Appendix D2: Geotechnical Engineering

Size: px
Start display at page:

Download "Appendix D2: Geotechnical Engineering"

Transcription

1 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology Appendix D2: Geotechnical Engineering and Geology Fargo Moorhead Metropolitan Area Project Reach 5 Engineering and Design Phase P2# Doc Version: Post FTR Submittal 23 March 2015 DDR_FMM_R5_Appendix_D2_Post_FTR_ docx

2 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology This page is intentionally left blank DDR_FMM_R5_Appendix_D2_Post_FTR_ docx

3 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology Appendix D2: Geotechnical Engineering and Geology Table of Contents D.1 PROJECT DESCRIPTION... 1 D.2 REGIONAL GEOLOGY... 1 D.2.1 Physiography... 1 D.2.2 Topography... 1 D.2.3 Geology... 2 D.2.4 Structure... 2 D.2.5 Site Hydrogeology... 2 D.2.6 Seismic Risk and Earthquake History... 4 D.3 SUBSURFACE INVESTIGATION... 4 D.3.1 Exploration... 4 D.3.2 Testing... 5 D.3.3 Design Parameters... 5 D.4 DIVERSION CHANNEL ANALYSIS... 7 D.4.1 Modeling Summary... 7 D Lower Rush Inlet Geometry... 7 D Diversion Channel Geometry... 8 D.4.2 Sections... 9 D.4.3 Seepage D.4.4 Stability D.4.5 Results D.4.6 Future Work D.5 EXCAVATED MATERIAL BERM AND LEVEE ANALYSIS D.6 RIGHT BANK EMEDDED LEVEES D.7 SETTLEMENT AND REBOUND D.7.1 Consolidation Parameters DDR_FMM_R5_Appendix_D2_Post_FTR_ docx D i of D iii

4 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology D.7.2 Settlement of typical levee/ Right Bank EMB D.7.3 Rebound in the Channel Excavation D.8 DIVERSION EXCAVATION TYPES D.9 LOCAL DRAINAGE INLETS D.10 RIPRAP AND BEDDING D.11 CONSTRUCTABILITY D.11.1 Excavations D Past Experience D Methods D Stripping and Overexcavation D Dewatering D Sand Pockets / Lenses D.11.2 Access/Maintenance Road Foundations D.11.3 Embankment Construction D.11.4 Winter Conditions D.11.5 Levees and Excavated Material Berms D Net Swelling of Material Used for EMBs D.12 SOURCES OF CONSTRUCTION MATERIALS D.12.1 Levee Material D.12.2 Concrete Aggregate, Riprap, and Bedding D.13 PHASE 1 ENVIRONMENTAL SITE ASSESSMENT D.14 handled properly.references D.15 ATTACHMENTS TABLES Table D2 1: Summary of Soil Exploration for Lower Rush Structure... 5 Table D2 2: Channel Sections Geometry... 9 Table D2 3: Formation Contact Elevations Table D2 4: Summary of Diversion Channel Stability Results Table D2 5: Rock Ramp Stability Results DDR_FMM_R5_Appendix_D2_Post_FTR_ docx D ii of D iii

5 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology Table D2 6: Total Stress Parameters Table D2 7: Summary of EMB Maximum Grading Extents Table D2 8: Mean Consolidation Parameters Table D2 9: Settlement Check Analysis Results Table D2 10: Predicted EMB Settlement for Determination of Levee Overbuild Table D2 11: Predicted Ultimate Rebound in Diversion Channel Table D2 12: Summary of Diversion Channel Excavation Types FIGURES Figure D2 1: P Instrumentation Plot... 3 Figure D2 2: P Instrumentation Plot... 4 Figure D2 3 : Brenna Strength Plot... 6 Figure D2 4 : Lower Rush Rock Ramp Configuration Figure D2 6 : EMB Grading Extents Figure D2 6 : EMB Grading Extents Figure D2 7: In situ dry density data compared to standard proctor results ATTACHMENTS Attachment D2 1: Stratigraphy (Included in Reach 5 DDR) Attachment D2 2: Soil Exploration Location Maps (Included in Reach 5 DDR) Attachment D2 3: Boring Log Plates (Included in Reach 5 DDR) Attachment D2 4: Outlet and Diversion Stability Analysis Results Attachment D2 5: Settlement and Rebound Calculations DDR_FMM_R5_Appendix_D2_Post_FTR_ docx D iii of D iii

6 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology Appendix D2: Geotechnical Engineering and Geology D.1 PROJECT DESCRIPTION The Lower Rush River Drop Structure is located in the central area of the project where the Lower Rush River will be diverted into the diversion channel, within Reach 5. Within this reach, there are multiple features that require geotechnical design and considerations which are listed below. The reach that will encompass the rock ramp structure is between station and Inlet Structure Multi drop rock ramp o Stability of the excavated slope o Design of riprap and bedding that is used along the rock ramp o Estimate of rebound due to the unloading of the soil Diversion Channel o Stability of the excavated slope, accounting for the excavated material berms and low flow channel o Stability of the excavated slope, accounting for potential erosion of the low flow channel and sedimentation at the bottom of the diversion. o Estimate of rebound due to the unloading of the soil Levees within the Excavated Material Berms along the Diversion Channel o Settlement of the levees and excavated material berms o Minimum vegetation free zone requirements D.2 REGIONAL GEOLOGY D.2.1 Physiography Physiography is discussed in detail in the General Report: Geotechnical Engineering and Geology (Reference D2 1). D.2.2 Topography The topographic profile along the Reach 5 centerline begins at the downstream end at Sta where the ground surface is at typical elevation 890. Along Reach 5 moving upstream, the ground surface elevation rises very gradually to an average of about elevation 894 at Sta The ground surface from this point to the reach s end varies from elevation 893 to 894. A number of small roads and County Road 22 cross the alignment along embankments that are several feet higher than the average ground elevations. DDR_FMM_R5_Appendix_D2_Post_FTR_ docx Page D2 1 of D2 27

7 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology D.2.3 Geology A detailed description of the regional geology can be found in the General Report: Geotechnical Engineering and Geology (Reference D2 1). Generally speaking the Lower Rush Inlet Structure is defined by a sequence of glacio lacustrine deposits (Argusville, Brenna, and Sherack Formations) overlying a dense, overconsolidated glacial till. A layer of alluvial clay and topsoil typically caps the lacustrine sequence. The glacial till is not of great importance on the Lower Rush Inlet Structure, as no pile founded structures are planned. Borings indicate that the top of the glacial till is located at about El Above the till is the Argusville formation, which is approximately 10 to 15 ft thick. The contact between the Argusville Formation and the Brenna Formation is gradational and typically occurs over 10 or more feet. For the purposes of the stability analyses this gradational contact has been assumed as part of the Brenna Formation, which exhibits lower shear strengths than the Argusville Formation. The characterization of the 2012 and 2013 borings, which rely upon liquid limits, have been utilized in the determination of this contact for the Lower Rush analyses, as it is more conservative than the field classifications of the 2010 borings. The contact between the Brenna and Sherack Formations is located at between El. 879 and 884. Typically there is a portion at the top of the Brenna that is oxidized and sometimes desiccated. Testing indicates that this portion of the Brenna, typically several feet thick, is characterized by higher shear strengths, and so it has been broken out as a separate material for stability analyses. The Sherack Formation is typically around 5 ft thick, and its upper limit can range from El. 890 to the ground surface. The Sherack is typically overlain by alluvial clays that are usually several feet thick. The stratigraphy for the Lower Rush inlet structure and Reach 5 is presented in the attachments for the Reach 5 analysis and DDR prepared by the St. Paul District (MVP). D.2.4 Structure Geologic structures are discussed in detail in the General Report: Geotechnical Engineering and Geology (Reference D2 1). D.2.5 Site Hydrogeology The hydrogeology as discussed in the General Report: Geotechnical Engineering and Geology (Reference D2 1) applies to the Lower Rush Inlet Structure. Groundwater levels as measured during soil borings varied. In some borings water could be 2.3 ft from the ground surface after a day, and in other borings the hole would be dry to 20 ft for the same time period. Groundwater assumptions for modeling were made based on instrumentation located at other locations in the Fargo Moorhead area and seepage calibration modeling. Instrumentation consisting of nested vibrating wire piezometers was installed along the proposed alignment in August 2012 and February 2013 to verify groundwater assumptions along portions of the diversion. The nearest instrumentation clusters to Reach 5 are P and P P is located approximately 2.3 miles downstream in Reach P is located just upstream in Reach 6. Readings DDR_FMM_R5_Appendix_D2_Post_FTR_ docx Page D2 2 of D2 27

8 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology from these locations indicate that the groundwater depths have fluctuated between 3.5 to 12 feet below the ground surface. The highest groundwater table elevations occurred in June and July of 2013, with the levels dropping afterwards. All piezometers indicate downward gradients through the Lake Agassiz clays into the Unit A Till. Piezometer P indicates a downward gradient of 0.1 to 0.35 (Figure D2 1). Piezometer P indicates a downward gradient of about 0.15 to 0.65 (Figure D2 2). The USGS Fargo gage on the Red River is shown for reference only. Please refer to the General Report: Geotechnical Engineering and Geology (Reference D2 1) for additional information and details concerning the instrumentation. Figure D2 1: P Instrumentation Plot DDR_FMM_R5_Appendix_D2_Post_FTR_ docx Page D2 3 of D2 27

9 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology Figure D2 2: P Instrumentation Plot D.2.6 Seismic Risk and Earthquake History Seismic Risk and Earthquake History are discussed in the General Report: Geotechnical Engineering and Geology (Reference D2 1). The main conclusion is that the Fargo Moorhead area is one of the least seismically active places in the United States. The estimated peak horizontal ground accelerations are small, g and 0.04g for a mean return time of 2475 years and 4975 years. Considering the low risk, the low ground accelerations, and the fact that the foundation soils are not prone to liquefaction, seismic analysis is not required for the diversion channel and inlet structure. D.3 SUBSURFACE INVESTIGATION D.3.1 Exploration Soil borings and cone penetration test (CPT) soundings were completed within the project area to determine the stratigraphy. The number and type of exploration method is summarized below in the table. The location of the completed soil exploration can be found in Attachment D2 2 for the Reach 5 DDR submitted by MVP. The boring logs can be found in Attachment D2 3 for the Reach 5 DDR DDR_FMM_R5_Appendix_D2_Post_FTR_ docx Page D2 4 of D2 27

10 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology submitted by MVP. Details concerning the subsurface investigation can be found in the General Report: Geotechnical Engineering and Geology (Reference D2 1). Table D2 1: Summary of Soil Exploration for Lower Rush Structure Location Machine Borings Undisturbed Borings Hand Auger Topsoil Borings CPT Lower Rush River Drop Structure D.3.2 Testing While conducting the soil borings, samples are collected. Some of these samples are tested to determine the in situ moisture content and Atterberg limits. At less frequency, grain size analysis including hydrometer testing is completed on the samples. The results of these tests are including in the boring log staffs. One undisturbed soil boring (12 162MU) was taken in the vicinity of the Drop Structure, west of the Lower Rush River. Five samples were obtained from this boring and tested for shear strengths and consolidation parameters. D.3.3 Design Parameters Geotechnical design parameters are discussed in detail in the General Report: Geotechnical Engineering and Geology (Reference D2 1). The design parameters presented in the general report were used in the analysis and design of the Lower Rush Structure and Reach 5. Many undisturbed borings were conducted throughout the Fargo Moorhead area. The samples were tested to determine the shear strength and consolidation parameters of the materials. The results were broken up into the different formations and the results combined together to determine the parameters required for design. The results of the undisturbed testing can be found in the General Report: Geotechnical Engineering and Geology (Reference D2 1). During the 35% phase of this project, final changes were made to the project stratigraphic profile by St. Paul District. The changes reflect geologic interpretations based on a review of laboratory testing, contact elevations and selection of most relevant soil borings. The changes in Reach 5 were generally detrimental to the design, lowering the Brenna/Argusville contact and therefore reducing the shear strengths in the lower part of the stratigraphy. In an effort to minimize changes to the layout, MVP performed a thorough review of shear strength testing. An increase in the drained shear strength of the Brenna formation was considered defensible and reduced the impact to layout and schedule. DDR_FMM_R5_Appendix_D2_Post_FTR_ docx Page D2 5 of D2 27

11 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology The drained shear strength of the Brenna formation was reviewed and it was found that increasing the shear envelope by 20 psf was an acceptable change as the envelope still was within the range of the test results. Additionally it is has been noted that legacy testing performed for the Horace to West Fargo and West Fargo diversions, south of Reach 5, plots well below tests performed for the current project. There is no geologic reason to expect such a discrepancy, and additional investigation is planned to explore potential causes. The updated shear strength data parameters to the Brenna formation is displayed in the below Figure D2 3. Figure D2 3 : Brenna Strength Plot DDR_FMM_R5_Appendix_D2_Post_FTR_ docx Page D2 6 of D2 27

12 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology D.4 DIVERSION CHANNEL ANALYSIS D.4.1 Modeling Summary This section discusses the basic geometric features of the diversion channel within Reach 5 and the Lower Rush River Rock Ramp as it drains into the diversions channel and as it pertains to geotechnical analysis. D Lower Rush Inlet Geometry The Lower Rush River will empty into the FMM Diversion Channel via a rock ramp which employs rock weirs and a 5% slope to achieve the majority of the elevation change. 1V:8H side slopes are required throughout the ramp to meet stability requirements. Throughout the outlet the base of the excavation will be covered with a layer of rock and bedding material in order to prevent erosion. This erosion protection extends up to the 500 year + 2 feet flood elevation and will be up to five feet thick. In the undrained case it was verified that the additional excavation prior to placing the rock was not detrimental to stability. The geometry of the critical section for the inlet structure is taken at the bottom of the 5% ramp at LRR Station During construction with overexcavation for riprap, this section has the lowest invert elevation within the rock ramp. The invert of the rock ramp at this point is elevation At this location the centerline of the diversion channel low flow channel is about 270 feet away from the rock structure channel centerline. Five feet of riprap are required for erosion protection at this section. Due to the geometry of the rock ramp and corresponding layout of the excavated material berms, the EMBs to the north of the ramp require flatter slopes than those on the EMB to the south of the ramp. The EMB to the north of the ramp is higher in elevation where the critical section occurs at Sta A southern EMB does not exist at this location, and develops very slowly from this point to its maximum elevation much further up the ramp where it has much flatter slopes and a higher invert elevation. To evaluate the stability of the ramp where the southern EMB with slopes 1:8 has a significant height, a section was analyzed at Sta This section has the greatest differential in maximum EMB elevation and invert elevation, and was therefore determined to be a critical location for this analysis. The 1:8 EMB slopes for the EMB south of the Rock Ramp were determined to be stable for this section. Utilizing two different EMB slopes for this reach along the rock ramp optimizes storage area of the excavated material compared to that which would be achieved if both EMBs were constructed at 1:10 slopes. Figure D2 4 displays the location of the two sections. DDR_FMM_R5_Appendix_D2_Post_FTR_ docx Page D2 7 of D2 27

13 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology D Diversion Channel Geometry Figure D2 4 : Lower Rush Rock Ramp Configuration In cross section, the channel features can be divided in three parts: 1) Main channel: The main diversion channel will be described separately from the meandering low flow channel at its base. The main channel provides the vast majority of the channel s capacity and was sized to handle large flows associated with flooding. It is characterized by excavated side slopes of 1V:7H and a 300 ft wide base sloping at 1V:50H (2%) towards the channel centerline. Within Reach 5 the side slopes are typically around 19 ft in height. 2) Meandering Low Flow Channel: A smaller low flow channel at the base of the main channel is required in order to convey the smaller flows anticipated over most of the channel s design life. For environmental reasons, the low flow channel meanders sinuously within the base of the main channel. The geometry of the channel and its spatial relationship to the main channel have been selected in order to meet both hydraulic and geotechnical requirements. The channel itself is 90 ft wide at the top with 5.6 ft high side slopes and a 46 ft wide base sloping at 2% to the low flow channel invert. Side slopes vary with the meander in order to maintain the above dimensions, but are roughly 1V:4H for the stability design case (Case 2, as described in section D.4.4) The low flow channel meanders within a 200 ft wide band centered in the main channel, leaving 50 ft between the toe of the main channel and the top of the low flow channel at its maximum offset from centerline. This was the cross section chosen for stability analysis. DDR_FMM_R5_Appendix_D2_Post_FTR_ docx Page D2 8 of D2 27

14 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology 3) Excavated Material Berms (EMBs): Material excavated for the diversion channel will be placed adjacent to the channel in berms that could be a maximum of 20 ft in height. The berms will be offset from the top of excavation by 50 ft and the side slopes facing the channel will be 1V:7H. Side slopes facing away from the channel are currently shown as 1V:6H. Excavation and stability requirements were achieved by maintaining a simple EMB configuration, and, therefore, stepped EMBs analyses were not required. A design envelope was developed in order to help the Civil layout of the EMBs, which provides maximum grading extents for the material that would still remain stable. The results of this process will be presented in section D.5. Models were not updated from the 65% DDR Submittal for the Lower Rush Diversion channel. The parameters chosen and profile assumed in this report were verified by additional borings completed in Formation contact elevations generally varied by less than one foot with all original assumptions being more conservative than those determined by additional exploration. The largest variation was in the contact of the Oxidized Brenna and Brenna formation at Section 8a, which was interpreted to be from 2010 borings and interpreted to be from 2013 boring. This variation was determined to be insignificant in the overall stability of the cross sections, as it did not improve conditions enough to change the required geometry of the cross section. D.4.2 Sections The geometric configurations of the cross sections analyzed for stability are summarized below Table D2 2. Formation contact elevations for each are provided in Table D2 3. Section # Station Ground El. (ft) Channel Side Slopes (V:H) Table D2 2: Channel Sections Geometry EMB Side Slopes (V:H) Section Geometry Toe EL. (ft) Main Channel Base Slope (V:H) Low Flow Slope (V:H) Low Flow Base Slope (V:H) Low Flow invert El. (ft) Ramp invert EL. (ft) :7 1: :50 (2%) 1:4 1:50 (2%) N/A Simple 8A :7 1: :50 (2%) 1:4 1:50 (2%) N/A Simple LRR :8 1:10 (2) :100 (3%) N/A N/A N/A N/A LRR :8 1:8/1:10 (3) :100 (3%) N/A N/A N/A N/A Notes: (1) The EMB configuration and geometry will be detailed in the summary for the stability analysis. (2) Side Slopes for Northern EMB (3) Side Slopes for Southern EMB/Northern EMB EMB (1) DDR_FMM_R5_Appendix_D2_Post_FTR_ docx Page D2 9 of D2 27

15 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology Table D2 3: Formation Contact Elevations Section 8 8a LRR1 LRR Geologic Unit Top El. (ft) Bottom El. (ft) Top El. (ft) Bottom El. (ft) Top El. (ft) Bottom El. (ft) Top El. (ft) Bottom El. (ft) Alluvium (1) Sherack Ox Brenna Brenna Argusville Till (2) Notes: (1) The top of the Alluvium is considered the Ground Surface Elevation (GSE). (2) The bottom of the Till is equal to the bottom of the model used for stability purposes. D.4.3 Seepage Seepage analysis was conducted according to the MFR 002, Diversion Channel and Low Flow Chanel Design (Reference D2 3), in which the analysis methodology is described in detail. These pore pressures are then used in the long term (drained) slope stability analysis. Briefly, half space models were constructed with a total head condition at the far field boundary, located 2000 ft from the channel centerline. The total head condition is equivalent to 10 ft below the ground surface. This assumes a hydrostatic groundwater condition at the far field boundary, which is thought to be a reasonable assumption based on available instrumentation data. A potential seepage face boundary condition was applied to the face of the channel slope and the base of the low flow channel. Currently the low flow channel is modeled as dry as it is anticipated that the channel could dry up occasionally during the project s design life, and this would represent a critical design condition. Seepage analyses of the were performed similar to the diversion channel analyses. However, the interface between the riprap and the excavated surface was modeled as a zero pressure boundary condition for Section LRR1 at Station This method produced a realistic pore pressure regime while preventing water from ponding in the sizable pore space of the riprap. This was considered a reasonable assumption because the Lower Rush River is known to dry up at times, in which case ponded water below the riprap surface would not be present. Due to the higher elevation of the ramp at Section LRR2, Station 12+00, it is not realistic to assume the piezometric surface will be above the riprap and would pond within its pore space. Therefore, a potential seepage face boundary condition was applied between the riprap and excavated surface. This produced the most realistic ground water conditions for the geometry of this section. A seepage calibration has been performed using piezometer data in the FMM area. The purpose of the calibration was to verify that assumptions regarding boundary conditions and hydraulic conductivities DDR_FMM_R5_Appendix_D2_Post_FTR_ docx Page D2 10 of D2 27

16 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology correlated reasonably well with field data. The calibration is discussed in detail in the General Report: Geotechnical Engineering and Geology (Reference D2 1). D.4.4 Stability The methodology used to analyze slope stability is described in detail in the MFR 002, Diversion Channel and Low Flow Chanel Design (Reference D2 3), and will be summarized only briefly here. The analyses considered both drained and undrained cases. The pore pressures from the seepage analysis are coupled in the long term (drained) stability analysis. For the drained case, several search zones were identified with varying required factors of safety based on criticality of the slip surface. Two geometric configurations (Case 2 and 5) were analyzed for stability of the diversion channel and have varying required factors of safety depending on the occurrence of each configuration. Two cases analyzed in the 35% DDR (Case 3 and 4) were rendered obsolete in light of the Meander Belt Width Analysis completed by Barr Engineering and the HEC RAS Sediment Transport Analysis completed by USACE St. Paul District. Case 2 represents the design geometry of the low flow channel as described in Section D.4.1. Case 5 represents two vertical feet of erosion at the base of the low flow channel and along the low flow side slopes and sedimentation above the bottom of the diversion channel. The intent of Case 5 is to estimate the stability of the diversion channel throughout the lifetime of the project, considering that erosion of the low flow and sedimentation of the diversion will likely occur. The stability analysis of the inlet structure did not consider the two geometric configurations because the channel was centered within the cut and riprap and bedding is being placed to prevent erosion. It was therefore unnecessary to look at cases in which the inlet channel migrated towards the toe of the main channel. D.4.5 Results Stability results for the Diversion channel are summarized below in Table D2 4. DDR_FMM_R5_Appendix_D2_Post_FTR_ docx Page D2 11 of D2 27

17 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology Table D2 4: Summary of Diversion Channel Stability Results Minimum Required FS General Section Information CASE 2 (1) CASE 5 2 Feet Sedimentation (6) Max crack depth Global Check Left Slope Left Slope EMB Undrained Undrained Global Check Section Station (ft) (3) Global (4) Lower Localized EMB (5) (2) Global (4) Lower Localized a Notes: (1) All factors of safety presented are the optimized factors of safety. The non optimized factors were checked and yield larger values in all cases. (2) The results of the Left Slope EMB analysis stay the same regardless of the low flow case. (3) Tension cracks were started at 1 foot deep and progressively increased until tension forces in the slices were removed. (4) Global Check analysis accounts for the influence of the large EMB. (5) The Undrained analysis has the same entry and exit extents as the Global Check to account for the influence of the EMB (6) Sedimentation was started at 2 feet and increased by 2 feet increments until the factor of safety was not met. Sedimentation greater than 2 feet yielded factors of safety less than those required for all lower and localized analyses. (7) Drained analysis with 5' rock over excavation and riprap in place of soil. Permeability of riprap assumed as 1000 ft/day. Potential seepage face modeled on top of the ramp slopes where riprap is not expected, and zero pressure head placed beneath the riprap material. The diversion stability analysis was performed in accordance with MFR 002, Diversion Channel and Low Flow Chanel Design (Reference D2 3) and also follows the guidance provided in the EMB Regional Webinar presented on June 21 st, The results indicate that benches will not be needed in the diversion slopes along Reach 5 in order to meet stability criteria. Stability results for the Rock Ramp can be summarized in Table D2 5 below. DDR_FMM_R5_Appendix_D2_Post_FTR_ docx Page D2 12 of D2 27

18 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology Section (1) Stationing Max crack depth (ft) Table D2 5: Rock Ramp Stability Results Minimum Required FS Global Global Check Lower Localized LRR Undrained During Construction 1.23 (3) 1.45 (4) Undrained End of Construction (5) LRR Notes: (1) Drained analysis with 5' rock over excavation and riprap in place of soil. Permeability of riprap assumed as 1000 ft/day. Potential seepage face modeled on top of the ramp slopes where riprap is not expected, and zero pressure head placed beneath the riprap material. (2) Temporary excavation for riprap included in the analysis with no material type present. Peak undrained material strengths utilized. (3) Using Ultimate Undrained Material Strengths (4) Using Peak Undrained Material Strengths (5) Riprap in place. Ultimate Undrained Material Strengths utilized. In order to meet stability criteria for the undrained case, the slopes of the Lower Rush Ramp must be 1V:8H. Models of the rock ramp were run with different boundary conditions in the seepage model in order to determine how the difference would be reflected in the stability analysis. These different boundary conditions resulted in a slight variation in Factors of Safety for the drained cases, but utilizing the zero pressure head boundary condition is believed to be the more accurate representation of actual conditions. For the undrained case two conditions were considered, the during construction case in which overexcavation of five feet is modeled for the riprap and the end of construction case in which riprap has been placed within the ramp. For Section LRR1, peak undrained strengths were utilized for the temporary excavation condition, which yielded a Factor of Safety of Utilizing the ultimate undrained strengths resulted in a Factor of Safety of 1.23, which is acceptable for the temporary conditions. Ultimate material strengths are considered when significant deformation may be expected in the soils. The short term, during construction condition is not expected to experience such deformation and can therefore be reasonably expected to attain peak strength characteristics. For Section LRR2, ultimate undrained strengths yielded a Factor of Safety greater than the required 1.3, and therefore, peak strengths were not modeled. End of construction analyses utilized ultimate undrained strengths. A comparison of peak and undrained strengths of foundation materials is displayed in Table D2 6. A typical stress strain relationship obtained from testing of Brenna Formation within the Lower Rush reach is displayed in Figure D2 5. A complete listing of Soil Parameters and testing data is available in the General Report: Geotechnical Engineering and Geology (Reference D2 1) DDR_FMM_R5_Appendix_D2_Post_FTR_ docx Page D2 13 of D2 27

19 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology Notes: Table D2 6: Total Stress Parameters Formation Total Stress, c (psf) Ultimate (1) Peak (2) Alluvium Sherack Oxidized Brenna Brenna Argusville See Note (3) 825 Unit A Till (1) The ultimate total stress parameters are based on unconsolidated undrained triaxial shear tests with the failure criterion defined at ultimate deviator stress which equates to the deviator stress at 15% axial strain. (2) The peak total stress parameters are based on unconsolidated undrained triaxial shear tests with the failure criterion defined at peak deviator stress. (3) The Argusville formation ultimate undrained shear strength was assumed to be linearly increasing with depth. Initial cohesion was assumed to be 575 psf, with an increase of 10 psf/ft. Figure D2 5 : Boring MU Uncosolidated Undrained Triaxial Test Results The seepage and stability analyses are presented in Attachment D2 4. DDR_FMM_R5_Appendix_D2_Post_FTR_ docx Page D2 14 of D2 27

20 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology D.4.6 Future Work Any changes to the channel geometry or EMB geometry that occur for non geotechnical reasons may require re analysis for stability. For example, on one side of the channel the EMBs will likely be shaped in undulating hills for recreational purposes. This may have stability implications and will require verification as the grading plan moves forward. D.5 EXCAVATED MATERIAL BERM AND LEVEE ANALYSIS In some areas the EMBs will be subject to differential head conditions for the most significant diversion discharges. It has been determined that for the right bank of the diversion channel the EMBs will in some capacity act as levees. The levees will be designed in accordance with the parameters provided in MFR 001, Levees and Excavated Material Berms along the Diversion (5). The MFR outlines slopes for the levee prism, material and compaction requirements and also covers the Vegetation Free Zone and Vegetation Management Zone requirements needed for the levees and EMBs. The levee prism will be completely encapsulated by the larger EMB for the Lower Rush Reach. There is no need for an embedded levee in the left bank EMB. Analyses were conducted to determine the maximum grading extents of the EMBS based on the current design concepts and restrictions. The crown of the EMB must not extend more than 21 feet above existing grade at the time of construction because of viewshed height limitation requirements. In order to accommodate the 2% crown slope, the initial EMB height is less than the EMB crown height. A simple EMB and different configurations of stepped EMBs, with varied stepped height, width and offset, were analyzed in order to establish a design envelope that the civil layout could fall within and still be stable. The results indicate that for both Sections 8 and 8a, the simple would be the most practical and efficient design. The maximum EMB height and width was then determined for the civil layout to be completed. Once the civil layout of the EMB was determined, verification analyses were performed to assure that the section meets stability requirements. Based on the results, the EMB initial height should be limited to 16 feet with a maximum EMB height of 20 feet and width of 400 feet for both Sections 8 and 8a. A summary of the maximum grading extents is below in Table D2 7. The diversion channel stability plates in Attachment D2 4 show the simple EMB Configuration. The results of the maximum EMB grading extents based solely on the geotechnical slope stability concerns are summarized below in Table D2 7. The heights indicated are based on a generalized existing ground surface elevation. If the existing ground surface is higher than the assumed ground surface, then the elevations of the maximum grading extents need to control the layout. The geotechnical analysis was conducted using the left side of the diversion channel centerline. The stratigraphy has been assumed to be symmetrical along the centerline, so the results of the maximum grading extents of the left EMB can be applied to the right EMB. This is of importance when the DDR_FMM_R5_Appendix_D2_Post_FTR_ docx Page D2 15 of D2 27

21 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology undulations are being designed for the right bank recreational plan. The undulations shall be designed such that the undulation grading does not exceed the maximum grading extents. Table D2 7: Summary of EMB Maximum Grading Extents Left Bank EMB Maximum Grading Extents based only on Geotechnical Engineering Considerations (2) Existing Ground EMB Width Configuration EMB Height Section Location Section Extents (1) (ELEV) (ft) (ELEV) (ft) Simple a Simple Notes: (1) Simple EMB without a step and top crowned at 2% (2) All stability analyses completed for left bank EMB. The maximum grading extents for the right bank EMB will be the same. Elevation (FT) Fargo Moorhead Metro Project Geotechnical EMB Maxium Gradients Extents Sections 8 and 8a EMB Crown: 2% EMB Slope 1V:6H EMB Width = 400 ft EMB Height = 20 EMB Slope 1V:7H Case 2 Simplified EMB Stationing Figure D2 6 : EMB Grading Extents DDR_FMM_R5_Appendix_D2_Post_FTR_ docx Page D2 16 of D2 27

22 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology D.6 RIGHT BANK EMEDDED LEVEES As previously mentioned, an embedded levee will be required within the right bank for flood risk reduction reasons. There is no need for a levee on the left bank. The requirements for the right bank embedded levee are summarized below. Additional details concerning the levees and EMBs can be found in MFR 001, Levees and Excavated Material Berms along the Diversion (5). Crest Elevation The crest elevation will be the estimated maximum flood fight flow profile plus overbuild to account for estimated settlement Typical Section The typical cross section will be the St. Paul District typical section for levees within the Red River Valley which has a 10ft top width and a 1V:3H side slopes Construction Requirements The construction requirements are: o o o o o Stripping: All organic materials beneath the footprint of the levee shall be removed. Inspection Trench: An inspection trench will not be required because the diversion channel will act as a large inspection trench. If any pervious layers are encountered during excavation, an analysis should be completed to determine if a cut off trench will be needed Utilities and Drain Tile: If utilities and drain tile are encountered within the diversion channel excavation or they are known to be beneath the footprint of the levee, at a minimum, the utilities and drain tile shall be removed from beneath the footprint of the levee and extending out 15 feet from both toes of the levee. The exception would be utilities relocated as part of this project in compliance with MFR 010, Utility Relocation Requirements (Reference D2 4). Fill Material: Alluvium or Sherack materials shall be used as fill material. These formations will be located in the upper portion of the diversion channel excavation. These materials are identified in the specifications as those with a liquid limit of less than or equal to 90 (LL 90). Placement: The materials shall be placed in lifts of 12 inches or less. o Compaction: The fill material will be required to be compacted to a minimum 90 percent of maximum dry densisty as determined by the standard proctor. o o Moisture Control: Moisture control will not be specified but this will not relieve the contractor from obtaining the required compaction. Testing: Minimum testing will be completed on materials placed. Testing will include proctors, density, Atterberg limits, and grain size analysis. DDR_FMM_R5_Appendix_D2_Post_FTR_ docx Page D2 17 of D2 27

23 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology D.7 SETTLEMENT AND REBOUND The large scale excavation and placement of soil introduces the potential for significant soil rebound and settlement, respectively. Since the final grade is important for many project features, including the drainage structures, embedded levees, and the low flow invert, rebound and settlement need to be analyzed in order to plan potential mitigation measures. Settlement and rebound calculations are presented in Attachment D 2 5 and explained in this section. Calculations were not updated from the 65% DDR Submittal for the Lower Rush Diversion channel. The parameters chosen and profile assumed in this report were verified by additional borings completed in Formation contact elevations generally varied by less than one foot with all original assumptions being more conservative than those determined by additional exploration. The largest variation was in the contact of the Oxidized Brenna and Brenna formation at Section 8a, which was interpreted to be from 2010 borings and interpreted to be from 2013 boring. This variation was determined to be insignificant in the overall settlement and rebound findings. D.7.1 Consolidation Parameters Soil parameters used for settlement and rebound calculations were taken from consolidation tests performed throughout the Fargo Moorhead metro area for several USACE projects. In situ effective vertical stresses were estimated based on the stratigraphy indicated in the adjacent machine boring and assuming a groundwater table 10 ft below ground surface when no other groundwater data was available. Preconsolidation pressures were determined both by the laboratory and by the Casagrande approach. Generally there was good agreement between laboratory determined values and Corps determined values. The glacial till was assumed to be incompressible for the purposes of estimating settlement. The consolidation parameters selected for the settlement and rebound analyses represent the mean or expected value parameters based on the available data. The mean consolidation parameters are shown below in Table D2 8. Table D2 8: Mean Consolidation Parameters Formation sat (pcf) ' OCR C r C c e o C er C ec Alluvium Sherack OX Brenna Brenna Argusville D.7.2 Settlement of typical levee/ Right Bank EMB Settlement of the right bank EMB was estimated in order to approximate the amount of required overbuild for encapsulated levees in order to maintain the maximum flood fight flow profile of the levee. The final grade of the EMBs is not a concern since overbuild will be applied directly to the encapsulated levee section. The levee and right bank EMB were assumed to be practically DDR_FMM_R5_Appendix_D2_Post_FTR_ docx Page D2 18 of D2 27

24 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology incompressible for the purposes of analysis. An analysis considering an infinite surcharge equivalent to the maximum allowable EMB height of 20 ft of compacted clay fill and the mean consolidation parameters resulted in a settlement of roughly 17 inches. This value would decrease somewhat by accounting for the finite nature of the loading. Also, the stripping of the upper several feet of topsoil and replacement with compacted levee fill would further reduce this estimate. Check analyses using the settlement program CSETT and the same consolidation parameters were conducted using both infinite and finite loading for Section 8. The resulting settlement values were in agreement with the results calculated using the spreadsheet developed by MVP. Considering overbuild required throughout the entire Reach 5 extents, recommended overbuild for the right bank levee is 1.5 feet. Settlement analyses results are located in Attachment D2 5. Table D2 9: Settlement Check Analysis Results Sta Section 8 EMB Settlement Material δ CSETT infinite (ft) δ CSETT finite (ft) δ EXCEL (ft) Alluvium Sherack Ox Brenna Brenna Argusville Total (ft) Total (in) D.7.3 Table D2 10: Predicted EMB Settlement for Determination of Levee Overbuild EMB Settlement for Determination of Levee Overbuild Section 8 8a EMB Height (ft) Depth of Compressible Material (ft) Predicted Settlement (ft) Rebound in the Channel Excavation The net change in grade resulting from excavation for the diversion channel the will result in rebound. Analysis considering infinite excavation to the level of the diversion channel invert calculated this rebound to be roughly 15 inches. DDR_FMM_R5_Appendix_D2_Post_FTR_ docx Page D2 19 of D2 27

25 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology Table D2 11: Predicted Ultimate Rebound in Diversion Channel Rebound at Diversion Invert Section 8 8a Excavation Depth (ft) Depth of Compressible Material beneath Excavation (ft) Predicted Ultimate Rebound (ft) Additional details on time rate of rebound calculations can be found in the General Report: Geotechnical Engineering and Geology (Reference D2 1). Over excavation of the diversion channel to account for rebound is not recommended based on geotechnical and hydraulic analyses it is anticipated that hydraulic capacity will be sufficient even if rebound occurs. If and when changes in grade due to sedimentation and/or rebound become a hydraulic issue, cleanout will be required in order to maintain the necessary flow capacity. MVP will monitor rebound in Reach 1 and determine if adjustments should be made prior to construction of subsequent reaches, including Reach 5. D.8 DIVERSION EXCAVATION TYPES The construction of the diversion channel will require excavation through different materials. The type of equipment used, production rates, and excavation costs will depend on the characteristics of these different material. In order to complete a comprehensive cost estimate, the diversion channel excavation was broken into five different excavation types. A profile was developed along the Reach 5 alignment discerning the five different excavation types in order to estimate quantities. A summary of the excavation types is below in Table D2 12. For diversion excavation types 1 and 2, the groundwater table was based on water level readings in the boring logs or the bottom of the local drainage features and was generally 5 to 7.5 feet below the ground surface. This assumption is different from that which is used in the seepage and stability analysis. Table D2 12: Summary of Diversion Channel Excavation Types DDR_FMM_R5_Appendix_D2_Post_FTR_ docx Page D2 20 of D2 27

26 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology D.9 LOCAL DRAINAGE INLETS The local drainage plan does not call for any drainage inlets at the location of the Lower Rush River Drop/Inlet structure. D.10 RIPRAP AND BEDDING Riprap will be required at several locations where the Lower Rush River meets the Diversion Channel. Riprap gradation R30 and R270 will be used. Further details on the Riprap sizing, gradations, and locations can be found in Appendix C. D.11 CONSTRUCTABILITY D.11.1 Excavations This section discusses several considerations with regards to the constructability of the proposed excavations. D Past Experience MVP has experience with excavations in the Fargo Moorhead area as a result of the Horace to West Fargo and West Fargo Diversion Channels (HWF Diversions) and frequent flood fighting efforts that have required use of borrow material. The HWF Diversions were on the order of 10 feet deep, placing the bottom of the excavation in the Sherack formation or just into the Brenna formation. The side slopes of these channels where excavated at 1V:7H using scrapers. No constructability issues sloughing of the excavated slopes or seepage into the excavation were encountered in the tight clay materials. During flood fights, a substantial amount of borrow is needed to construct emergency levees. The fill is obtained from local borrow pits and have been excavated with very steep to nearly vertical faces with depths ranging from 10 to 20 feet. These steep faces typically show little to no sloughing failures during the time they remain open, which could be up to a couple months. Also, seepage is not a concern as very little water seepages into the excavation. D Methods MVP recognized that the soils change with depth; the materials will become wetter and weaker with depth. Due to the changing nature of the soils with depth, it is anticipated that different excavation techniques will be employed as the excavation increases in depth. Specifically, the stronger upper soils (Alluvium, Sherack) will likely be excavated with a scraper as was the case for the HWF Diversions. As the excavation penetrates into the Brenna Formation the soils may have a reduced capacity to support construction equipment. Therefore, it is likely an excavator will be used and material loaded into offroad haul trucks to transport the excavated materials. DDR_FMM_R5_Appendix_D2_Post_FTR_ docx Page D2 21 of D2 27

27 Project and Reach 5 Appendix D2: Geotechnical Engineering and Geology D Stripping and Overexcavation It is anticipated that 1 to 2 feet of topsoil will need to be stripped from the footprint of the project based on the results of the top soil survey. However, localized variations could be encountered along the alignment. This layer should be readily distinguishable as it will be black and contain organics. Topsoil should be stripped from the diversion footprint and stockpiled as needed for placement during final grading. This layer should be readily distinguishable as it will be black and contain organics. It is anticipated that soft surface soils will be encountered at several locations along the alignment and will require special treatment beneath fill areas (EMBs, levees, and other embankments). Slopes of 1V:4H or steeper need to be stepped prior to subgrade preparation. D Dewatering Dewatering prior to the start of excavation will not be required due to the impervious nature of the soils, and the flow of water into the excavation will be minimal. The diversion channel will need to be excavated with a slope such that any precipitation that occurs will runoff towards a low area. If a large amount of precipitation occurs, the contractor may be required to pump this water out of the excavation. D Sand Pockets / Lenses There is the possibility of encountering sand pockets or lenses. If sand pockets or lenses are encountered during excavation and have a perched water table, there could be a large quantity of flow into the excavation. If dewater efforts could not keep up with the flow, an impervious cutoff trench could be constructed adjacent to the diversion channel to reduce flow into the excavation. D.11.2 Access/Maintenance Road Foundations Access and maintenance roads along the project will require adequate foundations in order to minimize surface degradation and associated maintenance over the project lifespan. Aggregate base course will require a minimum 8 thickness, and will be placed atop a separation geotextile. The subgrade shall consist of 3 ft of impervious fill placed in lifts no greater than 9 thick and compacted to 95% of standard proctor with a moisture content between plus 3% and minus 2% of optimum. This design is similar to the standard design used by Cass County. Additionally, calculations following the Giroud and Han design method for unpaved roads (Reference D2 6) were completed as part of the Reach 1 design. The results of the calculations indicate that strong subgrade (undrained shear strength of 1500 psf), geotextile separation fabric, and 9 inches of gravel was needed to support a minimal number of passes (500) of heavy construction traffic (~12,600 lb wheel load). This supports the need to compact the 3 feet of subgrade beneath the aggregate surfacing. D.11.3 Embankment Construction Construction of embankments in the Red River Valley can pose to be problematic due to the weak foundation conditions. Placement of materials along the banks of existing rivers can reactivate existing slides or initiate a new slope failure. Rapid placement of material for embankments can also lead to DDR_FMM_R5_Appendix_D2_Post_FTR_ docx Page D2 22 of D2 27

Attachment D-7: Rebound and Uplift of the Stilling Basin, Deep Soil Mixing Design

Attachment D-7: Rebound and Uplift of the Stilling Basin, Deep Soil Mixing Design Attachment D-7: Rebound and Uplift of the Stilling Basin, Deep Soil Mixing Design Attachment D-7: Rebound and Uplift of the Stilling Basin, Deep Soil Mixing Design Fargo Moorhead Metropolitan Area Flood

More information

3.12 Geology and Topography Affected Environment

3.12 Geology and Topography Affected Environment 3 Affected Environment and Environmental Consequences 3.12 Geology and Topography 3.12.1 Affected Environment 3.12.1.1 Earthquakes Sterling Highway MP 45 60 Project Draft SEIS The Kenai Peninsula is predisposed

More information

Geotechnical Properties of Soil

Geotechnical Properties of Soil Geotechnical Properties of Soil 1 Soil Texture Particle size, shape and size distribution Coarse-textured (Gravel, Sand) Fine-textured (Silt, Clay) Visibility by the naked eye (0.05 mm is the approximate

More information

H.1 SUMMARY OF SUBSURFACE STRATIGRAPHY AND MATERIAL PROPERTIES (DATA PACKAGE)

H.1 SUMMARY OF SUBSURFACE STRATIGRAPHY AND MATERIAL PROPERTIES (DATA PACKAGE) DRAFT ONONDAGA LAKE CAPPING AND DREDGE AREA AND DEPTH INITIAL DESIGN SUBMITTAL H.1 SUMMARY OF SUBSURFACE STRATIGRAPHY AND MATERIAL PROPERTIES (DATA PACKAGE) Parsons P:\Honeywell -SYR\444576 2008 Capping\09

More information

3.18 GEOLOGY AND SOILS

3.18 GEOLOGY AND SOILS 3.18 GEOLOGY AND SOILS This section discusses geologic resource concerns as they relate to the environment, public safety, and project design both during construction and after completion of the project.

More information

Stone Outlet Sediment Trap

Stone Outlet Sediment Trap 3.12 Sediment Control Description: A stone outlet sediment trap is a small detention area formed by placing a stone embankment with an integral stone filter outlet across a drainage swale for the purpose

More information

APPENDIX B WORKSHEETS & EXHIBITS

APPENDIX B WORKSHEETS & EXHIBITS APPENDIX B WORKSHEETS & EXHIBITS A worksheet provides the designer a representation of a measure that allows for input of specific design criteria. The plan designer will be required to assess field conditions

More information

June 9, R. D. Cook, P.Eng. Soils Engineer Special Services Western Region PUBLIC WORKS CANADA WESTERN REGION REPORT ON

June 9, R. D. Cook, P.Eng. Soils Engineer Special Services Western Region PUBLIC WORKS CANADA WESTERN REGION REPORT ON PUBLIC WORKS CANADA WESTERN REGION REPORT ON GEOTECHNICAL INVESTIGATION PROPOSED MARTIN RIVER BRIDGE MILE 306.7 MACKENZIE HIGHWAY Submitted by : R. D. Cook, P.Eng. Soils Engineer Special Services Western

More information

10. GEOTECHNICAL EXPLORATION PROGRAM

10. GEOTECHNICAL EXPLORATION PROGRAM Geotechnical site investigations should be conducted in multiple phases to obtain data for use during the planning and design of the tunnel system. Geotechnical investigations typically are performed in

More information

R-1 Conveyor Relocation Project Legend 0 500 1000 1500 ft. This map is a user generated static output from an Internet mapping site and is for general reference only. Data layers that appear on this map

More information

QUESTION BANK DEPARTMENT: CIVIL SUBJECT CODE / Name: CE 2251 / SOIL MECHANICS SEMESTER: IV UNIT 1- INTRODUCTION PART - A (2 marks) 1. Distinguish between Residual and Transported soil. (AUC May/June 2012)

More information

Slope Stability Evaluation Ground Anchor Construction Area White Point Landslide San Pedro District Los Angeles, California.

Slope Stability Evaluation Ground Anchor Construction Area White Point Landslide San Pedro District Los Angeles, California. Slope Stability Evaluation Ground Anchor Construction Area White Point Landslide San Pedro District Los Angeles, California Submitted To: Mr. Gene Edwards City of Los Angeles Department of Public Works

More information

DRAFT ONONDAGA LAKE CAPPING AND DREDGE AREA AND DEPTH INITIAL DESIGN SUBMITTAL H.4 SEISMIC SLOPE STABILITY ANALYSES

DRAFT ONONDAGA LAKE CAPPING AND DREDGE AREA AND DEPTH INITIAL DESIGN SUBMITTAL H.4 SEISMIC SLOPE STABILITY ANALYSES DRAFT ONONDAGA LAKE CAPPING AND DREDGE AREA AND DEPTH INITIAL DESIGN SUBMITTAL H.4 SEISMIC SLOPE STABILITY ANALYSES Parsons P:\Honeywell -SYR\444576 2008 Capping\09 Reports\9.3 December 2009_Capping and

More information

Table of Contents Chapter 1 Introduction to Geotechnical Engineering 1.1 Geotechnical Engineering 1.2 The Unique Nature of Soil and Rock Materials

Table of Contents Chapter 1 Introduction to Geotechnical Engineering 1.1 Geotechnical Engineering 1.2 The Unique Nature of Soil and Rock Materials Table of Contents Chapter 1 Introduction to Geotechnical Engineering 1.1 Geotechnical Engineering 1.2 The Unique Nature of Soil and Rock Materials 1.3 Scope of This Book 1.4 Historical Development of Geotechnical

More information

Geosynthetics Applications and Performance Reviews Select Case Histories

Geosynthetics Applications and Performance Reviews Select Case Histories Geosynthetics Applications and Performance Reviews Select Case Histories Debora J. Miller, Ph.D., P.E.; Dean B. Durkee,, Ph.D., P.E.; Michael A. Morrison, P.E., David B. Wilson, P.E., and Kevin Smith,

More information

THE MINISTRY OF ENERGY AND ENERGY INDUSTRIES MINERALS DIVISION MINE DESIGN TEMPLATE OPERATOR NAME: OPERATOR ADDRESS: PHONE NUMBER: FACSIMILE:

THE MINISTRY OF ENERGY AND ENERGY INDUSTRIES MINERALS DIVISION MINE DESIGN TEMPLATE OPERATOR NAME: OPERATOR ADDRESS: PHONE NUMBER: FACSIMILE: THE MINISTRY OF ENERGY AND ENERGY INDUSTRIES MINERALS DIVISION MINE DESIGN TEMPLATE 1.0 GENERAL INFORMATION OPERATOR NAME: OPERATOR ADDRESS: PHONE NUMBER: FACSIMILE: NAME OF CONTACT: CELLULAR PHONE: EMAIL

More information

B805 TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES - OPSS 805

B805 TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES - OPSS 805 B805 MEASURES - OPSS 805 805.1 GENERAL Construction activities frequently remove protective cover and expose soil to accelerated rates of erosion. Sediments generated thereby can be conveyed via runoff

More information

UPPER MISSISSIPPI RIVER RESTORATION FEASIBILITY REPORT WITH INTEGRATED ENVIRONMENTAL ASSESSMENT

UPPER MISSISSIPPI RIVER RESTORATION FEASIBILITY REPORT WITH INTEGRATED ENVIRONMENTAL ASSESSMENT UPPER MISSISSIPPI RIVER RESTORATION FEASIBILITY REPORT WITH INTEGRATED ENVIRONMENTAL ASSESSMENT BEAVER ISLAND HABITAT REHABILITATION AND ENHANCEMENT PROJECT POOL 14, UPPER MISSISSIPPI RIVER MILES 513.0-517.0

More information

CCR Rule Annual Inspection Report (cont.) 2

CCR Rule Annual Inspection Report (cont.) 2 The inspection findings consisted of maintenance items and items that were not observed to be signs or potential signs of significant structural weakness. No deficiencies or disrupting conditions that

More information

Instructor : Dr. Jehad Hamad. Chapter (7)

Instructor : Dr. Jehad Hamad. Chapter (7) Instructor : Dr. Jehad Hamad Chapter (7) 2017-2016 Soil Properties Physical Properties Mechanical Properties Gradation and Structure Compressibility Soil-Water Relationships Shear Strength Bearing Capacity

More information

PRINCIPLES OF GEOTECHNICAL ENGINEERING

PRINCIPLES OF GEOTECHNICAL ENGINEERING PRINCIPLES OF GEOTECHNICAL ENGINEERING Fourth Edition BRAJA M. DAS California State University, Sacramento I(T)P Boston Albany Bonn Cincinnati London Madrid Melbourne Mexico City New York Paris San Francisco

More information

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area.

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area. Sediment Trench SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils [1] Performance of

More information

(C) Global Journal of Engineering Science and Research Management

(C) Global Journal of Engineering Science and Research Management GEOTECHNCIAL ASSESSMENT OF PART OF PORT HARCOURT, NIGER DELTA FOR STRUCTURAL ANALYSIS Warmate Tamunonengiyeofori Geostrat International Services Limited, www.geostratinternational.com. *Correspondence

More information

DATA REPORT GEOTECHNICAL INVESTIGATION GALVESTON CRUISE TERMINAL 2 GALVESTON, TEXAS

DATA REPORT GEOTECHNICAL INVESTIGATION GALVESTON CRUISE TERMINAL 2 GALVESTON, TEXAS DATA REPORT GEOTECHNICAL INVESTIGATION GALVESTON CRUISE TERMINAL 2 GALVESTON, TEXAS SUBMITTED TO PORT OF GALVESTON 123 ROSENBERG AVENUE, 8TH FLOOR GALVESTON, TEXAS 77553 BY HVJ ASSOCIATES, INC. HOUSTON,

More information

R.M.HARW & ASSOCIATES LTD. GEOTECHNICAL INVESTIGATION PROPOSED BRIDGE SITE. HELAVA CREEKl MILE MACKENZIE HIGHWAY E-2510 OCTOBER 16, 1973

R.M.HARW & ASSOCIATES LTD. GEOTECHNICAL INVESTIGATION PROPOSED BRIDGE SITE. HELAVA CREEKl MILE MACKENZIE HIGHWAY E-2510 OCTOBER 16, 1973 El R.M.HARW & ASSOCIATES LTD. GEOTECHNICAL INVESTIGATION PROPOSED BRIDGE SITE HELAVA CREEKl MILE 616.4 MACKENZIE HIGHWAY E-2510 OCTOBER 16, 1973 R,M,HARDV & ASSOCIATES LTD. CONSULTING ENGINEERING & TESTING

More information

STRUCTURAL STABILITY ASSESSMENT

STRUCTURAL STABILITY ASSESSMENT STRUCTURAL STABILITY ASSESSMENT CFR 257.73(d) Bottom Ash Pond Complex Cardinal Plant Brilliant, Ohio October, 2016 Prepared for: Cardinal Operating Company Cardinal Plant Brilliant, Ohio Prepared by: Geotechnical

More information

Summary of Hydraulic and Sediment-transport. Analysis of Residual Sediment: Alternatives for the San Clemente Dam Removal/Retrofit Project,

Summary of Hydraulic and Sediment-transport. Analysis of Residual Sediment: Alternatives for the San Clemente Dam Removal/Retrofit Project, Appendix N SUMMARY OF HYDRAULIC AND SEDIMENT-TRANSPORT ANALYSIS OF RESIDUAL SEDIMENT: ALTERNATIVES FOR THE SAN CLEMENTE DAM REMOVAL/RETROFIT PROJECT, CALIFORNIA the San Clemente Dam Removal/Retrofit Project,

More information

Class Principles of Foundation Engineering CEE430/530

Class Principles of Foundation Engineering CEE430/530 Class Principles of Foundation Engineering CEE430/530 1-1 General Information Lecturer: Scott A. Barnhill, P.E. Lecture Time: Thursday, 7:10 pm to 9:50 pm Classroom: Kaufmann, Room 224 Office Hour: I have

More information

ATTACHMENT A PRELIMINARY GEOTECHNICAL SUMMARY

ATTACHMENT A PRELIMINARY GEOTECHNICAL SUMMARY ATTACHMENT A PRELIMINARY GEOTECHNICAL SUMMARY Kevin M. Martin, P.E. KMM Geotechnical Consultants, LLC 7 Marshall Road Hampstead, NH 0384 603-489-6 (p)/ 603-489-8 (f)/78-78-4084(m) kevinmartinpe@aol.com

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS G. GEOLOGY AND SOILS

IV. ENVIRONMENTAL IMPACT ANALYSIS G. GEOLOGY AND SOILS IV. ENVIRONMENTAL IMPACT ANALYSIS G. GEOLOGY AND SOILS The following section is a summary of the geotechnical report conducted for the proposed project. The Report of Geotechnical Investigation Proposed

More information

SLOPE STABILITY EVALUATION AND ACCEPTANCE STANDARDS

SLOPE STABILITY EVALUATION AND ACCEPTANCE STANDARDS INFORMATION BULLETIN / PUBLIC - BUILDING CODE REFERENCE NO.: LABC 7006.3, 7014.1 Effective: 01-01-2017 DOCUMENT NO.: P/BC 2017-049 Revised: 12-21-2016 Previously Issued As: P/BC 2014-049 SLOPE STABILITY

More information

Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services

Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services Ms. Rebecca Mitchell Mt. San Antonio College Facilities Planning & Management 1100 North

More information

Soils. Technical English - I 10 th week

Soils. Technical English - I 10 th week Technical English - I 10 th week Soils Soil Mechanics is defined as the branch of engineering science which enables an engineer to know theoretically or experimentally the behavior of soil under the action

More information

Appendix I Geotechnical Design and Geology

Appendix I Geotechnical Design and Geology Appendix I Fargo-Moorhead Metropolitan Area Flood Risk Management Final Feasibility Report and Environmental Impact Statement Prepared by: U.S. Army Corps of Engineers St. Paul District 180 Fifth Street

More information

Chapter (12) Instructor : Dr. Jehad Hamad

Chapter (12) Instructor : Dr. Jehad Hamad Chapter (12) Instructor : Dr. Jehad Hamad 2017-2016 Chapter Outlines Shear strength in soils Direct shear test Unconfined Compression Test Tri-axial Test Shear Strength The strength of a material is the

More information

Materials. Use materials meeting the following.

Materials. Use materials meeting the following. 208.01 Section 208. SOIL EROSION AND SEDIMENTATION CONTROL 208.01 Description. Install and maintain erosion and sedimentation controls to minimize soil erosion and to control sedimentation from affecting

More information

Landslide FE Stability Analysis

Landslide FE Stability Analysis Landslide FE Stability Analysis L. Kellezi Dept. of Geotechnical Engineering, GEO-Danish Geotechnical Institute, Denmark S. Allkja Altea & Geostudio 2000, Albania P. B. Hansen Dept. of Geotechnical Engineering,

More information

How & Where does infiltration work? Summary of Geologic History Constraints/benefits for different geologic units

How & Where does infiltration work? Summary of Geologic History Constraints/benefits for different geologic units June 26, 2007: Low Impact Development 1 Associated Earth Sciences, Inc. Associated Earth Sciences, Inc. Presented by: Matthew A. Miller, PE April 24, 2012 How & Where does infiltration work? Summary of

More information

SLOPE STABILITY EVALUATION AND ACCEPTANCE STANDARDS

SLOPE STABILITY EVALUATION AND ACCEPTANCE STANDARDS INFORMATION BULLETIN / PUBLIC - BUILDING CODE REFERENCE NO.: LAMC 98.0508 Effective: 1-26-84 DOCUMENT NO. P/BC 2002-049 Revised: 11-1-02 Previously Issued As: RGA #1-84 SLOPE STABILITY EVALUATION AND ACCEPTANCE

More information

LIQUEFACTION OF EARTH EMBANKMENT DAMS TWO CASE HISTORIES: (1) LIQUEFACTION OF THE EMBANKMENT SOILS, AND (2) LIQUEFACTION OF THE FOUNDATIONS SOILS

LIQUEFACTION OF EARTH EMBANKMENT DAMS TWO CASE HISTORIES: (1) LIQUEFACTION OF THE EMBANKMENT SOILS, AND (2) LIQUEFACTION OF THE FOUNDATIONS SOILS LIQUEFACTION OF EARTH EMBANKMENT DAMS TWO CASE HISTORIES: (1) LIQUEFACTION OF THE EMBANKMENT SOILS, AND (2) LIQUEFACTION OF THE FOUNDATIONS SOILS Antonio Fernandez, Ph.D. 1 ABSTRACT Paul C. Rizzo Associates,

More information

CHAPTER GEOLOGICALLY HAZARDOUS AREAS Applicability Regulations.

CHAPTER GEOLOGICALLY HAZARDOUS AREAS Applicability Regulations. CHAPTER 19.07 GEOLOGICALLY HAZARDOUS AREAS 19.07.010 Applicability. Geologically hazardous areas may pose a threat to the health and safety of citizens when incompatible development is sited in areas of

More information

RESERVOIR DRAWDOWN RATES/RESERVOIR DRAWDOWN TEST Iron Gate, Copco (I & II), and JC Boyle Dams

RESERVOIR DRAWDOWN RATES/RESERVOIR DRAWDOWN TEST Iron Gate, Copco (I & II), and JC Boyle Dams TECHNICAL MEMORANDUM No. 1 TO: Michael Bowen California Coastal Conservancy Geotechnical & Earthquake Engineering Consultants CC: Eric Ginney Philip Williams & Associates PREPARED BY: Paul Grant SUBJECT:

More information

Pierce County Department of Planning and Land Services Development Engineering Section

Pierce County Department of Planning and Land Services Development Engineering Section Page 1 of 7 Pierce County Department of Planning and Land Services Development Engineering Section PROJECT NAME: DATE: APPLICATION NO.: PCDE NO.: LANDSLIDE HAZARD AREA (LHA) GEOLOGICAL ASSESSMENT REPORT

More information

This report was prepared by Klohn Crippen Consultants Ltd. for Alberta Transportation Central Region under Contract No. CE053/2000.

This report was prepared by Klohn Crippen Consultants Ltd. for Alberta Transportation Central Region under Contract No. CE053/2000. Alberta Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 June 7, 2002 Mr. Melvin Mayfield, P.Eng. Project Engineer Dear Mr. Mayfield: Central Region Landslide Assessment Site

More information

VALLIAMMAI ENGINEERING COLLEGE

VALLIAMMAI ENGINEERING COLLEGE VALLIAMMAI ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING SUBJECT CODE : CE6405 YEAR : II SUBJECT NAME : SOIL MECHANICS SEM : IV QUESTION BANK (As per Anna University 2013 regulation) UNIT 1- SOIL

More information

FUNDAMENTALS SOIL MECHANICS. Isao Ishibashi Hemanta Hazarika. >C\ CRC Press J Taylor & Francis Group. Taylor & Francis Group, an Informa business

FUNDAMENTALS SOIL MECHANICS. Isao Ishibashi Hemanta Hazarika. >C\ CRC Press J Taylor & Francis Group. Taylor & Francis Group, an Informa business SOIL MECHANICS FUNDAMENTALS Isao Ishibashi Hemanta Hazarika >C\ CRC Press J Taylor & Francis Group Boca Raton London New York CRC Press is an imprint of the Taylor & Francis Group, an Informa business

More information

Introduction to Soil Mechanics

Introduction to Soil Mechanics Introduction to Soil Mechanics Sela Sode and Colin Jones WILEY Blackwell Contents Preface Dedication and Acknowledgments List of Symbols Soil Structure 1.1 Volume relationships 1.1.1 Voids ratio (e) 1.1.2

More information

September 7, 2017 (Revised November 1, 2017)

September 7, 2017 (Revised November 1, 2017) September 7, 2017 (Revised November 1, 2017) Project No. 10113.002 Environmental Advisors 2400 East Katella Avenue, Suite 800 Anaheim, California 92806 Attention: Subject: Mr. Greg McCafferty Response

More information

Principles of Foundation Engineering 8th Edition Das SOLUTIONS MANUAL

Principles of Foundation Engineering 8th Edition Das SOLUTIONS MANUAL Principles of Foundation Engineering 8th Edition SOLUTIONS MANUAL Full clear download (no formatting errors) at: https://testbankreal.com/download/principles-foundation-engineering- 8th-edition-das-solutions-manual/

More information

ISSUED FOR CONSTRUCTION

ISSUED FOR CONSTRUCTION PAGE No. DESCRIPTION 1 Cover Page 2 Overview Map 3 Western Road Plan View 4 Eastern Road Plan View West Road Profiles & Cross Sections 6-7 East Road Profiles 8- East Road Cross Sections 11-14 Campsite

More information

APPENDIX F CORRELATION EQUATIONS. F 1 In-Situ Tests

APPENDIX F CORRELATION EQUATIONS. F 1 In-Situ Tests APPENDIX F 1 APPENDIX F CORRELATION EQUATIONS F 1 In-Situ Tests 1. SPT (1) Sand (Hatanaka and Uchida, 1996), = effective vertical stress = effective friction angle = atmosphere pressure (Shmertmann, 1975)

More information

Rock & Aggregate Drop Inlet Protection

Rock & Aggregate Drop Inlet Protection Rock & Aggregate Drop Inlet Protection SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System Supplementary Trap Dispersive Soils

More information

Numerical analysis of effect of mitigation measures on seismic performance of a liquefiable tailings dam foundation

Numerical analysis of effect of mitigation measures on seismic performance of a liquefiable tailings dam foundation Numerical analysis of effect of mitigation measures on seismic performance of a liquefiable tailings dam foundation Yong-Beom Lee, Jorge Castillo Ausenco, USA Aurelian C. Trandafir Fugro GeoConsulting

More information

Preliminary Geotechnical Evaluation Gooseberry Point Pedestrian Improvements Whatcom County, Washington SITE AND PROJECT DESCRIPTION

Preliminary Geotechnical Evaluation Gooseberry Point Pedestrian Improvements Whatcom County, Washington SITE AND PROJECT DESCRIPTION File No. 12-100 Geotechnical & Earthquake Engineering Consultants Mr. Kevin Brown, P.E. Gray & Osborne, Inc. 3710 168 th Street NE, Suite B210 Arlington, Washington 98223 Subject: Draft Report Preliminary

More information

CEMEX Eliot Quarry. Lake A Evaluation Report. Alameda County, California

CEMEX Eliot Quarry. Lake A Evaluation Report. Alameda County, California May 7, 2015 May 7, 2015 Project No. GT13-16 Prepared for: CEMEX 5180 Golden Foothills, Parkway El Dorado Hills, California 95762 7400 Shoreline Drive, Ste. 6 Stockton, California 95219 Tel: 209-472-1822

More information

ADVANCED SOIL MECHANICS FINAL EXAM (TAKE HOME):DUE THURSDAY, DECEMBER 19, 6PM.

ADVANCED SOIL MECHANICS FINAL EXAM (TAKE HOME):DUE THURSDAY, DECEMBER 19, 6PM. 14.531 ADVANCED SOIL MECHANICS FINAL EXAM (TAKE HOME):DUE THURSDAY, DECEMBER 19, 2013 @ 6PM. Problem #1. Field load tests on strip footings yielded the test data provided below in Figure 1 and Table 1

More information

*** ***! " " ) * % )!( & ' % # $. 0 1 %./ +, - 7 : %8% 9 ) 7 / ( * 7 : %8% 9 < ;14. " > /' ;-,=. / ١

*** ***!   ) * % )!( & ' % # $. 0 1 %./ +, - 7 : %8% 9 ) 7 / ( * 7 : %8% 9 < ;14.  > /' ;-,=. / ١ ١ ******!" #$ % & '!( ) % * ") +,-./ % 01. 3 ( 4 56 7/4 ) 8%9 % : 7 ;14 < 8%9 % : *7./ = ;-, >/'." Soil Permeability & Seepage ٢ Soil Permeability- Definition ٣ What is Permeability? Permeability is the

More information

Date: April 2, 2014 Project No.: Prepared For: Mr. Adam Kates CLASSIC COMMUNITIES 1068 E. Meadow Circle Palo Alto, California 94303

Date: April 2, 2014 Project No.: Prepared For: Mr. Adam Kates CLASSIC COMMUNITIES 1068 E. Meadow Circle Palo Alto, California 94303 City of Newark - 36120 Ruschin Drive Project Draft Initial Study/Mitigated Negative Declaration Appendix C: Geologic Information FirstCarbon Solutions H:\Client (PN-JN)\4554\45540001\ISMND\45540001 36120

More information

HURRICANE SANDY LIMITED REEVALUATION REPORT UNION BEACH, NEW JERSEY DRAFT ENGINEERING APPENDIX SUB APPENDIX A PRELIMINARY FLOODWALL DESIGN

HURRICANE SANDY LIMITED REEVALUATION REPORT UNION BEACH, NEW JERSEY DRAFT ENGINEERING APPENDIX SUB APPENDIX A PRELIMINARY FLOODWALL DESIGN HURRICANE SANDY LIMITED REEVALUATION REPORT UNION BEACH, NEW JERSEY DRAFT ENGINEERING APPENDIX SUB APPENDIX A PRELIMINARY FLOODWALL DESIGN March 2014Revised March 2015 UNITED STATES ARMY CORPS OF ENGINEERS

More information

Gotechnical Investigations and Sampling

Gotechnical Investigations and Sampling Gotechnical Investigations and Sampling Amit Prashant Indian Institute of Technology Gandhinagar Short Course on Geotechnical Investigations for Structural Engineering 12 14 October, 2017 1 Purpose of

More information

Chapter (11) Pile Foundations

Chapter (11) Pile Foundations Chapter (11) Introduction Piles are structural members that are made of steel, concrete, or timber. They are used to build pile foundations (classified as deep foundations) which cost more than shallow

More information

GEOTECHNICAL POLICIES AND PROCEDURES MANUAL CHAPTER 5 GEOTECHNICAL INVESTIGATION PLANNING GUIDELINES

GEOTECHNICAL POLICIES AND PROCEDURES MANUAL CHAPTER 5 GEOTECHNICAL INVESTIGATION PLANNING GUIDELINES GEOTECHNICAL POLICIES AND PROCEDURES MANUAL CHAPTER 5 GEOTECHNICAL INVESTIGATION PLANNING GUIDELINES GEOTECHNICAL INVESTIGATION PLANNING GUIDELINES 5-i TABLE OF CONTENTS 1. PURPOSE... 1 2. INTRODUCTION...

More information

1 PROJECT BACKGROUND. August 14, Alberta Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8

1 PROJECT BACKGROUND. August 14, Alberta Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8 August 14, 2013 Alberta Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 Mr. Dennis Grace, P.Eng. Construction Engineer Dear Mr. Grace: Central Region Geohazard Assessment 2013

More information

CHARACTERIZATION OF SOFT CLAY- A CASE STUDY AT CRANEY ISLAND

CHARACTERIZATION OF SOFT CLAY- A CASE STUDY AT CRANEY ISLAND National Defense Industrial Association 2005 Tri-Service Infrastructure Systems Conference and Exhibition Re-Energizing Engineering Excellence CHARACTERIZATION OF SOFT CLAY- A CASE STUDY AT CRANEY ISLAND

More information

U-Shaped Sediment Traps

U-Shaped Sediment Traps U-Shaped Sediment Traps SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils [1] Type 3 System Supplementary Trap Dispersive Soils [1] Generally

More information

GEOLOGY, SOILS, AND SEISMICITY

GEOLOGY, SOILS, AND SEISMICITY 4.9 GEOLOGY, SOILS, AND SEISMICITY 4.9.1 Introduction Information about the geological conditions and seismic hazards in the study area was summarized in the FEIR, and was based on the Geotechnical Exploration

More information

Volume 2. Geotechnical Evaluation for FINGER LAKES STORAGE BRINE POND. February 25, Prepared for:

Volume 2. Geotechnical Evaluation for FINGER LAKES STORAGE BRINE POND. February 25, Prepared for: February 25, 2011 Volume 2 Geotechnical Evaluation for FINGER LAKES STORAGE BRINE POND Prepared for: Mr. Michael LaRose Finger Lakes Storage, LLC 111 North Franklin Street Watkins Glen, New York 14891

More information

REPORT OF PRELIMINARY SUBSURFACE EXPLORATION SITE DESIGN EVALUATION FOR REHABILITATION OF PINE GROVE LAKE DAM

REPORT OF PRELIMINARY SUBSURFACE EXPLORATION SITE DESIGN EVALUATION FOR REHABILITATION OF PINE GROVE LAKE DAM REPORT OF PRELIMINARY SUBSURFACE EXPLORATION SITE DESIGN EVALUATION FOR REHABILITATION OF PINE GROVE LAKE DAM VILLAGE OF SLOATSBURG, ROCKLAND COUNTY, NEW YORK SUBMITTED TO: ASSOCIATION OF PROPERTY OWNERS

More information

APPENDIX B DESIGN CRITERIA FOR TEMPORARY WATER QUALITY BMPS USED DURING CONSTRUCTION

APPENDIX B DESIGN CRITERIA FOR TEMPORARY WATER QUALITY BMPS USED DURING CONSTRUCTION APPENDIX B DESIGN CRITERIA FOR TEMPORARY WATER QUALITY BMPS USED DURING CONSTRUCTION This Appendix presents design criteria and example calculations for the following temporary water quality BMPs for use

More information

KDOT Geotechnical Manual Edition. Table of Contents

KDOT Geotechnical Manual Edition. Table of Contents KDOT Geotechnical Manual 2007 Edition The KDOT Geotechnical Manual is available two volumes. Both volumes are very large electronic (pdf) files which may take several minutes to download. The table of

More information

Sediment Trap. A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff through a stabilized spillway.

Sediment Trap. A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff through a stabilized spillway. Sediment Trap SC-15 Source: Caltrans Construction Site Best Management Practices Manual, 2003. Description A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff

More information

Degradation Concerns related to Bridge Structures in Alberta

Degradation Concerns related to Bridge Structures in Alberta Degradation Concerns related to Bridge Structures in Alberta Introduction There has been recent discussion regarding the identification and assessment of stream degradation in terms of how it relates to

More information

SASKATCHEWAN STRATIGRAPHY GLACIAL EXAMPLE BOULDERS IN GLACIAL DEPOSITS

SASKATCHEWAN STRATIGRAPHY GLACIAL EXAMPLE BOULDERS IN GLACIAL DEPOSITS SASKATCHEWAN STRATIGRAPHY GLACIAL EXAMPLE BOULDERS IN GLACIAL DEPOSITS 51 SASKATCHEWAN STRATIGRAPHY GLACIAL SURFICIAL STRATIFIED DEPOSITS 52 SASKATCHEWAN STRATIGRAPHY GLACIAL EXAMPLE OF SEDIMENT DEPOSITION

More information

SCOPE OF INVESTIGATION Simple visual examination of soil at the surface or from shallow test pits. Detailed study of soil and groundwater to a

SCOPE OF INVESTIGATION Simple visual examination of soil at the surface or from shallow test pits. Detailed study of soil and groundwater to a Lecture-5 Soil Exploration Dr. Attaullah Shah 1 Today s Lecture Purpose of Soil Exploration Different methods 1. Test trenches and Pits 2. Auger and Wash Boring 3. Rotary Drilling 4. Geophysical Methods

More information

6.1 Water. The Water Cycle

6.1 Water. The Water Cycle 6.1 Water The Water Cycle Water constantly moves among the oceans, the atmosphere, the solid Earth, and the biosphere. This unending circulation of Earth s water supply is the water cycle. The Water Cycle

More information

Predicting Settlement and Stability of Wet Coal Ash Impoundments using Dilatometer Tests

Predicting Settlement and Stability of Wet Coal Ash Impoundments using Dilatometer Tests Predicting Settlement and Stability of Wet Coal Ash Impoundments using Dilatometer Tests Chris Hardin, P.E. CH2M Hill, Charlotte, North Carolina, E-mail: Chris.Hardin@ch2m.com Roger Failmezger, P.E., F.

More information

Prentice Hall EARTH SCIENCE

Prentice Hall EARTH SCIENCE Prentice Hall EARTH SCIENCE Tarbuck Lutgens Running Water and Groundwater Running Water The Water Cycle Water constantly moves among the oceans, the atmosphere, the solid Earth, and the biosphere. This

More information

APPENDIX G APPENDIX G SEDIMENT CONTAINMENT SYSTEM DESIGN RATIONALE

APPENDIX G APPENDIX G SEDIMENT CONTAINMENT SYSTEM DESIGN RATIONALE APPENDIX G SEDIMENT CONTAINMENT SYSTEM DESIGN RATIONALE March 18, 2003 This page left blank intentionally. March 18, 2003 G-2 FIGURES Page # Figure G.1 Estimated Runoff from Precipitation Over Different

More information

Geotechnical Evaluation

Geotechnical Evaluation : Geotechnical Evaluation Lower Pool 2 Channel Management Study: Boulanger Bend to Lock and Dam No. 2 This Page Intentionally Left Blank Pool 2: Boulanger Bend to Lock and Dam 2 J-2 1. PURPOSE The purpose

More information

An Introduction to Field Explorations for Foundations

An Introduction to Field Explorations for Foundations An Introduction to Field Explorations for Foundations J. Paul Guyer, P.E., R.A. Paul Guyer is a registered mechanical engineer, civil engineer, fire protection engineer and architect with over 35 years

More information

STEVENS CREEK DAM SEISMIC STABILITY EVALUATIONS OF CHESBRO, LENIHAN, STEVENS CREEK, AND UVAS DAMS (SSE2) PHASE A: STEVENS CREEK AND LENIHAN DAMS

STEVENS CREEK DAM SEISMIC STABILITY EVALUATIONS OF CHESBRO, LENIHAN, STEVENS CREEK, AND UVAS DAMS (SSE2) PHASE A: STEVENS CREEK AND LENIHAN DAMS SEISMIC STABILITY EVALUATIONS OF CHESBRO, LENIHAN, STEVENS CREEK, AND UVAS DAMS (SSE2) PHASE A: STEVENS CREEK AND LENIHAN DAMS STEVENS CREEK DAM COMPILATION REPORT (REPORT No. SSE2A-SC) Prepared for SANTA

More information

IAEA SAFETY STANDARDS Geotechnical Aspects of Site Evaluation and Foundations in NPPs, NS-G-3.6

IAEA SAFETY STANDARDS Geotechnical Aspects of Site Evaluation and Foundations in NPPs, NS-G-3.6 IAEA SAFETY STANDARDS Geotechnical Aspects of Site Evaluation and Foundations in NPPs, NS-G-3.6 Regional Workshop on Volcanic, Seismic, and Tsunami Hazard Assessment Related to NPP Siting Activities and

More information

Rock Sizing for Waterway & Gully Chutes

Rock Sizing for Waterway & Gully Chutes Rock Sizing for Waterway & Gully Chutes WATERWAY MANAGEMENT PRACTICES Photo 1 Rock-lined waterway chute Photo 2 Rock-lined gully chute 1. Introduction A waterway chute is a stabilised section of channel

More information

Deep Foundations 2. Load Capacity of a Single Pile

Deep Foundations 2. Load Capacity of a Single Pile Deep Foundations 2 Load Capacity of a Single Pile All calculations of pile capacity are approximate because it is almost impossible to account for the variability of soil types and the differences in the

More information

Calibration of Seepage and Stability Models for analysis of Dams and Levees. Francke C Walberg Consulting Geotechnical Engineer, AECOM

Calibration of Seepage and Stability Models for analysis of Dams and Levees. Francke C Walberg Consulting Geotechnical Engineer, AECOM Calibration of Seepage and Stability Models for analysis of Dams and Levees Francke C Walberg Consulting Geotechnical Engineer, AECOM Focus Use of models for; Evaluation of existing dams and levees Rehabilitation

More information

April 30, City of Oxbow C/o Moore Engineering th Avenue East West Fargo, ND 58078

April 30, City of Oxbow C/o Moore Engineering th Avenue East West Fargo, ND 58078 April 30, 2010 City of Oxbow C/o Moore Engineering 925 10 th Avenue East West Fargo, ND 58078 Attn: Subject: Mr. Kyle Volk Stability Evaluation of Flood Protection Levee Flood Protection Levees City of

More information

PROBLEMS AND SOLUTIONS THAT MAY EMERGE IN THE FOUNDATION AND BODY OF A HOMOGENEOUS FILL DAM ON A WEAK CLAYEY-SILTY-SANDY FORMATION ÇIKRIKÇI DAM

PROBLEMS AND SOLUTIONS THAT MAY EMERGE IN THE FOUNDATION AND BODY OF A HOMOGENEOUS FILL DAM ON A WEAK CLAYEY-SILTY-SANDY FORMATION ÇIKRIKÇI DAM PROBLEMS AND SOLUTIONS THAT MAY EMERGE IN THE FOUNDATION AND BODY OF A HOMOGENEOUS FILL DAM ON A WEAK CLAYEY-SILTY-SANDY FORMATION ÇIKRIKÇI DAM Esen Yalım KARADUMAN BAR-SU Eng. & Conc. Inc. Ankara Turkey

More information

Horizontal Directional Drilling: An Approach to Design and Construction. Presenter: John Briand, PE Co-Author: Danielle Neamtu, PE

Horizontal Directional Drilling: An Approach to Design and Construction. Presenter: John Briand, PE Co-Author: Danielle Neamtu, PE Horizontal Directional Drilling: An Approach to Design and Construction Presenter: John Briand, PE Co-Author: Danielle Neamtu, PE Presentation Outline General HDD overview Conceptual-level evaluation Detailed

More information

Sediment Trap. At multiple locations within the project site where sediment control is needed.

Sediment Trap. At multiple locations within the project site where sediment control is needed. Sediment Trap SE-3 Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control

More information

Final Exam. Running Water Erosion and Deposition. Willamette Discharge. Running Water

Final Exam. Running Water Erosion and Deposition. Willamette Discharge. Running Water Final Exam Running Water Erosion and Deposition Earth Science Chapter 5 Pages 120-135 Scheduled for 8 AM, March 21, 2006 Bring A scantron form A calculator Your 3 x 5 paper card of formulas Review questions

More information

SOIL MECHANICS: palgrave. Principles and Practice. Graham Barnes. macmiiian THIRD EDITION

SOIL MECHANICS: palgrave. Principles and Practice. Graham Barnes. macmiiian THIRD EDITION SOIL MECHANICS: Principles and Practice THIRD EDITION Graham Barnes palgrave macmiiian 'running Contents Preface xii Fine soil 19 List of symbols xiv Mass structure 21 Note on units xix Degree of weathering

More information

Manual on Subsurface Investigations National Highway Institute Publication No. FHWA NHI Federal Highway Administration Washington, DC

Manual on Subsurface Investigations National Highway Institute Publication No. FHWA NHI Federal Highway Administration Washington, DC Manual on Subsurface Investigations National Highway Institute Publication No. FHWA NHI-01-031 Federal Highway Administration Washington, DC Geotechnical Site Characterization July 2001 by Paul W. Mayne,

More information

4.9 GEOLOGY AND SOILS

4.9 GEOLOGY AND SOILS 4.9 GEOLOGY AND SOILS 4.9.1 EXISTING CONDITIONS TOPOGRAPHY AND RELIEF Zone 40 is located in the central portion of Sacramento County. The topography of the county is represented by three physiographic

More information

PERENNIAL PROBLEM OF EARTHEN BUND OF WELLINGDON RESERVOIR. ANALYSIS OF CAUSES AND REMEDIAL MEASURES A CASE STUDY.

PERENNIAL PROBLEM OF EARTHEN BUND OF WELLINGDON RESERVOIR. ANALYSIS OF CAUSES AND REMEDIAL MEASURES A CASE STUDY. PERENNIAL PROBLEM OF EARTHEN BUND OF WELLINGDON RESERVOIR. ANALYSIS OF CAUSES AND REMEDIAL MEASURES A CASE STUDY. By Er. S. Muthu Parvatha Vardhini, Asst. Executive Engineer, (Designs) Water Resources

More information

Lesson 25. Static Pile Load Testing, O-cell, and Statnamic. Reference Manual Chapter 18

Lesson 25. Static Pile Load Testing, O-cell, and Statnamic. Reference Manual Chapter 18 Lesson 25 Static Pile Load Testing, O-cell, and Statnamic Reference Manual Chapter 18 STATIC LOAD TESTING Most accurate method to determine static pile capacity Perform at design or construction stage

More information

3.12 Geology and Topography Affected Environment

3.12 Geology and Topography Affected Environment 3 Affected Environment and Environmental Consequences 3.12 Geology and Topography 3.12.1 Affected Environment 3.12.1.1 Earthquakes Sterling Highway MP 45 60 Project Final EIS The Kenai Peninsula is predisposed

More information

REPORT OF PRELIMINARY GEOTECHNICAL EXPLORATION

REPORT OF PRELIMINARY GEOTECHNICAL EXPLORATION REPORT OF PRELIMINARY GEOTECHNICAL EXPLORATION ENKA INTERMEDIATE SCHOOL Sand Hill Road Candler, North Carolina Prepared For: BUNCOMBE COUNTY SCHOOLS Prepared By: AMEC ENVIRONMENT & INFRASTRUCTURE, INC.

More information

Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay 19 Module 5: Lecture -1 on Stability of Slopes Contents Stability analysis of a slope and finding critical slip surface; Sudden Draw down condition, effective stress and total stress analysis; Seismic

More information

Background. Valley fills Sites in the Area. Construction over Mine Spoil Fills

Background. Valley fills Sites in the Area. Construction over Mine Spoil Fills Construction over Mine Spoil Fills Wayne A. Karem, PhD, PE, PG, D.GE 2014 KSPE Annual Conference Background Strip mining; mountaintop and contour mining Creates huge quantities of mine spoil The mine spoil

More information

Salt Lake County Tailings Impoundment Study (Final)

Salt Lake County Tailings Impoundment Study (Final) Salt Lake County Tailings Impoundment Study (Final) Prepared for: Salt Lake County Government Center 2001 South State Street Suite N-4500 Salt Lake City, Utah 84190-3100 Prepared by: Tetra Tech, Inc, 715

More information