SOUTHERN REGIONAL POWER COMMITTEE

Size: px
Start display at page:

Download "SOUTHERN REGIONAL POWER COMMITTEE"

Transcription

1

2 SOUTHERN REGIONAL POWER COMMITTEE BENGALURU Minutes of the Meeting of Protection System Analysis Group - 14 (PSAG-14) held on 16 th December, 2015 at MAPS, Kalpakkam a) The Protection System Analysis Group (PSAG-14) meeting was held on 16 th December, 2015 at Madras Atomic Power Station (MAPS), Kalpakkam. Shri R. Satyanarayana, Chief Superintendent, MAPS welcomed the members and participants. The List of Participants is enclosed at Annexure - I. b) MAPS on 230 kv side is equipped with 2x265 MVA, 230/16.5 kv GTs, 2x25 MVA, 230/7 kv SUT s four grid connected feeders, [viz., 230 kv MAPS SP Koil line-1 (L-1); 230 kv MAPS SP Koil line- 2 (L-2); 230 kv MAPS Arani line (L-3); and 230 kv MAPS Acharapakkam line (L-4)], two radially connected feeders to IGCAR through 2x25 MVA, 230/33 kv transformers, and one radially connected UG cable to BHAVINI. The station is equipped with two buses named Main Bus and Transfer Bus. There is a bus sectionalizer on the Main Bus. Functionally, Station is operating on Single Bus. The Station SLD is enclosed at Annexure-II. c) S.P. Koil SS on 230 kv side is equipped with a Main bus and Auxiliary bus with Bus-coupler. There are six feeders emanating from this substation, viz., MAPS - 1 & 2, Kalavindapattu, Veerapuram, Oragadam, and Tiruvalam. Functionally, Station is operating on Single Bus. The Substation SLD is enclosed at Annexure-III. d) MAPS personnel delivered a presentation regarding the Grid Disturbance that occurred on The following issues were deliberated in the meeting: A. Action taken by MAPS and TANTRANSCO w.r.t the recommendations given by the System Studies Sub-Group of SRPC in its meeting held on (Minutes issued vide SRPC letter no: SRPC/SE/ SG/2014/ dated ) The compliance status of the said recommendations as informed to the PSAG-team is enclosed at Annexure-IV. B. Analysis of the Grid Disturbance that occurred at S.P. Koil & MAPS on It is brought out with concern that MAPS have not uploaded the copies of DR / EL / Numerical relay indications / SoE in the required manner in to the web portal of SRLDC for detailed analysis. MAPS confirmed that the same will be strictly ensured in future kv Kalapakkam Arani line (L3): The line tripped at 18:28 hrs on first on B-E fault (fault current ka) due to DPR, Z1 operation at a distance of m from MAPS. The line was kept holding from Arani end. As the line was in charged condition from Arani end, MAPS personnel had tried to charge the line by closing the

3 corresponding line-cb at 18:55 hrs. However, the line tripped again on B-E fault (fault current ka) due to DPR, Z1 operation at 82.5 m from MAPS end. Cause of the event: On field visit, it was observed the B-ph (RYB) Tension insulator at 1 st tower towards switchyard end got broken, and on impact over head conductor clamp at tower end got cut and conductor had fallen on ground causing ground fault. It was found that the stem of ball-andsocket assembly got fully corroded and pin got broken even for the moderate wind speed. Action taken: Line-3 was declared faulty and message given to TNEB for attending the fault. TNEB team arrived on and replaced the tension insulator string with a new one and reconnected the conductor using jumper. Line-3 was taken back in to service at 21:45 hrs on Issue: Line tripped at MAPS end only, and was holding from Arani end. Explanation: The snapping of conductor created a Ph-Ground fault for MAPS, and Open-conductor fault for SP Koil. Due to this, even though protection at MAPS end acted in time to result in 3-ph trip at MAPS and consequent sending of carrier to SP Koil end, protection at SP Koil end neither sensed the fault nor received the carrier. Similarly, as the above fault resulted in 3-ph trip MAPS, brokenconductor condition could not be sensed by the protection at SP Koil end, even though the same has been kept enabled for Alarm. Accordingly, it is found that the operation of the protection system is in order kv MAPS Acharapakkam line (L4): Line tripped at 08:21 hrs on on Y-B fault due to DPR, Z1 operation at a distance of 352 mts from MAPS end. Cause of the event: For line-4, the portion between MAPS 1 st tower to 2 nd tower after crossing main road for Y and B phases got cut and fallen on ground on the road, obstructing movement of vehicle on main road. For Y-phase, tension string insulator at 1 st tower got cut, and on impact the conductor clamp at 1 st tower end got cut and conductor had fallen on ground. For B-phase, tension string insulator at 2nd tower got cut, and on impact the conductor clamp at 2 nd tower end got cut and conductor fallen on ground. It was found that the stem of ball-and-socket assembly got fully corroded and pin got broken even for the moderate wind speed. Action taken: Line-4 was declared faulty and message given to TNEB for attending the fault. On 1 st tower, the tension insulator string was replaced for Y phase, and the conductor was reconnected using jumper. On 2 nd tower, the tension insulator string was replaced with spare and conductor was reconnected using a jumper. Line 3 was taken back in to service at 23:45 hrs on Accordingly, it is found that the protection system operated correctly kv MAPs SP Koil line (L2): As per MAPS, the line tripped at MAPS end at 8:50 hrs on on B-E fault due to DPR, Z1 operation at a distance of km from MAPS.

4 As per TANTRANSCO, the line tripped at 9:06 hrs on on B-E fault due to DPR, Z2, Carrier- Aided-Trip operation. Issue: Even though the line tripped at 9:06 hrs, it could not be normalized till 10:45 hrs due to apparent breaker problem at SP Koil end. TANTRANSCO representative informed that there was a false SF6 gas pressure low alarm for line-1 CB, which the operator mistook for line-2. As there was a heavy downpour accompanied by strong winds outside, the shift personnel took time in mobilizing their resources to inspect the switchyard and attend to the problem. Finally, the line was restored by 10:45 hrs. It is noted that though the tripping of line is with correct operation of respective protection system, the attempt for immediate trial charging could not be done due to misunderstanding of the Substation operator during heavy rain. The situation could have been averted, had A/R been enabled at both ends in line with CEA s Technical Standards and insistence of SRPC forum in various PCSC meetings kv MAPS SP Koil line (L1): As per MAPS, the line tripped at 9:32 hrs on on Y-E fault due to DPR, Z1 operation at a distance of 9.15 km from MAPS. As per TANTRANSCO, on since 06:00 hrs the line-cb at SP Koil end on SP Koil MAPS line-1 was under lock-out due to Compressor s low air-pressure. Subsequently at 09:32hrs., line fault occurred in the above feeder; however the breaker had not tripped due to lock-out condition; as a result, LBB relay acted and tripped all the 230kV feeders & all the four Auto-transformers. From the DR furnished by TANTRANSCO, it was seen that LBB protection had taken 560 msec for its operation. Issues: The breaker of 230kV SP.Koil-MAPS feeder-1 at SP Koil end was under lock-out due to airpressure lock-out of the compressor since 6:00 am on , but no actions were taken at SP Koil end to rectify the same till the occurrence of the line fault at 9:32 hrs. LBB protection acted with a delay of 560 msec. TANTRANSCO representative informed that due to shorting of supply cable to Compressor motor, air pressure lock-out occurred for Compressor. The fault current had persisted for 560 msec due to sluggish operation of LBB relay, and the matter was taken up with their OEM and would soon revert on the action taken. In this regard, TANTRANSCO is recommended to provide (i) separate alarm window for Air Pressure & SF6 Pressure indication in the Sub-station (SP Koil) Control room, and (ii) Standby Compressor arrangement in all critical sub-stations like SP Koil. 5. Tripping of both Units at MAPS: With the tripping of Acharapakkam line (L-4) at 8:20 hrs on , Reactors power was reduced in both units by 5%. Currents on lines 1, 2, 3, and 4 were monitored and maintained at (400/360/0/0) AMPS respectively. Subsequently, when the SP Koil line-2 (L-2) also tripped at 9:02 hrs on , the current on the only remaining line (L-1) shot up to over 500 A due to which both Units small dump valves

5 opened; as a result, generation got reduced to 130 / 112 MW (e) and line current on L-1 was brought down to 480 Amps. Finally, when the only evacuating line, viz., SP Koil line-1 (L-1) also tripped at 9:32 hrs, both units got tripped on high frequency and total class IV failure. Both Reactors also got tripped on high boiler delta-t. From the above, it is observed that had one Unit been withdrawn on tripping of three evacuating lines, the station could have survived on house load with one Unit in service during the loss of evacuation of the station (i.e., during tripping of the fourth line). Therefore, for the survival of the nuclear station, it is always advised to ensure generation level of MAPS without compromising (n-1) condition of evacuation system. C. General Operational & Protection Issues pertaining to MAPS in the context of the Grid Disturbance that occurred on Replacement of Disc type string insulators on all the 230 kv lines emanating from MAPS. It is seen that Arani & Acharapakkam lines tripped due to the failure of disc type string insulators of the 230kV towers at MAPS end due to wear of ball and socket assembly on corrosion. Also there are more no. of jumpers existing on lines 3 & 4 at first & second towers from MAPS end. To this, TANTRANSCO informed that for the total 688 towers, 159 cut joints had already been replaced. The work relating to replacement of disc type string insulators by polymer type at all tension towers is already under progress, and will be completed by April, The action plan for the same at all suspension towers will also be furnished shortly. In this regard, TANTRANSCO is recommended to furnish their comprehensive plan for replacing disc insulators by polymer type at all tension and suspension towers on all the 230 kv lines emanating from MAPS before the 50th Protection Co-ordination Sub-Committee (PCSC) meeting scheduled to be held on 27 th January, Improving the flow/ exchange of information between MAPS and TANTRANSCO substations for the faults occurring on the connecting lines. Between the trippings of MAPS SP Koil line-2 (L2) at 9:06 hrs and SP Koil line-1 (L1) at 9:32 hrs on , it is seen that due to delay in exchanging proper information on the fault data, opportunity has been lost in taking the necessary remedial action to bring back MAPS - SP Koil line-2 into service. As the shift personnel at SP Koil end were under the impression that the line CB was under lock-out due to SF6 pressure low, proactive action was not initiated even though MAPS personnel had tried to contact them over phone. It is seen that even though MAPS was already operating under depleted network conditions at the time of tripping of SP Koil line-2 [due to tripping of MAPS Arani line (at 18:28 hrs on ) and MAPS Acharapakkam line (at 08:21 hrs on )], concerned shift personnel have not shown the alertness required in handling the distressed system. It was emphasized that to avoid similar incidents in future, better vigilance and alertness need to be exercised by the shift personnel.

6 In this regard, it is agreed by MAPS and TANTRANACO that whenever any fault takes place on the transmission lines between MAPS and TANTRANSCO substations, the relevant fault data, viz., location, zone, magnitude and phase of the fault current will be mutually exchanged, within minutes. Parallelly, the concerned shift personnel will also put efforts to get first hand information on the condition of the equipment involved by physically inspecting the yard. Thus both the ends shall ensure trial charging of the line within 15 (Fifteen) minutes of tripping of the element, if the tripping was on single phase fault. 3. Providing dual AC supply to Compressor Motor and redundant Compressor Unit. It is seen that the lock-out of the SP Koil end line-cb on the MAPS SP Koil line 1 (L1) happened due to air lock-out of the Compressor unit, which in turn occurred because of the failure of the Compressor Motor due to shorting of its supply cable. Had the redundancy been provided to the supply to the compressor motor and/ or the Compressor unit, the breaker s lock-out could have been prevented. In this regard, TANTRANSCO is recommended to provide (i) dual AC supply to Compressor unit of the CB s, and (ii) a redundant/ standby Compressor unit that would automatically takeover in case the main unit stops functioning at SP Koil end for the CB s on the MAPS-bound lines 1 & 2. As SP Koil is essentially on single-bus operation, the issue of providing bus-sectionalizer CB was also discussed. To this, it was informed that as SP Koil was a very old station, there was no space available to make way for bus-sectionalizer. TANTRANSCO is advised to consider the possibility of providing bus-sectionalizer breaker arrangement during renovation. It was also noticed that DG-set had been kept in manual mode during tripping event at SP Koil. As this is not desirable for handling emergency situations, TANTRANSCO is recommended to keep DG set always in auto-mode at its SP Koil SS. 4. Carrier communication/ PLCC related issues on 230kV MAPS-Arani line (L-3). It is noted that MAPS have not provided any relevant files like Event Logger and Disturbance Recorder to verify the issues relating to carrier communication on 230 kv MAPS Arani line. However, to ensure healthiness of carrier communication on L-3, the following is recommended to be carried out by MAPS and Arani SS personnel in coordination: Healthiness of PLCC system components (hardware and software) at both ends shall be checked and faulty components shall be repaired/ replaced. End-to-end communication for DT/ permissive & other signals may be ensured by testing at both the ends. 5. Status of providing Line CVT s in the Y phase of all feeders excepting SP Koil-2. This is one of the recommendations given by the audit team that carried out protection audit of MAPS switchyard in the year TANTANSCO informed that the procurement of line CVTs had been completed, and line CVT s would be commissioned soon. To this, TANTRANSCO was requested to furnish the schedule of commissioning of line CVT s before the 50 th PCSC meeting scheduled to be held on 27 th January, 2016.

7 6. Provision of Auto-reclosure (A/R) on all 230kV lines emanating from MAPS. TANTRANSCO informed that though A/R is available at their end on all evacuating lines of MAPS, the same was not put into service in view of MAPS decision to not to provide A/R at their ends. MAPS informed that due to the possibility of damage to/ reduction in life of turbine and generator rotor, NPCIL management have decided not to keep A/R in service on all 230 kv lines emanating from their Nuclear stations. It is noted with concern that in spite of the CEA s mandated requirement of providing auto-reclose on all 220 kv/ 230 kv lines, and the earlier recommendation of sub-group which held its meeting on to that effect, A/R has not been put into service on any of the four evacuating lines of MAPS by TANTRANSCO as well as MAPS at their respective ends. In this regard, SRLDC mentioned that either single phase A/R scheme or three phase A/R scheme as felt appropriate by MAPS can be implemented at MAPS end. However, if MAPS feels that attempt for A/R is to be prevented strictly from MAPS end, then a Lead-Follow three phase A/R scheme could be followed by MAPS to comply with CEA s standards and maintain grid discipline. It was explained that the proposed lead-follow A/R scheme would effectively take care of chances of generating end closing on to a permanent fault. In this master-follower A/R supervision scheme, the grid-station end would reclose first, and send a permissive-signal to the generating end on successful auto-reclosure. By ensuring that the generating end would reclose only after the receipt of the permissive signal from the remote end after a predetermined time (say 1.5 sec, this shall be less than the pole discrepancy relay operation time), the chances of it closing on to a permanent fault can be eliminated. In the event of non-receipt of carrier signal, the generating end can go for 3-ph trip. In this regard, the Topic 6.1 on Common Considerations for Auto-reclosing of the IEEE Guide for Automatic Reclosing of Line Circuit Breakers for AC Distribution and Transmission Lines may be referred to. It was reiterated that as providing auto-reclose on all 220 kv/ 230 kv lines is mandatory under Regulation 43 (2) (c) of CEA s Technical Standards for Construction of Electrical Plants & Electric lines, action plan for providing A/R on all 230 kv evacuating lines of MAPS has to be provided by MAPS. It is therefore recommended that MAPS shall take up the issue of providing lead/follow A/R scheme on its 230 kv evacuating lines with their Management and present their action plan for implementing the same before the 50 th meeting of PCSC scheduled to be held on 27 th January, Ensuring Grid Connectivity of MAPS. MAPS informed that the following mechanism exists at MAPS to bring down generation in case of tripping of evacuating lines of MAPS: When two of the four evacuating lines go out, 5% reduction in generation output is effected. It was, however, informed that due to the limitation imposed by nuclear reactor s controls, such reduction can at most be sustained for a period of 30 minutes before which requisite action should be taken to bring back lines into service, lest the reactors may get poisoned out. Under these conditions, when one more line goes out, and the flow on the only remaining line crosses 500 Amps, generation output is further reduced to 130/112 MW in each Unit by venting

8 out the excessive steam (by opening small dump valves), and the current will be brought down to 480 Amps. It was, however, informed that such operation can be entertained for at most 15 minutes before which requisite action should be taken to bring back lines into service, lest the reactors may get poisoned out. At MAPS, the power from 2x220 MW Units is being evacuated through the following four evacuating lines (Kunda type conductors with 213 MVA rating), viz., (i) 230 kv MAPS SP Koil line-1 (L-1); (ii) 230 kv MAPS SP Koil line-2 (L-2); (iii) 230 kv MAPS Arani line (L-3); and (iv) 230 kv MAPS Acharapakkam line (L-4). In addition to above, there is one radially connected Under Ground (UG) Cable to BHAVINI to supply start-up and commissioning power to BHAVINI. The cable has been provided with line differential protection as primary protection and over current and earth fault protections as back-up protection. From the above, the non-availability of (n-1) when two of the four evacuating lines get tripped is quite apparent. To provide (n-1), the combined generation of two Units has to be brought down to MW. However, as brought out above, the generation can only be brought down to 130/ 110 MW in each Unit (thus 260/220 MW in total) by resorting to extreme contingency measure of venting out excessive steam, which operation can be sustained for at most 15 minutes without any of the Reactor s getting poisoned out. Moreover, once such a thing happens, it takes one-to-three days to bring Units back on to bars. It was therefore originally proposed to utilize the existing UG Cable between MAPS and BHAVINI to its fullest capacity by connecting it to the grid at BHAVINI. However, considering its rating (133 MVA or 106 MW), it can be seen that (n-1) will not be fulfilled even after connecting this Cable to grid when MAPS operates with two evacuating lines. Considering the above limitations, and the need to ensure better connectivity of MAPS to grid, it is proposed to lay a Single-Circuit Over-Head Transmission Line with Twin-Moose type Conductor along the RoW of the present UG Cable. As the distance between MAPS and BHAVINI is only 800 mts., the proposed S/C over-head transmission line would be the ideal solution in the long-term to evacuate power from MAPS with (n-1) even after losing the two out of the four existing evacuating lines. MAPS and BHAVINI are therefore recommended to examine this proposal, and, after obtaining the consent of their respective managements, are requested to approach SP&PA Division of Central Electricity Authority to get the scheme ratified in the Standing Committee on Power System Planning for Southern Region (SCPSPSR) for implementation. Till such time, MAPS is recommended to maintain the generation level such that the line loading of available evacuation system will always satisfy the requirement of n-1 criteria. In the process, if the situation requires withdrawing one of the two Units, the same may be followed by MAPS to avoid tripping of both Units on loss of evacuation.

9 The necessary system studies to make out a strong case for the above proposal have been carried out, and are presented at Annexure-V. The assumptions made and the scenarios considered for the above studies are detailed below: Assumptions made/ Data considered: (i) The following UG Cable characteristics as informed by BHAVINI have been considered: Sl. Description Value No. 1 Rating Voltage: 230 kv (Max. 245 kv) Current: 850 A in air 646 A in duct 335 A when directly buried in ground [Cable is directly buried in ground] 2 Length of the Cable 3 runs of 800 mt. cable 3 Conductor Max. DC Resistance per km (i) At 20 C Ω/ km (ii) At 90 C Ω/ km 4 Positive & Negative sequence reactance per km j Zero sequence data per km j Protection equipment rating at both ends of the Cable VT 100 VA; CT 30 VA (ii) Share of various States in BHAVINI s first Unit of 500 MW capacity has been considered as follows: Andhra Pradesh + Telangana Karnataka TamilNadu Kerala Puducherry Unallocated Power 132 MW 72 MW 167 MW 43 MW 11 MW 75 MW (iii)expected commissioning schedule of the first Unit of BHAVINI (of 500 MW capacity) has been taken as September, (iv)the Ex-bus generation considered for MAPS and BHAVINI are 2x200 MW and 1x450 MW respectively. (v) For the studies with & without generation at BHAVINI, present operational base-case only has been considered, as the effect of transmission elements that would get added to the grid by September, 2016 would be minimal on the existing 230 kv network in & around MAPS.

10 Various Scenarios considered: Sl. CASE No. Scenario considered Line flow violations No. 1 Base Case (BC) MAPS with L1, L2, L3 & L4 in service NIL 2 CASE-1 BC + Outage of [L1] NIL 3 CASE-2 BC + Outage of [L1 + L3] 235 MW on L2 4 CASE-3 BC + Outage of [L1 + L3 + L4] 400 MW on L2 5 CASE-4 (BC1) BC kv MAPS BHAVINI Cable NIL 6 CASE-5 BC1 + Outage of [L1] NIL 7 CASE-6 BC1 + Outage of [L1 + L3] NIL 8 CASE-7 BC1 + Outage of [L1 + L3 + L4] 320 MW on L2 9 CASE-8 [= New Base Base Case (BC) MW generation at NIL Case (NBC)] BHAVINI 10 CASE-9 NBC + Outage of [L3] NIL 11 CASE-10 NBC + Outage of [L3 + L2] 215 MW on L1 12 CASE-11 NBC + Outage of [L3 + L2 + L1] 400 MW on L4 13 CASE-12 (NBC1) NBC kv MAPS BHAVINI Cable NIL 14 CASE-13 NBC1 + Outage of [L3] NIL 15 CASE-14 NBC1 + Outage of [L3 + L2] MMW on L1 16 CASE-15 NBC1 + Outage of [L3 + L2 + L4] MW on L1 17 CASE-16 (BC2) Base Case (BC) kv MAPS BHAVINI NIL Twin Moose S/C line 18 CASE-17 BC2 + Outage of [L1] NIL 19 CASE-18 BC2 + Outage of [L1 + L2] NIL 20 CASE-19 BC2 + Outage of [L1 + L2 + L3] NIL 21 CASE-20 BC2 + Outage of [L1 + L2 + L3 + L4] NIL 22 CASE-21 (NBC2) Base Case (BC) MW generation at NIL BHAVINI kv MAPS BHAVINI Twin Moose S/C line 23 CASE-22 NBC2 + Outage of [L1] NIL 24 CASE-23 NBC2 + Outage of [L1 + L2] NIL 25 CASE-24 NBC2 + Outage of [L1 + L2 + L3] NIL 26 CASE-25 NBC2 + Outage of [L1 + L2 + L3 + L4] NIL

11 Short Circuit Studies for various scenarios have also been carried out and tabulated below: Since both MAPS and BHAVINI stations have been designed for a Short Circuit Level of 10,000 MVA, it can be concluded from the above that laying of Twin-Moose type S/C Over-Head transmission line between MAPS and BHAVINI poses no problem. 8. Furnishing of tripping details in compliance of Regulation 5.2 (r) of IEGC, and providing monthly status of healthiness of batteries MAPS s attention has been brought to their obligation of fulfilling requirements under Regulation 5.2 (r) of IEGC, as per which all Users, STU/ SLDC, and CTU are required to furnish for analysis purpose the relevant information relating to tripping events in their system along with Disturbance Recorder (DR) and Event Logger (EL) to SRLDC/ SRPC within 24-hrs of occurrence of the same. Though this issue was regularly brought to Constituents (including MAPS) attention vide various SRLDC & SRPC (fort-nightly) letters, still data w.r.t. all events was either not being furnished or being made available with unacceptable delay of few weeks. MAPS is recommended to upload various tripping files (FIR/ DR/ EL/ TR) whenever any tripping involving their station takes place in SRLDC s web-portal within 24-hrs of the occurrence of the tripping event in compliance of Regulation 5.2 (r) of IEGC. 9. Patrolling Protocol/Guidelines for Over Head Transmission Lines: SRPC brought to the notice of TNEB regarding the Patrolling Protocol/Guidelines for Over Head Transmission Lines to be followed by them. It was noted that in compliance of Hon ble CERC Order dated in respect of Petition No. 146/MP/2013 wit IA 36/2013, Patrolling Protocol/Guidelines for Over Head Transmission Lines had been formulated by SRPC Secretariat in due consultation with all the stake holders and the same had been communicated to Hon ble CERC and all the Transmission Utilities (Central/State) vide SRPC letter dated with a request to strictly follow the guidelines. It was noted that as per Guidelines, each transmission utility should furnish the Annual Schedule of Patrolling to SRPC/SRLDC along with Annual Outage data by October each year and compliance report of the patrolling/maintenance carried out during previous month with respect to schedule would be furnished to SRLDC/SRPC in the OCC Meeting. TANTRANSCO agreed to follow the same and requested SRPC to kindly furnish a copy of the Patrolling Protocol/Guidelines for Over Head Transmission Lines to help in their needful action. In this regard, a copy of the sought Guidelines is enclosed at Annexure-VI.

12 10. Line Clearance issues: The following suggestions/recommendations given by the System Studies Sub-Group of SRPC which held its meeting on regarding line clearance were reiterated: Information regarding the lines kept open in MAPS vicinity to be informed to MAPS. Restoration of the same also may be informed pertinently. If any line clearance (LC) is there in downstream/upstream MAPS area for maintenance, then further opening of the lines which may cause non availability of evacuation lines from MAPS have to be restricted for avoiding undesired island formation of MAPS generation with TANTRANSCO loads/house Load operation of MAPS Units / Poisoning of Units etc. 11.Providing information relating to line outages and Declared Capacity (DC) revision in case of generating Unit outages SRLDC mentioned with concern that revision of DC by MAPS is not being done by MAPS as and when there is tripping / synchronization / change in level of generation. This lead to operational difficulties as well as huge financial implication on the constituents when the corrections were incorporated post facto. MAPS assured for necessary action in this regard and strict compliance in future. The issue of not providing proper information to SRPC/ SRLDC regarding line outages and in case of line outages by TANTRANSCO was also discussed. TANTRANSCO assured that they would take effective steps to ensure that such lapses won t take place. *****

13 Page 1 of 2 Annexure-I

14 Page 2 of 2 Annexure-I

15 Page 1 of 2 Annexure-II

16 Page 2 of 2 Annexure-II

17 Page 1 of 2 Annexure-III

18 Page 2 of 2 Annexure-III

19 Action taken by MAPS and TANTRANSCO w.r.t the recommendations given by the System Studies Sub-Group of SRPC in its meeting held on Sl. No. Observation/ Recommendation Action taken Annexure-IV 1 It was learned in the sub-group meeting at Chennai on that PHT pump-7 of the Unit-I tripped on under frequency or other supply conditions. Though pumps of the both the units were subjected to same frequency and other supply conditions, only the specific pump of Unit-1. On account of this, MAPS is requested to review the protection settings of the affected pump of Unit- 1 and furnish a detailed report to the SRPC indicating the protection settings (for voltage, current, frequency, etc.) of the pump, and exact reason for tripping of the pump of Unit-I and corrective actions taken to prevent reoccurrence. 2 MAPS is also requested to draw an action plan for facing the similar situation (i.e. that was experienced on ) due to countless & unforeseeable combinations of arrangement of network elements in the vicinity of MAPS. This plan of action shall include retaining auxiliary supply and ensuring successful and sustained house load operation till grid returns to normalcy. 3 TANTRANSCO was requested to carry out line patrolling for locating any trouble spots, if any. 4 If any Line Clearance (LC) is there in that area for maintenance, then further opening of the lines have to be restricted for avoiding undesired island formation of MAPS generation with TANTRANSCO loads. 5 Alternate anchoring through Oragadam Bus coupler and SP Koil Bus coupler could be provided (Study results are attached in the Annexure). At least 2-3 links to be ensured with N-1 in future to avoid islanding of critical areas/generation complexes. 6 Line loadings should be controlled by taking up adequate load shedding, especially during a critical shutdown, rather than resorting to network rearrangement. N-1 to be ensured in real time operation. Page 1 of 2 Action taken by MAPS in this regard is awaited. Complied by MAPS. It was informed that Transient Handling Procedure (THP) is in place to successfully handle the house load operation. Complied by TANTRANSCO. From the events leading to Grid Disturbance on , it is seen that due diligence has not been exercised by TANTRANSCO in preventing the same. The issue was discussed in detail in PSAG-14 meeting. Complied by TANTRANSCO. Complied by TANTRANSCO. It was informed that with the commissioning of additional 400 kv and 230 kv lines, TANTRANSCO is relying on load shedding rather than resorting to

20 network rearrangement Annexure-IV to ensure line loadings stay within permissible limits during critical shutdown. 7 Many of the 230 KV and below lines in Chennai area are heavily loaded without N-1. Systematic augmentation for the same needs to be planned and executed on priority. 8 AIR facility to be provided on all lines from MAPS as well as critical S/Ss of TANTRANSCO to guard against transient faults. Action taken by TANTRANSCO in this regard is awaited. MAPS: Not complied. TANTRNSCO: Though A/R was provided at their Substations for all connecting 230 kv lines to MAPS, the same was kept disabled. The issue was discussed in detail in PSAG-14 meeting. 9 Information about lines kept open in MAPS vicinity is to he informed to MAPS. Information about status is to be given to MAPS while restoration also. 10 Outage of both circuits of 400 KV Kalivandapattu-Vallur would cease to be a concern when 400 KV Kalivandapaltu-Pugalur/Thiruvalam are in place. Complied by TANTRANSCO. TANTRANSCO informed that this had been taken care of by the commissioning of 400 kv KV Pattu Pugalur D/C line. Page 2 of 2

21 BHAVANI ARNI MAPS SIRSERI H 50.0H SPBUDUR SPET SPKOIL ACHARAP BASECASE Annexure-V Page 1 of 26

22 1 CASE-1: BASECASE + 230kV SP KOIL- MAPS -1 OUTAGE SIRSERI2 Annexure-V BHAVANI SPET ARNI SPBUDUR MAPS SPKOIL ACHARAP Page 2 of R 39.0R

23 1 CASE 2 : CASE kV MAPS - ARNI S/C OUTAGE SIRSERI2 Annexure-V BHAVANI SPET ARNI SPBUDUR MAPS SPKOIL ACHARAP Page 3 of R 28.8R

24 1 CASE 3: CASE kV MAPS - ACHARAPKAM S/C OUTAGE SIRSERI2 Annexure-V BHAVANI SPET ARNI SPBUDUR MAPS SPKOIL ACHARAP Page 4 of R 25.6R

25 1 CASE 4 : BASECASE + 230kV MAPS - BHAVINI CABLE IN-SERVICE SIRSERI2 Annexure-V BHAVANI SPET ARNI SPBUDUR MAPS SPKOIL ACHARAP Page 5 of H 50.0H

26 1 CASE 5 : CASE kV MAPS - SP KOIL -1 OUTAGE SIRSERI2 Annexure-V BHAVANI SPET ARNI SPBUDUR MAPS SPKOIL ACHARAP Page 6 of R 43.2R

27 1 CASE 6: CASE kV MAPS - ARNI S/C OUTAGE SIRSERI2 Annexure-V BHAVANI SPET ARNI SPBUDUR MAPS SPKOIL ACHARAP Page 7 of R 34.3R

28 1 CASE 7 : CASE kV MAPS - ACHARAPAKAM S/C OUTAGE SIRSERI2 Annexure-V BHAVANI SPET ARNI SPBUDUR MAPS SPKOIL ACHARAP Page 8 of R 29.1R

29 1 CASE 8 : BASECASE + BHAVINI 450 MW GENERATION SIRSERI2 Annexure-V BHAVANI SPET ARNI SPBUDUR MAPS R SPKOIL ACHARAP Page 9 of R 37.0R

30 1 CASE 9 : CASE kV MAPS - ARNI S/C OUTAGE SIRSERI2 Annexure-V BHAVANI SPET ARNI SPBUDUR MAPS R SPKOIL ACHARAP Page 10 of R 31.1R

31 1 CASE 10 : CASE kV MAPS - SP KOIL-2 OUTAGE SIRSERI2 Annexure-V BHAVANI SPET ARNI SPBUDUR MAPS R SPKOIL ACHARAP Page 11 of R 17.1R

32 1 CASE 11 : CASE kV MAPS - SP KOIL - 1 OUTAGE SIRSERI2 Annexure-V BHAVANI SPET ARNI SPBUDUR MAPS H SPKOIL ACHARAP Page 12 of R 17.4R

33 1 CASE - 12: CASE kV MAPS - BHAVINI S/C CABLE IN-SERVICE SIRSERI2 Annexure-V BHAVANI SPET ARNI SPBUDUR MAPS R SPKOIL ACHARAP Page 13 of R 35.0R

34 1 CASE 13: CASE kV MAPS - ARNI S/C LINE OUTAGE SIRSERI2 Annexure-V BHAVANI SPET ARNI SPBUDUR MAPS R SPKOIL ACHARAP Page 14 of R 28.3R

35 1 CASE 14: CASE kV MAPS - SP KOIL-2 OUTAGE SIRSERI2 Annexure-V BHAVANI SPET ARNI SPBUDUR MAPS R SPKOIL ACHARAP Page 15 of R 13.2R

36 1 CASE 15: CASE kV MAPS - ACHARAPAKAM SC OUTAGE SIRSERI Annexure-V BHAVANI SPET ARNI SPBUDUR MAPS H SPKOIL ACHARAP Page 16 of R 7.9R

37 1 Annexure-V CASE 16: BASECASE + 230kV MAPS - BHAVINI TWIN MOOSE SC LINE SIRSERI BHAVANI SPET ARNI SPBUDUR MAPS SPKOIL ACHARAP H 50.0H Page 17 of 26

38 1 Annexure-V CASE 17: CASE kV MAPS - SP KOIL -1 OUTAGE SIRSERI BHAVANI SPET ARNI SPBUDUR MAPS SPKOIL ACHARAP H 50.0H Page 18 of 26

39 1 Annexure-V CASE 18: CASE kV MAPS - SP KOIL -2 OUTAGE SIRSERI BHAVANI SPET ARNI SPBUDUR MAPS SPKOIL ACHARAP H 50.0H Page 19 of 26

40 1 Annexure-V CASE 19: CASE kV MAPS - ARNI SC OUTAGE SIRSERI BHAVANI SPET ARNI SPBUDUR MAPS SPKOIL ACHARAP H 50.0H Page 20 of 26

41 1 Annexure-V CASE 20: CASE kV MAPS - ACHARAPAKAM S OUTAGE SIRSERI BHAVANI SPET ARNI SPBUDUR MAPS SPKOIL ACHARAP H 50.0H Page 21 of 26

42 1 Annexure-V CASE 21: CASE kV MAPS - BHAVINI TWIN MOOSE S/C LINE SIRSERI BHAVANI SPET ARNI SPBUDUR MAPS H SPKOIL ACHARAP R 3.4R Page 22 of 26

43 1 Annexure-V CASE 22: CASE kV MAPS - ARNI SC OUTAGE SIRSERI BHAVANI SPET ARNI SPBUDUR MAPS H SPKOIL ACHARAP R 7.2R Page 23 of 26

44 1 Annexure-V CASE 23: CASE kV MAPS - SP KOIL -2 OUTAGE SIRSERI BHAVANI SPET ARNI SPBUDUR MAPS H SPKOIL ACHARAP R -1.4R Page 24 of 26

45 1 Annexure-V CASE 24: CASE kV MAPS - SP KOIL - 1 OUTAGE SIRSERI BHAVANI SPET ARNI SPBUDUR MAPS H SPKOIL ACHARAP R -20.1R Page 25 of 26

46 1 Annexure-V CASE 25 : CASE kV MAPS - ACHARAPAKAM SC OUTAGE SIRSERI BHAVANI SPET ARNI SPBUDUR MAPS H SPKOIL ACHARAP R -16.0R Page 26 of 26

47 Page 1 of 12 Annexure-VI

48 Page 2 of 12 Annexure-VI

49 Page 3 of 12 Annexure-VI

50 Page 4 of 12 Annexure-VI

51 Page 5 of 12 Annexure-VI

52 Page 6 of 12 Annexure-VI

53 Page 7 of 12 Annexure-VI

54 Page 8 of 12 Annexure-VI

55 Page 9 of 12 Annexure-VI

56 Page 10 of 12 Annexure-VI

57 Page 11 of 12 Annexure-VI

58 Page 12 of 12 Annexure-VI

Section 5. TADS Data Reporting Instruction Manual DRAFT Section 5 and Associated Appendices With Proposed Event Type Numbers

Section 5. TADS Data Reporting Instruction Manual DRAFT Section 5 and Associated Appendices With Proposed Event Type Numbers Section 5 TADS Data Reporting Instruction Manual DRAFT Section 5 and Associated Appendices With Proposed Event Type Numbers Rev. 5/10/2010 1 Section 5 Form for Event ID and Event Type Number Data TO s

More information

Case Study on Fault Analysis Using PMU

Case Study on Fault Analysis Using PMU Case Study on Fault Analysis Using PMU Prithwish Mukhopadhyay General Manager, WRLDC prithwish.mukhopadhyay@posoco.in Abhimanyu Gartia Deputy General Manager, WRLDC agartia@posoco.in Pushpa Seshadri Chief

More information

Pursuant to Section 205 of the Federal Power Act ( FPA ) 1 and the Commission s

Pursuant to Section 205 of the Federal Power Act ( FPA ) 1 and the Commission s PJM Interconnection 2750 Monroe Boulevard Norristown, PA 19403-2497 Steven R. Pincus Associate General Counsel 610.666.4370 fax 610.666.8211 steven.pincus@pjm.com July 31, 2017 Honorable Kimberly D. Bose

More information

Chapter 3 AUTOMATIC VOLTAGE CONTROL

Chapter 3 AUTOMATIC VOLTAGE CONTROL Chapter 3 AUTOMATIC VOLTAGE CONTROL . INTRODUCTION TO EXCITATION SYSTEM The basic function of an excitation system is to provide direct current to the field winding of the synchronous generator. The excitation

More information

7. Transient stability

7. Transient stability 1 7. Transient stability In AC power system, each generator is to keep phase relationship according to the relevant power flow, i.e. for a certain reactance X, the both terminal voltages V1and V2, and

More information

Fault Calculation Methods

Fault Calculation Methods ELEC9713 Industrial and Commercial Power Systems Fault Calculation Methods There are two major problems that can occur in electrical systems: these are open circuits and short circuits. Of the two, the

More information

Peterborough Distribution Inc Ashburnham Drive, PO Box 4125, Station Main Peterborough ON K9J 6Z5

Peterborough Distribution Inc Ashburnham Drive, PO Box 4125, Station Main Peterborough ON K9J 6Z5 Peterborough Distribution Inc. 1867 Ashburnham Drive, PO Box 4125, Station Main Peterborough ON K9J 6Z5 November 15, 2017 Ontario Energy Board PO Box 2319 27 th Floor, 2300 Yonge St Toronto ON M4P 1E4

More information

System Impact Assessment Addendum #2 Greenfield & St. Clair Energy Centres

System Impact Assessment Addendum #2 Greenfield & St. Clair Energy Centres IESO_REP_0292 System Impact Assessment Addendum #2 Greenfield & St. lair Energy entres onnection Assessment & Approval Process Issue 3.0 Greenfield Energy entre AA I 2004-167 Applicant: Greenfield Energy

More information

Chapter 9: Transient Stability

Chapter 9: Transient Stability Chapter 9: Transient Stability 9.1 Introduction The first electric power system was a dc system built by Edison in 1882. The subsequent power systems that were constructed in the late 19 th century were

More information

VKES. Contents. Page 2 No 213, 13th Main RBI Layout JP Nagar 7th Phase, Bangalore Vidyuth Kanti Engineering Services

VKES. Contents. Page 2 No 213, 13th Main RBI Layout JP Nagar 7th Phase, Bangalore Vidyuth Kanti Engineering Services Contents What is earthing... 4 Why do we do earthing... 4 What is the Scope of this guideline... 4 How to protect a person in a substation against electrical shock... 4 What happens during a fault... 4

More information

1. Explain the various methods of methods of grounding. In power system, grounding or earthing means connecting frame of electrical equipment (non-cur

1. Explain the various methods of methods of grounding. In power system, grounding or earthing means connecting frame of electrical equipment (non-cur 1. Explain the various methods of methods of grounding. In power system, grounding or earthing means connecting frame of electrical equipment (non-current carrying part) or some electrical part of the

More information

F F FAULT CURRENT Prospective. 1. Introduction. 2. Types of fault conditions

F F FAULT CURRENT Prospective. 1. Introduction. 2. Types of fault conditions FAULT CURRENT F F13-13 FAULT CURRENT - Contents 1. Introduction 2. Types of fault conditions 3 fault current must be determined 3.1 Purposes for which of prospective fault current magnitudes are used 3.2

More information

Instruction. Vacuum Circuit Breaker Operator Module. Type 3AH 4.16kV to 38kV. Power Transmission & Distribution

Instruction. Vacuum Circuit Breaker Operator Module. Type 3AH 4.16kV to 38kV. Power Transmission & Distribution Instruction 0001-22-2--00 Vacuum Circuit Breaker Operator Module Type 3AH 4.16kV to 38kV Power Transmission & Distribution Hazardous voltages and high-speed moving parts. Will cause death, serious injury

More information

'l:l1w m:q;n: government of India. ~~gtf'~ Central Electricity Authority. ~m~~

'l:l1w m:q;n: government of India. ~~gtf'~ Central Electricity Authority. ~m~~ 'l:l1w m:q;n: government of India ~~gtf'~ Central Electricity Authority ~m~~ ~~I Western Regional Power Committee IS/ISO: 9001-2008 q;:fi-3, t:;i1.~ Wr, 3iirfr(' ), ~ - 400093 F-3, MIDC Area, Andheri (East),

More information

PUB NLH 185 Island Interconnected System Supply Issues and Power Outages Page 1 of 9

PUB NLH 185 Island Interconnected System Supply Issues and Power Outages Page 1 of 9 PUB NLH 1 Page 1 of 1 Q. Provide Hydro s list of outage cause codes and indicate how troublemen are managed and trained to properly use the codes. Explain the method used to report outage causes. A. Hydro

More information

Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian Institute of Technology, Kharagpur

Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian Institute of Technology, Kharagpur Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian Institute of Technology, Kharagpur Lecture - 9 Transmission Line Steady State Operation Welcome to lesson 9, in Power

More information

IS YOUR BUSINESS PREPARED FOR A POWER OUTAGE?

IS YOUR BUSINESS PREPARED FOR A POWER OUTAGE? IS YOUR BUSINESS PREPARED FOR A POWER OUTAGE? Keeping your power on is our business Whether your business is large, small or somewhere in between, we understand that a power outage presents special challenges

More information

Module 6 : Preventive, Emergency and Restorative Control. Lecture 27 : Normal and Alert State in a Power System. Objectives

Module 6 : Preventive, Emergency and Restorative Control. Lecture 27 : Normal and Alert State in a Power System. Objectives Module 6 : Preventive, Emergency and Restorative Control Lecture 27 : Normal and Alert State in a Power System Objectives In this lecture you will learn the following Different states in a power system

More information

B.E. / B.Tech. Degree Examination, April / May 2010 Sixth Semester. Electrical and Electronics Engineering. EE 1352 Power System Analysis

B.E. / B.Tech. Degree Examination, April / May 2010 Sixth Semester. Electrical and Electronics Engineering. EE 1352 Power System Analysis B.E. / B.Tech. Degree Examination, April / May 2010 Sixth Semester Electrical and Electronics Engineering EE 1352 Power System Analysis (Regulation 2008) Time: Three hours Answer all questions Part A (10

More information

GENERATOR INTERCONNECTION APPLICATION

GENERATOR INTERCONNECTION APPLICATION GENERATOR INTERCONNECTION APPLICATION FOR BUY-ALL/SELL-ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 20 KW BUT LESS THAN OR EQUAL TO 1 MW Electric Utility Contact Information Great Lakes Energy

More information

Reliability of Bulk Power Systems (cont d)

Reliability of Bulk Power Systems (cont d) Reliability of Bulk Power Systems (cont d) Important requirements of a reliable electric power service Voltage and frequency must be held within close tolerances Synchronous generators must be kept running

More information

SSC-JE EE POWER SYSTEMS: GENERATION, TRANSMISSION & DISTRIBUTION SSC-JE STAFF SELECTION COMMISSION ELECTRICAL ENGINEERING STUDY MATERIAL

SSC-JE EE POWER SYSTEMS: GENERATION, TRANSMISSION & DISTRIBUTION SSC-JE STAFF SELECTION COMMISSION ELECTRICAL ENGINEERING STUDY MATERIAL 1 SSC-JE STAFF SELECTION COMMISSION ELECTRICAL ENGINEERING STUDY MATERIAL Power Systems: Generation, Transmission and Distribution Power Systems: Generation, Transmission and Distribution Power Systems:

More information

Request Ensure that this Instruction Manual is delivered to the end users and the maintenance manager.

Request Ensure that this Instruction Manual is delivered to the end users and the maintenance manager. Request Ensure that this Instruction Manual is delivered to the end users and the maintenance manager. 1 -A - Introduction - Thank for your purchasing MITSUBISHI ELECTRIC MELPRO TM D Series Digital Protection

More information

Outage Coordination and Business Practices

Outage Coordination and Business Practices Outage Coordination and Business Practices 1 2007 Objectives What drove the need for developing a planning/coordination process. Why outage planning/coordination is crucial and important. Determining what

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Interconnection for Wind Energy ) Docket No. RM

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Interconnection for Wind Energy ) Docket No. RM UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Interconnection for Wind Energy ) Docket No. RM05-4-000 REQUEST FOR REHEARING OF THE NORTH AMERICAN ELECTRIC RELIABILITY COUNCIL

More information

DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING QUESTION BANK

DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING QUESTION BANK DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING QUESTION BANK SUBJECT CODE & NAME: EE 2303 - TRANSMISSION & DISTRIBUTION YEAR / SEM: III/V UNIT-I TRANSMISSION SYSTEM INTRODUCTION PART-A 1. What is

More information

Staging for Utility Personnel and Mutual Aid. 1. Hermine- Meeting dates were August 29th_31 st, 2016 and September 1st, 2016.

Staging for Utility Personnel and Mutual Aid. 1. Hermine- Meeting dates were August 29th_31 st, 2016 and September 1st, 2016. Town of Havana, Fl. Response to Review of Electric Utility Hurricane Preparedness and Restoration Actions- Applies only to Hermine and Irma. Maria and Nate posed no serious threat to Havana. Staging for

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS 10782 Wattsburg Road Erie, PA 16509 The WATTSBURG AREA SCHOOL DISTRICT invites qualified vendors to submit proposals for CONTRACTED SNOW REMOVAL MANDATORY PRE-SUBMISSION MEETING All

More information

EE2351 POWER SYSTEM OPERATION AND CONTROL UNIT I THE POWER SYSTEM AN OVERVIEW AND MODELLING PART A

EE2351 POWER SYSTEM OPERATION AND CONTROL UNIT I THE POWER SYSTEM AN OVERVIEW AND MODELLING PART A EE2351 POWER SYSTEM OPERATION AND CONTROL UNIT I THE POWER SYSTEM AN OVERVIEW AND MODELLING PART A 1. What are the advantages of an inter connected system? The advantages of an inter-connected system are

More information

Faults on Electrical System. A Research

Faults on Electrical System. A Research Faults on Electrical System A Research Presented to Electrical Engineering School of Engineering and Architecture Mindanao University of Science and Technology Cagayan de Oro City In partial fulfilment

More information

1. Introduction. Keywords Transient Stability Analysis, Power System, Swing Equation, Three-Phase Fault, Fault Clearing Time

1. Introduction. Keywords Transient Stability Analysis, Power System, Swing Equation, Three-Phase Fault, Fault Clearing Time Energy and Power 17, 7(1): -36 DOI: 1.593/j.ep.1771.3 Numerical Simulations for Transient Stability Analysis of Two-Machine Power System Considering Three-Phase Fault under Different Fault Clearing Times

More information

KINGS COLLEGE OF ENGINEERING Punalkulam

KINGS COLLEGE OF ENGINEERING Punalkulam KINGS COLLEGE OF ENGINEERING Punalkulam 613 303 DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING POWER SYSTEM ANALYSIS QUESTION BANK UNIT I THE POWER SYSTEM AN OVERVIEW AND MODELLING PART A (TWO MARK

More information

Risk Assessment and Mitigation. Hurricane Checklist

Risk Assessment and Mitigation. Hurricane Checklist Risk Assessment and Mitigation Hurricane Checklist Hurricane Checklist Hurricanes are severe tropical storms with sustained winds of at least 74 miles per hour. Hurricane winds can reach 160 miles per

More information

SNOW REMOVAL - REQUEST FOR PROPOSAL. Snow Removal/Clearing and Sanding/Salting for Winter Fundy Ocean Research Center for Energy

SNOW REMOVAL - REQUEST FOR PROPOSAL. Snow Removal/Clearing and Sanding/Salting for Winter Fundy Ocean Research Center for Energy Fundy Ocean Research Center for Energy SNOW REMOVAL - REQUEST FOR PROPOSAL Snow Removal/Clearing and Sanding/Salting for Winter 2016-17 Sites 1. FORCE Sub-Station Driveway (portion of Old Black Rock Road),

More information

Hydra Fault Current Limiting HTS Cable to be Installed in the Consolidated Edison Grid

Hydra Fault Current Limiting HTS Cable to be Installed in the Consolidated Edison Grid Hydra Fault Current Limiting HTS Cable to be Installed in the Consolidated Edison Grid J. McCall, J. Yuan, D. Folts, N. Henderson, American Superconductor D. Knoll, Southwire M. Gouge, R. Duckworth, J.

More information

Role of Synchronized Measurements In Operation of Smart Grids

Role of Synchronized Measurements In Operation of Smart Grids Role of Synchronized Measurements In Operation of Smart Grids Ali Abur Electrical and Computer Engineering Department Northeastern University Boston, Massachusetts Boston University CISE Seminar November

More information

POWER SEMICONDUCTOR BASED ELECTRIC DRIVES

POWER SEMICONDUCTOR BASED ELECTRIC DRIVES POWER SEMICONDUCT BASED ELECTRIC DRIVES [Time: 3 Hrs] [Max. Marks: 80] Instructions: Solve any six questions from Q.No (1 or 2), Q.No (3 or 4), Q.No (5 or 6), Q.No (7 or 8), Q.No (9 or 10), Q.No (11 or

More information

PROCEDURE NO.: SO5-2-6 PAGES: 1 OF 10 CHIEF SYSTEM OPERATOR

PROCEDURE NO.: SO5-2-6 PAGES: 1 OF 10 CHIEF SYSTEM OPERATOR CON EDISON SYSTEM OPERATION DEPARTMENT PROCEDURE SUBJECT: THUNDERSTORM/STORM PROCEDURE PROCEDURE NO.: SO5-2-6 PAGES: 1 OF 10 REVISED BY: S. BUFFAMANTE APPROVED: T. HALLERAN CHIEF SYSTEM OPERATOR DATE:

More information

EE Branch GATE Paper 2010

EE Branch GATE Paper 2010 Q.1 Q.25 carry one mark each 1. The value of the quantity P, where, is equal to 0 1 e 1/e 2. Divergence of the three-dimensional radial vector field is 3 1/r 3. The period of the signal x(t) = 8 is 0.4

More information

5SJ4...-.HG Circuit Breakers to IEC and UL 489

5SJ4...-.HG Circuit Breakers to IEC and UL 489 Siemens AG 009 5SJ...-.HG Circuit Breakers to IEC and UL 89 BETA Low-Voltage Circuit Protection Compliance with industry standards is a must in today's manufacturing environment. Worldwide acceptance is

More information

RESULTS OF ON-GRID OPERATION OF SUPERCONDUCTOR DYNAMIC SYNCHRONOUS CONDENSER

RESULTS OF ON-GRID OPERATION OF SUPERCONDUCTOR DYNAMIC SYNCHRONOUS CONDENSER 1 RESULTS OF ON-GRID OPERATION OF SUPERCONDUCTOR DYNAMIC SYNCHRONOUS CONDENSER Dr. Swarn S. Kalsi, David Madura, and Michael Ross American Superconductor Corporation (USA) Abstract: A high-temperature

More information

Modeling of Power System Components During Electromagnetic Transients

Modeling of Power System Components During Electromagnetic Transients Modeling of Power System Components During Electromagnetic Transients 1 Paweł Sowa, 2 Rafał Kumala and 3 Katarzyna Łuszcz 1, 2,3 Faculty of Electrical Engineering, Silesian University of Technology/ Institute

More information

Correlation between Lightning Impacts and Outages of Transmission Lines. H-D. BETZ Nowcast GmbH Munich Germany

Correlation between Lightning Impacts and Outages of Transmission Lines. H-D. BETZ Nowcast GmbH Munich Germany CIGRE C4 Colloquium on Power Quality and Lightning Sarajevo, Bosnia and Herzegovina, 13 16 May, 2012 Paper 01. Correlation between Lightning Impacts and Outages of Transmission Lines I. UGLEŠIĆ V. MILARDIĆ

More information

Effects of Capacitor Bank Installation in a Medium Voltage (MV) Substation

Effects of Capacitor Bank Installation in a Medium Voltage (MV) Substation Effects of Capacitor Bank Installation in a Medium Voltage (MV) Substation Adesina, Lambe Mutalub Department of Engineering & Standardization, Eko Electricity Distribution Plc, 24/25, Marina, Lagos Island,

More information

INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous)

INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad - 500 043 ELECTRICAL AND ELECTRONICS ENGINEERING QUESTION BANK Course Name : Computer Methods in Power Systems Course Code : A60222

More information

Overview of Control System Design

Overview of Control System Design Overview of Control System Design General Requirements 1. Safety. It is imperative that industrial plants operate safely so as to promote the well-being of people and equipment within the plant and in

More information

Dynamic simulation of a five-bus system

Dynamic simulation of a five-bus system ELEC0047 - Power system dynamics, control and stability Dynamic simulation of a five-bus system Thierry Van Cutsem t.vancutsem@ulg.ac.be www.montefiore.ulg.ac.be/~vct November 2017 1 / 16 System modelling

More information

An Introduction to Insulation Resistance Testing

An Introduction to Insulation Resistance Testing An Introduction to Insulation Resistance Testing In a perfect world, electrical insulation would allow no current to flow through it. Unfortunately, a number of factors can over time result in the deterioration

More information

Module 3 : Sequence Components and Fault Analysis

Module 3 : Sequence Components and Fault Analysis Module 3 : Sequence Components and Fault Analysis Lecture 12 : Sequence Modeling of Power Apparatus Objectives In this lecture we will discuss Per unit calculation and its advantages. Modeling aspects

More information

EBS IT Meeting July 2016

EBS IT Meeting July 2016 EBS IT Meeting 18 19 July 2016 Conference Call Details Conference call: UK Numbers Tel: 0808 238 9819 or Tel: 0207 950 1251 Participant code: 4834 7876... Join online meeting https://meet.nationalgrid.com/antonio.delcastillozas/hq507d31

More information

Using Operating Experience to Prevent or Mitigate Nuclear Events. What Is, Was and Will Be Available

Using Operating Experience to Prevent or Mitigate Nuclear Events. What Is, Was and Will Be Available Using Operating Experience to Prevent or Mitigate Nuclear Events What Is, Was and Will Be Available Introduction Remember, it is by understanding the lessons learned from past events that we can adequately

More information

Chapter 2. Planning Criteria. Turaj Amraee. Fall 2012 K.N.Toosi University of Technology

Chapter 2. Planning Criteria. Turaj Amraee. Fall 2012 K.N.Toosi University of Technology Chapter 2 Planning Criteria By Turaj Amraee Fall 2012 K.N.Toosi University of Technology Outline 1- Introduction 2- System Adequacy and Security 3- Planning Purposes 4- Planning Standards 5- Reliability

More information

URD Cable Fault Prediction Model

URD Cable Fault Prediction Model 1 URD Cable Fault Prediction Model Christopher Gubala ComEd General Engineer Reliability Analysis 2014 IEEE PES General Meeting Utility Current Practices & Challenges of Predictive Distribution Reliability

More information

SECTION 2 BIDDING DATA

SECTION 2 BIDDING DATA SECTION 2 BIDDING DATA The following specific data for the works to be procured shall complement, amend, or supplement the provisions in Section1, Instructions to Bidders. Whenever there is a conflict,

More information

Vegetation Related Transmission Outage Report

Vegetation Related Transmission Outage Report Vegetation Related Transmission Outage Report Third Quarter 0 5 Peachtree Road NE Suite 00, North Tower Atlanta, GA 0 404-44-50 www.nerc.com The NERC Board of Trustees Compliance Committee has reviewed

More information

Electric Distribution Storm Hardening Initiatives. Paul V. Stergiou Distribution Engineering October 14 th, 2015

Electric Distribution Storm Hardening Initiatives. Paul V. Stergiou Distribution Engineering October 14 th, 2015 Consolidated Edison Company of New York, Inc. Electric Distribution Storm Hardening Initiatives Paul V. Stergiou Distribution Engineering October 14 th, 2015 Energy For New York City And Westchester 3.3

More information

Managing Emergency Generators

Managing Emergency Generators Managing Emergency Generators with nonlinear loads Author akshay thakur Application Engineer Kohler Co. Power Systems Division In this paper we will be focusing on the harmonic distortion that occurs in

More information

Vegetation Related Transmission Outage Report

Vegetation Related Transmission Outage Report Vegetation Related Transmission Outage Report Third 2013 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com Executive Summary The NERC Board of Trustees Compliance

More information

Procedure To Be Adopted When Working on High Voltage Mechanically Switched Capacitors with Damping Network (MSCDN)

Procedure To Be Adopted When Working on High Voltage Mechanically Switched Capacitors with Damping Network (MSCDN) 1. SCOPE This document details the procedures to be adopted when working on High Voltage Mechanically Switched Capacitors with. 2. ISSUE RECORD This is a Reference document. The current version is held

More information

ROLLING RIVER SCHOOL DIVISION POLICY

ROLLING RIVER SCHOOL DIVISION POLICY ROLLING RIVER SCHOOL DIVISION POLICY Transportation Storm EBCD/P The School Division is responsible for the safe transportation of students on school buses. The Division shall exercise due care and caution

More information

BETA Protecting. Low-Voltage Fuse Systems. LV HRC fuse links. 3/36 Siemens ET B1 2008

BETA Protecting. Low-Voltage Fuse Systems. LV HRC fuse links. 3/36 Siemens ET B1 2008 LV HRC fuse links Overview LV HRC fuses are used for installation systems in non-residential, commercial and industrial buildings as well as in switchboards of power supply companies. They therefore protect

More information

JP experience of earthquake, tsunami, and nuclear plant accident

JP experience of earthquake, tsunami, and nuclear plant accident JP experience of earthquake, tsunami, and nuclear plant accident ccnso Members Meeting 21 June 2011 Hiro Hotta What happened (1) Earthquake Friday, March 11, 2011 14:46 JST Earthquake

More information

THIRD GENERATION SYSTEM PROTECTION SCHEME PROJECT FOR ZEYA HYDRO POWER PLANT

THIRD GENERATION SYSTEM PROTECTION SCHEME PROJECT FOR ZEYA HYDRO POWER PLANT THIRD GENERATION SYSTEM PROTECTION SCHEME PROJECT FOR ZEYA HYDRO POWER PLANT Andrey GROBOVOY Power System Emergency Control Laboratory Ltd. - Russia andrey.grobovoy@ieee.org Elena DEDUKHINA Zeya Hydro

More information

Calibration of Temperature Block Calibrators

Calibration of Temperature Block Calibrators European Association of National Metrology Institutes Calibration of Temperature Block Calibrators EURAMET cg-13 Version 2.0 (03/2011) Previously EA-10/13 Calibration Guide EURAMET cg-13 Version 2.0 (03/2011)

More information

NORDIC AND BALTIC GRID DISTURBANCE STATISTICS 2015

NORDIC AND BALTIC GRID DISTURBANCE STATISTICS 2015 NORDIC AND BALTIC GRID DISTURBANCE STATISTICS 23.01.2017 REGIONAL GROUP NORDIC 1 INTRODUCTION... 4 1.1 DESCRIPTION OF THE REPORT... 4 1.2 CONTACT PERSONS... 5 1.3 VOLTAGE LEVELS IN THE NORDIC AND BALTIC

More information

Natural Disaster :.JP s Experience and Preparation

Natural Disaster :.JP s Experience and Preparation Natural Disaster :.JP s Experience and Preparation 14 March. 2018 Hiro Hotta 1 Where s Japan Japan Puerto Rico earthquakes large enough to feel : 2,000-20,000 times a year typhoons disastrous

More information

Periodic Inspection and Testing of Electrical Installations Sample Test ( ) Version 1.3 July 2018

Periodic Inspection and Testing of Electrical Installations Sample Test ( ) Version 1.3 July 2018 Periodic Inspection and Testing of Electrical Installations Sample Test (2391-051) Version 1.3 July 2018 Sample Questions Version and date Change detail Section 1.3 July 2018 Modified questions/answers

More information

Chapter 8: Unsymmetrical Faults

Chapter 8: Unsymmetrical Faults Chapter 8: Unsymmetrical Faults Introduction The sequence circuits and the sequence networks developed in the previous chapter will now be used for finding out fault current during unsymmetrical faults.

More information

1 Introduction. Station Type No. Synoptic/GTS 17 Principal 172 Ordinary 546 Precipitation

1 Introduction. Station Type No. Synoptic/GTS 17 Principal 172 Ordinary 546 Precipitation Use of Automatic Weather Stations in Ethiopia Dula Shanko National Meteorological Agency(NMA), Addis Ababa, Ethiopia Phone: +251116639662, Mob +251911208024 Fax +251116625292, Email: Du_shanko@yahoo.com

More information

YMCA UNIVERSITY OF SCIENCE AND TECHNOLOGY, FARIDABAD SCHEME OF STUDIES & EXAMINATIONS B.TECH 2 nd YEAR (SEMESTER IV) ELECTRICAL ENGINEERING ( )

YMCA UNIVERSITY OF SCIENCE AND TECHNOLOGY, FARIDABAD SCHEME OF STUDIES & EXAMINATIONS B.TECH 2 nd YEAR (SEMESTER IV) ELECTRICAL ENGINEERING ( ) YMCA UNIVERSITY OF SCIENCE AND TECHNOLOGY, FARIDABAD SCHEME OF STUDIES & EXAMINATIONS B.TECH 2 nd YEAR (SEMESTER IV) ELECTRICAL ENGINEERING (2017-18) Sl. Course Course Title L T P Credits CAT code No.

More information

QUESTION BANK ENGINEERS ACADEMY. Power Systems Power System Stability 1

QUESTION BANK ENGINEERS ACADEMY. Power Systems Power System Stability 1 ower ystems ower ystem tability QUETION BANK. A cylindrical rotor generator delivers 0.5 pu power in the steady-state to an infinite bus through a transmission line of reactance 0.5 pu. The generator no-load

More information

Agenda for the meeting to discuss Revision of LTA quantum in respect of Kudgi STPS

Agenda for the meeting to discuss Revision of LTA quantum in respect of Kudgi STPS Agenda for the meeting to discuss Revision of LTA quantum in respect of Kudgi STPS 1. LTA pertaining to Kudgi STPS a. KSEB vide letter dated 25-09-2017 (ANNEXURE A) had stated that with installed capacity

More information

Improving Forecasting Through Accurate Data. Jim Blatchford Sr. Policy Issues Representative. Rizwaan Sahib Telemetry Engineer CAISO.

Improving Forecasting Through Accurate Data. Jim Blatchford Sr. Policy Issues Representative. Rizwaan Sahib Telemetry Engineer CAISO. Improving Forecasting Through Accurate Data By Jim Blatchford Sr. Policy Issues Representative Rizwaan Sahib Telemetry Engineer Abstract Poor meteorological and production data quality can raise significant

More information

Report on El Paso Electric Company Weather-Related Issues in February 2011

Report on El Paso Electric Company Weather-Related Issues in February 2011 2011 Report on El Paso Electric Company Weather-Related Issues in February 2011 Staff of the Public Utility Commission of Texas May 2011 1 Table of Contents I. Executive Summary... 3 II. EPE Preparations

More information

Analysis of surge arresters failures in the installation of broadcasting transmitter

Analysis of surge arresters failures in the installation of broadcasting transmitter Analysis of surge arresters failures in the installation of broadcasting transmitter iktor Milardić, Ivica Pavić, Amir Tokić Abstract--In the operation of the broadcasting transmitter, during a lightning

More information

AM 500A 500 WATT AM 1A 1 KILOWATT AM BROADCAST TRANSMITTERS. October, 1999 IM No

AM 500A 500 WATT AM 1A 1 KILOWATT AM BROADCAST TRANSMITTERS. October, 1999 IM No AM 500A 500 WATT AM 1A 1 KILOWATT AM BROADCAST TRANSMITTERS October, 1999 IM No. 597 1112 EQUIPMENT LOST OR DAMAGED IN TRANSIT. When delivering the equipment to you, the truck driver or carrier s agent

More information

Flood Scenario Worksheet

Flood Scenario Worksheet Flood Scenario Worksheet Scenario adapted from: http://www.epa.gov/watersecurity/tools/trainingcd/simple/source/scenario-8/ssc8-0.pdf Simple Tabletop Exercise, Interdependency Natural Disaster Scenario,

More information

Issued August DATA SHEET. 3VT3 MCCB up to 630 A

Issued August DATA SHEET. 3VT3 MCCB up to 630 A ssued August 9 DATA SHEET VT MCCB up to 6 A Based on Siemens Catalog V 6 8 Circuit breakers Switch disconnectors Technical specifications Specifications Type VT 76-AA6/6/56-AA, VT 76-AA6/6/56-AA Circuit

More information

Reactive Power Solutions

Reactive Power Solutions GE Digital Energy Reactive Power Solutions Effects of Series Capacitors on Line Protection Relaying Design and Settings Presented by: Paul Datka, GE Energy Consulting Luis Polanco, GE Energy Consulting

More information

Commissioning and Testing of AVR and PSS

Commissioning and Testing of AVR and PSS Commissioning and Testing of AVR and PSS Excitation System Upgrade and commissioning challenges Vetti Bala Principal C&I Engineer G E N E S I S E N E R G Y L I M I T E D Contents Asset Testing - AVR AVR

More information

INCLEMENT WEATHER CLOSING CODES

INCLEMENT WEATHER CLOSING CODES INCLEMENT WEATHER CLOSING CODES Code 0 Code 1 Code 2 Code 3 Code 4 Code 5 Code 6 ALL operations are closed and no employees should report to work. Transportation personnel, maintenance personnel, ALL custodial

More information

Power System Stability and Control. Dr. B. Kalyan Kumar, Department of Electrical Engineering, Indian Institute of Technology Madras, Chennai, India

Power System Stability and Control. Dr. B. Kalyan Kumar, Department of Electrical Engineering, Indian Institute of Technology Madras, Chennai, India Power System Stability and Control Dr. B. Kalyan Kumar, Department of Electrical Engineering, Indian Institute of Technology Madras, Chennai, India Contents Chapter 1 Introduction to Power System Stability

More information

Municipal Act, 2001 Loi de 2001 sur les municipalités

Municipal Act, 2001 Loi de 2001 sur les municipalités Municipal Act, 2001 Loi de 2001 sur les municipalités ONTARIO REGULATION 239/02 MINIMUM MAINTENANCE STANDARDS FOR MUNICIPAL HIGHWAYS Consolidation Period: From January 25, 2013 to the e-laws currency date.

More information

NPCIL ISGS. Units Units Capacity in MW Stage-I&II Stage-III Stage- II Stage- II 1&2 3&4 Unit-1. Stage -II

NPCIL ISGS. Units Units Capacity in MW Stage-I&II Stage-III Stage- II Stage- II 1&2 3&4 Unit-1. Stage -II ANNEXURE ( Page 1 of 3) REVISED PERCENTAGE ALLOCATION ( FIRM+UNALLOCATED ) FROM ISGS OF SR w.e.f.26.02.2015 From 18:00 hrs to 22:00 hrs. NTPC NLC NTECL NPCIL ISGS Ramagundam Talcher Simhadri TPS-II @ TPS-

More information

Evaluation of the risk of failure due to switching overvoltages of a phase to phase insulation

Evaluation of the risk of failure due to switching overvoltages of a phase to phase insulation Evaluation of the risk of failure due to switching overvoltages of a phase to phase insulation A. Xemard, J. Michaud, A. Guerrier, I. Uglesic, G. Levacic, M. Mesic Abstract-- The upgrade of an overhead

More information

Cold Weather Preparation

Cold Weather Preparation 0-0.0 January 2012 Country of Origin: United Kingdom Cold Weather Preparation Introduction In addition to the freezing of sprinkler pipes and general water pipes, low temperatures can damage boilers, compressors,

More information

IJSER. 1. Introduction

IJSER. 1. Introduction International Journal of Scientific & Engineering Research, Volume 7, Issue 5, May-2016 1543 Transient Stability Analysis of Generation and Transmission system of a thermal power plant of Pakistan. Izhar

More information

Causal & Frequency Analysis

Causal & Frequency Analysis Causal & Frequency Analysis Arshad Ahmad arshad@utm.my Fishbone Diagram 2 The Cause and Effect (CE) Diagram (Ishikawa Fishbone) Created in 1943 by Professor Kaoru Ishikawa of Tokyo University Used to investigate

More information

Data Bulletin. SEPAM 49RMS Application Note Protection for Motor Applications Class Number SEPAM 49RMS Protection for Motor Applications

Data Bulletin. SEPAM 49RMS Application Note Protection for Motor Applications Class Number SEPAM 49RMS Protection for Motor Applications Data Bulletin 3000DB08 09/008 LaVergne, TN, USA SEPAM 49RMS Application Note Protection for Motor Applications Class Number 3000 SEPAM 49RMS Protection for Motor Applications Introduction Thermal protection

More information

URTDSM Initiative in India and Controlled Islanding using PMU Measurements

URTDSM Initiative in India and Controlled Islanding using PMU Measurements URTDSM Initiative in India and Controlled Islanding using PMU Measurements Akhil Raj Gopal Gajjar Meenal Chougule Narayanan Rajagopal Prashant Navalkar Rajeev Gajbhiye S. A. Soman PowerAnser Labs, IIT

More information

CONTENTS. and 62 of MCDR Flow Diagram for Notice of opening of mine under Rule 20, 2.1 Rule - 18 Beneficiation studies to be carried out 11

CONTENTS. and 62 of MCDR Flow Diagram for Notice of opening of mine under Rule 20, 2.1 Rule - 18 Beneficiation studies to be carried out 11 Part NO. CONTENTS CHAPTER I Flow Diagram for Rule 20, 21, 28, 30, 35, 45, 49, 50, 51 and 62 of MCDR 2017 1.1 Flow Diagram for Notice of opening of mine under Rule 20, PAGE NO. 1 MCDR 2017 1.2 Flow diagram

More information

WEEKLY STATUS OF MATERIAL AS ON IN RESPECT ELECTRIC CENTRAL STORES DIVISION JAMMU.

WEEKLY STATUS OF MATERIAL AS ON IN RESPECT ELECTRIC CENTRAL STORES DIVISION JAMMU. S.No. Description of material Unit Opening balance as on 4-3.2017 Receipt during the week Issue during the week Closing Bal. as on 11/03/2017 1 2 3 4 5 6 7 8 1 Conductor ACSR Squirrel ( 20mm 2 ) Km. 0.000

More information

Southern California Edison Wildfire Mitigation & Grid Resiliency

Southern California Edison Wildfire Mitigation & Grid Resiliency Southern California Edison Wildfire Mitigation & Grid Resiliency California State Legislative Conference Committee on Wildfire Preparedness and Response August 7, 2018 CALIFORNIA S WILDFIRE RISK Year-Round

More information

Operations Report. Tag B. Short, Director South Region Operations. Entergy Regional State Committee (ERSC) February 14, 2018

Operations Report. Tag B. Short, Director South Region Operations. Entergy Regional State Committee (ERSC) February 14, 2018 Operations Report Tag B. Short, Director South Region Operations Entergy Regional State Committee (ERSC) February 14, 2018 1 Winter Operations Highlights South Region Max Gen Event Regional Dispatch Transfer

More information

Superconducting Fault Current Limiters

Superconducting Fault Current Limiters Superconducting Fault Current Limiters First Friday Club 1 st April 2011 Gerhard Novak UK Technical Manager Joachim Bock Managing Director, Nexans Superconductors 1 Smart Grid Solutions 2 Fault current

More information

Table-Top Exercise for Emergency Preparedness Evaluation: Little Anse, Isle Madame

Table-Top Exercise for Emergency Preparedness Evaluation: Little Anse, Isle Madame Table-Top Exercise for Emergency Preparedness Evaluation: Little Anse, Isle Madame Alexander Chung, M.Sc. Candidate C-Change Student Research Associate May 2013 The Community of Little Anse Coastal community

More information

Fault Location in Distribution Feeders with Distributed Generation using Positive Sequence Apparent Impedance

Fault Location in Distribution Feeders with Distributed Generation using Positive Sequence Apparent Impedance Fault Location in Distribution Feeders with Distributed Generation using Positive Sequence Apparent Impedance ARTURO SUMAN BRETAS Federal University of Rio Grande do Sul Department of Electrical Engineering

More information

ECE 585 Power System Stability

ECE 585 Power System Stability Homework 1, Due on January 29 ECE 585 Power System Stability Consider the power system below. The network frequency is 60 Hz. At the pre-fault steady state (a) the power generated by the machine is 400

More information

CHEMICAL MANAGEMENT PLAN

CHEMICAL MANAGEMENT PLAN POLICY EDB CHEMICAL MANAGEMENT PLAN Section I: Annual Review The Chemical Management Plan shall be reviewed at least annually by the Chemical Management Officer and the Chemical Management Committee. Section

More information

How to buy a telescope for your institution

How to buy a telescope for your institution How to buy a telescope for your institution by Dr. Frank Melsheimer DFM Engineering, Inc. 1035 Delaware Avenue, Unit D Longmont, Colorado 80501 phone 303-678-8143 fax 303-772-9411 www.dfmengineering.com

More information