Reliability Indices Measurement Reliability Indices Measurement for three 11 kv and 66 kv substations in Brunei Darussalam (PWR 01)

Size: px
Start display at page:

Download "Reliability Indices Measurement Reliability Indices Measurement for three 11 kv and 66 kv substations in Brunei Darussalam (PWR 01)"

Transcription

1 BNERI Reliability Indices Measurement Reliability Indices Measurement for three 11 kv and 66 kv substations in Brunei Darussalam (PWR 01) NUR SABIQAH HAJI ROSLI

2 ACKNOWLEDGEMENT I would like to express my deepest appreciation to all those who provided me the possibility to complete this report. I would also like to acknowledge with much appreciation the crucial role of Robinson Goh, Hajah Zuriyati and Haziqah Nordin, the staff of Department of Electrical Services in the Distribution Department, who provided their power outages and Single Line Network data to complete this Reliability Indices Measurement project. A special gratitude I give to our supervisor, Chief Researcher of Power Department, Dr. Arvind K S Chaudhary, whose contribution in stimulating suggestions and words of encouragement helped me to coordinate this project especially in writing this report. Draft dated 27 th May 2015 i

3 EXECUTIVE SUMMARY One of the Key Performance Indicators (KPI) under the Energy White Paper 2014 is to reduce the number of power outages by 2035, which is in line with Wawasan Therefore, quantitative reliability indices measurement such as System Average Interruption Duration Index (SAIDI) and System Average Interruption Frequency Index (SAIFI) has been calculated for three 11 kv and 66 kv substations in Brunei Darussalam. In this study, IEEE Guide for Electric Power Distribution Reliability Indices (IEEE Std ) is used as the methodology and only unplanned and sustained interruptions are taken into account to provide consistency in all four districts, to review and improve current reliability and performance of distribution system in Brunei Darussalam. To further improve the performance of distribution system, design and implementation of Smart Grid technologies can be utilized in Brunei Darussalam Draft dated 27 th May 2015 ii

4 Table of Contents ACKNOWLEDGEMENT... i EXECUTIVE SUMMARY... ii 1. INTRODUCTION Scope of Work ACRONYMS GLOSSARY POWER SYSTEM RELIABILITY Background SYSTEM AVERAGE INTERRUPTION DURATION INDEX (SAIDI) Distribution System METHODOLOGY IEEE GUIDE Factors that cause variation in reported indices Outages that should not be taken into account when calculating indices Example of using MED definition to identify Major Event Sample System to calculate SAIDI and SAIFI with no MED Catastrophic Days List of data requested from DES for both 11 kv and 66 kv substations SYSTEM RELIABILITY CALCULATION FOR BRUNEI DARUSSALAM Step Restoration Analysis of three 11 kv substations in Brunei Darussalam SAIDI calculation for 11 kv substations SAIFI calculation for 11 kv substations Analysis of three 66 kv substations in Brunei Darussalam SAIDI calculation for 66 kv substations SAIFI POWER OUTAGE Causes of power outages Weather related power outages Faulty Equipment Overcurrent Flashover transformer Animal Contacts People induced including: pole and overhead contacts and underground digging Draft dated 27 th May 2015 iii

5 7.1.7 Short Circuit Electrical Trees Examples of power outages (historical blackouts) CONCLUSION FUTURE WORK References Appendix... A Appendix 1: Power Outages for 2014 and A Appendix 2: List of required data for accurate calculation of SAIDI and SAIFI... W Draft dated 27 th May 2015 iv

6 1. INTRODUCTION More than half of Brunei Darussalam s revenue comes from the energy sector. The Energy White paper has outlined three strategic goals to realize Brunei Darussalam s energy vision. One of the Key Performance Indicator (KPI) is to reduce the number of power outages by 2035, in line with the goals of Wawasan 2035 [1]. The main aim of this project is to provide electric power distribution reliability indices, namely System Average Interruption Duration Index (SAIDI) and System Average Interruption Frequency Index (SAIFI), to benchmark DES (Department of Electrical Services) and chart improvements used in all utilities worldwide. As well as to identify root causes of power outages in Brunei Darussalam. The reliability indices of electric power distribution will follow a set of methodology outlined in IEEE Guide for Electric Power Distribution Reliability Indices [2] to ensure the indices obtained are consistent with best practices in the Power Industry. 1.1 Scope of Work Understand existing distribution equipment and protection philosophy. This includes the understanding of IEEE Std methodology (and other standards Department of Electrical Services (DES) used) and consultation from DES personnel. Gather information from DES. Conduct survey at a few substations and their feeders. Create and understand scenarios given by DES. Obtain and analyze the data given to calculate SAIDI (in minutes) and SAIFI. Compare the results obtained for SAIDI and SAIFI with DES. Write report on SAIDI and SAIFI results and peer review. Execution plan (Gantt chart) is attached at the back of this report. Draft dated 27 th May of 34

7 2. ACRONYMS SAIDI SAIFI DES MIS System Average Interruption Duration Index System Average Interruption Frequency Index Department of Electrical Services Main Intake Station Draft dated 27 th May of 34

8 3. GLOSSARY Customer Interruption Interruption Duration Major Event Major Event Day (MED) Momentary Interruption Outage Planned Interruption Reporting period Sustained Interruption Total number of served A metered electrical service point for which an active bill account is established at a specific location. The total loss of electric power on one or more normally energy conductors to one or more connected to the distribution portion of the system. The time period from the initiation of an interruption until service has been to the affected. An event that exceeds the reasonable design and or operational limits of the electric power system. A day where the daily SAIDI index exceeds a Major Event Day (MED) threshold value. Interruptions which occur on MED should be separately analyzed. The brief loss of power delivery to one or more caused by opening and closing operation of an interrupting device. Usually less than 5 minutes. The loss of ability of a component to deliver power. The loss of electric power to one or more that results from a planned outage. The time period from which interruption data is to be included in the reliability index calculations. Any interruption not classified as a part of a momentary event. Interruption which lasts more than 5 minutes. The average number of served during the reporting period. If a different customer total is used, it must be clearly defined in the report. Draft dated 27 th May of 34

9 4. POWER SYSTEM RELIABILITY 4.1 Background Electric power system is one of the most important and complex systems created by human. It comprises countless facilities and structures, systems and subsystems, components and equipments and interactions between all [3]. It was also reported that more than 50% of reliability depends on the performance of distribution system [3] Electric power has become an essential part of humans lives up to an extent that it is impossible to live without electrical power. This stresses the importance of power system reliability. Reliability of power system is mainly concerned with customer interruptions, thus, it is a subset of power quality [4]. In this report, two main power system reliability indices are looked into, particularly SAIDI (System Average Interruption Duration Index) and SAIFI (System Average Interruption Frequency Index). Additional index such as CAIDI (Customer Average Interruption Duration Index) can also be derived from the initial indices. There are mainly two main types of interruptions, sustained and momentary. Where sustained interruption is closely related to reliability issue (more than five minutes), and momentary interruptions as power quality issue (usually less than five minutes) [2,4]. Figure 1: shows Power Quality Subset [4] Draft dated 27 th May of 34

10 4.2 SYSTEM AVERAGE INTERRUPTION DURATION INDEX (SAIDI) The System Average Interruption Duration Index (SAIDI) indicates the sum duration of interruption for the average customer during a predefined set of time [2]. The unit used to measure SAIDI is in minutes or hours of interruption. The equation used to measure SAIDI is given in Eq. (1)[2]. CustomerMinutesof Interruption SAIDI (1) Total Number of Served To calculate the index, Eq (2) can be used, where r i is restoration time for each interruption event, N i stands for number of for each sustained interruption event during a reporting period, N T is total number of served for the area and CMI stands for customer minutes of interruption [2]. ri Ni CMI SAIDI (2) N N T T Figure 2 shows Unplanned SAIDI for various countries, including exceptional event [5]. Draft dated 27 th May of 34

11 Figure 3 shows Unplanned SAIDI for various countries, excluding exceptional events [5] From Figures 2 and 3, it can be observed that due to the elimination of exceptional events, the SAIDI decreases. Draft dated 27 th May of 34

12 4.3 SYSTEM AVERAGE INTERRUPTION FREQUENCY INDEX (SAIFI) The System Average Interruption Frequency Index (SAIFI) shows how frequently the average customer experiences a sustained interruption over a predefined period of time. The equation used to calculate SAIFI is (Eq 3) [2]. Total Number of Interrupted SAIFI (3) Total Number of Served To calculate the index, Eq (4) can be used. Where CI is [2], Ni CI SAIFI (4) N N T T Figure 4 shows Unplanned SAIFI for various countries, including exceptional event [5]. Draft dated 27 th May of 34

13 Figure 5 shows Unplanned SAIFI for various countries, including exceptional event [5]. 4.4 Distribution System The distribution system is the final stage in delivering electrical power to consumers. An ordinary distribution system consists of step down transformer with various lengths (a few hundred meters to several kilometers), so the voltage can be stepped down to distributed levels for industrial, commercial and residential users [9]. Draft dated 27 th May of 34

14 5. METHODOLOGY IEEE GUIDE In order to accurately develop indices of a power system reliability measurement, IEEE Std was used as a methodology, so as to obtain consistent results amongst utilities in the region. A Major Event Day (MED) is an identified day in which the daily system SAIDI exceeds a threshold value called T MED. Thus, the SAIDI index obtained will be consistent regardless of size of utility and any anomaly (MED value) which may lead to a higher SAIDI value is analyzed separately and removed from indices calculation. A T MED value is typically obtained at the end of each reporting period (one year) for use during the next reporting period as follows [2]: Obtain daily SAIDI values for five years, which ends on the final day of the last entire reporting period. Only include days which have SAIDI/day value which can contribute in calculation of T MED, i.e exclude days where interruptions did not occur. Take the natural log of each daily SAIDI value in the data set Find alpha, the average of the log of the data set Find Beta, the standard deviation of the log of the data set. Compute the MED threshold, using Eq. (5) [2] ( 2.5 ) T MED e (5) Any day with daily SAIDI greater than the threshold value T med that occurs during the subsequent reporting period is classified as MED. 5.1 Factors that cause variation in reported indices There are various factors that can cause difference in the indices reported by different utilities. Some examples are in [2]; Level of automated data collection Geography System design Data classification Draft dated 27 th May of 34

15 It is highly essential to classify performance for each day in the data set to be analyzed as either day-today or MED; false decision may occur when this important step is not performed, as MED may disguise overall daily performance. 5.2 Outages that should not be taken into account when calculating indices There are several types of outages that should not be included when calculating the indices, such as [2]: Interruptions that occur as a result of outage on customer owned facilities Loss of supply from another utility Planned interruptions Momentary interruptions These interruptions are not included in calculation of SAIDI and SAIFI as to provide uniform and consistent policy in all four districts. Furthermore, the calculation is done to review and improve current performance of unplanned events. 5.3 Example of using MED definition to identify Major Event. The following example shows the calculation of Daily SAIDI MED threshold, T MED Identification of MEDs and calculation of adjusted indices. Table 1 shows selected data for all interruptions which occur on a certain day for a utility which serves 2000 DATE TIME DURATION (MIN) NUMBER OF CUSTOMERS INTERRUPTION TYPE July 15, :34: Sustained July 15, :38: Momentary July 15, :42: Sustained Table 1 shows Interruption data for July 15, Draft dated 27 th May of 34

16 For July 15, 1995, daily SAIDI (assumption: a 2000 customer utility) is given in Eq (6): (20 200) ( ) SAIDI min 5.4 Sample System to calculate SAIDI and SAIFI with no MED Table 2 below shows an extract from one utility s customer information system (CIS) database for feeder 7055 [2], which serve 2000 with a total load of 4MW. In this sample system, Circuit 7055 is a representation for the system where the indices are to be calculated. Furthermore, the system consists of all the circuits together in a region for a whole company. Date Time off Time on Circuit Number of Duration Interruption Load kva (min) type Jan :20: S Feb 15 18:23:56 18:24: M Mar 13 00:23:10 01:34: S Apr 24 23:17:00 23:47: S May 27 09:30:10 09:31: M June 22 15:45:39 20:12: S July 19 08:20:00 10:20: S Aug 31 17:10:00 17:20: S Sep 3 10:15:00 10:55: S Table 2: An example of interruption data for a utility Note: S Sustained Interruption, M Momentary Interruption Equations (2) and (3) should be used to calculate the annual indices, using the data shown in Table 2, assuming there were no MEDs in the data. ( ) ( ) ( ) ( ) ( ) (101500) (40100) SAIDI 86.11min SAIFI Draft dated 27 th May of 34

17 5.5 Catastrophic Days It is assumed that, when calculating the daily SAIDI and the 2.5β method, the distribution of the natural log values will look like a Gaussian distribution (a bell-shaped curve) [2]. Events such as hurricanes or ice storms typically result in abnormally higher daily SAIDI values, and these events are called catastrophic events, and have a slim probability of happening [2]. It is typical for catastrophic event, which leads to higher SAIDI values to exist in data sets and this will cause relatively small outward shift in the resulting reliability metric trends [2]. Thus, measures have been taken to identify and process catastrophic, in order to remove the effect it has on reliability metric trends [2]. Furthermore, when catastrophic events are not taken into account, this may cause a huge increase in the events identified as MEDs. It was also proposed that catastrophic events should be processed and determined on an individual company basis by regulators and utilities itself, as no universal solution has been devised to achieve acceptable results [2]. Draft dated 27 th May of 34

18 5.6 List of data requested from DES for both 11 kv and 66 kv substations Data Requested Mentiri Substation Beribi Substation Kuala Belait Substation Mentiri Substation Beribi Substation Kuala Belait Substation Date of power outage Duration of power outage Number of Number of served Step restoration information Stages required to restore power Duration to restore power at each stage Number of at each stage Causes of outage Draft dated 27 th May of 34

19 6. SYSTEM RELIABILITY CALCULATION FOR BRUNEI DARUSSALAM. 6.1 Step Restoration When power outages occur, power is not always fully in one stage, but, it takes a series of stages to restore power to all, this process is called step restoration. A sample calculation is shown below to illustrate how SAIDI is calculated when step restoration takes place. It is also important to know the duration of outages during restoration and number of at a particular restoration time to accurately calculate SAIDI. Figure 6: Single line network representation Draft dated 27 th May of 34

20 Figure 6 shows a representation of single line network. A sample case of step restoration can be broken down into a few steps as follow: When a fault occurs at X, Breaker number 1 opens and isolates the fault. Operation on Breaker number 1 also opens the load break switch (LBS) of substations A, B, C and D. At this point, outage of power occurs at A, B, C and D Operator is sent to site to locate the Fault Circuit Indicator (FCI) which identifies the fault location path. 1. LBS at A 1 is closed to restore partial power. Since load at substation A is, then A 2 is closed. 2. Operator arrives at substation B, checks the FCI and closes LBS B 1 to restore partial power. Since the load at substation B 1 is, then B 2 is closed. 3. Operator arrives at substation C, checks the FCI and closes LBS C 1 to restore partial power. Since the load at substation C 1 is, then C 2 is closed. 4. Operator arrives at substation D, checks the FCI and closes LBS D 1 to restore partial power. Since the load at substation D 1 is, and then D 2 is closed but due to the presence of fault, power is not back to the affected, and fault is detected. This fault is then isolated and reported by operator. Permanent repairs are completed, and power to all is. The outage event is concluded. One example of step restoration took place in Kuala Belait on the 28 th of March 2014; the number of at each restoration was not known in detail. Thus, percentages of are used to illustrate how the amount of initially affects the SAIDI value. Three sample cases are tabulated to calculate SAIDI where the percentages of are varied. The three sample cases are: In Table 4: Equal number of is in four separate restoration times (25%). In Table 5: More are in the first 20 minutes (75%) In Table 6: Remaining 75% of after 80 minutes. Scenario orders numbered 1-4, in Tables 4, 5 and 6 represent the steps (stages) taken to close each LBS (A B, C and D refer to Figure 6), locate the fault and restore power back to Draft dated 27 th May of 34

21 Scenario Order % of remaining Time off Time on Interruption duration (min) (CI) Customer minutes of interruption(cmi) - 0% % :00 12: % :00 12: % :00 1: % :00 1: % SAIDI in mins 50 Table 4: Sample step restoration with equal number of at each stage Scenario Order % of remaining Time off Time on Interruption duration (min) (CI) Customer minutes of interruption(cmi) - 0% % :00 12: % :00 12: % :00 1: % :00 1: % SAIDI in mins 29 Table 5: Sample step restoration where 75% of are in the first 20 minutes Draft dated 27 th May of 34

22 Scenario Order % of remaining Time off Time on Interruption duration (min) (CI) Customer minutes of interruption(cmi) - 0% % :00 12: % :00 12: % :00 1: % :00 1: % SAIDI in mins 71 Table 6: Sample step restoration where 75% of are in the last 20 minutes From the SAIDI values obtained from Table (4), Table (5) and Table (6) above, it can be observed that SAIDI value is smaller when the first batch of are higher (29 mins from Table 5). Meanwhile, when the remaining 75% of are after 80 minutes, the SAIDI value increases to 71 minutes and when equal number of takes place at each restoration time, the value of SAIDI lies in between 71 and 29 minutes, that is 50 minutes. In conclusion, when the distribution of and the number of at each restoration time are not known, it can be seen that, the SAIDI value lies more towards the time when the largest number of are at. 6.2 Analysis of three 11 kv substations in Brunei Darussalam To carry out the calculation to estimate the SAIDI and SAIFI for Brunei Darussalam, three 11 kv substations have been analyzed, which are: Kuala Belait Substation Mentiri Substation Beribi Substation Draft dated 27 th May of 34

23 6.2.1 SAIDI calculation for 11 kv substations To develop the estimates of SAIDI for the three 11 kv substations, a few parameters were looked into in the power outages data provided by DES (Appendix 2), as mentioned in previous chapter (Chapter 5). The parameters are: If restoration of power occur in full or in steps (step restoration) If Major Event Day (MED) is involved (outage which will increase the SAIDI value typically due to natural disasters where outages can last for days) A few step restoration scenarios were identified in Kuala Belait outages in year 2014 and 2013 (no step restoration identified in Beribi and Mentiri). The identified step restoration outages are highlighted in Appendix 2. Further breakdown on calculation of SAIDI for step restoration is laid out below (Tables 7-11). The calculation of SAIDI which involves step restoration cannot be done accurately as the number of at a particular restoration time is not known in detail. Moreover, due to unavailability of five historical years of data, calculation of MED threshold, as per reference from IEEE Std [2] cannot be performed. Thus, in this calculation, it is assumed that equal number of are at each restoration time. KB outage on 22/06/2013 Scenario order % of remaining Time off Time on Interruption duration (min) (CI) Customer minutes of interruption (CMI) - 0% % :00 AM 9:40 AM % :00 AM 10:45 AM TOTAL 100% Table 7: Step restoration calculation for power outage in KB on 22/06/2013 Draft dated 27 th May of 34

24 KB outage 03/08/2013 Scenario order % of remaining Time off Time on Interruption duration (min) (CI) Customer minutes of interruption (CMI) - 0% % :30 AM 4:00 PM % :30 AM 10:00 PM TOTAL 100% Table 8: Step restoration calculation for power outage in KB on 03/08/2013 Scenario order KB Outage 20/01/2014 % of customer s remaining interrupte d Time off Time on Interruption duration (min) (CI) Customer minutes of interruption (CMI) - 0% % :20 PM 7:03 PM % :20 PM 8:55 PM % :20 PM 10:40 PM TOTAL 100% Table 9: Step restoration calculation for power outage in KB on 20/01/2014 Scenario order KB Outage 11/05/2014 % of remaining Time off Time on Interruption duration (min) (CI) Customer minutes of interruption (CMI) - 0% % :15 PM 5:00 PM % :15 PM 5:25 PM TOTAL 100% Table 10: Step restoration calculation for power outage in KB on 11/05/2014 Draft dated 27 th May of 34

25 Scenario order KB Outage 28/05/14 % of remaining Time off Time on Interruption duration (min) (CI) Customer minutes of interruption (CMI) - 0% % :37 AM 1:15 PM % :37 AM 5:15 PM % :37 AM 6:00 PM TOTAL 100% Table 11: Step restoration calculation for power outage in KB on 28/05/2014 To calculate the SAIDI values for Kuala Belait, Mentiri and Beribi; the number of served at each is defined in Table 10, this information is obtained from DES. Venue Number of served Description Kuala Belait Mentiri *84167 Beribi *84167 Table 12: Number of served Total number of accounts in KB Total number of accounts in Brunei Muara Total number of accounts in Brunei Muara *NOTE: No detailed information on the number of served in Mentiri and Beribi, thus total number of accounts in Brunei Muara is used. Upon calculation of customer minutes of interruptions (CMI) for respective 11 kv substations for year 2013 and 2014 (Appendix 2), SAIDI values were calculated and have been tabulated in Figures 7a and 7b as shown below. Draft dated 27 th May of 34

26 Figure 7a: SAIDI chart for 11 kv substations Figure 7b: SAIDI chart for 11 kv substations - with step restoration analysis Draft dated 27 th May of 34

27 6.2.2 SAIFI calculation for 11 kv substations Estimate of SAIFI is carried out for the three substations mentioned earlier. It is observed that the value of SAIFI for Kuala Belait and Mentiri increases from 2013 to 2014, this is possibly due to deteriorating of the equipment for example excess lightning, storm and animal contact. Figure 8: SAIFI chart for 11 kv substations Draft dated 27 th May of 34

28 6.3 Analysis of three 66 kv substations in Brunei Darussalam. Three representative 66 kv substations have also been analyzed to obtain the SAIDI and SAIFI values, which are: Kuala Belait Substation Mentiri Substation Beribi Substation SAIDI calculation for 66 kv substations To develop the estimates of SAIDI for the three 66 kv substations, a few parameters were looked into in the power outages data provided by DES (Appendix 2), as mentioned in previous chapter (Chapter 5). The parameters are: If restoration of power occur in full or in steps (step restoration) If Major Event Day is involved (outage which will increase the SAIDI value typically due to natural disasters where outages can last for days) Scenario order A few step restoration scenarios were identified in Kuala Belait outages in the year 2014 and From the data given by DES, there were no recorded outages in 66 kv substations Mentiri for year 2014 and Beribi for the year 2014 and Further breakdown on calculation of SAIDI for step restoration is laid out below (Tables 13-21). The calculation of SAIDI which involves step restoration cannot be done accurately as the number of at a particular restoration time is not known in detail. Thus, in this calculation, it is assumed that equal number of are at each restoration time. KB Outage on 04/06/2014 % of remaining Time off Time on Interruption duration (min) (CI) Customer minutes of interruption (CMI) - 0% % :30 PM 1:55 PM % :30 PM 2:35 PM TOTAL 100% Table 13: Step restoration calculation for power outage in KB on 04/06/2014 Draft dated 27 th May of 34

29 KB Outage on 21/07/2014 Scenario order % of remaining Time off Time on Interruption duration (min) (CI) Customer minutes of interruption (CMI) - 0% % :15 AM 12:45 PM % :15 AM 1:23 PM % :15 AM 1:47 PM TOTAL 100% Table 14: Step restoration calculation for power outage in KB on 21/07/2014 KB Outage on 07/08/2014 Scenario order % of remaining Time off Time on Interruption duration (min) (CI) Customer minutes of interruption (CMI) - 0% % :19 PM 10:50 PM % :19 PM 11:23 PM TOTAL 100% Table 15: Step restoration calculation for power outage in KB on 07/08//2014 Scenario order KB Outage on 20/03/13 % of remaining Time off Time on Interruption duration (min) (CI) Customer minutes of interruption (CMI) - 0% % :37 AM 8:57 AM % :37 AM 9:45 AM % :37 AM 10:55 AM % :37 AM 12:56 PM TOTAL 100% Table 16: Step restoration calculation for power outage in KB on 20/03/2013 Draft dated 27 th May of 34

30 Scenario order KB Outage on 20/06/13 % of remaining Time off Time on Interruption duration (min) (CI) Customer minutes of interruption (CMI) - 0% % :50 AM 12:45 PM % :50 AM 2:10 PM % :50 AM 6:09 PM TOTAL 100% Table 17: Step restoration calculation for power outage in KB on 20/06//2013 KB Outage on 02/07/13 Scenario order % of remaining Time off Time on Interruption duration (min) (CI) Customer minutes of interruption (CMI) - 0% % :15 PM 2:05 PM % :15 PM 2:57 PM TOTAL 100% Table 18: Step restoration calculation for power outage in KB on 02/07/13 Scenario order KB Outage 18/07/13 % of remaining Time off Time on Interruption duration (min) (CI) Customer minutes of interruption (CMI) - 0% % :37 PM 9:00 PM % :37 PM 9:38 PM TOTAL 100% Table 19: Step restoration calculation for power outage in KB on 18/07//2013 Draft dated 27 th May of 34

31 Scenario order KB outage 02/08/2013 % of remaining Time off Time on Interruption duration (min) (CI) Customer minutes of interruption (CMI) - 0% % :48 PM 12:21 AM % :48 PM 12:52 AM % :48 PM 1:26 AM TOTAL 100% Table 20: Step restoration calculation for power outage in KB on 02/08//2013 Scenario order KB Outage 07/11/2013 % of remaining Time off Time on Interruption duration (min) (CI) Customer minutes of interruption (CMI) - 0% % :00 AM 11:14 AM % :00 AM 11:45 AM TOTAL 100% Table 21: Step restoration calculation for power outage in KB on 07/11/2013 Upon calculation of customer minutes of interruptions (CMI) for respective 66 kv substations for year 2013 and 2014 (Appendix 2), SAIDI values were calculated and have been tabulated in Figures 9a and 9b as shown below. Draft dated 27 th May of 34

32 Figure 9a: SAIDI chart for 66 kv substations Figure 9b: SAIDI chart for 66 kv substations with step restoration calculation Draft dated 27 th May of 34

33 6.3.2 SAIFI SAIFI calculations have been carried out for the three substations mentioned earlier. It can be observed that the SAIFI values for Kuala Belait and Mentiri decrease from 2013 to Since, there were no recorded outages in Beribi for the two consecutive years, the SAIFI value remains zero. Figure 10: SAIFI chart for 66 kv substations Draft dated 27 th May of 34

34 7. POWER OUTAGE Power system outage means a failure of part of the power supply system for example transformer out of service, an open breaker when it should be closed, and a line down [6], a power outage consequentially will lead to a number of consumers being in an absence of electrical energy for a duration of time [3]. Power outage can last a few hours up to several days, and this may greatly impact businesses, manufacturers (in downtime and lost production) [8], and hospitals. 7.1 Causes of power outages. There are several reasons that may contribute to power outages, such as weather related outages (i.e lightning, rain) and other outages caused by man and animals. While it is possible to identify the causes of power outages, absolute future power outage prevention is highly unlikely to take place, but it can be minimized up to a certain degree. Weather related power outages Faulty equipment faulty underground cable Overcurrent trip Flashover transformer Animal contacts People induced including pole and overhead contacts underground digging [9] Weather related power outages. A large number of power failures and outages are caused by natural weather such as thunderstorm, high winds, snow, ice and even dust [7]. In Brunei Darussalam, the occurrence of lightning and thunderstorm is highly frequent, thus, this can be categorized as one of the main causes of power outages in this country. Power outages are mainly caused by damage from trees falling on electrical lines and poles, especially on longer transmission lines which carry bulk power [8], thus circuit breakers or other protective equipment shut off power flow [13] Draft dated 27 th May of 34

35 7.1.2 Faulty Equipment Faulty underground cable has also been identified as one of the reasons for power outages in Brunei Darussalam Overcurrent Overcurrent occurs when excessive electric current flows through a conductor, which may dangerously lead to excessive generation of heat and cause failure in equipment. Thus, circuit breakers trip to shut off power flow Flashover transformer This happens when power lines touch each other or the ground, and consequently lead to short circuit and an arc or a flashover Animal Contacts Animals such as monkeys and squirrels may climb on certain pieces of equipment (transformers and fuses), which consequently causes the equipment to shut down [13] People induced including: pole and overhead contacts and underground digging Pole and overhead contacts during maintenance and excavation work by contractors may accidentally hit underground cables, thus, directly affecting power supply [9] Short Circuit Short circuit happens when an electric current travels a different path from the planned one in an electrical circuit [7]. Due to the excessive electric current, this may lead to circuit damage and consequentially fire and explosion Electrical Trees Electrical treeing is a scenario which affects high power installations such as high power cables and transformers [7]. Partial electric discharges may form in the equipment due to impurities or mechanical defect used in high voltage installations [7]. If the fault goes undetected, this can lead to constant degradation of the equipment and finally result in a major breakdown power loss [7] Draft dated 27 th May of 34

36 7.2 Examples of power outages (historical blackouts). Power outages are common in this modern world, but its adverse effects have played a major role in trying to improve the electrical power system. Some power outages have affected thousands of people, and lasted for a couple of days, in which, this has led to further economic losses. Brazil and Paraguay (10 November 2009) This outage occurred due to natural event; where continuous heavy rain and strong winds had caused a number of transformers to short circuit and consequentially shutting all 20 turbines in the hydroelectric power plant due to sudden fall of power demand. This incident has put a halt to subways operations, and most of Brazil s phone network collapsed. This outage has affected about 87 million people, and lasted from 25 minutes to 7 hours [10]. India (2 January 2001)[cite] A technical failure, more specifically, failure of substation in Uttar Pradesh has caused a widespread of power outages which affected major hospitals, treatment plants, and pumping stations. As a result from this failure, millions of people were affected as the water supply broke down. The outage has also caused chaos in train and land operations. This disruption has affected 226 million people, and lasted for 12 hours and economic losses were estimated to be USD 110million [10]. USA (North East) + Canada (Central) 14 August A large area of Midwest and Northeast United States and Ontario, Canada suffered from power outages due to human error, lack of maintenance and total equipment break down. The power outage lasted for four consecutive days and 50 million people were affected. A total economic loss of USD 6 Billion was also recorded. [10] From the list of examples of outages, it can be observed that reliability of electrical power system plays a major role in everyday life. A power outage may last from a few hours to a few days, and the economic loss a country has to endure during this period can reach billions of dollars. Thus, it is important to put emphasis on reliability of power system, to benchmark and simultaneously improve the electrical power system supplied to consumers. Draft dated 27 th May of 34

37 8. CONCLUSION Reliability indices measurement for SAIDI and SAIFI has been carried out for three 11 kv and 66 kv substations in Brunei Darussalam which are Kuala Belait, Mentiri and Beribi substation. Different types of interruptions were looked into, and to provide consistent policy to all four districts, only sustained and unplanned interruptions are included to review and improve current reliability performance. In the event of widespread of power outages, restoration of power needs to be done in stages (steps). Thus, step restoration sample calculation has been outlined to calculate SAIDI more effectively, by varying the number of per stage since the number of at each stage is not known in detail. A few causes of power outages have also been identified in Brunei Darussalam such as weather related causes (lightning and thunderstorms), faulty equipment, and animal contacts. Furthermore, collection of more data (five years of data) would enable the study of the reliability trend of SAIDI and SAIFI numbers. Specific power outages could also be identified such as problematic circuits or failing of specific equipment, thus, further corrective action can be taken to benchmark DES to other utilities worldwide. This power failure may affect a large number of people and may greatly impact businesses, manufacturers, hospitals and cause economic losses; thus, improving power reliability is of utmost importance. Draft dated 27 th May of 34

38 9. FUTURE WORK From the SAIDI and SAIFI calculations developed for Brunei Darussalam, a few measures can be taken to improve the accuracy of the calculations, such as having a more detailed record of power outages. DES is currently doing a remarkable job at recording power outages across Brunei Darussalam; further addition on the number of at each restoration stage would greatly increase the accuracy of SAIDI and SAIFI calculation. One of the causes of prolonged power outages in Brunei Darussalam is due to the delay in mobilization of personnel to affected areas. Further design improvement of distribution systems using Smart Grid technologies [13] would identify fault location, and enable personnel to reach the affected area faster, thus, a decrease in time to normalize the power outage [11] and a reduced SAIDI number. Furthermore, implementation of advanced intelligent real time communications-based load shedding schemes can be employed to minimize the number of by matching actual loads to required loads to be shed [14]. Typically, pre determined feeders regardless of actual load (based on peak loading conditions) are selected to shed the required loads. Assume priority order for load shedding is Feeder 1, Feeder 2, Feeder 3 and finally, Feeder 4. Assume that the required load shed in stage 1 under frequency is 8 MW. Assuming peak loading for Feeder 1, Feeder 2, Feeder 3 and Feeder 4 is 2, 3, 5 and 8 MW, respectively. During the requirement for under frequency load shedding, the actual loading is 1, 2, 3 and 6 MW respectively. This conventional scheme will result in a total of 12 MW; 4 MW greater than what is necessary. Thus, the utilization of intelligent load shedding [14] would only select Feeder 2 and Feeder 4 to total 8 MW and unnecessary load shedding can be avoided and a better SAIDI and SAIFI number achieved. Draft dated 27 th May of 34

39 References [1] Energy Department, Prime Minister s Office, Energy White Paper, Bandar Seri Begawan: Energy Department, Prime Minister s Office, [2] IEEE Guide for Electric Power Distribution Reliability Indices, IEEE Std , [3] Marko Cepin, Assessment of Power System Reliability: Methods and Applications, London: Springer. [Online]. [4] Richard E. Brown, Electric Power Distribution Reliability, 2 nd edition, USA: CRC Press, 2008 [Online] [5] Council of European Energy Regulators, CEER Benchmarking Report 5.1 on the Continuity of Electricity Supply, CEER, Brussels, Belgium, REF: C13-EQS-57-03, 2014 [Online]. [6] H. Lee Willis, Power Distribution Planning Reference book, 2 nd edition, USA: New York: Marcel Dekker AG, [7] The Many Causes of Power Failures Internet: [Apr. 31, 2015] [8] Richard J. Campbell Weather Related Power Outages and Electric System Resiliency, Congressional Research Service, [9] Distribution Feeder Principles Internet: [Date accessed] [10] Power Blackout Risks. Internet: kout_risks.pdf [11] How the Smart Grid Makes Restoration Faster and Easier for Utilities Internet: [12] Causes of Power Outages Internet: [13] Smart Grid Investments Improve Grid Reliability, Resilience, and Storm Responses [14] Farrokh Shokooh, et. Al. An Intelligent Load Shedding (ILS) System Application in a Large Industrial Facility, in Proc. Industry Applications Conference, 2005, pp , vol. 1. Draft dated 27 th May of 34

40 Appendix Appendix 1: Power Outages for 2014 and 2013 Kuala Belait Outages for 2014 (for 11 kv substation) Date Description Action Taken Time off Time on Duration of Interruptio n in mins Affected area No. of custo mers affecte d Customer minutes of interruption Transformer tripped at substation Telekom Fault was due to bushing HT terminal yellow phase which leaked. Temporary power supplied through gengset. Transformer was replaced by SEC Mashibah at 8.00 am and power supply is normalized. 7.45pm 9.30pm Faulty underground cable from substation Jalan A until X22 Found out that MIS Setia Di-Raja TAMCO (panel 10) and MIS Hospital (Panel 3 Panglima 1) tripped. 6.20pm 10:40pm 260 PekanBelait Kg Pandan RPN Kg Pandan Sg Tujoh and Mumong received power at 7:03 PM. Pandan 3&4 Pandan 6 Jln Panglima and Jalan Maulana received power at 8:55PM. Kg Mumong Utara Kg Mumong Selatan JlnPandan received power at 10:40 PM Mumong (postpaid) JalanSetiaDiraja Incoming panel number 2 from SetiaDiraja tripped on o/c at MIS BatuTiga Overcurrent trip triggered, open bus section to distribute loading. 7:00pm 7:28pm 28 Pandan 6 Kg Pandan Draft dated 27 th May 2015 A

41 RPN Kg Pandan JalanMaulana JalanMaulana, SgPandan Faulty underground cable from in between substation Pandan 5 and Substation Wisma Yakin Power supply given from S/S Kerma Negara to S/S Wisma Yakin at 5:00PM. Power supplied from S/S Batu 2 to S/S Pandan 5 at 5:25 PM 12:15pm 5:25pm 310 Kg Pandan RPN Kg Pandan JalanMaulana JalanMaulana, SgPandan RMU flashover at substation H3 Spg 15 Pandan 5 Trip at TAMCO MIS SetiaDiraja Panel 5 and found RMU flashover at S/S H3. 11:37 PM 6:00 PM 98 JalanMaulana JalanMaulana, Sg. Pandan Normalised affected area at 1:15 PM. Temporary power given to Spg 15 at 5:15 PM. Kg Pandan RPN Kg. Pandan Pandan 3&4 Spg 29 and Spg received power supply at 6:30 PM. Repairs of RMU started at 6:00 PM and ended at 12:50 AM KVA transformer flashover at substation H21 Spg Temporary power supply given through gengset from 8:00 PM until 2:50 AM. Power normalized back at 3:00 AM. 5:00 pm 8:00 pm 180 JalanMaulana JalanMaulana, SgPandan Pandan Kg. Pandan RPN Kg. Pandan Draft dated 27 May 2015 B

42 Panel 5 Panaga Fuji to circuit Kuala Balai trip on overcurrent Switch on again. Intermittent fault. 9:30 am 11:15 am 105 Kg Kuala Balai Panel number 5 to circuit Kuala Belait trip on overcurrent at MIS Panaga Switch on again. Intermittent fault. 7:00 pm 7:15pm 15 Kg Kuala Balai Panel number 5 Fuji to circuit Kuala Balai trip on overcurrent at MIS Panaga Switch on again. Intermittent fault. 5:45pm 7:30 pm 105 Kg Kuala Balai Fault 800KVA transformer at substation Buruh housing Temporary power supplied through 500 kva started at 4:20 PM. 2:45pm 4:20pm 95 Kg Mumong Utara Kg Mumong Selatan Mumong (postpaid) ERM feeder (Substation SekolahPersediaan Arab to Substation Mumong A) trip due to BSP contractor (seismic project) hit underground cable (blue phase) between substation Jati 6 and Jati 7. Affected areas normalized at 3:20 pm. 2:07 pm 3:20 pm 73 Kg Mumong Utara Kuala Belait Outages for 2013 (11 kv substation) Date Description Action Taken Time off Time on Duration of Interruptio n in mins Affected area No. of custo mers affecte d Customer minutes of interruption Received complaint from 144 informing low voltage Low voltage found at S/S w7 and S/S Batu 4 due to 66 kv transformer at MIS Panaga low tapping and changed tapping from 6 to 9. 10:00 PM 12:00 AM 120 JalanMaulana JalanMaulana (postpaid) Draft dated 27 May 2015 C

43 Flashover of transformer at substation Jati 1 Spg Changed to a new transformer. Temporary power supplied using two gengset. 5:00 PM 12:00 AM 420 STKRJA area, SPG , SPG and JalanDipa Negara Faulty underground cable from human work? Isolated faulty cable between MIS Batu 3 until S.S Eng Hong. Supplied power through ring. 9:30AM 12:05 PM 155 JalanMaulana JalanMaulana (postpaid) JalanPandan 1 JalanPandan 2 JalanPandan 3 Pandan 7 Pandan Faulty underground cable from MIS BT.3 to substation Eng Hong Power supplied via alternative circuit. 8:50 AM 9:31 AM 41 JalanSingaMenteri Pandan Faulty underground cable between MIS Panaga to Substation Kuala Balai Power supplied from 4 gengset at S/S Kuala Balai. 9:40 AM 6:30 PM 530 JalanSingaMenteri Kuala Balai Power cut off Power cut off due to animal contact on jumper HT cable and aerial cable, which caused breaker at Panel Bandaran to get tripped. Switched off supply to S/S SgDuhon and switched breaker back on at MIS SetiaDiraja Power cut off Found RMU 2R2T (ABB) flashover at s/s Kuala Balai A. Temporary power supplied using 4 gengset Power cut off Found out transformer 1000Kva tripped at S/S 4:25 PM 4:45 PM 20 Jalan Sungai Duhun :00 AM 10:45 AM 225 Jalan Kuala Balai :18 AM 9:45 AM Draft dated 27 May 2015 D

44 Kuala Balai E HjTalip. Switched back on, and normalized affected area No power Found faults at station transformer. Temporary power supplied using mobile generator. 7:50 PM 10:45 PM Faulty underground cable due to human work?? Found out underground cable from Jati 7 to S/S penapisan najis 1 (JKR) faulty and a trip at MIS Panaga. Isolated faulty underground cable and found out more faults at cable from S/S Mumong to package unit (RMU) at S/S. Power supply normalized at 4:00 PM except Spg 284 Mumong, power supplied through generator at S/S Saluran najis at 10: 00 PM 11:30 AM 10:00 PM 630 JalanSingaMenteri Pandan 8 Mumong B Kg Mumongutara Mumong (postpaid) Power cut off Checked and found out transformer No. 3 tripped due to overcurrent at MIS Setia DiRaja Siemen. Transformer switched back on and normalized affected areas Power cut off 1000 kva transformer tripped at S/S Jalan Patai. Transformer switched back on. 1:45 PM 3:30 PM 105 Pekan KB Kg Pandan RPN Kg Pandan JlnMaulana, SgPandan (postpaid) Pandan 3&4 Pandan 6 4:00 PM 4:30 PM 30 JlnPetai LubokNipah Power cut off Electricity tripped at TAMCO Panel 5 at MIS 10:50 AM 12:26 PM 96 JalanSetiaPahlawan Draft dated 27 May 2015 E

45 Setia Di Raja. Found out there was a flashover at termination in RMU in S/S Pejabat Elecktrik. Normalised affected areas. JalanSgSatu Pandan 5 Pandan 6 Beribi Outages for 11kV substation 2014 Date Description Action Taken Time off Time on Duration of Interruptio n in mins Affected area No. of custome rs Affected Customer minutes of interruption Substation Jalan Jasmin Beribi The RMU oil type (Long &Crowfort). 2:00 PM 3:30 PM 90 Jalan Jasmin Kg Beribi Feeder T tripped. Change to RMU (Brush Hacker Siddley) Overcurrent due to load transfer Transferred load and energized one by one by considering the load. 9:00 AM 11:32 AM 152 Baiduri Bank Kg Kiarong Kg Beribi Kg Kiulap MIS Telanai P#13 tripped and indicated earthfault and overcurrent. HV underground yellow phase faulty. 12:30 AM 1:50 AM 80 Spg 493, Spg 2, Flat E, SgSunda Housing New Housing Kg Beribi MIS Beribi Industry Phase 1 P#4 tripped to ERM Beribi Industry 3 and indicated earthfault. 3:00 AM 4:30 PM 90 Light Beribi Industrial area Draft dated 27 May 2015 F

DISTRIBUTION SYSTEM ELECTRIC INFRASTRUCTURE RELIABILITY PERFORMANCE INDICATORS

DISTRIBUTION SYSTEM ELECTRIC INFRASTRUCTURE RELIABILITY PERFORMANCE INDICATORS EB-- Exhibit D Page of DISTRIBUTION SYSTEM ELECTRIC INFRASTRUCTURE RELIABILITY PERFORMANCE INDICATORS FIVE-YEAR HISTORICAL RELIABILITY PERFORMANCE THESL tracks System Average Interruption Frequency Index

More information

BVES Annual Reliability Public Presentation 2016 Performance

BVES Annual Reliability Public Presentation 2016 Performance BVES Annual Reliability Public Presentation 2016 Performance December 13, 2017 Agenda Company Overview What is Electric Utility Reliability? Requirements & Definitions Reliability Indices 2016 Reliability

More information

ELECTRIC SYSTEM RELIABILITY ANNUAL REPORT

ELECTRIC SYSTEM RELIABILITY ANNUAL REPORT ELECTRIC SYSTEM RELIABILITY ANNUAL REPORT 2015 LIBERTY UTILITIES (CALPECO ELECTRIC) LLC (U 933 E) -- PUBLIC VERSION -- Prepared for California Public Utilities Commission July 15, 2016 EXECUTIVE SUMMARY

More information

PUB NLH 185 Island Interconnected System Supply Issues and Power Outages Page 1 of 9

PUB NLH 185 Island Interconnected System Supply Issues and Power Outages Page 1 of 9 PUB NLH 1 Page 1 of 1 Q. Provide Hydro s list of outage cause codes and indicate how troublemen are managed and trained to properly use the codes. Explain the method used to report outage causes. A. Hydro

More information

Network Quality and Reliability of Supply

Network Quality and Reliability of Supply Network Quality and Reliability of Supply Performance Report 2010/11 Prepared by: Operations Asset & Works Audited by: Qualeng Left blank intentionally DMS 3444560 2 CONTENTS Horizon Power service area

More information

Section 5. TADS Data Reporting Instruction Manual DRAFT Section 5 and Associated Appendices With Proposed Event Type Numbers

Section 5. TADS Data Reporting Instruction Manual DRAFT Section 5 and Associated Appendices With Proposed Event Type Numbers Section 5 TADS Data Reporting Instruction Manual DRAFT Section 5 and Associated Appendices With Proposed Event Type Numbers Rev. 5/10/2010 1 Section 5 Form for Event ID and Event Type Number Data TO s

More information

Electric Distribution Storm Hardening Initiatives. Paul V. Stergiou Distribution Engineering October 14 th, 2015

Electric Distribution Storm Hardening Initiatives. Paul V. Stergiou Distribution Engineering October 14 th, 2015 Consolidated Edison Company of New York, Inc. Electric Distribution Storm Hardening Initiatives Paul V. Stergiou Distribution Engineering October 14 th, 2015 Energy For New York City And Westchester 3.3

More information

Peterborough Distribution Inc Ashburnham Drive, PO Box 4125, Station Main Peterborough ON K9J 6Z5

Peterborough Distribution Inc Ashburnham Drive, PO Box 4125, Station Main Peterborough ON K9J 6Z5 Peterborough Distribution Inc. 1867 Ashburnham Drive, PO Box 4125, Station Main Peterborough ON K9J 6Z5 November 15, 2017 Ontario Energy Board PO Box 2319 27 th Floor, 2300 Yonge St Toronto ON M4P 1E4

More information

URD Cable Fault Prediction Model

URD Cable Fault Prediction Model 1 URD Cable Fault Prediction Model Christopher Gubala ComEd General Engineer Reliability Analysis 2014 IEEE PES General Meeting Utility Current Practices & Challenges of Predictive Distribution Reliability

More information

IS YOUR BUSINESS PREPARED FOR A POWER OUTAGE?

IS YOUR BUSINESS PREPARED FOR A POWER OUTAGE? IS YOUR BUSINESS PREPARED FOR A POWER OUTAGE? Keeping your power on is our business Whether your business is large, small or somewhere in between, we understand that a power outage presents special challenges

More information

Superconducting Fault Current Limiters

Superconducting Fault Current Limiters Superconducting Fault Current Limiters First Friday Club 1 st April 2011 Gerhard Novak UK Technical Manager Joachim Bock Managing Director, Nexans Superconductors 1 Smart Grid Solutions 2 Fault current

More information

Norm Hann Performance Manager, Performance Management Department Hydro One Networks Inc.

Norm Hann Performance Manager, Performance Management Department Hydro One Networks Inc. Norm Hann Performance Manager, Performance Management Department Hydro One Networks Inc. Phone: (416)-345-5407 Email: Norm.Hann@HydroOne.com Closing the Crevice Achieving A Process For Asset Performance

More information

Power System Research Group Electrical Engineering Dept., University of Saskatchewan Saskatoon, Canada

Power System Research Group Electrical Engineering Dept., University of Saskatchewan Saskatoon, Canada Abstract Failure Bunching Phenomena in Electric Power Transmission Systems Roy Billinton Gagan Singh Janak Acharya Power System Research Group Electrical Engineering Dept., University of Saskatchewan Saskatoon,

More information

Report on Reliability of ComEd Electrical Service within Downers Grove. Prepared September 1, 2013

Report on Reliability of ComEd Electrical Service within Downers Grove. Prepared September 1, 2013 Report on Reliability of ComEd Electrical Service within Downers Grove Prepared September 1, 2013 1 Executive Summary Since 2011, the Village of Downers Grove has worked closely with ComEd to improve electrical

More information

Resiliency of Power Grids After Earthquakes

Resiliency of Power Grids After Earthquakes Resiliency of Power Grids After Earthquakes John Eidinger, Alex Tang ATC 16th US - Japan - New Zealand Workshop Nara, June 27-29, 2016 eidinger@geengineeringsystems.com alexktang@mac.com No Power = No

More information

The Study of Overhead Line Fault Probability Model Based on Fuzzy Theory

The Study of Overhead Line Fault Probability Model Based on Fuzzy Theory Energy and Power Engineering, 2013, 5, 625-629 doi:10.4236/epe.2013.54b121 Published Online July 2013 (http://www.scirp.org/journal/epe) The Study of Overhead Line Fault Probability Model Based on Fuzzy

More information

Review of. Florida s Investor-Owned Electric Utilities Service Reliability reports. State of Florida

Review of. Florida s Investor-Owned Electric Utilities Service Reliability reports. State of Florida Review of Florida s Investor-Owned Electric Utilities 2 0 1 1 Service Reliability reports N O V E M B E R 2 0 1 2 State of Florida Florida Public Service Commission Division of ENGINEERING Review of Florida

More information

Cascading Outages in Power Systems. Rui Yao

Cascading Outages in Power Systems. Rui Yao Cascading Outages in Power Systems Rui Yao yaorui.thu@gmail.com Outline Understanding cascading outages Characteristics of cascading outages Mitigation of cascading outages Understanding cascading outages

More information

Circuit Reliability Review

Circuit Reliability Review Circuit Reliability Review Marina Del Rey January 2018 Building a Smarter Grid for Southern California Southern California Edison is developing an electric grid to support California s transition to a

More information

Minnesota Public Utilities Commission Staff Briefing Papers

Minnesota Public Utilities Commission Staff Briefing Papers Minnesota Public Utilities Commission Staff Briefing Papers Meeting Date: March 7, 2006 Agenda Item # *10 Company: Docket Nos. Minnesota Power Northwestern Wisconsin Electric Company Interstate Power and

More information

Debbie Lee, Communications and Public Affairs Officer. Update on Southern California Edison s Capital Improvement Projects

Debbie Lee, Communications and Public Affairs Officer. Update on Southern California Edison s Capital Improvement Projects Information Item Date: June 22, 2015 To: From: Subject: Mayor and City Council Debbie Lee, Communications and Public Affairs Officer Update on Southern California Edison s Capital Improvement Projects

More information

Review of. Florida s Investor-Owned Electric Utilities Service Reliability reports. State of Florida

Review of. Florida s Investor-Owned Electric Utilities Service Reliability reports. State of Florida Review of Florida s Investor-Owned Electric Utilities 2 0 1 2 Service Reliability reports N O V E M B E R 2 0 1 3 State of Florida Florida Public Service Commission Division of ENGINEERING Review of Florida

More information

NORDIC AND BALTIC GRID DISTURBANCE STATISTICS 2015

NORDIC AND BALTIC GRID DISTURBANCE STATISTICS 2015 NORDIC AND BALTIC GRID DISTURBANCE STATISTICS 23.01.2017 REGIONAL GROUP NORDIC 1 INTRODUCTION... 4 1.1 DESCRIPTION OF THE REPORT... 4 1.2 CONTACT PERSONS... 5 1.3 VOLTAGE LEVELS IN THE NORDIC AND BALTIC

More information

Reliability Assessment of Radial distribution system incorporating weather effects

Reliability Assessment of Radial distribution system incorporating weather effects International Journal of Engineering Research and Development e-issn: 2278-067X, p-issn: 2278-800X, www.ijerd.com Volume 6, Issue 7 (pril 2013), PP. 45-51 Reliability ssessment of Radial distribution system

More information

1. Wind turbines are designed to operate within specified design criteria. Often the operating environment extends beyond these limits and causes

1. Wind turbines are designed to operate within specified design criteria. Often the operating environment extends beyond these limits and causes 1 2 1. Wind turbines are designed to operate within specified design criteria. Often the operating environment extends beyond these limits and causes outages. How these outages are classified can be challenging

More information

Report on Reliability of ComEd Electrical Service within Downers Grove. Prepared November 13, 2015

Report on Reliability of ComEd Electrical Service within Downers Grove. Prepared November 13, 2015 Report on Reliability of ComEd Electrical Service within Downers Grove Prepared November 13, 2015 1 Executive Summary Since 2011, the Village of Downers Grove has worked closely with ComEd to improve electrical

More information

How Power is Restored After a Severe Storm. Presented by Stacy Shaw, Safety Director & Nolan Hartzler, GIS Mapping Technician

How Power is Restored After a Severe Storm. Presented by Stacy Shaw, Safety Director & Nolan Hartzler, GIS Mapping Technician How Power is Restored After a Severe Storm Presented by Stacy Shaw, Safety Director & Nolan Hartzler, GIS Mapping Technician Hurricanes, ice storms, tornadoes One inch of ice on a single span of electric

More information

Director, Operations Services, Met-Ed

Director, Operations Services, Met-Ed Director, Operations Services, Met-Ed Pennsylvania House Republican Policy Committee Hearing on Storm Response Tobyhanna Township Municipal Building Pocono Pines, Pa. August 9, 2018 Planning and Forecast

More information

Fault Calculation Methods

Fault Calculation Methods ELEC9713 Industrial and Commercial Power Systems Fault Calculation Methods There are two major problems that can occur in electrical systems: these are open circuits and short circuits. Of the two, the

More information

Risk Analysis for Assessment of Vegetation Impact on Outages in Electric Power Systems. T. DOKIC, P.-C. CHEN, M. KEZUNOVIC Texas A&M University USA

Risk Analysis for Assessment of Vegetation Impact on Outages in Electric Power Systems. T. DOKIC, P.-C. CHEN, M. KEZUNOVIC Texas A&M University USA 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium Risk Analysis for Assessment of Vegetation Impact on Outages in Electric Power Systems

More information

Network Quality and Reliability of Supply Code

Network Quality and Reliability of Supply Code Network Quality and Reliability of Supply Code 2017/18 Performance Report Prepared by: Asset Services Left blank intentionally DM#10417247 2017/18 Page 2 of 22 Contents 1. INTRODUCTION 5 2. AUDIT REQUIREMENTS

More information

Deep Thunder. Local Area Precision Forecasting for Weather-Sensitive Business Operations (e.g. Electric Utility)

Deep Thunder. Local Area Precision Forecasting for Weather-Sensitive Business Operations (e.g. Electric Utility) 1 Deep Thunder Local Area Precision Forecasting for Weather-Sensitive Business Operations (e.g. Electric Utility) Dipl. Ing. Helmut Ludwar Chief Technologist Wien, im Oktober 2010 Forecasts for Weather-Sensitive

More information

Review of Florida s Investor-Owned Electric Utilities Service Reliability Reports. September

Review of Florida s Investor-Owned Electric Utilities Service Reliability Reports. September Review of Florida s Investor-Owned Electric Utilities 2 0 1 5 Service Reliability Reports September 2 0 1 6 State of Florida Florida Public Service Commission Division of Engineering Review of Florida

More information

Reven ue Req u i remen t Ap pl icat ion 2004/05 and 2005/06. BC hydro m W. Volume 2. Appendix L. System Performance Indicators

Reven ue Req u i remen t Ap pl icat ion 2004/05 and 2005/06. BC hydro m W. Volume 2. Appendix L. System Performance Indicators Reven ue Req u i remen t Ap pl icat ion 00/0 and 00/0 BC hydro m W Volume Appendix L. System Performance Indicators BChydro m ui Table of Contents LIST OF FIGURES... I LIST OF TABLES... I LIST OF SCHEDULES...

More information

A new FMECA model for reliability computations in electrical distribution systems

A new FMECA model for reliability computations in electrical distribution systems Proceedings of the 6th WSEAS/IASME Int. Conf. on Electric Power Systems, High Voltages, Electric Machines, Tenerife, Spain, December 6-8, 2006 A new FMECA model for reliability computations in electrical

More information

Vegetation Related Transmission Outage Report

Vegetation Related Transmission Outage Report Vegetation Related Transmission Outage Report Third 2013 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com Executive Summary The NERC Board of Trustees Compliance

More information

Study of Time Correlation Between Lightning Data Recorded by LLS and Relay Protection

Study of Time Correlation Between Lightning Data Recorded by LLS and Relay Protection 2012 International Conference on Lightning Protection (ICLP), Vienna, Austria Study of Time Correlation Between Lightning Data Recorded by LLS and Relay Protection Ivo Uglešić, Viktor Milardić, Bojan Franc

More information

Applications of GIS in Electrical Power System

Applications of GIS in Electrical Power System Applications of GIS in Electrical Power System Abdulrahman M. AL-Sakkaf 201102310 CRP 514 May 2013 Dr. Baqer M. AL-Ramadan Abstract GIS has been widely used in various areas and disciplines. This paper

More information

HAZUS-MH: Earthquake Event Report

HAZUS-MH: Earthquake Event Report HAZUS-MH: Earthquake Event Report Region Name: El Paso County Earthquake Scenario: El Paso County Random EQ Print Date: February 08, 2006 Disclaimer: The estimates of social and economic impacts contained

More information

Review of Florida s Investor-Owned Electric Utilities Service Reliability Reports. November

Review of Florida s Investor-Owned Electric Utilities Service Reliability Reports. November Review of Florida s Investor-Owned Electric Utilities 2 0 1 6 Service Reliability Reports November 2 0 1 7 State of Florida Florida Public Service Commission Division of Engineering Review of Florida

More information

Effects of Capacitor Bank Installation in a Medium Voltage (MV) Substation

Effects of Capacitor Bank Installation in a Medium Voltage (MV) Substation Effects of Capacitor Bank Installation in a Medium Voltage (MV) Substation Adesina, Lambe Mutalub Department of Engineering & Standardization, Eko Electricity Distribution Plc, 24/25, Marina, Lagos Island,

More information

2013 December Ice Storm

2013 December Ice Storm 2013 December Ice Storm The 2013 December ice storm caused major damage to the Lansing Board of Water & Light (BWL) electric distribution system and had a devastating effect on many BWL customers. We realize

More information

P.O BOX 429, NUKU ALOFA, Tel: (676) Fax: (676)

P.O BOX 429, NUKU ALOFA, Tel: (676) Fax: (676) P.O BOX 429, NUKU ALOFA, Tel: (676) 21-400 Fax: (676) 23-047 Email: afernando@tongapower.to 27 February, 2015 Lord Dalgety Electricity Commission Tu atakilangi Nuku alofa Dear Lord Dalgety Re: Monthly

More information

1. Explain the various methods of methods of grounding. In power system, grounding or earthing means connecting frame of electrical equipment (non-cur

1. Explain the various methods of methods of grounding. In power system, grounding or earthing means connecting frame of electrical equipment (non-cur 1. Explain the various methods of methods of grounding. In power system, grounding or earthing means connecting frame of electrical equipment (non-current carrying part) or some electrical part of the

More information

Renewables and the Smart Grid. Trip Doggett President & CEO Electric Reliability Council of Texas

Renewables and the Smart Grid. Trip Doggett President & CEO Electric Reliability Council of Texas Renewables and the Smart Grid Trip Doggett President & CEO Electric Reliability Council of Texas North American Interconnected Grids The ERCOT Region is one of 3 North American grid interconnections. The

More information

Storm Damage Modeling at Pacific Gas & Electric

Storm Damage Modeling at Pacific Gas & Electric 1 Storm Damage Modeling at Pacific Gas & Electric Mike Voss PG&E Applied Technology Insert damage photos March 2015 Gas System Operations Electric Operations Power-Gen/ Hydro 2 Short Term Energy Supply

More information

Complete Weather Intelligence for Public Safety from DTN

Complete Weather Intelligence for Public Safety from DTN Complete Weather Intelligence for Public Safety from DTN September 2017 White Paper www.dtn.com / 1.800.610.0777 From flooding to tornados to severe winter storms, the threats to public safety from weather-related

More information

APPLICATION OF GIS IN ELECTRICAL DISTRIBUTION NETWORK SYSTEM

APPLICATION OF GIS IN ELECTRICAL DISTRIBUTION NETWORK SYSTEM See discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/305263658 APPLICATION OF GIS IN ELECTRICAL DISTRIBUTION NETWORK SYSTEM Article October 2015

More information

Reducing Wildfire Risk through the Use of Advanced Electrical Waveform Monitoring and Analytics

Reducing Wildfire Risk through the Use of Advanced Electrical Waveform Monitoring and Analytics 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2013 Grid of the Future Symposium Reducing Wildfire Risk through the Use of Advanced Electrical Waveform Monitoring and

More information

OPALCO Outage Analysis. December 2017 Board Meeting

OPALCO Outage Analysis. December 2017 Board Meeting OPALCO Outage Analysis December 217 Board Meeting What causes power outages in the islands? Wind Rain Major outages happen most often during wind storms - when winds are blowing above 3 miles per hour.

More information

The Pennsylvania State University. The Graduate School. College of Engineering ANALYSIS OF HOURLY WEATHER FORECASTS AS AN INDICATOR OF OUTAGE

The Pennsylvania State University. The Graduate School. College of Engineering ANALYSIS OF HOURLY WEATHER FORECASTS AS AN INDICATOR OF OUTAGE The Pennsylvania State University The Graduate School College of Engineering ANALYSIS OF HOURLY WEATHER FORECASTS AS AN INDICATOR OF OUTAGE CHARATERISTICS IN AN ELECRIC POWER SERVICE SYSTEM A Thesis in

More information

PROCEDURE NO.: SO5-2-6 PAGES: 1 OF 10 CHIEF SYSTEM OPERATOR

PROCEDURE NO.: SO5-2-6 PAGES: 1 OF 10 CHIEF SYSTEM OPERATOR CON EDISON SYSTEM OPERATION DEPARTMENT PROCEDURE SUBJECT: THUNDERSTORM/STORM PROCEDURE PROCEDURE NO.: SO5-2-6 PAGES: 1 OF 10 REVISED BY: S. BUFFAMANTE APPROVED: T. HALLERAN CHIEF SYSTEM OPERATOR DATE:

More information

Correlation between Lightning Impacts and Outages of Transmission Lines. H-D. BETZ Nowcast GmbH Munich Germany

Correlation between Lightning Impacts and Outages of Transmission Lines. H-D. BETZ Nowcast GmbH Munich Germany CIGRE C4 Colloquium on Power Quality and Lightning Sarajevo, Bosnia and Herzegovina, 13 16 May, 2012 Paper 01. Correlation between Lightning Impacts and Outages of Transmission Lines I. UGLEŠIĆ V. MILARDIĆ

More information

Reference: US Department of Energy.

Reference: US Department of Energy. Center for Energy, Economic & Environmental Policy Rutgers, The State University of New Jersey 33 Livingston Avenue, First Floor New Brunswick, NJ 08901 http://ceeep.rutgers.edu/ 732-932-5680 Fax: 732-932-0394

More information

Winter Ready DC District of Columbia Public Service Commission

Winter Ready DC District of Columbia Public Service Commission Winter Ready DC District of Columbia Public Service Commission Presented by: Michael Poncia, Vice President, Customer Operations, Pepco Holdings October 26, 2017 Preparing our System Improving our system

More information

elgian energ imports are managed using forecasting software to increase overall network e 칁 cienc.

elgian energ imports are managed using forecasting software to increase overall network e 칁 cienc. Elia linemen install Ampacimon real time sensors that will communicate with the dynamic thermal ratings software to control energy import levels over this transmission line. OV RH AD TRAN MI ION D namic

More information

COMPANY NEWS JANUARY 2019 BE PREPARED FOR OUTAGES

COMPANY NEWS JANUARY 2019 BE PREPARED FOR OUTAGES COMPANY NEWS JANUARY 2019 BE PREPARED FOR OUTAGES None of us will forget the monster storm in January 2012 where snow and ice blanketed Western Washington. Plunging temperatures and freezing rain encased

More information

Lake Lure Community Meeting with Duke Energy

Lake Lure Community Meeting with Duke Energy Lake Lure Community Meeting with Duke Energy A community meeting was held on February 11, 2019 at Lake Lure Town Hall to discuss electric service to the town and surrounding areas. Lake Lure staff worked

More information

Alternating Current (AC): Alternating Current is electric current that reverses directions at regular intervals.

Alternating Current (AC): Alternating Current is electric current that reverses directions at regular intervals. Glossary Alternating Current (AC): Alternating Current is electric current that reverses directions at regular intervals. American National Standards Institute (ANSI): American National Standards Institute

More information

OFFSHORE INTEGRATION STUDY. Analysis, benchmark and mitigation of storm and ramping risks from offshore wind power in Belgium 05/02/2018

OFFSHORE INTEGRATION STUDY. Analysis, benchmark and mitigation of storm and ramping risks from offshore wind power in Belgium 05/02/2018 OFFSHORE INTEGRATION STUDY Analysis, benchmark and mitigation of storm and ramping risks from offshore wind power in Belgium 05/02/2018 This study has been developed in close collaboration with 1 TABLE

More information

Multivariate Regression Model Results

Multivariate Regression Model Results Updated: August, 0 Page of Multivariate Regression Model Results 4 5 6 7 8 This exhibit provides the results of the load model forecast discussed in Schedule. Included is the forecast of short term system

More information

PUBLIC SAFETY POWER SHUTOFF POLICIES AND PROCEDURES

PUBLIC SAFETY POWER SHUTOFF POLICIES AND PROCEDURES PACIFIC GAS AND ELECTRIC COMPANY PUBLIC SAFETY POWER SHUTOFF POLICIES AND PROCEDURES SEPTEMBER 2018 1 PACIFIC GAS AND ELECTRIC COMPANY PUBLIC SAFETY POWER SHUTOFF POLICIES AND PROCEDURES SEPTEMBER 2018

More information

Exploring the Reliability of U.S. Electric Utilities

Exploring the Reliability of U.S. Electric Utilities Exploring the Reliability of U.S. Electric Utilities Peter Larsen (Lawrence Berkeley National Laboratory/Stanford University) Kristina Hamachi LaCommare (LBNL) Joe Eto (LBNL) Jim Sweeney (Stanford) International

More information

This case study also provides recommendations for future lightning protection design for existing (brownfield) substation.

This case study also provides recommendations for future lightning protection design for existing (brownfield) substation. A Case Study for Substation Lightning Strike Risk Evaluation Stephen Chuang 111 Dunsmuir Street #400, Vancouver, BC V6B 5W3 604-6644123 Stephen.chuang@amecfw.com Abstract Shielding of substations from

More information

Southern California Edison Wildfire Mitigation & Grid Resiliency

Southern California Edison Wildfire Mitigation & Grid Resiliency Southern California Edison Wildfire Mitigation & Grid Resiliency California State Legislative Conference Committee on Wildfire Preparedness and Response August 7, 2018 CALIFORNIA S WILDFIRE RISK Year-Round

More information

A Model for Assessment of Power System Outages on Nigerian Transmission Network.

A Model for Assessment of Power System Outages on Nigerian Transmission Network. The International Journal Of Engineering And Science (IJES) Volume 4 Issue 4 Pages PP.73-8 215 ISSN (e): 2319 1813 ISSN (p): 2319 185 A Model for Assessment of Power System Outages on Nigerian Transmission

More information

The AIR Severe Thunderstorm Model for the United States

The AIR Severe Thunderstorm Model for the United States The AIR Severe Thunderstorm Model for the United States In 2011, six severe thunderstorms generated insured losses of over USD 1 billion each. Total losses from 24 separate outbreaks that year exceeded

More information

Determination of Fault Location in Shunt Capacitor Bank through Compensated Neutral Current

Determination of Fault Location in Shunt Capacitor Bank through Compensated Neutral Current International Journal of Advances in Scientific Research and Engineering (ijasre) E-ISSN : 2454-8006 DOI: http://dx.doi.org/10.7324/ijasre.2018.32630 Volume 4, Issue 3 March - 2018 Determination of Fault

More information

GENERATOR INTERCONNECTION APPLICATION

GENERATOR INTERCONNECTION APPLICATION GENERATOR INTERCONNECTION APPLICATION FOR BUY-ALL/SELL-ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 20 KW BUT LESS THAN OR EQUAL TO 1 MW Electric Utility Contact Information Great Lakes Energy

More information

More information from:

More information from: Report Information More information from: https://www.wiseguyreports.com/reports/3501422-global-temporary-power-market-size-study-by-power Global Temporary Power Market Size study, by Power Rating (Less

More information

Business Case: UV Facility Backup Generator

Business Case: UV Facility Backup Generator Business Case: UV Facility Backup Generator Eric Brainich December 13, 2010 Background The Portland Water Bureau is currently working on the design for a new Ultra Violet (UV) Treatment Facility and the

More information

Mitigation of Distributed Generation Impact on Protective Devices in a Distribution Network by Superconducting Fault Current Limiter *

Mitigation of Distributed Generation Impact on Protective Devices in a Distribution Network by Superconducting Fault Current Limiter * Energy and Power Engineering, 2013, 5, 258-263 doi:10.4236/epe.2013.54b050 Published Online July 2013 (http://www.scirp.org/journal/epe) Mitigation of Distributed Generation Impact on Protective Devices

More information

SCHOOL EMERGENCY MANAGEMENT PLAN FOR NATURAL DISASTERS

SCHOOL EMERGENCY MANAGEMENT PLAN FOR NATURAL DISASTERS SCHOOL EMERGENCY MANAGEMENT PLAN FOR NATURAL DISASTERS MANAGING EMERGENCIES EFFECTIVELY Keith Thomas, Loss Prevention & Risk Manager LEADERSHIP, ADVOCACY AND SERVICE FOR MANITOBA S PUBLIC SCHOOL BOARDS

More information

About the Author: Abstract:

About the Author: Abstract: Geospatial Technology: A Tool to estimate revenue loss from JJ Clusters in Delhi and implementation of Delhi Govt. Social Welfare Schemes Authors Name: Anil Kumar Rai+, Pooja Yadav+ & Varun Prakash* +Amity

More information

BEFORE THE CORPORATION COMMISSION OF OKLAHOMA

BEFORE THE CORPORATION COMMISSION OF OKLAHOMA BEFORE THE CORPORATION COMMISSION OF OKLAHOMA IN THE MATTER OF THE APPLICATION OF ) OKLAHOMA GAS AND ELECTRIC COMPANY ) FOR AN ORDER OF THE COMMISSION ) CAUSE NO. PUD 20110008 AUTHORIZING APPLICANT TO

More information

By choosing to view this document, you agree to all provisions of the copyright laws protecting it.

By choosing to view this document, you agree to all provisions of the copyright laws protecting it. This material is posted here with permission of the IEEE. Such permission of the IEEE does not in any way imply IEEE endorsement of any of Helsinki University of Technology's products or services. Internal

More information

NSP Electric - Minnesota Annual Report Peak Demand and Annual Electric Consumption Forecast

NSP Electric - Minnesota Annual Report Peak Demand and Annual Electric Consumption Forecast Page 1 of 5 7610.0320 - Forecast Methodology NSP Electric - Minnesota Annual Report Peak Demand and Annual Electric Consumption Forecast OVERALL METHODOLOGICAL FRAMEWORK Xcel Energy prepared its forecast

More information

Using Operating Experience to Prevent or Mitigate Nuclear Events. What Is, Was and Will Be Available

Using Operating Experience to Prevent or Mitigate Nuclear Events. What Is, Was and Will Be Available Using Operating Experience to Prevent or Mitigate Nuclear Events What Is, Was and Will Be Available Introduction Remember, it is by understanding the lessons learned from past events that we can adequately

More information

Research Article RELIABILITY ASSESSMENT OF RADIAL NETWORKS VIA MODIFIED RBD ANALYTICAL TECHNIQUE

Research Article RELIABILITY ASSESSMENT OF RADIAL NETWORKS VIA MODIFIED RBD ANALYTICAL TECHNIQUE Sigma J Eng & Nat Sci 35 (4), 2017, 717-726 Sigma Journal of Engineering and Natural Sciences Sigma Mühendislik ve Fen Bilimleri Dergisi Research Article RELIABILITY ASSESSMENT OF RADIAL NETWORKS VIA MODIFIED

More information

Chapter 2. Planning Criteria. Turaj Amraee. Fall 2012 K.N.Toosi University of Technology

Chapter 2. Planning Criteria. Turaj Amraee. Fall 2012 K.N.Toosi University of Technology Chapter 2 Planning Criteria By Turaj Amraee Fall 2012 K.N.Toosi University of Technology Outline 1- Introduction 2- System Adequacy and Security 3- Planning Purposes 4- Planning Standards 5- Reliability

More information

Twitter s Effectiveness on Blackout Detection during Hurricane Sandy

Twitter s Effectiveness on Blackout Detection during Hurricane Sandy Twitter s Effectiveness on Blackout Detection during Hurricane Sandy KJ Lee, Ju-young Shin & Reza Zadeh December, 03. Introduction Hurricane Sandy developed from the Caribbean stroke near Atlantic City,

More information

AWARD-WINNING SEASONAL SNOW & ICE MAINTENANCE

AWARD-WINNING SEASONAL SNOW & ICE MAINTENANCE AWARD-WINNING SEASONAL SNOW & ICE MAINTENANCE MONSTERPLOW.CA 647-967-PLOW DELIVERING ALL-INCLUSIVE SEASONAL SNOW & ICE COVERAGE SERVICE SPECIFICS UNLIMITED SERVICE OVER 1 CM Guaranteed service for every

More information

Superstorm Sandy What Risk Managers and Underwriters Learned

Superstorm Sandy What Risk Managers and Underwriters Learned Superstorm Sandy What Risk Managers and Underwriters Learned Gary Ladman Vice President, Property Underwriting AEGIS Insurance Services, Inc. Superstorm Sandy Change in the Weather Recent years appears

More information

DRAFT IEEE PES Winter Technical Meeting 2008 San Antonio, Texas Meeting Minutes

DRAFT IEEE PES Winter Technical Meeting 2008 San Antonio, Texas Meeting Minutes DRAFT IEEE PES Winter Technical Meeting 2008 San Antonio, Texas Meeting Minutes Working Group on Distribution Reliability Part 1 Tuesday January 8th, 2008 10:00 to 4:00 pm Chair - Cheri Warren (mailto:

More information

Major Event Response Reporting Guelph Hydro Electric Systems Inc. (Guelph Hydro) May 4, 2018 Wind Storm

Major Event Response Reporting Guelph Hydro Electric Systems Inc. (Guelph Hydro) May 4, 2018 Wind Storm Major Event Response Reporting (Guelph Hydro) May 4, 2018 Wind Storm Page 2 of 16 Contents Introduction... 3 Prior to the Major Event... 4 During the Major Event... 7 After the Major Event... 14 Appendix

More information

R E A D : E S S E N T I A L S C R U M : A P R A C T I C A L G U I D E T O T H E M O S T P O P U L A R A G I L E P R O C E S S. C H.

R E A D : E S S E N T I A L S C R U M : A P R A C T I C A L G U I D E T O T H E M O S T P O P U L A R A G I L E P R O C E S S. C H. R E A D : E S S E N T I A L S C R U M : A P R A C T I C A L G U I D E T O T H E M O S T P O P U L A R A G I L E P R O C E S S. C H. 5 S O F T W A R E E N G I N E E R I N G B Y S O M M E R V I L L E S E

More information

Role of Synchronized Measurements In Operation of Smart Grids

Role of Synchronized Measurements In Operation of Smart Grids Role of Synchronized Measurements In Operation of Smart Grids Ali Abur Electrical and Computer Engineering Department Northeastern University Boston, Massachusetts Boston University CISE Seminar November

More information

Implementation Status & Results Djibouti Djibouti Power Access and Diversification Project (P086379)

Implementation Status & Results Djibouti Djibouti Power Access and Diversification Project (P086379) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Djibouti Djibouti Power Access and Diversification Project (P086379) Operation Name: Djibouti Power

More information

TRANSIENTS POWER SYSTEM. Theory and Applications TERUO OHNO AKIH1RO AMETANI NAOTO NAGAOKA YOSHIHIRO BABA. CRC Press. Taylor & Francis Croup

TRANSIENTS POWER SYSTEM. Theory and Applications TERUO OHNO AKIH1RO AMETANI NAOTO NAGAOKA YOSHIHIRO BABA. CRC Press. Taylor & Francis Croup POWER SYSTEM TRANSIENTS Theory and Applications AKIH1RO AMETANI NAOTO NAGAOKA YOSHIHIRO BABA TERUO OHNO CRC Press Taylor & Francis Croup Boca Raton London New York CRC Press is an imprint of the Taylor

More information

CLIMATE CHANGE ASSESSMENT. A. Climate Change Risk Assessment and Adaptation Measures

CLIMATE CHANGE ASSESSMENT. A. Climate Change Risk Assessment and Adaptation Measures Solar Transmission Sector Project (RRP IND 49214) CLIMATE CHANGE ASSESSMENT I. Transmission System at Bhadla, Rajasthan A. Climate Change Risk Assessment and Adaptation Measures High temperature Risk is

More information

Development of a resistive model for overhead line poles

Development of a resistive model for overhead line poles Journal of Physics: Conference Series Development of a resistive model for overhead line poles To cite this article: Z Kvasznicza and G Elmer 2011 J. Phys.: Conf. Ser. 268 012017 Related content - Nonlinear

More information

Power System Security. S. Chakrabarti

Power System Security. S. Chakrabarti Power System Security S. Chakrabarti Outline Introduction Major components of security assessment On-line security assessment Tools for contingency analysis DC power flow Linear sensitivity factors Line

More information

RESILIENCY OF POWER SYSTEMS: EARTHQUAKES, WIND AND FIRE

RESILIENCY OF POWER SYSTEMS: EARTHQUAKES, WIND AND FIRE Abstract RESILIENCY OF POWER SYSTEMS: EARTHQUAKES, WIND AND FIRE John Eidinger G&E Engineering Systems Inc. Olympic Valley, California, USA Electric Power Systems are the backbone of our communities. High

More information

Outage Coordination and Business Practices

Outage Coordination and Business Practices Outage Coordination and Business Practices 1 2007 Objectives What drove the need for developing a planning/coordination process. Why outage planning/coordination is crucial and important. Determining what

More information

The Pennsylvania State University. The Graduate School. College of Engineering PREDICTIVE ANALYTICS FOR ENHANCING CUSTOMER SERVICE IN ELECTRIC UTILITY

The Pennsylvania State University. The Graduate School. College of Engineering PREDICTIVE ANALYTICS FOR ENHANCING CUSTOMER SERVICE IN ELECTRIC UTILITY The Pennsylvania State University The Graduate School College of Engineering PREDICTIVE ANALYTICS FOR ENHANCING CUSTOMER SERVICE IN ELECTRIC UTILITY A Thesis in Industrial Engineering by Raghav Goyal 2016

More information

Reliability Based Vegetation Management Through Intelligent System Monitoring

Reliability Based Vegetation Management Through Intelligent System Monitoring PSERC Reliability Based Vegetation Management Through Intelligent System Monitoring Final Project Report Power Systems Engineering Research Center A National Science Foundation Industry/University Cooperative

More information

Big Data Paradigm for Risk- Based Predictive Asset and Outage Management

Big Data Paradigm for Risk- Based Predictive Asset and Outage Management Big Data Paradigm for Risk- Based Predictive Asset and Outage Management M. Kezunovic Life Fellow, IEEE Regents Professor Director, Smart Grid Center Texas A&M University Outline Problems to Solve and

More information

Dynamic Voltage Stability Enhancement of a Microgrid with Static and Dynamic Loads Using Microgrid Voltage Stabilizer

Dynamic Voltage Stability Enhancement of a Microgrid with Static and Dynamic Loads Using Microgrid Voltage Stabilizer Dynamic Voltage Stability Enhancement of a Microgrid with Static and Dynamic Loads Using Microgrid Voltage Stabilizer Kenan Hatipoglu 1, Ismail Fidan 2, Ghadir Radman 3 1 Electrical and Computer Engineering

More information

Periodic Inspection and Testing of Electrical Installations Sample Test ( ) Version 1.3 July 2018

Periodic Inspection and Testing of Electrical Installations Sample Test ( ) Version 1.3 July 2018 Periodic Inspection and Testing of Electrical Installations Sample Test (2391-051) Version 1.3 July 2018 Sample Questions Version and date Change detail Section 1.3 July 2018 Modified questions/answers

More information

By David & Debbie Hibbert

By David & Debbie Hibbert By David & Debbie Hibbert Electricity Distribution G AS- F I R E D P O W E R S T A T I O N Electricity Distribution - David & Debbie Hibbert - Electricity is an invisible energy resulting from the existence

More information