The results of KCB s site inspection observations and our recommendations for further work are presented herein.

Size: px
Start display at page:

Download "The results of KCB s site inspection observations and our recommendations for further work are presented herein."

Transcription

1 July 14, 2015 Central Region 401, Street Red Deer, Alberta T4N 6K8 Mr. Tony Penney, P.Eng. Construction Engineer Dear Mr. Penney: June 25, 2015 Site Inspection Report The above site was visited on June 25, 2015 by Messrs. Darren Ratcliffe, P.Eng. and Chris Gräpel, P.Eng. of Klohn Crippen Berger (KCB) in the company of Messrs. Rocky Wang, P.Eng. and Tony Penney, P.Eng. of (AT). The site visit was conducted during the spring 2015 tour of the Central Region Geohazard Risk Management Program (GRMP). The site was previously visited on a Call-Out inspection on April 14, 2015 by Mr. Darren Ratcliffe, P.Eng. of KCB. Photographs from the inspections are included in Appendix I. This report was prepared by KCB for AT under Contract No. CON The results of KCB s site inspection observations and our recommendations for further work are presented herein. 1 PROJECT LOCATION The site is located on Highway 585:02 (km 18) about 2 km west of the Red Deer River crossing (Tolman) and about 13 km east of Trochu. The highway at this location is descending into the valley towards the Red Deer River. The 2013 Annual Average Daily Traffic (AADT) for H585 was 490. The site location is shown on Figures 1 and L H inspection.docx A03038A15 Klohn Crippen Berger Ltd Hopewell Place NE Calgary AB T1Y 7J7 CANADA t f

2 Figure 1 Location Plan Slide Area Page 2

3 Figure 2 Site Plan Culvert Slide Area Culvert Page 3

4 2 SITE OBSERVATIONS Observations made during the June 25, 2015 site inspection are briefly summarized as follows: The slide movement is observed at the crest of 3H:1V (approx.) fill slope about 2 m to 3 m high and is apparent as a 20 m long section of pavement with severe distress (see Photograph 1). The semi-circular crack is about 9 m long. The road width at this location is about 7.5 m and the maximum extent of the crack into the road is about 3 m. The crack has a maximum vertical displacement of about 100 mm near the guardrail. Photos 1 and 2 show the difference in pavement deformation between the June 2015 and the April 2015 site visits. Westbound traffic (travelling uphill), including tractor-trailers, were changing lanes over the double centreline to avoid the pavement roughness at this site. There is limited sight distance in a westbound direction due to curvature of the highway as shown in Photos 3 and 4. Bulging of the slope to the north of the highway was not observed; however, the guardrail posts are tipped over at the ground surface perpendicular to the edge of pavement as shown in Photo 3. Furthermore, the guardrails are also tipped in a westerly direction near the area of greatest pavement distress and thickness as shown in Photo 5. This suggests that shallow, surficial lateral spreading with associated settlement is occurring, possibly due to an underlying weak and/or saturated layer. The highway has been repeatedly patched at this location with asphalt at least 1 m thick observed at the edge. The guardrail is almost level with the highway surface which indicates that deformation at this site has been underway for several years. Vegetation is present on both sides of the highway at this location indicative of shallow groundwater conditions. An increase in vegetation density, including willows, were observed downslope of the area of most severe pavement distress as shown in Photo 5. Erosion channels associated with seepage were observed downslope of the willows as shown in Photos 6 and 7 which indicates that seepage is discharging further downslope with enough velocity to cause erosion. It is considered possible that the highway was constructed over a narrow valley or buried channel trending to the northeast at the observed area of pavement distress. The highway over a length of about 1 km to the west of the slide site contains numerous patches and evidence of previous zones of pavement distress. Steep slopes on the north side of the highway are also apparent. No areas of pavement distress were observed to the east of the subject site L H inspection.docx Page 4

5 3 SITE ASSESSMENT The subject area is limited in extent with a gently sloping, relatively low height fill slope below. The area of distress is considered to be slow moving (creep movement) and likely represents a shallow lateral spreading. The subgrade at this location (and at other locations to the west) is likely weakened by high groundwater associated with subsurface flow to the north/northeast towards the nearby ravine. The observed erosion gully caused by seepage indicates that groundwater flows can be substantial during periods of elevated groundwater. Based on KCB s observations in April and June of 2015, it seems reasonable to conclude that either a natural valley was in-filled during the original construction of the highway or that a spring was buried without adequate drainage measures being installed. Groundwater levels should be expected to vary seasonally. AT should monitor the site for evidence that rates of movement are dependent on periods of high runoff caused by snowmelt freshet or sustained periods of rainy weather. Based on the risk level criteria provided by relating to safety, a risk rating of 36 was assigned to this site. This is based on a probability factor of 9 for an active settlement zone, and a consequence factor of 4 due to the impact to vehicles travelling on the highway. 4 RECOMMENDATIONS It is recommended that the pavement distress can be managed in the short term with the provision of pavement milling, patching, and resetting the guardrail to the correct height to reduce the hazard to traffic and reduce the frequency of westbound traffic crossing into the east bound lane. A long term remedial approach would be to establish subsurface drainage to lower the groundwater table and replace weak materials beneath the pavement. This would start with removal of the thick layer of asphalt placed at this location. The embankment fill should then be excavated to a depth of about 1.5 m to 2.0 m and replaced with compacted gravel fill that includes filter fabric wrapped perforated drains that extend from the eastbound lane ditch to the erosion gully described earlier. Drains should typically comprise 150 mm diameter perforated HDPE pipes at about 3 m centres which can be joined to a common discharge point draining to the erosion gully. The excavation below the highway should be conducted to below the groundwater table, if possible, to increase the effectiveness of the drains. Depending on the depth and lateral extent of the excavation as well as the condition of the excavation subgrade, geo-grid reinforcement and a basal separation layer of nonwoven geotextile can be placed to further strengthen the subgrade. The intent is to lower the groundwater table, protect the drains from being eventually clogged with silt and replace weak material with coarse granular materials. The excavation may also expose a weak layer under the road that can be removed and replaced with a gravel shear key. The outlet from the drain pipe should be protected with armouring such as perforated geo-cell backfilled with coarse gravel to prevent the erosion gully from enlarging due to concentration of groundwater discharge L H inspection.docx Page 5

6 5 CLOSURE This report is an instrument of service of Klohn Crippen Berger Ltd. The report has been prepared for the exclusive use of for the specific application to the Central Region Geohazard Assessments. The report's contents may not be relied upon by any other party without the express written permission of Klohn Crippen Berger. In this report, Klohn Crippen Berger has endeavoured to comply with generally-accepted professional practice common to the local area. Klohn Crippen Berger makes no warranty, express or implied. Please contact the undersigned if you have any questions regarding this report. Yours truly, KLOHN CRIPPEN BERGER LTD. Chris Gräpel, P.Eng. Senior Civil Engineer APEGA Permit to Practice No Attachments Photographs L H inspection.docx Page 6

7 APPENDIX I Photographs L H inspection.docx

8 Site Photograph Photograph 1 Pavement distress on June 25, Photograph taken facing east Photograph 2 Pavement distress on April 14, 2015 from same perspective as Photograph 1. Note that Photograph 1 shows additional movement and pavement distress Site Photographs Page 1

9 Site Photograph Photograph 3 Pavement distress and limited sight distance to the west. Note that the guardrails have been tipped by ongoing deformation at this site. Photograph taken facing west. Photograph 4 Condition of pavement and limited sight distance to the west. Photograph taken facing southwest Site Photographs Page 2

10 Site Photograph Photograph 5 Inclination of guardrails in a westerly direction. Red arrow and highway markers indicate area of most severe pavement distress at this site. Note density of willows downslope of guardrail. Photograph taken facing south. Photograph 6 Start of erosion gully which appears to be due to groundwater discharge on the slope below the highway. Red arrow shows approximate location of most severe pavement distress. Photograph taken facing south west Site Photographs Page 3

11 Site Photograph Photograph 7 Erosion gully downslope of pavement distress and Photograph 6 location. Photograph taken facing north east Site Photographs Page 4

1 PROJECT BACKGROUND. August 14, Alberta Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8

1 PROJECT BACKGROUND. August 14, Alberta Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8 August 14, 2013 Alberta Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 Mr. Dennis Grace, P.Eng. Construction Engineer Dear Mr. Grace: Central Region Geohazard Assessment 2013

More information

This report was prepared by Klohn Crippen Consultants Ltd. for Alberta Transportation Central Region under Contract No. CE053/2000.

This report was prepared by Klohn Crippen Consultants Ltd. for Alberta Transportation Central Region under Contract No. CE053/2000. Alberta Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 June 7, 2002 Mr. Melvin Mayfield, P.Eng. Project Engineer Dear Mr. Mayfield: Central Region Landslide Assessment Site

More information

CENTRAL REGION GEOHAZARDS RISK ASSESSMENT SITE INSPECTION FORM

CENTRAL REGION GEOHAZARDS RISK ASSESSMENT SITE INSPECTION FORM SITE NUMBER AND NAME C55 H861:02 Slide LEGAL DESCRIPTION NW 14-40-14-W4 CENTRAL REGION GEOHAZARDS RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY & KM NAD 83 COORDINATES N 5811217 E 437291 PREVIOUS INSPECTION

More information

1. PROJECT BACKGROUND. July 18, Alberta Infrastructure & Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8

1. PROJECT BACKGROUND. July 18, Alberta Infrastructure & Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8 July 18, 2005 Alberta Infrastructure & Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 Mr. Alain Momedi, P.Eng. Project Engineer Dear Mr. Momedi: H11:04 km 11.1 Erosion along

More information

January 17, 2008 File:

January 17, 2008 File: January 17, 2008 File: 15-85-73 Alberta Infrastructure and Transportation Room 301, Provincial Building 9621-96 Avenue Peace River, Alberta T8S 1T4 Attention: Mr. Ed Szmata PEACE REGION (SWAN HILLS AREA)

More information

January 12, 2006 File:

January 12, 2006 File: January 12, 2006 File: 15-85-13 Alberta Infrastructure and Transportation Room 301, Provincial Building 9621-96 Avenue Peace River, Alberta T8S 1T4 Attention: Mr. Ed Szmata PEACE REGION (PEACE HIGH LEVEL

More information

February 18, 2003 File: NORTH CENTRAL REGION LANDSLIDE ASSESSMENT HWY 43:16 WHITECOURT EAST HILL (NC1) 2002 ANNUAL INSPECTION REPORT

February 18, 2003 File: NORTH CENTRAL REGION LANDSLIDE ASSESSMENT HWY 43:16 WHITECOURT EAST HILL (NC1) 2002 ANNUAL INSPECTION REPORT February 18, 2003 File: 15-76-11 Alberta Transportation Room 223, Provincial Building 4709 44 Avenue Stony Plain, Alberta T7Z 1N4 Attention: Mr. Rob Lonson, P.Eng. NORTH CENTRAL REGION LANDSLIDE ASSESSMENT

More information

August 10, 2007 File:

August 10, 2007 File: August 10, 2007 File: 15-85-72 Alberta Infrastructure and Transportation Room 301, Provincial Building 9621-96 Avenue Peace River, AB T8S 1T4 Attention: Mr. Ed Szmata PEACE REGION (PEACE HIGH LEVEL AREA)

More information

September 3, 2009 File: NORTH CENTRAL REGION GEOHAZARD ASSESSMENT HWY 40:28 NORTH OF CADOMIN (NC50) 2009 ANNUAL INSPECTION REPORT

September 3, 2009 File: NORTH CENTRAL REGION GEOHAZARD ASSESSMENT HWY 40:28 NORTH OF CADOMIN (NC50) 2009 ANNUAL INSPECTION REPORT GEOTECHNICAL ENVIRONMENTAL MATERIALS September 3, 2009 File: 15-16-226 Alberta Transportation 2 nd Floor, Provincial Building 111 54 Street Edson, Alberta T7E 1T2 Attention: Mr. Cliff Corner NORTH CENTRAL

More information

December 11, 2006 File:

December 11, 2006 File: December 11, 2006 File: 15-85-38 Alberta Infrastructure and Transportation Room 301, Provincial Building 9621-96 Avenue Peace River, Alberta T8S 1T4 Attention: Mr. Ed Szmata PEACE REGION (SWAN HILLS AREA)

More information

PEACE REGION GRANDE PRAIRIE GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM NAD 83 COORDINATES N 6,178,811 E 403,309

PEACE REGION GRANDE PRAIRIE GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM NAD 83 COORDINATES N 6,178,811 E 403,309 PEACE REGION GRANDE PRAIRIE GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM SITE NUMBER GP-4a LEGAL DESCRIPTION LSD 12-10-78-4-W6M SITE NAME Burnt River Bridge - West Approach Slide HIGHWAY & KM Hwy 49:06

More information

1.0 INSPECTION ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER PROJECT, CARMACKS, YUKON. Dear Mr. West-Sells,

1.0 INSPECTION ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER PROJECT, CARMACKS, YUKON. Dear Mr. West-Sells, Doc. No. 162 Rev. 0 Mr. Paul West-Sells President & Chief Operating Officer Western Copper Corporation 2060-1111 West Georgia Street Vancouver, BC V6E 4M3 ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER

More information

PEACE RIVER EAST HILL - HWY 2:60 (PH2) SELECT PHOTOGRAPHS August 22, 2007 File: Photo E003. Station May 2007

PEACE RIVER EAST HILL - HWY 2:60 (PH2) SELECT PHOTOGRAPHS August 22, 2007 File: Photo E003. Station May 2007 Photo E003 0+000 Viewing looking upslope at Site 4 from highway. Conditions unchanged from 2006. Photo E018 0+000 Localized erosion within road fill on upslope side of highway. Photo E022 0+250 Looking

More information

Construction Exits Rock pads

Construction Exits Rock pads Construction Exits Rock pads SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow [1] Clayey Soils Type 3 System Supplementary Trap Dispersive Soils [1] Minor

More information

CCR Rule Annual Inspection Report (cont.) 2

CCR Rule Annual Inspection Report (cont.) 2 The inspection findings consisted of maintenance items and items that were not observed to be signs or potential signs of significant structural weakness. No deficiencies or disrupting conditions that

More information

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area.

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area. Sediment Trench SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils [1] Performance of

More information

Rock & Aggregate Drop Inlet Protection

Rock & Aggregate Drop Inlet Protection Rock & Aggregate Drop Inlet Protection SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System Supplementary Trap Dispersive Soils

More information

An Evaluation of Pavement Drainage Interstate 64, Rowan-Carter Counties

An Evaluation of Pavement Drainage Interstate 64, Rowan-Carter Counties Transportation Kentucky Transportation Center Research Report University of Kentucky Year 1984 An Evaluation of Pavement Drainage Interstate 64, Rowan-Carter Counties David L. Allen Herbert F. Southgate

More information

1 INTRODUCTION 1.1 General

1 INTRODUCTION 1.1 General #701 475 Howe Street Vancouver, British Columbia V6C 2B3 August 1, 2014 Robin McCall Wolverine Mine Environmental Superintendent Dear Mr. McCall: 1 INTRODUCTION 1.1 General This letter report presents

More information

design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards.

design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards. design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards. In addition to the field inspection, Associated Engineers, Inc.

More information

U-Shaped Sediment Traps

U-Shaped Sediment Traps U-Shaped Sediment Traps SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils [1] Type 3 System Supplementary Trap Dispersive Soils [1] Generally

More information

APPENDIX B WORKSHEETS & EXHIBITS

APPENDIX B WORKSHEETS & EXHIBITS APPENDIX B WORKSHEETS & EXHIBITS A worksheet provides the designer a representation of a measure that allows for input of specific design criteria. The plan designer will be required to assess field conditions

More information

Geohazards Associated with Dispersive-Soil Voids

Geohazards Associated with Dispersive-Soil Voids Geohazards Associated with Dispersive-Soil Voids Chris Grapel, M.Eng., P.Eng. GRMP 2018 Dispersive-Soil GRMP Sites S040 Dorothy Hwy 848:02 S040 Dorothy Hwy 848:02 Dispersive Soils Dispersive clays are

More information

Preliminary Geotechnical Evaluation Gooseberry Point Pedestrian Improvements Whatcom County, Washington SITE AND PROJECT DESCRIPTION

Preliminary Geotechnical Evaluation Gooseberry Point Pedestrian Improvements Whatcom County, Washington SITE AND PROJECT DESCRIPTION File No. 12-100 Geotechnical & Earthquake Engineering Consultants Mr. Kevin Brown, P.E. Gray & Osborne, Inc. 3710 168 th Street NE, Suite B210 Arlington, Washington 98223 Subject: Draft Report Preliminary

More information

APPENDIX G APPENDIX G SEDIMENT CONTAINMENT SYSTEM DESIGN RATIONALE

APPENDIX G APPENDIX G SEDIMENT CONTAINMENT SYSTEM DESIGN RATIONALE APPENDIX G SEDIMENT CONTAINMENT SYSTEM DESIGN RATIONALE March 18, 2003 This page left blank intentionally. March 18, 2003 G-2 FIGURES Page # Figure G.1 Estimated Runoff from Precipitation Over Different

More information

Construction Exits Vibration grids

Construction Exits Vibration grids Construction Exits Vibration grids SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils [1] Type 3 System Supplementary Trap Dispersive Soils [1]

More information

Husky Oil Operations Limited

Husky Oil Operations Limited Husky Oil Operations Limited 707 8th Avenue S.W. Bus: (403) 298-6111 Box 6525, Station D Fax: (403) 298-6378 Calgary, Alberta, Canada T2P 3G7 October 31, 2014 Sahtu Land &Water Board SLWB File: S13L1-005

More information

Stormwater Inlet Sediment Traps

Stormwater Inlet Sediment Traps Stormwater Inlet Sediment Traps SEDIMENT CONTROL TECHNIQUES Photo 1 Kerb inlet Photo 2 Field (drop) inlet Table 1 provides the recommended default classification of various sediment control systems suitable

More information

Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services

Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services July 27, 2017 Ms. Rebecca Mitchell Mt. San Antonio College Facilities Planning & Management

More information

Slope Stability Evaluation Ground Anchor Construction Area White Point Landslide San Pedro District Los Angeles, California.

Slope Stability Evaluation Ground Anchor Construction Area White Point Landslide San Pedro District Los Angeles, California. Slope Stability Evaluation Ground Anchor Construction Area White Point Landslide San Pedro District Los Angeles, California Submitted To: Mr. Gene Edwards City of Los Angeles Department of Public Works

More information

Geosynthetics Applications and Performance Reviews Select Case Histories

Geosynthetics Applications and Performance Reviews Select Case Histories Geosynthetics Applications and Performance Reviews Select Case Histories Debora J. Miller, Ph.D., P.E.; Dean B. Durkee,, Ph.D., P.E.; Michael A. Morrison, P.E., David B. Wilson, P.E., and Kevin Smith,

More information

Coarse Sediment Traps

Coarse Sediment Traps Coarse Sediment Traps SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils [2] Type 3 System Supplementary Trap Dispersive Soils [1] Though primarily

More information

Materials. Use materials meeting the following.

Materials. Use materials meeting the following. 208.01 Section 208. SOIL EROSION AND SEDIMENTATION CONTROL 208.01 Description. Install and maintain erosion and sedimentation controls to minimize soil erosion and to control sedimentation from affecting

More information

Erosion and Sediment Control Measures 2.7 Silt Fences

Erosion and Sediment Control Measures 2.7 Silt Fences Erosion and Sediment Control Measures Silt fences are designed to intercept sheet flow sediment laden stormwater run-off and filter out both the larger and smaller particles of sediment. Silt fences and

More information

Sediment Weirs (Instream)

Sediment Weirs (Instream) Sediment Weirs (Instream) INSTREAM PRACTICES Flow Control No Channel Flow Dry Channels Erosion Control Low Channel Flows Shallow Water Sediment Control High Channel Flows [1] Deep Water [1] Sediment weirs

More information

Central Queensland Coal Project Appendix 4b Geotechnical Assessment. Environmental Impact Statement

Central Queensland Coal Project Appendix 4b Geotechnical Assessment. Environmental Impact Statement Central Queensland Coal Project Appendix 4b Geotechnical Assessment Environmental Impact Statement GEOTECHNICAL ASSESSMENT OF OPEN CUT MINING ADJACENT TO THE BRUCE HIGHWAY, CENTRAL QUEENSLAND COAL PROJECT

More information

MEMORANDUM. wa.tsr..-z.n~.e.s-t.i~at.i.o.ns... Branch... Mr. Webster contends that prior to excavation of the gravel

MEMORANDUM. wa.tsr..-z.n~.e.s-t.i~at.i.o.ns... Branch... Mr. Webster contends that prior to excavation of the gravel TO... J. C. Foweraker 2... Head Gr o w a t er S e c t i on... Hyar....og~~~.~.~vis.ion... wa.tsr..-z.n~.e.s-t.i~at.i.o.ns... Branch... eernment OF BRITISH COLUMBIA MEMORANDUM II 0 PROM A. P. Kohut, Geological

More information

MINISTRY OF ENERGY AND MINES Mines and Mineral Resources. REPORT OF GEOTECHNICAL INSPECTOR (Issued pursuant to Section 15 of the Mines Act)

MINISTRY OF ENERGY AND MINES Mines and Mineral Resources. REPORT OF GEOTECHNICAL INSPECTOR (Issued pursuant to Section 15 of the Mines Act) MINISTRY OF ENERGY AND MINES Mines and Mineral Resources REPORT OF GEOTECHNICAL INSPECTOR (Issued pursuant to Section 15 of the Mines Act) Name of Property: Permit No.: M-203 General Manager: Company:

More information

Chutes Part 5: Rock linings

Chutes Part 5: Rock linings Chutes Part 5: Rock linings DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent [2] [1] Chutes

More information

R.M.HARW & ASSOCIATES LTD. GEOTECHNICAL INVESTIGATION PROPOSED BRIDGE SITE. HELAVA CREEKl MILE MACKENZIE HIGHWAY E-2510 OCTOBER 16, 1973

R.M.HARW & ASSOCIATES LTD. GEOTECHNICAL INVESTIGATION PROPOSED BRIDGE SITE. HELAVA CREEKl MILE MACKENZIE HIGHWAY E-2510 OCTOBER 16, 1973 El R.M.HARW & ASSOCIATES LTD. GEOTECHNICAL INVESTIGATION PROPOSED BRIDGE SITE HELAVA CREEKl MILE 616.4 MACKENZIE HIGHWAY E-2510 OCTOBER 16, 1973 R,M,HARDV & ASSOCIATES LTD. CONSULTING ENGINEERING & TESTING

More information

Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils

Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils Sediment Weirs SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils [1] Type 3 classification

More information

Appendix C Benchmarking Cost Estimates

Appendix C Benchmarking Cost Estimates REPORT Appendix C Benchmarking Cost Estimates C-1 Table C-1 Permits, Notifications & Location Services Notes: Costs associated with delays in construction have not been included in this estimate OneCall

More information

1.0 INTRODUCTION 2.0 OBSERVATIONS EBA FILE: W nd Avenue Whitehorse, YT Y1A 1C2. Attention:

1.0 INTRODUCTION 2.0 OBSERVATIONS EBA FILE: W nd Avenue Whitehorse, YT Y1A 1C2. Attention: August 5, 2013 City of Whitehorse 2121 2 nd Avenue Whitehorse, YT Y1A 1C2 ISSUED FOR USE EBA FILE: W14103182-01 Via Email: ben.campbell@whitehorse.ca Attention: Subject: Ben Campbell, Planner II Planning

More information

HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR (c)(1)(i) (xii)

HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR (c)(1)(i) (xii) HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR 257.73(c)(1)(i) (xii) (i) Site Name and Ownership Information: Site Name: E.C. Gaston Steam Plant Site Location:

More information

Assessing Slope Instabilities. Victoria Leffel & Joey Franzino

Assessing Slope Instabilities. Victoria Leffel & Joey Franzino Assessing Slope Instabilities Victoria Leffel & Joey Franzino Slope Stability and Landslides Today s Presentation: Slope instability and landslide terms will be used interchangeably Landslide: downward

More information

Black Gore Creek 2013 Sediment Source Monitoring and TMDL Sediment Budget

Black Gore Creek 2013 Sediment Source Monitoring and TMDL Sediment Budget Black Gore Creek 2013 Sediment Source Monitoring and TMDL Sediment Budget Prepared for: Prepared By: - I. Introduction The Black Gore Creek Total Maximum Daily Load (TMDL) was developed in collaboration

More information

TRAFFIC ALERT FOR WEEK OF February 4 8, 2008

TRAFFIC ALERT FOR WEEK OF February 4 8, 2008 TRAFFIC ALERT FOR WEEK OF February 4 8, 2008 Highway work zones in the Staunton District The following is a list of highway work that might affect traffic in the Staunton transportation district during

More information

3.18 GEOLOGY AND SOILS

3.18 GEOLOGY AND SOILS 3.18 GEOLOGY AND SOILS This section discusses geologic resource concerns as they relate to the environment, public safety, and project design both during construction and after completion of the project.

More information

ALBERTA TRANSPORTATION PEACE REGION (PEACE RIVER / HIGH LEVEL) INSTRUMENTATION MONITORING RESULTS

ALBERTA TRANSPORTATION PEACE REGION (PEACE RIVER / HIGH LEVEL) INSTRUMENTATION MONITORING RESULTS ALBERTA TRANSPORTATION PEACE REGION (PEACE RIVER / HIGH LEVEL) INSTRUMENTATION MONITORING RESULTS SPRING 1 SECTION C SITE PH7-1: HWY 9:, DEADWOOD SLIDE 1. OBSERVATIONS 1.1 Field Program and Instrumentation

More information

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1]

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] Rock Linings DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1] The design of permanent installations

More information

patersongroup Consulting Engineers April 20, 2010 File: PG1887-LET.01R Novatech Engineering Consultants Suite 200, 240 Michael Cowpland Drive

patersongroup Consulting Engineers April 20, 2010 File: PG1887-LET.01R Novatech Engineering Consultants Suite 200, 240 Michael Cowpland Drive patersongroup April 20, 2010 File: PG1887-LET.01R Novatech Engineering Consultants Suite 200, 240 Michael Cowpland Drive Ottawa, Ontario K2M 1P6 Attention: Mr. Adam Thompson Consulting Engineers 28 Concourse

More information

APPENDIX H SOIL SURVEY

APPENDIX H SOIL SURVEY Environmental Impact Statement Beryl Solar Farm APPENDIX H SOIL SURVEY Beryl Solar Farm 16 347 Final V1 H i Geotechnical Engineers & Engineering Geologists NATA Accredited Laboratories for Asphalt, Aggregate,

More information

February 22, 2016 AG File No

February 22, 2016 AG File No Ainley Graham & Associates Limited 1-50 Grant Timmins Drive, Kingston, Ontario, K7M 8N2 Tel: (343) 266-0002 Fax: (343) 266-0028 E-mail Kingston@ainleygroup.com February 22, 2016 AG File No. 15062-1 Ministry

More information

Monitoring of suspended sediment concentration in discharge from regulated lakes in glacial deposits

Monitoring of suspended sediment concentration in discharge from regulated lakes in glacial deposits Erosion and Sediment Transport Monitoring Programmes in River Basins (Proceedings of the Oslo Symposium, August 1992). IAHS Publ. no. 210, 1992. 269 Monitoring of suspended sediment concentration in discharge

More information

Photographic Log. Photo No. 1. Date: 10/27/15. Direction Photo Taken: Southwest. Photo Taken By: JBH1

Photographic Log. Photo No. 1. Date: 10/27/15. Direction Photo Taken: Southwest. Photo Taken By: JBH1 1 Southwest 10/27/15 Looking southwest on Copper Park Lane viewing clearing and grubbing of area south of Copper Park Lane prior to excavation. 2 Southeast 10/29/15 Looking southeast at the sump and pump

More information

Prepared for. Mr. Denis A. Verdon 445, Wilson Road Rockland, Ontario K4K 1K7

Prepared for. Mr. Denis A. Verdon 445, Wilson Road Rockland, Ontario K4K 1K7 GEOTECHNICAL INVESTIGATION Proposed Verdon Subdivision Part of Lot 16, Concession I (Old Survey) Geographic Township of Clarence Now City of Clarence-Rockland Prepared for Mr. Denis A. Verdon 445, Wilson

More information

DETAILED TERRAIN MAPPING WITH INTERPRETATIONS FOR SLOPE STABILITY, EROSION POTENTIAL AND SEDIMENT TRANSFER. DILLARD CREEK FRBC Project # TO-96187

DETAILED TERRAIN MAPPING WITH INTERPRETATIONS FOR SLOPE STABILITY, EROSION POTENTIAL AND SEDIMENT TRANSFER. DILLARD CREEK FRBC Project # TO-96187 ,, DETALED TERRAN MAPPNG WTH NTERPRETATONS FOR SLOPE STABLTY, EROSON POTENTAL AND SEDMENT TRANSFER DLLARD CREEK FRBC Project # TO-96187 Prepared by Blythe Killam, B.Sc., G..T. For Weyerhaeuser Canada Ltd.

More information

SLOPE STABILITY ASSESSMENT PROPOSED RESIDENTIAL SUBDIVISION 161 LAKESHORE ROAD EAST TOWN OF THE BLUE MOUNTAINS, ONTARIO

SLOPE STABILITY ASSESSMENT PROPOSED RESIDENTIAL SUBDIVISION 161 LAKESHORE ROAD EAST TOWN OF THE BLUE MOUNTAINS, ONTARIO SLOPE STABILITY ASSESSMENT PROPOSED RESIDENTIAL SUBDIVISION 161 LAKESHORE ROAD EAST TOWN OF THE BLUE MOUNTAINS, ONTARIO PETO MacCALLUM LTD. 19 CHURCHILL DRIVE BARRIE, ONTARIO L4N 8Z5 PHONE: (705) 734-3900

More information

Re: Steep Slope Assessment for 2465 Waverly Drive, Blind Bay, BC; Legal Address: Lot 39, Section 18, Township 22, Range 10, Plan 25579, W6M, KDYD.

Re: Steep Slope Assessment for 2465 Waverly Drive, Blind Bay, BC; Legal Address: Lot 39, Section 18, Township 22, Range 10, Plan 25579, W6M, KDYD. OEL File 1563-1 May 30, 2017 Doug Wall PO Box 774 Salmon Arm, BC V1E 4N7 Re: Steep Slope Assessment for 2465 Waverly Drive, Blind Bay, BC; Legal Address: Lot 39, Section 18, Township 22, Range 10, Plan

More information

MINISTRY OF FORESTS, LANDS AND NATURAL RESOURCE OPERATIONS, POST-WILDFIRE RISK ANALYSIS PRELIMINARY REPORT

MINISTRY OF FORESTS, LANDS AND NATURAL RESOURCE OPERATIONS, POST-WILDFIRE RISK ANALYSIS PRELIMINARY REPORT MINISTRY OF FORESTS, ANDS AND NATURA RESOURCE OPERATIONS, POST-WIDFIRE RISK ANAYSIS PREIMINARY REPORT NOTE: The results given on this form are preliminary in nature and are intended to be a warning of

More information

Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay 19 Module 5: Lecture -1 on Stability of Slopes Contents Stability analysis of a slope and finding critical slip surface; Sudden Draw down condition, effective stress and total stress analysis; Seismic

More information

DRAFT. PRELIMINARY LANDSLIDE MODELING for KRAMER AVENUE LANDSLIDE SITKA, ALASKA. Prepared for: Andrew Friske 210 Kramer Ave. Sitka, Alaska 99835

DRAFT. PRELIMINARY LANDSLIDE MODELING for KRAMER AVENUE LANDSLIDE SITKA, ALASKA. Prepared for: Andrew Friske 210 Kramer Ave. Sitka, Alaska 99835 PRELIMINARY LANDSLIDE MODELING for KRAMER AVENUE LANDSLIDE SITKA, ALASKA Prepared for: Andrew Friske 210 Kramer Ave. Sitka, Alaska 99835 Prepared by: Northern Geotechnical Engineering, Inc. d.b.a. Terra

More information

GEOLOGY Local Geology Local geologic mapping shows the site underlain by Goble Volcanics consisting of basalt and andesite, with basalt breccia, volcanic conglomerate, and interbedded siltstone and pyroclastics

More information

Degradation Concerns related to Bridge Structures in Alberta

Degradation Concerns related to Bridge Structures in Alberta Degradation Concerns related to Bridge Structures in Alberta Introduction There has been recent discussion regarding the identification and assessment of stream degradation in terms of how it relates to

More information

CHAPTER GEOLOGICALLY HAZARDOUS AREAS Applicability Regulations.

CHAPTER GEOLOGICALLY HAZARDOUS AREAS Applicability Regulations. CHAPTER 19.07 GEOLOGICALLY HAZARDOUS AREAS 19.07.010 Applicability. Geologically hazardous areas may pose a threat to the health and safety of citizens when incompatible development is sited in areas of

More information

June 9, R. D. Cook, P.Eng. Soils Engineer Special Services Western Region PUBLIC WORKS CANADA WESTERN REGION REPORT ON

June 9, R. D. Cook, P.Eng. Soils Engineer Special Services Western Region PUBLIC WORKS CANADA WESTERN REGION REPORT ON PUBLIC WORKS CANADA WESTERN REGION REPORT ON GEOTECHNICAL INVESTIGATION PROPOSED MARTIN RIVER BRIDGE MILE 306.7 MACKENZIE HIGHWAY Submitted by : R. D. Cook, P.Eng. Soils Engineer Special Services Western

More information

Gully Erosion Part 1 GULLY EROSION AND ITS CAUSES. Introduction. The mechanics of gully erosion

Gully Erosion Part 1 GULLY EROSION AND ITS CAUSES. Introduction. The mechanics of gully erosion Gully Erosion Part 1 GULLY EROSION AND ITS CAUSES Gully erosion A complex of processes whereby the removal of soil is characterised by incised channels in the landscape. NSW Soil Conservation Service,

More information

4.5 GEOLOGY AND SOILS

4.5 GEOLOGY AND SOILS 4.5 GEOLOGY AND SOILS This section addresses the project site geology and soils and analyzes potential changes that would result from development of the Wye Specific Plan project. 4.5.1 Environmental Setting

More information

Mass Wasting. Requirements for Mass Wasting. Slope Stability. Geol 104: mass wasting

Mass Wasting. Requirements for Mass Wasting. Slope Stability. Geol 104: mass wasting Mass Wasting Movement of earth materials downslope, driven by Gravitational Forces. Landslides - general term for rock or soil movement. In U.S., on average, mass wasting causes 1 to 2 billion dollars

More information

Sediment Trap. At multiple locations within the project site where sediment control is needed.

Sediment Trap. At multiple locations within the project site where sediment control is needed. Sediment Trap SE-3 Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control

More information

Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services

Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services Ms. Rebecca Mitchell Mt. San Antonio College Facilities Planning & Management 1100 North

More information

October 26, Ms. Aimee Zack Canadian Pacific 120 S. Sixth Street Suite 900 Minneapolis, Minnesota 55402

October 26, Ms. Aimee Zack Canadian Pacific 120 S. Sixth Street Suite 900 Minneapolis, Minnesota 55402 October 26, 2017 Ms. Aimee Zack Canadian Pacific 120 S. Sixth Street Suite 900 Minneapolis, Minnesota 55402 Re: Soo Line Dump Site 2017 Annual Soil Cover Inspection Dear Aimee: The purpose of this letter

More information

Geotechnical Investigation Bow Ridge Subdivision Phase 3 Cochrane, Alberta

Geotechnical Investigation Bow Ridge Subdivision Phase 3 Cochrane, Alberta Geotechnical Investigation Bow Ridge Subdivision Phase 3 Cochrane, Alberta FINAL Prepared for: The Town of Cochrane 101 Ranchehouse Road Cochrane, Alberta Prepared by: Stantec Consulting Ltd. Calgary,

More information

GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE

GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE Prof. J. N. Mandal Department of civil engineering, IIT Bombay, Powai, Mumbai 400076, India. Tel.022-25767328 email: cejnm@civil.iitb.ac.in Module - 4

More information

B805 TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES - OPSS 805

B805 TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES - OPSS 805 B805 MEASURES - OPSS 805 805.1 GENERAL Construction activities frequently remove protective cover and expose soil to accelerated rates of erosion. Sediments generated thereby can be conveyed via runoff

More information

Template for Sediment and Erosion Control Plan General Instructions. Section Instructions

Template for Sediment and Erosion Control Plan General Instructions. Section Instructions Template for Sediment and Erosion Control Plan General Instructions Introduction: Soil erosion and sediment deposition from farmlands can contribute to degraded surface water quality. Sediment delivery

More information

Nipigon River Landslide, Ontario, Canada

Nipigon River Landslide, Ontario, Canada Nipigon River Landslide, Ontario, Canada A. Abdelaziz, S. Besner, R. Boger, B. Fu, J. Deng, and A. Farina Presenter: Jian Deng, Ph.D, P.Eng Centre of Excellence for Sustainable Mining and Exploration,

More information

Orica Australia Pty Ltd Ammonium Nitrate Facility Upgrade

Orica Australia Pty Ltd Ammonium Nitrate Facility Upgrade Orica Australia Pty Ltd Ammonium Nitrate Facility Upgrade January 2010 Revision 0 Contents 1. Introduction 1 1.1 Purpose 1 1.2 Objectives 1 1.3 Relevant Environmental Legislation, Guidelines and Policies

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS G. GEOLOGY AND SOILS

IV. ENVIRONMENTAL IMPACT ANALYSIS G. GEOLOGY AND SOILS IV. ENVIRONMENTAL IMPACT ANALYSIS G. GEOLOGY AND SOILS The following section is a summary of the geotechnical report conducted for the proposed project. The Report of Geotechnical Investigation Proposed

More information

3.12 Geology and Topography Affected Environment

3.12 Geology and Topography Affected Environment 3 Affected Environment and Environmental Consequences 3.12 Geology and Topography 3.12.1 Affected Environment 3.12.1.1 Earthquakes Sterling Highway MP 45 60 Project Draft SEIS The Kenai Peninsula is predisposed

More information

Subject: Desert Palisades Specific Plan - Tram Way Access Sight Distance

Subject: Desert Palisades Specific Plan - Tram Way Access Sight Distance Endo Engineering Traffic Engineering Air Quality Studies Noise Assessments July 13, 2015 Mr. Ed Freeman Pinnacle View, LLC P.O. Box 1754 Lake Oswego, OR 97035-0579 Subject: Desert Palisades Specific Plan

More information

ENGINEER S CERTIFICATION OF FAULT AREA DEMONSTRATION (40 CFR )

ENGINEER S CERTIFICATION OF FAULT AREA DEMONSTRATION (40 CFR ) PLATTE RIVER POWER AUTHORITY RAWHIDE ENERGY STATION BOTTOM ASH TRANSFER (BAT) IMPOUNDMENTS LARIMER COUNTY, CO ENGINEER S CERTIFICATION OF FAULT AREA DEMONSTRATION (40 CFR 257.62) FOR COAL COMBUSTION RESIDUALS

More information

Geotechnical Risks and Slope Management Systems: An FHWA Perspective

Geotechnical Risks and Slope Management Systems: An FHWA Perspective August 20, 2010 10 th Annual Technical Forum Geohazards Impacting Transportation in the Appalachian Region Geotechnical Risks and Slope Management Systems: An FHWA Perspective Silas C. Nichols, PE, Senior

More information

Active Traffic & Safety Management System for Interstate 77 in Virginia. Chris McDonald, PE VDOT Southwest Regional Operations Director

Active Traffic & Safety Management System for Interstate 77 in Virginia. Chris McDonald, PE VDOT Southwest Regional Operations Director Active Traffic & Safety Management System for Interstate 77 in Virginia Chris McDonald, PE VDOT Southwest Regional Operations Director Interstate 77 at Fancy Gap Mountain Mile markers 0-15 Built in late

More information

Canadian Consulting Engineering Awards 2017 Southern Alberta Rock Slope Stabilization & Other Work Amec Foster Wheeler

Canadian Consulting Engineering Awards 2017 Southern Alberta Rock Slope Stabilization & Other Work Amec Foster Wheeler Southern Alberta Rock Slope Stabilization & Other Work Amec Foster Wheeler To: Mr. Doug Picklyk Editor, Canadian Consulting Engineer magazine Date April 20, 2017 From: Chelsea Johnson, P.Eng. Amec Foster

More information

Location Restriction Demonstration

Location Restriction Demonstration Location Restriction Demonstration R.M. Heskett Station Coal Ash Landfill Prepared for Montana-Dakota Utilities Company October 2018 Minneapolis, MN, Bismarck, ND Location Restrictions Demonstration October

More information

ROCK EXCAVATION (GRADING) OPSS 206 INDEX

ROCK EXCAVATION (GRADING) OPSS 206 INDEX 206-2 - OPSS 206 INDEX 206-2.1 GENERAL 206-2.1.1 Classification of Rock Materials 206-2.1.2 Tender Items 206-2.1.3 Other Excavation Tender Items 206-2.1.4 Specifications 206-2.1.5 Special Provisions 206-2.1.6

More information

Rock Sizing for Waterway & Gully Chutes

Rock Sizing for Waterway & Gully Chutes Rock Sizing for Waterway & Gully Chutes WATERWAY MANAGEMENT PRACTICES Photo 1 Rock-lined waterway chute Photo 2 Rock-lined gully chute 1. Introduction A waterway chute is a stabilised section of channel

More information

January 16, Re: Soo Line Dump Site 2018 Annual Soil Cover Inspection. Dear Mr. Nichols:

January 16, Re: Soo Line Dump Site 2018 Annual Soil Cover Inspection. Dear Mr. Nichols: January 16, 2019 Mr. Andrew Nichols Minnesota Pollution Control Agency Voluntary Investigation and Cleanup Program 520 Lafayette Road Saint Paul, Minnesota 55155 Re: Soo Line Dump Site 2018 Annual Soil

More information

Rock Sizing for Small Dam Spillways

Rock Sizing for Small Dam Spillways Rock Sizing for Small Dam Spillways STORMWATER MANAGEMENT PRACTICES Photo 1 Rock-lined spillway on a construction site sediment basin Photo 2 Rock-lined spillway on a small farm dam 1. Introduction A chute

More information

Monmouthshire County Council Review of Landslips within the County December February 2014

Monmouthshire County Council Review of Landslips within the County December February 2014 Monmouthshire County Council Review of Landslips within the County December 2013- February 2014 Introduction The County of Monmouthshire suffered a period of extreme weather between December 2013 and February

More information

Mr. Michael Malone CPS Energy 145 Navarro Street San Antonio, Texas Project No

Mr. Michael Malone CPS Energy 145 Navarro Street San Antonio, Texas Project No January 17, 2018 Mr. Michael Malone 145 Navarro Street San Antonio, Texas 78205 Project No. 0337367 Environmental Resources Management CityCentre Four 840 West Sam Houston Pkwy N. Suite 600 Houston, Texas

More information

Geotechnical damage in rural areas caused by the 2015 Gorkha Nepal Earthquake

Geotechnical damage in rural areas caused by the 2015 Gorkha Nepal Earthquake Tokyo, 1 June 2015 Geotechnical damage in rural areas caused by the 2015 Gorkha Nepal Earthquake Chiaro Gabriele JSPS RESEARCH FELLOW, University of Tokyo Lecturer, University of Canterbury, New Zealand

More information

CE415L Applied Fluid Mechanics Laboratory

CE415L Applied Fluid Mechanics Laboratory Applied Fluid Mechanics Laboratory Learning Objective Following completion of this experiment and the analysis of the data, you should be able to 1. generalize results of introducing changes to a natural

More information

Geophysical Case studies From Texas

Geophysical Case studies From Texas Geophysical Case studies From Texas 1 PRESENTATION OUTLINE Active Growth Faults in Metropolitan Houston 1. Hockley 2. Tomball 3. Long Point 4. Pearland Foundation Case Studies Karst Geophysics in Austin:

More information

STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1. DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT

STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1. DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1 DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT Prepared by: PAULUS, SOKOLOWSKI & SARTOR STORMWATER MANAGEMENT 1. Methodology

More information

Analysis of Road Sediment Accumulation to Monumental Creek using the GRAIP Method

Analysis of Road Sediment Accumulation to Monumental Creek using the GRAIP Method Analysis of Road Sediment Accumulation to Monumental Creek using the GRAIP Method Introduction (from http://www.neng.usu.edu/cee/faculty/dtarb/graip/#over): The Geomorphologic Road Analysis and Inventory

More information

Area-wide geotechnical information summary for CERA zoning review panel

Area-wide geotechnical information summary for CERA zoning review panel Area-wide geotechnical information summary for CERA zoning review panel This document contains all the area-wide geotechnical information which was considered by CERA as part of the process for making

More information

Evaluation and Stabilization of a Slope Failure at Liard Highway No. 7, km 5.9 (Case Study)

Evaluation and Stabilization of a Slope Failure at Liard Highway No. 7, km 5.9 (Case Study) Evaluation and Stabilization of a Slope Failure at Liard Highway No. 7, km 5.9 (Case Study) Rita Kors-Olthof, P.Eng., Ed Hoeve, P.Eng. & Bob Patrick, P.Eng. Tetra Tech EBA Inc., Yellowknife, Northwest

More information