Pb1 y13 =-j10 Pb5. Pb4. y34 =-j10
|
|
- Ronald McBride
- 5 years ago
- Views:
Transcription
1 EE 55, Exam, Take-home. Due Monday, April, 06, 5:00pm. You may use class notes or any reference materials (e.g., books, etc.) that you like; however, you must work alone, i.e., you should not be communicating with anyone else about how to work the problems on this exam.. Generation planning (5 pts): Develop the complete set of equations for generation expansion plan formulation -b (GEP-b), based on the following data and assumptions. a. Plan for 30 years, at 5 year intervals (thus you should have 6 investment periods (at years 5, 0, 5, 0, 5, and 30). b. Use annual discount rate of 9%. c. Maintain a reserve of 5% above peak load. d. Assume a CO cost of $5/MT (you will need to add a term to the objective function to account for this). e. Transmission topology and data: Two comments follow Note the definitions of positive branch flow for each P bk, k=,,5. The admittances y ij are given on a 00 MVA power base. Pg Pg Pb3 y =-j0 Pb3 y4 =-j0 Pb y3 =-j0 Pb5 Pd y3 =-j0 4 Pb4 y34 =-j0 3 Pg4 Pd3 f. Line flow constraints: -500MW P bk 5000MW, k=,5. The per-unit expressions of these constraints, on a 00 MVA power base, are -500 P bk 500. Given the level of loads (see item (j) below), this implies the transmission has infinite capacity. g. Existing generation data: Bus Bus Bus 4 Technology PC (j=) NGCC (j=3) CT (j=4) Capacity (MW) h. Technology characteristics PC (j=) PC (j=) NGCC(j=3) CT (j=4) Wind (j=5) Capacity credit Investment cost (000$/MW) Fixed O&M costs (000$/MW/yr) Var O&M ($/MWhr) Full-load heat rate (MBTU/MWhr) Fuel cost ($/MBTU) CO emissions (lbs/mwhr) Capacity factor 0.35 Salvage value (000$/MW)
2 i. Load duration curve and corresponding blocks. Assume a load growth rate of %/year, applied to each value d, d, d 3, for each of the two loads in the system, with the durations h, h, and h 3 remaining the same. Therefore, for example, for the load at bus, d would be.0,.084,.95,.395,.4568,.6084,.7758 pu for years, 5, 0, 5, 0, 5, and 30, respectively. You will need to compute the values of d and d 3 for these years as well. Then you will need to do the same for the load at bus 3. d d L (MW) d3 h h+h h+h+h3 Number of hours that Load > L Initial load at bus (Pg) Block Block Block 3 Load (pu) d = d =0.8 d 3 =0.6 Duration (hrs) h =000 h =5000 h 3 =760 Initial load at bus 3 (Pg3) Block Block Block 3 Load (pu) d =. d =0.9 d 3 =0.7 Duration (hrs) h =900 h =500 h 3 =660. Production costing ( pts): a. (4 pts) A load duration curve characterizes the next year for a power system is given below. The power system is supplied by one 3 MW unit. Identify the minimum load, the loss of load probability, the loss of load expectation, and the expected unserved energy, assuming the 3 MW unit is perfectly reliable F Dr ( d e ) 0. d e (MW) b. (5 pts) Now consider that the power system is supplied with one 4 MW unit having a forced outage rate of 0.5. The load is still characterized by the load duration curve above. Compute loss of load probability, loss of load expectation, and expected unserved energy.
3 c. (3 pts) Consider the two situations you have assessed in parts (a) and (b) of this problem. Complete the following sentence: Although situation has the larger LOLP; situation has the larger EUE because. d. (4 pts) Compute the energy expected to be produced by the 4 MW unit of the year. e. (3 pts) Assume the 4 MW unit is a thermal unit. What is the minimum additional information you need to know to compute the cost incurred by unit 4 in producing the amount of energy developed in part (d)? f. (3 pts) After reviewing a production cost program which computes annual production costs in a way that is similar to the procedure suggested in parts (a)-(c) of this problem, an engineer decides to write a production cost simulation program that will allow representation of the power system with much greater operational fidelity. What is the single most important change that the engineer needs to make, relative to that suggested in parts (a)-(e)? 3. Benders (7 pts): The relation between primal and dual optimizations can be stated as: Primal subproblem : max z s. t. x 0 c A x b T A w * x Consider the following problem: max z subject to: 4x 5w x w 0 x 3w 8 w 0, w, x 0, w Dual subproblem : min z s. t. A integer T 0 c b A w* a. (4 pts) Express this problem in the form of Benders, i.e., express an appropriate master problem and an appropriate (primal) subproblem. b. (3 pts) Identify an initial solution to the master. c. (4 pts) Formulate the subproblem dual in terms of w*, and based on the dual formulation, and the solution to the master problem found in part (b), explain why you know that the primal subproblem is infeasible. T
4 d. (3 pts) Given the sub-problem primal is infeasible, explain why it is possible that we may still find a solution to this problem (and thus, that this solution will be feasible in the subproblem primal). e. (3 pts) Find a constraint on w which will make the subproblem primal feasible. 4. Planning principles (0 pts): A good paper on planning (you should read in its entirety - it can be found in IEEE XPlore) is: M. Awad, S. Broad, K. Casey, J. Chen, A. Geevarghese, J. Miller, A. Perez, A. Sheffrin, M. Zhang, E. Toolson, G. Drayton, A. Rahimi, and B. Hobbs, The California ISO transmission economic assessment methodology (TEAM): principles and application to Path 6, Power Engineering Society General Meeting, 006. This paper lists five principles to economic evaluation of proposed transmission upgrades. I have chosen from the paper an excerpt for each principle. For each one, identify how you would implement this principle. Where appropriate, base your answer on information, concepts, and/or methods we have covered in EE 55. I am expecting from you at minimum a -3 sentence paragraph for each principle. First key principle: Benefit Framework: Second key principle: Network Representation:
5 Third key principle: Market Prices: Fourth key principle: Uncertainty: Fifth key principle: Resource alternatives to transmission expansion: Fifth key principle (continued):
6 5. Transmission line parameters (6 pts): A 765 kv transmission line has phase separation of 36 feet. Each phase is a 4-conductor bundle with 4-inch diameter. The conductor type is Tern (795 kcmil). The following data is obtained from tables: Ind reactance ft spacing for 4-conductor bundle at 4 : X a =0.08Ω/mile Ind reactance spacing factor for 36 phase separation: X d =0.4348Ω/mile Cap reactance at ft spacing for 4 conductor bundle at 4 : X a =0.005MΩ-mile Cap reactance spacing factor for 36 phase separation: X d =0.06MΩ-mile a. (6 pts) Compute the SIL for this line configuration with 4 conductors per bundle. b. (4 pts) A designer considers reducing the number of conductors per bundle from 4 to 3, while maintaining conductor spacing and phase spacing at 4 inches and 36 feet, respectively. Would you expect this change to increase or decrease the surge impedance loading? Support your answer. c. (6 pts) The designer desires to maximize the power transfer capability of the line. Relative to the design of part (a) If the line is 30 miles long, what changes would you consider? If the line is 300 miles long, what changes would you consider?
Pb1 y13 =-j10 Pb5. Pb4. y34 =-j10
EE 55, Exam, ake-home. Due Monday, April, 06, 5:00pm. You may use class notes or any reference materials (e.g., books, etc.) that you like; however, you must work alone, i.e., you should not be communicating
More informationECEN 460 Exam 1 Fall 2018
ECEN 460 Exam 1 Fall 2018 Name: KEY UIN: Section: Score: Part 1 / 40 Part 2 / 0 Part / 0 Total / 100 This exam is 75 minutes, closed-book, closed-notes. A standard calculator and one 8.5 x11 note sheet
More informationA Model for a Zonal Operating Reserve Demand Curve
A Model for a Zonal Operating Reserve Demand Curve Yen-Yu Lee Electrical and Computer Engineering University of Texas at Austin March 5, Outline What is operating reserves? Why do we need elastic reserves
More informationTHE UNIVERSITY OF NEW SOUTH WALES. School of Electrical Engineering & Telecommunications FINALEXAMINATION. Session
Name: Student ID: Signature: THE UNIVERSITY OF NEW SOUTH WALES School of Electrical Engineering & Telecommunications FINALEXAMINATION Session 00 ELEC46 Power System Analysis TIME ALLOWED: 3 hours TOTAL
More informationProper Security Criteria Determination in a Power System with High Penetration of Renewable Resources
Proper Security Criteria Determination in a Power System with High Penetration of Renewable Resources Mojgan Hedayati, Kory Hedman, and Junshan Zhang School of Electrical, Computer, and Energy Engineering
More informationJavier Contreras Sanz- Universidad de Castilla-La Mancha Jesús María López Lezama- Universidad de Antioquia Antonio Padilha-Feltrin- Universidade
Javier Contreras Sanz- Universidad de Castilla-La Mancha Jesús María López Lezama- Universidad de Antioquia Antonio Padilha-Feltrin- Universidade Estadual Paulista Jose Ignacio Muñoz-Universidad de Castilla-La
More informationECE 476 Power System Analysis Fall 2014 Exam #1, Thursday, October 2, :30AM - 10:50AM
ECE 476 Power System Analysis Fall 4 Exam #, Thursday, October, 4. 9:3AM - :5AM Name: Problem (5 p) Two balanced 3-phase loads are connected in parallel. One is Y-connected and draws 75 kw (3-phase) at.8
More informationInternational Studies about the Grid Integration of Wind Generation
International Studies about the Grid Integration of Wind Generation Dr.-Ing. Markus Pöller/DIgSILENT GmbH Internation Studies About Grid Integration of Wind Generation Grid Integration of Wind Generationin
More informationSoftware Tools: Congestion Management
Software Tools: Congestion Management Tom Qi Zhang, PhD CompuSharp Inc. (408) 910-3698 Email: zhangqi@ieee.org October 16, 2004 IEEE PES-SF Workshop on Congestion Management Contents Congestion Management
More informationThe DC Optimal Power Flow
1 / 20 The DC Optimal Power Flow Quantitative Energy Economics Anthony Papavasiliou The DC Optimal Power Flow 2 / 20 1 The OPF Using PTDFs 2 The OPF Using Reactance 3 / 20 Transmission Constraints Lines
More informationSHORT QUESTIONS AND ANSWERS. Year/ Semester/ Class : III/ V/ EEE Academic Year: Subject Code/ Name: EE6501/ Power System Analysis
Srividya colllege of Engg & Tech,Virudhunagar Sri Vidya College of Engineering And Technology Virudhunagar 626 005 Department of Electrical and Electronics Engineering QUESTION BANK SHORT QUESTIONS AND
More informationECE 476. Exam #2. Tuesday, November 15, Minutes
Name: Answers ECE 476 Exam #2 Tuesday, November 15, 2016 75 Minutes Closed book, closed notes One new note sheet allowed, one old note sheet allowed 1. / 20 2. / 20 3. / 20 4. / 20 5. / 20 Total / 100
More informationThe L-Shaped Method. Operations Research. Anthony Papavasiliou 1 / 38
1 / 38 The L-Shaped Method Operations Research Anthony Papavasiliou Contents 2 / 38 1 The L-Shaped Method 2 Example: Capacity Expansion Planning 3 Examples with Optimality Cuts [ 5.1a of BL] 4 Examples
More informationAPPENDIX 7.4 Capacity Value of Wind Resources
APPENDIX 7.4 Capacity Value of Wind Resources This page is intentionally left blank. Capacity Value of Wind Resources In analyzing wind resources, it is important to distinguish the difference between
More informationEE 451 Power System Stability
EE 451 Power System Stability Power system operates in synchronous mode Power system is subjected to a wide range of disturbances (small and large) - Loads and generation changes - Network changes - Faults
More informationEE5250 TERM PROJECT. Report by: Akarsh Sheilendranath
EE5250 TERM PROJECT Analytical Approaches for Optimal Placement of Distributed Generation Sources in Power System Caisheng Wang, student member, IEEE, and M. Hashem Nehrir, senior member, IEEE Report by:
More informationA Unified Framework for Defining and Measuring Flexibility in Power System
J A N 1 1, 2 0 1 6, A Unified Framework for Defining and Measuring Flexibility in Power System Optimization and Equilibrium in Energy Economics Workshop Jinye Zhao, Tongxin Zheng, Eugene Litvinov Outline
More information03-Economic Dispatch 1. EE570 Energy Utilization & Conservation Professor Henry Louie
03-Economic Dispatch 1 EE570 Energy Utilization & Conservation Professor Henry Louie 1 Topics Generator Curves Economic Dispatch (ED) Formulation ED (No Generator Limits, No Losses) ED (No Losses) ED Example
More informationCapacity Planning with uncertainty in Industrial Gas Markets
Capacity Planning with uncertainty in Industrial Gas Markets A. Kandiraju, P. Garcia Herreros, E. Arslan, P. Misra, S. Mehta & I.E. Grossmann EWO meeting September, 2015 1 Motivation Industrial gas markets
More informationEE 6501 POWER SYSTEMS UNIT I INTRODUCTION
EE 6501 POWER SYSTEMS UNIT I INTRODUCTION PART A (2 MARKS) 1. What is single line diagram? A Single line diagram is diagrammatic representation of power system in which the components are represented by
More informationB.E. / B.Tech. Degree Examination, April / May 2010 Sixth Semester. Electrical and Electronics Engineering. EE 1352 Power System Analysis
B.E. / B.Tech. Degree Examination, April / May 2010 Sixth Semester Electrical and Electronics Engineering EE 1352 Power System Analysis (Regulation 2008) Time: Three hours Answer all questions Part A (10
More informationA three-level MILP model for generation and transmission expansion planning
A three-level MILP model for generation and transmission expansion planning David Pozo Cámara (UCLM) Enzo E. Sauma Santís (PUC) Javier Contreras Sanz (UCLM) Contents 1. Introduction 2. Aims and contributions
More informationCHAPTER 2 LOAD FLOW ANALYSIS FOR RADIAL DISTRIBUTION SYSTEM
16 CHAPTER 2 LOAD FLOW ANALYSIS FOR RADIAL DISTRIBUTION SYSTEM 2.1 INTRODUCTION Load flow analysis of power system network is used to determine the steady state solution for a given set of bus loading
More informationSome Observations on the Locational Marginal Prices and Loads
on the Locational Marginal Prices and Loads Xinbo Geng Texas A&M University gengxinbo@gmail.com October 15, 2014 Xinbo Geng (TAMU) Relationship between LMP and Load October 15, 2014 1 / 17 Overview 1 Preliminary
More informationTutorial 2: Modelling Transmission
Tutorial 2: Modelling Transmission In our previous example the load and generation were at the same bus. In this tutorial we will see how to model the transmission of power from one bus to another. The
More informationEVALUATION OF WIND ENERGY SOURCES INFLUENCE ON COMPOSITE GENERATION AND TRANSMISSION SYSTEMS RELIABILITY
EVALUATION OF WIND ENERGY SOURCES INFLUENCE ON COMPOSITE GENERATION AND TRANSMISSION SYSTEMS RELIABILITY Carmen Lucia Tancredo Borges João Paulo Galvão carmen@dee.ufrj.br joaopaulo@mercados.com.br Federal
More informationSINGLE OBJECTIVE RISK- BASED TRANSMISSION EXPANSION
Vol.2, Issue.1, Jan-Feb 2012 pp-424-430 ISSN: 2249-6645 SINGLE OBJECTIVE RISK- BASED TRANSMISSION EXPANSION V.Sumadeepthi 1, K.Sarada 2 1 (Student, Department of Electrical and Electronics Engineering,
More informationA Merchant Mechanism for Electricity Transmission Expansion
A Merchant Mechanism for Electricity Transmission Expansion Tarjei Kristiansen, Norwegian University of Science and Technology. Tarjei.Kristiansen@elkraft.ntnu.no Juan Rosellon, Harvard University/CIDE.
More informationThe L-Shaped Method. Operations Research. Anthony Papavasiliou 1 / 44
1 / 44 The L-Shaped Method Operations Research Anthony Papavasiliou Contents 2 / 44 1 The L-Shaped Method [ 5.1 of BL] 2 Optimality Cuts [ 5.1a of BL] 3 Feasibility Cuts [ 5.1b of BL] 4 Proof of Convergence
More informationMixed Integer Linear Programming Formulation for Chance Constrained Mathematical Programs with Equilibrium Constraints
Mixed Integer Linear Programming Formulation for Chance Constrained Mathematical Programs with Equilibrium Constraints ayed A. adat and Lingling Fan University of outh Florida, email: linglingfan@usf.edu
More informationChapter 5. Transmission networks and electricity markets
Chapter 5. Transmission networks and electricity markets 1 Introduction In most of the regions of the world: assumptions that electrical energy can be traded as if all generators were connected to the
More informationQUESTION BANK ENGINEERS ACADEMY. Power Systems Power System Stability 1
ower ystems ower ystem tability QUETION BANK. A cylindrical rotor generator delivers 0.5 pu power in the steady-state to an infinite bus through a transmission line of reactance 0.5 pu. The generator no-load
More informationStochastic Generation Expansion Planning
Engineering Conferences International ECI Digital Archives Modeling, Simulation, And Optimization for the 21st Century Electric Power Grid Proceedings Fall 10-23-2012 Stochastic Generation Expansion Planning
More informationEE 742 Chapter 3: Power System in the Steady State. Y. Baghzouz
EE 742 Chapter 3: Power System in the Steady State Y. Baghzouz Transmission Line Model Distributed Parameter Model: Terminal Voltage/Current Relations: Characteristic impedance: Propagation constant: π
More informationModule 3 : Sequence Components and Fault Analysis
Module 3 : Sequence Components and Fault Analysis Lecture 13 : Sequence Modeling (Tutorial) Objectives In this lecture we will solve tutorial problems on fault analysis in sequence domain Per unit values
More informationResearch on Calculation Method of Power Supply Radius Based on Voltage Deviation in Rural Power Network. Ning Wang
International Conference on Applied Science and Engineering Innovation (ASEI 015) Research on Calculation Method of Power Supply Radius Based on Voltage Deviation in Rural Power Network Ning Wang School
More informationImprovements to Benders' decomposition: systematic classification and performance comparison in a Transmission Expansion Planning problem
Improvements to Benders' decomposition: systematic classification and performance comparison in a Transmission Expansion Planning problem Sara Lumbreras & Andrés Ramos July 2013 Agenda Motivation improvement
More informationBilevel Programming-Based Unit Commitment for Locational Marginal Price Computation
Bilevel Programming-Based Unit Commitment for Locational Marginal Price Computation Presentation at 50 th North American Power Symposium Abdullah Alassaf Department of Electrical Engineering University
More informationIGEE 402 Power System Analysis. FINAL EXAMINATION - SAMPLE Fall 2004
IGEE 402 Power System Analysis FINAL EXAMINATION - SAMPLE Fall 2004 Special instructions: - Duration: 80 minutes. - Material allowed: a crib sheet (double sided 8.5 x ), calculator. - Attempt 5 out of
More informationOptimal Placement & sizing of Distributed Generator (DG)
Chapter - 5 Optimal Placement & sizing of Distributed Generator (DG) - A Single Objective Approach CHAPTER - 5 Distributed Generation (DG) for Power Loss Minimization 5. Introduction Distributed generators
More informationEvaluation of GA Performance in TNEP Considering Voltage Level, Network Losses and Number of Bundle Lines
International Journal of Discrete Mathematics 2018; 3(1): 1-10 http://www.sciencepublishinggroup.com/j/dmath doi: 10.11648/j.dmath.20180301.11 Evaluation of GA Performance in TNEP Considering Voltage Level,
More information16PESGM2316 Characterizing Transmission System Harmonic Impedances with R-X Loci Plots. David Mueller
1 16PESGM2316 Characterizing Transmission System Harmonic Impedances with R-X Loci Plots David Mueller 2 Transmission System Harmonics Studies In the US, the closure of older coal fired plants is a driver
More information4. The Dual Simplex Method
4. The Dual Simplex Method Javier Larrosa Albert Oliveras Enric Rodríguez-Carbonell Problem Solving and Constraint Programming (RPAR) Session 4 p.1/34 Basic Idea (1) Algorithm as explained so far known
More informationelgian energ imports are managed using forecasting software to increase overall network e 칁 cienc.
Elia linemen install Ampacimon real time sensors that will communicate with the dynamic thermal ratings software to control energy import levels over this transmission line. OV RH AD TRAN MI ION D namic
More informationPower Grid Partitioning: Static and Dynamic Approaches
Power Grid Partitioning: Static and Dynamic Approaches Miao Zhang, Zhixin Miao, Lingling Fan Department of Electrical Engineering University of South Florida Tampa FL 3320 miaozhang@mail.usf.edu zmiao,
More informationChapter 5 Integer Programming
Chapter 5 Integer Programming Chapter Topics Integer Programming (IP) Models Integer Programming Graphical Solution Computer Solution of Integer Programming Problems With Excel 2 1 Integer Programming
More informationCongestion Alleviation using Reactive Power Compensation in Radial Distribution Systems
IOSR Journal of Electrical and Electronics Engineering (IOSR-JEEE) e-issn: 2278-1676,p-ISSN: 2320-3331, Volume 11, Issue 6 Ver. III (Nov. Dec. 2016), PP 39-45 www.iosrjournals.org Congestion Alleviation
More informationDYNAMICS OF ELECTRIC POWER SUPPLY CHAIN NETWORKS UNDER RISK AND UNCERTAINTY
DYNAMICS OF ELECTRIC POWER SUPPLY CHAIN NETWORKS UNDER RISK AND UNCERTAINTY Dmytro Matsypura and Anna Nagurney International Conference on Computational Management Science, March 31 - April 3, 2005 University
More informationEE2351 POWER SYSTEM ANALYSIS UNIT I: INTRODUCTION
EE2351 POWER SYSTEM ANALYSIS UNIT I: INTRODUCTION PART: A 1. Define per unit value of an electrical quantity. Write equation for base impedance with respect to 3-phase system. 2. What is bus admittance
More informationAnalyzing the Effect of Loadability in the
Analyzing the Effect of Loadability in the Presence of TCSC &SVC M. Lakshmikantha Reddy 1, V. C. Veera Reddy 2, Research Scholar, Department of Electrical Engineering, SV University, Tirupathi, India 1
More informationIncreasing Transmission Capacities with Dynamic Monitoring Systems
INL/MIS-11-22167 Increasing Transmission Capacities with Dynamic Monitoring Systems Kurt S. Myers Jake P. Gentle www.inl.gov March 22, 2012 Concurrent Cooling Background Project supported with funding
More informationCAPACITOR PLACEMENT IN UNBALANCED POWER SYSTEMS
CAPACITOR PLACEMET I UBALACED POWER SSTEMS P. Varilone and G. Carpinelli A. Abur Dipartimento di Ingegneria Industriale Department of Electrical Engineering Universita degli Studi di Cassino Texas A&M
More informationChapter 2 Deterministic Unit Commitment Models and Algorithms
Chapter 2 Deterministic Unit Commitment Models and Algorithms This chapter introduces the basic formulations of unit commitment problems which are generally proposed to optimize the system operations by
More informationECEN 667 Power System Stability Lecture 25: FFT, Energy Methods
ECEN 667 Power System Stability Lecture 5: FFT, Energy Methods Prof. Tom Overbye Dept. of Electrical and Computer Engineering Texas A&M University, overbye@tamu.edu 1 Announcements Read Chapter 9 Final
More informationWind Generation Curtailment Reduction based on Uncertain Forecasts
Wind Generation Curtailment Reduction based on Uncertain Forecasts A. Alanazi & A. Khodaei University of Denver USA Authors M. Chamana & D. Kushner ComEd USA Presenter Manohar Chamana Introduction Wind
More informationThen the other two numbers may be represented as x + 1 and x + 2. Now we can represent 3 less than the second as (x + 1) 3.
1) Find three consecutive integers such that twice the first minus the third is less than the second. Discussion: Let x represent the smallest of the three integers. Then the other two numbers may be represented
More informationDecision Models Lecture 5 1. Lecture 5. Foreign-Currency Trading Integer Programming Plant-location example Summary and Preparation for next class
Decision Models Lecture 5 1 Lecture 5 Foreign-Currency Trading Integer Programming Plant-location example Summary and Preparation for next class Foreign Exchange (FX) Markets Decision Models Lecture 5
More informationMULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question. C) C) 31.
Eam Name MULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question. Write the sentence as a mathematical statement. 1) Negative twent-four is equal to negative
More informationSystem Planning Lecture 7, F7: Optimization
System Planning 04 Lecture 7, F7: Optimization System Planning 04 Lecture 7, F7: Optimization Course goals Appendi A Content: Generally about optimization Formulate optimization problems Linear Programming
More informationOptimal Location and Sizing of Distributed Generation Based on Gentic Algorithm
Location and Sizing of Distributed Generation Based on Gentic Algorithm Ahmed Helal #,Motaz Amer *, and Hussien Eldosouki # # Electrical and Control Engineering Dept., Arab Academy for Sciences & Technology
More information4. Duality and Sensitivity
4. Duality and Sensitivity For every instance of an LP, there is an associated LP known as the dual problem. The original problem is known as the primal problem. There are two de nitions of the dual pair
More informationRTO Winter Resource Adequacy Assessment Status Report
RTO Winter Resource Adequacy Assessment Status Report RAAS 03/31/2017 Background Analysis performed in response to Winter Season Resource Adequacy and Capacity Requirements problem statement. Per CP rules,
More informationGeneration Expansion Planning
Generation Exansion Planning Based on Multi-area eliability Exonential Analytic Model and Emission Control Lin Cheng singhua Univ. Generation Exansion Planning Considerationsrequirements of ower demands,
More informationLarge-scale optimization and decomposition methods: outline. Column Generation and Cutting Plane methods: a unified view
Large-scale optimization and decomposition methods: outline I Solution approaches for large-scaled problems: I Delayed column generation I Cutting plane methods (delayed constraint generation) 7 I Problems
More informationJ. Electrical Systems x-x (2010): x-xx. Regular paper
JBV Subrahmanyam Radhakrishna.C J. Electrical Systems x-x (2010): x-xx Regular paper A novel approach for Optimal Capacitor location and sizing in Unbalanced Radial Distribution Network for loss minimization
More informationMulti-Area Stochastic Unit Commitment for High Wind Penetration in a Transmission Constrained Network
Multi-Area Stochastic Unit Commitment for High Wind Penetration in a Transmission Constrained Network Anthony Papavasiliou Center for Operations Research and Econometrics Université catholique de Louvain,
More informationEECE421 Power System Analysis. Chapter 4: Transmission Line Capacitance
EECE421 Power System Analysis Chapter 4: Transmission Line Capacitance 1 Capacitance C: Capacitance Caused by the potential difference between the conductors (Charge) per (unit of potential difference)
More informationPower System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian Institute of Technology, Kharagpur
Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian Institute of Technology, Kharagpur Lecture - 9 Transmission Line Steady State Operation Welcome to lesson 9, in Power
More informationOutage Coordination and Business Practices
Outage Coordination and Business Practices 1 2007 Objectives What drove the need for developing a planning/coordination process. Why outage planning/coordination is crucial and important. Determining what
More informationInteger Programming. Chapter Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall
Integer Programming Chapter 5 5-1 Chapter Topics Integer Programming (IP) Models Integer Programming Graphical Solution Computer Solution of Integer Programming Problems With Excel and QM for Windows 0-1
More informationBenders Decomposition
Benders Decomposition Yuping Huang, Dr. Qipeng Phil Zheng Department of Industrial and Management Systems Engineering West Virginia University IENG 593G Nonlinear Programg, Spring 2012 Yuping Huang (IMSE@WVU)
More informationPROJECT ECONOMIC ANALYSIS
Electricity Transmission Expansion and Supply Improvement Project (RRP NEP 41155) PROJECT ECONOMIC ANALYSIS A. Overview 1. The economic analysis undertaken for the Electricity Transmission and Supply Improvement
More informationDecomposition Techniques in Mathematical Programming
Antonio J. Conejo Enrique Castillo Roberto Minguez Raquel Garcia-Bertrand Decomposition Techniques in Mathematical Programming Engineering and Science Applications Springer Contents Part I Motivation and
More informationA Decomposition Based Approach for Solving a General Bilevel Linear Programming
A Decomposition Based Approach for Solving a General Bilevel Linear Programming Xuan Liu, Member, IEEE, Zuyi Li, Senior Member, IEEE Abstract Bilevel optimization has been widely used in decisionmaking
More informationA Benders Decomposition Approach to Corrective Security Constrained OPF with Power Flow Control Devices
A Benders Decomposition Approach to Corrective Security Constrained OPF with Power Flow Control Devices Javad Mohammadi, Gabriela Hug, Soummya Kar Department of Electrical and Computer Engineering Carnegie
More informationDraft Wholesale Power Price Forecasts
Sixth & Electric Power Plan Draft Wholesale Power Price Forecasts Maury Galbraith Generating Resource Advisory Committee Meeting Portland, OR December 18, 28 Outline 1. Overall Perspective: Major AURORA
More informationPrediction of Power System Balancing Requirements and Tail Events
Prediction of Power System Balancing Requirements and Tail Events PNNL: Shuai Lu, Yuri Makarov, Alan Brothers, Craig McKinstry, Shuangshuang Jin BPA: John Pease INFORMS Annual Meeting 2012 Phoenix, AZ
More informationSSC-JE EE POWER SYSTEMS: GENERATION, TRANSMISSION & DISTRIBUTION SSC-JE STAFF SELECTION COMMISSION ELECTRICAL ENGINEERING STUDY MATERIAL
1 SSC-JE STAFF SELECTION COMMISSION ELECTRICAL ENGINEERING STUDY MATERIAL Power Systems: Generation, Transmission and Distribution Power Systems: Generation, Transmission and Distribution Power Systems:
More information1. Solve the following linear programming problem. and b =
LUDS TEKISKA HÖGSKOLA MATEMATIK HOME EXAM LIEAR AD COMBIATORIAL OPTIMIZATIO 015-03-09 You may use any books and computer programs (e.g. Matlab and Maple), but it is not permitted to get help from other
More informationSample Problems for Exam 1, EE Note:
Sample Problems for Exam, EE 57 Note: Problem 3) Has been changed from what was handed out Friday, this is closer to what will come on the quiz. Also note that the hour time period length must be incorporated
More informationTransmission and Distribution of Electrical Power
KINGDOM OF SAUDI ARABIA Ministry Of High Education Umm Al-Qura University College of Engineering & Islamic Architecture Department Of Electrical Engineering Transmission and Distribution of Electrical
More informationIn the original knapsack problem, the value of the contents of the knapsack is maximized subject to a single capacity constraint, for example weight.
In the original knapsack problem, the value of the contents of the knapsack is maximized subject to a single capacity constraint, for example weight. In the multi-dimensional knapsack problem, additional
More informationA COMPUTER PROGRAM FOR SHORT CIRCUIT ANALYSIS OF ELECTRIC POWER SYSTEMS
NIJOTECH VOL. 5 NO. 1 MARCH 1981 EJEBE 46 A COMPUTER PROGRAM FOR SHORT CIRCUIT ANALYSIS OF ELECTRIC POWER SYSTEMS BY G.C. EJEBE DEPARTMENT OF ELECTRICAL/ELECTRONIC ENGINEERING UNIVERSITY OF NIGERIA, NSUKKA.
More informationChapter 9 Balanced Faults, Part II. 9.4 Systematic Fault Analysis Using Bus Impedance Matrix
Chapter 9 Balanced Faults, Part II 9.4 Systematic Fault Analysis Using Bus Impedance Matrix In the previous analysis we employed the Thevenin model and ound the Thevenin voltage and impedance by means
More informationKINGS COLLEGE OF ENGINEERING Punalkulam
KINGS COLLEGE OF ENGINEERING Punalkulam 613 303 DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING POWER SYSTEM ANALYSIS QUESTION BANK UNIT I THE POWER SYSTEM AN OVERVIEW AND MODELLING PART A (TWO MARK
More informationCourse notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing
Course notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing Ross Baldick Copyright c 2013 Ross Baldick www.ece.utexas.edu/ baldick/classes/394v/ee394v.html Title Page 1 of 132
More informationCalculations of Capacitance for Transposed Bundled Conductor Transmission Lines
Calculations of Capacitance for Transposed Bundled Conductor Transmission Lines Multi-conductor Lines. An example with a conductor bundle r: conductor radius, d: distance between conductors of the same
More informationLecture 8: Column Generation
Lecture 8: Column Generation (3 units) Outline Cutting stock problem Classical IP formulation Set covering formulation Column generation A dual perspective Vehicle routing problem 1 / 33 Cutting stock
More informationChapter 2. Planning Criteria. Turaj Amraee. Fall 2012 K.N.Toosi University of Technology
Chapter 2 Planning Criteria By Turaj Amraee Fall 2012 K.N.Toosi University of Technology Outline 1- Introduction 2- System Adequacy and Security 3- Planning Purposes 4- Planning Standards 5- Reliability
More informationEE 581 Power Systems. Admittance Matrix: Development, Direct and Iterative solutions
EE 581 Power Systems Admittance Matrix: Development, Direct and Iterative solutions Overview and HW # 8 Chapter 2.4 Chapter 6.4 Chapter 6.1-6.3 Homework: Special Problem 1 and 2 (see handout) Overview
More informationInvestment and generation optimization in electricity systems with intermittent supply
Energy Systems manuscript No. (will be inserted by the editor) Investment and generation optimization in electricity systems with intermittent supply Athena Wu 1, Andy Philpott 2, Golbon Zakeri 2 1 Mighty
More informationCalifornia Independent System Operator (CAISO) Challenges and Solutions
California Independent System Operator (CAISO) Challenges and Solutions Presented by Brian Cummins Manager, Energy Management Systems - CAISO California ISO by the numbers 65,225 MW of power plant capacity
More informationDATA-DRIVEN RISK-AVERSE STOCHASTIC PROGRAM AND RENEWABLE ENERGY INTEGRATION
DATA-DRIVEN RISK-AVERSE STOCHASTIC PROGRAM AND RENEWABLE ENERGY INTEGRATION By CHAOYUE ZHAO A DISSERTATION PRESENTED TO THE GRADUATE SCHOOL OF THE UNIVERSITY OF FLORIDA IN PARTIAL FULFILLMENT OF THE REQUIREMENTS
More information4.6 Linear Programming duality
4.6 Linear Programming duality To any minimization (maximization) LP we can associate a closely related maximization (minimization) LP Different spaces and objective functions but in general same optimal
More informationReducing Contingency-based Windfarm Curtailments through use of Transmission Capacity Forecasting
Reducing Contingency-based Windfarm Curtailments through use of Transmission Capacity Forecasting Doug Bowman Southwest Power Pool Jack McCall Lindsey Manufacturing Co. CIGRE US National Committee 2017
More informationLab Day and Time: Instructions. 1. Do not open the exam until you are told to start.
Name: Lab Day and Time: Instructions 1. Do not open the exam until you are told to start. 2. This exam is closed note and closed book. You are not allowed to use any outside material while taking this
More informationA MIXED INTEGER DISJUNCTIVE MODEL FOR TRANSMISSION NETWORK EXPANSION
A MIXED INTEGER DISJUNCTIVE MODEL FOR TRANSMISSION NETWORK EXPANSION Laura Bahiense*, Gerson C. Oliveira (PUC/Rio), Mario Pereira*, Member, Sergio Granville*, Member Abstract: The classical non-linear
More informationA Nodal Capacity Market to Assure Resource Adequacy
212 45th Hawaii International Conference on System Sciences A odal Capacity Market to Assure Resource Adequacy Aleksandr M. Rudkevich Charles River Associates arudkevich@crai.com Anatoly I. Lazebnik CJSC
More informationReport on Phase 2: System Performance Evaluation. Prepared for:
THE EFFECTS OF INTEGRATING WIND POWER ON TRANSMISSION SYSTEM PLANNING, RELIABILITY, AND OPERATIONS Report on Phase 2: System Performance Evaluation Prepared for: THE NEW YORK STATE ENERGY RESEARCH AND
More informationELECTRICITY GENERATION CHOICES: COMBINED CYCLE GAS AND WIND IN PORTUGAL
ELECTRICITY GENERATION CHOICES: COMBINED CYCLE GAS AND WIND IN PORTUGAL APPLICATION PORTFOLIO November 2006 6 December 2006 Page 1 of 33 (intentionally blank) 6 December 2006 Page 2 of 33 EXECUTIVE SUMMARY
More information