September 3, 2009 File: NORTH CENTRAL REGION GEOHAZARD ASSESSMENT HWY 40:28 NORTH OF CADOMIN (NC50) 2009 ANNUAL INSPECTION REPORT

Size: px
Start display at page:

Download "September 3, 2009 File: NORTH CENTRAL REGION GEOHAZARD ASSESSMENT HWY 40:28 NORTH OF CADOMIN (NC50) 2009 ANNUAL INSPECTION REPORT"

Transcription

1 GEOTECHNICAL ENVIRONMENTAL MATERIALS September 3, 2009 File: Alberta Transportation 2 nd Floor, Provincial Building Street Edson, Alberta T7E 1T2 Attention: Mr. Cliff Corner NORTH CENTRAL REGION GEOHAZARD ASSESSMENT HWY 40:28 NORTH OF CADOMIN (NC50) 2009 ANNUAL INSPECTION REPORT Dear Sir: This letter documents the 2009 annual site inspection of the slope failure on Hwy 40:28 (km 11.7) north of the Hamlet of Cadomin at legal land description NW W5M (Figure NC50-1, Section F). Thurber Engineering Ltd. (Thurber) undertook this inspection in partial fulfillment of our Geotechnical Services for Geohazard Assessment, Instrumentation Monitoring and Related Work contract (CE103/2008) with Alberta Transportation (AT). Mr. Don Law, P.Eng. and Mr. Ken Froese, P.Eng., of Thurber undertook the inspection on June 16, 2009, in the presence of Mr. Roger Skirrow, P.Eng., Mr. Neil Kjelland, P.Eng., Mr. Howard Hawley, Mr. Jeff Zhang, E.I.T., and Mr. Cliff Corner, of AT. 1. BACKGROUND AND RECENT WORK A section of the highway located 200 m west of NC50 was realigned in about 2000 or 2001 due to slide activity. At that time, subdrains were installed in the south ditch to lower the groundwater table. The current distress at the NC50 location was first observed during a call-out conducted by Thurber on August 3, 2005, as summarized in a letter to AT dated August 16, 2005, included in Section E of the binder. Suite 200, Avenue, EDMONTON, AB, Canada T6E 6A5 T F EDMONTON CALGARY FORT McMURRAY VANCOUVER VICTORIA TORONTO KAMLOOPS SQUAMISH

2 A geotechnical investigation was conducted by Jacques Whitford (report dated December 19, 2006) which included the installation of two slope inclinometers and three standpipe piezometers. The report includes conceptual remedial measures for the slide. Since the 2007 site visit, several patches have been placed through this area to reduce the differential height across the crack for safety reasons. In early 2009, a conceptual design study was completed by Thurber and summarized in a report to AT dated April 30, The conceptual design study reviewed available published information regarding the site s history and geological environment. An airphoto interpretation was also undertaken for the site. Two primary alternatives were considered in the conceptual study: a pile retaining wall structure and realignment of the highway. The realignment design was undertaken by Genivar Consultants using LiDAR data for the site and considered 10 m and 20 m offset options. The pile wall alternative considered cantilever and tie-back options. The LiDAR data was also utilized for preliminary slope stability assessments of the existing slopes (downslope and upslope of the highway) to determine the improvements anticipated from and the feasibility of the options considered. Based on the cost of the alternatives and the relative risk including an assessment of the likelihood of additional slides developing in the realignment zone, it was recommended that the pile wall alternative be chosen. A geotechnical drilling program was undertaken by Thurber in May 2009 and the results of this investigation are presented under separate cover. Following the drilling program, the preliminary design was undertaken for the pile wall option. Based on the result of the preliminary design cost estimates, the chosen pile wall will be 1.8 m diameter cantilever piles spaced at 1.5 diameters (centre to centre). Detailed design and tender preparation is scheduled to be completed by the end of September with construction tentatively planned for the winter of 2009/ SITE OBSERVATIONS 2.1 Main Slide The roadway is located on a sidehill fill with the terrain sloping steeply to the north toward Gregg River. The river is located about 70 m (horizontal distance) from the edge of the highway and is approximately 25 m lower in elevation. Exposed bedrock was noted on the far (north) bank of the Gregg River below about 4 m above river elevation. The terrain between the highway and the creek was heavily treed with a thin organic cover. The distressed area of the pavement is about 45 m in length and affects the west-bound lanes. The crack pattern is arc-shaped and has a differential height File: Page 2 of 8

3 across the crack of up to 170 mm as noted on Figure NC50-1, attached for inclusion in Section F. The crack extends beyond the pavement into the sideslope of the highway and through the ditch an additional 40 m to the west (distance measured parallel to the highway alignment and corrected from previous reports) and 10 m east of where it leaves the pavement surface at the east end of the pavement distress. There was also evidence of an old slump located about 15 m north of the active scarp adjacent to the west half of the main scarp which appears to have re-activated since the 2007 site visit; however, does not appear to have changed substantially since the 2008 visit. As noted during previous visits, a toe roll exists near the toe of the slope adjacent to the Gregg River, located approximately as shown on the site plan. Water was also noted seeping from a few locations in the lower third of the sideslope as shown on the attached figures. The highway backslope is about 13 m high and inclined at a slope angle of about 3H:1V. A water collection ditch is located along the top of the backslope which discharges into a riprap-lined channel leading to a 1000 mm diameter culvert. Several shallow slides have formed in the backslope located as shown on the site plan and are similar in distribution as noted last year. There were no signs of seepage in the backslope. A small erosion gully was noted about 30 m west of the riprap channel as shown on the site plan. The 1000 mm diameter culvert is located at the edge of the eastern extent of the active scarp. At the time of the site visit, the culvert appeared to be unaffected by the current slope movement. A 150 mm diameter corrugated steel pipe subdrain outlet was observed at the base of the highway embankment near the west edge of the active scarp. No flow was observed from the pipe once the soil blocking the outlet was removed. There is no evidence in the backslope of an inlet for this pipe. Selected photographs taken during the site reconnaissance are attached. 2.2 Additional Slides The 2008 site reconnaissance was extended to include areas of potential instability observed on satellite imagery. The reconnaissance extended about 250 m west to the twin culverts and half-culvert drop structures at approximately km This are was observed again in Skin slides were observed on the sideslope on both sides of the twin half-culverts. An old slump was located about 80 m east of the culverts (160 m west of the main slide) and 18 m north of the highway. These feature locations are shown File: Page 3 of 8

4 approximately on Figure NC50-1. The scarp was about 1.5 m high and there was no evidence of recent movement. In addition, the three active slides first noted in 2008 between 70 m and 110 m west of the twin culverts (located approximately as shown on Figure NC50-1) were viewed during the 2009 site reconnaissance. These slides were located within the forested portion of the valley and about 40 m north of the highway. The slides range in width from about 4 m to 10 m with measured slope angles between 38 and 45 to the horizontal, and extend to the bottom of the slope at the river. These features do not appear to have increased size since the 2008 visit. 2.3 Other Locations with Potential to Impact the Highway The 2009 conceptual design study included a review of LiDAR imagery of the site and surrounding area. A total of five areas were identified during the study where impingement by the Gregg River on the slopes below the Hwy 40:28 embankment may result in future slope movements that may impact the highway embankment in the long term. The potential locations were ranked in order of estimated priority. During the 2009 site visit, a brief reconnaissance was made of each of the features to confirm that the ranking based on the review of LiDAR imagery was appropriate. A site plan showing the LiDAR image and the confirmed rankings is included as Figure NC50-3 for inclusion in Section F. Note that the highest rank (1) is the current instability and the lowest rank (5) is the least likely to exhibit failure in the future. In most cases, it was determined that the area of impingement had exposed bedrock well above river level and thus have a low risk for large-scale slope movement. 3. MONITORING RESULTS AND ASSESSMENT 3.1 Stratigraphy The soil conditions encountered during the instrumentation installation by Thurber in May 2009 generally consisted of surficial fill overlying clay, clay till, and siltstone bedrock. This is consistent with the results of previous investigation carried out at this site. The siltstone bedrock was encountered at depths between 14.5 m and 16.4 m below ground surface. An updated stratigraphic cross-section based on the recent drilling results is provided in Figure NC50-2 attached. 3.2 Instrumentation New instrumentation was installed about three weeks before the readings taken on June 4, As part of the pile wall investigation program, an additional set of readings was taken at this site on June 29, During the May 2009 installation File: Page 4 of 8

5 program, SP1, SI2, and SP2 were destroyed. The following summarizes the monitoring results from 2009: Slope inclinometers SI1 and SI2 were installed in July 2006 and had sheared off at the time of the Spring 2007 readings. The depths of shearing were confirmed in August 2007: SI1 at 5.1 m below ground surface and SI2 at 4.9 m. The zone of movement had been at about 5.5 m to 6 m below ground in both inclinometers. The open standpipe piezometers installed in July 2006 site had reported depths of between about 9.5 m and 10.5 m below ground surface. As of Spring 2008, SP2 had sheared off at 6.2 m below ground surface. SP1 was damaged in May 2009 and SP3 was not read. The movement depths measured in the slope inclinometers installed in the main slide (SI09-4, -5, -7, and -8) were measured between 5.6 m and 6.5 m below ground surface. The cumulative movements between May 22 (initial reading) and June 29 (most recent reading) were between 4 mm and 9 mm giving movement rates between 21 mm and 83 mm per year. The current movement rates are lower than those measured shortly after initialization on June 4, Two pneumatic piezometers (PN09-5 and -7) were installed in the main slide in May The measured water levels on June 29 were 10.5 m and 11.9 m, respectively, below ground surface. This water level is located in the lower 2 m of the clay till (just above the bedrock contact). A slope inclinometer and pneumatic piezometer pair (SI09-10 and PN09-10) were installed downslope of the old slump located about 160 m west of the centre of the main slide. The first reading (June 4, 2009) following initialization did not discern a movement zone. However, the second reading taken June 29, 2009, did note slight movement at 5.6 m below ground surface but the cumulative movement to date is only 1 mm at a rate of 10 mm per year. The water level measured in the pneumatic piezometer was 13.1 m below ground level which is in the clay till just above the bedrock contact. 3.3 Assessment Based on the observed cracking pattern at the surface, the depths of movement recorded in the slope inclinometers, and the presence of a toe-roll just above river elevation, it appears that the movement is a result of a translation slide. The slip surface appears to be located in the clay above the clay till and may be sliding along the bedrock surface near the toe of the slide. Groundwater does not appear to be a contributing factor to instability within the upper portion of the main slide File: Page 5 of 8

6 mass. Seepage was observed in the lower third of the slope which may be destabilizing the lower portion of the slide. High groundwater levels (when present) appear to be contributing to backslope instability in this area. As noted in the 2008 Geohazard report, it appears that the translational and skin slides are a frequent occurrence along this slope. The zones of movement observed to the west are expected to be similar to the main slide: potentially sliding in the clay on top of the clay till near the highway elevation and on top of the bedrock further down the slope. The presence of a slight movement in the slope inclinometer installed at the old scarp feature located near the twin culverts about 160 m west of the main slide indicates that this is a potential slide. It is expected that there is a low risk to the highway from this feature at this time as there is bedrock exposed at the toe of this slope which reduces the possibility of large-scale, deep-seated movement. It does not eliminate the possibility of a translation slide over the bedrock (such as the skin slides seen within the tree line) unloading the toe associated with the scarp and causing additional movement such as seen at the main slide. At this older scarp location, there is adequate distance from the highway such that remedial action could be taken before the embankment was threatened should the failure regress toward the highway. 4. RISK LEVEL The risk level for this site has been assessed as follows: PF(14) * CF(4) = 56 A Probability Factor of 14 is considered appropriate since the slide is active with a high rate of ongoing movement. A Consequence Factor of 4 is applicable since the embankment is relatively high and a partial closure of the road has already occurred as a result of slide movement and the east culvert could be threatened. This risk level is the same as applied in 2008 and higher than the risk level of 52 applied in RECOMMENDATIONS 5.1 Short Term It is understood that the previously recommended detour will be constructed on the south side of the highway. Additional fill material should not be placed on the north shoulder as its weight may accelerate the movements which may trigger retrogressive scarp development further into the traveling lanes of the highway. The detour fill should not impede the ditch drainage. It is also recommended that a File: Page 6 of 8

7 light-weight non-woven geotextile be placed on the ground surface prior to placing the granular fill for the detour to facilitate its removal once the roadway surface has been stabilized and repaired. This section of road should be monitored for further regression of the slide and signage or barricades should remain in place to warn motorists and to keep vehicle traffic away from the north shoulder. 5.2 Long Term Based on the results of the preliminary design and a meeting with AT, it has been determined that a large-diameter, cast-in-place concrete cantilever pile wall will be constructed to the stabilize the highway embankment. In conjunction with the installation of the pile wall, minor ditch grading will be undertaken downslope of the highway to facilitate drainage of surface away from the slip surface. It is anticipated that the pile wall will go to tender in late 2009 with all construction and roadway repair completed by mid Investigation The recommended geotechnical investigation at this site was completed by Thurber in May Further investigation is not warranted at this time. 5.4 Maintenance This section of highway should be inspected regularly by the MCI to check for significant changes in the movement which could lead to further risk to the highway and traffic. The patching and infilling that is currently being done may continue to be required; however, it is preferred that the detour recommended above be constructed rather than continuing to load the top of the slide with additional weight. It is recommended to continue monitoring the existing instrumentation on a semi-annual basis, and to undertake annual geotechnical inspections as currently programmed. File: Page 7 of 8

8 6. CLOSURE We trust this assessment and recommendations meet with your needs at this time. Please contact the undersigned should questions arise or if the slide condition worsens. Yours very truly, Thurber Engineering Ltd. Don Law, P.Eng. Review Principal Ken Froese, P.Eng. Project Engineer /dw Attachments Photographs 1 to 8 Figures NC50-1 and NC50-2 cc: Mr. Roger Skirrow, P.Eng., Director of Geotechnical Services, AT File: Page 8 of 8

January 17, 2008 File:

January 17, 2008 File: January 17, 2008 File: 15-85-73 Alberta Infrastructure and Transportation Room 301, Provincial Building 9621-96 Avenue Peace River, Alberta T8S 1T4 Attention: Mr. Ed Szmata PEACE REGION (SWAN HILLS AREA)

More information

February 18, 2003 File: NORTH CENTRAL REGION LANDSLIDE ASSESSMENT HWY 43:16 WHITECOURT EAST HILL (NC1) 2002 ANNUAL INSPECTION REPORT

February 18, 2003 File: NORTH CENTRAL REGION LANDSLIDE ASSESSMENT HWY 43:16 WHITECOURT EAST HILL (NC1) 2002 ANNUAL INSPECTION REPORT February 18, 2003 File: 15-76-11 Alberta Transportation Room 223, Provincial Building 4709 44 Avenue Stony Plain, Alberta T7Z 1N4 Attention: Mr. Rob Lonson, P.Eng. NORTH CENTRAL REGION LANDSLIDE ASSESSMENT

More information

January 12, 2006 File:

January 12, 2006 File: January 12, 2006 File: 15-85-13 Alberta Infrastructure and Transportation Room 301, Provincial Building 9621-96 Avenue Peace River, Alberta T8S 1T4 Attention: Mr. Ed Szmata PEACE REGION (PEACE HIGH LEVEL

More information

December 11, 2006 File:

December 11, 2006 File: December 11, 2006 File: 15-85-38 Alberta Infrastructure and Transportation Room 301, Provincial Building 9621-96 Avenue Peace River, Alberta T8S 1T4 Attention: Mr. Ed Szmata PEACE REGION (SWAN HILLS AREA)

More information

This report was prepared by Klohn Crippen Consultants Ltd. for Alberta Transportation Central Region under Contract No. CE053/2000.

This report was prepared by Klohn Crippen Consultants Ltd. for Alberta Transportation Central Region under Contract No. CE053/2000. Alberta Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 June 7, 2002 Mr. Melvin Mayfield, P.Eng. Project Engineer Dear Mr. Mayfield: Central Region Landslide Assessment Site

More information

1 PROJECT BACKGROUND. August 14, Alberta Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8

1 PROJECT BACKGROUND. August 14, Alberta Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8 August 14, 2013 Alberta Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 Mr. Dennis Grace, P.Eng. Construction Engineer Dear Mr. Grace: Central Region Geohazard Assessment 2013

More information

August 10, 2007 File:

August 10, 2007 File: August 10, 2007 File: 15-85-72 Alberta Infrastructure and Transportation Room 301, Provincial Building 9621-96 Avenue Peace River, AB T8S 1T4 Attention: Mr. Ed Szmata PEACE REGION (PEACE HIGH LEVEL AREA)

More information

PEACE REGION GRANDE PRAIRIE GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM NAD 83 COORDINATES N 6,178,811 E 403,309

PEACE REGION GRANDE PRAIRIE GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM NAD 83 COORDINATES N 6,178,811 E 403,309 PEACE REGION GRANDE PRAIRIE GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM SITE NUMBER GP-4a LEGAL DESCRIPTION LSD 12-10-78-4-W6M SITE NAME Burnt River Bridge - West Approach Slide HIGHWAY & KM Hwy 49:06

More information

CENTRAL REGION GEOHAZARDS RISK ASSESSMENT SITE INSPECTION FORM

CENTRAL REGION GEOHAZARDS RISK ASSESSMENT SITE INSPECTION FORM SITE NUMBER AND NAME C55 H861:02 Slide LEGAL DESCRIPTION NW 14-40-14-W4 CENTRAL REGION GEOHAZARDS RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY & KM NAD 83 COORDINATES N 5811217 E 437291 PREVIOUS INSPECTION

More information

1. PROJECT BACKGROUND. July 18, Alberta Infrastructure & Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8

1. PROJECT BACKGROUND. July 18, Alberta Infrastructure & Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8 July 18, 2005 Alberta Infrastructure & Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 Mr. Alain Momedi, P.Eng. Project Engineer Dear Mr. Momedi: H11:04 km 11.1 Erosion along

More information

The results of KCB s site inspection observations and our recommendations for further work are presented herein.

The results of KCB s site inspection observations and our recommendations for further work are presented herein. July 14, 2015 Central Region 401, 4902 51 Street Red Deer, Alberta T4N 6K8 Mr. Tony Penney, P.Eng. Construction Engineer Dear Mr. Penney: June 25, 2015 Site Inspection Report The above site was visited

More information

PEACE RIVER EAST HILL - HWY 2:60 (PH2) SELECT PHOTOGRAPHS August 22, 2007 File: Photo E003. Station May 2007

PEACE RIVER EAST HILL - HWY 2:60 (PH2) SELECT PHOTOGRAPHS August 22, 2007 File: Photo E003. Station May 2007 Photo E003 0+000 Viewing looking upslope at Site 4 from highway. Conditions unchanged from 2006. Photo E018 0+000 Localized erosion within road fill on upslope side of highway. Photo E022 0+250 Looking

More information

ALBERTA TRANSPORTATION PEACE REGION (PEACE RIVER / HIGH LEVEL) INSTRUMENTATION MONITORING RESULTS

ALBERTA TRANSPORTATION PEACE REGION (PEACE RIVER / HIGH LEVEL) INSTRUMENTATION MONITORING RESULTS ALBERTA TRANSPORTATION PEACE REGION (PEACE RIVER / HIGH LEVEL) INSTRUMENTATION MONITORING RESULTS SPRING 1 SECTION C SITE PH7-1: HWY 9:, DEADWOOD SLIDE 1. OBSERVATIONS 1.1 Field Program and Instrumentation

More information

3.12 Geology and Topography Affected Environment

3.12 Geology and Topography Affected Environment 3 Affected Environment and Environmental Consequences 3.12 Geology and Topography 3.12.1 Affected Environment 3.12.1.1 Earthquakes Sterling Highway MP 45 60 Project Draft SEIS The Kenai Peninsula is predisposed

More information

CCR Rule Annual Inspection Report (cont.) 2

CCR Rule Annual Inspection Report (cont.) 2 The inspection findings consisted of maintenance items and items that were not observed to be signs or potential signs of significant structural weakness. No deficiencies or disrupting conditions that

More information

design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards.

design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards. design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards. In addition to the field inspection, Associated Engineers, Inc.

More information

patersongroup Consulting Engineers April 20, 2010 File: PG1887-LET.01R Novatech Engineering Consultants Suite 200, 240 Michael Cowpland Drive

patersongroup Consulting Engineers April 20, 2010 File: PG1887-LET.01R Novatech Engineering Consultants Suite 200, 240 Michael Cowpland Drive patersongroup April 20, 2010 File: PG1887-LET.01R Novatech Engineering Consultants Suite 200, 240 Michael Cowpland Drive Ottawa, Ontario K2M 1P6 Attention: Mr. Adam Thompson Consulting Engineers 28 Concourse

More information

R.M.HARW & ASSOCIATES LTD. GEOTECHNICAL INVESTIGATION PROPOSED BRIDGE SITE. HELAVA CREEKl MILE MACKENZIE HIGHWAY E-2510 OCTOBER 16, 1973

R.M.HARW & ASSOCIATES LTD. GEOTECHNICAL INVESTIGATION PROPOSED BRIDGE SITE. HELAVA CREEKl MILE MACKENZIE HIGHWAY E-2510 OCTOBER 16, 1973 El R.M.HARW & ASSOCIATES LTD. GEOTECHNICAL INVESTIGATION PROPOSED BRIDGE SITE HELAVA CREEKl MILE 616.4 MACKENZIE HIGHWAY E-2510 OCTOBER 16, 1973 R,M,HARDV & ASSOCIATES LTD. CONSULTING ENGINEERING & TESTING

More information

Slope Stability Evaluation Ground Anchor Construction Area White Point Landslide San Pedro District Los Angeles, California.

Slope Stability Evaluation Ground Anchor Construction Area White Point Landslide San Pedro District Los Angeles, California. Slope Stability Evaluation Ground Anchor Construction Area White Point Landslide San Pedro District Los Angeles, California Submitted To: Mr. Gene Edwards City of Los Angeles Department of Public Works

More information

MEMORANDUM. wa.tsr..-z.n~.e.s-t.i~at.i.o.ns... Branch... Mr. Webster contends that prior to excavation of the gravel

MEMORANDUM. wa.tsr..-z.n~.e.s-t.i~at.i.o.ns... Branch... Mr. Webster contends that prior to excavation of the gravel TO... J. C. Foweraker 2... Head Gr o w a t er S e c t i on... Hyar....og~~~.~.~vis.ion... wa.tsr..-z.n~.e.s-t.i~at.i.o.ns... Branch... eernment OF BRITISH COLUMBIA MEMORANDUM II 0 PROM A. P. Kohut, Geological

More information

ROCK EXCAVATION (GRADING) OPSS 206 INDEX

ROCK EXCAVATION (GRADING) OPSS 206 INDEX 206-2 - OPSS 206 INDEX 206-2.1 GENERAL 206-2.1.1 Classification of Rock Materials 206-2.1.2 Tender Items 206-2.1.3 Other Excavation Tender Items 206-2.1.4 Specifications 206-2.1.5 Special Provisions 206-2.1.6

More information

1.0 INSPECTION ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER PROJECT, CARMACKS, YUKON. Dear Mr. West-Sells,

1.0 INSPECTION ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER PROJECT, CARMACKS, YUKON. Dear Mr. West-Sells, Doc. No. 162 Rev. 0 Mr. Paul West-Sells President & Chief Operating Officer Western Copper Corporation 2060-1111 West Georgia Street Vancouver, BC V6E 4M3 ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER

More information

APPROACH FILL DESIGN OF NORTH SASKATCHEWAN RIVER BRIDGE. A.F. Ruban, EBA Engineering Consultants Ltd., Edmonton, Alberta, Canada

APPROACH FILL DESIGN OF NORTH SASKATCHEWAN RIVER BRIDGE. A.F. Ruban, EBA Engineering Consultants Ltd., Edmonton, Alberta, Canada APPROACH FILL DESIGN OF NORTH SASKATCHEWAN RIVER BRIDGE A.F. Ruban, EBA Engineering Consultants Ltd., Edmonton, Alberta, Canada Paper prepared for presentation at the Slope and Embankment Engineering for

More information

Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services

Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services July 27, 2017 Ms. Rebecca Mitchell Mt. San Antonio College Facilities Planning & Management

More information

HYDROLOGY AND HYDRAULICS MUSKEG RIVER BRIDGE

HYDROLOGY AND HYDRAULICS MUSKEG RIVER BRIDGE PUBLIC WORKS CANADA HYDROLOGY AND HYDRAULICS MUSKEG RIVER BRIDGE KILOMETRE 207.9, LIARD HIGKWAY December 1978 I I f I I I I # Bolter Parish Trimble Ltd. ONLIULTINO Public Works, Canada, 9925-109 Street,

More information

Husky Oil Operations Limited

Husky Oil Operations Limited Husky Oil Operations Limited 707 8th Avenue S.W. Bus: (403) 298-6111 Box 6525, Station D Fax: (403) 298-6378 Calgary, Alberta, Canada T2P 3G7 October 31, 2014 Sahtu Land &Water Board SLWB File: S13L1-005

More information

June 9, R. D. Cook, P.Eng. Soils Engineer Special Services Western Region PUBLIC WORKS CANADA WESTERN REGION REPORT ON

June 9, R. D. Cook, P.Eng. Soils Engineer Special Services Western Region PUBLIC WORKS CANADA WESTERN REGION REPORT ON PUBLIC WORKS CANADA WESTERN REGION REPORT ON GEOTECHNICAL INVESTIGATION PROPOSED MARTIN RIVER BRIDGE MILE 306.7 MACKENZIE HIGHWAY Submitted by : R. D. Cook, P.Eng. Soils Engineer Special Services Western

More information

Preliminary Geotechnical Evaluation Gooseberry Point Pedestrian Improvements Whatcom County, Washington SITE AND PROJECT DESCRIPTION

Preliminary Geotechnical Evaluation Gooseberry Point Pedestrian Improvements Whatcom County, Washington SITE AND PROJECT DESCRIPTION File No. 12-100 Geotechnical & Earthquake Engineering Consultants Mr. Kevin Brown, P.E. Gray & Osborne, Inc. 3710 168 th Street NE, Suite B210 Arlington, Washington 98223 Subject: Draft Report Preliminary

More information

Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services

Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services Ms. Rebecca Mitchell Mt. San Antonio College Facilities Planning & Management 1100 North

More information

B805 TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES - OPSS 805

B805 TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES - OPSS 805 B805 MEASURES - OPSS 805 805.1 GENERAL Construction activities frequently remove protective cover and expose soil to accelerated rates of erosion. Sediments generated thereby can be conveyed via runoff

More information

Assessing Slope Instabilities. Victoria Leffel & Joey Franzino

Assessing Slope Instabilities. Victoria Leffel & Joey Franzino Assessing Slope Instabilities Victoria Leffel & Joey Franzino Slope Stability and Landslides Today s Presentation: Slope instability and landslide terms will be used interchangeably Landslide: downward

More information

ISSUED FOR CONSTRUCTION

ISSUED FOR CONSTRUCTION PAGE No. DESCRIPTION 1 Cover Page 2 Overview Map 3 Western Road Plan View 4 Eastern Road Plan View West Road Profiles & Cross Sections 6-7 East Road Profiles 8- East Road Cross Sections 11-14 Campsite

More information

Geosynthetics Applications and Performance Reviews Select Case Histories

Geosynthetics Applications and Performance Reviews Select Case Histories Geosynthetics Applications and Performance Reviews Select Case Histories Debora J. Miller, Ph.D., P.E.; Dean B. Durkee,, Ph.D., P.E.; Michael A. Morrison, P.E., David B. Wilson, P.E., and Kevin Smith,

More information

Drilled Shafts for Bridge Foundation Stability Improvement Ohio 833 Bridge over the Ohio River An Update

Drilled Shafts for Bridge Foundation Stability Improvement Ohio 833 Bridge over the Ohio River An Update Drilled Shafts for Bridge Foundation Stability Improvement Ohio 833 Bridge over the Ohio River An Update Meigs County, Ohio Mason County, West Virginia By Stan Harris, P.E. and Eric Kistner, P.E. FMSM

More information

Central Queensland Coal Project Appendix 4b Geotechnical Assessment. Environmental Impact Statement

Central Queensland Coal Project Appendix 4b Geotechnical Assessment. Environmental Impact Statement Central Queensland Coal Project Appendix 4b Geotechnical Assessment Environmental Impact Statement GEOTECHNICAL ASSESSMENT OF OPEN CUT MINING ADJACENT TO THE BRUCE HIGHWAY, CENTRAL QUEENSLAND COAL PROJECT

More information

WHITE POINT LANDSLIDE GEOTECHNICAL INVESTIGATION November 29, 2012 Status Report

WHITE POINT LANDSLIDE GEOTECHNICAL INVESTIGATION November 29, 2012 Status Report Gary Lee Moore, P.E., City Engineer Vince Jones, P.E., Deputy City Engineer WHITE POINT LANDSLIDE GEOTECHNICAL INVESTIGATION November 29, 2012 Status Report White Point Landslide Geotechnical Investigation

More information

U-Shaped Sediment Traps

U-Shaped Sediment Traps U-Shaped Sediment Traps SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils [1] Type 3 System Supplementary Trap Dispersive Soils [1] Generally

More information

CHRACTERISTICS OF LANDSLIDE OCCURRED IN LOPARE, BOSNIA AND HERZEGOVINA

CHRACTERISTICS OF LANDSLIDE OCCURRED IN LOPARE, BOSNIA AND HERZEGOVINA CHRACTERISTICS OF LANDSLIDE OCCURRED IN LOPARE, BOSNIA AND HERZEGOVINA Jun Sugawara 1 and Takao Aizawa 2 1 WorleyParsons, Australia 2 Suncoh Consultants, Japan ABSTRACT This paper presents results of detailed

More information

When Creek Meets Valley Wall: Prioritizing Erosion Mitigation alongside the Oshawa Landfill

When Creek Meets Valley Wall: Prioritizing Erosion Mitigation alongside the Oshawa Landfill 1 When Creek Meets Valley Wall: Prioritizing Erosion Mitigation alongside the Oshawa Landfill Robin McKillop 1, Dan McParland 1 & Cassie Scobie 2 TRIECA conference March 22-23, 2017 1 Palmer Environmental

More information

MINISTRY OF ENERGY AND MINES Mines and Mineral Resources. REPORT OF GEOTECHNICAL INSPECTOR (Issued pursuant to Section 15 of the Mines Act)

MINISTRY OF ENERGY AND MINES Mines and Mineral Resources. REPORT OF GEOTECHNICAL INSPECTOR (Issued pursuant to Section 15 of the Mines Act) MINISTRY OF ENERGY AND MINES Mines and Mineral Resources REPORT OF GEOTECHNICAL INSPECTOR (Issued pursuant to Section 15 of the Mines Act) Name of Property: Permit No.: M-203 General Manager: Company:

More information

The last three sections of the main body of this report consist of:

The last three sections of the main body of this report consist of: Threatened and Endangered Species Geological Hazards Floodplains Cultural Resources Hazardous Materials A Cost Analysis section that provides comparative conceptual-level costs follows the Environmental

More information

Internal C Unit Dilatanc y

Internal C Unit Dilatanc y 2 Grimsby Sub was not at any time definitively established. The preliminary analysis provided by Thurber Engineering Ltd indicates the slope should be stable with a factor of safety of 1.23 for a deep

More information

1 INTRODUCTION 1.1 General

1 INTRODUCTION 1.1 General #701 475 Howe Street Vancouver, British Columbia V6C 2B3 August 1, 2014 Robin McCall Wolverine Mine Environmental Superintendent Dear Mr. McCall: 1 INTRODUCTION 1.1 General This letter report presents

More information

Degradation Concerns related to Bridge Structures in Alberta

Degradation Concerns related to Bridge Structures in Alberta Degradation Concerns related to Bridge Structures in Alberta Introduction There has been recent discussion regarding the identification and assessment of stream degradation in terms of how it relates to

More information

Background. Valley fills Sites in the Area. Construction over Mine Spoil Fills

Background. Valley fills Sites in the Area. Construction over Mine Spoil Fills Construction over Mine Spoil Fills Wayne A. Karem, PhD, PE, PG, D.GE 2014 KSPE Annual Conference Background Strip mining; mountaintop and contour mining Creates huge quantities of mine spoil The mine spoil

More information

September 18, 2017 Project No.: 5077

September 18, 2017 Project No.: 5077 #109 3011 Underhill Avenue Burnaby, BC V5A 3C2 Phone: (604) 421-3288 Email: info@terrangeo.com September 18, 2017 Project No.: 5077 Kevin Brooks City of Campbell River 301 St. Ann s Road Campbell River,

More information

Mr. Michael Malone CPS Energy 145 Navarro Street San Antonio, Texas Project No

Mr. Michael Malone CPS Energy 145 Navarro Street San Antonio, Texas Project No January 17, 2018 Mr. Michael Malone 145 Navarro Street San Antonio, Texas 78205 Project No. 0337367 Environmental Resources Management CityCentre Four 840 West Sam Houston Pkwy N. Suite 600 Houston, Texas

More information

CHAPTER GEOLOGICALLY HAZARDOUS AREAS Applicability Regulations.

CHAPTER GEOLOGICALLY HAZARDOUS AREAS Applicability Regulations. CHAPTER 19.07 GEOLOGICALLY HAZARDOUS AREAS 19.07.010 Applicability. Geologically hazardous areas may pose a threat to the health and safety of citizens when incompatible development is sited in areas of

More information

Rock & Aggregate Drop Inlet Protection

Rock & Aggregate Drop Inlet Protection Rock & Aggregate Drop Inlet Protection SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System Supplementary Trap Dispersive Soils

More information

August 31, 2006 Embankment Failure Debris Flow at the Cascades Development Haywood County, North Carolina. Introduction. Findings

August 31, 2006 Embankment Failure Debris Flow at the Cascades Development Haywood County, North Carolina. Introduction. Findings August 31, 2006 Embankment Failure Debris Flow at the Cascades Development Haywood County, North Carolina Introduction North Carolina Geological Survey (NCGS) staff members visited the site of the August

More information

HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR (c)(1)(i) (xii)

HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR (c)(1)(i) (xii) HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR 257.73(c)(1)(i) (xii) (i) Site Name and Ownership Information: Site Name: E.C. Gaston Steam Plant Site Location:

More information

Effect of Toe Excavation on a Deep Bedrock Landslide

Effect of Toe Excavation on a Deep Bedrock Landslide Effect of Toe Excavation on a Deep Bedrock Landslide Timothy D. Stark 1 ; W. David Arellano 2 ; Ryan P. Hillman 3 ; Roger M. Hughes 4 ; Norman Joyal 5 ; and Don Hillebrandt 6 Abstract: Observations, data,

More information

PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0

PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0 PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0 LYCOMING COUNTY S.R.15, SECTION C41 FINAL HYDROLOGIC AND HYDRAULIC REPORT STEAM VALLEY RUN STREAM RELOCATION DATE: June, 2006 REVISED:

More information

Re: Steep Slope Assessment for 2465 Waverly Drive, Blind Bay, BC; Legal Address: Lot 39, Section 18, Township 22, Range 10, Plan 25579, W6M, KDYD.

Re: Steep Slope Assessment for 2465 Waverly Drive, Blind Bay, BC; Legal Address: Lot 39, Section 18, Township 22, Range 10, Plan 25579, W6M, KDYD. OEL File 1563-1 May 30, 2017 Doug Wall PO Box 774 Salmon Arm, BC V1E 4N7 Re: Steep Slope Assessment for 2465 Waverly Drive, Blind Bay, BC; Legal Address: Lot 39, Section 18, Township 22, Range 10, Plan

More information

1.0 INTRODUCTION 2.0 OBSERVATIONS EBA FILE: W nd Avenue Whitehorse, YT Y1A 1C2. Attention:

1.0 INTRODUCTION 2.0 OBSERVATIONS EBA FILE: W nd Avenue Whitehorse, YT Y1A 1C2. Attention: August 5, 2013 City of Whitehorse 2121 2 nd Avenue Whitehorse, YT Y1A 1C2 ISSUED FOR USE EBA FILE: W14103182-01 Via Email: ben.campbell@whitehorse.ca Attention: Subject: Ben Campbell, Planner II Planning

More information

POTENTIAL EFFECTS OF EARTHQUAKE SHAKING ON THE PROPOSED CRRRC LANDFILL

POTENTIAL EFFECTS OF EARTHQUAKE SHAKING ON THE PROPOSED CRRRC LANDFILL TECHNICAL MEMORANDUM DATE September 26, 2016 PROJECT No. 1211250045/14000 TO Andrew Evers Ministry of Environment and Climate Change FROM Alan Hull, Paul Smolkin POTENTIAL EFFECTS OF EARTHQUAKE SHAKING

More information

Nipigon River Landslide, Ontario, Canada

Nipigon River Landslide, Ontario, Canada Nipigon River Landslide, Ontario, Canada A. Abdelaziz, S. Besner, R. Boger, B. Fu, J. Deng, and A. Farina Presenter: Jian Deng, Ph.D, P.Eng Centre of Excellence for Sustainable Mining and Exploration,

More information

3.12 Geology and Topography Affected Environment

3.12 Geology and Topography Affected Environment 3 Affected Environment and Environmental Consequences 3.12 Geology and Topography 3.12.1 Affected Environment 3.12.1.1 Earthquakes Sterling Highway MP 45 60 Project Final EIS The Kenai Peninsula is predisposed

More information

FRIENDS OF THE EEL RIVER

FRIENDS OF THE EEL RIVER FRIENDS OF THE EEL RIVER Working for the recovery of our Wild & Scenic River, its fisheries and communities. Frank Blackett, Regional Engineer Office of Energy Projects Division of Dam Safety and Inspections

More information

Slope Stability Assessment Proposed Development 4401 Fallowfield Road Lands Ottawa, Ontario Rev-02

Slope Stability Assessment Proposed Development 4401 Fallowfield Road Lands Ottawa, Ontario Rev-02 REPORT August 2014 REPORT ON Slope Stability Assessment Proposed Development 4401 Fallowfield Road Lands Ottawa, Ontario Submitted to: DCR Phoenix Homes 18 Bentley Avenue Ottawa, Ontario K2E 6T8 Report

More information

#10, 340 MacAlpine Crescent, Fort McMurray, AB T9H 4A8 T: F: thurber.ca. Attachment #1

#10, 340 MacAlpine Crescent, Fort McMurray, AB T9H 4A8 T: F: thurber.ca. Attachment #1 #10, 340 MacAlpine Crescent, Fort McMurray, AB T9H 4A8 T: 780 743 1566 F: 780 743 1955 thurber.ca Attachment #1 TABLE OF CONTENTS 1. INTRODUCTION... 1 2. BACKGROUND AND SCOPE OF WORK... 1 3. METHODOLOGY...

More information

TABLE OF CONTENTS LIST OF TABLES. Page

TABLE OF CONTENTS LIST OF TABLES. Page TABLE OF CONTENTS Page 11.0 EFFECTS OF THE ENVIRONMENT ON THE PROJECT... 11-1 11.1 Weather Conditions... 11-1 11.2 Flooding... 11-2 11.3 Forest Fires... 11-2 11.4 Permafrost and Subsidence Risk... 11-3

More information

3.18 GEOLOGY AND SOILS

3.18 GEOLOGY AND SOILS 3.18 GEOLOGY AND SOILS This section discusses geologic resource concerns as they relate to the environment, public safety, and project design both during construction and after completion of the project.

More information

LANDSLIDES IN THE WHITE MOUNTAIN (GEOTECHNICAL STUDIES AND ENGINEERING TESTS)

LANDSLIDES IN THE WHITE MOUNTAIN (GEOTECHNICAL STUDIES AND ENGINEERING TESTS) J. Al Azhar University Gaza 2004, Vol. 7, NO. 2 P 15-26 LANDSLIDES IN THE WHITE MOUNTAIN (GEOTECHNICAL STUDIES AND ENGINEERING TESTS) Isam G. Jardaneh (1), Jalal Al-Dabeek (2), Abdel hakeem Al-Jawhari

More information

The Puvirnituq airstrip pilot project; results from the first three monitoring years

The Puvirnituq airstrip pilot project; results from the first three monitoring years The Puvirnituq airstrip pilot project; results from the first three monitoring years Félix Gravel Gaumond 1,2, ing. jr Guy Doré 1,2, ing. PhD., professor Chantal Lemieux 1,2, research coordinator ARQULUK

More information

Black Gore Creek 2013 Sediment Source Monitoring and TMDL Sediment Budget

Black Gore Creek 2013 Sediment Source Monitoring and TMDL Sediment Budget Black Gore Creek 2013 Sediment Source Monitoring and TMDL Sediment Budget Prepared for: Prepared By: - I. Introduction The Black Gore Creek Total Maximum Daily Load (TMDL) was developed in collaboration

More information

COTTON, SHIRES AND ASSOCIATES, INC. CONSULTING ENGINEERS AND GEOLOGISTS

COTTON, SHIRES AND ASSOCIATES, INC. CONSULTING ENGINEERS AND GEOLOGISTS COTTON, SHIRES AND ASSOCIATES, INC. CONSULTING ENGINEERS AND GEOLOGISTS June 23, 2016 G5056 TO: SUBJECT: Sam Herzberg Senior Planner SAN MATEO COUNTY PARKS DEPARTMENT 455 County Center, 4 th Floor Redwood

More information

ENGINEERING EVALUATION OF THE STANLEY MINE ADVENTURE PARK AREA CLEAR CREEK COUNTY, COLORADO. Prepared for:

ENGINEERING EVALUATION OF THE STANLEY MINE ADVENTURE PARK AREA CLEAR CREEK COUNTY, COLORADO. Prepared for: braun Braun Consulting Engineers ENGINEERING EVALUATION OF THE STANLEY MINE ADVENTURE PARK AREA CLEAR CREEK COUNTY, COLORADO Prepared for: STANLEY MINES ADENTURE PARK 3375 W. POWERS CIRCLE LITTLETON, COLORADO

More information

Yoshinori KAWAMURA, Oriental Consultants Global Co., Ltd.

Yoshinori KAWAMURA, Oriental Consultants Global Co., Ltd. Landslides along National Roads in Central Highland in Sri Lanka: Review on Current Situation and Suggestion for Further Development of Landslide Mitigation along Highways in Sri Lanka Yoshinori KAWAMURA,

More information

Crows Landing Naval Base Easement

Crows Landing Naval Base Easement 1 of 15 West Stanislaus Resource Conservation District Crows Landing Naval Base Easement Annual Reserve Monitoring Report Jamie McFarlin 11/112012 2 of 15 West Stanislaus Resource Conservation District

More information

An Introduction to Field Explorations for Foundations

An Introduction to Field Explorations for Foundations An Introduction to Field Explorations for Foundations J. Paul Guyer, P.E., R.A. Paul Guyer is a registered mechanical engineer, civil engineer, fire protection engineer and architect with over 35 years

More information

Gully Erosion Part 1 GULLY EROSION AND ITS CAUSES. Introduction. The mechanics of gully erosion

Gully Erosion Part 1 GULLY EROSION AND ITS CAUSES. Introduction. The mechanics of gully erosion Gully Erosion Part 1 GULLY EROSION AND ITS CAUSES Gully erosion A complex of processes whereby the removal of soil is characterised by incised channels in the landscape. NSW Soil Conservation Service,

More information

Gotechnical Investigations and Sampling

Gotechnical Investigations and Sampling Gotechnical Investigations and Sampling Amit Prashant Indian Institute of Technology Gandhinagar Short Course on Geotechnical Investigations for Structural Engineering 12 14 October, 2017 1 Purpose of

More information

Preliminary Geotechnical Review, Angels Crest Rock Fall, Stawamus Chief, Squamish, BC

Preliminary Geotechnical Review, Angels Crest Rock Fall, Stawamus Chief, Squamish, BC GeoPacific #215 1200 West 73 rd Avenue, Vancouver, BC, V6P 6G5 Consultants Ltd. Phone (604) 439-0922 / Fax (604) 439-9189 District of Squamish May 5, 2015 37955 Second Avenue File: 12942 P.O. Box 310 V8B

More information

1 City of Edmonton Quesnell Bridge, Roads and Associated Structures Assessment

1 City of Edmonton Quesnell Bridge, Roads and Associated Structures Assessment 1 City of Edmonton Quesnell Bridge, Roads and Associated Structures Assessment 1.1 Background Within the First National Engineering Vulnerability Assessment, the Public Infrastructure Engineering Vulnerability

More information

How Much Can it Cost to Remediate a Large Landslide? Theme Session No. 10 at GSA Cordilleran Section Meeting, May 13-15, 2002

How Much Can it Cost to Remediate a Large Landslide? Theme Session No. 10 at GSA Cordilleran Section Meeting, May 13-15, 2002 How Much Can it Cost to Remediate a Large Landslide? Theme Session No. 10 at GSA Cordilleran Section Meeting, May 13-15, 2002 Author and Presenter: Charles M. Hammond, CEG, Landslide Technology, 10250

More information

PRELIMINARY CULVERT ANALYSIS REPORT FOR CULVERT NO. 008-C OREGON AVENUE OVER PINEHURST CREEK

PRELIMINARY CULVERT ANALYSIS REPORT FOR CULVERT NO. 008-C OREGON AVENUE OVER PINEHURST CREEK PRELIMINARY CULVERT ANALYSIS REPORT FOR CULVERT NO. 008-C OREGON AVENUE OVER PINEHURST CREEK Prepared for The District of Columbia Department of Transportation Washington, D.C. Prepared by Parsons Transportation

More information

Materials. Use materials meeting the following.

Materials. Use materials meeting the following. 208.01 Section 208. SOIL EROSION AND SEDIMENTATION CONTROL 208.01 Description. Install and maintain erosion and sedimentation controls to minimize soil erosion and to control sedimentation from affecting

More information

Geophysical Case studies From Texas

Geophysical Case studies From Texas Geophysical Case studies From Texas 1 PRESENTATION OUTLINE Active Growth Faults in Metropolitan Houston 1. Hockley 2. Tomball 3. Long Point 4. Pearland Foundation Case Studies Karst Geophysics in Austin:

More information

DESIGN BULLETIN No. 39/2006 (Revised June 2007) June 2007 Amendment to Design Bulletin #39/2006

DESIGN BULLETIN No. 39/2006 (Revised June 2007) June 2007 Amendment to Design Bulletin #39/2006 Design Bulletin 39 - Revised Tender Submission Requirements DESIGN BULLETIN No. 39/2006 (Revised June 2007) TENDER SUBMISSION REQUIREMENTS June 2007 Amendment to Design Bulletin #39/2006 This amendment

More information

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area.

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area. Sediment Trench SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils [1] Performance of

More information

Area-wide geotechnical information summary for CERA zoning review panel

Area-wide geotechnical information summary for CERA zoning review panel Area-wide geotechnical information summary for CERA zoning review panel This document contains all the area-wide geotechnical information which was considered by CERA as part of the process for making

More information

Monmouthshire County Council Review of Landslips within the County December February 2014

Monmouthshire County Council Review of Landslips within the County December February 2014 Monmouthshire County Council Review of Landslips within the County December 2013- February 2014 Introduction The County of Monmouthshire suffered a period of extreme weather between December 2013 and February

More information

Date: April 2, 2014 Project No.: Prepared For: Mr. Adam Kates CLASSIC COMMUNITIES 1068 E. Meadow Circle Palo Alto, California 94303

Date: April 2, 2014 Project No.: Prepared For: Mr. Adam Kates CLASSIC COMMUNITIES 1068 E. Meadow Circle Palo Alto, California 94303 City of Newark - 36120 Ruschin Drive Project Draft Initial Study/Mitigated Negative Declaration Appendix C: Geologic Information FirstCarbon Solutions H:\Client (PN-JN)\4554\45540001\ISMND\45540001 36120

More information

Need of Proper Development in Hilly Urban Areas to Avoid

Need of Proper Development in Hilly Urban Areas to Avoid Need of Proper Development in Hilly Urban Areas to Avoid Landslide Hazard Dr. Arvind Phukan, P.E. Cosultant/Former Professor of Civil Engineering University of Alaska, Anchorage, USA RI District Governor

More information

Budge Road Landslide Jackson Extensometer installation report April 2014 with data to 20 May

Budge Road Landslide Jackson Extensometer installation report April 2014 with data to 20 May Budge Road Landslide Jackson Extensometer installation report 23-27 April 14 with data to May Four extensometers were installed across fissures at the head of the Budge Road landslide on the East Gros

More information

To: Rishi Adhikari and Roger Skirrow From: Leslie Cho and Ian Darrach Alberta Transportation File: Date: June 30, 2016

To: Rishi Adhikari and Roger Skirrow From: Leslie Cho and Ian Darrach Alberta Transportation File: Date: June 30, 2016 To: Rishi Adhikari and Roger Skirrow From: Leslie Cho and Ian Darrach Stantec File: Date: June, Reference: North Central Region Edson Site NC HWY :, Deer Lodge Spring Task C: Instrumentation Monitoring

More information

October 26, Ms. Aimee Zack Canadian Pacific 120 S. Sixth Street Suite 900 Minneapolis, Minnesota 55402

October 26, Ms. Aimee Zack Canadian Pacific 120 S. Sixth Street Suite 900 Minneapolis, Minnesota 55402 October 26, 2017 Ms. Aimee Zack Canadian Pacific 120 S. Sixth Street Suite 900 Minneapolis, Minnesota 55402 Re: Soo Line Dump Site 2017 Annual Soil Cover Inspection Dear Aimee: The purpose of this letter

More information

Geohazards Associated with Dispersive-Soil Voids

Geohazards Associated with Dispersive-Soil Voids Geohazards Associated with Dispersive-Soil Voids Chris Grapel, M.Eng., P.Eng. GRMP 2018 Dispersive-Soil GRMP Sites S040 Dorothy Hwy 848:02 S040 Dorothy Hwy 848:02 Dispersive Soils Dispersive clays are

More information

SLOPE STABILITY ASSESSMENT PROPOSED RESIDENTIAL SUBDIVISION 161 LAKESHORE ROAD EAST TOWN OF THE BLUE MOUNTAINS, ONTARIO

SLOPE STABILITY ASSESSMENT PROPOSED RESIDENTIAL SUBDIVISION 161 LAKESHORE ROAD EAST TOWN OF THE BLUE MOUNTAINS, ONTARIO SLOPE STABILITY ASSESSMENT PROPOSED RESIDENTIAL SUBDIVISION 161 LAKESHORE ROAD EAST TOWN OF THE BLUE MOUNTAINS, ONTARIO PETO MacCALLUM LTD. 19 CHURCHILL DRIVE BARRIE, ONTARIO L4N 8Z5 PHONE: (705) 734-3900

More information

Area-wide geotechnical information summary for CERA zoning review panel

Area-wide geotechnical information summary for CERA zoning review panel Area-wide geotechnical information summary for CERA zoning review panel This document contains all the area-wide geotechnical information which was considered by CERA as part of the process for making

More information

Use of Launched Soil Nails to Stabilize Landslides in Summit County, Ohio

Use of Launched Soil Nails to Stabilize Landslides in Summit County, Ohio Use of Launched Soil Nails to Stabilize Landslides in Summit County, Ohio Mitchell W. Weber, P.G. Gannett Fleming Engineers & Architects, P.C. Greg Bachman, P.E., P.S. County of Summit Engineer Robert

More information

25th International Conference on Ground Control in Mining

25th International Conference on Ground Control in Mining ANALYTICAL INVESTIGATION OF SHAFT DAMAGES AT WEST ELK MINE Tim Ross, Senior Associate Agapito Associates, Inc. Golden, CO, USA Bo Yu, Senior Engineer Agapito Associates, Inc. Grand Junction, CO, USA Chris

More information

10. GEOTECHNICAL EXPLORATION PROGRAM

10. GEOTECHNICAL EXPLORATION PROGRAM Geotechnical site investigations should be conducted in multiple phases to obtain data for use during the planning and design of the tunnel system. Geotechnical investigations typically are performed in

More information

RESERVOIR DRAWDOWN RATES/RESERVOIR DRAWDOWN TEST Iron Gate, Copco (I & II), and JC Boyle Dams

RESERVOIR DRAWDOWN RATES/RESERVOIR DRAWDOWN TEST Iron Gate, Copco (I & II), and JC Boyle Dams TECHNICAL MEMORANDUM No. 1 TO: Michael Bowen California Coastal Conservancy Geotechnical & Earthquake Engineering Consultants CC: Eric Ginney Philip Williams & Associates PREPARED BY: Paul Grant SUBJECT:

More information

The role of the ground model in design of low cost slip repairs on rural New Zealand roads

The role of the ground model in design of low cost slip repairs on rural New Zealand roads Watson, J. (2013) Proc. 19 th NZGS Geotechnical Symposium. Ed. CY Chin, Queenstown The role of the ground model in design of low cost slip repairs on rural New Zealand roads J Watson Engineering Geologist,

More information

TRAFFIC ALERT FOR WEEK OF February 4 8, 2008

TRAFFIC ALERT FOR WEEK OF February 4 8, 2008 TRAFFIC ALERT FOR WEEK OF February 4 8, 2008 Highway work zones in the Staunton District The following is a list of highway work that might affect traffic in the Staunton transportation district during

More information

Contrasting Behaviour of Two Recent, Large Landslides in Discontinuous Permafrost Little Salmon Lake, Yukon, Canada

Contrasting Behaviour of Two Recent, Large Landslides in Discontinuous Permafrost Little Salmon Lake, Yukon, Canada Contrasting Behaviour of Two Recent, Large Landslides in Discontinuous Permafrost Little Salmon Lake, Yukon, Canada Ryan R. Lyle BGC Engineering Inc. Kamloops, British Columbia D. Jean Hutchinson Queen

More information

Construction Exits Rock pads

Construction Exits Rock pads Construction Exits Rock pads SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow [1] Clayey Soils Type 3 System Supplementary Trap Dispersive Soils [1] Minor

More information