1 ANNEXURE I Site Location map of M/s. quarry lease A-1

2 Quarry Lease boundary map of M/s. A-2

3 a. Introduction M/s. proposes to conduct semi mechanized open cast method quarrying for Colour granite extraction in an area of 6.53 ha in Survey No. 31, Veerabadrapeta Village, Chidikada Mandal, Visakhapatnam District, Andhra Pradesh. The Director of Mines and Geology, Hyderabad vide Notice No /R1.2/2012 dated decided in principle to grant quarry lease for a period of 20 years subject to submission of Approved Mining plan. Mining plan approved by the Deputy Director of Mines and Geology, Government of Andhra Pradesh vide Letter no. 2851/MP-VSP/2015 dated It is proposes to conduct semi mechanized open cast method quarrying for Colour granite production of 8500 m 3 /annum from the lease area. Capital proposed for the quarrying is Rs. 57 Lakhs. b. Quarry Lease Area Location M/s. proposes to conduct semi mechanized open cast quarrying for Colour granite production of 8500 m 3 /Annum. The quarry lease area of 6.53 ha is located at Survey No. 31, Veerabadrapeta Village, Chidikada Mandal, Visakhapatnam District, Andhra Pradesh. The quarry lease area falls in the Survey of India topo sheet no. 65 K/13 of Latitude 17 56'57.20"N and Longitude 82 50'35.32"E with an elevation of 123 m. The nearest Village Gadabavidi is located at a distance of 2.7 Km from the QL area in E direction. Nearest habitation is Goppuru located at a distance of 1.0 km in SE direction. Nearest Railway station is Anakapalli at a distance of 33 km in SE direction. Nearest Town is Anakapalli located at a distance of 31.7 km in SE direction. Kumdampeta to Konam road passing at a distance of 2.1 Km from the QL area in East direction. Virabadhrapuram to Goppuru road passing at a distance of 1.0 Km from the QL area in SE direction. Madugula Reserved forest is at a distance of 50 m in N direction. Sankaram RF is at a distance of 5.5 km in NW direction. Olab RF is at a distance of 6.8km in NE direction. Valabu RF is at a distance of 3.0 km in NE direction. Chidikada RF is at a distance of 5.1 km in E direction. Seasonal nala Bodderu is flowing at a distance of 1.3 km in SE direction. There is no State/national boundary, national park, wildlife/bird sanctuary and critically polluted areas within 10km radius from the quarry lease area. Details of the quarry lease area are presented in table A-1. Latitude 17 56'53.02"N 17 56'53.77"N 17 56'56.22"N 17 56'57.59"N Longitude 82 50'30.16"E 82 50'30.62"E 82 50'27.67"E 82 50'30.19"E A-3

4 17 56'59.53"N 17 57'05.76"N 17 56'52.69"N 17 56'50.96"N 82 50'33.90"E 82 50'40.78"E 82 50'36.64"E 82 50'33.72"E Table A-1 Details of the Lease area State & District Mandal Village Sy. No./ Area in Ownership of Plot No. hectares occupancy Andhra Pradesh & Visakhapatnam Chidikada Veerabadrapeta Govt Land c. Exploration 1) Already carried out: In this area the applicant has undertaken following prospecting work: 1. Preliminary study of the visual examination of granite texture, design and pattern. 2. In this area the colour granite are exposed to surface with high elevation. The rock is stretching to a length of 300 m and an average width of 210 m only. The adjacent Quarry Lease holders are excavating the blocks and are marketing. The area is a proven area and the subject area is an extrapolated of the same hill ranges. However, the applicant has to carry out detailed prospecting operations to study the economic viability of the dimensional blocks. 3. The applicant, to study the feasibility of the applied area, has collected 2 no s of sample and examined for their structural details, fabric, texture and mineral grains distribution and polish surface. The percentage of recovery is arrived to be about 25%. However the percentage of recovery is anticipated to be increased with respect to the depth and the technology to be used. 2) Future Programme of exploration: Since, the deposit is exposed of big boulders and the preliminary collections of samples and study of the rock proved to be of marketable grade, and also the presence of existing quarry adjacent to the subject area. No further exploration of the deposit is envisaged. The applicant wishes to carry out excavations and conduct regular quarrying operations in systematic manner. d. Geological Reserves The reserves are computed basing on the available sub-surface lithology of the subject area and also excavations made in the existing quarries adjacent to the subject area by other lease holders. It reveals that the sheet rock is encountered from right from surface and it extended further A-4

5 depths. However, thickness available upto 110 m level is taken for computation of proved deposit and 10m each below the proved as probable and possible deposit. The proved deposit is considered as "Reserves" and the probable & possible deposit is considered as "Resources". The reserves available in the lease are complied as stated below table A-2 Category Section Influence Distance in m (A) Table A-2 Reserves Estimation Section Volume in Area in m² m³ (AxB) (B) 25% in m³ (AxB) 0.25 Rock 75% in m³ (AxB)0.75 Proved A-A B-B C-C Sub - Total Probable A-A B-B C-C Sub - Total Possible A-A B-B C-C Sub - Total Probable & Possible Grand total Total Reserves of Colour 25 % recovery = m 3 The reserves are blocked by the 7.5 barrier zone (5462m 2 x 36m (average thickness) x 25% recovery factor) From pit slopes, the reserves blocked are 2% of the reserves blocked in buffer zone = m 3 = 983 m 3 Total Non-mineable reserves (49158m m 3 ) = m 3 Mineable Reserves Total reserves assessed - Non-mineable reserves ( m m 3 ) = m 3 A-5

6 e. Mineable reserves and life of the mine Initially, the total quantity of mineable reserves is considered as (economic) marketable reserves. In this way a total mineable reserves of m 3 are available in this QL area. The average production is proposed to obtain 8500 m 3 per year. At this rate of production, the expected life of the mine is calculated as below. Life of the quarry: Mineable reserves/annual production = /8500 = years or say 51 years. f. Quarrying Method The mining operations are carried out by open cast semi mechanization method by developing multiple benches of 6 m height. The removal of side burden consisting of soil, weathered rocks and fractured rocks is the general practice of the opening of the quarry. The side burden of soil will be removed with the help of excavators. The weathered material further loosened using blasting by utilizing gun powder as explosive. The loosed soil and weathered granite will be loaded in tippers and lifted to dump yard. Separation of Large Primary Blocks from Mother Rock by Pre-Splitting The primary cuts i.e. the lateral and horizontal cuts by diamond wire saw cuts through slaughter holes (A 50 m wire saw run gets around 600 sqm. Cut) and if situation permits by use of detonating cords a close spaced blast is performed (To leverage natural Joint). 10 m in length and 8 m in width and 6 m height Sizes are produced. The wire for Granite is made of the steel wire, sintered beds with plastics injected on the steel wire and between diamond beds in order to safeguard the steel wire from the abrasive components of granite (i.e Quartz, Feldspar, etc). The stationary diamond wire machines were born for three main purposes: Squaring and dressing of irregularly shaped blocks, preparing them for final processing in slabs and tiles. Making thickness of stone of certain width in order to utilize the best gangsaws and blocks cutter having maximum productions and profit from the processing machines. Perform automatic cuts of block into slabs of different thickness. The block can so be programmed to have a certain number of slabs each of prescribed thickness. A-6

7 Sub Division of Large Primary Block Into Secondary Block i. Once the primary blocks are dislodged from sheet rock depending up on the dislodged material secondary blocks are cut, fractures, block lines and penetrative cracks are carefully trimmed and removed by this way. ii. The commercial blocks will be trimmed so as that the sites form right angles to each other iii. The size of blocks could be formed from the ROM of this property will be in the following dimensional ranges. Gang saw sizes Cutter sizes Length : 190 to 380 cm 90 to 180 cm Width : 140 to 200 cm 60 to 90 cm Height : 120 to 170 cm 40 to 70 cm Production of commercial blocks To give a regular shape, the removed blocks are dressed with cutting and polishing face, and the other direction perpendicular to it. For this purpose also Jack Hammer drills and feather wedges are widely used. Below sizes were produced in the ratio of 1:3 and also depending upon the recovery. g. List of Machinery S. No. Type of Machinery Unit 1 Excavator 370 & Tippers 2 3 Jack Hammer Drills 6 4 Air Compressors 2 5 Water Pump 1 6 Tam rock 1 7 Wire-saw cutting machines 2 8 Slaughter 1 h. Year wise Development and production for five years 1 st Year: The First year quarrying operations will be commenced from the northern end of the Q.L applied area by cutting a bench face of 5-6 m height and advancing towards southern side from 132m R.L in the Q. L and reducing the floor level to 124 R.L. The floor level shall be kept intact and as when the mining operation advances towards southern side the bench height decreases. It is A-7

8 proposed to excavate an area of 5200 m 2 with an average thickness of 4 m. With 25% recovery a volume of 5200 m 3 saleable granite and waste of m 3 of rock mass will be removed. 2 nd year: The Second year quarrying operations will be continued from the northern end by continuing with floor level of 126m R.L and advances further southern and E-W side keeping the floor R.L 126 m intact throughout. It is proposed to cover an area of 6182 m 2 with an average thickness of 5.5 m. A volume of 8500 m 3 of salable granite is produced and a volume of m 3 of rock mass has to be handled as waste at 25% recovery. 3 rd year: The third year quarrying operations will be commenced from the northern side of the Q.L area by opening multiple benches of 6m height and shall be continued going further depths towards south of the Q.L area. During the year, the quarry operations shall be between 124m R.L. to 112m R.L with two benches simultaneously advancing, keeping the floor level as 112m. An area of 2834 m 2 shall be destructed to achieve a volume of 8500 m 3 of saleable granite with an average thickness of 12 m in multiple benches. A volume of m 3 of waste rock mass will be generated and dumped at the waste dump area. 4 th year: The fourth year quarrying operations shall be continued from the northern side of previous year working and two benches of 6m height each shall be simultaneously advanced towards south of the Q.L area. During the year, the quarry operations shall be between 124 m R.L. to 112m R.L with two benches simultaneously advancing, keeping the floor level as 112 m. An area of 2834 m 2 shall be destructed to achieve a volume of 8500 m 3 of saleable granite with an average thickness of 12 m in multiple benches. A volume of m 3 of waste rock mass will be generated and dumped at the waste dump area. 5 th year: The fifth year quarrying operations shall be continued further from the northern side of previous year working and two benches of 6m height each shall be simultaneously advanced towards south of the Q.L area. During the year, the quarry operations shall be between 124m R.L. to 112m R.L with two benches simultaneously advancing, keeping the floor level as 112 m. An area of 2834 m 2 shall be destructed to achieve a volume of 8500 m 3 of saleable granite with an average thickness of 12m in multiple benches. A volume of m 3 of waste rock mass will be generated and dumped at the waste dump area. From the five year quarrying operations a volume of m 3 rock mass will be excavated out of which m 3 dimensional granite will be recovered. A total waste of m 3 has to be A-8

9 handled including the additional waste in the form of overburden soil. Year wise production and waste generation details are presented in table A-3 S. No Year Area in m 2 Table A-3 Year wise Granite Production and Waste generation Average Volume Volume of granite thickness in m 3 25 % in m in m 3 Volume of intercalated 75 % in m 3 1 I II III IV V Total Average i. Employment Table A-4 Employment Potential S. No Description Quantity 1 Manager/ Supervisor 1 2 Mines Supervisor 1 3 Skilled Workers 10 4 Unskilled Workers 10 5 Machine Operators 2 6 Watch Man 1 Total 25 A-9

10 ANNEXURE - II Drilling and Blasting Drilling and blasting plays vital role in determining the size and shape of rough blocks. Drilling Pattern is important in developing a working face and also preparing the rough blocks suitable for their use in appropriate processing units. There are no important places in and around the area, blasting will be carried with precautionary measures. 1. Drilling Parameters i. Drill holes diameter: 74/Pmm ii. Depth and inclination of the blast holes: 3 meter in case of separation primary blocks depending on the block size. Then the drill-hole will be vertical. iii. Burden and Spacing: 1.5m X 3 m iv. Stemming and charging of the blast hole: The blast hole will be charged with 100 grams of explosives and filled with clan pills subsequently; the shot hole will be stemmed using brass stemming rods. v. Explosive type: (1) Slurry based explosives or Gun Powder. Broad Blasting parameter Drill-Hole patterns for primary and secondary smooth blasting. Uniform single line equidistant holes (line drilling) will be deployed for separation of blocks from mother rock. In the case of sheet rock the primary drilling will be in the form of equidistant vertical holes to take out blocks of Gang Saw. A-10

11 ANNEXURE - III Water Requirement Water requirement for the project is mainly for Domestic source, maintaining the green belt and also for sprinkling on the haulage roads to mitigate dust emissions. The water shall be drawn from nearby villages. The water requirement of the project is presented in Table A-5. Table A-5 Water Requirement S. No Water Usage Quantity KLD 1 Wet drilling operation (On production 100 Ltr/1 m 3 ) Water sprinkling on haul 1Ltr/Sq.Mt (500 m 2 )+1/4 th for waste dump Ltr/Head (25 No s) Green 0.2 KL for 0.06 ha 2 times a day 0.4 Total 5.8 Site Services It is proposed to provide the site services like mine office and other statutory constructions like rest shelter, first aid, work shed and drinking water as required at the quarry lease area. Drinking water will be supplied to the workers from the bore well opened in the adjacent agricultural field or from nearby village. A-11

12 Solid Wastes Generation and Management Plan ANNEXURE IV During five years operations a total rock mass m 3 will be excavated and m 3 of granite blocks will be recoverable from this rock mass and remaining material of about m 3 will go as waste. Solid waste generated year wise for first five years plan as below Table A-6. Table A-6 Solid waste generated year wise S. No. Year Total waste generated m 3 1 I Year II Year III Year IV Year V Year Total waste generated for five years Dump Area During plan period about m 3 of granite waste will be produced this will be dumped over an area of 7500 m 2 in Northern direction within lease area. By the end of lease period total waste produced will be dumped in an area of ha to a height of 30 m. Step dumping will be resorted. This material can be utilized to fill the pits after quarry operations are over. When the dumps reach their optimum height suitable greenery will be grown on these dumps to stabilize them. A-12

PRE FEASIBILITY REPORT. Quartz and Feldspar Sy No 119 & 126/3, Kambampadu Village A. Konduru Mandal, Krishna District, Andhra Pradesh

PRE FEASIBILITY REPORT. Quartz and Feldspar Sy No 119 & 126/3, Kambampadu Village A. Konduru Mandal, Krishna District, Andhra Pradesh PRE FEASIBILITY REPORT Of Quartz and Feldspar Sy No 119 & 126/3, Kambampadu Village A. Konduru Mandal, Krishna District, Andhra Pradesh Area of Mining Lease 2.720 Ha For 1, 09,055.08 MT/Annum OF Quartz

More information

Kurnool vide Proceedings No. 712/Q1/2012 dated Ulindakonda Village, Kallur Mandal, Kurnool District,

Kurnool vide Proceedings No. 712/Q1/2012 dated Ulindakonda Village, Kallur Mandal, Kurnool District, 1.0 EXECUTIVE SUMMARY 1.1 Introduction The proposed mining area of 1.157Ha. in survey No. 291 of Ulindakonda Village, Kallur Mandal, Kurnool District has been leased to M/s.Sri Lakshmi Sreenivasa Stone

More information

FOR Sand Stone Quarry Village : Chhirraleva Tehsil : Basna District : Mahasamund

FOR Sand Stone Quarry Village : Chhirraleva Tehsil : Basna District : Mahasamund Project Report FOR Sand Stone Quarry at Village : Chhirraleva Tehsil : Basna District : Mahasamund Contents 1. About the Firm... 1 2. Location of the Project... 1 3. Environmental Setting of Project...

More information

KRISHNA MERCHANTS PVT. LTD.

KRISHNA MERCHANTS PVT. LTD. (Color Granite Quarry lease area 15.00 Ha. Sy. No.1) ADDUKONDA VILLAGE TEKKALI MANDAL SRIKAKULAM DISTRICT ANDHRA PRADESH ENVIRONMENTAL MANAGEMENT PLAN PREPARED BY 6-3-652 Flat # 7-3 Dhruvatara Apartments

More information

SRI E.DEVARAJULU, S/O.E.Ramachandra Naidu, D.No: 26-39, Palamaner Road,Kajur, Chittoor (District), Andhara Pradesh State. Contact No:

SRI E.DEVARAJULU, S/O.E.Ramachandra Naidu, D.No: 26-39, Palamaner Road,Kajur, Chittoor (District), Andhara Pradesh State. Contact No: MINING SCHEME FOR BLACK GRANITE OVER AN EXTENT OF 1.800Hects. IN Sy.No. 1406 OF VAVILTHOTA(V), PUTHALAPATTU (M), CHITTOOR (Dist) A.P (Under Rule 18(2) of GCDR 1999) BLOCK PERIOD 2015-16 TO 2021-22 BALANCE

More information

TABLE OF CONTENTS. 1.0 Introduction. 2.0 Geology, Exploration and Reserves. 3.0 Mining. 4.0 Blasting. 5.0 Mine Drainage. 6.

TABLE OF CONTENTS. 1.0 Introduction. 2.0 Geology, Exploration and Reserves. 3.0 Mining. 4.0 Blasting. 5.0 Mine Drainage. 6. TABLE OF CONTENTS 1.0 Introduction 2.0 Geology, Exploration and Reserves 3.0 Mining 4.0 Blasting 5.0 Mine Drainage 6.0 Site Services 1.0 INTRODUCTION Pankaj Chandrakar a resident oftemri, P.O. Deopuri

More information

EMP. In respect of. Cluster of Two Mines (Cluster area Ha)

EMP. In respect of. Cluster of Two Mines (Cluster area Ha) M/s. NSC Consortium, Road Metal Mine 12.146 Ha. EMP In respect of Cluster of Two Mines (Cluster area 22.146 Ha) AT Sy. No. 734/P, Yadavalli Village, Dornala Mandal, Prakasam district, Andhra Pradesh Cluster

More information

MCDR INSPECTION General. Date of Inspection Name of the Mine Bhatbhera Limestone Mine 2 Total Lease Area (Ha)

MCDR INSPECTION General. Date of Inspection Name of the Mine Bhatbhera Limestone Mine 2 Total Lease Area (Ha) ::1:: MCDR INSPECTION General SN Particulars Details Date of Inspection 23.8.2015 1 Name of the Mine Bhatbhera Limestone Mine 2 Total Lease Area (Ha) 4.808 Hect (Govt. Revenue Land), Non-forest land with

More information

MCDR INSPECTION REPORT. S. N. Particulars Details 1 Name of the Mine, Inspecting officer with Designation, Date of Inspection

MCDR INSPECTION REPORT. S. N. Particulars Details 1 Name of the Mine, Inspecting officer with Designation, Date of Inspection MCDR INSPECTION REPORT General S. N. Particulars Details 1 Name of the Mine, Inspecting officer with Designation, Date of Inspection Bharuadih Limestone Mine,Rajesh Kumar Das,Sr.ACOM,18.08.2017 2 Total

More information

MCDR INSPECTION REPORT

MCDR INSPECTION REPORT MCDR INSPECTION REPORT General S. N. Particulars Details 1 Name of the Mine Matia Limestone Mine 2 Total Lease Area (Ha) with breakup of Non-forest and forest 12.137 Ha. land 3 Mine code 38CHG14086 4 IBM

More information

SRI E.DEVARAJULU, S/O.E.Ramachandra Naidu, D.No: 26-39, Palamaner Road,Kajur, Chittoor (District), Andhara Pradesh State. Contact No:

SRI E.DEVARAJULU, S/O.E.Ramachandra Naidu, D.No: 26-39, Palamaner Road,Kajur, Chittoor (District), Andhara Pradesh State. Contact No: MINING SCHEME FOR BLACK GRANITE OVER AN EXTENT OF 1.500Hects. IN Sy.No. 1406 OF VAVILTHOTA(V), PUTHALAPATTU (M), CHITTOOR (Dist) A.P (Under Rule 18(2) of GCDR 1999) 1st SCHEME PERIOD 2017-18 TO 2021-22

More information

FORM -1 MINING PLAN & PRE-FEASIBILITY REPORT FOR QUARRYING OF BLACK GRANITE

FORM -1 MINING PLAN & PRE-FEASIBILITY REPORT FOR QUARRYING OF BLACK GRANITE FORM -1 MINING PLAN & PRE-FEASIBILITY REPORT TO OBTAIN ENVIRONMENTAL CLEARANCE FOR QUARRYING OF BLACK GRANITE (Extent 2.3.0Ha)-B2 Project IN S.F.Nos 248/2 (P), 248/1A (P), 248/1B(P) and 248/1C (P) Village

More information

M/s BENITA INDUSTRIES LIMITED

M/s BENITA INDUSTRIES LIMITED M/s BENITA INDUSTRIES LIMITED (Colour Granite Quarry 19.150 Ha.) Sy. No: 82-1 of Kambadur (V), Kambadur (M), Ananthapur District, Andhra Pradesh State. ENVIRONMENTAL MANAGEMENT PLAN 0 P a g e INDEX S.

More information

INDEX. Environmental Management Plan

INDEX. Environmental Management Plan Environmental Management Plan M/s. N.V. Exports [Quarry Lease Area - 0.615 Ha.( 1.52 Acres)] Sy. No. : 11/1 Village : R.L. Puram Mandal : Chimakurthy District : Prakasam State : Andhra Pradesh ENVIRONMENTAL

More information

Smt. M. Hari Chandana

Smt. M. Hari Chandana Smt. M. Hari Chandana Quarry lease area 11.201 Ha. (27.68 Acres) in Sy. No. 22, Kudavanandapur Village, Raikode Mandal, Sangareddy District, Telangana CLUSTER ENVIRONMENTAL MANAGEMENT PLAN PREPARED BY

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN ENVIRONMENTAL MANAGEMENT PLAN Of M/s. B.K.R. GRANITES 4.790 HA. BLACK GRANITE MINING COMP NO. 205 &215 RAGIMANUPENTA & PARADARAMI R.F., YADAMARRI (M) CHITTOOR (DT), ANDHRA PRADESH. Submitted by SV ENVIRO

More information

FOR QUARRYING OF KAGANAM ROUGH STONE AND GRAVEL QUARRY

FOR QUARRYING OF KAGANAM ROUGH STONE AND GRAVEL QUARRY PROPOSAL TO OBTAIN ENVIRONMENTAL CLEARANCE FROM District Level Environment Impact Assessment Authority (DEIAA), Tiruvannamalai District, Tamilnadu FOR QUARRYING OF KAGANAM ROUGH STONE AND GRAVEL QUARRY

More information

FORM -1 MINING PLAN & PRE-FEASIBILITY REPORT

FORM -1 MINING PLAN & PRE-FEASIBILITY REPORT FORM -1 MINING PLAN & PRE-FEASIBILITY REPORT TO OBTAIN ENVIRONMENTAL CLEARANCE FOR QUARRYING OF ROUGH STONE (Extent 1.91.5Ha)-B2 Project IN S.F.No 1257/1 Village Nagamangalam Taluk Denkanikottai District

More information

MCDR INSPECTION REPORT

MCDR INSPECTION REPORT MCDR INSPECTION REPORT 1.0 GENERAL SN Particulars Details 1 Name of the inspecting officer J.S. Hada, AMG 2 Date of Inspection 9.9.2017 3 Accompanying mine official Lessee and Mining Engineer Shri K.L.

More information

Fragmentation Management for the Downstream Value Chain. Scott G. Giltner

Fragmentation Management for the Downstream Value Chain. Scott G. Giltner Fragmentation Management for the Downstream Value Chain Scott G. Giltner Topics to be Covered The purpose of drilling & blasting in producing crushed stone Relative cost of drilling & blasting vs. other

More information

MCDR INSPECTION REPORT

MCDR INSPECTION REPORT MCDR INSPECTION REPORT General S. N. Particulars Details 1 Name of the Mine Matia Limestone Mine 2 Total Lease Area (Ha) with breakup of Non-forest and forest 8.144 ha.,non forest land land 3 Mine code

More information

Managing Muckpile Fragmentation. Scott G. Giltner

Managing Muckpile Fragmentation. Scott G. Giltner Managing Muckpile Fragmentation Scott G. Giltner Topics to be Covered The purpose of drilling & blasting in producing crushed stone Relative cost of drilling & blasting vs other quarrying activities Cost/production

More information

APPLICANT: M/s. Rock Sand & Minerals Pvt Ltd PRE-FEASIBILITY REPORT

APPLICANT: M/s. Rock Sand & Minerals Pvt Ltd PRE-FEASIBILITY REPORT PRE- FEASIBILITY REPORT 1.1 Introduction EXECUTIVE SUMMARY The proposed mining lease of 19.80ha in survey no. 345 was granted to M/s. Rock Sand Minerals Pvt Ltd, for a period of 15 years by Asst. Director

More information

JAI MAA SHARDA STONE CRUSHING

JAI MAA SHARDA STONE CRUSHING JAI MAA SHARDA STONE CRUSHING Prop. Hukum Singh (M. No. 9425585252) Near-Pahunadukan Kedarpur Ambikapur, (C.G.) To, The Member Secretary, SLEIAA(State Level Environment Impact Assessment Authority), Ministry

More information

lit)'*'" m ( Reft- Representation received from M/s. Kasturi Granites and Exports, Proprietor Smt. C. Kasturibai Dated:

lit)'*' m ( Reft- Representation received from M/s. Kasturi Granites and Exports, Proprietor Smt. C. Kasturibai Dated: Lr.No.233 /QlzOrL GOVERNMENT OF ANDHRA PRADESH DEPARTMENT OF MINES & GEOLOGY D Dated: 7.03.2018 From Sri G. Shivaji, M.Sc., Tech.,, Asst. Director of Mines and Geology (FACJ, Srikakulam. To The SEIAA Govt.

More information

Of Sri. Mohammad Akram. At Karigala Village, H.D. KoteTaluk, Mysore District, Karnataka Latitude & Longitude Piller Latitude Longitude Coordinates

Of Sri. Mohammad Akram. At Karigala Village, H.D. KoteTaluk, Mysore District, Karnataka Latitude & Longitude Piller Latitude Longitude Coordinates 1.0 EXECUTIVE SUMMARY 1.1 Introduction The proposed mining lease area applied for quarrying of Steatite Stone (soap stone) by Sri. Mohammad Akramis situated in survey no. No. 402of 1-30 Acres of Karigala

More information

Over an extent of 1.36 Hectares in Sy. No. 60 / 33 Vennaram (V), Dornakal (M), Mahabubabad District, Telangana State

Over an extent of 1.36 Hectares in Sy. No. 60 / 33 Vennaram (V), Dornakal (M), Mahabubabad District, Telangana State SECOND SCHEME OF QUARRYING FOR BLACK GRANITE Extent : 1.36 Hectares 2019 SECOND SCHEME OF QUARRYING FOR BLACK GRANITE (Under Rule 7 B of TSMMC Rules, 1966) INCLUDING PROGRESSIVE QUARRY CLOSURE PLAN (Under

More information

C. SHASHI KUMAR. Mine lease area Ha. in Sy. No. 120/1, Mailaram Village, Balmoor Mandal, Nagarkurnool District, Telangana

C. SHASHI KUMAR. Mine lease area Ha. in Sy. No. 120/1, Mailaram Village, Balmoor Mandal, Nagarkurnool District, Telangana C. SHASHI KUMAR Mine lease area 24.28 Ha. in Sy. No. 120/1, Mailaram Village, Balmoor Mandal, Nagarkurnool District, Telangana ENVIRONMENTAL MANAGEMENT PLAN PREPARED BY ISO 9001: 2008 Certified Accredited

More information

INDIAN BUREAU OF MINES MINERALS DEVELOPMEMT AND REGULATION DIVISION MCDR INSPECTION REPORT. Chennai regional office

INDIAN BUREAU OF MINES MINERALS DEVELOPMEMT AND REGULATION DIVISION MCDR INSPECTION REPORT. Chennai regional office 1. Mine file No : (i) Name of the Inspecting : Officer and ID No. INDIAN BUREAU OF MINES MINERALS DEVELOPMEMT AND REGULATION DIVISION TN/TCR/LST-1, MDS (ii) Designation : (iii) Accompaning mine : Official

More information

INDIAN BUREAU OF MINES MINERALS DEVELOPMEMT AND REGULATION DIVISION MCDR inspection REPORT Jabalpur regional office

INDIAN BUREAU OF MINES MINERALS DEVELOPMEMT AND REGULATION DIVISION MCDR inspection REPORT Jabalpur regional office INDIAN BUREAU OF MINES MINERALS DEVELOPMEMT AND REGULATION DIVISION MCDR inspection REPORT Jabalpur regional office Mine file No : MP/KTN/LST-96 (i) Name of the Inspecting : Officer and ID No. (ii) Designation

More information

PRE-FEASIBILITY REPORT VASAI LIMESTONE MINE (APPLICANT: SHRI KHERAJBHA KARUBHA KER)

PRE-FEASIBILITY REPORT VASAI LIMESTONE MINE (APPLICANT: SHRI KHERAJBHA KARUBHA KER) PRE-FEASIBILITY REPORT OF VASAI LIMESTONE MINE (APPLICANT: SHRI KHERAJBHA KARUBHA KER) 1. EXECUTIVE SUMMARY: The existing Mining lease for mineral Limestone over 4.9000 Hectares for a period of thirty

More information

Lessee. Sri.B.Srinivasa Rao S/o Seetha Ramaiah D.No:6-122/1 Guntupalli Village Ibrahimpatnam Mandal Krishna Dist.

Lessee. Sri.B.Srinivasa Rao S/o Seetha Ramaiah D.No:6-122/1 Guntupalli Village Ibrahimpatnam Mandal Krishna Dist. MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN FOR ROAD METAL (Under Rule 7 A of APMMC Rules 1966 & Rule 23 (B) of MCDR 1988) (FOR THE PLAN PERIOD 2017 18 TO 2021 22) Over an extent of 2.024 Hectares

More information

QUARRY PLAN FOR LIMESTONE SLABS

QUARRY PLAN FOR LIMESTONE SLABS QUARRY PLAN FOR LIMESTONE SLABS (Under Rule 7 B of TSMMC Rules, 1966) INCLUDING PROGRESSIVE QUARRY CLOSURE PLAN (Under Rule 7 B (viii) of TSMMC Rules, 1966) (FOR THE PLAN PERIOD 2016 17 TO 2020 21) (FOR

More information

GEOLOGIC ASSESSMENT / QUARRY PLAN REVIEW BLACK GOLD GRANITE QUARRY DEVELOPMENT

GEOLOGIC ASSESSMENT / QUARRY PLAN REVIEW BLACK GOLD GRANITE QUARRY DEVELOPMENT GEOLOGIC ASSESSMENT / QUARRY PLAN REVIEW BLACK GOLD GRANITE QUARRY DEVELOPMENT GARIBALDI RESOURCES CORP. BLACK GOLD GRANITE CLAIMS GREENWOOD MINING DIVISION GRAND FORKS, B.C., CANADA NTS 82 E/7 E UTM (Zone

More information

Blast design parameters and their impact on rock fragmentation

Blast design parameters and their impact on rock fragmentation Blast design parameters and their impact on rock fragmentation By Pradeep K Singh, Chief Scientist & Professor, Academy of Scientific & Innovative Research CSIR Central Institute of Mining and Fuel Research,

More information

1.1 INTRODUCTION. EMP Report For 3.30 Ha. of Feldspar &, Quartz Mine located in Budharam village, Gopalpet Mandal, Wanaparthy District, T.S.

1.1 INTRODUCTION. EMP Report For 3.30 Ha. of Feldspar &, Quartz Mine located in Budharam village, Gopalpet Mandal, Wanaparthy District, T.S. 1. INTRODUCTION 1.1 INTRODUCTION M/s.SRI SAI MINES & MINERALS was granted Mining lease for Quartz & Feldspar in Survey Number 3.30 over an extent of 3.30 Hect. In sy No. 326 & 330 Budharam village, Gopalpet

More information

DIMENSIONAL STONE QUARRYING AND RECOVERY PERCENTAGE

DIMENSIONAL STONE QUARRYING AND RECOVERY PERCENTAGE DIMENSIONAL STONE QUARRYING AND RECOVERY PERCENTAGE By A. Rajan Babu Principal Scientist, Centre for Testing Services & HOD, Dimensional Stone Technology, National Institute of Rock Mechanics, KGF 563

More information

The mining plan for the above quarry lease was approved on Copy of the approved mining plan is enclosed as Annexure III.

The mining plan for the above quarry lease was approved on Copy of the approved mining plan is enclosed as Annexure III. 1.0 EXECUTIVE SUMMARY M/s. Bhargavi Granites was granted a prospective license for Color Granite over an extent of 1.820 Ha in Survey No: 319 of Byripuram Village, Kanchili Mandal, for a period of 2 years

More information

ENVIRONMENTAL MANAGEMENT (CLUSTER)

ENVIRONMENTAL MANAGEMENT (CLUSTER) /+ ENVIRONMENTAL MANAGEMENT (CLUSTER) PLAN Of M/s. APARNA ENTERPRISES LIMITED MINING OF QUARTZ & FELDSPAR OVER AN EXTENT: 2.720 HA Mine Address: Sy. No.119 & 126/3 Khambhampadu (V), A.konduru (M) Krishna

More information

MINING PLAN FORMAT (A & B CATEGORY MINES) As per MCDR,1988

MINING PLAN FORMAT (A & B CATEGORY MINES) As per MCDR,1988 MINING PLAN FORMAT (A & B CATEGORY MINES) As per MCDR,988 INTRODUCTORY NOTES. 'A' category mines : all mines excluding 'B' Category mines. B' category mines : all 'B' Category mines excluding very small

More information

Early Exploration Plan Activity Information

Early Exploration Plan Activity Information Early Exploration Plan Activity Information Activities That Require an Early Exploration Plan: Line cutting that is a width of 1.5 metres or less; Geophysical surveys on the ground requiring the use of

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN ENVIRONMENTAL MANAGEMENT PLAN Of GRAVEL & BUILDING STONE QUARRY For Sri Prathipati. Ram Prasad 1.235 HA GRAVEL & BUILDING STONE QUARRY SY. NO. 860, Vedurupavuluru (V), Gannavaram(M), Krishna(DT), ANDHRA

More information

SITE INVESTIGATION 1

SITE INVESTIGATION 1 SITE INVESTIGATION 1 Definition The process of determining the layers of natural soil deposits that will underlie a proposed structure and their physical properties is generally referred to as site investigation.

More information

TABLE 1.1: Salient features of the project Black Granite Mine of M/s. Shashi Granites

TABLE 1.1: Salient features of the project Black Granite Mine of M/s. Shashi Granites 1. EXECUTIVE SUMMARY 1.1 Introduction M/s. Shashi Granites, is having quarry lease area for Black Granite mine over an extent of 1.0 Hectares at Survey No. 249/4, Chinthapally(V), Kuravi(M), Mahabubabad

More information

PRE FEASIBILITY REPORT OF QUARTZ & FELDSPAR MINING PROJECT (ML No- 80/03) FOR TERMS OF REFERENCE

PRE FEASIBILITY REPORT OF QUARTZ & FELDSPAR MINING PROJECT (ML No- 80/03) FOR TERMS OF REFERENCE PRE FEASIBILITY REPORT OF QUARTZ & FELDSPAR MINING PROJECT (ML No- 80/03) FOR TERMS OF REFERENCE Village Ashapura Tehsil Nasirabad District Ajmer State Rajasthan Capacity 35945 TPA ROM (Max) Lease Area

More information

WHAT IS MINERAL EXPLORATION?

WHAT IS MINERAL EXPLORATION? INDABA PRESENTATION CAPE TOWN FEBRUARY 2017 AIM:SAV WHAT IS MINERAL EXPLORATION? AIM:SAV What is mineral exploration? 2 Exploration is the term used to describe a wide range of activities aimed at searching

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT (Under the Guidelines of Ministry of Environment and Forest in terms of the provisions of EIA notification 2006 and specifically in circular No J-11013/41/2006-IA.II (I) dated 30

More information

MAD345 - Mining II INTRODUCTION. 10 October Hacettepe University. Introduction Prospecting Mining Dilution Resource and Reserve Estimation

MAD345 - Mining II INTRODUCTION. 10 October Hacettepe University. Introduction Prospecting Mining Dilution Resource and Reserve Estimation MAD345 - Mining II INTRODUCTION 10 October 2018 Course content MAD345 THEORY Date October, 10 October, 17 October, 24 October, 31 November, 7 November, 14 November, 21 Topic Introduction Prospecting, exploration

More information

Granite Building Stone Quarry of Sri. Sajan Mani.

Granite Building Stone Quarry of Sri. Sajan Mani. 1. EXECUTIVE SUMMARY: Sri. Sajan Mani had made an application for Granite building stone quarrying located in Sy. No. 2398, Peechi Village, Thrissur Taluk, Thrissur District, Kerala State. Over an extent

More information

(3) The consent letter/declaration/undertaking may have uniform signature of the lessee.

(3) The consent letter/declaration/undertaking may have uniform signature of the lessee. Annexure SCRUTINY COMMENTS ON THE DRAFT REVIEW OF MINING PLAN AND PMCP OF RAJABERA IRON ORE MINE (41.697 HA.) OF SHRI PADAM KUMAR JAIN LOCATED IN SINGHBHUM (WEST) DISTRICT, JHARKHAND SUBMITTED UNDER RULE

More information

Over an extent of 9.28 Acres in Sy. No. 72 / P of Jangameswarapuram (V), Martur (M), Prakasam District, Andhra Pradesh State

Over an extent of 9.28 Acres in Sy. No. 72 / P of Jangameswarapuram (V), Martur (M), Prakasam District, Andhra Pradesh State MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN FOR ROAD METAL (Under Rule 7 A of APMMC Rules 1966 & Rule 23 (B) of MCDR 1988) (FOR THE PLAN PERIOD 2014 15 TO 2018 19) (FOR THE ENSUING BALANCE 2 YEARS

More information

(FOR THE ENSUING BALANCE 2 YEARS PERIOD i.e to ) (UPTO END OF LEASE PERIOD ) For

(FOR THE ENSUING BALANCE 2 YEARS PERIOD i.e to ) (UPTO END OF LEASE PERIOD ) For MINING PLAN (QUARRYING OPERATIONS) FOR ROAD METAL & BUILDING STONE Over an extent of 2.000 Hectares in Sy. No. 134 Routhusuramala (V), Thottambedu (M), Chittoor District Andhra Pradesh State (FOR THE PLAN

More information

APPLICANT: MD. SARFARAZ ANSARI & VIVEKA NAND RAY PRE FEASIBILITY REPORT PRE- FEASIBILITY REPORT

APPLICANT: MD. SARFARAZ ANSARI & VIVEKA NAND RAY PRE FEASIBILITY REPORT PRE- FEASIBILITY REPORT PRE- FEASIBILITY REPORT 0 CONTENTS EXECUTIVE SUMMARY... 3 1.0 INTRODUCTION... 3 1.1 SALIENT FEATURES OF THE PROJECT... 4 1.2 PRESENT LAND USE PLAN... 5 1.3 PROPOSED PLANNING... 5 1.4 UTILIZATION... 5 2.

More information

Granite Building Stone Quarry of M/s Ulikkal Stone Crusher

Granite Building Stone Quarry of M/s Ulikkal Stone Crusher 1. EXECUTIVE SUMMARY: M/s. Ulikkal Stone Crusher had made an application for Granite building stones quarrying located in Sy. No. 28/1A2 in Vayathur Village, Iritty taluk, Kannur District, Kerals State.

More information

For Sale - 56 Acre Sandstone Quarry State Route 511, Oberlin/Kipton, OH 44075

For Sale - 56 Acre Sandstone Quarry State Route 511, Oberlin/Kipton, OH 44075 14647 State Route 511, Oberlin/Kipton, OH 44075 56 ACRES Vermilion Rd Gifford Rd Haigh Rd 44 Summary The Kipton sandstone quarry is included in 56 acre tract owned by Terry A. Johnson, of Huron, Ohio.

More information

FIELD MONITORING OF STABILITY OF DUMP A CASE STUDY

FIELD MONITORING OF STABILITY OF DUMP A CASE STUDY FIELD MONITORING OF STABILITY OF DUMP A CASE STUDY Dr. Singam Jayanthu*, and Dr. Simantini Behera** Professor, Associate Professor Department of Mining Engineering National Institute of Technology Rourkela-769008

More information

Early Exploration Permit Activity Information

Early Exploration Permit Activity Information Early Exploration Permit Activity Information Activities That Require an Early Exploration Permit: Line cutting that is a width greater than 1.5 metres Mechanized stripping of a total surface area of greater

More information

1. INTRODUCTION. EMP Report For Colour Granite Mine of Ha, located in Nellipudi Village, Gangavaram Mandal, East Godavari District, A.P.

1. INTRODUCTION. EMP Report For Colour Granite Mine of Ha, located in Nellipudi Village, Gangavaram Mandal, East Godavari District, A.P. 1. INTRODUCTION 1.1 INTRODUCTION M/S MARS GRANITES was granted a quarry lease over an extent of 1.520 Ha in Sy No: 486/1 & 488/1, Nellipudi Village, Gangavaram Mandal, East Godavari District in the State

More information

Appendix D Rock Blasting Report

Appendix D Rock Blasting Report Appendix D Rock Blasting Report 02-2500-01 May 20, 2005 Frank Arciero Jr. Fallingstar Homes 27231 Burbank Foothill Ranch, California 92610 Subject: ANTICIPATED ROCK EXCAVATION FRAZIER PARK ESTATES DEVELOPMENT

More information

GROUNDWATER CONFIGURATION IN THE UPPER CATCHMENT OF MEGHADRIGEDDA RESERVOIR, VISAKHAPATNAM DISTRICT, ANDHRA PRADESH

GROUNDWATER CONFIGURATION IN THE UPPER CATCHMENT OF MEGHADRIGEDDA RESERVOIR, VISAKHAPATNAM DISTRICT, ANDHRA PRADESH GROUNDWATER CONFIGURATION IN THE UPPER CATCHMENT OF MEGHADRIGEDDA RESERVOIR, VISAKHAPATNAM DISTRICT, ANDHRA PRADESH Prof.P.Jagadeesara Rao Department of Geo-Engineering and Centre for Remote Sensing, College

More information

Geological Report on Limestone Exploration Of Bhatvadiya B Block Of EXECUTIVE SUMMARY

Geological Report on Limestone Exploration Of Bhatvadiya B Block Of EXECUTIVE SUMMARY Geological Report on Limestone Exploration Of Bhatvadiya B Block Of Kalyanpur Taluka, Devbhumi Dwarka District, Gujarat EXECUTIVE SUMMARY Prepared for: Gujarat Mineral Research & Development Society Government

More information

Boreholes. Implementation. Boring. Boreholes may be excavated by one of these methods: 1. Auger Boring 2. Wash Boring 3.

Boreholes. Implementation. Boring. Boreholes may be excavated by one of these methods: 1. Auger Boring 2. Wash Boring 3. Implementation Boreholes 1. Auger Boring 2. Wash Boring 3. Rotary Drilling Boring Boreholes may be excavated by one of these methods: 4. Percussion Drilling The right choice of method depends on: Ground

More information

TABLE 1: Salient features of the project. Black Granite Mine of Sri D. Rama Rao GCP LATITUDE (N) LONGITUDE (E)

TABLE 1: Salient features of the project. Black Granite Mine of Sri D. Rama Rao GCP LATITUDE (N) LONGITUDE (E) 1. EXECUTIVE SUMMARY 1.1 Introduction The proposed mining lease area of Black Granite over an extent of 1.205 Ha. is located in Sy. No. 99/1B of Gurijepalli Village, Santhamaguluru Mandal, Prakasam District,

More information

ROCK EXCAVATION (GRADING) OPSS 206 INDEX

ROCK EXCAVATION (GRADING) OPSS 206 INDEX 206-2 - OPSS 206 INDEX 206-2.1 GENERAL 206-2.1.1 Classification of Rock Materials 206-2.1.2 Tender Items 206-2.1.3 Other Excavation Tender Items 206-2.1.4 Specifications 206-2.1.5 Special Provisions 206-2.1.6

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT TABLE OF CONTENTS Sr. No. Content Page No. 1.0 Executive Summary 29 2.0 Introduction of Project / Background Information 30 3.0 Project Description 32 4.0 Site Analysis 39 5.0 Planning

More information

Coal Loss and Dilution Considerations for Western Canadian Foothills Open Pit Coal Projects

Coal Loss and Dilution Considerations for Western Canadian Foothills Open Pit Coal Projects Coal Loss and Dilution Considerations for Western Canadian Foothills Open Pit Coal Projects Presenter: Mike Allen Manager, Surface Mining April 29, 2015 Outline Terms / Definitions Factors affecting coal

More information

Oktoberforum 2005: Case Histories in Engineering Geology and Geotechnical Engineering,, 4 th Oct. 2005, Petaling Jaya

Oktoberforum 2005: Case Histories in Engineering Geology and Geotechnical Engineering,, 4 th Oct. 2005, Petaling Jaya IEM-GSM Oktoberforum 2005: Case Histories in Engineering Geology and Geotechnical Engineering,, 4 th Oct. 2005, Petaling Jaya DISCONTINUITIES STUDY AND ROCK SLOPES STABILITY ANALYSIS FOR ROCK MASS AT DAMANSARA

More information

Resource and Reserve estimation for a marble quarry using quality indicators

Resource and Reserve estimation for a marble quarry using quality indicators http://dx.doi.org/10.17159/2411-9717/2018/v118n1a5 Resource and Reserve estimation for a marble quarry using quality indicators by I. Kapageridis* and C. Albanopoulos The use of standard estimation and

More information

Rock slope rock wedge stability

Rock slope rock wedge stability Engineering manual No. 28 Updated: 02/2018 Rock slope rock wedge stability Program: Rock stability File: Demo_manual_28.gsk The aim of the chapter of this engineering manual is to explain a rock slope

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN ENVIRONMENTAL MANAGEMENT PLAN Submission By M/s PIONEER TOR STEEL MILLS PVT LIMITED FOR LATERITE [ROM]-11,19,144.60 TPA@67% PRODUCTION-7,49,826.88 TPA Extent-9.813 Hect. Sy. No. 396 / P, Bheemanpally[V],

More information

NZQA unit standard New US6 to replace and version 1 Page 1 of 5

NZQA unit standard New US6 to replace and version 1 Page 1 of 5 Page 1 of 5 Title Demonstrate knowledge of mining methods, and analyse and select plant for metalliferous underground extraction Level 6 Credits 20 Purpose People credited with this unit standard are able

More information

PROGRESS GALLERY Advancing our projects

PROGRESS GALLERY Advancing our projects November 23, 2017. Ignition of the detonating cord for the first blast marked the start of development of the twin declines to access the ultra-high-grade Kakula Copper Discovery on the Tier One Kamoa-Kakula

More information

NOA ASSESSMENT HARRIS QUARRY MENDOCINO COUNTY, CALIFORNIA TABLE OF CONTENTS

NOA ASSESSMENT HARRIS QUARRY MENDOCINO COUNTY, CALIFORNIA TABLE OF CONTENTS NOA ASSESSMENT HARRIS QUARRY MENDOCINO COUNTY, CALIFORNIA TABLE OF CONTENTS Introduction... 1 Scope of Services... 1 Project Location and Description... 1 Geologic Setting... 1 Regional Geology... 1 Site

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT 1. INTRODUCTION Thiru S. Baskar Babu, S/o. Late Sri S. Selvaraj, No.2, First cross street, Anna Nagar, Nellithope S.O., Pondicherry has a mining lease area for the production of

More information

Geological Report on Limestone Exploration of Mudhvay Sub-block B, Lakhpat Taluka, Kachchh District, Gujarat. Executive Summary

Geological Report on Limestone Exploration of Mudhvay Sub-block B, Lakhpat Taluka, Kachchh District, Gujarat. Executive Summary Geological Report on Limestone Exploration of Mudhvay Sub-block B, Lakhpat Taluka, Kachchh District, Gujarat Executive Summary Prepared for Commissioner of Geology & Mining Government of Gujarat Prepared

More information

& ADJOINING QUARRY LEASE AREA Lease Name Extent- Ha

& ADJOINING QUARRY LEASE AREA Lease Name Extent- Ha ENVIRONMENTAL MANAGEMENT PLAN FOR CLUSTER MINES For M/s VIGNESHWARA MINES & MINERALS RAVALUDIKI DOLOMITE & STEATITE MINE Production : Dolomite-4500 TPA, High Grade Steatite-3375, Low Grade Steatite-2250

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN 1.0 Introduction Sri K. Ravi Shankar filed an application to Department of Mines and Geology for grant of Quarry lease for Colour Granite in Sy. No. 100, Odulapalle Village,

More information

[Penumaka, 7(1): January-March 2017] ISSN Impact Factor

[Penumaka, 7(1): January-March 2017] ISSN Impact Factor INTERNATIONAL JOURNAL OF ENGINEERING SCIENCES &MANAGEMENT HYDROGEOMORPHOLOGY OF CHEVELLA BASIN, RANGA REDDY DISTRICT, TELANGANA STATE Penumaka Ramesh* 1 & Podila Sankara Pitchaiah 2 * 1&2 Department of

More information

Gotechnical Investigations and Sampling

Gotechnical Investigations and Sampling Gotechnical Investigations and Sampling Amit Prashant Indian Institute of Technology Gandhinagar Short Course on Geotechnical Investigations for Structural Engineering 12 14 October, 2017 1 Purpose of

More information

List of Sites in District 2C Source Number

List of Sites in District 2C Source Number List of Sites in District 2C Source Number 03-002-1...2 03-021-1...4 03-070-1...6 14-002-1...8 14-007-1...10 14-011-1...12 14-015-1...14 26-004-1...16 26-007-1...18 26-010-1...20 26-013-1...22 26-036-1...24

More information

Report for Area Drainage Studies for 1320 MW (2x660 MW) THERMAL POWER PROJECT AT MIRZAPUR, U.P.

Report for Area Drainage Studies for 1320 MW (2x660 MW) THERMAL POWER PROJECT AT MIRZAPUR, U.P. Report for Area Drainage Studies for 1320 MW (2x660 MW) THERMAL POWER PROJECT AT MIRZAPUR, U.P. 1. Introduction M/s Welspun Energy Uttar Pradesh Ltd. (WEUPL) is putting up 1320 MW (2 x 660 MW) coal fired

More information

10. GEOTECHNICAL EXPLORATION PROGRAM

10. GEOTECHNICAL EXPLORATION PROGRAM Geotechnical site investigations should be conducted in multiple phases to obtain data for use during the planning and design of the tunnel system. Geotechnical investigations typically are performed in

More information

THE MINISTRY OF ENERGY AND ENERGY INDUSTRIES MINERALS DIVISION MINE DESIGN TEMPLATE OPERATOR NAME: OPERATOR ADDRESS: PHONE NUMBER: FACSIMILE:

THE MINISTRY OF ENERGY AND ENERGY INDUSTRIES MINERALS DIVISION MINE DESIGN TEMPLATE OPERATOR NAME: OPERATOR ADDRESS: PHONE NUMBER: FACSIMILE: THE MINISTRY OF ENERGY AND ENERGY INDUSTRIES MINERALS DIVISION MINE DESIGN TEMPLATE 1.0 GENERAL INFORMATION OPERATOR NAME: OPERATOR ADDRESS: PHONE NUMBER: FACSIMILE: NAME OF CONTACT: CELLULAR PHONE: EMAIL

More information

QUARRYING PLAN FOR. PARATAPUR SAND MINING BLOCK - 2 EXTENT Acres (4.93 Hectare)

QUARRYING PLAN FOR. PARATAPUR SAND MINING BLOCK - 2 EXTENT Acres (4.93 Hectare) QUARRYING PLAN FOR PARATAPUR SAND MINING BLOCK - 2 EXTENT 12.20 Acres (4.93 Hectare) IN KRISHNA RIVER BED ADJACENT TO SY.NO 8/1, 8/2, 7/1 & 7/2 OF PARATAPUR - VILLAGE DEVADURGA - TALUK RAICHUR- DISTRICT

More information

data becomes available to us. We already have crude maps of the Mars and the Moon. A map gives a picture of one or several of the elements of the

data becomes available to us. We already have crude maps of the Mars and the Moon. A map gives a picture of one or several of the elements of the FUNDAMENTALS OF MAPS THE SPHERICAL earth is best represented bya three-dimensional model of the earth, called a globe. All parts of the earth can be shown on it in their true shape, area and location along

More information

WE DELIVER THE USE OF RTK GPS IN BLAST OPTIMIZATION THE USE OF RTK GPS IN BLAST OPTIMIZATION THE CASE OF GOLD FIELDS GHANA LTD, TARKWA

WE DELIVER THE USE OF RTK GPS IN BLAST OPTIMIZATION THE USE OF RTK GPS IN BLAST OPTIMIZATION THE CASE OF GOLD FIELDS GHANA LTD, TARKWA THE USE OF RTK GPS IN BLAST OPTIMIZATION THE CASE OF GOLD FIELDS GHANA LTD, TARKWA BY FRANCIS MENSAH EILAT 2009, FIG WORKING WEEK PRESENTATION OUTLINE 2 BACKGROUND Tarkwa Gold Mine is owned by Gold Fields

More information

Meghalaya. Mining their own business. Arwat Challam

Meghalaya. Mining their own business. Arwat Challam Meghalaya Mining their own business Arwat Challam Introduction Area of 22,429 sq. km. Divided into 7 Districts Meghalaya Three Main tribes- Khasi, Pnar and Garo Indo-Malayan Biodiversity Hotspot. Major

More information

EXTENT : HA. S.F.No. : 378/5 VILLAGE : KARANDAPALLI TALUK : DENKANIKOTTAI DISTRICT : KRISHNAGIRI STATE : TAMIL NADU

EXTENT : HA. S.F.No. : 378/5 VILLAGE : KARANDAPALLI TALUK : DENKANIKOTTAI DISTRICT : KRISHNAGIRI STATE : TAMIL NADU SCHEME OF MINING FOR BLACK GRANITE QUARRY EXTENT : 1.14.0HA. S.F.No. : 378/5 VILLAGE : KARANDAPALLI TALUK : DENKANIKOTTAI DISTRICT : KRISHNAGIRI STATE : TAMIL NADU (UNDER RULE 12 OF GCDR 1999) LESSEE m/s.

More information

Curriculum Document Mining Technician: Strata Control Practitioner (Surface) Occupational Curriculum

Curriculum Document Mining Technician: Strata Control Practitioner (Surface) Occupational Curriculum Curriculum Document Curriculum Code Curriculum Title 311701-008 Mining Technician: Strata Control Practitioner (Surface) TABLE OF CONTENTS SECTION 1: CURRICULUM OVERVIEW 1 Occupational Information 1 Associated

More information

The Kennady North Project Investor Presentation Q2 2017

The Kennady North Project Investor Presentation Q2 2017 The Kennady North Project Investor Presentation Q2 2017 Forward Looking Statement This presentation may contain forward-looking statements. These forward-looking statements are made as of the date of the

More information

APPENDIX Q BLASTING IMPACT ASSESSMENT REPORT

APPENDIX Q BLASTING IMPACT ASSESSMENT REPORT APPENDIX Q BLASTING IMPACT ASSESSMENT REPORT BLASTING IMPACT ASSESSMENT: FUTURE BLASTING OPERATIONS AT THE MOOSE RIVER OPEN PIT GOLD MINE DEVELOPMENT SITE TOUQUOY GOLD PROJECT MOOSE RIVER, HALIFAX COUNTY,

More information

LOGGING AND SAMPLING PROTOCOL

LOGGING AND SAMPLING PROTOCOL LOGGING AND SAMPLING PROTOCOL The following discussion will address a number of issues including; the physical taking of the samples, geological descriptions, sample numbering and handling, and the dispatch

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN M/s. RADHAKRISHNA MICA MINING COMPANY [QL area - 13.27 Ha.(32.8 Acres)] Sy. Nos.1134/2, 1135/1A, 1136/1, 1137/1, 1138, 1139 & 1141, Griddaluru Village, Sydapuram Mandal, SPSR Nellore District ENVIRONMENTAL

More information

Geological report on Limestone Exploration of Goyla Block, Abadasa Taluka, Kachchh District, Gujarat. Executive Summary

Geological report on Limestone Exploration of Goyla Block, Abadasa Taluka, Kachchh District, Gujarat. Executive Summary Geological report on Limestone Exploration of Goyla Block, Abadasa Taluka, Kachchh District, Gujarat Executive Summary Prepared for Commissioner of Geology & Mining Government of Gujarat Prepared by Geovale

More information

List of Abstracts. Automation and Introduction of New Technologies in Blasting Operations (9)

List of Abstracts. Automation and Introduction of New Technologies in Blasting Operations (9) List of Abstracts Automation and Introduction of New Technologies in Blasting Operations (9) A review of dam foundation excavation techniques in China Building Accurate and Inexpensive Accelerometer-Based

More information

CHAPTER 3 SPECIFIC METHODS FOR SAMPLING ROAD CONSTRUCTION MATERIALS

CHAPTER 3 SPECIFIC METHODS FOR SAMPLING ROAD CONSTRUCTION MATERIALS CHAPTER 3 SPECIFIC METHODS FOR SAMPLING ROAD CONSTRUCTION MATERIALS NATURAL MATERIALS SAMPLING METHOD MA 1 SAMPLING OF A NATURAL ROCK MASS 1. SCOPE This method describes the taking of samples from a test

More information

Borehole mining removes the need for pit cut back and associated waste removal

Borehole mining removes the need for pit cut back and associated waste removal Merlin Diamonds Limited has being investigating the use of borehole mining at Merlin, as a means to optimise the economics of ore extraction at Merlin. Borehole mining involves the use of high pressure

More information

Over an extent of Hectares in Sy. No. 01 of Kachavaram (V), Ibrahimpatnam (M), Krishna District, Andhra Pradesh State

Over an extent of Hectares in Sy. No. 01 of Kachavaram (V), Ibrahimpatnam (M), Krishna District, Andhra Pradesh State MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN FOR ROAD METAL & GRAVEL (Under Rule 7 A of APMMC Rules 1966 & Rule 23 (B) of MCDR 1988) INTRODUCTION Over an extent of 0.810 Hectares in Sy. No. 01 of

More information

SCHEME OF MINING FOR BLACK GRANITE(DOLERITE) MINE LESSEE

SCHEME OF MINING FOR BLACK GRANITE(DOLERITE) MINE LESSEE SCHEME OF MINING FOR BLACK GRANITE(DOLERITE) MINE EXTENT : 1.20.0HA. S.F.Nos. : 1/6, 2/1, 2/2A, 2/3B1 & 2/3B2 VILLAGE : SEMANGALAM TALUK : VANUR DISTRICT : VILUPPURAM STATE : TAMIL NADU (UNDER RULE 12

More information

MCDR INSPECTION REPORT hect. (All Non-forest) IBM/4816/2011

MCDR INSPECTION REPORT hect. (All Non-forest) IBM/4816/2011 MCDR INSPECTION REPORT 1.0 GENERAL SN Particulars Details 1 Name of the Mine, Name of Inspecting officer with designation and date of inspection 2 Total Lease Area (Ha) with breakup of Non-forest and forest

More information