THE ITAPEBI HYDROELECTRIC DEVELOPMENT IN THE JEQUITINHONHA RIVER

Size: px
Start display at page:

Download "THE ITAPEBI HYDROELECTRIC DEVELOPMENT IN THE JEQUITINHONHA RIVER"

Transcription

1 THE ITAPEBI HYDROELECTRIC DEVELOPMENT IN THE JEQUITINHONHA RIVER Author: Silvano Custódio Albertoni

2 THE ITAPEBI HYDROELECTRIC DEVELOPMENT IN THE JEQUITINHONHA RIVER 1. INTRODUCTION The Itapebi HPP is located in the basin of the Jequitinhonha River, in the municipality of Itapebi, southern region of the state of Bahia (see Figure 1). The power plant has three Francis generator units of 150 MW each, totalling 450 MW of installed power. The small area flooded by its reservoir, of around 62 km 2, and the predominance of pastures, minimized the environmental impacts. Figure 1 - Location of the Itapebi Hydroelectric Power Plant The concession for the energy exploitation belongs to Itapebi Geração de Energia S.A., a firm of the Iberdrola Group. The works were initiated in October of 1999, and the beginning of commercial generation of the first unit took place in January of The civil works were executed by the contractors Norberto Odebrecht and Andrade Gutierrez. The electromechanical equipment was supplied by Alstom Power, and erected by the Construtora Norberto Odebrecht. The executive project was developed by Engevix and by Intertechne. 2. DESCRIPTION OF THE ENTERPRISE The river diversion was effected through three tunnels of arch-trapezoidal section, with maximum height of 16 m and an average length of 680 m located in the left bank of the river, under the site for the implantation of the future spillway. The diversion occurred at the end of October of 2000, six months in advance of the original schedule, thanks to the prior planning of the job and the strategy employed. The dewatering of the foundation area of the dam was carried out by means of soil and rockfill cofferdams, with a maximum height of 42 m, implanted upon a thick alluvial deposit. For waterproofing the alluvium, "jet-grouting" curtains and clayey blankets were executed. The infiltrations were controlled by a system of deep shafts for lowering the water table at the downstream toe of the cofferdams. The generation circuit, located in the right bank, is constituted by a water intake of the hollow gravity type, three pressure tunnels with a diameter of 7.40 m, an average length of 160 m, supplying the semi-indoor powerhouse, equipped with three vertical shaft Francis turbines. The spillway is of the surface type with a ski-jump, constituted by 6 spillway bays with radial-type gates, 17.4 m in width and 20.0 m in height, which discharge the ten thousand year flood of 20,915 m³/s. The dam is of the concrete face rockfill type (CFR), with crest at El , a length of 583 m and a maximum height of 121 m. Figure 2 presents the general layout of the enterprise and Figure 3 the cross and longitudinal sections of the CFR dam in the riverbed. 3. GEOLOGY, GEOTECHNOLOGY AND FOUNDATIONS The rock mass at the site of the Itapebi Hydroelectric Power Plant is inserted into the geological context of the ancient crystalline shield, of the Pre-Cambrian Era south of Bahia, constituted by metamorphic rocks of the Super Group Espinhaço. At the site of the development there are outcroppings of granitic gneisses intercalated with sub-horizontal lenses and layers of biotite-schist/ amphibolite (BX/AF). The regional direction of the deformation (foliation) structures is NW with a gentle dip towards the E quadrant. The structural framework is constituted by sub-vertical joints in the following directions: NS/85ºE, N85ºW/80ºSW, N50ºW/75ºSW and N42ºE/40ºSE. Relief joints are also observed and sheared joints in the NS and EW directions, and sub-vertical faults in the NS direction. The relief joints observed in the gneissic mass were 222

3 Figure 2 - General Layout of the Hydroelectric Power Plant Figure 3 - Cross and Longitudinal Sections of the Concrete Face Rockfill Dam in the Riverbed 223

4 produced due to the intense erosive process in the valley, which created vertical cuts more than 100 m in depth, opening, in this manner, the existing joints oriented in the NS and EW directions. These openings permitted the infiltration of water to depths of more than 50 m, a fact that produced an alteration in the layers of BX/AF, principally at the contacts with the granite gneiss. The commencement of the works produced the exposure and permitted access to the diverse layers of BX/AF, as exemplified in the Photos 1 and 2, which depict the layers present in the right abutment of the dam. The diverse sub-horizontal lenses and layers of BX/ AF were mapped and designated for differentiation concerning each bank or structure. This is due to the lack of correlation between the left and the right banks resulting from the erosive discontinuity of the river valley, aggravated by the existence of bifurcations and ramifications of the layers. In the right bank, between the dam and the powerhouse, the layers are truncated by a fault in the NS direction, impeding their correlation in the upstream/downstream direction. In July of 2001, during the excavation for the spillway, a large rock slide occurred in the left abutment. This rock slide took place along one of the layers of biotite-schist present, with a mean inclination of about 13º and along a length of approximately 210 m, involving a rock volume of about 170,000 m³. Photo 3 shows the site of the slide. Photo 1 - General View of the Right Abutment with the Presence of Various Planes of BX/AF Photo 3 - General View of the Left Abutment straight after the Slide of the Rock Mass over the Layer of Biotite-Schist. Photo 2 - Detail of a Layer of BX/AF of Metric Thickness In the left hillside the erosive relief of the valley promoted the release of large blocks of rock according to the reticulation of the fractures, released at the base by the planes of the weathered BX/AF. The layers and lenses of BX/AF present undulations in the scales of decametres, metres and centimetres, and attain lengths greater than 500 m. Their thickness varies between 0.20 and 3.00 m, and the granite gneiss package between the layers varies from 5.00 m to m. The planes formed by the layers and lenses of BX/AF dips between 10º and 20º to the NE (downstream), being liable to present localized inflections of the dip of around 30º. The uncommon and unforeseeable nature of a rock slide of this magnitude led to a minute evaluation of its causes, requiring a re-evaluation of the shear-resistance parameters of the weathered layers of BX/AF, whose adopted values had been obtained by triaxial and direct shear tests on blocks of undisturbed samples withdrawn from the excavations at the beginning of the job. A reevaluation was also made of the geomechanical model in order to dimension the type and quantity of the reinforcements to be utilized in the foundations of the structures of the development after the slide, without affecting the contractual commitments for the start of generation. Different intervention approaches were initially considered for treating the layers of BX/AF present in the foundations of the main structures of the project. Meanwhile, the underground interventions were granted priority since they permitted the simultaneous execution of the reinforcements to the foundation and of the superstructures themselves, with a minimum of interference between these jobs, thus allowing maintaining the time schedule of the contracted services. 224

5 To this effect, the solutions that resulted most appropriate both from the construction aspect as also regarding the questions of job safety were: Reinforcements of the foundations through the construction of concrete shear keys implanted along the tunnels and trenches excavated in the rock, in order to intercept the layers of BX/AF Excavation of complementary drainage tunnels in the abutments to assist in relieving the uplift pressures imposed by the reservoir; Placement of tendons through the shallow BX/AF layers permitting safe excavation and concrete placement of shear-keys and structures. Subsequently, these tendons were incorporated into the final containment elements and considered in the global safety analysis of the structures. Figures 4 and 5 show the typical shear-key section and the foundation reinforcement of the dam in the area of the abutments. In addition to the adverse conditions in the abutments, the Jequitinhonha riverbed at the Itapebi dam-site is constituted by a large deposit of sand that covers the bedrock over the entire width of the river. The investigations carried out to subsidize the project of the dam and the cofferdams included boreholes effected by percussion, rotary and piezocone drills, as well as geophysical soundings by the geo-radar method. These investigations indicated an alluvial layer with a maximum thickness of around 28 m. During the removal of the alluvium from the riverbed in the region of the foundation plinth, the existence was verified, furthermore, of a deep paleochannel that had not been detected in the investigations. Figure 4 - Foundation Treatment of CFR Dam - Typical Shear-Key Figure 5 - Typical Section of Foundation Treatment - Area of the Abutments 225

6 The Itapebi CFRD was the sixth concrete face rockfill dam to be built in Brazil and presents some peculiar characteristics, such as, the incorporation into the embankment of part of the riverbed alluvial deposit, and the declivity of the upstream slope being equal to 1.25H: 1V. Other relevant aspects related to the foundations were the presence of sub-horizontal layers of biotite-schist/ amphibolite, with thicknesses ranging from centimetres to metres cutting the gneissic rock in the abutments, and the presence of a deep paleochannel in the riverbed. Photo 4 - View of the Alluvial Layer in the Riverbed The principal dam data are listed below: Maximum height in the plinth of the paleochannel region: 121 m Length of the crest: 583 m Volume of rockfill and transitions: 3,841,000 m³ Area of the face: 66,500 m 2 Photo 6 presents a view of the dam from upstream before the filling of the reservoir. 4. HYDROLOGY Photo 5 - Paleochannel in the Riverbed The drainage area of the undertaking is 68,100 km 2, with a flooded area of km 2. The mean long term flow MLT is 406 m 3 /s, the maximum monthly mean flow is 4,140 m 3 /s and the minimum is 48 m 3 /s. The diversion of the river was sized for a flow of 9,300 m 3 /s and the ten thousand year flood passing through the spillway is 20,915 m 3 /s. 5. DAM Three alternative arrangements were contemplated during the feasibility studies, one of which demonstrated the technical and economical advantage of a concrete face rockfill dam - CFRD. The other two alternatives contemplated dams of roller compacted concrete - RCC, which were at a disadvantage due to the balance of the materials available and the risks imposed by the local geology, in addition to the higher costs required for the execution of this type of dam. Photo 6 - View of the Dam and Upstream Cofferdam before the Filling of the Reservoir 6. SPILLWAY The spillway, located in the left abutment, was designed for a ten thousand year flood of 20,150 m 3 /s. Due to the unforeseen geological condition that caused a large rock slide during the excavation, there was the need to modify the design of the geometry of the chute, executing a block of RCC at its end, in the area already excavated for the dissipation basin, in order to stabilize the excavation and launch the jet of water further away, thus also avoiding the risk of regressive erosions of the rock. In order to permit the adaptation of the ski jump to the already excavated local conditions, the solution presented was a flip bucket inclined 45º with respect to the axis of the chute. This unusual solution of a jet not orthogonal to the flow was studied on the reduced scale model, and its operation after various years qualifies it as an adequate solution. The Photos 7 and 8 show the spillway after its conclusion and in operation. 226

7 Photo 7 - Spillway at the End of Construction Photo 8 - Spillway in Operation Figure 6 - Plan View of Location of Monitoring Instruments installed in the CFRD 227

8 7. PERFORMANCE OF THE DEVELOPMENT The plan of the monitoring instrumentation of the dam considered the installation of instruments within the rockfill embankment and in its concrete face as also in the foundations of the abutments and drainage galleries installed in both abutments of the dam. Figure 6 presents the plan view of the dam with the positions of the instrumented key sections and the location of the other instruments in the concrete face and the rockfill embankment. More than a 100 monitoring instruments were installed in the CFRD, all of them with the purpose of measuring the displacements suffered both in the rockfill and in the concrete face. To monitor the behaviour of the abutments, in which were placed shear-keys filled with concrete and intercepting the layers of biotite-schist, the instrument types installed were load cells, multiple extensometers and inclinometers. The drainage galleries received manometer piezometers, triorthogonal jointmeters and flowmeters. During filling of the reservoir, when the water level reached El. 102 m, eight metres below the normal water level, a significant increase in percolation rate in the dam was observed, as well as an increase in the deformation of the rockfill embankment in the right abutment, due to its saturation. This increase in deformation of the embankment led to a major deflection of the slabs, mainly at the crest, beside the parapet wall. Inspections in the foundation drainage galleries of the dam failed to indicate an increase in seepage through the rock mass. The leakage of the dam occurred through the slabs of the upstream facing, as confirmed by the underwater inspection which detected the existence of horizontal cracks in the concrete. After mapping the cracks, a process was begun of launchig fine silty sand from the crest of the dam, to silt up the cracks in the facing. This procedure proved effective, reducing the maximum measured flow from 902 l/s to 127 l/s, at the beginning, and at present the measured percolation flow has stabilized at 50 l/s. The instruments installed in the foundations of the abutments don't indicate increases in piezometric levels nor significant deformations or displacements in the rockfill embankment, all of which indicates that the treatments executed in the foundations have proven adequate. 8. TECHNICAL FEATURES General Location Rio Jequitinhonha - Itapebi - South of Bahia State Year job initiated 1999 Year of conclusion 2003 Owner Itapebi Geração de Energia S.A. Designer Engevix Engenharia S.A. - Intertechne Consultores Ltda. Civil Contractors Construtora Norberto Odebrecht and Andrade Gutierrez Erection Construtora Norberto Odebrecht Electromechanical equipment supplier Alstom Power Basic data Area of the hydrographic basin 68,100 km 2 Average annual precipitation 877 mm Reservoir Area at the maximum normal level km 2 Total storage volume 1, hm 3 Maximum normal water level m Maximum flood water level m Minimum water level m Tailrace channel Maximum normal water level Maximum flood water level Minimum water level m m m Flows Average incoming flow 406 m 3 /s Maximum recorded flow 4,140 m 3 /s Minimum daily flow recorded 48 m 3 /s Maximum diversion flow and period of recurrence 9,300 m 3 /s, PR=25 years Maximum Probable Flood MPF or ten thousand year flood 20,915 m 3 /s Dam Concrete Face Rockfill Dam - CFRD Length 583 m Maximum Height 121 m Crest elevation El m Width at the crest 7 m Spillway Surface with Ski Jump Length of the Structure m Height of the Structure m Discharge capacity 20,915 m 3 /s 228

9 Spillway Gates radial Number 6 Dimensions Width m Height m Manufacturer Alstom Water intake Hollow Gravity Structure Length m Maximum height m Turbine Francis Number of units 3 Rated power MW Reference Head 76.7 m Maximum discharge 213 m 3 /s Generator Rated Power 160 MVA Rated voltage 13.8 kv Power factor 95% Rotation clockwise Intake gates Dimensions Width Height Manufacturer 3 Fixed Wheel Gates and 1 Stoplog 5.50 m 7.20 m Alstom Step-up transformers Number 3 Three-phase Rated power 160 MVA Rated Voltage (Primary) 13.8 kv Rated Voltage (Secondary) 230 kv Diversion Diversion gates Height Width Tunnels 3 Sliding Gates m 4.20 m Diversion tunnel Number 3 and dimensions of section Arch-rectangle 16x14 m Length 579/683/727 Penstock Pressure Tunnels Number 3 Internal diameter 6.70 m Length 175 m of Tunnel and 45 m of Armour Plating Manufacturer Alstom Powerhouse Height Length Installed capacity Indoor 34 m 112 m 450 MW 9. BIBLIOGRAPHY [1] ANTUNES, José Sobrinho; ALBERTONI, Silvano C.: "Escolha da Barragem Tipo EFC para a UHE Itapebi" - II Simpósio sobre Barragens de Enrocamento com Face de Concreto - Florianópolis [2] RESENDE, Fernando Dias: "Novo Método Executivo para Barragens de Enrocamento com Face de Concreto" - XXIII SNGB - Belo Horizonte [3] CONCRETE FACE ROCKFILL DAMS:"J. Barry Cooke Volume" - CFRD Beijing, China [4] FERNANDES, Rafael; BELITARDO, Gustavo: "Projeto e Instalação da Instrumentação da BEFC Itapebi" - XXIV SNGB - Fortaleza [5] RESENDE, Fernando Dias, ALBERTONI, Silvano C, FERNANDES, Rafael: "Aspectos do Projeto da Barragem EFC no AHE Itapebi - XXIV SNGB - Fortaleza [6] RESENDE, Fernando Dias; BELITARTO, Gustavo; ALBERTONI, Silvano C, Moraes Roberto B.; FERNANDES, Rafael: "AHE Itapebi - Tratamentos Especiais das Fundações" - XXV SNGB - Salvador [7] ALBERTONI, Silvano C, FERNANDES, Rafael; ANTUNES, Jaqueline: " Instrumentation and Auscultation of Itapebi CFRD During and After Filling the Reservoir" - Seminário BEFC - Florianopolis

10

DISPLACEMENTS OF THE XINGÓ CONCRETE FACE ROCKFILL DAM - BRAZIL

DISPLACEMENTS OF THE XINGÓ CONCRETE FACE ROCKFILL DAM - BRAZIL DISPLACEMENTS OF THE XINGÓ CONCRETE FACE ROCKFILL DAM - BRAZIL Ricardo José Barbosa de SOUZA 1, Aurélio Alves de VASCONCELOS 2, Alberto Jorge C CAVALCANTI 3 Companhia Hidro Elétrica do São Francisco CHESF

More information

Practical aspects of dam break analysis

Practical aspects of dam break analysis Practical aspects of dam break analysis Louis C Hattingh Hattingh Anderson Associates CC Dam break analysis It is a model You need to understand what you model & have an idea of the answers that you expect

More information

NAM NGUM 2 CFRD - BEHAVIOUR DURING CONSTRUCTION AND FIRST IMPOUNDING

NAM NGUM 2 CFRD - BEHAVIOUR DURING CONSTRUCTION AND FIRST IMPOUNDING 6 TH INTERNATIONAL CONFERENCE ON DAM ENGINEERING C.Pina, E.Portela, J.Gomes (ed.) Lisbon, Portugal, February 15-17, 2011 NAM NGUM 2 CFRD - BEHAVIOUR DURING CONSTRUCTION AND FIRST IMPOUNDING S. Moll *,

More information

Birecik Dam & HEPP Downstream River Arrangement R. Naderer, G. Scharler Verbundplan GmbH, 5021 Salzburg, Austria

Birecik Dam & HEPP Downstream River Arrangement R. Naderer, G. Scharler Verbundplan GmbH, 5021 Salzburg, Austria Birecik Dam & HEPP Downstream River Arrangement R. Naderer, G. Scharler Verbundplan GmbH, 5021 Salzburg, Austria e-mail: scharlerg@verbund.co.at Abstract Birecik Dam & HEPP on the Euphrates river in Turkey

More information

Seismic Studies of Foz Tua and Fridão Dams DDDamsDAdams

Seismic Studies of Foz Tua and Fridão Dams DDDamsDAdams Seismic Studies of Foz Tua and Fridão Dams DDDamsDAdams D. Silva Matos & José Paixão EDP - Gestão da Produção de Energia, S.A., Porto J.V. Lemos & N. Azevedo Laboratório Nacional de Engenharia Civil, Lisboa

More information

MONITORING SEEPAGE FLOW THROUGH CARUACHI LEFT EMBANKMENT DAM DURING INITIAL RESERVOIR FILLING

MONITORING SEEPAGE FLOW THROUGH CARUACHI LEFT EMBANKMENT DAM DURING INITIAL RESERVOIR FILLING MONITORING SEEPAGE FLOW THROUGH CARUACHI LEFT EMBANKMENT DAM DURING INITIAL RESERVOIR FILLING EMILIO MARTINEZ Senior Hydraulic Engineer, Department of Hydraulic, CVG EDELCA Hid. Macagua I, Apartado 28

More information

THE FOZ DO CHAPECÓ HYDROELECTRIC POWER PLANT

THE FOZ DO CHAPECÓ HYDROELECTRIC POWER PLANT THE FOZ DO CHAPECÓ HYDROELECTRIC POWER PLANT Authors: Miguel Zerbini de Faria, Paulo Eduardo de Almeida Godoy, Francisco Cordero Donha Filho, Alceu Reusing THE FOZ DO CHAPECÓ HYDROELECTRIC POWER PLANT

More information

WHAT SEISMIC HAZARD INFORMATION THE DAM ENGINEERS NEED FROM SEISMOLOGISTS AND GEOLOGISTS?

WHAT SEISMIC HAZARD INFORMATION THE DAM ENGINEERS NEED FROM SEISMOLOGISTS AND GEOLOGISTS? WHAT SEISMIC HAZARD INFORMATION THE DAM ENGINEERS NEED FROM SEISMOLOGISTS AND GEOLOGISTS? Martin WIELAND 1 ABSTRACT For large dam projects a site-specific seismic hazard analysis is usually recommended.

More information

CASE STUDY BINGA, PHILIPPINES

CASE STUDY BINGA, PHILIPPINES SEDIMENT MANAGEMENT CASE STUDY BINGA, PHILIPPINES Key project features Name: Binga Country: Philippines Category: modify operating rule (focus or redistribute sediment); adaptive strategies Binga hydropower

More information

The owner and designer is the Comisiòn Federal de Electricidad (Federal Comission of Electricity).

The owner and designer is the Comisiòn Federal de Electricidad (Federal Comission of Electricity). Location The La Yesca Hydroelectric Project named Ing. Elías Ayub in honor of a former General Director of CFE, is part of the Santiago Hydrological System, 105 km northwest of the city of Guadalajara,

More information

CASE STUDY NATHPA JHAKRI, INDIA

CASE STUDY NATHPA JHAKRI, INDIA SEDIMENT MANAGEMENT CASE STUDY NATHPA JHAKRI, INDIA Key project features Name: Nathpa Jhakri Country: India Category: reduce sediment production (watershed management); upstream sediment trapping; bypass

More information

WP2.1 BREACH FORMATION LARGE SCALE EMBANKMENT FAILURE

WP2.1 BREACH FORMATION LARGE SCALE EMBANKMENT FAILURE WP2. BREACH FORMATION LARGE SCALE EMBANKMENT FAILURE Kjetil Arne Vaskinn, Sweco Gröner Norway Aslak Løvoll, Norconsult AS Norway Kaare Höeg, Norwegian Geotechnical Institute (NGI), Norway WP2. BREACH FORMATION

More information

Final design of Belesar III and Los Peares III Hydropower Projects. (Galicia, Spain).

Final design of Belesar III and Los Peares III Hydropower Projects. (Galicia, Spain). Final design of Belesar III and Los Peares III Hydropower Projects. (Galicia, Spain). J. Baztán and A. Martín Gas Natural Fenosa Engineering, S.L.U, Madrid, Spain. J. M. Galera and D. Santos Subterra Ingeniería

More information

CASE STUDY BINGA, PHILIPPINES

CASE STUDY BINGA, PHILIPPINES SEDIMENT MANAGEMENT CASE STUDY BINGA, PHILIPPINES Key project features Name: Binga Country: Philippines Category: modify operating rule (focus or redistribute sediment); adaptive strategies Reservoir volume

More information

Geotechnical Engineering and Dams

Geotechnical Engineering and Dams Geotechnical Engineering and Dams Solving Geotechnical Challenges for Hydropower and Water Resources Projects Geological and geotechnical challenges are often very demanding when planning hydraulic structures.

More information

PROBLEMS AND SOLUTIONS THAT MAY EMERGE IN THE FOUNDATION AND BODY OF A HOMOGENEOUS FILL DAM ON A WEAK CLAYEY-SILTY-SANDY FORMATION ÇIKRIKÇI DAM

PROBLEMS AND SOLUTIONS THAT MAY EMERGE IN THE FOUNDATION AND BODY OF A HOMOGENEOUS FILL DAM ON A WEAK CLAYEY-SILTY-SANDY FORMATION ÇIKRIKÇI DAM PROBLEMS AND SOLUTIONS THAT MAY EMERGE IN THE FOUNDATION AND BODY OF A HOMOGENEOUS FILL DAM ON A WEAK CLAYEY-SILTY-SANDY FORMATION ÇIKRIKÇI DAM Esen Yalım KARADUMAN BAR-SU Eng. & Conc. Inc. Ankara Turkey

More information

DONA FRANCISCA HYDROELECTRIC DEVELOPMENT ON THE JACUÍ RIVER

DONA FRANCISCA HYDROELECTRIC DEVELOPMENT ON THE JACUÍ RIVER DONA FRANCISCA HYDROELECTRIC DEVELOPMENT ON THE JACUÍ RIVER Author: Sérgio de Pauli Basso DONA FRANCISCA HYDROELECTRIC DEVELOPMENT ON THE JACUÍ RIVER 1. INTRODUCTION Owned by the consortium formed by the

More information

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area.

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area. Sediment Trench SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils [1] Performance of

More information

Session 3 - Case histories KARIBA DAM

Session 3 - Case histories KARIBA DAM ICOLD COMMITTEE ON CONCRETE DAMS SPANISH COMMITTEE ON CONCRETE FOR DAMS INTERNATIONAL JOURNAL ON HYDROPOWER & DAMS WORKSHOP October 18 & 19, 2007 Granada, Spain CHEMICAL EXPANSION OF CONCRETE IN DAMS &

More information

MACHADINHO HYDROPOWER PLANT ON THE PELOTAS RIVER

MACHADINHO HYDROPOWER PLANT ON THE PELOTAS RIVER MACHADINHO HYDROPOWER PLANT ON THE PELOTAS RIVER This article was written by a team composed by: Duilio Diniz de Figueiredo of MAESA - Machadinho Energética S.A., Roberto Pizzato of Machadinho Joint Venture

More information

HOOVER DAM: Grout Curtain Failure and Lessons Learned in Site Characterization

HOOVER DAM: Grout Curtain Failure and Lessons Learned in Site Characterization HOOVER DAM: Grout Curtain Failure and Lessons Learned in Site Characterization J. David Rogers Dams Symposium Association of Engineering Geologists Annual Meeting Las Vegas, Nevada September 22, 2005 The

More information

RETIRO BAIXO HYDROPOWER PLANT ON THE PARAOPEBA RIVER

RETIRO BAIXO HYDROPOWER PLANT ON THE PARAOPEBA RIVER RETIRO BAIXO HYDROPOWER PLANT ON THE PARAOPEBA RIVER Authors: Vicente de Paulo Soares Sobrinho and Newton Goulart Graça RETIRO BAIXO HYDROPOWER PLANT ON THE PARAOPEBA RIVER 1. INTRODUCTION 1.1. Background

More information

AN OVERVIEW OF KONAR DAM ON NEED OF REHABILITATION

AN OVERVIEW OF KONAR DAM ON NEED OF REHABILITATION AN OVERVIEW OF KONAR DAM ON NEED OF REHABILITATION Dipankar Chaudhuri, SE (Civil) A. K. Dubey, SE (Civil) and S. B. Pandey, DCE (Civil) DAMODAR VALLEY CORPORATION OVER VIEW Problems Cracks Potential Conclusion

More information

CONSTRUCTION DEWATERING AT SALUDA DAM

CONSTRUCTION DEWATERING AT SALUDA DAM CONSTRUCTION DEWATERING AT SALUDA DAM Paul C. Rizzo, P.E., Ph.D., Jeffrey M. Bair. P.E., John P. Osterle, P.E., Howard W. Gault, P.G. Saluda Dam, owned and operated by South Carolina Electric & Gas Company

More information

CCR Rule Annual Inspection Report (cont.) 2

CCR Rule Annual Inspection Report (cont.) 2 The inspection findings consisted of maintenance items and items that were not observed to be signs or potential signs of significant structural weakness. No deficiencies or disrupting conditions that

More information

1.060 Engineering Mechanics II Spring Problem Set 8

1.060 Engineering Mechanics II Spring Problem Set 8 1.060 Engineering Mechanics II Spring 2006 Due on Monday, May 1st Problem Set 8 Important note: Please start a new sheet of paper for each problem in the problem set. Write the names of the group members

More information

CASE STUDY NATHPA JHAKRI, INDIA

CASE STUDY NATHPA JHAKRI, INDIA SEDIMENT MANAGEMENT CASE STUDY NATHPA JHAKRI, INDIA Key project features Name: Nathpa Jhakri Country: India Category: reforestation/revegetation; upstream sediment trapping; bypass channel/tunnel; reservoir

More information

Rock Sizing for Waterway & Gully Chutes

Rock Sizing for Waterway & Gully Chutes Rock Sizing for Waterway & Gully Chutes WATERWAY MANAGEMENT PRACTICES Photo 1 Rock-lined waterway chute Photo 2 Rock-lined gully chute 1. Introduction A waterway chute is a stabilised section of channel

More information

BKS Palace Consortium conducted the geotechnical investigation for the proposed pumped storage scheme (PSS) in the Steelpoort area.

BKS Palace Consortium conducted the geotechnical investigation for the proposed pumped storage scheme (PSS) in the Steelpoort area. 6. GEOLOGY 6.1 Introduction The high-lying Nebo Plateau to the west of the Steelpoort Valley comprises gently undulating terrain at elevations of around 1700m at the upper reservoir site. To the east,

More information

Seepage Analysis for Shurijeh Reservoir Dam Using Finite Element Method. S. Soleymani 1, A. Akhtarpur 2

Seepage Analysis for Shurijeh Reservoir Dam Using Finite Element Method. S. Soleymani 1, A. Akhtarpur 2 Seepage Analysis for Shurijeh Reservoir Dam Using Finite Element Method S. Soleymani 1, A. Akhtarpur 2 1 Group of Dam Construction, Toossab Company, P.O. Box 917751569, Mashhad City, Iran, PH (+98) 511-7684091;

More information

THE CONSTRUCTION OF THE SERRA DO FACÃO HYDROELECTRIC POWER PLANT

THE CONSTRUCTION OF THE SERRA DO FACÃO HYDROELECTRIC POWER PLANT THE CONSTRUCTION OF THE SERRA DO FACÃO HYDROELECTRIC POWER PLANT Authors: Geraldo Martins Filho, Marcilio Martins Dias and Dionésio Werner Junior THE CONSTRUCTION OF THE SERRA DO FACÃO HYDROELECTRIC POWER

More information

Moglicë HPP - Albania. Jorge Terron

Moglicë HPP - Albania. Jorge Terron Moglicë HPP - Albania Jorge Terron DEVOLL MOGLICË PROJECT Background Location Project Summary Sweco duties Plant overview Geology Cavern complex Layout Site investigations Rock mass characterization Geology

More information

Dam Safety Aspects of Reservoir-Triggered Seismicity

Dam Safety Aspects of Reservoir-Triggered Seismicity Dam Safety Aspects of Reservoir-Triggered Seismicity Dr. Martin Wieland Chairman, Committee on Seismic Aspects of Dam Design, International Commission on Large Dams (ICOLD) Poyry Energy Ltd., Zurich, Switzerland

More information

THE MULTIPURPOSE CASTANHÃO DEVELOPMENT ON THE JAGUARIBE RIVER

THE MULTIPURPOSE CASTANHÃO DEVELOPMENT ON THE JAGUARIBE RIVER THE MULTIPURPOSE CASTANHÃO DEVELOPMENT ON THE JAGUARIBE RIVER This paper was written by Ana Teresa Mattos Marques de Sousa Ponte, Keila Margareth Cândido Rolim, Maria Zita Timbó Araújo, Vanda Tereza Costa

More information

Foundation Preparation for RCC Dams Founded on Difficult Foundation Conditions By Paul C. Rizzo and John Charlton. 1.

Foundation Preparation for RCC Dams Founded on Difficult Foundation Conditions By Paul C. Rizzo and John Charlton. 1. Foundation Preparation for RCC Dams Founded on Difficult Foundation Conditions By Paul C. Rizzo and John Charlton 1.0 Introduction RCC Dams, normally designed as traditional gravity structures similar

More information

14 Geotechnical Hazards

14 Geotechnical Hazards Volume 2: Assessment of Environmental Effects 296 14 Geotechnical Hazards Overview This Chapter provides an assessment of the underlying geotechnical conditions to identify: any potential liquefaction

More information

Rock Sizing for Small Dam Spillways

Rock Sizing for Small Dam Spillways Rock Sizing for Small Dam Spillways STORMWATER MANAGEMENT PRACTICES Photo 1 Rock-lined spillway on a construction site sediment basin Photo 2 Rock-lined spillway on a small farm dam 1. Introduction A chute

More information

Geosynthetics Applications and Performance Reviews Select Case Histories

Geosynthetics Applications and Performance Reviews Select Case Histories Geosynthetics Applications and Performance Reviews Select Case Histories Debora J. Miller, Ph.D., P.E.; Dean B. Durkee,, Ph.D., P.E.; Michael A. Morrison, P.E., David B. Wilson, P.E., and Kevin Smith,

More information

Phase II Report: Project Definition Options. Dam Safety

Phase II Report: Project Definition Options. Dam Safety OSHPC BARKI TOJIK Phase II Report: Project Definition Options Dam Safety Part 1: Basic data & Dam Design DAM Safety 2 Geology / Geotechnics...: Tectonics / Seismicity : DAM Design - Dam Location - Type

More information

Assessment of the Post-earthquake Safety and the Maximum Anti-Seismic Capability of Zipingpu Concrete Face Rockfill Dam

Assessment of the Post-earthquake Safety and the Maximum Anti-Seismic Capability of Zipingpu Concrete Face Rockfill Dam Assessment of the Post-earthquake Safety and the Maximum Anti-Seismic Capability of Zipingpu Concrete Face Rockfill Dam Jian-ming Zhao, Jinsheng Jia, Yanfeng Wen China Institute of Water Resources and

More information

Siva Bharatha Murthy. T Page 4.31

Siva Bharatha Murthy. T Page 4.31 Importance of Geological Structures: The physical properties of rocks, mineral and other materials of civil engineering, like textures, grain size are very important for a civil engineer. Similarly the

More information

DISTRIBUTION of WATER RESOURCES

DISTRIBUTION of WATER RESOURCES DAM GEOLOGY DISTRIBUTION of WATER RESOURCES Definition A dam is a structure which prevents the flow of water and accumulates it in a reservoir Karakaya Dam/Diyarbakır Atatürk Dam/Şanlıurfa Needs for Dam

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

Strategies for managing sediment in dams. Iwona Conlan Consultant to IKMP, MRCS

Strategies for managing sediment in dams. Iwona Conlan Consultant to IKMP, MRCS Strategies for managing sediment in dams Iwona Conlan Consultant to IKMP, MRCS 1 Sediment trapping by dams Active storage capacity Dead storage coarse material (bed load) Fine materials (suspension) Francis

More information

FRED BURR DAM FEASIBILITY STUDY

FRED BURR DAM FEASIBILITY STUDY FRED BURR DAM FEASIBILITY STUDY Fred Burr Dam Feasibility Study Purpose: Develop pre-feasibility risk reduction alternatives and recommendations for short-term operations and long-term rehabilitation.

More information

design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards.

design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards. design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards. In addition to the field inspection, Associated Engineers, Inc.

More information

HYDROGEOLOGICAL PROPERTIES OF THE UG2 PYROXENITE AQUIFERS OF THE BUSHVELD COMPLEX

HYDROGEOLOGICAL PROPERTIES OF THE UG2 PYROXENITE AQUIFERS OF THE BUSHVELD COMPLEX R. Gebrekristos, P.Cheshire HYDROGEOLOGICAL PROPERTIES OF THE UG2 PYROXENITE AQUIFERS OF THE BUSHVELD COMPLEX R. Gebrekristos Digby Wells Environmental P. Cheshire Groundwater Monitoring Services Abstract

More information

LIQUEFACTION OF EARTH EMBANKMENT DAMS TWO CASE HISTORIES: (1) LIQUEFACTION OF THE EMBANKMENT SOILS, AND (2) LIQUEFACTION OF THE FOUNDATIONS SOILS

LIQUEFACTION OF EARTH EMBANKMENT DAMS TWO CASE HISTORIES: (1) LIQUEFACTION OF THE EMBANKMENT SOILS, AND (2) LIQUEFACTION OF THE FOUNDATIONS SOILS LIQUEFACTION OF EARTH EMBANKMENT DAMS TWO CASE HISTORIES: (1) LIQUEFACTION OF THE EMBANKMENT SOILS, AND (2) LIQUEFACTION OF THE FOUNDATIONS SOILS Antonio Fernandez, Ph.D. 1 ABSTRACT Paul C. Rizzo Associates,

More information

IAEA SAFETY STANDARDS Geotechnical Aspects of Site Evaluation and Foundations in NPPs, NS-G-3.6

IAEA SAFETY STANDARDS Geotechnical Aspects of Site Evaluation and Foundations in NPPs, NS-G-3.6 IAEA SAFETY STANDARDS Geotechnical Aspects of Site Evaluation and Foundations in NPPs, NS-G-3.6 Regional Workshop on Volcanic, Seismic, and Tsunami Hazard Assessment Related to NPP Siting Activities and

More information

Dams may either be human-built or result from natural phenomena, such as

Dams may either be human-built or result from natural phenomena, such as Chapter 1 Dam failures C. Deangeli 1, G.P. Giani 2, B. Chiaia 1 & A.P. Fantilli 1 1 Politecnico di Torino, Turin, Italy 2 State University of Milan, Milan, Italy Abstract Dams may either be human-built

More information

The 2011 Tohoku earthquake and dams

The 2011 Tohoku earthquake and dams The 2011 Tohoku earthquake and dams N. Matsumoto & T. Sasaki Japan Dam Engineering Center, Japan T. Ohmachi Tokyo Institute of Technology, Japan ABSTRACT: The magnitude 9.0 Tohoku earthquake occurred on

More information

Amistad Dam Investigation and Oversight: Karst- Founded Dam on the USA-Mexico Border

Amistad Dam Investigation and Oversight: Karst- Founded Dam on the USA-Mexico Border Amistad Dam Investigation and Oversight: Karst- Founded Dam on the USA-Mexico Border Brook Brosi, CPG, PG USACE Lisa Nowicki Perks, PG USACE Kimberly Heenan, PE AECOM US Army Corps of Engineers BUILDING

More information

ICOLD TCDS - Technical Committe on Dam Surveillance

ICOLD TCDS - Technical Committe on Dam Surveillance Click to edit Master title ICOLD TCDS - Technical Committe on Dam Surveillance Sam Johansson TCDS Foundation SwedCold, 2017-10-09 1 Click TCDS to - edit Master title Technical Committe on Dam Surveillance

More information

U-Shaped Sediment Traps

U-Shaped Sediment Traps U-Shaped Sediment Traps SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils [1] Type 3 System Supplementary Trap Dispersive Soils [1] Generally

More information

Seismic Design of a Hydraulic Fill Dam by Nonlinear Time History Method

Seismic Design of a Hydraulic Fill Dam by Nonlinear Time History Method Seismic Design of a Hydraulic Fill Dam by Nonlinear Time History Method E. Yıldız & A.F. Gürdil Temelsu International Engineering Services Inc., Ankara, Turkey SUMMARY: Time history analyses conducted

More information

Rogun Hydropower Project

Rogun Hydropower Project Rogun Hydropower Project Dam site Geological investigations in the Downstream Right Bank Ascencio Lara Coyne et Bellier Almaty, 11-12 February 2013 Objectives of the presentation As the stability conditions

More information

Module 9 : Foundation on rocks. Content

Module 9 : Foundation on rocks. Content FOUNDATION ON ROCKS Content 9.1 INTRODUCTION 9.2 FOUNDATION TYPES ON ROCKS 9.3 BEARING CAPCITY- SHALLOW FOUNDATION 9.3.1 Ultimate bearing capacity 9.3.2 Safe bearing pressure 9.3.3 Estimation of bearing

More information

Practical methodology for inclusion of uplift and pore pressures in analysis of concrete dams

Practical methodology for inclusion of uplift and pore pressures in analysis of concrete dams Practical methodology for inclusion of uplift and pore pressures in analysis of concrete dams Michael McKay 1 and Francisco Lopez 2 1 Dams Engineer, GHD Pty 2 Principal Dams/Structural Engineer, GHD Pty

More information

TWO DIMENSIONAL MODELING AND STABILITY ANALYSIS OF SLOPES OVERLAYING TO SHAHID RAGAEE POWER PLANT

TWO DIMENSIONAL MODELING AND STABILITY ANALYSIS OF SLOPES OVERLAYING TO SHAHID RAGAEE POWER PLANT 4 th International Conference on Earthquake Geotechnical Engineering June 25-28, 2007 Paper No. 1637 TWO DIMENSIONAL MODELING AND STABILITY ANALYSIS OF SLOPES OVERLAYING TO SHAHID RAGAEE POWER PLANT Mohammad

More information

Application of Energy Approach to Estimating Scour Depth

Application of Energy Approach to Estimating Scour Depth Nature and Science, (), 004, Zhang, et al, Application of Energy Approach Application of Energy Approach to Estimating Scour Depth Xiaodong Zhang 1, Zhiping Liu 1, Chuan Liang, Qiang Fu 3 (1. IWHR, Beijing

More information

RESERVOIR DRAWDOWN RATES/RESERVOIR DRAWDOWN TEST Iron Gate, Copco (I & II), and JC Boyle Dams

RESERVOIR DRAWDOWN RATES/RESERVOIR DRAWDOWN TEST Iron Gate, Copco (I & II), and JC Boyle Dams TECHNICAL MEMORANDUM No. 1 TO: Michael Bowen California Coastal Conservancy Geotechnical & Earthquake Engineering Consultants CC: Eric Ginney Philip Williams & Associates PREPARED BY: Paul Grant SUBJECT:

More information

UGRC 144 Science and Technology in Our Lives/Geohazards

UGRC 144 Science and Technology in Our Lives/Geohazards UGRC 144 Science and Technology in Our Lives/Geohazards Flood and Flood Hazards Dr. Patrick Asamoah Sakyi Department of Earth Science, UG, Legon College of Education School of Continuing and Distance Education

More information

High-Precision Strength Evaluation of Rock Materials and Stability Analysis for Rockfill Dams

High-Precision Strength Evaluation of Rock Materials and Stability Analysis for Rockfill Dams 1st International Symposium on Rockfill Dams High-Precision Strength Evaluation of Rock Materials and Stability Analysis for Rockfill Dams Hiroki SAKAMOTO Research Engineer Public Works Research Institute,

More information

Climate effects on landslides

Climate effects on landslides GEORAMP ONE DAY SYMPOSIUM Climate effects on landslides E. E. Alonso, M. Sondón, N. M. Pinyol Universitat Politècnica de Catalunya October 14th, 2016. UPC, Barcelona Infiltration (evaporation) and slope

More information

*** ***! " " ) * % )!( & ' % # $. 0 1 %./ +, - 7 : %8% 9 ) 7 / ( * 7 : %8% 9 < ;14. " > /' ;-,=. / ١

*** ***!   ) * % )!( & ' % # $. 0 1 %./ +, - 7 : %8% 9 ) 7 / ( * 7 : %8% 9 < ;14.  > /' ;-,=. / ١ ١ ******!" #$ % & '!( ) % * ") +,-./ % 01. 3 ( 4 56 7/4 ) 8%9 % : 7 ;14 < 8%9 % : *7./ = ;-, >/'." Soil Permeability & Seepage ٢ Soil Permeability- Definition ٣ What is Permeability? Permeability is the

More information

Settlement characteristics of major infrastructures in Shanghai

Settlement characteristics of major infrastructures in Shanghai doi:10.5194/piahs-372-475-2015 Author(s) 2015. CC Attribution 3.0 License. Settlement characteristics of major infrastructures in Shanghai X. Jiao 1,2, X. X. Yan 1,2, and H. M. Wang 1,2 1 Shanghai Institute

More information

Geotechnical Monitoring for Safe Excavation of Large Rock Cavern: A Case Study

Geotechnical Monitoring for Safe Excavation of Large Rock Cavern: A Case Study The 31st International Symposium on Automation and Robotics in Construction and Mining (ISARC 2014) Geotechnical Monitoring for Safe Excavation of Large Rock Cavern: A Case Study A.Mandal a, C. Kumar b,

More information

PRELIMINARY INVESTIGATION ON THE FAILURE OF THE BA-LING CHECK DAM IN THE WATERSHED OF SHI-MEN RESERVOIR IN TAIWAN

PRELIMINARY INVESTIGATION ON THE FAILURE OF THE BA-LING CHECK DAM IN THE WATERSHED OF SHI-MEN RESERVOIR IN TAIWAN PRELIMINARY INVESTIGATION ON THE FAILURE OF THE BA-LING CHECK DAM IN THE WATERSHED OF SHI-MEN RESERVOIR IN TAIWAN Su-Chin Chen. 1 *, Yu-Hsan Chang 2, Ben-Kang Chen 3, Yi-Chuan Liu 4, Zheng-Yi Feng, 5*,

More information

Qualitative Foundation Rock Block Stability Evaluation Performed for Green Peter Dam

Qualitative Foundation Rock Block Stability Evaluation Performed for Green Peter Dam Qualitative Foundation Rock Block Stability Evaluation Performed for Green Peter Dam Todd N. Loar, CEG Senior Geological Engineer USACE Risk Management Center AAARRR!!!... Peck, Peck, Terzaghi, Goodman,

More information

Engineer. Engineering. Engineering. (in-ja-neer ) A person trained and skilled in any of the various branches of engineering: a civil engineer

Engineer. Engineering. Engineering. (in-ja-neer ) A person trained and skilled in any of the various branches of engineering: a civil engineer Engineer (in-ja-neer ) A person trained and skilled in any of the various branches of engineering: a civil engineer (Random House Webster s College Dictionary, 1991) CE100 Introduction to Civil Geotechnical

More information

November 20, 2003 Project

November 20, 2003 Project November 20, 2003 Project 032810 1021 Main Street Winchester, MA 01890-1970 781.721.4000 781.721.4073 fax Mr. Bobby Van Cleave Geotechnical Engineer Little Rock District Federal Building, 7th Floor 700

More information

1 PROJECT BACKGROUND. August 14, Alberta Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8

1 PROJECT BACKGROUND. August 14, Alberta Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8 August 14, 2013 Alberta Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 Mr. Dennis Grace, P.Eng. Construction Engineer Dear Mr. Grace: Central Region Geohazard Assessment 2013

More information

3/8/17. #20 - Landslides: Mitigation and Case Histories. Questions for Thought. Questions for Thought

3/8/17. #20 - Landslides: Mitigation and Case Histories. Questions for Thought. Questions for Thought #20 - Landslides: Mitigation and Case Histories Web Exercise #3 (Volcanoes) Due Wednesday There is a 2-point penalty for every day the assignment is late. Exam 1 Scores Scores and exam key are posted Vaiont

More information

SPILLWAY CHUTES DESCARREGADORES DE CHEIA COM QUEDA GUIADA

SPILLWAY CHUTES DESCARREGADORES DE CHEIA COM QUEDA GUIADA SPILLWAY CHUTES DESCARREGADORES DE CHEIA COM QUEDA GUIADA Hydropower Hidroenergia Jorge Matos 1 and Inês Lúcio 2 1 jorge.matos@tecnico.ulisboa.pt 2 ines.lucio@tecnico.ulisboa.pt 1 Spillway chutes Descarregadores

More information

GEOTECHNICAL ENGINEERING II. Subject Code : 06CV64 Internal Assessment Marks : 25 PART A UNIT 1

GEOTECHNICAL ENGINEERING II. Subject Code : 06CV64 Internal Assessment Marks : 25 PART A UNIT 1 GEOTECHNICAL ENGINEERING II Subject Code : 06CV64 Internal Assessment Marks : 25 PART A UNIT 1 1. SUBSURFACE EXPLORATION 1.1 Importance, Exploration Program 1.2 Methods of exploration, Boring, Sounding

More information

Teton Dam Failure A Review of the Technical Factors Contributing to the Failure

Teton Dam Failure A Review of the Technical Factors Contributing to the Failure Teton Dam Failure A Review of the Technical Factors Contributing to the Failure Outline of Presentation Location, Background and Project Statistics Technical Causes of Failure to be Discussed Geology

More information

STEVENS CREEK DAM SEISMIC STABILITY EVALUATIONS OF CHESBRO, LENIHAN, STEVENS CREEK, AND UVAS DAMS (SSE2) PHASE A: STEVENS CREEK AND LENIHAN DAMS

STEVENS CREEK DAM SEISMIC STABILITY EVALUATIONS OF CHESBRO, LENIHAN, STEVENS CREEK, AND UVAS DAMS (SSE2) PHASE A: STEVENS CREEK AND LENIHAN DAMS SEISMIC STABILITY EVALUATIONS OF CHESBRO, LENIHAN, STEVENS CREEK, AND UVAS DAMS (SSE2) PHASE A: STEVENS CREEK AND LENIHAN DAMS STEVENS CREEK DAM COMPILATION REPORT (REPORT No. SSE2A-SC) Prepared for SANTA

More information

Nipigon River Landslide, Ontario, Canada

Nipigon River Landslide, Ontario, Canada Nipigon River Landslide, Ontario, Canada A. Abdelaziz, S. Besner, R. Boger, B. Fu, J. Deng, and A. Farina Presenter: Jian Deng, Ph.D, P.Eng Centre of Excellence for Sustainable Mining and Exploration,

More information

Design of RC Retaining Walls

Design of RC Retaining Walls Lecture - 09 Design of RC Retaining Walls By: Prof Dr. Qaisar Ali Civil Engineering Department UET Peshawar www.drqaisarali.com 1 Topics Retaining Walls Terms Related to Retaining Walls Types of Retaining

More information

STRUCTURAL STABILITY ASSESSMENT

STRUCTURAL STABILITY ASSESSMENT STRUCTURAL STABILITY ASSESSMENT CFR 257.73(d) Bottom Ash Pond Complex Cardinal Plant Brilliant, Ohio October, 2016 Prepared for: Cardinal Operating Company Cardinal Plant Brilliant, Ohio Prepared by: Geotechnical

More information

Delineation of Zones at Risk from Groundwater Inflows at an Underground Platinum Mine in South Africa

Delineation of Zones at Risk from Groundwater Inflows at an Underground Platinum Mine in South Africa Delineation of Zones at Risk from Groundwater Inflows at an Underground Platinum Mine in South Africa Mr Andreas Stoll andreas.stoll@erm.com Environmental Resources Management Swiss GmbH (ERM), Switzerland

More information

The effectiveness of check dams in controlling upstream channel stability in northeastern Taiwan

The effectiveness of check dams in controlling upstream channel stability in northeastern Taiwan Erosion, Debris Mows and Environment in Mountain Regions (Proceedings of the Chengdu Symposium, July 1992). IAHS Publ. no. 209, 1992. 423 The effectiveness of check dams in controlling upstream channel

More information

Instructor : Dr. Jehad Hamad. Chapter (7)

Instructor : Dr. Jehad Hamad. Chapter (7) Instructor : Dr. Jehad Hamad Chapter (7) 2017-2016 Soil Properties Physical Properties Mechanical Properties Gradation and Structure Compressibility Soil-Water Relationships Shear Strength Bearing Capacity

More information

Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils

Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils Sediment Weirs SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils [1] Type 3 classification

More information

Landslide FE Stability Analysis

Landslide FE Stability Analysis Landslide FE Stability Analysis L. Kellezi Dept. of Geotechnical Engineering, GEO-Danish Geotechnical Institute, Denmark S. Allkja Altea & Geostudio 2000, Albania P. B. Hansen Dept. of Geotechnical Engineering,

More information

Carlos Baião Cenorgeo DESIGN AND CONSTRUCTION OF THE MACHICO-CANIÇAL CANIÇAL EXPRESSWAY TUNNELS

Carlos Baião Cenorgeo DESIGN AND CONSTRUCTION OF THE MACHICO-CANIÇAL CANIÇAL EXPRESSWAY TUNNELS Carlos Baião Cenorgeo carlos.baiao@cenor.pt DESIGN AND CONSTRUCTION OF THE MACHICO-CANIÇAL CANIÇAL EXPRESSWAY TUNNELS PRESENTATION LAYOUT Overall considerations Geological conditions Geological-geotechnical

More information

GEOL 1121 Earth Processes and Environments

GEOL 1121 Earth Processes and Environments GEOL 1121 Earth Processes and Environments Wondwosen Seyoum Department of Geology University of Georgia e-mail: seyoum@uga.edu G/G Bldg., Rm. No. 122 Seyoum, 2015 Chapter 6 Streams and Flooding Seyoum,

More information

PERENNIAL PROBLEM OF EARTHEN BUND OF WELLINGDON RESERVOIR. ANALYSIS OF CAUSES AND REMEDIAL MEASURES A CASE STUDY.

PERENNIAL PROBLEM OF EARTHEN BUND OF WELLINGDON RESERVOIR. ANALYSIS OF CAUSES AND REMEDIAL MEASURES A CASE STUDY. PERENNIAL PROBLEM OF EARTHEN BUND OF WELLINGDON RESERVOIR. ANALYSIS OF CAUSES AND REMEDIAL MEASURES A CASE STUDY. By Er. S. Muthu Parvatha Vardhini, Asst. Executive Engineer, (Designs) Water Resources

More information

PRELIMINARY COST ESTIMATES OF STORAGE OPTIONS IN THE HURUNUIWAIRAU ZONE

PRELIMINARY COST ESTIMATES OF STORAGE OPTIONS IN THE HURUNUIWAIRAU ZONE PRELIMINARY COST ESTIMATES OF STORAGE OPTIONS IN THE HURUNUIWAIRAU ZONE Engineers and Geologists PRELIMINARY COST ESTIMATES OF STORAGE OPTIONS IN THE HURUNUI-WAIRAU ZONE Report prepared for: Environment

More information

Rock Sizing for Batter Chutes

Rock Sizing for Batter Chutes Rock Sizing for Batter Chutes STORMWATER MANAGEMENT PRACTICES Photo 1 Rock-lined batter chute Photo 2 Rock-lined batter chute 1. Introduction In the stormwater industry a chute is a steep drainage channel,

More information

Gotechnical Investigations and Sampling

Gotechnical Investigations and Sampling Gotechnical Investigations and Sampling Amit Prashant Indian Institute of Technology Gandhinagar Short Course on Geotechnical Investigations for Structural Engineering 12 14 October, 2017 1 Purpose of

More information

1. Rock Mechanics and mining engineering

1. Rock Mechanics and mining engineering 1. Rock Mechanics and mining engineering 1.1 General concepts Rock mechanics is the theoretical and applied science of the mechanical behavior of rock and rock masses; it is that branch of mechanics concerned

More information

Further Research into Methods of Analysing the October 2000 Stability of Deep Open Pit Mines EXECUTIVE SUMMARY

Further Research into Methods of Analysing the October 2000 Stability of Deep Open Pit Mines EXECUTIVE SUMMARY EXECUTIVE SUMMARY This report presents the results of a program of further research into the use of a combined approach of numerical and centrifuge modeling in assessing the stability of deep open pit

More information

Analysis of soil failure modes using flume tests

Analysis of soil failure modes using flume tests Analysis of soil failure modes using flume tests A. Spickermann & J.-P. Malet Institute of Earth Physics, CNRS UMR 751, University of Strasbourg, Strasbourg, France Th.W.J. van Asch, M.C.G. van Maarseveen,

More information

Instructional Objectives

Instructional Objectives GE 6477 DISCONTINUOUS ROCK 8. Fracture Detection Dr. Norbert H. Maerz Missouri University of Science and Technology (573) 341-6714 norbert@mst.edu Instructional Objectives 1. List the advantages and disadvantages

More information

10. GEOTECHNICAL EXPLORATION PROGRAM

10. GEOTECHNICAL EXPLORATION PROGRAM Geotechnical site investigations should be conducted in multiple phases to obtain data for use during the planning and design of the tunnel system. Geotechnical investigations typically are performed in

More information

Scoping Calculations of TBM Advancement in Flysch and Breccias of Strait-of-Gibraltar Tunnel

Scoping Calculations of TBM Advancement in Flysch and Breccias of Strait-of-Gibraltar Tunnel EURO:TUN 2009 2 nd International Conference on Computational Methods in Tunnelling Ruhr University Bochum, 9-11 September 2009 Aedificatio Publishers, 369-376 Scoping Calculations of TBM Advancement in

More information

Engineering Geological Evaluation of Siyan Gad Small Hydroelectric Project, Uttarakashi District, Uttarakhand

Engineering Geological Evaluation of Siyan Gad Small Hydroelectric Project, Uttarakashi District, Uttarakhand IOSR ournal of Applied Geology and Geophysics (IOSR-AGG) e-issn: 2321 0990, p-issn: 2321 0982.Volume 5, Issue 1 Ver. I (an. - Feb. 2017), PP 46-51 www.iosrjournals.org Engineering Geological Evaluation

More information

CHAPTER 6, PRELIMINARY SITE INVESTIGATION CONTENTS

CHAPTER 6, PRELIMINARY SITE INVESTIGATION CONTENTS CHAPTER 6, PRELIMINARY SITE INVESTIGATION CONTENTS - Page Purpose... 6-1 Assembly of data... 6-1 Use of aerial photographs... 6-2 Field study... 6-3 Mappix... 6-4 Repcrt of preliminary investigation...

More information

SPECIFIC DEGRADATION AND RESERVOIR SEDIMENTATION. By Renee Vandermause & Chun-Yao Yang

SPECIFIC DEGRADATION AND RESERVOIR SEDIMENTATION. By Renee Vandermause & Chun-Yao Yang SPECIFIC DEGRADATION AND RESERVOIR SEDIMENTATION By Renee Vandermause & Chun-Yao Yang Outline Sediment Degradation - Erosion vs Sediment Yield - Sediment Yield - Methods for estimation - Defining Sediment

More information