6.4 Sensitivity Tests

Size: px
Start display at page:

Download "6.4 Sensitivity Tests"

Transcription

1 6.4 Sensitivity Tests Sensitivity of Floodplain Inundation to Width of Dry Culvert The preliminary design for the Expressway based on consideration of possible future climate effects to 2090 assumed a 40m wide dry culvert through the Expressway embankment to provide continuity for the secondary flow path along the floodplain, parallel with and to the north of the right stopbank system protecting Ōtaki Township. This included the definition of dimensions and levels for the secondary flood containment bund to prevent the spread northwards of stopbank overtopping flows into the Mangapouri Stream. A sensitivity test was carried out to check the effect on flood levels within the flood ponding area formed by the secondary flood containment bund of increasing the width of the proposed dry culvert through the Expressway embankment. The culvert width was increased from 40m to 50m. Figure 6-18 shows a graph of predicted flood levels along the alignment of the proposed secondary flood containment bund for floods of varying magnitudes overtopping the Chrystall s Bend extended stopbank Level (m MSL) Offset (m) 0.2% AEP - 40m wide culvert 0.2% AEP + CC m wide culvert 0.2% AEP + CC m wide culvert 0.2% AEP + CC m wide culvert Breach Scenario - 0.2% AEP + CC m wide culvert Ground level Figure 6-18 Predicted peak flood level profiles along alignment of proposed secondary flood containment bund on Ōtaki River floodplain for floods overtopping Chrystall s Bend stopbank. Status Issue 1 Page 78 September 2013

2 For the 0.2% AEP +CC 2130 flood (average climate change scenario), the peak flood in the containment bund area with a 50m wide dry culvert is only marginally (0.05m) lower than with a 40m wide dry culvert. For a flood of this magnitude, operation of the overflow weir on the Expressway embankment therefore is clearly the predominant control on flood levels in the containment bund basin. Figure 6-18 also indicates that the nominated crest level of the secondary containment bund of 16.05m (MSL Wellington (1953) datum) from Smith and Webby (2013d) would need to be raised slightly by about 0.3m. The vertical profile of the overflow weir on the Expressway embankment would also need to be modified slightly Sensitivity of Floodplain Inundation to Floodplain Surface roughness Peak flood depths across the Ōtaki River floodplain resulting from overtopping of the Chrystall s Bend extended stopbank are affected by the surface roughness of the floodplain. This is represented in the MIKEFLOOD model by means of Manning s n surface roughness values. Table 6-7 summarises the standard set of Manning s n values assumed for the model simulations of overland flow resulting from stopbank overtopping. It was considered appropriate to consider the sensitivity of the peak flood depths across the floodplain for increased values of surface roughness for each roughness category. Table 6-7 also summarises these increased values. Table 6-7 Manning's n surface roughness values for Ōtaki River floodplain. Manning s n Roughness Value Surface Roughness Type Standard Set Increased Set Areas covered by buildings Vegetated areas Grass-covered areas Figure 6-19 shows a peak flood depth difference map between the two model simulations with the different sets of floodplain roughness values for the 0.2% AEP +CC 2130 flood (average climate change scenario). Peak flood levels across the floodplain resulting from the increased surface roughness are all less than +0.10m Sensitivity of Floodplain Inundation to Flood in Mangapouri Stream All flood simulations of overland flow across the Ōtaki River floodplain described previously have deliberately avoided the complication of a simultaneous flood in the Mangapouri Stream on the northern edge of the floodplain. This strategy was adopted so as to isolate the effects of the Expressway on secondary flows across the floodplain arising from stopbank overtopping. A further sensitivity test was therefore carried out for the following flood combination: Status Issue 1 Page 79 September 2013

3 a 0.2% AEP +CC 2130 (average climate change scenario) flood overtopping the Chrystall s Bend extended stopbank (with the existing SH1 bridge removed and replaced). A 1% AEP +CC 2130 flood in the Mangapouri Stream. This choice of flood combination reflects the fact that the annual exceedance probability of the flood in the Mangapouri Stream is likely to be smaller than that of the simultaneous flood in the Ōtaki River. Figure 6-20 shows a peak flood depth difference map for the proposed situation for the 0.2% AEP +CC 2130 flood with and without the 1% AEP +CC 2130 flood in the Mangapouri incorporated. This figure illustrates the incremental effect of adding the 1% AEP +CC 2130 flood in the Mangapouri Stream to the floodplain inundation pattern and peak flood depths. The increases in peak flood depth across the floodplain are confined to the area of the two flood storage basins on the Mangapouri Stream, the area upstream of the Expressway embankment between Rahui Road (along the southern edge of the two storage basins) and the secondary flood containment bund, and a short distance along the course of the Mangapouri Stream downstream of the SH1 culvert. There is negligible change across the rest of the floodplain, indicating that the Mangapouri Stream flows downstream of the SH1 culvert would largely be confined to the channel. The maximum increase in peak flood level along the course of the Mangapouri Stream is predicted to be less than 0.1m. Status Issue 1 Page 80 September 2013

4 Figure 6-19 Changes in peak flood depth across Ōtaki River floodplain due to increased surface roughness for 0.2% AEP +CC 2130 (average climate change scenario) flood with existing SH1 bridge removed. Status Issue 1 Page 81 September 2013

5 Figure 6-20 Changes in peak flood depth across Ōtaki River floodplain for 0.2% AEP +CC 2130 (mid-high climate change scenario) flood in proposed situation with addition of 1% AEP +CC 2130 flood in Mangapouri Stream. Status Issue 1 Page 82 September 2013

6 6.5 Duration of Ponding in Secondary Containment Bund Area The duration of ponding in the secondary containment bund area in the proposed situation would be very similar to that indicated by Figure 5-13 in Technical Report TR9-C (Smith and Webby 2013d). Floodwaters in this area could pond for a period of about 4 hours for the 0.2% AEP +CC 2130 flood (average climate change scenario) although this would be influenced by the duration of the flood discharge hydrograph in the river. 6.6 Interpretation of Effects for Floodplain Increases in peak flood depth across the Ōtaki River floodplain in the proposed situation due to stopbank overtopping by the 0.2% AEP + CC 2130 flood (average and mid-high climate change scenarios) are confined to the area contained by the Expressway embankment, the Chrystall s Bend extended stopbank, and secondary flood containment bund. Elsewhere across the floodplain, peak flood depth changes area well within the estimated accuracy of the flood depth predictions. This implies that there is effectively no change between the proposed and existing situations based on the 0.2% AEP +CC 2130 flood (average or mid-high climate change scenarios). Peak flood depths (levels) across the floodplain are fairly insensitive to changes in surface roughness and very insensitive to a concurrent flood in the Mangapouri Stream. The duration of ponding in the secondary flood containment bund area in the proposed situation for the 0.2% AEP + CC 2130 flood (average climate change scenario) could be likely to be in the order of 4 hours although this would be influenced by the shape of the flood discharge hydrograph in the river. 6.7 Impact on River and Floodplain Crossing Design As for the Waitohu Stream crossing, the design of the Ōtaki River and floodplain crossing is predicated on the assumption of predicted peak flood levels for the 1% AEP + CC 2090 flood (average climate change scenario). The predicted peak flood levels in Table 6-1 for the 1% AEP + CC 2130 flood (average climate change scenario) indicate that the effect on the river crossing design (i.e. in setting design levels) will be minimal with an increase in peak level at the Expressway bridges of only about 0.1m. The floodplain crossing design incorporates a very wide culvert through the Expressway embankment and an emergency overflow weir. This design is robust enough not to need any significant modification except for some minor adjustments to vertical profile at the northern end of the weir section to contain overtopping floodwaters. The design crest level of the secondary flood containment bund will need to be raised by about 0.25m. Status Issue 1 Page 83 September 2013

7 7. Effects of Mangaone Stream Crossing 7.1 Peak Flood Level and Discharge Predictions Flood hydrographs for the estimated 1% AEP +CC 2130 floods based on average and mid-high climate change scenarios were routed across the Mangaone Stream alluvial fan past the proposed Expressway, existing NIMT railway and existing SH1 transport links. Table 7-1 compares predicted peak levels at key locations across the fan within the area of interest between the existing and proposed situations for both flood cases. includes locations on the Mangaone Stream and on the Mangaone Overflow. Table 7-1 Predicted peak flood levels for existing and proposed situations for different 1% AEP + CC 2130 Location Mangaone Stream floods (red text indicates proposed culverts, black text indicates existing culverts). Local link road (eastern side) Expressway NIMT railway - existing SH1 - existing Local link road (western side) Mangaone Overflow Local link road (eastern side) Expressway NIMT railway - existing SH1 - existing School Rd Drain School Rd / Gear Rd intersection Local link road culvert Lucinsky Overflow Local link road (western side) Peak Flood Level (m MSL Wellington (1953) datum) CC to 2090 (average scenario) Existing Proposed CC to 2130 (average scenario) Existing Proposed This CC to 2130 (mid high scenario) Existing Proposed US US DS US DS US DS US DS US DS US DS US DS US DS US DS US DS US DS US DS US DS US DS US DS US DS US DS US DS US DS US DS US DS US DS * with Lucinsky Overflow unblocked sensitivity test for CC to 2090 scenario US DS US DS US DS US * Status Issue 1 Page 84 September 2013

8 Similarly, Table 7-2 compares predicted peak discharges at the same locations between the existing and proposed situations or both flood cases. Peak flood levels and discharges in the existing and proposed situations for the 1% AEP +CC 2090 flood from Technical Report 9-D (Smith and Webby, 2013e) are also given in Table 7-1 and Table 7-2 for comparison. Table 7-2 Predicted peak flood discharges for existing and proposed situations for different 1% AEP + CC 2130 floods (red text indicates proposed culverts, black text indicates existing culverts). Peak Flood Discharge (m 3 /s) Location Mangaone Stream Local link road (eastern side) Expressway NIMT railway - existing SH1 - existing Local link road (western side) Mangaone Overflow Local link road (eastern side) Expressway NIMT railway - existing SH1 - existing School Rd Drain School Rd / Gear Rd intersection Local link road culvert CC to 2090 (average scenario) Existing Proposed CC to 2130 (average scenario) Existing Proposed CC to 2130 (mid high scenario) Existing Proposed culvert 1.8 road overflow culvert 1.0 road overflow culvert 1.2 road overflow culvert 1.2 road overflow 26.8 culvert 1.6 road overflow 25.6 culvert 1.5 road overflow 26.5 culvert 2.8 road overflow 25.6 culvert 1.52 road overflow 26.5 culvert 2.8 road overflow Status Issue 1 Page 85 September 2013

9 The peak flood level and discharge predictions in Table 7-1 and Table 7-2 need to be interpreted in conjunction with the peak flood depth inundation maps and peak flood depth difference maps in Figure 7-1 to Figure 7-6. However, examination of Table 7-1 and Table 7-2 gives rise to the following observations. The increases in peak flood level between the proposed and existing situations upstream of the local link road culverts on both the main stream channel and on the overflow in each 1% AEP +CC 2130 flood case reflect the partial barrier effect of the local link road embankment with respect to overland flow. Similarly, the increases in peak flood level between the proposed and existing situations upstream of the Expressway culverts on the main stream channel and on the overflow in both flood cases reflect the flood containment function of the bund upstream of the proposed Expressway. The flood level increases are greatest upstream of the Expressway culvert on the overflow where ground levels are naturally lower and the preferential flow path for overland flow down the fan is located. Peak flood levels upstream of the NIMT railway culvert on the main stream channel are slightly reduced between the proposed and existing situations in both 1% AEP +CC 2130 flood cases (-0.10m and -0.11m). Peak flood discharges through the railway culvert are also reduced between the existing and proposed situations in both flood cases due to the throttling effect of the Expressway / NIMT railway / SH1 culvert system and the flood containment effect of the Expressway bund (the flow areas of the existing railway and SH1 culverts are about 70% of the flow area of the proposed Expressway culvert). Peak flood levels upstream of the NIMT railway culvert on the Overflow are increased very slightly between the proposed and existing situations for each 1% AEP +CC 2130 flood case (+0.15m and +0.17m respectively). This reflects the fact that ground levels are locally slightly lower along the course of the overflow due to this flow path being the former course of the Mangaone Stream. Peak flood discharges through the railway culvert are increased very slightly between the proposed and existing situations (+0.6m³/s and 0.4m³/s respectively). However these discharges are substantially attenuated by the existing SH1 culvert immediately downstream which has a flow area of only about 60% of the new railway culvert upstream and the proposed Expressway culvert. The proposed modifications to the Lucinsky Overflow (including a lowered bank area along the main stream channel adjacent to the Overflow entrance and a 5m wide by 1m high box culvert through the western approach embankment to the local link road overbridge) appropriately replicate the original discharge characteristics of this secondary flow path. 7.2 Peak Flood Depth Maps Figure 7-1 and Figure 7-2 show peak flood depth inundation maps for the existing and proposed situations respectively across the Mangaone Stream alluvial fan for the 1% AEP +CC 2130 (average climate change scenario) flood. Both figures show that the 1% AEP +CC 2130 flood breaks out of the main stream channel and starts to flow overland more than 700m upstream of the Expressway crossing of the fan. In the existing situation flood ponding would occur upstream of the NIMT railway line over a distance of about 560m along the railway line and extending about 70m up the fan. The maximum depth of flood inundation above natural ground levels would be about 1.0m at the railway culvert on the main stream channel and 1.4m at the railway culvert on the overflow. Status Issue 1 Page 86 September 2013

10 In the proposed situation, flood ponding would occur upstream of the local link road (over a distance of about 440m along the road and extending about 75m up the fan) and upstream of the proposed Expressway (over a distance of about 640m along the road and covering most of the area enclosed by the Expressway and local link road, and an additional area to the north of the local link road overbridge crossing). The maximum depth of inundation in the flood ponding area upstream of the local link road would be less than 2m. The maximum depth of inundation above natural ground levels in the flood ponding area upstream of Expressway would be about 1.3m at the culvert on the main stream channel less than 2m at the culvert on the overflow. The two flood ponding areas upstream of the local link road and the Expressway represent the primary effects of the Project. The flood ponding areas affect only pastoral land, much of it within the proposed designation for the Project. None of this land features any buildings that will not be acquired by the Project. This flood inundation would be very infrequent, of limited duration and confined to this limited area. Therefore the effects of flood inundation will be minimal and acceptable. Figure 7-7 compares flood discharge hydrographs through the Expressway culvert in the proposed situation and through the NIMT railway culvert on the main stream channel for the 0.2% AEP +CC 2130 (average climate change scenario) flood. Similarly, Figure 7-8 compares flood discharge hydrographs through the Expressway culvert in the proposed situation and through the NIMT railway culvert in the existing situation on the Mangaone Overflow for the same flood case. Both Figure 7-7 and Figure 7-8 provide a comparative measure of the duration of the flood along each primary flow path. The shape of the flood hydrograph used for routing purposes is shown in Figure 2-4 of Smith and Webby (2013e). The hydrograph is an extended duration one with three peaks. The total flood discharge for the 1% AEP +CC 2090 flood exceeds 14m³/s (the estimated flow at which breakout from the main stream channel towards the Overflow is estimated to occur) for up to 20 hours. The pattern of the discharge hydrographs in Figure 7-7and Figure 7-8 suggest that the duration of ponding in the flood ponding area upstream of the Expressway could be at least 12 hours. However this is heavily influenced by the shape of the base hydrograph for the flood. A single peaked flood hydrograph would cause the duration of ponding to be reduced. Figure 7-3 shows changes in peak flood depth across the alluvial fan between the proposed and existing situations for the 0.2% AEP +CC 2130 (average climate change scenario) flood. This peak flood depth difference map confirms that the major changes in flood depths will occur in the two identified flood ponding areas, upstream of the local link road and upstream of the Expressway. The maximum change in peak flood depth is about 1.3m in the local link road ponding area while the maximum change is less than 1m in the Expressway ponding area. Upstream of the two flood ponding areas, the flood inundation patterns shown in Figure 7-1 for the existing situation and Figure 7-2 for the proposed situation are much the same. The apparent differences in peak flood depth over this upstream are within the estimated accuracy of the model predictions so that there is effectively no change between the proposed and existing situations. Downstream of the existing SH1, Figure 7-3 and Figure 7-6 both show a broad central strip (250m wide in the case of the average climate change scenario flood and smaller in the case of the mid-high climate change scenario flood) of light pink shading (indicating less than a +0.05m change in flood depth) with flanking strips either side of light green shading (indicating less than a -0.05m change in flood depth). Again these changes Status Issue 1 Page 87 September 2013

11 in peak flood depth over both the central strip and the flanking strips are within the estimated accuracy of the model predictions. To the south of this wider strip, peak flood depths along an old remnant channel are reduced slightly in the proposed situation due to the elimination of overtopping of the NIMT railway and SH1 in the existing situation seen in Figure 7-1. Another rail and road overflow path at Te Waka Road to the north is also eliminated (this is just off the peak flood depth map in Figure 7-2). Along Te Horo Beach Road between SH1 and the local link road tee intersection, peak flood depths are also reduced slightly in the proposed situation. Similarly to the north of the local link road western overbridge approach embankment, peak flood depths are also reduced slightly due to confinement of SH1 road overflow by the bridge approach embankment at the site of the SH1 culvert on the main stream channel. The partial damming effect of the western approach embankment to the local link road overbridge causes slightly increased peak flood depths within the area between the main stream channel and the approach embankment. Overall the impact of the Project on the inundation area to the west of the existing SH1 is no worse than in the existing situation even though peak flood discharges through the SH1 culvert and over SH1 on the Mangaone Overflow are marginally increased (see Table 7-2). Figure 7-4 and Figure 7-5 contain peak flood inundation depth maps for the existing and proposed situations respectively for the 1% AEP +CC 2130 flood (mid-high climate change scenario). These figures show a similar flood inundation pattern to Figure 7-1 and Figure 7-2, albeit with slightly higher maximum depths. The proposed bund upstream of the Expressway to provide flood containment remains sufficiently high to contain this flood with an 8% larger peak than the 1% AEP +CC 2130 (average climate change scenario) flood. Similarly the peak flood depth difference map in Figure 7-6 shows a very similar pattern to that in Figure 7-3. The previous conclusions that the effects of flood inundation outside of the two primary food ponding areas (upstream of the local link road and upstream of the Expressway) are no worse than in the existing situation remain valid for this larger flood. Over most of the area downstream of SH1, peak flood level differences between the proposed and existing situations are within ±0.05m which is within the estimated accuracy of the flood level predictions. Status Issue 1 Page 88 September 2013

12 Figure 7-1 Flood peak depths across Mangaone River alluvial fan in existing situation for 1% AEP +CC 2130 flood based on average (mid-range) climate change scenario. Status Issue 1 Page 89 September 2013

13 Figure 7-2 Peak flood depths across Mangaone Stream alluvial fan in proposed situation for 1% AEP +CC 2130 flood based on average (mid-range) climate change scenario. Status Issue 1 Page 90 September 2013

14 Figure 7-3 Changes in peak flood depths across Mangaone River alluvial fan between proposed and existing situations for 1% AEP +CC 2130 flood based on average (mid-range) climate change scenario (note: pink and red shading indicates areas of increased flow depths, green shading indicates areas of decreased flow depths). Status Issue 1 Page 91 September 2013

15 Figure 7-4 Peak flood depths across the Mangaone Stream alluvial fan in existing situation for 1% AEP +CC 2130 flood based on mid-high climate change scenario. Status Issue 1 Page 92 September 2013

16 Figure 7-5 Peak flood depths across the Mangaone Stream alluvial fan in proposed situation for 1% AEP +CC 2130 flood based on mid-high climate change scenario. Status Issue 1 Page 93 September 2013

17 Figure 7-6 Changes in peak flood depths across the Mangaone Stream alluvial fan between proposed and existing situations for 1% AEP +CC 2130 flood based on mid-high climate change scenario (note: pink and red shading indicates areas of increased flow depths, green shading indicates areas of decreased flow depths). Status Issue 1 Page 94 September 2013

18 Discharge (m 3 /s) Existing 5 Proposed Time (hours) Figure 7-7 Comparison of flood discharge hydrographs on the main stream channel through the Expressway culvert in the proposed situation and the NIMT railway culvert in the existing situation (1% AEP +CC 2130 flood average climate change scenario). Status Issue 1 Page 95 September 2013

19 Discharge (m 3 /s) Existing Proposed Time (hours) Figure 7-8 Comparison of flood discharge hydrographs on Mangaone Overflow through Expressway culvert in the proposed situation and the NIMT railway culvert in the existing situation (1% AEP + CC 2130 flood average climate change scenario). Status Issue 1 Page 96 September 2013

Appendix C MIKEFLOOD Model Predictions for 28 October 1998 Flood Event

Appendix C MIKEFLOOD Model Predictions for 28 October 1998 Flood Event Appendix C MIKEFLOOD Model Predictions for 28 October 1998 Flood Event Status Issue 2 Page 99 January 2013 The predictions of the MIKEFLOOD model were checked against anecdotal evidence of flood inundation

More information

IMPACTS OF SECONDARY FLOOD EMBANKMENTS ON THE WAIMAKARIRI FLOODPLAIN, NEW ZEALAND

IMPACTS OF SECONDARY FLOOD EMBANKMENTS ON THE WAIMAKARIRI FLOODPLAIN, NEW ZEALAND IMPACTS OF SECONDARY FLOOD EMBANKMENTS ON THE WAIMAKARIRI FLOODPLAIN, NEW ZEALAND Terry van Kalken (1), Tony Oliver (2), Ian Heslop (2), Tony Boyle (2) (1) DHI Water & Environment, e-centre, Oaklands Road,

More information

Geotechnical Engineering and Resilience

Geotechnical Engineering and Resilience Chapter 14 Part G VOLUME 2 Geotechnical Engineering and Resilience Page 192 Overview Key geotechnical aspects of the Project include: Cut slopes in dune sand, including erodibility and erosion protection;

More information

Report R08/23 ISBN Kilmore Street PO Box 345 Christchurch Phone (03) Fax (03)

Report R08/23 ISBN Kilmore Street PO Box 345 Christchurch Phone (03) Fax (03) Report R08/23 ISBN 978-1-86937-804-2 58 Kilmore Street PO Box 345 Christchurch Phone (03) 365 3828 Fax (03) 365 3194 75 Church Street PO Box 550 Timaru Phone (03) 688 9069 Fax (03) 688 9067 Website: www.ecan.govt.nz

More information

GEOL 1121 Earth Processes and Environments

GEOL 1121 Earth Processes and Environments GEOL 1121 Earth Processes and Environments Wondwosen Seyoum Department of Geology University of Georgia e-mail: seyoum@uga.edu G/G Bldg., Rm. No. 122 Seyoum, 2015 Chapter 6 Streams and Flooding Seyoum,

More information

Karamea floodplain investigation

Karamea floodplain investigation Karamea floodplain investigation NIWA Client Report: CHC2010-107 October 2010 NIWA Project: ELF 10234/1 Karamea floodplain investigation Graeme Smart Jo Bind NIWA contact/corresponding author Graeme Smart

More information

Mt Ruapehu Crater Lake lahar hazard

Mt Ruapehu Crater Lake lahar hazard Mt Ruapehu Crater Lake lahar hazard Prepared by M G Webby Opus International Consultants Limited PO Box 12-003 Wellington Published by Department of Conservation Head Office, PO Box 10-420 Wellington,

More information

Restoring Meanders to Straightened Rivers 1.7 Reconnecting remnant meanders

Restoring Meanders to Straightened Rivers 1.7 Reconnecting remnant meanders .7 Reconnecting remnant meanders River Little Ouse Location - Thetford, Norfolk TL87082 Date of construction - 994 Length 900m Cost 5,000 Maximum extent of flooding during winter floods BTO boundary Small

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

Appendix E Guidance for Shallow Flooding Analyses and Mapping

Appendix E Guidance for Shallow Flooding Analyses and Mapping Appendix E Guidance for Shallow Flooding Analyses and Mapping E.1 Introduction Different types of shallow flooding commonly occur throughout the United States. Types of flows that result in shallow flooding

More information

YELLOWSTONE RIVER FLOOD STUDY REPORT TEXT

YELLOWSTONE RIVER FLOOD STUDY REPORT TEXT YELLOWSTONE RIVER FLOOD STUDY REPORT TEXT TECHNICAL REPORT Prepared for: City of Livingston 411 East Callender Livingston, MT 59047 Prepared by: Clear Creek Hydrology, Inc. 1627 West Main Street, #294

More information

Floodplain Risk Management in Dungog after the April 2015 Super Storm. Presentation Outline

Floodplain Risk Management in Dungog after the April 2015 Super Storm. Presentation Outline Presentation Outline Floodplain Risk Management in after the April 2015 Super Storm Rohan Hudson, Royal HaskoningDHV FMA 2017 Preparing for the Next Great Flood 17th May 2017 Background and Flood Mechanisms

More information

LOMR SUBMITTAL LOWER NEHALEM RIVER TILLAMOOK COUNTY, OREGON

LOMR SUBMITTAL LOWER NEHALEM RIVER TILLAMOOK COUNTY, OREGON LOMR SUBMITTAL LOWER NEHALEM RIVER TILLAMOOK COUNTY, OREGON Prepared for: TILLAMOOK COUNTY DEPARTMENT OF COMMUNITY DEVELOPMENT 1510-B THIRD STREET TILLAMOOK, OR 97141 Prepared by: 10300 SW GREENBURG ROAD,

More information

Flow regime, floodplain inundation and floodplain waterbody connectivity at Congaree National Park

Flow regime, floodplain inundation and floodplain waterbody connectivity at Congaree National Park Flow regime, floodplain inundation and floodplain waterbody connectivity at Congaree National Park John Kupfer Dept. of Geography Univ. of South Carolina Kimberly Meitzen Duke University Nature Conservancy

More information

Natural hazards in Glenorchy Summary Report May 2010

Natural hazards in Glenorchy Summary Report May 2010 Natural hazards in Glenorchy Summary Report May 2010 Contents Glenorchy s hazardscape Environment setting Flood hazard Earthquakes and seismic hazards Hazards Mass movement Summary Glossary Introduction

More information

Review of Dunedin City District Plan Natural Hazards Flood Hazard on the Taieri Plain and Strath Taieri

Review of Dunedin City District Plan Natural Hazards Flood Hazard on the Taieri Plain and Strath Taieri Review of Dunedin City District Plan Natural Hazards Flood Hazard on the Taieri Plain and Strath Taieri Mosgiel and the East Taieri Plain (Source: NZ Stock Library) Otago Regional Council Private Bag 1954,

More information

Report for Area Drainage Studies for 1320 MW (2x660 MW) THERMAL POWER PROJECT AT MIRZAPUR, U.P.

Report for Area Drainage Studies for 1320 MW (2x660 MW) THERMAL POWER PROJECT AT MIRZAPUR, U.P. Report for Area Drainage Studies for 1320 MW (2x660 MW) THERMAL POWER PROJECT AT MIRZAPUR, U.P. 1. Introduction M/s Welspun Energy Uttar Pradesh Ltd. (WEUPL) is putting up 1320 MW (2 x 660 MW) coal fired

More information

ERDC/LAB TR-0X-X 100. Figure 7-3 Maximum velocity magnitudes for existing conditions for 100-year flood event

ERDC/LAB TR-0X-X 100. Figure 7-3 Maximum velocity magnitudes for existing conditions for 100-year flood event ERDC/LAB TR-0X-X 100 Figure 7-3 Maximum velocity magnitudes for existing conditions for 100-year flood event ERDC/LAB TR-0X-X 101 Figure 7-4 Model schematization of Option 1 Figure 7-5 Bed displacement

More information

Flood hazard on the Taieri Plain. Review of Dunedin City District Plan: Natural hazards

Flood hazard on the Taieri Plain. Review of Dunedin City District Plan: Natural hazards Flood hazard on the Taieri Plain Review of Dunedin City District Plan: Natural hazards 1 st revision: June 2015 Otago Regional Council Private Bag 1954, Dunedin 9054 70 Stafford Street, Dunedin 9016 Phone

More information

The key natural hazards relevant to the Project area relate to seismic activity and flood risk.

The key natural hazards relevant to the Project area relate to seismic activity and flood risk. 21. NATURAL HAZARDS Overview The key natural hazards relevant to the Project area relate to seismic activity and flood risk. Seismic activity, including ground shaking and liquefaction, is a significant

More information

Four Mile Run Levee Corridor Stream Restoration

Four Mile Run Levee Corridor Stream Restoration Four Mile Run Levee Corridor Stream Restoration 30% Design Summary U.S. Army Corps of Engineers, Baltimore District Presentation Outline Four Mile Run 1.) Historic Perspective 2.) Existing Conditions 3.)

More information

Grant 0299-NEP: Water Resources Project Preparatory Facility

Grant 0299-NEP: Water Resources Project Preparatory Facility Document Produced under Grant Project Number: 45206 May 2016 Grant 0299-NEP: Water Resources Project Preparatory Facility Final Report Volume 3 East Rapti (1 of 9) Prepared by Pvt. Ltd. For Ministry of

More information

Flood Map. National Dataset User Guide

Flood Map. National Dataset User Guide Flood Map National Dataset User Guide Version 1.1.5 20 th April 2006 Copyright Environment Agency 1 Contents 1.0 Record of amendment... 3 2.0 Introduction... 4 2.1 Description of the Flood Map datasets...4

More information

6.11 Naas River Management Unit

6.11 Naas River Management Unit 6.11 Naas River Management Unit 6.11.1 Site 41 Issue: Bed and bank erosion Location: E 0685848 N 6058358 Waterway: Naas River Management Unit: Naas River Facing downstream from Bobeyan Rd bridge Facing

More information

Historical channel change on the Upper Gila River, Arizona and New Mexico in response to anthropogenic modifications and extreme floods

Historical channel change on the Upper Gila River, Arizona and New Mexico in response to anthropogenic modifications and extreme floods Historical channel change on the Upper Gila River, Arizona and New Mexico in response to anthropogenic modifications and extreme floods www.archives.gov www.paztcn.wr.usgs.gov wrh.noaa.gov Upper Gila River

More information

Advanced /Surface Hydrology Dr. Jagadish Torlapati Fall 2017 MODULE 2 - ROUTING METHODS

Advanced /Surface Hydrology Dr. Jagadish Torlapati Fall 2017 MODULE 2 - ROUTING METHODS Routing MODULE - ROUTING METHODS Routing is the process of find the distribution of flow rate and depth in space and time along a river or storm sewer. Routing is also called Flow routing or flood routing.

More information

The River Restoration Centre therrc.co.uk. Understanding Fluvial Processes: supporting River Restoration. Dr Jenny Mant

The River Restoration Centre therrc.co.uk. Understanding Fluvial Processes: supporting River Restoration. Dr Jenny Mant The River Restoration Centre therrc.co.uk Understanding Fluvial Processes: supporting River Restoration Dr Jenny Mant Jenny@therrc.co.uk Understanding your catchment Hydrology Energy associated with the

More information

APPENDIX E. GEOMORPHOLOGICAL MONTORING REPORT Prepared by Steve Vrooman, Keystone Restoration Ecology September 2013

APPENDIX E. GEOMORPHOLOGICAL MONTORING REPORT Prepared by Steve Vrooman, Keystone Restoration Ecology September 2013 APPENDIX E GEOMORPHOLOGICAL MONTORING REPORT Prepared by Steve Vrooman, Keystone Restoration Ecology September 2 Introduction Keystone Restoration Ecology (KRE) conducted geomorphological monitoring in

More information

Rucker Pond. Background

Rucker Pond. Background Rucker Pond Background The Rucker Basin consists of two subbasins (East and West) that drain to a single area known as Rucker Pond. Both subbasins have the same hydraulic parameters, but have different

More information

Modeling Great Britain s Flood Defenses. Flood Defense in Great Britain. By Dr. Yizhong Qu

Modeling Great Britain s Flood Defenses. Flood Defense in Great Britain. By Dr. Yizhong Qu Modeling Great Britain s Flood Defenses AIRCurrents Editor s note: AIR launched its Inland Flood Model for Great Britain in December 2008. The hazard module captures the physical processes of rainfall-runoff

More information

ENGINEERING HYDROLOGY

ENGINEERING HYDROLOGY ENGINEERING HYDROLOGY Prof. Rajesh Bhagat Asst. Professor Civil Engineering Department Yeshwantrao Chavan College Of Engineering Nagpur B. E. (Civil Engg.) M. Tech. (Enviro. Engg.) GCOE, Amravati VNIT,

More information

The last three sections of the main body of this report consist of:

The last three sections of the main body of this report consist of: Threatened and Endangered Species Geological Hazards Floodplains Cultural Resources Hazardous Materials A Cost Analysis section that provides comparative conceptual-level costs follows the Environmental

More information

Controlling Processes That Change Land

Controlling Processes That Change Land 1 Name Date Controlling Processes That Change Land People try to control some of the processes that change land. To do this, people apply technology- the use of science to solve problems in everyday life.

More information

UGRC 144 Science and Technology in Our Lives/Geohazards

UGRC 144 Science and Technology in Our Lives/Geohazards UGRC 144 Science and Technology in Our Lives/Geohazards Flood and Flood Hazards Dr. Patrick Asamoah Sakyi Department of Earth Science, UG, Legon College of Education School of Continuing and Distance Education

More information

APPENDIX B: HYDROTECHNICAL ASSESSMENT

APPENDIX B: HYDROTECHNICAL ASSESSMENT Sheep Paddocks Trail Alignment Analysis APPENDIX B: HYDROTECHNICAL ASSESSMENT LEES+Associates -112- 30 Gostick Place North Vancouver, BC V7M 3G3 604.980.6011 www.nhcweb.com 300217 15 August 2013 Lees +

More information

Streams. Stream Water Flow

Streams. Stream Water Flow CHAPTER 14 OUTLINE Streams: Transport to the Oceans Does not contain complete lecture notes. To be used to help organize lecture notes and home/test studies. Streams Streams are the major geological agents

More information

Why Geomorphology for Fish Passage

Why Geomorphology for Fish Passage Channel Morphology - Stream Crossing Interactions An Overview Michael Love Michael Love & Associates mlove@h2odesigns.com (707) 476-8938 Why Geomorphology for Fish Passage 1. Understand the Scale of the

More information

PRELIMINARY CULVERT ANALYSIS REPORT FOR CULVERT NO. 008-C OREGON AVENUE OVER PINEHURST CREEK

PRELIMINARY CULVERT ANALYSIS REPORT FOR CULVERT NO. 008-C OREGON AVENUE OVER PINEHURST CREEK PRELIMINARY CULVERT ANALYSIS REPORT FOR CULVERT NO. 008-C OREGON AVENUE OVER PINEHURST CREEK Prepared for The District of Columbia Department of Transportation Washington, D.C. Prepared by Parsons Transportation

More information

Aquifer an underground zone or layer of sand, gravel, or porous rock that is saturated with water.

Aquifer an underground zone or layer of sand, gravel, or porous rock that is saturated with water. Aggradation raising of the streambed by deposition that occurs when the energy of the water flowing through a stream reach is insufficient to transport sediment conveyed from upstream. Alluvium a general

More information

Fish Passage at Road Crossings

Fish Passage at Road Crossings Fish Passage at Road Crossings 1 Crossing Design Workshop Outline 1:00 to 2:00 Intro, Design Overview, Channel Width 2:00 to 2:15 Break 2:15 to 3:15 No-Slope, Stream Simulation Design 3:15 to 3:30 Break

More information

Tom Ballestero University of New Hampshire. 1 May 2013

Tom Ballestero University of New Hampshire. 1 May 2013 Tom Ballestero University of New Hampshire 1 May 2013 1 Hydrology 2 Basic Hydrology Low flows most common Flows that fill the stream to the banks and higher are much less common Filling the stream to the

More information

Surface Water Short Study Guide

Surface Water Short Study Guide Name: Class: Date: Surface Water Short Study Guide Multiple Choice Identify the letter of the choice that best completes the statement or answers the question. 1. The three ways in which a stream carries

More information

Chelmsford Borough Council LDF: Level 1 SFRA

Chelmsford Borough Council LDF: Level 1 SFRA Chelmsford Borough Council LDF: Level 1 SFRA Urban Capacity Study Sites PPS25 Flood Zones 2007 Figure B20-1 Preliminary Core Strategy Assessment Flood Zone Potential Housing Potential Employment 1, 2 &

More information

PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0

PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0 PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0 LYCOMING COUNTY S.R.15, SECTION C41 FINAL HYDROLOGIC AND HYDRAULIC REPORT STEAM VALLEY RUN STREAM RELOCATION DATE: June, 2006 REVISED:

More information

How Do Human Impacts and Geomorphological Responses Vary with Spatial Scale in the Streams and Rivers of the Illinois Basin?

How Do Human Impacts and Geomorphological Responses Vary with Spatial Scale in the Streams and Rivers of the Illinois Basin? How Do Human Impacts and Geomorphological Responses Vary with Spatial Scale in the Streams and Rivers of the Illinois Basin? Bruce Rhoads Department of Geography University of Illinois at Urbana-Champaign

More information

CONCEPTUAL AND TECHNICAL CHALLENGES IN DEFINING FLOOD PLANNING AREAS IN URBAN CATCHMENTS

CONCEPTUAL AND TECHNICAL CHALLENGES IN DEFINING FLOOD PLANNING AREAS IN URBAN CATCHMENTS CONCEPTUAL AND TECHNICAL CHALLENGES IN DEFINING FLOOD PLANNING AREAS IN URBAN CATCHMENTS C Ryan 1, D Tetley 2, C Kinsey 3 1 & 2 Catchment Simulation Solutions, NSW 3 Co-ordinator Stormwater and Structural

More information

L OWER N OOKSACK R IVER P ROJECT: A LTERNATIVES A NALYSIS A PPENDIX A: H YDRAULIC M ODELING. PREPARED BY: LandC, etc, LLC

L OWER N OOKSACK R IVER P ROJECT: A LTERNATIVES A NALYSIS A PPENDIX A: H YDRAULIC M ODELING. PREPARED BY: LandC, etc, LLC L OWER N OOKSACK R IVER P ROJECT: A LTERNATIVES A NALYSIS A PPENDIX A: H YDRAULIC M ODELING PREPARED BY: LandC, etc, LLC TABLE OF CONTENTS 1 Introduction... 1 2 Methods... 1 2.1 Hydraulic Model... 1 2.2

More information

1 INTRODUCTION AND MAJOR FINDINGS... 1

1 INTRODUCTION AND MAJOR FINDINGS... 1 Memorandum To: Lindsey Clark, Stillwater Valley Watershed Council Coordinator From: Chad Raisland, Pioneer Technical Services, Inc. and Karin Boyd, Applied Geomorphology, Inc. CC: Tanya Lester, Stillwater

More information

NATURAL RIVER. Karima Attia Nile Research Institute

NATURAL RIVER. Karima Attia Nile Research Institute NATURAL RIVER CHARACTERISTICS Karima Attia Nile Research Institute NATURAL RIVER DEFINITION NATURAL RIVER DEFINITION Is natural stream of water that flows in channels with ih more or less defined banks.

More information

9. Flood Routing. chapter Two

9. Flood Routing. chapter Two 9. Flood Routing Flow routing is a mathematical procedure for predicting the changing magnitude, speed, and shape of a flood wave as a function of time at one or more points along a watercourse (waterway

More information

Waipatiki Catchment Flood Hazard Analysis. June 2008 AM 08/04 HBRC Plan Number 4029

Waipatiki Catchment Flood Hazard Analysis. June 2008 AM 08/04 HBRC Plan Number 4029 Waipatiki Catchment Flood Hazard Analysis June 2008 AM 08/04 HBRC Plan Number 4029 Asset Management Group Technical Report ISSN 1174 3085 Engineering Section Waipatiki Catchment: Flood Hazard Analysis

More information

SCOPE OF PRESENTATION STREAM DYNAMICS, CHANNEL RESTORATION PLANS, & SEDIMENT TRANSPORT ANALYSES IN RELATION TO RESTORATION PLANS

SCOPE OF PRESENTATION STREAM DYNAMICS, CHANNEL RESTORATION PLANS, & SEDIMENT TRANSPORT ANALYSES IN RELATION TO RESTORATION PLANS DESIGN METHODS B: SEDIMENT TRANSPORT PROCESSES FOR STREAM RESTORATION DESIGN PETER KLINGEMAN OREGON STATE UNIVERSITY CIVIL ENGINEERING DEPT., CORVALLIS 2 ND ANNUAL NORTHWEST STREAM RESTORATION DESIGN SYMPOSIUM

More information

STRUCTURAL STABILITY ASSESSMENT

STRUCTURAL STABILITY ASSESSMENT STRUCTURAL STABILITY ASSESSMENT CFR 257.73(d) Bottom Ash Pond Complex Cardinal Plant Brilliant, Ohio October, 2016 Prepared for: Cardinal Operating Company Cardinal Plant Brilliant, Ohio Prepared by: Geotechnical

More information

EA SOUTH WEST. Hillfarrance. Flood defence scheme

EA SOUTH WEST. Hillfarrance. Flood defence scheme EA SOUTH WEST Hillfarrance Flood defence scheme E n v ir o n m e n t A g e n c y Hillfarrance flood defence scheme The village of Hillfarrance - six kilometres west of Taunton, Somerset - lies on the floodplain

More information

FLOOD HAZARD AND RISK ASSESSMENT IN MID- EASTERN PART OF DHAKA, BANGLADESH

FLOOD HAZARD AND RISK ASSESSMENT IN MID- EASTERN PART OF DHAKA, BANGLADESH FLOOD HAZARD AND RISK ASSESSMENT IN MID- EASTERN PART OF DHAKA, BANGLADESH Muhammad MASOOD MEE07180 Supervisor: Prof. Kuniyoshi TAKEUCHI ABSTRACT An inundation simulation has been done for the mid-eastern

More information

GEOL 652. Poudre River Fieldtrip

GEOL 652. Poudre River Fieldtrip GEOL 652. Poudre River Fieldtrip One of the more difficult variables to measure and/or estimate when studying flow in natural channels is that of roughness. Roughness, usually approximated with Manning

More information

Technical Memorandum No

Technical Memorandum No Pajaro River Watershed Study in association with Technical Memorandum No. 1.2.10 Task: Evaluation of Four Watershed Conditions - Sediment To: PRWFPA Staff Working Group Prepared by: Gregory Morris and

More information

A SIMPLE GIS METHOD FOR OBTAINING FLOODED AREAS

A SIMPLE GIS METHOD FOR OBTAINING FLOODED AREAS A SIMPLE GIS METHOD FOR OBTAINING FLOODED AREAS ROMAN P., I. 1, OROS C., R. 2 ABSTRACT. A simple GIS method for obtaining flooded areas. This paper presents a method for obtaining flooded areas near to

More information

MATHEMATICAL MODELING OF FLUVIAL SEDIMENT DELIVERY, NEKA RIVER, IRAN. S.E. Kermani H. Golmaee M.Z. Ahmadi

MATHEMATICAL MODELING OF FLUVIAL SEDIMENT DELIVERY, NEKA RIVER, IRAN. S.E. Kermani H. Golmaee M.Z. Ahmadi JOURNAL OF ENVIRONMENTAL HYDROLOGY The Electronic Journal of the International Association for Environmental Hydrology On the World Wide Web at http://www.hydroweb.com VOLUME 16 2008 MATHEMATICAL MODELING

More information

UK Flooding Feb 2003

UK Flooding Feb 2003 UK Flooding 2000 06 Feb 2003 Britain has taken a battering from floods in the last 5 years, with major events in 1998 and 2000, significant floods in 2001 and minor events in each of the other years. So

More information

Illinois State Water Survey Division

Illinois State Water Survey Division Illinois State Water Survey Division SURFACE WATER SECTION SWS Miscellaneous Publication 108 SEDIMENT YIELD AND ACCUMULATION IN THE LOWER CACHE RIVER by Misganaw Demissie Champaign, Illinois June 1989

More information

Pirai river (Bolivia)

Pirai river (Bolivia) Pirai river (Bolivia) Confluent of the Amazon river which average discharge is only 6 m3/s, but with peak discharge over 5000 m3/s, a challenge for river basin management and for flood control HYDROEUROPE

More information

Running Water Earth - Chapter 16 Stan Hatfield Southwestern Illinois College

Running Water Earth - Chapter 16 Stan Hatfield Southwestern Illinois College Running Water Earth - Chapter 16 Stan Hatfield Southwestern Illinois College Hydrologic Cycle The hydrologic cycle is a summary of the circulation of Earth s water supply. Processes involved in the hydrologic

More information

Solutions to Flooding on Pescadero Creek Road

Solutions to Flooding on Pescadero Creek Road Hydrology Hydraulics Geomorphology Design Field Services Photo courtesy Half Moon Bay Review Solutions to Flooding on Pescadero Creek Road Prepared for: San Mateo County Resource Conservation District

More information

Flash flood disaster in Bayangol district, Ulaanbaatar

Flash flood disaster in Bayangol district, Ulaanbaatar Flash flood disaster in Bayangol district, Ulaanbaatar Advanced Training Workshop on Reservoir Sedimentation Management 10-16 October 2007. IRTCES, Beijing China Janchivdorj.L, Institute of Geoecology,MAS

More information

Project Description. Project Options. End Analysis On... Apr 26, :00:00. Rainfall Details

Project Description. Project Options. End Analysis On... Apr 26, :00:00. Rainfall Details Project Description File Name... 323 - Att Pond 3 East PIPES ONLY.SPF Project Options Flow Units... Elevation Type... Hydrology Method... EPA SWMM Infiltration Method... Link Routing Method... Enable Overflow

More information

DRAFT Design Hydraulic Study. Bridge 04C-0055, Mattole Road Bridge over Mattole River at Honeydew. Humboldt County. Prepared for:

DRAFT Design Hydraulic Study. Bridge 04C-0055, Mattole Road Bridge over Mattole River at Honeydew. Humboldt County. Prepared for: DRAFT Design Hydraulic Study Bridge 04C-0055, Mattole Road Bridge over Mattole River at Honeydew Humboldt County Prepared for: Morrison Structures Incorporated 1890 Park Marina Drive, Suite 104 Redding,

More information

Earth Science Chapter 6 Section 2 Review

Earth Science Chapter 6 Section 2 Review Name: Class: Date: Earth Science Chapter 6 Section Review Multiple Choice Identify the choice that best completes the statement or answers the question. 1. Most streams carry the largest part of their

More information

Summary. Streams and Drainage Systems

Summary. Streams and Drainage Systems Streams and Drainage Systems Summary Streams are part of the hydrologic cycle and the chief means by which water returns from the land to the sea. They help shape the Earth s surface and transport sediment

More information

LOMR SUBMITTAL LOWER NESTUCCA RIVER TILLAMOOK COUNTY, OREGON

LOMR SUBMITTAL LOWER NESTUCCA RIVER TILLAMOOK COUNTY, OREGON LOMR SUBMITTAL LOWER NESTUCCA RIVER TILLAMOOK COUNTY, OREGON Prepared for: TILLAMOOK COUNTY DEPARTMENT OF COMMUNITY DEVELOPMENT 1510-B THIRD STREET TILLAMOOK, OR 97141 Prepared by: 10300 SW GREENBURG ROAD,

More information

Appendix O. Sediment Transport Modelling Technical Memorandum

Appendix O. Sediment Transport Modelling Technical Memorandum Appendix O Sediment Transport Modelling Technical Memorandum w w w. b a i r d. c o m Baird o c e a n s engineering l a k e s design r i v e r s science w a t e r s h e d s construction Final Report Don

More information

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area.

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area. Sediment Trench SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils [1] Performance of

More information

How to integrate wetland processes in river basin modeling? A West African case study

How to integrate wetland processes in river basin modeling? A West African case study How to integrate wetland processes in river basin modeling? A West African case study stefan.liersch@pik-potsdam.de fred.hattermann@pik-potsdam.de June 2011 Outline Why is an inundation module required?

More information

Page 1. Name:

Page 1. Name: Name: 1) Which event is the best example of erosion? dissolving of rock particles on a limestone gravestone by acid rain breaking apart of shale as a result of water freezing in a crack rolling of a pebble

More information

3/3/2013. The hydro cycle water returns from the sea. All "toilet to tap." Introduction to Environmental Geology, 5e

3/3/2013. The hydro cycle water returns from the sea. All toilet to tap. Introduction to Environmental Geology, 5e Introduction to Environmental Geology, 5e Running Water: summary in haiku form Edward A. Keller Chapter 9 Rivers and Flooding Lecture Presentation prepared by X. Mara Chen, Salisbury University The hydro

More information

Paper presented in the Annual Meeting of Association of American Geographers, Las Vegas, USA, March 2009 ABSTRACT

Paper presented in the Annual Meeting of Association of American Geographers, Las Vegas, USA, March 2009 ABSTRACT Paper presented in the Annual Meeting of Association of American Geographers, Las Vegas, USA, March 2009 ABSTRACT CHANGING GEOMORPHOLOGY OF THE KOSI RIVER SYSTEM IN THE INDIAN SUBCONTINENT Nupur Bose,

More information

Section 5. Low-Gradient Streams. What Do You See? Think About It. Investigate. Learning Outcomes

Section 5. Low-Gradient Streams. What Do You See? Think About It. Investigate. Learning Outcomes Chapter 4 Surface Processes Section 5 Low-Gradient Streams What Do You See? Learning Outcomes In this section, you will Use models and real-time streamflow data to understand the characteristics of lowgradient

More information

Flooding in Dolgellau

Flooding in Dolgellau Flooding in Dolgellau Graham Hall MMath, PhD University of Wales, Bangor Background Flooding has historically been a cause for concern in Dolgellau. Following a serious flood in December 1964 when shops

More information

Hydrologic Forecast Centre Manitoba Infrastructure, Winnipeg, Manitoba. FEBRUARY OUTLOOK REPORT FOR MANITOBA February 23, 2018

Hydrologic Forecast Centre Manitoba Infrastructure, Winnipeg, Manitoba. FEBRUARY OUTLOOK REPORT FOR MANITOBA February 23, 2018 Page 1 of 17 Hydrologic Forecast Centre Manitoba Infrastructure, Winnipeg, Manitoba FEBRUARY OUTLOOK REPORT FOR MANITOBA February 23, 2018 Overview The February Outlook Report prepared by the Hydrologic

More information

HYDROLOGIC AND HYDRAULIC REPORT FOR SR. 0522, SECTION 5BN ALONG BLACKLOG CREEK CROMWELL TOWNSHIP HUNTINGDON COUNTY. Prepared for:

HYDROLOGIC AND HYDRAULIC REPORT FOR SR. 0522, SECTION 5BN ALONG BLACKLOG CREEK CROMWELL TOWNSHIP HUNTINGDON COUNTY. Prepared for: HYDROLOGIC AND HYDRAULIC REPORT FOR SR. 0522, SECTION 5BN ALONG BLACKLOG CREEK CROMWELL TOWNSHIP Prepared for: KCI Technologies, Inc. Mechanicsburg, PA and Pennsylvania Department of Transportation Engineering

More information

Extreme Phenomena in Dobrogea - Floods and Droughts

Extreme Phenomena in Dobrogea - Floods and Droughts Extreme Phenomena in Dobrogea - Floods and Droughts PhD eng. Carmen Maftei Ovidius University of Constanta (Partner no 4) OUTLINES Introduction Study area Drought Floods Conclusion What is the problem?

More information

STREAM RESTORATION AWRA Summer Specialty Conference, GIS and Water Resources IX

STREAM RESTORATION AWRA Summer Specialty Conference, GIS and Water Resources IX STREAM RESTORATION 2016 AWRA Summer Specialty Conference, GIS and Water Resources IX Innovative Use of 2D Hydraulic Modeling in Stream Restoration Design Presented by: Li Gao, PE and Robert Scrafford,

More information

Observations on Surface Water in the Seminary Fen in Spring, Prepared 6/4/13 by Sam Wetterlin; updated 7/28/13

Observations on Surface Water in the Seminary Fen in Spring, Prepared 6/4/13 by Sam Wetterlin; updated 7/28/13 Observations on Surface Water in the Seminary Fen in Spring, 2013 Prepared 6/4/13 by Sam Wetterlin; updated 7/28/13 Ordinarily, a calcareous fen is primarily dependent on upwelling mineral-rich, oxygen-poor

More information

27. Running Water I (p ; )

27. Running Water I (p ; ) 27. Running Water I (p. 424-436; 440-444) Hydrosphere How much of the Earth s surface is covered by water? Earth's water is collectively called the and is stored in a number of so-called as follows: 1.

More information

design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards.

design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards. design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards. In addition to the field inspection, Associated Engineers, Inc.

More information

Appendix 1: UK climate projections

Appendix 1: UK climate projections Appendix 1: UK climate projections The UK Climate Projections 2009 provide the most up-to-date estimates of how the climate may change over the next 100 years. They are an invaluable source of information

More information

mountain rivers fixed channel boundaries (bedrock banks and bed) high transport capacity low storage input output

mountain rivers fixed channel boundaries (bedrock banks and bed) high transport capacity low storage input output mountain rivers fixed channel boundaries (bedrock banks and bed) high transport capacity low storage input output strong interaction between streams & hillslopes Sediment Budgets for Mountain Rivers Little

More information

Stream Geomorphology. Leslie A. Morrissey UVM July 25, 2012

Stream Geomorphology. Leslie A. Morrissey UVM July 25, 2012 Stream Geomorphology Leslie A. Morrissey UVM July 25, 2012 What Functions do Healthy Streams Provide? Flood mitigation Water supply Water quality Sediment storage and transport Habitat Recreation Transportation

More information

Hydrologic Forecast Centre Manitoba Infrastructure, Winnipeg, Manitoba. MARCH OUTLOOK REPORT FOR MANITOBA March 23, 2018

Hydrologic Forecast Centre Manitoba Infrastructure, Winnipeg, Manitoba. MARCH OUTLOOK REPORT FOR MANITOBA March 23, 2018 Page 1 of 21 Hydrologic Forecast Centre Manitoba Infrastructure, Winnipeg, Manitoba MARCH OUTLOOK REPORT FOR MANITOBA March 23, 2018 Overview The March Outlook Report prepared by the Hydrologic Forecast

More information

7.3 Sediment Delivery Analysis

7.3 Sediment Delivery Analysis 7.3 Sediment Delivery Analysis In order to evaluate potential changes in sedimentation patterns that could occur due to impacts from the FCP and LPP alignments, sediment assessment models were constructed

More information

The most important equation to describe the water balance of a reservoir is the water balance: Equation 3.1

The most important equation to describe the water balance of a reservoir is the water balance: Equation 3.1 3 FLOOD PROPAGATION 3.1 Reservoir routing The most important equation to describe the water balance of a reservoir is the water balance: ds = I Q + A P E dt ( ) In finite differences form this equation

More information

Gully Erosion Part 1 GULLY EROSION AND ITS CAUSES. Introduction. The mechanics of gully erosion

Gully Erosion Part 1 GULLY EROSION AND ITS CAUSES. Introduction. The mechanics of gully erosion Gully Erosion Part 1 GULLY EROSION AND ITS CAUSES Gully erosion A complex of processes whereby the removal of soil is characterised by incised channels in the landscape. NSW Soil Conservation Service,

More information

4.17 Spain. Catalonia

4.17 Spain. Catalonia 4.17 Spain Catalonia In Spain, inundation studies are the responsibility of the respective Hydrographic Confederations of each river basin (River Basin Authorities). The actual status of inundation studies

More information

Case Study 2: Twenty-mile Creek Rock Fords

Case Study 2: Twenty-mile Creek Rock Fords Case Study : Twenty-mile Creek Rock Fords Location Crossing Description Washington. Okanagan National Forest. Methow Valley Ranger District. Chewuch river basin, East Chewuch Road. The Twenty-mile Creek

More information

Stage Discharge Tabulation for Only Orifice Flow

Stage Discharge Tabulation for Only Orifice Flow Stage Discharge Tabulation for Only Orifice Flow DEPTH STAGE DISCHARGE (meters) (feet) (meters) (feet) (m 3 /s) (ft 3 /s) 0 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 2.00 0.7 1.3 2.0 2.6 3.3 3.9 4.6

More information

GIS data classes used within the November 2013 Environmental Statement Engineering Maps

GIS data classes used within the November 2013 Environmental Statement Engineering Maps LWM-HS2-EN-DAT-000-000001 P01 22 January 2014 GIS data classes used within the November 2013 Environmental Statement Engineering Maps Document No.:LWM-HS2-EN-DAT-000-000001 Revision Author Checked by Approved

More information

IMPORTANCE OF GEOLOGIC CHARACTERIZATION FOR LEVEE FOUNDATION AND BORROW MATERIALS AS STUDIED AT THE INDIAN GRAVES LEVEE DISTRICT, ADAMS COUNTY, IL

IMPORTANCE OF GEOLOGIC CHARACTERIZATION FOR LEVEE FOUNDATION AND BORROW MATERIALS AS STUDIED AT THE INDIAN GRAVES LEVEE DISTRICT, ADAMS COUNTY, IL IMPORTANCE OF GEOLOGIC CHARACTERIZATION FOR LEVEE FOUNDATION AND BORROW MATERIALS AS STUDIED AT THE INDIAN GRAVES LEVEE DISTRICT, ADAMS COUNTY, IL Conor Watkins Missouri University of Science and Technology

More information

Hydro-engineers.ch HEC-RAS ANALAYSIS. River: L Aïre Mesfin Tewolde. Hydro-engineers.ch 23 oct. 2017

Hydro-engineers.ch HEC-RAS ANALAYSIS. River: L Aïre Mesfin Tewolde. Hydro-engineers.ch 23 oct. 2017 Hydro-engineers.ch HEC-RAS ANALAYSIS River: L Aïre Mesfin Tewolde 17 Hydro-engineers.ch 23 oct. 2017 PREPARED BY MESFIN TEWOLDE [TEMPORARY MISSION] Hydro-engineers.ch HEC-RAS ANALYSIS [January- March 2014]

More information

Dam Break Analysis Using HEC-RAS and HEC-GeoRAS A Case Study of Ajwa Reservoir

Dam Break Analysis Using HEC-RAS and HEC-GeoRAS A Case Study of Ajwa Reservoir Journal of Water Resources and Ocean Science 2016; 5(6): 108-113 http://www.sciencepublishinggroup.com/j/wros doi: 10.11648/j.wros.20160506.15 ISSN: 2328-7969 (Print); ISSN: 2328-7993 (Online) Case Report

More information

Vermont River Sensitivity Coarse Screen

Vermont River Sensitivity Coarse Screen Vermont River Sensitivity Coarse Screen Presented by Roy Schiff, Milone & MacBroom Waterbury, Vermont roys@miloneandmacbroom.com Acknowledgements Jessica Louisos, Jim MacBroom, Milone & MacBroom Evan Fitzgerald

More information