Stormwater Management Report

Size: px
Start display at page:

Download "Stormwater Management Report"

Transcription

1 1150 Morrison Drive, Suite 410 Ottawa, ON, K2H 8S9 T F Project No A Stormwater Management Report Hydro Ottawa Hunt Club Drive, Gloucester, Ontario Prepared for November 28, 2016

2 Hydro Ottawa, East Campus Stormwater Management Report Table of Contents 1 Introduction Objective Design Parameters Water Quantity Controls Pre-development Conditions Allowable release rate Post-development Conditions Pipe Design Onsite stormwater detention Proposed release rates Water Quality Control Erosion and Sediment Control Conclusion... 4 Figure 1 Stormwater Management Sub-Drainage Areas Appendix A Record of Pre-Consultation Appendix B Stormwater Management Calculations Appendix C OttHymo Model Results Appendix D Roof Drainage Jp2g Consultants Inc. ENGINEERS PLANNERS PROJECT MANAGERS

3 Hydro Ottawa East Campus Stormwater Management Report 1 Introduction Jp2g Consultants Inc. was retained by M. Sullivans & Sons (Sullivan) to complete a Stormwater Management Report suitable for City of Ottawa Site Plan Control Application, for the proposed Hydro Ottawa construction project located on Hunt Club Drive, east of Hawthorne Road, within the City of Ottawa. The site area of approximately 8.5 ha is to be developed with three buildings, associated parking areas and landscaped areas. A Pre-Consultation meeting was held with City of Ottawa staff, December 1, 2015 to determine the project constraints and requirements; see Record of Pre-Consultation in Appendix A. The following report details the stormwater management calculations used for water quantity and quality control. Reference Drawings: Figure 1 Stormwater Management Sub-Drainage Areas, C1 - Site Servicing Plan (November 28, 2016), and C2 - Site Grading and Drainage, Erosion and Sediment Control Plan (November 28, 2016). 2 Objective The objective of the stormwater management plan is to meet the requirements of LEED SSc6.1 and SSc6.2, the City of Ottawa, and the Rideau Valley Conservation Authority (RVCA), for up to and including the 100-year storm event without effecting adjacent lands. 3 Design Parameters Stormwater management criteria for this site, in terms of quality and quantity control, is based on the following targets: City of Ottawa: restrict post-development 1:100 year flows to not greater than pre-development 1:5 year flows, assuming C=0.5 and using existing Tc. Normal level of Water Quality Treatment is achieved immediately downstream, so no further treatment is required. Rideau Valley Conservation Authority: restrict post-development flows to not greater than predevelopment flow rates, LEED: post development flow rate and volume will not exceed the predevelopment flow rate and volume for the 1:1 and 1:2 year event; TSS removal will be not less than 80% for the 19mm rainfall event. Visual Otthymo was used to calculate release rates for the critical events. Detailed stormwater management calculations are included in Appendix B. All proposed storm sewers were assigned a Manning s coefficient of roughness of corresponding to smooth wall pipes. Runoff coefficients were calculated considering soils, surface treatment, and slope. In addition, 25% was added to the C value for the 100-year storm calculations. The rainfall intensities used in this analysis are based on the IDF curves and equations, as per City of Ottawa Sewer Design Guidelines (Section 5.4.2). Sub-surface storage is estimated using a void ratio of 0.3, and percolation rates are assumed using the value for loamy sand (60mm/hr) from Table 4.4 of the Stormwater Management Planning and Design Manual (Ministry of the Environment, 2003). Jp2g Consultants Inc. ENGINEERS PLANNERS PROJECT MANAGERS page 1 of 5

4 Hydro Ottawa East Campus Stormwater Management Report 4 Water Quantity Controls 4.1 Pre-development Conditions The existing site is an undeveloped parcel with a generally flat site topography that is sloped toward the east side of the property with an approximate elevation difference of 7 meters over a 180 meter length. Offsite flows draining 6.02ha across the property through the middle of the site. The eastern and northern property boundary contains a drainage easement and swale that is currently receiving all of the runoff from this site. The swale outlets into a quality and quantity treatment pond immediately downstream of the site. The in-situ soils are variable, with sandier materials in the top 2m, and clayier materials lower. Much of the site is a reclaimed quarry, with highly variable soil conditions where fill was placed. The average infiltration rate is estimated to be 15mm/hr 2m below the surface. The soil groundwater elevation was found around 76m down to 73m generally 3 to 4m below existing grade. 4.2 Allowable release rate The stormwater management design criteria for this site is based on LEED and City of Ottawa requirements. The City requires that the 1:100 discharge from the site is to not exceed the 1:5 year event, assuming C=0.5 and a calculated Tc. LEED credit SS6.1 requires that the post-development runoff rate and volume for the 1:1 and 1:2 year event be restricted to the pre-development rate and volume for the 1:1 and 1:2 year event. The pre-development flows are: Event Duration Runoff depth Runoff volume Peak flow rate Allowable release rate 1:1 year 24 hr 9.0 mm 449 m mm/h m3/s 1:2 year 24 hr 13.6 mm 657 m mm/h m3l/s 1:5 year 24 hr 21.9 mm 1089 m mm/h m3/s 1:5 year 4 hr 26.1 mm 1299 m mm/h m3/s 1:100 year 24 hr 47.8 mm 2375 m mm/h m3/s 1:100 year 4 hr 55.2 mm 2743 m mm/h m3/s 1:5 year, C= hr 37.1 mm 1844 m mm/h m3/s 1:5 year, C=0.5 4 hr 32.8 mm 1629 m mm/h m3/s Table 1: Pre development flows blue highlight shows constrained release rates 4.3 Post-development Conditions The proposed site development includes the construction of 3 new buildings (Administration Building, Operations Building, and Warehouse), an associated parking lot and landscaped areas. The site grading has been designed to direct stormwater runoff from parking areas to enhanced bioswales, while the rooftop and landscaped areas drain to an infiltration basin. Flows beyond the capacity of the infiltration basin will spill over towards the adjacent municipal drainage ditch. The site development area is approximately 5.22 ha and has a post-development average weighted runoff coefficient of C=0.72, and C=0.82 for the 1:5 year, and 1:100year events, respectively. Offsite flows coming overland through the site drain an area of 6.2 ha with runoff coefficient of C=0.80 and C=1.0. This flow is diverted within a ditch around the project site, entering the same watercourse but in a different location, without any additional quality or quantity treatment. The ditch is sized to carry the 1:100 year event from the offsite area. Jp2g Consultants Inc. ENGINEERS PLANNERS PROJECT MANAGERS page 2 of 5

5 Hydro Ottawa East Campus Stormwater Management Report Stormwater management techniques are required to reduce peak flows from the site, so that post-development peak flows will not exceed targets. The site was modelled using Visual Otthymo 3.0, and the output of the model runs have been included in Appendix C. 4.4 Pipe Design Pipe diameter sizing was based on the 100-year storm event, and will not be surcharged, i.e. flow/capacity <90%. 4.5 Onsite stormwater detention The bioswales within the site are sized to capture and percolate parking runoff into clearstone subsurface storage. There it will be retained until the runoff has been infiltrated. Expected infiltration rates will allow infiltration of the subsurface storage in 8 to 12 hours. Surface storage will infiltrate in 6 to 24 hours. Surface storage is provided for short, intense events, to allow the runoff to have a chance to percolate into the clear stone. This ensures that the entirety of the 19mm event required by LEED is captured and treated for quality by infiltration. Flows in excess of the 1:2 year, 24 hour event will enter a catchbasin in each bioswale. Each catch basin has an orifice to control the release rate, and is directed to an infiltration basin, so that the 1:100 year event produces a runoff rate that is less than the pre-development 1:5 year event, for both the 4 hour and 24 hour events. Flow will also be detained on the roof of EC1 by installing flow controls at the 14 proposed roof drains, limiting the flow from the roof to 12 l/s.the restricted flow will create rooftop storage of 70 m 3 and 130 m 3 for the 5- year and 100-year event, respectively. Based on an approximate ponding depth of 150mm on the roof, the total available storage is approximately 139 m 3, which is sufficient to accommodate the 100-year event. Roof drainage options are included in Appendix D, however equivalent performing products can also be used. Flows from the front parking areas and the gravel pad are directed to an infiltration swale, with rock check dams designed to capture a specific volume and force infiltration. Remaining flows will reach the drainage swale the surrounds the site and be directed to the SWM pond downstream of the site. The ponding limits for the 5-year and the 100-year event are indicated on Figure 1. In the event the capacity of this system is exceeded, emergency runoff will overflow towards the existing drainage swale. 4.6 Proposed release rates The proposed release rate for this site during various critical events are shown in Table 2 below. Jp2g Consultants Inc. ENGINEERS PLANNERS PROJECT MANAGERS page 3 of 5

6 Hydro Ottawa East Campus Stormwater Management Report Event Target volume (m3) Target release rate (l/s) Rainfall volume (m3) Surface Storage (m3) Infiltration (m3) Release volume (m3) Peak release rate (l/s) 19mm :1 year :2 year :5 year 4 hour :5 year 24 hour :100 year 4 hour :100 year 24 hour Table 2: Post-development runoff volumes and flows 5 Water Quality Control Based on preconsultation with the City of Ottawa and Rideau Valley Conservation Authority (RVCA), no stormwater quality control is required for this site due to the downstream quality pond. The LEED target requires that the 19mm event would receive 80% TSS removal treatment or better. This will be achieved by capturing the 19mm event and allowing it to infiltrate. The runoff from much of the site will be directed to bioswales and through a sandy topsoil layer and into underlying clearstone trench. The remainder of the site is directed to either an infiltration basin, or a grassed swale with check dams. The check dams capture and force infiltration of a specific volume, and allow additional volume to overtop and be released. Ongoing maintenance will be required to remove accumulated sediment from the bioswales. This will be done on an as-required basis, by vacuum truck. Sediment will accumulate no faster than 0.7 kg of sediment per year per m2 of road surface, and will be mostly sand from winter road maintenance. The performance of the system would not be seriously affected from 10 years of such accumulation. 6 Erosion and Sediment Control In accordance with City of Ottawa requirements, best management practices are to be implemented by the Contractor to provide protection of the area drainage system and the receiving water course, during construction activities. This includes limiting the amount of exposed soil, using filter bag inserts under the grates of catch basins and manholes, installing silt fences and other effective sediment traps, and installing and maintaining mud mats for outgoing construction traffic during construction activities. 7 Conclusion The proposed site development includes 3 buildings, associated parking lot, a granular pad, and landscaped areas. Roof drainage and surface runoff will be collected in bioswales and infiltration basin, and events up to the 1:1 year event will infiltrate entirely. Post-development peak flows will be detained on the roof and in the bioswales to limit the post-development release rate to allowable targets. There is sufficient onsite storage to accommodate the 100-year event. Excess flows are directed to the on-site municipal drainage course, which drains to the McEwan Creek SWM facility, immediately adjacent to the site. Jp2g Consultants Inc. ENGINEERS PLANNERS PROJECT MANAGERS page 4 of 5

7 Hydro Ottawa East Campus Stormwater Management Report Summary of report ID Description Value/result 01 Allowable release rate 1:1 year = 167 l/s, 1:2 year = 291 l/s, 1:100 year = 535 l/s 02 Proposed release rate 1:1 year = 0, 1:2 year = 0, 1:100 year = 501 l/s 03 Post-development runoff coefficient C 5=0.72, and C 100= Post-development onsite storage requirement 1685m3 05 Proposed onsite storage (including rooftop) 1821m3 without overtopping asphalt, 4265m3 without uncontrolled flows. 06 Discharge outlet location Overland into McEwan Creek drain 07 Emergency runoff overflow location Overland into McEwan Creek drain Prepared by END OF REPORT Nov. 28, 2016 Douglas Nuttall, P.Eng. Senior Civil Engineer Jp2g Consultants Inc. ENGINEERS PLANNERS PROJECT MANAGERS page 5 of 5

8 Hydro Ottawa East Campus Stormwater Management Report Appendix A - Record of Pre-Consultation Jp2g Consultants Inc. ENGINEERS PLANNERS PROJECT MANAGERS

9 Hydro Ottawa East Campus Stormwater Management Report Appendix B - Stormwater Management Calculations Jp2g Consultants Inc. ENGINEERS PLANNERS PROJECT MANAGERS

10 Hydro Ottawa East Campus Stormwater Management Report Appendix C - Visual Otthymo Model Results Jp2g Consultants Inc. ENGINEERS PLANNERS PROJECT MANAGERS

11 Hydro Ottawa East Campus Stormwater Management Report Appendix D Roof Drainage Jp2g Consultants Inc. ENGINEERS PLANNERS PROJECT MANAGERS

12

13 Hydro Ottawa East Campus Stormwater Management Report Appendix A - Record of Pre-Consultation Jp2g Consultants Inc. ENGINEERS PLANNERS PROJECT MANAGERS

14 Doug Nuttall From: Sent: To: Subject: Moore, Sean Monday, November 7, :26 AM FW: Hydro Ottawa preconsultation Hi Doug, See the City s comments on the Hawthorne site below from Dec 2015: Sean. From: Moore, Sean Sent: Friday, December 04, :47 PM To: 'Lloyd Phillips' Cc: Buchanan, Richard; Robertson, Syd; Morgan, Brian; Hayley, Matthew; Moise, Christopher; McEwen, Jeff; 'Jocelyn Chandler'; Kearney, Michel; Carter, Riley Subject: Hydro Ottawa preconsultation Hi Lloyd, Regarding our preconsultation meeting of December 1 st please find below the submission requirements and our preliminary staff comments concerning the two proposed site plan control applications (3475 Hawthorne Road and 201 Dibblee Road). If you have any questions or concerns with the information provided don t hesitate to call me to discuss. APPLICATION #1: 3475 Hawthorne Road Site Plan Control Application: Application Type: Manager Approval, Public Consultation Fee: $20, Conservation Authority Fee: $ Link to Site Plan Control application form: List of required Plans with your application: Site Plan (55 copies) Landscape Plan (55 copies) Grading Plan (55 copies) Site Servicing Plan (55 copies) Survey Plan (2 copies) Erosion Sediment and Control Plan (8 copies) Roadway Modification Plan (55 copies at 80% design completion) Architectural Elevation Drawings (5 copies) List of required Reports with your application: Phase 1 Environmental Site Assessment (5 copies) Transportation Impact Study (10 copies) Servicing Brief, including Stormwater Management (5 copies) 1

15 Scoped Environmental Impact Statement (5 copies) Tree Conservation Report (5 copies) Geotechnical Study / Slope Stability Study (4 copies) Noise Study (3 copies) Note: please submit a CD with pdf s of all plans / reports Preliminary Staff Comments: Staff encourage you to consult with the local Ward Councillor (Diane Deans) Please be aware that MTO are expanding their control area and this site could trigger their comments We along the Hunt Club frontage, tying into the exiting sidewalk Please consider sharing / bicycle trips (including bike parking) in your site design The proposed shared access with the adjacent future commercial site should be included in TIS Please address the Significant Valley Lands and Species at Risk (as per the Official Plan) in your EIS. We understand that information regarding an easement agreement on the valley lands is to be sent to us for review. In 2010, CLV submitted an IER for a development at this address, this IER can form the basis of the EIS and be up-dated to reflect the endangered and threatened species and the new project. Please consult with Charles Goulet at the local MOECC office for your requirements for industrial sewage works We would like to review architectural elevations prior to the procurement process to ensure the bidding teams have City feedback on this matter Please be aware that the NCC easement must be resolved prior to approval/registration We will review any access option you propose for the eastern most proposed access (for example if this is to be a Hydro Ottawa access only, right-in right-out, or a shared access with NCC, right-in-right out or full movement access; and whether this access is proposed to be situated on Hydro Ottawa property, City property, or straddling the properties). Another option could be to make the western access a right-in right out, with the full movement access being at the eastern end of the site. All options will be reviewed by the City which are put forth to us. In the event you wish to put forth a second full movement access we would ask for a transportation rationale in advance of the application for our review and comment/decision. The City s Asset Management Unit & SWM Unit confirmed that the subject site is located within the drainage catchment area of the McEwan Creek system which outfalls to the McEwan Creek SWM Facility #1625. We are therefore presently seeking input from Sewer Operations to permit a connection to the 3600mm dia East Hunt Club Storm Sewer. The existing 600mm diametre storm sewer on Hunt Club Road is within a different catchment area and that system was not designed to receive run-off from 3475 Hawthorne Road. The SWM Unit indicated that undeveloped properties, within the McEwen system, are subject to an area specific stormwater DC charge which was set up to fund the McEwen SWF. Refer to the following link: APPLICATION #2: 201 Dibblee Road Site Plan Control Application: Application Type: Manager Approval, Public Consultation Fee: $20, Conservation Authority Fee: $ Link to Site Plan Control application form: List of required Plans with your application: 2

16 Site Plan (55 copies) Landscape Plan (55 copies) Grading Plan (55 copies) Site Servicing Plan (55 copies) Survey Plan (2 copies) Erosion Sediment and Control Plan (8 copies) Roadway Modification Plan (55 copies at 80% design completion) *if any improvements are identified through the TIS and required Architectural Elevation Drawings (5 copies) List of required Reports with your application: Phase 1 Environmental Site Assessment (5 copies) Transportation Impact Study (10 copies) Servicing Brief, including Stormwater Management (5 copies) Environmental Impact Statement (5 copies) Tree Conservation Report (5 copies) Hydrogeological Analysis (5 copies) Geotechnical Study / Slope Stability Study (4 copies) Reasonable Use Study (5 copies) could be required if the septic system surpasses 10,000 L/day (required for assessment of impact on ground water) Preliminary Staff Comments: Staff encourage you to consult with the local Ward Councillor (Scott Moffatt) This falls within the MTO control area and requires Land-Use and Sign permit from MTO. Further consultation with MTO on stormwater requirements is advised, as I understand MTO will request to review the SWM report to ensure it complies with their requirements The site is identified as Significant Woodlands in the Official Plan, thus the EIS must address this, as well as endangered and threatened species We would like to review architectural elevations prior to the procurement process to ensure the bidding teams have City feedback on this matter As discussed the snow plow turnaround and snow storage aspect of Dibblee Road will need to be investigated further You will require MOECC approvals and permits for stormwater, and industrial sewage works (please consult with Charles Goulet) Please reduce the site entrance where feasible below 10 metres in width (provide truck turning radius lines on the plans to demonstrate your needs) The water quality in this area is known to have salt contamination issues. City Staff will have to determine to what extent hydrogeological work will be required to show there is potable water available, the site to the south is requiring reverse osmosis which may have limitations on how long it will be sustainable if the salt contamination levels rise. Further, the geology in the area is affected by a fault which makes locating a suitable water supply aquifer challenging. Due to potential challenging water conditions within the Bobcaygeon formation we recommend a well drilled in advance to determine the type of water conditions that are present on site see the Regional Geology Mapping below. It is practice that the Part 8 Sewage System application be submitted and receive a permit in advance of approving site plan control (confirmation that the design and sizing are appropriate). The length of pumping test (D5-5 is a minimum standard) should be longer than D5-5, as quantity and quality could be an issue at this site. The longer the pumping test, the better information gathered. Please be aware that mechanical design could be an issue with ensuring potable water, such as the need for extensive treatment (we would need a conceptual design of this) 3

17 The threshold for an MOECC requirement on the septic field is 10,000 L per day. If the septic design exceeds this threshold we will require you to go through MOECC and submit a Reasonable Use Study for determining the impact on groundwater (if under 10,000 l per day Ottawa Septic System Office reviews the septic system Please be aware that any reject water which may result from the poor water quality may have to be accounted and designed for in the septic system. Stormwater will be directed to the roadside ditches running along the HWY 416 ROW. This stormwater runs under a culvert to lands on the east side of the highway. The receiver is the O Keefe system which requires enhanced quality control (80% TSS removal). Like the site directly south (220 Dibblee Road), the quantity controls will be determined by the culvert capacity. Please take note of the adjacent site at 220 Dibblee Road (see link provided to the City s development application website, and the stormwater requirements as information for your site). DevApps website (220 Dibblee Road): 0REKYS Note: CD with pdf s of all plans / reports Regional Geology Mapping: Regards, Sean Moore MCIP, RPP, LEED Green Associate Planner III, Acting Development Review (Rural Services) Urbaniste III, Intérimaire Examen des demandes d'aménagement (services ruraux) City of Ottawa Ville d'ottawa ext/poste ottawa.ca/planning / ottawa.ca/urbanisme This originates from the City of Ottawa system. Any distribution, use or copying of this or the information it contains by other than the intended recipient(s) is unauthorized. Thank you. 4

18 Le présent courriel a été expédié par le système de courriels de la Ville d'ottawa. Toute distribution, utilisation ou reproduction du courriel ou des renseignements qui s'y trouvent par une personne autre que son destinataire prévu est interdite. Je vous remercie de votre collaboration. 5

19 Hydro Ottawa East Campus Stormwater Management Report Appendix B - Stormwater Management Calculations Jp2g Consultants Inc. ENGINEERS PLANNERS PROJECT MANAGERS

20 PROJECT: Ottawa Hydro East Campus DESIGNED BY: D. Nuttall DETAIL: Reservoir properties CHECKED BY: S. Arends FROM: DATE: Nov. 28, 2016 Depth Volume Flowrate Depth Volume Flowrate Depth Volume Flowrate Depth Volume Flowrate infiltrate overflow infiltrate overflow Percolate CB outlet overflow infiltrate overflow m m3 l/s l/s m m3 l/s l/s m m3 l/s l/s l/s m m3 l/s l/s Ditch Ditch Bioswale Infiltration Basin Depth Volume Flowrate Depth Volume Flowrate Depth Volume Flowrate Depth Volume Flowrate Percolate CB outlet overflow Percolate CB outlet overflow controlled uncontrolled Into CB overflow m m3 l/s l/s l/s m m3 l/s l/s l/s m m3 l/s l/s m m3 l/s l/s Bioswale Bioswale EC Meadow

21 Hydro Ottawa East Campus Stormwater Management Report Appendix C - Visual Otthymo Model Results Jp2g Consultants Inc. ENGINEERS PLANNERS PROJECT MANAGERS

22

23 Hydro Ottawa East Campus Visual Otthymo Schematic Explanation and logic Node Glyph Represents Used for 60 Standhyd Site, existing conditions Pre-development 59 Standhyd Site, existing conditions Pre-development, assuming site at C=0.5 1 Standhyd Entrance Post-development 2 Standhyd In front of EC1 3 Standhyd In front of EC2 4 Standhyd Beside EC2 5 Standhyd Beside & Behind EC2 6 Standhyd EC3 7 Standhyd Gravel Pad 8 Standhyd EC2 9 Standhyd A7, beside EC2 10 Standhyd EC1 11 Addhyd Into MH 2 Calculating pipe size 12 Route pipe From MH 2 13 Addhyd Into MH 3 Calculating pipe size 14 Route pipe From MH 3 15 Addhyd Into MH 4 Calculating pipe size 16 Route pipe From MH 4 17 Addhyd Into MH 5 Calculating pipe size 18 Route reservoir Ditch 1 19 Diverthyd Infiltration under ditch 1 vs Spilling Sizing rock check over rock check 20 Addhyd Flows coming into Ditch 2 21 Route reservoir Ditch 2 22 Diverthyd Infiltration under ditch 2 vs Spilling Sizing rock check over rock check 26 Standhyd A6, between EC2 and Bioswale 2 27 Route Reservoir Bioswale 1 Sizing bioswale 28 Diverthyd Spilling overland vs percolation Sizing bioswale from bioswale 31 Route Reservoir Bioswale 2 Sizing bioswale 32 Diverthyd Spilling overland vs percolation Sizing bioswale from bioswale 33 Route Reservoir EC1 rooftop storage 35 Standhyd Meadow in front of building 36 Standhyd Patio 37 Addhyd Flow into CB 5 Calculating pipe size 39 Addhyd Flow into Infiltration basin Calculating pipe size 40 Route Reservoir Infiltration basin 41 Divert hyd Spilling overland vs infiltration from infiltration basin

24 43 Addhyd All infiltration Mass balance for checking 44 Addhyd All releases off-site Comparing flows 45 Standhyd Landscaped area in front of EC1 46 Standhyd A5 47 Addhyd Entering bioswale 3 48 Route Reservoir Bioswale 3 50 Diverthyd Spill into infiltration basin vs infiltration 54 Route Reservoir Clearstone trench under Bioswale 2 Check to confirm reservoir capacity not exceeded 55 Route Reservoir Clearstone trench under Bioswale 1 Check to confirm reservoir capacity not exceeded 56 Route Reservoir Clearstone trench under Bioswale 3 Check to confirm reservoir capacity not exceeded 62 Addhyd All flows into MH 5 Size orifice 63 Addhyd CBMH 6 Calculating pipe size 64 Diverthyd Split EC2 in half

25 =========================================================================================================== V V I SSSSS U U A L V V I SS U U A A L V V I SS U U AAAAA L V V I SS U U A A L VV I SSSSS UUUUU A A LLLLL OOO TTTTT TTTTT H H Y Y M M OOO TM O O T T H H Y Y MM MM O O O O T T H H Y M M O O OOO T T H H Y M M OOO Developed and Distributed by Civica Infrastructure Copyright Civica Infrastructure All rights reserved. ***** D E T A I L E D O U T P U T ***** Input filename: C:\Program Files (x86)\vh Suite 3.0\VO2\voin.dat Output filename: C:\Users\Doug Nuttall\AppData\Local\Temp\b9e5156a-fd50-4b54-80fe-70a8fa140284\Scenario.out Summary filename: C:\Users\Doug Nuttall\AppData\Local\Temp\b9e5156a-fd50-4b54-80fe-70a8fa140284\Scenario.sum DATE: 11/28/2016 TIME: 11:26:58 USER: COMMENTS: Page 1

26 **************************** ** SIMULATION NUMBER: 1 ** **************************** READ STORM Filename: C:\Users\Doug Nuttall\AppD ata\local\temp\ b9e5156a-fd50-4b54-80fe-70a8fa140284\1a49bca0 Ptotal= mm Comments: 19 mm 4 Hours step 10 min TIME RAIN TIME RAIN ' TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr ' hrs mm/hr hrs mm/hr CALIB STANDHYD (0001) Area (ha)= 0.27 ID= 1 DT= 2.0 min Total Imp(%)= Dir. Conn.(%)= IMPERVIOUS PERVIOUS (i) Surface Area (ha)= Dep. Storage (mm)= Average Slope (%)= Length (m)= Mannings n = NOTE: RAINFALL WAS TRANSFORMED TO 2.0 MIN. TIME STEP. Page 2

27 ---- TRANSFORMED HYETOGRAPH ---- TIME RAIN TIME RAIN ' TIME RAIN TIME RAIN hrs mm/hr hrs mm/hr ' hrs mm/hr hrs mm/hr Max.Eff.Inten.(mm/hr)= over (min) Page 3

28 Storage Coeff. (min)= 1.32 (ii) 1.62 (ii) Unit Hyd. Tpeak (min)= Unit Hyd. peak (cms)= *TOTALS* PEAK FLOW (cms)= (iii) TIME TO PEAK (hrs)= RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = ***** WARNING: STORAGE COEFF. IS SMALLER THAN TIME STEP! (i) HORTONS EQUATION SELECTED FOR PERVIOUS LOSSES: Fo (mm/hr)= K (1/hr)= 4.00 Fc (mm/hr)= 4.00 Cum.Inf. (mm)= (ii) TIME STEP (DT) SHOULD BE SMALLER OR EQUAL THAN THE STORAGE COEFFICIENT. (iii) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY CALIB STANDHYD (0002) Area (ha)= 0.24 ID= 1 DT= 2.0 min Total Imp(%)= Dir. Conn.(%)= IMPERVIOUS PERVIOUS (i) Surface Area (ha)= Dep. Storage (mm)= Average Slope (%)= Length (m)= Mannings n = Max.Eff.Inten.(mm/hr)= over (min) Storage Coeff. (min)= 1.67 (ii) 2.43 (ii) Unit Hyd. Tpeak (min)= Unit Hyd. peak (cms)= Page 4

29 *TOTALS* PEAK FLOW (cms)= (iii) TIME TO PEAK (hrs)= RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = ***** WARNING: STORAGE COEFF. IS SMALLER THAN TIME STEP! (i) HORTONS EQUATION SELECTED FOR PERVIOUS LOSSES: Fo (mm/hr)= K (1/hr)= 4.00 Fc (mm/hr)= 4.00 Cum.Inf. (mm)= (ii) TIME STEP (DT) SHOULD BE SMALLER OR EQUAL THAN THE STORAGE COEFFICIENT. (iii) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY CALIB STANDHYD (0003) Area (ha)= 0.11 ID= 1 DT= 2.0 min Total Imp(%)= Dir. Conn.(%)= IMPERVIOUS PERVIOUS (i) Surface Area (ha)= Dep. Storage (mm)= Average Slope (%)= Length (m)= Mannings n = Max.Eff.Inten.(mm/hr)= over (min) Storage Coeff. (min)= 1.34 (ii) 2.38 (ii) Unit Hyd. Tpeak (min)= Unit Hyd. peak (cms)= *TOTALS* PEAK FLOW (cms)= (iii) TIME TO PEAK (hrs)= Page 5

30 RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = ***** WARNING: STORAGE COEFF. IS SMALLER THAN TIME STEP! (i) HORTONS EQUATION SELECTED FOR PERVIOUS LOSSES: Fo (mm/hr)= K (1/hr)= 4.00 Fc (mm/hr)= 4.00 Cum.Inf. (mm)= (ii) TIME STEP (DT) SHOULD BE SMALLER OR EQUAL THAN THE STORAGE COEFFICIENT. (iii) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY ADD HYD (0011) = 3 AREA QPEAK TPEAK R.V. (ha) (cms) (hrs) (mm) ID1= 1 (0001): ID2= 2 (0002): ================================================== ID = 3 (0011): NOTE: PEAK FLOWS DO NOT INCLUDE BASEFLOWS IF ANY ADD HYD (0011) = 1 AREA QPEAK TPEAK R.V. (ha) (cms) (hrs) (mm) ID1= 3 (0011): ID2= 2 (0003): ================================================== ID = 1 (0011): Page 6

31 NOTE: PEAK FLOWS DO NOT INCLUDE BASEFLOWS IF ANY ROUTE PIPE (0012) PIPE Number = 1.00 IN= 2---> OUT= 1 Diameter (mm)= DT= 2.0 min Length (m)= Slope (m/m)= Manning n = < TRAVEL TIME TABLE > DEPTH VOLUME FLOW RATE VELOCITY TRAV.TIME (m) (cu.m.) (cms) (m/s) min E E E E E E E E E E E E E E E E E E E <---- hydrograph ----> <-pipe / channel-> AREA QPEAK TPEAK R.V. MAX DEPTH MAX VEL (ha) (cms) (hrs) (mm) (m) (m/s) INFLOW : ID= 2 (0011) OUTFLOW: ID= 1 (0012) Page 7

32 CALIB STANDHYD (0004) Area (ha)= 0.19 ID= 1 DT= 2.0 min Total Imp(%)= Dir. Conn.(%)= IMPERVIOUS PERVIOUS (i) Surface Area (ha)= Dep. Storage (mm)= Average Slope (%)= Length (m)= Mannings n = Max.Eff.Inten.(mm/hr)= over (min) Storage Coeff. (min)= 1.57 (ii) 3.13 (ii) Unit Hyd. Tpeak (min)= Unit Hyd. peak (cms)= *TOTALS* PEAK FLOW (cms)= (iii) TIME TO PEAK (hrs)= RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = ***** WARNING: STORAGE COEFF. IS SMALLER THAN TIME STEP! (i) HORTONS EQUATION SELECTED FOR PERVIOUS LOSSES: Fo (mm/hr)= K (1/hr)= 4.00 Fc (mm/hr)= 4.00 Cum.Inf. (mm)= (ii) TIME STEP (DT) SHOULD BE SMALLER OR EQUAL THAN THE STORAGE COEFFICIENT. (iii) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY Page 8

33 CALIB STANDHYD (0008) Area (ha)= 0.53 ID= 1 DT= 2.0 min Total Imp(%)= Dir. Conn.(%)= IMPERVIOUS PERVIOUS (i) Surface Area (ha)= Dep. Storage (mm)= Average Slope (%)= Length (m)= Mannings n = Max.Eff.Inten.(mm/hr)= NaN over (min) Storage Coeff. (min)= 2.61 (ii) 4.19 (ii) Unit Hyd. Tpeak (min)= Unit Hyd. peak (cms)= *TOTALS* PEAK FLOW (cms)= (iii) TIME TO PEAK (hrs)= RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = (i) HORTONS EQUATION SELECTED FOR PERVIOUS LOSSES: Fo (mm/hr)= K (1/hr)= 4.00 Fc (mm/hr)= 4.00 Cum.Inf. (mm)= (ii) TIME STEP (DT) SHOULD BE SMALLER OR EQUAL THAN THE STORAGE COEFFICIENT. (iii) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY DIVERT HYD (0064) IN= 1 # OUT= 5 Page 9

34 Outflow / Inflow Relationships Nov 28 detailled Flow 1 + Flow 2 + Flow 3 + Flow 4 + Flow 5 = Total (cms) (cms) (cms) (cms) (cms) (cms) AREA QPEAK TPEAK R.V. (ha) (cms) (hrs) (mm) TOTAL HYD.(ID= 1): ===================================================== ID= 2 ( 2) : ID= 3 ( 2) : ID= 4 ( 2) : ID= 5 ( 2) : ID= 6 ( 2) : ADD HYD (0013) = 3 AREA QPEAK TPEAK R.V. (ha) (cms) (hrs) (mm) ID1= 1 (0012): ID2= 2 (0004): ================================================== ID = 3 (0013): NOTE: PEAK FLOWS DO NOT INCLUDE BASEFLOWS IF ANY ADD HYD (0013) = 1 AREA QPEAK TPEAK R.V. (ha) (cms) (hrs) (mm) ID1= 3 (0013): Page 10

35 + ID2= 2 (0064): ================================================== ID = 1 (0013): NOTE: PEAK FLOWS DO NOT INCLUDE BASEFLOWS IF ANY ROUTE PIPE (0014) PIPE Number = 1.00 IN= 2---> OUT= 1 Diameter (mm)= DT= 2.0 min Length (m)= Slope (m/m)= Manning n = < TRAVEL TIME TABLE > DEPTH VOLUME FLOW RATE VELOCITY TRAV.TIME (m) (cu.m.) (cms) (m/s) min E E E E E E E E E E E E E E E E E E E <---- hydrograph ----> <-pipe / channel-> Page 11

36 AREA QPEAK TPEAK R.V. MAX DEPTH MAX VEL (ha) (cms) (hrs) (mm) (m) (m/s) INFLOW : ID= 2 (0013) OUTFLOW: ID= 1 (0014) CALIB STANDHYD (0005) Area (ha)= 0.25 ID= 1 DT= 2.0 min Total Imp(%)= Dir. Conn.(%)= IMPERVIOUS PERVIOUS (i) Surface Area (ha)= Dep. Storage (mm)= Average Slope (%)= Length (m)= Mannings n = Max.Eff.Inten.(mm/hr)= over (min) Storage Coeff. (min)= 1.70 (ii) 2.03 (ii) Unit Hyd. Tpeak (min)= Unit Hyd. peak (cms)= *TOTALS* PEAK FLOW (cms)= (iii) TIME TO PEAK (hrs)= RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = ***** WARNING: STORAGE COEFF. IS SMALLER THAN TIME STEP! (i) HORTONS EQUATION SELECTED FOR PERVIOUS LOSSES: Fo (mm/hr)= K (1/hr)= 4.00 Fc (mm/hr)= 4.00 Cum.Inf. (mm)= (ii) TIME STEP (DT) SHOULD BE SMALLER OR EQUAL Page 12

37 THAN THE STORAGE COEFFICIENT. (iii) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY ADD HYD (0015) = 3 AREA QPEAK TPEAK R.V. (ha) (cms) (hrs) (mm) ID1= 1 (0014): ID2= 2 (0005): ================================================== ID = 3 (0015): NOTE: PEAK FLOWS DO NOT INCLUDE BASEFLOWS IF ANY ROUTE PIPE (0016) PIPE Number = 1.00 IN= 2---> OUT= 1 Diameter (mm)= DT= 2.0 min Length (m)= Slope (m/m)= Manning n = < TRAVEL TIME TABLE > DEPTH VOLUME FLOW RATE VELOCITY TRAV.TIME (m) (cu.m.) (cms) (m/s) min E E E E E E E E E E Page 13

38 E E E E E E E E E <---- hydrograph ----> <-pipe / channel-> AREA QPEAK TPEAK R.V. MAX DEPTH MAX VEL (ha) (cms) (hrs) (mm) (m) (m/s) INFLOW : ID= 2 (0015) OUTFLOW: ID= 1 (0016) CALIB STANDHYD (0006) Area (ha)= 0.09 ID= 1 DT= 2.0 min Total Imp(%)= Dir. Conn.(%)= IMPERVIOUS PERVIOUS (i) Surface Area (ha)= Dep. Storage (mm)= Average Slope (%)= Length (m)= Mannings n = Max.Eff.Inten.(mm/hr)= over (min) Storage Coeff. (min)= 0.56 (ii) 2.63 (ii) Unit Hyd. Tpeak (min)= Unit Hyd. peak (cms)= *TOTALS* PEAK FLOW (cms)= (iii) TIME TO PEAK (hrs)= Page 14

39 RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = ***** WARNING: STORAGE COEFF. IS SMALLER THAN TIME STEP! (i) HORTONS EQUATION SELECTED FOR PERVIOUS LOSSES: Fo (mm/hr)= K (1/hr)= 4.00 Fc (mm/hr)= 4.00 Cum.Inf. (mm)= (ii) TIME STEP (DT) SHOULD BE SMALLER OR EQUAL THAN THE STORAGE COEFFICIENT. (iii) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY ADD HYD (0017) = 3 AREA QPEAK TPEAK R.V. (ha) (cms) (hrs) (mm) ID1= 1 (0016): ID2= 2 (0006): ================================================== ID = 3 (0017): NOTE: PEAK FLOWS DO NOT INCLUDE BASEFLOWS IF ANY RESERVOIR (0018) IN= 2---> OUT= 1 DT= 2.0 min OUTFLOW STORAGE OUTFLOW STORAGE (cms) (ha.m.) (cms) (ha.m.) Page 15

40 AREA QPEAK TPEAK R.V. (ha) (cms) (hrs) (mm) INFLOW : ID= 2 (0017) OUTFLOW: ID= 1 (0018) PEAK FLOW REDUCTION [Qout/Qin](%)= 7.09 TIME SHIFT OF PEAK FLOW (min)= MAXIMUM STORAGE USED (ha.m.)= DIVERT HYD (0019) IN= 1 # OUT= 5 Outflow / Inflow Relationships Flow 1 + Flow 2 + Flow 3 + Flow 4 + Flow 5 = Total (cms) (cms) (cms) (cms) (cms) (cms) Page 16

41 AREA QPEAK TPEAK R.V. (ha) (cms) (hrs) (mm) TOTAL HYD.(ID= 1): ===================================================== ID= 2 ( 2) : ID= 3 ( 2) : ID= 4 ( 2) : ID= 5 ( 2) : ID= 6 ( 2) : CALIB STANDHYD (0007) Area (ha)= 0.48 ID= 1 DT= 2.0 min Total Imp(%)= Dir. Conn.(%)= IMPERVIOUS PERVIOUS (i) Surface Area (ha)= Dep. Storage (mm)= Average Slope (%)= Length (m)= Mannings n = Max.Eff.Inten.(mm/hr)= over (min) Storage Coeff. (min)= 1.83 (ii) (ii) Unit Hyd. Tpeak (min)= Unit Hyd. peak (cms)= *TOTALS* PEAK FLOW (cms)= (iii) TIME TO PEAK (hrs)= RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = ***** WARNING: STORAGE COEFF. IS SMALLER THAN TIME STEP! Page 17

42 (i) HORTONS EQUATION SELECTED FOR PERVIOUS LOSSES: Fo (mm/hr)= K (1/hr)= 4.00 Fc (mm/hr)= 4.00 Cum.Inf. (mm)= (ii) TIME STEP (DT) SHOULD BE SMALLER OR EQUAL THAN THE STORAGE COEFFICIENT. (iii) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY ADD HYD (0020) = 3 AREA QPEAK TPEAK R.V. (ha) (cms) (hrs) (mm) ID1= 1 (0019): ID2= 2 (0007): ================================================== ID = 3 (0020): NOTE: PEAK FLOWS DO NOT INCLUDE BASEFLOWS IF ANY RESERVOIR (0021) IN= 2---> OUT= 1 DT= 2.0 min OUTFLOW STORAGE OUTFLOW STORAGE (cms) (ha.m.) (cms) (ha.m.) Page 18

43 AREA QPEAK TPEAK R.V. (ha) (cms) (hrs) (mm) INFLOW : ID= 2 (0020) OUTFLOW: ID= 1 (0021) PEAK FLOW REDUCTION [Qout/Qin](%)= TIME SHIFT OF PEAK FLOW (min)= MAXIMUM STORAGE USED (ha.m.)= DIVERT HYD (0022) IN= 1 # OUT= 5 Outflow / Inflow Relationships Flow 1 + Flow 2 + Flow 3 + Flow 4 + Flow 5 = Total (cms) (cms) (cms) (cms) (cms) (cms) AREA QPEAK TPEAK R.V. (ha) (cms) (hrs) (mm) Page 19

44 TOTAL HYD.(ID= 1): ===================================================== ID= 2 ( 2) : ID= 3 ( 2) : ID= 4 ( 2) : ID= 5 ( 2) : ID= 6 ( 2) : CALIB STANDHYD (0009) Area (ha)= 0.34 ID= 1 DT= 2.0 min Total Imp(%)= Dir. Conn.(%)= IMPERVIOUS PERVIOUS (i) Surface Area (ha)= Dep. Storage (mm)= Average Slope (%)= Length (m)= Mannings n = Max.Eff.Inten.(mm/hr)= NaN over (min) Storage Coeff. (min)= 1.86 (ii) 2.00 (ii) Unit Hyd. Tpeak (min)= Unit Hyd. peak (cms)= *TOTALS* PEAK FLOW (cms)= (iii) TIME TO PEAK (hrs)= RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = ***** WARNING: STORAGE COEFF. IS SMALLER THAN TIME STEP! (i) HORTONS EQUATION SELECTED FOR PERVIOUS LOSSES: Fo (mm/hr)= K (1/hr)= 4.00 Fc (mm/hr)= 4.00 Cum.Inf. (mm)= Page 20

45 (ii) TIME STEP (DT) SHOULD BE SMALLER OR EQUAL THAN THE STORAGE COEFFICIENT. (iii) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY CALIB STANDHYD (0010) Area (ha)= 0.28 ID= 1 DT= 2.0 min Total Imp(%)= Dir. Conn.(%)= IMPERVIOUS PERVIOUS (i) Surface Area (ha)= Dep. Storage (mm)= Average Slope (%)= Length (m)= Mannings n = Max.Eff.Inten.(mm/hr)= over (min) Storage Coeff. (min)= 2.16 (ii) 3.73 (ii) Unit Hyd. Tpeak (min)= Unit Hyd. peak (cms)= *TOTALS* PEAK FLOW (cms)= (iii) TIME TO PEAK (hrs)= RUNOFF VOLUME (mm)= TOTAL RAINFALL (mm)= RUNOFF COEFFICIENT = (i) HORTONS EQUATION SELECTED FOR PERVIOUS LOSSES: Fo (mm/hr)= K (1/hr)= 4.00 Fc (mm/hr)= 4.00 Cum.Inf. (mm)= (ii) TIME STEP (DT) SHOULD BE SMALLER OR EQUAL THAN THE STORAGE COEFFICIENT. (iii) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY. Page 21

Stormwater Management Report

Stormwater Management Report 1150 Morrison Drive, Suite 410 Ottawa, ON, K2H 8S9 T.613.828.7800 F.613.828.2600 Project No. 2151738A Stormwater Management Report Hydro Ottawa Hunt Club Drive, Gloucester, Ontario Prepared for Rev.1;

More information

Caledon Villas Corporation

Caledon Villas Corporation Caledon Villas Corporation Functional Servicing Report Caledon Villas Residential Subdivision Town of Caledon Project No. L11-557 April 2014 Caledon Villas Corporation Town of Caledon Caledon Villas Residential

More information

D. B. G R A Y E N G I N E E R I N G I N C.

D. B. G R A Y E N G I N E E R I N G I N C. STORMWATER MANAGEMENT REPORT 948 Hunt lub Road Ottawa, Ontario Report No. 12020-SWM August 27, 2012 Revised April 21, 2014 Revised December 9, 2014 Revised April 14, 2015 D. B. G R A Y E N G I N E E R

More information

HOTEL KANATA 160 HEARST WAY KANATA, ONTARIO SERVICING REPORT. Prepared for: David Johnston Architect. Prepared By:

HOTEL KANATA 160 HEARST WAY KANATA, ONTARIO SERVICING REPORT. Prepared for: David Johnston Architect. Prepared By: HOTEL KANATA 160 HEARST WAY KANATA, ONTARIO SERVICING REPORT Prepared for: David Johnston Architect Prepared By: BaseTech Consulting Inc. 309 Roywood Crescent Newmarket, Ontario L3Y 1A6 BCI Project No.

More information

SERVICING BRIEF & STORMWATER MANAGEMENT REPORT Colonial Road Sarsfield (Ottawa), Ontario. Report No June 15, 2017

SERVICING BRIEF & STORMWATER MANAGEMENT REPORT Colonial Road Sarsfield (Ottawa), Ontario. Report No June 15, 2017 SERVICING BRIEF & STORMWATER MANAGEMENT REPORT 2980 Colonial Road Sarsfield (Ottawa), Ontario Report No. 16033 June 15, 2017 D. B. G R A Y E N G I N E E R I N G I N C. Stormwater Management - Grading &

More information

Stormwater Guidelines and Case Studies. CAHILL ASSOCIATES Environmental Consultants West Chester, PA (610)

Stormwater Guidelines and Case Studies. CAHILL ASSOCIATES Environmental Consultants West Chester, PA (610) Stormwater Guidelines and Case Studies CAHILL ASSOCIATES Environmental Consultants West Chester, PA (610) 696-4150 www.thcahill.com Goals and Challenges for Manual State Stormwater Policy More Widespread

More information

STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1. DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT

STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1. DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1 DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT Prepared by: PAULUS, SOKOLOWSKI & SARTOR STORMWATER MANAGEMENT 1. Methodology

More information

WELCOME Lake Wabukayne OPEN HOUSE

WELCOME Lake Wabukayne OPEN HOUSE WELCOME Lake Wabukayne Sediment Removal Project OPEN HOUSE We are here to: Update you, the community, on recent developments and activities at Lake Wabukayne Present the preferred alternative and receive

More information

B805 TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES - OPSS 805

B805 TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES - OPSS 805 B805 MEASURES - OPSS 805 805.1 GENERAL Construction activities frequently remove protective cover and expose soil to accelerated rates of erosion. Sediments generated thereby can be conveyed via runoff

More information

FUNCTIONAL SERVICING REPORT AND SWM REPORT

FUNCTIONAL SERVICING REPORT AND SWM REPORT FUNCTIONAL SERVICING REPORT AND SWM REPORT 104 WHITE CRESCENT CITY OF BARRIE, COUNTY OF SIMCOE December 2018 18058 TABLE OF CONTENTS 1. INTRODUCTION... 4 2. SUPPORTING DOCUMENTS... 4 3. DESIGN POPULATION...

More information

ARTICLE 5 (PART 2) DETENTION VOLUME EXAMPLE PROBLEMS

ARTICLE 5 (PART 2) DETENTION VOLUME EXAMPLE PROBLEMS ARTICLE 5 (PART 2) DETENTION VOLUME EXAMPLE PROBLEMS Example 5.7 Simple (Detention Nomograph) Example 5.8 Offsite and Unrestricted Areas (HEC-HMS) Example 5.9 Ponds in Series w/ Tailwater (HEC-HMS) Example

More information

Table 1 - Infiltration Rates

Table 1 - Infiltration Rates Stantec Consulting Ltd. 100-300 Hagey Boulevard, Waterloo ON N2L 0A4 November 14, 2017 File: 161413228/10 Attention: Mr. Michael Witmer, BES, MPA, MCIP, RPP City of Guelph 1 Carden Street Guelph ON N1H

More information

1.0 INSPECTION ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER PROJECT, CARMACKS, YUKON. Dear Mr. West-Sells,

1.0 INSPECTION ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER PROJECT, CARMACKS, YUKON. Dear Mr. West-Sells, Doc. No. 162 Rev. 0 Mr. Paul West-Sells President & Chief Operating Officer Western Copper Corporation 2060-1111 West Georgia Street Vancouver, BC V6E 4M3 ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER

More information

STORMWATER DESIGN CALCULATIONS

STORMWATER DESIGN CALCULATIONS STORMWATER DESIGN CALCULATIONS REF : C7011-2390 AT 19a-23 MEMORIAL AVENUE BLACKWALL FOR MR KERR Contents 1.0 Detention System Requirements 1.1 Storage-Area calcs. 1.2 Data Files for Pre & Post Developed

More information

WATER MANAGEMENT REPORT FOR PAGE ESTATES

WATER MANAGEMENT REPORT FOR PAGE ESTATES WATER MANAGEMENT REPORT FOR PAGE ESTATES SLB Consulting of SW Florida, LLC PO Box 2826 Bonita Springs, FL. 34133 Phone: 239-948-9566 sandra@slbconsult.com C.O.A. # 25395 September 1, 2014 Sandra L. Bottcher

More information

Section 4: Model Development and Application

Section 4: Model Development and Application Section 4: Model Development and Application The hydrologic model for the Wissahickon Act 167 study was built using GIS layers of land use, hydrologic soil groups, terrain and orthophotography. Within

More information

Continuing Education Associated with Maintaining CPESC and CESSWI Certification

Continuing Education Associated with Maintaining CPESC and CESSWI Certification Continuing Education Associated with Maintaining CPESC and CESSWI Certification Module 2: Stormwater Management Principles for Earth Disturbing Activities Sponsors: ODOTs Local Technical Assistance Program

More information

EROSION CONTROL NARRATIVE

EROSION CONTROL NARRATIVE EROSION CONTROL NARRATIVE Erosion and sediment control has been designed for the Willow Bend Phase I Subdivision according to UDFCD and the City of Thornton criteria, in order to minimize erosion and sediment

More information

STORMWATER REPORT FRITO LAY SUBDIVISION NO. 3

STORMWATER REPORT FRITO LAY SUBDIVISION NO. 3 STORMWATER REPORT FRITO LAY SUBDIVISION NO. 3 May 2018 STORMWATER REPORT I. Subdivision Data a. The parcel is adjacent to the existing Frito Lay property in Topeka; and the subject plat application encompasses

More information

Guide to the use of the Erosion and Sediment Control Evaluation Tool

Guide to the use of the Erosion and Sediment Control Evaluation Tool Guide to the use of the Erosion and Sediment Control Evaluation Tool December 2017 If you require content in an alternate format please contact us at 905-895-1281 or by email at Accessibility@LSRCA.on.ca

More information

Materials. Use materials meeting the following.

Materials. Use materials meeting the following. 208.01 Section 208. SOIL EROSION AND SEDIMENTATION CONTROL 208.01 Description. Install and maintain erosion and sedimentation controls to minimize soil erosion and to control sedimentation from affecting

More information

City of Thornton Attn: Tim Semones Development Engineeering 9500 Civic Center Dr. Thornton, CO 80229

City of Thornton Attn: Tim Semones Development Engineeering 9500 Civic Center Dr. Thornton, CO 80229 Development Engineering Land Surveying Construction Administration District Services October 20, 2017 City of Thornton Attn: Tim Semones Development Engineeering 9500 Civic Center Dr. Thornton, CO 80229

More information

STORMWATER MANAGEMENT COMPUTATIONS. Mount Prospect

STORMWATER MANAGEMENT COMPUTATIONS. Mount Prospect STORMWATER MANAGEMENT COMPUTATIONS Mount Prospect MHG PROJECT No. 2011.173.11 November 6, 2014 Prepared for: Piney Meetinghouse Investments c/o Mr. Dennis Fling 14801 Clopper Road Boyds, MD 20841 (301)

More information

Rock & Aggregate Drop Inlet Protection

Rock & Aggregate Drop Inlet Protection Rock & Aggregate Drop Inlet Protection SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System Supplementary Trap Dispersive Soils

More information

Coarse Sediment Traps

Coarse Sediment Traps Coarse Sediment Traps SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils [2] Type 3 System Supplementary Trap Dispersive Soils [1] Though primarily

More information

Chapter 7 Mudflow Analysis

Chapter 7 Mudflow Analysis Chapter 7 Mudflow Analysis 7.0 Introduction This chapter provides information on the potential and magnitude of mud floods and mudflows that may develop in Aspen due to rainfall events, snowmelt, or rain

More information

D.M. Wills Associates Limited PARTNERS IN ENGINEERING. Stormwater Management Report. City of Peterborough

D.M. Wills Associates Limited PARTNERS IN ENGINEERING. Stormwater Management Report. City of Peterborough Stormwater Management Report City of Peterborough P-20-12 Parkway Corridor Class Environmental Assessment Jackson Park Parkhill Road West to Chemong Road D.M. Wills Project No. 12-5061 D.M. Wills Associates

More information

September 6, City of Thornton 9500 Civic Center Drive Thornton, CO (303) RE: Maverik Thornton, CO - Drainage Report

September 6, City of Thornton 9500 Civic Center Drive Thornton, CO (303) RE: Maverik Thornton, CO - Drainage Report September 6, 2016 City of Thornton 9500 Civic Center Drive Thornton, CO 80229 (303) 538-7295 RE: Maverik Thornton, CO - Drainage Report As per your request, we are submitting to you the drainage report

More information

Template for Sediment and Erosion Control Plan General Instructions. Section Instructions

Template for Sediment and Erosion Control Plan General Instructions. Section Instructions Template for Sediment and Erosion Control Plan General Instructions Introduction: Soil erosion and sediment deposition from farmlands can contribute to degraded surface water quality. Sediment delivery

More information

Construction Exits Rock pads

Construction Exits Rock pads Construction Exits Rock pads SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow [1] Clayey Soils Type 3 System Supplementary Trap Dispersive Soils [1] Minor

More information

Chapter 7 Mudflow Analysis

Chapter 7 Mudflow Analysis Chapter 7 Mudflow Analysis 7.0 Introduction This chapter provides information on the potential and magnitude of mud floods and mudflows that may develop in Aspen due to rainfall events, snowmelt, or rain

More information

STORMWATER MANAGEMENT ASSESSMENT TECHNICAL MEMORANDUM DRAFT FINAL FOSTER DRIVE AREA SANITARY SERVICING AND STORMWATER MANAGEMENT CLASS EA

STORMWATER MANAGEMENT ASSESSMENT TECHNICAL MEMORANDUM DRAFT FINAL FOSTER DRIVE AREA SANITARY SERVICING AND STORMWATER MANAGEMENT CLASS EA The City of Committed to Total Service Excellence STORMWATER MANAGEMENT ASSESSMENT TECHNICAL MEMORANDUM DRAFT FINAL FOSTER DRIVE AREA SANITARY SERVICING AND STORMWATER MANAGEMENT CLASS EA April 2015 Revised

More information

ENGINEERING HYDROLOGY

ENGINEERING HYDROLOGY ENGINEERING HYDROLOGY Prof. Rajesh Bhagat Asst. Professor Civil Engineering Department Yeshwantrao Chavan College Of Engineering Nagpur B. E. (Civil Engg.) M. Tech. (Enviro. Engg.) GCOE, Amravati VNIT,

More information

4. TEMPORARY ROAD CLOSURE MODIFICATION EMOND STREET MODIFICATION APPORTÉE À LA FERMETURE TEMPORAIRE DE LA RUE EMOND

4. TEMPORARY ROAD CLOSURE MODIFICATION EMOND STREET MODIFICATION APPORTÉE À LA FERMETURE TEMPORAIRE DE LA RUE EMOND 98 COMITÉ DES TRANSPORTS 4. TEMPORARY ROAD CLOSURE MODIFICATION EMOND STREET MODIFICATION APPORTÉE À LA FERMETURE TEMPORAIRE DE LA RUE EMOND COMMITTEE RECOMMENDATION That Council approve that the chain

More information

Project Description. Project Options. End Analysis On... Apr 26, :00:00. Rainfall Details

Project Description. Project Options. End Analysis On... Apr 26, :00:00. Rainfall Details Project Description File Name... 323 - Att Pond 3 East PIPES ONLY.SPF Project Options Flow Units... Elevation Type... Hydrology Method... EPA SWMM Infiltration Method... Link Routing Method... Enable Overflow

More information

Etobicoke Exfiltration System: Monitoring and Evaluation. Tim Van Seters Ryerson University July 24, 2015

Etobicoke Exfiltration System: Monitoring and Evaluation. Tim Van Seters Ryerson University July 24, 2015 Etobicoke Exfiltration System: Monitoring and Evaluation Tim Van Seters Ryerson University July 24, 2015 Presentation Outline Summary of 1994 1995 Candaras Associates study Summary of 1996-1998 SWAMP Study

More information

Submitted to: St. Johns River Power Park New Berlin Road Jacksonville, FL 32226

Submitted to: St. Johns River Power Park New Berlin Road Jacksonville, FL 32226 RUN-ON/RUN-OFF CONTROL SYSTEM PLAN RUN-ON AND RUN-OFF CONTROL SYSTEM PLAN St. Johns River Power Park Byproduct Storage Area B Phase I Development Submitted to: St. Johns River Power Park 11201 New Berlin

More information

Sediment Trap. At multiple locations within the project site where sediment control is needed.

Sediment Trap. At multiple locations within the project site where sediment control is needed. Sediment Trap SE-3 Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control

More information

U-Shaped Sediment Traps

U-Shaped Sediment Traps U-Shaped Sediment Traps SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils [1] Type 3 System Supplementary Trap Dispersive Soils [1] Generally

More information

ROCK EXCAVATION (GRADING) OPSS 206 INDEX

ROCK EXCAVATION (GRADING) OPSS 206 INDEX 206-2 - OPSS 206 INDEX 206-2.1 GENERAL 206-2.1.1 Classification of Rock Materials 206-2.1.2 Tender Items 206-2.1.3 Other Excavation Tender Items 206-2.1.4 Specifications 206-2.1.5 Special Provisions 206-2.1.6

More information

BRANDON LAKES AVENUE PRE AND POST CONDITIONS DRAINAGE REPORT

BRANDON LAKES AVENUE PRE AND POST CONDITIONS DRAINAGE REPORT BRANDON LAKES AVENUE PRE AND POST CONDITIONS DRAINAGE REPORT Hillsborough County Public Works County Center, 22nd Floor 601 E. Kennedy Blvd. Tampa, FL 33602 BRANDON LAKES AVENUE DRAINAGE IMPROVEMENTS Capital

More information

Advanced /Surface Hydrology Dr. Jagadish Torlapati Fall 2017 MODULE 2 - ROUTING METHODS

Advanced /Surface Hydrology Dr. Jagadish Torlapati Fall 2017 MODULE 2 - ROUTING METHODS Routing MODULE - ROUTING METHODS Routing is the process of find the distribution of flow rate and depth in space and time along a river or storm sewer. Routing is also called Flow routing or flood routing.

More information

Hydrogeological Assessment for Part of Lots 2 and 3, Concession 5, Township of Thurlow, County of Hastings 1.0 INTRODUCTION. 1.

Hydrogeological Assessment for Part of Lots 2 and 3, Concession 5, Township of Thurlow, County of Hastings 1.0 INTRODUCTION. 1. February 10,2017 25506400 Ontario Ltd. Foxboro, ON Attention: Brad Newbatt Re: Hydrogeological Assessment for Part of Lots 2 and 3, Concession 5, Township of Thurlow, County of Hastings 1.0 INTRODUCTION

More information

LOCATED IN INDIAN RIVER COUNTY PREPARED FOR S.J.R.W.M.D. AND F.W.C.D. DECEMBER, 2003 Updated 2007 Updated May 2014 PREPARED BY

LOCATED IN INDIAN RIVER COUNTY PREPARED FOR S.J.R.W.M.D. AND F.W.C.D. DECEMBER, 2003 Updated 2007 Updated May 2014 PREPARED BY FELLSMERE WATER CONTROL DISTRICT EAST MASTER DRAINAGE PLAN AND STORMWATER HYDROLOGIC ANALYSIS OF THE GRAVITY DRAINAGE SYSTEM LOCATED BETWEEN THE EAST BOUNDARY, LATERAL U, THE MAIN CANAL, AND DITCH 24 LOCATED

More information

TPDES: Soil, Erosion and Sedimentation Methods

TPDES: Soil, Erosion and Sedimentation Methods SAWS TPDES: Soil, Erosion and Sedimentation Methods Philip Handley Supervisor-Resource Protection & Compliance August 25, 2014 TPDES: Soil, Erosion and Sedimentation Methods Soil Common term: Dirt Common

More information

Drainage Analysis. Appendix F

Drainage Analysis. Appendix F Drainage Analysis Appendix F Golden View Drive Elizabeth Street LMORE CREEK Ricky Road Rabbit Creek Road LITTLE RABBIT CREEK East 156th Avenue MOA Project #10-026 Golden View Drive Intersection

More information

STORMWATER MANAGEMENT REPORT

STORMWATER MANAGEMENT REPORT STORMWATER MANAGEMENT REPORT THE FAIRWAYS AT EDGEWOOD LOTS 5 & 6, BLOCK 1201 TOWNSHIP OF RIVER VALE BERGEN COUNTY, NEW JERSEY PREPARED BY: DAPHNE A. GALVIN PROFESSIONAL ENGINEER LICENSE NO. 24GE03434900

More information

Suitable Applications Sediment traps should be considered for use:

Suitable Applications Sediment traps should be considered for use: Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective

More information

Sediment Control Practices. John Mathews Ohio Dept. of Natural Resources, Division of Soil and Water Resources

Sediment Control Practices. John Mathews Ohio Dept. of Natural Resources, Division of Soil and Water Resources Sediment Control Practices John Mathews Ohio Dept. of Natural Resources, Division of Soil and Water Resources Practices Treat the Largest Soil Particles Sand Sand Silt Clay Treated Untreated Settleable

More information

APPENDIX E GREATER SPRINGFIELD RELIABILTIY PROJECT DRAINAGE ANALYSIS FOR THE NEWGATE/PHELPS ROAD AND THE HATCHETT HILL ROAD AREAS

APPENDIX E GREATER SPRINGFIELD RELIABILTIY PROJECT DRAINAGE ANALYSIS FOR THE NEWGATE/PHELPS ROAD AND THE HATCHETT HILL ROAD AREAS APPENDIX E GREATER SPRINGFIELD RELIABILTIY PROJECT DRAINAGE ANALYSIS FOR THE NEWGATE/PHELPS ROAD AND THE HATCHETT HILL ROAD AREAS New England East-West Solution (NEEWS) Greater Springfield Reliability

More information

Specifications Whitcomb Elementary School Demolition January 15, 2016

Specifications Whitcomb Elementary School Demolition January 15, 2016 SECTION 31 2500 - EROSION CONTROL PART 1 - GENERAL 1.1 RELATED DOCUMENTS: A. The provisions of the Contract Documents apply to the work of this Section. B. The Virginia Erosion and Sediment Control Handbook,

More information

Flood Map. National Dataset User Guide

Flood Map. National Dataset User Guide Flood Map National Dataset User Guide Version 1.1.5 20 th April 2006 Copyright Environment Agency 1 Contents 1.0 Record of amendment... 3 2.0 Introduction... 4 2.1 Description of the Flood Map datasets...4

More information

Drainage Study for Civic Center Way

Drainage Study for Civic Center Way Drainage Study for 23401 Civic Center Way P.C.C.E. INC. CIVIL ENGINEERING AND DESIGN Drainage Study for 23401 Civic Center Way WHOLE FOODS AT THE PARK Prepared by: P.C.C.E. INC STEPHEN R. SMITH, P.E. 23801

More information

Selected Site BMPs: Why s the Water Muddy? John C. Hayes, Ph.D., P. E. Biosystems Engineering Clemson University

Selected Site BMPs: Why s the Water Muddy? John C. Hayes, Ph.D., P. E. Biosystems Engineering Clemson University Selected Site BMPs: Why s the Water Muddy? John C. Hayes, Ph.D., P. E. Biosystems Engineering Clemson University The BMP worked fine until last week when it rained! Turbidity Best Management Practices

More information

Woodford County Erosion Prevention Plan and Permit. Application #

Woodford County Erosion Prevention Plan and Permit. Application # Woodford County Erosion Prevention Plan and Permit Application # Date Instructions: Applicant will complete Parts A and B, and attach a proposed site diagram. This diagram must be completed in accordance

More information

APPENDIX G APPENDIX G SEDIMENT CONTAINMENT SYSTEM DESIGN RATIONALE

APPENDIX G APPENDIX G SEDIMENT CONTAINMENT SYSTEM DESIGN RATIONALE APPENDIX G SEDIMENT CONTAINMENT SYSTEM DESIGN RATIONALE March 18, 2003 This page left blank intentionally. March 18, 2003 G-2 FIGURES Page # Figure G.1 Estimated Runoff from Precipitation Over Different

More information

Template for Sediment and Erosion Control Plan General Instructions

Template for Sediment and Erosion Control Plan General Instructions Template for Sediment and Erosion Control Plan General Instructions Introduction: Soil erosion and sediment deposition from farmlands can contribute to degraded surface water quality. Sediment delivery

More information

Stage Discharge Tabulation for Only Orifice Flow

Stage Discharge Tabulation for Only Orifice Flow Stage Discharge Tabulation for Only Orifice Flow DEPTH STAGE DISCHARGE (meters) (feet) (meters) (feet) (m 3 /s) (ft 3 /s) 0 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 2.00 0.7 1.3 2.0 2.6 3.3 3.9 4.6

More information

Stormwater Inlet Sediment Traps

Stormwater Inlet Sediment Traps Stormwater Inlet Sediment Traps SEDIMENT CONTROL TECHNIQUES Photo 1 Kerb inlet Photo 2 Field (drop) inlet Table 1 provides the recommended default classification of various sediment control systems suitable

More information

The effectiveness of the Natural Resource Conservation Service (NRCS) and Huff rainfall distribution methods for use in detention basin design

The effectiveness of the Natural Resource Conservation Service (NRCS) and Huff rainfall distribution methods for use in detention basin design Scholars' Mine Masters Theses Student Theses and Dissertations Spring 2010 The effectiveness of the Natural Resource Conservation Service (NRCS) and Huff rainfall distribution methods for use in detention

More information

Orica Australia Pty Ltd Ammonium Nitrate Facility Upgrade

Orica Australia Pty Ltd Ammonium Nitrate Facility Upgrade Orica Australia Pty Ltd Ammonium Nitrate Facility Upgrade January 2010 Revision 0 Contents 1. Introduction 1 1.1 Purpose 1 1.2 Objectives 1 1.3 Relevant Environmental Legislation, Guidelines and Policies

More information

INTRODUCTION TO HYDROLOGIC MODELING USING HEC-HMS

INTRODUCTION TO HYDROLOGIC MODELING USING HEC-HMS INTRODUCTION TO HYDROLOGIC MODELING USING HEC-HMS By Thomas T. Burke, Jr., PhD, PE Luke J. Sherry, PE, CFM Christopher B. Burke Engineering, Ltd. October 8, 2014 1 SEMINAR OUTLINE Overview of hydrologic

More information

Jp2g Consultants Inc.

Jp2g Consultants Inc. Jp2g Consultants Inc. ENGINEERS PLANNERS PROJECT MANAGERS 1150 Morrison Drive, Suite 410 Ottawa, ON K2H 8S9 T 613-828-7800, F 613-828-2600, www.jp2g.com September 20, 2018 City of Ottawa Development Review

More information

Gully Erosion Part 1 GULLY EROSION AND ITS CAUSES. Introduction. The mechanics of gully erosion

Gully Erosion Part 1 GULLY EROSION AND ITS CAUSES. Introduction. The mechanics of gully erosion Gully Erosion Part 1 GULLY EROSION AND ITS CAUSES Gully erosion A complex of processes whereby the removal of soil is characterised by incised channels in the landscape. NSW Soil Conservation Service,

More information

Hydrology and Hydraulics Design Report. Background Summary

Hydrology and Hydraulics Design Report. Background Summary To: National Park Services Montezuma Castle National Monument Richard Goepfrich, Facility Manager From: Multicultural Technical Engineers Date: Tuesday - February 13, 2018 Subject: 30% Hydrology and Hydraulics

More information

ATTACHMENT D SNOW REMOVAL AND DE-ICING PROCEDURES

ATTACHMENT D SNOW REMOVAL AND DE-ICING PROCEDURES Interstate Reliability Project 345-kV Transmission Lines Development & Management Plan Volume 2 ATTACHMENT D SNOW REMOVAL AND DE-ICING PROCEDURES INTERSTATE RELIABILITY PROJECT The Interstate Reliability

More information

FHWA - HIGHWAY HYDROLOGY

FHWA - HIGHWAY HYDROLOGY The unit peak discharge is computed with Equation 5.6 by interpolating c 0, c, and c Table 5.5 using a type II distribution. The peak discharge is also calculated as follows. from Variable SI Unit U Unit.5444

More information

This site will utilize an infiltration berm to manage the two-year/24-hour volume increase.

This site will utilize an infiltration berm to manage the two-year/24-hour volume increase. Gates TETRA TECH, INC. By: RH Date: 1/30/2017 Subject: Gates Road Checked By: JB Date: 2/1/2017 PCSM Design and Evaluation PURPOSE: The purpose of these calculations is to design a Post-Construction Stormwater

More information

MS4: MAPPING CHALLENGES. Mike Towle Associate Planner, WestCOG

MS4: MAPPING CHALLENGES. Mike Towle Associate Planner, WestCOG MS4: MAPPING CHALLENGES Mike Towle Associate Planner, WestCOG mtowle@westcog.org Please contact or attribute author before using any images or data from this presentation Overview I. Theory and background

More information

The key natural hazards relevant to the Project area relate to seismic activity and flood risk.

The key natural hazards relevant to the Project area relate to seismic activity and flood risk. 21. NATURAL HAZARDS Overview The key natural hazards relevant to the Project area relate to seismic activity and flood risk. Seismic activity, including ground shaking and liquefaction, is a significant

More information

DRAINAGE REPORT FOR THORNTON SELF STORAGE THORNTON, COLORADO

DRAINAGE REPORT FOR THORNTON SELF STORAGE THORNTON, COLORADO DRAINAGE REPORT FOR THORNTON SELF STORAGE THORNTON, COLORADO Prepared by: Bowman Consulting 603 Park Point Dr. Suite 100 Golden, CO 80401 (303)-801-2900 June 29, 2015 Revised August 14, 2015 CERTIFICATE

More information

Hydrology Study Report

Hydrology Study Report Hafeez Consulting www.hafeezconsulting.com Civil/ Structural Engineering, Design & Construction 1451 S. Hacienda St. Anaheim CA 92804 (714) 225-4565 Fax (714)917-2977 engineer@hafeezconsulting.com Hydrology

More information

UTILITY REPORT FOR THORNTON SELF STORAGE THORNTON, COLORADO

UTILITY REPORT FOR THORNTON SELF STORAGE THORNTON, COLORADO UTILITY REPORT FOR THORNTON SELF STORAGE THORNTON, COLORADO Prepared by: Bowman Consulting 63 Park Point Dr. Suite 1 Golden, CO 841 (33)-81-29 June 29, 215 Revised August 14, 215 Revised September 3, 215

More information

PW 001 SNOW REMOVAL AND SANDING FOR ROADWAYS AND SIDEWALKS October 6, 2014 (#223-14) Original October 19, 2015; October 15, 2018 Public Works

PW 001 SNOW REMOVAL AND SANDING FOR ROADWAYS AND SIDEWALKS October 6, 2014 (#223-14) Original October 19, 2015; October 15, 2018 Public Works Policy Statement: The Village of Kitscoty will provide snow and ice control on municipal streets and sidewalks according to determined priorities. Purpose: To provide direction and information to employees

More information

THE MINISTRY OF ENERGY AND ENERGY INDUSTRIES MINERALS DIVISION MINE DESIGN TEMPLATE OPERATOR NAME: OPERATOR ADDRESS: PHONE NUMBER: FACSIMILE:

THE MINISTRY OF ENERGY AND ENERGY INDUSTRIES MINERALS DIVISION MINE DESIGN TEMPLATE OPERATOR NAME: OPERATOR ADDRESS: PHONE NUMBER: FACSIMILE: THE MINISTRY OF ENERGY AND ENERGY INDUSTRIES MINERALS DIVISION MINE DESIGN TEMPLATE 1.0 GENERAL INFORMATION OPERATOR NAME: OPERATOR ADDRESS: PHONE NUMBER: FACSIMILE: NAME OF CONTACT: CELLULAR PHONE: EMAIL

More information

APPENDIX B HYDROLOGY

APPENDIX B HYDROLOGY APPENDIX B HYDROLOGY TABLE OF CONTENTS 1.0 INTRODUCTION... 1 2.0 PROBABLE MAXIMUM PRECIPITATION (PMP)... 1 3.0 DESIGN FLOW CALCULATION... 1 4.0 DIVERSION CHANNEL SIZING... 2 5.0 REFERENCES... 4 LIST OF

More information

Technical Memorandum. City of Salem, Stormwater Management Design Standards. Project No:

Technical Memorandum. City of Salem, Stormwater Management Design Standards. Project No: Technical Memorandum 6500 SW Macadam Avenue, Suite 200 Portland, Oregon, 97239 Tel: 503-244-7005 Fax: 503-244-9095 Prepared for: Project Title: City of Salem, Oregon City of Salem, Stormwater Management

More information

APPENDIX A: EROSION & SEDIMENT CONTROL FORMS

APPENDIX A: EROSION & SEDIMENT CONTROL FORMS APPENDIX A: EROSION & SEDIMENT CONTROL FORMS Croy Engineering # 1580.08 EROSION & SEDIMENT CONTROL FORMS Appendix-1 This page intentionally left blank. Croy Engineering # 1580.08 EROSION & SEDIMENT CONTROL

More information

CONSTRUCTION EXIT SEDIMENT BARRIER

CONSTRUCTION EXIT SEDIMENT BARRIER 241428_itizen ield Guide_v3 2/22/06 11:09 M Page 1 (1,1) ONSTRUTION EXIT stone pad located where traffic leaves a construction site to eliminate the transport of soil to public streets. SEDIMENT BRRIER

More information

December 11, 2006 File:

December 11, 2006 File: December 11, 2006 File: 15-85-38 Alberta Infrastructure and Transportation Room 301, Provincial Building 9621-96 Avenue Peace River, Alberta T8S 1T4 Attention: Mr. Ed Szmata PEACE REGION (SWAN HILLS AREA)

More information

Instream Sediment Control Systems

Instream Sediment Control Systems Instream Sediment Control Systems INSTREAM PRACTICES Photo 1 Photo 2 Modular sediment The information contained within this series of fact sheets deals only with the design of temporary instream sediment

More information

Stone Outlet Sediment Trap

Stone Outlet Sediment Trap 3.12 Sediment Control Description: A stone outlet sediment trap is a small detention area formed by placing a stone embankment with an integral stone filter outlet across a drainage swale for the purpose

More information

Bachelor of Biosystems Technology Faculty of Technology South Eastern University of Sri Lanka

Bachelor of Biosystems Technology Faculty of Technology South Eastern University of Sri Lanka Bachelor of Biosystems Technology Faculty of Technology South Eastern University of Sri Lanka BSE 11042 Principles of Irrigation Furrow Irrigation Running water in small channels (furrows) Water infiltration

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

Sediment Capture in Pervious Concrete Pavement tsystems: Effects on Hydrological Performance and Suspended Solids

Sediment Capture in Pervious Concrete Pavement tsystems: Effects on Hydrological Performance and Suspended Solids Concrete Sustainability Conference April 14 th 2010, Tempe, AZ Sediment Capture in Pervious Concrete Pavement tsystems: Effects on Hydrological l Performance and Suspended Solids Discharge Luis A. Mata,

More information

Rock Sizing for Multi-Pipe & Culvert Outlets

Rock Sizing for Multi-Pipe & Culvert Outlets Rock Sizing for Multi-Pipe & Culvert Outlets STORMWATER AND WATERWAY MANAGEMENT PRACTICES Photo 1 Rock pad outlet structure at end of a duel stormwater pipe outlet Photo 2 Rock pad outlet structure at

More information

Modeling Great Britain s Flood Defenses. Flood Defense in Great Britain. By Dr. Yizhong Qu

Modeling Great Britain s Flood Defenses. Flood Defense in Great Britain. By Dr. Yizhong Qu Modeling Great Britain s Flood Defenses AIRCurrents Editor s note: AIR launched its Inland Flood Model for Great Britain in December 2008. The hazard module captures the physical processes of rainfall-runoff

More information

CITY OF CAPE CORAL STORMWATER MASTER PLAN PHASE II - PART 1 BASINS 4, 10, & 14 SUB-BASIN DRAINAGE IMPROVEMENTS HYDRAULIC ANALYSIS SUMMARY

CITY OF CAPE CORAL STORMWATER MASTER PLAN PHASE II - PART 1 BASINS 4, 10, & 14 SUB-BASIN DRAINAGE IMPROVEMENTS HYDRAULIC ANALYSIS SUMMARY CITY OF CAPE CORAL STORMWATER MASTER PLAN PHASE II - PART 1 BASINS 4, 10, & 14 SUB-BASIN DRAINAGE IMPROVEMENTS HYDRAULIC ANALYSIS SUMMARY Cape Coral, FL Prepared for: The City of Cape Coral Public Works

More information

Climate Adaptation Challenges for Boston s Water and Sewer Systems

Climate Adaptation Challenges for Boston s Water and Sewer Systems National Association of Flood & Stormwater Management Agencies Climate Adaptation Challenges for Boston s Water and Sewer Systems John P Sullivan P.E. October 15,2014 Boston 1630 Boston 1630-2012 Boston

More information

Independent Environmental Audit Erosion and Sediment Control

Independent Environmental Audit Erosion and Sediment Control Independent Environmental Audit Erosion and Sediment Control Commencement of YOUNG TO BETHUNGRA LOOPING PIPELINE JUNE 2016 suite 1, 39 fitzmaurice st (po box 5464) wagga wagga nsw 2650 australia t (02)

More information

Sediment Trap. A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff through a stabilized spillway.

Sediment Trap. A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff through a stabilized spillway. Sediment Trap SC-15 Source: Caltrans Construction Site Best Management Practices Manual, 2003. Description A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff

More information

COUNCIL POLICY MANUAL

COUNCIL POLICY MANUAL COUNCIL POLICY MANUAL SECTION: PUBLIC WORKS SUBJECT: SNOW & ICE CONTROL POLICY 2012/2013 GOAL: Pages: 1 of 10 Approval Date: Dec. 3, 2012 Res. # 1001/2012 To annually identify the winter maintenance costs

More information

patersongroup Consulting Engineers April 20, 2010 File: PG1887-LET.01R Novatech Engineering Consultants Suite 200, 240 Michael Cowpland Drive

patersongroup Consulting Engineers April 20, 2010 File: PG1887-LET.01R Novatech Engineering Consultants Suite 200, 240 Michael Cowpland Drive patersongroup April 20, 2010 File: PG1887-LET.01R Novatech Engineering Consultants Suite 200, 240 Michael Cowpland Drive Ottawa, Ontario K2M 1P6 Attention: Mr. Adam Thompson Consulting Engineers 28 Concourse

More information

Agenda. INDOT Office of Environmental Services. Describe Results of FHWA QAR. Landscape and Waterway Permitting Unit. Interviews Site Inspections

Agenda. INDOT Office of Environmental Services. Describe Results of FHWA QAR. Landscape and Waterway Permitting Unit. Interviews Site Inspections Nathan Saxe Administrator, Ecology and Waterway Permitting Section Back to Basics: Erosion and Sediment Control FHWA INDOT Quality Assurance Review (QAR) Results 1 Agenda INDOT Office of Environmental

More information

Stormwater Outlet Sediment Traps

Stormwater Outlet Sediment Traps Stormwater Outlet Traps SEDIMENT CONTROL TECHNIQUES Photo 1 Excavated sediment trap just prior to scheduled clean-out (note energy dissipater at end of pipe) Photo 2 A supplementary straw bale barrier

More information

Appendix E Guidance for Shallow Flooding Analyses and Mapping

Appendix E Guidance for Shallow Flooding Analyses and Mapping Appendix E Guidance for Shallow Flooding Analyses and Mapping E.1 Introduction Different types of shallow flooding commonly occur throughout the United States. Types of flows that result in shallow flooding

More information

Roadway Traffic Noise Feasibility Assessment. Conservancy Subdivision. Ottawa, Ontario

Roadway Traffic Noise Feasibility Assessment. Conservancy Subdivision. Ottawa, Ontario Conservancy Subdivision Ottawa, Ontario REPORT: GWE17 151 Traffic Noise Prepared For: Andrew Finnson Barrhaven Conservancy East Inc. Ottawa, Ontario Prepared By: Joshua Foster, P.Eng., Principal Omar Daher,

More information

APPENDIX B DRAINAGE REPORT

APPENDIX B DRAINAGE REPORT APPENDIX B DRAINAGE REPORT B-1 South Lamar Blvd. Transportation Corridor Study Drainage Report Prepared for: City of Austin and HDR, Inc. Prepared by: and Services, Inc. Final 07-09-2015 Michael C. Meriwether,

More information

Standards for Soil Erosion and Sediment Control in New Jersey May 2012

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SEDIMENT BASIN Definition A barrier, dam, excavated pit, or dugout constructed across a waterway or at other suitable locations to intercept and retain sediment. Basins created by construction

More information

This site will utilize an infiltration berm to manage the two-year/24-hour volume increase.

This site will utilize an infiltration berm to manage the two-year/24-hour volume increase. Gates TETRA TECH, INC. By: RH Date: 11/11/2016 Subject: Gates Road Checked By: JB Date: 11/13/2016 PCSM Design and Evaluation PURPOSE: The purpose of these calculations is to design a Post-Construction

More information