Re: Experimental Evaluation of Fishway Modifications on the Passage Behavior of Adult Pacific Lamprey at Bonneville Dam

Size: px
Start display at page:

Download "Re: Experimental Evaluation of Fishway Modifications on the Passage Behavior of Adult Pacific Lamprey at Bonneville Dam"

Transcription

1 Page 1 Summary Report To: David Clugston, USACE From: Eric Johnson, Matt Keefer, and Chris Peery (Fish Ecology Research Laboratory, University of Idaho), and Mary Moser (Northwest Fisheries Science Center, NOAA-Fisheries) Re: Experimental Evaluation of Fishway Modifications on the Passage Behavior of Adult Pacific Lamprey at Bonneville Dam Introduction Radiotelemetry studies suggest that lamprey have difficulty negotiating fishways at hydropower dams that were designed to pass adult salmonids (Moser et al. 2002). At Bonneville Dam, less than half of the radio tagged lamprey that approach the dam successfully pass (Moser et. 2002, 2005, Johnson el al. in review). Relatively low passage success for Pacific lamprey has been presumed to be a result of unfavorable conditions in and near fishways that create complex environments for migration, including high turbulent flows, physical barriers (serpentine weirs, diffuser gratings, sharp corners) and artificial lighting (count windows). Tests were conducted in an experimental fishway at the Bonneville Dam adult fish facility between 16 July and 4 August 2008 to evaluate the response of adult Pacific lamprey to proposed modifications at the Cascade Island fishway entrance. Modifications include redesigning the entrance, adding artificial rock structures to the bottom of the fishway to create velocity refuges for lamprey passage during high flows, and building a lamprey passage structure (LPS). Tests were conducted to evaluate passage times and behavior of Pacific lamprey under high flow conditions with and without velocity refuges. Additional tests were also performed to determine if lamprey using these refuges could be directed to a LPS. These tests were initiated after results from previous experimental flume studies indicated that velocity disruptors (artificial rocks) placed along the bottom of the fishway significantly decreased the passage time through orifices and through fishways under moderate flow (< 16 head and < 8.8 ft s -1 ) and did not affect fishway passage success rate (Daigle et. al 2005). Our goal was to test passage times and success using similar prototype rock structures at higher flows (24 head and > 11 ft s -1 ) that occur at fishway entrances. Tests where run to assess fish behavior and passage times under conditions with and without artificial rock refuges situated along the bottom of the experimental flume downstream of the orifice as well as upstream of the orifice along one side. The placement of refuges upstream of the orifice was to test the applicability to direct fish to a LPS once fish enter the fishway. Methods Flume design: The fishway was comprised of three main sections (listed from the upstream end; Figure 1). 1) A 2.0 long 8.0 deep collection area with fykes that allowed lamprey to enter but inhibited exits. The collection area was divided to separate lamprey that used the side of the fishway with rock refuges from those that used the smooth-bottomed side. 2) A 27 4 experimental section (10% slope) that consisted of a non-overflow weir with a submerged square

2 Page 2 orifice (18 ) with rounded bulkhead edges. The orifice was centered in the middle of the weir (Figure 2). Upstream of the weir along the bottom of the fishway was a 4 4 removable aluminum plate with wooden rocks refuges (3.5 high and 4.0 diameter). These refuges were positioned along one side of the flume upstream of the weir that led to a wall that divided the flume lengthwise (Figure 2). Downstream of the weir was a second removable aluminum plate (4 2 ) with refuges. Refuges were spaced 7.75 apart from their centers (crosscurrent) and 11.5 (upstream-to-downstream) in the first series of trials and 15.5 and 11.5 in subsequent trials. Rocks were positioned in a staggered pattern to break up flow along the bottom of the fishway. 3). At the downstream end was 2.6 long 8.0 deep rest box bounded by a removable perforated plate and a permanent perforated plate on the downstream end where fish were placed at the beginning of the test and allowed to acclimate to conditions before the plate was lifted to allow access to the experimental section of the flume. At the downstream end of the flume was an adjustable outflow wall to control pool height in the fishway. Water was supplied to the experimental flume by two 14 pipes capable of generating flows of 220 gal s -1. Lamprey collection: Fish were collected at night by portable traps as they ascended the Washington shore fishway at Bonneville Dam. Weights, lengths, and girths were taken for each fish and a half-duplex passive integrated transponder tag (HD PIT) was sutured to the base of the dorsal fin. Fish were held at least 10 hrs in covered aluminum tanks prior to each test. Movement through the experimental fishway was monitored using a series of swim-through HD PIT antennas just upstream of the release area, at the weir, and upstream of the weir on either side of the divided wall (Figure 3). Movements past the weir were observed at viewpoints built into the sides of the experimental channel and were also recorded using an infrared video camera. Two to four replicates of 10 fish each were performed during nighttime hours using a total of 130 HD PIT tagged fish. Tests were run for 2 h. Experiments were run with and without the rock structures and at head differentials of 2.0 (water velocities ft s -1 ) and 1.5 ft (water velocities ( ft s -1 ).

3 Page 3 Figure1. Experimental fishway configuration used for lamprey evaluations inside the Bonneville Dam adult fish facility. Figure 2. Photos of the experimental fishway looking downstream (left) and overhead (right) showing the placement of the divider wall, rock refuges, orifice (with swim-through antenna), and downstream swim-through antenna.

4 Page 4 Results Fish size.--there was no significant difference in fish weight by test (F = 0.3, P = 0.885, df = 4) or by trial (F = 0.9, P = 0.523, df = 11). Length and girth tests had similar results (Table 1). Table 1. Summary of tests Test Mean size Trial Test Head Rocks Spacing Date n Length Weight Girth Yes July Yes July Yes July No 21 July No 22 July No 23 July Yes July Yes July No 27 July No 28 July Yes July Yes August Passage success. PIT tag records and final locations of fish at the end of the 2 h trails were used to determine percent passage success. Chi-sq results with trials pooled within test: all five tests (χ 2 = 53.2, P < 0.001). Significant pairs: Test 1 v 3; Test 1 v 5; Test 2 v 3; Test 2 v 5; Test 3 v 4; Test 4 v 5 (P < in all cases). The majority of lamprey were able to pass the length of the flume with the lower (1.5 ft) head and at the high head (2 ft) without rocks (Figure 1). Fewer fish were successful with rocks present at the high head level. From visual observations, it was apparent that the spacing of the rocks was too narrow and interfered with fish attempts to move forward at the higher flow levels. A second series of tests were initiated using wider spacing intervals. Results were improved from the original design (40% vs 20% success). We modified the pattern further based on observations, but in the second trial 9 or 10 fish failed to move from the base of the flume during the trial. Because of the late date and warm water temperature, we suspected that the lamprey were less motivated to migrate and so trials were terminated for the year at this point.

5 Page Successful (%) Head (ft): Rocks: 1.5 Yes 1.5 No 2.0 Yes 2.0 No 2.0 Yes Spacing (in): Figure 1. Lamprey conversion rates through the experimental fishway (%). Different bar markings = Tests 1-5, from left. Passage times. Using PIT tag records and visual observation, we determined time for fish to pass through the test area of the flume (Figure 2). With all tests included, passage times were significantly different by test (F = 3.1, P = 0.022, df = 4). The trial term was non-significant (F = 1.0, P = 0.440, df = 7). Overall model (time = trial(test) + test) had F = 2.6, P = 0.009, df = 11. Tukey s pairwise tests were significant (P < 0.05) for: Test 3 v 4; Test 3 v 1; Test 3 v 2. Basically, the original 2.0 ft of head with original rocks pattern was the slow version.

6 Page Passage time (min) Head (ft): Rocks: Yes No Yes No Yes Spacing (in): Figure 2. Box plots of Antenna 4-Antenna 3 passage times using the first records at each antenna. Numbers above bar = n. Tests 1-5, from left. Mean and median passage times (minutes): 13.5, 12.0 (Test 1), 22.3, 13.5 (Test 2), 50.3, 49.0 (Test 3), 25.8, 20.5 (Test 4), 26.2, 25.0 (Test 5). Passage guidance. We used the final locations of lamprey at the end of the 2 h trials to determine the effectiveness of using rocks to guide lamprey direction of movement. In general, the lamprey appeared to favor moving along the left (facing upstream) side of the flume, with or without rocks (Figure 3). Statistically, there was not a significant difference in side selected by lamprey, relative to rock placement. Chi-sq results with trials pooled within tests (χ 2 = 2.4, P = 0.49) indicated that there was no significant difference in the proportion of lamprey caught in the rock refuge side of the trap compared to the smooth side of the trap.

7 Page 7 Figure 3. Percentage of lamprey caught in each side of the trap at the end of the 2 hours. Number above bar = n. Gray bars represent the side of trap fish were caught using the smooth side of the experimental flume and the black bars indicate trap location for those fish using the rock refuge side of the experimental flume. Entry time. We used visual recording to time to make a successful entry through the test configuration. Times were variable across trials. In general, times to pass though the entry area were consistent with behaviors notes above. At high velocities tested here, lamprey took 4 to 8 min on average to pass through the entry area (Table 2). Fish moved slowly along the bottom, often stationary (resting) for several minutes at a time between upstream movements. At time these upstream movements were interfered with by presence of rocks, lengthening passage times.

8 Page 8 Table 2. Numbers of lamprey observed approaching the submerged orifice, numbers of fish falling back through the orifice, the numbers of fish that successfully passed the orifice without falling back and mean passage time through the orifice. Times were calculated from the first time a lamprey came into camera view until it completely passed through the orifice. Test Trial Head Rocks Spacing Date Video No. Approach Fallback No. Pass Mean Passage time (min) Range (min) Yes July No Yes July No Yes July No No 21 July No No 22 July No No 23 July No Yes July Yes :54 4: Yes July Yes No 27 July Yes :03 2:25-6: No 28 July Yes :14 3:47-12: Yes July Yes :45 10: Yes August Yes :50 4:50 Discussion Designing a fishway entrance to accommodate both lamprey and salmon passage can be difficult. High velocities at entrances that are used to attract returning salmonids can result in reduced passage efficiencies of adult Pacific lamprey (Moser et al. 2002, Johnson et al. in review). We compared passage behavior in the experimental fishway flume to simulated conditions lamprey may encounter at a newly designed fishway entrance. Based on our comparison of passage efficiencies and times between treatments, the benefits of closely spaced artificial velocity refuges were unfavorable at higher flows (24 head and > 11 ft s -1 ) and insignificant at intermediate flows (18 head and < 10.1 ft s -1 ). When velocity refuges were present passage times (from release to passage through the submerged orifice) were significantly longer. Conversion rates through the flume during the high velocity treatments decreased from 60-90% success without rock refuges to < 20% with refuges. Daigle et al. (2005) observed passage efficiencies greater than 90% for seven of eight treatment groups with and without velocity refuges at head differentials ranging from and water velocities < 8.8 ft s -1 and found that velocity refuges at these flows significantly decreased the passage time through the submerged orifice as well as through the fishway. The two trials (n = 20) that we ran with 18 head and water velocities between ft s -1 resulted in similar passage efficiencies (90%). However, the presence of refuges did not significantly improve passage efficiencies or passage times.

9 Page 9 Observations at key locations during the high velocity treatments using infrared lights and camera indicated as many fish falling back through the orifice as those that passed. Passage times through the submerged orifice ranged from 3:47-12:44 minutes for individual fish with the average time ranging from 4:03-8:14 min (during trials of 2.0 ft without rocks). Passage times for the few fish that successfully passed the submerged orifice during the high velocity treatment with refuges ranged from 4:45 to 10:45 min. This is roughly a 2-4 fold increase in the average orifice passage times compared to those observed by Daigle et al. (2005) without refuges and at lower water velocities. Three general behaviors summarize fish behavior as they approached the submerged orifice during the high velocity with refuges resulting in low passage success 1) fish would approach the orifice from the side using the low flow area directly downstream of the weir followed by lateral movement toward the orifice. Refuges in front of the weir would inhibit lateral movement and fish would resort to other means to pass such as: 2) climbing over the downstream side of the weir or attaching to the rounded bulkhead; or 3) fish would approach the orifice directly downstream but upon entry into the high-velocity area inside the orifice, turbulent current would whip their body against a refuge immediately downstream and they would subsequently be pried from the fishway floor. In later trials we attempted to test modified patterns and spacing of refuges. There appeared to be improvement over the original refuge design, but time was not sufficient to continue experimentation to determine optimal spacing. Effects of fishway modifications such as velocity refuges in the experimental flume are designed and intended to provide information on the concept of using such structures to improve fish passage. However, due to large differences in scale rigorous conclusions based on these results can be confounding and should be used with caution. Based on initial studies conducted in the experimental fishway (Daigle et al. 2005), we demonstrated that velocity refuges can be beneficial. However, high velocities that occur at fishway entrances (up to 14 ft s -1 or more) make developing design criteria more challenging. Results of this study suggest that velocity refuges placed in close proximity especially in and just downstream from high velocity areas could be problematic to Pacific lamprey passage, particularly in areas where fish are forced to move laterally such as downstream of an LPS or directly downstream of a submerged orifice. Literature Cited Daigle, W.R. C.A. Peery, S.R. Lee, and M.L. Moser Evaluation of adult Pacific lamprey passage and behavior in an experimental fishway at Bonneville Dam. Idaho Cooperative Fish and Wildlife Research Unit, University of Idaho, Moscow, Idaho. Technical Report Johnson, E.L., C.A. Peery, and M.L. Moser. In review. Effects of lowered nighttime velocities on fishway entrance success by Pacific Lamprey at Bonneville Dam, Idaho Cooperative Fish and Wildlife Research Unit, University of Idaho, Moscow, Idaho. Moser, M.L., P.A. Ocker, L.C. Stuehrenberg, and T.C. Bjornn Passage efficiency of

10 Page 10 adult Pacific lamprey at hydropower dams on the lower Columbia River, USA. Transactions of the American Fisheries Society 131:

ANALYSIS OF THE 2010 AMERICAN SHAD RADIO TELEMETRY ANIMATIONS RSP 3.5 CONOWINGO HYDROELECTRIC PROJECT FERC PROJECT NUMBER 405

ANALYSIS OF THE 2010 AMERICAN SHAD RADIO TELEMETRY ANIMATIONS RSP 3.5 CONOWINGO HYDROELECTRIC PROJECT FERC PROJECT NUMBER 405 ANALYSIS OF THE 2010 AMERICAN SHAD RADIO TELEMETRY ANIMATIONS RSP 3.5 CONOWINGO HYDROELECTRIC PROJECT FERC PROJECT NUMBER 405 Prepared for: Prepared by: Normandeau Associates, Inc. Gomez and Sullivan Engineers,

More information

ADULT LAMPREY PASSAGE AND ENUMERATION STUDY, WELLS DAM, 2013:

ADULT LAMPREY PASSAGE AND ENUMERATION STUDY, WELLS DAM, 2013: ADULT LAMPREY PASSAGE AND ENUMERATION STUDY, WELLS DAM, 2013: The Effects of Head Differential on Entrance Efficiency, and of Picketed Leads on Count Window Enumeration Efficiency David Robichaud LGL Limited

More information

Final Report for the Green Valley Creek Winter Refugia Enhancement Project Monitoring December 2016

Final Report for the Green Valley Creek Winter Refugia Enhancement Project Monitoring December 2016 Final Report for the Green Valley Creek Winter Refugia Enhancement Project Monitoring December 2016 Prepared by: Mariska Obedzinski and Sarah Nossaman University of California Cooperative Extension & California

More information

Amherst. University of Massachusetts - Amherst

Amherst. University of Massachusetts - Amherst University of Massachusetts - Amherst ScholarWorks@UMass Amherst International Conference on Engineering and Ecohydrology for Fish Passage International Conference on Engineering and Ecohydrology for Fish

More information

CFD Modeling for Structure Designs in Environmental Impacts Mitigation

CFD Modeling for Structure Designs in Environmental Impacts Mitigation CFD Modeling for Structure Designs in Environmental Impacts Mitigation June 05 Navid Nekouee, Hugo Rodriguez and Steven Davie Environmental Impact Mitigation Design Savannah Harbor Expansion Project (SHEP)

More information

Fish Passage at Road Crossings

Fish Passage at Road Crossings Fish Passage at Road Crossings 1 Crossing Design Workshop Outline 1:00 to 2:00 Intro, Design Overview, Channel Width 2:00 to 2:15 Break 2:15 to 3:15 No-Slope, Stream Simulation Design 3:15 to 3:30 Break

More information

Thinking Outside the Box (Culvert) Making difficult decisions for Fish Passage. Dave Stewart Oregon Department of Fish and Wildlife

Thinking Outside the Box (Culvert) Making difficult decisions for Fish Passage. Dave Stewart Oregon Department of Fish and Wildlife Thinking Outside the Box (Culvert) Making difficult decisions for Fish Passage Dave Stewart Oregon Department of Fish and Wildlife Overview Fish Passage History Fast Version Where are we at Now Approval

More information

Appendix F Channel Grade Control Structures

Appendix F Channel Grade Control Structures Stream Simulation Appendix F Channel Grade Control Structures This appendix briefly describes permanent grade control structures that are sometimes needed in the upstream and/or downstream reaches adjacent

More information

Case Study 2: Twenty-mile Creek Rock Fords

Case Study 2: Twenty-mile Creek Rock Fords Case Study : Twenty-mile Creek Rock Fords Location Crossing Description Washington. Okanagan National Forest. Methow Valley Ranger District. Chewuch river basin, East Chewuch Road. The Twenty-mile Creek

More information

INTERACTION OF STRESS, PATHOGENS AND DEVELOPMENT ON THE BEHAVIOR OF TELEOSTS

INTERACTION OF STRESS, PATHOGENS AND DEVELOPMENT ON THE BEHAVIOR OF TELEOSTS INTERACTION OF STRESS, PATHOGENS AND DEVELOPMENT ON THE BEHAVIOR OF TELEOSTS Carl B. Schreck Oregon Cooperative Fish and Wildlife Research Unit (U.S.G.S.) Oregon State University, Corvallis, Oregon 97331,

More information

Upper Mississippi River Basin Environmental Management Program Workshop

Upper Mississippi River Basin Environmental Management Program Workshop Presentation to the Upper Mississippi River Basin Environmental Management Program Workshop by Michael Rodgers River Engineer US Army Corps of Engineers, St. Louis District August 17, 2007 Engineering

More information

Tom Ballestero University of New Hampshire. 1 May 2013

Tom Ballestero University of New Hampshire. 1 May 2013 Tom Ballestero University of New Hampshire 1 May 2013 1 Hydrology 2 Basic Hydrology Low flows most common Flows that fill the stream to the banks and higher are much less common Filling the stream to the

More information

Numerical Simulation of Flow and Upstream Fish Movement inside a Pool-and-Weir Fishway

Numerical Simulation of Flow and Upstream Fish Movement inside a Pool-and-Weir Fishway Proceedings of 2013 IAHR World Congress Numerical Simulation of Flow and Upstream Fish Movement inside a Pool-and-Weir Fishway Shokry Abdelaziz Assistant researcher, Institute of Hydraulic and Water Resources

More information

Rock Sizing for Multi-Pipe & Culvert Outlets

Rock Sizing for Multi-Pipe & Culvert Outlets Rock Sizing for Multi-Pipe & Culvert Outlets STORMWATER AND WATERWAY MANAGEMENT PRACTICES Photo 1 Rock pad outlet structure at end of a duel stormwater pipe outlet Photo 2 Rock pad outlet structure at

More information

Impact of Climate Change on Chinook Salmon

Impact of Climate Change on Chinook Salmon Region: Western Coastlines Grade Level(s): 5-8 Impact of Climate Change on Chinook Salmon Time Required: 2-3 class periods Focus Question(s): How will long term climate changes impact northwest Pacific

More information

2016 FPC Adult Ladder Hourly Water Temperature Graph and Query Metadata

2016 FPC Adult Ladder Hourly Water Temperature Graph and Query Metadata 2016 FPC Adult Ladder Hourly Water Graph and Query Metadata Query Description This graph compares the hourly ladder water temperatures for the entrance monitor, exit monitor and monitors located midway

More information

Evaluation of Public Safety at Run-of-River Dams

Evaluation of Public Safety at Run-of-River Dams Evaluation of Public Safety at Run-of-River Dams - An Illinois Statewide Program By G. Nicholas Textor, PE, CFM Daniel W. Tornil Lee Von Gynz-Guethle, CFM Authority Section 23a of the Rivers, Lakes and

More information

Appendix G. Meso-Habitat Surveys. DRAFT Annual Technical Report

Appendix G. Meso-Habitat Surveys. DRAFT Annual Technical Report Appendix G Meso-Habitat Surveys DRAFT Annual Technical Report Draft March 2010 1.0 Introduction 1 2 3 4 5 6 1.0 Introduction The following appendix includes a report provided by the California Department

More information

Stage Discharge Tabulation for Only Orifice Flow

Stage Discharge Tabulation for Only Orifice Flow Stage Discharge Tabulation for Only Orifice Flow DEPTH STAGE DISCHARGE (meters) (feet) (meters) (feet) (m 3 /s) (ft 3 /s) 0 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 2.00 0.7 1.3 2.0 2.6 3.3 3.9 4.6

More information

Northwest Outlook October 2016

Northwest Outlook October 2016 Northwest Outlook October 2016 Rainfall Opportunities and Challenges Rainfall over the month of September presented some challenges for the fall harvest while other producers benefitted. Figure 1a shows

More information

WP2.1 BREACH FORMATION LARGE SCALE EMBANKMENT FAILURE

WP2.1 BREACH FORMATION LARGE SCALE EMBANKMENT FAILURE WP2. BREACH FORMATION LARGE SCALE EMBANKMENT FAILURE Kjetil Arne Vaskinn, Sweco Gröner Norway Aslak Løvoll, Norconsult AS Norway Kaare Höeg, Norwegian Geotechnical Institute (NGI), Norway WP2. BREACH FORMATION

More information

U.S. ARMY CORPS OF ENGINEERS

U.S. ARMY CORPS OF ENGINEERS CORPS FACTS Regulating Mississippi River Navigation Pools U.S. ARMY CORPS OF ENGINEERS BUILDING STRONG Historical Background Federal improvements in the interest of navigation on the Mississippi River

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

Rock Sizing for Waterway & Gully Chutes

Rock Sizing for Waterway & Gully Chutes Rock Sizing for Waterway & Gully Chutes WATERWAY MANAGEMENT PRACTICES Photo 1 Rock-lined waterway chute Photo 2 Rock-lined gully chute 1. Introduction A waterway chute is a stabilised section of channel

More information

Flow-net Relationships in the Forebay of John Day Dam Annual Report 1982

Flow-net Relationships in the Forebay of John Day Dam Annual Report 1982 Flow-net Relationships in the Forebay of John Day Dam Annual Report 1982 DOE/BP-0011 April 1983 This Document should be cited as follows: Giorgi, A., ''Flow-net Relationships in the Forebay of John Day

More information

Application of an ultrasonic velocity profile monitor in a hydraulic laboratory

Application of an ultrasonic velocity profile monitor in a hydraulic laboratory Application of an ultrasonic velocity profile monitor in a hydraulic laboratory Abstract Helmut Knoblauch 1, Roman Klasinc 1, Thomas Geisler 1 Velocity profile measurement using the ultrasound-pulse-doppler

More information

SUMMARY OF OPERATIONS AT THE HOLTWOOD FISH PASSAGE FACILITY SPRING AND FALL, 2017

SUMMARY OF OPERATIONS AT THE HOLTWOOD FISH PASSAGE FACILITY SPRING AND FALL, 2017 SUMMARY OF OPERATIONS AT THE HOLTWOOD FISH PASSAGE FACILITY SPRING AND FALL, 2017 November 2017 SUMMARY OF OPERATIONS AT THE HOLTWOOD FISH PASSAGE FACILITY SPRING AND FALL, 2017 Prepared for HOLTWOOD HYDRO

More information

Study of the rate of sediment trapping and water loss in the vortex tube structure at different placement angles

Study of the rate of sediment trapping and water loss in the vortex tube structure at different placement angles Journal of Scientific Research and Development 2 (5): 4-1, 2015 Available online at www.jsrad.org ISSN 1115-5 2015 JSRAD Study of the rate of sediment trapping and water loss in the vortex tube structure

More information

SEDIMENTATION STUDY OF THE MIDDLE MISSISSIPPI RIVER AT BUFFALO ISLAND RIVER MILES 28.0 TO 22.0 HYDRAULIC MICRO MODEL INVESTIGATION

SEDIMENTATION STUDY OF THE MIDDLE MISSISSIPPI RIVER AT BUFFALO ISLAND RIVER MILES 28.0 TO 22.0 HYDRAULIC MICRO MODEL INVESTIGATION Technical Report M29 SEDIMENTATION STUDY OF THE MIDDLE MISSISSIPPI RIVER AT BUFFALO ISLAND RIVER MILES 28.0 TO 22.0 HYDRAULIC MICRO MODEL INVESTIGATION By Jasen L. Brown Michael T. Rodgers Dawn M.Lamm

More information

1. Review/Approve Agenda and Minutes (B. Klatte)

1. Review/Approve Agenda and Minutes (B. Klatte) AGENDA Fish Passage O&M Coordination (FPOM) Team NOAA Fisheries Office 1201 NE Lloyd Blvd (Lloyd Center MAX stop) St. Helens Room (10 TH Floor) February 14, 2008 (900-1200) Call in number- 503-808-5199

More information

External Flow and Boundary Layer Concepts

External Flow and Boundary Layer Concepts 1 2 Lecture (8) on Fayoum University External Flow and Boundary Layer Concepts By Dr. Emad M. Saad Mechanical Engineering Dept. Faculty of Engineering Fayoum University Faculty of Engineering Mechanical

More information

Smolt Monitoring Program Two Week Passage Index Report Page 1 of 7

Smolt Monitoring Program Two Week Passage Index Report Page 1 of 7 Page 1 of 7 COMBINED YEARLING CHINOOK 09/15/2018 0 0 0 0 09/18/2018 0 0 0 0 0 09/20/2018 0 0 0 0 09/21/2018 0 0 1 0 09/23/2018 1 0 0 09/25/2018 0 1 0 09/26/2018 1 0 0 0 09/28/2018 0 0 0 Total: 0 0 0 0

More information

Port of Kalama, 2013 TEMCO Berth Maintenance Dredging and In-water Flow-Lane Placement Project

Port of Kalama, 2013 TEMCO Berth Maintenance Dredging and In-water Flow-Lane Placement Project 2014 WEDA ENVIRONMENTAL EXCELLENCE AWARDS Category: Navigation Dredging Port of Kalama, 2013 TEMCO Berth Maintenance Dredging and In-water Flow-Lane Placement Project Port of Kalama, Washington 18 April

More information

17-20 November 2007 Incidental Take Monitoring Methodology and Results

17-20 November 2007 Incidental Take Monitoring Methodology and Results Sample Site Selection Protocol 17-20 November 2007 Incidental Take Monitoring Methodology and Results On 16 November 2007, the U.S. Fish and Wildlife Service (USFWS) provided the USACE Mobile District

More information

DETAILED DESCRIPTION OF STREAM CONDITIONS AND HABITAT TYPES IN REACH 4, REACH 5 AND REACH 6.

DETAILED DESCRIPTION OF STREAM CONDITIONS AND HABITAT TYPES IN REACH 4, REACH 5 AND REACH 6. DETAILED DESCRIPTION OF STREAM CONDITIONS AND HABITAT TYPES IN REACH 4, REACH 5 AND REACH 6. The Eklutna River was divided into study reaches (figure 1) prior to this site visit. Prominent geologic or

More information

Photo 1: Assen Brothers Splash Dam in 1912, Middle Creek Oregon. Photo courtesy of Coos County Historical Society

Photo 1: Assen Brothers Splash Dam in 1912, Middle Creek Oregon. Photo courtesy of Coos County Historical Society Spatial Correlation of Historical Salmon Spawning Sites to Historical Splash Dam Locations in the Oregon Coast Range By Rebecca Miller Geo 565 Option 2 Final Introduction Photo 1: Assen Brothers Splash

More information

FE Fluids Review March 23, 2012 Steve Burian (Civil & Environmental Engineering)

FE Fluids Review March 23, 2012 Steve Burian (Civil & Environmental Engineering) Topic: Fluid Properties 1. If 6 m 3 of oil weighs 47 kn, calculate its specific weight, density, and specific gravity. 2. 10.0 L of an incompressible liquid exert a force of 20 N at the earth s surface.

More information

847 NE 19 th Avenue, #250, Portland, OR Phone: (503) Fax: (503) us at

847 NE 19 th Avenue, #250, Portland, OR Phone: (503) Fax: (503) us at FISH PASSAGE CENTER 847 NE 19 th Avenue, #250, Portland, OR 97232 Phone: (503) 833-3900 Fax: (503) 232-1259 www.fpc.org/ e-mail us at fpcstaff@fpc.org MEMORANDUM TO: Fish Passage Advisory Committee FROM:

More information

53:071 Principles of Hydraulics Laboratory Experiment #3 ANALYSIS OF OPEN-CHANNEL FLOW TRANSITIONS USING THE SPECIFIC ENERGY DIAGRAM

53:071 Principles of Hydraulics Laboratory Experiment #3 ANALYSIS OF OPEN-CHANNEL FLOW TRANSITIONS USING THE SPECIFIC ENERGY DIAGRAM 53:071 Principles of Hydraulics Laboratory Experiment #3 ANALYSIS OF OPEN-CHANNEL FLOW TRANSITIONS USING THE SPECIFIC ENERGY DIAGRAM Principle Adaptation of the Bernoulli equation to open-channel flows

More information

Restoration Goals TFG Meeting. Agenda

Restoration Goals TFG Meeting. Agenda San Joaquin River Restoration Program Restoration Goals TFG Meeting Reach 2B Update April 28, 2010 Agenda 1. Introductions 2. Program Restoration Goal Context 3. Program Update a) Interim Flows b) EIS/EIR

More information

Incipient sediment motion across the river to debris-flow transition

Incipient sediment motion across the river to debris-flow transition Movie DR1 Movie DR2 Movie DR3 Movie DR4 GSA DATA REPOSITORY 2014067 SUPPLEMENTARY MATERIALS FOR Incipient sediment motion across the river to debris-flow transition Jeff P. Prancevic, Michael P. Lamb,

More information

Stream Restoration and Environmental River Mechanics. Objectives. Pierre Y. Julien. 1. Peligre Dam in Haiti (deforestation)

Stream Restoration and Environmental River Mechanics. Objectives. Pierre Y. Julien. 1. Peligre Dam in Haiti (deforestation) Stream Restoration and Environmental River Mechanics Pierre Y. Julien Malaysia 2004 Objectives Brief overview of environmental river mechanics and stream restoration: 1. Typical problems in environmental

More information

ONE ROCK DAM ORD. capture more sediment. The original ORD becomes the splash apron for the new layer. STEP 4: When ORD fills in, add a new layer

ONE ROCK DAM ORD. capture more sediment. The original ORD becomes the splash apron for the new layer. STEP 4: When ORD fills in, add a new layer ONE ROCK DAM ORD A low grade control structure built with a single layer of rock on the bed of the channel. ORDs stabilize the bed of the channel by slowing the flow of water, increasing roughness, recruiting

More information

Cavitation occurs whenever the pressure in the flow of water drops to the value of the pressure of the saturated water vapour, pv (at the prevailing

Cavitation occurs whenever the pressure in the flow of water drops to the value of the pressure of the saturated water vapour, pv (at the prevailing Cavitation occurs whenever the pressure in the flow of water drops to the value of the pressure of the saturated water vapour, pv (at the prevailing temperature); cavities filled by vapour, and partly

More information

Predicting ecosystem response to the removal of the Elwha River Dams, Washington State, U.S.A.

Predicting ecosystem response to the removal of the Elwha River Dams, Washington State, U.S.A. Predicting ecosystem response to the removal of the Elwha River Dams, Washington State, U.S.A. G.Pess 1, M. McHenry 2,T. Beechie 1, S. Morley 1, J. Duda 3,H. Coe 1, K. Kloehn 1, M. Liermann 1 1 NOAA, rthwest

More information

EARTH S SYSTEMS: PROCESSES THAT SHAPE THE EARTH

EARTH S SYSTEMS: PROCESSES THAT SHAPE THE EARTH 9 Week Unit UNIT 2 EARTH S SYSTEMS: PROCESSES THAT SHAPE THE EARTH Fourth Grade Rogers Public Schools : Earth s Systems: Processes that Shape the Earth 9 weeks In this unit, students develop understandings

More information

SEDIMENTATION STUDY OF THE MIDDLE MISSISSIPPI RIVER AT SALT LAKE CHUTE, RIVER MILES 141 TO 133 HYDRAULIC MICRO MODEL INVESTIGATION

SEDIMENTATION STUDY OF THE MIDDLE MISSISSIPPI RIVER AT SALT LAKE CHUTE, RIVER MILES 141 TO 133 HYDRAULIC MICRO MODEL INVESTIGATION Technical Report M16 SEDIMENTATION STUDY OF THE MIDDLE MISSISSIPPI RIVER AT SALT LAKE CHUTE, RIVER MILES 141 TO 133 HYDRAULIC MICRO MODEL INVESTIGATION By David C. Gordon Robert D. Davinroy Peter M. Russell

More information

COMPARISON OF LABORATORY AND FIELD MEASUREMENTS OF BRIDGE PIER SCOUR

COMPARISON OF LABORATORY AND FIELD MEASUREMENTS OF BRIDGE PIER SCOUR COMPARISON OF LABORATORY AND FIELD MEASUREMENTS OF BRIDGE PIER SCOUR LEE, SEUNGOH, STURM, T. W., School of Civil and Environ. Engrg., Georgia Institute of Technology Atlanta, GA 30332-0512 USA GOTVALD,

More information

Reverse Flow in A Converging Channel with An Obstruction at The Entry - A Flow Visualization Study

Reverse Flow in A Converging Channel with An Obstruction at The Entry - A Flow Visualization Study 14 Reverse Flow in A Converging Channel with An Obstruction at The Entry - A Flow Visualization Study B. H. L. Gowda, BTL Institute of Technology, Department of Mechanical Engineering, Bommasandra, Bengaluru,

More information

Connecticut Coastal Management Program

Connecticut Coastal Management Program Connecticut Coastal Management Program Fact Sheet for SHORELINE FLOOD AND EROSION CONTROL STRUCTURES What are Shoreline Flood and Erosion Control Structures? The Connecticut General Statutes (CGS) define

More information

Tom Glass, B.S. Whitman College Sarah Wasssmund, B.S. Humboldt State University Edgar Verdin, B.S. Portland State University Kelsi Lakey, B.S.

Tom Glass, B.S. Whitman College Sarah Wasssmund, B.S. Humboldt State University Edgar Verdin, B.S. Portland State University Kelsi Lakey, B.S. Tom Glass, B.S. Whitman College Sarah Wasssmund, B.S. Humboldt State University Edgar Verdin, B.S. Portland State University Kelsi Lakey, B.S. Washington State University Overview 1. Background 2. History

More information

Predicting ecosystem response to the removal of the Elwha River Dams, Washington State, U.S.A.

Predicting ecosystem response to the removal of the Elwha River Dams, Washington State, U.S.A. Predicting ecosystem response to the removal of the Elwha River Dams, Washington State, U.S.A. G.Pess 1, M. McHenry 2,T. Beechie 1, S. Morley 1, J. Duda 3,H. Coe 1, K. Kloehn 1, M. Liermann 1 1 NOAA, Northwest

More information

Hydraulics of bendway weirs

Hydraulics of bendway weirs River Basin Management IV 389 Hydraulics of bendway weirs C. Thornton 1, S. Abt 1, D. Baird 2 & R. Padilla 3 1 Colorado State University, Fort Collins, CO, USA 2 U.S. Bureau of Reclamation, Denver, CO,

More information

Lab 7: Nonuniform Flow and Open Channel Transitions

Lab 7: Nonuniform Flow and Open Channel Transitions CE 3620: Water Resources Engineering Spring 2015 Lab 7: Nonuniform Flow and Open Channel Transitions BACKGROUND An open channel transition may be defined as a change either in the direction, slope, or

More information

Physical modeling to guide river restoration projects: An Overview

Physical modeling to guide river restoration projects: An Overview Physical modeling to guide river restoration projects: An Overview Scott Dusterhoff¹, Leonard Sklar², William Dietrich³, Frank Ligon¹, Yantao Cui¹, and Peter Downs¹ ¹Stillwater Sciences, 2855 Telegraph

More information

Rock Sizing for Small Dam Spillways

Rock Sizing for Small Dam Spillways Rock Sizing for Small Dam Spillways STORMWATER MANAGEMENT PRACTICES Photo 1 Rock-lined spillway on a construction site sediment basin Photo 2 Rock-lined spillway on a small farm dam 1. Introduction A chute

More information

Visualization of flow pattern over or around immersed objects in open channel flow.

Visualization of flow pattern over or around immersed objects in open channel flow. EXPERIMENT SEVEN: FLOW VISUALIZATION AND ANALYSIS I OBJECTIVE OF THE EXPERIMENT: Visualization of flow pattern over or around immersed objects in open channel flow. II THEORY AND EQUATION: Open channel:

More information

Addressing the Impact of Road-Stream Crossing Structures on the Movement of Aquatic Organisms

Addressing the Impact of Road-Stream Crossing Structures on the Movement of Aquatic Organisms Scott Jackson University of Massachusetts Amherst Addressing the Impact of Road-Stream Crossing Structures on the Movement of Aquatic Organisms Dams Sub-standard Culverts Excessive Velocities Inlet Drop

More information

Appendix A Total Dissolved Gas. Fixed Monitoring Stations

Appendix A Total Dissolved Gas. Fixed Monitoring Stations Appendix A 2017 Total Dissolved Gas Fixed Monitoring Stations Updated October 2017 This page is purposely left blank for duplex printing. Introduction The Corps fixed monitoring station (FMS) system is

More information

Habitat Assessment. Peggy Compton UW-Extension Water Action Volunteers Program Coordinator

Habitat Assessment. Peggy Compton UW-Extension Water Action Volunteers Program Coordinator Habitat Assessment Peggy Compton UW-Extension Water Action Volunteers Program Coordinator Adapted from a presentation by Jean Unmuth, Water Quality Biologist, WI DNR dnr.wi.gov www.uwex.edu erc.cals.wisc.edu

More information

Laboratory experiences on open channel flow (in collaboration with Dr. Ing. Luca Milanesi)

Laboratory experiences on open channel flow (in collaboration with Dr. Ing. Luca Milanesi) Classwork 8 Laboratory experiences on open channel flow (in collaboration with Dr. Ing. Luca Milanesi) Why a practical lesson on open channel flow? In the first part of the course we studied open channel

More information

B805 TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES - OPSS 805

B805 TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES - OPSS 805 B805 MEASURES - OPSS 805 805.1 GENERAL Construction activities frequently remove protective cover and expose soil to accelerated rates of erosion. Sediments generated thereby can be conveyed via runoff

More information

WORKSHOP #2 [Modeling and Sediment Transfers Review of alternative solutions] Bucharest 07 October 2015

WORKSHOP #2 [Modeling and Sediment Transfers Review of alternative solutions] Bucharest 07 October 2015 STUDIU DE FEZABILITATE PENTRU SOLUŢII TEHNICE ALTERNATIVE/COMPLEMENTARE PRIVIND LUCRĂRILE CE SE VOR EXECUTA ÎN PUNCTUL CRITIC 01 BALA DIN CADRUL PROIECTULUI ÎMBUNĂTĂŢIREA CONDIŢIILOR DE NAVIGAŢIE PE DUNĂRE

More information

Storm Water Best Management Practice: Development of Debris Filtering Structure for Supercritical Flow

Storm Water Best Management Practice: Development of Debris Filtering Structure for Supercritical Flow Storm Water Best Management Practice: Development of Debris Filtering Structure for Supercritical Flow Jungseok Ho 1, Todd Marti 2, and Julie Coonrod 3 1 Department of Civil Engineering, University of

More information

2017 Technical Revision to the Marine Survival Forecast of the OCN Coho Work Group Harvest Matrix Erik Suring Oregon Department of Fish and Wildlife

2017 Technical Revision to the Marine Survival Forecast of the OCN Coho Work Group Harvest Matrix Erik Suring Oregon Department of Fish and Wildlife 2017 Technical Revision to the Marine Survival Forecast of the OCN Coho Work Group Harvest Matrix Erik Suring Oregon Department of Fish and Wildlife Agenda Item D.2 Attachment 1 November 2017 Introduction

More information

Start of Presentation: No notes (Introductory Slide 1) 1) Salmonid Habitat Intrinsic Potential (IP) models are a type of habitat potential

Start of Presentation: No notes (Introductory Slide 1) 1) Salmonid Habitat Intrinsic Potential (IP) models are a type of habitat potential The What and How of Salmonid Habitat Intrinsic Potential Modeling Start of Presentation: No notes (Introductory Slide 1) 1) Salmonid Habitat Intrinsic Potential (IP) models are a type of habitat potential

More information

APPLIED FLUID DYNAMICS HANDBOOK

APPLIED FLUID DYNAMICS HANDBOOK APPLIED FLUID DYNAMICS HANDBOOK ROBERT D. BLEVINS H imhnisdia ttodisdiule Darmstadt Fachbereich Mechanik 'rw.-nr.. [VNR1 VAN NOSTRAND REINHOLD COMPANY ' ' New York Contents Preface / v 1. Definitions /

More information

Experimental Study of the Sediment Trap Effect of Steel Grid-Type Sabo Dams

Experimental Study of the Sediment Trap Effect of Steel Grid-Type Sabo Dams Experimental Study of the Sediment Trap Effect of Steel Grid-Type Sabo Dams Teruyoshi TAKAHARA 1 and Kazuki MATSUMURA 1 1 Graduate school of Agriculture, Kyoto Pref. University (1-5 Shimogamonakaragicyo,

More information

Lower Snake River Programmatic Sediment Management Plan Final Environmental Impact Statement

Lower Snake River Programmatic Sediment Management Plan Final Environmental Impact Statement U.S. Army Corps of Engineers Walla Walla District Lower Snake River Programmatic Sediment Management Plan Final Environmental Impact Statement EXECUTIVE SUMMARY August 2014 EXECUTIVE SUMMARY Introduction

More information

Relatively little hard substrate occurs naturally in the

Relatively little hard substrate occurs naturally in the CHAPTER FIVE Rock Habitats Relatively little hard substrate occurs naturally in the estuary, owing mainly to the vast quantities of fine sediment that have been deposited by the rivers. Rock habitat is

More information

Vermont Stream Geomorphic Assessment. Appendix J. Vermont Regional Hydraulic Geometry Curves

Vermont Stream Geomorphic Assessment. Appendix J. Vermont Regional Hydraulic Geometry Curves Vermont Stream Geomorphic Assessment Appendix J Vermont Regional Hydraulic Geometry Curves River Management Program Vermont Water Quality Division November, 2001 Natural Resources - J0 - VT Agency of Background

More information

Fish Passage and Abundance around Grade Control Structures on Incised Streams in Western Iowa

Fish Passage and Abundance around Grade Control Structures on Incised Streams in Western Iowa Fish Passage and Abundance around Grade Control Structures on Incised Streams in Western Iowa John Thomas Hungry Canyons Alliance Mary Culler Iowa State University / Missouri DNR Dimitri Dermisis IIHR

More information

Topic 4 &11 Review Waves & Oscillations

Topic 4 &11 Review Waves & Oscillations Name: Date: Topic 4 &11 Review Waves & Oscillations 1. A source produces water waves of frequency 10 Hz. The graph shows the variation with horizontal position of the vertical displacement of the surface

More information

Hydromechanics: Course Summary

Hydromechanics: Course Summary Hydromechanics: Course Summary Hydromechanics VVR090 Material Included; French: Chapters to 9 and 4 + Sample problems Vennard & Street: Chapters 8 + 3, and (part of it) Roberson & Crowe: Chapter Collection

More information

Recap: Static Fluids

Recap: Static Fluids Recap: Static Fluids Archimedes principal states that the buoyant force acting on an object is equal to the weight of fluid displaced. If the average density of object is greater than density of fluid

More information

A Study of Bankfull Culvert Design Effectiveness. PI: Dr. Mark Tumeo, Ph.D., J.D., P.E. Student: Joe Pavlick State Job Number:

A Study of Bankfull Culvert Design Effectiveness. PI: Dr. Mark Tumeo, Ph.D., J.D., P.E. Student: Joe Pavlick State Job Number: A Study of Bankfull Culvert Design Effectiveness PI: Dr. Mark Tumeo, Ph.D., J.D., P.E. Student: Joe Pavlick State Job Number: 134465 Outline of Presentation Introduction Research Objectives Research Approach

More information

APPENDIX 15-S KSM PROJECT: 2012 FISH BEARING STATUS ASSESSMENT MEMORANDUM

APPENDIX 15-S KSM PROJECT: 2012 FISH BEARING STATUS ASSESSMENT MEMORANDUM APPENDIX 15-S KSM PROJECT: 2012 FISH BEARING STATUS ASSESSMENT MEMORANDUM TM Memorandum Refer to File No.: N:\868 Seabridge\868-017 KSM 2012 Fieldwork\868- DATE: December 17, 2012 017-19 Fisheries - Treaty

More information

Review of Vermont Yankee Thermal Discharge Permit Requirements and Analysis of Connecticut River Water Temperature and Flow

Review of Vermont Yankee Thermal Discharge Permit Requirements and Analysis of Connecticut River Water Temperature and Flow Review of Vermont Yankee Thermal Discharge Permit Requirements and Analysis of Connecticut River Water Temperature and Flow August 17, 2012 Prepared by: Ken Hickey Peter Shanahan, Ph.D., P.E. 481 Great

More information

R09. d water surface. Prove that the depth of pressure is equal to p +.

R09. d water surface. Prove that the depth of pressure is equal to p +. Code No:A109210105 R09 SET-1 B.Tech II Year - I Semester Examinations, December 2011 FLUID MECHANICS (CIVIL ENGINEERING) Time: 3 hours Max. Marks: 75 Answer any five questions All questions carry equal

More information

The Dalles Dam Fishway Status Report

The Dalles Dam Fishway Status Report The Dalles Dam Fishway Status Report 5/14/2016 Inspection Period: 05/08-05/14/2016 THE DALLES DAM The Dalles Project-Fisheries P.O. Box 564 The Dalles, OR 97058-9998 Phone: 541-506-3800 Exit differential

More information

The Mac & Jack study: Size and domestication effects on minijack rates of summer Chinook salmon from McCall Fish Hatchery, Idaho.

The Mac & Jack study: Size and domestication effects on minijack rates of summer Chinook salmon from McCall Fish Hatchery, Idaho. The Mac & Jack study: Size and domestication effects on minijack rates of summer Chinook salmon from McCall Fish Hatchery, Idaho. Deb Harstad 1 *, Don Larsen 1, Abby Fuhrman 1, Dina Spangenberg 1, Chris

More information

1) the intermittence of the vortex-shedding regime at the critical angle of incidence in smooth flow; ) the inversion of the lift coefficient slope at

1) the intermittence of the vortex-shedding regime at the critical angle of incidence in smooth flow; ) the inversion of the lift coefficient slope at The Seventh International Colloquium on Bluff Body Aerodynamics and Applications (BBAA7) Shanghai, China; September -6, 01 Experimental investigation on the aerodynamic behavior of square cylinders with

More information

9. Flood Routing. chapter Two

9. Flood Routing. chapter Two 9. Flood Routing Flow routing is a mathematical procedure for predicting the changing magnitude, speed, and shape of a flood wave as a function of time at one or more points along a watercourse (waterway

More information

SUMMARY OF OPERATIONS AT THE CONOWINGO DAM EAST FISH PASSAGE FACILITY SPRING 2017

SUMMARY OF OPERATIONS AT THE CONOWINGO DAM EAST FISH PASSAGE FACILITY SPRING 2017 SUMMARY OF OPERATIONS AT THE CONOWINGO DAM EAST FISH PASSAGE FACILITY SPRING 2017 December 2017 SUMMARY OF OPERATIONS AT THE CONOWINGO DAM EAST FISH PASSAGE FACILITY SPRING 2017 Prepared for EXELON GENERATION

More information

Local Scouring due to Flow Jet at Downstream of Rectangular Sharp-Crested Weirs

Local Scouring due to Flow Jet at Downstream of Rectangular Sharp-Crested Weirs Local Scouring due to Flow Jet at Downstream of Rectangular Sharp-Crested Weirs DEHGHANI, AMIR. AHMAD 1, BASHIRI, HAMID and MESHKATI SHAHMIRZADI, MOHAMMAD. EBRAHIM 3 1,3 Dept. of Water Engineering, Gorgan

More information

EAGLES NEST AND PIASA ISLANDS

EAGLES NEST AND PIASA ISLANDS EAGLES NEST AND PIASA ISLANDS HABITAT REHABILITATION AND ENHANCEMENT PROJECT MADISON AND JERSEY COUNTIES, ILLINOIS ENVIRONMENTAL MANAGEMENT PROGRAM ST. LOUIS DISTRICT FACT SHEET I. LOCATION The proposed

More information

Stormwater Outlet Sediment Traps

Stormwater Outlet Sediment Traps Stormwater Outlet Traps SEDIMENT CONTROL TECHNIQUES Photo 1 Excavated sediment trap just prior to scheduled clean-out (note energy dissipater at end of pipe) Photo 2 A supplementary straw bale barrier

More information

2013 Snake River Fall Chinook Salmon Spawning Summary 2,667 2, ,391

2013 Snake River Fall Chinook Salmon Spawning Summary 2,667 2, ,391 2013 Snake River Fall Chinook Salmon Spawning Summary by Bill Arnsberg, Nez Perce Tribe Phil Groves, Idaho Power Company Frank Mullins, U.S. Fish and Wildlife Service Debbie Milks, Washington Department

More information

Experimental Investigation on the Influence of Density of Fluid. On Efficiency of V- Notch

Experimental Investigation on the Influence of Density of Fluid. On Efficiency of V- Notch International Journal of Advances in Scientific Research and Engineering (ijasre) E-ISSN : 2454-8006 DOI: http://dx.doi.org/10.7324/ijasre.2017.32515 Vol.3 (9) Oct - 2017 Experimental Investigation on

More information

C. STUDENT FIELD DATA SHEETS

C. STUDENT FIELD DATA SHEETS C. STUDENT FIELD DATA SHEETS Student Name Date Time Stream Location Parameter to find Your Group s Results Units trial trial average Transparency cm Water Temperature Air Temperature Weather N sunny N

More information

DEVELOPING AN ECOLOGICAL AND MIGRATION SYSTEM FOR ICHTHYOFAUNA ON THE CRIŞUL REPEDE RIVER NEAR THE CITY HALL OF ORADEA

DEVELOPING AN ECOLOGICAL AND MIGRATION SYSTEM FOR ICHTHYOFAUNA ON THE CRIŞUL REPEDE RIVER NEAR THE CITY HALL OF ORADEA Management of Sustainable Development Sibiu, Romania, Volume 5, No.2, December 2013 DOI 10.2478/msd-2013-0012 DEVELOPING AN ECOLOGICAL AND MIGRATION SYSTEM FOR ICHTHYOFAUNA ON THE CRIŞUL REPEDE RIVER NEAR

More information

Open Channel Hydraulics III - Sharpcrested

Open Channel Hydraulics III - Sharpcrested PDHonline Course H140 (2 PDH) Open Channel Hydraulics III - Sharpcrested Weirs Instructor: Harlan H. Bengtson, Ph.D., PE 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone

More information

Evaluation of spatial sampling designs for redd surveys

Evaluation of spatial sampling designs for redd surveys Evaluation of spatial sampling designs for redd surveys Martin Liermann 1, Dan Rawding 2, George Pess 1, Bryce Glaser 2 1 Northwest Fisheries Science Center, 2 Washington Department of Fish and Wildlife.

More information

Erosion Surface Water. moving, transporting, and depositing sediment.

Erosion Surface Water. moving, transporting, and depositing sediment. + Erosion Surface Water moving, transporting, and depositing sediment. + Surface Water 2 Water from rainfall can hit Earth s surface and do a number of things: Slowly soak into the ground: Infiltration

More information

Chapter 8: Flow in Pipes

Chapter 8: Flow in Pipes 8-1 Introduction 8-2 Laminar and Turbulent Flows 8-3 The Entrance Region 8-4 Laminar Flow in Pipes 8-5 Turbulent Flow in Pipes 8-6 Fully Developed Pipe Flow 8-7 Minor Losses 8-8 Piping Networks and Pump

More information

The distortion observed in the bottom channel of Figure 1 can be predicted from the full transport equation, C t + u C. y D C. z, (1) x D C.

The distortion observed in the bottom channel of Figure 1 can be predicted from the full transport equation, C t + u C. y D C. z, (1) x D C. 1 8. Shear Dispersion. The transport models and concentration field solutions developed in previous sections assume that currents are spatially uniform, i.e. u f(,y,). However, spatial gradients of velocity,

More information

A Simple Procedure for Estimating Loss of Life from Dam Failure. Wayne J. Graham, P.E. 1

A Simple Procedure for Estimating Loss of Life from Dam Failure. Wayne J. Graham, P.E. 1 A Simple Procedure for Estimating Loss of Life from Dam Failure Wayne J. Graham, P.E. 1 INTRODUCTION Evaluating the consequences resulting from a dam failure is an important and integral part of any dam

More information

TOP:018.7 U.S. Fish and Wildlife Service TECHNICAL OPERATING PROCEDURE

TOP:018.7 U.S. Fish and Wildlife Service TECHNICAL OPERATING PROCEDURE TOP:018.7 January 31, 2014 U.S. Fish and Wildlife Service Marquette Biological Station 3090 Wright Street Marquette, Michigan 49855 U.S.A. and U.S. Fish and Wildlife Service Ludington Biological Station

More information

Chapter 2 Planet Earth

Chapter 2 Planet Earth Chapter 2 Planet Earth Section Notes Earth and the Sun s Energy Water on Earth The Land Close-up The Water Cycle World Almanac Major Eruptions in the Ring of Fire Quick Facts Chapter 2 Visual Summary Video

More information

Magnetism and Electricity

Magnetism and Electricity Magnetism and Electricity UNIT 7 Student Reader E3 Student Reader v. 9 Unit 7 Page 1 2016 KnowAtom TM Front Cover: The front cover shows a photograph of a girl with her hair standing straight up. This

More information