CHRISTIAN WHEELER E N G I N E E R I N G

Size: px
Start display at page:

Download "CHRISTIAN WHEELER E N G I N E E R I N G"

Transcription

1 CHRISTIAN WHEELER E N G I N E E R I N G REPORT OF PRELIMINARY GEOTECHNICAL INVESTIGATION PROPOSED HIGH STREET APARTMENTS A.P.N. S & HIGH STREET, LA MESA, CALIFORNIA PREPARED FOR N.T.C. DEVELOPMENT, INC EL CAJON BOULEVARD EL CAJON, CALIFORNIA PREPARED BY CHRISTIAN WHEELER ENGINEERING 3980 HOME AVENUE SAN DIEGO, CALIFORNIA H o m e A v e n u e S a n D i e g o, C A F A X

2 CHRISTIAN WHEELER E N G I N E E R I N G October 7, 2015 N.T.C. Development, Inc. CWE El Cajon Boulevard El Cajon, California Attention: Michael Martineau Subject: Report of Preliminary Geotechnical Investigation Proposed High Street Apartments, A.P.N. s & High Street, La Mesa, California Ladies and Gentlemen: In accordance with our proposal dated July 29, 2015, we have completed a preliminary geotechnical investigation for the subject project. We are presenting herein our findings and recommendations. In general, we found the subject property suitable for the proposed development, provided the recommendations provided herein are followed. The main geotechnical condition to affect the proposed construction is the presence of potentially compressible fill of variable thickness, which underlies the entire site. This condition will require special site preparation considerations as described in the attached report. If you have any questions after reviewing this report, please do not hesitate to contact our office. This opportunity to be of professional service is sincerely appreciated. Respectfully submitted, CHRISTIAN WHEELER ENGINEERING Jesse D. Bearfield, R.C.E. #84335 David R. Russell, C.E.G. #2215 JDB:drr:dba ntc-michael@sbcglobal.net H o m e A v e n u e S a n D i e g o, C A F A X

3 TABLE OF CONTENTS PAGE introduction and Project Description... 1 Project Scope... 2 Findings... 3 Site Description... 3 General Geology and Subsurface Conditions... 3 Geologic Setting and Soil Description... 3 Artificial Fill... 3 Metavolcanic Rock... 4 Groundwater... 4 Tectonic Setting... 4 Geologic Hazards... 5 Seismic Hazard... 5 Landslide Potential and Slope Stability... 5 Liquefaction... 6 Flooding... 6 Tsunamis... 6 Seiches... 6 Conclusions... 6 Recommendations... 7 Grading and Earthwork... 7 General... 7 Observation of Grading... 8 Clearing and Grubbing... 8 Site Preparation... 8 Debris... 8 Oversized Rock Placement... 8 Processing of Fill Areas... 9 Compaction and Method of Filling... 9 Temporary Cut Slopes... 9 Surface Drainage... 9 Grading Plan Review Conventional Shallow Foundations General Dimensions Footing Reinforcing Lateral Load Resistance Settlement Characteristics Expansive Characteristics Foundation Plan Review Foundation Excavation Observation: On-Grade Slabs General Interior Slab Under-Slab Vapor Retarders Exterior Concrete Flatwork Earth Retaining Walls Foundations Passive Pressures CWE Proposed High Street Apartments A.P.N. s & High Street, La Mesa, California

4 Active Pressures Waterproofing and Wall Drainage Systems Backfill Preliminary Pavement Sections General Preliminary Asphalt Concrete Pavements Concrete Pavements Limitations Review, Observation and Testing Uniformity of Conditions Change in Scope Time Limitations Professional Standard Client's Responsibility Field Explorations Laboratory Testing TABLES Table I: CBC 2013 Edition Seismic Design Parameters... 5 Table II: Preliminary Asphalt Concrete Pavement Section Table III: Concrete Pavement Design Parameters Table IV: Minimum Concrete Pavement Thickness FIGURES Figure 1 Site Vicinity Map, Follows Page 1 PLATES Plate 1 Site Plan and Geotechnical Map Plate 2 Oversize Rock Placement Plate 3 Retaining Wall Subdrain Detail APPENDICES Appendix A Test Trench Logs Appendix B Laboratory Test Results Appendix C References Appendix D Recommended Grading Specifications General Provisions CWE Proposed High Street Apartments A.P.N. s & High Street, La Mesa, California

5 CHRISTIAN WHEELER E N G I N E E R I N G REPORT OF PRELIMINARY GEOTECHNICAL INVESTIGATION PROPOSED HIGH STREET APARTMENTS A.P.N. S & HIGH STREET, LA MESA, CALIFORNIA INTRODUCTION AND PROJECT DESCRIPTION This report presents the results of a preliminary geotechnical investigation performed for proposed apartment development to be constructed at a vacant lot located adjacent to and north of High Street in the city of La Mesa, California. The following Figure Number 1 presents a vicinity map showing the location of the project. We understand that it is proposed to construct two or three, two-story apartment structures with partially subterranean garages and associated improvements. The garage level finished floors are expected to be about 5 feet below proposed site grades with the 1 st level proposed to be about 5 feet above proposed grades. We anticipate that subterranean portions of the apartment structures level will be of masonry construction and will include a concrete floor slab. The above ground portions of the structures are anticipated to be of conventional, wood frame construction. We anticipate that the structures will be supported by conventional shallow foundations. Grading to accommodate the proposed improvements is expected to consist of cuts and fills of less than five feet from existing grades. To assist in the preparation of this report, we were provided with an topographic map of the site prepared by San-Lo Aerial Surveys, with a fly date of October 27, A copy of this plan was used as a base map for our geologic mapping, and is included herein as Plate Number 1. This report has been prepared for the exclusive use of N.T.C. Development, Inc. and its consultants for specific application to the project described herein. Should the project be modified, the conclusions and recommendations presented in this report should be reviewed by Christian Wheeler Engineering for conformance with our recommendations and to determine whether any additional subsurface investigation, laboratory testing and/or recommendations are necessary. Our professional services have been performed, our findings obtained, and our recommendations prepared in accordance with generally accepted engineering principles and practices. This warranty is in lieu of all other warranties, expressed or implied H o m e A v e n u e S a n D i e g o, C A F A X

6 SITE VICINITY OpenStreetMap contributors PROJECT SITE DATE: OCTOBER 2015 BY: SRD PROPOSED HIGH STREET APARTMENTS A.P.N.'S & HIGH STREET, LA MESA, CALIFORNIA JOB NO.: FIGURE NO.: 1 CHRISTIAN WHEELER E N G I N E E R I N G

7 CWE October 7, 2015 Page 2 PROJECT SCOPE Our preliminary geotechnical investigation consisted of surface reconnaissance, subsurface exploration, obtaining representative soil samples, laboratory testing, analysis of the field and laboratory data and review of relevant geologic literature. Our scope of service did not include assessment of hazardous substance contamination, recommendations to prevent floor slab moisture intrusion or the formation of mold within the structure, an evaluation of the gross and surficial stability of the existing rock cliffs, nor does it include analysis of the global stability of the site and/or surrounding areas, or any other services not specifically described in the scope of services presented below. More specifically, our intent was to provide the services listed below. Explore the subsurface conditions of the site to the depths influenced by the proposed construction. Evaluate, by laboratory tests and our past experience with similar soil types, the engineering properties of the various strata that may influence the proposed construction, including bearing capacities, expansive characteristics, settlement potential, and corrosive characteristics. Describe the general geology at the site including possible geologic hazards that could have an effect on the proposed construction, and provide the seismic design parameters as required by the 2013 edition of the California Building Code. Address potential construction difficulties that may be encountered due to soil conditions, groundwater or geologic hazards, and provide recommendations concerning these problems. Develop soil engineering criteria for site preparation and grading. Provide temporary cut slope recommendations, as necessary. Recommend an appropriate foundation system for the type of structures anticipated and develop soil engineering design criteria for the recommended foundation design. Provide geotechnical design parameters for the construction or restrained and unrestrained retaining walls. Prepare this report, which includes, in addition to our conclusions and recommendations, a plot plan showing the aerial extent of the geological units and the locations of our exploratory borings, exploration logs, and a summary of the laboratory test results. Although a test for the presence of soluble sulfates within the soils that may be in contact with reinforced concrete was performed as part of the scope of our services, it should be understood Christian Wheeler Engineering does not practice corrosion engineering. If such an analysis is considered necessary, we recommend that the client retain an engineering firm that specializes in this field to consult with them on this

8 CWE October 7, 2015 Page 3 matter. The results of the test should only be used as a guideline to determine whether additional testing and analysis is necessary. FINDINGS SITE DESCRIPTION The subject site is an abandoned rock quarry, identified as Assessor s Parcel Numbers and The property is located adjacent to and north of High Street in La Mesa, California. The site is currently vacant and was previously used as a rock quarry sometime before the 1940 s. The property is bound by High Street to the south, vacant lots to the east and west, and developed residential lots to the north. Topographically, the site is characterized by a gently southeastern sloping pad that is surrounded by steep cliffs on the north, west and east sides. Based on the topographic map elevations, cliff heights range from about 30 feet to 135 feet. Numerous boulders are present along the base of the cliff and comprise a sloughed pile at the north side of the pad. The pad area slopes from an elevation of about 580 feet to about 550 feet from the north to south toward High Street. On-site vegetation consists of grasses and shrubs. GENERAL GEOLOGY AND SUBSURFACE CONDITIONS GEOLOGIC SETTING AND SOIL DESCRIPTION: The subject site is located in the Foothills Physiographic Province of San Diego County. Based upon the results of our subsurface exploration, analysis of readily available, pertinent geologic literature, and review of the referenced documents, it was determined that the project site is underlain by Mesozoic-age metavolcanic rock and artificial fill of varying thickness. These materials are described below. ARTIFICIAL FILL (Qaf): Man-placed fill soils were encountered within each of our six exploratory trenches. The thickness of the fill encountered in our trenches ranged from approximately 14 feet in trenches T-1 and T-2, to about 16 feet in trench T-5. The fill extended beyond the bottom of trenches for T-3, T-4, and T-6. The depth of the old existing fill was found to extend beyond the maximum excavation depth of 18 feet in T-4. The encountered fill materials generally consisted of orangish-brown clayey sand/silty gravel (SC/GM), dark brown clayey sand (SC), orangish-brown silty gravel (GM), and brown to orangish-brown, silty sand (SM). The artificial fills were found to be generally loose to medium dense, and was dry to damp. This material was found to include cobbles and boulders up to about 2 feet in length and minor debris consisting of pipes, paper, cloth, wood, and concrete and asphalt concrete.

9 CWE October 7, 2015 Page 4 METAVOLCANIC ROCK (Mzu): Mesozoic-age metavolcanic rock, commonly referred to as the Santiago Peak Volcanics, was encountered below the fill in trenches T-1, T-2 and T-5 and is anticipated to underlie the fill soils throughout the site. Within our trenches, the metamorphosed volcanic rock primarily consisted of olive to dark brown crystalline rock, that when excavated or blasted, breaks down to angular sandy gravel, cobble, and boulders. GROUNDWATER: No groundwater or seepage was encountered in our subsurface explorations and we do not expect any groundwater related conditions during or after the proposed construction provided that proper drainage is maintained at the site. It should, however be recognized that minor groundwater seepage problems might occur after development of a site even where none were present before development. These are usually minor phenomena and are often the result of an alteration in drainage patterns and/or an increase in irrigation water. Given the anticipated geologic conditions of the site following development, resulting in artificial fill over metavolcanic rock, such problems can be most effectively corrected during site remedial grading and also on an individual basis if and when they occur. TECTONIC SETTING: No faults are known to traverse the subject site. However, it should be noted that much of Southern California, including the San Diego County area, is characterized by a series of Quaternary-age fault zones that consist of several individual, en echelon faults that generally strike in a northerly to northwesterly direction. Some of these fault zones (and the individual faults within the zone) are classified as active according to the criteria of the California Division of Mines and Geology. Active fault zones are those that have shown conclusive evidence of faulting during the Holocene Epoch (the most recent 11,000 years). The Division of Mines and Geology used the term potentially active on Earthquake Fault Zone maps until 1988 to refer to all Quaternary-age (last 1.6 million years) faults for the purpose of evaluation for possible zonation in accordance with the Alquist-Priolo Earthquake Fault Zoning Act and identified all Quaternary-age faults as potentially active except for certain faults that were presumed to be inactive based on direct geologic evidence of inactivity during all of Holocene time or longer. Some faults considered to be potentially active would be considered to be active but lack specific criteria used by the State Geologist, such as sufficiently active and well-defined. Faults older than Quaternary-age are not specifically defined in Special Publication 42, Fault Rupture Hazard Zones in California, published by the California Division of Mines and Geology. However, it is generally accepted that faults showing no movement during the Quaternary period may be considered to be inactive. The City of San Diego guidelines indicate that since the beginning of the Pleistocene Epoch marks the boundary between potentially active and inactive faults, unfaulted Pleistocene-age deposits are accepted as evidence that a fault may be considered to be inactive.

10 CWE October 7, 2015 Page 5 A review of available geologic maps indicates that the nearest active fault zone is the Rose Canyon Fault Zone (RCFZ), located approximately 9 miles west of the site. Other active fault zones in the region that could possibly affect the site include the Coronado Bank Fault Zone to the southwest; the Newport-Inglewood and Palos Verdes Fault Zones to the northwest; and the Elsinore, Earthquake Valley, San Jacinto, and San Andreas Fault Zones to the northeast. GEOLOGIC HAZARDS SEISMIC HAZARD: A likely geologic hazard to affect the site is ground shaking as a result of movement along one of the major active fault zones mentioned in the Tectonic Setting section of this report. Per Chapter 16 of the 2013 California Building Code (CBC), the Maximum Considered Earthquake (MCE) ground motion is that considered to have a two percent probability of being exceeded in 50 years. Figures (3) and (4) of the CBC present regional MCE spectral accelerations for short (0.2 sec.) and long (1.0 sec.) periods, respectively, based on a soil Site Class B (CBC Table ) and a structural damping of five percent. For the subject site, we expect that correlation with field penetration resistance values will indicate that the upper 100 feet of geologic subgrade can be characterized as Site Class D. In this case, the mapped MCE spectral accelerations are modified using the Site Coefficients presented in Tables (1) and (2). The modified MCE spectral accelerations are then multiplied by two-thirds in order to obtain the design spectral accelerations. These seismic design parameters for the subject site (32.752, ), based on Chapter 16 of the CBC, are presented in Table I below. TABLE I: CBC 2013 EDITION SEISMIC DESIGN PARAMETERS CBC Chapter 16 Section Seismic Design Parameter Recommended Value Table Soil Site Class D Figure (3) Mapped Spectral Acceleration for Short Periods (0.2 sec), S s g Figure (4) Mapped Spectral Acceleration for 1.0 Sec Periods (1.0 sec), S g Table (1) Site Coefficient, F a Table (2) Site Coefficient, F v Section S MS = MCE Spectral Response at 0.2 sec. = (S s)(f a) g Section S M1 = MCE Spectral Response at 1.0 sec. = (S 1)(F v) g Section S DS = Design Spectral Response at 0.2 sec. = 2/3(S MS) g Section S D1 = Design Spectral Response at 1.0 sec. = 2/3(S M1) g LANDSLIDE POTENTIAL AND SLOPE STABILITY: The Relative Landslide Susceptibility and Landslide Distribution Map of the La Mesa Quadrangle prepared by the California Division of Mines and Geology indicates that the site is situated within Relative Landslide Susceptibility Area 3-1. Area 3 is considered to be generally susceptible to slope failures; Subarea 3-1 includes areas that contain slopes at or near their

11 CWE October 7, 2015 Page 6 stability limits due to a combination of steep slope angles and weak underlying materials. Although slopes within Subarea 3-1 are not known to contain landslides, they may be expected to fail when adversely modified. Given the gently sloping topography of the areas within and adjacent to the site, the risk of slope failures at or adjacent to the subject site is considered to be low. We understand that the proposed construction includes the construction of two or three two-story apartment buildings at the subject site. It has been discussed that these structures may be located a distance of about 20 feet away from the base of the rock cliffs. We further understand it is proposed that the existing rock cliffs will not be altered or affected during the construction of site improvements. Our authorized scope of service did not include an evaluation of the gross and surficial stability of the existing rock cliffs, nor did it include analysis of the global stability of the site and/or surrounding areas. We understand that any required analysis of the gross and surficial stability of the rock cliffs including the potential for rock falls will be performed by others. If the project s reviewing agency does not require analysis of the existing rock slopes along the west, north, and east sides of the site, the client should contact our firm for further discussion. LIQUEFACTION: The near-surface soils encountered at the site are not considered susceptible to liquefaction due to such factors as depth to the groundwater table, soil density and grain-size distribution. FLOODING: The site is located outside the boundaries of both the 100-year and the 500-year floodplains according to the maps prepared by the Federal Emergency Management Agency. TSUNAMIS: Tsunamis are great sea waves produced by submarine earthquakes or volcanic eruptions. Due to the site s elevation and location, the site will not be affected by tsunamis. SEICHES: Seiches are periodic oscillations in large bodies of water such as lakes, harbors, bays or reservoirs. Due to the site s location, it will not be affected by seiches. CONCLUSIONS It is our professional opinion and judgment that no geotechnical conditions exist within the subject site that would preclude the construction of the proposed development, provided the recommendations presented herein are followed. The main geotechnical conditions affecting the proposed construction are the presence of relatively deep, potentially compressible fills soils of variable depth and the stability and rock fall potential of the steep slopes bounding the site. The presence of the existing old fills will require special site preparation considerations as described in the recommendations section of the report. Assessment of and

12 CWE October 7, 2015 Page 7 recommendations to mitigate any potentially hazardous conditions including slope stability and rock fall potential at or adjacent to the subject site should be evaluated by others. The site was found to be underlain by variable density, potentially compressible fill materials extending to variable depths. In general, the fill increases in depth from north to south and from west to east across the site. The depths of the fills were found to be 14 feet, 14 feet, and 16 feet, within test trenches T-1, T-2, and T-5, respectively. The fills extended deeper than the bottom of our test trenches excavations for T-3, T-4, and T-6 and depth of the fill was found to extend beyond the maximum excavation depth of 18 feet in T-4. The existing fill soils are considered unsuitable, in their present condition, for the support of settlement-sensitive improvements. This condition will require special site preparation, considerations and requirements as described herein. The site is located in an area that is relatively free of geologic hazards that will have a significant effect on the proposed construction. The most likely geologic hazard that could affect the site after development is ground shaking due to seismic activity along one of the regional active faults. However, construction in accordance with the requirements of the most recent edition of the California Building Code and the local governmental agencies should provide a level of life-safety suitable for the type of development proposed. The final project plans should be submitted to this office for review in order to ascertain that the geotechnical recommendations remain applicable to the final plan and that no additional recommendations are needed due to changes in the anticipated development. Additionally, while analysis of the surficial and global stability of the existing rock cliffs is not within our project scope, we do recommend that preventative measures be considered for rock fall potential including proper setbacks, rock fall barriers, fences or drapes. We understand that any required analysis of the gross and surficial stability of the rock cliffs including the potential for rock falls will be performed by others, and that the finding of such analyses will be made available for our review. RECOMMENDATIONS GRADING AND EARTHWORK GENERAL: All grading should conform to the guidelines presented in Appendix J of the California Building Code, the minimum requirements of the City of La Mesa, and the recommended Grading Specifications and Special Provisions attached hereto, except where specifically superseded in the text of this report. Prior to

13 CWE October 7, 2015 Page 8 grading, a representative of Christian Wheeler Engineering should be present at the pre-construction meeting to provide additional grading guidelines, if necessary, and to review the earthwork schedule. OBSERVATION OF GRADING: Continuous observation by the Geotechnical Consultant is essential during the grading operation to confirm conditions anticipated by our investigation, to allow adjustments in design criteria to reflect actual field conditions exposed, and to determine that the grading proceeds in general accordance with the recommendations contained herein. CLEARING AND GRUBBING: Site preparation should begin with the removal of vegetation, debris and other deleterious materials from the site. This should include all significant root material. The resulting materials should be disposed of off-site in a legal dumpsite. SITE PREPARATION: In order to support the proposed apartment structures on conventional shallow foundations, the existing fill materials will need to be removed in their entirety and recompacted. The removals should extend down to the contact with competent metavolcanic rock. Laterally, the removals should extend at least 5 feet outward of the proposed building footprints and associated improvements or equivalent to the depth of the excavation, whichever is greater. The bottom of all excavations should be approved by our project geologist, engineer, or technician supervisor prior to placing fills or constructing improvements. The fill material is expected to have a thickness of about 10 feet to in excess of 18 feet across the project site. DEBRIS: Various concrete, asphalt, metal, and organic debris was encountered within our trenches during our investigation. All debris encountered during grading should be removed from new fill materials and properly disposed of off-site. Concrete debris without protruding rebar may be included in new fill placemntas described in the Oversized Rock Placement section below. OVERSIZED ROCK PLACEMENT: For the purpose of placement in general compacted fill, oversized rock is defined as rock or concrete exceeding 12 inches in maximum dimension. However, for placement within four feet from finish pad grade it is defined as rock or concrete fragments exceeding 6 inches in maximum dimension. For retaining wall and trench backfill use, oversized material is defined as having a maximum dimension of 3 inches. Oversized material should be anticipated throughout the existing fills onsite. Oversized material may be broken into smaller pieces, utilized for landscaping purposes or placed in accordance with the recommendations contained in the Compaction and Method of Filling section of this report, Plate No. 2, or City of La Mesa specifications, whichever are more stringent.

14 CWE October 7, 2015 Page 9 PROCESSING OF FILL AREAS: Prior to placing any new fill soils or constructing any new improvements in areas that have been cleaned out to receive fill and approved by the geotechnical consultant or his representative, any exposed soils should be scarified to a depth of 12 inches, moisture conditioned, and compacted to at least 90 percent relative compaction. COMPACTION AND METHOD OF FILLING: All structural fill and backfill material placed at the site should be compacted to a relative compaction of at least 90 percent of maximum dry density as determined by ASTM Laboratory Test D1557. Fills should be placed at or slightly above optimum moisture content, in lifts six to eight inches thick, with each lift compacted by mechanical means. Fills should consist of approved earth material, free of trash or debris, roots, vegetation, or other materials determined to be unsuitable by our soil technicians or project geologist. Fill material should be free of rocks or lumps of soil in excess of twelve inches in maximum dimension; however, this should be reduced to six inches within four feet of finish grade. All utility trench backfill should be compacted to a minimum of 90 percent of its maximum dry density. The upper twelve inches of subgrade beneath paved areas should be compacted to 95 percent of the materials maximum dry density. This compaction should be obtained by the paving contractor just prior to placing the aggregate base material and should not be part of the mass grading requirements or operation. TEMPORARY CUT SLOPES: Based on the anticipated fill thickness, we anticipate that temporary excavations of up to about 20 feet or greater in depth will be required. Temporary cut slopes up to 25 feet in height can be excavated at an inclination of 1.0 to 1.0 (horizontal to vertical) or flatter. Our firm should be contacted to observe all temporary cut slopes during grading to ascertain that no unforeseen adverse conditions exist. No surcharge loads such as foundation loads, or soil or equipment stockpiles, vehicles, etc. should be allowed within a distance from the top of temporary slopes equal to half the slope height. The contractor is solely responsible for designing and constructing stable, temporary excavations and will need to shore, slope, or bench the sides of trench excavations as required to maintain the stability of the excavation sides. The contractor s competent person, as defined in the OSHA Construction Standards for Excavations, 29 CFR, Part 1926, should evaluate the soil exposed in the excavations as part of the contractor s safety process. Temporary cut slopes should be constructed in accordance with the recommendations presented in this section. In no other case should slope height, slope inclination, or excavation depth, including utility trench excavation depth, exceed those specified in local, state, and federal safety regulations. SURFACE DRAINAGE: The ground around the proposed structures should be graded so that surface water flows rapidly away from the structure without ponding. In general, we suggest that the ground adjacent to

15 CWE October 7, 2015 Page 10 structure slope away at a gradient of at least 2 percent. Densely vegetated areas where runoff can be impaired should have a minimum gradient of 5 percent within the first 5 feet from the structure. In our opinion, the project site is not suitable for storm water infiltration/percolation BMPs. We recommend that pervious pavements, bio retention areas, and bio swales be lined in such a manner as to prevent the storm water from infiltrating into the underlying soils and should be connected via pipes to the storm drain system. GRADING PLAN REVIEW: The final grading plans should be submitted to this office for review in order to ascertain that the geotechnical recommendations remain applicable to the final plan and that no additional recommendations are needed due to changes in the anticipated development. Our firm should be notified of changes to the proposed project that could necessitate revisions of or additions to the information contained herein. CONVENTIONAL SHALLOW FOUNDATIONS GENERAL: Provided the existing fill soils are removed and recompacted as recommended above, the proposed apartment structures and associated improvements may be supported by conventional shallow foundations founded in new compacted fill soil. The following recommendations are considered the minimum based on the anticipated soil conditions and are not intended to be in lieu of structural considerations. All foundations should be designed by a qualified structural engineer. DIMENSIONS: Conventional spread footings supporting the proposed apartment structures should be embedded at least 24 inches below the lowest adjacent finish grade. Continuous footings should have a minimum width of 12 inches for the buildings and 24 inches for retaining walls. Isolated footings should have a minimum width of 24 inches. Foundations with these dimensions can be designed for an allowable soil bearing pressure of 2,000 pounds per square foot. This bearing pressure can be increased by an additional 500 psf and 300 psf for each additional foot of embedment and width, respectively, up to a maximum of 4,000 psf. The allowable bearing capacity may be increased by one-third for combinations of temporary loads, such as those due to wind or seismic loads. Footings located adjacent to slopes should be extended to a depth such that a minimum horizontal distance of 10 feet exists between the bottom, outside edge of the footing and the face of the slope. New spread footings supporting minor at-grade structures such as trash enclosures should be embedded at least 18 inches below the finish pad grade. Continuous and isolated footings should have minimum widths of 12 and 24 inches, respectively. New spread footings supporting site retaining walls should be embedded at least 18 inches below the finish pad grade and should have a minimum width of 24 inches. For these

16 CWE October 7, 2015 Page 11 improvements, footings with the above recommended minimum dimensions may be designed for an allowable soil bearing pressure of 2,000 pounds per square foot. The allowable bearing capacities may be increased by one-third for combinations of temporary loads, such as those due to wind or seismic loads. FOOTING REINFORCING: Reinforcement requirements for conventional foundations should be provided by a structural engineer. However, based on the existing soil conditions, we recommend that the minimum reinforcing for new continuous footings consist of at least two No. 5 bars positioned near the bottom of the footing and at least two No. 5 bars positioned near the top of the footing. LATERAL LOAD RESISTANCE: Lateral loads against foundations may be resisted by friction between the bottom of the footing and the supporting soil, and by the passive pressure against the footing. The coefficient of friction between concrete and soil may be considered to be The passive resistance may be considered to be equal to an equivalent fluid weight of 350 pounds per cubic foot. This assumes the footings are poured tight against undisturbed soil. If a combination of the passive pressure and friction is used, the friction value should be reduced by one-third. SETTLEMENT CHARACTERISTICS: Provided the recommendations presented in this report are followed, the anticipated total and differential foundation settlement is expected to be less than about 1 inch and 1 inch over 40 feet, respectively. It should be recognized that minor cracks normally occur in concrete slabs and foundations due to shrinkage during curing or redistribution of stresses, therefore some cracks should be anticipated. Such cracks are not necessarily an indication of excessive vertical movements. EXPANSIVE CHARACTERISTICS: The foundation soils are expected to have a low expansive potential (EI between 21 and 50). The recommendations presented in this report reflect this condition. FOUNDATION PLAN REVIEW: The final foundation plan and accompanying details and notes should be submitted to this office for review. The intent of our review will be to verify that the plans used for construction reflect the minimum dimensioning and reinforcing criteria presented in this section and that no additional criteria are required due to changes in the foundation type or layout. It is not our intent to review structural plans, notes, details, or calculations to verify that the design engineer has correctly applied the geotechnical design values. It is the responsibility of the design engineer to properly design/specify the foundations and other structural elements based on the requirements of the structure and considering the information presented in this report.

17 CWE October 7, 2015 Page 12 FOUNDATION EXCAVATION OBSERVATION: All foundation excavations should be observed by the geotechnical consultant prior to placing reinforcing steel or formwork in order to determine if the foundation recommendations presented herein are followed. All footing excavations should be excavated neat, level, and square. All loose or unsuitable material should be removed prior to the placement of concrete. ON-GRADE SLABS GENERAL: It is our understanding that the floor system of the proposed apartment structures will consist of concrete slabs-on-grade. The following recommendations are considered the minimum slab requirements based on the soil conditions and are not intended to be in lieu of structural considerations. INTERIOR SLAB: We recommend that the interior slab-on-grade floor be at least 5 inches thick (actual) and be reinforced with at least No. 4 bars spaced at 18 inches on center each way. The reinforcing bars should extend at least 12 inches into the foundations and should be supported by chairs and be positioned in the center of the slab. UNDER-SLAB VAPOR RETARDERS: Steps should be taken to minimize the transmission of moisture vapor from the subsoil through the interior slabs where it can potentially damage the interior floor coverings. Local industry standards typically include the placement of a vapor retarder, such as plastic, in a layer of coarse sand placed directly beneath the concrete slab. Two inches of sand are typically used above and below the plastic, respectively. The vapor retarder should be at least 15-mil Stegowrap or similar material with sealed seams and should extend at least 12 inches down the sides of the interior and perimeter footings. The sand should have a sand equivalent of at least 30, and contain less than 10% passing the Number 100 sieve and less than 5% passing the Number 200 sieve. The membrane should be placed in accordance with the recommendation and consideration of ACI 302, Guide for Concrete Floor and Slab Construction and ASTM E1643, Standards Practice for Installation of Water Vapor Retarder Used in Contact with Earth or Granular Fill Under Concrete Slabs. It is the flooring contractor s responsibility to place floor coverings in accordance with the flooring manufacturer specifications. EXTERIOR CONCRETE FLATWORK: Exterior concrete on-grade slabs should have a minimum thickness of 4 inches and be reinforced with at least No. 3 bars placed at 18 inches on center each way. All slabs should be provided with weakened plane joints in accordance with the American Concrete Institute (ACI) guidelines. Alternative patterns consistent with ACI guidelines can also be used. A concrete mix with a 1-inch maximum aggregate size and a water/cement ratio of less than 0.6 is recommended for exterior slabs.

18 CWE October 7, 2015 Page 13 Lower water content will decrease the potential for shrinkage cracks. Both coarse and fine aggregate should conform to the latest edition of the Standard Specifications for Public Works Construction ( Greenbook ). Special attention should be paid to the method of concrete curing to reduce the potential for excessive shrinkage and resultant random cracking. It should be recognized that minor cracks occur normally in concrete slabs due to shrinkage. Some shrinkage cracks should be expected and are not necessarily an indication of excessive movement or structural distress. EARTH RETAINING WALLS FOUNDATIONS: Foundations for retaining walls can be designed in accordance with the foundation recommendations previously presented. PASSIVE PRESSURES: The passive pressure for the anticipated foundation soils may be considered to be 300 pounds per square foot per foot of depth. The upper foot of embedment should be neglected when calculating passive pressures, unless the foundation abuts a hard surface such as a concrete slab. The passive pressure may be increased by one-third for seismic loading. The coefficient of friction for concrete to soil may be assumed to be 0.30 for the resistance to lateral movement. When combining frictional and passive resistance, the friction should be reduced by one-third. ACTIVE PRESSURES: The active soil pressure for the design of unrestrained earth retaining structures with level backfill surface may be assumed to be equivalent to the pressure of a fluid weighing 40 pounds per cubic foot. In the design of walls restrained from movement at the top (non-yielding walls), the at-rest soil pressure may be assumed to be equivalent to the pressure of a fluid weighing 60 pounds per cubic foot, provided there is a level backfill surface. An additional 15 pounds per cubic foot can be added to the above values for 2:1 (H:V) sloping backfill. Thirty percent of any area surcharge placed adjacent to the retaining wall may be assumed to act as a uniform horizontal pressure against the wall. Special cases such as a combination of shored and sloping temporary slopes, or other surcharge loads not described above, may require an increase in the design values recommended above. These conditions should be evaluated by the project geotechnical engineer on a case-bycase basis. If any other loads are anticipated, the Geotechnical Consultant should be contacted for the necessary increase in soil pressure. All values are based on a drained backfill condition. Seismic lateral earth pressures may be assumed to equal an inverted triangle starting at the bottom of the wall with the maximum pressure equal to 9H pounds per square foot (where H = wall height in feet) occurring at the top of the wall.

19 CWE October 7, 2015 Page 14 WATERPROOFING AND WALL DRAINAGE SYSTEMS: The need for waterproofing should be evaluated by others. If required, the project architect should provide (or coordinate) waterproofing details for the retaining walls. The design values presented above are based on a drained backfill condition and do not consider hydrostatic pressures. Unless hydrostatic pressures are incorporated into the design, the retaining wall designer should provide a detail for a wall drainage system. Typical retaining wall drain system details are presented as Plate No. 3 of this report for informational purposes. Additionally, outlets points for the retaining wall drain system should be coordinated with the project civil engineer. BACKFILL: All retaining wall backfill should be compacted to at least 90 percent relative compaction. Expansive or clayey soils should not be used for backfill material. Retaining walls should not be backfilled until the masonry/concrete has reached an adequate strength. PRELIMINARY PAVEMENT SECTIONS GENERAL: We expect that new pavement will be installed for new access driveways and parking areas leading to the proposed apartment structures. The following presents preliminary sections for asphalt concrete (AC) or Portland Cement Concrete (PCC) construction. The pavement sections provided in Table II and Table IV should be considered preliminary and should be used for planning purposes only. Final pavement designs should be determined after R-value tests have been performed in the actual subgrade material in place after grading. Presuming the grading recommendations presented previously are followed, we have assumed a subgrade R-Value of 25 for preliminary planning purposes. The Traffic Index and Traffic Categories shown below are also assumed. The client and/or project civil engineer should determine whether these assumed values are appropriate for the traffic conditions. PRELIMINARY ASPHALT CONCRETE PAVEMENTS: We expect that new streets and driveways will primarily support passenger vehicles with only occasional heavily loaded vehicles. The preliminary asphalt concrete pavement sections were calculated using the Caltrans design method using an assumed Traffic Index of 6.0 and 4.5 for driveways and parking areas, respectively. TABLE II: PRELIMINARY ASPHALT CONCRETE PAVEMENT SECTION Traffic Pavement Base Base Subgrade Pavement Type Index Thickness Thickness Material Compaction Asphalt Concrete Main Driveways in. 9.5 in. CAB or Class II 95% in upper 12 Parking Areas in. 5.0 in. CAB or Class II 95% in upper 12

20 CWE October 7, 2015 Page 15 Prior to placing the base material beneath asphalt concrete pavements, the subgrade soil should be scarified to a depth of 12 inches and compacted to at least 95 percent of its maximum dry density at a moisture content one to three percent above optimum. The base material could consist of Class II Aggregate Base. The Class II Aggregate Base should conform to requirements set forth in Section 26 of the Standard Specifications for California Department of Transportation. As an alternate, the base material for the pavements may consist of Crushed Miscellaneous Base (recycled base material) which conforms to the requirements set forth in Section of the Standard Specifications for Public Works Construction. It should be noted, however, that Crushed Miscellaneous Base material has lower durability characteristics than Crushed Aggregate Base or Class II Aggregate Base, which may result in a shorter pavement life. As such, the owner of the project should approve the use of this material for the pavement base. All aggregate base material should be compacted to at least 95 percent of its maximum dry density as determined by ASTM Test D1557. Asphalt concrete shall be compacted to attain at least 95 percent relative compaction. CONCRETE PAVEMENTS: Portland cement concrete (PCC) pavement thickness can be determined from Table IV below. The PCC pavement section was determined in general accordance with the procedure recommended within the American Concrete Institute report ACI-330R-08 Guide for Design and Construction of Concrete Parking Lots using the parameters listed in following Table III. TABLE III: CONCRETE PAVEMENT DESIGN PARAMETERS Design Parameter Design Value Modulus of Subgrade Reaction, k 125 pci Modulus of Rupture for Concrete, M R 500 psi Traffic Category (Main Driveways) A (ADTT = 25) ADTT = Average Daily Truck Traffic. Trucks defined as vehicles with at least six wheels. Based on the design parameters summarized in Table III, the PCC pavements should have the minimum thicknesses shown in Table IV. TABLE IV: MINIMUM CONCRETE PAVEMENT THICKNESS Pavement Use Main Driveway Parking Areas Thickness 6.0 in. 5.0 in.

21 CWE October 7, 2015 Page 16 Prior to placing concrete pavement, the subgrade soils should be scarified to a depth of 12 inches and compacted to at least 90 percent of their maximum dry density at a moisture content one to three percent above optimum. Concrete pavement construction should comply with the requirements set forth in Sections and of the Standard Specifications for Public Works Construction (concrete Class 560-C- 3250). Portland Cement Concrete slabs are recommended in front of each trash enclosures. These slabs should have a minimum thickness of 7.0 inches of concrete and should be underlain by at least 4 inches of base and minimum slab reinforcement should consist of at least No. 4 bars placed at 16 inches on center each way. A similar concrete section may be used inside the enclosures. Concrete slab construction should comply with the requirements set forth in Sections and of the Standard Specifications for Public Works Construction. The concrete materials should be a Class 560-C-3250 mix. All slabs should be provided with weakened plane joints in accordance with the American Concrete Institute (ACI) guidelines. Special attention should be paid to the method of concrete curing to reduce the potential for excessive shrinkage cracking. It should be recognized that minor cracks occur normally in concrete slabs due to shrinkage. Some shrinkage cracks should be expected and are not necessarily an indication of excessive movement or structural distress. LIMITATIONS REVIEW, OBSERVATION AND TESTING The recommendations presented in this report are contingent upon our review of final plans and specifications. Such plans and specifications should be made available to the geotechnical engineer and engineering geologist so that they may review and verify their compliance with this report and with the California Building Code. It is recommended that Christian Wheeler Engineering be retained to provide continuous soil engineering services during the earthwork operations. This is to verify compliance with the design concepts, specifications or recommendations and to allow design changes in the event that subsurface conditions differ from those anticipated prior to start of construction. UNIFORMITY OF CONDITIONS The recommendations and opinions expressed in this report reflect our best estimate of the project requirements based on an evaluation of the subsurface soil conditions encountered at the subsurface exploration locations and on the assumption that the soil conditions do not deviate appreciably from those encountered. It should be

22 CWE October 7, 2015 Page 17 recognized that the performance of the foundations and/or cut and fill slopes may be influenced by undisclosed or unforeseen variations in the soil conditions that may occur in the intermediate and unexplored areas. Any unusual conditions not covered in this report that may be encountered during site development should be brought to the attention of the geotechnical engineer so that he may make modifications if necessary. CHANGE IN SCOPE This office should be advised of any changes in the project scope or proposed site grading so that we may determine if the recommendations contained herein are appropriate. This should be verified in writing or modified by a written addendum. TIME LIMITATIONS The findings of this report are valid as of this date. Changes in the condition of a property can, however, occur with the passage of time, whether they be due to natural processes or the work of man on this or adjacent properties. In addition, changes in the Standards-of-Practice and/or Government Codes may occur. Due to such changes, the findings of this report may be invalidated wholly or in part by changes beyond our control. Therefore, this report should not be relied upon after a period of two years without a review by us verifying the suitability of the conclusions and recommendations. PROFESSIONAL STANDARD In the performance of our professional services, we comply with that level of care and skill ordinarily exercised by members of our profession currently practicing under similar conditions and in the same locality. The client recognizes that subsurface conditions may vary from those encountered at the locations where our test pits, surveys, and explorations are made, and that our data, interpretations, and recommendations be based solely on the information obtained by us. We will be responsible for those data, interpretations, and recommendations, but shall not be responsible for the interpretations by others of the information developed. Our services consist of professional consultation and observation only, and no warranty of any kind whatsoever, express or implied, is made or intended in connection with the work performed or to be performed by us, or by our proposal for consulting or other services, or by our furnishing of oral or written reports or findings.

23 CWE October 7, 2015 Page 18 CLIENT'S RESPONSIBILITY It is the client s responsibility, or its representatives, to ensure that the information and recommendations contained herein are brought to the attention of the structural engineer and architect for the project and incorporated into the project's plans and specifications. It is further their responsibility to take the necessary measures to insure that the contractor and his subcontractors carry out such recommendations during construction. FIELD EXPLORATIONS Six subsurface explorations were made at the locations indicated on the Site Plan included herewith as Plate Number 1 on July 31, These explorations consisted of six trenches excavated by a Case 580L backhoe equipped with an 18-inch bucket. The fieldwork was conducted under the observation of our engineering geology personnel. The explorations were carefully logged when made. The trench logs are presented within Appendix A. The soils are described in accordance with the Unified Soils Classification System. In addition, a verbal textural description, the wet color, the apparent moisture and the density or consistency are provided. The density of granular soils is given as very loose, loose, medium dense, dense or very dense. The consistency of silts or clays is given as either very soft, soft, medium stiff, stiff, very stiff, or hard. LABORATORY TESTING Laboratory tests were performed in accordance with the generally accepted American Society for Testing and Materials (ASTM) test methods or suggested procedures. A brief description of the tests performed is presented in Appendix B.

24 T-1 Qaf Mzu T-3 T-2 Qaf Mzu T-6 T-5 T-4 Qaf Mzu 0 100' 200' SCALE: 1" = 100' CWE LEGEND T-6 APPROXIMATE TEST TRENCH LOCATION Qaf Mzu ARTIFICIAL FILL UNDERLAIN BY METAMORPHOSED VOLCANIC ROCK SITE PLAN AND GEOTECHNICAL MAP DATE: OCTOBER 2015 BY: SRD PROPOSED HIGH STREET APARTMENTS A.P.N.'S & HIGH STREET, LA MESA, CALIFORNIA JOB NO.: PLATE NO.: 1 CHRISTIAN WHEELER E N G I N E E R I N G

IV. ENVIRONMENTAL IMPACT ANALYSIS G. GEOLOGY AND SOILS

IV. ENVIRONMENTAL IMPACT ANALYSIS G. GEOLOGY AND SOILS IV. ENVIRONMENTAL IMPACT ANALYSIS G. GEOLOGY AND SOILS The following section is a summary of the geotechnical report conducted for the proposed project. The Report of Geotechnical Investigation Proposed

More information

CHRISTIAN WHEELER E N G I N E E R I N G

CHRISTIAN WHEELER E N G I N E E R I N G CHRISTIAN WHEELER E N G I N E E R I N G REPORT OF GEOTECHNICAL INVESTIGATION PROPOSED FOUNDATION UNDERPINNING SMOKETREE CONDOMINIUMS, BUILDINGS 8 AND 9 6050 HENDERSON DRIVE LA MESA, CALIFORNIA SUBMITTED

More information

CHRISTIAN WHEELER E N G I N E E R I N G

CHRISTIAN WHEELER E N G I N E E R I N G CHRISTIAN WHEELER E N G I N E E R I N G REPORT OF PRELIMINARY GEOTECHNICAL INVESTIGATION PROPOSED SOLTYS RESIDENCE 56 LA GLORIETA RANCHO SANTA FE, CALIFORNIA PREPARED FOR ROBERT AND MICHELLE SOLTYS 038

More information

Guidelines for Site-Specific Seismic Hazard Reports for Essential and Hazardous Facilities and Major and Special-Occupancy Structures in Oregon

Guidelines for Site-Specific Seismic Hazard Reports for Essential and Hazardous Facilities and Major and Special-Occupancy Structures in Oregon Guidelines for Site-Specific Seismic Hazard Reports for Essential and Hazardous Facilities and Major and Special-Occupancy Structures in Oregon By the Oregon Board of Geologist Examiners and the Oregon

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS E. GEOLOGY AND SOILS

IV. ENVIRONMENTAL IMPACT ANALYSIS E. GEOLOGY AND SOILS IV. ENVIRONMENTAL IMPACT ANALYSIS E. GEOLOGY AND SOILS The following section is a summary of the geotechnical report conducted for the Proposed Project. The Geotechnical Engineering Investigation (the

More information

SLOPE STABILITY EVALUATION AND ACCEPTANCE STANDARDS

SLOPE STABILITY EVALUATION AND ACCEPTANCE STANDARDS INFORMATION BULLETIN / PUBLIC - BUILDING CODE REFERENCE NO.: LAMC 98.0508 Effective: 1-26-84 DOCUMENT NO. P/BC 2002-049 Revised: 11-1-02 Previously Issued As: RGA #1-84 SLOPE STABILITY EVALUATION AND ACCEPTANCE

More information

CHAPTER GEOLOGICALLY HAZARDOUS AREAS Applicability Regulations.

CHAPTER GEOLOGICALLY HAZARDOUS AREAS Applicability Regulations. CHAPTER 19.07 GEOLOGICALLY HAZARDOUS AREAS 19.07.010 Applicability. Geologically hazardous areas may pose a threat to the health and safety of citizens when incompatible development is sited in areas of

More information

Geotechnical Engineering Study, Conifer Senior High School Football Field Improvements, Conifer, Colorado

Geotechnical Engineering Study, Conifer Senior High School Football Field Improvements, Conifer, Colorado 2390 South Lipan Street Denver, CO 80223 phone: (303) 742-9700 fax: (303) 742-9666 email: kadenver@kumarusa.com www.kumarusa.com Office Locations: Denver (HQ), Colorado Springs, Fort Collins, and Frisco,

More information

SLOPE STABILITY EVALUATION AND ACCEPTANCE STANDARDS

SLOPE STABILITY EVALUATION AND ACCEPTANCE STANDARDS INFORMATION BULLETIN / PUBLIC - BUILDING CODE REFERENCE NO.: LABC 7006.3, 7014.1 Effective: 01-01-2017 DOCUMENT NO.: P/BC 2017-049 Revised: 12-21-2016 Previously Issued As: P/BC 2014-049 SLOPE STABILITY

More information

3.0 SUMMARY OF POTENTIAL GEOTECHNICAL IMPACTS AND MITIGATION MEASURES

3.0 SUMMARY OF POTENTIAL GEOTECHNICAL IMPACTS AND MITIGATION MEASURES 3.0 SUMMARY OF POTENTIAL GEOTECHNICAL IMPACTS AND MITIGATION MEASURES This section summarizes the principal geotechnical conditions that occur in the project area. The potential impact that each condition

More information

Impact : Changes to Existing Topography (Less than Significant)

Impact : Changes to Existing Topography (Less than Significant) 4.2 Land Resources 4.2.1 Alternative A Proposed Action Impact 4.2.1-1: Changes to Existing Topography (Less than Significant) Development of the project site would involve grading and other earthwork as

More information

ATTACHMENT A PRELIMINARY GEOTECHNICAL SUMMARY

ATTACHMENT A PRELIMINARY GEOTECHNICAL SUMMARY ATTACHMENT A PRELIMINARY GEOTECHNICAL SUMMARY Kevin M. Martin, P.E. KMM Geotechnical Consultants, LLC 7 Marshall Road Hampstead, NH 0384 603-489-6 (p)/ 603-489-8 (f)/78-78-4084(m) kevinmartinpe@aol.com

More information

R-1 Conveyor Relocation Project Legend 0 500 1000 1500 ft. This map is a user generated static output from an Internet mapping site and is for general reference only. Data layers that appear on this map

More information

GEOLOGY AND SOILS. This chapter summarizes geologic and geotechnical aspects of the site as they relate to the Project.

GEOLOGY AND SOILS. This chapter summarizes geologic and geotechnical aspects of the site as they relate to the Project. 9 GEOLOGY AND SOILS INTRODUCTION This chapter summarizes geologic and geotechnical aspects of the site as they relate to the Project. This chapter utilizes information from the following reports prepared

More information

Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services

Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services Ms. Rebecca Mitchell Mt. San Antonio College Facilities Planning & Management 1100 North

More information

Should you have any questions regarding this clarification, please contact the undersigned at or (925)

Should you have any questions regarding this clarification, please contact the undersigned at or (925) October 8, 2015 Revised October 13, 2015 Contra Costa Community College District 500 Court Street Martinez, CA 94553 Attention: Ron Johnson Subject: Clarification of Grading Requirements Diablo Valley

More information

SUPPLEMENTARY INVESTIGATION AND LABORATORY TESTING Aggregate Resource Evaluation Proposed Bernand Quarry San Diego County, California

SUPPLEMENTARY INVESTIGATION AND LABORATORY TESTING Aggregate Resource Evaluation Proposed Bernand Quarry San Diego County, California October 3, 2 Mr. Mark San Agustin Project No. 28-- Home Land Investments Document No. -92 2239 Curlew Street San Diego, CA 92 SUBJECT: SUPPLEMENTARY INVESTIGATION AND LABORATORY TESTING Aggregate Resource

More information

Geotechnical Evaluation

Geotechnical Evaluation Geotechnical Evaluation Neighborhood No. 1 Sewer Pump Station Replacement 16106 4S Ranch Parkway San Diego, California Infrastructure Engineering Corporation 14271 Danielson Street San Diego, California

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS E. GEOLOGY AND SOILS

IV. ENVIRONMENTAL IMPACT ANALYSIS E. GEOLOGY AND SOILS IV. ENVIRONMENTAL IMPACT ANALYSIS E. GEOLOGY AND SOILS The following analysis is based on the Geotechnical Investigation Report, Proposed Mid-Rise Multi- Family Residential Development Project Wetherly

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS E. GEOLOGY/SOILS

IV. ENVIRONMENTAL IMPACT ANALYSIS E. GEOLOGY/SOILS IV. ENVIRONMENTAL IMPACT ANALYSIS E. GEOLOGY/SOILS Except where otherwise noted, the following Section is based on the Preliminary Geotechnical Investigation, Proposed Medical Office Buildings and Mixed-Use

More information

COMMUNITY DEVELOPMENT DEPARTMENT POLICY & PROCEDURE

COMMUNITY DEVELOPMENT DEPARTMENT POLICY & PROCEDURE COMMUNITY DEVELOPMENT DEPARTMENT POLICY & PROCEDURE Policy No: DSP-OO3 Release Date: January 1, 2014 Effective Date: January 1, 2014 Revision Date: March 1, 2018 TITLE: The City Policy for Site Specific

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS E. GEOLOGY/SOILS

IV. ENVIRONMENTAL IMPACT ANALYSIS E. GEOLOGY/SOILS IV. ENVIRONMENTAL IMPACT ANALYSIS E. GEOLOGY/SOILS The following discussion is based upon information contained in the Hollywood Redevelopment Plan Amendment EIR and a letter prepared by Geotechnologies,

More information

ENVIRONMENTAL IMPACT ANALYSIS C. GEOLOGY AND SOILS

ENVIRONMENTAL IMPACT ANALYSIS C. GEOLOGY AND SOILS IV. ENVIRONMENTAL IMPACT ANALYSIS The following analysis of geology, soils and seismic hazards is based primarily upon the technical report Geotechnical Engineering Investigation Proposed Fashion Square

More information

Appendix C - Geotechnical Report. Landmark Consultants, Inc.

Appendix C - Geotechnical Report. Landmark Consultants, Inc. Appendix C - Geotechnical Report Landmark Consultants, Inc. LCI Report No. LP18128 Fault Map Regional Review of the current Alquist-Priolo Earthquake Fault Zone maps (CGS, 2000a) indicates that

More information

GEOTECHNICAL INVESTIGATION FUTURE ATHLETIC COMPLEX AT PALOMAR COLLEGE 1140 WEST MISSION ROAD SAN MARCOS, CALIFORNIA. Prepared for:

GEOTECHNICAL INVESTIGATION FUTURE ATHLETIC COMPLEX AT PALOMAR COLLEGE 1140 WEST MISSION ROAD SAN MARCOS, CALIFORNIA. Prepared for: GEOTECHNICAL INVESTIGATION FUTURE ATHLETIC COMPLEX AT PALOMAR COLLEGE 1140 WEST MISSION ROAD SAN MARCOS, CALIFORNIA Prepared for: PALOMAR COMMUNITY COLLEGE DISTRICT 1140 WEST MISSION ROAD SAN MARCOS, CALIFORNIA

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS E. GEOLOGY AND SOILS

IV. ENVIRONMENTAL IMPACT ANALYSIS E. GEOLOGY AND SOILS IV. ENVIRONMENTAL IMPACT ANALYSIS E. GEOLOGY AND SOILS INTRODUCTION This section evaluates potential impacts related to geology, including seismicity, and soils associated with development of the proposed

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS E. GEOLOGY/SEISMIC HAZARDS

IV. ENVIRONMENTAL IMPACT ANALYSIS E. GEOLOGY/SEISMIC HAZARDS IV. ENVIRONMENTAL IMPACT ANALYSIS E. GEOLOGY/SEISMIC HAZARDS 1. ENVIRONMENTAL SETTING The following analysis of geology and seismic hazards for the Middle School Project is based on the Report of Geotechnical

More information

3.1.3 Geology and Soils

3.1.3 Geology and Soils 3.1.3 Geology and Soils This section addresses the potential geology and soils impacts associated with implementation of The Villages Escondido Country Club Project (Project). The section describes the

More information

REPORT OF SUBSURFACE INVESTIGATION AND GEOTECHNICAL EVALUATION POTABLE WATER STORAGE TANK REPLACEMENT EL CAPITAN STATE PARK, CALIFORNIA.

REPORT OF SUBSURFACE INVESTIGATION AND GEOTECHNICAL EVALUATION POTABLE WATER STORAGE TANK REPLACEMENT EL CAPITAN STATE PARK, CALIFORNIA. REPORT OF SUBSURFACE INVESTIGATION AND GEOTECHNICAL EVALUATION POTABLE WATER STORAGE TANK REPLACEMENT EL CAPITAN STATE PARK, CALIFORNIA prepared for Winzler & Kelly Consulting Engineers 4180 Ruffin Road,

More information

Appendix B. Geotechnical Investigation

Appendix B. Geotechnical Investigation Appendix B Geotechnical Investigation PRELIMINARY GEOTECHNICAL INVESTIGATION PROPOSED REGAL CINEMAS WESTFIELD NORTH COUNTY SHOPPING CENTER ESCONDIDO, CALIFORNIA Prepared for: WESTFIELD, LLC 2049 Century

More information

4.5 GEOLOGY AND SOILS

4.5 GEOLOGY AND SOILS 4.5 GEOLOGY AND SOILS This section addresses the project site geology and soils and analyzes potential changes that would result from development of the Wye Specific Plan project. 4.5.1 Environmental Setting

More information

Geotechnical Geologic Coastal Environmental

Geotechnical Geologic Coastal Environmental Geotechnical Geologic Coastal Environmental 26590 Madison Avenue Murrieta, California 92562 (951) 677-9651 FAX (951) 677-9301 www.geosoilsinc.com April 22, 2014 c/o Matthew Fagan Consulting Services 42011

More information

NOA ASSESSMENT HARRIS QUARRY MENDOCINO COUNTY, CALIFORNIA TABLE OF CONTENTS

NOA ASSESSMENT HARRIS QUARRY MENDOCINO COUNTY, CALIFORNIA TABLE OF CONTENTS NOA ASSESSMENT HARRIS QUARRY MENDOCINO COUNTY, CALIFORNIA TABLE OF CONTENTS Introduction... 1 Scope of Services... 1 Project Location and Description... 1 Geologic Setting... 1 Regional Geology... 1 Site

More information

GEOTECHNICAL EVALUATION ESA SECONDARY CONNECTION PROJECT LAKESIDE, CALIFORNIA PDMWD JN

GEOTECHNICAL EVALUATION ESA SECONDARY CONNECTION PROJECT LAKESIDE, CALIFORNIA PDMWD JN GEOTECHNICAL EVALUATION ESA SECONDARY CONNECTION PROJECT LAKESIDE, CALIFORNIA PDMWD JN 214007 PREPARED FOR: RBF Consulting 9755 Clairemont Mesa Boulevard, Suite 100 San Diego, California 92124 PREPARED

More information

GEOLOGY, SOILS, AND SEISMICITY

GEOLOGY, SOILS, AND SEISMICITY 4.9 GEOLOGY, SOILS, AND SEISMICITY 4.9.1 Introduction Information about the geological conditions and seismic hazards in the study area was summarized in the FEIR, and was based on the Geotechnical Exploration

More information

Geotechnical Investigation Report

Geotechnical Investigation Report Geotechnical Investigation Report El Centro Aquatic Center Adams Avenue to Park Avenue and 4 th Street to 6 th Street El Centro, California Prepared for: Kimley-Horn and Associates, Inc. 401 B Street,

More information

GEOTECHNICAL EVALUATION CHAPEL HILLS WATER CAMPUS MALLARD DRIVE AND STATE ROUTE 179 SEDONA, ARIZONA

GEOTECHNICAL EVALUATION CHAPEL HILLS WATER CAMPUS MALLARD DRIVE AND STATE ROUTE 179 SEDONA, ARIZONA GEOTECHNICAL EVALUATION CHAPEL HILLS WATER CAMPUS MALLARD DRIVE AND STATE ROUTE 179 SEDONA, ARIZONA PREPARED FOR: Arizona Water Company 7580 North Dobson Road, Suite 200 Scottsdale, Arizona 85256 PREPARED

More information

5.5 Geology and Soils

5.5 Geology and Soils 5.5 Geology and Soils The analysis in this section of the EIR addresses the potential impacts associated with geology and soils that may occur due to implementation of the proposed Collier Park Renovations

More information

5.11 Geology and Soils

5.11 Geology and Soils 5.11 Geology and Soils 5.11 GEOLOGY AND SOILS This section evaluates the geologic and seismic conditions within the City of Azusa and evaluates the potential for geologic hazard impacts associated with

More information

Geology, Soils, and Seismicity

Geology, Soils, and Seismicity Section 3.8 Geology, Soils, and Seismicity Introduction This section generally evaluates the effects of the alternatives analyzed in this Supplemental DEIS with regard to geology, soils and seismicity.

More information

TCMC Parking Structure and Main Entry 06/12/2018 ADDENDUM #1. The following items are issued as part of this Addendum:

TCMC Parking Structure and Main Entry 06/12/2018 ADDENDUM #1. The following items are issued as part of this Addendum: TCMC Parking Structure and Main Entry 06/12/2018 ADDENDUM #1 The following items are issued as part of this Addendum: 1. The RFI deadline has been changed to June 18, 2018 at 5 P.M. 2. The project bid

More information

Date: April 2, 2014 Project No.: Prepared For: Mr. Adam Kates CLASSIC COMMUNITIES 1068 E. Meadow Circle Palo Alto, California 94303

Date: April 2, 2014 Project No.: Prepared For: Mr. Adam Kates CLASSIC COMMUNITIES 1068 E. Meadow Circle Palo Alto, California 94303 City of Newark - 36120 Ruschin Drive Project Draft Initial Study/Mitigated Negative Declaration Appendix C: Geologic Information FirstCarbon Solutions H:\Client (PN-JN)\4554\45540001\ISMND\45540001 36120

More information

Background. Valley fills Sites in the Area. Construction over Mine Spoil Fills

Background. Valley fills Sites in the Area. Construction over Mine Spoil Fills Construction over Mine Spoil Fills Wayne A. Karem, PhD, PE, PG, D.GE 2014 KSPE Annual Conference Background Strip mining; mountaintop and contour mining Creates huge quantities of mine spoil The mine spoil

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS E. GEOLOGY AND SOILS

IV. ENVIRONMENTAL IMPACT ANALYSIS E. GEOLOGY AND SOILS IV. ENVIRONMENTAL IMPACT ANALYSIS E. GEOLOGY AND SOILS INTRODUCTION This section of the (Draft EIR) evaluates potential geology and soils impacts associated with development of the proposed (proposed Project

More information

ENGINEER S CERTIFICATION OF FAULT AREA DEMONSTRATION (40 CFR )

ENGINEER S CERTIFICATION OF FAULT AREA DEMONSTRATION (40 CFR ) PLATTE RIVER POWER AUTHORITY RAWHIDE ENERGY STATION BOTTOM ASH TRANSFER (BAT) IMPOUNDMENTS LARIMER COUNTY, CO ENGINEER S CERTIFICATION OF FAULT AREA DEMONSTRATION (40 CFR 257.62) FOR COAL COMBUSTION RESIDUALS

More information

REPORT OF PRELIMINARY GEOTECHNICAL EXPLORATION

REPORT OF PRELIMINARY GEOTECHNICAL EXPLORATION REPORT OF PRELIMINARY GEOTECHNICAL EXPLORATION ENKA INTERMEDIATE SCHOOL Sand Hill Road Candler, North Carolina Prepared For: BUNCOMBE COUNTY SCHOOLS Prepared By: AMEC ENVIRONMENT & INFRASTRUCTURE, INC.

More information

TABLE OF CONTENTS /FLD7R Kleinfelder

TABLE OF CONTENTS /FLD7R Kleinfelder TABLE OF CONTENTS CHAPTER PAGE 1 INTRODUCTION 1 1.1 Proposed Construction 1 1.2 Purpose and Scope of Services 2 1.2.1 Geologic and Seismic Hazards 2 1.2.2 Geotechnical Engineering Exploration 3 2 SITE

More information

Preliminary Geotechnical Evaluation Gooseberry Point Pedestrian Improvements Whatcom County, Washington SITE AND PROJECT DESCRIPTION

Preliminary Geotechnical Evaluation Gooseberry Point Pedestrian Improvements Whatcom County, Washington SITE AND PROJECT DESCRIPTION File No. 12-100 Geotechnical & Earthquake Engineering Consultants Mr. Kevin Brown, P.E. Gray & Osborne, Inc. 3710 168 th Street NE, Suite B210 Arlington, Washington 98223 Subject: Draft Report Preliminary

More information

GEOTECHNICAL ENGINEERING II. Subject Code : 06CV64 Internal Assessment Marks : 25 PART A UNIT 1

GEOTECHNICAL ENGINEERING II. Subject Code : 06CV64 Internal Assessment Marks : 25 PART A UNIT 1 GEOTECHNICAL ENGINEERING II Subject Code : 06CV64 Internal Assessment Marks : 25 PART A UNIT 1 1. SUBSURFACE EXPLORATION 1.1 Importance, Exploration Program 1.2 Methods of exploration, Boring, Sounding

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS C. GEOLOGY/SOILS

IV. ENVIRONMENTAL IMPACT ANALYSIS C. GEOLOGY/SOILS IV. ENVIRONMENTAL IMPACT ANALYSIS C. GEOLOGY/SOILS The following section is a summary of the preliminary geotechnical consultation conducted for the Proposed Project. The Report of Geotechnical Engineering

More information

REPORT OF GEOTECHNICAL INVESTIGATION CUYAMACA COLLEGE BUILDING H RENOVATION EL CAJON, CALIFORNIA. Prepared for

REPORT OF GEOTECHNICAL INVESTIGATION CUYAMACA COLLEGE BUILDING H RENOVATION EL CAJON, CALIFORNIA. Prepared for REPORT OF GEOTECHNICAL INVESTIGATION CUYAMACA COLLEGE BUILDING H RENOVATION EL CAJON, CALIFORNIA Prepared for GROSSMONT-CUYAMACA COMMUNITY COLLEGE DISTRICT GAFCON Campus Project Manager 900 Rancho San

More information

Roy Pyle March 24, 2017 Chief Facilities Planner Contra Costa Community College District 500 North Court Street Martinez, CA 94533

Roy Pyle March 24, 2017 Chief Facilities Planner Contra Costa Community College District 500 North Court Street Martinez, CA 94533 State of California Natural Resources Agency Edmund G. Brown Jr., Governor Department of Conservation John G. Parrish, Ph.D., State Geologist California Geological Survey 801 K Street MS 12-31 Sacramento,

More information

Northern Colorado Geotech

Northern Colorado Geotech PRELIMINARY GEOTECHNICAL ENGINEERING REPORT PROPOSED CECIL FARMS DEVELOPMENT WELD COUNTY ROAD 7, BETWEEN ROADS 7 AND 7 SEVERANCE, COLORADO NORTHERN COLORADO GEOTECH PROJECT NO. 0-6 APRIL 0, 06 Prepared

More information

APPENDIX D. Geotechnical Report

APPENDIX D. Geotechnical Report APPENDIX D Geotechnical Report Geotechnical Engineering Engineering Geology Geotechnical Engineering Report Texonia Park Apartments Redlands, California Prepared for: A Community of Friends 3701 Wilshire

More information

9. GEOLOGY, SOILS, AND MINERALS

9. GEOLOGY, SOILS, AND MINERALS June 28, 2018 Page 9-1 9. GEOLOGY, SOILS, AND MINERALS This EIR chapter describes the existing geological, soil, and mineral conditions in the planning area. The chapter includes the regulatory framework

More information

An Introduction to Field Explorations for Foundations

An Introduction to Field Explorations for Foundations An Introduction to Field Explorations for Foundations J. Paul Guyer, P.E., R.A. Paul Guyer is a registered mechanical engineer, civil engineer, fire protection engineer and architect with over 35 years

More information

4.5 GEOLOGY AND SOILS

4.5 GEOLOGY AND SOILS 4.5 GEOLOGY AND SOILS This section discusses the proposed project s potential impacts relating to geologic hazards. This section is partially based on the Preliminary Soil Engineering and Geologic Hazards

More information

J.H. Campbell Generating Facility Pond A - Location Restriction Certification Report

J.H. Campbell Generating Facility Pond A - Location Restriction Certification Report J.H. Campbell Generating Facility Pond A - Location Restriction Certification Report Pursuant to: 40 CFR 257.60 40 CFR 257.61 40 CFR 257.62 40 CFR 257.63 40 CFR 257.64 Submitted to: Consumers Energy Company

More information

GEOTECHNICAL INVESTIGATION VEHICLE WASH FACILITY OCEANO DUNES STATE VEHICLE RECREATION AREA

GEOTECHNICAL INVESTIGATION VEHICLE WASH FACILITY OCEANO DUNES STATE VEHICLE RECREATION AREA GEOTECHNICAL INVESTIGATION VEHICLE WASH FACILITY OCEANO DUNES STATE VEHICLE RECREATION AREA PREPARED FOR CALIFORNIA NORTHERN SERVICE CENTER ONE CAPITOL MALL SUITE 500 SACRAMENTO, CALIFORNIA 95814 GEOCON

More information

Construction Exits Rock pads

Construction Exits Rock pads Construction Exits Rock pads SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow [1] Clayey Soils Type 3 System Supplementary Trap Dispersive Soils [1] Minor

More information

GEOTECHNICAL INVESTIGATION

GEOTECHNICAL INVESTIGATION GEOTECHNICAL INVESTIGATION Soquel Drive, Santa Cruz County, California Submitted to: Soquel Creek Water District P.O. Box 1550 Capitola, California 95010 Prepared by: CMAG ENGINEERING, INC. August 23,

More information

Photo 1 - Southerly view across 2700 parking lot toward existing building. Multi-residential building borders western side of property in upper right of view. Photo 2 - Southerly view across 2750 parking

More information

Setting MOUNTAIN HOUSE NEIGHBORHOODS I AND J INITIAL STUDY 5. ENVIRONMENTAL CHECKLIST 6. GEOLOGY AND SOILS. Issue

Setting MOUNTAIN HOUSE NEIGHBORHOODS I AND J INITIAL STUDY 5. ENVIRONMENTAL CHECKLIST 6. GEOLOGY AND SOILS. Issue Issue Less Than Significant or No Impact Potential Significant Impact Adequately Addressed in MEIR MEIR Required Additional Review: No Significant Impact Less Than Significant Impact Due to Mitigation

More information

4.9 GEOLOGY AND SOILS

4.9 GEOLOGY AND SOILS 4.9 GEOLOGY AND SOILS 4.9.1 EXISTING CONDITIONS TOPOGRAPHY AND RELIEF Zone 40 is located in the central portion of Sacramento County. The topography of the county is represented by three physiographic

More information

COMMUNITY DEVELOPMENT DEPARTMENT POLICY & PROCEDURE

COMMUNITY DEVELOPMENT DEPARTMENT POLICY & PROCEDURE COMMUNITY DEVELOPMENT DEPARTMENT POLICY & PROCEDURE Policy No: DSP-OO3 Release Date: January 1, 2014 Effective Date: January 1, 2014 Revision Date: March 1, 2018 TITLE: The City Policy for Site Specific

More information

4.5 GEOLOGY AND SOILS

4.5 GEOLOGY AND SOILS 4.5 GEOLOGY AND SOILS This section discusses the Project s potential impacts relating to geologic hazards. This section is partially based on the Geotechnical Engineering Report included in Appendix E.

More information

COMMUNITY DEVELOPMENT DEPARTMENT POLICY & PROCEDURE

COMMUNITY DEVELOPMENT DEPARTMENT POLICY & PROCEDURE COMMUNITY DEVELOPMENT DEPARTMENT POLICY & PROCEDURE Policy No: DSP-OO3 Release Date: January 1, 2014 Effective Date: January 1, 2014 Revision Date: July 1, 2018 TITLE: The City Policy for Site-Specific

More information

Implementation of the Alquist-Priolo Earthquake Fault Zoning Act in Los Angeles County

Implementation of the Alquist-Priolo Earthquake Fault Zoning Act in Los Angeles County Implementation of the Alquist-Priolo Earthquake Fault Zoning Act in Los Angeles County Charles Nestle County of Los Angeles Dept. of Public Works Surface Fault Rupture Workshop May 10, 2013 What Work is

More information

3.18 GEOLOGY AND SOILS

3.18 GEOLOGY AND SOILS 3.18 GEOLOGY AND SOILS This section discusses geologic resource concerns as they relate to the environment, public safety, and project design both during construction and after completion of the project.

More information

F_._G_. _.E_._,_L_T_D_ ~-11'-~~L ~

F_._G_. _.E_._,_L_T_D_ ~-11'-~~L ~ : e 99o'3 (} rr WtR!'~ _;, F G E,_L_T_D_ ~11'~~L ~ Fewell Geotechhicai Engineering, Ltd 3 2825 Koapaka St Honolulu, Hawaii 96819 (88) 8362171 {/~ ' File No 328,1 October 29, 198 Mr Evan Cruthers c/o Media

More information

Slope Stability Evaluation Ground Anchor Construction Area White Point Landslide San Pedro District Los Angeles, California.

Slope Stability Evaluation Ground Anchor Construction Area White Point Landslide San Pedro District Los Angeles, California. Slope Stability Evaluation Ground Anchor Construction Area White Point Landslide San Pedro District Los Angeles, California Submitted To: Mr. Gene Edwards City of Los Angeles Department of Public Works

More information

Earth Mechanics, Inc. Geotechnical & Earthquake Engineering

Earth Mechanics, Inc. Geotechnical & Earthquake Engineering TECHNICAL MEMORANDUM EMI PROJECT NO: 13-116 DATE: October 29, 2013 PREPARED FOR: Mr. Todd W. Dudley / AECOM PREPARED BY: SUBJECT: (Raja) S. Pirathiviraj and Lino Cheang / (EMI) Preliminary Foundation Report

More information

Pierce County Department of Planning and Land Services Development Engineering Section

Pierce County Department of Planning and Land Services Development Engineering Section Page 1 of 7 Pierce County Department of Planning and Land Services Development Engineering Section PROJECT NAME: DATE: APPLICATION NO.: PCDE NO.: LANDSLIDE HAZARD AREA (LHA) GEOLOGICAL ASSESSMENT REPORT

More information

2. Initial Summary of Preliminary Expert Opinion of Converse and Psomas Reports

2. Initial Summary of Preliminary Expert Opinion of Converse and Psomas Reports UNITED WALNUT TAXPAYERS PRELIMINARY REVIEW OF NEGATIVE GEOTECHNICAL AND GEOLOGICAL ASPECTS OF CONSTRUCTING EARTHFILL PAD FOR A SOLAR FARM ON THE WEST PARCEL - DRAFT 1. Introduction A licensed Engineering

More information

Limited Geotechnical Engineering Evaluation Classroom Additions Albany County Campus Laramie, Wyoming

Limited Geotechnical Engineering Evaluation Classroom Additions Albany County Campus Laramie, Wyoming Limited Geotechnical Engineering Evaluation Classroom Additions Albany County Campus 2300 Missile Drive, Cheyenne, Wyoming 82001 Phone 307-635-0222 www.stratageotech.com Limited Geotechnical Engineering

More information

4.5 GEOLOGY AND SEISMICITY

4.5 GEOLOGY AND SEISMICITY 4.5 GEOLOGY AND SEISMICITY INTRODUCTION This section identifies the potential for geologic and seismic hazards to occur on or near the proposed project site. Issues of concern include suitability of soil

More information

NOTES ON SUBBASE AGGREGATE SPECIFICATION TNZ M/3. These notes must not be included in the Contract Documents.

NOTES ON SUBBASE AGGREGATE SPECIFICATION TNZ M/3. These notes must not be included in the Contract Documents. TNZ M/3 Notes : 1986 NOTES ON SUBBASE AGGREGATE SPECIFICATION TNZ M/3 These notes must not be included in the Contract Documents. 1. INTRODUCTION There is no standard TNZ M/3 Specification for subbase

More information

3.10 GEOLOGY AND SOILS

3.10 GEOLOGY AND SOILS 3.10 GEOLOGY AND SOILS This section evaluates the potential impacts of the proposed project on geology, soils, and seismic hazards. This evaluation is based on the Preliminary Geotechnical Investigation

More information

4.4 GEOLOGY AND SOILS

4.4 GEOLOGY AND SOILS 4.4 GEOLOGY AND SOILS This section analyzes potential geotechnical hazards that may adversely affect the project site or that may be exacerbated by implementation of the proposed project. Information presented

More information

GEOLOGIC HAZARDS ASSESSMENT AND GEOTECHNICAL EVALUATION NEW ACADEMIC BUILDING LAS POSITAS COLLEGE LIVERMORE, CALIFORNIA

GEOLOGIC HAZARDS ASSESSMENT AND GEOTECHNICAL EVALUATION NEW ACADEMIC BUILDING LAS POSITAS COLLEGE LIVERMORE, CALIFORNIA GEOLOGIC HAZARDS ASSESSMENT AND GEOTECHNICAL EVALUATION NEW ACADEMIC BUILDING LAS POSITAS COLLEGE LIVERMORE, CALIFORNIA PREPARED FOR: Chabot-Las Positas Community College District 5020 Franklin Drive Pleasanton,

More information

Appendix F. Geotechnical Study

Appendix F. Geotechnical Study Appendix F Geotechnical Study This page intentionally left blank. November 12, 2015 Project No. 20154777.001A Ms. Sarah Marijana San Diego Gas & Electric Civil/Structural Engineering 8316 Century Park

More information

BONSALL UNIFIED SCHOOL DISTRICT

BONSALL UNIFIED SCHOOL DISTRICT PRELIMINARY GEOTECHNICAL ENGINEERING AND GEOLOGIC HAZARD REPORT PROPOSED HIGH SCHOOL GIRD ROAD PROPERTY, APN: 124-340-34-00 FALLBROOK AREA, SAN DIEGO COUNTY, CALIFORNIA Prepared for BONSALL UNIFIED SCHOOL

More information

3.4 Geology/Soils/Paleontological Resources

3.4 Geology/Soils/Paleontological Resources Section 3.4 Geology, Soils, and Paleontological Resources This section evaluates potential geology and soils impacts, and also paleontological impacts. The analysis is based on a preliminary geotechnical

More information

ROCK EXCAVATION (GRADING) OPSS 206 INDEX

ROCK EXCAVATION (GRADING) OPSS 206 INDEX 206-2 - OPSS 206 INDEX 206-2.1 GENERAL 206-2.1.1 Classification of Rock Materials 206-2.1.2 Tender Items 206-2.1.3 Other Excavation Tender Items 206-2.1.4 Specifications 206-2.1.5 Special Provisions 206-2.1.6

More information

June 5, 2013 J.N.: Mr. John Reischl The Olson Company 3010 Old Ranch Parkway, Suite 100 Seal Beach, California 90740

June 5, 2013 J.N.: Mr. John Reischl The Olson Company 3010 Old Ranch Parkway, Suite 100 Seal Beach, California 90740 June 5, 2013 Mr. John Reischl The Olson Company 3010 Old Ranch Parkway, Suite 100 Seal Beach, California 90740 Subject: Geotechnical Due-Diligence Investigation, Proposed Residential Development, East

More information

Geotechnical Investigation

Geotechnical Investigation 2015 Cal Poly Pomona, Portland State University, and others. See full permissions statement at end of document. Civil Engineering Writing Project - Genre Unit 3 Geotechnical Site Investigation Report What

More information

Sacramento Modesto Roseville Pleasanton September 19, 2013 Marcia Medina GHD Inc. 417 Montgomery Street, Suite 700 San Francisco, CA Subject: GE

Sacramento Modesto Roseville Pleasanton September 19, 2013 Marcia Medina GHD Inc. 417 Montgomery Street, Suite 700 San Francisco, CA Subject: GE Sacramento Modesto Roseville Pleasanton September 19, 2013 Marcia Medina GHD Inc. 417 Montgomery Street, Suite 700 San Francisco, CA 94104 Subject: GEOTECHNICAL REPORT AMENDMENT Stonybrook Creek Crossings

More information

Important Concepts. Earthquake hazards can be categorized as:

Important Concepts. Earthquake hazards can be categorized as: Lecture 1 Page 1 Important Concepts Monday, August 17, 2009 1:05 PM Earthquake Engineering is a branch of Civil Engineering that requires expertise in geology, seismology, civil engineering and risk assessment.

More information

Re: Steep Slope Assessment for 2465 Waverly Drive, Blind Bay, BC; Legal Address: Lot 39, Section 18, Township 22, Range 10, Plan 25579, W6M, KDYD.

Re: Steep Slope Assessment for 2465 Waverly Drive, Blind Bay, BC; Legal Address: Lot 39, Section 18, Township 22, Range 10, Plan 25579, W6M, KDYD. OEL File 1563-1 May 30, 2017 Doug Wall PO Box 774 Salmon Arm, BC V1E 4N7 Re: Steep Slope Assessment for 2465 Waverly Drive, Blind Bay, BC; Legal Address: Lot 39, Section 18, Township 22, Range 10, Plan

More information

3.8 Geology/Soils. Environmental Setting. Topography. Geology and Soils

3.8 Geology/Soils. Environmental Setting. Topography. Geology and Soils 3.8 Geology/Soils This section examines whether implementation of the 2004 Land Use Mobility Elements, Zoning Code Revisions, and Central District Specific Plan the will expose people or structures to

More information

DATA REPORT GEOTECHNICAL INVESTIGATION GALVESTON CRUISE TERMINAL 2 GALVESTON, TEXAS

DATA REPORT GEOTECHNICAL INVESTIGATION GALVESTON CRUISE TERMINAL 2 GALVESTON, TEXAS DATA REPORT GEOTECHNICAL INVESTIGATION GALVESTON CRUISE TERMINAL 2 GALVESTON, TEXAS SUBMITTED TO PORT OF GALVESTON 123 ROSENBERG AVENUE, 8TH FLOOR GALVESTON, TEXAS 77553 BY HVJ ASSOCIATES, INC. HOUSTON,

More information

APPENDIX E SOILS TEST REPORTS

APPENDIX E SOILS TEST REPORTS Otsego County, NY Site Work Specifications APPENDIX E SOILS TEST REPORTS Blue Wing Services, Inc. July 1, 2010 Blue Wing Services May 20, 2010 Page 2 the site, was not made available to Empire at this

More information

The results of KCB s site inspection observations and our recommendations for further work are presented herein.

The results of KCB s site inspection observations and our recommendations for further work are presented herein. July 14, 2015 Central Region 401, 4902 51 Street Red Deer, Alberta T4N 6K8 Mr. Tony Penney, P.Eng. Construction Engineer Dear Mr. Penney: June 25, 2015 Site Inspection Report The above site was visited

More information

Mitigation of Liquefaction Potential Using Rammed Aggregate Piers

Mitigation of Liquefaction Potential Using Rammed Aggregate Piers ASCE 2011 557 Mitigation of Liquefaction Potential Using Rammed Aggregate Piers R.W. Rudolph, M. ASCE, G.E. 1, B. Serna, M. ASCE, P.E. 2, and T. Farrell, M. ASCE, G.E. 3 1 Principal Consultant, ENGEO,

More information

SOUTHERN CALIFORNIA EDISON

SOUTHERN CALIFORNIA EDISON SOUTHERN CALIFORNIA EDISON Geotechnical Investigation Triton 115/12 KV Substation City of Temecula Riverside County, California September 26, 2008 TDBU Civil/Geotechnical Engineering Group GEOTECHNICAL

More information

Report of Subsurface Exploration and Geotechnical Engineering Evaluation

Report of Subsurface Exploration and Geotechnical Engineering Evaluation Report of Subsurface Exploration and Geotechnical Engineering Evaluation Proposed Chatham County Jail Pittsboro, North Carolina F&R Project No. 66N-0097 Prepared For: CHATHAM COUNTY P.O. Box 1809 Pittsboro,

More information

Section 4.6 Geology and Soils Introduction

Section 4.6 Geology and Soils Introduction 4.6 invisible_toc_marker County of Kern Section 4.6 Geology and Soils 4.6.1 Introduction As described in Chapter 2 of this Supplemental EIR (SEIR), an EIR was previously certified for the Alta Oak Creek

More information

Appendix 6A Geologic Information about the Project Area prepared by Ninyo & Moore October 2008

Appendix 6A Geologic Information about the Project Area prepared by Ninyo & Moore October 2008 Appendix 6A Geologic Information about the Project Area prepared by Ninyo & Moore October 2008 Appendix 6A: Geologic Information about the Project Area 6A-1Existing Geologic and Subsurface Conditions

More information

Preliminary Geotechnical Engineering Report

Preliminary Geotechnical Engineering Report Preliminary Geotechnical Engineering Report Park 3 Barrow County, Georgia July, Terracon Project No. 4906 Prepared For: Winder Barrow Industrial Authority Prepared By: Terracon Consultants, Inc. Atlanta,

More information

C.Y. Geotech, Inc. Soil Engineering Investigation Victory Boulevard, Van Nuys, California. August 31, Ibid.

C.Y. Geotech, Inc. Soil Engineering Investigation Victory Boulevard, Van Nuys, California. August 31, Ibid. E. SOILS AND GEOLOGY The purpose of this section is to assess impacts related to geologic resources resulting from construction and development of the proposed project and adjacent Add Area, such as seismically

More information