Benefits of PERT/CPM. 2018, Jayant Rajgopal
|
|
- Pierce Payne
- 6 years ago
- Views:
Transcription
1 Project: ny set of complex, interrelated activities aimed at some specific goal. Typically, characterized by a clear starting point and a clear end point. Examples: onstruction (buildings, roads, bridges, etc.) New product introduction New systems installation One-at-a-time manufacturing (e.g., ships, aircraft) Space flight launches Large scale logistics projects etc. enefits of PERT/PM Forces detailed planning Improves communications Identifies potential bottlenecks and problem areas Provides timely progress reports ssists with long range planning including budgets
2 Objective: To find the shortest time in which a project (comprising many interrelated tasks or activities) can be completed, along with a list of the critical activities, and the slack available for the noncritical ones. Network Representation ctivity-on-node (ON) convention: Node a project task/activity with an associated duration rc representation of a precedence relationship one arc for each precedence relationship: if has to precede there is an arc from node to node one STRT and one FINISH node (each of zero duration) ctivity-on-arc (O) convention: rc a project task/activity with an associated duration Node a project event signifying that all activities represented by arcs entering that node have been completed, and that all activities represented by arcs leaving that node can therefore commence Rules Exactly one arc for representing each activity Exactly one arc connecting any two nodes Numbering onvention Node is the STRT node and signifies project commencement has no incoming arcs The highest numbered node is the FINISH node & signifies project completion has no outgoing arcs For the activity (i-j), the numbering should be such that j>i, i.e., flow is always from a lower to a higher numbered node Use dummy arcs (and perhaps, extra nodes) to ensure correct precedence structures: all precedence requirements must be correctly taken into account, yet no unnecessary or extraneous precedence requirement may be introduced into the problem
3 Precedence ON Representation O Representation < < 2 3 <, 2 3,< 2 3,<, 2 3 5
4 Precedence ON Representation O Representation <,, < < <,E < E E E E E WRONG!! WRONG!! WRONG!!
5 company is considering the purchase of several units of an expensive new machine for its plants around the country. However, management would first like to set up a test facility and test the machine thoroughly before committing itself to the entire order; the machine tool manufacturer has agreed to lend them a machine for this purpose. Since it is important to complete this project quickly, it is of interest to find the shortest schedule for the entire project along with some indication of which activities in the project are critical and how much of slack is available for the various phases of the project. The sequence of activities is as follows: first the test facility must be prepared and the paperwork for borrowing the machine must be completed; these can go on concurrently and are expected to take about days. Once these formalities have been completed, the machine must be transported to the facility and repair personnel and operators need to hired. The transportation is expected to take 8 days, while the hiring of personnel for the repair team and operators are expected to take 7 and 6 days respectively. fter the machine has arrived and the repair team is complete, training of the team can begin - this is expected to take 5 days, and can proceed while the actual installation of the machine is still in progress. For the machine to be installed correctly at the test facility after arrival it is expected to take 9 days. fter installation, the hired operators must be trained to run the machine and this is expected to take days. Finally, once the operators and the repair personnel are fully trained, the actual testing can commence and the testing process is expected to take 20 days. Plan the project.
6 esigner Genes (G), a rapidly expanding genetic engineering firm, is relocating to a new office building. Jean Ettic, the project manager, has already leased a vacant office building and approved architectural plans for renovating it. To save money and to gain more control over the project, Jean herself will act as the general contractor for the renovation. She has already selected the subcontractors that she will employ. The move to the new building is complicated by the fact that G will use this opportunity to purchase a new computer and establish an in-house omputer Services epartment. The present decentralized computer capacity is simply inadequate to meet the future needs of G. Project Formulation for esigner Genes' Relocation ode escription of ctivity Estimated uration (days) Predecessors E F G H I J K L M N Hiring of Manager of omputer Services ept. Structural Modifications Enlarging and Resurfacing of Parking Lot Hiring of Staff of omputer Services ept. Purchase and Receipt of omputer Electrical Modifications Heating and ooling Modifications Plumbing Modifications Exterior Painting & Installation of Fixtures Installation of omputer Sheetrocking of Walls and eilings Training of Staff of omputer Services ept. Interior Painting and Interior ecorating Landscaping None None None E,F,G F,G,H,J K,I
7 Objectives: To find the minimum time required to complete the project, and to evaluate the criticality of each activity with respect to this goal. EFINITIONS Earliest Start Time for ctivity j (ES j ): Earliest time at which the activity can start: ES j = Max i P(j) {ES i + i } where P(j) is the set of all prerequisite activities that immediately precede activity j Earliest ompletion Time for ctivity j (E j ): Earliest time at which the activity can end: E j = ES j + j
8 onsider the portion of a network shown below with activities and durations as shown in the nodes. Focus on Node j=. = ES = 2 2 =3 ES 2 =6 3 3 = 6 ES 3 = = 5 ES =? y definition: ES E, ES E 2, ES E 3 i.e., ES (ES + ) = + = 8 ES (ES ) = = 9 ES (ES ) = + 6 = 0 Thus ES = Max{8,9,0} = 0, (and E = 0+5=5)
9 Latest ompletion Time for ctivity j (L j ): Latest time at which activity j can be completed without causing the project to be delayed beyond its minimum duration: L j = Min i S(j) {L i - i } where S(j) is the set of all activities that immediately succeed activity j Latest Start Time for ctivity j (LS j ): Latest possible time at which activity i can start without causing the project to be delayed beyond its minimum duration: LS j = L j - j
10 Once again, focus on Node j=. = 5 L =? 5 5 =3 L 5 = =6 L 6 = = 3 L 7 =25 y definition: L LS 5, L LS 6, L LS 7 i.e., L (L 5-5 ) = 28-3 = 25 L (L 6-6 ) = 27-6 = L (L 7-7 ) = 25-3 = 22 Thus L = Min{5,,22} =, (and LS = -5=6)
11 Total Float for ctivity j (TF j ): The maximum "excess" or slack time available for activity j in the optimal project schedule: TF j = {(L j - ES j ) - j } Note that (L j -ES j ) represents the window of time available in the optimal schedule for activity j. ritical ctivity: One that has a total float equal to 0, i.e., activity j is critical if TF j =0. Note that TF j =0 (L j -ES j )= j ES j + j =L j. Thus, a critical activity has no excess time available for its completion - it MUST start as soon as possible (at ES j ) so that it is completed no later than the time at which it must be completed in order for the project to not be delayed (L j ). ritical Path: path of critical actvities in the project network that link the STRT node and the FINISH node. It is possible for a project to have more than one critical path!
12 . Forward Pass: egin at the STRT node with ES STRT =0; find ES j =Max i P(j) {ES i + i } for each activity j, going from left to right. Ensure that ES j is computed only after finding ES i for all i P(j), i.e., for all activities that immediately precede activity j. This step ends with the computation of ES FINISH (which is also equal to E FINISH ). 2. ackward Pass: Starting at the FINISH node with L FINISH =E FINISH find L j = Min i S(j) {L i - i } for each activity j, going from right to left. Ensure that L j is computed only after finding L i for all i S(j), i.e., for all activities that immediately follow activity j. This step ends with the computation of L STRT =0 (which is also equal to LS STRT ). 3. ompute TF j = {(L j -ES j ) - j } for each activity j in the project network to identify the critical activities and the critical path.
13 , Start, 0,, 8 H, 20 Finish, 0 0 0, 6 0 F, 5 E, 9 The forward pass first yields the ES values, and then the backward pass yields the L values in the table below: Node j ES j L j Start 0 {L - }= {-}= 0 {ES start + start }= 0+0= Min{L -,L -,L - } = Min{-8,8-7, -6}= 5 0 G, {ES + }=0+= Min{L E - E, L F - F } = Min{-9, -5}= {ES + }=0+= {L F - F }=-5 = 8 {ES + }=0+= {L G - G }=- = E {ES + }=+8= {L G - G }=- = F Max{ES +, ES + } =Max(+8,+7) = {L H - H }=-20 = G Max{ES +, ES E + E } =Max(+6,+9) = {L H - H }=-20 = H Max{ES F + F, ES G + G } =Max(+5,+)= {L Finish - finish }= -0 = Finish {ES H + H }=+20= = E finish = ES finish + finish = 8 27
14 , Start, 0,, 8 H, 20 Finish, 0 0 0, 6 0 F, 5 E, 9 The forward pass first yields the ES values, and then the backward pass yields the L values in the table below: Node j ES j L j Start 0 {L - }= {-}= 0 {ES start + start }= 0+0= Min{L -,L -,L - } = Min{-8,8-7, -6}= 5 0 G, {ES + }=0+= Min{L E - E, L F - F } = Min{-9, -5}= {ES + }=0+= {L F - F }=-5 = 8 {ES + }=0+= {L G - G }=- = E {ES + }=+8= {L G - G }=- = F Max{ES +, ES + } =Max(+8,+7) = {L H - H }=-20 = G Max{ES +, ES E + E } =Max(+6,+9) = {L H - H }=-20 = H Max{ES F + F, ES G + G } =Max(+5,+)= {L Finish - finish }= -0 = Finish {ES H + H }=+20= = E finish = ES finish + finish = 8 27
15 We now go to Step 3 for TF values for each activity ctivity(j) j ES j L j TF j = (L j -ES j )- j E 9 0 F 5 6 G 0 H 20 0 The critical activities are,, E, G and H and the critical path is shown below:, 7 F, 5 Start, 0,, 8 H, 20 Finish, 0 E, 9, 6 G,
16 TIVITIES IN THE ORER S ENTERE ctivity ctivity Earliest Latest Name Symb Time Start/Fin Start/Fin Slack T c T c T T T 5 E c T 6 F T 7 G c T 8 H c The computations were based on 8 activities Earliest project completion time =.0000
17 PM EXMPLE R HRT: NONRITIL TIVITIES SORTE Y SLK ccccc ccccccccc E cccccccccc G ccccccccccccc H ccccccccccccccccccccccc F xxxxxxxxxxxxxxxxx... xxxxxxx... xxxxxx PM EXMPLE R HRT: NONRITIL TIVITIES SORTE Y ERLIEST STRT ccccc ccccccccc E cccccccccc G ccccccccccccc H ccccccccccccccccccccccc xxxxxxx... xxxxxx... F xxxxxxxxxxxxxxxxx
Time Planning and Control
Time Planning and ontrol Precedence iagram G44 NGINRING MNGMNT 1 Precedence iagramming S ctivity I LS T L n important extension to the original activity-on-node concept appeared around 14. The sole relationship
More informationA scheme developed by Du Pont to figure out
CPM Project Management scheme. A scheme developed by Du Pont to figure out Length of a normal project schedule given task durations and their precedence in a network type layout (or Gantt chart) Two examples
More information4. Network Calculations
Construction Project Management (CE 110401346) 4. Network Calculations Dr. Khaled Hyari Department of Civil Engineering Hashemite University Calculations On a Precedence Network I Early Activity Start
More informationPROGRAMMING CPM. Network Analysis. Goal:
PROGRAMMING CPM 5/21/13 Network Analysis Goal: Calculate completion time Calculate start and finish date for each activity Identify critical activities Identify requirements and flows of resources (materials,
More information. Introduction to CPM / PERT Techniques. Applications of CPM / PERT. Basic Steps in PERT / CPM. Frame work of PERT/CPM. Network Diagram Representation. Rules for Drawing Network Diagrams. Common Errors
More informationSAMPLE STUDY MATERIAL. GATE, IES & PSUs Civil Engineering
SAMPLE STUDY MATERIAL Postal Correspondence Course GATE, IES & PSUs Civil Engineering CPM & CONSTRUCTION EQUIPMENT C O N T E N T 1. CPM AND PERT... 03-16 2. CRASHING OF NETWORK... 17-20 3. ENGINEERING
More informationTime Planning and Control. Time-Scaled Network
Time Planning and Control Time-Scaled Network Processes of Time Planning and Control 1.Visualize and define the activities..sequence the activities (Job Logic). 3.stimate the activity duration. 4.Schedule
More information57:022 Principles of Design II Midterm Exam #2 Solutions
57:022 Principles of Design II Midterm Exam #2 Solutions Part: I II III IV V Total Possible Pts: 20 15 12 16 12 75 PART ONE Indicate "+" if True and "O" if False: _+_a. If a component's lifetime has exponential
More information11/8/2018. Overview. PERT / CPM Part 2
/8/08 PERT / CPM Part BSAD 0 Dave Novak Fall 08 Source: Anderson et al., 0 Quantitative Methods for Business th edition some slides are directly from J. Loucks 0 Cengage Learning Overview Last class introduce
More informationNetwork Techniques - I. t 5 4
Performance:Slide.doc Network Techniques - I. t s v u PRT time/cost : ( Program valuation & Review Technique ) vent-on-node typed project-model with probabilistic (stochastic) data set as weights (inp)
More informationProject Time Planning. Ahmed Elyamany, PhD
Project Time Planning Ahmed Elyamany, PhD 1 What is Planning The Development of a workable program of operations to accomplish established objectives when put into action. Done before project starts Planning
More informationST. JOSEPH S COLLEGE OF ARTS & SCIENCE (AUTONOMOUS) CUDDALORE-1
ST. JOSEPH S COLLEGE OF ARTS & SCIENCE (AUTONOMOUS) CUDDALORE-1 SUB:OPERATION RESEARCH CLASS: III B.SC SUB CODE:EMT617S SUB INCHARGE:S.JOHNSON SAVARIMUTHU 2 MARKS QUESTIONS 1. Write the general model of
More informationTopic 10 Directed graphs and networks
Topic 1 irected graphs and networks TOPI 1 irected graphs and networks XIS 1. 1 xercise 1. ritical path analysis 1 arliest completion time is minutes., 1 1,,,,,,, 11 L, 1,, 1 The earliest completion time
More information07/09/2011. A.AMRANI-ZOUGGAR IMS-Lab, University Bordeaux1. These products specific management
A.AMRANI-ZOUGGAR IMS-Lab, University Bordeaux These products specific management What leads the industrialist to start projects? BENEFITS Ageing of the range Benchmarking, comparing the market and industrial
More informationNetwork analysis. A project is a temporary endeavor undertaken to create a "unique" product or service
Network analysis Introduction Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects. One definition of a project
More informationMEI Decision Mathematics 1
Chapter assessment MEI Decision Mathematics Critical Path Analysis. The diagram below shows a precedence network for a particular project. 9 A() D(4) I(8) Durations are in days B() E() H(5) J(4) L() 5
More informationVehicle Routing and Scheduling. Martin Savelsbergh The Logistics Institute Georgia Institute of Technology
Vehicle Routing and Scheduling Martin Savelsbergh The Logistics Institute Georgia Institute of Technology Vehicle Routing and Scheduling Part II: Algorithmic Enhancements Handling Practical Complexities
More information(1) The starting point is the precedence table (aka dependence table) Immediately preceding activities
Critical Path Analysis (10 pages; 1/5/16) fmng.uk (1) The starting point is the precedence table (aka dependence table) Example Activity Duration Immediately preceding activities A 4 - B 5 - C 6 A,B D
More informationSUBPART MULTIYEAR CONTRACTING (Revised December 19, 2006)
SUBPART 217.1--MULTIYEAR CONTRACTING (Revised December 19, 2006) 217.103 Definitions. As used in this subpart-- Advance procurement means an exception to the full funding policy that allows acquisition
More information56:171 Operations Research Midterm Exam--15 October 2002
Name 56:171 Operations Research Midterm Exam--15 October 2002 Possible Score 1. True/False 25 _ 2. LP sensitivity analysis 25 _ 3. Transportation problem 15 _ 4. LP tableaux 15 _ Total 80 _ Part I: True(+)
More informationDecision Mathematics Module D1
E Examinations ecision Mathematics Module 1 Advanced Subsidiary / Advanced Level Paper E Time: 1 hour 3 minutes Instructions and Information andidates may use any calculator except those with a facility
More informationCHAPTER 12. (The interpretation of the symbols used in the equations is given in page 3)
CHAPTER 12 The equations needed: (The interpretation of the symbols used in the equations is given in page 3) 1. ATI = t D 35 4. ws = I average weekly CU 2. I turn = CU I average 5. ds = I average daily
More informationTown of Barnstable. Department of Public Work. Snow and Ice Control Operations Plan
Town of Barnstable Department of Public Work Snow and Ice Control Operations Plan I. Mission: The mission of the Department of Public Works is to remove accumulations of snow and ice from town, county
More informationOFFSHORE. Advanced Weather Technology
Contents 3 Advanced Weather Technology 5 Working Safely, While Limiting Downtime 6 Understanding the Weather Forecast Begins at the Tender Stage 7 Reducing Time and Costs on Projects is a Priority Across
More informationSYMBIOSIS CENTRE FOR DISTANCE LEARNING (SCDL) Subject: production and operations management
Sample Questions: Section I: Subjective Questions 1. What are the inputs required to plan a master production schedule? 2. What are the different operations schedule types based on time and applications?
More informationMathematics (JAN12MD0201) General Certificate of Education Advanced Level Examination January Unit Decision TOTAL.
Centre Number Candidate Number For Examiner s Use Surname Other Names Candidate Signature Examiner s Initials Mathematics Unit Decision 2 Wednesday 25 January 2012 General Certificate of Education Advanced
More informationWays to study a system System
Simulation What is simulation? Simple synonym: imitation We are interested in studying a system Instead of experimenting with the system itself we experiment with a model of the system Ways to study a
More informationMINUTES SPOA BOARD MEETING December 17, 2018
h Open Forum 6:30 PM MINUTES SPOA BOARD MEETING December 17, 2018 There were no Open Forum Items this month. Board Meeting 7:00 PM Review and Approval of Minutes George Graham submitted the previous month
More informationM.SC. MATHEMATICS - II YEAR
MANONMANIAM SUNDARANAR UNIVERSITY DIRECTORATE OF DISTANCE & CONTINUING EDUCATION TIRUNELVELI 627012, TAMIL NADU M.SC. MATHEMATICS - II YEAR DKM24 - OPERATIONS RESEARCH (From the academic year 2016-17)
More informationBachelor s Degree Programme Operations Research (Valid from 1st January, 2012 to 30th November, 2012.)
AOR-01 ASSIGNMENT BOOKLET Bachelor s Degree Programme Operations Research (Valid from 1st January, 2012 to 30th November, 2012.) It is compulsory to submit the assignment before filling in the exam form.
More informationQi Jian-xun,Sun Dedong
Physics Procedia 24 (2012) 1530 1540 2012 International Conference on Applied Physics and Industrial Engineering One Improvement Method of Reducing Duration Directly to Solve Time-Cost Tradeoff Problem
More informationA Critical Path Problem Using Triangular Neutrosophic Number
A ritical Path Problem Using Triangular Neutrosophic Number Mai Mohamed 1 Department of Operations Research Faculty of omputers and Informatics Zagazig University, Sharqiyah, Egypt Yongquan Zhou 2 ollege
More informationALAMEDA ISLES PROPOSED BUDGET FACT SHEET
ALAMEDA ISLES PROPOSED BUDGET FACT SHEET These sheets outline the proposed 2015/2016 budget in two parts. The first part is the operating budget which shows our income and anticipated expenses with a comparative
More informationFood Safety and Quality Management System
Introduction The company has planned, established, documented and implemented a food safety and quality management system for the site, which is maintained in order to continually improve its effectiveness
More information56:171 Operations Research Final Exam December 12, 1994
56:171 Operations Research Final Exam December 12, 1994 Write your name on the first page, and initial the other pages. The response "NOTA " = "None of the above" Answer both parts A & B, and five sections
More informationIncome Statement Lakeview Accrual Basis Jun 2018
Lakeview Accrual Basis Jun 2018 Property: Lakeview Income Revenues 4010-0000 Gross Market Rent - 30,656.00 30,656.00 30,656.00 30,656.00 30,563.00 30,499.00 30,467.00 30,403.00 30,403.00 30,339.00 30,307.00
More informationChapter 7 Network Flow Problems, I
Chapter 7 Network Flow Problems, I Network flow problems are the most frequently solved linear programming problems. They include as special cases, the assignment, transportation, maximum flow, and shortest
More informationEmbedded Systems - FS 2018
Institut für Technische Informatik und Kommunikationsnetze Prof. L. Thiele Embedded Systems - FS 2018 Sample solution to Exercise 3 Discussion Date: 11.4.2018 Aperiodic Scheduling Task 1: Earliest Deadline
More information2. Project management
2. Project management In what follows, we consider production processes where only a single item of a specific product is produced in the planning horizon In this case specific instruments for planning
More informationKnapsack and Scheduling Problems. The Greedy Method
The Greedy Method: Knapsack and Scheduling Problems The Greedy Method 1 Outline and Reading Task Scheduling Fractional Knapsack Problem The Greedy Method 2 Elements of Greedy Strategy An greedy algorithm
More informationReed School/Westover Library U USE PERMIT AMENDMENT. Staff Presentation to the County Board November 17, 2018
Reed School/Westover Library U-3175-07-1 USE PERMIT AMENDMENT Staff Presentation to the County Board November 17, 2018 Site Location 2 Background 1644 N. McKinley Road 1938: Walter Reed Elementary School
More informationForecasting without Fear
Forecasting without Fear How to keep the business informed and keep your cool NY SPIN December 15, 2015 Drivers, Challenges why you have to forecast, and why it s not easy what you forecast Refinement
More informationWednesday 25 January 2012 Afternoon
Wednesday 25 January 2012 Afternoon A2 GCE MATHEMATICS 4737 Decision Mathematics 2 QUESTION PAPER *4733040112* Candidates answer on the Printed Answer Book. OCR supplied materials: Printed Answer Book
More informationAdvanced/Advanced Subsidiary
Paper Reference(s) 6689/01 dexcel GC ecision Mathematics 1 dvanced/dvanced Subsidiary Thursday 16 June 2005 fternoon Time: 1 hour 30 minutes Materials required for examination Nil Items included with question
More informationDecision Mathematics D1
Pearson Edexcel GCE Decision Mathematics D1 Advanced/Advanced Subsidiary Friday 17 June 2016 Afternoon Time: 1 hour 30 minutes Paper Reference 6689/01 You must have: D1 Answer Book Candidates may use any
More informationChapter 3: Discrete Optimization Integer Programming
Chapter 3: Discrete Optimization Integer Programming Edoardo Amaldi DEIB Politecnico di Milano edoardo.amaldi@polimi.it Sito web: http://home.deib.polimi.it/amaldi/ott-13-14.shtml A.A. 2013-14 Edoardo
More informationMessage Passing Algorithms and Junction Tree Algorithms
Message Passing lgorithms and Junction Tree lgorithms Le Song Machine Learning II: dvanced Topics S 8803ML, Spring 2012 Inference in raphical Models eneral form of the inference problem P X 1,, X n Ψ(
More informationDecision Mathematics Module D1
GCE Examinations Decision Mathematics Module D1 Advanced Subsidiary / Advanced Level Paper B Time: 1 hour 30 minutes Instructions and Information Candidates may use any calculator except those with a facility
More informationCS521 CSE IITG 11/23/2012
Today Scheduling: lassification Ref: Scheduling lgorithm Peter rukerook Multiprocessor Scheduling : List PTS Ref job scheduling, by uwe schweigelshohn Tomorrow istributed Scheduling ilk Programming and
More informationMathematics (JUN13MD0201) General Certificate of Education Advanced Level Examination June Unit Decision TOTAL.
Centre Number Candidate Number For Examiner s Use Surname Other Names Candidate Signature Examiner s Initials Mathematics Unit Decision 2 Thursday 13 June 2013 General Certificate of Education Advanced
More informationMorning Time: 1 hour 30 minutes
ADVANCED SUBSIDIARY GCE 477/0 MATHEMATICS (MEI) Decision Mathematics THURSDAY 2 JUNE 2008 Morning Time: hour 30 minutes *CUP/T44383* Additional materials: Printed Answer Book (enclosed) MEI Examination
More informationNew Theory and Algorithms for Scheduling Arc Shutdown Jobs in Networks
New Theory and Algorithms for Scheduling Arc Shutdown Jobs in Networks Patrick Andersen February 27, 2014 This project explores a recently developed type of scheduling problem that combines the two Operations
More informationGUIDELINES FOR FILMING IN TOMBALL, TEXAS
GUIDELINES FOR FILMING IN TOMBALL, TEXAS I. PURPOSE The following guidelines are intended to protect the personal and property rights of our Tomball, Texas residents and businesses. The City Manager reserves
More informationPW 001 SNOW REMOVAL AND SANDING FOR ROADWAYS AND SIDEWALKS October 6, 2014 (#223-14) Original October 19, 2015; October 15, 2018 Public Works
Policy Statement: The Village of Kitscoty will provide snow and ice control on municipal streets and sidewalks according to determined priorities. Purpose: To provide direction and information to employees
More informationPROJECT MANAGEMENT CHAPTER 1
PROJECT MANAGEMENT CHAPTER 1 Project management is the process and activity of planning, organizing, motivating, and controlling resources, procedures and protocols to achieve specific goals in scientific
More information1.225 Transportation Flow Systems Quiz (December 17, 2001; Duration: 3 hours)
1.225 Transportation Flow Systems Quiz (December 17, 2001; Duration: 3 hours) Student Name: Alias: Instructions: 1. This exam is open-book 2. No cooperation is permitted 3. Please write down your name
More informationReview Exercise 2. 1 a Chemical A 5x+ Chemical B 2x+ 2y12 [ x+ Chemical C [ 4 12]
Review Exercise a Chemical A 5x+ y 0 Chemical B x+ y [ x+ y 6] b Chemical C 6 [ ] x+ y x+ y x, y 0 c T = x+ y d ( x, y) = (, ) T = Pearson Education Ltd 08. Copying permitted for purchasing institution
More informationProject management model for constructing a renewable energy plant
Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 74 (207 ) 45 54 206 Global Congress on Manufacturing and Management Project management model for constructing a renewable energy
More informationDuration of online examination will be of 1 Hour 20 minutes (80 minutes).
Program Name: SC Subject: Production and Operations Management Assessment Name: POM - Exam Weightage: 70 Total Marks: 70 Duration: 80 mins Online Examination: Online examination is a Computer based examination.
More informationDynamic Programming Models
Chapter 19 Page 1 Dynamic Programming Models Many planning and control problems in manufacturing, telecommunications and capital budgeting call for a sequence of decisions to be made at fixed points in
More informationTemple City Unified School District A District of High Achieving Schools
Kathryn E. Perini Superintendent Temple City Unified School A of High Achieving Schools Board of Education John Pomeroy, President Vinson Bell, Vice President Kien C. Tiet, Clerk Kenneth Knollenberg, Member
More informationThe Minimum Cost Network Flow Problem
EMIS 8374 [MCNFP Review] 1 The Minimum Cost Network Flow Problem Problem Instance: Given a network G = (N, A), with a cost c ij, upper bound u ij, and lower bound l ij associated with each directed arc
More informationMonitoring Radar Mechanical Drive Systems FAA's choice of monitoring solutions
Monitoring Radar Mechanical Drive Systems FAA's choice of monitoring solutions Mission-critical Ask the public to name mission-critical systems, and air traffic control radar will be at the top of the
More informationphysicsandmathstutor.com
ADVANCED GCE MATHEMATICS 4737 Decision Mathematics 2 Candidates answer on the Answer Booklet OCR Supplied Materials: 8 page Answer Booklet Graph paper Insert for Questions 5 and 6 (inserted) List of Formulae
More informationTime allowed: 1.5 hours
Student name College of ngineering Civil ngineering Department G 404: NGINRING MNGMNT Second Semester 1438/1439H (MODL NSWR) FIRST MIDTRM XM Monday 24/6/1439H (12/3/2018G) from 7:00 to 8:30 PM Time allowed:
More informationReal Estate Investor Calculator Project Workbook. Quick Estimate Factors MAIN DATA ENTRY
MAIN DATA ENTRY 1 2 Current List / Asking Price: $ 175,000.00 Project Updated: 12/18/17 Original or Current Appraised / Market Value / AsIs: $ 180,000.00 AsIs Date: 12/18/17 Est. Resale Value / Post Renovations
More informationLogistical and Transportation Planning. QUIZ 1 Solutions
QUIZ 1 Solutions Problem 1. Patrolling Police Car. A patrolling police car is assigned to the rectangular sector shown in the figure. The sector is bounded on all four sides by a roadway that requires
More information19.0 Practical Issues in Regression
19.0 Practical Issues in Regression 1 Answer Questions Nonparametric Regression Residual Plots Extrapolation 19.1 Nonparametric Regression Recall that the multiple linear regression model is Y = β 0 +
More informationEfficient Workplan Management in Maintenance Tasks
Efficient Workplan Management in Maintenance Tasks Michel Wilson a Nico Roos b Bob Huisman c Cees Witteveen a a Delft University of Technology, Dept of Software Technology b Maastricht University, Dept
More informationProject scheduling with calendars
OR Spektrum (2001) 23: 325 334 c Springer-Verlag 2001 Project scheduling with calendars Birger Franck, Klaus Neumann, and Christoph Schwindt Institut für Wirtschaftstheorie und Operations Research, University
More informationUNIT 4 TRANSPORTATION PROBLEM
UNIT 4 TRANSPORTATION PROLEM Structure 4.1 Introduction Objectives 4.2 Mathematical Formulation of the Transportation Problem 4.3 Methods of Finding Initial asic Feasible Solution North-West orner Rule
More informationEmbedded Systems 15. REVIEW: Aperiodic scheduling. C i J i 0 a i s i f i d i
Embedded Systems 15-1 - REVIEW: Aperiodic scheduling C i J i 0 a i s i f i d i Given: A set of non-periodic tasks {J 1,, J n } with arrival times a i, deadlines d i, computation times C i precedence constraints
More informationBUILDING AND SAFETY FEE SCHEDULE (Effective July1, 2013)
BUILDING AND SAFETY DIVISION TELEPHONE (949) 724-6300 BUILDING AND SAFETY FEE SCHEDULE (Effective July1, 2013) Payment: When a plan is required by the Administrative Authority to be submitted, a plan check
More informationUnit 7 Systems and Linear Programming
Unit 7 Systems and Linear Programming PREREQUISITE SKILLS: students should be able to solve linear equations students should be able to graph linear equations students should be able to create linear equations
More informationMethods and Models for Combinatorial Optimization
Methods and Models for Combinatorial Optimization Modeling by Linear Programming Luigi De Giovanni, Marco Di Summa Dipartimento di Matematica, Università di Padova De Giovanni, Di Summa MeMoCO 1 / 35 Mathematical
More informationDrilling Commences at Bolivian Tin Sites
ASX ANNOUNCEMENT 17 October 2017 Drilling Commences at Bolivian Tin Sites Highlights Drilling and sampling has commenced at Victory s tin tail deposits in Bolivia. Approximately 105m of drilling has been
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS STRUCTURAL ENGINEERING FIRM TO PERFORM A STRUCTURAL EVALUATION OF THE MARKET STREET PARKADE FACILITY REFERENCE RFP 14-148 Addendum Issued: August 22, 2014 ADDENDUM No. 2 Page 1 of
More informationDesign Example: 4-bit Sequence Detector
Design Example: 4-bit Sequence Detector We are asked to design a 4-bit sequence detector. For each 4 bits that are input, we need to see whether they match one of two given sequences: 1010 or 0110. The
More informationPREPARED BY: INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad
INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad - 500 043 PREPARED BY: A. SOMAIAH, ASST. PROFESSOR T. VANAJA, ASST. PROFESSOR DEPT. OF MECHANICAL ENGINEERING 1 Syllabus UNIT-I Development
More informationCalculation exercise 1 MRP, JIT, TOC and SOP. Dr Jussi Heikkilä
Calculation exercise 1 MRP, JIT, TOC and SOP Dr Jussi Heikkilä Problem 1: MRP in XYZ Company fixed lot size Item A Period 1 2 3 4 5 6 7 8 9 10 Gross requirements 71 46 49 55 52 47 51 48 56 51 Scheduled
More informationDecision Mathematics D1 Advanced/Advanced Subsidiary. Friday 17 May 2013 Morning Time: 1 hour 30 minutes
Paper Reference(s) 6689/01 Edexcel GCE Decision Mathematics D1 Advanced/Advanced Subsidiary Friday 17 May 2013 Morning Time: 1 hour 30 minutes Materials required for examination Nil Items included with
More informationINCLEMENT WEATHER CLOSING CODES
INCLEMENT WEATHER CLOSING CODES Code 0 Code 1 Code 2 Code 3 Code 4 Code 5 Code 6 ALL operations are closed and no employees should report to work. Transportation personnel, maintenance personnel, ALL custodial
More informationSPECIAL REVENUE (GRANT) FUNDS
SPECIAL REVENUE (GRANT) FUNDS Special Revenue (Grant) Funds are comprised of grants and awards from various State, Federal and Local agencies or organizations. These funds are awarded by grantor and subject
More informationA comparison of sequencing formulations in a constraint generation procedure for avionics scheduling
A comparison of sequencing formulations in a constraint generation procedure for avionics scheduling Department of Mathematics, Linköping University Jessika Boberg LiTH-MAT-EX 2017/18 SE Credits: Level:
More informationSCHOOLING FOR LIFE FOUNDATION FINANCIAL STATEMENT FOR THE MONTH OF
SCHOOLING FOR LIFE FOUNDATION FINANCIAL STATEMENT FOR THE MONTH OF MAY 2014 TO JUNE 2015 SCHOOLING FOR LIFE FOUNDATION CONTENTS: PAGE GENERAL INFORMATION 3 REPORT ON THE ACCOUNT DEPT. 4 FINANCIAL STATEMENT
More informationPeavine Estates HOA. Annual Review Without Site Visit. Better Reserve Consultants. Start Date: 01/01/2015. Mari Jo Betterley, RSS
Peavine Estates HOA Annual Review Without Site Visit Start Date: 01/01/2015 Better Reserve Consultants Mari Jo Betterley, RSS 0000025 Table of Contents Introduction Page 1 Important Information Page 8
More informationCoordinated Replenishments at a Single Stocking Point
Chapter 11 Coordinated Replenishments at a Single Stocking Point 11.1 Advantages and Disadvantages of Coordination Advantages of Coordination 1. Savings on unit purchase costs.. Savings on unit transportation
More information2.2. The parties provided the following factual background (condensed to relevant facts)
1. Introduction Guidance No: DAB-24 The Delay Attribution Board (the Board) received a request for guidance in relation to the Attribution of TRUST delay incident 715839 (8 th January 2010) The Board received
More informationFood Safety Management System
Introduction The company has planned, established, documented and implemented a food safety management system for the site, in order to continually improve its effectiveness in accordance with legislation,
More informationCOST SEGREGATION. For Building Owners
180 Montgomery Street Suite 1950 San Francisco, CA 94104 phone : 415.394.7200 fax : 415.398.6501 web : moskowitzllp.com COST SEGREGATION For Building Owners 2 Moskowitz, LLP What is Cost Segregation? Cost
More informationFY18 YTD Activity by Fund Group Summary For Fiscal: Period Ending: 11/30/2017
City of Dana Point, CA FY18 by Fund Group Summary For Fiscal: 2017-2018 Period Ending: 11/30/2017 Fund: 01 - GENERAL Revenue RevenueType: 10 - Taxes & Franchises 6101 - Sec & Unsec Property Taxes 6103
More informationProduction Planning and Control
Production Planning and Control MAERIAL REQUIREMEN PLANNING Haeryip Sihombing BMFP 453 4 Universiti eknikal Malaysia Melaka (UeM) HAERY SIHOMBING First widely available software implementation of a manufacturing
More informationChapter 3: Discrete Optimization Integer Programming
Chapter 3: Discrete Optimization Integer Programming Edoardo Amaldi DEIB Politecnico di Milano edoardo.amaldi@polimi.it Website: http://home.deib.polimi.it/amaldi/opt-16-17.shtml Academic year 2016-17
More informationSEXTANT & SEXTANT PE frequently asked questions
SEXTANT & SEXTANT PE frequently asked questions What is SEXTANT? SEXTANT is a software application that helps Financial Executives and Estimators determine their costing and budgeting standards also known
More informationSource: % % FINANCING SHORT TERM HOLDING / RESALE. 30 Maximun Offer to Resell (Fix/Flip): $ 424,000.00
MAIN DATA ENTRY Current List / Asking Price: $ 499,000.00 Project Updated: 11/15/17 Original or Current Appraised / Market Value / AsIs: $ 520,000.00 AsIs Date: 11/1/17 Est. Resale Value / Post Renovations
More informationGIS ADMINISTRATOR / WEB DEVELOPER EVANSVILLE-VANDERBURGH COUNTY AREA PLAN COMMISSION
GIS ADMINISTRATOR / WEB DEVELOPER EVANSVILLE-VANDERBURGH COUNTY AREA PLAN COMMISSION SALARY RANGE INITIATION $43,277 SIX MONTHS $45,367 POSITION GRADE PAT VI The Evansville-Vanderburgh County Area Plan
More informationGlobe Calendar Corporation
+91-8048076367 Globe Calendar Corporation https://www.indiamart.com/globe-calendar/ We are engaged in designing, manufacturing and supplying Wall and Table Calenders. Our range is widely appreciated owing
More informationNetwork Flows. 4. Maximum Flows Problems. Fall 2010 Instructor: Dr. Masoud Yaghini
In the name of God Network Flows 4. Maximum Flows Problems 4.1 Introduction Fall 2010 Instructor: Dr. Masoud Yaghini Introduction Introduction The maximum flow problem In a capacitated network, we wish
More informationNotice of Strata Committee Meeting. Strata Plan Name Mirage Apartments Address 1-29 Bunn Street PYRMONT NSW 2009
Notice of Strata Committee Meeting Strata Plan 54229 Name Mirage Apartments Address PYRMONT NSW 2009 Meeting Date Tuesday, 30 May 2017 Time 6:30 PM Venue Boardroom, Novotel Darling Harbour Address 100
More informationThe City of Houston is committed to work in partnership with the community to promote and protect the health and social well being of Houstonians
Integrating GIS in Decision Making y from the Process: A Case Study City of Houston, Texas Riju Stephen MS Brenda Reyes, MD, MPH MS MBA Ketan Inamdar Inamdar, MS, Mark Perry MPH Office of Surveillance
More information