EDSA IEC 909 SHORT CIRCUIT ANALYSIS

Size: px
Start display at page:

Download "EDSA IEC 909 SHORT CIRCUIT ANALYSIS"

Transcription

1 1.0 Tutorial Exercise This tutorial exercise will serve as a validation and verification test for the EDSA IEC 909 short circuit program. The tutorial will be based on two examples documented in the IEC 909 Short circuit current calculation in three-phase AC systems. These examples are: Example 1: Example 2: Calculation of short-circuit currents in a low-voltage system. Appendix A, section A-1, page 109. EDSA File Name: IEC1.eds Calculation of balanced short-circuit currents in a medium-voltage system, including the influence of motors. Appendix A, section A-2, page 125. EDSA File Name: IEC2.eds Each example will first be solved by longhand calculations, and then the corresponding pre-created EDSA file will be used to re-calculate the short circuit results. Once both analyses have been completed, a table of comparison will be presented. It is assumed, for this exercise, that the user is familiar with building EDSA job files using the ECAD interface. If not, please refer to sections 1.0 and 2.0 of the EDSA User s Guide to review the process. The program options used in this tutorial are as follows: IEC 909 Methodology IEC Maximum Voltages Peak Method C 2.0 IEC 909 Example 1 / Longhand Calculations 250 MVA (cq = 1.1) X/R = j kv 15 kv T1 630 kva 15/0.4kV 4% P = 6.5 LOAD T2 400 kva 15/0.4 kv 4% P = 4.6 LOAD j j F1 C j F2 Un = 380 V C j C j14.85 F3 C j0.136 F j F2 Vpu = j j F j Figure 1. Single line diagram and equivalent impedance diagram for IEC Example 1. Page 1

2 Figure 1 shows the system under study for the IEC example 1. The diagram shown in this figure is given, both in ohms and per unit. The calculation, however, will be done in per unit. Original data for the example had the following cable info. C mm 2, 10 meter length and j ohms/meter/ph = j 0.79 milliohms. C mm 2, 4 meter length and j ohms/meter/ph = j milliohms. C3 2-70mm 2, 20 meter length and j ohms/meter/ph = j milliohms. C4 2-50mm 2, 50 meter length and j ohms/meter/ph = j milliohms. The PU bases selected are 10 MVA, 15 kv and 0.4 kv. Utility source - The source is <35 kv, therefore the X/R = 10 per IEC (X = 0.995*Z, R = 0.1 X). c (Z EQUIPMENT BASE ) (MVA COMMON BASE ) Z COMMON BASE = MVA EQUIPMENT BASE Transformers using equation below Z QT = 1.1 * 1.0 * 10/250 = PU R MULTIPLIER = , R PU = X MULTIPLIER = , X PU = (Z EQUIPMENT BASE ) (MVA COMMON BASE ) Z COMMON BASE = MVA EQUIPMENT BASE 630 kva transformer T1, impedances on 630 kva base is: R PU = P LOSS /KVA RATED = 6.5/630 = X PU = (Z 2 - R 2 ) ½ = ( ) ½ = , X PU /R PU = kva transformer T2, impedance on a 400-kVA base is: Convert to 10 MVA base R PU = P LOSS /KVA RATED = 4.6/400 = X PU = (Z 2 - R 2 ) ½ = ( ) ½ = , X PU /R PU = 3.33 Z PU = 10 * ( j0.0387)/0.63 = j for 630 kva Tx Z PU = 10 * ( j0.0383)/0.4 = j for 400 kva Tx Cables are converted from ohms to per-unit on 10 MVA and 0.4-kV bases Z PU = Z OHM * (MVA COMMON BASE )/kv 2 BASE C1= j0.395 mohms = j PU C2= j0.136 mohms = j PU C3= j1.740 mohms = j PU C4= mohms = j PU These per unit values are shown on Figure 1. Page 2

3 Fault at F1, the impedance network is reduced by having the impedance of T1 in parallel with sum of the impedances of T2 +C2 +C1. C1 = j PU C2 = j PU T2 = j Sum j = deg T1 = j = deg Parallel of T1 and Sum = j Add source Z j Total = j = X/R = V PREFAULT = (380/400V) = 0.95 PU V I PU 400 =1/ = I k= c *(V PREFAULT )(I PU )(MVA COMMON BASE )/(1.732*kV) I k= 1.05* *10 /(1.732*0.4) = ka X/R = To determine the circuit X/R ratio to be used to determine the peak current all reactances are multiplied 0.40 and the system then reduced. The new per-unit impedances are: Source = j T1 = j T2 = j C1= j PU C2= j PU C3= j PU C4= j PU C1 = j PU C2 = j PU T2 = j Sum j = deg T1 = j = deg Parallel of T1 and Sum = j Add source Z j Total = j (X/R = ). X/R ADJ = 2.5 * (X/R 0.4 ) = 2.5* = This compares with X/R = 3.64 for the 50 Hz system. The X/R = 3.67 is used to calculate the peak current from i PEAK = 2 I k ( e -3(R/X) ). i PEAK = 2*32.81*( e 3/3.67) ) = ka Page 3

4 Fault at F2, the impedance network is reduced by having the impedance of T1 and C1 in parallel with the impedances of T2 +C2. C1 = j PU T1 = j PU Sum j = @ deg C2 = j PU T2 = j pu Sum j = deg Parallel of branches = j Add source Z j Total = j = X/R = (V PREFAULT ) = (380/400V) = 0.95 PU V I PU 400 =1/ = I k= c *(V PREFAULT )(I PU )(MVA COMMON BASE )/(1.732*kV) I k= 1.05* *10 /(1.732*0.4) = ka X/R = For peak currents using 0.4 times the impedance. C1 = j PU T1 = j pu Sum j = deg C2 = j PU T2 = j Sum j = deg Parallel of branches = j Add source Z j Total = j , R/X = X/R ADJ = 2.5 * (X/R 0.4 ) = 2.5* = This compares with X/R = for the 50 Hz system. The X/R = 3.51 is used to calculate the peak current from i PEAK = 2 I k ( e -3(R/X) ). i PEAK = 2*32.333*( e 3/3.512) ) = ka IEC calculated using a rounded value for( e 3/3.512) )=1.44 instead of Fault at F3, the impedance network was reduced for fault F2 to the common point. Cables C3 and C4 are added to that impedance. From fault F2 = j Complex, j using 0.4*X C3 = j j C4 = j j Total = j j @ X/R = Page 4

5 Fault current I k is , X/R = (V PREFAULT ) = (380/400V) = 0.95 PU V I PU 400 =1/ = I k= c *(V PREFAULT )(I PU )(MVA COMMON BASE )/(1.732*kV) I k= 1.05*0.95 *0.4581*10 /(1.732*0.4) = ka 0, X/R = system. X/R ADJ = 2.5 * (X/R 0.4 ) = 2.5* = This compares with X/R = for the 50 Hz The X/R = is used to calculate the peak current from i PEAK = 2 I k ( e -3(R/X) ). i PEAK = 2*6.595*( e 3/0.9055) ) = ka IEC calculated 9.89 using a rounded values I k and ( e -3(R/X) ). 3.0 IEC 909 Example 1 / EDSA Analysis Step 1. Select File. Step 2. Select Open. Step 3. Select IEC1.EDS. Step 4. Select Open. 3.1 Invoke the ECAD interface, and proceed to load the pre-formatted file for IEC example 1. The file is called IEC1.eds, and it can be loaded according to the procedure shown in the above screen capture. Page 5

6 Step 1. Click here to invoke the Short Circuit program. 3.2 Next, proceed to invoke the short circuit program, as indicated in the above screen capture. Page 6

7 Step 6 Select OK. Step 1 Select the Options icon. Step 2 Fill out the Options screen exactly as indicated here. Step 3 Select IEC. Step 4 Fill out the IEC 909 Calculation Control screen exactly as indicated here. Step 5 Select OK. 3.3 Once the Short Circuit interface appears, proceed to specify the required short circuit components, the calculation methodology, and the specific IEC calculation controls. Follow the methodology outlined in the screen-capture shown above. Page 7

8 Step 1 Select Update Answer File Step 2 Select Faults at all busses Step 3 Select OK. 3.4 Finally, run the analysis by following the procedure shown in the screen-capture above. Page 8

9 3.5 The IEC 909 report, showing the selected sections, is now presented in the output screen. At this point, the report can be printed out, copied to the clipboard or saved as a text file for third party software customisation. To exit, select Done from the menu. Page 9

10 4.0 IEC 909 Example 1 / Validation and Verification Table The following table shows a comparison between the results obtained using longhand calculations, EDSA and the results documented in the IEC 909 standard. IEC 909 example 1 (pp ) Location F1 F2 F3 Result Type Program Hand Calc Variance with IEC 909 Value Value Hand Calcs Example i peak % ½ cyc % I k % i peak % ½ cyc % I k % i peak % 9890 ½ cyc % I k % 6600 All variances with Hand Calculations and IEC 909 documents are attributed to round off on input data or results. 5.0 IEC 909 Example 2 / Longhand Calculations 750 MVA (cq = 1.1) X/R = j kv 33 kv C j ohm C j ohm C j C j T1 15 MVA 33/6.3 k V 15% X/R = 25 T2 15 MVA 33/6.3 k V 15% X/R = 25 T j T j Un = 6 kv F1 6 kv F1 M1 M2 M1 5 MW, U M = 6kV pf=0.86, eff = 0.97 I LR/ I M= 4, 4 pole X/R = 10 M3 M4 M2, M3, M4 1 MW, U M = 6kV pf=0.83, eff = 0.94 I LR/ I M= 5.5, 2 pole X/R = 10 M1 M2 M3 M j st Cy (IEC) j Int (IEC) M4 M2, M3, M j st Cy (IEC) j Int (IEC) Figure 2. Single line diagram and equivalent impedance diagram for IEC Example 2. Page 10

11 Figure 2 shows the system under study for the IEC example 2. The diagram shown in this figure is given both, in ohms and per unit. The calculation, however, will be done in per unit. The following table shows the data that corresponds to the motors. Size X/R Reactance >= 500 kw/pole (670 HP/pole) ZM < 500 kw/pole (670 HP/pole) ZM Grouped Low Voltage Motors ZM ZM = 100* IRATED/ILOCKED ROTOR IEC Motor X/R Ratios to be Used Example 2 - Impedance Calculations Source = MVA BASE * c/mva SOURCE = 10 * 1.1/750 = X/R = 10 = j PU Cable C1 & C2:Ohms (MVA BASE )/kv 2 = ( j0.485)10/33 2 = j PU Transformer T1 & T2: 25 MVA, X=15%, R = 0.6% MVA BASE (%Z)/(MVA TRAN * 100) = 0.1 X/R = 15/0.6 = 25 = j PU Equipment Data X/R Base kv PU R PU X Source 750 MVA Cable C j Cable C j Transf. T1 15 MVA,15%Z Transf T2 15 MVA,15%Z Data used in Short Circuit Calculations. Motor M1 at 6.0 kv, 5 MW and 4 Pole to 6.3 kv base 5MW/4pole = 1.25 MW/Pole has a X/R = 10 Motor MVA = MVA/PF/Eff = 5/0.86/0.97 = MVA 1st Cy Imp.= MVA BASE *kv MOT 2 /(kv BASE 2 *MVA MOT *I LR /I MOT ) = 10*6*6/(6.3*6.3*5.994/4)= PU = j PU Motors M2, M3, M4 at 6 kv 1 MW and 2 Pole to 6.3 kv base. 1MW/2pole = 0.5 MW/Pole has a X/R = 10 Motor MVA = MVA/PF/Eff = 1/0.83/0.94 = MVA 1st Cy Imp.=MVA BASE *kv MOT 2 /(kv BASE 2 *MVA MOT *I LR /I MOT ) =10*6*6/(6.3*6.3*1.282/5.5)= = j PU The standard provides both curves and equations to determine the currents from motors at breaking time. The interrupting time impedances are determined by using the factors : and q. Factor : accounts currents in both synchronous and asynchronous (induction motors) decaying from substransient to transient Page 11

12 impedance. Factor q is a second correction for asynchronous machines that accounts for different decay rates based on the motor size. The IEC example used 0.10 seconds for the breaking time. : = γ -0.26/X kg for t MIN = 0.02 seconds, Z kg = I kg/irg # : = γ -0.30/X kg for t MIN = 0.05 seconds : = γ -0.32/X kg for t MIN = 0.10 seconds : = γ -0.38/X kg for t MIN => 0.25 seconds, (not shown) # for a fault on generator terminals Z kg = c/[k G (Z G )] q = ln [m] for minimum time = 0.02 seconds q = ln [m] for minimum time = 0.05 seconds q = ln [m] for minimum time = 0.10 seconds m is the active power in MW per motor pole pair Motor M1, has 4 times inrush current at rated voltage. The inrush current is adjusted by the voltage factor c and is 4*1.1 = 4.4 and the motor has 2.5 MW per pole. Motors M2, M3, and M4 have 5.5 * 1.1 inrush current of 6.05 and 1 MW per pole. For motors => 1.0 MW per pole pair, the Standard specifies a X/R ratio of 10. The : and q values at 0.10 seconds are: Motor M1: : = 0.796, q = 0.680, :q = 0.541, Impedance multiplier = 1/:q = 1.85 Motor M2: : = 0.724, q = 0.570, :q = 0.413, Impedance multiplier = 1/:q = 2.42 The standard uses these multipliers to adjust the first cycle currents. The same total current will be calculated if the inverse multiplies are applied to the impedances. Motor MW Rating KV RPM Poles %X MVA HP per pole-pair X/R R PU Resistance X PU Reactance M1 M2 M3 M First Cycle Per-unit Motor Impedances on a 10-MVA base IEC First Cycle IEC Breaking Time (0.10 seconds) Motor MVA PU Resist. PU React. : Multiplier q Multiplier PU Resist. PU React. M1 M2 M3 M Motor Impedance for 1 st Cy. and Interrupting Time (10 MVA Base) Factors : and q for Rotating Equipment (Decay of Symmetrical Current) Following the procedure given in IEC-60909, the non-decaying ac fault current is first calculated on the 6 kv bus, then the motor contributions are added to it. Page 12

13 The equivalent impedance is determined by adding impedances C1 to T1 and C2 to T2 then paralleling the two and adding the remote source impedance. Transf T1 or T2 = j Cable C1 or C2 = j Total = Parallel transf and cables = j Source impedance = j Total = j = PU on 10 MVA, 6.3 kv base. I k of non-ac decay = 1.1*10 /0.067//3/6.3 = ka at X/R = Since the bus is operated at 6.0 kv, I k = *6.0/6.3 = = j ka Next, adding the decaying motor sources at 6.0 kv gives M1 = 1.1*10(6.0/6.3)/( j )//3/6.3 =2.553 = j 2.54 ka (X/R = 10) M2 = 1.1*10(6.0/6.3)/( j1.28)//3/6.3 = = j0.745ka (X/R =10) M3 and M4 are the same as M2. Total Sym. ka = * j( *0.745) = ka at X/R =11.2. The peak currents are added for each contribution separately. Using the equation for peak current I k PEAK =I k *[ , -3/(X/R) ]*/2 Transformer Source(X/R = 11.71) = *2.515 = ka = j ka peak Motor M1 (X/R = 10) = *2.469 = 6.3 ka = j ka peak Motor M1, M2, M3 (X/R = 10) = 3*0.748* = 5.540kA = j ka peak IbASYM = j = ka (Value in IEC Standard = ka due to rounding) Example 2 - Breaking Current Calculations at F1 To calculate the breaking time current at 0.10 seconds, the motor breaking currents are added to the nondecaying ac source current Ib ASYM = (I k 2 + I 2 DC ) ½ _(2Β f t /(X/R)), where I DC =I k */2, Transformers I k = j ka = ka I DC =I k*/2, _(2Β f t /(X/R)) = ( j )/2, _(2Β 50*0.1 /11.71) = j1.38 ka = Ib ASYM = [ ] 1/2 = ka M1 = 1.1*10 (6.0/6.3)/( j )//3/6.3 = ka at X/R = 10 (due to rounding of : and q Standard calculated 1.38 ka) Ik = j ka I DC =( j 2.54)/2, _(2Β 50*0.1 /10) = j ka = ka Ib ASYM = [ ] 1/2 = ka M2 = 1.1*10 (6.0/6.3)/( j )//3/6.3 = ka at X/R = 10 each motor (due to rounding of : and q Standard calculated ka) Page 13

14 Ik = j ka I DC =( j 0.745kA)/2, _(2Β 50*0.1 /10) = j ka = ka Ib ASYM = [ ] 1/2 = ka Total I SYM of transformer, M1, M2, M3, and M4 currents are: Transf. = j ka M1 = j ka M2(3) = j Total = j = ka Total I DC of transformer, M1, M2, M3, and M4 currents are: Transf. = j1.38 ka M1 = j ka M2(3) = j Total = j = ka (The Standard did a scale addition on the dc magnitude and left off the /2 in the IbASYM calcs.) IbASYM = [ ] 1/2 = ka (Standard gives ka) Since the sources having decaying ac current components are greater than 5% (>15% in this system) the fault currents are referred to as near to generator. This problem was redone using Method C for the first cycle peak. The motor impedances were included in the network reduction. Computer software was used reduce the network with reactances at 40% the 50Hz values. The final solution is given below with the Method C X/R AJD being used for both the peak and dc component. Total Sym. ka = ka at X/R =11.2. i PEAK = ka, X/R AJD = IbASYM = ka Comments on Calculation procedure The solution for Example 2 followed the procedure given in IEC To me it has several questionable items. 1. Why isn t method A, B, or C used in this example. It appears to present a 4 th method. Therefore, if this example is given to several engineers, a number of different correct answers can be obtained. Why not include the motors in the impedance reduction and let the math take care of the contribution? Including motor impedances would be more acceptable to computer programs. 2. From the IEC examples given, it is not clear how to handle a network in which the cable impedances to the motors are represented. If the fault currents at the terminal of the motors are to be calculated, and if the motors currents are added after the far from generator network is reduced, it appears that ohms law can be violated for some system configuration. Network action will affect the currents coming Page 14

15 from adjacent motors due to their cable impedances. To me, to motor current should not be added directly as if it does not make a difference. 3 The procedure shows that the first cycle network impedance from remote sources is assumed not to change for breaking time currents. While in example 2 this is correct, but in Example 3 ( not worked out here) the motor contribution from Busbar B and C have an influence on each other which was not taken into account during breaking time sample calculations. To me this again violates ohms law. 4 While I agree that a complex network reduction X/R ratio may not accurately represent the X/R ratio needed to obtain the peak current, IEC indicate that Method C is more accurate. But, the examples only use it on the first example. The Standard gives no references to support method C or several other procedures used in the Standard. 6.0 IEC 909 Example 2 / EDSA Analysis 6.1 Following the instructions outlined in steps 3.1 and 3.2, proceed to load the file IEC2.eds, and launch the short circuit program interface. Page 15

16 6.2 Following the same instructions outlined in step 3.3, proceed to select the options, and calculation control settings for this example. The above screen capture shows the what is needed. Notice that in IEC example 2, the 6 cycle X/R and AC component have been included in the calculation. Next, run the analysis according to the procedure explained in step 3.4. Page 16

17 6.3 Once again, the IEC 909 output screen, presents the selected output sections. At this point, the report can be printed out, copied to the clipboard or saved as a text file for third party software customisation. To exit, select Done from the menu. Page 17

18 7.0 IEC 909 Example 2 / Validation and Verification Table The following table shows a comparison between the results obtained using longhand calculations, EDSA and the results documented in the IEC 909 standard. IEC 909 example 2 (pp ) Location F1 Result Type Program Hand Calc Variance with IEC 909 Value Value Hand Calcs Example i peak % ½ cyc % I k % cyc Break % All variances with Hand Calculations and IEC 909 documents are attributed to round off on input data or results. Page 18

Fault Calculation Methods

Fault Calculation Methods ELEC9713 Industrial and Commercial Power Systems Fault Calculation Methods There are two major problems that can occur in electrical systems: these are open circuits and short circuits. Of the two, the

More information

Technical Concepts - Fault Analysis Methods

Technical Concepts - Fault Analysis Methods RATIO X/R Technical Concepts - Fault Analysis Methods Technical Concepts - Fault Analysis Methods (Continued) "What is the difference between a traditional fault calculation and an ANSI-based fault calculation"

More information

Module 3 : Sequence Components and Fault Analysis

Module 3 : Sequence Components and Fault Analysis Module 3 : Sequence Components and Fault Analysis Lecture 13 : Sequence Modeling (Tutorial) Objectives In this lecture we will solve tutorial problems on fault analysis in sequence domain Per unit values

More information

KINGS COLLEGE OF ENGINEERING Punalkulam

KINGS COLLEGE OF ENGINEERING Punalkulam KINGS COLLEGE OF ENGINEERING Punalkulam 613 303 DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING POWER SYSTEM ANALYSIS QUESTION BANK UNIT I THE POWER SYSTEM AN OVERVIEW AND MODELLING PART A (TWO MARK

More information

THE UNIVERSITY OF NEW SOUTH WALES. School of Electrical Engineering & Telecommunications FINALEXAMINATION. Session

THE UNIVERSITY OF NEW SOUTH WALES. School of Electrical Engineering & Telecommunications FINALEXAMINATION. Session Name: Student ID: Signature: THE UNIVERSITY OF NEW SOUTH WALES School of Electrical Engineering & Telecommunications FINALEXAMINATION Session 00 ELEC46 Power System Analysis TIME ALLOWED: 3 hours TOTAL

More information

EE 6501 POWER SYSTEMS UNIT I INTRODUCTION

EE 6501 POWER SYSTEMS UNIT I INTRODUCTION EE 6501 POWER SYSTEMS UNIT I INTRODUCTION PART A (2 MARKS) 1. What is single line diagram? A Single line diagram is diagrammatic representation of power system in which the components are represented by

More information

SSC-JE EE POWER SYSTEMS: GENERATION, TRANSMISSION & DISTRIBUTION SSC-JE STAFF SELECTION COMMISSION ELECTRICAL ENGINEERING STUDY MATERIAL

SSC-JE EE POWER SYSTEMS: GENERATION, TRANSMISSION & DISTRIBUTION SSC-JE STAFF SELECTION COMMISSION ELECTRICAL ENGINEERING STUDY MATERIAL 1 SSC-JE STAFF SELECTION COMMISSION ELECTRICAL ENGINEERING STUDY MATERIAL Power Systems: Generation, Transmission and Distribution Power Systems: Generation, Transmission and Distribution Power Systems:

More information

Fault Analysis Power System Representation

Fault Analysis Power System Representation .1. Power System Representation Single Line Diagram: Almost all modern power systems are three phase systems with the phases of equal magnitude and equal phase difference (i.e., 10 o ). These three phase

More information

Request Ensure that this Instruction Manual is delivered to the end users and the maintenance manager.

Request Ensure that this Instruction Manual is delivered to the end users and the maintenance manager. Request Ensure that this Instruction Manual is delivered to the end users and the maintenance manager. 1 -A - Introduction - Thank for your purchasing MITSUBISHI ELECTRIC MELPRO TM D Series Digital Protection

More information

Module 3 : Sequence Components and Fault Analysis

Module 3 : Sequence Components and Fault Analysis Module 3 : Sequence Components and Fault Analysis Lecture 12 : Sequence Modeling of Power Apparatus Objectives In this lecture we will discuss Per unit calculation and its advantages. Modeling aspects

More information

Modeling of Power System Components During Electromagnetic Transients

Modeling of Power System Components During Electromagnetic Transients Modeling of Power System Components During Electromagnetic Transients 1 Paweł Sowa, 2 Rafał Kumala and 3 Katarzyna Łuszcz 1, 2,3 Faculty of Electrical Engineering, Silesian University of Technology/ Institute

More information

B.E. / B.Tech. Degree Examination, April / May 2010 Sixth Semester. Electrical and Electronics Engineering. EE 1352 Power System Analysis

B.E. / B.Tech. Degree Examination, April / May 2010 Sixth Semester. Electrical and Electronics Engineering. EE 1352 Power System Analysis B.E. / B.Tech. Degree Examination, April / May 2010 Sixth Semester Electrical and Electronics Engineering EE 1352 Power System Analysis (Regulation 2008) Time: Three hours Answer all questions Part A (10

More information

Dynamic simulation of a five-bus system

Dynamic simulation of a five-bus system ELEC0047 - Power system dynamics, control and stability Dynamic simulation of a five-bus system Thierry Van Cutsem t.vancutsem@ulg.ac.be www.montefiore.ulg.ac.be/~vct November 2017 1 / 16 System modelling

More information

QUESTION BANK ENGINEERS ACADEMY. Power Systems Power System Stability 1

QUESTION BANK ENGINEERS ACADEMY. Power Systems Power System Stability 1 ower ystems ower ystem tability QUETION BANK. A cylindrical rotor generator delivers 0.5 pu power in the steady-state to an infinite bus through a transmission line of reactance 0.5 pu. The generator no-load

More information

Chapter 21. Harmonic Analysis

Chapter 21. Harmonic Analysis Chapter 21 Harmonic Analysis Because of the wide and ever increasing applications of power electronic devices, such as variable speed drives, uninterruptible power supplies (UPS), static power converters,

More information

INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous)

INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad - 500 043 ELECTRICAL AND ELECTRONICS ENGINEERING QUESTION BANK Course Name : Computer Methods in Power Systems Course Code : A60222

More information

Basic Math for Relay Technicians. Hands On Relay School 2015 Presented by Charlene Reyes

Basic Math for Relay Technicians. Hands On Relay School 2015 Presented by Charlene Reyes Basic Math for Relay Technicians Hands On Relay School 2015 Presented by Charlene Reyes Overview Order of Operations and Order of Magnitude Unit Analysis and Conversions Trigonometry Rectangular and Polar

More information

EE2351 POWER SYSTEM ANALYSIS UNIT I: INTRODUCTION

EE2351 POWER SYSTEM ANALYSIS UNIT I: INTRODUCTION EE2351 POWER SYSTEM ANALYSIS UNIT I: INTRODUCTION PART: A 1. Define per unit value of an electrical quantity. Write equation for base impedance with respect to 3-phase system. 2. What is bus admittance

More information

7. Transient stability

7. Transient stability 1 7. Transient stability In AC power system, each generator is to keep phase relationship according to the relevant power flow, i.e. for a certain reactance X, the both terminal voltages V1and V2, and

More information

Introduction to Synchronous. Machines. Kevin Gaughan

Introduction to Synchronous. Machines. Kevin Gaughan Introduction to Synchronous Machines Kevin Gaughan The Synchronous Machine An AC machine (generator or motor) with a stator winding (usually 3 phase) generating a rotating magnetic field and a rotor carrying

More information

SHORT QUESTIONS AND ANSWERS. Year/ Semester/ Class : III/ V/ EEE Academic Year: Subject Code/ Name: EE6501/ Power System Analysis

SHORT QUESTIONS AND ANSWERS. Year/ Semester/ Class : III/ V/ EEE Academic Year: Subject Code/ Name: EE6501/ Power System Analysis Srividya colllege of Engg & Tech,Virudhunagar Sri Vidya College of Engineering And Technology Virudhunagar 626 005 Department of Electrical and Electronics Engineering QUESTION BANK SHORT QUESTIONS AND

More information

Generators. What its all about

Generators. What its all about Generators What its all about How do we make a generator? Synchronous Operation Rotor Magnetic Field Stator Magnetic Field Forces and Magnetic Fields Force Between Fields Motoring Generators & motors are

More information

ECE 325 Electric Energy System Components 7- Synchronous Machines. Instructor: Kai Sun Fall 2015

ECE 325 Electric Energy System Components 7- Synchronous Machines. Instructor: Kai Sun Fall 2015 ECE 325 Electric Energy System Components 7- Synchronous Machines Instructor: Kai Sun Fall 2015 1 Content (Materials are from Chapters 16-17) Synchronous Generators Synchronous Motors 2 Synchronous Generators

More information

University of Jordan Faculty of Engineering & Technology Electric Power Engineering Department

University of Jordan Faculty of Engineering & Technology Electric Power Engineering Department University of Jordan Faculty of Engineering & Technology Electric Power Engineering Department EE471: Electrical Machines-II Tutorial # 2: 3-ph Induction Motor/Generator Question #1 A 100 hp, 60-Hz, three-phase

More information

Symmetrical Fault Current Calculations Unlv

Symmetrical Fault Current Calculations Unlv We have made it easy for you to find a PDF Ebooks without any digging. And by having access to our ebooks online or by storing it on your computer, you have convenient answers with symmetrical fault current

More information

5SJ4...-.HG Circuit Breakers to IEC and UL 489

5SJ4...-.HG Circuit Breakers to IEC and UL 489 Siemens AG 009 5SJ...-.HG Circuit Breakers to IEC and UL 89 BETA Low-Voltage Circuit Protection Compliance with industry standards is a must in today's manufacturing environment. Worldwide acceptance is

More information

ECEN 460 Exam 1 Fall 2018

ECEN 460 Exam 1 Fall 2018 ECEN 460 Exam 1 Fall 2018 Name: KEY UIN: Section: Score: Part 1 / 40 Part 2 / 0 Part / 0 Total / 100 This exam is 75 minutes, closed-book, closed-notes. A standard calculator and one 8.5 x11 note sheet

More information

Synchronous Machines

Synchronous Machines Synchronous Machines Synchronous generators or alternators are used to convert mechanical power derived from steam, gas, or hydraulic-turbine to ac electric power Synchronous generators are the primary

More information

SESSION 3. Short Circuit Calculations, Unsymmetrical Faults. Leonard Bohmann, Michigan State University Elham Makram, Clemson University

SESSION 3. Short Circuit Calculations, Unsymmetrical Faults. Leonard Bohmann, Michigan State University Elham Makram, Clemson University SESSON Short Circuit Calculations, Unsymmetrical Faults Leonard Bohmann, Michigan State University Elham Makram, Clemson University Short Circuit Calculations Leonard Bohmann Michigan State University

More information

EE 451 Power System Stability

EE 451 Power System Stability EE 451 Power System Stability Power system operates in synchronous mode Power system is subjected to a wide range of disturbances (small and large) - Loads and generation changes - Network changes - Faults

More information

ECEN 667 Power System Stability Lecture 18: Voltage Stability, Load Models

ECEN 667 Power System Stability Lecture 18: Voltage Stability, Load Models ECEN 667 Power System Stability Lecture 18: Voltage Stability, Load Models Prof. Tom Overbye Dept. of Electrical and Computer Engineering Texas A&M University, overbye@tamu.edu 1 Announcements Read Chapter

More information

POWER SEMICONDUCTOR BASED ELECTRIC DRIVES

POWER SEMICONDUCTOR BASED ELECTRIC DRIVES POWER SEMICONDUCT BASED ELECTRIC DRIVES [Time: 3 Hrs] [Max. Marks: 80] Instructions: Solve any six questions from Q.No (1 or 2), Q.No (3 or 4), Q.No (5 or 6), Q.No (7 or 8), Q.No (9 or 10), Q.No (11 or

More information

ELEC Introduction to power and energy systems. The per unit system. Thierry Van Cutsem

ELEC Introduction to power and energy systems. The per unit system. Thierry Van Cutsem ELEC0014 - Introduction to power and energy systems The per unit system Thierry Van Cutsem t.vancutsem@ulg.ac.be www.montefiore.ulg.ac.be/~vct October 2018 1 / 12 Principle The per unit system Principle

More information

C60N circuit breakers0 B, C and D curves IEC 60898: 6000 A, IEC : 10 ka

C60N circuit breakers0 B, C and D curves IEC 60898: 6000 A, IEC : 10 ka C0N circuit breakers0 B, C and s IEC 0898: 000 A, IEC 097-: 0 ka Function b The circuit-breakers combine the following functions: v protection of circuits against short-circuit currents v protection of

More information

DISTANCE RELAY SETTINGS

DISTANCE RELAY SETTINGS DISTANCE RELAY SETTINGS Introduction Commonly used >33kV Determine whether impedance measured is within set characteristic. Non-unit protection (boundaries not defined) During normal operation impedance

More information

Last Comments on Short-Circuit Analysis

Last Comments on Short-Circuit Analysis Last Comments on Short-Circuit Analysis.0 Exam summary Work all HW problems and know them; Read notes Read related book sections Topics:. Symmetrical faults (no book section) 2. Zbus building (9.3-9.6)

More information

EE Branch GATE Paper 2010

EE Branch GATE Paper 2010 Q.1 Q.25 carry one mark each 1. The value of the quantity P, where, is equal to 0 1 e 1/e 2. Divergence of the three-dimensional radial vector field is 3 1/r 3. The period of the signal x(t) = 8 is 0.4

More information

Chapter 8: Unsymmetrical Faults

Chapter 8: Unsymmetrical Faults Chapter 8: Unsymmetrical Faults Introduction The sequence circuits and the sequence networks developed in the previous chapter will now be used for finding out fault current during unsymmetrical faults.

More information

Equivalent Circuits with Multiple Damper Windings (e.g. Round rotor Machines)

Equivalent Circuits with Multiple Damper Windings (e.g. Round rotor Machines) Equivalent Circuits with Multiple Damper Windings (e.g. Round rotor Machines) d axis: L fd L F - M R fd F L 1d L D - M R 1d D R fd R F e fd e F R 1d R D Subscript Notations: ( ) fd ~ field winding quantities

More information

Lesson 17: Synchronous Machines

Lesson 17: Synchronous Machines Lesson 17: Synchronous Machines ET 332b Ac Motors, Generators and Power Systems Lesson 17_et332b.pptx 1 Learning Objectives After this presentation you will be able to: Explain how synchronous machines

More information

Motor-CAD combined electromagnetic and thermal model (January 2015)

Motor-CAD combined electromagnetic and thermal model (January 2015) Motor-CAD combined electromagnetic and thermal model (January 2015) Description The Motor-CAD allows the machine performance, losses and temperatures to be calculated for a BPM machine. In this tutorial

More information

Massachusetts Institute of Technology Department of Electrical Engineering and Computer Science Electric Machines

Massachusetts Institute of Technology Department of Electrical Engineering and Computer Science Electric Machines Massachusetts Institute of Technology Department of Electrical Engineering and Computer Science 6.685 Electric Machines Problem Set 10 Issued November 11, 2013 Due November 20, 2013 Problem 1: Permanent

More information

EE2351 POWER SYSTEM OPERATION AND CONTROL UNIT I THE POWER SYSTEM AN OVERVIEW AND MODELLING PART A

EE2351 POWER SYSTEM OPERATION AND CONTROL UNIT I THE POWER SYSTEM AN OVERVIEW AND MODELLING PART A EE2351 POWER SYSTEM OPERATION AND CONTROL UNIT I THE POWER SYSTEM AN OVERVIEW AND MODELLING PART A 1. What are the advantages of an inter connected system? The advantages of an inter-connected system are

More information

Reading a GE PSLF *.epc into PWS. Tracy Rolstad Avista System Planning WECC PWSUG, 14 March 2012

Reading a GE PSLF *.epc into PWS. Tracy Rolstad Avista System Planning WECC PWSUG, 14 March 2012 Reading a GE PSLF *.epc into PWS Tracy Rolstad Avista System Planning WECC PWSUG, 14 March 2012 Open Case, Select What Options (these are defaults)? Start with GE Nothing

More information

Lecture (20) DC Machine Examples Start of Synchronous Machines

Lecture (20) DC Machine Examples Start of Synchronous Machines Lecture (20) DC Machine Examples Start of Synchronous Machines Energy Systems Research Laboratory, FIU All rights reserved. 20-1 Energy Systems Research Laboratory, FIU All rights reserved. 20-2 Ra R f

More information

Tutorial 2: Modelling Transmission

Tutorial 2: Modelling Transmission Tutorial 2: Modelling Transmission In our previous example the load and generation were at the same bus. In this tutorial we will see how to model the transmission of power from one bus to another. The

More information

DHANALAKSHMI SRINIVASAN COLLEGE OF ENGINEERING AND TECHNOLOGY Mamalapuram Chennai QUESTION BANK V SEMESTER. EE6501-Power system Analysis

DHANALAKSHMI SRINIVASAN COLLEGE OF ENGINEERING AND TECHNOLOGY Mamalapuram Chennai QUESTION BANK V SEMESTER. EE6501-Power system Analysis DHANALAKSHMI SRINIVASAN COLLEGE OF ENGINEERING AND TECHNOLOGY Mamalapuram Chennai DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING QUESTION BANK V SEMESTER EE6501-Power system Analysis Regulation 2013

More information

In the previous chapter, attention was confined

In the previous chapter, attention was confined 4 4 Principles of Power System CHAPTE CHAPTE 8 Unsymmetrical Fault Calculations 8. Usymmetrical Faults on -Phase System 8. Symmetrical Components Method 8. Operator a 8.4 Symmetrical Components in Terms

More information

ROEVER COLLEGE OF ENGINEERING & TECHNOLOGY ELAMBALUR, PERAMBALUR DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING ELECTRICAL MACHINES I

ROEVER COLLEGE OF ENGINEERING & TECHNOLOGY ELAMBALUR, PERAMBALUR DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING ELECTRICAL MACHINES I ROEVER COLLEGE OF ENGINEERING & TECHNOLOGY ELAMBALUR, PERAMBALUR-621220 DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING ELECTRICAL MACHINES I Unit I Introduction 1. What are the three basic types

More information

GATE 2010 Electrical Engineering

GATE 2010 Electrical Engineering GATE 2010 Electrical Engineering Q.1 Q.25 carry one mark each 1. The value of the quantity P, where P = xe dx, is equal to (A) 0 (B) 1 (C) e (D) 1/e 2. Divergence of the three-dimensional radial vector

More information

RLC Circuits. 1 Introduction. 1.1 Undriven Systems. 1.2 Driven Systems

RLC Circuits. 1 Introduction. 1.1 Undriven Systems. 1.2 Driven Systems RLC Circuits Equipment: Capstone, 850 interface, RLC circuit board, 4 leads (91 cm), 3 voltage sensors, Fluke mulitmeter, and BNC connector on one end and banana plugs on the other Reading: Review AC circuits

More information

Regulating Transformers in Sequence Domain

Regulating Transformers in Sequence Domain ECE523: Lecture 25; Page 1/8 pu 1 Regulating Transformers in Sequence Domain A three-phase voltage regulating transformer has a per unit leakage reactance of.1, and steps the voltage from 69 kv to 35 kv.

More information

CHAPTER 5 SIMULATION AND TEST SETUP FOR FAULT ANALYSIS

CHAPTER 5 SIMULATION AND TEST SETUP FOR FAULT ANALYSIS 47 CHAPTER 5 SIMULATION AND TEST SETUP FOR FAULT ANALYSIS 5.1 INTRODUCTION This chapter describes the simulation model and experimental set up used for the fault analysis. For the simulation set up, the

More information

UNIT I INTRODUCTION Part A- Two marks questions

UNIT I INTRODUCTION Part A- Two marks questions ROEVER COLLEGE OF ENGINEERING & TECHNOLOGY ELAMBALUR, PERAMBALUR-621220 DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING DESIGN OF ELECTRICAL MACHINES UNIT I INTRODUCTION 1. Define specific magnetic

More information

Electromagnetic Torque From Event Report Data A Measure of Machine Performance

Electromagnetic Torque From Event Report Data A Measure of Machine Performance Electromagnetic Torque From Event Report Data A Measure of Machine Performance Derrick Haas and Dale Finney Schweitzer Engineering Laboratories, Inc. 7 SEL Overview Electromagnetic torque calculation Modeling

More information

BETA Protecting. Low-Voltage Fuse Systems. LV HRC fuse links. 3/36 Siemens ET B1 2008

BETA Protecting. Low-Voltage Fuse Systems. LV HRC fuse links. 3/36 Siemens ET B1 2008 LV HRC fuse links Overview LV HRC fuses are used for installation systems in non-residential, commercial and industrial buildings as well as in switchboards of power supply companies. They therefore protect

More information

EE 742 Chapter 3: Power System in the Steady State. Y. Baghzouz

EE 742 Chapter 3: Power System in the Steady State. Y. Baghzouz EE 742 Chapter 3: Power System in the Steady State Y. Baghzouz Transmission Line Model Distributed Parameter Model: Terminal Voltage/Current Relations: Characteristic impedance: Propagation constant: π

More information

MCB NB1-63H Miniature Circuit Breaker

MCB NB1-63H Miniature Circuit Breaker NB-H Miniature Circuit Breaker. General. Function protection of circuits against short-circuit currents, protection of circuits against overload currents, switch, isolation, NB-H circuit-breakers are used

More information

ELECTRIC POWER CIRCUITS BASIC CONCEPTS AND ANALYSIS

ELECTRIC POWER CIRCUITS BASIC CONCEPTS AND ANALYSIS Contents ELEC46 Power ystem Analysis Lecture ELECTRC POWER CRCUT BAC CONCEPT AND ANALY. Circuit analysis. Phasors. Power in single phase circuits 4. Three phase () circuits 5. Power in circuits 6. ingle

More information

and cables for offshore wind connection

and cables for offshore wind connection Transient analysis of transformers and cables for offshore wind connection Bjørn Gustavsen SINTEF Energy Research Trondheim, Norway Wind power R&D seminar deep sea offshore wind: Trondheim, Norway, 20-21

More information

Fault Locating PRESENTED BY ERIK SCHELLENBERG IDAHO POWER

Fault Locating PRESENTED BY ERIK SCHELLENBERG IDAHO POWER Fault Locating PRESENTED BY ERIK SCHELLENBERG IDAHO POWER Topics Impedance Based Reactance Method Takagi Method Modifications to Takagi Method TWS & Double Ended Negative Sequence One Line Equivalent Thevenin

More information

Lab 10: DC RC circuits

Lab 10: DC RC circuits Name: Lab 10: DC RC circuits Group Members: Date: TA s Name: Objectives: 1. To understand current and voltage characteristics of a DC RC circuit 2. To understand the effect of the RC time constant Apparatus:

More information

POWER SYSTEM STABILITY

POWER SYSTEM STABILITY LESSON SUMMARY-1:- POWER SYSTEM STABILITY 1. Introduction 2. Classification of Power System Stability 3. Dynamic Equation of Synchronous Machine Power system stability involves the study of the dynamics

More information

ECE 585 Power System Stability

ECE 585 Power System Stability Homework 1, Due on January 29 ECE 585 Power System Stability Consider the power system below. The network frequency is 60 Hz. At the pre-fault steady state (a) the power generated by the machine is 400

More information

TELANGANA/ANDHRA PRADESH TRANSCO/GENCO/DISCUM Assistant Engineer Examination ELECTRICAL ENGINEERING (Previous Paper 7) AP TRANSCO - AP GENCO-AE QUESTION PAPER 1. In two wattmeter method of 3-phase power

More information

Varius SUMMARY OF MODELS OF HRC FUSE-LINKS. Type PVA10 / PV10 PV14 PV22 Rated current I n up to 32 A up to 63 A up to 125 A Rated voltage U n

Varius SUMMARY OF MODELS OF HRC FUSE-LINKS. Type PVA10 / PV10 PV14 PV22 Rated current I n up to 32 A up to 63 A up to 125 A Rated voltage U n Varius SUMMARY OF MODELS OF HRC FUSE-LINKS Type A / Rated current I n up to A up to up to A Rated voltage U n AC V, V V, V, 9 V V, V, 9 V DC V V V Fuse-link size x8 x x8 Utilization category of the fuse-link

More information

IGEE 402 Power System Analysis. FINAL EXAMINATION - SAMPLE Fall 2004

IGEE 402 Power System Analysis. FINAL EXAMINATION - SAMPLE Fall 2004 IGEE 402 Power System Analysis FINAL EXAMINATION - SAMPLE Fall 2004 Special instructions: - Duration: 80 minutes. - Material allowed: a crib sheet (double sided 8.5 x ), calculator. - Attempt 5 out of

More information

SCHOOL OF ELECTRICAL, MECHANICAL AND MECHATRONIC SYSTEMS. Transient Stability LECTURE NOTES SPRING SEMESTER, 2008

SCHOOL OF ELECTRICAL, MECHANICAL AND MECHATRONIC SYSTEMS. Transient Stability LECTURE NOTES SPRING SEMESTER, 2008 SCHOOL OF ELECTRICAL, MECHANICAL AND MECHATRONIC SYSTEMS LECTURE NOTES Transient Stability SPRING SEMESTER, 008 October 7, 008 Transient Stability Transient stability refers to the ability of a synchronous

More information

Brief Steady of Power Factor Improvement

Brief Steady of Power Factor Improvement International Journal of Electrical Engineering. ISSN 0974-2158 Volume 6, Number 5 (2013), pp. 531-539 International Research PublicationHouse http://www.irphouse.com Brief Steady of Power Factor Improvement

More information

C120N circuit-breakers B, C and D curves EN 60898/EN 61009: IEC : 10 ka

C120N circuit-breakers B, C and D curves EN 60898/EN 61009: IEC : 10 ka C0N circuit-breakers B, C and D curves EN 09/EN 009: 0000 - IEC 097-: 0 ka function # protection of cables against overloads and short-circuits in final distribution # manual control and isolation # earth

More information

Dynamics of the synchronous machine

Dynamics of the synchronous machine ELEC0047 - Power system dynamics, control and stability Dynamics of the synchronous machine Thierry Van Cutsem t.vancutsem@ulg.ac.be www.montefiore.ulg.ac.be/~vct October 2018 1 / 38 Time constants and

More information

LESSON 20 ALTERNATOR OPERATION OF SYNCHRONOUS MACHINES

LESSON 20 ALTERNATOR OPERATION OF SYNCHRONOUS MACHINES ET 332b Ac Motors, Generators and Power Systems LESSON 20 ALTERNATOR OPERATION OF SYNCHRONOUS MACHINES 1 LEARNING OBJECTIVES After this presentation you will be able to: Interpret alternator phasor diagrams

More information

You know for EE 303 that electrical speed for a generator equals the mechanical speed times the number of poles, per eq. (1).

You know for EE 303 that electrical speed for a generator equals the mechanical speed times the number of poles, per eq. (1). Stability 1 1. Introduction We now begin Chapter 14.1 in your text. Our previous work in this course has focused on analysis of currents during faulted conditions in order to design protective systems

More information

Section 5. TADS Data Reporting Instruction Manual DRAFT Section 5 and Associated Appendices With Proposed Event Type Numbers

Section 5. TADS Data Reporting Instruction Manual DRAFT Section 5 and Associated Appendices With Proposed Event Type Numbers Section 5 TADS Data Reporting Instruction Manual DRAFT Section 5 and Associated Appendices With Proposed Event Type Numbers Rev. 5/10/2010 1 Section 5 Form for Event ID and Event Type Number Data TO s

More information

ECEN 667 Power System Stability Lecture 20: Oscillations, Small Signal Stability Analysis

ECEN 667 Power System Stability Lecture 20: Oscillations, Small Signal Stability Analysis ECEN 667 Power System Stability Lecture 20: Oscillations, Small Signal Stability Analysis Prof. Tom Overbye Dept. of Electrical and Computer Engineering Texas A&M University, overbye@tamu.edu 1 Announcements

More information

Boise State University Department of Electrical and Computer Engineering ECE 212L Circuit Analysis and Design Lab

Boise State University Department of Electrical and Computer Engineering ECE 212L Circuit Analysis and Design Lab Objectives Boise State University Department of Electrical and Computer Engineering ECE 22L Circuit Analysis and Design Lab Experiment #4: Power Factor Correction The objectives of this laboratory experiment

More information

Behaviour of synchronous machine during a short-circuit (a simple example of electromagnetic transients)

Behaviour of synchronous machine during a short-circuit (a simple example of electromagnetic transients) ELEC0047 - Power system dynamics, control and stability (a simple example of electromagnetic transients) Thierry Van Cutsem t.vancutsem@ulg.ac.be www.montefiore.ulg.ac.be/~vct October 2018 1 / 25 Objectives

More information

ES205 Analysis and Design of Engineering Systems: Lab 1: An Introductory Tutorial: Getting Started with SIMULINK

ES205 Analysis and Design of Engineering Systems: Lab 1: An Introductory Tutorial: Getting Started with SIMULINK ES205 Analysis and Design of Engineering Systems: Lab 1: An Introductory Tutorial: Getting Started with SIMULINK What is SIMULINK? SIMULINK is a software package for modeling, simulating, and analyzing

More information

JRE SCHOOL OF Engineering

JRE SCHOOL OF Engineering JRE SCHOOL OF Engineering Class Test-1 Examinations September 2014 Subject Name Electromechanical Energy Conversion-II Subject Code EEE -501 Roll No. of Student Max Marks 30 Marks Max Duration 1 hour Date

More information

SRV02-Series Rotary Experiment # 1. Position Control. Student Handout

SRV02-Series Rotary Experiment # 1. Position Control. Student Handout SRV02-Series Rotary Experiment # 1 Position Control Student Handout SRV02-Series Rotary Experiment # 1 Position Control Student Handout 1. Objectives The objective in this experiment is to introduce the

More information

Incorporation of Asynchronous Generators as PQ Model in Load Flow Analysis for Power Systems with Wind Generation

Incorporation of Asynchronous Generators as PQ Model in Load Flow Analysis for Power Systems with Wind Generation Incorporation of Asynchronous Generators as PQ Model in Load Flow Analysis for Power Systems with Wind Generation James Ranjith Kumar. R, Member, IEEE, Amit Jain, Member, IEEE, Power Systems Division,

More information

ISSP User Guide CY3207ISSP. Revision C

ISSP User Guide CY3207ISSP. Revision C CY3207ISSP ISSP User Guide Revision C Cypress Semiconductor 198 Champion Court San Jose, CA 95134-1709 Phone (USA): 800.858.1810 Phone (Intnl): 408.943.2600 http://www.cypress.com Copyrights Copyrights

More information

Transient Stability Assessment of Synchronous Generator in Power System with High-Penetration Photovoltaics (Part 2)

Transient Stability Assessment of Synchronous Generator in Power System with High-Penetration Photovoltaics (Part 2) Journal of Mechanics Engineering and Automation 5 (2015) 401-406 doi: 10.17265/2159-5275/2015.07.003 D DAVID PUBLISHING Transient Stability Assessment of Synchronous Generator in Power System with High-Penetration

More information

Analysis of factors affecting station capacitor bank switching transients

Analysis of factors affecting station capacitor bank switching transients Scholars' Mine Masters Theses Student Research & Creative Works 1971 Analysis of factors affecting station capacitor bank switching transients M. Davarpanah Follow this and additional works at: http://scholarsmine.mst.edu/masters_theses

More information

Varius SUMMARY OF MODELS OF HRC FUSE-LINKS

Varius SUMMARY OF MODELS OF HRC FUSE-LINKS SUMMARY OF MODELS OF HRC FUSE-LINKS Type PNA000 PHNA000 PNA00 PHNA00 Rated current I n up to A up to 0 A up to A up to 0 A Rated voltage U n AC 00 V, 00 V 90 V 00 V 90 V DC 0 V 0 V 0 V 0 V Fuse-link size

More information

Q. 1 Q. 5 carry one mark each.

Q. 1 Q. 5 carry one mark each. GATE 2019 General Aptitude (GA) Set-3 Q. 1 Q. 5 carry one mark each. Q.1 I am not sure if the bus that has been booked will be able to all the students. (A) sit (B) deteriorate (C) fill (D) accommodate

More information

CHAPTER 3 ENERGY EFFICIENT DESIGN OF INDUCTION MOTOR USNG GA

CHAPTER 3 ENERGY EFFICIENT DESIGN OF INDUCTION MOTOR USNG GA 31 CHAPTER 3 ENERGY EFFICIENT DESIGN OF INDUCTION MOTOR USNG GA 3.1 INTRODUCTION Electric motors consume over half of the electrical energy produced by power stations, almost the three-quarters of the

More information

Selecting the current rating for equipment

Selecting the current rating for equipment Selecting the current rating for equipment 1. Rated current: the maximum continuous load current. Short-time withstand current: thermal withstand current term term is given for 1s or 3s short circuit current

More information

MSBCCL Series Asynchronous Three-Phase Brake Motors With Squirrel Cage Rotor Direct Current Brake

MSBCCL Series Asynchronous Three-Phase Brake Motors With Squirrel Cage Rotor Direct Current Brake NEMA MOTOR GOST MOTOR IEC MOTOR MSBCCL Series Asynchronous Three-Phase Motors ith Squirrel Cage Rotor Direct Current PUMP D.C. MOTOR GENERATOR MSBCCL series-enclosed construction externally ventilated-sizes

More information

Data Bulletin. SEPAM 49RMS Application Note Protection for Motor Applications Class Number SEPAM 49RMS Protection for Motor Applications

Data Bulletin. SEPAM 49RMS Application Note Protection for Motor Applications Class Number SEPAM 49RMS Protection for Motor Applications Data Bulletin 3000DB08 09/008 LaVergne, TN, USA SEPAM 49RMS Application Note Protection for Motor Applications Class Number 3000 SEPAM 49RMS Protection for Motor Applications Introduction Thermal protection

More information

DATA RACK BUSBAR. Data Rack Busbar Systems A.

DATA RACK BUSBAR. Data Rack Busbar Systems A. Data Rack Busbar Systems 250...1000 A www.eae.com.tr Overview Overview To power the mission critical IT infrastructures on the Data Rack Cabinets, EAE offers a highly flexible and reliable Busbar System

More information

Chapter 4. Synchronous Generators. Basic Topology

Chapter 4. Synchronous Generators. Basic Topology Basic Topology Chapter 4 ynchronous Generators In stator, a three-phase winding similar to the one described in chapter 4. ince the main voltage is induced in this winding, it is also called armature winding.

More information

A Comparative Analysis of Three Phase Induction Motor Performance Evaluation

A Comparative Analysis of Three Phase Induction Motor Performance Evaluation RESEARCH ARTICLE International Journal of Engineering and Techniques - Volume 2 Issue 3, May June 216 OPEN ACCESS A Comparative Analysis of Three Phase Induction Motor Performance Evaluation 1 France O.

More information

Commissioning testing of a 1 MVA Superconducting transformer featuring 2G HTS Roebel cable

Commissioning testing of a 1 MVA Superconducting transformer featuring 2G HTS Roebel cable Commissioning testing of a 1 MVA Superconducting transformer featuring 2G HTS Roebel cable Glasson N, Staines M, Allpress N, Badcock R 10:45 2M-LS-O2 OUTLINE Introduction Electrical Design Specifications

More information

EE2351 POWER SYSTEM ANALYSIS

EE2351 POWER SYSTEM ANALYSIS EE351 POWER SYSTEM ANALYSIS A.Ahamed Riazudeen EEE DEPARTMENT 1 UNIT I INTRODUCTION Power system network 3 SINGLE LINE DIAGRAM It is a diagrammatic representation of a power system in which the components

More information

Chapter 6. Induction Motors. Copyright The McGraw-Hill Companies, Inc. Permission required for reproduction or display.

Chapter 6. Induction Motors. Copyright The McGraw-Hill Companies, Inc. Permission required for reproduction or display. Chapter 6 Induction Motors 1 The Development of Induced Torque in an Induction Motor Figure 6-6 The development of induced torque in an induction motor. (a) The rotating stator field B S induces a voltage

More information

CHAPTER 2 CAPACITANCE REQUIREMENTS OF SIX-PHASE SELF-EXCITED INDUCTION GENERATORS

CHAPTER 2 CAPACITANCE REQUIREMENTS OF SIX-PHASE SELF-EXCITED INDUCTION GENERATORS 9 CHAPTER 2 CAPACITANCE REQUIREMENTS OF SIX-PHASE SELF-EXCITED INDUCTION GENERATORS 2.. INTRODUCTION Rapidly depleting rate of conventional energy sources, has led the scientists to explore the possibility

More information

The Operation of a Generator on Infinite Busbars

The Operation of a Generator on Infinite Busbars The Operation of a Generator on Infinite Busbars In order to simplify the ideas as much as possible the resistance of the generator will be neglected; in practice this assumption is usually reasonable.

More information

EEE3405 ELECTRICAL ENGINEERING PRINCIPLES 2 - TEST

EEE3405 ELECTRICAL ENGINEERING PRINCIPLES 2 - TEST ATTEMPT ALL QUESTIONS (EACH QUESTION 20 Marks, FULL MAKS = 60) Given v 1 = 100 sin(100πt+π/6) (i) Find the MS, period and the frequency of v 1 (ii) If v 2 =75sin(100πt-π/10) find V 1, V 2, 2V 1 -V 2 (phasor)

More information

University of TN Chattanooga Physics 1040L 8/18/2012 PHYSICS 1040L LAB LAB 4: R.C. TIME CONSTANT LAB

University of TN Chattanooga Physics 1040L 8/18/2012 PHYSICS 1040L LAB LAB 4: R.C. TIME CONSTANT LAB PHYSICS 1040L LAB LAB 4: R.C. TIME CONSTANT LAB OBJECT: To study the discharging of a capacitor and determine the time constant for a simple circuit. APPARATUS: Capacitor (about 24 μf), two resistors (about

More information