Benefits of PERT/CPM. 2018, Jayant Rajgopal

Size: px
Start display at page:

Download "Benefits of PERT/CPM. 2018, Jayant Rajgopal"

Transcription

1 Project: ny set of complex, interrelated activities aimed at some specific goal. Typically, characterized by a clear starting point and a clear end point. Examples: onstruction (buildings, roads, bridges, etc.) New product introduction New systems installation One-at-a-time manufacturing (e.g., ships, aircraft) Space flight launches Large scale logistics projects etc. enefits of PERT/PM Forces detailed planning Improves communications Identifies potential bottlenecks and problem areas Provides timely progress reports ssists with long range planning including budgets

2 Objective: To find the shortest time in which a project (comprising many interrelated tasks or activities) can be completed, along with a list of the critical activities, and the slack available for the noncritical ones. Network Representation ctivity-on-node (ON) convention: Node a project task/activity with an associated duration rc representation of a precedence relationship one arc for each precedence relationship: if has to precede there is an arc from node to node one STRT and one FINISH node (each of zero duration) ctivity-on-arc (O) convention: rc a project task/activity with an associated duration Node a project event signifying that all activities represented by arcs entering that node have been completed, and that all activities represented by arcs leaving that node can therefore commence Rules Exactly one arc for representing each activity Exactly one arc connecting any two nodes Numbering onvention Node is the STRT node and signifies project commencement has no incoming arcs The highest numbered node is the FINISH node & signifies project completion has no outgoing arcs For the activity (i-j), the numbering should be such that j>i, i.e., flow is always from a lower to a higher numbered node Use dummy arcs (and perhaps, extra nodes) to ensure correct precedence structures: all precedence requirements must be correctly taken into account, yet no unnecessary or extraneous precedence requirement may be introduced into the problem

3 Precedence ON Representation O Representation < < 2 3 <, 2 3,< 2 3,<, 2 3 5

4 Precedence ON Representation O Representation <,, < < <,E < E E E E E WRONG!! WRONG!! WRONG!!

5 company is considering the purchase of several units of an expensive new machine for its plants around the country. However, management would first like to set up a test facility and test the machine thoroughly before committing itself to the entire order; the machine tool manufacturer has agreed to lend them a machine for this purpose. Since it is important to complete this project quickly, it is of interest to find the shortest schedule for the entire project along with some indication of which activities in the project are critical and how much of slack is available for the various phases of the project. The sequence of activities is as follows: first the test facility must be prepared and the paperwork for borrowing the machine must be completed; these can go on concurrently and are expected to take about days. Once these formalities have been completed, the machine must be transported to the facility and repair personnel and operators need to hired. The transportation is expected to take 8 days, while the hiring of personnel for the repair team and operators are expected to take 7 and 6 days respectively. fter the machine has arrived and the repair team is complete, training of the team can begin - this is expected to take 5 days, and can proceed while the actual installation of the machine is still in progress. For the machine to be installed correctly at the test facility after arrival it is expected to take 9 days. fter installation, the hired operators must be trained to run the machine and this is expected to take days. Finally, once the operators and the repair personnel are fully trained, the actual testing can commence and the testing process is expected to take 20 days. Plan the project.

6 esigner Genes (G), a rapidly expanding genetic engineering firm, is relocating to a new office building. Jean Ettic, the project manager, has already leased a vacant office building and approved architectural plans for renovating it. To save money and to gain more control over the project, Jean herself will act as the general contractor for the renovation. She has already selected the subcontractors that she will employ. The move to the new building is complicated by the fact that G will use this opportunity to purchase a new computer and establish an in-house omputer Services epartment. The present decentralized computer capacity is simply inadequate to meet the future needs of G. Project Formulation for esigner Genes' Relocation ode escription of ctivity Estimated uration (days) Predecessors E F G H I J K L M N Hiring of Manager of omputer Services ept. Structural Modifications Enlarging and Resurfacing of Parking Lot Hiring of Staff of omputer Services ept. Purchase and Receipt of omputer Electrical Modifications Heating and ooling Modifications Plumbing Modifications Exterior Painting & Installation of Fixtures Installation of omputer Sheetrocking of Walls and eilings Training of Staff of omputer Services ept. Interior Painting and Interior ecorating Landscaping None None None E,F,G F,G,H,J K,I

7 Objectives: To find the minimum time required to complete the project, and to evaluate the criticality of each activity with respect to this goal. EFINITIONS Earliest Start Time for ctivity j (ES j ): Earliest time at which the activity can start: ES j = Max i P(j) {ES i + i } where P(j) is the set of all prerequisite activities that immediately precede activity j Earliest ompletion Time for ctivity j (E j ): Earliest time at which the activity can end: E j = ES j + j

8 onsider the portion of a network shown below with activities and durations as shown in the nodes. Focus on Node j=. = ES = 2 2 =3 ES 2 =6 3 3 = 6 ES 3 = = 5 ES =? y definition: ES E, ES E 2, ES E 3 i.e., ES (ES + ) = + = 8 ES (ES ) = = 9 ES (ES ) = + 6 = 0 Thus ES = Max{8,9,0} = 0, (and E = 0+5=5)

9 Latest ompletion Time for ctivity j (L j ): Latest time at which activity j can be completed without causing the project to be delayed beyond its minimum duration: L j = Min i S(j) {L i - i } where S(j) is the set of all activities that immediately succeed activity j Latest Start Time for ctivity j (LS j ): Latest possible time at which activity i can start without causing the project to be delayed beyond its minimum duration: LS j = L j - j

10 Once again, focus on Node j=. = 5 L =? 5 5 =3 L 5 = =6 L 6 = = 3 L 7 =25 y definition: L LS 5, L LS 6, L LS 7 i.e., L (L 5-5 ) = 28-3 = 25 L (L 6-6 ) = 27-6 = L (L 7-7 ) = 25-3 = 22 Thus L = Min{5,,22} =, (and LS = -5=6)

11 Total Float for ctivity j (TF j ): The maximum "excess" or slack time available for activity j in the optimal project schedule: TF j = {(L j - ES j ) - j } Note that (L j -ES j ) represents the window of time available in the optimal schedule for activity j. ritical ctivity: One that has a total float equal to 0, i.e., activity j is critical if TF j =0. Note that TF j =0 (L j -ES j )= j ES j + j =L j. Thus, a critical activity has no excess time available for its completion - it MUST start as soon as possible (at ES j ) so that it is completed no later than the time at which it must be completed in order for the project to not be delayed (L j ). ritical Path: path of critical actvities in the project network that link the STRT node and the FINISH node. It is possible for a project to have more than one critical path!

12 . Forward Pass: egin at the STRT node with ES STRT =0; find ES j =Max i P(j) {ES i + i } for each activity j, going from left to right. Ensure that ES j is computed only after finding ES i for all i P(j), i.e., for all activities that immediately precede activity j. This step ends with the computation of ES FINISH (which is also equal to E FINISH ). 2. ackward Pass: Starting at the FINISH node with L FINISH =E FINISH find L j = Min i S(j) {L i - i } for each activity j, going from right to left. Ensure that L j is computed only after finding L i for all i S(j), i.e., for all activities that immediately follow activity j. This step ends with the computation of L STRT =0 (which is also equal to LS STRT ). 3. ompute TF j = {(L j -ES j ) - j } for each activity j in the project network to identify the critical activities and the critical path.

13 , Start, 0,, 8 H, 20 Finish, 0 0 0, 6 0 F, 5 E, 9 The forward pass first yields the ES values, and then the backward pass yields the L values in the table below: Node j ES j L j Start 0 {L - }= {-}= 0 {ES start + start }= 0+0= Min{L -,L -,L - } = Min{-8,8-7, -6}= 5 0 G, {ES + }=0+= Min{L E - E, L F - F } = Min{-9, -5}= {ES + }=0+= {L F - F }=-5 = 8 {ES + }=0+= {L G - G }=- = E {ES + }=+8= {L G - G }=- = F Max{ES +, ES + } =Max(+8,+7) = {L H - H }=-20 = G Max{ES +, ES E + E } =Max(+6,+9) = {L H - H }=-20 = H Max{ES F + F, ES G + G } =Max(+5,+)= {L Finish - finish }= -0 = Finish {ES H + H }=+20= = E finish = ES finish + finish = 8 27

14 , Start, 0,, 8 H, 20 Finish, 0 0 0, 6 0 F, 5 E, 9 The forward pass first yields the ES values, and then the backward pass yields the L values in the table below: Node j ES j L j Start 0 {L - }= {-}= 0 {ES start + start }= 0+0= Min{L -,L -,L - } = Min{-8,8-7, -6}= 5 0 G, {ES + }=0+= Min{L E - E, L F - F } = Min{-9, -5}= {ES + }=0+= {L F - F }=-5 = 8 {ES + }=0+= {L G - G }=- = E {ES + }=+8= {L G - G }=- = F Max{ES +, ES + } =Max(+8,+7) = {L H - H }=-20 = G Max{ES +, ES E + E } =Max(+6,+9) = {L H - H }=-20 = H Max{ES F + F, ES G + G } =Max(+5,+)= {L Finish - finish }= -0 = Finish {ES H + H }=+20= = E finish = ES finish + finish = 8 27

15 We now go to Step 3 for TF values for each activity ctivity(j) j ES j L j TF j = (L j -ES j )- j E 9 0 F 5 6 G 0 H 20 0 The critical activities are,, E, G and H and the critical path is shown below:, 7 F, 5 Start, 0,, 8 H, 20 Finish, 0 E, 9, 6 G,

16 TIVITIES IN THE ORER S ENTERE ctivity ctivity Earliest Latest Name Symb Time Start/Fin Start/Fin Slack T c T c T T T 5 E c T 6 F T 7 G c T 8 H c The computations were based on 8 activities Earliest project completion time =.0000

17 PM EXMPLE R HRT: NONRITIL TIVITIES SORTE Y SLK ccccc ccccccccc E cccccccccc G ccccccccccccc H ccccccccccccccccccccccc F xxxxxxxxxxxxxxxxx... xxxxxxx... xxxxxx PM EXMPLE R HRT: NONRITIL TIVITIES SORTE Y ERLIEST STRT ccccc ccccccccc E cccccccccc G ccccccccccccc H ccccccccccccccccccccccc xxxxxxx... xxxxxx... F xxxxxxxxxxxxxxxxx

Time Planning and Control

Time Planning and Control Time Planning and ontrol Precedence iagram G44 NGINRING MNGMNT 1 Precedence iagramming S ctivity I LS T L n important extension to the original activity-on-node concept appeared around 14. The sole relationship

More information

A scheme developed by Du Pont to figure out

A scheme developed by Du Pont to figure out CPM Project Management scheme. A scheme developed by Du Pont to figure out Length of a normal project schedule given task durations and their precedence in a network type layout (or Gantt chart) Two examples

More information

4. Network Calculations

4. Network Calculations Construction Project Management (CE 110401346) 4. Network Calculations Dr. Khaled Hyari Department of Civil Engineering Hashemite University Calculations On a Precedence Network I Early Activity Start

More information

PROGRAMMING CPM. Network Analysis. Goal:

PROGRAMMING CPM. Network Analysis. Goal: PROGRAMMING CPM 5/21/13 Network Analysis Goal: Calculate completion time Calculate start and finish date for each activity Identify critical activities Identify requirements and flows of resources (materials,

More information

. Introduction to CPM / PERT Techniques. Applications of CPM / PERT. Basic Steps in PERT / CPM. Frame work of PERT/CPM. Network Diagram Representation. Rules for Drawing Network Diagrams. Common Errors

More information

SAMPLE STUDY MATERIAL. GATE, IES & PSUs Civil Engineering

SAMPLE STUDY MATERIAL. GATE, IES & PSUs Civil Engineering SAMPLE STUDY MATERIAL Postal Correspondence Course GATE, IES & PSUs Civil Engineering CPM & CONSTRUCTION EQUIPMENT C O N T E N T 1. CPM AND PERT... 03-16 2. CRASHING OF NETWORK... 17-20 3. ENGINEERING

More information

Time Planning and Control. Time-Scaled Network

Time Planning and Control. Time-Scaled Network Time Planning and Control Time-Scaled Network Processes of Time Planning and Control 1.Visualize and define the activities..sequence the activities (Job Logic). 3.stimate the activity duration. 4.Schedule

More information

57:022 Principles of Design II Midterm Exam #2 Solutions

57:022 Principles of Design II Midterm Exam #2 Solutions 57:022 Principles of Design II Midterm Exam #2 Solutions Part: I II III IV V Total Possible Pts: 20 15 12 16 12 75 PART ONE Indicate "+" if True and "O" if False: _+_a. If a component's lifetime has exponential

More information

11/8/2018. Overview. PERT / CPM Part 2

11/8/2018. Overview. PERT / CPM Part 2 /8/08 PERT / CPM Part BSAD 0 Dave Novak Fall 08 Source: Anderson et al., 0 Quantitative Methods for Business th edition some slides are directly from J. Loucks 0 Cengage Learning Overview Last class introduce

More information

Network Techniques - I. t 5 4

Network Techniques - I. t 5 4 Performance:Slide.doc Network Techniques - I. t s v u PRT time/cost : ( Program valuation & Review Technique ) vent-on-node typed project-model with probabilistic (stochastic) data set as weights (inp)

More information

Project Time Planning. Ahmed Elyamany, PhD

Project Time Planning. Ahmed Elyamany, PhD Project Time Planning Ahmed Elyamany, PhD 1 What is Planning The Development of a workable program of operations to accomplish established objectives when put into action. Done before project starts Planning

More information

ST. JOSEPH S COLLEGE OF ARTS & SCIENCE (AUTONOMOUS) CUDDALORE-1

ST. JOSEPH S COLLEGE OF ARTS & SCIENCE (AUTONOMOUS) CUDDALORE-1 ST. JOSEPH S COLLEGE OF ARTS & SCIENCE (AUTONOMOUS) CUDDALORE-1 SUB:OPERATION RESEARCH CLASS: III B.SC SUB CODE:EMT617S SUB INCHARGE:S.JOHNSON SAVARIMUTHU 2 MARKS QUESTIONS 1. Write the general model of

More information

Topic 10 Directed graphs and networks

Topic 10 Directed graphs and networks Topic 1 irected graphs and networks TOPI 1 irected graphs and networks XIS 1. 1 xercise 1. ritical path analysis 1 arliest completion time is minutes., 1 1,,,,,,, 11 L, 1,, 1 The earliest completion time

More information

07/09/2011. A.AMRANI-ZOUGGAR IMS-Lab, University Bordeaux1. These products specific management

07/09/2011. A.AMRANI-ZOUGGAR IMS-Lab, University Bordeaux1. These products specific management A.AMRANI-ZOUGGAR IMS-Lab, University Bordeaux These products specific management What leads the industrialist to start projects? BENEFITS Ageing of the range Benchmarking, comparing the market and industrial

More information

Network analysis. A project is a temporary endeavor undertaken to create a "unique" product or service

Network analysis. A project is a temporary endeavor undertaken to create a unique product or service Network analysis Introduction Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects. One definition of a project

More information

MEI Decision Mathematics 1

MEI Decision Mathematics 1 Chapter assessment MEI Decision Mathematics Critical Path Analysis. The diagram below shows a precedence network for a particular project. 9 A() D(4) I(8) Durations are in days B() E() H(5) J(4) L() 5

More information

Vehicle Routing and Scheduling. Martin Savelsbergh The Logistics Institute Georgia Institute of Technology

Vehicle Routing and Scheduling. Martin Savelsbergh The Logistics Institute Georgia Institute of Technology Vehicle Routing and Scheduling Martin Savelsbergh The Logistics Institute Georgia Institute of Technology Vehicle Routing and Scheduling Part II: Algorithmic Enhancements Handling Practical Complexities

More information

(1) The starting point is the precedence table (aka dependence table) Immediately preceding activities

(1) The starting point is the precedence table (aka dependence table) Immediately preceding activities Critical Path Analysis (10 pages; 1/5/16) fmng.uk (1) The starting point is the precedence table (aka dependence table) Example Activity Duration Immediately preceding activities A 4 - B 5 - C 6 A,B D

More information

SUBPART MULTIYEAR CONTRACTING (Revised December 19, 2006)

SUBPART MULTIYEAR CONTRACTING (Revised December 19, 2006) SUBPART 217.1--MULTIYEAR CONTRACTING (Revised December 19, 2006) 217.103 Definitions. As used in this subpart-- Advance procurement means an exception to the full funding policy that allows acquisition

More information

56:171 Operations Research Midterm Exam--15 October 2002

56:171 Operations Research Midterm Exam--15 October 2002 Name 56:171 Operations Research Midterm Exam--15 October 2002 Possible Score 1. True/False 25 _ 2. LP sensitivity analysis 25 _ 3. Transportation problem 15 _ 4. LP tableaux 15 _ Total 80 _ Part I: True(+)

More information

Decision Mathematics Module D1

Decision Mathematics Module D1 E Examinations ecision Mathematics Module 1 Advanced Subsidiary / Advanced Level Paper E Time: 1 hour 3 minutes Instructions and Information andidates may use any calculator except those with a facility

More information

CHAPTER 12. (The interpretation of the symbols used in the equations is given in page 3)

CHAPTER 12. (The interpretation of the symbols used in the equations is given in page 3) CHAPTER 12 The equations needed: (The interpretation of the symbols used in the equations is given in page 3) 1. ATI = t D 35 4. ws = I average weekly CU 2. I turn = CU I average 5. ds = I average daily

More information

Town of Barnstable. Department of Public Work. Snow and Ice Control Operations Plan

Town of Barnstable. Department of Public Work. Snow and Ice Control Operations Plan Town of Barnstable Department of Public Work Snow and Ice Control Operations Plan I. Mission: The mission of the Department of Public Works is to remove accumulations of snow and ice from town, county

More information

OFFSHORE. Advanced Weather Technology

OFFSHORE. Advanced Weather Technology Contents 3 Advanced Weather Technology 5 Working Safely, While Limiting Downtime 6 Understanding the Weather Forecast Begins at the Tender Stage 7 Reducing Time and Costs on Projects is a Priority Across

More information

SYMBIOSIS CENTRE FOR DISTANCE LEARNING (SCDL) Subject: production and operations management

SYMBIOSIS CENTRE FOR DISTANCE LEARNING (SCDL) Subject: production and operations management Sample Questions: Section I: Subjective Questions 1. What are the inputs required to plan a master production schedule? 2. What are the different operations schedule types based on time and applications?

More information

Mathematics (JAN12MD0201) General Certificate of Education Advanced Level Examination January Unit Decision TOTAL.

Mathematics (JAN12MD0201) General Certificate of Education Advanced Level Examination January Unit Decision TOTAL. Centre Number Candidate Number For Examiner s Use Surname Other Names Candidate Signature Examiner s Initials Mathematics Unit Decision 2 Wednesday 25 January 2012 General Certificate of Education Advanced

More information

Ways to study a system System

Ways to study a system System Simulation What is simulation? Simple synonym: imitation We are interested in studying a system Instead of experimenting with the system itself we experiment with a model of the system Ways to study a

More information

MINUTES SPOA BOARD MEETING December 17, 2018

MINUTES SPOA BOARD MEETING December 17, 2018 h Open Forum 6:30 PM MINUTES SPOA BOARD MEETING December 17, 2018 There were no Open Forum Items this month. Board Meeting 7:00 PM Review and Approval of Minutes George Graham submitted the previous month

More information

M.SC. MATHEMATICS - II YEAR

M.SC. MATHEMATICS - II YEAR MANONMANIAM SUNDARANAR UNIVERSITY DIRECTORATE OF DISTANCE & CONTINUING EDUCATION TIRUNELVELI 627012, TAMIL NADU M.SC. MATHEMATICS - II YEAR DKM24 - OPERATIONS RESEARCH (From the academic year 2016-17)

More information

Bachelor s Degree Programme Operations Research (Valid from 1st January, 2012 to 30th November, 2012.)

Bachelor s Degree Programme Operations Research (Valid from 1st January, 2012 to 30th November, 2012.) AOR-01 ASSIGNMENT BOOKLET Bachelor s Degree Programme Operations Research (Valid from 1st January, 2012 to 30th November, 2012.) It is compulsory to submit the assignment before filling in the exam form.

More information

Qi Jian-xun,Sun Dedong

Qi Jian-xun,Sun Dedong Physics Procedia 24 (2012) 1530 1540 2012 International Conference on Applied Physics and Industrial Engineering One Improvement Method of Reducing Duration Directly to Solve Time-Cost Tradeoff Problem

More information

A Critical Path Problem Using Triangular Neutrosophic Number

A Critical Path Problem Using Triangular Neutrosophic Number A ritical Path Problem Using Triangular Neutrosophic Number Mai Mohamed 1 Department of Operations Research Faculty of omputers and Informatics Zagazig University, Sharqiyah, Egypt Yongquan Zhou 2 ollege

More information

ALAMEDA ISLES PROPOSED BUDGET FACT SHEET

ALAMEDA ISLES PROPOSED BUDGET FACT SHEET ALAMEDA ISLES PROPOSED BUDGET FACT SHEET These sheets outline the proposed 2015/2016 budget in two parts. The first part is the operating budget which shows our income and anticipated expenses with a comparative

More information

Food Safety and Quality Management System

Food Safety and Quality Management System Introduction The company has planned, established, documented and implemented a food safety and quality management system for the site, which is maintained in order to continually improve its effectiveness

More information

56:171 Operations Research Final Exam December 12, 1994

56:171 Operations Research Final Exam December 12, 1994 56:171 Operations Research Final Exam December 12, 1994 Write your name on the first page, and initial the other pages. The response "NOTA " = "None of the above" Answer both parts A & B, and five sections

More information

Income Statement Lakeview Accrual Basis Jun 2018

Income Statement Lakeview Accrual Basis Jun 2018 Lakeview Accrual Basis Jun 2018 Property: Lakeview Income Revenues 4010-0000 Gross Market Rent - 30,656.00 30,656.00 30,656.00 30,656.00 30,563.00 30,499.00 30,467.00 30,403.00 30,403.00 30,339.00 30,307.00

More information

Chapter 7 Network Flow Problems, I

Chapter 7 Network Flow Problems, I Chapter 7 Network Flow Problems, I Network flow problems are the most frequently solved linear programming problems. They include as special cases, the assignment, transportation, maximum flow, and shortest

More information

Embedded Systems - FS 2018

Embedded Systems - FS 2018 Institut für Technische Informatik und Kommunikationsnetze Prof. L. Thiele Embedded Systems - FS 2018 Sample solution to Exercise 3 Discussion Date: 11.4.2018 Aperiodic Scheduling Task 1: Earliest Deadline

More information

2. Project management

2. Project management 2. Project management In what follows, we consider production processes where only a single item of a specific product is produced in the planning horizon In this case specific instruments for planning

More information

Knapsack and Scheduling Problems. The Greedy Method

Knapsack and Scheduling Problems. The Greedy Method The Greedy Method: Knapsack and Scheduling Problems The Greedy Method 1 Outline and Reading Task Scheduling Fractional Knapsack Problem The Greedy Method 2 Elements of Greedy Strategy An greedy algorithm

More information

Reed School/Westover Library U USE PERMIT AMENDMENT. Staff Presentation to the County Board November 17, 2018

Reed School/Westover Library U USE PERMIT AMENDMENT. Staff Presentation to the County Board November 17, 2018 Reed School/Westover Library U-3175-07-1 USE PERMIT AMENDMENT Staff Presentation to the County Board November 17, 2018 Site Location 2 Background 1644 N. McKinley Road 1938: Walter Reed Elementary School

More information

Forecasting without Fear

Forecasting without Fear Forecasting without Fear How to keep the business informed and keep your cool NY SPIN December 15, 2015 Drivers, Challenges why you have to forecast, and why it s not easy what you forecast Refinement

More information

Wednesday 25 January 2012 Afternoon

Wednesday 25 January 2012 Afternoon Wednesday 25 January 2012 Afternoon A2 GCE MATHEMATICS 4737 Decision Mathematics 2 QUESTION PAPER *4733040112* Candidates answer on the Printed Answer Book. OCR supplied materials: Printed Answer Book

More information

Advanced/Advanced Subsidiary

Advanced/Advanced Subsidiary Paper Reference(s) 6689/01 dexcel GC ecision Mathematics 1 dvanced/dvanced Subsidiary Thursday 16 June 2005 fternoon Time: 1 hour 30 minutes Materials required for examination Nil Items included with question

More information

Decision Mathematics D1

Decision Mathematics D1 Pearson Edexcel GCE Decision Mathematics D1 Advanced/Advanced Subsidiary Friday 17 June 2016 Afternoon Time: 1 hour 30 minutes Paper Reference 6689/01 You must have: D1 Answer Book Candidates may use any

More information

Chapter 3: Discrete Optimization Integer Programming

Chapter 3: Discrete Optimization Integer Programming Chapter 3: Discrete Optimization Integer Programming Edoardo Amaldi DEIB Politecnico di Milano edoardo.amaldi@polimi.it Sito web: http://home.deib.polimi.it/amaldi/ott-13-14.shtml A.A. 2013-14 Edoardo

More information

Message Passing Algorithms and Junction Tree Algorithms

Message Passing Algorithms and Junction Tree Algorithms Message Passing lgorithms and Junction Tree lgorithms Le Song Machine Learning II: dvanced Topics S 8803ML, Spring 2012 Inference in raphical Models eneral form of the inference problem P X 1,, X n Ψ(

More information

Decision Mathematics Module D1

Decision Mathematics Module D1 GCE Examinations Decision Mathematics Module D1 Advanced Subsidiary / Advanced Level Paper B Time: 1 hour 30 minutes Instructions and Information Candidates may use any calculator except those with a facility

More information

CS521 CSE IITG 11/23/2012

CS521 CSE IITG 11/23/2012 Today Scheduling: lassification Ref: Scheduling lgorithm Peter rukerook Multiprocessor Scheduling : List PTS Ref job scheduling, by uwe schweigelshohn Tomorrow istributed Scheduling ilk Programming and

More information

Mathematics (JUN13MD0201) General Certificate of Education Advanced Level Examination June Unit Decision TOTAL.

Mathematics (JUN13MD0201) General Certificate of Education Advanced Level Examination June Unit Decision TOTAL. Centre Number Candidate Number For Examiner s Use Surname Other Names Candidate Signature Examiner s Initials Mathematics Unit Decision 2 Thursday 13 June 2013 General Certificate of Education Advanced

More information

Morning Time: 1 hour 30 minutes

Morning Time: 1 hour 30 minutes ADVANCED SUBSIDIARY GCE 477/0 MATHEMATICS (MEI) Decision Mathematics THURSDAY 2 JUNE 2008 Morning Time: hour 30 minutes *CUP/T44383* Additional materials: Printed Answer Book (enclosed) MEI Examination

More information

New Theory and Algorithms for Scheduling Arc Shutdown Jobs in Networks

New Theory and Algorithms for Scheduling Arc Shutdown Jobs in Networks New Theory and Algorithms for Scheduling Arc Shutdown Jobs in Networks Patrick Andersen February 27, 2014 This project explores a recently developed type of scheduling problem that combines the two Operations

More information

GUIDELINES FOR FILMING IN TOMBALL, TEXAS

GUIDELINES FOR FILMING IN TOMBALL, TEXAS GUIDELINES FOR FILMING IN TOMBALL, TEXAS I. PURPOSE The following guidelines are intended to protect the personal and property rights of our Tomball, Texas residents and businesses. The City Manager reserves

More information

PW 001 SNOW REMOVAL AND SANDING FOR ROADWAYS AND SIDEWALKS October 6, 2014 (#223-14) Original October 19, 2015; October 15, 2018 Public Works

PW 001 SNOW REMOVAL AND SANDING FOR ROADWAYS AND SIDEWALKS October 6, 2014 (#223-14) Original October 19, 2015; October 15, 2018 Public Works Policy Statement: The Village of Kitscoty will provide snow and ice control on municipal streets and sidewalks according to determined priorities. Purpose: To provide direction and information to employees

More information

PROJECT MANAGEMENT CHAPTER 1

PROJECT MANAGEMENT CHAPTER 1 PROJECT MANAGEMENT CHAPTER 1 Project management is the process and activity of planning, organizing, motivating, and controlling resources, procedures and protocols to achieve specific goals in scientific

More information

1.225 Transportation Flow Systems Quiz (December 17, 2001; Duration: 3 hours)

1.225 Transportation Flow Systems Quiz (December 17, 2001; Duration: 3 hours) 1.225 Transportation Flow Systems Quiz (December 17, 2001; Duration: 3 hours) Student Name: Alias: Instructions: 1. This exam is open-book 2. No cooperation is permitted 3. Please write down your name

More information

Review Exercise 2. 1 a Chemical A 5x+ Chemical B 2x+ 2y12 [ x+ Chemical C [ 4 12]

Review Exercise 2. 1 a Chemical A 5x+ Chemical B 2x+ 2y12 [ x+ Chemical C [ 4 12] Review Exercise a Chemical A 5x+ y 0 Chemical B x+ y [ x+ y 6] b Chemical C 6 [ ] x+ y x+ y x, y 0 c T = x+ y d ( x, y) = (, ) T = Pearson Education Ltd 08. Copying permitted for purchasing institution

More information

Project management model for constructing a renewable energy plant

Project management model for constructing a renewable energy plant Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 74 (207 ) 45 54 206 Global Congress on Manufacturing and Management Project management model for constructing a renewable energy

More information

Duration of online examination will be of 1 Hour 20 minutes (80 minutes).

Duration of online examination will be of 1 Hour 20 minutes (80 minutes). Program Name: SC Subject: Production and Operations Management Assessment Name: POM - Exam Weightage: 70 Total Marks: 70 Duration: 80 mins Online Examination: Online examination is a Computer based examination.

More information

Dynamic Programming Models

Dynamic Programming Models Chapter 19 Page 1 Dynamic Programming Models Many planning and control problems in manufacturing, telecommunications and capital budgeting call for a sequence of decisions to be made at fixed points in

More information

Temple City Unified School District A District of High Achieving Schools

Temple City Unified School District A District of High Achieving Schools Kathryn E. Perini Superintendent Temple City Unified School A of High Achieving Schools Board of Education John Pomeroy, President Vinson Bell, Vice President Kien C. Tiet, Clerk Kenneth Knollenberg, Member

More information

The Minimum Cost Network Flow Problem

The Minimum Cost Network Flow Problem EMIS 8374 [MCNFP Review] 1 The Minimum Cost Network Flow Problem Problem Instance: Given a network G = (N, A), with a cost c ij, upper bound u ij, and lower bound l ij associated with each directed arc

More information

Monitoring Radar Mechanical Drive Systems FAA's choice of monitoring solutions

Monitoring Radar Mechanical Drive Systems FAA's choice of monitoring solutions Monitoring Radar Mechanical Drive Systems FAA's choice of monitoring solutions Mission-critical Ask the public to name mission-critical systems, and air traffic control radar will be at the top of the

More information

physicsandmathstutor.com

physicsandmathstutor.com ADVANCED GCE MATHEMATICS 4737 Decision Mathematics 2 Candidates answer on the Answer Booklet OCR Supplied Materials: 8 page Answer Booklet Graph paper Insert for Questions 5 and 6 (inserted) List of Formulae

More information

Time allowed: 1.5 hours

Time allowed: 1.5 hours Student name College of ngineering Civil ngineering Department G 404: NGINRING MNGMNT Second Semester 1438/1439H (MODL NSWR) FIRST MIDTRM XM Monday 24/6/1439H (12/3/2018G) from 7:00 to 8:30 PM Time allowed:

More information

Real Estate Investor Calculator Project Workbook. Quick Estimate Factors MAIN DATA ENTRY

Real Estate Investor Calculator Project Workbook. Quick Estimate Factors MAIN DATA ENTRY MAIN DATA ENTRY 1 2 Current List / Asking Price: $ 175,000.00 Project Updated: 12/18/17 Original or Current Appraised / Market Value / AsIs: $ 180,000.00 AsIs Date: 12/18/17 Est. Resale Value / Post Renovations

More information

Logistical and Transportation Planning. QUIZ 1 Solutions

Logistical and Transportation Planning. QUIZ 1 Solutions QUIZ 1 Solutions Problem 1. Patrolling Police Car. A patrolling police car is assigned to the rectangular sector shown in the figure. The sector is bounded on all four sides by a roadway that requires

More information

19.0 Practical Issues in Regression

19.0 Practical Issues in Regression 19.0 Practical Issues in Regression 1 Answer Questions Nonparametric Regression Residual Plots Extrapolation 19.1 Nonparametric Regression Recall that the multiple linear regression model is Y = β 0 +

More information

Efficient Workplan Management in Maintenance Tasks

Efficient Workplan Management in Maintenance Tasks Efficient Workplan Management in Maintenance Tasks Michel Wilson a Nico Roos b Bob Huisman c Cees Witteveen a a Delft University of Technology, Dept of Software Technology b Maastricht University, Dept

More information

Project scheduling with calendars

Project scheduling with calendars OR Spektrum (2001) 23: 325 334 c Springer-Verlag 2001 Project scheduling with calendars Birger Franck, Klaus Neumann, and Christoph Schwindt Institut für Wirtschaftstheorie und Operations Research, University

More information

UNIT 4 TRANSPORTATION PROBLEM

UNIT 4 TRANSPORTATION PROBLEM UNIT 4 TRANSPORTATION PROLEM Structure 4.1 Introduction Objectives 4.2 Mathematical Formulation of the Transportation Problem 4.3 Methods of Finding Initial asic Feasible Solution North-West orner Rule

More information

Embedded Systems 15. REVIEW: Aperiodic scheduling. C i J i 0 a i s i f i d i

Embedded Systems 15. REVIEW: Aperiodic scheduling. C i J i 0 a i s i f i d i Embedded Systems 15-1 - REVIEW: Aperiodic scheduling C i J i 0 a i s i f i d i Given: A set of non-periodic tasks {J 1,, J n } with arrival times a i, deadlines d i, computation times C i precedence constraints

More information

BUILDING AND SAFETY FEE SCHEDULE (Effective July1, 2013)

BUILDING AND SAFETY FEE SCHEDULE (Effective July1, 2013) BUILDING AND SAFETY DIVISION TELEPHONE (949) 724-6300 BUILDING AND SAFETY FEE SCHEDULE (Effective July1, 2013) Payment: When a plan is required by the Administrative Authority to be submitted, a plan check

More information

Unit 7 Systems and Linear Programming

Unit 7 Systems and Linear Programming Unit 7 Systems and Linear Programming PREREQUISITE SKILLS: students should be able to solve linear equations students should be able to graph linear equations students should be able to create linear equations

More information

Methods and Models for Combinatorial Optimization

Methods and Models for Combinatorial Optimization Methods and Models for Combinatorial Optimization Modeling by Linear Programming Luigi De Giovanni, Marco Di Summa Dipartimento di Matematica, Università di Padova De Giovanni, Di Summa MeMoCO 1 / 35 Mathematical

More information

Drilling Commences at Bolivian Tin Sites

Drilling Commences at Bolivian Tin Sites ASX ANNOUNCEMENT 17 October 2017 Drilling Commences at Bolivian Tin Sites Highlights Drilling and sampling has commenced at Victory s tin tail deposits in Bolivia. Approximately 105m of drilling has been

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS STRUCTURAL ENGINEERING FIRM TO PERFORM A STRUCTURAL EVALUATION OF THE MARKET STREET PARKADE FACILITY REFERENCE RFP 14-148 Addendum Issued: August 22, 2014 ADDENDUM No. 2 Page 1 of

More information

Design Example: 4-bit Sequence Detector

Design Example: 4-bit Sequence Detector Design Example: 4-bit Sequence Detector We are asked to design a 4-bit sequence detector. For each 4 bits that are input, we need to see whether they match one of two given sequences: 1010 or 0110. The

More information

PREPARED BY: INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad

PREPARED BY: INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad - 500 043 PREPARED BY: A. SOMAIAH, ASST. PROFESSOR T. VANAJA, ASST. PROFESSOR DEPT. OF MECHANICAL ENGINEERING 1 Syllabus UNIT-I Development

More information

Calculation exercise 1 MRP, JIT, TOC and SOP. Dr Jussi Heikkilä

Calculation exercise 1 MRP, JIT, TOC and SOP. Dr Jussi Heikkilä Calculation exercise 1 MRP, JIT, TOC and SOP Dr Jussi Heikkilä Problem 1: MRP in XYZ Company fixed lot size Item A Period 1 2 3 4 5 6 7 8 9 10 Gross requirements 71 46 49 55 52 47 51 48 56 51 Scheduled

More information

Decision Mathematics D1 Advanced/Advanced Subsidiary. Friday 17 May 2013 Morning Time: 1 hour 30 minutes

Decision Mathematics D1 Advanced/Advanced Subsidiary. Friday 17 May 2013 Morning Time: 1 hour 30 minutes Paper Reference(s) 6689/01 Edexcel GCE Decision Mathematics D1 Advanced/Advanced Subsidiary Friday 17 May 2013 Morning Time: 1 hour 30 minutes Materials required for examination Nil Items included with

More information

INCLEMENT WEATHER CLOSING CODES

INCLEMENT WEATHER CLOSING CODES INCLEMENT WEATHER CLOSING CODES Code 0 Code 1 Code 2 Code 3 Code 4 Code 5 Code 6 ALL operations are closed and no employees should report to work. Transportation personnel, maintenance personnel, ALL custodial

More information

SPECIAL REVENUE (GRANT) FUNDS

SPECIAL REVENUE (GRANT) FUNDS SPECIAL REVENUE (GRANT) FUNDS Special Revenue (Grant) Funds are comprised of grants and awards from various State, Federal and Local agencies or organizations. These funds are awarded by grantor and subject

More information

A comparison of sequencing formulations in a constraint generation procedure for avionics scheduling

A comparison of sequencing formulations in a constraint generation procedure for avionics scheduling A comparison of sequencing formulations in a constraint generation procedure for avionics scheduling Department of Mathematics, Linköping University Jessika Boberg LiTH-MAT-EX 2017/18 SE Credits: Level:

More information

SCHOOLING FOR LIFE FOUNDATION FINANCIAL STATEMENT FOR THE MONTH OF

SCHOOLING FOR LIFE FOUNDATION FINANCIAL STATEMENT FOR THE MONTH OF SCHOOLING FOR LIFE FOUNDATION FINANCIAL STATEMENT FOR THE MONTH OF MAY 2014 TO JUNE 2015 SCHOOLING FOR LIFE FOUNDATION CONTENTS: PAGE GENERAL INFORMATION 3 REPORT ON THE ACCOUNT DEPT. 4 FINANCIAL STATEMENT

More information

Peavine Estates HOA. Annual Review Without Site Visit. Better Reserve Consultants. Start Date: 01/01/2015. Mari Jo Betterley, RSS

Peavine Estates HOA. Annual Review Without Site Visit. Better Reserve Consultants. Start Date: 01/01/2015. Mari Jo Betterley, RSS Peavine Estates HOA Annual Review Without Site Visit Start Date: 01/01/2015 Better Reserve Consultants Mari Jo Betterley, RSS 0000025 Table of Contents Introduction Page 1 Important Information Page 8

More information

Coordinated Replenishments at a Single Stocking Point

Coordinated Replenishments at a Single Stocking Point Chapter 11 Coordinated Replenishments at a Single Stocking Point 11.1 Advantages and Disadvantages of Coordination Advantages of Coordination 1. Savings on unit purchase costs.. Savings on unit transportation

More information

2.2. The parties provided the following factual background (condensed to relevant facts)

2.2. The parties provided the following factual background (condensed to relevant facts) 1. Introduction Guidance No: DAB-24 The Delay Attribution Board (the Board) received a request for guidance in relation to the Attribution of TRUST delay incident 715839 (8 th January 2010) The Board received

More information

Food Safety Management System

Food Safety Management System Introduction The company has planned, established, documented and implemented a food safety management system for the site, in order to continually improve its effectiveness in accordance with legislation,

More information

COST SEGREGATION. For Building Owners

COST SEGREGATION. For Building Owners 180 Montgomery Street Suite 1950 San Francisco, CA 94104 phone : 415.394.7200 fax : 415.398.6501 web : moskowitzllp.com COST SEGREGATION For Building Owners 2 Moskowitz, LLP What is Cost Segregation? Cost

More information

FY18 YTD Activity by Fund Group Summary For Fiscal: Period Ending: 11/30/2017

FY18 YTD Activity by Fund Group Summary For Fiscal: Period Ending: 11/30/2017 City of Dana Point, CA FY18 by Fund Group Summary For Fiscal: 2017-2018 Period Ending: 11/30/2017 Fund: 01 - GENERAL Revenue RevenueType: 10 - Taxes & Franchises 6101 - Sec & Unsec Property Taxes 6103

More information

Production Planning and Control

Production Planning and Control Production Planning and Control MAERIAL REQUIREMEN PLANNING Haeryip Sihombing BMFP 453 4 Universiti eknikal Malaysia Melaka (UeM) HAERY SIHOMBING First widely available software implementation of a manufacturing

More information

Chapter 3: Discrete Optimization Integer Programming

Chapter 3: Discrete Optimization Integer Programming Chapter 3: Discrete Optimization Integer Programming Edoardo Amaldi DEIB Politecnico di Milano edoardo.amaldi@polimi.it Website: http://home.deib.polimi.it/amaldi/opt-16-17.shtml Academic year 2016-17

More information

SEXTANT & SEXTANT PE frequently asked questions

SEXTANT & SEXTANT PE frequently asked questions SEXTANT & SEXTANT PE frequently asked questions What is SEXTANT? SEXTANT is a software application that helps Financial Executives and Estimators determine their costing and budgeting standards also known

More information

Source: % % FINANCING SHORT TERM HOLDING / RESALE. 30 Maximun Offer to Resell (Fix/Flip): $ 424,000.00

Source: % % FINANCING SHORT TERM HOLDING / RESALE. 30 Maximun Offer to Resell (Fix/Flip): $ 424,000.00 MAIN DATA ENTRY Current List / Asking Price: $ 499,000.00 Project Updated: 11/15/17 Original or Current Appraised / Market Value / AsIs: $ 520,000.00 AsIs Date: 11/1/17 Est. Resale Value / Post Renovations

More information

GIS ADMINISTRATOR / WEB DEVELOPER EVANSVILLE-VANDERBURGH COUNTY AREA PLAN COMMISSION

GIS ADMINISTRATOR / WEB DEVELOPER EVANSVILLE-VANDERBURGH COUNTY AREA PLAN COMMISSION GIS ADMINISTRATOR / WEB DEVELOPER EVANSVILLE-VANDERBURGH COUNTY AREA PLAN COMMISSION SALARY RANGE INITIATION $43,277 SIX MONTHS $45,367 POSITION GRADE PAT VI The Evansville-Vanderburgh County Area Plan

More information

Globe Calendar Corporation

Globe Calendar Corporation +91-8048076367 Globe Calendar Corporation https://www.indiamart.com/globe-calendar/ We are engaged in designing, manufacturing and supplying Wall and Table Calenders. Our range is widely appreciated owing

More information

Network Flows. 4. Maximum Flows Problems. Fall 2010 Instructor: Dr. Masoud Yaghini

Network Flows. 4. Maximum Flows Problems. Fall 2010 Instructor: Dr. Masoud Yaghini In the name of God Network Flows 4. Maximum Flows Problems 4.1 Introduction Fall 2010 Instructor: Dr. Masoud Yaghini Introduction Introduction The maximum flow problem In a capacitated network, we wish

More information

Notice of Strata Committee Meeting. Strata Plan Name Mirage Apartments Address 1-29 Bunn Street PYRMONT NSW 2009

Notice of Strata Committee Meeting. Strata Plan Name Mirage Apartments Address 1-29 Bunn Street PYRMONT NSW 2009 Notice of Strata Committee Meeting Strata Plan 54229 Name Mirage Apartments Address PYRMONT NSW 2009 Meeting Date Tuesday, 30 May 2017 Time 6:30 PM Venue Boardroom, Novotel Darling Harbour Address 100

More information

The City of Houston is committed to work in partnership with the community to promote and protect the health and social well being of Houstonians

The City of Houston is committed to work in partnership with the community to promote and protect the health and social well being of Houstonians Integrating GIS in Decision Making y from the Process: A Case Study City of Houston, Texas Riju Stephen MS Brenda Reyes, MD, MPH MS MBA Ketan Inamdar Inamdar, MS, Mark Perry MPH Office of Surveillance

More information