W.M.D. AND F.W.C.D. DECEMBER, 2003 Updated 2007 Updated May 2014 PREPARED BY
FELLSMERE WATER CONTROL DISTRICT EAST MASTER DRAINAGE PLAN AND STORMWATER HYDROLOGIC ANALYSIS OF THE GRAVITY DRAINAGE SYSTEM LOCATED BETWEEN THE EAST BOUNDARY, LATERAL U, THE MAIN CANAL, AND DITCH 24 LOCATED
More informationWQ Outlet Design Single Orifice Orifice diameter = 24. Perforated riser/orifice Plate Outlet area per perforation row = 4
These calculations should be used when designing the outlet structures for extended wet and dry detention basins (Sections 4. 7 and 4.8). The water quality outlet size and the trash rack design will vary
More informationREPORT FOR: ISLAND LAKE ESTATES 4275 Placida Road Englewood, FL 34224
REPORT FOR: ISLAND LAKE ESTATES 4275 Placida Road Englewood, FL 34224 OWNER/APPLICANT: Edgewater Opportunity Fund II Contact: Ronald S Greenland 300 East Bay Heights Road Englewood, FL 34223 SUBMITTED
More informationINTRODUCTION TO HEC-HMS
INTRODUCTION TO HEC-HMS Hydrologic Engineering Center- Hydrologic Modeling System US Army Corps of Engineers Hydrologic Engineering Center HEC-HMS Uses Schematics Enter properties: watershed, rivers (reaches),
More informationATTACHMENT A. STORMWATER MANAGEMENT REPORT Tamiami Trail East Ochopee, FL 34141
ATTACMENT A STORMWATER MANAGEMENT REPORT 57985 Tamiami Trail East Ochopee, FL 34141 April 2nd, 2018 Seminole Tribe of Florida 6300 Stirling Road ollywood, FL 33024 Prepared By: 880 SW 145th Avenue Suite
More informationBushkill Creek 3 rd Street Dam Removal Analysis
Bushkill Creek 3 rd Street Dam Removal Analysis HEC HMS Runoff and Routing Model Stephen Beavan, Melanie DeFazio, David Gold, Peter Mara and Dan Moran CE 421: Hydrology Fall 2010 December 15, 2010 Contents
More informationChapter 5 : Design calculations
Chapter 5 : Design calculations 5. Purpose of design calculations For design calculations, it is important to assess the maximum flow, maximum water level and maximum velocity which occur in every node
More informationNine Minimum Controls No. 2
Nine Minimum Controls No. 2 2.0 MAXIMIZATION OF STORAGE IN THE COLLECTION SYSTEM 2.1 OVERVIEW The 2 nd NMC is titled Maximization of Storage in the Collection system. EPA s NMC Guidance explains that this
More informationSTORMWATER MANAGEMENT COMPUTATIONS. Mount Prospect
STORMWATER MANAGEMENT COMPUTATIONS Mount Prospect MHG PROJECT No. 2011.173.11 November 6, 2014 Prepared for: Piney Meetinghouse Investments c/o Mr. Dennis Fling 14801 Clopper Road Boyds, MD 20841 (301)
More informationChapter 5 CALIBRATION AND VERIFICATION
Chapter 5 CALIBRATION AND VERIFICATION This chapter contains the calibration procedure and data used for the LSC existing conditions model. The goal of the calibration effort was to develop a hydraulic
More informationEtobicoke Exfiltration System: Monitoring and Evaluation. Tim Van Seters Ryerson University July 24, 2015
Etobicoke Exfiltration System: Monitoring and Evaluation Tim Van Seters Ryerson University July 24, 2015 Presentation Outline Summary of 1994 1995 Candaras Associates study Summary of 1996-1998 SWAMP Study
More informationHydrology Study Report
Hafeez Consulting www.hafeezconsulting.com Civil/ Structural Engineering, Design & Construction 1451 S. Hacienda St. Anaheim CA 92804 (714) 225-4565 Fax (714)917-2977 engineer@hafeezconsulting.com Hydrology
More informationThe Sensitivity Analysis of Runoff from Urban Catchment Based on the Nonlinear Reservoir Rainfall-Runoff Model
PUBLS. INST. GEOPHYS. POL. ACAD. SC., E-6 (390), 2006 The Sensitivity Analysis of Runoff from Urban Catchment Based on the Nonlinear Reservoir Rainfall-Runoff Model Marcin SKOTNICKI and Marek SOWIŃSKI
More informationStormwater Drainage Design Report. Reeve & Associates, Inc. Maverik, Inc. 88th Avenue and Pecos Street. Thornton, CO
88th Avenue and Pecos Street Stormwater Drainage Design Report Reeve & Associates, Inc. Solutions You Can Build On for Maverik, Inc. 88th Avenue and Pecos Street Thornton, CO submitted to Reeve & Associates,
More informationCity of Thornton Attn: Tim Semones Development Engineeering 9500 Civic Center Dr. Thornton, CO 80229
Development Engineering Land Surveying Construction Administration District Services October 20, 2017 City of Thornton Attn: Tim Semones Development Engineeering 9500 Civic Center Dr. Thornton, CO 80229
More informationMonitoring Considerations and Costs
Monitoring Considerations and Costs Stormwater BMP Selection, Design, and Monitoring Florida Stormwater Association September 9, 2016 Harvey H. Harper, Ph.D., P.E. Environmental Research & Design, Inc.
More informationThis site will utilize an infiltration berm to manage the two-year/24-hour volume increase.
Gates TETRA TECH, INC. By: RH Date: 1/30/2017 Subject: Gates Road Checked By: JB Date: 2/1/2017 PCSM Design and Evaluation PURPOSE: The purpose of these calculations is to design a Post-Construction Stormwater
More informationGEOL 474/674 Practice Exam #1 Fall This exam counts 20% of your grade for this course; your instructions are as follows:
Write your name here: This exam counts 20% of your grade for this course; your instructions are as follows: 1) You have 75 minutes to finish this exam. 2) No books, notes, or discussion is allowed. If
More informationHYDROLOGY REPORT Tentative Tract No. 5978
ATTACHMENT 5 October 2016 HYDROLOGY REPORT Tentative Tract No. 5978 City of Simi Valley County of Ventura Prepared For: Landsea Holdings Corporation 7525 Irvine Center Drive Suite 200 Irvine, CA 92618
More informationLECTURE 9: Open channel flow: Uniform flow, best hydraulic sections, energy principles, Froude number
LECTURE 9: Open channel flow: Uniform flow, best hydraulic sections, energy principles, Froude number Assist. Prof. Neslihan SEMERCİ Marmara University Department of Environmental Engineering Open channel
More informationPressure Head: Pressure head is the height of a column of water that would exert a unit pressure equal to the pressure of the water.
Design Manual Chapter - Stormwater D - Storm Sewer Design D- Storm Sewer Sizing A. Introduction The purpose of this section is to outline the basic hydraulic principles in order to determine the storm
More informationFlood Forecasting Tools for Ungauged Streams in Alberta: Status and Lessons from the Flood of 2013
Flood Forecasting Tools for Ungauged Streams in Alberta: Status and Lessons from the Flood of 2013 John Pomeroy, Xing Fang, Kevin Shook, Tom Brown Centre for Hydrology, University of Saskatchewan, Saskatoon
More informationCoal Combustion Residuals Unit Inflow Design Flood Control System Plan
Coal Combustion Residuals Unit Inflow Design Flood Control System Plan Virginia Electric and Power Company Chesterfield Power Station Upper (East) Pond Chesterfield County, Virginia GAI Project Number:
More informationThis site will utilize an infiltration berm to manage the two-year/24-hour volume increase.
Gates TETRA TECH, INC. By: RH Date: 11/11/2016 Subject: Gates Road Checked By: JB Date: 11/13/2016 PCSM Design and Evaluation PURPOSE: The purpose of these calculations is to design a Post-Construction
More informationDAVID NOEL KELLY CIVIL. David Noel Kelly :24:14-04'00'
DAVID NOEL KELLY CIVIL David Noel Kelly 2014.07.22 10:24:14-04'00' TABLE OF CONTENTS Stormwater Management Summary Checklist for Stormwater Report Illicit Discharge Statement Runoff Summary Existing Conditions
More informationEROSION CONTROL NARRATIVE
EROSION CONTROL NARRATIVE Erosion and sediment control has been designed for the Willow Bend Phase I Subdivision according to UDFCD and the City of Thornton criteria, in order to minimize erosion and sediment
More informationD. B. G R A Y E N G I N E E R I N G I N C.
STORMWATER MANAGEMENT REPORT 948 Hunt lub Road Ottawa, Ontario Report No. 12020-SWM August 27, 2012 Revised April 21, 2014 Revised December 9, 2014 Revised April 14, 2015 D. B. G R A Y E N G I N E E R
More informationSTORMWATER REPORT FRITO LAY SUBDIVISION NO. 3
STORMWATER REPORT FRITO LAY SUBDIVISION NO. 3 May 2018 STORMWATER REPORT I. Subdivision Data a. The parcel is adjacent to the existing Frito Lay property in Topeka; and the subject plat application encompasses
More informationA Study on Storm Water Drainage System of Annanagara and Ashokanagara of Shimoga City Karnataka India
A Study on Storm Water Drainage System of Annanagara and Ashokanagara of Shimoga City Karnataka India Veena D Savanth Lecturer, Department of Civil Engineering Jain Institute of Technology, Davanagere,
More information9. Flood Routing. chapter Two
9. Flood Routing Flow routing is a mathematical procedure for predicting the changing magnitude, speed, and shape of a flood wave as a function of time at one or more points along a watercourse (waterway
More informationREGULATORY, TECHNICAL AND MODELING CHALLENGES TO DEVELOPING A FREQUENCY BASED SSO CONTROL PROJECT IN WAYNE COUNTY, MICHIGAN
REGULATORY, TECHNICAL AND MODELING CHALLENGES TO DEVELOPING A FREQUENCY BASED SSO CONTROL PROJECT IN WAYNE COUNTY, MICHIGAN Robert Czachorski, P.E., P.H., Orchard, Hiltz & McCliment, Inc. * John Baratta.
More informationIntensity-Duration-Frequency (IDF) Curves Example
Intensity-Duration-Frequency (IDF) Curves Example Intensity-Duration-Frequency (IDF) curves describe the relationship between rainfall intensity, rainfall duration, and return period (or its inverse, probability
More informationHaiti and Dominican Republic Flash Flood Initial Planning Meeting
Dr Rochelle Graham Climate Scientist Haiti and Dominican Republic Flash Flood Initial Planning Meeting September 7 th to 9 th, 2016 Hydrologic Research Center http://www.hrcwater.org Haiti and Dominican
More informationψ ae is equal to the height of the capillary rise in the soil. Ranges from about 10mm for gravel to 1.5m for silt to several meters for clay.
Contents 1 Infiltration 1 1a Hydrologic soil horizons...................... 1 1b Infiltration Process......................... 2 1c Measurement............................ 2 1d Richard s Equation.........................
More informationAppendix B Equations and Examples
Equations and Examples Purpose The purpose of this appendix is to provide background equations and example problems for clarity of calculations used throughout the manual. This appendix is divided into
More informationHydrologic Modeling System HEC-HMS
Hydrologic Engineering Center Hydrologic Modeling System HEC-HMS Quick Start Guide Version 3.3 September 2008 Approved for Public Release Distribution Unlimited CPD-74D REPORT DOCUMENTATION PAGE Form Approved
More informationFINAL DRAINAGE REPORT Villages at Riverdale Carriage Homes Thornton, CO
FINAL DRAINAGE REPORT Villages at Riverdale Carriage Homes Thornton, CO October 14, 2016 Revised: March 30, 2017 JN: 15096 Prepared for: PCS Group, Inc. 1001 16 th Street #3 B-180 Denver, CO 80265 P: 303.561.4905
More informationObjectives: After completing this assignment, you should be able to:
Data Analysis Assignment #1 Evaluating the effects of watershed land use on storm runoff Assignment due: 21 February 2013, 5 pm Objectives: After completing this assignment, you should be able to: 1) Calculate
More informationENGINEERING HYDROLOGY
ENGINEERING HYDROLOGY Prof. Rajesh Bhagat Asst. Professor Civil Engineering Department Yeshwantrao Chavan College Of Engineering Nagpur B. E. (Civil Engg.) M. Tech. (Enviro. Engg.) GCOE, Amravati VNIT,
More informationSusanna Glaze, Bobby Creel, and Christopher Brown New Mexico State University AWRA Spring Specialty Conference 4-6 May 2009 Anchorage, Alaska
Susanna Glaze, Bobby Creel, and Christopher Brown New Mexico State University 2009 AWRA Spring Specialty Conference 4-6 May 2009 Anchorage, Alaska Outline Introduction to general water resources issues
More informationHydrologic Modeling System HEC-HMS
Hydrologic Engineering Center Hydrologic Modeling System HEC-HMS Quick Start Guide Version 3.5 August 2010 Approved for Public Release Distribution Unlimited CPD-74D REPORT DOCUMENTATION PAGE Form Approved
More informationFigure C-1 Model Network Diagram: Existing Land Use
Figure C-1 Model Network Diagram: Existing Land Use March 2003 P:\GIS\santaclaraWD\projects\Chapter 4\FigureC-1 Model Network Diagram: Existing Land Use Condtions GeoSyntec Consultants Figure C-2 Modeled
More informationApplication of Real-Time Rainfall Information System to CSO control. 2 October 2011 Naruhito Funatsu METAWATER Co., Ltd.
Application of Real-Time Rainfall Information System to CSO control 2 October 2011 Naruhito Funatsu METAWATER Co., Ltd. Presentation Points Objectives To verify the applicability of the real-time rainfall
More informationSacramento Area Hydrology Model (SAHM) Guidance Document. Clear Creek Solutions, Inc.
Sacramento Area Hydrology Model (SAHM) Guidance Document Clear Creek Solutions, Inc. www.clearcreeksolutions.com ii To download the Sacramento Area Hydrology Model and the electronic version of this document,
More informationAppendix E Guidance for Shallow Flooding Analyses and Mapping
Appendix E Guidance for Shallow Flooding Analyses and Mapping E.1 Introduction Different types of shallow flooding commonly occur throughout the United States. Types of flows that result in shallow flooding
More informationHOTEL KANATA 160 HEARST WAY KANATA, ONTARIO SERVICING REPORT. Prepared for: David Johnston Architect. Prepared By:
HOTEL KANATA 160 HEARST WAY KANATA, ONTARIO SERVICING REPORT Prepared for: David Johnston Architect Prepared By: BaseTech Consulting Inc. 309 Roywood Crescent Newmarket, Ontario L3Y 1A6 BCI Project No.
More informationD.M. Wills Associates Limited PARTNERS IN ENGINEERING. Stormwater Management Report. City of Peterborough
Stormwater Management Report City of Peterborough P-20-12 Parkway Corridor Class Environmental Assessment Jackson Park Parkhill Road West to Chemong Road D.M. Wills Project No. 12-5061 D.M. Wills Associates
More information2012 Rainfall, Runoff, Water Level & Temperature Beebe Lake Wright County, MN (# )
www.fixmylake.com 18029 83 rd Avenue North Maple Grove, MN 55311 mail@freshwatersci.com (651) 336-8696 2012 Rainfall, Runoff, Water Level & Temperature Beebe Lake Wright County, MN (#86-0023) Prepared
More informationHomework 10. Logan Dry Canyon Detention Basin Design Case Study Date: 4/14/14 Due: 4/25/14
Homework 10. Logan Dry Canyon Detention Basin Design Case Study Date: 4/14/14 Due: 4/25/14 Section 1: Case Study Introduction This case study serves as an integrative problem based learning exercise. In
More informationFUNCTIONAL SERVICING REPORT AND SWM REPORT
FUNCTIONAL SERVICING REPORT AND SWM REPORT 104 WHITE CRESCENT CITY OF BARRIE, COUNTY OF SIMCOE December 2018 18058 TABLE OF CONTENTS 1. INTRODUCTION... 4 2. SUPPORTING DOCUMENTS... 4 3. DESIGN POPULATION...
More informationSediment Control Practices. John Mathews Ohio Dept. of Natural Resources, Division of Soil and Water Resources
Sediment Control Practices John Mathews Ohio Dept. of Natural Resources, Division of Soil and Water Resources Practices Treat the Largest Soil Particles Sand Sand Silt Clay Treated Untreated Settleable
More informationQuantifying model uncertainty in the simulation of sewer overflow volume
Quantifying model uncertainty in the simulation of sewer overflow volume Ambuj Sriwastava Marie Curie Early Stage Researcher, University of Sheffield This project has received funding from the European
More informationDRAFT. REVISED Draft. Paso Robles Subbasin Groundwater Sustainability Plan Chapter 6
REVISED Draft Paso Robles Subbasin Groundwater Sustainability Plan Chapter 6 Prepared for the Paso Robles Subbasin Cooperative Committee and the Groundwater Sustainability Agencies February 14, 2019 Paso
More informationGeorge Mason University Department of Civil, Environmental and Infrastructure Engineering
George Mason University Department of Civil, Environmental and Infrastructure Engineering Dr. Celso Ferreira Prepared by Lora Baumgartner December 2015 Revised by Brian Ross July 2016 Exercise Topic: Getting
More information