PROGRAMMING CPM. Network Analysis. Goal:
|
|
- Gerard Mosley
- 5 years ago
- Views:
Transcription
1 PROGRAMMING CPM 5/21/13 Network Analysis Goal: Calculate completion time Calculate start and finish date for each activity Identify critical activities Identify requirements and flows of resources (materials, labour, equipment, $$$) 1
2 Network Analysis Programme Evaluation Review Technique (PERT) Monte Carlo Simulation Line-of-Balance (LOB) Location-based Scheduling (LBS) Deterministic analysis: Shortest completion time For each activity: n Earliest and latest start dates (ES and LS) and consequently Earliest and latest finish dates (EF and LF) n Float (F) available Critical Path 2
3 Gives: Shortest completion time For each activity: n Earliest and latest start dates (ES and LS) and consequently Earliest and latest finish dates (EF and LF) n Float (F) available Critical Path Assumes: For each activity: n Fixed duration n Well-defined precedence relations 3
4 Activity-oriented Activity-on-Node representation is preferred 4
5 ID Activity Predecessor A Site Clearance - B Grading general area A C Excavation utility trenches B D Excavation foundations B E Placing formworks D F Placing reinforcements E G Installing sewer lines C H Installing other utilities C I Pouring concrete F J Remove formworks I (Lag = 4days) K Refill utility trenches G,H L Refill foundations J M Cleanup K,L 5
6 n Forward pass n Forward pass 6
7 n Forward pass Earliest completion date 3. Calculate LS & LF for each activity Total Float (TF) n Backward pass 7
8 3. Calculate LS & LF for each activity Total Float (TF) n Backward pass Activity Float: Total Float (TF): TF = LF LS LF n TF>0 Programming Flexibility: ES D ES EF n As long as the activity does not start before ES and does not finish after LF, the project earliest completion date remains unchanged: n For the same D, S can be delay up to TF days n For the same ES, D can be increased by up to TF days n A combination of the two above. 8
9 Activity Float: Total Float (TF): TF LF LS LF n TF>0 Programming Flexibility: = ES D ES EF n TF = 0 No programming Flexibility Critical Activity 3. Calculate LS & LF for each activity Total Float (TF) n Backward pass 9
10 3. Calculate LS & LF for each activity Total Float (TF) 4. Identify Critical Path 3. Calculate LS & LF for each activity Total Float (TF) 4. Identify Critical Path 10
11 3. Calculate LS & LF for each activity Total Float (TF) 4. Identify Critical Path Activity Float: Total Float (TF): Free Float (FF): FF Earliest of the ES of all successors Latest of the EF of all predecessors ES = successors ES EF successors predecessors EF D n = Delay that can be assigned to an activity without impacting the start time of all its successors. 11
12 Activity Float: Total Float (TF): Free Float (FF): Independent Float (IF): Earliest of the ES of all successors Latest of the LF of all predecessors IF = max( ES LF D;0) successors predecessors n = Float in «worst case situation» n = Float that cannot be used by any other activity n Rarely used. Activity Float: Total Float (TF): Free Float (FF): TF = LF ES D FF = ES EF Independent Float (IF): IF = max( ES LF D;0) succ succ predec D predec 12
13 Activity Float: ID Activity FF IF TF A Site Clearance B Grading general area C Excavation utility trenches D Excavation foundations E Placing formworks F Placing reinforcements G Installing sewer lines H Installing other utilities I Pouring concrete J Remove formworks K Refill utility trenches L Refill foundations M Cleanup Activity Float: 0 IF FF TF TF = 0 ( = FF = IF) OnCriticalPath TF is most commonly used But: A lot of float is shared between consecutive activities! 13
14 (Linked) Gantt/bar Chart Task Description (Name, Duration, Predec., Start / End, etc.) Calendar Non-linked: Activity defined by Start Date + Duration Linked: Activitiy defined by Predecessors + Duration n Automated calculation of ES, EF, LS, LF, TF(, FF, IF), Critical Path 14
15 Advantage: Calendar (+ holidays ) n Dates as opposed to days Communication Aggregation: WBS Standard types of activities n SMM7 (UK), CSI s Masterformat (USA), ASTM s Uniformat (USA) Spatial divisions 15
4. Network Calculations
Construction Project Management (CE 110401346) 4. Network Calculations Dr. Khaled Hyari Department of Civil Engineering Hashemite University Calculations On a Precedence Network I Early Activity Start
More informationA scheme developed by Du Pont to figure out
CPM Project Management scheme. A scheme developed by Du Pont to figure out Length of a normal project schedule given task durations and their precedence in a network type layout (or Gantt chart) Two examples
More information11/8/2018. Overview. PERT / CPM Part 2
/8/08 PERT / CPM Part BSAD 0 Dave Novak Fall 08 Source: Anderson et al., 0 Quantitative Methods for Business th edition some slides are directly from J. Loucks 0 Cengage Learning Overview Last class introduce
More information. Introduction to CPM / PERT Techniques. Applications of CPM / PERT. Basic Steps in PERT / CPM. Frame work of PERT/CPM. Network Diagram Representation. Rules for Drawing Network Diagrams. Common Errors
More informationSAMPLE STUDY MATERIAL. GATE, IES & PSUs Civil Engineering
SAMPLE STUDY MATERIAL Postal Correspondence Course GATE, IES & PSUs Civil Engineering CPM & CONSTRUCTION EQUIPMENT C O N T E N T 1. CPM AND PERT... 03-16 2. CRASHING OF NETWORK... 17-20 3. ENGINEERING
More informationCHAPTER 12. (The interpretation of the symbols used in the equations is given in page 3)
CHAPTER 12 The equations needed: (The interpretation of the symbols used in the equations is given in page 3) 1. ATI = t D 35 4. ws = I average weekly CU 2. I turn = CU I average 5. ds = I average daily
More informationProject Time Planning. Ahmed Elyamany, PhD
Project Time Planning Ahmed Elyamany, PhD 1 What is Planning The Development of a workable program of operations to accomplish established objectives when put into action. Done before project starts Planning
More information07/09/2011. A.AMRANI-ZOUGGAR IMS-Lab, University Bordeaux1. These products specific management
A.AMRANI-ZOUGGAR IMS-Lab, University Bordeaux These products specific management What leads the industrialist to start projects? BENEFITS Ageing of the range Benchmarking, comparing the market and industrial
More informationMEI Decision Mathematics 1
Chapter assessment MEI Decision Mathematics Critical Path Analysis. The diagram below shows a precedence network for a particular project. 9 A() D(4) I(8) Durations are in days B() E() H(5) J(4) L() 5
More informationTime Planning and Control
Time Planning and ontrol Precedence iagram G44 NGINRING MNGMNT 1 Precedence iagramming S ctivity I LS T L n important extension to the original activity-on-node concept appeared around 14. The sole relationship
More informationSample Chapter. Basic Hard Systems. Engineering: Part I
Basic Hard Systems 10 Engineering: Part I 10.1 Introduction: Hard Systems Analysis In Chapter 1 we dealt briefly with the rudiments of the systems approach to problem solving. In this chapter, we begin
More informationNetwork Techniques - I. t 5 4
Performance:Slide.doc Network Techniques - I. t s v u PRT time/cost : ( Program valuation & Review Technique ) vent-on-node typed project-model with probabilistic (stochastic) data set as weights (inp)
More informationQi Jian-xun,Sun Dedong
Physics Procedia 24 (2012) 1530 1540 2012 International Conference on Applied Physics and Industrial Engineering One Improvement Method of Reducing Duration Directly to Solve Time-Cost Tradeoff Problem
More informationLine Of Balance. Dr. Ahmed Elyamany
Line Of Balance Dr Ahmed Elyamany Intended Learning Outcomes Define the principles of Line of Balance (LOB) Demonstrate the application of LOB Understand the importance of LOB Understand the process of
More informationTime Planning and Control. Time-Scaled Network
Time Planning and Control Time-Scaled Network Processes of Time Planning and Control 1.Visualize and define the activities..sequence the activities (Job Logic). 3.stimate the activity duration. 4.Schedule
More informationBenefits of PERT/CPM. 2018, Jayant Rajgopal
Project: ny set of complex, interrelated activities aimed at some specific goal. Typically, characterized by a clear starting point and a clear end point. Examples: onstruction (buildings, roads, bridges,
More informationTime allowed: 1.5 hours
Student name College of ngineering Civil ngineering Department G 404: NGINRING MNGMNT Second Semester 1438/1439H (MODL NSWR) FIRST MIDTRM XM Monday 24/6/1439H (12/3/2018G) from 7:00 to 8:30 PM Time allowed:
More informationEmbedded Systems 15. REVIEW: Aperiodic scheduling. C i J i 0 a i s i f i d i
Embedded Systems 15-1 - REVIEW: Aperiodic scheduling C i J i 0 a i s i f i d i Given: A set of non-periodic tasks {J 1,, J n } with arrival times a i, deadlines d i, computation times C i precedence constraints
More informationNetwork analysis. A project is a temporary endeavor undertaken to create a "unique" product or service
Network analysis Introduction Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects. One definition of a project
More informationMSA 640 Homework #2 Due September 17, points total / 20 points per question Show all work leading to your answers
Name MSA 640 Homework #2 Due September 17, 2010 100 points total / 20 points per question Show all work leading to your answers 1. The annual demand for a particular type of valve is 3,500 units. The cost
More informationSolving Fuzzy PERT Using Gradual Real Numbers
Solving Fuzzy PERT Using Gradual Real Numbers Jérôme FORTIN a, Didier DUBOIS a, a IRIT/UPS 8 route de Narbonne, 3062, Toulouse, cedex 4, France, e-mail: {fortin, dubois}@irit.fr Abstract. From a set of
More informationA Critical Path Problem Using Triangular Neutrosophic Number
A Critical Path Problem Using Triangular Neutrosophic Number Excerpt from NEUTROSOPHIC OPERATIONAL RESEARCH, Volume I. Editors: Prof. Florentin Smarandache, Dr. Mohamed Abdel-Basset, Dr. Yongquan Zhou.
More information(1) The starting point is the precedence table (aka dependence table) Immediately preceding activities
Critical Path Analysis (10 pages; 1/5/16) fmng.uk (1) The starting point is the precedence table (aka dependence table) Example Activity Duration Immediately preceding activities A 4 - B 5 - C 6 A,B D
More informationA Critical Path Problem in Neutrosophic Environment
A Critical Path Problem in Neutrosophic Environment Excerpt from NEUTROSOPHIC OPERATIONAL RESEARCH, Volume I. Editors: Prof. Florentin Smarandache, Dr. Mohamed Abdel-Basset, Dr. Yongquan Zhou. Foreword
More information2. Project management
2. Project management In what follows, we consider production processes where only a single item of a specific product is produced in the planning horizon In this case specific instruments for planning
More informationST. JOSEPH S COLLEGE OF ARTS & SCIENCE (AUTONOMOUS) CUDDALORE-1
ST. JOSEPH S COLLEGE OF ARTS & SCIENCE (AUTONOMOUS) CUDDALORE-1 SUB:OPERATION RESEARCH CLASS: III B.SC SUB CODE:EMT617S SUB INCHARGE:S.JOHNSON SAVARIMUTHU 2 MARKS QUESTIONS 1. Write the general model of
More informationChapter 16: Program Evaluation and Review Techniques (PERT)
Chapter 16: Program Evaluation and Review Techniques (PERT) PERT PERT is a method for determining the length of a construction project and the probability of project completion by a specified date PERT
More informationProject management model for constructing a renewable energy plant
Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 74 (207 ) 45 54 206 Global Congress on Manufacturing and Management Project management model for constructing a renewable energy
More informationProject Planning & Control Prof. Koshy Varghese Department of Civil Engineering Indian Institute of Technology, Madras
Project Planning & Control Prof. Koshy Varghese Department of Civil Engineering Indian Institute of Technology, Madras (Refer Slide Time: 00:16) Lecture - 52 PERT Background and Assumptions, Step wise
More informationA Critical Path Problem Using Triangular Neutrosophic Number
A ritical Path Problem Using Triangular Neutrosophic Number Mai Mohamed 1 Department of Operations Research Faculty of omputers and Informatics Zagazig University, Sharqiyah, Egypt Yongquan Zhou 2 ollege
More informationSOLVING STOCHASTIC PERT NETWORKS EXACTLY USING HYBRID BAYESIAN NETWORKS
SOLVING STOCHASTIC PERT NETWORKS EXACTLY USING HYBRID BAYESIAN NETWORKS Esma Nur Cinicioglu and Prakash P. Shenoy School of Business University of Kansas, Lawrence, KS 66045 USA esmanur@ku.edu, pshenoy@ku.edu
More informationContents college 5 and 6 Branch and Bound; Beam Search (Chapter , book)! general introduction
Contents college 5 and 6 Branch and Bound; Beam Search (Chapter 3.4-3.5, book)! general introduction Job Shop Scheduling (Chapter 5.1-5.3, book) ffl branch and bound (5.2) ffl shifting bottleneck heuristic
More information20217 CLEAR STONE TON $14.20 $5, $ $ $ %
ACCOUNT NO: 10332-84-174-84300: 54250(91223) ACCOUNT NO: 10529-403-172: 54440 (91226) ACCOUNT NO: 10463-51-130: 54250 (91223) ACCOUNT NO: 10332-84-174-84300: 54250 (91223) 20217 CLEAR STONE 375.00 TON
More informationChapter 7 (Cont d) PERT
Chapter 7 (Cont d) PERT Project Management for Business, Engineering, and Technology Prepared by John Nicholas, Ph.D. Loyola University Chicago & Herman Steyn, PhD University of Pretoria Variability of
More informationDuration of online examination will be of 1 Hour 20 minutes (80 minutes).
Program Name: SC Subject: Production and Operations Management Assessment Name: POM - Exam Weightage: 70 Total Marks: 70 Duration: 80 mins Online Examination: Online examination is a Computer based examination.
More informationM.SC. MATHEMATICS - II YEAR
MANONMANIAM SUNDARANAR UNIVERSITY DIRECTORATE OF DISTANCE & CONTINUING EDUCATION TIRUNELVELI 627012, TAMIL NADU M.SC. MATHEMATICS - II YEAR DKM24 - OPERATIONS RESEARCH (From the academic year 2016-17)
More informationNetwork Techniques - II.
erformance:lide1.doc Network Techniques - II. CM time - CM time+ : Overlapping, open network and non-broken activity keep being problematic ( chedules for roduction Management?! ) MM time : ( METRA otentials'
More informationUsing Neutrosophic Sets to Obtain PERT Three-Times Estimates in Project Management
Using Neutrosophic Sets to Obtain PERT Three-Times Estimates in Project Management Mai Mohamed 1* Department of Operations Research Faculty of Computers and Informatics Zagazig University Sharqiyah Egypt
More informationEmbedded Systems - FS 2018
Institut für Technische Informatik und Kommunikationsnetze Prof. L. Thiele Embedded Systems - FS 2018 Sample solution to Exercise 3 Discussion Date: 11.4.2018 Aperiodic Scheduling Task 1: Earliest Deadline
More informationA SIMULATION-BASED FRAMEWORK FOR QUANTIFYING THE COLD REGIONS WEATHER IMPACTS ON CONSTRUCTION SCHEDULES
Proceedings of the 2007 Winter Simulation Conference S. G. Henderson, B. Biller, M.-H. Hsieh, J. Shortle, J. D. Tew, and R. R. Barton, eds. A SIMULATIO-BASED FRAMEWORK FOR QUATIFIG THE COLD REGIOS WEATHER
More information20217 CLEAR STONE TON $14.20 $5, $ $ $ %
ACCOUNT NO: 10332-84-174-84300: 54250(91223) ACCOUNT NO: 10529-403-172: 54440 (91226) ACCOUNT NO: 10463-51-130: 54250 (91223) ACCOUNT NO: 10332-84-174-84300: 54250 (91223) 20217 CLEAR STONE 375.00 TON
More information= (, ) V λ (1) λ λ ( + + ) P = [ ( ), (1)] ( ) ( ) = ( ) ( ) ( 0 ) ( 0 ) = ( 0 ) ( 0 ) 0 ( 0 ) ( ( 0 )) ( ( 0 )) = ( ( 0 )) ( ( 0 )) ( + ( 0 )) ( + ( 0 )) = ( + ( 0 )) ( ( 0 )) P V V V V V P V P V V V
More informationINSTITUT FÜR WIRTSCHAFTSTHEORIE UND OPERATIONS RESEARCH UNIVERSITÄT KARLSRUHE
INSTITUT FÜR WIRTSCHAFTSTHEORIE UND OPERATIONS RESEARCH UNIVERSITÄT KARLSRUHE Proects with Minimal and Maximal Time Lags: Construction of Activity-on-Node Networks and Applications Klaus Neumann Christoph
More informationHistory and Some Latest Developments of Precedence Diagramming Method
History and Some Latest Developments of Precedence Diagramming Method Miklós Hajdu Szent István University, Gödöllő, Hungary; Department of Architecture; Facuty of Architecture and Civil Engineering; miklos.hajdu63@gmail.com
More informationEmbedded Systems 14. Overview of embedded systems design
Embedded Systems 14-1 - Overview of embedded systems design - 2-1 Point of departure: Scheduling general IT systems In general IT systems, not much is known about the computational processes a priori The
More informationUsing Method of Moments in Schedule Risk Analysis
Raymond P. Covert MCR, LLC rcovert@mcri.com BACKGROUND A program schedule is a critical tool of program management. Program schedules based on discrete estimates of time lack the necessary information
More informationToward the Resolution of Resource Conflict in a MPL-CCPM Representation Approach
Toward the Resolution of Resource Conflict in a MPL-CCPM Representation Approach MUNENORI KASAHARA Nagaoka University of Technology Nagaoka, Niigata 940-2188 JAPAN s063349@ics.nagaokaut.ac.jp HIROTAKA
More informationCook County Health and Hospital Systems. Schedule Submission Guidelines
Cook County Health and Hospital Systems Schedule Submission Guidelines 1 This document is intended to provide guidelines for submitting construction schedules for the contractors performing work in Cook
More informationAlgorithm Design. Scheduling Algorithms. Part 2. Parallel machines. Open-shop Scheduling. Job-shop Scheduling.
Algorithm Design Scheduling Algorithms Part 2 Parallel machines. Open-shop Scheduling. Job-shop Scheduling. 1 Parallel Machines n jobs need to be scheduled on m machines, M 1,M 2,,M m. Each machine can
More informationNeutrosophic Sets, Project, Project Management, Gantt chart, CPM, PERT, Three-Time Estimate.
Using Neutrosophic Sets to Obtain PERT Three-Times Estimates in Project Management Excerpt from NEUTROSOPHIC OPERATIONAL RESEARCH, Volume I. Editors: Prof. Florentin Smarandache, Dr. Mohamed Abdel-Basset,
More informationProject scheduling with calendars
OR Spektrum (2001) 23: 325 334 c Springer-Verlag 2001 Project scheduling with calendars Birger Franck, Klaus Neumann, and Christoph Schwindt Institut für Wirtschaftstheorie und Operations Research, University
More information10701 TRAFFIC CONTROL 1.00 LUMP SUM $4, $4, $ $4, $4, %
ACCOUNT NO. 10154-403-172 ACCOUNT NO. 10154-403-174 ACCOUNT NO. 11712-84-174-84600 ACCOUNT NO. 10154-403-172 10701 TRAFFIC CONTROL 1.00 LUMP SUM $4,000.00 $4,000.00 0.00 $0.00 1.00 $4,000.00 1.00 $4,000.00
More informationSummary of Bids Received For
Summary of Bids Received For Mt. Carmel Road, Vicbarb Lane & Apple Blossom Lane Local Sewer MSD ID: 10370045 Firm Name Bid Total $ $1,074,100.00 Howell Contractors Inc. $1,083,694.00 Sunesis Construction
More informationTHE NONSIMULTANEITY CONSTRAINT IN NETWORK-BASED PROJECT MANAGEMENT SYSTEMS A THESIS. The Faculty of the Graduate Division. J.
In presenting the dissertation as a partial fulfillment of the requirements for an advanced degree from the Georgia Institute of Technology, I agree that the Library of the Institute shall make it available
More informationm~bmslnr.rmruu1nlw~~~unaiuaa"u~'u4au ~n'onsruioudl#~u~ubba::b$z t.4 CI
t.4 CI m~bmslnr.rmruu1nlw~~~unaiuaa"u~'u4au ~n'onsruioudl#~u~ubba::b$z d3uln"~iiuadu2u"~.riiuauuin ~1n1rdii~u'um~d~ul~d~uw~dnwmnv~a~i$i8o:d~e1anr::w d-ru8uq i5uqnlirn::1wnwa~duuin~~iuwiuui ah kiuquntnii.rud~::uitu
More informationOperation management
Operation management Vigneron Loic December 3, 2008 1 Operations and productivity 1.1 Productivity Productivity = Units produced Imput used Units produced Labor productivity = Labor hours used One resource
More informationExam Spring Embedded Systems. Prof. L. Thiele
Exam Spring 20 Embedded Systems Prof. L. Thiele NOTE: The given solution is only a proposal. For correctness, completeness, or understandability no responsibility is taken. Sommer 20 Eingebettete Systeme
More informationCS 6901 (Applied Algorithms) Lecture 3
CS 6901 (Applied Algorithms) Lecture 3 Antonina Kolokolova September 16, 2014 1 Representative problems: brief overview In this lecture we will look at several problems which, although look somewhat similar
More informationAppendix C Benchmarking Cost Estimates
REPORT Appendix C Benchmarking Cost Estimates C-1 Table C-1 Permits, Notifications & Location Services Notes: Costs associated with delays in construction have not been included in this estimate OneCall
More informationCritical Paths Identification on Fuzzy Network Project
IOSR Journal of Mathematics (IOSR-JM) e-issn: 2278-5728, p-issn: 2319-765X. Volume 11, Issue 1 Ver. VI (Jan - Feb. 2015), PP 49-54 www.iosrjournals.org Critical Paths Identification on Fuzzy Network Project
More informationA comparison of sequencing formulations in a constraint generation procedure for avionics scheduling
A comparison of sequencing formulations in a constraint generation procedure for avionics scheduling Department of Mathematics, Linköping University Jessika Boberg LiTH-MAT-EX 2017/18 SE Credits: Level:
More information57:022 Principles of Design II Homework #1 Solutions. Spring 1997
57:022 Principles of Design II Homework #1 Solutions Spring 1997 Be sure to state what probability distribution you assume in each problem! You may find the necessary probabilities in tables, compute them
More informationMathematics (JUN13MD0201) General Certificate of Education Advanced Level Examination June Unit Decision TOTAL.
Centre Number Candidate Number For Examiner s Use Surname Other Names Candidate Signature Examiner s Initials Mathematics Unit Decision 2 Thursday 13 June 2013 General Certificate of Education Advanced
More informationA Dynamic Programming algorithm for minimizing total cost of duplication in scheduling an outtree with communication delays and duplication
A Dynamic Programming algorithm for minimizing total cost of duplication in scheduling an outtree with communication delays and duplication Claire Hanen Laboratory LIP6 4, place Jussieu F-75 252 Paris
More informationORIGINATOR: CITY OF MADISON STREETS DIVISION REV. DATE: _ PLOT NAME: _ PLOT SCALE: _ SHORELINE TREATMENT SCHEDULE PROJECT NO. 10332/10529 U-10 SHORELINE TREATMENT SCHEDULE MAINLAND CITY OF MADISON MAINLAND
More information1 Basic Definitions. 2 Proof By Contradiction. 3 Exchange Argument
1 Basic Definitions A Problem is a relation from input to acceptable output. For example, INPUT: A list of integers x 1,..., x n OUTPUT: One of the three smallest numbers in the list An algorithm A solves
More informationTask Models and Scheduling
Task Models and Scheduling Jan Reineke Saarland University June 27 th, 2013 With thanks to Jian-Jia Chen at KIT! Jan Reineke Task Models and Scheduling June 27 th, 2013 1 / 36 Task Models and Scheduling
More informationMorning Time: 1 hour 30 minutes
ADVANCED SUBSIDIARY GCE 477/0 MATHEMATICS (MEI) Decision Mathematics THURSDAY 2 JUNE 2008 Morning Time: hour 30 minutes *CUP/T44383* Additional materials: Printed Answer Book (enclosed) MEI Examination
More informationALG 5.4. Lexicographical Search: Applied to Scheduling Theory. Professor John Reif
Algorithms Professor John Reif ALG 54 input assume problem Scheduling Problems Set of n tasks in precidence relation on tasks Also, given m processors Unit time cost to process task using single processor
More informationReview Exercise 2. 1 a Chemical A 5x+ Chemical B 2x+ 2y12 [ x+ Chemical C [ 4 12]
Review Exercise a Chemical A 5x+ y 0 Chemical B x+ y [ x+ y 6] b Chemical C 6 [ ] x+ y x+ y x, y 0 c T = x+ y d ( x, y) = (, ) T = Pearson Education Ltd 08. Copying permitted for purchasing institution
More informationDeterministic Models: Preliminaries
Chapter 2 Deterministic Models: Preliminaries 2.1 Framework and Notation......................... 13 2.2 Examples... 20 2.3 Classes of Schedules... 21 2.4 Complexity Hierarchy... 25 Over the last fifty
More informationA mathematical model for assembly line balancing model to consider disordering sequence of workstations
A mathematical model for assembly line balancing model to consider disordering sequence of workstations William Ho,* and Ali Emrouznejad Operations and Information Management Group Aston Business School,
More informationSingle Machine Problems Polynomial Cases
DM204, 2011 SCHEDULING, TIMETABLING AND ROUTING Lecture 2 Single Machine Problems Polynomial Cases Marco Chiarandini Department of Mathematics & Computer Science University of Southern Denmark Outline
More informationSingle Machine Models
Outline DM87 SCHEDULING, TIMETABLING AND ROUTING Lecture 8 Single Machine Models 1. Dispatching Rules 2. Single Machine Models Marco Chiarandini DM87 Scheduling, Timetabling and Routing 2 Outline Dispatching
More informationAs Soon As Probable. O. Maler, J.-F. Kempf, M. Bozga. March 15, VERIMAG Grenoble, France
As Soon As Probable O. Maler, J.-F. Kempf, M. Bozga VERIMAG Grenoble, France March 15, 2013 O. Maler, J.-F. Kempf, M. Bozga (VERIMAG Grenoble, France) As Soon As Probable March 15, 2013 1 / 42 Executive
More informationRCPSP Single Machine Problems
DM204 Spring 2011 Scheduling, Timetabling and Routing Lecture 3 Single Machine Problems Marco Chiarandini Department of Mathematics & Computer Science University of Southern Denmark Outline 1. Resource
More informationDecomposition Method for Project Scheduling with Spatial Resources
Decomposition Method for Project Scheduling with Spatial Resources J.L. Hurink, A.L. Kok and J.J. Paulus University of Twente, PO box 217, 7500AE Enschede, The Netherlands, j.j.paulus@ewi.utwente.nl Project
More informationCore Mathematics C1 (AS) Unit C1
Core Mathematics C1 (AS) Unit C1 Algebraic manipulation of polynomials, including expanding brackets and collecting like terms, factorisation. Graphs of functions; sketching curves defined by simple equations.
More informationFuzzy Numerical Results Derived From Crashing CPM/PERT Networks of Padma Bridge in Bangladesh
Fuzzy Numerical Results Derived From Crashing CPM/PERT Networks of Padma Bridge in Bangladesh Md. Mijanoor Rahman 1, Mrinal Chandra Barman 2, Sanjay Kumar Saha 3 1 Assistant Professor, Department of Mathematics,
More information56:171 Operations Research Midterm Exam--15 October 2002
Name 56:171 Operations Research Midterm Exam--15 October 2002 Possible Score 1. True/False 25 _ 2. LP sensitivity analysis 25 _ 3. Transportation problem 15 _ 4. LP tableaux 15 _ Total 80 _ Part I: True(+)
More informationMINIMIZING TOTAL TARDINESS FOR SINGLE MACHINE SEQUENCING
Journal of the Operations Research Society of Japan Vol. 39, No. 3, September 1996 1996 The Operations Research Society of Japan MINIMIZING TOTAL TARDINESS FOR SINGLE MACHINE SEQUENCING Tsung-Chyan Lai
More informationResearch Article Analysis of an Anomaly: The Increase in Time Float following Consumption
e Scientific World Journal Volume 214, Article ID 4158, pages http://dx.doi.org/1.1155/214/4158 Research Article Analysis of an Anomaly: The Increase in Time Float following Consumption Jianxun Qi 1 and
More informationTwo Processor Scheduling with Real Release Times and Deadlines
Two Processor Scheduling with Real Release Times and Deadlines Hui Wu School of Computing National University of Singapore 3 Science Drive 2, Singapore 117543 wuh@comp.nus.edu.sg Joxan Jaffar School of
More informationTENDER NO TABULATION OF TENDERS INFRASTRUCTURE AND TRANSPORTATION SUMMARY OF PRICES CONTRACTOR SECTION 1 BID TOTAL
SUMMARY OF PRICES CONTRACTOR SECTION 1 BID TOTAL M.D. Steele Construction Ltd. 886,000.00 886,000.00 Gateway Construction & Engineering Ltd. 973,368.80 973,368.80 Graham Construction and Engineering Inc.
More informationSimulation & Modeling Event-Oriented Simulations
Simulation & Modeling Event-Oriented Simulations Outline Simulation modeling characteristics Concept of Time A DES Simulation (Computation) DES System = model + simulation execution Data Structures Program
More informationShedding the Shackles of Time-Division Multiplexing
Shedding the Shackles of Time-Division Multiplexing Farouk Hebbache with Florian Brandner, 2 Mathieu Jan, Laurent Pautet 2 CEA List, LS 2 LTCI, Télécom ParisTech, Université Paris-Saclay Multi-core Architectures
More informationVehicle Routing and Scheduling. Martin Savelsbergh The Logistics Institute Georgia Institute of Technology
Vehicle Routing and Scheduling Martin Savelsbergh The Logistics Institute Georgia Institute of Technology Vehicle Routing and Scheduling Part II: Algorithmic Enhancements Handling Practical Complexities
More informationReinforcement Learning. Value Function Updates
Reinforcement Learning Value Function Updates Manfred Huber 2014 1 Value Function Updates Different methods for updating the value function Dynamic programming Simple Monte Carlo Temporal differencing
More informationThere are three priority driven approaches that we will look at
Priority Driven Approaches There are three priority driven approaches that we will look at Earliest-Deadline-First (EDF) Least-Slack-Time-first (LST) Latest-Release-Time-first (LRT) 1 EDF Earliest deadline
More informationOperational modal analysis using forced excitation and input-output autoregressive coefficients
Operational modal analysis using forced excitation and input-output autoregressive coefficients *Kyeong-Taek Park 1) and Marco Torbol 2) 1), 2) School of Urban and Environment Engineering, UNIST, Ulsan,
More informationCS 6783 (Applied Algorithms) Lecture 3
CS 6783 (Applied Algorithms) Lecture 3 Antonina Kolokolova January 14, 2013 1 Representative problems: brief overview of the course In this lecture we will look at several problems which, although look
More informationScientific Journal Impact Factor: (ISRA), Impact Factor: 2.114
IJESRT INTERNATIONAL JOURNAL OF ENGINEERING SCIENCES & RESEARCH TECHNOLOGY Certain Application of GERT Network Analysis in Statistical Quality Control Resmi R Asst. Professor, Department of Mathematics,
More informationCMSC 451: Lecture 7 Greedy Algorithms for Scheduling Tuesday, Sep 19, 2017
CMSC CMSC : Lecture Greedy Algorithms for Scheduling Tuesday, Sep 9, 0 Reading: Sects.. and. of KT. (Not covered in DPV.) Interval Scheduling: We continue our discussion of greedy algorithms with a number
More information6.231 DYNAMIC PROGRAMMING LECTURE 9 LECTURE OUTLINE
6.231 DYNAMIC PROGRAMMING LECTURE 9 LECTURE OUTLINE Rollout algorithms Policy improvement property Discrete deterministic problems Approximations of rollout algorithms Model Predictive Control (MPC) Discretization
More informationTension zone applications, i.e., cable trays and strut, pipe supports, fire sprinklers Seismic and wind loading
General Information Mechanical Anchors General Information Power-Stud + SD1 Wedge Expansion Anchor Product Description The Power-Stud+ SD1 anchor is a fully threaded, torque-controlled, wedge expansion
More informationAnt Colony Optimization for Resource-Constrained Project Scheduling
Ant Colony Optimization for Resource-Constrained Project Scheduling Daniel Merkle, Martin Middendorf 2, Hartmut Schmeck 3 Institute for Applied Computer Science and Formal Description Methods University
More informationABSTRACT TIMING VERIFICATION AND OPTIMIZATION OF CIRCUITS WITH LEVEL-SENSITIVE LATCHES. by Timothy Michael Burks
ABSTRACT TIMING VERIFICATION AND OPTIMIZATION OF CIRCUITS WITH LEVEL-SENSITIVE LATCHES by Timothy Michael Burks Chair: Karem Sakallah This work describes the development of a model for the static timing
More informationMONTE CARLO SIMULATION RISK ANALYSIS AND ITS APPLICATION IN MODELLING THE INCLEMENT WEATHER FOR PROGRAMMING CIVIL ENGINEERING PROJECTS
MONTE CARLO SIMULATION RISK ANALYSIS AND ITS APPLICATION IN MODELLING THE INCLEMENT WEATHER FOR PROGRAMMING CIVIL ENGINEERING PROJECTS Pedram Daneshmand Associate Director Blue Visions Management (bluevisions)
More informationScheduling with AND/OR Precedence Constraints
Scheduling with AND/OR Precedence Constraints Seminar Mathematische Optimierung - SS 2007 23th April 2007 Synthesis synthesis: transfer from the behavioral domain (e. g. system specifications, algorithms)
More informationMATHEMATICAL ANALYSIS OF LINEAR SCHEDULES Gunnar Lucko 1
MATHEMATICAL ANALYSIS OF LINEAR SCHEDULES Gunnar Lucko ABSTRACT The interplay of various managerial dimensions of construction projects requires careful control. Some criticisms have been raised regarding
More information