1 ALBERTA TRANSPORTATION PEACE REGION (PEACE RIVER / HIGH LEVEL) INSTRUMENTATION MONITORING RESULTS SPRING 1 SECTION C SITE PH7-1: HWY 9:, DEADWOOD SLIDE 1. OBSERVATIONS 1.1 Field Program and Instrumentation Status Two slope inclinometers (SI15-1 and SI15-) were installed at the Hwy 9: Deadwood Slide site during construction in the fall of 15. The majority of construction work was completed by the end of November 15. The two SIs were read on June 1, 1 by Mr. Niraj Regmi, G.I.T. and Mr. Eddy Mar, E.I.T., both of Thurber Engineering Ltd. The SIs were read using a RST Digital Inclinometer probe with a ft. wheelbase and a RST Pocket PC readout. Inclinometer reading depths were defined as per cable markings with respect to the top of the inclinometer casings.. INTERPRETATION.1 General SI plots with A and B directions are presented in Section D and are summarized below. Where movement has been recorded, the resultant plot (X direction, if applicable) and a rate of movement have also been provided. 17 Roper Road, Edmonton, AB TB 3S5 T: F: thurber.ca
2 . Zones of Movement Zones of new movement were not observed in slope inclinometers SI15-1 and SI15- since the fall of 17 readings. Zones of movement are summarized in Table PH7-1-1 at the end of this report. This table also provides a historical account of the total movement, the depth of movement and the maximum rate of movement that has occurred at this site since the initialization of the slope inclinometers..3 Interpretation of Monitoring Results Slope inclinometer SI15-1 showed a rate of movement of. mm/yr over 5. m to 7. m depth since the fall of 17 readings. SI15- showed a rate of movement of 1. mm/yr over. m to 5. m depth since the fall of 17 readings. Historical groundwater levels recorded in the piezometers are summarized in Tables PH7-1- and PH7-1-3 at the end of this report. All piezometers at this site were damaged prior to or during construction. 3. RECOMMENDATIONS 3.1 Future Work The instruments should be read again during the fall of Instrumentation Repairs No instrumentation repairs are required at this time. Client: Alberta Transportation Date: August, 1 File: e-file: \\H\13351 rpt PH7-1 - Edm Page of
3 Date Monitored: June 1, 1 INSTRUMENT # SI15-1 SI15- DATE INITIALIZED October 1, 15 October 1, 15 TABLE PH7-1-1 SPRING 1 HWY 9: DEADWOOD SLIDE SLOPE INCLINOMETER INSTRUMENTATION READING SUMMARY TOTAL CUMULATIVE RESULTANT MOVEMENT AT NOTED DEPTH SINCE INITIAL READING (mm) 7.9 mm over 5. m to 7. m depth in 19 direction 5. mm over. m to 5. m depth in 15 direction MAXIMUM RATE OF MOVEMENT (mm/yr) 5 in October in October 15 CURRENT STATUS Operational Operational DATE OF PREVIOUS READING October 1, 17 October 1, 17 INCREMENTAL MOVEMENT SINCE PREVIOUS READING (mm) Drawing PH7-1-1 in Section D provides a sketch of the approximate locations of the monitoring instrumentation for this site. CURRENT RATE OF MOVEMENT (mm/yr) CHANGE IN RATE OF MOVEMENT SINCE PREVIOUS READING (mm/yr) Client: Alberta Transportation Date: August, 1 File: e-file: \\H\13351 rpt PH7-1 -Edm Page 3 of
4 INSTRUMENT # TABLE PH7-1- SPRING 1 HWY 9: DEADWOOD SLIDE STANDPIPE PIEZOMETER INSTRUMENTATION READING SUMMARY DATE INITIALIZED TIP DEPTH GROUND ELEV. SP1-1 November, CURRENT STATUS Blocked at 1.7 mbgs MAXIMUM GROUNDWATER LEVEL BGS. on November, on May 7, 11.3 on July 7, 11 GROUNDWATER LEVEL BGS.9 (Sept. 5, 13) SP1-3 November, Destroyed 1.9 (Oct. 1, 1) SP1-5 April 7, Damaged 1. (Sept. 17, 15) Drawing PH7-1-1 in Section D provides a sketch of the approximate locations of the monitoring instrumentation for this site. TABLE PH7-1-3 SPRING 1 HWY 9: DEADWOOD SLIDE VIBRATING WIRE PIEZOMETER INSTRUMENTATION READING SUMMARY INSTRUMENT DATE INITIALIZED TIP ELEV. GROUND ELEV. CURRENT STATUS MAXIMUM GROUNDWATER ELEVATION GROUNDWATER ELEVATION VW m on May 3, April 7, Destroyed (1D191) (1. mbgs) (May 3, 15) VW m on June, April 7, Destroyed (1D1917) (. mbgs) (June, 1) Drawing PH7-1-1 in Section D provides a sketch of the approximate locations of the monitoring instrumentation for this site. Client: Alberta Transportation Date: August, 1 File: e-file: \\H\13351 rpt PH7-1 -Edm Page of
5 ALBERTA TRANSPORTATION PEACE REGION (PEACE RIVER / HIGH LEVEL) INSTRUMENTATION MONITORING RESULTS SPRING 1 SECTION D DATA PRESENTATION SITE PH7-1: HWY 9:, DEADWOOD SLIDE
6 ALBERTA TRANSPORTATION PEACE REGION (PEACE RIVER / HIGH LEVEL) INSTRUMENTATION MONITORING FIELD SUMMARY (PH7-1) SPRING 1 Location: Deadwood Slide (HWY 9: C1.31) Readout: File Number: Extension: 3.3 Probe: RST Set 5R and R Temp: 1 Cable: RST Set 5R and R Read by: NKR/EM SLOPE INCLINOMETER (SI) READINGS SI# GPS Location Date Stickup from top Magn. North Current Bottom Remarks (UTM 11) of casing (ft) A+ Groove Readings Easting Northing A+ A- B+ B- SI Jun-1. 5 to SI Jun to * *USE DUMMY PROBE for next reading INSPECTOR REPORT
7 H:\13\13351 Geohazard Assessment - Peace RiverHigh Level (CON17)\Drafting\1\INST - SPRING\13351-PH7-1-1.dwg - Layout1 - Jul. 5, CREEK 57 5 EXTENT OF STOCKPILING (SEPT, 15) FRENCH DRAINS (TYP). (SEE DETAIL SHEET ) LIMIT OF TREE CLEARING SILT FENCE INSTALLED CLASS RIP RAP mm Ø C.SP. CULVERT SP1-3 (TH1-3) SI1-1 (TH1-) 9% SI15-1 SOIL COVERING MAT 5 5 CRACK AS OF SEPT, 15) VW1-1 VW1- SP1-5 SI15- DIP DOWNSLOPE SUBDRAIN (SEE DETAIL SHEET ) 53 SI1- (TH1-5) CRACK 55 5 SWALE LINED WITH TYPE "A" TEMPORARY RECP T T ACP PATCH SILT FENCE INSTALLED 5 USED NON-PERFORATED PIPE THROUGH CULVERT CLAY SEAL ZONE CLASS RIP RAP 5 HIGHWAY CREEK 53 W 5 51 SILT FENCE INSTALLED N S E 559 SP EXISTING CULVERT REMOVED NEW mm CULVERT INSTALLED (BF7371) Dunvegan Hines Creek PH7-1 Fairview Manning Peace River m SCALE 1: PEACE REGION (PEACE RIVER/ HIGH LEVEL) 1 LEGEND: 55 PH7-1: HWY 9: - DEADWOOD SLIDE INSTRUMENT LOCATIONS SI INSTRUMENT LOCATION INSTRUMENT NOT IN USE SLOPE INCLINOMETER SLOPE INCLINOMETER MOVEMENT DIRECTION DRAWN BY DESIGNED BY APPROVED BY SCALE DATE FILE No. ML BWN DWP 1: JULY DWG No PH7-1-1
8 Thurber Engineering Ltd LEGEND Initial 1 Oct 15 9 Oct Nov 15 1 Nov 15 May 1 Oct 1 1 Jun 17 1 Oct 17 1 Jun Ref. Elevation m Cumulative Deflection Direction A Incremental Deflection Direction A PH7-1 Deadwood Slide, Inclinometer SI15-1 Alberta Transportation H:\13\13351 Geohazard Assessment - Peace RiverHigh Level (CON17)\Instruments\Spring 1\SI Readings\PH 7\SI15-1.gtl
9 Thurber Engineering Ltd LEGEND Initial 1 Oct 15 9 Oct Nov 15 1 Nov 15 May 1 Oct 1 1 Jun 17 1 Oct 17 1 Jun Ref. Elevation m Cumulative Deflection Direction B Incremental Deflection Direction B PH7-1 Deadwood Slide, Inclinometer SI15-1 Alberta Transportation H:\13\13351 Geohazard Assessment - Peace RiverHigh Level (CON17)\Instruments\Spring 1\SI Readings\PH 7\SI15-1.gtl
10 Thurber Engineering Ltd. 1 Jan 1 1 Jul 1 1 Jan 17 1 Jul 17 1 Jan 1 1 Jul 1 7 Displacements shown are in the A Direction 7 5./7. m 5 5 Displ. (mm) Jan 1 1 Jul 1 1 Jan 17 1 Jul 17 1 Jan 1 1 Jul 1 PH7-1 Deadwood Slide, Inclinometer SI15-1 Alberta Transportation
11 Thurber Engineering Ltd LEGEND Initial 1 Oct 15 9 Oct Nov 15 1 Nov 15 May 1 Oct 1 1 Jun 17 1 Oct 17 1 Jun Ref. Elevation 51.3 m Cumulative Deflection Direction A Incremental Deflection Direction A PH7-1 Deadwood Slide, Inclinometer SI15- Alberta Transportation H:\13\13351 Geohazard Assessment - Peace RiverHigh Level (CON17)\Instruments\Spring 1\SI Readings\PH 7\SI15-.gtl
12 Thurber Engineering Ltd LEGEND Initial 1 Oct 15 9 Oct Nov 15 1 Nov 15 May 1 Oct 1 1 Jun 17 1 Oct 17 1 Jun Ref. Elevation 51.3 m Cumulative Deflection Direction B Incremental Deflection Direction B PH7-1 Deadwood Slide, Inclinometer SI15- Alberta Transportation H:\13\13351 Geohazard Assessment - Peace RiverHigh Level (CON17)\Instruments\Spring 1\SI Readings\PH 7\SI15-.gtl
13 Thurber Engineering Ltd LEGEND Initial 1 Oct 15 9 Oct Nov 15 1 Nov 15 May 1 Oct 1 1 Jun 17 1 Oct 17 1 Jun Ref. Elevation 51.3 m 1 1 skew = 31deg Cumulative Deflection Direction X Incremental Deflection Direction X PH7-1 Deadwood Slide, Inclinometer SI15- Alberta Transportation H:\13\13351 Geohazard Assessment - Peace RiverHigh Level (CON17)\Instruments\Spring 1\SI Readings\PH 7\SI15-.gtl
14 Thurber Engineering Ltd. 1 Jan 1 1 Jul 1 1 Jan 17 1 Jul 17 1 Jan 1 1 Jul 1 7 Displacements shown are in the X Direction (skew = 31 degrees) 7./5. m 5 5 Displ. (mm) Jan 1 1 Jul 1 1 Jan 17 1 Jul 17 1 Jan 1 1 Jul 1 PH7-1 Deadwood Slide, Inclinometer SI15- Alberta Transportation
To: Rishi Adhikari and Roger Skirrow From: Leslie Cho and Ian Darrach Alberta Transportation File: Date: June 30, 2016
To: Rishi Adhikari and Roger Skirrow From: Leslie Cho and Ian Darrach Stantec File: Date: June, Reference: North Central Region Edson Site NC HWY :, Deer Lodge Spring Task C: Instrumentation Monitoring
More informationThis report was prepared by Klohn Crippen Consultants Ltd. for Alberta Transportation Central Region under Contract No. CE053/2000.
Alberta Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 June 7, 2002 Mr. Melvin Mayfield, P.Eng. Project Engineer Dear Mr. Mayfield: Central Region Landslide Assessment Site
More informationJanuary 17, 2008 File:
January 17, 2008 File: 15-85-73 Alberta Infrastructure and Transportation Room 301, Provincial Building 9621-96 Avenue Peace River, Alberta T8S 1T4 Attention: Mr. Ed Szmata PEACE REGION (SWAN HILLS AREA)
More information1 PROJECT BACKGROUND. August 14, Alberta Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8
August 14, 2013 Alberta Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 Mr. Dennis Grace, P.Eng. Construction Engineer Dear Mr. Grace: Central Region Geohazard Assessment 2013
More informationFebruary 18, 2003 File: NORTH CENTRAL REGION LANDSLIDE ASSESSMENT HWY 43:16 WHITECOURT EAST HILL (NC1) 2002 ANNUAL INSPECTION REPORT
February 18, 2003 File: 15-76-11 Alberta Transportation Room 223, Provincial Building 4709 44 Avenue Stony Plain, Alberta T7Z 1N4 Attention: Mr. Rob Lonson, P.Eng. NORTH CENTRAL REGION LANDSLIDE ASSESSMENT
More informationSeptember 3, 2009 File: NORTH CENTRAL REGION GEOHAZARD ASSESSMENT HWY 40:28 NORTH OF CADOMIN (NC50) 2009 ANNUAL INSPECTION REPORT
GEOTECHNICAL ENVIRONMENTAL MATERIALS September 3, 2009 File: 15-16-226 Alberta Transportation 2 nd Floor, Provincial Building 111 54 Street Edson, Alberta T7E 1T2 Attention: Mr. Cliff Corner NORTH CENTRAL
More informationJanuary 12, 2006 File:
January 12, 2006 File: 15-85-13 Alberta Infrastructure and Transportation Room 301, Provincial Building 9621-96 Avenue Peace River, Alberta T8S 1T4 Attention: Mr. Ed Szmata PEACE REGION (PEACE HIGH LEVEL
More informationPEACE REGION (PEACE RIVER- HIGH LEVEL AREA) GEOHAZARD ASSESSMENT CALL-OUT PH56: EMBANKMENT FAILURE ON HWY 35:08 SOUTHWEST OF MEIKLE RIVER CROSSING
( (/)...,. - (D
More informationAugust 10, 2007 File:
August 10, 2007 File: 15-85-72 Alberta Infrastructure and Transportation Room 301, Provincial Building 9621-96 Avenue Peace River, AB T8S 1T4 Attention: Mr. Ed Szmata PEACE REGION (PEACE HIGH LEVEL AREA)
More informationCENTRAL REGION GEOHAZARDS RISK ASSESSMENT SITE INSPECTION FORM
SITE NUMBER AND NAME C55 H861:02 Slide LEGAL DESCRIPTION NW 14-40-14-W4 CENTRAL REGION GEOHAZARDS RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY & KM NAD 83 COORDINATES N 5811217 E 437291 PREVIOUS INSPECTION
More informationPEACE RIVER EAST HILL - HWY 2:60 (PH2) SELECT PHOTOGRAPHS August 22, 2007 File: Photo E003. Station May 2007
Photo E003 0+000 Viewing looking upslope at Site 4 from highway. Conditions unchanged from 2006. Photo E018 0+000 Localized erosion within road fill on upslope side of highway. Photo E022 0+250 Looking
More informationDrilled Shafts for Bridge Foundation Stability Improvement Ohio 833 Bridge over the Ohio River An Update
Drilled Shafts for Bridge Foundation Stability Improvement Ohio 833 Bridge over the Ohio River An Update Meigs County, Ohio Mason County, West Virginia By Stan Harris, P.E. and Eric Kistner, P.E. FMSM
More informationSlope Stability Evaluation Ground Anchor Construction Area White Point Landslide San Pedro District Los Angeles, California.
Slope Stability Evaluation Ground Anchor Construction Area White Point Landslide San Pedro District Los Angeles, California Submitted To: Mr. Gene Edwards City of Los Angeles Department of Public Works
More informationJackson County 2013 Weather Data
Jackson County 2013 Weather Data 61 Years of Weather Data Recorded at the UF/IFAS Marianna North Florida Research and Education Center Doug Mayo Jackson County Extension Director 1952-2008 Rainfall Data
More informationDecember 11, 2006 File:
December 11, 2006 File: 15-85-38 Alberta Infrastructure and Transportation Room 301, Provincial Building 9621-96 Avenue Peace River, Alberta T8S 1T4 Attention: Mr. Ed Szmata PEACE REGION (SWAN HILLS AREA)
More informationWHITE POINT LANDSLIDE GEOTECHNICAL INVESTIGATION November 29, 2012 Status Report
Gary Lee Moore, P.E., City Engineer Vince Jones, P.E., Deputy City Engineer WHITE POINT LANDSLIDE GEOTECHNICAL INVESTIGATION November 29, 2012 Status Report White Point Landslide Geotechnical Investigation
More informationThe results of KCB s site inspection observations and our recommendations for further work are presented herein.
July 14, 2015 Central Region 401, 4902 51 Street Red Deer, Alberta T4N 6K8 Mr. Tony Penney, P.Eng. Construction Engineer Dear Mr. Penney: June 25, 2015 Site Inspection Report The above site was visited
More information1 INTRODUCTION 1.1 General
#701 475 Howe Street Vancouver, British Columbia V6C 2B3 August 1, 2014 Robin McCall Wolverine Mine Environmental Superintendent Dear Mr. McCall: 1 INTRODUCTION 1.1 General This letter report presents
More informationPEACE REGION GRANDE PRAIRIE GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM NAD 83 COORDINATES N 6,178,811 E 403,309
PEACE REGION GRANDE PRAIRIE GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM SITE NUMBER GP-4a LEGAL DESCRIPTION LSD 12-10-78-4-W6M SITE NAME Burnt River Bridge - West Approach Slide HIGHWAY & KM Hwy 49:06
More informationChiang Rai Province CC Threat overview AAS1109 Mekong ARCC
Chiang Rai Province CC Threat overview AAS1109 Mekong ARCC This threat overview relies on projections of future climate change in the Mekong Basin for the period 2045-2069 compared to a baseline of 1980-2005.
More informationGAMINGRE 8/1/ of 7
FYE 09/30/92 JULY 92 0.00 254,550.00 0.00 0 0 0 0 0 0 0 0 0 254,550.00 0.00 0.00 0.00 0.00 254,550.00 AUG 10,616,710.31 5,299.95 845,656.83 84,565.68 61,084.86 23,480.82 339,734.73 135,893.89 67,946.95
More informationTable 1 - Infiltration Rates
Stantec Consulting Ltd. 100-300 Hagey Boulevard, Waterloo ON N2L 0A4 November 14, 2017 File: 161413228/10 Attention: Mr. Michael Witmer, BES, MPA, MCIP, RPP City of Guelph 1 Carden Street Guelph ON N1H
More informationdesign, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards.
design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards. In addition to the field inspection, Associated Engineers, Inc.
More informationHydro One (Sept 2014) Hydro One (Sept 2014) Hydro One (Sept 2014)
TABLE 1 WELL CONSTRUCTION DETAILS MOE WWR No Well ID Location Installation Date Status Easting Coordinates Northing Source Elevation Screened Interval Screened Material Borehole Well Stick-up Ground Top
More informationMonitoring on Subsidence Claims. John Parvin Subsidence Claims Manager
Monitoring on Subsidence Claims John Parvin Subsidence Claims Manager Key Milestones Subsidence cover 1972 Surge of claims1989/1990/1991 Project Management 1992 onwards Mitigation Surge 1995/2003 Delegated
More informationISSUED FOR CONSTRUCTION
PAGE No. DESCRIPTION 1 Cover Page 2 Overview Map 3 Western Road Plan View 4 Eastern Road Plan View West Road Profiles & Cross Sections 6-7 East Road Profiles 8- East Road Cross Sections 11-14 Campsite
More informationREDWOOD VALLEY SUBAREA
Independent Science Review Panel Conceptual Model of Watershed Hydrology, Surface Water and Groundwater Interactions and Stream Ecology for the Russian River Watershed Appendices A-1 APPENDIX A A-2 REDWOOD
More information3.12 Geology and Topography Affected Environment
3 Affected Environment and Environmental Consequences 3.12 Geology and Topography 3.12.1 Affected Environment 3.12.1.1 Earthquakes Sterling Highway MP 45 60 Project Draft SEIS The Kenai Peninsula is predisposed
More informationAppin Colliery - Longwall 705
REPORT: END OF PANEL SUBSIDENCE MONITORING REPORT BHP BILLITON ILLAWARRA COAL: Appin Colliery - Longwall 705 End of Panel Subsidence Monitoring Report for Appin Longwall 705 MSEC JUNE 2014 REPORT NUMBER:
More information1. PROJECT BACKGROUND. July 18, Alberta Infrastructure & Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8
July 18, 2005 Alberta Infrastructure & Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 Mr. Alain Momedi, P.Eng. Project Engineer Dear Mr. Momedi: H11:04 km 11.1 Erosion along
More informationGeosynthetics Applications and Performance Reviews Select Case Histories
Geosynthetics Applications and Performance Reviews Select Case Histories Debora J. Miller, Ph.D., P.E.; Dean B. Durkee,, Ph.D., P.E.; Michael A. Morrison, P.E., David B. Wilson, P.E., and Kevin Smith,
More informationJackson County 2018 Weather Data 67 Years of Weather Data Recorded at the UF/IFAS Marianna North Florida Research and Education Center
Jackson County 2018 Weather Data 67 Years of Weather Data Recorded at the UF/IFAS Marianna North Florida Research and Education Center Doug Mayo Jackson County Extension Director 1952-2008 Rainfall Data
More informationWEST QUESNEL LAND STABILITY PROGRAM ANNUAL MONITORING REPORT Prepared for:
AMEC Earth & Environmental A division of AMEC Americas Limited 3456 Opie Crescent, Prince George, BC Canada V2N 2P9 Tel +1 (250) 564-3243 Fax +1 (250) 562-7045 www.amec.com WEST QUESNEL LAND STABILITY
More informationData Report for White Point Landslide Boring B-12 W.O. E Task Order Solicitation San Pedro District Los Angeles, California
Data Report for White Point Landslide Boring B-12 W.O. E1907483 Task Order Solicitation 11-087 San Pedro District Los Angeles, California Submitted To: Mr. Christopher F. Johnson, P.E., G.E. City of Los
More informationStormwater Outlet Sediment Traps
Stormwater Outlet Traps SEDIMENT CONTROL TECHNIQUES Photo 1 Excavated sediment trap just prior to scheduled clean-out (note energy dissipater at end of pipe) Photo 2 A supplementary straw bale barrier
More information12"CMP DIA. ELEV. PVC CI DI CMP VCP RCP RCAP LRCP LCPP STA. LA LB BM-2 ROW PI POT LF TH PVC
PLANS FOR X-REFS: FILE PATH: Z:\WEST BRANCH 3682 MAIN STREET SIDEWALK IMPROVEMENTS - PHASE 3\DRAWINGS\_PRODUCTION DRAWINGS\TITLE & INDEX PLOTTED: Thursday, May 26, 216 4:7:42 PM MAIN STREET SIDEWALK PHASE
More information#10, 340 MacAlpine Crescent, Fort McMurray, AB T9H 4A8 T: F: thurber.ca. Attachment #1
#10, 340 MacAlpine Crescent, Fort McMurray, AB T9H 4A8 T: 780 743 1566 F: 780 743 1955 thurber.ca Attachment #1 TABLE OF CONTENTS 1. INTRODUCTION... 1 2. BACKGROUND AND SCOPE OF WORK... 1 3. METHODOLOGY...
More informationGeotechnical Investigation and Monitoring Results of a Landslide Failure at Southern Peninsular Malaysia (Part 1: Investigating Causes of Failure)
Geotechnical Investigation and Monitoring Results of a Landslide Failure at Southern Peninsular Malaysia (Part 1: Investigating Causes of Failure) Liew, S. S., Gue, S. S., Liong, C. H. Director, Gue &
More information8 VISIBILITY. 8.1 Setting. 8.2 Assessment Focus. Table 8-1: Key Issue for Visibility
Volume 2: Environmental and Sturgeon Upgrader Project 8 VISIBILITY 8.1 Setting The Project is in Sturgeon County within Alberta s Industrial Heartland area (the Heartland). The Heartland includes a number
More informationDrought Characterization. Examination of Extreme Precipitation Events
Drought Characterization Examination of Extreme Precipitation Events Extreme Precipitation Events During the Drought For the drought years (1999-2005) daily precipitation data was analyzed to find extreme
More informationChanging Hydrology under a Changing Climate for a Coastal Plain Watershed
Changing Hydrology under a Changing Climate for a Coastal Plain Watershed David Bosch USDA-ARS, Tifton, GA Jeff Arnold ARS Temple, TX and Peter Allen Baylor University, TX SEWRU Objectives 1. Project changes
More informationWind Resource Data Summary Cotal Area, Guam Data Summary and Transmittal for December 2011
Wind Resource Data Summary Cotal Area, Guam Data Summary and Transmittal for December 2011 Prepared for: GHD Inc. 194 Hernan Cortez Avenue 2nd Floor, Ste. 203 Hagatna, Guam 96910 January 2012 DNV Renewables
More informationSediment Trap. A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff through a stabilized spillway.
Sediment Trap SC-15 Source: Caltrans Construction Site Best Management Practices Manual, 2003. Description A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff
More informationGEOMECHANICAL MODELING OF THE STEINERNASE LANDSLIDE Alessio Ferrari, Lyesse Laloui and Christophe Bonnard
GEOMECHANICAL MODELING OF THE STEINERNASE LANDSLIDE Alessio Ferrari, Lyesse Laloui and Christophe Bonnard Ecole Polytechnique Fédérale de Lausanne Steinernase, 13 May 8 CONTENTS Main features Analysis
More informationProject No India Basin Shadow Study San Francisco, California, USA
Project No. 432301 India Basin Shadow Study San Francisco, California, USA Numerical Modelling Studies 04 th June 2018 For Build Inc. Report Title: India Basin Shadow Study San Francisco, California, USA
More informationGEOLOGICAL BRANCH ASSESSMENT REPORT 12. FItE NO: ACTION: THE GOLDEN MINING DIVISION, GOLDEN, Including THE NTS MAP; M82K/15W
ACTION: FItE NO: Including 1990 GEO-CHEM SURVEY RESULTS -- THE AVD CLAIMS - THE GOLDEN MINING DIVISION, GOLDEN, B.C. NTS MAP; M82K/15W Lat. 50 deg. 55 Min. Long 116 deg. 55 min. For GEOLOGICAL BRANCH ASSESSMENT
More informationConverse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services
Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services July 27, 2017 Ms. Rebecca Mitchell Mt. San Antonio College Facilities Planning & Management
More informationR.M.HARW & ASSOCIATES LTD. GEOTECHNICAL INVESTIGATION PROPOSED BRIDGE SITE. HELAVA CREEKl MILE MACKENZIE HIGHWAY E-2510 OCTOBER 16, 1973
El R.M.HARW & ASSOCIATES LTD. GEOTECHNICAL INVESTIGATION PROPOSED BRIDGE SITE HELAVA CREEKl MILE 616.4 MACKENZIE HIGHWAY E-2510 OCTOBER 16, 1973 R,M,HARDV & ASSOCIATES LTD. CONSULTING ENGINEERING & TESTING
More informationCoarse Sediment Traps
Coarse Sediment Traps SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils [2] Type 3 System Supplementary Trap Dispersive Soils [1] Though primarily
More informationAppendix A. Producer Statement Advisory Note
Appendix A Producer Statement Advisory Note Ref. No. 17095 26 May 2017 PRODUCER STATEMENT CONSTRUCTION REVIEW (PS4) IMPORTANT ADVISORY NOTE The Building Consent Authority (BCA) frequently requires Producer
More informationLandslide Investigation on State Route 7 along the Ohio River
Landslide Investigation on State Route 7 along the Ohio River Peter Narsavage, P.E. DLZ Ohio, Inc. Paul D. deverteuil, P.E. Hull & Associates, Inc. Site Location Gallia 7 Landslide Area Gallipolis, Ohio
More informationAppendix C Surface Water and Groundwater Interaction Memorandum
Texas Custodial Trust 2301 West Paisano Drive El Paso, Texas 79922 Appendix C Surface Water and Groundwater Interaction Memorandum 6835001 Malcolm Pirnie, Inc. 410 N. 44 th Street, Suite 1000 Phoenix,
More informationButte County Drought Task Force December 1, :00 AM noon 202 Mira Loma Drive, Tahoe Room Oroville, CA. Agenda
WATER AND RESOURCE CONSERVATION 308 Nelson Avenue, Oroville, CA 95965 Telephone: (530) 538-4343 Fax: (530) 538-3807 www.buttecounty.net/waterandresource bcwater@buttecounty.net Paul Gosselin, Director
More informationSediment Trap. At multiple locations within the project site where sediment control is needed.
Sediment Trap SE-3 Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control
More informationMemo. I. Executive Summary. II. ALERT Data Source. III. General System-Wide Reporting Summary. Date: January 26, 2009 To: From: Subject:
Memo Date: January 26, 2009 To: From: Subject: Kevin Stewart Markus Ritsch 2010 Annual Legacy ALERT Data Analysis Summary Report I. Executive Summary The Urban Drainage and Flood Control District (District)
More informationMinnesota s Climatic Conditions, Outlook, and Impacts on Agriculture. Today. 1. The weather and climate of 2017 to date
Minnesota s Climatic Conditions, Outlook, and Impacts on Agriculture Kenny Blumenfeld, State Climatology Office Crop Insurance Conference, Sep 13, 2017 Today 1. The weather and climate of 2017 to date
More informationSOIL INVESTIGATION REPORT. PROPOSED HOUSING DEVELOPMENT PROJECT Coral Spring, Trelawny, Jamaica.
SOIL INVESTIGATION REPORT PROPOSED HOUSING DEVELOPMENT PROJECT Coral Spring, Trelawny, Jamaica. Prepared for: FCS Consultants 7a Barbados Avenue Kingston 5, Jamaica Prepared by: NHL Engineering Limited
More informationRock & Aggregate Drop Inlet Protection
Rock & Aggregate Drop Inlet Protection SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System Supplementary Trap Dispersive Soils
More informationBudge Road Landslide Jackson Extensometer installation report April 2014 with data to 20 May
Budge Road Landslide Jackson Extensometer installation report 23-27 April 14 with data to May Four extensometers were installed across fissures at the head of the Budge Road landslide on the East Gros
More informationLEGEND BUSINESS ZONE NORTH OF AGRESEARCH BOREHOLE CPT SEISMIC CPT AUGER SCALE. Powells Road TEST PIT AGRESEARCH INNOVATION PARK. Hamilton Ring Road
LEGEND ra R aku Ru BUSINESS ZONE NORTH OF Powells Road oad AGRESEARCH BOREHOLE CPT SEISMIC CPT AUGER SCALE 3 mm TEST PIT AS121 SCPT12 TP18 BH13 TP15 2 AS125 AS126 TP14 BH12 AGRESEARCH CPT13 TP17 INNOVATION
More informationNational Integrated Drought Information System. Southeast US Pilot for Apalachicola- Flint-Chattahoochee River Basin 20-March-2012
National Integrated Drought Information System Southeast US Pilot for Apalachicola- Flint-Chattahoochee River Basin 20-March-2012 Current drought status from Drought Monitor http://www.drought.unl.edu/dm/monitor.html
More informationMARMOT CREEK BASIN: MANAGING FORESTS FOR WATER
MARMOT CREEK BASIN: MANAGING FORESTS FOR WATER CABIN AND TWIN CREEK EXPERIMENTS 1962-1987 MARMOT CREEK SUBBASINS Subbasin Drainage Treatment Area (ha) (completion date) Cabin Creek 212 (50%)* Commercial
More informationU-Shaped Sediment Traps
U-Shaped Sediment Traps SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils [1] Type 3 System Supplementary Trap Dispersive Soils [1] Generally
More informationSeptember 18, 2017 Project No.: 5077
#109 3011 Underhill Avenue Burnaby, BC V5A 3C2 Phone: (604) 421-3288 Email: info@terrangeo.com September 18, 2017 Project No.: 5077 Kevin Brooks City of Campbell River 301 St. Ann s Road Campbell River,
More informationTreasury Metals Incorporated Goliath Gold Project Environmental Impact Statement
Treasury Metals Incorporated Environmental Impact Statement APPENDIX N SURFACE HYDROLOGY STUDY N TREASURY METALS INC. GOLIATH GOLD PROJECT HYDROLOGY 2013 BASELINE STUDY Prepared for: Treasury Metals Inc.
More informationRock Sizing for Multi-Pipe & Culvert Outlets
Rock Sizing for Multi-Pipe & Culvert Outlets STORMWATER AND WATERWAY MANAGEMENT PRACTICES Photo 1 Rock pad outlet structure at end of a duel stormwater pipe outlet Photo 2 Rock pad outlet structure at
More informationSTREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1. DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT
STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1 DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT Prepared by: PAULUS, SOKOLOWSKI & SARTOR STORMWATER MANAGEMENT 1. Methodology
More informationMass Wasting. Mass Wasting. Earth s s External Processes
1 Mass Wasting Presentation Modified from Instructor Resource Center on CD-ROM, Foundations of Earth Science, 4 th Edition, Lutgens & Tarbuck Mass Wasting 2 Down-slope movement of rock, loose material
More informationSTATISTICAL FORECASTING and SEASONALITY (M. E. Ippolito; )
STATISTICAL FORECASTING and SEASONALITY (M. E. Ippolito; 10-6-13) PART I OVERVIEW The following discussion expands upon exponential smoothing and seasonality as presented in Chapter 11, Forecasting, in
More informationSuitable Applications Sediment traps should be considered for use:
Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective
More informationClimate Change Impact Assessment on Long Term Water Budget for Maitland Catchment in Southern Ontario
215 SWAT CONFERENCE, PURDUE Climate Change Impact Assessment on Long Term Water Budget for Maitland Catchment in Southern Ontario By Vinod Chilkoti Aakash Bagchi Tirupati Bolisetti Ram Balachandar Contents
More informationWoodford County Erosion Prevention Plan and Permit. Application #
Woodford County Erosion Prevention Plan and Permit Application # Date Instructions: Applicant will complete Parts A and B, and attach a proposed site diagram. This diagram must be completed in accordance
More informationGotechnical Investigations and Sampling
Gotechnical Investigations and Sampling Amit Prashant Indian Institute of Technology Gandhinagar Short Course on Geotechnical Investigations for Structural Engineering 12 14 October, 2017 1 Purpose of
More informationComparison of Particulate Monitoring Methods at Fort Air Partnership Monitoring Stations
Comparison of Particulate Monitoring Methods at Fort Air Partnership Monitoring Stations Melanie Larsen Harry Benders RS Environmental (Tom Dann) March 13, 2014 Executive Summary Historically FAP has acquired
More informationUse of Shredded Tires for Lightweight Fill
36 TANSPOTATION ESEACH ECOD 1422 Use of Shredded Tires for Lightweight Fill ICHAD J. UPTON AND GEOGE MACHAN Shredded waste tires were used as lightweight fill to repair a landslide in a highway improvement
More informationThree main areas of work:
Task 2: Climate Information 1 Task 2: Climate Information Three main areas of work: Collect historical and projected weather and climate data Conduct storm surge and wave modeling, sea-level rise (SLR)
More information2019 Settlement Calendar for ASX Cash Market Products. ASX Settlement
2019 Settlement Calendar for ASX Cash Market Products ASX Settlement Settlement Calendar for ASX Cash Market Products 1 ASX Settlement Pty Limited (ASX Settlement) operates a trade date plus two Business
More informationFluvial Driven Alluvial Fans
Fluvial Driven Alluvial Fans Restoration Project Evaluations - Examples from the Russian and Napa River Watersheds Mia Docto Masters Thesis UC Berkeley 1. Basic Fan Description 2. Fluvial Driven Fan Characteristics
More informationCLIMOGRAPH UNIT: s^io
Narrre: Block: Date: CLIMOGRAPH UNIT: s^io The climate can be defined as the average amount of rainfall, and the average temperature in a region. The climate of a region affects the type of soil that is
More informationNORTHUMBERLAND COUNTY, PA
QUAKER RUN Stream and Wetland Restoration As-Built Completion Report and First Year Monitoring Data Coal Township NORTHUMBERLAND COUNTY, PA Upstream Before Upstream After Prepared for: COAL TOWNSHIP 805
More informationCulvert and Pipe Phasing
Culvert and Pipe Phasing Barney Blackburn, PE, CPESC, CPSWQ NCDOT Roadside Environmental Unit Soil & Water Engineering Section Supervisor NCDOT Culvert Phasing Process Hydraulics Unit: Culvert Survey Report
More informationAPPENDIX A: EROSION & SEDIMENT CONTROL FORMS
APPENDIX A: EROSION & SEDIMENT CONTROL FORMS Croy Engineering # 1580.08 EROSION & SEDIMENT CONTROL FORMS Appendix-1 This page intentionally left blank. Croy Engineering # 1580.08 EROSION & SEDIMENT CONTROL
More informationEffects of the slope toe evolution on the behaviour of a slow-moving large landslide
Effects of the slope toe evolution on the behaviour of a slow-moving large landslide A. Ferrari, A. Ledesma, J. Corominas MOUNTAIN RISKS - Topic Meeting WB1 Dynamic spatial modelling of landslide hazards
More informationJuly 2017 LOGISTICAL HARMONY
Li s&staging(wpedestriansidewalkprot.) (4/18/through7/18/2017) July2017 101BelvidereEastFaçadeWorkPipeStaging (4/18/through7/18/2017) 101BelvidereEastFaçadeWork (through8/31/2017) Legend RampaccesstoTMCX
More informationQuality Pavement Markings
Quality Pavement Markings Idaho Asphalt Conference Moscow, Idaho October 26, 2006 Purpose of Pavement Markings Provide the visual information needed by the driver to guide their vehicle Ed Lagergren,,
More informationZUMWALT WEATHER AND CLIMATE ANNUAL REPORT ( )
ZUMWALT WEATHER AND CLIMATE ANNUAL REPORT (26-29) FINAL DRAFT (9 AUGUST 21) J.D. HANSEN 1, R.V. TAYLOR 2, AND V.S. JANSEN 3 INTRODUCTION The Zumwalt Prairie in northeastern Oregon is a unique grassland
More informationAgry 465 Exam October 18, 2006 (100 points) (9 pages)
Agry 465 Exam October 18, 2006 (100 points) (9 pages) Name (4) 1. In each of the following pairs of soils, indicate which one would have the greatest volumetric heat capacity, and which would have the
More informationOctober 26, Ms. Aimee Zack Canadian Pacific 120 S. Sixth Street Suite 900 Minneapolis, Minnesota 55402
October 26, 2017 Ms. Aimee Zack Canadian Pacific 120 S. Sixth Street Suite 900 Minneapolis, Minnesota 55402 Re: Soo Line Dump Site 2017 Annual Soil Cover Inspection Dear Aimee: The purpose of this letter
More information2 Groundwater Basin Monitoring
Zone 7 Water Agency 2 Groundwater Basin Monitoring Programs 2.1 Climatological Monitoring 2 Groundwater Basin Monitoring Programs This section describes Zone 7's Climatological Monitoring Program which
More informationEtobicoke Exfiltration System: Monitoring and Evaluation. Tim Van Seters Ryerson University July 24, 2015
Etobicoke Exfiltration System: Monitoring and Evaluation Tim Van Seters Ryerson University July 24, 2015 Presentation Outline Summary of 1994 1995 Candaras Associates study Summary of 1996-1998 SWAMP Study
More information[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area.
Sediment Trench SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils [1] Performance of
More informationJanuary 16, Re: Soo Line Dump Site 2018 Annual Soil Cover Inspection. Dear Mr. Nichols:
January 16, 2019 Mr. Andrew Nichols Minnesota Pollution Control Agency Voluntary Investigation and Cleanup Program 520 Lafayette Road Saint Paul, Minnesota 55155 Re: Soo Line Dump Site 2018 Annual Soil
More informationArea-wide geotechnical information summary for CERA zoning review panel
Area-wide geotechnical information summary for CERA zoning review panel This document contains all the area-wide geotechnical information which was considered by CERA as part of the process for making
More informationDrainage Used to Control Movements of a Large Rock Slide in Canada
SECTION2 Drainage Control for Surface Mines 19 Drainage Used to Control Movements of a Large Rock Slide in Canada by John C. Sharp, Consultant/Principal, Golder Associates, Maidenhead, Berkshire, United
More informationJackson County 2014 Weather Data
Jackson County 2014 Weather Data 62 Years of Weather Data Recorded at the UF/IFAS Marianna North Florida Research and Education Center Doug Mayo Jackson County Extension Director 1952-2008 Rainfall Data
More informationChampaign-Urbana 2000 Annual Weather Summary
Champaign-Urbana 2000 Annual Weather Summary ILLINOIS STATE WATER SURVEY 2204 Griffith Dr. Champaign, IL 61820 wxobsrvr@sws.uiuc.edu Maria Peters, Weather Observer January: January started on a mild note,
More informationPractice Test Chapter 8 Sinusoidal Functions
FOM 12 Practice Test Chapter 8 Sinusoidal Functions Name: Multiple Choice Identify the choice that best completes the statement or answers the question. Block: _ 1. Convert 120 into radians. A. 2" 3 B.
More informationMonitoring and Characterization of the Meadowview Lane Landslide: Boyd County, KY
Monitoring and Characterization of the Meadowview Lane Landslide: Boyd County, KY Matt Crawford Appalachian Coalition for Geologic Hazards in Transportation 13 th Annual Technical Forum Harrisonburg, VA
More informationSlope Stability Assessment Proposed Development 4401 Fallowfield Road Lands Ottawa, Ontario Rev-02
REPORT August 2014 REPORT ON Slope Stability Assessment Proposed Development 4401 Fallowfield Road Lands Ottawa, Ontario Submitted to: DCR Phoenix Homes 18 Bentley Avenue Ottawa, Ontario K2E 6T8 Report
More informationEvaluation of Geotechnical Hazards
Evaluation of Geotechnical Hazards by Geoffrey R. Martin Appendix B: Evaluation of Geotechnical Hazards Describes Evaluation Procedures Soil Liquefaction Soil Settlement Surface Fault Rupture Flooding
More information