Request for bridge scour analysis for complex pier foundations

Size: px
Start display at page:

Download "Request for bridge scour analysis for complex pier foundations"

Transcription

1 Technical Memorandum To: Theresa Maahs-Henderson, Stantec Dale Grove, Stantec Keith Farquhar, HNTB Corporation From: Hugh Zeng, P.E. & Mark Abrahams, HZ United, LLC Date: 03/22/2016 RE: Request for bridge scour analysis for complex pier foundations HZU has completed the requested bridge scour analysis for complex pier foundation. Our findings are based on the updated HEC-RAS model (as discussed below). The proposed bridge geometry was provided for two design alternatives, 4-span and 5-spans bridge. Scour analysis was conducted using the procedure outlined in FHWA HEC-18 for scour at complex pier foundations. The revised HEC-RAS model included the confluence of the Baudette River and the Rainy River. A newly created junction in the HEC-RAS model represents the river confluence. Discharges of the Baudette River was obtained from the USGS Streamstat website, which incorporates USGS Regression Equation using GIS drainage boundaries and the stream gauge data. Because the drainage tributary area of the Baudette River is much smaller than that of the Rainy River, coincidental factor was considered to correlate the peak discharges from each river. The results of the HEC-RAS model with the confluence showed minor water surface increases. The Baudette River connects to the Rainy River near a right angle. The velocity is slow compared to the Rainy River. Sand delta bars formed at the mouth of the Baudette River indicate a low stream energy from the tributary. As a result, the effects of the Baudette River on the mainstream is minimum. The stream attack-angle of 18.7 was unchanged in the scour calculation. The scour calculation took into account of both contraction scour and pier scour. The contraction scour was calculated from the HEC-RAS model. HEC-18 equations were used to predict the pier scour instead of using HEC-RAS model due to the complex pier footing configurations, which consist of pile caps over pile groups. Results for the two proposed pier configuration bridges are provided below: 1

2 Table 1: Complex Pier Foundation Scour Analysis (100-yr Event) Alternative 1: Continuous Steel I- Girder, 4-Span Alternative 1: Continuous Steel I- Girder, 5-Span Contraction Scour (ft) Pier Stem Scour [ft] Pile Cap (Footing) Scour [ft] Pile Group Scour [ft] Total Scour [ft] Table 2: Complex Pier Foundation Scour Analysis (500-yr Event) Alternative 1: Continuous Steel I- Girder, 4-Span Alternative 1: Continuous Steel I- Girder, 5-Span Contraction Scour (ft) Pier Stem Scour [ft] Pile Cap (Footing) Scour [ft] Pile Group Scour [ft] Total Scour [ft] The results shown above are preliminary and subject to revision. The predicted scour depths are comparable to the 30ft scour depth, which was documented in a June 19, 2009 MnDOT memorandum. Our analysis shows only a slight difference between the two proposed pier configurations. Preliminary bridge design provides identical pier geometry for the two proposed alternatives, so the only source of variance is due to any impact in water surface and velocity in the channel at the Bridge. It should also be noted that this analysis was conducted using a pier skew at 18.7 relative to the channel thaweg. Aligning piers normal to the channel flow will effectively reduce the overall scour estimates. Detailed calculations for the complex scour analysis are attached. 2

3 Attachment A: Complex Scour Calculations for 4-span Alternative

4 S.P Scour for Complex Pier Foundations Baudette Bridge PE 3 Pier Alternative Rev Date By Ck 0 03/22/2016 MBA HZ Live-bed or clear water scour Ref: FHWA HEC-18, sect. 6.3 Live-Bed Contraction Scour V * = shear velocity in the upstream section g = Acceleration of gravity (32.2 ft/s 2 ) y 1 = average depth in the upstream main channel = ft (7.83 m) S 1 = slope of energy grade line of main channel (ft/ft) = ft/s (0.084 m/s) T = fall velocity of bed material based on the D 50, (use D 50 = 0.50 mm) for fall velocity in English units multiply T in m/s by 3.28 Use T = 10 C, ω 0.06 m/s Use live-bed scour. 1

5 100-yr Event 1. Contraction Scour Depth Contration Scour computed from HEC-RAS river analysis. Refer to HEC-RAS model for contraction scour computation and inputs < R:\1502-Baudette Br PE\Design\Calculations\HEC-RAS>. Channel Contraction Scour: Ref: HEC-18, sect. 7.5 Scour for Complex Pier y s = Total Scour from superposition of components 100-yr event 2. Pier Stem Scour Depth (7.23) Where: f = Distance between front edge of pile cap or footing and pier 9 ft. (2.74 m) a pier = pier width = 7 ft (2.13 m) h 1 = h 0 + T = height of the pier stem above the bed before scour = 0 K h pier = Coefficient to account for the height of pier stem above bed and shielding effect by pile cap overhang distance f in front of pier stem. 2

6 100-yr Event K h pier 0.32 (from figure 7.6) For 100-year event (from HEC-RAS output) WSE = ft ( m) Ground = ft ( m) y 1 = 25.7 ft (7.83 m) V 1 = 3.74 fps (1.14 m/s) K 1 = correction factor for pier nose shape; round nose = 1.0 K 2 = correction factor for angle of attack of flow; K 3 = correction factor for bed condition; (From Table 7.3, use plane bed) = 1.1 g = acceleration of gravity = 32.2 ft/s 2 3

7 3. Pile Cap (Footing) Scour Depth Use Case 2; bottom of pile cap is on or below bed 3025 Harbor Lane, Suite 121, Plymouth, MN yr Event y f = distance from the bed (after degredation, contraction scour, and pier stem scour) to the top of footing. k s = Grain roughness, use estimate D 84 for sand, 2.5 mm = ft (0.0025m) Average velocity of flow at the exposed footing (V f ) is determined using the following: (7.25) The scour component equation for the footing can be written as: (7.24) K W = wide pier factor for shallow flow, not applicable. a pc = pile cap width = 20.0 ft (6.10 m) 4

8 4. Determination of Pile Group Scour Depth Component 3025 Harbor Lane, Suite 121, Plymouth, MN yr Event Where: a proj = sum of non-overlapping projected widths of piles = 6.67 ft K sp = coefficient for pile spacing a = 1.33 ft (16 in) s = 4 ft (7.28) K sp 0.49 (from figure 7.11) 5

9 100-yr Event K m = coefficient for number of aligned rows 1.4 (from figure 7.12) (7.29) (7.30) K h pg 0.45 (from figure 7.13) (7.31) Total Pier Scour (100yr): Total Scour (100yr): 6

10 Scour Design Check Flood Frequency (500-yr) 1. Contraction Scour Depth 3025 Harbor Lane, Suite 121, Plymouth, MN yr Event Contration Scour computed from HEC-RAS river analysis. Refer to HEC-RAS model for contraction scour computation and inputs < R:\1502-Baudette Br PE\Design\Calculations\HEC-RAS>. Channel Contraction Scour: 2. Pier Stem Scour Depth Where: f = Distance between front edge of pile cap or footing and pier 9 ft. a pier = pier width = 7 ft h 1 = h 0 + T = height of the pier stem above the bed before scour = 0. K h pier = Coefficient to account for the height of pier stem above bed and shielding effect by pile cap overhang distance f in front of pier stem. 7

11 K h pier 0.32 (from figure 7.6) For 500-year event (from HEC-RAS output) WSE = ft ( m) Ground = ft ( m) y 1 = ft (8.36 m) V 1 = 4.10 fps (1.25 m/s) 3025 Harbor Lane, Suite 121, Plymouth, MN yr Event K 1 = correction factor for pier nose shape; round nose = 1.0 K 2 = correction factor for angle of attack of flow; K 3 = correction factor for bed condition; (From Table 7.3, use plane bed) = 1.1 g = acceleration of gravity = 32.2 ft/s 2 3. Pile Cap (Footing) Scour Depth Use Case 2; bottom of pile cap is on or below bed y f = distance from the bed (after degredation, contraction scour, and pier stem scour) to the top of footing. k s = Grain roughness, use estimate D 84 for sand, 2.5 mm = ft Average velocity of flow at the exposed footing (V f ) is determined using the following: 8

12 500-yr Event ft/s The scour component equation for the footing can be written as: K W = wide pier factor, not applicable. a pc = pile cap width = 20.0 ft 4. Determination of the Pile Group Scour Depth Component Where: a proj = sum of non-overlapping projected widths of piles = 6.67 ft K sp = coefficient for pile spacing a = 1.33 ft (16 in) s = 4 ft, (7.28) K sp 0.49 (from figure 7.11) 9

13 500-yr Event K m = coefficient for number of aligned rows 1.4 (from figure 7.12) (7.29) (7.30) K h pg 0.45 (from figure 7.13) 10

14 500-yr Event (7.31) Total Pier Scour (500yr): Total Scour (500yr): 11

15 Attachment B: Complex Scour Calculations for 5-span Alternative

16 S.P Scour for Complex Pier Foundations Baudette Bridge PE 4 Pier Alternative Rev Date By Ck 0 03/22/2016 MBA HZ Live-bed or clear water scour Ref: FHWA HEC-18, sect. 6.3 Live-Bed Contraction Scour V * = shear velocity in the upstream section g = Acceleration of gravity (32.2 ft/s 2 ) y 1 = average depth in the upstream main channel = ft (7.83 m) S 1 = slope of energy grade line of main channel (ft/ft) = ft/s T = fall velocity of bed material based on the D 50, (use D 50 = 0.50 mm) for fall velocity in English units multiply T in m/s by 3.28 Use T = 10 C, ω 0.06 m/s Use live-bed scour. 1

17 100-yr Event 1. Contraction Scour Depth Contration Scour computed from HEC-RAS river analysis. Refer to HEC-RAS model for contraction scour computation and inputs < R:\1502-Baudette Br PE\Design\Calculations\HEC-RAS>. Channel Contraction Scour: Ref: HEC-18, sect. 7.5 Scour for Complex Pier y s = Total Scour from superposition of components 100-yr event 2. Pier Stem Scour Depth (7.23) Where: f = Distance between front edge of pile cap or footing and pier 9 ft. (2.74 m) a pier = pier width = 7 ft (2.13 m) h 1 = h 0 + T = height of the pier stem above the bed before scour = 0 K h pier = Coefficient to account for the height of pier stem above bed and shielding effect by pile cap overhang distance f in front of pier stem. 2

18 100-yr Event K h pier 0.32 (from figure 7.6) For 100-year event (from HEC-RAS output) WSE = ft ( m) Ground = ft ( m) y 1 = 25.7 ft (7.83 m) V 1 = 3.81 fps (1.16 m/s) K 1 = correction factor for pier nose shape; round nose = 1.0 K 2 = correction factor for angle of attack of flow; K 3 = correction factor for bed condition; (From Table 7.3, use plane bed) = 1.1 g = acceleration of gravity = 32.2 ft/s 2 3

19 3. Pile Cap (Footing) Scour Depth Use Case 2; bottom of pile cap is on or below bed 3025 Harbor Lane, Suite 121, Plymouth, MN yr Event y f = distance from the bed (after degredation, contraction scour, and pier stem scour) to the top of footing. k s = Grain roughness, use estimate D 84 for sand, 2.5 mm = ft (0.0025m) Average velocity of flow at the exposed footing (V f ) is determined using the following: (7.25) The scour component equation for the footing can be written as: (7.24) K W = wide pier factor for shallow flow, not applicable. a pc = pile cap width = 20.0 ft (6.10 m) 4

20 4. Determination of Pile Group Scour Depth Component 3025 Harbor Lane, Suite 121, Plymouth, MN yr Event Where: a proj = sum of non-overlapping projected widths of piles = 6.67 ft K sp = coefficient for pile spacing a = 1.33 ft (16 in) s = 4 ft (7.28) K sp 0.49 (from figure 7.11) 5

21 100-yr Event K m = coefficient for number of aligned rows 1.4 (from figure 7.12) (7.29) (7.30) K h pg 0.45 (from figure 7.13) (7.31) Total Pier Scour (100yr): Total Scour (100yr): 6

22 Scour Design Check Flood Frequency (500-yr) 1. Contraction Scour Depth 3025 Harbor Lane, Suite 121, Plymouth, MN yr Event Contration Scour computed from HEC-RAS river analysis. Refer to HEC-RAS model for contraction scour computation and inputs < R:\1502-Baudette Br PE\Design\Calculations\HEC-RAS>. Channel Contraction Scour: 2. Pier Stem Scour Depth Where: f = Distance between front edge of pile cap or footing and pier 9 ft. a pier = pier width = 7 ft h 1 = h 0 + T = height of the pier stem above the bed before scour = 0. K h pier = Coefficient to account for the height of pier stem above bed and shielding effect by pile cap overhang distance f in front of pier stem. 7

23 K h pier 0.32 (from figure 7.6) For 500-year event (from HEC-RAS output) WSE = ft ( m) Ground = ft ( m) y 1 = ft V 1 = 4.17 fps (1.27 m/s) 3025 Harbor Lane, Suite 121, Plymouth, MN yr Event K 1 = correction factor for pier nose shape; round nose = 1.0 K 2 = correction factor for angle of attack of flow; K 3 = correction factor for bed condition; (From Table 7.3, use plane bed) = 1.1 g = acceleration of gravity = 32.2 ft/s 2 3. Pile Cap (Footing) Scour Depth Use Case 2; bottom of pile cap is on or below bed y f = distance from the bed (after degredation, contraction scour, and pier stem scour) to the top of footing. k s = Grain roughness, use estimate D 84 for sand, 2.5 mm = ft Average velocity of flow at the exposed footing (V f ) is determined using the following: 8

24 500-yr Event ft/s The scour component equation for the footing can be written as: K W = wide pier factor, not applicable. a pc = pile cap width = 20.0 ft 4. Determination of the Pile Group Scour Depth Component Where: a proj = sum of non-overlapping projected widths of piles = 6.67 ft K sp = coefficient for pile spacing a = 1.33 ft (16 in) s = 4 ft, (7.28) K sp 0.49 (from figure 7.11) 9

25 500-yr Event K m = coefficient for number of aligned rows 1.4 (from figure 7.12) (7.29) (7.30) K h pg 0.45 (from figure 7.13) 10

26 500-yr Event (7.31) Total Pier Scour (500yr): Total Scour (500yr): 11

A STUDY OF LOCAL SCOUR AT BRIDGE PIERS OF EL-MINIA

A STUDY OF LOCAL SCOUR AT BRIDGE PIERS OF EL-MINIA A STUDY OF LOCAL SCOUR AT BRIDGE PIERS OF EL-MINIA Dr. Gamal A. Sallam 1 and Dr. Medhat Aziz 2 ABSTRACT Bridges are critical structures that require a substantial investment to construct and serve an important

More information

LOMR SUBMITTAL LOWER NEHALEM RIVER TILLAMOOK COUNTY, OREGON

LOMR SUBMITTAL LOWER NEHALEM RIVER TILLAMOOK COUNTY, OREGON LOMR SUBMITTAL LOWER NEHALEM RIVER TILLAMOOK COUNTY, OREGON Prepared for: TILLAMOOK COUNTY DEPARTMENT OF COMMUNITY DEVELOPMENT 1510-B THIRD STREET TILLAMOOK, OR 97141 Prepared by: 10300 SW GREENBURG ROAD,

More information

LOMR SUBMITTAL LOWER NESTUCCA RIVER TILLAMOOK COUNTY, OREGON

LOMR SUBMITTAL LOWER NESTUCCA RIVER TILLAMOOK COUNTY, OREGON LOMR SUBMITTAL LOWER NESTUCCA RIVER TILLAMOOK COUNTY, OREGON Prepared for: TILLAMOOK COUNTY DEPARTMENT OF COMMUNITY DEVELOPMENT 1510-B THIRD STREET TILLAMOOK, OR 97141 Prepared by: 10300 SW GREENBURG ROAD,

More information

Pressure Head: Pressure head is the height of a column of water that would exert a unit pressure equal to the pressure of the water.

Pressure Head: Pressure head is the height of a column of water that would exert a unit pressure equal to the pressure of the water. Design Manual Chapter - Stormwater D - Storm Sewer Design D- Storm Sewer Sizing A. Introduction The purpose of this section is to outline the basic hydraulic principles in order to determine the storm

More information

Field Observations and One-Dimensional Flow Modeling of Summit Creek in Mack Park, Smithfield, Utah

Field Observations and One-Dimensional Flow Modeling of Summit Creek in Mack Park, Smithfield, Utah Intermountain Center for River Rehabilitation and Restoration, Utah State University 31 July 2018 Field Observations and One-Dimensional Flow Modeling of Summit Creek in Mack Park, Smithfield, Utah I.

More information

MODELING OF LOCAL SCOUR AROUND AL-KUFA BRIDGE PIERS Saleh I. Khassaf, Saja Sadeq Shakir

MODELING OF LOCAL SCOUR AROUND AL-KUFA BRIDGE PIERS Saleh I. Khassaf, Saja Sadeq Shakir ISSN 2320-9100 11 International Journal of Advance Research, IJOAR.org Volume 1, Issue 8,August 2013, Online: ISSN 2320-9100 MODELING OF LOCAL SCOUR AROUND AL-KUFA BRIDGE PIERS Saleh I. Khassaf, Saja Sadeq

More information

Evaluation of Scour Depth around Bridge Piers with Various Geometrical Shapes

Evaluation of Scour Depth around Bridge Piers with Various Geometrical Shapes Evaluation of Scour Depth around Bridge Piers with Various Geometrical Shapes Dr. P. D. Dahe * Department of Civil Engineering, SGGSIE&T, Vishnupuri, Nanded (Maharashtra) S. B. Kharode Department of Civil

More information

YELLOWSTONE RIVER FLOOD STUDY REPORT TEXT

YELLOWSTONE RIVER FLOOD STUDY REPORT TEXT YELLOWSTONE RIVER FLOOD STUDY REPORT TEXT TECHNICAL REPORT Prepared for: City of Livingston 411 East Callender Livingston, MT 59047 Prepared by: Clear Creek Hydrology, Inc. 1627 West Main Street, #294

More information

STREAM RESTORATION AWRA Summer Specialty Conference, GIS and Water Resources IX

STREAM RESTORATION AWRA Summer Specialty Conference, GIS and Water Resources IX STREAM RESTORATION 2016 AWRA Summer Specialty Conference, GIS and Water Resources IX Innovative Use of 2D Hydraulic Modeling in Stream Restoration Design Presented by: Li Gao, PE and Robert Scrafford,

More information

UPPER COSUMNES RIVER FLOOD MAPPING

UPPER COSUMNES RIVER FLOOD MAPPING UPPER COSUMNES RIVER FLOOD MAPPING DRAFT BASIC DATA NARRATIVE FLOOD INSURANCE STUDY SACRAMENTO COUTY, CALIFORNIA Community No. 060262 November 2008 Prepared By: CIVIL ENGINEERING SOLUTIONS, INC. 1325 Howe

More information

Technical Memorandum No Sediment Model

Technical Memorandum No Sediment Model Pajaro River Watershed Study in association with Technical Memorandum No. 1.2.9 Sediment Model Task: Development of Sediment Model To: PRWFPA Staff Working Group Prepared by: Gregory Morris and Elsie Parrilla

More information

PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0

PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0 PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0 LYCOMING COUNTY S.R.15, SECTION C41 FINAL HYDROLOGIC AND HYDRAULIC REPORT STEAM VALLEY RUN STREAM RELOCATION DATE: June, 2006 REVISED:

More information

Design Hydraulic Study. Bridge 09C-0134, Blairsden-Graeagle Road over Middle Fork Feather River. Plumas County. Prepared for:

Design Hydraulic Study. Bridge 09C-0134, Blairsden-Graeagle Road over Middle Fork Feather River. Plumas County. Prepared for: Design Hydraulic Study Bridge 09C-0134, Blairsden-Graeagle Road over Middle Fork Feather River Plumas County Prepared for: Quincy Engineering, Inc 3247 Ramos Circle Sacramento, CA 95827-2501 Prepared by:

More information

DRAFT Design Hydraulic Study. Bridge 04C-0055, Mattole Road Bridge over Mattole River at Honeydew. Humboldt County. Prepared for:

DRAFT Design Hydraulic Study. Bridge 04C-0055, Mattole Road Bridge over Mattole River at Honeydew. Humboldt County. Prepared for: DRAFT Design Hydraulic Study Bridge 04C-0055, Mattole Road Bridge over Mattole River at Honeydew Humboldt County Prepared for: Morrison Structures Incorporated 1890 Park Marina Drive, Suite 104 Redding,

More information

Sediment Transport Analysis for Stream Restoration Design: The Good, the Bad, and the Ugly.

Sediment Transport Analysis for Stream Restoration Design: The Good, the Bad, and the Ugly. Sediment Transport Analysis for Stream Restoration Design: The Good, the Bad, and the Ugly. Brett Jordan Phd, PE HydroGeo Designs LLC. Land and Water Services Inc. THE GOOD THE BAD THE UGLY THE GOOD THE

More information

Technical Memorandum. To: From: Copies: Date: 10/19/2017. Subject: Project No.: Greg Laird, Courtney Moore. Kevin Pilgrim and Travis Stroth

Technical Memorandum. To: From: Copies: Date: 10/19/2017. Subject: Project No.: Greg Laird, Courtney Moore. Kevin Pilgrim and Travis Stroth Technical Memorandum To: From: Greg Laird, Courtney Moore Kevin Pilgrim and Travis Stroth 5777 Central Avenue Suite 228 Boulder, CO 80301 www.otak.com Copies: [Electronic submittal] Date: 10/19/2017 Subject:

More information

APPENDIX B HYDROLOGY

APPENDIX B HYDROLOGY APPENDIX B HYDROLOGY TABLE OF CONTENTS 1.0 INTRODUCTION... 1 2.0 PROBABLE MAXIMUM PRECIPITATION (PMP)... 1 3.0 DESIGN FLOW CALCULATION... 1 4.0 DIVERSION CHANNEL SIZING... 2 5.0 REFERENCES... 4 LIST OF

More information

!"#$%&&'()*+#$%(,-./0*)%(!

!#$%&&'()*+#$%(,-./0*)%(! 8:30 Sign in Hoosic River Revival Coalition!"#$%&&'()*+#$%(,-./0*)%(! 12-#30+4/#"5-(60 9:00 Welcome and Introductions 9:15 Goals for Today s Program: A Description of the Planning Process 9:30 First Session:

More information

Diego Burgos. Geology 394. Advisors: Dr. Prestegaard. Phillip Goodling

Diego Burgos. Geology 394. Advisors: Dr. Prestegaard. Phillip Goodling Sediment Transport into an Urban Tributary Junction Diego Burgos Geology 394 Advisors: Dr. Prestegaard Phillip Goodling 1 Abstract Tributary junctions are an important component of stream morphology and

More information

Technical Memorandum No

Technical Memorandum No Pajaro River Watershed Study in association with Technical Memorandum No. 1.2.10 Task: Evaluation of Four Watershed Conditions - Sediment To: PRWFPA Staff Working Group Prepared by: Gregory Morris and

More information

NUMERICAL ANALYSIS OF THE BED MORPHOLOGY IN THE REACH BETWEEN CABRUTA AND CAICARA IN ORINOCO RIVER.

NUMERICAL ANALYSIS OF THE BED MORPHOLOGY IN THE REACH BETWEEN CABRUTA AND CAICARA IN ORINOCO RIVER. NUMERICAL ANALYSIS OF THE BED MORPHOLOGY IN THE REACH BETWEEN CABRUTA AND CAICARA IN ORINOCO RIVER. Raul A CABRITA F MEE13634 Supervisor: Shinji EGASHIRA ABSTRACT The present study aims to evaluate numerically

More information

Countermeasure Calculations and Design

Countermeasure Calculations and Design Countermeasure Calculations and Design Summarized from Bridge Scour and Stream Instability Countermeasures, Experience, Selection, and Design Guidance, Second Edition, Publication No. FHWA NHI 01-003,

More information

Evaluation and Incorporation of USACE HEC-RAS Model of Chicago Waterway System into the Development of the North Branch DWP

Evaluation and Incorporation of USACE HEC-RAS Model of Chicago Waterway System into the Development of the North Branch DWP M E M O R A N D U M Evaluation and Incorporation of USACE HEC-RAS Model of Chicago Waterway System into the Development of the North Branch DWP TO: FROM: Joseph Spradling, PE, HDR Steven Vassos, PE, FluidClarity

More information

HEC-RAS Reservoir Transport Simulation of Three Reservoirs in the Lower Susquehanna River Basin. Mike Langland and Ed Koerkle

HEC-RAS Reservoir Transport Simulation of Three Reservoirs in the Lower Susquehanna River Basin. Mike Langland and Ed Koerkle HEC-RAS Reservoir Transport Simulation of Three Reservoirs in the Lower Susquehanna River Basin Mike Langland and Ed Koerkle Topics Background / Project Objectives Data Selection - Sediment and Geometric

More information

ARMSTRONG COUNTY, PA

ARMSTRONG COUNTY, PA ARMSTRONG COUNTY, PA Revised Preliminary DFIRM Mapping March 31, 2013 Kevin Donnelly, P.E., CFM GG3, Greenhorne & O Mara, Inc. Presentation Agenda Armstrong County DFIRM Overview - June 25, 2010 DFIRM

More information

Modified Level II Streambed-Scour Analysis for Structure Crossing Little Eagle Creek and I-65 in Marion County, Indiana

Modified Level II Streambed-Scour Analysis for Structure Crossing Little Eagle Creek and I-65 in Marion County, Indiana Modified Level II Streambed-Scour Analysis for Structure 1-65-120-6016 Crossing Little Eagle Creek and I-65 in Marion County, Indiana By ROBERT L. MILLER, BRET A. ROBINSON, and DAVID C. VOELKER Prepared

More information

Section 4: Model Development and Application

Section 4: Model Development and Application Section 4: Model Development and Application The hydrologic model for the Wissahickon Act 167 study was built using GIS layers of land use, hydrologic soil groups, terrain and orthophotography. Within

More information

TSEGI WASH 50% DESIGN REPORT

TSEGI WASH 50% DESIGN REPORT TSEGI WASH 50% DESIGN REPORT 2/28/2014 Daniel Larson, Leticia Delgado, Jessica Carnes I Table of Contents Acknowledgements... IV 1.0 Project Description... 1 1.1 Purpose... 1 Figure 1. Erosion of a Headcut...

More information

HYDROLOGY AND HYDRAULICS MUSKEG RIVER BRIDGE

HYDROLOGY AND HYDRAULICS MUSKEG RIVER BRIDGE PUBLIC WORKS CANADA HYDROLOGY AND HYDRAULICS MUSKEG RIVER BRIDGE KILOMETRE 207.9, LIARD HIGKWAY December 1978 I I f I I I I # Bolter Parish Trimble Ltd. ONLIULTINO Public Works, Canada, 9925-109 Street,

More information

Debris Loads, Bridge/Culvert failure, and Climate Change Identifying stream reaches most susceptible to climate-exacerbated debris load

Debris Loads, Bridge/Culvert failure, and Climate Change Identifying stream reaches most susceptible to climate-exacerbated debris load Debris Loads, Bridge/Culvert failure, and Climate Change Identifying stream reaches most susceptible to climate-exacerbated debris load Seth Lawler, Mathew Mampara, Kristine Mosuela, Mathini Sreetharan

More information

Big Wood River. General Information

Big Wood River. General Information General Information The flows out of the southern portion of the Sawtooth National Recreation Area in central Idaho. The study reach is about a,200 ft length of river about.5 miles upstream from the discontinued

More information

FHWA/IN/JTRP-2000/12. Final Report. D. A. Lyn E. Neseem A. Ramachandra Rao A. G. Altschaeffl

FHWA/IN/JTRP-2000/12. Final Report. D. A. Lyn E. Neseem A. Ramachandra Rao A. G. Altschaeffl FHWA/IN/JTRP-2000/12 Final Report A LABORATORY SENSITIVITY STUDY OF HYDRAULIC PARAMETERS IMPORTANT IN THE DEPLOYMENT OF FIXED-IN-PLACE SCOUR-MONITORING DEVICES D. A. Lyn E. Neseem A. Ramachandra Rao A.

More information

CR AAO Bridge. Dead River Flood & Natural Channel Design. Mitch Koetje Water Resources Division UP District

CR AAO Bridge. Dead River Flood & Natural Channel Design. Mitch Koetje Water Resources Division UP District CR AAO Bridge Dead River Flood & Natural Channel Design Mitch Koetje Water Resources Division UP District Old County Road AAO Bridge Map courtesy of Marquette County Silver Lake Basin McClure Basin

More information

Ways To Identify Background Verses Accelerated Erosion

Ways To Identify Background Verses Accelerated Erosion Ways To Identify Background Verses Accelerated Erosion Establish Background Condition From Old Ground Photos, Aerial Photos, and Maps Compare Rate Over Time At the Same Location, or for Reaches Channel

More information

Summary of Hydraulic and Sediment-transport. Analysis of Residual Sediment: Alternatives for the San Clemente Dam Removal/Retrofit Project,

Summary of Hydraulic and Sediment-transport. Analysis of Residual Sediment: Alternatives for the San Clemente Dam Removal/Retrofit Project, Appendix N SUMMARY OF HYDRAULIC AND SEDIMENT-TRANSPORT ANALYSIS OF RESIDUAL SEDIMENT: ALTERNATIVES FOR THE SAN CLEMENTE DAM REMOVAL/RETROFIT PROJECT, CALIFORNIA the San Clemente Dam Removal/Retrofit Project,

More information

(3) Sediment Movement Classes of sediment transported

(3) Sediment Movement Classes of sediment transported (3) Sediment Movement Classes of sediment transported Dissolved load Suspended (and wash load ) Important for scouring algae Bedload (5-10% total load Moves along bed during floods Source of crushing for

More information

EXAMPLES (SEDIMENT TRANSPORT) AUTUMN 2018

EXAMPLES (SEDIMENT TRANSPORT) AUTUMN 2018 EXAMPLES (SEDIMENT TRANSPORT) AUTUMN 2018 Q1. Using Cheng s formula estimate the settling velocity of a sand particle of diameter 1 mm in: (a) air; (b) water. Q2. Find the critical Shields parameter diameter

More information

Modelling of flow and sediment transport in rivers and freshwater deltas Peggy Zinke

Modelling of flow and sediment transport in rivers and freshwater deltas Peggy Zinke 1 Modelling of flow and sediment transport in rivers and freshwater deltas Peggy Zinke with contributions from Norwegian and international project partners 2 Outline 1. Introduction 2. Basic ideas of flow

More information

Estimating Scour. CIVE 510 October 21 st, 2008

Estimating Scour. CIVE 510 October 21 st, 2008 Estimating Scour CIVE 510 October 21 st, 2008 1 Causes of Scour 2 Site Stability 3 Mass Failure Downward movement of large and intact masses of soil and rock Occurs when weight on slope exceeds the shear

More information

Overview of fluvial and geotechnical processes for TMDL assessment

Overview of fluvial and geotechnical processes for TMDL assessment Overview of fluvial and geotechnical processes for TMDL assessment Christian F Lenhart, Assistant Prof, MSU Research Assoc., U of M Biosystems Engineering Fluvial processes in a glaciated landscape Martin

More information

New computation method for flood flows and bed variations in a low-lying river with complex river systems

New computation method for flood flows and bed variations in a low-lying river with complex river systems River Flow 2014 Schleiss et al. (Eds) 2014 Taylor & Francis Group, London, ISBN 978-1-138-02674-2 New computation method for flood flows and bed variations in a low-lying river with complex river systems

More information

(3) Sediment Movement Classes of sediment transported

(3) Sediment Movement Classes of sediment transported 9/17/15 (3) Sediment Movement Classes of sediment transported Dissolved load Suspended load Important for scouring algae Bedload (5-10% total load) Moves along bed during floods Source of crushing for

More information

Factors affecting confluence scour

Factors affecting confluence scour & Wang (eds) River Sedimentation 1999., Balkema, Rotterdam. ISBN 9 9 3. 17 19 Factors affecting confluence scour R. B. Rezaur & A. W. Jayawardena. Department of Civil Engineering, The University of Hong

More information

Degradation Concerns related to Bridge Structures in Alberta

Degradation Concerns related to Bridge Structures in Alberta Degradation Concerns related to Bridge Structures in Alberta Introduction There has been recent discussion regarding the identification and assessment of stream degradation in terms of how it relates to

More information

Squaw Creek. General Information

Squaw Creek. General Information General Information is a tributary to the Salmon River. It enters the north side of the river about 0 miles downstream of North Fork, Idaho. The study reach is about a 30 ft length of stream about 2 miles

More information

Fish Passage at Road Crossings

Fish Passage at Road Crossings Fish Passage at Road Crossings 1 Crossing Design Workshop Outline 1:00 to 2:00 Intro, Design Overview, Channel Width 2:00 to 2:15 Break 2:15 to 3:15 No-Slope, Stream Simulation Design 3:15 to 3:30 Break

More information

STUDY ON LOCAL SCOURING AT SURAMADU BRIDGE PIERS FOR STRUCTURAL INTEGRITY MONITORING

STUDY ON LOCAL SCOURING AT SURAMADU BRIDGE PIERS FOR STRUCTURAL INTEGRITY MONITORING Proceedings of the 7 th International Conference on Asian and Pacific Coasts (APAC 03) ali, Indonesia, September 4-6, 03 STUDY ON LOCAL SCOURING AT SURAMADU BRIDGE PIERS FOR STRUCTURAL INTEGRITY MONITORING

More information

Fluvial Processes in River Engineering

Fluvial Processes in River Engineering Fluvial Processes in River Engineering Howard H. Chang San Diego State University... A WILEY-INTERSCIENCE PUBLTCATION John Wiley & Sons New York Chicbester Brisbane Toronto Singapore CONTENTS PARTI FLUVIAL

More information

Highland Lake Bathymetric Survey

Highland Lake Bathymetric Survey Highland Lake Bathymetric Survey Final Report, Prepared For: The Town of Highland Lake 612 Lakeshore Drive Oneonta, AL 35121 Prepared By: Tetra Tech 2110 Powers Ferry Road SE Suite 202 Atlanta, GA 30339

More information

Lecture 10: River Channels

Lecture 10: River Channels GEOG415 Lecture 10: River Channels 10-1 Importance of channel characteristics Prediction of flow was the sole purpose of hydrology, and still is a very important aspect of hydrology. - Water balance gives

More information

Vegetation effects on river hydraulics. Johannes J. (Joe) DeVries David Ford Consulting Engineers, Inc. Sacramento, CA

Vegetation effects on river hydraulics. Johannes J. (Joe) DeVries David Ford Consulting Engineers, Inc. Sacramento, CA Vegetation effects on river hydraulics Johannes J. (Joe) DeVries David Ford Consulting Engineers, Inc. Sacramento, CA jjdevries@ford-consulting.com SAC05 D2P31 RM 99.0L VIEW UPSTREAM AT UPSTREAM END DWR

More information

Analysis of the Cause for the Collapse of a Temporary Bridge Using Numerical Simulation

Analysis of the Cause for the Collapse of a Temporary Bridge Using Numerical Simulation Engineering, 2013, 5, 997-1005 Published Online December 2013 (http://www.scirp.org/journal/eng) http://dx.doi.org/10.4236/eng.2013.512121 Analysis of the Cause for the Collapse of a Temporary Bridge Using

More information

JACINTO. Sediment Transport and Scour Analysis San Jacinto River, Stage 4 North and South Levees SAN ENGINEERING STUDY. Prepared for: Prepared by:

JACINTO. Sediment Transport and Scour Analysis San Jacinto River, Stage 4 North and South Levees SAN ENGINEERING STUDY. Prepared for: Prepared by: ENGINEERING STUDY Sediment Transport and Scour Analysis San Jacinto River, Stage 4 North and South Levees Prepared for: Prepared by: RIVERSIDE COUNTY FLOOD CONTROL & WATER CONSERVATION DISTRICT & SAN JACINTO

More information

Sediment transport and river bed evolution

Sediment transport and river bed evolution 1 Chapter 1 Sediment transport and river bed evolution 1.1 What is the sediment transport? What is the river bed evolution? System of the interaction between flow and river beds Rivers transport a variety

More information

The last three sections of the main body of this report consist of:

The last three sections of the main body of this report consist of: Threatened and Endangered Species Geological Hazards Floodplains Cultural Resources Hazardous Materials A Cost Analysis section that provides comparative conceptual-level costs follows the Environmental

More information

Geomorphology 5. Stream Sediment Stream Sediment

Geomorphology 5. Stream Sediment Stream Sediment Geomorphology 5. Stream Sediment 1 Name 47 Points LEARNING OUTCOMES 5. Stream Sediment By the end of this assignment you should be able to: Describe the relationship between particle size and critical

More information

FOLLOW-UP ON CHANNELIZATION IN SPRING CREEK SUB-WATERSHED

FOLLOW-UP ON CHANNELIZATION IN SPRING CREEK SUB-WATERSHED FOLLOW-UP ON CHANNELIZATION IN SPRING CREEK SUB-WATERSHED Justin R. Beebe, Department of Earth Sciences, University of South Alabama, Mobile, AL 36688. jrb308@jaguar1.usouthal.edu. Spring Creek is a tributary

More information

Streams. Stream Water Flow

Streams. Stream Water Flow CHAPTER 14 OUTLINE Streams: Transport to the Oceans Does not contain complete lecture notes. To be used to help organize lecture notes and home/test studies. Streams Streams are the major geological agents

More information

Swift Creek Sediment Management Action Plan (SCSMAP)

Swift Creek Sediment Management Action Plan (SCSMAP) Swift Creek Sediment Management Action Plan (SCSMAP) PHASE 2 PROJECT PLAN PROPOSAL Whatcom County Public Works Department 322 N. Commercial Street, Suite 210 Bellingham, WA 98225 (360) 676-6692 June 2013

More information

Rivers and Streams. Streams. Hydrologic Cycle. Drainage Basins and Divides. Colorado River Drainage Basin. Colorado Drainage Basins.

Rivers and Streams. Streams. Hydrologic Cycle. Drainage Basins and Divides. Colorado River Drainage Basin. Colorado Drainage Basins. Chapter 14 Hydrologic Cycle Rivers and Streams Streams A stream is a body of water that is confined in a channel and moves downhill under the influence of gravity. This definition includes all sizes of

More information

Vermont Stream Geomorphic Assessment. Appendix J. Vermont Regional Hydraulic Geometry Curves

Vermont Stream Geomorphic Assessment. Appendix J. Vermont Regional Hydraulic Geometry Curves Vermont Stream Geomorphic Assessment Appendix J Vermont Regional Hydraulic Geometry Curves River Management Program Vermont Water Quality Division November, 2001 Natural Resources - J0 - VT Agency of Background

More information

Appendix I. Dredged Volume Estimates. Draft Contractor Document: Subject to Continuing Agency Review

Appendix I. Dredged Volume Estimates. Draft Contractor Document: Subject to Continuing Agency Review Appendix I Dredged Volume Estimates Draft Contractor Document: Subject to Continuing Agency Review Interoffice Correspondence Date: April 6, 2007 To: L. Bossi (WHI) Copy: S. Thompson (WHI), B. Fidler (NNJ)

More information

U.S. Army Corps of Engineers Detroit District. Sediment Trap Assessment Saginaw River, Michigan

U.S. Army Corps of Engineers Detroit District. Sediment Trap Assessment Saginaw River, Michigan U.S. Army Corps of Engineers Detroit District December 2001 December 2001 This report has been prepared for USACE, Detroit District by: W.F. BAIRD & ASSOCIATES LTD. 2981 YARMOUTH GREENWAY MADISON, WISCONSIN

More information

Growing and decaying processes and resistance of sand waves in the vicinity of the Tone River mouth

Growing and decaying processes and resistance of sand waves in the vicinity of the Tone River mouth Advances in River Sediment Research Fukuoka et al. (eds) 2013 Taylor & Francis Group, London, ISBN 978-1-138-00062-9 Growing and decaying processes and resistance of sand waves in the vicinity of the Tone

More information

Development of a Fluvial Erosion Hazard Mitigation Program for Indiana

Development of a Fluvial Erosion Hazard Mitigation Program for Indiana Development of a Fluvial Erosion Hazard Mitigation Program for Indiana Indiana Watersheds Webinar Series October 12,2011 Robert Barr Center for Earth and Environmental Science Department of Earth Sciences

More information

EXPERIMENTAL STUDY OF BACKWATER RISE DUE TO BRIDGE PIERS AS FLOW OBSTRUCTIONS

EXPERIMENTAL STUDY OF BACKWATER RISE DUE TO BRIDGE PIERS AS FLOW OBSTRUCTIONS Tenth International Water Technology Conference, IWTC1 6, Alexandria, Egypt 19 EXPERIMENTAL STUDY OF BACKWATER RISE DUE TO BRIDGE PIERS AS FLOW OBSTRUCTIONS Kassem Salah El-Alfy Associate Prof., Irrigation

More information

1.060 Engineering Mechanics II Spring Problem Set 8

1.060 Engineering Mechanics II Spring Problem Set 8 1.060 Engineering Mechanics II Spring 2006 Due on Monday, May 1st Problem Set 8 Important note: Please start a new sheet of paper for each problem in the problem set. Write the names of the group members

More information

COMPARISON OF LABORATORY AND FIELD MEASUREMENTS OF BRIDGE PIER SCOUR

COMPARISON OF LABORATORY AND FIELD MEASUREMENTS OF BRIDGE PIER SCOUR COMPARISON OF LABORATORY AND FIELD MEASUREMENTS OF BRIDGE PIER SCOUR LEE, SEUNGOH, STURM, T. W., School of Civil and Environ. Engrg., Georgia Institute of Technology Atlanta, GA 30332-0512 USA GOTVALD,

More information

Addressing the Impact of Road-Stream Crossing Structures on the Movement of Aquatic Organisms

Addressing the Impact of Road-Stream Crossing Structures on the Movement of Aquatic Organisms Scott Jackson University of Massachusetts Amherst Addressing the Impact of Road-Stream Crossing Structures on the Movement of Aquatic Organisms Dams Sub-standard Culverts Excessive Velocities Inlet Drop

More information

Preliminary Hydraulic Report

Preliminary Hydraulic Report Tarrant County, Texas Preliminary Hydraulic Report Prepared for: Texas Department of Transportation Fort Worth District Prepared by: AECOM Corporation Scott C. Williams, P.E. No. 101334, Date 2009 This

More information

3 Theoretical Basis for SAM.sed Calculations

3 Theoretical Basis for SAM.sed Calculations 3 Theoretical Basis for SAM.sed Calculations Purpose Sediment transport functions can be used to calculate the bed material portion of the sediment discharge rating curve. This rating curve can then be

More information

Geomorphology Geology 450/750 Spring Fluvial Processes Project Analysis of Redwood Creek Field Data Due Wednesday, May 26

Geomorphology Geology 450/750 Spring Fluvial Processes Project Analysis of Redwood Creek Field Data Due Wednesday, May 26 Geomorphology Geology 450/750 Spring 2004 Fluvial Processes Project Analysis of Redwood Creek Field Data Due Wednesday, May 26 This exercise is intended to give you experience using field data you collected

More information

Evaluation of flood discharge hydrographs and bed variations in a channel network on the Ota River delta, Japan

Evaluation of flood discharge hydrographs and bed variations in a channel network on the Ota River delta, Japan 3 Floods: From Risk to Opportunity (IAHS Publ. 357, 3). Evaluation of flood discharge hydrographs and bed variations in a channel network on the Ota River delta, Japan T. GOTOH, S. FUKUOKA & R. TANAKA

More information

Erosion Surface Water. moving, transporting, and depositing sediment.

Erosion Surface Water. moving, transporting, and depositing sediment. + Erosion Surface Water moving, transporting, and depositing sediment. + Surface Water 2 Water from rainfall can hit Earth s surface and do a number of things: Slowly soak into the ground: Infiltration

More information

GEOL 652. Poudre River Fieldtrip

GEOL 652. Poudre River Fieldtrip GEOL 652. Poudre River Fieldtrip One of the more difficult variables to measure and/or estimate when studying flow in natural channels is that of roughness. Roughness, usually approximated with Manning

More information

June 9, R. D. Cook, P.Eng. Soils Engineer Special Services Western Region PUBLIC WORKS CANADA WESTERN REGION REPORT ON

June 9, R. D. Cook, P.Eng. Soils Engineer Special Services Western Region PUBLIC WORKS CANADA WESTERN REGION REPORT ON PUBLIC WORKS CANADA WESTERN REGION REPORT ON GEOTECHNICAL INVESTIGATION PROPOSED MARTIN RIVER BRIDGE MILE 306.7 MACKENZIE HIGHWAY Submitted by : R. D. Cook, P.Eng. Soils Engineer Special Services Western

More information

HYDROLOGIC AND HYDRAULIC REPORT FOR SR. 0522, SECTION 5BN ALONG BLACKLOG CREEK CROMWELL TOWNSHIP HUNTINGDON COUNTY. Prepared for:

HYDROLOGIC AND HYDRAULIC REPORT FOR SR. 0522, SECTION 5BN ALONG BLACKLOG CREEK CROMWELL TOWNSHIP HUNTINGDON COUNTY. Prepared for: HYDROLOGIC AND HYDRAULIC REPORT FOR SR. 0522, SECTION 5BN ALONG BLACKLOG CREEK CROMWELL TOWNSHIP Prepared for: KCI Technologies, Inc. Mechanicsburg, PA and Pennsylvania Department of Transportation Engineering

More information

APPENDIX A. Watershed Delineation and Stream Network Defined from WMS

APPENDIX A. Watershed Delineation and Stream Network Defined from WMS APPENDIX A Watershed Delineation and Stream Network Defined from WMS Figure A.1. Subbasins Delineation and Stream Network for Goodwin Creek Watershed APPENDIX B Summary Statistics of Monthly Peak Discharge

More information

L OWER N OOKSACK R IVER P ROJECT: A LTERNATIVES A NALYSIS A PPENDIX A: H YDRAULIC M ODELING. PREPARED BY: LandC, etc, LLC

L OWER N OOKSACK R IVER P ROJECT: A LTERNATIVES A NALYSIS A PPENDIX A: H YDRAULIC M ODELING. PREPARED BY: LandC, etc, LLC L OWER N OOKSACK R IVER P ROJECT: A LTERNATIVES A NALYSIS A PPENDIX A: H YDRAULIC M ODELING PREPARED BY: LandC, etc, LLC TABLE OF CONTENTS 1 Introduction... 1 2 Methods... 1 2.1 Hydraulic Model... 1 2.2

More information

L.O: SLOWING STREAMS DEPOSIT (SORT) SEDIMENT HORIZONTALLY BY SIZE.

L.O: SLOWING STREAMS DEPOSIT (SORT) SEDIMENT HORIZONTALLY BY SIZE. L.O: SLOWING STREAMS DEPOSIT (SORT) SEDIMENT HORIZONTALLY BY SIZE. 1. Base your answer to the following question on the profile shown below, which shows the pattern of horizontal sorting produced at a

More information

Las Colonias Subdivision September 2010 Flood Study

Las Colonias Subdivision September 2010 Flood Study Las Colonias Subdivision September 2010 Flood Study Curtis Beitel, P.E., CFM Scott Muchard, P.E. Project Engineer William Badini, CFM Senior Meteorologist Location Map Background Los Colonias Subdivision

More information

PRELIMINARY CULVERT ANALYSIS REPORT FOR CULVERT NO. 008-C OREGON AVENUE OVER PINEHURST CREEK

PRELIMINARY CULVERT ANALYSIS REPORT FOR CULVERT NO. 008-C OREGON AVENUE OVER PINEHURST CREEK PRELIMINARY CULVERT ANALYSIS REPORT FOR CULVERT NO. 008-C OREGON AVENUE OVER PINEHURST CREEK Prepared for The District of Columbia Department of Transportation Washington, D.C. Prepared by Parsons Transportation

More information

STABILIZATION OF THE H&CT RAILWAY STONE DAM WALTER E. SKIPWITH, PE, JOYCE CRUM, AIA AND JOHN BAUMGARTNER, PE. Introduction.

STABILIZATION OF THE H&CT RAILWAY STONE DAM WALTER E. SKIPWITH, PE, JOYCE CRUM, AIA AND JOHN BAUMGARTNER, PE. Introduction. STABILIZATION OF THE H&CT RAILWAY STONE DAM WALTER E. SKIPWITH, PE, JOYCE CRUM, AIA AND JOHN BAUMGARTNER, PE I. A. Introduction General The Old Stone Dam is located in the upper reach of Cottonwood Creek

More information

DETAILED DESCRIPTION OF STREAM CONDITIONS AND HABITAT TYPES IN REACH 4, REACH 5 AND REACH 6.

DETAILED DESCRIPTION OF STREAM CONDITIONS AND HABITAT TYPES IN REACH 4, REACH 5 AND REACH 6. DETAILED DESCRIPTION OF STREAM CONDITIONS AND HABITAT TYPES IN REACH 4, REACH 5 AND REACH 6. The Eklutna River was divided into study reaches (figure 1) prior to this site visit. Prominent geologic or

More information

Sediment and Erosion Design Guide

Sediment and Erosion Design Guide Sediment and Erosion Design Guide Sediment Transport & Bulking Factors Goals of this Session Review key principals Review basic relationships and available tools Review bulking factor relationships Purposes

More information

Upper Mississippi River Basin Environmental Management Program Workshop

Upper Mississippi River Basin Environmental Management Program Workshop Presentation to the Upper Mississippi River Basin Environmental Management Program Workshop by Michael Rodgers River Engineer US Army Corps of Engineers, St. Louis District August 17, 2007 Engineering

More information

Module 2. The Science of Surface and Ground Water. Version 2 CE IIT, Kharagpur

Module 2. The Science of Surface and Ground Water. Version 2 CE IIT, Kharagpur Module The Science of Surface and Ground Water Lesson Sediment Dynamics in Alluvial Rivers and Channels Instructional Objectives On completion of this lesson, the student shall be able to learn the following:.

More information

Project (Project No. US-CA-62-2) Maintenance Inspection and Reports (Subtask 14.1) Inspection Report No.2

Project (Project No. US-CA-62-2) Maintenance Inspection and Reports (Subtask 14.1) Inspection Report No.2 MEMORANDUM TO: FROM: Jim Well, Ducks Unlimited Mike Harvey, PhD, PG SUBJECT: M&T/ Llano Seco Fish Screen Project (Project No. US-CA-62-2) Maintenance Inspection and Reports (Subtask 14.1) Inspection Report

More information

OPEN CHANNEL FLOW. One-dimensional - neglect vertical and lateral variations in velocity. In other words, Q v = (1) A. Figure 1. One-dimensional Flow

OPEN CHANNEL FLOW. One-dimensional - neglect vertical and lateral variations in velocity. In other words, Q v = (1) A. Figure 1. One-dimensional Flow OPEN CHANNEL FLOW Page 1 OPEN CHANNEL FLOW Open Channel Flow (OCF) is flow with one boundary exposed to atmospheric pressure. The flow is not pressurized and occurs because of gravity. Flow Classification

More information

GIS in Water Resources Exercise #4 Solution

GIS in Water Resources Exercise #4 Solution GIS in Water Resources Exercise #4 Solution 1. Table giving the length of the Logan River main stream from NHDPlus Length (km) column, Landscape.gdb\NHDPlusv shape_length and Logan.gdb\Basemap\LoganMain

More information

http://water.usgs.gov/waterwatch/ Stream Flow Measurement: Velocity-Area method Stream discharge = Q = U * A Q = volumetric flow rate in [L 3 T -1 ] U= average stream velocity [L 2 T -1 ] A = cross sectional

More information

-- Lessons from a successful salmon stream and estuary relocation on Gravina Island

-- Lessons from a successful salmon stream and estuary relocation on Gravina Island Re-inventing Government Creek -- Lessons from a successful salmon stream and estuary relocation on Gravina Island Jon Houghton, Ph.D. and Derek Ormerod, M.S., P.E. - Pentec Environmental/Hart Crowser,

More information

ESTIMATING JOINT FLOW PROBABILITIES AT STREAM CONFLUENCES USING COPULAS

ESTIMATING JOINT FLOW PROBABILITIES AT STREAM CONFLUENCES USING COPULAS ESTIMATING JOINT FLOW PROBABILITIES AT STREAM CONFLUENCES USING COPULAS Roger T. Kilgore, P.E., D. WRE* Principal Kilgore Consulting and Management 2963 Ash Street Denver, CO 80207 303-333-1408 David B.

More information

GREENE COUNTY, PA. Revised Preliminary DFIRM Mapping FEMA. Kevin Donnelly, P.E., CFM GG3, Greenhorne & O Mara, Inc. April 10, 2013

GREENE COUNTY, PA. Revised Preliminary DFIRM Mapping FEMA. Kevin Donnelly, P.E., CFM GG3, Greenhorne & O Mara, Inc. April 10, 2013 GREENE COUNTY, PA Revised Preliminary DFIRM Mapping April 10, 2013 Kevin Donnelly, P.E., CFM GG3, Greenhorne & O Mara, Inc. Presentation Agenda Greene County DFIRM Overview September 30, 2010 DFIRM Countywide

More information

Beaver Creek Corridor Design and Analysis. By: Alex Previte

Beaver Creek Corridor Design and Analysis. By: Alex Previte Beaver Creek Corridor Design and Analysis By: Alex Previte Overview Introduction Key concepts Model Development Design Accuracy Conclusion Refresh v = Beaver Creek Site = Wittenberg Introduction Low head

More information

SCALING ISSUES FOR LABORATORY MODELING OF BRIDGE PIER SCOUR

SCALING ISSUES FOR LABORATORY MODELING OF BRIDGE PIER SCOUR A-2 Fourth International Conference on Scour and Erosion 2008 SCALING ISSUES FOR LABORATORY MODELING OF BRIDGE PIER SCOUR Seung Oh LEE 1 and Terry STURM 2 1 Instructor, School of Urban and Civil Engineering,

More information

Monitoring Scour Critical Bridges During Floods For Local Bridge Owners. Presented by

Monitoring Scour Critical Bridges During Floods For Local Bridge Owners. Presented by Monitoring Scour Critical Bridges During Floods For Local Bridge Owners Presented by SAFETY FIRST DO NOT ENDANGER YOURSELF OR OTHERS WHILE MONITORING BRIDGES DO NOT ENTER FLOOD WATERS FLOOD WATERS INCLUDE

More information

11/12/2014. Running Water. Introduction. Water on Earth. The Hydrologic Cycle. Fluid Flow

11/12/2014. Running Water. Introduction. Water on Earth. The Hydrologic Cycle. Fluid Flow Introduction Mercury, Venus, Earth and Mars share a similar history, but Earth is the only terrestrial planet with abundant water! Mercury is too small and hot Venus has a runaway green house effect so

More information

TECHNICAL REPORT STANDARD PAGE

TECHNICAL REPORT STANDARD PAGE TECHNICAL REPORT STANDARD PAGE 1. Report No. FHWA/LA.11/491 4. Title and Subtitle Evaluation of Design Methods to Determine Scour Depths for Bridge Structures 7. Author(s) Guoping Zhang, Shi A. Hsu, Tingzong

More information

Stream Simulation: A Simple Example

Stream Simulation: A Simple Example Stream Simulation: A Simple Example North Thompson Creek, CO Paul T. Anderson U.S.D.A. Forest Service Here s How We Started May 2011 2-1 USDA-Forest Service Here s How We Finished Forest Service Aquatic

More information