MINISTRY OF ENERGY AND MINES Mines and Mineral Resources. REPORT OF GEOTECHNICAL INSPECTOR (Issued pursuant to Section 15 of the Mines Act)

Size: px
Start display at page:

Download "MINISTRY OF ENERGY AND MINES Mines and Mineral Resources. REPORT OF GEOTECHNICAL INSPECTOR (Issued pursuant to Section 15 of the Mines Act)"

Transcription

1 MINISTRY OF ENERGY AND MINES Mines and Mineral Resources REPORT OF GEOTECHNICAL INSPECTOR (Issued pursuant to Section 15 of the Mines Act) Name of Property: Permit No.: M-203 General Manager: Company: Address: Persons Contacted: Copies To: Kent T. Christensen, P.Eng. s Ltd Hastings St W, Vancouver, BC V6C 2W2 Shane Flynn and Randall Thompson Al Hoffman, Chief Inspector of Mines, MEM Diane Howe, Deputy Chief Inspector of Mines, MEM George Warnock, Manager, Geotechnical Engineering, MEM Heather Narynski, Manager, Geotechnical Engineering, MEM Doug Flynn, Senior Inspector of Mines, MEM Scott Parker, Inspector of Mines, Health & Safety, MEM Date of Inspection: August 12, 2014 In this document, Code means the Health, Safety and Reclamation Code for Mines in British Columbia INTRODUCTION A geotechnical inspection of was conducted by the writer and Scott Parker, on August 12, 2014 in the company of employee, Shane Flynn. This report summarizes observations made during the inspection. Inspection orders related to the EPRP were discussed with Messrs Flynn and Thompson following the inspection, and are linked to TMF-3 within this report. The purpose of this inspection was as follows: To determine if the mine is meeting the requirements of the Code and Permit No. M-203. To determine if the geotechnical practices at the mine are consistent with generally accepted engineering practices at mines in British Columbia. To identify potential ground stability hazards or concerns at the mine. To verify the classification of mine dams within the MEM database. The following areas were observed during the mine tour: The Main Zone Expansion Pit. The MZO area of tailings excavation. The NAG quarry. The tailings management cells east of the open pit. The landslide above (north of) the East Cell Tailings. The tailings management facilities immediately west of the open pit (TMF-2). The newly activated tailings management facility (TMF-3). Sediment control ponds SC1 to SC3 and SC5 to SC8. Figure 1, attached, provides the general layout of the Site, other than TMF-3 and SC6 through SC8, which are located west of TMF-2.

2 Report of Geotechnical Inspector August 20, 2014 Page 2 of 11 OBSERVATIONS AND INSPECTION ORDERS Location: Active Open Pit Men and equipment were working in the base of the Main Zone Expansion Pit at the time of the site visit (Photo 1). The radar system used to monitor the high wall (north side of the pit), where slope movements were detected in late 2012, is still active. This system quantifies movements on the basis of changes from previous scans. The results are regularly reviewed by the engineering staff and the extent of the movement zone is now well defined. Movement criteria are in place and alerts are sent out to key mine personnel as soon as any of the key warning criteria are exceeded. It is understood the radar system data currently indicate that a significant wall failure is not imminent. Water management, both surface and ground, is a key factor in maintaining stable pit slopes at Huckleberry. Ditches and horizontal drains which tie into the ditch system have been in place for some time and, based on feedback from Mr. Flynn, have been performing well. Al Chance, P.Eng., of Golder Associates continues to undertake annual inspections in relation to pit slope design and performance. It is understood that Mr. Chance completed a 4-day inspection earlier this summer, i.e. approximately in June. Location: MZO Area As part of the December 2011 amendment to Permit No. M-203, tailings and waste rock deposited previously in the open pit were approved for rehandling and storage at TMF-3. An amendment to Permit No. M-203, dated February 2014, approved changes to the MZO backfill excavation (principally in relation to the tailings) based on the requirement that the recommendations contained in the geotechnical design report issued by Golder Associates in January 2014 are implemented. Observations from the site visit indicated that the transfer of tailings from the MZO to TMF-3 is well advanced. The current base of the MZO excavation is at 958m elevation. Observations of exposed faces within the tailings indicate that, in general, the tailings are well consolidated, i.e. the fine grained material has a stiff to very stiff consistency (see the area highlighted by the red oval in Photo 2). However, in some areas, the tailings have shown a propensity to flow (an example is highlighted by the yellow oval in Photo 2). It is understood that the excavation has been occurring in accordance with the geotechnical design report. Furthermore, Al Chance, who was primarily responsible for the geotechnical design report issued by Golder Associates in January 2014, included an assessment of the MZO excavation and related stability issues during a 4-day visit to site earlier this summer.

3 Report of Geotechnical Inspector August 20, 2014 Page 3 of 11 Location: NAG Quarry The NAG quarry (Photo 3), which is relatively small compared to the main pit, provided non-acid generating andesite as rock fill for the construction of the east cell TSF raise. The quarry has been dormant for an extended period and there are no plans to re-open it. No geotechnical concerns were noted. It is understood that options for potential use of this quarry are being considered. However, there is apparently no defined timeline for any related decisions. Location: West Cell Pond and East Cell Tailings The general layout of the West Cell Pond (Photo 4) and the East Cell Tailings (Photo 5), both of which were part of the East Zone Pit, is illustrated on Figure 1. The East Pit Plug Dam provides containment for the tailings placed previously within the East Zone Pit. Once the starter dam for TMF-3 was constructed and approved for operation, tailings deposition into the West Cell Pond and the East Cell Tailings ceased. At the time of the inspection, water was being pumped to the West Cell Pond (Photo 4). There was ample freeboard on the external south wall of the West Cell Pond. No water was present on the East Cell Tailings (Photo 5). No geotechnical concerns were noted. The Engineer of Record for these structures is Todd Martin, P.Eng., of BGC Engineering Inc. It is understood that Mr. Martin was on site earlier this summer. Location: Inactive Open Pit Slope above the East Cell Tailings The high wall north of the East Tailings Cell that failed a number of years ago is shown in Photo 6. Following the slope failure, a buttress was subsequently installed at the toe of the slope. It is understood that monitoring of this slope is continuing and the data apparently indicates the buttress has essentially stabilized the area. Current plans call for a cover to be constructed over the slide area, from approximately the 1030 level up to the top of the slide scarp. The timing of the cover construction was not discussed.

4 Report of Geotechnical Inspector August 20, 2014 Page 4 of 11 Location: TMF-2 The general layout of TMF-2 is illustrated on Figure 1. Confinement on the west and southwest sides of TMF-2 is provided by the TMF-2 Dam; on the southeast by the Orica Saddle Dam; and on the east by the East Dam. Not shown on Figure 1 is the South Saddle Dam which previously divided TMF-2 from the Main Zone Pit. However, this pit was subsequently filled in. Tailings have not been actively discharged to TMF-2 for some time. A relatively small, shallow pond is present over exposed tailings on the north side of TMF-2, close to the adjacent hill side (Photo 1). A soil cover has been constructed over part of TMF-2 for closure purposes, and waste rock from the active pit is being placed over another part of TMF-2 (Photos 1 and 2). The placement of the waste rock is being done in accordance with a plan developed by the mine staff. The geotechnical stability of the waste rock storage plan is understood to have been assessed, and confirmed as satisfactory, by BGC Engineering Inc. Location: TMF-3 Approval to operate TMF-3 was issued as a permit amendment in July TMF-3 is essentially a sidehill facility situated west of TMF-2 and is the main storage location for tailings associated with current mining and ore processing activities. The main dam segment at TMF-3 runs in an east-west orientation. There is also a short dam segment oriented in a northsouth direction at the west end of TMF-3 that will connect to the main dam as the two dam segments are raised. The design section for the dam consists of a wide till core with filter zones downstream of the core, and granular material as upstream and downstream shells. At the time of the inspection, the starter dam was at elevation 945m and additional rock fill was being dumped against its upstream face (Photo 7). Tailings from the MZO excavation were being placed inside the impoundment, in the area immediately adjacent to the west end of the main dam segment (Photo 7). At the east end of the impoundment, immediately adjacent to the main dam segment, tailings were being discharged into the facility. A pond separated the MZO tailings and the tailings pumped from the processing plant. Away from the current pond, but still within the TMF-3 footprint, rock was being quarried for use in the construction of the dam shell. The Engineer of Record for the TMF-3 is Todd Martin, P.Eng., of BGC Engineering Inc. As noted earlier, Mr. Martin was on site for an inspection of the TMF facilities earlier this summer. On August 12, 2014, one of BGC s field engineers was on site in anticipation of the next round of earthworks construction at the TMF-3 starter dam. The current OMS manual for the tailings facilities was completed in July It includes an Emergency Preparedness and Response Plan (EPRP).

5 Report of Geotechnical Inspector August 20, 2014 Page 5 of 11 A schedule for testing the Emergency Preparedness and Response Plan (EPRP) shall be prepared and submitted to the Ministry by September 5, A summary of the EPRP test including lessons learned shall be submitted to the Ministry within 30 days of the completion of the test along with a schedule for updating the EPRP based on these lessons learned. Note that the EPRP shall be reviewed at least annually and updated as required. Location: SC1, SC2. SC3, SC5, SC6, SC7 and SC8 Downstream of the tailings management facilities are a series of sediment control ponds. For example, Figure 1 shows the location of four small ponds (SC1, SC2, SC3 and SC5) downstream of TMF-2. SC4 (SC4A on Figure 1) is situated downstream of the East Pit Plug Dam. Downstream of TMF-3 are three relatively new ponds (SC6, SC7 and SC8). The design of most of the dams at the sediment control ponds is the same and consists largely of a till embankment with thin shells of rock fill on one or both sides of the embankment. Water from many of the sediment control ponds passes over v-notch weir and into pipes that that direct this water into the channel base immediately downstream of the respective sediment control pond. At the time of the inspection, the water levels in SC6, SC7 and SC8 were very low, having been recently drawn down. No geotechnical concerns were noted. General Observations: The appears to be managing geotechnical risks in an appropriate way. Appropriate methods to manage surface and groundwater at the main pit area are in place. In addition, a high quality system for wall displacement monitoring is in place at the open pit. The dam construction and tailings deposition practices at TMF-3 appear orderly and well managed. Advice is sought from consultant geotechnical engineers on a regular basis. An inspection of the pit slopes is undertaken annually by a senior rock mechanics engineer from Golder Associates. A senior geotechnical engineer from BGC makes at least an annual visit to inspect the TMF s (more frequently than that at present, due to recent commencement of tailings deposition and the incremental construction of the TMF-3 starter dam). It is concluded, therefore, that genuine efforts are made to manage the geotechnical issues on site in a manner which is consistent with best practices. The instruction orders that have been issued with this document are related to testing of the EPRP, and based on "lessons learned," subsequent updating of the EPRP. Lastly, as discussed on site, there is ambiguity in the hazard classification of some of the dams on site. I will contact Shane Flynn with a view to updating MEM s database of dams at (an extension of the related inspection order from 2013).

6 Report of Geotechnical Inspector August 20, 2014 Page 6 of 11 CLOSURE Under Section 15 (6) of the Mines Act, a written response is required from the Mine Manager within 15 days of the receipt of this Inspection Report. The response should be directed to the author, with a cc to George Warnock (George.Warnock@gov.bc.ca) and Heather Narynski (Heather.Narynski@gov.bc.ca). In addition, Section 30 (1) of the Mines Act requires this Inspection Report to be posted in a conspicuous location at the mine site for 30 days. Please feel free to contact the undersigned with any questions or comments. Cameron C.Scott, P. Eng. Geotechnical Inspector Ministry of Energy & Mines Signature Dated: August 20, 2014

7

8 Report of Geotechnical Inspector August 20, 2014 Page 8 of 11 Photo 1: Westward view across the Main Zone Expansion Pit. The MZO excavation of tailings (for pit expansion) is visible behind the pit, at the left, and TMF-2 is visible in the background. Photo 2: Westward view across the MZO excavation. Exposed tailings slopes within the red oval are standing up well; those within the yellow oval are showing a propensity to run or flow.

9 Report of Geotechnical Inspector August 20, 2014 Page 9 of 11 Photo 3: Eastward view across the NAG quarry situated to the south of TMF-2. Photo 4: Westward view across the West Cell Pond (taken from the top of the landslide area above the East Cell Tailings).

10 Report of Geotechnical Inspector August 20, 2014 Page 10 of 11 Photo 5: Eastward view across the crest of the starter dam at TMF-3. Photo 6: Eastward view across TMF-2. The Main Zone Expansion Pit high wall and the landslide above the East Cell Tailings are visible on the left and rights sides, respectively, of the photo.

11 Report of Geotechnical Inspector August 20, 2014 Page 11 of 11 Photo 7: Westward view across TMF 3. From left to right are SC8, the TMF-3 starter dam, tailings from the MZO excavation (background) and the area of active tailings deposition (foreground). Photo 8: Westward view along the upstream face of the dam at SC8. Note the low water level behind the dam. The TMF-3 starter dam is visible at the upper right corner of the photo.

This report was prepared by Klohn Crippen Consultants Ltd. for Alberta Transportation Central Region under Contract No. CE053/2000.

This report was prepared by Klohn Crippen Consultants Ltd. for Alberta Transportation Central Region under Contract No. CE053/2000. Alberta Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 June 7, 2002 Mr. Melvin Mayfield, P.Eng. Project Engineer Dear Mr. Mayfield: Central Region Landslide Assessment Site

More information

1 PROJECT BACKGROUND. August 14, Alberta Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8

1 PROJECT BACKGROUND. August 14, Alberta Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8 August 14, 2013 Alberta Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 Mr. Dennis Grace, P.Eng. Construction Engineer Dear Mr. Grace: Central Region Geohazard Assessment 2013

More information

1.0 INSPECTION ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER PROJECT, CARMACKS, YUKON. Dear Mr. West-Sells,

1.0 INSPECTION ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER PROJECT, CARMACKS, YUKON. Dear Mr. West-Sells, Doc. No. 162 Rev. 0 Mr. Paul West-Sells President & Chief Operating Officer Western Copper Corporation 2060-1111 West Georgia Street Vancouver, BC V6E 4M3 ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER

More information

South Dam Quinsam Mine. Submitted to: Hillsborough Resources Limited Quinsam Coal Corporation PO Box 5000 Campbell River, BC V9W 8A3

South Dam Quinsam Mine. Submitted to: Hillsborough Resources Limited Quinsam Coal Corporation PO Box 5000 Campbell River, BC V9W 8A3 2015 ANNUAL DAM SAFETY INSPECTION South Dam Quinsam Mine Submitted to: Hillsborough Resources Limited Quinsam Coal Corporation PO Box 5000 Campbell River, BC V9W 8A3 Attention: Mr. Gary Gould REPORT Reference

More information

February 18, 2003 File: NORTH CENTRAL REGION LANDSLIDE ASSESSMENT HWY 43:16 WHITECOURT EAST HILL (NC1) 2002 ANNUAL INSPECTION REPORT

February 18, 2003 File: NORTH CENTRAL REGION LANDSLIDE ASSESSMENT HWY 43:16 WHITECOURT EAST HILL (NC1) 2002 ANNUAL INSPECTION REPORT February 18, 2003 File: 15-76-11 Alberta Transportation Room 223, Provincial Building 4709 44 Avenue Stony Plain, Alberta T7Z 1N4 Attention: Mr. Rob Lonson, P.Eng. NORTH CENTRAL REGION LANDSLIDE ASSESSMENT

More information

Coarse Sediment Traps

Coarse Sediment Traps Coarse Sediment Traps SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils [2] Type 3 System Supplementary Trap Dispersive Soils [1] Though primarily

More information

J.H. Campbell Generating Facility Pond A - Location Restriction Certification Report

J.H. Campbell Generating Facility Pond A - Location Restriction Certification Report J.H. Campbell Generating Facility Pond A - Location Restriction Certification Report Pursuant to: 40 CFR 257.60 40 CFR 257.61 40 CFR 257.62 40 CFR 257.63 40 CFR 257.64 Submitted to: Consumers Energy Company

More information

design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards.

design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards. design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards. In addition to the field inspection, Associated Engineers, Inc.

More information

The results of KCB s site inspection observations and our recommendations for further work are presented herein.

The results of KCB s site inspection observations and our recommendations for further work are presented herein. July 14, 2015 Central Region 401, 4902 51 Street Red Deer, Alberta T4N 6K8 Mr. Tony Penney, P.Eng. Construction Engineer Dear Mr. Penney: June 25, 2015 Site Inspection Report The above site was visited

More information

Numerical analysis of effect of mitigation measures on seismic performance of a liquefiable tailings dam foundation

Numerical analysis of effect of mitigation measures on seismic performance of a liquefiable tailings dam foundation Numerical analysis of effect of mitigation measures on seismic performance of a liquefiable tailings dam foundation Yong-Beom Lee, Jorge Castillo Ausenco, USA Aurelian C. Trandafir Fugro GeoConsulting

More information

Rock & Aggregate Drop Inlet Protection

Rock & Aggregate Drop Inlet Protection Rock & Aggregate Drop Inlet Protection SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System Supplementary Trap Dispersive Soils

More information

December 11, 2006 File:

December 11, 2006 File: December 11, 2006 File: 15-85-38 Alberta Infrastructure and Transportation Room 301, Provincial Building 9621-96 Avenue Peace River, Alberta T8S 1T4 Attention: Mr. Ed Szmata PEACE REGION (SWAN HILLS AREA)

More information

1 INTRODUCTION 1.1 General

1 INTRODUCTION 1.1 General #701 475 Howe Street Vancouver, British Columbia V6C 2B3 August 1, 2014 Robin McCall Wolverine Mine Environmental Superintendent Dear Mr. McCall: 1 INTRODUCTION 1.1 General This letter report presents

More information

CCR Rule Annual Inspection Report (cont.) 2

CCR Rule Annual Inspection Report (cont.) 2 The inspection findings consisted of maintenance items and items that were not observed to be signs or potential signs of significant structural weakness. No deficiencies or disrupting conditions that

More information

U-Shaped Sediment Traps

U-Shaped Sediment Traps U-Shaped Sediment Traps SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils [1] Type 3 System Supplementary Trap Dispersive Soils [1] Generally

More information

Landslide stability analysis using the sliding block method

Landslide stability analysis using the sliding block method Landslide stability analysis using the sliding block method E. Lino, R. Norabuena, M. Villanueva & O. Felix SRK Consulting (Peru) S.A., Lima, Peru A. Lizcano SRK Consulting (Vancouver) S.A., British Columbia,

More information

Seismic Evaluation of Tailing Storage Facility

Seismic Evaluation of Tailing Storage Facility Australian Earthquake Engineering Society 2010 Conference, Perth, Western Australia Seismic Evaluation of Tailing Storage Facility Jonathan Z. Liang 1, David Elias 2 1 Senior Geotechnical Engineer, GHD

More information

Central Queensland Coal Project Appendix 4b Geotechnical Assessment. Environmental Impact Statement

Central Queensland Coal Project Appendix 4b Geotechnical Assessment. Environmental Impact Statement Central Queensland Coal Project Appendix 4b Geotechnical Assessment Environmental Impact Statement GEOTECHNICAL ASSESSMENT OF OPEN CUT MINING ADJACENT TO THE BRUCE HIGHWAY, CENTRAL QUEENSLAND COAL PROJECT

More information

Materials. Use materials meeting the following.

Materials. Use materials meeting the following. 208.01 Section 208. SOIL EROSION AND SEDIMENTATION CONTROL 208.01 Description. Install and maintain erosion and sedimentation controls to minimize soil erosion and to control sedimentation from affecting

More information

Tailing Storage at the Fort Knox Mine An Innovative Expansion to Continue a History of Success

Tailing Storage at the Fort Knox Mine An Innovative Expansion to Continue a History of Success Tailing Storage at the Fort Knox Mine An Innovative Expansion to Continue a History of Success Thomas F. Kerr, P.E. President, Knight Piésold and Co., Denver, USA Peter D. Duryea, Ph.D., P.E. Senior Project

More information

Stormwater Outlet Sediment Traps

Stormwater Outlet Sediment Traps Stormwater Outlet Traps SEDIMENT CONTROL TECHNIQUES Photo 1 Excavated sediment trap just prior to scheduled clean-out (note energy dissipater at end of pipe) Photo 2 A supplementary straw bale barrier

More information

Oposura Scoping Study Nearing Completion

Oposura Scoping Study Nearing Completion 20 AUGUST 2018 KEY POINTS: Oposura Scoping Study Nearing Completion Mining study with open pit optimisations and underground mine designs completed High grade massive sulphide mineralisation occurs near

More information

September 3, 2009 File: NORTH CENTRAL REGION GEOHAZARD ASSESSMENT HWY 40:28 NORTH OF CADOMIN (NC50) 2009 ANNUAL INSPECTION REPORT

September 3, 2009 File: NORTH CENTRAL REGION GEOHAZARD ASSESSMENT HWY 40:28 NORTH OF CADOMIN (NC50) 2009 ANNUAL INSPECTION REPORT GEOTECHNICAL ENVIRONMENTAL MATERIALS September 3, 2009 File: 15-16-226 Alberta Transportation 2 nd Floor, Provincial Building 111 54 Street Edson, Alberta T7E 1T2 Attention: Mr. Cliff Corner NORTH CENTRAL

More information

August 10, 2007 File:

August 10, 2007 File: August 10, 2007 File: 15-85-72 Alberta Infrastructure and Transportation Room 301, Provincial Building 9621-96 Avenue Peace River, AB T8S 1T4 Attention: Mr. Ed Szmata PEACE REGION (PEACE HIGH LEVEL AREA)

More information

Slope Stability Evaluation Ground Anchor Construction Area White Point Landslide San Pedro District Los Angeles, California.

Slope Stability Evaluation Ground Anchor Construction Area White Point Landslide San Pedro District Los Angeles, California. Slope Stability Evaluation Ground Anchor Construction Area White Point Landslide San Pedro District Los Angeles, California Submitted To: Mr. Gene Edwards City of Los Angeles Department of Public Works

More information

Re: Steep Slope Assessment for 2465 Waverly Drive, Blind Bay, BC; Legal Address: Lot 39, Section 18, Township 22, Range 10, Plan 25579, W6M, KDYD.

Re: Steep Slope Assessment for 2465 Waverly Drive, Blind Bay, BC; Legal Address: Lot 39, Section 18, Township 22, Range 10, Plan 25579, W6M, KDYD. OEL File 1563-1 May 30, 2017 Doug Wall PO Box 774 Salmon Arm, BC V1E 4N7 Re: Steep Slope Assessment for 2465 Waverly Drive, Blind Bay, BC; Legal Address: Lot 39, Section 18, Township 22, Range 10, Plan

More information

GOLDPLAY OUTLINES FIVE NEW EXPLORATION TARGETS AT THE SAN MARCIAL PROJECT IN MEXICO

GOLDPLAY OUTLINES FIVE NEW EXPLORATION TARGETS AT THE SAN MARCIAL PROJECT IN MEXICO January 18, 2019 GOLDPLAY OUTLINES FIVE NEW EXPLORATION TARGETS AT THE SAN MARCIAL PROJECT IN MEXICO Vancouver, BC - Goldplay Exploration Ltd. (TSXV: GPLY, FRANKFURT: GPE, OTCQB: GLYXF) ( Goldplay or the

More information

January 17, 2008 File:

January 17, 2008 File: January 17, 2008 File: 15-85-73 Alberta Infrastructure and Transportation Room 301, Provincial Building 9621-96 Avenue Peace River, Alberta T8S 1T4 Attention: Mr. Ed Szmata PEACE REGION (SWAN HILLS AREA)

More information

1. PROJECT BACKGROUND. July 18, Alberta Infrastructure & Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8

1. PROJECT BACKGROUND. July 18, Alberta Infrastructure & Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8 July 18, 2005 Alberta Infrastructure & Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 Mr. Alain Momedi, P.Eng. Project Engineer Dear Mr. Momedi: H11:04 km 11.1 Erosion along

More information

Location. Mt Owen Complex. Overview. Mine Layout. Mining Method. Mitsubishi Lecture. In-Pit Lowwall Dump Design and Stability at Mt Owen Mine

Location. Mt Owen Complex. Overview. Mine Layout. Mining Method. Mitsubishi Lecture. In-Pit Lowwall Dump Design and Stability at Mt Owen Mine Location In-Pit Lowwall Dump Design and Stability at Mt Owen Mine Wayne Bartlett Senior Engineering Geologist Mt Owen Complex Overview In the past Mt Owen Mine lowwall dumps have failed. Lowwall dumps

More information

WHAT IS MINERAL EXPLORATION?

WHAT IS MINERAL EXPLORATION? INDABA PRESENTATION CAPE TOWN FEBRUARY 2017 AIM:SAV WHAT IS MINERAL EXPLORATION? AIM:SAV What is mineral exploration? 2 Exploration is the term used to describe a wide range of activities aimed at searching

More information

B805 TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES - OPSS 805

B805 TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES - OPSS 805 B805 MEASURES - OPSS 805 805.1 GENERAL Construction activities frequently remove protective cover and expose soil to accelerated rates of erosion. Sediments generated thereby can be conveyed via runoff

More information

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area.

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area. Sediment Trench SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils [1] Performance of

More information

ENGINEER S CERTIFICATION OF FAULT AREA DEMONSTRATION (40 CFR )

ENGINEER S CERTIFICATION OF FAULT AREA DEMONSTRATION (40 CFR ) PLATTE RIVER POWER AUTHORITY RAWHIDE ENERGY STATION BOTTOM ASH TRANSFER (BAT) IMPOUNDMENTS LARIMER COUNTY, CO ENGINEER S CERTIFICATION OF FAULT AREA DEMONSTRATION (40 CFR 257.62) FOR COAL COMBUSTION RESIDUALS

More information

HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR (c)(1)(i) (xii)

HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR (c)(1)(i) (xii) HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR 257.73(c)(1)(i) (xii) (i) Site Name and Ownership Information: Site Name: E.C. Gaston Steam Plant Site Location:

More information

The Following was Noted: US Army Corps of Engineers Philadelphia District Geotechnical Section, CENAP-EN-DG

The Following was Noted: US Army Corps of Engineers Philadelphia District Geotechnical Section, CENAP-EN-DG US Army Corps of Engineers Philadelphia District Geotechnical Section, CENAP-EN-DG Wanamaker Bldg, 7th Floor 100 Penn Square East Philadelphia, PA 19107-3396,USA Site Visit Report Date: Tuesday, Nov. 6,

More information

RESERVOIR DRAWDOWN RATES/RESERVOIR DRAWDOWN TEST Iron Gate, Copco (I & II), and JC Boyle Dams

RESERVOIR DRAWDOWN RATES/RESERVOIR DRAWDOWN TEST Iron Gate, Copco (I & II), and JC Boyle Dams TECHNICAL MEMORANDUM No. 1 TO: Michael Bowen California Coastal Conservancy Geotechnical & Earthquake Engineering Consultants CC: Eric Ginney Philip Williams & Associates PREPARED BY: Paul Grant SUBJECT:

More information

Rock Sizing for Multi-Pipe & Culvert Outlets

Rock Sizing for Multi-Pipe & Culvert Outlets Rock Sizing for Multi-Pipe & Culvert Outlets STORMWATER AND WATERWAY MANAGEMENT PRACTICES Photo 1 Rock pad outlet structure at end of a duel stormwater pipe outlet Photo 2 Rock pad outlet structure at

More information

OceanaGold (NZ) Ltd P O Box 5442 Dunedin OTAGO. File: Macraes Round Hill East Project, Technical Report - Final ( )

OceanaGold (NZ) Ltd P O Box 5442 Dunedin OTAGO. File: Macraes Round Hill East Project, Technical Report - Final ( ) 6786 OCEANA GOLD (NZ) LTD MACRAES GOLD PROJECT MINING OF ROUND HILL SOUTHERN PIT MTI, SP10 & SP11A TAILING STORAGE FACILITIES AND RECLAIMED TAILINGS STACK TECHNICAL REPORT Prepared for: 28 April 2011 OceanaGold

More information

CHAPTER GEOLOGICALLY HAZARDOUS AREAS Applicability Regulations.

CHAPTER GEOLOGICALLY HAZARDOUS AREAS Applicability Regulations. CHAPTER 19.07 GEOLOGICALLY HAZARDOUS AREAS 19.07.010 Applicability. Geologically hazardous areas may pose a threat to the health and safety of citizens when incompatible development is sited in areas of

More information

STRUCTURAL STABILITY ASSESSMENT

STRUCTURAL STABILITY ASSESSMENT STRUCTURAL STABILITY ASSESSMENT CFR 257.73(d) Bottom Ash Pond Complex Cardinal Plant Brilliant, Ohio October, 2016 Prepared for: Cardinal Operating Company Cardinal Plant Brilliant, Ohio Prepared by: Geotechnical

More information

Flood Map. National Dataset User Guide

Flood Map. National Dataset User Guide Flood Map National Dataset User Guide Version 1.1.5 20 th April 2006 Copyright Environment Agency 1 Contents 1.0 Record of amendment... 3 2.0 Introduction... 4 2.1 Description of the Flood Map datasets...4

More information

Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services

Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services July 27, 2017 Ms. Rebecca Mitchell Mt. San Antonio College Facilities Planning & Management

More information

Early Exploration Plan Activity Information

Early Exploration Plan Activity Information Early Exploration Plan Activity Information Activities That Require an Early Exploration Plan: Line cutting that is a width of 1.5 metres or less; Geophysical surveys on the ground requiring the use of

More information

Template for Sediment and Erosion Control Plan General Instructions. Section Instructions

Template for Sediment and Erosion Control Plan General Instructions. Section Instructions Template for Sediment and Erosion Control Plan General Instructions Introduction: Soil erosion and sediment deposition from farmlands can contribute to degraded surface water quality. Sediment delivery

More information

Appendix C: Surface Investigations

Appendix C: Surface Investigations Independent Expert Engineering Investigation and Review Panel Report on Mount Polley Tailings Storage Facility Breach Appendix C: Surface Investigations January 30, 2015 Report on Mount Polley Tailings

More information

THE MINISTRY OF ENERGY AND ENERGY INDUSTRIES MINERALS DIVISION MINE DESIGN TEMPLATE OPERATOR NAME: OPERATOR ADDRESS: PHONE NUMBER: FACSIMILE:

THE MINISTRY OF ENERGY AND ENERGY INDUSTRIES MINERALS DIVISION MINE DESIGN TEMPLATE OPERATOR NAME: OPERATOR ADDRESS: PHONE NUMBER: FACSIMILE: THE MINISTRY OF ENERGY AND ENERGY INDUSTRIES MINERALS DIVISION MINE DESIGN TEMPLATE 1.0 GENERAL INFORMATION OPERATOR NAME: OPERATOR ADDRESS: PHONE NUMBER: FACSIMILE: NAME OF CONTACT: CELLULAR PHONE: EMAIL

More information

Orica Australia Pty Ltd Ammonium Nitrate Facility Upgrade

Orica Australia Pty Ltd Ammonium Nitrate Facility Upgrade Orica Australia Pty Ltd Ammonium Nitrate Facility Upgrade January 2010 Revision 0 Contents 1. Introduction 1 1.1 Purpose 1 1.2 Objectives 1 1.3 Relevant Environmental Legislation, Guidelines and Policies

More information

POTENTIAL EFFECTS OF EARTHQUAKE SHAKING ON THE PROPOSED CRRRC LANDFILL

POTENTIAL EFFECTS OF EARTHQUAKE SHAKING ON THE PROPOSED CRRRC LANDFILL TECHNICAL MEMORANDUM DATE September 26, 2016 PROJECT No. 1211250045/14000 TO Andrew Evers Ministry of Environment and Climate Change FROM Alan Hull, Paul Smolkin POTENTIAL EFFECTS OF EARTHQUAKE SHAKING

More information

patersongroup Consulting Engineers April 20, 2010 File: PG1887-LET.01R Novatech Engineering Consultants Suite 200, 240 Michael Cowpland Drive

patersongroup Consulting Engineers April 20, 2010 File: PG1887-LET.01R Novatech Engineering Consultants Suite 200, 240 Michael Cowpland Drive patersongroup April 20, 2010 File: PG1887-LET.01R Novatech Engineering Consultants Suite 200, 240 Michael Cowpland Drive Ottawa, Ontario K2M 1P6 Attention: Mr. Adam Thompson Consulting Engineers 28 Concourse

More information

1.0 INTRODUCTION 2.0 OBSERVATIONS EBA FILE: W nd Avenue Whitehorse, YT Y1A 1C2. Attention:

1.0 INTRODUCTION 2.0 OBSERVATIONS EBA FILE: W nd Avenue Whitehorse, YT Y1A 1C2. Attention: August 5, 2013 City of Whitehorse 2121 2 nd Avenue Whitehorse, YT Y1A 1C2 ISSUED FOR USE EBA FILE: W14103182-01 Via Email: ben.campbell@whitehorse.ca Attention: Subject: Ben Campbell, Planner II Planning

More information

Tailings Dam Classification and Breach Analyses, Perspectives from the Canadian Dam Association

Tailings Dam Classification and Breach Analyses, Perspectives from the Canadian Dam Association Tailings Dam Classification and Breach Analyses, Perspectives from the Canadian Dam Association May 10, 2017 Amec Foster Wheeler 2017. Tailings Dam Classification and Breach Analyses, Perspectives from

More information

Chutes Part 5: Rock linings

Chutes Part 5: Rock linings Chutes Part 5: Rock linings DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent [2] [1] Chutes

More information

Stone Outlet Sediment Trap

Stone Outlet Sediment Trap 3.12 Sediment Control Description: A stone outlet sediment trap is a small detention area formed by placing a stone embankment with an integral stone filter outlet across a drainage swale for the purpose

More information

For personal use only

For personal use only ACN 092 471 513 28 November 2016 ASX Release PENNY S FIND GOLD MINE UPGRADED POTENTIAL FOR MINE LIFE EXTENSION Empire Resources Limited ( Empire, ASX code: ERL) is pleased to give an update on the progress

More information

Modeling Great Britain s Flood Defenses. Flood Defense in Great Britain. By Dr. Yizhong Qu

Modeling Great Britain s Flood Defenses. Flood Defense in Great Britain. By Dr. Yizhong Qu Modeling Great Britain s Flood Defenses AIRCurrents Editor s note: AIR launched its Inland Flood Model for Great Britain in December 2008. The hazard module captures the physical processes of rainfall-runoff

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS G. GEOLOGY AND SOILS

IV. ENVIRONMENTAL IMPACT ANALYSIS G. GEOLOGY AND SOILS IV. ENVIRONMENTAL IMPACT ANALYSIS G. GEOLOGY AND SOILS The following section is a summary of the geotechnical report conducted for the proposed project. The Report of Geotechnical Investigation Proposed

More information

Slope Stability Model of the Questa Rock Pile Phase 2

Slope Stability Model of the Questa Rock Pile Phase 2 2 Proceedings Tailings and Mine Waste 2011 Slope Stability Model of the Questa Rock Pile Phase 2 Murray Fredlund SoilVision Systems Ltd., Saskatoon, Canada Haihua Lu SoilVision Systems Ltd., Saskatoon,

More information

Rock Sizing for Small Dam Spillways

Rock Sizing for Small Dam Spillways Rock Sizing for Small Dam Spillways STORMWATER MANAGEMENT PRACTICES Photo 1 Rock-lined spillway on a construction site sediment basin Photo 2 Rock-lined spillway on a small farm dam 1. Introduction A chute

More information

Introduction 3. Basic Mine Fill Materials 13

Introduction 3. Basic Mine Fill Materials 13 C O N T E N T S 1 Introduction 3 2 1.1 Preamble... 3 1.2 Why mine fill?... 3 1.2.1 Ensuring long-term regional stability... 4 1.2.2 Limiting excavation exposure... 5 1.2.3 Waste disposal... 6 1.3 Considerations

More information

6 MACRAES MINING PROJECT MINERAL ZONE

6 MACRAES MINING PROJECT MINERAL ZONE 6 MACRAES MINING PROJECT MINERAL ZONE 6.1 ZONE STATEMENT The Macraes Mining Zone applies to the area of land controlled by Macraes Mining Limited and included in Mining Permit 41-064 at the date of public

More information

Mark Hawley, Piteau Associates Engineering Ltd. John Cunning, Golder Associates Ltd.

Mark Hawley, Piteau Associates Engineering Ltd. John Cunning, Golder Associates Ltd. Introducing: GUIDELINES FOR MINE WASTE DUMP AND STOCKPILE DESIGN Editors: Mark Hawley, Piteau Associates Engineering Ltd. John Cunning, Golder Associates Ltd. 8 November 2017 Sponsorship 8 November 2017

More information

PEACE REGION GRANDE PRAIRIE GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM NAD 83 COORDINATES N 6,178,811 E 403,309

PEACE REGION GRANDE PRAIRIE GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM NAD 83 COORDINATES N 6,178,811 E 403,309 PEACE REGION GRANDE PRAIRIE GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM SITE NUMBER GP-4a LEGAL DESCRIPTION LSD 12-10-78-4-W6M SITE NAME Burnt River Bridge - West Approach Slide HIGHWAY & KM Hwy 49:06

More information

July 15, 2015 News Release Valley of the Kings Underground Infill Drilling Progresses

July 15, 2015 News Release Valley of the Kings Underground Infill Drilling Progresses July 15, 2015 News Release 15-13 Valley of the Kings Underground Infill Drilling Progresses Vancouver, British Columbia July 15, 2015; Pretium Resources Inc. (TSX/NYSE:PVG) ( Pretivm or the Company ) is

More information

Big Rivers Electric Corporation Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Impoundment Liner Assessment Report

Big Rivers Electric Corporation Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Impoundment Liner Assessment Report Big Rivers Electric Corporation Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Impoundment Liner Assessment Report CCR Surface Impoundment Information Name: Operator:

More information

Early Exploration Permit Activity Information

Early Exploration Permit Activity Information Early Exploration Permit Activity Information Activities That Require an Early Exploration Permit: Line cutting that is a width greater than 1.5 metres Mechanized stripping of a total surface area of greater

More information

The Owl Creek Pit Part 1: Relocating Mine Rock from Surface Stockpiles to the Pit to Mitigate Acid Drainage

The Owl Creek Pit Part 1: Relocating Mine Rock from Surface Stockpiles to the Pit to Mitigate Acid Drainage The Owl Creek Pit Part 1: Relocating Mine Rock from Surface Stockpiles to the Pit to Mitigate Acid Drainage Jeff Martin 1, Thomas Sulatycky 2, Brian Fraser 1, Rina Parker 1, Bruce Rodgers 1 and Ron Nicholson

More information

DESIGN OF WASTE DUMPS WITH FLOW-THROUGH ROCK DRAINS by Peter C. Lighthall, C. David Sellars, and W.D. Burton ABSTRACT

DESIGN OF WASTE DUMPS WITH FLOW-THROUGH ROCK DRAINS by Peter C. Lighthall, C. David Sellars, and W.D. Burton ABSTRACT ABSTRACT DESIGN OF WASTE DUMPS WITH FLOW-THROUGH ROCK DRAINS by Peter C. Lighthall, C. David Sellars, and W.D. Burton A number of mines in mountainous regions of British Columbia are being forced by topographic

More information

9. SLOPE AND EMBANKMENT FAILURES

9. SLOPE AND EMBANKMENT FAILURES 9. SLOPE AND EMBANKMENT FAILURES 9.1 Soil Slope Failures There were some soil slope failures on the banks of roadways and along Ceyhan river (Figures 9.1, 9.2 and 9.3). These are observed Mercimekköy,Yüreğir

More information

Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services

Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services Ms. Rebecca Mitchell Mt. San Antonio College Facilities Planning & Management 1100 North

More information

Review of static and seismic stability of a cross-valley sand tailings embankment in a high rainfall, high seismicity setting

Review of static and seismic stability of a cross-valley sand tailings embankment in a high rainfall, high seismicity setting Tailings and Mine Waste Management for the 21 st Century 2015 Paper Number: 52 Review of static and seismic stability of a cross-valley sand tailings embankment in a high rainfall, high seismicity setting

More information

HUDSON BAY MINING AND SMELTING CO., LIMITED FLIN FLON TAILINGS IMPOUNDMENT SYSTEM. Dust Control Guidelines

HUDSON BAY MINING AND SMELTING CO., LIMITED FLIN FLON TAILINGS IMPOUNDMENT SYSTEM. Dust Control Guidelines HUDSON BAY MINING AND SMELTING CO., LIMITED FLIN FLON TAILINGS IMPOUNDMENT SYSTEM Dust Page 1 of 10 TABLE OF CONTENTS 1.0 INTRODUCTION... 3 2.0 DEFINITIONS OF TERMINOLOGY... 3 3.0 METHODS OF DUST CONTROL...

More information

January 12, 2006 File:

January 12, 2006 File: January 12, 2006 File: 15-85-13 Alberta Infrastructure and Transportation Room 301, Provincial Building 9621-96 Avenue Peace River, Alberta T8S 1T4 Attention: Mr. Ed Szmata PEACE REGION (PEACE HIGH LEVEL

More information

V Sample from C.O.D vein 15 metres southwest of V

V Sample from C.O.D vein 15 metres southwest of V TSX-V: GGX Gold Drop Property Multiple Gold Bearing Rock Samples including 19.6 g/t Gold at Historic C.O.D Shaft And 14.1 g/t Gold at New Vein Showing Greenwood BC Vancouver, British Columbia June 8, 2017

More information

Information Request 12

Information Request 12 Information Request 12 Information Request 12 12-1 Responses to Information Request 12 Response to Information Request 12a Response to Information Request 12b Response to Information Request 12c 12-3 12-7

More information

TAKING THE MYSTERY OUT OF USACE S ER DRILLING IN EARTH EMBANKMENT DAMS AND LEVEES

TAKING THE MYSTERY OUT OF USACE S ER DRILLING IN EARTH EMBANKMENT DAMS AND LEVEES TAKING THE MYSTERY OUT OF USACE S ER 1110-1-1807 DRILLING IN EARTH EMBANKMENT DAMS AND LEVEES 237 237 237 217 217 217 200 200 200 80 119 27 252 174.59 1 255 255 255 0 0 0 163 163 163 131 132 122 239 65

More information

ASANKO GOLD ANNOUNCES ENCOURAGING INITIAL DRILL RESULTS FROM NEW EXPLORATION TARGET

ASANKO GOLD ANNOUNCES ENCOURAGING INITIAL DRILL RESULTS FROM NEW EXPLORATION TARGET PRESS RELEASE ASANKO GOLD ANNOUNCES ENCOURAGING INITIAL DRILL RESULTS FROM NEW EXPLORATION TARGET Highlights: Highly encouraging results from new near-mine exploration target, Akwasiso 10,000 metres of

More information

Implementation of spigot discharge systems for high-density tailings at Sierra Gorda Sociedad Contractual Minera, Chile

Implementation of spigot discharge systems for high-density tailings at Sierra Gorda Sociedad Contractual Minera, Chile Paste 2018 RJ Jewell and AB Fourie (eds) 2018 Australian Centre for Geomechanics, Perth, ISBN 978-0-9924810-8-7 https://papers.acg.uwa.edu.au/p/1805_32_engels/ Implementation of spigot discharge systems

More information

Goldplay President and CEO Marcio Fonseca commented

Goldplay President and CEO Marcio Fonseca commented February 7, 2019 GOLDPLAY ANNOUNCES ITS MAIDEN MINERAL RESOURCE, CONTAINING 36 MILLION Oz AgEq (INDICATED) AND 11 MILLION Oz AgEq (INFERRED), AT THE SAN MARCIAL PROJECT Vancouver, BC - Goldplay Exploration

More information

BEFORE THE ENVIRONMENTAL PROTECTION AUTHORITY AT WELLINGTON

BEFORE THE ENVIRONMENTAL PROTECTION AUTHORITY AT WELLINGTON BEFORE THE ENVIRONMENTAL PROTECTION AUTHORITY AT WELLINGTON IN THE MATTER of the Exclusive Economic Zone and Continental Shelf (Environmental Effects) Act 2012 (EEZ Act) AND IN THE MATTER BETWEEN AND AND

More information

GOLDPLAY ANNOUNCES FURTHER SAMPLING RESULTS FROM SAN MARCIAL HISTORICAL CORE; CONFIRMS OPEN PIT TARGET NEAR SURFACE WITH gpt AgEq.

GOLDPLAY ANNOUNCES FURTHER SAMPLING RESULTS FROM SAN MARCIAL HISTORICAL CORE; CONFIRMS OPEN PIT TARGET NEAR SURFACE WITH gpt AgEq. GOLDPLAY ANNOUNCES FURTHER SAMPLING RESULTS FROM SAN MARCIAL HISTORICAL CORE; CONFIRMS OPEN PIT TARGET NEAR SURFACE WITH 46.0 METERS @ 129 gpt AgEq. August 28, 2018, Vancouver, BC - Goldplay Exploration

More information

Technical Memorandum

Technical Memorandum 2855 Telegraph Avenue, Suite 4, Berkeley, CA 9475, Phone (51) 848-898, Fax (51) 848-8398 Technical Memorandum Date: September 6, 27 To: Mr. Michael Bowen, Project Manager From: Yantao Cui, Ph.D., Hydraulic

More information

VERIFICATION OF MATERIAL PARAMETERS OF EARTHEN DAMS AT DIAMOND VALLEY LAKE USING GEODETIC MEASUREMENTS

VERIFICATION OF MATERIAL PARAMETERS OF EARTHEN DAMS AT DIAMOND VALLEY LAKE USING GEODETIC MEASUREMENTS VERIFICATION OF MATERIAL PARAMETERS OF EARTHEN DAMS AT DIAMOND VALLEY LAKE USING GEODETIC MEASUREMENTS Anna SZOSTAK-CHRZANOWSKI, Canada, Michel MASSIERA, Canada, Adam CHRZANOWSKI, Canada, Fabien LE HOAN,

More information

Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay 19 Module 5: Lecture -1 on Stability of Slopes Contents Stability analysis of a slope and finding critical slip surface; Sudden Draw down condition, effective stress and total stress analysis; Seismic

More information

Background. Valley fills Sites in the Area. Construction over Mine Spoil Fills

Background. Valley fills Sites in the Area. Construction over Mine Spoil Fills Construction over Mine Spoil Fills Wayne A. Karem, PhD, PE, PG, D.GE 2014 KSPE Annual Conference Background Strip mining; mountaintop and contour mining Creates huge quantities of mine spoil The mine spoil

More information

CanAlaska Uranium Details Extensive Rare Earth Mineralization at NE Wollaston

CanAlaska Uranium Details Extensive Rare Earth Mineralization at NE Wollaston FOR IMMEDIATE RELEASE NEWS RELEASE CanAlaska Uranium Details Extensive Rare Earth Mineralization at NE Wollaston Vancouver, Canada, October 20 th, 2009 CanAlaska Uranium Ltd. (CVV TSX.V) (the Company )

More information

(TSXV: GPLY, OTCQB: GLYXF

(TSXV: GPLY, OTCQB: GLYXF GOLDPLAY ANNOUNCES POSITIVE RESULTS FROM SAMPLING OF HISTORICAL CORE AT SAN MARCIAL - ATTRACTIVE SILVER-LEAD-ZINC MINERALIZATION SUPPORTS OPEN PIT POTENTIAL October 09, 2018, Vancouver, BC - Goldplay Exploration

More information

Limited Visual Dam Safety Inspections OA Oahu Reservoir No Oahu, Hawaii

Limited Visual Dam Safety Inspections OA Oahu Reservoir No Oahu, Hawaii Limited Visual Dam Safety Inspections OA00137 Oahu Reservoir No. 155 Oahu, Hawaii Prepared by: U.S. ARMY CORPS OF ENGINEERS HONOLULU DISTRICT STATE OF HAWAII DEPARTMENT OF LAND AND NATURAL RESOURCES May

More information

Sediment Weirs (Instream)

Sediment Weirs (Instream) Sediment Weirs (Instream) INSTREAM PRACTICES Flow Control No Channel Flow Dry Channels Erosion Control Low Channel Flows Shallow Water Sediment Control High Channel Flows [1] Deep Water [1] Sediment weirs

More information

Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils

Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils Sediment Weirs SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils [1] Type 3 classification

More information

June 9, R. D. Cook, P.Eng. Soils Engineer Special Services Western Region PUBLIC WORKS CANADA WESTERN REGION REPORT ON

June 9, R. D. Cook, P.Eng. Soils Engineer Special Services Western Region PUBLIC WORKS CANADA WESTERN REGION REPORT ON PUBLIC WORKS CANADA WESTERN REGION REPORT ON GEOTECHNICAL INVESTIGATION PROPOSED MARTIN RIVER BRIDGE MILE 306.7 MACKENZIE HIGHWAY Submitted by : R. D. Cook, P.Eng. Soils Engineer Special Services Western

More information

Mr. Michael Malone CPS Energy 145 Navarro Street San Antonio, Texas Project No

Mr. Michael Malone CPS Energy 145 Navarro Street San Antonio, Texas Project No January 17, 2018 Mr. Michael Malone 145 Navarro Street San Antonio, Texas 78205 Project No. 0337367 Environmental Resources Management CityCentre Four 840 West Sam Houston Pkwy N. Suite 600 Houston, Texas

More information

Frozen Core Tailings Dam: Part 1, Long-Term Thermal Performance

Frozen Core Tailings Dam: Part 1, Long-Term Thermal Performance Frozen Core Tailings Dam: Part 1, Long-Term Thermal Performance Maritz Rykaart SRK Consulting (Canada) Inc., Vancouver, British Columbia, Canada Peter Luedke SRK Consulting (Canada) Inc., Vancouver, British

More information

16 January 2018 Job Number: RICHARD NEWMAN C\- CLARK FORTUNE MCDONALD AND ASSOCIATES PO BOX 553 QUEENSTOWN

16 January 2018 Job Number: RICHARD NEWMAN C\- CLARK FORTUNE MCDONALD AND ASSOCIATES PO BOX 553 QUEENSTOWN 16 January 2018 Job Number: 50595 RICHARD NEWMAN C\- CLARK FORTUNE MCDONALD AND ASSOCIATES PO BOX 553 QUEENSTOWN CHANSEN@CFMA.CO.NZ STORMWATER DISPOSAL ASSESSMENT Dear Richard, RDAgritech were requested

More information

For personal use only

For personal use only Madagascar Graphite Project Update Drilling Continuing on Main Zone New SW Zone Confirmed Trenching Programme Commenced Cougar Metals NL (ASX Code: CGM) is pleased to provide an update on its exploration

More information

Location Restriction Demonstration

Location Restriction Demonstration Location Restriction Demonstration R.M. Heskett Station Coal Ash Landfill Prepared for Montana-Dakota Utilities Company October 2018 Minneapolis, MN, Bismarck, ND Location Restrictions Demonstration October

More information

CENTRAL REGION GEOHAZARDS RISK ASSESSMENT SITE INSPECTION FORM

CENTRAL REGION GEOHAZARDS RISK ASSESSMENT SITE INSPECTION FORM SITE NUMBER AND NAME C55 H861:02 Slide LEGAL DESCRIPTION NW 14-40-14-W4 CENTRAL REGION GEOHAZARDS RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY & KM NAD 83 COORDINATES N 5811217 E 437291 PREVIOUS INSPECTION

More information

For personal use only

For personal use only ASX ANNOUNCEMENT / MEDIA RELEASE 16 th August, 2013 ASX:ABU Trial Mining Continues and Commissioning of the Old Pirate Processing Plant is Underway ABM Resources NL ( ABM or The Company ) presents an update

More information

Procedure To Be Adopted When Working on High Voltage Mechanically Switched Capacitors with Damping Network (MSCDN)

Procedure To Be Adopted When Working on High Voltage Mechanically Switched Capacitors with Damping Network (MSCDN) 1. SCOPE This document details the procedures to be adopted when working on High Voltage Mechanically Switched Capacitors with. 2. ISSUE RECORD This is a Reference document. The current version is held

More information