Gold Creek / Rock Creek Inspections Monitoring, Road Deactivation and Environmental Road Maintenance Planning Risk Analysis

Size: px
Start display at page:

Download "Gold Creek / Rock Creek Inspections Monitoring, Road Deactivation and Environmental Road Maintenance Planning Risk Analysis"

Transcription

1 2006 FIA Gold Creek / Rock Creek Inspections Monitoring, Road Deactivation and Environmental Road Maintenance Planning Risk Analysis Prepared for: Prepared by: Forsite Consultants Ltd. #330 42nd St SW Salmon Arm, BC V1E 4R1 Tel: (250) Fax: (250) October 31 st, 2006

2 Table of Contents TABLE OF CONTENTS...II 1.0 INTRODUCTION SCOPE OF ASSESSMENT CONVENTIONS FOLLOWED OFFICE AND FIELD REVIEW TERRAIN CHARACTERISTICS AND GEOMORPHOLOGICAL PROCESSES RISK ANALYSIS PROCEDURE OBSERVATIONS ANALYSIS AND RECOMMENDATIONS GOLD CREEK SITE A (REACH 0139) GOLD CREEK SITE B (REACH 2902) GOLD CREEK REACH GOLD CREEK REACH 0134 / GOLD CREEK REACH GOLD CREEK REACH GOLD CREEK REACH 4700 / GOLD CREEK REACH GOLD CREEK REACH 6207 / GOLD CREEK REACH GOLD CREEK REACH GOLD CREEK REACH GOLD CREEK REACH GOLD CREEK SITE GOLD CREEK SITE GOLD CREEK SITE GOLD CREEK SITE 9 / ROCK CREEK SITE ROCK CREEK SITE ROCK CREEK SITE ROCK CREEK SITE ROCK CREEK SITE ROCK CREEK SITE ROCK CREEK SITE ROCK CREEK SITE ROCK CREEK SITE ROCK CREEK SITE ROCK CREEK SITE ROCK CREEK SITE ROCK CREEK SITE X ROCK CREEK SITE MOSQUITO CREEK (SITE 1) HONEYMOON BAY (SITE 2) MOMICH LAKE SITE MOMICH LAKE SITE CLOSURE...78 ii

3 LIST OF FIGURES Figure 1 Figure 2 Figure 3 Figure 4 Figure 5 Figure 6 Figure 7 Location Key Map..6 Gold Creek Sites..... attached Rock Creek Sites..... attached Site 0139 detail Site R-9, Branch D Road detail...55 Site R-11, Branch C Road detail Mosquito Creek Site 1 detail...70 iii

4 1.0 Introduction Forsite Consultants Ltd. (Forsite) was retained to carry out post work inspections, monitoring and prescriptions for sites in the Rock Creek, Gold Creek, Mosquito Creek, Marjory Creek and Momich Watersheds. (see figure 1 for a key map).these sites have had previous work and/or inspections completed. The objective of this report is to address remaining concerns and to establish closure on these sites. 1.1 Scope of Assessment The purpose of this report is: To describe conditions at specific assessment sites and where such conditions may have a specific impact. To provide a Risk Analysis of the potential environmental impacts of the assessment sites To recommend site-specific actions to reduce the likelihood of further environmental impacts. 1.2 Conventions Followed Soil classifications and landform descriptions use terminology defined in the publication Terrain Classification System for British Columbia B.C. Ministry of Environment Slope gradient classification follows the convention defined in the publication Terrain Classification System for British Columbia B.C. Ministry of Environment Gentle 5-27% Moderate 28-49% Moderately Steep 50-70% Steep > 70% Page 4

5 2.0 Office and Field Review Prior to and following the field assessment the following materials were reviewed: Stereo air photo coverage of the study area (~1:20,000 scale) 1:20,000 digital design file maps Geologic Survey of Canada Bedrock Geology Mapping located on Ministry of Energy and Mines MapPlace webpage Gold Creek Level 2 Fish Habitat Assessment (Silvatech 1995) Level 2 Road Condition Assessment 9silvatech 1996) Detailed Proposal Zone 1 and 2 Works Phase (Silvatech 1996) Level 2 Stream Channel Assessment (Silvatech 1998) Bioengineering as-builts (Silvatech 1998) Watershed Restoration Plan (Silvatech 2001) Road Assessment 9Silvatech 2004) Fieldwork was completed by Peter Weisinger M.Sc. GIT of Forsite on August 14, 15 th and 18th-19 th See Figure 2 for a map of the study area and location of the assessment sites. A helicopter over-flight of the Gold Creek sites was completed on August 11 th Attending were Peter Weisinger M.Sc. GIT and Rod Williams P.Geo of Forsite. The helicopter overflight focussed primarily on previously identified sites, but observations of general watershed condition and sediment sources and other potential problem areas were noted. Rock Creek Environmental Maintenance Project Plan (Summit 2003) Road Assessment (2004) Environmental Maintenance Projects (Mosquito, Honeymoon, Marjory) Fieldwork was completed by Peter Weisinger M.Sc. GIT of Forsite on August 1-4 th, See Figure 3 for a map of the study area and location of the assessment sites. Additional field review of the Rock Creek site R11 was conducted on October 20, Page 5

6 Birch Island Vavenby Rock Creek Sites (Figure 3) Mosquito Creek Rock Creek Honeymoon Bay Momich Lake Seymour Arm Blucher Hall Gold Creek Sites (Figure 2) St. Ives Gold Creek Magna Bay Anglemont Adams Lake Celista Eagle Bay Sun Peaks Squilax Scotch Creek Lee Creek Blind Bay Sorrento Notch Hill Balmoral Solsqua Sicamous Figure 1 Key Map Annis Page 6

7 3.0 Terrain Characteristics and Geomorphological Processes 3.1 Rock Creek / North Adams Lake Sites The sites in the Rock Creek area are generally located either in the valley bottoms, or on mid slopes. Soils encountered were generally either sandy tills or sandy glaciofluvial and fluvial materials. These soils wee found to have low cohesion and were easily eroded. The upper portion of Rock Creek is on a wet rolling plateau, with the creek becoming incised in its lower reaches. Instability in this area was generally limited to sediment production due to drainage diversions as a result of road construction. In the incised lower draw, drainage diversions leading to gentle over step types of landslides were found to be of concern. 3.1 Gold Creek Watershed The sites in Gold Creek are located primarily on the Adams Plateau. Soils encountered ranged from sandy glaciofluvial materials in draws and in the Gold Creek Draw, to weathered colluvial rubble and tills on the flat upland areas. The sides of the Gold Creek watershed are steep, with significant relief. Gentle-over-steep types of failures are associated with a number of these sites, and pose the highest hazard. Concerns were primarily drainage diversions which had led to instability downslope, or were directly related to minor sediment production adjacent to streams. 4.0 Risk Analysis Procedure This report provides a qualitative evaluation of hazards associated with sites previously identified in the study area, a description of the potential consequences, and recommendations to reduce the hazards and associated risks. Acceptance of the qualitative consequence values and the subsequent risk analysis is the responsibility of the licensee or the regulatory authority, as is the determination of acceptable risk and the decision to proceed with any action based on that risk analysis. Consequence ratings have been estimated based on standard practice and identification of downslope resources in the area. The main streams in the study area (Gold Creek and Rock Creek) are fish bearing. Sediment delivery to a fish stream is considered a moderate to high consequence dependent on the magnitude of the hazard and location of the identified site in relation to the stream. Page 7

8 5.0 Observations, Analysis and Recommendations 5.1 Gold Creek Site A (Reach 0139) Location: Gold Creek Reach 1039, Map Reference: G-0139 Previously identified issues: The old road location was constructed across a slide with sediment from road surface and fillslope eroding, depositing material in the stream. (Silvatech 1998) Restoration undertaken: The road has been relocated and the original road deactivated. The portion of road adjacent the slide area has been recontoured and grass seeded as per Option A in the Silvatech (1998) Report. The remainder of the road has been deactivated through cross ditching. Observations: The road section located directly downslope of the slide area is experiencing some streambank erosion (see photo plates and ) Although grass seeding has been successful on the open slopes reducing surface erosion, lateral erosion of the streambank is continuing, with sediment mobilising events likely occurring during periods of peak flow. The channel appears to be migrating laterally towards the former road location, being confined by bedrock on the opposite (right) side. Severity of erosion has decreased since remediation measures have been implemented. Risk Analysis: There is judged to be a high likelihood of sloughing of road fill materials and ongoing delivery (with peak / seasonal flows) of sediment to Gold Creek at this site, on the order of 1-2m 3 annually. This is considered a moderate consequence. The risk is therefore high. Prescription: Place large diameter Rip Rap along ravelling cut bank to slow lateral stream erosion Revegetate with deciduous species adjacent to stream. Plant coniferous species on rehabilitated road surface and on old slide area Page 8

9 Photo Aerial view of Reach 0139 Photo Eroding streambank Reach 0139 Page 9

10 Figure 4 Site 0139 detail Page 10

11 5.2 Gold Creek Site B (Reach 2902) Location: Gold Creek, Reach 2902, Map Reference: G-2902 Previously identified issues Fillslope failure and unstable cutslopes in fine grained soils contributing sediment to stream (Silvatech 1998). Restoration undertaken Road has been relocated, old road pulled back and hydroseeded / bio-engineered. Observations The road has been bypassed, and the site has been fully recontoured. Grass seeding was partially successful, having taken on the recontoured road, though not on the upper portion of old cutslopes (Photo plate 5.2.1). Bio-remediation attempts were unsuccessful (Photo 5.2.3) and the site has not yet revegetated. The former bridge (log box?) at the stream crossing has been removed, though cribbing was left in place. The stream appears to be stable. Only minor amounts of sediment from the old road location appears currently to be entering the stream at high streamflows, where some material may be entrained at the crossing. Risk Analysis There is judged to be a moderate likelihood of sediment producing events (small surficial slides, rilling) at this site. This would result in a small amount (< 5m 3 ) of material mobilised at the stream crossing during a peak flow event and from small erosional events on the unvegetated upper cutslope. This would be considered a low consequence. The risk is therefore low. Prescription Bioengineering of slopes recommended to further stabilise the area as per (Silvatech 1998) Report. Consider planting area with coniferous species Hand grass seed the remaining open slopes Page 11

12 Photo Deactivated road at reach 2902 Photo Wooden cribbing left in place, minor sloughing of old road fill. Page 12

13 Photo Evidence of unsuccessful bio-remediation. Page 13

14 5.3 Gold Creek Reach 0106 Location: Gold Creek, Reach 0106 Map Reference: G-0106 Previously identified issues Severely aggraded active channel, deposition area/ sediment wedge above bedrock constriction. Restoration undertaken None reported. Previous prescriptions suggest monitoring and controlling sediment input from upstream. Observations The stream is heavily aggrading, with multiple channels and significant lateral movement where the channel is not confined by bedrock. Numerous log jams were noted along this reach. There is no sign of direct connectivity to the road system. Problems in this area are symptomatic of overall hydrologic conditions in the watershed. Risk Analysis No risk analysis was performed at this site. A risk analysis for this reach would be a function of hydrology of entire watershed, which is beyond the scope of this study. Prescription Continue to monitor drainage issues in the watershed / control sediment sources in previously developed areas. Photo Aerial view of reach 0106 showing severe aggradation. Page 14

15 5.4 Gold Creek Reach 0134 / 7902 Location: Road [~2.5 km] Map Reference: G-0134 Field Identification: Previously identified issues A spur road has diverted flows from upslope leading to slope failures below (Silvatech 1998). Restoration undertaken Natural drainage patterns have been restored, spur and branch roads deactivated. Observations The upper spur road has been thoroughly deactivated with numerous cross drains. The natural flow of the main drainage path has been restored. Large cross ditches effectively prevent further diversion on the upper spur road. Some intercepted small flows on the upper spur have been diverted to cross drain culverts on the 100 Road. The crossing at the upper road is well armoured, with some very minor sediment input from ravelling road fills. Some drainage intercepted by lower road and 600CMP at 218. There is evidence of previously large flows in the ditchline on the lower road. The lower stream crossing at 220 is eroding some fill material. Aerial observations the slide has partially naturally revegetated. The site is likely still a significant sediment source as it is adjacent to Gold Creek. Bio-engineering and seeding should be carried out as per the prescription in Silvatech (1998) report. Risk Analysis As the natural drainage patterns have been restored, there is judged to be a low likelihood of initiating another large landslide which could impact Gold Creek at this site. Such a slide would result from drainage diversion and concentration in a gentle over steep type of scenario as happened with the previous slide. This would result in significant input of sediment to Gold Creek, and result in long-term sediment source production. This is considered a high consequence. The risk is therefore moderate There is a moderate to high likelihood of further sediment mobilisation on the old slide path, with sediment delivery of <25m 3 to Gold Creek. This would result in input of a small to moderate (to 25m 3 ) amount of sediment to Gold Creek, which would be considered a moderate to high consequence. The risk is therefore moderate to high. Prescription If the 100 Road is to continue to remain operational, monitor exiting culverts and restoration efforts on the road to ensure continued functioning. If no future use of the road is anticipated, permanent deactivation should be considered (i.e. pull all culverts) Revegetate slide as per Silvatech (1998) bioremediation prescription. Page 15

16 Photo Stream crossing Page 16

17 Photo Lower portion of slide entering Gold Creek Page 17

18 5.5 Gold Creek Reach 1901 Location: Tributary 250m upslope of Reach 1901 of Gold Creek Map Reference: G-1901 Previously identified issues Collapsed bridge on old road has diverted flows south along road, through forested area and into Gold Creek. Deposition of materials in forested area. Restoration undertaken Collapsed culvert has been removed, berm constructed and planted with dogwood. Observations Observation from helicopter overflight revealed no further disturbance of tributary channel. Risk Analysis There is judged to be a low likelihood of a future breach of the stream channel as a result of the old road location, which could result in minor sediment deposition into gold Creek. This is considered a moderate consequence. The risk is therefore low. Prescription None required Page 18

19 5.6 Gold Creek Reach 3801 Location: Gold Creek Reach 3801, Map Reference: G-3801 Field Identification: 203 Previously identified issues Large log jam/pile at bottom of slide, perched fills at deactivated road crossing ( 203). Restoration undertaken Road crossing has been deactivated. Upper road at initiation point of failure has been deactivated. Observations Crossing at lower road still has some minor perched fills present, though the crossing has been sloped back and rehabilitated. Current flow is crossing over old road surface in a self-armoured channel no sign of recent disturbance. Road surface is revegetating (grass seeding effective). Some perched fills are still present but most material appears to have been pulled back in critical areas. Sediment mobilisation is not likely to be a catastrophic failure but rather a progressive erosion of fill materials. Risk Analysis There is judged to be a moderate likelihood of a mobilisation of road fill materials, resulting in transport of fine sediment (<5m 3 ) to the tributary of Gold Creek. This is considered a low consequence. The risk is therefore low. Prescription No further work required / continue to monitor Page 19

20 Photo Stream crossing old road. Page 20

21 5.7 Gold Creek Reach 4700 / 4601 Location: Road upslope of Reach 4700, and bridge crossing of Reach 4601 Map Reference: G-4700 / G-4601 Field Identification: 122 Previously identified issues Creek diverted by old skid trail and mainline. Failure 300m below mainline and channelized debris flow into Gold Creek. Restoration undertaken Natural drainage was restored on mainline, 500mm culvert installed. Failure was grass seeded. Observations The slide headwall and main portion of the slide is revegatating and appears to be stabilising some sidewall failures are taking place on the channelized portion of the slide. Some coniferous vegetation is starting to reestablish. Material had been scoured to bedrock in track of the slide, and remobilisation is unlikely. On the eastern side of the headwall, there is significant flow emanating at the base, with soil materials perched upslope. There remains the possibility that further headward erosion will continue. The area upslope of the slide ( 121) and to the south of the main slide have a number of old revegetated slide scarps present. At 122, the road cuts through a rock outcrop, and as a result the ditchline is very shallow and prone to overflowing onto the road. Evidence of water flow downslope suggests that this may be a point at which some water had previously been diverted to the slide. The drainage diversions identified in the Silvatech 1998 report have been restored. Risk Analysis Drainage diversions upslope have been repaired, however natural drainage is seeping from the headwall of the scarp. There is judged to be a low to moderate likelihood of further sliding of material at the landslide site, resulting in delivery of <25m 3 of material to the reach and a moderate likelihood of delivery to Gold Creek. This is considered a moderate consequence. The risk is therefore low to moderate. Prescription Monitor and maintain ditchline on road / Improve ditchline through 117 Allow slide area to revegetate naturally. Page 21

22 Photo View up headwall of slide Photo View down slide path Page 22

23 5.8 Gold Creek Reach 6402 Location: Spur in Block 81-1 Map Reference: G-6204 Field Identification: Previously identified issues Stream diverted by skid trail. Restoration undertaken Stream restored to original channel. Roads and trails deactivated. Observations The point of diversion by the old skid trail has been restored and the stream is now flowing in what appears to be the original channel. The diversion has been blocked by a vegetated berm, however water is seeping through this berm and still flowing down the skid trail. There is a low to moderate likelihood that a large streamflow could ovetop the structure and again be diverted by the skid trail. In some areas the skid trail is at a lower elevation than the natural stream draw. 128 is a low point on the trail. Some seepage is emanating on the road at 124. This appears to be an area where some of the stream flow is diverted, primarily as subsurface flows, to the road. There is no cross drain structure here, and water flows down the ditch to pond on the high side of the road at the junction of the deactivated road downslope, resulting in wet road conditions. There is a 400mm CMP which takes the flow at 126 across the mainline. Risk Analysis There is judged to be a low to moderate likelihood of a stream avulsion at the previous point of diversion, resulting in flows being diverted down the skid trail, entrainment of fine materials at the road crossing and subsequent delivery to the stream system to the north. This would also result in the loss of a small amount of productive area. This is considered a low to moderate consequence. The risk is therefore low to moderate. Prescription Upgrade berm by hand, increasing height by ~0.3m, and width by about 1m, with locally available rock. Monitor berm on skid trail for future avulsions. Improve ditchline to 126 (400mm CMP), clean sump. Page 23

24 Diverted stream flow along skid trail and ditchline Natural stream channel Photo Aerial view of site Photo seepage onto road Page 24

25 Photo There is still some minor drainage along the old skid trail (left). (photo taken from top of berm.) Page 25

26 5.9 Gold Creek Reach 6207 / 6208 Location: Block 81-1 Map Reference: G-6207 / G-6208 Field Identification: 126 Previously identified issues: (6207) Stream diverted by skid trail, no riparian buffer maintained through block. (6208)Stream diverted by skid trail causing twin channels. Poorly defined channel at mainline crossing, some flows follow ditch south. Restoration undertaken (6207) Stream restored to original channel, roads and trails deactivated. (6208) Culvert entrance and ditch grading improved, channel definition improved near culvert Observations Streams have been restored to original flows. Skid trail that had been an issue on 6207 is revegetating. Culvert functioning well. Risk Analysis There is judged to be a low to negligible likelihood of further diversions at these two sites. Prescription No further works required Photo Culvert 6208 Page 26

27 Photo Reach 6208 Page 27

28 5.10 Gold Creek Reach 7001 Location: Reach 7001 Map Reference: G-7001 Field Identification: Previously identified issues Creek was temporarily diverted by skid trail, deposition at culvert inlet. Restoration undertaken Creek restored to natural channel, inlet cleaned. Observations The point of diversion was repaired, the stream appears to currently be taking about 90% of the flow. There is still some minor diversion taking place along the old skid trail. Diverted flow returns to channel downstream. Risk Analysis There is judged to be a low likelihood of recurrence of a stream avulsion at this site. This would resulting in streamflow being diverted by the skid trail with some minor sediment entrainment. Sediment is not likely to reach a fish bearing stream. This is considered a low consequence. The risk is therefore low. Prescription Potential disturbance by machine likely to be more disruptive than leaving the site undisturbed. Restoration (cross-ditching) could be conducted by hand, however the majority of the flow is likely to stay in the natural channel. Cross drain flow on trail back to stream draw by hand. Install wide shallow swale (culvert backup) at stream crossing 130. Page 28

29 Photo Stream looking towards road. Direction of diversion along old skid trail indicated. Page 29

30 5.11 Gold Creek Reach 7203 Location: Road in Block Map Reference: G-7203 Field Identification: 204 Previously identified issues Streams had been diverted by skid trails in the block, culverts washed out, deposition downstream. Restoration undertaken Diversions have been restored by hand, road deactivated. Observations Streams at road crossing have stabilised, and are well incised. Swales at stream crossing are revegetating. There is some minor lateral erosion of road fill materials at crossings, but this is expected to decrease as riparian vegetation re-establishes. Risk Analysis There is judged to be a low to negligible likelihood of mobilising sufficient sediment to impact a fish bearing reach of the Gold Creek from this site. Prescription No works required Photo Stream crossing reach 7203 Page 30

31 5.12 Gold Creek Reach 7205 Location: Reach 7205 at road crossing Map Reference: G-7205 Previously identified issues Creek diverted by skid trails, hazard of diversion along mainline. Restoration undertaken Channel restored, culvert improved. Observations Deflector berm and culvert have been upgraded no issues at crossing. Risk Analysis There is judged to be a low to negligible likelihood of mobilising sufficient sediment to impact a fish bearing stream from this site. Prescription No further works required. Photo Reach 7205 at road crossing Page 31

32 5.13 Gold Creek Reach 7604 Location: Reach 604 in Block Map Reference: G-7604 Field Identification: 134 Previously identified issues No riparian buffer in block, slash in streams, blocked and damaged culvert. Restoration undertaken None Observations 600mm CMP in place, functioning. There is evidence of significant flows in this draw. Riparian area well vegetated and regrowing. Soils in this area are rocky and free draining. No immediate concerns as long as culvert remains functional. Risk Analysis Given the past history of plugging, and evidence of significant seasonal flows in this stream, there is a moderate likelihood that this culvert will become plugged or fail, leading to a washout of the road and subsequent sediment delivery to the stream system. There is a moderate likelihood of material being delivered downstream to Gold Creek. This would be considered a moderate consequence. The risk is therefore moderate. Prescription Pull culvert / construct broad armoured swale with planned road deactivation, or install failsafe cross ditch as per Silvatech (1998) prescription. Photo Crossing at Reach 7604 Page 32

33 Photo mm CMP at Reach 7604 crossing Page 33

34 5.14 Gold Creek Site 1 Location: Road in Block Map Reference: G-1 Field Identification: 115 Previously identified issues Damaged and blocked 300mm culvert, road requires deactivation. (Silvatech 2004) Restoration undertaken None Observations Crushed and mangled culvert still in place. There is evidence of significant ditch flow in the past (foreground in photo). The culvert is at a low point in the road, with ponding water on the high side. Risk Analysis This site is on flat to gently sloping plateau. There is judged to be a low to negligible likelihood that significant drainage diversion could take place at this site. Prescription Remove culvert and install cross ditch. This can be done with deactivation on the remainder of the road. Photo Crushed culvert. Page 34

35 5.15 Gold Creek Site 7 Location: Road in Block Map Reference: G-7 Field Identification: 201 Previously identified issues Deck material rotting, but crib wall and stringers look in good shape. (Silvatech 2004) Restoration undertaken None Observations Deck on the bridge is rotting out. There has been a small slide to the northwest of the bridge in the road cut (see photo ). No significant amount of debris has entered the stream as a result, however several trees have been uprooted and are threatening to fall onto the bridge deck / upstream of the bridge which may result in a temporary blockage. The cribbing on the downstream side of the town side approach is beginning to erode. The stream gradient downslope is 80% for about 7m immediately after the crossing. A blockage / collapse of the structure may lead to alteration of flow and/or significant erosion of the stream bed and / or mobilisation of debris downslope. The bridge could likely be left in place for some time before significant problems arise, however a high flow event or mass movement event in the channel may accelerate deterioration and lead to significant sediment input. Note: Reach 4700 is located upslope of this bridge. There is no evidence of the debris flow reaching this location. Risk Analysis There is judged to be a low likelihood of a structural failure on this bride (cribbing collapse / creek blockage) within the next 20 years that could result in significant sediment delivery to Gold Creek. This is considered a high consequence. The risk is therefore moderate. Prescription Bridge superstructure and cribbing should be removed, and approaches sloped back and revegetated. Pull back all materials adjacent the creek to create a broad swale, and armour stream crossing with coarse rock Remove material slumping into creek at road cut Supervision of deactivation works by a qualified registered professional is recommended. Page 35

36 Photo Log Bridge, 201 (Silvatech 1998 Site 7 ) Photo Log Bridge, 201 (Silvatech 1998 Site 7 ) SE corner of Cribbing starting to collapse. Page 36

37 5.16 Gold Creek Site 8 Location: Bridge at crossing between blocks and Map Reference: G-8 Field Identification: 202 Previously identified issues Bridge, Site 8. No significant issues identified guardrails were beginning to rot. Silvatech (1998) Restoration undertaken None Observations Bridge is showing significant rot, but no sign of imminent collapse. Bridge will likely remain intact for a number of years, but continued degradation will compromise load bearing capacity. Risk Analysis There is judged to be a low likelihood of a structural failure on this bridge that would result in delivery of a small to moderate amount of sediment to the stream, considered a low to moderate consequence. The risk is therefore low. Note: This bridge will continue to deteriorate, holes have formed in the deck and the structure may become unsafe to use in the next 20 years. The bridge may not be safe for vehicular traffic. If this bridge is to remain, a load rating should be performed. Prescription This bridge will not support machinery. Works planned for site 7 require removal of this bridge for access. Bridge superstructure and cribbing should be removed. Pull back all materials adjacent the creek to create a broad swale, and armour stream crossing with coarse rock Supervision of deactivation works by a qualified registered professional is recommended. Page 37

38 Photo Bridge at 202, ( Site 8 in Silvatech 1998 report) Page 38

39 5.17 Gold Creek Site 9 / 10 Location: Block Road Map Reference: G-9, G-10 Field Identification: 113, 114 Previously identified issues (9) Failed 400mm CMP, water running along road surface, then back into natural channel. (10) Infilled ditch is causing creek to flow down the road. Restoration undertaken None Observations A number of diversions of natural drainage paths along the road system were observed. This road system should be deactivated and have natural drainage patterns restored. These sites are not part of the Gold Creek watershed and drain to the watershed to the west. This road system has not been deactivated, and though no significant issues were identified at the specific sites addressed in this report, ( 9 and 10) the entire road system accessing Blocks should be assessed in detail and deactivated. These roads and blocks are located on the plateau, with drainage to the west into a deeply incised creek draw. The draw is mapped as terrain class IV and V (potentially unstable and unstable). Risk Analysis There is judged to be a moderate likelihood that improper drainage management in this entire road system (including sites 9 and 10) could lead to drainage diversions which would result in landslides in the class IV and V terrain in the watershed downslope (to the east). This could result in significant disturbances in the watershed and subsequent downstream effects on Adams Lake. This is considered a high consequence. The risk is therefore high. Prescription At stations 113, 114 and 115 (corresponding to the area of Silvatech (2004) sites 9 and 10), culverts should be removed and cross ditched. This entire road system associated with Blocks 502 (1-6) should have a deactivation prescription prepared as it presents a possible gentle-over-steep hazard. (note: Preparation of deactivation prescriptions for this area are planned for Summer of 2007) Page 39

40 Photo Blocked culvert causing ponding in ditchline with seasonal runoff over road. Photo Damaged culvert at Site 9 ( 114) Page 40

41 5.18 Rock Creek Site 1 Location: Forest Service Rec. Site ( Silviculture Camp ) at Tsikwustum (Rock) Creek. Map Reference: R-1 Field Identification: 52, 53 Previously identified issues Considerable bank erosion along right bank adjacent to rec site. Potential to loose rec. site land, sediment delivery to creek and lake. Restoration undertaken Unstable bank material was excavated back, and separated boulders placed as armour at the toe of the bank and the area was grass seeded. Observations The forest recreation site is located on the right bank of Tsikwustum (Rock) Creek, at the mouth of the river on Adams Lake. This recreation site is built on an active fan, and as such is subject to large debris flood events, and large annual high flow events. There is a 1-4m high bank along the edge of the site (see composite photo ) that had been sloped back and armoured in The bank is being eroded and there is undercut portion of this bank adjacent to the recreation site. Toe protection on the bank appears inadequate, as further erosion has taken place (compared to 2004 photos). Erosion is being accelerated by human activities; there is evidence in this area of disturbance by campers (walking access, digging). A large open grassy area (grass seeded in 2004) is located adjacent to the bank, as well as an access route to one of the lower camp sites. Note: A large flood event could significantly impact the camp site. This assessment addresses only on the possibility of sediment delivery to the creek as a function of normal (annual) high flows at the site indicated in the Silvatech (2004) report. No evaluation of risk to the site infrastructure or human life is made with respect to large, low return period flood events. Such an assessment is likely warranted, and should be carried out separately. Risk Analysis There is judged to be a moderate to high likelihood of further erosion along this slope, resulting in delivery of sandy material to Rock Creek. This is likely to occur during flood / high water events, and would be significantly diluted. This is therefore considered a low to moderate consequence. The risk is therefore moderate to high Prescription Slope back steep section (blue arrows in photo ) where overhang and exposed roots threaten to collapse. Place large rip rap (~2m diameter) at the base of the section 52 to 53, slope back top of the bank and grass seed. Restrict vehicle access at the top of the bank by placing a row of large boulders ~ 5m back from the top of the break in slope Consider restricting access with a fence along the top bank leaving a well marked path to the river to limit bank disturbance. Continue to monitor site, inspect after high flow events. Page 41

42 52 53 Photo Photo composite Eroding bank of Rock Creek adjacent to Silviculture Camp Forest Rec. Site. Photo Detail of eroding bank. Page 42

43 5.19 Rock Creek Site 2 Location: Tributary to Rock Creek Map Reference: R-2 Field Identification: 51 Previously identified issues 1800 mm CMP plugged with woody debris. Cutslope to the east (bush side of crossing) is delivering fine sediment Restoration undertaken Culvert has been cleared Observations Culvert log jam has been cleared, and is now unobstructed. Given the size of this creek, there is a moderate to high likelihood that future jams will take place. The recommendations in the Silvatech (2003) report to inspect the culvert frequently (twice per year); this should be done prior to and following freshet. A large jam could cause a significant blockage and subsequent debris flow at this site that would impact the S3 reach of Rock Creek downstream. The large cutslope to the east of the site continues to ravel and has infilled the ditchline, causing ditch flows to flow across the road and onto the fillslopes on the bush side of the crossing (see photo ; blue arrow indicates flow). This is leading to erosion of the fillslope and deposition of sediment into the stream. If this condition persists, it could lead to more significant erosion and / or fillslope failures. Risk Analysis There is judged to be a moderate likelihood of a significant washout of the road, resulting in significant sediment delivery and possibly a debris flow in the creek. This is considered a high consequence. The risk is therefore high Prescription. Inspect culvert regularly (twice per year; prior to and following freshet) Clean and widen ditchline, carry flow to crossing (red arrow in Figure ) Grass seed ditch and cutslope by hand or optionally hydroseed slope if feasible as per Silvatech (2003) Page 43

44 Photo Rock Creek tributary (Site 2 Silvatech 2003) 51 in field Photo Rock Creek tributary culvert inlet Page 44

45 5.20 Rock Creek Site 3 Location: Slide S-19 downslope of Rock Creek road near bridge crossing Map Reference: R-3 Field Identification: 50 Previously identified issues Surface soils in slide susceptible to surface erosion, sediment delivery potential to creek is high. Restoration undertaken Has been hand grass seeded several times. Observations The slide location is at a low point on the road, there is a long ditch run to this point, and water likely had saturated the road prism / run over the edge at the slide site. Perched fill materials are still present and are prone to ravelling. The slide is partially revegetating, some grass seeding has taken on the lower portions, but the steep upper portion is likely to continue to be a sediment source. Rock Creek (S2) is located directly downslope. Risk Analysis The site is a permanent sediment source because slopes at the top are too steep to revegetate. There is judged to be a moderate likelihood of a small slide initiating on oversteepened materials at the headscarp of the slide with resulting minor sediment delivery (<5m 3 ) to the S-2 creek downslope. This is considered a moderate consequence. The risk is therefore moderate. Prescription Carefully pull back top of slide area to 1.5V:1H (66%) maximum slope for the top portion of the slide. Hand-grass seed the slope. Upgrade ditchline along road this site. Page 45

46 Photo , slide S-19 looking down at exposed soils. Page 46

47 5.21 Rock Creek Site 4 Location: Non-status road near reach break 5/6 Map Reference: R-4 Field Identification: 4 Previously identified issues Erosion along 9m length of left bank of road poses a risk to the road and is a minor sediment source to the creek. Restoration undertaken Done as per Silvatech (2003) report Observations This is a broad low gradient reach, with significant coarse woody debris in creek. Comparison of pictures of previous site suggests low debris movement. Stream is classed as S2. Site has been restored, and remaining ravelling is expected to be very minor. Site is revegetating, road surface erosion has ceased. Risk Analysis There is judged to be a low to negligible likelihood of delivery of significant sediment to Rock Creek at this site. Prescription None / continue to monitor site. Page 47

48 5.22 Rock Creek Site 5 Location: Non status road (Tsikwustum Lake Road) near junction with Branch C Block C-206. Map Reference: R-5 Field Identification: 44 Previously identified issues Erosion of road surface near 450mm CMP due to plugged inlet 50% function only. Restoration undertaken None (Pre work indicated done) Observations The ditch block at the 450mm culvert has failed, and flow has eroded ditchline. Drainage flows through 1000mm CMP downstream. There is significant flow coming down the ditchline that has eroded the ditchblocks of the culverts upstream, and has resulted in significant sediment mobilisation (photo ) in the ditch and subsequent deposition (photo ) in the ditch at lower gradient areas. Sediment is being transported downstream, with significant aggradation in the channel and fines washing into Rock Creek. Restoration at this site should be done in conjunction with remainder of the road to the east (Sites 6 and 7). The culvert is experiencing severe piping because of excessive flows at this site, and material is eroding at the outlet. Risk Analysis There is judged to be a high likelihood that the culvert at this site will continue to fail and erode sediment form the outlet and road surface. This will result in significant fine sediment transport downstream to Rock Creek. This is considered a high consequence. The risk is therefore high Prescription Repair (re-install) culvert (600mm CMP minimum) and armour sump. Ensure drainage measures in ditch upstream are addressed. Repair in conjunction with Site 11 (R-11) deactivation. Page 48

49 Photo Erosion of ditchline Photo Significant deposition at low point before culvert. Page 49

50 5.23 Rock Creek Site 6 Location: Non status road (Tsikwustum Lake Road) Map Reference: R-6 Field Identification: 42 Previously identified issues Non functioning culvert is filly suspended above ditch, which has downcut ~0.4m in sandy materials. Restoration undertaken None (Pre work indicated done, but comparison to Silvatech report photos reveals site has not been repaired) Observations Culvert is still fully suspended and ditchblock has not been repaired. This is resulting in severe ditch runs downstream, scouring ditchline and transporting sediment to Site 5, and subsequently to Rock Creek. Risk Analysis There is judged to be a high likelihood that the non-functioing of this culvert will will result in significant runoff and subsequent fine sediment transport downstream to Site 5 and then Rock Creek. This is considered a high consequence. The risk is therefore high Prescription Install large ditch block, constructed out of large rock. Install broad failsafe cross ditch to prevent further breaches of the ditch block. Repair in conjunction with Site 11 (R-11) deactivation. Page 50

51 Photo Eroded ditchblock at 42 (R6) Photo Perched Culvert at 42 (R6) Page 51

52 5.24 Rock Creek Site 7 Location: Non status road (Tsikwustum Lake Road) Map Reference: R-7 Field Identification: 40 Previously identified issues Piping of fine-textured soils at a 1400mm culvert has caused slumping of road surface. Restoration undertaken Road repaired Observations The culvert at this site is functional and in good condition. The ditch block and sump may have been overtopped, at some point in the past resulting in increased flow down the ditch line. Risk Analysis There is judged to be a low likelihood that the ditch block will be overtopped and eroded and result in further significant runoff and subsequent fine sediment transport downstream to Sites 5 and 6 and subsequently to Rock Creek downstream. This is considered a high consequence. The risk is therefore moderate. Prescription Improve ditch block with large rip-rap Repair in conjunction with Site 11 (R-11) deactivation. Photo culvert inlet and ditchblock Page 52

53 5.25 Rock Creek Site 8 Location: Non status road (Tsikwustum Lake Road) Map Reference: R-8 Field Identification: 39 Previously identified issues Inlet slumping, piping of fine textured materials. Restoration undertaken Repaired road and armoured inlet. Observations 1000mm CMP. Site has been repaired using coarse materials. No recent significant sediment production was noted. Note that this stream is connected to the streams diverted at site 11. this site should be monitored after restoration, to ensure flow capacities and sediment mobilisation changes are noted. Risk Analysis There is judged to be a low likelihood of significant sediment production at this site. Further deterioration and piping of fines would transport sediment to a fish bearing portion of the reach immediately downslope, with a high to moderate likelihood of deposition of materials into Tsikwustum Lake. This is considered a high consequence. The risk is therefore moderate. Prescription Continue to monitor site Ensure site 11 restoration (R-11) does not divert excessive flows to this stream Page 53

54 5.26 Rock Creek Site 9 Location: Branch D Map Reference: R-9 Field Identification: 14 ( 9-16) Previously identified issues Waterbars and cross-ditches between Tsikwustum Lake Road and the first junction off branch road D are filling with sand and losing functionality. Restoration undertaken Reported as done as per Silvatech (2003) Observations Waterbars have been improved but problems of road surface erosion still present. Sandy soils highly prone to erosion. Additionally, ditchlines experiencing significant erosion. Culvert ditch block at 9 could fail, diverting significant drainage to lower ditch. Waterbar at 13 infilling. This road system is intercepting and diverting significant flows. Full deactivation should likely be considered for the future. Risk Analysis There is judged to be a moderate to high likelihood of road surface degradation and sediment production on this road section, however there is no direct connectivity to Rock Creek. Road surface degradation is considered a low consequence. The risk is therefore low. Prescription 9 Improve failsafe cross ditch. Riprap ditchblock. 10 Improve waterbar 12 Install failsafe cross ditch 13 Clean / improve backup cross ditch Page 54

55 Rock Creek Main Branch D Figure 5 (Site R-9), Branch D Road Photo existing 600mm CMP Page 55

56 5.27 Rock Creek Site 10 Location: Branch D crossing on Tributary #1 Map Reference: R-10 Field Identification: 6, 7 Previously identified issues A section of approximately 500m of road is at risk of erosion by tributary #1 had breached a ditch block at a 1400mm CMP resulting in streamflows being routed along the ditch, and had washed out a block of a 600mm ditch block downslope. Restoration undertaken Work done by Interfor as per instructions provided by Silvatech in September 2002 Observations Large ditchblocks put in place at 1400mm culvert and at 600mm downslope. Ditchblocks functioning. 1400mm ditch block is adequate, but contains a high proportion of fines and rock of smaller diameter and may be washed out in the event of an extreme flow. Ditchblock construction at 600mm culvert is very good. There are no failsafe cross ditches in place. Risk Analysis There is judged to be a moderate likelihood of the ditchblock at the 1400mm pipe to be breached, resulting in another stream avulsion and subsequent ditch erosion and sediment production. The area downstream of the two culverts is flat and marshy, and any sediment entrained is likely to settle out before entering Rock Creek. This is considered a low consequence. The risk is therefore low. Prescription Improve ditch block at 1400mm culvert with large diameter rock Install broad failsafe cross ditches at both culvert locations Page 56

57 Photo mm culvert with ditchblock Photo Ditch block at 600mm Culvert Page 57

58 5.28 Rock Creek Site 11 Location: Branch C Map Reference: R-11 Field Identification: 19-40, Previously identified issues Severe ditch erosion along 75m of road has resulted in a deep ditch in sandy tills. Sediment delivery to stream network moderate. Site R11 was examined as part of the current study. It was determined from this initial investigation that additional issues with drainage diversions in the road network upslope of the site were contributing to the problems identified at site R11. It was decided that a second, more detailed investigation should be carried out. This separate investigation was done on October by the author, and has been included in this final revision of the report. Restoration undertaken None evident. Observations The original study and the follow-up detailed study focused on the two road systems, Branch C and the associated spur to the south (See Figure 6). Soils in this area consist of a veneer to blanket of sandy tills and bouldery glacio-fluvial materials over relatively impermeable gneissic bedrock. There is significant shallow groundwater flow which has been intercepted by road construction and exacerbated by harvesting in this area. As a result, ditch flows are significant, and diversions have led to washouts in culverts downslope, notably at assessment Sites 5, 6 and 7. At site R11, the ditch and road surface have been severely eroded and a significant amount of sediment has been mobilised in the ditchline and where the ditch flow has washed out the road. The ditchline had eroded to a significant depth, and original crossdrains / culverts have been perched The upper portion of Branch C has been deactivated from 1 to 18. This portion of the road is not contributing to the drainage issues identified in the previous studies, and only minor remediation, if any, is required It appears that interception of subsurface groundwater and subsequent diversion by roads and trails in the area of the branch to the south of (Waypoints ) have contributed to the excessive ditch flows on Branch C. The spur road has been deactivated, with frequent cross ditches dispersing drainage, and natural stream channels have been restored to satisfaction at waypoints 100 and 131. The road surface in this area is revegetating, and sediment production is minimal in this area. The lower portion of the spur, from 131 to the POC with Branch C has also been deactivated, however the deactivation has been in large part unsuccessful, and significant water is intercepted and channelled along the road surface and ditch to Branch C. Waterbars in this area need to be extended as cross ditches from stations Risk Analysis Due to drainage interception/diversion and concentration, there is judged to be a high likelihood of further Page 58

59 sediment production at these sites, with a moderate likelihood of sediment delivery to the stream system (S5 stream through R7 and the S6 stream through R6) and subsequently to Rock Creek (S2). This is considered a high consequence. The risk is therefore high Prescription The following prescription is meant to disperse ground water flows as much as possible where such flows have been intercepted and concentrated as ditch flows, as well as to restore stream flows to natural channels where these may have been diverted by road construction. Note: all cross ditches on this road section should be deep enough to intercept all ditch drainage, and should be broad, with gentle approaches. Armour all cross ditches with large rock. Install ditch blocks constructed with coarse rock and boulders. Branch C Road 1 existing cross drain - no action required 2 existing 500 CMP at low point in road with functioning failsafe cross ditch - no action required CMP, perched inlet. Low risk - no action required 500 CMP, good ditchblock in place Low risk - no action required Stations 6, 7, 9, 10, 11, 13, 14, 16, 17 are all existing cross ditches, functioning well, low risk. - no further action required 17B 18 block 20 POC of several spurs upslope, start of deepened ditchline - no action required 500CMP, ponding upslope - Pull culvert and install broad armoured cross ditch. and ditch Existing waterbar install broad armoured cross ditch and ditch block 20A Install broad armoured cross ditch and ditch block. Extend cross ditch south to ribbon, to intercept surface flows on old trail on south side of ditch. 21 S5 Stream, ditch block has been overtopped leading to significant diversion. - Install broad armoured cross ditch and ditch block. 21A Existing culvert, significant seepage from old spur upslope. - Pull culvert and install broad armoured cross ditch. and ditch block 22 Existing culvert - Pull culvert and install broad armoured cross ditch 23 Existing culvert - Pull culvert and install broad armoured cross ditch, install ditch block on bush side Page 59

60 25 Install broad armoured cross ditch and ditch block CMP with good ditch block - Pull culvert and install broad armoured cross ditch. and ditch block Install broad armoured cross ditch and ditch block Install broad armoured cross ditch and ditch block 29 S6 channel - Install broad armoured cross ditch and ditch block, restore natural stream channel Construct a large armoured cross ditch from station 30 to 31 across the POC of the spur road to the south, and across Branch C. The intent of this ditch is to channel runoff from the spur to the S6 which crosses at 29. Ditch should have a gradient of 2-3%. Install a large ditch block in the existing ditch Exisiting cross ditch is perched. - Install broad armoured cross ditch and ditch block Install broad armoured cross ditch and ditch block Exisitng 500 CMP Pull culvert Install broad armoured cross ditch and ditch block Install broad armoured cross ditch and ditch block Install broad armoured cross ditch and ditch block 39 Low gradient portion of road. - Install broad armoured cross ditch and ditch block angle ditch across as indicated by ribbons. Spur Road 131, 132, 133 Existing waterbars do not intercept the ditchline, leading to significant ditch flows. cross ditch waterbars to ditch line (drain ditch flow across road to disperse drainage) Page 60

61 Photo severe ditch erosion. Page 61

62 Figure 6 (Site R-11), Branch C Road detail Page 62

63 5.29 Rock Creek Site 12 Location: Non-Status Road (Tsikwustum Lake Road) north end of Tsikwustum Lake Map Reference: R-12 Field Identification: 45 Previously identified issues 400mm culvert draining a small pond plugged with woody debris. Evidence of flooding on road surface. Restoration undertaken None evident Observations Culvert inlet obscured by woody debris, but pond has drained. Inlet of culvert completely blocked by coarse woody debris. Road shows signs of being overtopped by seasonal flows resulting in road surface erosion. Culvert is located in large road fill, removal would likely result in road being impassable. Creek is classed as S3, but fish passage is not possible upstream of this location. A fish passage assessment should be performed at this site. Risk Analysis There is judged to be a moderate likelihood of a road washout in this location, resulting in delivery of sediment to the S3 class stream and subsequently to Tsikwustum Lake, and loss of use of the road. This is considered a moderate consequence. The risk is therefore moderate. Prescription Depending on management objectives: Pull culvert and pull back fill material and armour crossing with rock OR Install failsafe cross ditch and continue to monitor site and clean out as necessary. A fish passage assessment should be performed at this site. Page 63

64 Photo Site 12 Ponding upstream of culvert. Page 64

65 5.30 Rock Creek Site 13 Location: Permitted Road (Tsikwustum Lake Road) Near Branch E Junction Map Reference: R-13 Field Identification: 48 Previously identified issues Surface erosion at a 600mm CMP possibly due to undersized culvert. Restoration undertaken Replaced with 1000mm CMP Observations 1000mm CMP on S4 class creek, functioning normally. Minor sediment production on cutslopes. Risk Analysis There is judged to be a low to negligible likelihood of further sediment production at this site. Prescription No further work required Photo mm CMP 48, Site 12 Page 65

66 5.31 Rock Creek Site 14 Location: Tsikwustum Lake Road (North Rock Creek Road) Map Reference: R-14 Previously identified issues Road fill erosion and slumping at 400mm CMP. Sediment source with a high potential to enter stream network. Restoration undertaken Culvert replaced, works completed as per Silvatech (2003) report. Observations Culvert replaced with 800 mm CMP functioning. No apparent issues since replacement. Connectivity to S2 immediately downstream. Risk Analysis There is judged to be a low to negligible likelihood of further sediment production at this site. Prescription No further work required Page 66

67 5.32 Mosquito Creek (Site 1) Location: Mosquito Creek Map Reference: M-1 Field Identification: Previously identified issues Stream diversions Restoration undertaken Works as prescribed by Silvatech (2004) report completed by October 29, Observations Works completed as described in Silvatech (2004) report were reviewed. This report recommended grass seeding, which appears to have been completed to satisfaction. Cross drain structures and culverts have been put in place. Flow appears to have been redirected back to the original stream locations satisfactorily. There is some evidence of minor road surface runoff taking place the road has been rutted by vehicle traffic, and minor runoff is eroding the road surface. This road surface flow is intercepted by waterbars and cross ditches, and is only a minor concern. The road is still accessible by truck; consider limiting vehicle access to ATVs only. Concerns on the upper rehabbed portion of road are generally with shallow cross drain structures which could fail and divert drainage down the road, and lack of failsafe cross ditches at culvert locations, where a blockage would send water down ditchlines, altering natural drainage patterns a portion of the cross drained flow runs down the ditch and partly down the road surface. Although it is intercepted by the cross ditch at station 56. At 58 creek crossing cross ditch is not sufficiently deep, large flows could run down the road. The ditchline from 62 back is taking substantial flows. Base mapping provided indicates that this flow comes from a stream which has been diverted along the ditch line, and had been ditched across the new road at the switchback ( 66). There is an armoured cross ditch at 63, which puts this stream back into what appears to be a the natural channel again. This stream then joins the S5 stream, crossing the road at 67 in a 1200mm culvert. The 600mm culvert at 66 (previous diverted flow path) is now experiencing only minimal flows. There is a failing box culvert at 69, which is only about 30% effective and will soon fail. Risk Analysis There is judged to be a moderate likelihood of ditch flows and cross drained flows running over or down the road surface due to shallow / non-existent waterbars / failsafe cross ditching. This would result in road surface erosion and drainage diversions on the access road and sediment delivery to S-6 and S5 classed streams. This is considered a moderate consequence. The risk is therefore moderate. Prescription Install waterbars to remove road surface diversions 58 Deepen cross ditch. 61 Install failsafe cross ditch 67 Install broad shallow failsafe cross ditch large flow potential, and overflow could run down Page 67

68 road Significant sediment production in ditchline, seepage all along this ditch. Grass seed. 69 Replace failing box culvert with 800mm CMP CMP Install broad backup cross ditch CPP Install broad backup cross ditch. Consider restricting the deactivated portion of the road to ATV traffic only to minimise sediment production from rutting. Note: The road back of 71 to the road junction is cut into poorly consolidated weathered schistose bedrock and tills. Ditchlines are slumping and infilling. This road will require inspection and significant maintenance measures (beyond the scope of this assessment) Photo Road surface drainage being intercepted by Cross Ditch, grass seeding effective. Page 68

69 Photo , Failing wood culvert Page 69

70 Figure 7 Mosquito Creek Site 1 Detail Page 70

71 5.33 Honeymoon Bay (Site 2) Location: Honeymoon Bay recreation site. Map Reference: H-2 Previously identified issues Grass seeding may be required in areas of previous restoration works. Restoration undertaken Ditch line cleanout Half-waterbars allowing trailer access to rec. site. Construction of rock weirs in ditching and settlement ponds at the lower end adjacent to the lake Minor grading of road surface CMP cleanout, armour ditch in areas of past erosion / concentrated flows Observations Works as described in Silvatech (2004) report have been completed. Ditchline clean and functioning, some grass and shrub vegetation establishing naturally. Road cut materials exposed and some ravelling into ditchline taking place. Shallow waterbars are located on the upper portion of the road, and are effectively draining road surface runoff into the ditchline. These are starting to wear / infill due to traffic with some washboarding taking place. The sumps for the two 300 mm pipes appear to have been very recently cleaned out (Spring 2006?) The material removed has been piled directly adjacent to the sumps and is slumping back in. Drainage laden with fine sediment is discharging into the lake directly below (See photos a c). Culverts are undersized and have a high likelihood of becoming plugged. Risk Analysis There is judged to be a high likelihood of continuous delivery of a small amount of fine sediment via the ditchline and inadequate sumps at the culvert inlets to Adams Lake. This is considered a low consequence. The risk is therefore moderate. Prescription Remove slumping material adjacent to culvert sumps, establish broad shallow armoured sumps and grass seed. Grass seed ditchline and cut slopes as prescribed in Silvatech (2004). Monitor and maintain waterbars on upper portion of access road. Page 71

72 Photo a Honeymoon Bay 300mm pipe at end of ditch above lake. Photo b Honeymoon Bay. Sump at end of road, appears recently cleaned out. Page 72

73 Photo c Honeymoon Bay. Culvert discharge directly into lake. Photo Berm deflecting creek drainage down ditchline. Page 73

74 Photo Improved ditchline on Honeymoon Bay recreation site road. Page 74

75 5.34 Momich Lake Site 3 Location: South of Momich Lake Map Reference: M-3 Previously identified issues Old log box culvert holes have developed in the road, with water passing beneath the road. Road has existing deactivation.(silvatech 2004) Restoration undertaken This site is located near the end of a road which has been deactivated (primarily cross ditched) and is revegetating. Observations The road has been deactivated with frequent cross ditches and is revegetating with alder and immature coniferous species. The site in question is an old log box culvert which is conveying water under the road surface. Holes have formed in several places. Immediately downslope of this site, the outlet of this cross drainage is armoured with very large boulders (>1.5m diameter). The site is in a broad shallow draw. Slopes below are planar at about 40-45%. There is a failsafe cross ditch in place. The road prism is unlikely to fail catastrophically, and blockage of the current flow would be conveyed across the road surface in the failsafe back into the natural channel. Risk Analysis Because of the existence of a backup cross ditch and heavy armouring of the outlet, There is judged to be a low to negligible likelihood that this failing log box will significantly in a slope failure. Prescription Removal of this structure will not result in a significant reduction in risk, and bringing equipment up this already deactivated road is likely to result in excessive disturbance. No further work required Page 75

76 Photo Site 3 Momich Lake area. Page 76

77 5.35 Momich Lake Site 5 Location: South of Gannet Lake Map Reference: M-5 Field Identification: 5 Previously identified issues Ravelling has blocked a culvert. Restoration undertaken None Observations Culvert inlet almost entirely blocked by boulders but still partially functioning. Cross drain culvert taking about 5% of the flow. Significant stream upslope could lead to large washout if not repaired. Risk Analysis There is judged to be a high likelihood of the culvert completely failing and causing a washout resulting in sediment delivery to the S5 stream downslope, with a moderate likelihood of sediment delivery to the S3 reach of the same stream. This is considered a moderate consequence. The risk is therefore high. Prescription Clean out or replace culvert OR Pull culvert and re-establish natural stream course. Photo Site 5 Gannet Lake area. Page 77

78 6.0 Closure This assessment focussed primarily on previously identified sites, but observations of general watershed condition and sediment sources and other potential problem areas were noted. Several natural sediment producing sites were noted during the Gold Creek helicopter overflight, but no additional areas with significant issues related to forest harvesting or road construction, other than those identified in this report, were observed. This risk analysis has been carried out in accordance with generally accepted engineering and geoscientific practice for the area. Conclusions and recommendations presented herein are based on air photo interpretation and visual site inspections of selected areas in each watershed. Further, assessments of soils and slope stability are based on interpretation of surface features and limited sub-surface investigation; actual ground conditions may vary from those inferred. This report provides a qualitative evaluation of hazards associated with sites previously identified in the study area, a description of the potential consequences, and recommendations to reduce the hazards and associated risks. Acceptance of the qualitative consequence values and the subsequent risk analysis is the responsibility of the licensee or the regulatory authority, as is the determination of acceptable risk and the decision to proceed with any action based on that risk analysis. We trust that this report satisfies your present requirements. Should you have any questions or comments, please contact our office at your convenience. Sincerely, Forsite Consultants Ltd. Prepared by: Reviewed By: Peter Weisinger, M.Sc. G.I.T. Project Geoscientist Rod Williams, P.Geo Project Geoscientist Page 78

Why Geomorphology for Fish Passage

Why Geomorphology for Fish Passage Channel Morphology - Stream Crossing Interactions An Overview Michael Love Michael Love & Associates mlove@h2odesigns.com (707) 476-8938 Why Geomorphology for Fish Passage 1. Understand the Scale of the

More information

Stream Geomorphology. Leslie A. Morrissey UVM July 25, 2012

Stream Geomorphology. Leslie A. Morrissey UVM July 25, 2012 Stream Geomorphology Leslie A. Morrissey UVM July 25, 2012 What Functions do Healthy Streams Provide? Flood mitigation Water supply Water quality Sediment storage and transport Habitat Recreation Transportation

More information

1.0 INSPECTION ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER PROJECT, CARMACKS, YUKON. Dear Mr. West-Sells,

1.0 INSPECTION ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER PROJECT, CARMACKS, YUKON. Dear Mr. West-Sells, Doc. No. 162 Rev. 0 Mr. Paul West-Sells President & Chief Operating Officer Western Copper Corporation 2060-1111 West Georgia Street Vancouver, BC V6E 4M3 ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER

More information

3.12 Geology and Topography Affected Environment

3.12 Geology and Topography Affected Environment 3 Affected Environment and Environmental Consequences 3.12 Geology and Topography 3.12.1 Affected Environment 3.12.1.1 Earthquakes Sterling Highway MP 45 60 Project Draft SEIS The Kenai Peninsula is predisposed

More information

Degradation Concerns related to Bridge Structures in Alberta

Degradation Concerns related to Bridge Structures in Alberta Degradation Concerns related to Bridge Structures in Alberta Introduction There has been recent discussion regarding the identification and assessment of stream degradation in terms of how it relates to

More information

Gully Erosion Part 1 GULLY EROSION AND ITS CAUSES. Introduction. The mechanics of gully erosion

Gully Erosion Part 1 GULLY EROSION AND ITS CAUSES. Introduction. The mechanics of gully erosion Gully Erosion Part 1 GULLY EROSION AND ITS CAUSES Gully erosion A complex of processes whereby the removal of soil is characterised by incised channels in the landscape. NSW Soil Conservation Service,

More information

Step 5: Channel Bed and Planform Changes

Step 5: Channel Bed and Planform Changes Step 5: Channel Bed and Planform Changes When disturbed, streams go through a series of adjustments to regain equilibrium with the flow and sediment supply of their watersheds. These adjustments often

More information

Aquifer an underground zone or layer of sand, gravel, or porous rock that is saturated with water.

Aquifer an underground zone or layer of sand, gravel, or porous rock that is saturated with water. Aggradation raising of the streambed by deposition that occurs when the energy of the water flowing through a stream reach is insufficient to transport sediment conveyed from upstream. Alluvium a general

More information

Rock & Aggregate Drop Inlet Protection

Rock & Aggregate Drop Inlet Protection Rock & Aggregate Drop Inlet Protection SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System Supplementary Trap Dispersive Soils

More information

Case Study 2: Twenty-mile Creek Rock Fords

Case Study 2: Twenty-mile Creek Rock Fords Case Study : Twenty-mile Creek Rock Fords Location Crossing Description Washington. Okanagan National Forest. Methow Valley Ranger District. Chewuch river basin, East Chewuch Road. The Twenty-mile Creek

More information

Dan Miller + Kelly Burnett, Kelly Christiansen, Sharon Clarke, Lee Benda. GOAL Predict Channel Characteristics in Space and Time

Dan Miller + Kelly Burnett, Kelly Christiansen, Sharon Clarke, Lee Benda. GOAL Predict Channel Characteristics in Space and Time Broad-Scale Models Dan Miller + Kelly Burnett, Kelly Christiansen, Sharon Clarke, Lee Benda GOAL Predict Channel Characteristics in Space and Time Assess Potential for Fish Use and Productivity Assess

More information

Re: Steep Slope Assessment for 2465 Waverly Drive, Blind Bay, BC; Legal Address: Lot 39, Section 18, Township 22, Range 10, Plan 25579, W6M, KDYD.

Re: Steep Slope Assessment for 2465 Waverly Drive, Blind Bay, BC; Legal Address: Lot 39, Section 18, Township 22, Range 10, Plan 25579, W6M, KDYD. OEL File 1563-1 May 30, 2017 Doug Wall PO Box 774 Salmon Arm, BC V1E 4N7 Re: Steep Slope Assessment for 2465 Waverly Drive, Blind Bay, BC; Legal Address: Lot 39, Section 18, Township 22, Range 10, Plan

More information

APPENDIX E. GEOMORPHOLOGICAL MONTORING REPORT Prepared by Steve Vrooman, Keystone Restoration Ecology September 2013

APPENDIX E. GEOMORPHOLOGICAL MONTORING REPORT Prepared by Steve Vrooman, Keystone Restoration Ecology September 2013 APPENDIX E GEOMORPHOLOGICAL MONTORING REPORT Prepared by Steve Vrooman, Keystone Restoration Ecology September 2 Introduction Keystone Restoration Ecology (KRE) conducted geomorphological monitoring in

More information

6.11 Naas River Management Unit

6.11 Naas River Management Unit 6.11 Naas River Management Unit 6.11.1 Site 41 Issue: Bed and bank erosion Location: E 0685848 N 6058358 Waterway: Naas River Management Unit: Naas River Facing downstream from Bobeyan Rd bridge Facing

More information

December 11, 2006 File:

December 11, 2006 File: December 11, 2006 File: 15-85-38 Alberta Infrastructure and Transportation Room 301, Provincial Building 9621-96 Avenue Peace River, Alberta T8S 1T4 Attention: Mr. Ed Szmata PEACE REGION (SWAN HILLS AREA)

More information

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area.

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area. Sediment Trench SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils [1] Performance of

More information

Black Gore Creek 2013 Sediment Source Monitoring and TMDL Sediment Budget

Black Gore Creek 2013 Sediment Source Monitoring and TMDL Sediment Budget Black Gore Creek 2013 Sediment Source Monitoring and TMDL Sediment Budget Prepared for: Prepared By: - I. Introduction The Black Gore Creek Total Maximum Daily Load (TMDL) was developed in collaboration

More information

Instream Erosion Control General

Instream Erosion Control General Instream Erosion Control General EROSION CONTROL TECHNIQUES Revegetation Temperate Climates Short-Term Non Vegetation Wet Tropics Long-Term Weed Control [1] Semi-Arid Zones Permanent [1] Weed control attributes

More information

APPENDIX A REACH DECRIPTIONS. Quantico Creek Watershed Assessment April 2011

APPENDIX A REACH DECRIPTIONS. Quantico Creek Watershed Assessment April 2011 APPENDIX A REACH DECRIPTIONS Basin 615, South Fork of Quantico Creek - Project Reach Descriptions Reach Name: 615-A Coordinates (NAD 83, Virginia State Plane North): 11796510.57, 6893938.95 to 11801555.79,

More information

CASE STUDIES. Introduction

CASE STUDIES. Introduction Introduction The City of Winston-Salem faces the challenge of maintaining public infrastructure (e.g., water and sewer lines, storm drains, roads, culverts and bridges) while minimizing the potential impacts

More information

Construction Exits Rock pads

Construction Exits Rock pads Construction Exits Rock pads SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow [1] Clayey Soils Type 3 System Supplementary Trap Dispersive Soils [1] Minor

More information

1 INTRODUCTION AND MAJOR FINDINGS... 1

1 INTRODUCTION AND MAJOR FINDINGS... 1 Memorandum To: Lindsey Clark, Stillwater Valley Watershed Council Coordinator From: Chad Raisland, Pioneer Technical Services, Inc. and Karin Boyd, Applied Geomorphology, Inc. CC: Tanya Lester, Stillwater

More information

Track design and management

Track design and management 1 Track design and management Peter Fogarty, Certified Professional Soil Scientist NSW Soil Knowledge Network Cooma, June 18, 2018 Acknowledgements Antia Brademann, Cooma Waterwatch, Organiser Jo Powells,

More information

EFFECTS OF RIPARIAN RETENTION (IN WATERSHEDS) ON ALLUVIAL FANS

EFFECTS OF RIPARIAN RETENTION (IN WATERSHEDS) ON ALLUVIAL FANS EFFECTS OF RIPARIAN RETENTION (IN WATERSHEDS) ON ALLUVIAL FANS TIM GILES GEOMORPHOLOGIST FLNRO EFFECTS OF RIPARIAN RETENTION (IN WATERSHEDS) ON ALLUVIAL FANS Description of alluvial fans Three case studies

More information

Fluvial Driven Alluvial Fans

Fluvial Driven Alluvial Fans Fluvial Driven Alluvial Fans Restoration Project Evaluations - Examples from the Russian and Napa River Watersheds Mia Docto Masters Thesis UC Berkeley 1. Basic Fan Description 2. Fluvial Driven Fan Characteristics

More information

January 17, 2008 File:

January 17, 2008 File: January 17, 2008 File: 15-85-73 Alberta Infrastructure and Transportation Room 301, Provincial Building 9621-96 Avenue Peace River, Alberta T8S 1T4 Attention: Mr. Ed Szmata PEACE REGION (SWAN HILLS AREA)

More information

BCTS BC TIMBER SALES STRAIT OF GEORGIA BUSINESS AREA

BCTS BC TIMBER SALES STRAIT OF GEORGIA BUSINESS AREA Terrain Stability Assessment Additional area added to Cutblock C34M McNab Creek PREPARED FOR: BCTS BC TIMBER SALES STRAIT OF GEORGIA BUSINESS AREA PREPARED BY: COAST OPERATIONS #213-1720 14TH AVE. CAMPBELL

More information

MINISTRY OF FORESTS, LANDS AND NATURAL RESOURCE OPERATIONS, POST-WILDFIRE RISK ANALYSIS PRELIMINARY REPORT

MINISTRY OF FORESTS, LANDS AND NATURAL RESOURCE OPERATIONS, POST-WILDFIRE RISK ANALYSIS PRELIMINARY REPORT MINISTRY OF FORESTS, ANDS AND NATURA RESOURCE OPERATIONS, POST-WIDFIRE RISK ANAYSIS PREIMINARY REPORT NOTE: The results given on this form are preliminary in nature and are intended to be a warning of

More information

DETAILED DESCRIPTION OF STREAM CONDITIONS AND HABITAT TYPES IN REACH 4, REACH 5 AND REACH 6.

DETAILED DESCRIPTION OF STREAM CONDITIONS AND HABITAT TYPES IN REACH 4, REACH 5 AND REACH 6. DETAILED DESCRIPTION OF STREAM CONDITIONS AND HABITAT TYPES IN REACH 4, REACH 5 AND REACH 6. The Eklutna River was divided into study reaches (figure 1) prior to this site visit. Prominent geologic or

More information

When Creek Meets Valley Wall: Prioritizing Erosion Mitigation alongside the Oshawa Landfill

When Creek Meets Valley Wall: Prioritizing Erosion Mitigation alongside the Oshawa Landfill 1 When Creek Meets Valley Wall: Prioritizing Erosion Mitigation alongside the Oshawa Landfill Robin McKillop 1, Dan McParland 1 & Cassie Scobie 2 TRIECA conference March 22-23, 2017 1 Palmer Environmental

More information

The last three sections of the main body of this report consist of:

The last three sections of the main body of this report consist of: Threatened and Endangered Species Geological Hazards Floodplains Cultural Resources Hazardous Materials A Cost Analysis section that provides comparative conceptual-level costs follows the Environmental

More information

CHAPTER GEOLOGICALLY HAZARDOUS AREAS Applicability Regulations.

CHAPTER GEOLOGICALLY HAZARDOUS AREAS Applicability Regulations. CHAPTER 19.07 GEOLOGICALLY HAZARDOUS AREAS 19.07.010 Applicability. Geologically hazardous areas may pose a threat to the health and safety of citizens when incompatible development is sited in areas of

More information

In-channel coarse sediment trap Best Management Practice

In-channel coarse sediment trap Best Management Practice In-channel coarse sediment trap Best Management Practice By Henry R. Hudson July 2002 Environmental Management Associates Ltd., Christchurch Complexity Environmental Value Cost Low Moderate High Low Moderate

More information

February 18, 2003 File: NORTH CENTRAL REGION LANDSLIDE ASSESSMENT HWY 43:16 WHITECOURT EAST HILL (NC1) 2002 ANNUAL INSPECTION REPORT

February 18, 2003 File: NORTH CENTRAL REGION LANDSLIDE ASSESSMENT HWY 43:16 WHITECOURT EAST HILL (NC1) 2002 ANNUAL INSPECTION REPORT February 18, 2003 File: 15-76-11 Alberta Transportation Room 223, Provincial Building 4709 44 Avenue Stony Plain, Alberta T7Z 1N4 Attention: Mr. Rob Lonson, P.Eng. NORTH CENTRAL REGION LANDSLIDE ASSESSMENT

More information

CCR Rule Annual Inspection Report (cont.) 2

CCR Rule Annual Inspection Report (cont.) 2 The inspection findings consisted of maintenance items and items that were not observed to be signs or potential signs of significant structural weakness. No deficiencies or disrupting conditions that

More information

B805 TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES - OPSS 805

B805 TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES - OPSS 805 B805 MEASURES - OPSS 805 805.1 GENERAL Construction activities frequently remove protective cover and expose soil to accelerated rates of erosion. Sediments generated thereby can be conveyed via runoff

More information

Erosion and Sediment Control Measures 2.7 Silt Fences

Erosion and Sediment Control Measures 2.7 Silt Fences Erosion and Sediment Control Measures Silt fences are designed to intercept sheet flow sediment laden stormwater run-off and filter out both the larger and smaller particles of sediment. Silt fences and

More information

Riparian Assessment. Steps in the right direction... Drainage Basin/Watershed: Start by Thinking Big. Riparian Assessment vs.

Riparian Assessment. Steps in the right direction... Drainage Basin/Watershed: Start by Thinking Big. Riparian Assessment vs. Riparian Assessment vs. Monitoring Riparian Assessment What is a healthy stream? Determine stream/riparian health Determine change or trend, especially in response to mgmt Classification = designation

More information

Carmel River Bank Stabilization at Rancho San Carlos Road Project Description and Work Plan March 2018

Carmel River Bank Stabilization at Rancho San Carlos Road Project Description and Work Plan March 2018 Carmel River Bank Stabilization at Rancho San Carlos Road Project Description and Work Plan March 2018 EXISTING CONDITION The proposed Carmel River Bank Stabilization at Rancho San Carlos Road Project

More information

3.18 GEOLOGY AND SOILS

3.18 GEOLOGY AND SOILS 3.18 GEOLOGY AND SOILS This section discusses geologic resource concerns as they relate to the environment, public safety, and project design both during construction and after completion of the project.

More information

Coarse Sediment Traps

Coarse Sediment Traps Coarse Sediment Traps SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils [2] Type 3 System Supplementary Trap Dispersive Soils [1] Though primarily

More information

PEACE REGION GRANDE PRAIRIE GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM NAD 83 COORDINATES N 6,178,811 E 403,309

PEACE REGION GRANDE PRAIRIE GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM NAD 83 COORDINATES N 6,178,811 E 403,309 PEACE REGION GRANDE PRAIRIE GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM SITE NUMBER GP-4a LEGAL DESCRIPTION LSD 12-10-78-4-W6M SITE NAME Burnt River Bridge - West Approach Slide HIGHWAY & KM Hwy 49:06

More information

SCOPE OF PRESENTATION STREAM DYNAMICS, CHANNEL RESTORATION PLANS, & SEDIMENT TRANSPORT ANALYSES IN RELATION TO RESTORATION PLANS

SCOPE OF PRESENTATION STREAM DYNAMICS, CHANNEL RESTORATION PLANS, & SEDIMENT TRANSPORT ANALYSES IN RELATION TO RESTORATION PLANS DESIGN METHODS B: SEDIMENT TRANSPORT PROCESSES FOR STREAM RESTORATION DESIGN PETER KLINGEMAN OREGON STATE UNIVERSITY CIVIL ENGINEERING DEPT., CORVALLIS 2 ND ANNUAL NORTHWEST STREAM RESTORATION DESIGN SYMPOSIUM

More information

Rock Sizing for Waterway & Gully Chutes

Rock Sizing for Waterway & Gully Chutes Rock Sizing for Waterway & Gully Chutes WATERWAY MANAGEMENT PRACTICES Photo 1 Rock-lined waterway chute Photo 2 Rock-lined gully chute 1. Introduction A waterway chute is a stabilised section of channel

More information

Erosion Surface Water. moving, transporting, and depositing sediment.

Erosion Surface Water. moving, transporting, and depositing sediment. + Erosion Surface Water moving, transporting, and depositing sediment. + Surface Water 2 Water from rainfall can hit Earth s surface and do a number of things: Slowly soak into the ground: Infiltration

More information

PHYSICAL GEOGRAPHY. By Brett Lucas

PHYSICAL GEOGRAPHY. By Brett Lucas PHYSICAL GEOGRAPHY By Brett Lucas FLUVIAL PROCESSES Fluvial Processes The Impact of Fluvial Processes on the Landscape Streams and Stream Systems Stream Channels Structural Relationships The Shaping and

More information

SECTION G SEDIMENT BUDGET

SECTION G SEDIMENT BUDGET SECTION G SEDIMENT BUDGET INTRODUCTION A sediment budget has been constructed for the for the time period 1952-2000. The purpose of the sediment budget is to determine the relative importance of different

More information

MEMORANDUM. wa.tsr..-z.n~.e.s-t.i~at.i.o.ns... Branch... Mr. Webster contends that prior to excavation of the gravel

MEMORANDUM. wa.tsr..-z.n~.e.s-t.i~at.i.o.ns... Branch... Mr. Webster contends that prior to excavation of the gravel TO... J. C. Foweraker 2... Head Gr o w a t er S e c t i on... Hyar....og~~~.~.~vis.ion... wa.tsr..-z.n~.e.s-t.i~at.i.o.ns... Branch... eernment OF BRITISH COLUMBIA MEMORANDUM II 0 PROM A. P. Kohut, Geological

More information

PEACE RIVER EAST HILL - HWY 2:60 (PH2) SELECT PHOTOGRAPHS August 22, 2007 File: Photo E003. Station May 2007

PEACE RIVER EAST HILL - HWY 2:60 (PH2) SELECT PHOTOGRAPHS August 22, 2007 File: Photo E003. Station May 2007 Photo E003 0+000 Viewing looking upslope at Site 4 from highway. Conditions unchanged from 2006. Photo E018 0+000 Localized erosion within road fill on upslope side of highway. Photo E022 0+250 Looking

More information

Best Management Practices for Coldwater Fisheries Enhancement and Restoration

Best Management Practices for Coldwater Fisheries Enhancement and Restoration Best Management Practices for Coldwater Fisheries Enhancement and Restoration MACC Annual Environmental Conference 2017 March 3, 2017 Tim Dexter, MassDOT Highway Division 1 Leading the Nation in Transportation

More information

Channel Assessments of Selected Watersheds within TFL 52

Channel Assessments of Selected Watersheds within TFL 52 Channel Assessments of Selected Watersheds within TFL 52 prepared for: West Fraser Mills Ltd. Quesnel, BC prepared by: John Berry, M.Sc., R.P.F. Victoria, BC Channel Assessments TFL 52 Summary SUMMARY

More information

January 12, 2006 File:

January 12, 2006 File: January 12, 2006 File: 15-85-13 Alberta Infrastructure and Transportation Room 301, Provincial Building 9621-96 Avenue Peace River, Alberta T8S 1T4 Attention: Mr. Ed Szmata PEACE REGION (PEACE HIGH LEVEL

More information

Template for Sediment and Erosion Control Plan General Instructions. Section Instructions

Template for Sediment and Erosion Control Plan General Instructions. Section Instructions Template for Sediment and Erosion Control Plan General Instructions Introduction: Soil erosion and sediment deposition from farmlands can contribute to degraded surface water quality. Sediment delivery

More information

Diagnostic Geomorphic Methods for Understanding Future Behavior of Lake Superior Streams What Have We Learned in Two Decades?

Diagnostic Geomorphic Methods for Understanding Future Behavior of Lake Superior Streams What Have We Learned in Two Decades? Diagnostic Geomorphic Methods for Understanding Future Behavior of Lake Superior Streams What Have We Learned in Two Decades? Faith Fitzpatrick USGS WI Water Science Center, Middleton, WI fafitzpa@usgs.gov

More information

ADDRESSING GEOMORPHIC AND HYDRAULIC CONTROLS IN OFF-CHANNEL HABITAT DESIGN

ADDRESSING GEOMORPHIC AND HYDRAULIC CONTROLS IN OFF-CHANNEL HABITAT DESIGN ADDRESSING GEOMORPHIC AND HYDRAULIC CONTROLS IN OFF-CHANNEL HABITAT DESIGN Conor Shea - Hydrologist U.S. Fish and Wildlife Service Conservation Partnerships Program Arcata, CA Learning Objectives Examine

More information

Clyde River Landslide

Clyde River Landslide Clyde River Landslide Department of Geology, Perkins Hall, University of Vermont, Burlington, VT 05405 Abstract: This paper investigates a landslide on the Clyde River in Newport, Vermont. The landslide

More information

GEOL 1121 Earth Processes and Environments

GEOL 1121 Earth Processes and Environments GEOL 1121 Earth Processes and Environments Wondwosen Seyoum Department of Geology University of Georgia e-mail: seyoum@uga.edu G/G Bldg., Rm. No. 122 Seyoum, 2015 Chapter 6 Streams and Flooding Seyoum,

More information

U-Shaped Sediment Traps

U-Shaped Sediment Traps U-Shaped Sediment Traps SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils [1] Type 3 System Supplementary Trap Dispersive Soils [1] Generally

More information

Rosgen Classification Unnamed Creek South of Dunka Road

Rosgen Classification Unnamed Creek South of Dunka Road Rosgen Classification Unnamed Creek South of Dunka Road Prepared for Poly Met Mining Inc. September 2013 Rosgen Classification Unnamed Creek South of Dunka Road Prepared for Poly Met Mining Inc. September

More information

Running Water Earth - Chapter 16 Stan Hatfield Southwestern Illinois College

Running Water Earth - Chapter 16 Stan Hatfield Southwestern Illinois College Running Water Earth - Chapter 16 Stan Hatfield Southwestern Illinois College Hydrologic Cycle The hydrologic cycle is a summary of the circulation of Earth s water supply. Processes involved in the hydrologic

More information

Materials. Use materials meeting the following.

Materials. Use materials meeting the following. 208.01 Section 208. SOIL EROSION AND SEDIMENTATION CONTROL 208.01 Description. Install and maintain erosion and sedimentation controls to minimize soil erosion and to control sedimentation from affecting

More information

Chapter 3 Erosion in the Las Vegas Wash

Chapter 3 Erosion in the Las Vegas Wash Chapter 3 Erosion in the Las Vegas Wash Introduction As described in Chapter 1, the Las Vegas Wash (Wash) has experienced considerable change as a result of development of the Las Vegas Valley (Valley).

More information

ES 105 Surface Processes I. Hydrologic cycle A. Distribution % in oceans 2. >3% surface water a. +99% surface water in glaciers b.

ES 105 Surface Processes I. Hydrologic cycle A. Distribution % in oceans 2. >3% surface water a. +99% surface water in glaciers b. ES 105 Surface Processes I. Hydrologic cycle A. Distribution 1. +97% in oceans 2. >3% surface water a. +99% surface water in glaciers b. >1/3% liquid, fresh water in streams and lakes~1/10,000 of water

More information

Gully Assessment Procedure Guidebook

Gully Assessment Procedure Guidebook of BRITISH COLUMBIA Gully Assessment Procedure Guidebook Fourth edition Version 4.1 February 2001 Ministry of Forests of BRITISH COLUMBIA Gully Assessment Procedure Guidebook Fourth edition Version 4.1

More information

Contrasting Behaviour of Two Recent, Large Landslides in Discontinuous Permafrost Little Salmon Lake, Yukon, Canada

Contrasting Behaviour of Two Recent, Large Landslides in Discontinuous Permafrost Little Salmon Lake, Yukon, Canada Contrasting Behaviour of Two Recent, Large Landslides in Discontinuous Permafrost Little Salmon Lake, Yukon, Canada Ryan R. Lyle BGC Engineering Inc. Kamloops, British Columbia D. Jean Hutchinson Queen

More information

SECTION A MASS WASTING

SECTION A MASS WASTING SECTION A MASS WASTING INTRODUCTION This section summarizes the methods and results of a mass wasting assessment conducted on the Mendocino Redwood Company, LLC (MRC) ownership in the Ackerman Creek and

More information

PolyMet NorthMet Project

PolyMet NorthMet Project RS 26 Draft-01 December 8, 2005 RS26 Partridge River Level 1 Rosgen Geomorphic Survey Rosgen Classification Partridge River from Headwaters to Colby Lake Prepared for PolyMet NorthMet Project December

More information

Rock Sizing for Small Dam Spillways

Rock Sizing for Small Dam Spillways Rock Sizing for Small Dam Spillways STORMWATER MANAGEMENT PRACTICES Photo 1 Rock-lined spillway on a construction site sediment basin Photo 2 Rock-lined spillway on a small farm dam 1. Introduction A chute

More information

Continuing Education Associated with Maintaining CPESC and CESSWI Certification

Continuing Education Associated with Maintaining CPESC and CESSWI Certification Continuing Education Associated with Maintaining CPESC and CESSWI Certification Module 2: Stormwater Management Principles for Earth Disturbing Activities Sponsors: ODOTs Local Technical Assistance Program

More information

Four Mile Run Levee Corridor Stream Restoration

Four Mile Run Levee Corridor Stream Restoration Four Mile Run Levee Corridor Stream Restoration 30% Design Summary U.S. Army Corps of Engineers, Baltimore District Presentation Outline Four Mile Run 1.) Historic Perspective 2.) Existing Conditions 3.)

More information

Black Gore Creek Sediment Source Monitoring and TMDL Sediment Budget

Black Gore Creek Sediment Source Monitoring and TMDL Sediment Budget Black Gore Creek 2012 Sediment Source Monitoring and TMDL Sediment Budget Prepared for: The Eagle River Watershed Council Prepared By: RiverRestoration.org - I. Introduction Interstate 70 is a major highway

More information

CR AAO Bridge. Dead River Flood & Natural Channel Design. Mitch Koetje Water Resources Division UP District

CR AAO Bridge. Dead River Flood & Natural Channel Design. Mitch Koetje Water Resources Division UP District CR AAO Bridge Dead River Flood & Natural Channel Design Mitch Koetje Water Resources Division UP District Old County Road AAO Bridge Map courtesy of Marquette County Silver Lake Basin McClure Basin

More information

patersongroup Consulting Engineers April 20, 2010 File: PG1887-LET.01R Novatech Engineering Consultants Suite 200, 240 Michael Cowpland Drive

patersongroup Consulting Engineers April 20, 2010 File: PG1887-LET.01R Novatech Engineering Consultants Suite 200, 240 Michael Cowpland Drive patersongroup April 20, 2010 File: PG1887-LET.01R Novatech Engineering Consultants Suite 200, 240 Michael Cowpland Drive Ottawa, Ontario K2M 1P6 Attention: Mr. Adam Thompson Consulting Engineers 28 Concourse

More information

DRAFT DRAFT DRAFT DRAFT DRAFT SEDIMENT CONTROLS Method Application Description BMP Sediment fencing Flat Ground Y Anywhere low flow runoff is Sloping Ground Y Geotextile fabric, buried at the bottom

More information

June 9, R. D. Cook, P.Eng. Soils Engineer Special Services Western Region PUBLIC WORKS CANADA WESTERN REGION REPORT ON

June 9, R. D. Cook, P.Eng. Soils Engineer Special Services Western Region PUBLIC WORKS CANADA WESTERN REGION REPORT ON PUBLIC WORKS CANADA WESTERN REGION REPORT ON GEOTECHNICAL INVESTIGATION PROPOSED MARTIN RIVER BRIDGE MILE 306.7 MACKENZIE HIGHWAY Submitted by : R. D. Cook, P.Eng. Soils Engineer Special Services Western

More information

Solutions to Flooding on Pescadero Creek Road

Solutions to Flooding on Pescadero Creek Road Hydrology Hydraulics Geomorphology Design Field Services Photo courtesy Half Moon Bay Review Solutions to Flooding on Pescadero Creek Road Prepared for: San Mateo County Resource Conservation District

More information

Appendix F Channel Grade Control Structures

Appendix F Channel Grade Control Structures Stream Simulation Appendix F Channel Grade Control Structures This appendix briefly describes permanent grade control structures that are sometimes needed in the upstream and/or downstream reaches adjacent

More information

Overview of fluvial and geotechnical processes for TMDL assessment

Overview of fluvial and geotechnical processes for TMDL assessment Overview of fluvial and geotechnical processes for TMDL assessment Christian F Lenhart, Assistant Prof, MSU Research Assoc., U of M Biosystems Engineering Fluvial processes in a glaciated landscape Martin

More information

MISSION CREEK WATERSHED (2002 Report Year 4)

MISSION CREEK WATERSHED (2002 Report Year 4) Stream Channel Monitoring Program for the MISSION CREEK WATERSHED (2002 Report Year 4) (Penticton Forest District) Prepared for RIVERSIDE FOREST PRODUCTS LTD. Prepared by DOBSON ENGINEERING LTD. #4, 1960

More information

Dolores River Watershed Study

Dolores River Watershed Study CHAPTER 4: RIVER AND FLOODPLAIN ISSUES The Dolores River falls into a category of streams in Colorado that share some unique characteristics. Like some other mountain streams in the state, it has a steep

More information

TABLE OF CONTENTS LIST OF TABLES. Page

TABLE OF CONTENTS LIST OF TABLES. Page TABLE OF CONTENTS Page 11.0 EFFECTS OF THE ENVIRONMENT ON THE PROJECT... 11-1 11.1 Weather Conditions... 11-1 11.2 Flooding... 11-2 11.3 Forest Fires... 11-2 11.4 Permafrost and Subsidence Risk... 11-3

More information

Rock Sizing for Batter Chutes

Rock Sizing for Batter Chutes Rock Sizing for Batter Chutes STORMWATER MANAGEMENT PRACTICES Photo 1 Rock-lined batter chute Photo 2 Rock-lined batter chute 1. Introduction In the stormwater industry a chute is a steep drainage channel,

More information

Rapid Geomorphic Assessments: RGA s

Rapid Geomorphic Assessments: RGA s Establishing Current Reference Conditions Rates and concentrations of suspended-sediment transport vary over time and space due to factors such as precipitation characteristics and discharge, geology,

More information

Flood and Stream Restoration

Flood and Stream Restoration 2 3 4 Pedestrian bridge under construction 3 CSPs perched on DS side Large area of sand deposition Bottom layer of gabions has been scoured out large bar of gabion stone Gabions slumping bank slope failure

More information

This report was prepared by Klohn Crippen Consultants Ltd. for Alberta Transportation Central Region under Contract No. CE053/2000.

This report was prepared by Klohn Crippen Consultants Ltd. for Alberta Transportation Central Region under Contract No. CE053/2000. Alberta Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 June 7, 2002 Mr. Melvin Mayfield, P.Eng. Project Engineer Dear Mr. Mayfield: Central Region Landslide Assessment Site

More information

Instream Sediment Control Systems

Instream Sediment Control Systems Instream Sediment Control Systems INSTREAM PRACTICES Photo 1 Photo 2 Modular sediment The information contained within this series of fact sheets deals only with the design of temporary instream sediment

More information

September 3, 2009 File: NORTH CENTRAL REGION GEOHAZARD ASSESSMENT HWY 40:28 NORTH OF CADOMIN (NC50) 2009 ANNUAL INSPECTION REPORT

September 3, 2009 File: NORTH CENTRAL REGION GEOHAZARD ASSESSMENT HWY 40:28 NORTH OF CADOMIN (NC50) 2009 ANNUAL INSPECTION REPORT GEOTECHNICAL ENVIRONMENTAL MATERIALS September 3, 2009 File: 15-16-226 Alberta Transportation 2 nd Floor, Provincial Building 111 54 Street Edson, Alberta T7E 1T2 Attention: Mr. Cliff Corner NORTH CENTRAL

More information

Fluvial Geomorphic Guidelines

Fluvial Geomorphic Guidelines Fluvial Geomorphic Guidelines FACT SHEET I: GEOMORPHOLOGICAL HAZARDS CONFINED AND UNCONFINED WATERCOURSES Channel migration and erosion can create substantial risk to inappropriately located infrastructure

More information

EAGLES NEST AND PIASA ISLANDS

EAGLES NEST AND PIASA ISLANDS EAGLES NEST AND PIASA ISLANDS HABITAT REHABILITATION AND ENHANCEMENT PROJECT MADISON AND JERSEY COUNTIES, ILLINOIS ENVIRONMENTAL MANAGEMENT PROGRAM ST. LOUIS DISTRICT FACT SHEET I. LOCATION The proposed

More information

HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR (c)(1)(i) (xii)

HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR (c)(1)(i) (xii) HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR 257.73(c)(1)(i) (xii) (i) Site Name and Ownership Information: Site Name: E.C. Gaston Steam Plant Site Location:

More information

RESERVOIR DRAWDOWN RATES/RESERVOIR DRAWDOWN TEST Iron Gate, Copco (I & II), and JC Boyle Dams

RESERVOIR DRAWDOWN RATES/RESERVOIR DRAWDOWN TEST Iron Gate, Copco (I & II), and JC Boyle Dams TECHNICAL MEMORANDUM No. 1 TO: Michael Bowen California Coastal Conservancy Geotechnical & Earthquake Engineering Consultants CC: Eric Ginney Philip Williams & Associates PREPARED BY: Paul Grant SUBJECT:

More information

Template for Sediment and Erosion Control Plan General Instructions

Template for Sediment and Erosion Control Plan General Instructions Template for Sediment and Erosion Control Plan General Instructions Introduction: Soil erosion and sediment deposition from farmlands can contribute to degraded surface water quality. Sediment delivery

More information

Chapter 11. Rivers: Shaping our landscape

Chapter 11. Rivers: Shaping our landscape Chapter 11 Rivers: Shaping our landscape Learning outcomes In this presentation you will learn: Common terms associated with rivers About the three stages of a river About the processes of river erosion

More information

SCOTCH, KWIKOIT and CORNING CREEKS DETAILED and RECONNAISSANCE TERRAIN STABILITY MAPPING SALMON ARM FOREST DISTRICT. P. oject No.

SCOTCH, KWIKOIT and CORNING CREEKS DETAILED and RECONNAISSANCE TERRAIN STABILITY MAPPING SALMON ARM FOREST DISTRICT. P. oject No. SCOTCH, KWIKOIT and CORNING CREEKS DETAILED and RECONNAISSANCE TERRAIN STABILITY MAPPING SALMON ARM FOREST DISTRICT P. oject No. 0808-98-89822 DETAILED and RECONNAISSANCE TERRAIN MAPPING with INTERPRETATIONS

More information

ISSUED FOR CONSTRUCTION

ISSUED FOR CONSTRUCTION PAGE No. DESCRIPTION 1 Cover Page 2 Overview Map 3 Western Road Plan View 4 Eastern Road Plan View West Road Profiles & Cross Sections 6-7 East Road Profiles 8- East Road Cross Sections 11-14 Campsite

More information

Why Stabilizing the Stream As-Is is Not Enough

Why Stabilizing the Stream As-Is is Not Enough Why Stabilizing the Stream As-Is is Not Enough Several examples of alternatives to the County s design approach have been suggested. A common theme of these proposals is a less comprehensive effort focusing

More information

The Effects of Hydraulic Structures on Streams Prone to Bank Erosion in an Intense Flood Event: A Case Study from Eastern Hokkaido

The Effects of Hydraulic Structures on Streams Prone to Bank Erosion in an Intense Flood Event: A Case Study from Eastern Hokkaido Symposium Proceedings of the INTERPRAENENT 2018 in the Pacific Rim The Effects of Hydraulic Structures on Streams Prone to Bank Erosion in an Intense Flood Event: A Case Study from Eastern Hokkaido Daisuke

More information

1 PROJECT BACKGROUND. August 14, Alberta Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8

1 PROJECT BACKGROUND. August 14, Alberta Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8 August 14, 2013 Alberta Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 Mr. Dennis Grace, P.Eng. Construction Engineer Dear Mr. Grace: Central Region Geohazard Assessment 2013

More information

M. Sloat, AAg., CPESC R.J. Redden, R.P.Bio., A.Sc.T., CPESC. EDI Environmental Dynamics Inc Continental Way Prince George, B.C.

M. Sloat, AAg., CPESC R.J. Redden, R.P.Bio., A.Sc.T., CPESC. EDI Environmental Dynamics Inc Continental Way Prince George, B.C. OVERVIEW OF BEST PRACTICES FOR SURFACE EROSION PROTECTION AND SEDIMENT CONTROL FOR THE DEVELOPMENT PHASE OF SURFACE MINING FOR COAL IN NORTHEAST BRITISH COLUMBIA M. Sloat, AAg., CPESC R.J. Redden, R.P.Bio.,

More information

Rivers T. Perron

Rivers T. Perron 1 Rivers T. Perron 12.001 After our discussions of large-scale topography, how we represent topography in maps, and how topography interacts with geologic structures, you should be frothing at the mouth

More information