1 Power Supply Position in Northern Region For 28-Oct-2018 POWER SYSTEM OPERATION CORPORATION LIMITED NORTHERN REGIONAL LOAD DESPATCH CENTRE DAILY OPERATION REPORT OF NORTHERN REGION Date of Reporting:29-Oct Regional Availability/Demand: Evening Peak (19:00) MW Off-Peak (03:00) MW Day Energy(Net MU) Demand Met Shortage(-)/Surplus(+) Requirement Freq (Hz) Demand Met Shortage(-)/Surplus.. Requirement Freq (Hz) Demand Met Shortage 40, , , , (A)'s Load Deails (At Periphery) in MU: 's Control Area Generation (Net MU) Drawal Sch Act Drawal UI Requirement Shortage Consumption Thermal Hydro Gas/Naptha/ OthersBiomass/Small Diesel Solar Wind Hyd/Co-gen etc.) Total (Net MU) (Net MU) (Net MU) (Net MU) (Net MU) (Net MU) PUNJAB HARYANA RAJASTHAN DELHI UTTAR PRADESH UTTARAKHAND HIMACHAL PRADESH JAMMU & KASHMIR CHANDIGARH Region (B) Demand Met (Peak and off-peak Hrs) Evening Peak (19:00) MW Off-Peak (03:00) MW Demand Met Shortage(-)/Surplus(+) UI STOA/PX Transaction Demand Met Shortage(-)/Sur.. UI STOA/PX Transaction PUNJAB 5, ,650 4, ,145 HARYANA 5, , RAJASTHAN 9, ,506 8, ,086 DELHI 3, , ,444 UTTAR PRADESH 12, , UTTARAKHAND 1, , HIMACHAL PRADESH JAMMU & KASHMIR 1, , , CHANDIGARH Region 40, ,805 34, ,482 2(C)'s Demand Met in MWs (Maximum Demand Met and Maximum requirement of the day details) Maximum Demand, corresponding shortage and requirement details for the day Maximum requirement, corresponding shortage and demand details for the day Maximum Demand Met Shortage(-) /Surplus(+) Requirement at the of the day Time during at maximum max demand met of Maximum Requirement of Shortage(-) /Surplus(+) demand the day the day Time during at maximum Demand Met at maximum Requirement requiremnet PUNJAB 5,475 8:00 0 5,475 5,475 8:00 0 5,475 HARYANA 5,547 19:00 0 5,547 5,547 19:00 0 5,547 RAJASTHAN 10,780 8: ,780 10,780 8: ,780 DELHI 3,301 12:00 0 3,301 3,301 12:00 0 3,301 UP 13,034 20: ,034 13,034 20: ,034 UTTARAKHAND 1,641 19:00 0 1,641 1,641 19:00 0 1,641 HP 1,361 9:00 0 1,361 1,361 9:00 0 1,361 J&K 2,022 20: ,527 2,527 20: ,022 CHANDIGARH : : NR 40,934 19: ,394 41,394 19: ,934 3(A) Entities Generation: CHANDIGARH NIL Inst. Capacity N/A N/A Day Peak Day Energy Total Total
2 DELHI BADARPUR TPS( 2 * * 100 ) : RAJGHAT TPS( 2 * 67.5 ) Total THERMAL BAWANA GPS( 2 * * 216 ) 1, : DELHI GAS TURBINES( 3 * * 30 ) : PRAGATI GAS TURBINES( 1 * * ) : RITHALA GPS( 3 * 36 ) Total GAS/NAPTHA/DIESEL 2, BIOMASS( 1 * 16 ) SOLAR( 1 * 2 ) Total DELHI 2, HARIYANA DCRTPP (YAMUNA NAGAR)( 2 * 300 ) JHAJJAR(CLP)( 2 * 660 ) 1, MAGNUM DIESEL (IPP)( 4 * 6.3 ) PANIPAT TPS( 2 * * 250 ) RGTPP( KHEDAR)( 2 * 600 ) 1, Total THERMAL 4,065 1,134 1, ,144 FARIDABAD GPS( 1 * * ) Total GAS/NAPTHA/DIESEL TOTAL HYDRO HARYANA( 1 * 62 ) Total HYDEL BIOMASS( 1 * 106 ) SOLAR( 1 * 50 ) Total HARYANA 4,715 1,162 1, ,208 HIMACHAL PRADESH BASPA (IPP) HPS( 3 * 100 ) : MALANA (IPP) HPS( 2 * 43 ) : OTHER HYDRO HP( 1 * 372 ) Total HYDEL BIOMASS SOLAR : SMALL HYDRO( 1 * 486 ) Total SMALL HYDRO Total HP 1, JAMMU & KASHMIR GAS/DIESEL/OTHERS J&K( 1 * 190 ) Total GAS/NAPTHA/DIESEL BAGLIHAR (IPP) HPS( 6 * 150 ) OTHER HYDRO/IPP J&K( 1 * 308 ) Total HYDEL 1, BIOMASS SOLAR SMALL HYDRO( 1 * 98 ) Total SMALL HYDRO Total J&K 1,
3 PUNJAB GOINDWAL(GVK)( 2 * 270 ) GURU GOBIND SINGH TPS (ROPAR)( 6 * 210 ) GURU HARGOBIND SINGH TPS (LEHRA MOHABBAT)( 2 * * 250 ) GURU NANAK DEV TPS (BHATINDA)( 4 * 110 ) 1, RAJPURA(NPL) TPS( 2 * 700 ) 1,400 1,320 1,320 1, ,318 TALWANDI SABO TPS( 3 * 660 ) 1,980 1, , ,093 Total THERMAL 6,560 2,871 2, ,719 TOTAL HYDRO PUNJAB( 1 * 1000 ) 1, Total HYDEL 1, BIOMASS( 1 * 303 ) SOLAR( 1 * 859 ) Total PUNJAB 8,722 3,469 3, ,812 RAJASTHAN BARSINGSAR (IPP) LTPS( 2 * 125 ) CHHABRA TPS( 1 * * 250 ) 1,660 1,409 1, ,445 GIRAL (IPP) LTPS( 2 * 125 ) KALISINDH TPS( 2 * 600 ) 1, KAWAI TPS( 2 * 660 ) 1,320 1,207 1, ,140 KOTA TPS( 2 * * * 210 ) 1, RAJWEST (IPP) LTPS( 8 * 135 ) 1, SURATGARH TPS ( 6 * 250 ) 1,500 1,281 1, ,171 VSLPP (IPP)( 1 * 135 ) Total THERMAL 8,635 5,912 5, ,888 DHOLPUR GPS( 3 * 110 ) RAMGARH GPS( 1 * * * * 37.5 ) Total GAS/NAPTHA/DIESEL RAPS-A( 1 * * 200 ) Total NUCLEAR TOTAL HYDRO RAJASTHAN( 1 * 550 ) Total HYDEL WIND 4, BIOMASS( 1 * 102 ) SOLAR( 1 * 1995 ) 1, Total RAJASTHAN 16,475 6,500 6, ,107 UTTAR PRADESH ANPARA TPS( 2 * * 210 ) 1,630 1,338 1, ,393 ANPARA-C TPS( 2 * 600 ) 1,200 1,095 1, ,045 ANPARA-D TPS( 2 * 500 ) 1, BAJAJ ENERGY PVT LTD (IPP) TPS( 10 * 45 ) BARA PPGCL TPS( 3 * 660 ) 1, , HARDUAGANJ TPS( 1 * * * 250 ) LALITPUR TPS( 3 * 660 ) 1, MEJA TPS( 1 * 660 ) OBRA TPS ( 2 * * 200 ) 1, PANKI TPS( 2 * 105 ) PARICHA TPS( 2 * * * 250 ) 1, ROSA TPS( 4 * 300 ) 1, TANDA TPS( 4 * 110 ) Total THERMAL 13,763 6,185 6, ,221 ALAKHANDA HEP( 4 * 82.5 ) VISHNUPARYAG HPS( 4 * 110 ) OTHER HYDRO UP( 1 * 527 ) Total HYDEL 1, BIOMASS( 1 * 26 ) SOLAR( 1 * 472 ) CO-GENERATION( 1 * 1360 ) 1, Total OTHERs 1, Total UP 16,918 6,728 7, ,907
4 UTTARAKHAND TOTAL GAS UK( 1 * 450 ) : Total GAS/NAPTHA/DIESEL OTHER HYDRO UK( 1 * 1250 ) 1, : Total HYDEL 1, BIOMASS( 1 * 127 ) SOLAR( 1 * 100 ) : SMALL HYDRO( 1 * 180 ) Total SMALL HYDRO Total UTTARAKHAND 2, (B) Regional Entities Generation Inst. Capacity (MW) (MW) Peak MW BBMB Declared Capacity 19:00 03:00 Day Peak Day Energy Off Peak MW (MW) Hrs SCHD (MU) ACT (MU) BHAKRA HPS( 2 * * * 157 ) 1, , ,085 19: DEHAR HPS( 6 * 165 ) : PONG HPS( 6 * 66 ) : Sub-Total 2,765 1, , , NHPC BAIRASIUL HPS( 3 * 60 ) CHAMERA HPS( 3 * 180 ) : CHAMERA II HPS( 3 * 100 ) : CHAMERA III HPS( 3 * 77 ) : DHAULIGANGA HPS( 4 * 70 ) : DULHASTI HPS( 3 * 130 ) : KISHANGANGA( 2 * 110 ) : PARBATI III HEP( 4 * 130 ) : SALAL HPS( 6 * 115 ) : SEWA-II HPS( 3 * 40 ) : TANAKPUR HPS( 1 * * 31.4 ) : URI HPS( 4 * 120 ) : URI-II HPS( 4 * 60 ) : Sub-Total 4,525 1, , , NPCL NAPS( 2 * 220 ) : RAPS-B( 2 * 220 ) : RAPS-C( 2 * 220 ) : Sub-Total 1,320 1,013 1,121 1, , NTPC ANTA GPS( 1 * * ) : AURAIYA GPS( 2 * * ) : DADRI GPS( 2 * * ) DADRI SOLAR( 1 * 5 ) : DADRI-I TPS( 4 * 210 ) : DADRI-II TPS( 2 * 490 ) : ISTPP (JHAJJAR)( 3 * 500 ) 1, ,012 05: KOLDAM HPS( 4 * 200 ) RIHAND-I STPS( 2 * 500 ) 1, , : RIHAND-II STPS( 2 * 500 ) 1, , : RIHAND-III STPS( 2 * 500 ) 1, : SINGRAULI STPS( 2 * * 200 ) 2,000 1,810 1,945 1,977 1,945 19: , SINGRAULI SOLAR( 1 * 15 ) UNCHAHAR II TPS( 2 * 210 ) : UNCHAHAR III TPS( 1 * 210 ) : UNCHAHAR IV TPS( 1 * 500 ) UNCHAHAR SOLAR( 1 * 10 ) : UNCHAHAR TPS( 2 * 210 ) : Sub-Total 12,612 9, ,243 7, , SJVNL NATHPA-JHAKRI HPS( 6 * 250 ) 1,500 1, , ,501 18: RAMPUR HEP( 6 * ) : Sub-Total 1,912 1, , THDC KOTESHWAR HPS( 4 * 100 ) : TEHRI HPS( 4 * 250 ) 1,000 1, ,027 18: Sub-Total 1,400 1, , Total 24,534 16, ,584 10, , UI
5 IPP/JV IPP Inst. Capacity Declared Capacity 19:00 03:00 Day Peak Day Energy (MW) (MW) Peak MW Off Peak MW (MW) Hrs SCHD (MU) ACT (MU) ADHPL(IPP) HPS( 2 * 96 ) : BUDHIL HPS (IPP)( 2 * 35 ) : KARCHAM WANGTOO HPS( 4 * 250 ) 1, , ,000 19: MALANA2( 2 * 50 ) : SAINJ HEP( 2 * 50 ) : SHREE CEMENT (IPP) TPS( 2 * 150 ) Sub-Total 1, , Total 1, , Summary Section Inst. Capacity PEAK OFF-PEAK Day Energy Day AVG. Total Control Area Generation 54,626 20,208 19, ,289 J. Net Inter Regional Exchange [Import (+ve)/export (-ve)] 3,770 5, ,402 Total Regional Availability(Gross) 80,872 42,791 35, ,932 Total Hydro Generation Inst. Capacity PEAK OFF-PEAK Day Energy Day AVG. Regional Entities Hydro 12,814 10,173 1, ,867 Control Area Hydro 6,125 2,455 2, ,300 Total Regional Hydro 18,939 12,628 3, ,167 Total Renewable Generation Inst. Capacity PEAK OFF-PEAK Day Energy Day AVG. Regional Entities Renewable Control Area Renewable 9, ,693 Total Regional Renewable 9, ,698 4(A) INTER-REGIONAL EXCHANGES (Import=(+ve) /Export =(-ve)) 19:00 03:00 Maximum Interchange (MW) SL.No. Element (MW) MW Import (MW) Export (MW) Import/Export between EAST REGION and NORTH REGION Import in MU 1 132KV-Garhwa-Rihand KV-Karmnasa(PG)-Sahupuri(U KV-Rihand-Sonnagar(PG) KV-Pusauli(PG)-Sahupuri(UP) Biharsharif(PG)-Balia(PG) Biharsharif(PG)-Varanasi(P Fatehpur(UP)-Sasaram Motihari(DMT)-Gorakhpur Muzaffarpur(PG)-Gorakhp Patna(PG)-Balia(PG) Sasaram-Allahabad(PG) Sasaram-Varanasi(PG) Fatehpur(PG)-Sasaram Gaya(PG)-Balia(PG) Gaya(PG)-Varanasi(PG) HVDC800KV-Alipurduar-Agra(PG) Sub-Total EAST REGION , Import/Export between NORTH_EAST REGION and NORTH REGION 1 HVDC800KV-BiswanathCharialli Sub-Total NORTH_EAST REGION Import/Export between WEST REGION and NORTH REGION 1 220KV-Auraiya(NT)-Malanpur(PG) KV-Badod(MP)-Kota(PG) KV-Badod(MP)-Modak(RJ) RAPS C(NP)-Sujalpur Vindhyachal(PG)-Rihand(N Zerda(PG)-Bhinmal(PG) Zerda(PG)-Kankroli(RJ) rai-Gwalior(PG) rai-Jabalpur rai-Satna 1,340 1,451 1, Gwalior(PG)-Agra(PG) 750 1,129 1, Phagi(RJ)-Gwalior(PG) HVDC500KV-Mundra(JH)-Mohind , HVDC500KV-Vindhyachal(PG)-Vindhaychal B/B HVDC800KV-Champa(PG)-Kuruks.. 1,000 1,000 1, Sub-Total WEST REGION 2,915 4,322 5,575 2, TOTAL IR EXCHANGE 3,770 5,446 8,522 3, (B) Inter Regional Schedule & Actual Exchange (Import=(+ve) /Export =(-ve)) in MU ISGS/(LT+MT) Schedule BILT Schedule PX Schedule Total IR Schedule Total IR Actual NET IR UI NR-ER Export in MU UI NET
6 NR-WR Total Inter National Exchange with Nepal [Import (+ve)/export(-ve)] [Linkwise] Element Peak Off-Peak Maximum Interchange(MW) Energy (MU) Net Energy MW MW Import Export Import Export (MU) 132KV-Tanakpur(NH)-Mahendranagar(PG) Frequency Profile RANGE(Hz) < 49.2 < 49.7 < 49.8 < 49.9 < 50.0 >= <= > <= 50.1 > <= 50.2 > 50.2 > % < Frequency (Hz) > Maximum Minimum Average Freq Variation Standard Freq. in 15 mnt blk Freq Dev Index Frequency Time Frequency Time Frequency Index Deviation Max. Min. (% of Time) :02: :13: Voltage Profile: 400kV Maximum Minimum Voltage (in %) Voltage Deviation Index STATION VOLTAGE TIME VOLTAGE TIME < 380 < 390 > 420 > 430 (% of time) Abdullapur(PG) : : Abdullapur(PG) : : Amritsar(PG) : : Ballabgarh(PG) : : Bareilly II(PG) : : Bareilly(UP) : : Baspa(HP) : : Bassi(PG) : : Bawana(DTL) : : Dadri HVDC(PG) : : Gorakhpur(PG) : : Hisar(PG) : : Kanpur(PG) : : Kashipur(UT) : : Kishenpur(PG) : : Moga(PG) : : Nallagarh(PG) : : Rihand HVDC(PG) : : Rihand(NT) : : Voltage Profile: 765kV Maximum Minimum Voltage (in %) Voltage Deviation Index STATION VOLTAGE TIME VOLTAGE TIME < 728 < 742 > 800 > 820 (% of time) Anta RS(RJ) : : Balia(PG) : : Bareilly II(PG) : : Bhiwani(PG) : : Fatehpur(PG) : : Jhatikara(PG) : : Lucknow II(PG) : : Meerut(PG) : : Moga(PG) : : Phagi(RJ) : : Unnao(UP) : :
7 7(A). Short-Term Open Access Details: Off- Peak Hours (03:00) Peak Hours (19:00) Day Energy (MU) Bilateral (MW) IEX (MW) PXIL (MW) Bilateral (MW) IEX (MW) PXIL (MW) ISGS /(LT+MT) BILT Schedule PX Schedule Total (MU) Schedule PUNJAB -1, HARYANA RAJASTHAN , , DELHI , UTTAR PRADESH UTTARAKHAND HIMACHAL PRADESH JAMMU & KASHMIR CHANDIGARH TOTAL , , (B). Short-Term Open Access Details ISGS/(LT+MT) Schedule Bilateral (MW) IEX (MW) PXIL (MW) Maximum Minimum Maximum Minimum Maximum Minimum Maximum Minimum PUNJAB 3, , , HARYANA 4, , RAJASTHAN 3, , , DELHI 3, , , UTTAR PRADESH 6, , UTTARAKHAND HIMACHAL PRADESH 1, JAMMU & KASHMIR 1, CHANDIGARH Major Reservoir Particulars Parameters Present Parameters LAST YEAR LAST DAY RESERVOIR MDDL (Mts) FRL (Mts) Level (Mts) Energy (MU) Level (Mts) Energy (MU) Inflow (m3/s) Usage (m3/s) Bhakra , , Chamera-I Gandhisagar Jawahar Sagar Koteshwar Pong , RPS RSD Rihand Tehri TOTAL ,496-2, System Reliability Indices(Violation of TTC and ATC): (i)%age of times N-1 Criteria was violated in the inter - regional corridors WR 0 ER 0 Simultaneous 0 ii)%age of times ATC violated on the inter-regional corridors WR 0 ER 0 Simultaneous 0 iii)%age of times Angular Difference on Important Buses was beyond permissible limits(40 deg.) Rihand-Dadri Zero Crossing Violations No. of violations(maximum 8 in a day) Maximum number of continuous blocks without sign change CHANDIGARH 4 27 DELHI 4 26 HARYANA 0 12 HIMACHAL PRADESH 3 21 JAMMU & KASHMIR 3 26 PUNJAB 1 13 RAJASTHAN 3 22 UTTAR PRADESH 2 17 UTTARAKHAND Significant events (If any):
8 12.Grid Disturbance / Any Other Significant Event: 13.Weather Conditions : 14.Synchronisation of new generating units : 15.Synchronisation of new 220 / 400 / 765 KV lines and energising of bus / /substation : 16.Tripping of lines in pooling stations : 17.Complete generation loss in a generating station : Note: Data(regarding drawal,generation, shortage, inter-regional flows and reservoir levels)of the constituents filled in the report are as per last furnished data by the respective state/constituent to NRLDC. Shift In Charge
Shortage(-)/Surplus.. Requirement Freq (Hz) Demand Met Shortage 42, , , ,
Power Supply Position in Northern Region For 16-Feb-2019 POWER SYSTEM OPERATION CORPORATION LIMITED NORTHERN REGIONAL LOAD DESPATCH CENTRE DAILY OPERATION REPORT OF NORTHERN REGION Date of Reporting:17-Feb-2019
More informationShortage(-)/Surplus.. Requirement Freq (Hz) Demand Met Shortage 47, , , , ,
Power Supply Position in Northern Region For 30-Sep-2018 POWER SYSTEM OPERATION CORPORATION LIMITED NORTHERN REGIONAL LOAD DESPATCH CENTRE DAILY OPERATION REPORT OF NORTHERN REGION Date of Reporting:01-Oct-2018
More information'+fl"«phcfli «Government of India ~JOj?tI~4 Ministry of Power. ~~~~ Northern Regional Power Committee
'+fl"«phcfli «Government of India ~JOj?tI~4 Ministry of Power ~~~~ Northern Regional Power Committee No: NRPCIOPRJI03/02/201S13179-3204 Dated:01.03.201S ('Q'1f J!. ~. tft. flr~') ttch-4 ~ 18-n:,"Tth- ~
More informationCHAPTER 5 ELECTRIC POWER SUPPLY AND SYSTEM LOSSES
CHAPTER 5 ELECTRIC POWER SUPPLY AND SYSTEM LOSSES REVIEW: Central Electricity Authority General Review 2006 CHAPTER 5 ELECTRIC POWER SUPPLY AND SYSTEM LOSSES During the year 2004-05 gross electricity generation
More informationTODAY'S PROGRAM SOUTHERN
ALL INDIA/ REGIONS NORTHERN INSTALLED CAPACITY ** CAPACITY CENTRAL ELECTRICITY AUTHORITY GRID OPERATION & DISTRIBUTION WING OPERATION PERFORMANCE MONITORING DIVISION ALL INDIA / REGIONWISE POWER GENERATION
More informationMORNING MEGAWATT. MARKET MOVERS 7 October 2017 PRICE IEX DAM. Delivery: 7 October 2017 Last updated: 10:00 AM. Price (Rs/MWh) Power (MW)
MORNING MEGAWATT Delivery: 7 October 2017 Last updated: 10:00 AM MARKET MOVERS 7 October 2017 7000 Price West Bengal Buy Himachal Pradesh Sale 2500 5250 1875 Price (Rs/MWh) 3500 1250 1750 625 0 0 1700-1715
More informationPOWER HOUSE WISE DESPATCH Date September 17, Provisional Fig in '000 tes on date Monthly Progressive Sum of Daily
RAJGHAT S BADARPUR BADARPUR (TO TALCHER STPS) CCL Rail 3.82 76.44 PANIPAT B CCL Rail 0.00 40.49 NCL RGTPP (HISSAR) BCCL Rail 0.00 3.56 MCL Rail 0.00 28.81 NCL Rail 0.00 37.01 IGTPP (JHAJJAR)-APCPL CCL
More informationFig in '000 tes on date Monthly Progressive
DESP RAJGHAT BADARPUR CCL Rail 0.00 163.60 BADARPUR (TO TALCHER STPS) CCL Rail 0.00 3.83 PANIPAT BCCL Rail 10.55 52.05 CCL Rail 0.00 7.54 NCL RGTPP (HISSAR) CCL Rail 3.76 125.32 MCL Rail 7.47 22.41 NCL
More informationALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS
Region Northern Region Western Region Southern Region Eastern Region North Eastern Region Islands ALL INDIA Figures at decimal may not tally due to rounding off ALL INDIA INSTALLED CAPACITY (IN MW) OF
More informationPOWER SYSTEM OPERATION CORPORATION LIMITED.
POWER SYSTEM OPERATION CORPORATION LIMITED. SOUTHERN REGIONAL LOAD DESPATCH CENTRE DAILY OPERATION REPORT POWER SUPPLY POSITION IN SOUTHERN REGION FOR 03-AUG-2017 DATE OF REPORTING : 04-AUG-2017 AT 06:00HRS
More informationREGION WISE, STATE WISE, SECTOR WISE, TYPE WISE, STATION WISE, UNIT WISE GENERATION REPORT FOR 19-Mar-2017 Sub-Report 2/Page/ 1
REGION WISE, STATE WISE, SECTOR WISE, TYPE WISE, STATION WISE, UNIT WISE GENERATION REPORT FOR 19-Mar-2017 Sub-Report 2/Page/ 1 PROG. UNDER DATE NORTHERN REGION TOTAL 67006.53 776.04 617.05 289150.12 281637.43
More informationALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS
Region Northern Region Western Region Southern Region Eastern Region North Eastern Region Islands ALL INDIA Figures at decimal may not tally due to rounding off ALL INDIA INSTALLED CAPACITY (IN MW) OF
More informationMonthly Progressive. Sum of Daily
RAJGHAT BADARPUR CCL Rail 3.76 129.09 BADARPUR (To Talc CCL Rail 0.00 0.00 PANIPAT BCCL Rail 7.07 137.10 CCL Rail 0.00 41.60 NCL WCL Rail 0.00 23.03 RGTPP (HISSAR) CCL Rail 0.00 79.49 NCL Rail 3.60 105.60
More informationALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS
Region Northern Region Western Region Southern Region Eastern Region North Eastern Region Islands ALL INDIA Figures at decimal may not tally due to rounding off ALL INDIA INSTALLED CAPACITY (IN MW) OF
More informationSUMMARY STATEMENT Power projects yielding benefit during the XIth Plan
SUMMARY STATEMENT Power projects yielding benefit during the XIth Plan ---------------- -------------------- Sl. Hydro Nuclear Grand No. Coal Lignite
More informationALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS
Region Northern Region Western Region Southern Region Eastern Region North Eastern Region Islands ALL INDIA Figures at decimal may not tally due to rounding off ALL INDIA INSTALLED CAPACITY (IN MW) OF
More informationBusiness Plan for 5-Year MYT Control Period FY to FY Submitted To: Jammu & Kashmir State Electricity Regulatory Commission
FY 2016-17 to FY 2020-21 Business Plan for 5-Year MYT Control Period Submitted To: Jammu & Kashmir State Electricity Regulatory Commission Submitted By: Jammu & Kashmir Power Development Department-Distribution
More informationCharges for Deviation (Paise/kWh) applicable for: 19 December 2018
Annexure-I Annexure-II Average Frequency of the time block (Hz) र ट र य भ र प र षण क द र, ब -9 (प रथम तल), क त ब इ ट ट य शनल ए रय, कटव रय सर य, नई द ल -110016 Date of Issue: Charges for Deviation (Paise/kWh)
More informationALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS
Region Northern Region Western Region Southern Region Eastern Region North Eastern Region Islands ALL INDIA Figures at decimal may not tally due to rounding off ALL INDIA INSTALLED CAPACITY (IN MW) OF
More informationCENTRAL ELECTRICITY AUTHORITY G O & D WING OPERATION PERFORMANCE MONITORING DIVISION ENERGY GENERATION, PROGRAMME, AND PLANT LOAD FACTOR
1.SUMMARY - ALL INDIA Category CENTRAL ELECTRICITY AUTHORITY G O & D WING OPERATION PERFORMANCE MONITORING DIVISION ENERGY GENERATION, ME, AND PLANT LOAD FACTOR AN OVERVIEW : DATE : REPORT 1 / PAGE 1 MAY-2016
More informationAgenda for Long Term Access NVVNL Solar Power Projects
Agenda for Long Term Access NVVNL Solar Power Projects NTPC Vidyut Vyapar Nigam Ltd. (NVVNL) vide letter dated 04/11/2014 had applied for Long term Access (LTA) for transfer of 150MW power i.e. 100MW from
More informationSUMMARY REPORT FOR COUNCIL OF MINISTERS ON IMPORTANT DEVELOPMENTS IN POWER SECTOR DURING THE MONTH OF OCTOBER, 2018
SUMMARY REPORT FOR COUNCIL OF MINISTERS ON IMPORTANT DEVELOPMENTS IN POWER SECTOR DURING THE MONTH OF OCTOBER, 2018 1. CAPACITY ADDITION (Generation and Transmission) (i) Thermal capacity 600 MW has been
More informationPower Engineering II. Fundamental terms and definitions
Fundamental terms and definitions Power engineering A scientific discipline that focuses on: Generation of electrical energy (EE) Transmission and distribution of EE Consumption of EE Power grid operation
More informationN. K. Manglik Director
N. K. Manglik Director Hydro-meteorological observations could be broadly defined as the scientific way for collection of flow data at a specific location along the river including selected meteorological
More informationMINISTRY OF POWER O/O CONTROLLER OF ACCOUNTS SEWA BHAWAN, RK PURAM
MINISTRY OF POWER O/O CONTROLLER OF ACCOUNTS SEWA BHAWAN, RK PURAM NEW DELHI-110066 (Rs. In Crores) Statement of Receipts and Disbursements/Cash Flow for the year 2014-15 Head/Item Actuals up to COPPY
More informationMINISTRY OF POWER O/O CHIEF CONTROLLER OF ACCOUNTS SEWA BHAWAN, RK PURAM
MINISTRY OF POWER O/O CHIEF CONTROLLER OF ACCOUNTS SEWA BHAWAN, RK PURAM NEW DELHI-110066 Statement of Receipts and Disbursements/Cash Flow for the year 2017-18 Head/Item Actuals up to COPPY % Variation
More informationभ रत सरक र Government of India व द य त म त र लय Ministry of Power उत तर क ष त र य व द य त सवमवत Northern Regional Power Committee
भ रत सरक र Government of India व द य त म त र लय Ministry of Power उत तर क ष त र य व द य त सवमवत Northern Regional Power Committee स.-उक ष व स/प रच लन/106/01/2017/9477-517 द न क: 17.08.2017 स म : प रच लन
More informationMINISTRY OF POWER O/O CHIEF CONTROLLER OF ACCOUNTS SEWA BHAWAN, RK PURAM
MINISTRY OF POWER O/O CHIEF CONTROLLER OF ACCOUNTS SEWA BHAWAN, RK PURAM NEW DELHI-110066 Statement of Receipts and Disbursements/Cash Flow for the year 2017-18 Head/Item Actuals up to COPPY % Variation
More informationCURRENT STATUS OF MONSOON Main Meteorological conditions of the last week (27August to 2 September)
CURRENT STATUS OF MONSOON 2009 Main Meteorological conditions of the last week (27August to 2 September) Last week s low pressure area over Orissa and neighbourhood moved west-northwestwards across central
More information3. HYDROMETEROLOGY. 3.1 Introduction. 3.2 Hydro-meteorological Aspect. 3.3 Rain Gauge Stations
3. HYDROMETEROLOGY 3.1 Introduction Hydrometeorology is a branch of meteorology and hydrology that studies the transfer of water and energy between the land surface and the lower atmosphere. Detailed hydrological
More informationW E E K L Y MONSOON INSIGHT
W E E K L Y MONSOON INSIGHT 08 th July 2016 Indian Monsoon Dynamics Recent Weather Development India received 35% surplus rainfall in the week ended 6 July with all regions recording above-normal rainfall
More informationReal-Life Observations of Power System Dynamic Phenomena Some Interesting Aspects
Real-Life Observations of Power System Dynamic Phenomena Some Interesting Aspects A.M.Kulkarni Department of Electrical Engineering, IIT Bombay and Visiting Professor, University of Manitoba The Indian
More informationALL INDIA WEATHER SUMMARY AND FORECAST BULLETIN
Tuesday 08 May 2018 MID DAY Time of Issue: 1345 hours IST ALL INDIA WEATHER SUMMARY AND FORECAST BULLETIN Significant Weather Features Under the influence of the present Western Disturbance over Jammu
More informationMINISTRY OF POWER O/O CONTROLLER OF ACCOUNTS SEWA BHAWAN, RK PURAM
MINISTRY OF POWER O/O CONTROLLER OF ACCOUNTS SEWA BHAWAN, RK PURAM NEW DELHI-110066 (Rs. In Crores) Statement of Receipts and Disbursements/Cash Flow for the year 2014-15 Head/Item Actuals up to COPPY
More informationNational Project on Organic Farming
National Project on Organic Farming Department of Agriculture and Cooperation, Ministry of Agriculture Government of India Biofertilizers and Organic Fertilizers Statistics Year 2005-06 to 2009-10 Compiled
More informationAFP Surveillance Bulletin - India Report for week 1, ending 5 January 2019
Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Table 1: cases by month of paralysis onset, last 13 months State/UT's Total cases in cases as on week 1, cases
More informationSuppressed Surface Heating over northwestern parts of the Country and the ensuing Monsoon Rainfall
Suppressed Surface Heating over northwestern parts of the Country and the ensuing Monsoon Rainfall During this year, the temperatures have been below normal over north and northwestern parts of India.
More informationCHAPTER 4 CIRCULATION OF PUBLICATIONS
Circulation of Publications 49 CHAPTER 4 CIRCULATION OF PUBLICATIONS 4.1. A total number of 29,599 publications furnished their circulation figures online for 2016-17 claiming a total circulation of 48,80,89,490
More information1. HIGHLIGHTS OF POWER SECTOR a Installed Generation Capacity (As on 31-03-12 ) All Thermal Nuclear Hydro RES@ Grand Total India Coal Gas Diesel Total (Renewable) (MNRE) MW 112022.38 18381.05 1199.75 131603.18
More informationPOWER SYSTEM STATISTICS
POWER SYSTEM STATISTICS 2015-16 KERALA STATE ELECTRICITY BOARD LIMITED Table No. LIST OF TABLES Title 1 Growth of Kerala Power System 1 2 Plan wise Achievements 2 3 Particulars of Generators 3 4 Installed
More informationALL INDIA WEATHER SUMMARY AND FORECAST BULLETIN
Saturday 21 April 2018 MORNING Time of Issue: 0800 hours IST ALL INDIA WEATHER SUMMARY AND FORECAST BULLETIN Significant Weather Features Isolated thunder squalls and hailstorms are very likely over Sub
More informationMINISTRY OF POWER O/O CHIEF CONTROLLER OF ACCOUNTS SEWA BHAWAN, RK PURAM
MINISTRY OF POWER O/O CHIEF CONTROLLER OF ACCOUNTS SEWA BHAWAN, RK PURAM NEW DELHI-110066 (Rs. In Crores) Statement of Receipts and Disbursements/Cash Flow for the year 2015-16 Head/Item Actuals up to
More informationPrediction of western disturbances and associated weather over Western Himalayas
Prediction of western disturbances and associated weather over Western Himalayas H. R. Hatwar*, B. P. Yadav and Y. V. Rama Rao India Meteorological Department, Lodi Road, New Delhi 110 003, India Two cases
More informationALL INDIA WEATHER SUMMARY AND FORECAST BULLETIN
Sunday 22 April 2018 NIGHT Time of Issue: 2000 hours IST ALL INDIA WEATHER SUMMARY AND FORECAST BULLETIN Significant Weather Features The ongoing fairly widespread rainfall activity with isolated thunder
More informationLong Range Forecast Update for 2014 Southwest Monsoon Rainfall
Earth System Science Organization (ESSO) Ministry of Earth Sciences (MoES) India Meteorological Department PRESS RELEASE New Delhi, 9 June 2014 Long Update for 2014 Southwest Monsoon Rainfall HIGHLIGHTS
More informationMINISTRY OF POWER O/O CHIEF CONTROLLER OF ACCOUNTS SEWA BHAWAN, RK PURAM
MINISTRY OF POWER O/O CHIEF CONTROLLER OF ACCOUNTS SEWA BHAWAN, RK PURAM NEW DELHI-110066 (Rs. In Crores) Statement of Receipts and Disbursements/Cash Flow for the year 2015-16 Head/Item Actuals up to
More informationCalifornia Independent System Operator (CAISO) Challenges and Solutions
California Independent System Operator (CAISO) Challenges and Solutions Presented by Brian Cummins Manager, Energy Management Systems - CAISO California ISO by the numbers 65,225 MW of power plant capacity
More informationGOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA UNSTARRED QUESTION NO.74 ANSWERED ON PERFORMANCE OF POWER FINANCE CORPORATION
74. SHRI T. RATHINAVEL: GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA UNSTARRED QUESTION NO.74 ANSWERED ON 18.07.2016 PERFORMANCE OF POWER FINANCE CORPORATION Will the Minister of POWER be pleased
More informationJawaharlal Nehru National Solar Mission
Jawaharlal Nehru National Solar Mission National Solar Mission-Phase-I Journey so far NTPC Vidyut Vyapar Nigam Ltd. 1 11/5/2012 Background India is located in the equatorial sun belt of the earth, thereby
More informationAutomatic Dam Control System with Vidyut Cable Saver DI-731 for Automation of Barrage Gates
Automatic Dam Control System with Vidyut Cable Saver DI-731 for Automation of Barrage Gates Advantages of Cable Saver System DI-731 Saves around 90 percent Cable. For example : In normal system for a Dam
More informationREVIEW OF PERFORMANCE OF HYDRO POWER STATIONS CENTRAL ELECTRICITY AUTHORITY. Goverment of India Ministry of Power
जल व त ग ह क क य न प दन क प न व ल कन REVIEW OF PERFORMANCE OF HYDRO POWER STATIONS 2014-15 भ रत सरक र व त म लय क य व त धकरण Goverment of India Ministry of Power CENTRAL ELECTRICITY AUTHORITY व त अ ध नयम,
More informationFrequency-Bias Tie-Line Control of Hydroelectric Generating Stations for Long Distances
Frequency-Bias Tie-Line Control of Hydroelectric Generating Stations for Long Distances Sukhbir Singh Abstract In this work I have tried to apply effective dedicated online control systems to two equal
More informationSN Region/State/Centre Discipline Resi. Non-Resi. SOUTHERN B G T B G T Karnataka 1 Dharwad Athletic Basketball
SAI TRAINING CENTERS (STC) SCHEME SN Region/State/Centre Discipline Resi. Non-Resi. SOUTHERN B G T B G T Karnataka 1 Dharwad Athletic 20 04 24 02 02 04 Basketball 11 0 11 01 0 01 Gymnastic 11 10 21 0 0
More informationINDIA METEOROLOGICAL DEPARTMENT (MINISTRY OF EARTH SCIENCES) SOUTHWEST MONSOON-2014 END OF SEASON REPORT For the state of RAJASTHAN
INDIA METEOROLOGICAL DEPARTMENT (MINISTRY OF EARTH SCIENCES) SOUTHWEST MONSOON-2014 END OF SEASON REPORT For the state of RAJASTHAN HIGHLIGHTS For the country as a whole, the rainfall for the season (June-September)
More informationAlberto Troccoli, Head of Weather and Energy Research Unit, CSIRO, Australia ICCS 2013 Jamaica, 5 December 2013 (remotely, unfortunately)
013 Alberto Troccoli, Head of Weather and Energy Research Unit, CSIRO, Australia ICCS 013 Jamaica, 5 December 013 (remotely, unfortunately) Historical and projected changes in World primary energy demand
More informationBoundary Definition. Islamabad Srinagar. Leh Ngari. Tibetan Plateau. Joshimath. Birendranagar Khatmandu Bharatpur Mt.
Himalayas Islamabad Srinagar Leh Ngari Joshimath Tibetan Plateau Birendranagar Khatmandu Bharatpur Mt. Everest 8,848m Thimphu Lhasa Himalayan Range Extent Hindukush Himalayan Range Damauli Boundary Definition
More informationO.I.H. GOVERNMENT OF INDIA MINISTRY OF AGRICULTURE AND FARMERS WELFARE DEPARTMENT OF AGRICULTURE, COOPERATION AND FARMERS WELFARE
O.I.H. GOVERNMENT OF INDIA MINISTRY OF AGRICULTURE AND FARMERS WELFARE DEPARTMENT OF AGRICULTURE, COOPERATION AND FARMERS WELFARE 185. SHRI DEVJI M. PATEL: LOK SABHA UNSTARRED QUESTION NO.185 TO BE ANSWERED
More informationभ त क Government of India ववद य त म त र लय Ministry of Power उत त क ष त र य ववद य त वमवत Northern Regional Power Committee
भ त क Government of India ववद य त म त र लय Ministry of Power उत त क ष त र य ववद य त वमवत Northern Regional Power Committee.-उक ष वव /प रच लन/106/01/20/12507-47 ददन क: 8.11.20 व म : प रच लन मन वय उप वमवत
More informationORIGINAL IN HINDI GOVERNMENT OF INDIA MINISTRY OF CONSUMER AFFAIRS, FOOD & PUBLIC DISTRIBUTION DEPARTMENT OF FOOD AND PUBLIC DISTRIBUTION
ORIGINAL IN HINDI GOVERNMENT OF INDIA MINISTRY OF CONSUMER AFFAIRS, FOOD & PUBLIC DISTRIBUTION DEPARTMENT OF FOOD AND PUBLIC DISTRIBUTION LOK SABHA UNSTARRED QUESTION NO. 4122 TO BE ANSWERED ON 20 TH MARCH,
More informationAPPENDIX A 5 BUSSYSTEM DATA
5 BUSSYSTEM DATA APPENDIX A A. BUSDATA S.No P gen Q gen P load Q Load Voltage Shunt 1 90 0 0 0 1.06 0 2 120 0 40 10 1.0707 0 3 120 0 90 60. 1.068 0 4 0 0 80 20 1.0 0 5 0 0 120 0 1.0 0 B. LINE DATA S. No
More informationPerformance Evaluation and Review of System Protection Scheme Design with the help of Synchrophasor Measurements
Performance Evaluation and Review of System Protection Scheme Design with the help of Synchrophasor Measurements P. Mukhopadhyay V. Pandey Rajkumar Anumasula Chandan Kumar Sunil Patil Srinivas Chitturi
More informationRenewables and the Smart Grid. Trip Doggett President & CEO Electric Reliability Council of Texas
Renewables and the Smart Grid Trip Doggett President & CEO Electric Reliability Council of Texas North American Interconnected Grids The ERCOT Region is one of 3 North American grid interconnections. The
More informationApplication of Monte Carlo Simulation to Multi-Area Reliability Calculations. The NARP Model
Application of Monte Carlo Simulation to Multi-Area Reliability Calculations The NARP Model Any power system reliability model using Monte Carlo simulation consists of at least the following steps: 1.
More informationSITUATION REPORT 2. North India Floods 2010 (Uttarakhand, Haryana, Delhi, UP, Bihar)
A. KEY HIGHLIGHTS: SITUATION REPORT 2 North India Floods 2010 (Uttarakhand, Haryana, Delhi, UP, Bihar) 21 st Sept 2010, 1300h The flood situation on monday continued to remain grim in many parts of North
More informationEVALUATION OF WIND ENERGY SOURCES INFLUENCE ON COMPOSITE GENERATION AND TRANSMISSION SYSTEMS RELIABILITY
EVALUATION OF WIND ENERGY SOURCES INFLUENCE ON COMPOSITE GENERATION AND TRANSMISSION SYSTEMS RELIABILITY Carmen Lucia Tancredo Borges João Paulo Galvão carmen@dee.ufrj.br joaopaulo@mercados.com.br Federal
More informationDr BR Ambedkar Institute of
1 Andaman & Nicobar 2 Assam Kamrup 3 Dibrugarh University & Dibrugarh Electronics & Dr BR Ambedkar 1 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 2 Port Blair Sub-total 1 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0
More informationSection 2: Installed Capacity and Capacity Utilisation
Section 2: Installed Capacity and Capacity Utilisation COKING COAL : Table 2.1: Installed Capacity of Coal Washeries in India as on 31.3.08 and 31.03.09 Sl. No. Washery & Operator State of Location Capacity
More informationWind power and management of the electric system. EWEA Wind Power Forecasting 2015 Leuven, BELGIUM - 02/10/2015
Wind power and management of the electric system EWEA Wind Power Forecasting 2015 Leuven, BELGIUM - 02/10/2015 HOW WIND ENERGY IS TAKEN INTO ACCOUNT WHEN MANAGING ELECTRICITY TRANSMISSION SYSTEM IN FRANCE?
More informationGrid Integration and Technology Trends. State Load Despatch Centre, Gujarat
Grid Integration and Technology Trends State Load Despatch Centre, Gujarat 16 th June 2016 Way of presentation Wind Energy in Gujarat Power System Grid Integration Wind Generation Characteristics Impact
More informationinvestment decisions
Climate modelling: A guide to investment decisions Vicky Pope Met Office Hadley Centre This is not an ADB material. The views expressed in this document are the views of the author/s and/or their organizations
More informationGOVERNMENT OF INDIA MINISTRY OF HEALTH AND FAMILY WELFARE DEPARTMENT OF HEALTH AND FAMILY WELFARE
GOVERNMENT OF INDIA MINISTRY OF HEALTH AND FAMILY WELFARE DEPARTMENT OF HEALTH AND FAMILY WELFARE LOK SABHA STARRED QUESTION NO. 183 TO BE ANSWERED ON THE 29 TH JULY, 2016 VECTOR BORNE DISEASES *183. SHRI
More informationInternational Studies about the Grid Integration of Wind Generation
International Studies about the Grid Integration of Wind Generation Dr.-Ing. Markus Pöller/DIgSILENT GmbH Internation Studies About Grid Integration of Wind Generation Grid Integration of Wind Generationin
More informationOptimal Placement & sizing of Distributed Generator (DG)
Chapter - 5 Optimal Placement & sizing of Distributed Generator (DG) - A Single Objective Approach CHAPTER - 5 Distributed Generation (DG) for Power Loss Minimization 5. Introduction Distributed generators
More informationCASE STUDY NATHPA JHAKRI, INDIA
SEDIMENT MANAGEMENT CASE STUDY NATHPA JHAKRI, INDIA Key project features Name: Nathpa Jhakri Country: India Category: reduce sediment production (watershed management); upstream sediment trapping; bypass
More informationPROJECT ECONOMIC ANALYSIS
Electricity Transmission Expansion and Supply Improvement Project (RRP NEP 41155) PROJECT ECONOMIC ANALYSIS A. Overview 1. The economic analysis undertaken for the Electricity Transmission and Supply Improvement
More informationURTDSM Initiative in India and Controlled Islanding using PMU Measurements
URTDSM Initiative in India and Controlled Islanding using PMU Measurements Akhil Raj Gopal Gajjar Meenal Chougule Narayanan Rajagopal Prashant Navalkar Rajeev Gajbhiye S. A. Soman PowerAnser Labs, IIT
More informationCASE STUDY NATHPA JHAKRI, INDIA
SEDIMENT MANAGEMENT CASE STUDY NATHPA JHAKRI, INDIA Key project features Name: Nathpa Jhakri Country: India Category: reforestation/revegetation; upstream sediment trapping; bypass channel/tunnel; reservoir
More informationCONTENTS. 3 Capacity Addition for February 2013 and upto February 2013 in the current year
CONTENTS S.N. ITEM Highlights of Power Sector 1 Capacity Addition & Generation Target/Achievement during February 2013 2 Capacity Addition- Programme/ feasible during 12th PLAN 3 Capacity Addition for
More informationBringing Renewables to the Grid. John Dumas Director Wholesale Market Operations ERCOT
Bringing Renewables to the Grid John Dumas Director Wholesale Market Operations ERCOT 2011 Summer Seminar August 2, 2011 Quick Overview of ERCOT The ERCOT Market covers ~85% of Texas overall power usage
More informationDownloaded from
BAL BHARATI PUBLIC SCHOOL, PITAMPURA, DELHI GEOGRAPHY CLASS IX CHAPTER -3 DRAINAGE (summative assessment 1) Q.1. What is a River System? Ans. A river along with its tributaries is known as a River System
More information, and ignoring all load currents, determine
ECE43 Test 3 Dec 8, 5 Q. (33 pts.) The Zbus for the above 3-bus network with bus as reference, in per unit, is given to be 3.87 j.798 j.8 j Z.798 j.87 j.8 j bus.8 j.8 j j Assuming that the prefault values
More informationTutorial 2: Modelling Transmission
Tutorial 2: Modelling Transmission In our previous example the load and generation were at the same bus. In this tutorial we will see how to model the transmission of power from one bus to another. The
More informationPresented by R. Sasi Kumar Scientist, SRRA, C-WET
MINISTRY OF NEW AND RENEWABLE ENERGY Presented by R. Sasi Kumar Scientist, SRRA, C-WET E-mail: sasikumar@cwet.res.in National Solar Energy Summit-2012 DSIIDC,New Delhi (13-14/12/2012) CENTRE FOR WIND ENERGY
More informationEIA411 May 1, A Report to the Office of Energy Emergency Operations Department of Energy Under EIA-411
EIA411 May 1, 2006 A Report to the Office of Energy Emergency Operations Department of Energy Under EIA-411 All questions concerning this data should be directed to: Jason Speer Southwest Power Pool 415
More informationSOUTH AUSTRALIAN WIND STUDY REPORT SOUTH AUSTRALIAN ADVISORY FUNCTIONS
SOUTH AUSTRALIAN WIND STUDY REPORT SOUTH AUSTRALIAN ADVISORY FUNCTIONS Published: October 2015 IMPORTANT NOTICE Purpose The purpose of this publication is to provide information about wind generation in
More informationPROCEDURE NO.: SO5-2-6 PAGES: 1 OF 10 CHIEF SYSTEM OPERATOR
CON EDISON SYSTEM OPERATION DEPARTMENT PROCEDURE SUBJECT: THUNDERSTORM/STORM PROCEDURE PROCEDURE NO.: SO5-2-6 PAGES: 1 OF 10 REVISED BY: S. BUFFAMANTE APPROVED: T. HALLERAN CHIEF SYSTEM OPERATOR DATE:
More informationSystem Impact Assessment Addendum #2 Greenfield & St. Clair Energy Centres
IESO_REP_0292 System Impact Assessment Addendum #2 Greenfield & St. lair Energy entres onnection Assessment & Approval Process Issue 3.0 Greenfield Energy entre AA I 2004-167 Applicant: Greenfield Energy
More informationCost of Inflow Forecast Uncertainty for Day Ahead Hydropower Production Scheduling
Cost of Inflow Forecast Uncertainty for Day Ahead Hydropower Production Scheduling HEPEX 10 th University Workshop June 25 th, 2014 NOAA Center for Weather and Climate Thomas D. Veselka and Les Poch Argonne
More informationTransient Stability Analysis of Single Machine Infinite Bus System by Numerical Methods
International Journal of Electrical and Electronics Research ISSN 348-6988 (online) Vol., Issue 3, pp: (58-66), Month: July - September 04, Available at: www.researchpublish.com Transient Stability Analysis
More informationCSIR-Central Building Research Institute, Roorkee (UK)
CSIR-Central Building Research Institute, Roorkee (UK) Introduction: Training programme on Control Measures for Landslides held during July 18-22, 2016 Landslides problem in hilly terrains are one of the
More informationPower System Seminar Presentation Wind Forecasting and Dispatch 7 th July, Wind Power Forecasting tools and methodologies
Power System Seminar Presentation Wind Forecasting and Dispatch 7 th July, 2011 Wind Power Forecasting tools and methodologies Amanda Kelly Principal Engineer Power System Operational Planning Operations
More informationOptimal Demand Response
Optimal Demand Response Libin Jiang Steven Low Computing + Math Sciences Electrical Engineering Caltech June 2011 Outline o Motivation o Demand response model o Some results Wind power over land (outside
More informationWeather Outlook. 1 July 2016 METEOROLOGICAL RESEARCH GROUP. INDIA HEADQUART ERS G 31 Quest Offices DLF Golf Course Road Gurgaon India
Weather Outlook 1 July 2016 METEOROLOGICAL RESEARCH GROUP INDIA HEADQUART ERS G 31 Quest Offices DLF Golf Course Road Gurgaon 122 002 India NORTH AMERICA 350 Fifth Avenue 59 th Floor, New York City NY
More informationAlectra Utilities List of Station Capacity
lectra Utilities List of Station Capacity s per Distribution System Code this list represents the llocated Capacity on stations owned by lectra Utilities (formerly PowerStream) as of July 1st, 2018. llocated
More informationCHAPTER 2 MATHEMATICAL MODELLING OF AN ISOLATED HYBRID POWER SYSTEM FOR LFC AND BPC
20 CHAPTER 2 MATHEMATICAL MODELLING OF AN ISOLATED HYBRID POWER SYSTEM FOR LFC AND BPC 2.1 INTRODUCTION The technology of the hybrid power system is at an exciting stage of development. Much research effort
More informationLOAD FREQUENCY CONTROL WITH THERMAL AND NUCLEAR INTERCONNECTED POWER SYSTEM USING PID CONTROLLER
LOAD FREQUENCY CONTROL WITH THERMAL AND NUCLEAR INTERCONNECTED POWER SYSTEM USING PID CONTROLLER Amitesh Kumar, Prof. SulataBhandari, Dr. RintuKhanna 3,,3 Pec University of Technology, Chandigarh,( India)
More informationContents. Diaphragm in pressure pipe: Steady state head loss evolution and transient phenomena. Nicolas J. Adam Giovanni De Cesare
Diaphragm in pressure pipe: Steady state head loss evolution and transient phenomena Nicolas J. Adam Giovanni De Cesare Contents Introduction FMHL pumped-storage plant Experimental set-up Steady head losses
More information2011 Summer Operating Expected Conditions. Bulk Power Operations Power Coordination Center
2011 Summer Operating Expected Conditions Bulk Power Operations Power Coordination Center TOPICS 2010 Review 2011 SOCO Balancing Authority (BA) Area Summer Weather Forecast Peak Demand Forecast Transmission
More informationWater Resource & Management Strategies
Water Resource & Management Strategies National Conference on Integrated Water Resource Management for enhancing Farmers' Income March 22, 2017, Hotel Park, New Delhi Nalin Rawal Chief Business head Agribusiness
More informationEconomic Operation of Power Systems
Economic Operation of Power Systems Section I: Economic Operation Of Power System Economic Distribution of Loads between the Units of a Plant Generating Limits Economic Sharing of Loads between Different
More information