Project management model for constructing a renewable energy plant

Size: px
Start display at page:

Download "Project management model for constructing a renewable energy plant"

Transcription

1 Available online at ScienceDirect Procedia Engineering 74 (207 ) Global Congress on Manufacturing and Management Project management model for constructing a renewable energy plant Amy H. I. Lee a, He-Yau Kang b, *, zu-ing Huang b a Department of echnology Management,Chung Hua University, aiwan b Department of Industrial Engineering and Management, National Chin-Yi University of echnology, aiwan Abstract A project management model is developed for constructing a renewable energy plant in this research. Program evaluation and review technique (PER) is applied first to find the critical activities when constructing the plant and to calculate the total project cost and total duration time for the project under normal condition. When some activities are crashed, the total duration time can be reduced. he total project cost and the total duration time for crashing various activities are calculated. he fuzzy PER model is developed by the fuzzy multiple objective linear programming, and the model can devise the project implementation plan to maximize the total degree of satisfaction while minimizing total project cost and total duration time. A case study of a wind turbine construction in aiwan is presented to show the practicality of the proposed models he he Authors. Authors. Published Published by Elsevier by Elsevier Ltd. his Ltd. is an his open is access open article under under the the CC CC BY-NC-ND BY-NC-ND license license ( Peer review under responsibility of the organizing committee of GCMM206 Peer-review under responsibility of the organizing committee of the 3th Global Congress on Manufacturing and Management Keywords: Renewable energy; project management; program evaluation and review technique (PER); fuzzy. * Corresponding He-Yau Kang. el.: Ext address: kanghy@ncut.edu.tw he Authors. Published by Elsevier Ltd. his is an open access article under the CC BY-NC-ND license ( Peer-review under responsibility of the organizing committee of the 3th Global Congress on Manufacturing and Management doi:0.06/j.proeng

2 46 Amy H.I. Lee et al. / Procedia Engineering 74 ( 207 ) Introduction With an enormous investment in time, capital and effort, the development a renewable energy plant is a very complicated task. A good project management for the construction of a plant is necessary. In a largescale project, the management needs to coordinate numerous activities throughout the organization. Several models, which aim to overcome the disadvantages with critical path method (CPM) and program evaluation and review technique (PER), have been introduced for the scheduling of construction projects, and some examples are vertical method, linear scheduling method and time scheduling method []. PER, developed in the late 950 s, was first applied for the US Navy to plan and control the Polaris missile program, and its emphasis was to complete the program in the shortest possible time. PER has the ability to cope with uncertain activity completion times, and it has the potential to reduce both the time and cost required to complete the project [2]. Some recent works on the project scheduling problem include Chrysafis and Papadopoulos [3], Jeang [4], Creemers et al.[5] and Yaghoubi et al.[6]. he rest of this paper is organized as follows. In section 2, two proposed models are introduced: a discrete PER model and a fuzzy PER model. In section 3, the proposed models are applied in the construction project of a wind turbine in aiwan. Some conclusion remarks are made in the last section. Nomenclature i j (, i j ) Node number, i =,2,,N. Node number, j =,2,,N. Sequence of nodes, j will be processed after i is processed. P C R otal duration time for the project otal cost for the project otal crashing cost for the project. E i Start time for activity i. S Slack time for node (, i j ). K D Direct cost of node (i, j) under normal time. D d Y s s l Normal duration time for node (i, j). Shortest duration time for node (i, j). Duration time for node (i, j). Crash time for node (i, j). Fuzzy crashing cost per unit time for node (i, j). Crashing cost per unit time for node (i, j). Fuzzy penalty cost per unit time.

3 Amy H.I. Lee et al. / Procedia Engineering 74 ( 207 ) l Penalty cost per unit time. 2. Proposed models 2.. Discrete PER model In this section, we assume that there is no uncertainty in implementing the project. hus, the duration time and cost parameters are known and certain. When crashing is considered, the total duration time and cost under various crashing activities can be calculated for the management as a reference. he mathematical model is as follows: D 0, N () Min C K Y s l Max E P i j i j Subject to: E E 0 i, j i j D Y i, j Y D d i, j E 0 E, E,, Y 0 i, j i j 2.2. Fuzzy PER model In this section, we assume that the crashing cost and penalty cost are uncertain. Crashing activities are considered to obtain a compromise solution [7]. he steps of the model are as follows: Step : Consider the fuzziness of crashing cost in each activity. Step 2: Construct a mathematical model. An optimal project planning and cost reduction alternative can be obtained by balancing the project duration time and cost. he original multiple objective linear programing model is as follows, and the objective function is to minimize the total crashing cost, which includes the crashing cost and the penalty cost, for the project: Min R Ys l Max0, EN P (7) Subject to: Eqs. (2)-(6) i j In the objective function, fuzzy crashing cost per unit time for node (i, j), s, and fuzzy penalty cost per unit time, l, are fuzzy in nature and can be represented by triangular fuzzy numbers. Ys is the total direct crashing cost, including the personnel cost, machinery cost, outsourcing cost and overtime cost. l Max{0,( EN P)} is the penalty cost if the project completion time is delayed. Eq. (2) is the constraint for the precedence of activities. Eq. (3) shows that the duration time for a node is the normal duration time for the node minus the crash time for the node. Eq. (4) shows that the crash time for a node must be less than or equal to the normal duration time for the node minus the shortest duration time for the node. Eq. (5) i j (2) (3) (4) (5) (6)

4 48 Amy H.I. Lee et al. / Procedia Engineering 74 ( 207 ) indicates that the start time for the first activity is 0. Eq. (6) ensures that the decision variables are nonnegative Step 3: Establish fuzzy multiple objective functions. () Based on Lai and Hwang [8], use the triangular fuzzy number to represent the crashing cost for l m u each activity, s, i.e. ( s, s, s ), as shown in Fig.. In addition, a fuzzy membership function,, is set to have a value between 0 and. s 0 l s m s u s s Fig.. Fuzzy membership function for the crashing cost, s In real practice, the distribution of triangular fuzzy number can contain three values: the most u l m pessimistic value, ( s ), the most optimistic value ( s ), and the most possible value ( s ). he fuzzy multiple objective linear programing model is as follows: Min GR i x (8) Subject to: Ax B x 0 l m u where G ( R, R, R ) Ri (9) (0) () Because G R i in the objective function is a triangular fuzzy number, its three prominent m u l points, R, R and R, can be used to transform the original fuzzy objective function into three objective functions. hey are to minimize the most possible value of the total crashing cost, G R, maximize the most optimistic value of the total crashing cost, G R 2, and minimize the most pessimistic value of the total crashing cost, G R 3. (2) Calculate the positive ideal solution (PIS) and negative ideal solution (NIS) for each objective function based on Hwang and Yoon [9]. he constraints are then added. (3) Based on the values of PIS and NIS, establish a membership function for each of the three objective functions. Step 4: Based on the membership function values and the fuzzy programming proposed by Zimmermann [0], auxiliary variable is introduced, and the original fuzzy multiple objective linear programming problem can be transformed into a crisp single-goal linear programming problem. By maximizing, a compromise solution can be obtained as follows:

5 Amy H.I. Lee et al. / Procedia Engineering 74 ( 207 ) Max Subject to: ( ) G R ( ) 2 (4) G R 2 G R 3 ( ) 3 E 0 E E 0 i, j i j D Y i, j Y D d i, j E, E,, Y 0 i, j i j 0 Step 5: Analyze the results. After solving the model, a compromise solution can be obtained. () otal crashing cost: R( G G, G, G G ) (22) R R3 R R R2 '' (2) otal project duration time: From P in the model, the optimal total project duration time after crashing activities can be obtained. 3. Case study In this section, the construction project of a wind turbine is used as an example to examine the practicality of the proposed models. he estimated time and costs are shown in able. Under normal condition, the completion time is 245 days. Under uncertain condition, triangular fuzzy number is applied, and the completion time is (70, 245, 255) days. If crashing occurs, a fuzzy crashing cost per unit time for node (i, j), s, incurs. In addition, 20 thousand N dollars or (5.5, 20, 23.5) thousand N dollars of variable penalty costs incurs for each day under normal condition and fuzzy condition, respectively. he network for the project is as depicted in Fig. 2. able. Basic information of the wind turbine project. Normal condition Fuzzy condition Completion time (days) 245 (70, 245, 255) Penalty cost (,000) 20 (5.5, 20, 23.5) (2) (3) (5) (6) (7) (8) (9) (20) (2) 4 Q W Z 2 3 F M 5 O 8 H 9 X 6 7

6 50 Amy H.I. Lee et al. / Procedia Engineering 74 ( 207 ) Fig. 2. Network for the wind turbine project. able 2. Basic construction data for wind turbine. 3.. Discrete PER model Activity Code Activity Duration time (day) Crashing cost per day (,000) W Foundation 84 $ X Generator 42 $ system Z Power 40 $ distribution box Q ower 30 $ M Nacelle 56 $9.4 6 F Rotor blade 84 $ O Wind turbine 7 $ H rial operation 30 $ Possible crashed time (day) he procedure for the discrete PER model in the case study is as follows: Step and 2: Calculate the earliest start time (ES), latest start time (LS), earliest finish time (EF), latest finish time (LF), and slack time of each activity, as shown in able 3. able 3. Four different times and slack time for each activity Activity code ES LS EF LF Slack W X Z Q M F O H Step 3: Find the critical path, which is shown as the dark path in Fig Q W Z 2 3 F M 5 O 8 H 9 X 6 7 Fig.. Critical path of the project.

7 Amy H.I. Lee et al. / Procedia Engineering 74 ( 207 ) Step 4: Based on the critical path depicted in Fig. 3, the total project cost and duration time can be calculated under the normal condition. he total project cost is thousand dollars, and the total duration time is 245 days, as shown in able 4. Next, based on Eqs. ()-(6), the total project cost and duration time with crashing activities can be obtained, as shown in able 4. For example, if the activity H is crashed for one day or two days, the total project cost will increase to and , respectively. able 4. Project duration and cost Project duration(day) Crashing activity and crashing days otal project cost(,000) H H H Z 5H W 3Z 2H W 3Z 2H W 23Z 2H W 24Z 2F 9H W 24Z 2F 9H W 24Z 2F 24H W 24Z 2F 24O H W 24Z 2F 24O 2H Fuzzy PER model he procedure for the fuzzy PER model in the case study is as follows: Step : Consider the fuzziness of crashing costs. able 5. Project activity durations and costs Activity Code Activity Crashing cost per day (,000) (l,m,u) W Foundation (0.64,5.05,6.4) X Generator system (7.38,8.85,2.38) Z Power distribution box (4.23,4.72,8.48) Q ower (5.36,6.32,25.5) M Nacelle (8.5,9.4,3.2) F Rotor blade (4.52,5.2,8) O Wind turbine (63.05,68.77,92.33) H rial operation (.7,2.67,5.47) Step 2Establish an objective function for the project by applying Eq. (7). Min R (0.64,5.05,6.4* Y (7.38,8.85,2.38)* Y (4.23,4.72,8.48)* Y (5.36,6.32,25.5)* Y (8.5,9.4,3.2)* Y (4.52,5.2,8)* Y (63.05,68.77,92.33)* Y (.7, 2.67,5.47)* Y ((5.5, 20, 23.5)* Max 0,(E 73) ) 89 9

8 52 Amy H.I. Lee et al. / Procedia Engineering 74 ( 207 ) Step 3: Establish fuzzy multiple objective functions. () List three objective functions Min G 5.05* Y 8.85* Y 4.72* Y 6.32* Y 9.4* Y R * Y 68.77* Y 2.67* Y (20* Max {0,(E Min G.09* Y 3.53* Y 3.76* Y 9.8* Y 4.06* Y R * Y 2.8* Y 3.5*(E Max G 4.4* Y.47* Y 0.49* Y 0.96* Y 0.64* Y R * Y 5.72* Y.5* Y 4.5*(E (2) Calculate the positive ideal solution (PIS) and negative ideal solution (NIS) for each objective function. he results are shown in able 6. able 6. he PIS and NIS for each objective function. G R G R 2 G R 3 PIS NIS (3) Based on the values of PIS and NIS, establish a membership function for each of the three objective functions. hey are as follows:, GR GR ( GR ), G R , GR , GR GR 2 2( GR ), G R , GR , GR GR ( GR ), G R , GR Step 4: he fuzzy multiple objective linear programming problem can be transformed into a crisp single-goal linear programming problem using Eqs. (2)-(2). By maximizing, a compromise solution can be obtained. Max Subject to G R G R

9 Amy H.I. Lee et al. / Procedia Engineering 74 ( 207 ) G R E =0 E2E2 0 E7E7 0 E223E3 0 E334E4 0 E335E5 0 E445E5 0 E336E6 0 E556E6 0 E668E8 0 E778E8 0 E889E Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y E9 240, Y, E 0 i, j i 0 Step 5: Analyze the results. hey are as follows. () otal project cost: We can obtain dollars, and GR 3 GR thousand dollars, GR thousand thousand dollars. By applying Eq. (22), the total project cost is

10 54 Amy H.I. Lee et al. / Procedia Engineering 74 ( 207 ) R =(668.22, 22.68, ) thousand dollars. (2) otal project duration time: With crashing activities, the optimal duration time is P days. 4. Conclusions In this research, program evaluation and review technique (PER) is adopted to find the critical activities when constructing the plant. he total project cost and total duration time for the project under normal condition are calculated first. When some activities are crashed, the total duration time can be reduced. hus, the total project cost and the total duration time for crashing various activities are obtained for reference. Because the crash time of each activity is usually uncertain, the fuzzy set theory is incorporated with the PER next. A fuzzy multiple objective linear programming is constructed to solve the fuzzy PER model. By maximizing the total degree of satisfaction through minimizing total project cost and total duration time, a compromise solution can be obtained. he practicality of the proposed models is examined by carrying out a case study of a wind turbine construction in aiwan. he proposed model can help the management consider relevant information in the construction process systematically so that resources can be best utilized and costs can be minimized. Acknowledgements his work was supported in part by the Ministry of Science and echnology in aiwan under Grant MOS E MY2. References [] K.A. Chrysafis, B.K. Papadopoulos. Approaching activity duration in PER by means of fuzzy sets theory and statistics. J Intell Fuzzy Syst 204;26(2): [2] A. Azaron, R.. Moghaddam. A multi-objective resource allocation problem in dynamic PER networks. Appl Math Comput 2006;8(): [3] K.A. Chrysafis, B.K. Papadopoulos. Approaching activity duration in PER by means of fuzzy sets theory and statistics. J Intell Fuzzy Syst 204;26(2): [4] A. Jeang. Project management for uncertainty with multiple objectives optimisation of time, cost and reliability. Int J Prod Res 205; 53: [5] S. Creemers, B. DeReyck, R. Leus. Project planning with alternative technologies in uncertain environments. Eur J Oper Res 205;242: [6] S. Yaghoubi, S. Noori, A. Azaron, B. Fynes. Resource allocation in multi-class dynamic PER networks with finite capacity. Eur J Oper Res 205;247: [7].F. Liang,.S. Huang, M.F. Yang. Application of fuzzy mathematical programming to imprecise project management decisions. Qual Quant 202;46: [8] Y.J. Lai, C.L. Hwang. A new approach to some possibilistic linear programming problems. Fuzzy Set Syst 992;49(2):2-33. [9] C.L. Hwang, K. Yoon. Multiple attribute decision making: methods and applications. New York: Springer-Verlag; 98. [0] H.J. Zimmermann. Fuzzy programming and linear programming with several objective functions. Fuzzy Set Syst 978;:45-55.

11/8/2018. Overview. PERT / CPM Part 2

11/8/2018. Overview. PERT / CPM Part 2 /8/08 PERT / CPM Part BSAD 0 Dave Novak Fall 08 Source: Anderson et al., 0 Quantitative Methods for Business th edition some slides are directly from J. Loucks 0 Cengage Learning Overview Last class introduce

More information

. Introduction to CPM / PERT Techniques. Applications of CPM / PERT. Basic Steps in PERT / CPM. Frame work of PERT/CPM. Network Diagram Representation. Rules for Drawing Network Diagrams. Common Errors

More information

A scheme developed by Du Pont to figure out

A scheme developed by Du Pont to figure out CPM Project Management scheme. A scheme developed by Du Pont to figure out Length of a normal project schedule given task durations and their precedence in a network type layout (or Gantt chart) Two examples

More information

Available online at ScienceDirect. Procedia Engineering 133 (2015 ) th Fatigue Design conference, Fatigue Design 2015

Available online at  ScienceDirect. Procedia Engineering 133 (2015 ) th Fatigue Design conference, Fatigue Design 2015 Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 133 (2015 ) 613 621 6th Fatigue Design conference, Fatigue Design 2015 Response Spectra and Expected Fatigue Reliability: A

More information

Fuzzy Numerical Results Derived From Crashing CPM/PERT Networks of Padma Bridge in Bangladesh

Fuzzy Numerical Results Derived From Crashing CPM/PERT Networks of Padma Bridge in Bangladesh Fuzzy Numerical Results Derived From Crashing CPM/PERT Networks of Padma Bridge in Bangladesh Md. Mijanoor Rahman 1, Mrinal Chandra Barman 2, Sanjay Kumar Saha 3 1 Assistant Professor, Department of Mathematics,

More information

A Critical Path Problem in Neutrosophic Environment

A Critical Path Problem in Neutrosophic Environment A Critical Path Problem in Neutrosophic Environment Excerpt from NEUTROSOPHIC OPERATIONAL RESEARCH, Volume I. Editors: Prof. Florentin Smarandache, Dr. Mohamed Abdel-Basset, Dr. Yongquan Zhou. Foreword

More information

SAMPLE STUDY MATERIAL. GATE, IES & PSUs Civil Engineering

SAMPLE STUDY MATERIAL. GATE, IES & PSUs Civil Engineering SAMPLE STUDY MATERIAL Postal Correspondence Course GATE, IES & PSUs Civil Engineering CPM & CONSTRUCTION EQUIPMENT C O N T E N T 1. CPM AND PERT... 03-16 2. CRASHING OF NETWORK... 17-20 3. ENGINEERING

More information

Operation management

Operation management Operation management Vigneron Loic December 3, 2008 1 Operations and productivity 1.1 Productivity Productivity = Units produced Imput used Units produced Labor productivity = Labor hours used One resource

More information

Using Neutrosophic Sets to Obtain PERT Three-Times Estimates in Project Management

Using Neutrosophic Sets to Obtain PERT Three-Times Estimates in Project Management Using Neutrosophic Sets to Obtain PERT Three-Times Estimates in Project Management Mai Mohamed 1* Department of Operations Research Faculty of Computers and Informatics Zagazig University Sharqiyah Egypt

More information

A Critical Path Problem Using Triangular Neutrosophic Number

A Critical Path Problem Using Triangular Neutrosophic Number A Critical Path Problem Using Triangular Neutrosophic Number Excerpt from NEUTROSOPHIC OPERATIONAL RESEARCH, Volume I. Editors: Prof. Florentin Smarandache, Dr. Mohamed Abdel-Basset, Dr. Yongquan Zhou.

More information

Conception of effective number of lanes as basis of traffic optimization

Conception of effective number of lanes as basis of traffic optimization Available online at www.sciencedirect.com ScienceDirect Procedia Computer Science 91 (016 ) 94 100 Information Technology and Quantitative Management (ITQM 016) Conception of effective number of lanes

More information

Network analysis. A project is a temporary endeavor undertaken to create a "unique" product or service

Network analysis. A project is a temporary endeavor undertaken to create a unique product or service Network analysis Introduction Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects. One definition of a project

More information

PROGRAMMING CPM. Network Analysis. Goal:

PROGRAMMING CPM. Network Analysis. Goal: PROGRAMMING CPM 5/21/13 Network Analysis Goal: Calculate completion time Calculate start and finish date for each activity Identify critical activities Identify requirements and flows of resources (materials,

More information

Qi Jian-xun,Sun Dedong

Qi Jian-xun,Sun Dedong Physics Procedia 24 (2012) 1530 1540 2012 International Conference on Applied Physics and Industrial Engineering One Improvement Method of Reducing Duration Directly to Solve Time-Cost Tradeoff Problem

More information

CHAPTER 12. (The interpretation of the symbols used in the equations is given in page 3)

CHAPTER 12. (The interpretation of the symbols used in the equations is given in page 3) CHAPTER 12 The equations needed: (The interpretation of the symbols used in the equations is given in page 3) 1. ATI = t D 35 4. ws = I average weekly CU 2. I turn = CU I average 5. ds = I average daily

More information

A New Fuzzy Positive and Negative Ideal Solution for Fuzzy TOPSIS

A New Fuzzy Positive and Negative Ideal Solution for Fuzzy TOPSIS A New Fuzzy Positive and Negative Ideal Solution for Fuzzy TOPSIS MEHDI AMIRI-AREF, NIKBAKHSH JAVADIAN, MOHAMMAD KAZEMI Department of Industrial Engineering Mazandaran University of Science & Technology

More information

Neutrosophic Sets, Project, Project Management, Gantt chart, CPM, PERT, Three-Time Estimate.

Neutrosophic Sets, Project, Project Management, Gantt chart, CPM, PERT, Three-Time Estimate. Using Neutrosophic Sets to Obtain PERT Three-Times Estimates in Project Management Excerpt from NEUTROSOPHIC OPERATIONAL RESEARCH, Volume I. Editors: Prof. Florentin Smarandache, Dr. Mohamed Abdel-Basset,

More information

Available online at ScienceDirect. Procedia Engineering 91 (2014 ) 63 68

Available online at   ScienceDirect. Procedia Engineering 91 (2014 ) 63 68 Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 9 (204 ) 63 68 XXIII R-S-P seminar, Theoretical Foundation of Civil Engineering (23RSP) (TFOC204) Solving an Unsteady-State

More information

Research Article A Compensatory Approach to Multiobjective Linear Transportation Problem with Fuzzy Cost Coefficients

Research Article A Compensatory Approach to Multiobjective Linear Transportation Problem with Fuzzy Cost Coefficients Mathematical Problems in Engineering Volume 2011, Article ID 103437, 19 pages doi:10.1155/2011/103437 Research Article A Compensatory Approach to Multiobjective Linear Transportation Problem with Fuzzy

More information

Available online at ScienceDirect. Procedia Computer Science 22 (2013 )

Available online at   ScienceDirect. Procedia Computer Science 22 (2013 ) Available online at www.sciencedirect.com ScienceDirect Procedia Computer Science 22 (2013 ) 1121 1125 17 th International Conference in Knowledge Based and Intelligent Information and Engineering Systems

More information

Available online at ScienceDirect. Procedia Engineering 106 (2015 ) Dynamics and Vibroacoustics of Machines (DVM2014)

Available online at  ScienceDirect. Procedia Engineering 106 (2015 ) Dynamics and Vibroacoustics of Machines (DVM2014) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering (5 ) 49 57 Dynamics and Vibroacoustics of Machines (DVM4) Process simulation of energy behaviour of pneumatic drives Elvira

More information

Cost Analysis of a vacation machine repair model

Cost Analysis of a vacation machine repair model Available online at www.sciencedirect.com Procedia - Social and Behavioral Sciences 25 (2011) 246 256 International Conference on Asia Pacific Business Innovation & Technology Management Cost Analysis

More information

07/09/2011. A.AMRANI-ZOUGGAR IMS-Lab, University Bordeaux1. These products specific management

07/09/2011. A.AMRANI-ZOUGGAR IMS-Lab, University Bordeaux1. These products specific management A.AMRANI-ZOUGGAR IMS-Lab, University Bordeaux These products specific management What leads the industrialist to start projects? BENEFITS Ageing of the range Benchmarking, comparing the market and industrial

More information

4. Network Calculations

4. Network Calculations Construction Project Management (CE 110401346) 4. Network Calculations Dr. Khaled Hyari Department of Civil Engineering Hashemite University Calculations On a Precedence Network I Early Activity Start

More information

Estimating analytically the capacity of batch plants with shared equipment: a yoghurt plant case study

Estimating analytically the capacity of batch plants with shared equipment: a yoghurt plant case study Procedia Food Science (0) 79 798 th International Congress on Engineering and Food (ICEF) Estimating analytically the capacity of batch plants with shared equipment: a yoghurt plant case study Alexandros

More information

Solving Fuzzy PERT Using Gradual Real Numbers

Solving Fuzzy PERT Using Gradual Real Numbers Solving Fuzzy PERT Using Gradual Real Numbers Jérôme FORTIN a, Didier DUBOIS a, a IRIT/UPS 8 route de Narbonne, 3062, Toulouse, cedex 4, France, e-mail: {fortin, dubois}@irit.fr Abstract. From a set of

More information

Available online at ScienceDirect. Procedia Engineering 174 (2017 )

Available online at  ScienceDirect. Procedia Engineering 174 (2017 ) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 174 (2017 ) 1257 1261 13th Global Congress on Manufacturing and Management, GCMM 2016 Research on the High resolution precision

More information

ScienceDirect. Centre of pressure detection and analysis with a high-resolution and low-cost smart insole

ScienceDirect. Centre of pressure detection and analysis with a high-resolution and low-cost smart insole Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 112 (2015 ) 146 151 7th Asia-Pacific Congress on Sports Technology, APCST 2015 Centre of pressure detection and analysis with

More information

Available online at ScienceDirect. Procedia Engineering 154 (2016 )

Available online at   ScienceDirect. Procedia Engineering 154 (2016 ) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 154 (2016 ) 574 581 12th International Conference on Hydroinformatics, HIC 2016 Research on the Strength and Space-time Distribution

More information

Robust Speed Controller Design for Permanent Magnet Synchronous Motor Drives Based on Sliding Mode Control

Robust Speed Controller Design for Permanent Magnet Synchronous Motor Drives Based on Sliding Mode Control Available online at www.sciencedirect.com ScienceDirect Energy Procedia 88 (2016 ) 867 873 CUE2015-Applied Energy Symposium and Summit 2015: ow carbon cities and urban energy systems Robust Speed Controller

More information

Available online at ScienceDirect. Procedia Engineering 100 (2015 )

Available online at   ScienceDirect. Procedia Engineering 100 (2015 ) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 100 (015 ) 345 349 5th DAAAM International Symposium on Intelligent Manufacturing and Automation, DAAAM 014 Control of Airflow

More information

Available online at ScienceDirect. Procedia Engineering 150 (2016 )

Available online at  ScienceDirect. Procedia Engineering 150 (2016 ) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 150 (2016 ) 126 131 International Conference on Industrial Engineering, ICIE 2016 The Thermo-Gas-Dynamic Modeling of Afterburning

More information

Available online at ScienceDirect. Procedia Engineering 81 (2014 ) Fengfeng Hu, Yu Sun*, Binbin Peng

Available online at   ScienceDirect. Procedia Engineering 81 (2014 ) Fengfeng Hu, Yu Sun*, Binbin Peng Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 81 (14 ) 1651 1656 11th International Conference on Technology of Plasticity, ICTP 14, 19-4 October 14, Nagoya Congress Center,

More information

Available online at ScienceDirect. Procedia Technology 25 (2016 )

Available online at   ScienceDirect. Procedia Technology 25 (2016 ) Available online at www.sciencedirect.com ScienceDirect Procedia Technology 25 (2016 ) 801 807 Global Colloquium in Recent Advancement and Effectual Researches in Engineering, Science and Technology (RAEREST

More information

Available online at ScienceDirect. Procedia Engineering 119 (2015 ) 13 18

Available online at   ScienceDirect. Procedia Engineering 119 (2015 ) 13 18 Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 119 (2015 ) 13 18 13th Computer Control for Water Industry Conference, CCWI 2015 Real-time burst detection in water distribution

More information

ScienceDirect. Experimental study of influence of movements on airflow under stratum ventilation

ScienceDirect. Experimental study of influence of movements on airflow under stratum ventilation Available online at www.sciencedirect.com ScienceDirect Energy Procedia 7 (15 ) 7 11 th International Building Physics Conference, IBPC 15 Experimental study of influence of movements on airflow under

More information

A Critical Path Problem Using Triangular Neutrosophic Number

A Critical Path Problem Using Triangular Neutrosophic Number A ritical Path Problem Using Triangular Neutrosophic Number Mai Mohamed 1 Department of Operations Research Faculty of omputers and Informatics Zagazig University, Sharqiyah, Egypt Yongquan Zhou 2 ollege

More information

Available online at ScienceDirect. Procedia Engineering 121 (2015 )

Available online at   ScienceDirect. Procedia Engineering 121 (2015 ) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 121 (2015 ) 2176 2183 9th International Symposium on Heating, Ventilation and Air Conditioning (ISHVAC) and the 3rd International

More information

Available online at ScienceDirect. Procedia CIRP 17 (2014 )

Available online at   ScienceDirect. Procedia CIRP 17 (2014 ) Available online at www.sciencedirect.com ScienceDirect Procedia CIRP 17 (14 ) 398 43 Variety Management in Manufacturing. Proceedings of the 47th CIRP Conference on Manufacturing Systems Adaptive Due

More information

MEAN-ABSOLUTE DEVIATION PORTFOLIO SELECTION MODEL WITH FUZZY RETURNS. 1. Introduction

MEAN-ABSOLUTE DEVIATION PORTFOLIO SELECTION MODEL WITH FUZZY RETURNS. 1. Introduction Iranian Journal of Fuzzy Systems Vol. 8, No. 4, (2011) pp. 61-75 61 MEAN-ABSOLUTE DEVIATION PORTFOLIO SELECTION MODEL WITH FUZZY RETURNS Z. QIN, M. WEN AND C. GU Abstract. In this paper, we consider portfolio

More information

Inclusion Relationship of Uncertain Sets

Inclusion Relationship of Uncertain Sets Yao Journal of Uncertainty Analysis Applications (2015) 3:13 DOI 10.1186/s40467-015-0037-5 RESEARCH Open Access Inclusion Relationship of Uncertain Sets Kai Yao Correspondence: yaokai@ucas.ac.cn School

More information

Available online at ScienceDirect. Procedia Engineering 127 (2015 )

Available online at   ScienceDirect. Procedia Engineering 127 (2015 ) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 127 (2015 ) 424 431 International Conference on Computational Heat and Mass Transfer-2015 Exponentially Fitted Initial Value

More information

Small size single-axis PV trackers: control strategies and system layout for energy optimization

Small size single-axis PV trackers: control strategies and system layout for energy optimization Available online at www.sciencedirect.com ScienceDirect Energy Procedia 82 (2015 ) 737 743 ATI 2015-70th Conference of the ATI Engineering Association Small size single-axis PV trackers: control strategies

More information

Available online at ScienceDirect. Energy Procedia 57 (2014 ) ISES Solar World Congress

Available online at   ScienceDirect. Energy Procedia 57 (2014 ) ISES Solar World Congress Available online at www.sciencedirect.com ScienceDirect Energy Procedia 57 (214 ) 1613 1622 213 ISES Solar World Congress Theoretical and Experimental Comparison of Box Solar Cookers with and without Internal

More information

Available online at ScienceDirect. Procedia Engineering 100 (2015 ) 41 45

Available online at  ScienceDirect. Procedia Engineering 100 (2015 ) 41 45 Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 100 (2015 41 45 25th DAAAM International Symposium on Intelligent Manufacturing and Automation, DAAAM 2014 Shear Stress Distribution

More information

Optimizing Project Time-Cost Trade-off Based on Uncertain Measure

Optimizing Project Time-Cost Trade-off Based on Uncertain Measure INFORMATION Volume xx, Number xx, pp.1-9 ISSN 1343-45 c 21x International Information Institute Optimizing Project Time-Cost Trade-off Based on Uncertain Measure Hua Ke 1, Huimin Liu 1, Guangdong Tian

More information

Power requirements for yield stress fluids in a vessel with forward-reverse rotating impeller

Power requirements for yield stress fluids in a vessel with forward-reverse rotating impeller Available online at www.sciencedirect.com Procedia Engineering 42 (2012 ) 1437 1444 20 th International Congress of Chemical and Process Engineering CHISA 2012 25 29 August 2012, Prague, Czech Republic

More information

Downloaded from iors.ir at 10: on Saturday May 12th 2018 Fuzzy Primal Simplex Algorithms for Solving Fuzzy Linear Programming Problems

Downloaded from iors.ir at 10: on Saturday May 12th 2018 Fuzzy Primal Simplex Algorithms for Solving Fuzzy Linear Programming Problems Iranian Journal of Operations esearch Vol 1, o 2, 2009, pp68-84 Fuzzy Primal Simplex Algorithms for Solving Fuzzy Linear Programming Problems ezam Mahdavi-Amiri 1 Seyed Hadi asseri 2 Alahbakhsh Yazdani

More information

Available online at ScienceDirect. Procedia Engineering 177 (2017 )

Available online at   ScienceDirect. Procedia Engineering 177 (2017 ) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 177 (2017 ) 204 209 XXI International Polish-Slovak Conference Machine Modeling and Simulations 2016 A finite element multi-mesh

More information

Fully fuzzy linear programming with inequality constraints

Fully fuzzy linear programming with inequality constraints Available online at http://ijim.srbiau.ac.ir/ Int. J. Industrial Mathematics (ISSN 2008-5621) Vol. 5, No. 4, 2013 Article ID IJIM-00280, 8 pages Research Article Fully fuzzy linear programming with inequality

More information

Available online at ScienceDirect. Procedia Engineering 105 (2015 )

Available online at   ScienceDirect. Procedia Engineering 105 (2015 ) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 05 (05 ) 858 864 6th BSME International Conference on Thermal Engineering (ICTE 04) Experimental investigation on friction coefficient

More information

CHAPTER-3 MULTI-OBJECTIVE SUPPLY CHAIN NETWORK PROBLEM

CHAPTER-3 MULTI-OBJECTIVE SUPPLY CHAIN NETWORK PROBLEM CHAPTER-3 MULTI-OBJECTIVE SUPPLY CHAIN NETWORK PROBLEM 3.1 Introduction A supply chain consists of parties involved, directly or indirectly, in fulfilling customer s request. The supply chain includes

More information

Available online at ScienceDirect. Procedia Engineering 90 (2014 )

Available online at   ScienceDirect. Procedia Engineering 90 (2014 ) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 9 (214 ) 599 64 1th International Conference on Mechanical Engineering, ICME 213 Validation criteria for DNS of turbulent heat

More information

Available online at ScienceDirect. Procedia Engineering 188 (2017 )

Available online at   ScienceDirect. Procedia Engineering 188 (2017 ) More info about this article: http://www.ndt.net/?id=22025 Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 188 (2017 ) 225 232 6th Asia Pacific Workshop on Structural Health

More information

Available online at ScienceDirect. Procedia Engineering 100 (2015 ) 56 63

Available online at   ScienceDirect. Procedia Engineering 100 (2015 ) 56 63 Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 100 (2015 ) 56 63 25th DAAAM International Symposium on Intelligent Manufacturing and Automation, DAAAM 2014 Definite Quadratic

More information

Computers and Mathematics with Applications. Project management for arbitrary random durations and cost attributes by applying network approaches

Computers and Mathematics with Applications. Project management for arbitrary random durations and cost attributes by applying network approaches Computers and Mathematics with Applications 56 (2008) 2650 2655 Contents lists available at ScienceDirect Computers and Mathematics with Applications journal homepage: www.elsevier.com/locate/camwa Project

More information

Decomposition and Intersection of Two Fuzzy Numbers for Fuzzy Preference Relations

Decomposition and Intersection of Two Fuzzy Numbers for Fuzzy Preference Relations S S symmetry Article Decomposition and Intersection of Two Fuzzy Numbers for Fuzzy Preference Relations Hui-Chin Tang ID Department of Industrial Engineering and Management, National Kaohsiung University

More information

A Comparative Study of Different Order Relations of Intervals

A Comparative Study of Different Order Relations of Intervals A Comparative Study of Different Order Relations of Intervals Samiran Karmakar Department of Business Mathematics and Statistics, St. Xavier s College, Kolkata, India skmath.rnc@gmail.com A. K. Bhunia

More information

ST. JOSEPH S COLLEGE OF ARTS & SCIENCE (AUTONOMOUS) CUDDALORE-1

ST. JOSEPH S COLLEGE OF ARTS & SCIENCE (AUTONOMOUS) CUDDALORE-1 ST. JOSEPH S COLLEGE OF ARTS & SCIENCE (AUTONOMOUS) CUDDALORE-1 SUB:OPERATION RESEARCH CLASS: III B.SC SUB CODE:EMT617S SUB INCHARGE:S.JOHNSON SAVARIMUTHU 2 MARKS QUESTIONS 1. Write the general model of

More information

Project Time Planning. Ahmed Elyamany, PhD

Project Time Planning. Ahmed Elyamany, PhD Project Time Planning Ahmed Elyamany, PhD 1 What is Planning The Development of a workable program of operations to accomplish established objectives when put into action. Done before project starts Planning

More information

Available online at ScienceDirect. Procedia Engineering 157 (2016 )

Available online at  ScienceDirect. Procedia Engineering 157 (2016 ) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 157 (2016 ) 264 270 IX International Conference on Computational Heat and Mass Transfer, ICCHMT2016 A device for measuring the

More information

ScienceDirect. The Stability of a Precessing and Nutating Viscoelastic Beam with a Tip Mass

ScienceDirect. The Stability of a Precessing and Nutating Viscoelastic Beam with a Tip Mass Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 144 (2016 ) 68 76 12th International Conference on Vibration Problems, ICOVP 2015 The Stability of a Precessing and Nutating

More information

A novel dual H infinity filters based battery parameter and state estimation approach for electric vehicles application

A novel dual H infinity filters based battery parameter and state estimation approach for electric vehicles application Available online at www.sciencedirect.com ScienceDirect Energy Procedia 3 (26 ) 375 38 Applied Energy Symposium and Forum, REM26: Renewable Energy Integration with Mini/Microgrid, 9-2 April 26, Maldives

More information

Available online at ScienceDirect. Procedia Engineering 79 (2014 ) 49 54

Available online at  ScienceDirect. Procedia Engineering 79 (2014 ) 49 54 Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 79 (2014 ) 49 54 37th National Conference on Theoretical and Applied Mechanics (37th NCTAM 2013) & The 1st International Conference

More information

The Trapezoidal Fuzzy Number. Linear Programming

The Trapezoidal Fuzzy Number. Linear Programming Journal of Innovative Technology and Education, Vol. 3, 2016, no. 1, 123-130 HIKARI Ltd, www.m-hikari.com http://dx.doi.org/10.12988/jite.2016.6825 The Trapezoidal Fuzzy Number Linear Programming Karyati

More information

Available online at ScienceDirect. Procedia Engineering 150 (2016 )

Available online at   ScienceDirect. Procedia Engineering 150 (2016 ) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 150 (2016 ) 260 265 International Conference on Industrial Engineering, ICIE 2016 Method for Determining of the Valve Cavitation

More information

Available online at ScienceDirect. Procedia Engineering 81 (2014 )

Available online at   ScienceDirect. Procedia Engineering 81 (2014 ) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 81 (2014 ) 132 136 11th International Conference on Technology of Plasticity, ICTP 2014, October 19-24, 2014, Nagoya Congress

More information

ScienceDirect. Fatigue life from sine-on-random excitations

ScienceDirect. Fatigue life from sine-on-random excitations Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 101 (2015 ) 235 242 3rd International Conference on Material and Component Performance under Variable Amplitude Loading, VAL2015

More information

IN many real-life situations we come across problems with

IN many real-life situations we come across problems with Algorithm for Interval Linear Programming Involving Interval Constraints Ibraheem Alolyan Abstract In real optimization, we always meet the criteria of useful outcomes increasing or expenses decreasing

More information

New Similarity Measures for Intuitionistic Fuzzy Sets

New Similarity Measures for Intuitionistic Fuzzy Sets Applied Mathematical Sciences, Vol. 8, 2014, no. 45, 2239-2250 HIKARI Ltd, www.m-hikari.com http://dx.doi.org/10.12988/ams.2014.43171 New Similarity Measures for Intuitionistic Fuzzy Sets Peerasak Intarapaiboon

More information

Available online at ScienceDirect. Procedia Computer Science 102 (2016 )

Available online at   ScienceDirect. Procedia Computer Science 102 (2016 ) Available online at www.sciencedirect.com ScienceDirect Procedia Computer Science 102 (2016 ) 309 316 12th International Conference on Application of Fuzzy Systems and Soft Computing, ICAFS 2016, 29-30

More information

Available online at ScienceDirect. Energy Procedia 74 (2015 )

Available online at   ScienceDirect. Energy Procedia 74 (2015 ) Available online at www.sciencedirect.com ScienceDirect Energy Procedia 74 (2015 ) 1440 1451 International Conference on Technologies and Materials for Renewable Energy, Environment and Sustainability,

More information

Nonlinear Transient Response of Basalt/Nickel FGM Composite Plates under Blast Load

Nonlinear Transient Response of Basalt/Nickel FGM Composite Plates under Blast Load Nonlinear Transient Response of Basalt/Nickel FGM Composite Plates under Blast Load Baştürk, S., Uyanık, H., & Kazancı, Z. (2016). Nonlinear Transient Response of Basalt/Nickel FGM Composite Plates under

More information

Spanning Tree Problem with Neutrosophic Edge Weights

Spanning Tree Problem with Neutrosophic Edge Weights Available online at www.sciencedirect.com ScienceDirect Procedia Computer Science 00 (08) 000 000 www.elsevier.com/locate/procedia The First International Conference On Intelligent Computing in Data Sciences

More information

Available online at ScienceDirect. Procedia Engineering 121 (2015 ) 19 26

Available online at   ScienceDirect. Procedia Engineering 121 (2015 ) 19 26 Availale online at www.sciencedirect.com ScienceDirect Procedia Engineering 121 (2015 ) 19 26 9th International Symposium on Heating, Ventilation and Air Conditioning (ISHVAC) and the 3rd International

More information

Bi-level Multi-objective Programming Problems with Fuzzy Parameters: Modified TOPSIS Approach

Bi-level Multi-objective Programming Problems with Fuzzy Parameters: Modified TOPSIS Approach International Journal of Management and Fuzzy Systems 2016; 2(5): 38-50 http://www.sciencepublishinggroup.com/j/ijmfs doi: 10.11648/j.ijmfs.20160205.11 Bi-level Multi-objective Programming Problems with

More information

Available online at ScienceDirect. Procedia Engineering 105 (2015 )

Available online at  ScienceDirect. Procedia Engineering 105 (2015 ) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 105 (015 ) 64 69 6th BSME International Conference on Thermal Engineering (ICTE 014) Numerical Study of Sub-Nozzle Flows for

More information

Available online at ScienceDirect. Procedia Engineering 90 (2014 )

Available online at   ScienceDirect. Procedia Engineering 90 (2014 ) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 9 (24 ) 55 556 th International Conference on Mechanical Engineering, ICME 23 Analysis of heat transfer and flow due to natural

More information

Sharif University of Technology. Scientia Iranica Transactions E: Industrial Engineering

Sharif University of Technology. Scientia Iranica Transactions E: Industrial Engineering Scientia Iranica E (2015) 22(6), 2571{254 Sharif University of Technology Scientia Iranica Transactions E: Industrial Engineering wwwscientiairanicacom A compromise decision-making model based on VIKOR

More information

Project Planning & Control Prof. Koshy Varghese Department of Civil Engineering Indian Institute of Technology, Madras

Project Planning & Control Prof. Koshy Varghese Department of Civil Engineering Indian Institute of Technology, Madras Project Planning & Control Prof. Koshy Varghese Department of Civil Engineering Indian Institute of Technology, Madras (Refer Slide Time: 00:16) Lecture - 52 PERT Background and Assumptions, Step wise

More information

Available online at ScienceDirect. Procedia Engineering 79 (2014 )

Available online at   ScienceDirect. Procedia Engineering 79 (2014 ) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 79 (2014 ) 617 621 CTAM 2013 The 37 th National Conference on Theoretical and Applied Mechanics (37th-NCTAM) The 1 st International

More information

Available online at ScienceDirect. Procedia Engineering 90 (2014 )

Available online at   ScienceDirect. Procedia Engineering 90 (2014 ) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 9 (4 ) 37 376 th International Conference on Mechanical Engineering, ICME 3 Free Convective Heat Transfer Flow of Temperature

More information

Interactive fuzzy programming for stochastic two-level linear programming problems through probability maximization

Interactive fuzzy programming for stochastic two-level linear programming problems through probability maximization ORIGINAL RESEARCH Interactive fuzzy programming for stochastic two-level linear programming problems through probability maximization Masatoshi Sakawa, Takeshi Matsui Faculty of Engineering, Hiroshima

More information

The Fault Diagnosis of Blower Ventilator Based-on Multi-class Support Vector Machines

The Fault Diagnosis of Blower Ventilator Based-on Multi-class Support Vector Machines Available online at www.sciencedirect.com Energy Procedia 17 (2012 ) 1193 1200 2012 International Conference on Future Electrical Power and Energy Systems The Fault Diagnosis of Blower Ventilator Based-on

More information

Fuzzy Systems for Multi-criteria Decision Making with Interval Data

Fuzzy Systems for Multi-criteria Decision Making with Interval Data International Journal of Mathematics And its Applications Volume 4, Issue 4 (2016), 201 206. (Special Issue) ISSN: 2347-1557 Available Online: http://imaa.in/ International Journal 2347-1557 of Mathematics

More information

Available online at ScienceDirect. Procedia Engineering 136 (2016 )

Available online at   ScienceDirect. Procedia Engineering 136 (2016 ) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 136 (2016 ) 275 279 The 20 th International Conference: Machine Modeling and Simulations, MMS 2015 Investigation of internal

More information

A note on the solution of fuzzy transportation problem using fuzzy linear system

A note on the solution of fuzzy transportation problem using fuzzy linear system 2013 (2013 1-9 Available online at wwwispacscom/fsva Volume 2013, Year 2013 Article ID fsva-00138, 9 Pages doi:105899/2013/fsva-00138 Research Article A note on the solution of fuzzy transportation problem

More information

LT10 program for solving basic problems connected with defect detection

LT10 program for solving basic problems connected with defect detection Available online at www.sciencedirect.com Physics Procedia 35 (2012 ) 122 127 Positron Studies of Defects 2011 LT10 program for solving basic problems connected with defect detection D. Giebel, J. Kansy

More information

Available online at ScienceDirect. Procedia Engineering 150 (2016 )

Available online at  ScienceDirect. Procedia Engineering 150 (2016 ) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 150 (2016 ) 579 583 International Conference on Industrial Engineering, ICIE 2016 Investigation of Cholesteric Liquid Crystals

More information

K. Zainuddin et al. / Procedia Engineering 20 (2011)

K. Zainuddin et al. / Procedia Engineering 20 (2011) Available online at www.sciencedirect.com Procedia Engineering 20 (2011) 154 158 The 2 nd International Building Control Conference 2011 Developing a UiTM (Perlis) Web-Based of Building Space Management

More information

Study of Fault Diagnosis Method Based on Data Fusion Technology

Study of Fault Diagnosis Method Based on Data Fusion Technology Available online at www.sciencedirect.com Procedia Engineering 29 (2012) 2590 2594 2012 International Workshop on Information and Electronics Engineering (IWIEE) Study of Fault Diagnosis Method Based on

More information

ScienceDirect. Contact Deformations under the Influence of Measurement Force

ScienceDirect. Contact Deformations under the Influence of Measurement Force Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 100 (2015 ) 569 573 25th DAAAM International Symposium on Intelligent Manufacturing and Automation, DAAAM 2014 Contact Deformations

More information

Available online at ScienceDirect. Procedia Engineering 74 (2014 )

Available online at   ScienceDirect. Procedia Engineering 74 (2014 ) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 74 (2014 ) 236 241 XV11 International Colloquim on Mechanical Fatigue of Metals (ICMFM17) ProFatigue: A software program for

More information

Available online at ScienceDirect. Energy Procedia 78 (2015 ) th International Building Physics Conference, IBPC 2015

Available online at  ScienceDirect. Energy Procedia 78 (2015 ) th International Building Physics Conference, IBPC 2015 Available online at www.sciencedirect.com ScienceDirect Energy Procedia 78 (2015 ) 146 151 6th International Building Physics Conference, IBPC 2015 A combined experimental and analytical approach for the

More information

Fuzzy Ridge Regression with non symmetric membership functions and quadratic models

Fuzzy Ridge Regression with non symmetric membership functions and quadratic models Fuzzy Ridge Regression with non symmetric membership functions and quadratic models S. Donoso, N. Marín, and M.A. Vila IDBIS Research Group - Dept. of Computer Science and A. I., E.T.S.I.I. - University

More information

Numerical Analysis In Short-Pulse Laser Heating Of Metals Based On The Dual-Phase-Lag Model Of Heat Conduction

Numerical Analysis In Short-Pulse Laser Heating Of Metals Based On The Dual-Phase-Lag Model Of Heat Conduction Proceedings of the World Congress on New echnologies (Newech 5) Barcelona, Spain July 5-7, 5 Paper No. Numerical Analysis In Short-Pulse Laser Heating Of Metals Based On he Dual-Phase-Lag Model Of Heat

More information

FUZZY MULTI OBJECTIVE MIXED INTEGER LINEAR PROGRAMMING TECHNIQUE FOR SUPPLY CHAIN MANAGEMENT

FUZZY MULTI OBJECTIVE MIXED INTEGER LINEAR PROGRAMMING TECHNIQUE FOR SUPPLY CHAIN MANAGEMENT International Journal of Pure and Applied Mathematics Volume 101 No. 5 2015, 781-790 ISSN: 1311-8080 (printed version); ISSN: 1314-3395 (on-line version) url: http://www.ijpam.eu PAijpam.eu FUZZY MULTI

More information

The parameterization of cloud cover

The parameterization of cloud cover vailable online at www.sciencedirect.com ScienceDirect Energy Procedia 57 (24 ) 293 298 23 ISES Solar World Congress The parameterization of cloud cover Heinrich Morf* Senior Member ISES, Buechraiweg 47,

More information

Available online at ScienceDirect. Procedia Computer Science 91 (2016 )

Available online at   ScienceDirect. Procedia Computer Science 91 (2016 ) Available online at www.sciencedirect.com ScienceDirect Procedia Computer Science 91 (2016 ) 101 108 Information Technology and Quantitative Management (ITQM 2016) About possible methods of generalization

More information

Available online at ScienceDirect. Procedia Technology 23 (2016 ) 42 50

Available online at   ScienceDirect. Procedia Technology 23 (2016 ) 42 50 Available online at www.sciencedirect.com ScienceDirect Procedia Technology 23 (216 ) 42 5 3rd International Conference on Innovations in Automation and Mechatronics Engineering, ICIAME 216 On the stiffness

More information