Pursuant to Section 205 of the Federal Power Act ( FPA ) 1 and the Commission s

Size: px
Start display at page:

Download "Pursuant to Section 205 of the Federal Power Act ( FPA ) 1 and the Commission s"

Transcription

1 PJM Interconnection 2750 Monroe Boulevard Norristown, PA Steven R. Pincus Associate General Counsel fax July 31, 2017 Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E., Room 1A Washington, D.C Re: PJM Interconnection, L.L.C., Docket No. ER Solar Resources Meteorological Data and Forced Outage Reporting Revisions to PJM Tariff Pro Forma Service Agreements Dear Ms. Bose: Pursuant to Section 205 of the Federal Power Act ( FPA ) 1 and the Commission s Regulations, 2 PJM Interconnection, L.L.C. ( PJM ) submits for filing proposed revisions to pro forma service agreements in the PJM Open Access Transmission Tariff ( Tariff ) to require solar resource Interconnection Customers ( ICs ) to provide meteorological and forced outage data to PJM for purposes of power production forecasting. PJM proposes to revise the Form of Interconnection Service Agreement ( ISA ), Schedule H; and the Form of Interconnection Construction Services Agreement ( ICSA ), Schedule N, to incorporate requirements for solar resources to provide force outage data and sitespecific meteorological data including: temperature, atmospheric pressure and irradiance. PJM requests an effective date of September 29, 2017, for the attached revised Tariff sections U.S.C. 824d C.F.R. Part 35.

2 I. BACKGROUND On June 22, 2012, the Commission issued the Final Rule on the Integration of Variable Energy Resources. 3 Order No. 764 requires each public utility transmission provider to incorporate provisions into the pro forma Large Generator Interconnection Agreement (LGIA) requiring interconnection customers whose generating facilities are Variable Energy Resources ( VERs ) to provide meteorological and forced outage data to the public utility transmission provider for the purpose of power production forecasting. The Commission did not create an obligation to require VERs to provide meteorological and forced outage data in case where the transmission provider is not engaged in power production forecasting. 4 On November 12, 2013, PJM submitted proposed revisions to amend its pro forma ISA to add the meteorological data and forced outage requirements applicable to wind resources because, at that time, PJM s power production forecasting applied only the wind resources ( November 12 Compliance filing ). PJM acknowledged that if PJM should adopt additional forecasting tools in the future, PJM will develop and file with the Commission Tariff revisions to include in the pro forma service agreements data reporting requirements for solar resources. In the Order Accepting in Part and Rejecting in Part Proposed Tariff Revisions issued on April 17, 2014, 5 the Commission accepted in part and rejected in part PJM s proposed Tariff revisions submitted in the November 12 Compliance Filing. Regarding PJM s proposed meteorological and forced outage data reporting requirements, the Commission conditionally accepted PJM s proposed Tariff revisions. PJM s compliance 3 Integration of Variable Energy Resources, Order No. 764, 139 FERC 61,246 (2012), order on reh g, Order No. 764-A, 141 FERC (2012) (Order No. 764). 4 Order No. 764 P PJM Interconnection, L.L.C., 147 FERC 61,045 (2014) ( April 17 Order ). 2

3 filing submitted on May 19, 2017, addressing the Commission s directives in the April 17 Order was accepted by the Commission by letter order issued on June 30, PJM and its stakeholders recently adopted solar power production forecasting tools in addition to the existing wind power production forecasting tools. As a result, PJM now proposes to amend the PJM Tariff pro forma agreements consistent with the requirements of Order No In Order No. 764 the Commission stated when a transmission provider employs power production forecasting for solar resources, the IC must provide, at a minimum, site-specific meteorological data including: temperature, atmospheric pressure and irradiance; however, the exact specifications of data to be provided by the IC will remain subject to negotiation between the parties. 7 PJM s proposed Tariff revisions comport with these requirements. The proposed Tariff revisions include the stated minimum site-specific meteorological data and outage reporting requirements. In addition, the current pro forma service agreements language applicable to wind resources will also apply to solar resources as follows: The Transmission Provider and Interconnection Customer may mutually agree to any additional meteorological data that are required for the development and deployment of a power production forecast. All requirements for meteorological and forced outage data must be commensurate with the power production forecasting employed by the Transmission Provider. Such additional mutually agreed upon requirements for meteorological and forced outage data re set for below: II. PROPOSED TARIFF REVISION PJM proposes to revise the pro form ISA Schedule H as necessary to add solar resources to wind resources throughout Schedule H and provide the meteorological and forced outage data reporting requirements for solar resource. PJM also proposes parallel Tariff revisions to Attachment P, Form of Interconnection Construction Service 6 See Order No. 764 P Order No. 764 P

4 Agreement ( pro form ICSA ) Schedule N. 8 These changes are necessary to align the addition of solar resource power forecasting and generator outage reporting requirements in the ISA with all the pro form service agreements which address the interconnection requirements for wind and solar generation facilities. PJM also proposes two ministerial changes to pro form ISA, Schedule H (the version applicable for New Service Requests received before May 1, 2015). Two references to special protection system are changed to remedial action scheme. These changes are necessary to align the Tariff terminology with the terminology used by the North American Electric Reliability Corporation ( NERC ). In 2014, NERC retired from its glossary of terms special protection system or SPS and retained remedial action scheme or RAS as the industry-recognized term. III. STAKEHOLDER PROCESS PJM received unanimous stakeholder support for the proposed PJM Tariff revisions described herein. The proposed Tariff revisions were endorsed by PJM s Markets and Reliability Committee ( MRC ) on May 25, 2017, and PJM s Members Committee ( MC ) on June 22, 2017, with no objections or abstentions. IV. EFFECTIVE DATE PJM requests an effective date of September 29, 2017, for the attached PJM Tariff sections, which is more than 60 days after the filing date. V. DOCUMENTS ENCLOSED PJM encloses with this transmittal letter electronic copies of the clean and redline PJM Tariff sections. 8 The revisions proposed herein apply to the pro forma ISA version of Schedule H and the pro forma ICSA version Schedule N applicable to New Service Requests received before May 1, 2015, and the versions applicable for New Service Requests received on or after May 1,

5 VI. CORRESPONDENCE AND COMMUNICATIONS Steven R. Pincus Assistant General Counsel PJM Interconnection, L.L.C Monroe Boulevard Norristown, PA (610) Craig Glazer Vice President, Federal Government Policy PJM Interconnection, L.L.C G Street, N.W, Suite 600 Washington, D.C (202) craig.glazer@pjm.com VII. SERVICE PJM has served a copy of this filing on all PJM Members and on all state utility regulatory commissions in the PJM Region by posting this filing electronically. In accordance with the Commission s regulations, 9 PJM will post a copy of this filing to the FERC filings section of its internet site, located at the following link: with a specific link to the newly-filed document, and will send an on the same date as this filing to all PJM Members and all state utility regulatory commissions in the PJM Region 10 alerting them this filing has been made by PJM and is available by following such link. If the document is not immediately available by using the referenced link, the document will be available through the referenced link within 24 hours of the filing. Also, a copy of this filing will be available on the FERC s elibrary website located at the following link: in accordance with the Commission s regulations and Order No Respectfully submitted, /s/ Steven R. Pincus Steven R. Pincus Craig Glazer PJM Interconnection, L.L.C. See 18C.F.R 35.2(e) and (f)(3). 10 PJM already maintains, updates and regularly uses lists for all PJM Members and affected state commissions. 5

6 Attachment A Revisions to Attachments O and P of the PJM Open Access Transmission Tariff (Marked / Redline Format)

7 {Include the following Schedule H, as applicable, for New Service Requests received before May 1, 2015} SCHEDULE H INTERCONNECTION REQUIREMENTS FOR A WIND GENERATION OR A SOLAR GENERATION FACILITY {Include the appropriate language from the alternatives below} {Include the following language if the Customer Facility is not a wind generation or a solar generation facility} Not Required [OR] {Include the following language when the Customer Facility is a wind generation or a solar generation facility} Schedule H sets forth requirements and provisions specific to the interconnection of a wind generation or a solar generation facility that is greater than 20 MW. All other requirements pertaining to the interconnection of generation facilities above 20 MW set forth in Appendix 2 of this ISA and Part IV of the Tariff continue to apply to wind generation or solar generation facility interconnections. A. Technical Standards Applicable to a Wind Generation or a Solar Generation Facility i. Low Voltage Ride-Through (LVRT) Capability A wind generation or a solar generation facility shall be able to remain online during voltage disturbances up to the time periods and associated voltage levels set forth in the standard below. The Schedule H LVRT standard provides for a transition period standard and a post-transition period standard. Transition Period LVRT Standard The transition period standard applies to wind generation or solar generation facilities subject to Commission Order No. 661 that have either: (i) Interconnection Service Agreements signed and filed with the Commission, filed with the Commission in unexecuted form, or filed with the Commission as non-conforming agreements between January 1, 2006 and December 31, 2006, with a scheduled in-service date no later than December 31, 2007, or (ii) wind generation Page 1

8 turbines subject to a wind turbine or solar generation procurement contract executed prior to December 31, 2005, for delivery through Wind generation or solar generation facilities are required to remain in-service during three-phase faults with normal clearing (which is a time period of approximately 4 9 cycles) and single line to ground faults with delayed clearing, and subsequent post-fault voltage recovery to prefault voltage unless clearing the fault effectively disconnects the generator from the system. The clearing time requirement for a three-phase fault will be specific to the wind generation or solar generation facility substation location, as determined by and documented by the transmission provider. The maximum clearing time the wind generation facility shall be required to withstand for a three-phase fault shall be 9 cycles at a voltage as low as 0.15 p.u., as measured at the high side of the wind generation or solar generation facility step-up transformer (i.e. the transformer that steps the voltage up to the transmission interconnection voltage or GSU ), after which, if the fault remains following the location-specific normal clearing time for three-phase faults, the wind generation or solar generation facility may disconnect from the transmission system. 2. This requirement does not apply to faults that would occur between the wind generator or solar generator terminals and the high side of the GSU or to faults that would result in a voltage lower than 0.15 per unit on the high side of the GSU serving the facility. 3. Wind generation or solar generation facilities may be tripped after the fault period if this action is intended as part of a special protection systemremedial action scheme. 4. Wind generation or solar generation facilities may meet the LVRT requirements of this standard by the performance of the generators or by installing additional equipment (e.g., Static VAr Compensator, etc.) within the wind generation or solar generation facility or by a combination of generator performance and additional equipment. 5. Existing individual generator units that are, or have been, interconnected to the network at the same location at the initial effective date of the Schedule H LVRT standard are exempt from meeting the Schedule H LVRT standard for the remaining life of the existing generation equipment. Existing individual generator units that are replaced are required to meet the Schedule H LVRT standard. Post-transition Period LVRT Standard All wind generation or solar generation facilities subject to Commission Order No. 661 and not covered by the transition period described above must meet the following requirements: 1. Wind generation or solar generation facilities are required to remain in-service during three-phase faults with normal clearing (which is a time period of approximately 4 9 cycles) and single line to ground faults with delayed clearing, and subsequent post-fault voltage recovery to prefault voltage unless clearing the fault effectively disconnects the generator from the system. The clearing time requirement for a three-phase fault will be specific to the wind generation or solar generation facility substation location, as determined by and documented by the Page 2

9 transmission provider. The maximum clearing time the wind generation or solar generation facility shall be required to withstand for a three-phase fault shall be 9 cycles after which, if the fault remains following the location-specific normal clearing time for three-phase faults, the wind generation or solar generation facility may disconnect from the transmission system. A wind generation or solar generation facility shall remain interconnected during such a fault on the transmission system for a voltage level as low as zero volts, as measured at the high voltage side of the wind or solar GSU. 2. This requirement does not apply to faults that would occur between the wind generator or solar generator terminals and the high side of the GSU. 3. Wind generation or solar generation facilities may be tripped after the fault period if this action is intended as part of a special protection systemremedial action scheme. 4. Wind generation or solar generation facilities may meet the LVRT requirements of this standard by the performance of the generators or by installing additional equipment (e.g., Static VAr Compensator) within the wind generation or solar generation facility or by a combination of generator performance and additional equipment. 5. Existing individual wind generator or solar generator units that are, or have been, interconnected to the network at the same location at the initial effective date of the Schedule H LVRT standard are exempt from meeting the Schedule H LVRT Standard for the remaining life of the existing wind generation or solar generation equipment. Existing individual generator units that are replaced are required to meet the Schedule H LVRT Standard. ii. Power Factor Design Criteria (Reactive Power) The power factor requirements for wind generation or solar generation facilities set forth in section 4.7 of Appendix 2 to Attachment O of the Tariff can be met by using, for example, power electronic devices designed to supply this level of reactive capability (taking into account any limitations due to voltage level, real power output, etc.) or fixed and switched capacitors, if agreed to by the Transmission Provider, or a combination of the two. The Interconnection Customer shall not disable power factor equipment while the wind generation or solar generation facility is in operation. Wind generation or solar generation facilities shall also be able to provide sufficient dynamic voltage support in lieu of the power system stabilizer and automatic voltage regulation at the generator excitation system if the System Impact Study shows this to be required for system safety or reliability. iii. Supervisory Control and Data Acquisition (SCADA) Capability The wind generation or solar generation facility shall provide SCADA capability to transmit data and receive instructions from the Transmission Provider to protect system reliability. The Transmission Provider and the wind generation or solar generation facility Interconnection Customer shall determine what SCADA information is essential for the proposed wind generation or solar generation facility, taking into account the size of the facility and its Page 3

10 characteristics, location, and importance in maintaining generation resource adequacy and transmission system reliability in its area. iv. Meteorological Data Reporting Requirement (Applicable to wind generation facilities only) The wind generation facility shall, at a minimum, be required to provide the Transmission Provider with site-specific meteorological data including: Temperature (degrees Fahrenheit) Wind speed (meters/second) Wind direction (degrees from True North) Atmospheric pressure (hectopascals) Forced outage data (wind turbine and MW unavailability) v. Meteorological Data Reporting Requirement (Applicable to solar generation facilities only) The solar generation facility shall, at a minimum, be required to provide the Transmission Provider with site-specific meteorological data including: Temperature (degrees Fahrenheit) Atmospheric pressure (hectopascals) Irradiance Forced outage data The Transmission Provider and Interconnection Customer may mutually agree to any additional meteorological data that are required for the development and deployment of a power production forecast. All requirements for meteorological and forced outage data must be commensurate with the power production forecasting employed by the Transmission Provider. Such additional mutually agreed upon requirements for meteorological and forced outage data are set forth below: [SPECIFICY AGREED UPON METEOROLOGICAL AND FORCED OUTAGE DATA REQUIREMENTS] OR [NOT APPLICABLE FOR THIS ISA] Page 4

11 {Include the following Schedule H, as applicable, for New Service Requests received on or after May 1, 2015} SCHEDULE H INTERCONNECTION REQUIREMENTS FOR ALL WIND, SOLAR AND NON-SYNCHRONOUS GENERATION FACILITIES {Include the appropriate language from the alternatives below} {Include the following language if the Customer Facility is not a wind, solar or non-synchronous generation facility} Not Required [OR] {Include the following language when the Customer Facility is a wind, solar or non-synchronous generation facility} A. Voltage Ride Through Requirements The Customer Facility shall be designed to remain in service (not trip) for voltages and times as specified for the Eastern Interconnection in Attachment 1 of NERC Reliability Standard PRC-024-1, and successor Reliability Standards, for both high and low voltage conditions, irrespective of generator size, subject to the permissive trip exceptions established in PRC (and successor Reliability Standards). B. Frequency Ride Through Requirements The Customer Facility shall be designed to remain in service (not trip) for frequencies and times as specified in Attachment 2 of NERC Reliability Standard PRC-024-1, and successor Reliability Standards, for both high and low frequency condition, irrespective of generator size, subject to the permissive trip exceptions established in PRC (and successor Reliability Standards). C. Supervisory Control and Data Acquisition (SCADA) Capability The wind, solar or non-synchronous generation facility shall provide SCADA capability to transmit data and receive instructions from the Transmission Provider to protect system reliability. The Transmission Provider and the wind, solar or non-synchronous generation facility Interconnection Customer shall determine what SCADA information is essential for the proposed wind, solar or non-synchronous generation facility, taking into account the size of the facility and its characteristics, location, and importance in maintaining generation resource adequacy and transmission system reliability in its area. Page 5

12 D. Meteorological Data Reporting Requirement (Applicable to wind generation facilities only) The wind generation facility shall, at a minimum, be required to provide the Transmission Provider with site-specific meteorological data including: Temperature (degrees Fahrenheit) Wind speed (meters/second) Wind direction (degrees from True North) Atmosphere pressure (hectopascals) Forced outage data (wind turbine and MW unavailability) E. Meteorological Data Reporting Requirement (Applicable to solar generation facilities only) Temperature (degrees Fahrenheit) Atmospheric pressure (hectopascals) Irradiance Forced outage data The Transmission Provider and Interconnection Customer may mutually agree to any additional meteorological data that are required for the development and deployment of a power production forecast. All requirements for meteorological and forced outage data must be commensurate with the power production forecasting employed by the Transmission Provider. Such additional mutually agreed upon requirements for meteorological and forced outage data are set forth below: [SPECIFY AGREED UPON METEOROLOGICAL AND FORCED OUTAGE DATA REQUIREMENTS] [OR] [NOT APPLICABLE FOR THIS ISA] Page 6

13 {Include the following Schedule N, as applicable, for New Service Requests recived before May 1, 2015} SCHEDULE N INTERCONNECTION REQUIREMENTS FOR A WIND GENERATION OR A SOLAR GENERATION FACILITY {Include the appropriate language from the alternatives below} {Include the following language if the Customer Facility is not a wind generation or a solar generation facility} Not Required [OR] {Include the following language when the Customer Facility is a wind generation facility} Schedule N sets forth requirements and provisions specific to the interconnection of a wind generation or a solar generation facility that is greater than 20 MW. All other requirements pertaining to the interconnection of generation facilities above 20 MW set forth in Part IV of the Tariff continue to apply to wind generation or solar generation facility interconnections. A. Technical Standards Applicable to a Wind Generation or a Solar Generation Facility i. Low Voltage Ride-Through (LVRT) Capability A wind generation or a solar generation facility shall be able to remain online during voltage disturbances up to the time periods and associated voltage levels set forth in the standard below. The Schedule N LVRT standard provides for a transition period standard and a post-transition period standard. Transition Period LVRT Standard The transition period standard applies to wind generation or solar generation facilities subject to Commission Order No. 661 that have either: (i) Interconnection Service Agreements signed and filed with the Commission, filed with the Commission in unexecuted form, or filed with the Commission as non-conforming agreements between January 1, 2006 and December 31, 2006, with a scheduled in-service date no later than December 31, 2007, or (ii) wind generation turbines or solar generation subject to a wind turbine or solar generation procurement contract executed prior to December 31, 2005, for delivery through Page 7

14 1. Wind generation or solar generation facilities are required to remain in-service during three-phase faults with normal clearing (which is a time period of approximately 4 9 cycles) and single line to ground faults with delayed clearing, and subsequent post-fault voltage recovery to prefault voltage unless clearing the fault effectively disconnects the generator from the system. The clearing time requirement for a three-phase fault will be specific to the wind generation or solar generation facility substation location, as determined by and documented by the transmission provider. The maximum clearing time the wind generation or solar generation facility shall be required to withstand for a three-phase fault shall be 9 cycles at a voltage as low as 0.15 p.u., as measured at the high side of the wind generation or solar generation facility stepup transformer (i.e. the transformer that steps the voltage up to the transmission interconnection voltage or GSU ), after which, if the fault remains following the location-specific normal clearing time for three-phase faults, the wind generation or solar generation facility may disconnect from the transmission system. 2. This requirement does not apply to faults that would occur between the wind generator or solar generator terminals and the high side of the GSU or to faults that would result in a voltage lower than 0.15 per unit on the high side of the GSU serving the facility. 3. Wind generation or solar generation facilities may be tripped after the fault period if this action is intended as part of a special protection system. 4. Wind generation or solar generation facilities may meet the LVRT requirements of this standard by the performance of the generators or by installing additional equipment (e.g., Static VAr Compensator, etc.) within the wind generation or solar generation facility or by a combination of generator performance and additional equipment. 5. Existing individual generator units that are, or have been, interconnected to the network at the same location at the initial effective date of the Schedule N LVRT standard are exempt from meeting the Schedule N LVRT standard for the remaining life of the existing generation equipment. Existing individual generator units that are replaced are required to meet the Schedule N LVRT standard. Post-transition Period LVRT Standard All wind generation or solar generation facilities subject to Commission Order No. 661 and not covered by the transition period described above must meet the following requirements: 1. Wind generation or solar generation facilities are required to remain in-service during three-phase faults with normal clearing (which is a time period of approximately 4 9 cycles) and single line to ground faults with delayed clearing, and subsequent post-fault voltage recovery to prefault voltage unless clearing the fault effectively disconnects the generator from the system. The clearing time requirement for a three-phase fault will be specific to the wind generation or solar generation facility substation location, as determined by and documented by the transmission provider. The maximum clearing time the wind generation or solar generation facility shall be required to withstand for a three-phase fault shall be 9 cycles after which, if the fault remains following the location-specific normal clearing time for three-phase faults, the Page 8

15 wind generation or solar generation facility may disconnect from the transmission system. A wind generation or solar generation facility shall remain interconnected during such a fault on the transmission system for a voltage level as low as zero volts, as measured at the high voltage side of the wind and solar GSU. 2. This requirement does not apply to faults that would occur between the wind generator or solar generator terminals and the high side of the GSU. 3. Wind generation or solar generation facilities may be tripped after the fault period if this action is intended as part of a special protection systemremedial action scheme. 4. Wind generation or solar generation facilities may meet the LVRT requirements of this standard by the performance of the generators or by installing additional equipment (e.g., Static VAr Compensator) within the wind generation or solar generation facility or by a combination of generator performance and additional equipment. 5. Existing individual generator units that are, or have been, interconnected to the network at the same location at the initial effective date of the Schedule N LVRT standard are exempt from meeting the Schedule N LVRT Standard for the remaining life of the existing generation equipment. Existing individual generator units that are replaced are required to meet the Schedule N LVRT Standard. ii. Power Factor Design Criteria (Reactive Power) The power factor requirements for wind generation or solar generation facilities set forth in section 4.7 of Appendix 2 to Attachment O of the Tariff can be met by using, for example, power electronic devices designed to supply this level of reactive capability (taking into account any limitations due to voltage level, real power output, etc.) or fixed and switched capacitors, if agreed to by the Transmission Provider, or a combination of the two. The Interconnection Customer shall not disable power factor equipment while the wind generation or solar generation facility is in operation. Wind generation facilities shall also be able to provide sufficient dynamic voltage support in lieu of the power system stabilizer and automatic voltage regulation at the generator excitation system if the System Impact Study shows this to be required for system safety or reliability. iii. Supervisory Control and Data Acquisition (SCADA) Capability The wind generation or solar generation facility shall provide SCADA capability to transmit data and receive instructions from the Transmission Provider to protect system reliability. The Transmission Provider and the wind generation or solar generation facility Interconnection Customer shall determine what SCADA information is essential for the proposed wind generation or solar generation facility, taking into account the size of the facility and its characteristics, location, and importance in maintaining generation resource adequacy and transmission system reliability in its area. iv. Meteorological Data Reporting Requirement (Applicable to wind generation facilities only) Page 9

16 The wind generation facility shall, at a minimum, be required to provide the Transmission Provider with site-specific meteorological data including: Temperature (degrees Fahrenheit) Wind speed (meters/second) Wind direction (degrees from True North) Atmospheric pressure (hectopascals) Forced outage data (wind turbine and MW unavailability) v. Meteorological Data Reporting Requirement (Applicable to solar generation facilities only) The solar generation facility shall, at a minimum, be required to provide the Transmission Provider with site-specific meteorological data including: Temperature (degrees Fahrenheit) Atmospheric pressure (hectopascals) Irradiance Forced outage data The Transmission Provider and Interconnection Customer may mutually agree to any additional meteorological data that are required for the development and deployment of a power production forecast. All requirements for meteorological and forced outage data must be commensurate with the power production forecasting employed by the Transmission Provider. Such additional mutually agreed upon requirements for meteorological and forced outage data are set forth below: [SPECIFICY AGREED UPON METEOROLOGICAL AND FORCED OUTAGE DATA REQUIREMENTS] OR [NOT APPLICABLE FOR THIS CSA] Page 10

17 {Include the following Schedule N, as applicable, for New Service Requests received on or after May 1, 2015} SCHEDULE N INTERCONNECTION REQUIREMENTS FOR ALL WIND AND NON-SYNCHRONOUS GENERATION FACILITIES {Include the appropriate language from the alternatives below} {Include the following language if the Customer Facility is not a wind or non-synchronous generation facility} Not Required [OR] {Include the following language when the Customer Facility is a wind or non-synchronous generation facility} A. Voltage Ride Through Requirements The Customer Facility shall be designed to remain in service (not trip) for voltages and times as specified for the Eastern Interconnection in Attachment 1 of NERC Reliability Standard PRC-024-1, and successor Reliability Standards, for both high and low voltage conditions, irrespective of generator size, subject to the permissive trip exceptions established in PRC (and successor Reliability Standards). B. Frequency Ride Through Requirements The Customer Facility shall be designed to remain in service (not trip) for frequencies and times as specified in Attachment 2 of NERC Reliability Standard PRC-024-1, and successor Reliability Standards, for both high and low frequency condition, irrespective of generator size, subject to the permissive trip exceptions established in PRC (and successor Reliability Standards). C. Supervisory Control and Data Acquisition (SCADA) Capability The wind or non-synchronous generation facility shall provide SCADA capability to transmit data and receive instructions from the Transmission Provider to protect system reliability. The Transmission Provider and the wind or non-synchronous generation facility Interconnection Customer shall determine what SCADA information is essential for the proposed wind or non-synchronous generation facility, taking into account the size of the facility and its characteristics, location, and importance in maintaining generation resource adequacy and transmission system reliability in its area. Page 11

18 D. Meteorological Data Reporting Requirement (Applicable to wind generation facilities only) The wind generation facility shall, at a minimum, be required to provide the Transmission Provider with site-specific meteorological data including: Temperature (degrees Fahrenheit) Wind speed (meters/second) Wind direction (degrees from True North) Atmosphere pressure (hectopascals) Forced outage data (wind turbine and MW unavailability) The Transmission Provider and Interconnection Customer may mutually agree to any additional meteorological data that are required for the development and deployment of a power production forecast. All requirements for meteorological and forced outage data must be commensurate with the power production forecasting employed by the Transmission Provider. Such additional mutually agreed upon requirements for meteorological and forced outage data are set forth below: [SPECIFY AGREED UPON METEOROLOGICAL AND FORCED OUTAGE DATA REQUIREMENTS] [OR] [NOT APPLICABLE FOR THIS CSA] Page 12

19 Attachment B Revisions to Attachments O and P of the PJM Open Access Transmission Tariff (Clean Format)

20 {Include the following Schedule H, as applicable, for New Service Requests received before May 1, 2015} SCHEDULE H INTERCONNECTION REQUIREMENTS FOR A WIND GENERATION OR A SOLAR GENERATION FACILITY {Include the appropriate language from the alternatives below} {Include the following language if the Customer Facility is not a wind generation or a solar generation facility} Not Required [OR] {Include the following language when the Customer Facility is a wind generation or a solar generation facility} Schedule H sets forth requirements and provisions specific to the interconnection of a wind generation or a solar generation facility that is greater than 20 MW. All other requirements pertaining to the interconnection of generation facilities above 20 MW set forth in Appendix 2 of this ISA and Part IV of the Tariff continue to apply to wind generation or solar generation facility interconnections. A. Technical Standards Applicable to a Wind Generation or a Solar Generation Facility i. Low Voltage Ride-Through (LVRT) Capability A wind generation or a solar generation facility shall be able to remain online during voltage disturbances up to the time periods and associated voltage levels set forth in the standard below. The Schedule H LVRT standard provides for a transition period standard and a post-transition period standard. Transition Period LVRT Standard The transition period standard applies to wind generation or solar generation facilities subject to Commission Order No. 661 that have either: (i) Interconnection Service Agreements signed and filed with the Commission, filed with the Commission in unexecuted form, or filed with the Commission as non-conforming agreements between January 1, 2006 and December 31, 2006, with a scheduled in-service date no later than December 31, 2007, or (ii) wind generation Page 1

21 turbines subject to a wind turbine or solar generation procurement contract executed prior to December 31, 2005, for delivery through Wind generation or solar generation facilities are required to remain in-service during three-phase faults with normal clearing (which is a time period of approximately 4 9 cycles) and single line to ground faults with delayed clearing, and subsequent post-fault voltage recovery to prefault voltage unless clearing the fault effectively disconnects the generator from the system. The clearing time requirement for a three-phase fault will be specific to the wind generation or solar generation facility substation location, as determined by and documented by the transmission provider. The maximum clearing time the wind generation facility shall be required to withstand for a three-phase fault shall be 9 cycles at a voltage as low as 0.15 p.u., as measured at the high side of the wind generation or solar generation facility step-up transformer (i.e. the transformer that steps the voltage up to the transmission interconnection voltage or GSU ), after which, if the fault remains following the location-specific normal clearing time for three-phase faults, the wind generation or solar generation facility may disconnect from the transmission system. 2. This requirement does not apply to faults that would occur between the wind generator or solar generator terminals and the high side of the GSU or to faults that would result in a voltage lower than 0.15 per unit on the high side of the GSU serving the facility. 3. Wind generation or solar generation facilities may be tripped after the fault period if this action is intended as part of a remedial action scheme. 4. Wind generation or solar generation facilities may meet the LVRT requirements of this standard by the performance of the generators or by installing additional equipment (e.g., Static VAr Compensator, etc.) within the wind generation or solar generation facility or by a combination of generator performance and additional equipment. 5. Existing individual generator units that are, or have been, interconnected to the network at the same location at the initial effective date of the Schedule H LVRT standard are exempt from meeting the Schedule H LVRT standard for the remaining life of the existing generation equipment. Existing individual generator units that are replaced are required to meet the Schedule H LVRT standard. Post-transition Period LVRT Standard All wind generation or solar generation facilities subject to Commission Order No. 661 and not covered by the transition period described above must meet the following requirements: 1. Wind generation or solar generation facilities are required to remain in-service during three-phase faults with normal clearing (which is a time period of approximately 4 9 cycles) and single line to ground faults with delayed clearing, and subsequent post-fault voltage recovery to prefault voltage unless clearing the fault effectively disconnects the generator from the system. The clearing time requirement for a three-phase fault will be specific to the wind generation or solar generation facility substation location, as determined by and documented by the Page 2

22 transmission provider. The maximum clearing time the wind generation or solar generation facility shall be required to withstand for a three-phase fault shall be 9 cycles after which, if the fault remains following the location-specific normal clearing time for three-phase faults, the wind generation or solar generation facility may disconnect from the transmission system. A wind generation or solar generation facility shall remain interconnected during such a fault on the transmission system for a voltage level as low as zero volts, as measured at the high voltage side of the wind or solar GSU. 2. This requirement does not apply to faults that would occur between the wind generator or solar generator terminals and the high side of the GSU. 3. Wind generation or solar generation facilities may be tripped after the fault period if this action is intended as part of a remedial action scheme. 4. Wind generation or solar generation facilities may meet the LVRT requirements of this standard by the performance of the generators or by installing additional equipment (e.g., Static VAr Compensator) within the wind generation or solar generation facility or by a combination of generator performance and additional equipment. 5. Existing individual wind generator or solar generator units that are, or have been, interconnected to the network at the same location at the initial effective date of the Schedule H LVRT standard are exempt from meeting the Schedule H LVRT Standard for the remaining life of the existing wind generation or solar generation equipment. Existing individual generator units that are replaced are required to meet the Schedule H LVRT Standard. ii. Power Factor Design Criteria (Reactive Power) The power factor requirements for wind generation or solar generation facilities set forth in section 4.7 of Appendix 2 to Attachment O of the Tariff can be met by using, for example, power electronic devices designed to supply this level of reactive capability (taking into account any limitations due to voltage level, real power output, etc.) or fixed and switched capacitors, if agreed to by the Transmission Provider, or a combination of the two. The Interconnection Customer shall not disable power factor equipment while the wind generation or solar generation facility is in operation. Wind generation or solar generation facilities shall also be able to provide sufficient dynamic voltage support in lieu of the power system stabilizer and automatic voltage regulation at the generator excitation system if the System Impact Study shows this to be required for system safety or reliability. iii. Supervisory Control and Data Acquisition (SCADA) Capability The wind generation or solar generation facility shall provide SCADA capability to transmit data and receive instructions from the Transmission Provider to protect system reliability. The Transmission Provider and the wind generation or solar generation facility Interconnection Customer shall determine what SCADA information is essential for the proposed wind generation or solar generation facility, taking into account the size of the facility and its Page 3

23 characteristics, location, and importance in maintaining generation resource adequacy and transmission system reliability in its area. iv. Meteorological Data Reporting Requirement (Applicable to wind generation facilities only) The wind generation facility shall, at a minimum, be required to provide the Transmission Provider with site-specific meteorological data including: Temperature (degrees Fahrenheit) Wind speed (meters/second) Wind direction (degrees from True North) Atmospheric pressure (hectopascals) Forced outage data (wind turbine and MW unavailability) v. Meteorological Data Reporting Requirement (Applicable to solar generation facilities only) The solar generation facility shall, at a minimum, be required to provide the Transmission Provider with site-specific meteorological data including: Temperature (degrees Fahrenheit) Atmospheric pressure (hectopascals) Irradiance Forced outage data The Transmission Provider and Interconnection Customer may mutually agree to any additional meteorological data that are required for the development and deployment of a power production forecast. All requirements for meteorological and forced outage data must be commensurate with the power production forecasting employed by the Transmission Provider. Such additional mutually agreed upon requirements for meteorological and forced outage data are set forth below: [SPECIFICY AGREED UPON METEOROLOGICAL AND FORCED OUTAGE DATA REQUIREMENTS] OR [NOT APPLICABLE FOR THIS ISA] Page 4

24 {Include the following Schedule H, as applicable, for New Service Requests received on or after May 1, 2015} SCHEDULE H INTERCONNECTION REQUIREMENTS FOR ALL WIND, SOLAR AND NON-SYNCHRONOUS GENERATION FACILITIES {Include the appropriate language from the alternatives below} {Include the following language if the Customer Facility is not a wind, solar or non-synchronous generation facility} Not Required [OR] {Include the following language when the Customer Facility is a wind, solar or non-synchronous generation facility} A. Voltage Ride Through Requirements The Customer Facility shall be designed to remain in service (not trip) for voltages and times as specified for the Eastern Interconnection in Attachment 1 of NERC Reliability Standard PRC-024-1, and successor Reliability Standards, for both high and low voltage conditions, irrespective of generator size, subject to the permissive trip exceptions established in PRC (and successor Reliability Standards). B. Frequency Ride Through Requirements The Customer Facility shall be designed to remain in service (not trip) for frequencies and times as specified in Attachment 2 of NERC Reliability Standard PRC-024-1, and successor Reliability Standards, for both high and low frequency condition, irrespective of generator size, subject to the permissive trip exceptions established in PRC (and successor Reliability Standards). C. Supervisory Control and Data Acquisition (SCADA) Capability The wind, solar or non-synchronous generation facility shall provide SCADA capability to transmit data and receive instructions from the Transmission Provider to protect system reliability. The Transmission Provider and the wind, solar or non-synchronous generation facility Interconnection Customer shall determine what SCADA information is essential for the proposed wind, solar or non-synchronous generation facility, taking into account the size of the facility and its characteristics, location, and importance in maintaining generation resource adequacy and transmission system reliability in its area. Page 5

25 D. Meteorological Data Reporting Requirement (Applicable to wind generation facilities only) The wind generation facility shall, at a minimum, be required to provide the Transmission Provider with site-specific meteorological data including: Temperature (degrees Fahrenheit) Wind speed (meters/second) Wind direction (degrees from True North) Atmosphere pressure (hectopascals) Forced outage data (wind turbine and MW unavailability) E. Meteorological Data Reporting Requirement (Applicable to solar generation facilities only) Temperature (degrees Fahrenheit) Atmospheric pressure (hectopascals) Irradiance Forced outage data The Transmission Provider and Interconnection Customer may mutually agree to any additional meteorological data that are required for the development and deployment of a power production forecast. All requirements for meteorological and forced outage data must be commensurate with the power production forecasting employed by the Transmission Provider. Such additional mutually agreed upon requirements for meteorological and forced outage data are set forth below: [SPECIFY AGREED UPON METEOROLOGICAL AND FORCED OUTAGE DATA REQUIREMENTS] [OR] [NOT APPLICABLE FOR THIS ISA] Page 6

26 {Include the following Schedule N, as applicable, for New Service Requests recived before May 1, 2015} SCHEDULE N INTERCONNECTION REQUIREMENTS FOR A WIND GENERATION OR A SOLAR GENERATION FACILITY {Include the appropriate language from the alternatives below} {Include the following language if the Customer Facility is not a wind generation or a solar generation facility} Not Required [OR] {Include the following language when the Customer Facility is a wind generation facility} Schedule N sets forth requirements and provisions specific to the interconnection of a wind generation or a solar generation facility that is greater than 20 MW. All other requirements pertaining to the interconnection of generation facilities above 20 MW set forth in Part IV of the Tariff continue to apply to wind generation or solar generation facility interconnections. A. Technical Standards Applicable to a Wind Generation or a Solar Generation Facility i. Low Voltage Ride-Through (LVRT) Capability A wind generation or a solar generation facility shall be able to remain online during voltage disturbances up to the time periods and associated voltage levels set forth in the standard below. The Schedule N LVRT standard provides for a transition period standard and a post-transition period standard. Transition Period LVRT Standard The transition period standard applies to wind generation or solar generation facilities subject to Commission Order No. 661 that have either: (i) Interconnection Service Agreements signed and filed with the Commission, filed with the Commission in unexecuted form, or filed with the Commission as non-conforming agreements between January 1, 2006 and December 31, 2006, with a scheduled in-service date no later than December 31, 2007, or (ii) wind generation turbines or solar generation subject to a wind turbine or solar generation procurement contract executed prior to December 31, 2005, for delivery through Page 7

27 1. Wind generation or solar generation facilities are required to remain in-service during three-phase faults with normal clearing (which is a time period of approximately 4 9 cycles) and single line to ground faults with delayed clearing, and subsequent post-fault voltage recovery to prefault voltage unless clearing the fault effectively disconnects the generator from the system. The clearing time requirement for a three-phase fault will be specific to the wind generation or solar generation facility substation location, as determined by and documented by the transmission provider. The maximum clearing time the wind generation or solar generation facility shall be required to withstand for a three-phase fault shall be 9 cycles at a voltage as low as 0.15 p.u., as measured at the high side of the wind generation or solar generation facility stepup transformer (i.e. the transformer that steps the voltage up to the transmission interconnection voltage or GSU ), after which, if the fault remains following the location-specific normal clearing time for three-phase faults, the wind generation or solar generation facility may disconnect from the transmission system. 2. This requirement does not apply to faults that would occur between the wind generator or solar generator terminals and the high side of the GSU or to faults that would result in a voltage lower than 0.15 per unit on the high side of the GSU serving the facility. 3. Wind generation or solar generation facilities may be tripped after the fault period if this action is intended as part of a special protection system. 4. Wind generation or solar generation facilities may meet the LVRT requirements of this standard by the performance of the generators or by installing additional equipment (e.g., Static VAr Compensator, etc.) within the wind generation or solar generation facility or by a combination of generator performance and additional equipment. 5. Existing individual generator units that are, or have been, interconnected to the network at the same location at the initial effective date of the Schedule N LVRT standard are exempt from meeting the Schedule N LVRT standard for the remaining life of the existing generation equipment. Existing individual generator units that are replaced are required to meet the Schedule N LVRT standard. Post-transition Period LVRT Standard All wind generation or solar generation facilities subject to Commission Order No. 661 and not covered by the transition period described above must meet the following requirements: 1. Wind generation or solar generation facilities are required to remain in-service during three-phase faults with normal clearing (which is a time period of approximately 4 9 cycles) and single line to ground faults with delayed clearing, and subsequent post-fault voltage recovery to prefault voltage unless clearing the fault effectively disconnects the generator from the system. The clearing time requirement for a three-phase fault will be specific to the wind generation or solar generation facility substation location, as determined by and documented by the transmission provider. The maximum clearing time the wind generation or solar generation facility shall be required to withstand for a three-phase fault shall be 9 cycles after which, if the fault remains following the location-specific normal clearing time for three-phase faults, the Page 8

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Interconnection for Wind Energy ) Docket No. RM

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Interconnection for Wind Energy ) Docket No. RM UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Interconnection for Wind Energy ) Docket No. RM05-4-000 REQUEST FOR REHEARING OF THE NORTH AMERICAN ELECTRIC RELIABILITY COUNCIL

More information

Transcontinental Gas Pipe Line Corporation Compliance Filing in Docket No. RP05-369

Transcontinental Gas Pipe Line Corporation Compliance Filing in Docket No. RP05-369 Gas Pipeline Transco 2800 Post Oak Boulevard (77056) P.O. Box 1396 Houston, Texas 77251-1396 713/215-4060 August 29, 2005 Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426

More information

Expedited Filing Draft August 22, 2017

Expedited Filing Draft August 22, 2017 Applicability 1 Section 304.9 applies to: (a) (b) Requirements Expedited Filing Draft August 22, 2017 the legal owner of a wind or solar aggregated generating facility connected to the interconnected electric

More information

Technical Requirements. Version No. 1.0 Effective Date 10/1/2008

Technical Requirements. Version No. 1.0 Effective Date 10/1/2008 PURPOSE This document applies to wind Generators and describes technical standards that such wind Generators must satisfy to be qualified as a Participating Intermittent Resource (PIR) under the CAISO

More information

Derogation Criteria for the Requirements for Generators Network Code

Derogation Criteria for the Requirements for Generators Network Code Derogation Criteria for the Requirements for Generators Network Code Decision Paper Reference: CER/17/084 Date Published: 13/04/2017 Closing Date: 0 Executive Summary Commission Regulation (EU) 2016/631

More information

The North American Electric Reliability Corporation hereby submits Informational Filing of the North American Electric Reliability Corporation.

The North American Electric Reliability Corporation hereby submits Informational Filing of the North American Electric Reliability Corporation. !! January 19, 2016 VIA ELECTRONIC FILING Jim Crone Director, Energy Division Manitoba Innovation, Energy and Mines 1200-155 Carlton Street Winnipeg MB R3C 3H8 Re: North American Electric Reliability Corporation

More information

Wind Rules and Forecasting Project Update Market Issues Working Group 12/14/2007

Wind Rules and Forecasting Project Update Market Issues Working Group 12/14/2007 Wind Rules and Forecasting Project Update Market Issues Working Group 12/14/2007 Background Over the past 3 MIWG meetings, NYISO has discussed a methodology for forecasting wind generation in the NYCA

More information

Re: Report on Yorktown Units I & 2 Operations Pursuant to Order No

Re: Report on Yorktown Units I & 2 Operations Pursuant to Order No a Services. inc Dominion 120 Tredegar Street, Richmond, VA 23219 r Energy Dominion E nergy,com The Honorable James Richard Perry Secretary of the Energy United States Department of Energy 1000 Independence

More information

PSEG Long Island LLC 111 Eighth Avenue, 13th Floor New York, NY 10011

PSEG Long Island LLC 111 Eighth Avenue, 13th Floor New York, NY 10011 PSEG Long Island LLC 111 Eighth Avenue, 13th Floor New York, NY 10011 December 31, 2013 Mr. John D. McMahon Chief Operating Officer Long Island Lighting Company d/b/a/ LIPA 333 Earle Ovington Boulevard,

More information

2018 Annual Review of Availability Assessment Hours

2018 Annual Review of Availability Assessment Hours 2018 Annual Review of Availability Assessment Hours Amber Motley Manager, Short Term Forecasting Clyde Loutan Principal, Renewable Energy Integration Karl Meeusen Senior Advisor, Infrastructure & Regulatory

More information

Re: Report on Yorktown Units 1 & 2 Operations Pursuant to Order No

Re: Report on Yorktown Units 1 & 2 Operations Pursuant to Order No Services, inc. ~ Dominion 120 Tredegar Street, Richmond, VA 23219 ~r Energy Dominion Energy.com The Honorable James Richard Perry Secretary of the Energy United States Department of Energy 1000 Independence

More information

Services, inc. Re: Report on Yorktown Units 1 & 2 Operations Pursuant to Order Nos and

Services, inc. Re: Report on Yorktown Units 1 & 2 Operations Pursuant to Order Nos and Services, inc ~ Dominion 120 Tredegar Street, Richmond, VA 23219 ~ Energy Damn onenergycom The Honorable James Richard Perry Secretary of the Energy United States Department of Energy 1000 Independence

More information

Centralized Forecasting Registration and Communication Requirements for Distribution Connected Variable Generators. IESO Training

Centralized Forecasting Registration and Communication Requirements for Distribution Connected Variable Generators. IESO Training Centralized Forecasting Registration and Communication Requirements for Distribution Connected Variable Generators IESO Training May 2017 Centralized Forecasting - Registration and Communication Requirements

More information

4/26/94 Revised 12/26/96 5/9/99 7/30/01 WSCC UNSCHEDULED FLOW MITIGATION PLAN

4/26/94 Revised 12/26/96 5/9/99 7/30/01 WSCC UNSCHEDULED FLOW MITIGATION PLAN 4/26/94 Revised 12/26/96 5/9/99 7/30/01 WSCC UNSCHEDULED FLOW MITIGATION PLAN WSCC UNSCHEDULED FLOW MITIGATION PLAN TABLE OF CONTENTS SECTION PAGE 1 PARTIES... 1 2 RECITALS...1 3 TERM... 3 4 DEFINITIONS...

More information

SUBPART MULTIYEAR CONTRACTING (Revised December 19, 2006)

SUBPART MULTIYEAR CONTRACTING (Revised December 19, 2006) SUBPART 217.1--MULTIYEAR CONTRACTING (Revised December 19, 2006) 217.103 Definitions. As used in this subpart-- Advance procurement means an exception to the full funding policy that allows acquisition

More information

Transmission and Dispatching Operations Manual

Transmission and Dispatching Operations Manual MANUAL 12 Transmission and Dispatching Operations Manual April 2016 4.2.9 Adverse Operating Conditions NYISO Actions The NYISO may perform the following actions under adverse operating conditions: 1. Notify

More information

SUBJECT: Adjustments to Photovoltaic and Electric Vehicle Forecasts to be Used in Southern California Edison Company's Distribution Planning

SUBJECT: Adjustments to Photovoltaic and Electric Vehicle Forecasts to be Used in Southern California Edison Company's Distribution Planning STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 December 5, 2017 Advice Letter 3670-E Russell G. Worden Director, State Regulatory

More information

Peterborough Distribution Inc Ashburnham Drive, PO Box 4125, Station Main Peterborough ON K9J 6Z5

Peterborough Distribution Inc Ashburnham Drive, PO Box 4125, Station Main Peterborough ON K9J 6Z5 Peterborough Distribution Inc. 1867 Ashburnham Drive, PO Box 4125, Station Main Peterborough ON K9J 6Z5 November 15, 2017 Ontario Energy Board PO Box 2319 27 th Floor, 2300 Yonge St Toronto ON M4P 1E4

More information

Subject: Availability of New and Revised Public Housing Agency (PHA) Five-Year and Annual Plan Templates and Other Forms

Subject: Availability of New and Revised Public Housing Agency (PHA) Five-Year and Annual Plan Templates and Other Forms Special Attention: U.S. Department of Housing and Urban Development Office of Public and Indian Housing Public Housing Agencies (PHA) NOTICE PIH-2015-18 (HA) Public Housing Hub Office Directors Public

More information

GENERATOR INTERCONNECTION APPLICATION

GENERATOR INTERCONNECTION APPLICATION GENERATOR INTERCONNECTION APPLICATION FOR BUY-ALL/SELL-ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 20 KW BUT LESS THAN OR EQUAL TO 1 MW Electric Utility Contact Information Great Lakes Energy

More information

Section 5. TADS Data Reporting Instruction Manual DRAFT Section 5 and Associated Appendices With Proposed Event Type Numbers

Section 5. TADS Data Reporting Instruction Manual DRAFT Section 5 and Associated Appendices With Proposed Event Type Numbers Section 5 TADS Data Reporting Instruction Manual DRAFT Section 5 and Associated Appendices With Proposed Event Type Numbers Rev. 5/10/2010 1 Section 5 Form for Event ID and Event Type Number Data TO s

More information

Transmission and Dispatching Operations Manual

Transmission and Dispatching Operations Manual MANUAL 12 Transmission and Dispatching Operations Manual October 2012 4.2.10 Adverse Operating Conditions NYISO Actions The NYISO may perform the following actions under adverse operating conditions: 1.

More information

June 26, Federal. Commissioners: Re: CP Pursuant to. the. Pursuant to. ordering

June 26, Federal. Commissioners: Re: CP Pursuant to. the. Pursuant to. ordering June 26, 2018 Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Attention: Ms. Kimberly D. Bose, Secretary Re: El Paso Natural Gas Company, L.L.C.; Semi-Annual Activity

More information

BEFORE THE OIL AND GAS CONSERVATION COMMISSION OF THE STATE OF COLORADO

BEFORE THE OIL AND GAS CONSERVATION COMMISSION OF THE STATE OF COLORADO BEFORE THE OIL AND GAS CONSERVATION COMMISSION OF THE STATE OF COLORADO IN THE MATTER OF THE APPLICATION OF ) BLACK HILLS PLATEAU PRODUCTION, LLC ) CAUSE NO. 166 FOR AN ORDER ALLOWING TWO HORIZONTAL )

More information

Colorado PUC E-Filings System

Colorado PUC E-Filings System Page 1 of 10 30-Minute Flex Reserve on the Public Service Company of Colorado System Colorado PUC E-Filings System Prepared by: Xcel Energy Services, Inc. 1800 Larimer St. Denver, Colorado 80202 May 13,

More information

System Impact Assessment Addendum #2 Greenfield & St. Clair Energy Centres

System Impact Assessment Addendum #2 Greenfield & St. Clair Energy Centres IESO_REP_0292 System Impact Assessment Addendum #2 Greenfield & St. lair Energy entres onnection Assessment & Approval Process Issue 3.0 Greenfield Energy entre AA I 2004-167 Applicant: Greenfield Energy

More information

1 Descriptions of Function

1 Descriptions of Function Wide-Area Wind Generation Forecasting 1 Descriptions of Function All prior work (intellectual property of the company or individual) or proprietary (non-publicly available) work should be so noted. 1.1

More information

NUCLEAR REGULATORY COMMISSION [NRC ] Instructions for Recording and Reporting Occupational Radiation Dose Data

NUCLEAR REGULATORY COMMISSION [NRC ] Instructions for Recording and Reporting Occupational Radiation Dose Data This document is scheduled to be published in the Federal Register on 12/08/2016 and available online at https://federalregister.gov/d/2016-29391, and on FDsys.gov [7590-01-P] NUCLEAR REGULATORY COMMISSION

More information

Department of Transportation. National Highway Traffic Safety Administration. [Docket No. NHTSA ; Notice 2]

Department of Transportation. National Highway Traffic Safety Administration. [Docket No. NHTSA ; Notice 2] This document is scheduled to be published in the Federal Register on 04/12/2016 and available online at http://federalregister.gov/a/2016-08362, and on FDsys.gov Department of Transportation National

More information

POLICY ISSUE (INFORMATION)

POLICY ISSUE (INFORMATION) POLICY ISSUE (INFORMATION) August 12, 2011 SECY-11-0112 FOR: FROM: SUBJECT: The Commissioners Michael R. Johnson, Director /RA/ Office of New Reactors STAFF ASSESSMENT OF SELECTED SMALL MODULAR REACTOR

More information

Renewables and the Smart Grid. Trip Doggett President & CEO Electric Reliability Council of Texas

Renewables and the Smart Grid. Trip Doggett President & CEO Electric Reliability Council of Texas Renewables and the Smart Grid Trip Doggett President & CEO Electric Reliability Council of Texas North American Interconnected Grids The ERCOT Region is one of 3 North American grid interconnections. The

More information

DEMAND FORECASTING PROTOCOL

DEMAND FORECASTING PROTOCOL FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 443 DEMAND FORECASTING PROTOCOL FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 444 DEMAND FORECASTING PROTOCOL Table of Contents DFP 1 OBJECTIVES,

More information

El Paso Natural Gas Company, L.L.C.; Semi-Annual Activity Report Washington Ranch Storage Facility Docket Nos. RP72-6, et al.

El Paso Natural Gas Company, L.L.C.; Semi-Annual Activity Report Washington Ranch Storage Facility Docket Nos. RP72-6, et al. January 9, 2017 Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Attention: Ms. Kimberly D. Bose, Secretary Re: El Paso Natural Gas Company, L.L.C.; Semi-Annual Activity

More information

Review of Anemometer Calibration Standards

Review of Anemometer Calibration Standards Review of Anemometer Calibration Standards Rachael V. Coquilla rvcoquilla@otechwind.com Otech Engineering, Inc., Davis, CA Anemometer calibration defines a relationship between the measured signals from

More information

Integrating Wind Resources Into the Transmission Grid

Integrating Wind Resources Into the Transmission Grid Integrating Wind Resources Into the Transmission Grid Gary D. Bachman Wisconsin Public Utility Institute May 26, 2010 Introduction Statement of FERC Chairman Jon Wellinghoff on Efficient Integration of

More information

Chapter 2. Planning Criteria. Turaj Amraee. Fall 2012 K.N.Toosi University of Technology

Chapter 2. Planning Criteria. Turaj Amraee. Fall 2012 K.N.Toosi University of Technology Chapter 2 Planning Criteria By Turaj Amraee Fall 2012 K.N.Toosi University of Technology Outline 1- Introduction 2- System Adequacy and Security 3- Planning Purposes 4- Planning Standards 5- Reliability

More information

El Paso Natural Gas Company, L.L.C.; Semi-Annual Activity Report Washington Ranch Storage Facility Docket Nos. RP72-6, et al., CP79-224, and CP15-516

El Paso Natural Gas Company, L.L.C.; Semi-Annual Activity Report Washington Ranch Storage Facility Docket Nos. RP72-6, et al., CP79-224, and CP15-516 January 8, 2018 Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Attention: Ms. Kimberly D. Bose, Secretary Re: ; Semi-Annual Activity Report Washington Ranch Storage

More information

Commissioning and Testing of AVR and PSS

Commissioning and Testing of AVR and PSS Commissioning and Testing of AVR and PSS Excitation System Upgrade and commissioning challenges Vetti Bala Principal C&I Engineer G E N E S I S E N E R G Y L I M I T E D Contents Asset Testing - AVR AVR

More information

NUCLEAR REGULATORY COMMISSION. [Docket No ; NRC ] Strata Energy, Inc.; Ross Uranium In Situ Recovery Facility; Source and

NUCLEAR REGULATORY COMMISSION. [Docket No ; NRC ] Strata Energy, Inc.; Ross Uranium In Situ Recovery Facility; Source and This document is scheduled to be published in the Federal Register on 01/29/2018 and available online at https://federalregister.gov/d/2018-01522, and on FDsys.gov [7590-01-P] NUCLEAR REGULATORY COMMISSION

More information

Turbines and turbine sets Measurement of emitted airborne noise Engineering/survey method

Turbines and turbine sets Measurement of emitted airborne noise Engineering/survey method INTERNATIONAL STANDARD ISO 10494 Second edition 2018-04 Turbines and turbine sets Measurement of emitted airborne noise Engineering/survey method Turbines et groupes de turbines Mesurage du bruit aérien

More information

Operations Report. Tag B. Short, Director South Region Operations. Entergy Regional State Committee (ERSC) February 14, 2018

Operations Report. Tag B. Short, Director South Region Operations. Entergy Regional State Committee (ERSC) February 14, 2018 Operations Report Tag B. Short, Director South Region Operations Entergy Regional State Committee (ERSC) February 14, 2018 1 Winter Operations Highlights South Region Max Gen Event Regional Dispatch Transfer

More information

REVISED UPDATED PREPARED DIRECT SAFETY ENHANCEMENT COST ALLOCATION TESTIMONY OF GARY LENART SAN DIEGO GAS & ELECTRIC COMPANY AND

REVISED UPDATED PREPARED DIRECT SAFETY ENHANCEMENT COST ALLOCATION TESTIMONY OF GARY LENART SAN DIEGO GAS & ELECTRIC COMPANY AND Application No: Exhibit No.: Witness: A.--00 ) In the Matter of the Application of San Diego Gas & ) Electric Company (U 0 G) and Southern California ) Gas Company (U 0 G) for Authority to Revise ) Their

More information

International Workshop on Wind Energy Development Cairo, Egypt. ERCOT Wind Experience

International Workshop on Wind Energy Development Cairo, Egypt. ERCOT Wind Experience International Workshop on Wind Energy Development Cairo, Egypt ERCOT Wind Experience March 22, 21 Joel Mickey Direcr of Grid Operations Electric Reliability Council of Texas jmickey@ercot.com ERCOT 2 2

More information

NOVALYNX CORPORATION MODEL 110-WS-16BP BAROMETRIC PRESSURE SENSOR INSTRUCTION MANUAL

NOVALYNX CORPORATION MODEL 110-WS-16BP BAROMETRIC PRESSURE SENSOR INSTRUCTION MANUAL NOVALYNX CORPORATION MODEL 110-WS-16BP BAROMETRIC PRESSURE SENSOR INSTRUCTION MANUAL REVISION DATE: OCT 2005 Receiving and Unpacking Carefully unpack all components and compare to the packing list. Notify

More information

Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian Institute of Technology, Kharagpur

Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian Institute of Technology, Kharagpur Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian Institute of Technology, Kharagpur Lecture - 9 Transmission Line Steady State Operation Welcome to lesson 9, in Power

More information

MEMORANDUM OF UNDERSTANDING. between the ASSOCIATION OF AMERICAN STATE GEOLOGISTS. and the U.S. DEPARTMENT OF THE INTERIOR OFFICE OF SURFACE MINING

MEMORANDUM OF UNDERSTANDING. between the ASSOCIATION OF AMERICAN STATE GEOLOGISTS. and the U.S. DEPARTMENT OF THE INTERIOR OFFICE OF SURFACE MINING MEMORANDUM OF UNDERSTANDING between the ASSOCIATION OF AMERICAN STATE GEOLOGISTS and the U.S. DEPARTMENT OF THE INTERIOR OFFICE OF SURFACE MINING MEMORANDUM OF UNDERSTANDING between the ASSOCIATION OF

More information

RESULTS OF ON-GRID OPERATION OF SUPERCONDUCTOR DYNAMIC SYNCHRONOUS CONDENSER

RESULTS OF ON-GRID OPERATION OF SUPERCONDUCTOR DYNAMIC SYNCHRONOUS CONDENSER 1 RESULTS OF ON-GRID OPERATION OF SUPERCONDUCTOR DYNAMIC SYNCHRONOUS CONDENSER Dr. Swarn S. Kalsi, David Madura, and Michael Ross American Superconductor Corporation (USA) Abstract: A high-temperature

More information

The following procedures describe how application managers will review chemical additives during the permit application review phase.

The following procedures describe how application managers will review chemical additives during the permit application review phase. Bureau of Point and Non-Point Source Management Standard Operating Procedure (SOP) 1 for Clean Water Program Chemical Additives SOP No. BPNPSM-PMT-030 Final, November 9, 2012 Version 1.4 This SOP describes

More information

C L I E N T A LERT. Ha r m o n i z i n g Ha z a rd Co m m u n i c a t i o n : OSHA Pr o p o s e s t o. I. Ba c k g r o u n d

C L I E N T A LERT. Ha r m o n i z i n g Ha z a rd Co m m u n i c a t i o n : OSHA Pr o p o s e s t o. I. Ba c k g r o u n d C L I E N T A LERT October 16, 2009 Authors: Mark N. Duvall 1350 I Street, N.W. Suite 700 Washington, DC 20005 (202) 789-6090 mduvall@bdlaw.com Jayni Lanham 201 N. Charles Street Suite 2210 Baltimore,

More information

Internal Audit Report

Internal Audit Report Internal Audit Report Right of Way Mapping TxDOT Internal Audit Division Objective To determine the efficiency and effectiveness of district mapping procedures. Opinion Based on the audit scope areas reviewed,

More information

Module 6 : Preventive, Emergency and Restorative Control. Lecture 27 : Normal and Alert State in a Power System. Objectives

Module 6 : Preventive, Emergency and Restorative Control. Lecture 27 : Normal and Alert State in a Power System. Objectives Module 6 : Preventive, Emergency and Restorative Control Lecture 27 : Normal and Alert State in a Power System Objectives In this lecture you will learn the following Different states in a power system

More information

f<~~ ~ Gulf Power April16, 2018

f<~~ ~ Gulf Power April16, 2018 ~ Gulf Power Rhonda J. Alexander One Energy Place I 1anage' Pensacola. ~l 32520-0780 Regulatory Fooecastmg & Procong 850 444 67,13 tel 850.:144 6026 fax r jale>xad @~out her nro com April16, 2018 Ms. Carlotta

More information

Establishment of Space Weather Information Service

Establishment of Space Weather Information Service Establishment of Space Weather Information Service For International Air Navigation Raul Romero Technical Officer MET ICAO Headquarters, Montreal NAM/CAR/SAM Seminar on Space Weather and ICAO Weather Information

More information

Outage Coordination and Business Practices

Outage Coordination and Business Practices Outage Coordination and Business Practices 1 2007 Objectives What drove the need for developing a planning/coordination process. Why outage planning/coordination is crucial and important. Determining what

More information

Weather Company Energy and Power Products

Weather Company Energy and Power Products IBM Terms of Use SaaS Specific Offering Terms Weather Company Energy and Power Products The Terms of Use ( ToU ) is composed of this IBM Terms of Use - SaaS Specific Offering Terms ( SaaS Specific Offering

More information

Responses to Questions Related to the October 10, 2012, Partners in Business Meeting

Responses to Questions Related to the October 10, 2012, Partners in Business Meeting Responses to Questions Related to the October 10, 2012, Partners in Business Meeting Question 1: Regarding the update on the ITC-Entergy transaction, what is the expected impact to ITC Midwest rates and

More information

RESOLUTION NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF SUPERVISORS OF THE CORKSCREW FARMS COMMUNITY DEVELOPMENT DISTRICT:

RESOLUTION NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF SUPERVISORS OF THE CORKSCREW FARMS COMMUNITY DEVELOPMENT DISTRICT: RESOLUTION 2017-08 A RESOLUTION OF THE BOARD OF SUPERVISORS OF THE CORKSCREW FARMS COMMUNITY DEVELOPMENT DISTRICT APPROVING PROPOSED BUDGET(S) FOR FISCAL YEAR 2017/2018 AND SETTING A PUBLIC HEARING THEREON

More information

NUCLEAR REGULATORY COMMISSION. 10 CFR Chapter 1 [NRC ] Clarification on Endorsement of Nuclear Energy Institute Guidance in Designing

NUCLEAR REGULATORY COMMISSION. 10 CFR Chapter 1 [NRC ] Clarification on Endorsement of Nuclear Energy Institute Guidance in Designing This document is scheduled to be published in the Federal Register on 06/25/2018 and available online at https://federalregister.gov/d/2018-13570, and on FDsys.gov [7590-01-P] NUCLEAR REGULATORY COMMISSION

More information

File OF-Surv-Inc April 2014

File OF-Surv-Inc April 2014 File OF-Surv-Inc-2014-33 01 14 April 2014 Mr. Russell K. Girling, President and Chief Executive Officer TransCanada Pipes Limited 450 1 st Street SW Calgary, AB T2P 5H1 Facsimile 403-920-2200 Dear Mr.

More information

Standard Practice for Calculating Formulation Physical Constants of Paints and Coatings 1

Standard Practice for Calculating Formulation Physical Constants of Paints and Coatings 1 Designation: D 5201 05 Standard Practice for Calculating Formulation Physical Constants of Paints and Coatings 1 This standard is issued under the fixed designation D 5201; the number immediately following

More information

COUNTY OF SONOMA PERMIT AND RESOURCE MANAGEMENT DEPARTMENT 2550 Ventura Avenue, Santa Rosa, CA (707) FAX (707)

COUNTY OF SONOMA PERMIT AND RESOURCE MANAGEMENT DEPARTMENT 2550 Ventura Avenue, Santa Rosa, CA (707) FAX (707) COUNTY OF SONOMA PERMIT AND RESOURCE MANAGEMENT DEPARTMENT 2550 Ventura Avenue, Santa Rosa, CA 95403 (707) 565-1900 FAX (707) 565-1103 DATE : TO: FROM: SUBJECT: July 21, 2009 at 2:30 p.m. Board of Supervisors

More information

CAISO Participating Intermittent Resource Program for Wind Generation

CAISO Participating Intermittent Resource Program for Wind Generation CAISO Participating Intermittent Resource Program for Wind Generation Jim Blatchford CAISO Account Manager Agenda CAISO Market Concepts Wind Availability in California How State Supports Intermittent Resources

More information

MUNICIPALITY OF ANCHORAGE PUBLIC TRANSPORTATION DEPARTMENT AnchorRIDES TRANSPORTATION SYSTEM

MUNICIPALITY OF ANCHORAGE PUBLIC TRANSPORTATION DEPARTMENT AnchorRIDES TRANSPORTATION SYSTEM Purpose: The Public Transportation Department and contracted provider will provide safe transportation for AnchorRIDES customers and employees during severe weather or emergency conditions. AnchorRIDES

More information

Report on El Paso Electric Company Weather-Related Issues in February 2011

Report on El Paso Electric Company Weather-Related Issues in February 2011 2011 Report on El Paso Electric Company Weather-Related Issues in February 2011 Staff of the Public Utility Commission of Texas May 2011 1 Table of Contents I. Executive Summary... 3 II. EPE Preparations

More information

Standard Practices for Air Speed Calibration Testing

Standard Practices for Air Speed Calibration Testing Standard Practices for Air Speed Calibration Testing Rachael V. Coquilla Bryza Wind Lab, Fairfield, California Air speed calibration is a test process where the output from a wind measuring instrument

More information

Dark Sky Initiative Draft Terms of Reference

Dark Sky Initiative Draft Terms of Reference Dark Sky Initiative Draft Terms of Reference July 2008 Table of Contents 1.0 Introduction 2 2.0 Initiative intent 2-3 3.0 Initiative goals 3 4.0 Legislation 3 5.0 Municipal Development Plan 3 6.0 Land

More information

Orbital Debris Mitigation

Orbital Debris Mitigation Orbital Debris Mitigation R. L. Kelley 1, D. R. Jarkey 2, G. Stansbery 3 1. Jacobs, NASA Johnson Space Center, Houston, TX 77058, USA 2. HX5 - Jacobs JETS Contract, NASA Johnson Space Center, Houston,

More information

METEOROLOGY PANEL (METP) WORKING GROUP- METEOROLOGICAL OPERATION GROUP (MOG) FIRST MEETING

METEOROLOGY PANEL (METP) WORKING GROUP- METEOROLOGICAL OPERATION GROUP (MOG) FIRST MEETING 8 28/7/15 METEOROLOGY PANEL (METP) WORKING GROUP- METEOROLOGICAL OPERATION GROUP (MOG) FIRST MEETING Gatwick, United Kingdom, 08 to 11 September 2015 Agenda Item 3: Matters relating to SADIS 3.3: Operations

More information

INTERNATIONAL STANDARD

INTERNATIONAL STANDARD INTERNATIONAL STANDARD ISO 8426 Second edition 2008-02-01 Hydraulic fluid power Positive displacement pumps and motors Determination of derived capacity Transmissions hydrauliques Pompes et moteurs volumétriques

More information

University of Tennessee Safety Procedure

University of Tennessee Safety Procedure University of Tennessee Safety Procedure Program Subject: Chemicals Requiring Review Prior to Use Procedure Review/Revised: 12/15/08 Affected Area/Department: Laboratories at the University Date Effective:

More information

Director, Operations Services, Met-Ed

Director, Operations Services, Met-Ed Director, Operations Services, Met-Ed Pennsylvania House Republican Policy Committee Hearing on Storm Response Tobyhanna Township Municipal Building Pocono Pines, Pa. August 9, 2018 Planning and Forecast

More information

Weather Company Energy and Power Products

Weather Company Energy and Power Products Service Weather Company Energy and Power Products This Service (SD) describes the Cloud Service IBM provides to Client. Client means the company and its authorized users and recipients of the Cloud Service.

More information

Ultra-Small Footprint N-Channel FemtoFET MOSFET Test EVM

Ultra-Small Footprint N-Channel FemtoFET MOSFET Test EVM User's Guide SLPU007 December 07 Ultra-Small Footprint N-Channel FemtoFET MOSFET Test EVM Contents Introduction... Description... Electrical Performance Specifications... 4 Schematic... 4 Test Setup....

More information

Appendix U. Communication with Shabogamo M.E. ALDERON IRON ORE CORP.

Appendix U. Communication with Shabogamo M.E. ALDERON IRON ORE CORP. ALDERON IRON ORE CORP. AMENDMENT TO THE ENVIRONMENTAL IMPACT STATEMENT VOLUME 3 APPENDICES INFORMATION REQUEST RESPONSES Appendix U Communication with Shabogamo M.E. VIA EMAIL October 31,2012 Dr. Rehan

More information

The Outer Space Treaty of 1967 Preamble

The Outer Space Treaty of 1967 Preamble 0 0 The Outer Space Treaty of Preamble Treaty on principles governing the activities of states in the exploration and use of outer space, including the moon and other celestial bodies. Opened for signature

More information

TC7WB66CFK,TC7WB66CL8X TC7WB67CFK,TC7WB67CL8X

TC7WB66CFK,TC7WB66CL8X TC7WB67CFK,TC7WB67CL8X CMOS Digital Integrated Circuits Silicon Monolithic TC7WB66CFK,TC7WB66CL8X TC7WB67CFK,TC7WB67CL8X 1. Functional Description Dual SPST Bus Switch 2. General TC7WB66CFK/L8X,TC7WB67CFK/L8X The TC7WB66CFK/L8X

More information

MUNICIPALITY OF ANCHORAGE PUBLIC TRANSPORTATION DEPARTMENT AnchorRIDES PARATRANSIT SYSTEM

MUNICIPALITY OF ANCHORAGE PUBLIC TRANSPORTATION DEPARTMENT AnchorRIDES PARATRANSIT SYSTEM Purpose: The Public Transportation Department (PTD) and AnchorRIDES paratransit contractor will provide transportation in as safe a manner as effectively possible. Paratransit vehicles primarily operate

More information

CECOER. Renewable Energy Control Center. How technologies have boosted remote operations. Agder Energi-konferansen

CECOER. Renewable Energy Control Center. How technologies have boosted remote operations. Agder Energi-konferansen CECOER Renewable Energy Control Center How technologies have boosted remote operations Agder Energi-konferansen 2018 30.-31. mai, Kristiansand GLOBAL LEADER IN INFRASTRUCTURE, WATER, SERVICES AND RENEWABLE

More information

UNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C FORM 8-K

UNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C FORM 8-K 9/3/2014 8-K 081814 8-K 1 a8-k081814.htm 8-K UNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C. 20549 FORM 8-K CURRENT REPORT Pursuant to Section 13 or 15(d) of the Securities Exchange Act

More information

Procedure To Be Adopted When Working on High Voltage Mechanically Switched Capacitors with Damping Network (MSCDN)

Procedure To Be Adopted When Working on High Voltage Mechanically Switched Capacitors with Damping Network (MSCDN) 1. SCOPE This document details the procedures to be adopted when working on High Voltage Mechanically Switched Capacitors with. 2. ISSUE RECORD This is a Reference document. The current version is held

More information

REGULATORY GUIDE 1.54 (Draft was issued as DG-1076) SERVICE LEVEL I, II, AND III PROTECTIVE COATINGS APPLIED TO NUCLEAR POWER PLANTS

REGULATORY GUIDE 1.54 (Draft was issued as DG-1076) SERVICE LEVEL I, II, AND III PROTECTIVE COATINGS APPLIED TO NUCLEAR POWER PLANTS U.S. NUCLEAR REGULATORY COMMISSION Revision 1 July 2000 REGULATORY GUIDE OFFICE OF NUCLEAR REGULATORY RESEARCH REGULATORY GUIDE 1.54 (Draft was issued as DG-1076) SERVICE LEVEL I, II, AND III PROTECTIVE

More information

Temporary College Closure Due to Inclement Weather or Other Adverse Conditions.

Temporary College Closure Due to Inclement Weather or Other Adverse Conditions. OTHER TOPICS Index No. X-1 PROCEDURES MEMORANDUM TO: FROM: SUBJECT: MCC Students and Staff Office of the President Temporary College Closure Due to Inclement Weather or Other Adverse Conditions. DATE:

More information

Advisory Circular. U.S. Department of Transportation Federal Aviation Administration

Advisory Circular. U.S. Department of Transportation Federal Aviation Administration U.S. Department of Transportation Federal Aviation Administration Subject: Use of Liquid Water Equivalent System to Determine Holdover Times or Check Times for Anti-Icing Fluids Advisory Circular Date:

More information

After publication, this Indian Standard will supersede the following Indian Standards:

After publication, this Indian Standard will supersede the following Indian Standards: For Comments Only Doc: PGD 26(1110)W Draft Indian Standard SPECIFICATION FOR NON-AUTOMATIC WEIGHING INSTRUMENTS PART 1 TERMINOLOGY AND DEFINITIONS ICS No. 01.040.17; 17.100 Not to be reproduced without

More information

Boundary Expansion of Thunder Bay National Marine Sanctuary; Correction and Expansion of Fagatele Bay National Marine

Boundary Expansion of Thunder Bay National Marine Sanctuary; Correction and Expansion of Fagatele Bay National Marine This document is scheduled to be published in the Federal Register on 12/23/2015 and available online at http://federalregister.gov/a/2015-32265, and on FDsys.gov Billing Code 3510-NK-P DEPARTMENT OF COMMERCE

More information

Exhibit A Proposed Order

Exhibit A Proposed Order Case 15-11755-CSS Doc 857-2 Filed 09/13/16 Page 1 of 94 Exhibit A Proposed Order DOCS_DE:209531.1 88601/001 Case 15-11755-CSS Doc 857-2 Filed 09/13/16 Page 2 of 94 UNITED STATES BANKRUPTCY COURT DISTRICT

More information

ECMA Measurement of airborne noise emitted and structure-borne vibration induced by small air-moving devices Part 1: Airborne noise measurement

ECMA Measurement of airborne noise emitted and structure-borne vibration induced by small air-moving devices Part 1: Airborne noise measurement ECMA-275-1 4 th Edition / December 2017 Measurement of airborne noise emitted and structure-borne vibration induced by small air-moving devices Part 1: Airborne noise measurement Reference number ECMA-123:2009

More information

DE PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE

DE PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE DE 05-142 PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE Petition for License to Construct and Maintain Electric Lines Over and Across the Public Waters of the Nashua River in the City of Nashua, New Hampshire

More information

Department of Energy OffIce of Worker Protection Programs and Hazards Management Radiological Control Technical Position RCTP

Department of Energy OffIce of Worker Protection Programs and Hazards Management Radiological Control Technical Position RCTP OffIce of Worker Protection Programs and Hazards Management Issue: The occupational radiation protection regulations established by the (DOE) and Nuclear Regulatory Commission (NRC) are similar in many

More information

August 12, Docket OSHA ; Comments on Review of Process Safety Management (PSM) Standard Hydrochloric and Hydrofluoric Acids

August 12, Docket OSHA ; Comments on Review of Process Safety Management (PSM) Standard Hydrochloric and Hydrofluoric Acids K E L L E Y D R Y E & W AR R E N LLP A LI MIT E D LIA BI LIT Y P ART N ER SHI P N E W Y O R K, NY L O S A N G E L E S, CA C H I C A G O, IL S T A M F O R D, CT P A R S I P P A N Y, NJ WASHINGTON HARBOUR,

More information

Power System Security. S. Chakrabarti

Power System Security. S. Chakrabarti Power System Security S. Chakrabarti Outline Introduction Major components of security assessment On-line security assessment Tools for contingency analysis DC power flow Linear sensitivity factors Line

More information

Health, Safety, Security and Environment

Health, Safety, Security and Environment Document owner and change code Document Owner Aaron Perronne Title HSSE Manager Mark X Change Code Description X N/A First Issue A Typographical/Grammatical correction; formatting change; text clarification-no

More information

PUB NLH 185 Island Interconnected System Supply Issues and Power Outages Page 1 of 9

PUB NLH 185 Island Interconnected System Supply Issues and Power Outages Page 1 of 9 PUB NLH 1 Page 1 of 1 Q. Provide Hydro s list of outage cause codes and indicate how troublemen are managed and trained to properly use the codes. Explain the method used to report outage causes. A. Hydro

More information

ISO INTERNATIONAL STANDARD. Geographic information Metadata Part 2: Extensions for imagery and gridded data

ISO INTERNATIONAL STANDARD. Geographic information Metadata Part 2: Extensions for imagery and gridded data INTERNATIONAL STANDARD ISO 19115-2 First edition 2009-02-15 Geographic information Metadata Part 2: Extensions for imagery and gridded data Information géographique Métadonnées Partie 2: Extensions pour

More information

Minnesota Public Utilities Commission Staff Briefing Papers

Minnesota Public Utilities Commission Staff Briefing Papers Minnesota Public Utilities Commission Staff Briefing Papers Meeting Date: March 7, 2006 Agenda Item # *10 Company: Docket Nos. Minnesota Power Northwestern Wisconsin Electric Company Interstate Power and

More information

City of Brainerd, Minnesota Snowplowing Policy

City of Brainerd, Minnesota Snowplowing Policy City of Brainerd, Minnesota Snowplowing Policy 1. Introduction The city of Brainerd, Minnesota, finds that it is in the best interest of the residents of the city to assume basic responsibility for control

More information

Status of implementation of the INSPIRE Directive 2016 Country Fiches. COUNTRY FICHE Croatia

Status of implementation of the INSPIRE Directive 2016 Country Fiches. COUNTRY FICHE Croatia Status of implementation of the INSPIRE Directive 2016 Country Fiches COUNTRY FICHE Croatia Introduction... 1 1. State of Play... 2 1.1 Coordination... 2 1.2 Functioning and coordination of the infrastructure...

More information

HAZARD COMMUNICATION PROGRAM

HAZARD COMMUNICATION PROGRAM HAZARD COMMUNICATION PROGRAM UNIVERSITY RISK MANAGEMENT Occupational Safety and Health Programs 19 Hagood Avenue, Suite 908 Charleston SC 29425 843-792-3604 Revised: January, 2015 TABLE OF CONTENTS Safety

More information

MICROCIRCUITS, DIGITAL, TTL, FLIP-FLOPS, MONOLITHIC SILICON. Inactive for new design after 7 September 1995

MICROCIRCUITS, DIGITAL, TTL, FLIP-FLOPS, MONOLITHIC SILICON. Inactive for new design after 7 September 1995 MILITARY SPECIFICATION INCH-POUND MIL-M-38510/2G 8 February 2005 SUPERSEDING MIL-M-38510/2E 24 December 1974 MIL-M-0038510/2F (USAF) 24 OCTOBER 1975 MICROCIRCUITS, DIGITAL, TTL, FLIP-FLOPS, MONOLITHIC

More information

Role of Synchronized Measurements In Operation of Smart Grids

Role of Synchronized Measurements In Operation of Smart Grids Role of Synchronized Measurements In Operation of Smart Grids Ali Abur Electrical and Computer Engineering Department Northeastern University Boston, Massachusetts Boston University CISE Seminar November

More information