1 Exhibit A Description of Services Section 37 Floodplain Storage Design Singhofen & Associates, Inc. (SAI, Consultant) is pleased to present this scope of services to the City of Palm Coast Engineering and Stormwater Department (City) for design and permitting services for stormwater improvements within Section 37. The Consultant has identified several locations along the Bellaire Canal for possible design solutions to create floodplain storage (refer to Figure 1). The intent of the project is to prepare construction plans, construction cost estimates, and provide permitting services for the proposed design solutions. The floodplain storage areas include three general locations which cover five individual parcels along the Bellaire Canal in Section 37 of the City. Two parcels are private property, all or part of which are to be acquired by the City for the project. The remaining three parcels are already owned by the City. This scope of services is separated into two phases. Phase 1 includes initial survey, environmental, and geotechnical services as well as a preliminary layout of the proposed design. Phase 2 includes finalizing the proposed design along with preparation of construction plans and permitting services. PHASE 1: Task 1. Data Collection and Surveying. This task primarily includes work to gather information and create a preliminary drawing for use in create the design solution and construction plans. Task 1.1 Data Collection and Site Reconnaissance. Most of the available information has already been obtained by the Consultant during the Section 31 & 37 Stormwater Management Master Plan (SWMMP) project. This task also includes field reconnaissance efforts. The Consultant shall conduct a reconnaissance trip by key design members to observe current site conditions and to inspect areas of special concern with respect to necessary design and permitting requirements. Task 1.2 Survey Services. Topographic survey will be required at the three locations in order to update the stormwater model and prepare the design. Survey information shall include topographic information on a 50 grid for each parcel. Survey services will be performed by CPH Inc. Note that no boundary survey, title work, right-of-ways, or surveyed wetland locations are included in this phase of the scope of work. A formal proposal from CPH has currently not been prepared. A scope of work for the survey services will be prepared by CPH and provided to the City prior to beginning work on the project. The cost included in the price schedule for the survey work is an estimate based on preliminary discussions between the City and CPH. Task 1.3 Environmental Study. An environmental report addressing wetland evaluations and endangered species assessments will be necessary during

2 permitting of the project. This task includes an environmental assessment and wetland delineations and will be performed by CPH Inc. to assist in project permitting as needed. Refer to Attachment 1 for more detailed information on the scope of these services. Task 1.4 Geotechnical Services. This task includes geotechnical evaluation for analysis of the subsurface soil conditions in the project areas in order to determine the quality and value of fill that will result from the project. The geotechnical analysis will be performed by Universal Engineering Sciences, Inc. and shall include a total of 4 borings along with the associated laboratory testing. Refer to Attachment 2 for more detailed information on the scope of these services. Task 2 Stormwater System Design. This task primarily includes work to update and finalize the stormwater model that was previously prepared during the Section 37 Stormwater Management Master Plan update. Task 3. Construction Documents. The Consultant shall prepare 30% construction drawings for review and approval by the City. The drawings shall include the existing topography prepared by CPH along with a preliminary layout of the proposed ponds. This scope of work does not include revisions to the 30% plans as a result of site conditions or changes by the City. Task 4. Meetings. This task includes one (1) pre-application meeting with St. Johns River Water Management District (SJRWMD) to discuss the proposed design and any anticipated permitting issues associated with the project. PHASE 2: Upon approval by the City of the proposed design from Phase 1, the Consultant will proceed with the Phase 2 work as listed below: Task 5. Supplemental Surveying. Additional construction level survey information will be required in order to finalize the design and complete the construction plans. Supplemental survey information will include wetland locations, parcel boundaries, rightof-ways, easements, and utilities. A scope of work for the survey services will be prepared by CPH and provided to the City prior to beginning work on the project. The cost included in the price schedule for the Phase 2 survey work is an estimate based on preliminary discussions between the City and CPH. Task 6. Construction Documents. The Consultant shall prepare drawings and documents suitable for construction and review by the jurisdictional agencies as described below. Task 6.1. Construction Plans. The Consultant shall prepare construction plans in general conformance with the FDOT Roadway Plans and Preparation Manual and shall be 22 x34. All three design locations will be included in one set of plans. This task includes a 90% plan set and 100% plan set submittals.

3 Upon completion of the 90% plan set, one electronic copy in PDF format will be provided to the City for review and comment. Upon completion of the City s review, the Consultant will prepare and submit three (3) sets of 100% construction plans at 11 x17 (half scale) for review and comments, along with an electronic copy in PDF format. Task 6.2. Quantities and Construction Cost Estimates. The Consultant shall prepare a detailed quantity estimate of each bid item using the FDOT Basis of Estimates Handbook in an Excel Spreadsheet and provide it to the City with the 90% submittal. SAI will revise the quantity estimate for submittal with the 100% submittal. Cost estimates shall likewise be provided at the 90% and 100% submittals. Task 7. Regulatory Permitting. This task includes permitting through SJRWMD. All three locations are to be permitted as a single project (i.e., a single permit/application to include all three locations). The Consultant shall prepare and submit the required permit application. This will include preparation of a drainage report for the stormwater models updated as a part of the Phase 1 work. A maximum of two (2) responses to request for additional information (RAIs) are included in this task. The City shall be responsible for all permit fees.

4 95 1 City of Palm Coast Map Document: (O:\COPC_SWMMP\Section 31 & 37\ArcView\COPC_Section37_35_Drummond_Parcels.mxd) 4/6/ :14:03 PM Bellaire Canal - Flood Storage Augmentation FIGURE: 1

5 Price Schedule Section 37 Floodplain Storage Design PHASE 1 Task Task Description 1 Data Collection and Surveying Project Manager Engineer III Engineer II Unreg. Engineer I Tech. Supervisory Tech. Technician Admin III Total Hours Labor Costs Hourly Rate $ $ $ $ $ $ $ $ Data Collection and Site Reconnaissance $ 2, Survey Services See subconsultant fees below Coordination w/ Surveyor $ 1, Environmental Study See subconsultant fees below Coordination w/ Environmental Consultant $ Geotechnical Services See subconsultant fees below Coordination w/ Geotech Consultant $ Stormwater System Design Subtotal = $ 5, Stormwater Model Updates $ 5, Construction Documents Subtotal = $ 5, Incorporate Survey Drawing(s) $ Prepare Base Drawing $ 4, % Construction Plans $ 4, Regulatory Permitting Subtotal = $ 8, Pre-application Meeting $ 1, Subtotal = $ 1, Phase 1 Total Estimated Labor Costs $ 20, Estimated Reimbursable Direct Costs Bond Plots (24" x 36") 3 plan sets = 30 $ 2.50 = $ Bond Plots (1/2 scale) 3 plan sets = 30 $ 2.50 = $ Bond Plots (permitting) 0 $ 2.50 = $ - Photocopies (8 1/2" x 11") 25 $ 0.15 = $ 3.75 Color Photocopies (8 1/2" x 11") 10 $ 0.55 = $ 5.50 Travel (2 - City & field recon) 200 $ 0.55 = $ Shipping = $ Survey Subconsultant (CPH) = $ 7, Geotechnical Consultant (Universal) = $ 2, Environmental Consultant (CPH) = $ 6, Phase 1 Total Estimated Reimbursable Direct Costs $ 16, Phase 1 Total Maximum Compensation $ 37, Singhofen Associates, Inc. Page 1 of 2

6 Price Schedule Section 37 Floodplain Storage Design PHASE 2 Task Task Description Project Manager Engineer III Engineer II Unreg. Engineer I Tech. Supervisory Tech. Technician Admin III Total Hours Labor Costs Hourly Rate $ $ $ $ $ $ $ $ Supplemental Surveying Survey Services See subconsultant fees below Coordination w/ Surveyor $ Construction Documents Subtotal = $ Construction Plans 0.00 $ - Incorporate Survey Drawing(s) $ % Construction Plans $ 11, % Construction Plans $ 6, Quantities and Construction Cost Estimates $ 4, Regulatory Permitting Subtotal = $ 23, Drainage Report $ 4, ERP Application Package $ 3, RAI Response (2 anticipated) $ 3, Subtotal = $ 10, Phase 2 Total Estimated Labor Costs $ 34, Estimated Reimbursable Direct Costs Bond Plots (24" x 36") 8 plan sets = 160 $ 2.50 = $ Bond Plots (1/2 scale) 3 plan sets = 60 $ 2.50 = $ Bond Plots (permitting) 0 $ 2.50 = $ - Photocopies (8 1/2" x 11") 50 $ 0.15 = $ 7.50 Color Photocopies (8 1/2" x 11") 25 $ 0.55 = $ Shipping = $ Survey Subconsultant (CPH) = $ 2, Phase 2 Total Estimated Reimbursable Direct Costs $ 3, Phase 2 Total Maximum Compensation $ 37, Total Compensation (Phases 1 and 2) = $ 75, Singhofen Associates, Inc. Page 2 of 2

RESOLUTION NO

RESOLUTION NO RESOLUTION NO. 14-31 A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF TREASURE ISLAND APPROVING THE EXECUTION OF A WORK AUTHORIZATION WITH MICHAEL BAKER JR., INC ENGINEERING TO COMPLETE ENGINEERING AND

More information

FOR PROJECTS INITIATED AFTER NOVEMBER 1, 2008 ITEM 716 EMBANKMENT EARTH OUTLET SEDIMENT TRAP

FOR PROJECTS INITIATED AFTER NOVEMBER 1, 2008 ITEM 716 EMBANKMENT EARTH OUTLET SEDIMENT TRAP AFTER NOVEMBER 1, 2008 ITEM 716 EMBANKMENT EARTH OUTLET SEDIMENT TRAP 716.1 Description. This work shall consist of furnishing, installing, maintaining, and removing temporary erosion protection and sediment

More information

APPLICATION TO AMEND THE FUTURE LAND USE MAP (FLUM) SMALL SCALE

APPLICATION TO AMEND THE FUTURE LAND USE MAP (FLUM) SMALL SCALE DEPARTMENT OF DEVELOPMENT & PLANNING 825 Ohio Avenue - Lynn Haven, FL 32444 (850) 265-2961 - (850) 265-3478 APPLICATION TO AMEND THE FUTURE LAND USE MAP (FLUM) SMALL SCALE Deadline to submit is 30 days

More information

Woodford County Erosion Prevention Plan and Permit. Application #

Woodford County Erosion Prevention Plan and Permit. Application # Woodford County Erosion Prevention Plan and Permit Application # Date Instructions: Applicant will complete Parts A and B, and attach a proposed site diagram. This diagram must be completed in accordance

More information

SAN FRANCISCO DISTRICT INFORMATION REQUESTED FOR VERIFICATION OF CORPS JURISDICTION

SAN FRANCISCO DISTRICT INFORMATION REQUESTED FOR VERIFICATION OF CORPS JURISDICTION DEPARTMENT OF THE ARMY SAN FRANCISCO DISTRICT, U.S. ARMY CORPS OF ENGINEERS 1455 MARKET STREET SAN FRANCISCO, CALIFORNIA 94103-1398 SAN FRANCISCO DISTRICT INFORMATION REQUESTED FOR VERIFICATION OF CORPS

More information

Chapter 7 Mudflow Analysis

Chapter 7 Mudflow Analysis Chapter 7 Mudflow Analysis 7.0 Introduction This chapter provides information on the potential and magnitude of mud floods and mudflows that may develop in Aspen due to rainfall events, snowmelt, or rain

More information

ADDENDUM NO. 1 TO THE BIDDING /CONTRACT DOCUMENTS AND SPECIFICATIONS CITY OF COCOA BEACH BID NO: CB15-002

ADDENDUM NO. 1 TO THE BIDDING /CONTRACT DOCUMENTS AND SPECIFICATIONS CITY OF COCOA BEACH BID NO: CB15-002 ADDENDUM NO. 1 TO THE BIDDING /CONTRACT DOCUMENTS AND SPECIFICATIONS CITY OF COCOA BEACH GEOGRAPHIC INFORMATION SYSTEM (GIS) SERVICES CONTRACT BID NO: CB15-002 March 11, 2016 To All Interested Bidders:

More information

Internal Audit Report

Internal Audit Report Internal Audit Report Right of Way Mapping TxDOT Internal Audit Division Objective To determine the efficiency and effectiveness of district mapping procedures. Opinion Based on the audit scope areas reviewed,

More information

Electronic Submission Format Guide Anthracite Preparation Plant Permit Application

Electronic Submission Format Guide Anthracite Preparation Plant Permit Application Electronic Submission Format Guide Anthracite Preparation Plant Permit Application Module 1: Application Section A through Section J, the Application Checklist, and all narrative responses Act 67 / 68

More information

Electronic Submission Format Guide Large Noncoal (Industrial Minerals) Mine Permit Application (5600-PM-BMP0315)

Electronic Submission Format Guide Large Noncoal (Industrial Minerals) Mine Permit Application (5600-PM-BMP0315) Electronic Submission Format Guide Large Noncoal (Industrial Minerals) Mine Permit Application (5600-PM-BMP0315) Module 1: Application Section A through Section I, the Application Checklist, and all narrative

More information

The following maps must be provided as a part of the ADA. The appropriate scale for each map should be determined at the pre application conference.

The following maps must be provided as a part of the ADA. The appropriate scale for each map should be determined at the pre application conference. Main Street @ Coconut Creek DRI QUESTION 9 MAPS The following maps must be provided as a part of the ADA. The appropriate scale for each map should be determined at the pre application conference. Map

More information

Minimum Standards for Wetland Delineations

Minimum Standards for Wetland Delineations Minimum Standards for Wetland Delineations Jason Gipson Chief, Utah/Nevada Regulatory Branch Sacramento District Regulatory Program Workshop 16 Mar 2016 US Army Corps of Engineers Delineation Report Minimum

More information

LOCATED IN INDIAN RIVER COUNTY PREPARED FOR S.J.R.W.M.D. AND F.W.C.D. DECEMBER, 2003 Updated 2007 Updated May 2014 PREPARED BY

LOCATED IN INDIAN RIVER COUNTY PREPARED FOR S.J.R.W.M.D. AND F.W.C.D. DECEMBER, 2003 Updated 2007 Updated May 2014 PREPARED BY FELLSMERE WATER CONTROL DISTRICT EAST MASTER DRAINAGE PLAN AND STORMWATER HYDROLOGIC ANALYSIS OF THE GRAVITY DRAINAGE SYSTEM LOCATED BETWEEN THE EAST BOUNDARY, LATERAL U, THE MAIN CANAL, AND DITCH 24 LOCATED

More information

.. lomfanln. Commlllee Memben: Cn gory,... Chalnnon Polrlc:k Gte!ve, Membef. freosury

.. lomfanln. Commlllee Memben: Cn gory,... Chalnnon Polrlc:k Gte!ve, Membef. freosury Commlllee Memben: Cn gory,... Chalnnon Polrlc:k Gte!ve, Membef. freosury James McCain. -- -- Member. -- -.. OGC SubconunltN RIMt.. lomfanln Steve long CC: c.o.aladlot ~-- ml!&aclloll P 20 10 Conllact Amendment

More information

Electronic Submission Format Guide Bituminous Coal Surface Mine Permit Application (5600-PM-BMP0311)

Electronic Submission Format Guide Bituminous Coal Surface Mine Permit Application (5600-PM-BMP0311) Electronic Submission Format Guide Bituminous Coal Surface Mine Permit Application (5600-PM-BMP0311) Module 1: Application Section A through Section J, the Application Checklist, and all narrative responses.

More information

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers This form should be completed by following the instructions provided in Section IV of the JD Form Instructional Guidebook. SECTION

More information

December 16, Mr. Lee Hughes Southwest Florida Water Management District Tampa Service Office 7601 Highway 301 North Tampa, FL 33637

December 16, Mr. Lee Hughes Southwest Florida Water Management District Tampa Service Office 7601 Highway 301 North Tampa, FL 33637 December 16, 2015 Mr. Lee Hughes Southwest Florida Water Management District Tampa Service Office 7601 Highway 301 North Tampa, FL 33637 RE: Response to SWFWMD Supplemental Information Request Dear Mr.

More information

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers This form should be completed by following the instructions provided in Section IV of the JD Form Instructional Guidebook. SECTION

More information

STORMWATER REPORT FRITO LAY SUBDIVISION NO. 3

STORMWATER REPORT FRITO LAY SUBDIVISION NO. 3 STORMWATER REPORT FRITO LAY SUBDIVISION NO. 3 May 2018 STORMWATER REPORT I. Subdivision Data a. The parcel is adjacent to the existing Frito Lay property in Topeka; and the subject plat application encompasses

More information

3.11 Floodplains Existing Conditions

3.11 Floodplains Existing Conditions Other stormwater control practices may be needed to mitigate water quality impacts. In addition to detention facilities, other practices such as vegetated basins/buffers, infiltration basins, and bioswales

More information

Chapter 7 Mudflow Analysis

Chapter 7 Mudflow Analysis Chapter 7 Mudflow Analysis 7.0 Introduction This chapter provides information on the potential and magnitude of mud floods and mudflows that may develop in Aspen due to rainfall events, snowmelt, or rain

More information

County of San Diego, Planning & Development Services

County of San Diego, Planning & Development Services County of San Diego, Planning & Development Services E N V I R O N M E N T A L R E V I E W U P D A T E A P P L I C A T I O N F O R A P P L I C A T I O N S C O V E R E D B Y A P R E V I O U S L Y C O M

More information

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers This form should be completed by following the instructions provided in Section IV of the JD Form Instructional Guidebook. SECTION

More information

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers This form should be completed by following the instructions provided in Section IV of the JD Form Instructional Guidebook. SECTION

More information

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers This form should be completed by following the instructions provided in Section IV of the JD Form Instructional Guidebook. SECTION

More information

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers This form should be completed by following the instructions provided in Section IV of the JD Form Instructional Guidebook. SECTION

More information

Document Title. Estimating the Value of Partner Contributions to Flood Mapping Projects. Blue Book

Document Title. Estimating the Value of Partner Contributions to Flood Mapping Projects. Blue Book Document Title Estimating the Value of Partner Contributions to Flood Mapping Projects Blue Book Version 1.1 November 2006 Table of Contents 1. Background...1 2. Purpose...1 3. Overview of Approach...2

More information

REQUEST FOR PROPOSALS CLOSING DATE:

REQUEST FOR PROPOSALS CLOSING DATE: Request for Proposals 110 Westlake Drive City of West Lake Hills 110 Westlake Drive REQUEST FOR PROPOSALS CLOSING DATE: Tuesday, October 23, 2018 City of West Lake Hills Request for Proposals 1 I. INTRODUCTION

More information

Design Idea C. Total SF: 893,347. Heights High 1680 Students Wiley Students Students Students.

Design Idea C. Total SF: 893,347. Heights High 1680 Students Wiley Students Students Students. Design Idea C Monticello Heights High 1680 Students Wiley Roxboro Total SF: 893,347 4-8 700 4-8 Students 4-8 700 4-8 Students 4-8 700 4-8 Students Oxford Canterbury Boulevard Roxboro PK-3 420 K-3 Students

More information

RESOLUTION NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF SUPERVISORS OF THE CORKSCREW FARMS COMMUNITY DEVELOPMENT DISTRICT:

RESOLUTION NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF SUPERVISORS OF THE CORKSCREW FARMS COMMUNITY DEVELOPMENT DISTRICT: RESOLUTION 2017-08 A RESOLUTION OF THE BOARD OF SUPERVISORS OF THE CORKSCREW FARMS COMMUNITY DEVELOPMENT DISTRICT APPROVING PROPOSED BUDGET(S) FOR FISCAL YEAR 2017/2018 AND SETTING A PUBLIC HEARING THEREON

More information

April 10, Mr. Curt Van De Walle, City Manager City of Castle Hills 209 Lemonwood Drive Castle Hills, Texas 78213

April 10, Mr. Curt Van De Walle, City Manager City of Castle Hills 209 Lemonwood Drive Castle Hills, Texas 78213 Mr. Curt Van De Walle, City Manager City of Castle Hills 209 Lemonwood Drive Castle Hills, Texas 78213 Subject: Revised Castle Hills BASIS Charter School Traffic Impact Analysis Review City of Castle Hills,

More information

Information for File MVP RMM

Information for File MVP RMM Information for File MVP-2013-03320-RMM Applicant: City of St. Cloud Corps Contact: Ryan Malterud Address: 180 Fifth Street East, Suite 700, St. Paul, MN 55101 E-Mail: Ryan.M.Malterud@usace.army.mil Phone:

More information

Temple City Unified School District Committed to 21 st Century Academic Excellence

Temple City Unified School District Committed to 21 st Century Academic Excellence Temple City Unified School Committed to 21 st Century Academic Excellence Board of Education Members Vinson Bell Kenneth Knollenberg Lawrence A. Marston John Pomeroy Robert S. Ridley Superintendent Kathryn

More information

Required Documents. Title: Number: AEP Administration 2017 No. 1. Provincial Wetlands and Water Boundaries Section. Effective Date: September 1, 2017

Required Documents. Title: Number: AEP Administration 2017 No. 1. Provincial Wetlands and Water Boundaries Section. Effective Date: September 1, 2017 Title: Number: Program Name: Provincial Wetlands and Water Boundaries Section Effective Date: September 1, 2017 This document was updated on: August 25, 2017 The Provincial Wetlands and Water Boundaries

More information

McHenry County Property Search Sources of Information

McHenry County Property Search Sources of Information Disclaimer: The information in this system may contain inaccuracies or typographical errors. The information in this system is a digital representation of information derived from original documents; as

More information

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers SECTION I: BACKGROUND INFORMATION A. REPORT COMPLETION DATE FOR APPROVED JURISDICTIONAL DETERMINATION (JD): November 3, 06 B. DISTRICT

More information

Delaware Bay Dikes Repair and Prevention Project Preliminary Design for New Castle Dikes

Delaware Bay Dikes Repair and Prevention Project Preliminary Design for New Castle Dikes City of New Castle Presentation Delaware Bay Dikes Repair and Prevention Project Preliminary Design for New Castle Dikes New Castle Conservation District DNREC August 22, 2012 Agenda Project Background

More information

HAPPY N6W Y6ARl. Committee Members: Gregory Pease. Chairman Patrick Grelve. Member. Treasury Jeff Close. Member. OGC. Subcommittee Members ThomosFomn

HAPPY N6W Y6ARl. Committee Members: Gregory Pease. Chairman Patrick Grelve. Member. Treasury Jeff Close. Member. OGC. Subcommittee Members ThomosFomn Committee Members: Gregory Pease. Chairman Patrick Grelve. Member. Treasury Jeff Close. Member. OGC PUBLIC NOTICE AGENDA PROFESSIONAL SERVICES EVALUATION COMMITIEE MEETING Thursday, January 4, 2018, 10:00

More information

COMMUNITY DEVELOPMENT DEPARTMENT POLICY & PROCEDURE

COMMUNITY DEVELOPMENT DEPARTMENT POLICY & PROCEDURE COMMUNITY DEVELOPMENT DEPARTMENT POLICY & PROCEDURE Policy No: DSP-OO3 Release Date: January 1, 2014 Effective Date: January 1, 2014 Revision Date: March 1, 2018 TITLE: The City Policy for Site Specific

More information

BUILDING AND SAFETY FEE SCHEDULE (Effective July1, 2013)

BUILDING AND SAFETY FEE SCHEDULE (Effective July1, 2013) BUILDING AND SAFETY DIVISION TELEPHONE (949) 724-6300 BUILDING AND SAFETY FEE SCHEDULE (Effective July1, 2013) Payment: When a plan is required by the Administrative Authority to be submitted, a plan check

More information

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers This form should be completed by following the instructions provided in Section IV of the JD Form Instructional Guidebook. SECTION

More information

McHenry County Property Search Sources of Information

McHenry County Property Search Sources of Information Disclaimer: The information in this system may contain inaccuracies or typographical errors. The information in this system is a digital representation of information derived from original documents; as

More information

Materials. Use materials meeting the following.

Materials. Use materials meeting the following. 208.01 Section 208. SOIL EROSION AND SEDIMENTATION CONTROL 208.01 Description. Install and maintain erosion and sedimentation controls to minimize soil erosion and to control sedimentation from affecting

More information

TATA CHEMICALS MAGADI LIMITED (Mining Section) TRONA CRUSHING PLANT AND PREWASH TANK FACILITY PROJECT

TATA CHEMICALS MAGADI LIMITED (Mining Section) TRONA CRUSHING PLANT AND PREWASH TANK FACILITY PROJECT 1 TATA CHEMICALS MAGADI LIMITED (Mining Section) TRONA CRUSHING PLANT AND PREWASH TANK FACILITY PROJECT RFQ for Geotechnical Investigations and Foundation Recommendations TCML/MS/RFQ1/2017 October 2017

More information

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers This form should be completed by following the instructions provided in Section IV of the JD Form Instructional Guidebook. SECTION

More information

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers This form should be completed by following the instructions provided in Section IV of the JD Form Instructional Guidebook. SECTION

More information

GOAL 7 AREAS SUBJECT TO NATURAL DISASTERS AND HAZARDS. To protect life and property from natural disasters and hazards.

GOAL 7 AREAS SUBJECT TO NATURAL DISASTERS AND HAZARDS. To protect life and property from natural disasters and hazards. GOAL 7 AREAS SUBJECT TO NATURAL DISASTERS AND HAZARDS A. GOALS: To protect life and property from natural disasters and hazards. B. POLICIES: 1. Floodplains shall be maintained as natural drainage-ways.

More information

LOMR SUBMITTAL LOWER NEHALEM RIVER TILLAMOOK COUNTY, OREGON

LOMR SUBMITTAL LOWER NEHALEM RIVER TILLAMOOK COUNTY, OREGON LOMR SUBMITTAL LOWER NEHALEM RIVER TILLAMOOK COUNTY, OREGON Prepared for: TILLAMOOK COUNTY DEPARTMENT OF COMMUNITY DEVELOPMENT 1510-B THIRD STREET TILLAMOOK, OR 97141 Prepared by: 10300 SW GREENBURG ROAD,

More information

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers This form should be completed by following the instructions provided in Section IV of the JD Form Instructional Guidebook. SECTION

More information

Template for Sediment and Erosion Control Plan General Instructions. Section Instructions

Template for Sediment and Erosion Control Plan General Instructions. Section Instructions Template for Sediment and Erosion Control Plan General Instructions Introduction: Soil erosion and sediment deposition from farmlands can contribute to degraded surface water quality. Sediment delivery

More information

An Introduction to Field Explorations for Foundations

An Introduction to Field Explorations for Foundations An Introduction to Field Explorations for Foundations J. Paul Guyer, P.E., R.A. Paul Guyer is a registered mechanical engineer, civil engineer, fire protection engineer and architect with over 35 years

More information

September 7, 2017 (Revised November 1, 2017)

September 7, 2017 (Revised November 1, 2017) September 7, 2017 (Revised November 1, 2017) Project No. 10113.002 Environmental Advisors 2400 East Katella Avenue, Suite 800 Anaheim, California 92806 Attention: Subject: Mr. Greg McCafferty Response

More information

Louisiana Transportation Engineering Conference. Monday, February 12, 2007

Louisiana Transportation Engineering Conference. Monday, February 12, 2007 Louisiana Transportation Engineering Conference Monday, February 12, 2007 Agenda Project Background Goal of EIS Why Use GIS? What is GIS? How used on this Project Other site selection tools I-69 Corridor

More information

AM01 - System Offices. Purchase Order

AM01 - System Offices. Purchase Order Page 1 of 5 AM01 - System ffices Purchase rder P.. Date: 10/5/2016 Purchase rder Number AM01-17-P034061 SHW THIS NUMBER N ALL PACKAGES, INVICES AND SHIPPING PAPERS. V E N D R Vendor Number: 00000842 FACILITY

More information

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers This form should be completed by following the instructions provided in Section IV of the JD Form Instructional Guidebook. SECTION

More information

TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M. To: Council Members AGENDA ITEM 4B10

TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M. To: Council Members AGENDA ITEM 4B10 TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M To: Council Members AGENDA ITEM 4B10 From: Date: Subject: Staff December 14, 2018 Council Meeting Local Government Comprehensive Plan Review

More information

MVP WMS, George Schorr

MVP WMS, George Schorr APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers This form should be completed by following the instructions provided in Section IV of the JD Form Instructional Guidebook. SECTION

More information

1.1 What is Site Fingerprinting?

1.1 What is Site Fingerprinting? Site Fingerprinting Utilizing GIS/GPS Technology 1.1 What is Site Fingerprinting? Site fingerprinting is a planning tool used to design communities where protection of natural resources is the primary

More information

Temple City Unified School District A District of High Achieving Schools

Temple City Unified School District A District of High Achieving Schools Kathryn E. Perini Superintendent Temple City Unified School A of High Achieving Schools Board of Education John Pomeroy, President Vinson Bell, Vice President Kien C. Tiet, Clerk Kenneth Knollenberg, Member

More information

FINAL AESTHETICS RESOURCES STUDY PLAN. Takatz Lake Hydroelectric Project, FERC No Prepared by: City and Borough of Sitka Electric Department

FINAL AESTHETICS RESOURCES STUDY PLAN. Takatz Lake Hydroelectric Project, FERC No Prepared by: City and Borough of Sitka Electric Department FINAL AESTHETICS RESOURCES STUDY PLAN Takatz Lake Hydroelectric Project, FERC No. 13234 Prepared by: City and Borough of Sitka Electric Department 105 Jarvis St., Sitka AK, 99835 INTRODUCTION and BACKGROUND

More information

ADDENDA #1 CONTRACT # C May 3, 2013 Page 1 of 1

ADDENDA #1 CONTRACT # C May 3, 2013 Page 1 of 1 State of California Natural Resources Agency Edmund G. Brown Jr., Governor DEPARTMENT OF PARKS AND RECREATION Major General Anthony L. Jackson, USMC (Ret), Director ADDENDA #1 CONTRACT # C1247040 May 3,

More information

PLANNING COMMISSION AGENDA

PLANNING COMMISSION AGENDA COUNTY OF IMPERIAL COMMISSIONERS: Chairman: Rudy Schaffner Dennis Bergh Norm Niver Vice Chairman: Carson Kalin Sergio Cabanas Russell Roben Max Castillo Carlton A. Hargrave Ernesto Medina JIM MINNICK,

More information

NORTH DAKOTA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TEMPORARY EROSION AND SEDIMENT BEST MANAGEMENT PRACTICES

NORTH DAKOTA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TEMPORARY EROSION AND SEDIMENT BEST MANAGEMENT PRACTICES Page 1 of 5 NORTH DAKOTA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TEMPORARY EROSION AND SEDIMENT BEST MANAGEMENT PRACTICES 1. GENERAL Install, maintain and remove appropriate Temporary Best Management

More information

The Role of Mapping, GPS, and GIS in Trail Design and Construction

The Role of Mapping, GPS, and GIS in Trail Design and Construction The Role of Mapping, GPS, and GIS in Trail Design and Construction How do we normally think about MAPS and TRAILS? Idea of map as final product Trail maps Kiosk / trailhead maps Survey plat Map as Product

More information

Pierce County Department of Planning and Land Services Development Engineering Section

Pierce County Department of Planning and Land Services Development Engineering Section Page 1 of 7 Pierce County Department of Planning and Land Services Development Engineering Section PROJECT NAME: DATE: APPLICATION NO.: PCDE NO.: LANDSLIDE HAZARD AREA (LHA) GEOLOGICAL ASSESSMENT REPORT

More information

Yavapai County Flood Control District. Prescott Valley Mapping Activity Statement Activities (Zone A Floodplain Delineation and Base Map Updates)

Yavapai County Flood Control District. Prescott Valley Mapping Activity Statement Activities (Zone A Floodplain Delineation and Base Map Updates) Yavapai County Flood Control District Prescott Valley Mapping Activity Statement Activities (Zone A Floodplain Delineation and Base Map Updates) Scope of ork Prepar by: October 2014 Scope of ork TABLE

More information

Template for Sediment and Erosion Control Plan General Instructions

Template for Sediment and Erosion Control Plan General Instructions Template for Sediment and Erosion Control Plan General Instructions Introduction: Soil erosion and sediment deposition from farmlands can contribute to degraded surface water quality. Sediment delivery

More information

IC ARTICLE LAND SURVEYORS

IC ARTICLE LAND SURVEYORS IC 25-21.5 ARTICLE 21.5. LAND SURVEYORS IC 25-21.5-1 Chapter 1. Definitions IC 25-21.5-1-1 Application of chapter Sec. 1. The definitions in this chapter apply throughout this article. As added by P.L.23-1991,

More information

YELLOWSTONE RIVER FLOOD STUDY REPORT TEXT

YELLOWSTONE RIVER FLOOD STUDY REPORT TEXT YELLOWSTONE RIVER FLOOD STUDY REPORT TEXT TECHNICAL REPORT Prepared for: City of Livingston 411 East Callender Livingston, MT 59047 Prepared by: Clear Creek Hydrology, Inc. 1627 West Main Street, #294

More information

Information for File # MMJ; Trunk Highway (TH) 7 / Louisiana Ave. Interchange Project

Information for File # MMJ; Trunk Highway (TH) 7 / Louisiana Ave. Interchange Project Information for File # 2013-00531-MMJ; Trunk Highway (TH) 7 / Louisiana Ave. Interchange Project Applicant: City of St. Louis Park Corps Contact: Melissa Jenny Address: U.S. Army Corps of Engineers Attn:

More information

Circular No.32/2017/TT/BCT Specifying and guiding the implementation of a number of articles of the Law on Chemicals and Decree No.

Circular No.32/2017/TT/BCT Specifying and guiding the implementation of a number of articles of the Law on Chemicals and Decree No. Circular No.32/2017/TT/BCT Specifying and guiding the implementation of a number of articles of the Law on Chemicals and Decree No.113/2017/ND-CP Vietnam Ministry of Industry and Trade (MOIT) Translated

More information

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers This form should be completed by following the instructions provided in Section IV of the JD Form Instructional Guidebook. SECTION

More information

Discovery Data Questionnaire

Discovery Data Questionnaire Region III Discovery Data Questionnaire Thank you for taking the time to complete this Discovery Data questionnaire. It will provide important information to help FEMA better understand flood risk issues

More information

THE MINISTRY OF ENERGY AND ENERGY INDUSTRIES MINERALS DIVISION MINE DESIGN TEMPLATE OPERATOR NAME: OPERATOR ADDRESS: PHONE NUMBER: FACSIMILE:

THE MINISTRY OF ENERGY AND ENERGY INDUSTRIES MINERALS DIVISION MINE DESIGN TEMPLATE OPERATOR NAME: OPERATOR ADDRESS: PHONE NUMBER: FACSIMILE: THE MINISTRY OF ENERGY AND ENERGY INDUSTRIES MINERALS DIVISION MINE DESIGN TEMPLATE 1.0 GENERAL INFORMATION OPERATOR NAME: OPERATOR ADDRESS: PHONE NUMBER: FACSIMILE: NAME OF CONTACT: CELLULAR PHONE: EMAIL

More information

Boone County GIS has the right to inquire about and investigate the use of any requested products and deny access to anyone based on concerns relating to privacy, security, public health, public safety,

More information

SURVEYING Chapter 1 Introduction

SURVEYING Chapter 1 Introduction PHILADELPHIA UNIVERSITY Faculty of Engineering. Department of Civil Engineering. SURVEYING Chapter 1 Introduction Surveying : the art or science of measuring and representing natural and artificial features

More information

GUIDELINES FOR FILMING IN TOMBALL, TEXAS

GUIDELINES FOR FILMING IN TOMBALL, TEXAS GUIDELINES FOR FILMING IN TOMBALL, TEXAS I. PURPOSE The following guidelines are intended to protect the personal and property rights of our Tomball, Texas residents and businesses. The City Manager reserves

More information

7. New Business 7.1 New items that the Committee or District Staff would like to discuss.

7. New Business 7.1 New items that the Committee or District Staff would like to discuss. TEMPLE CITY UNIFIED SCHOOL DISTRICT CITIZENS OVERSIGHT COMMITTEE MEETING AGENDA January 22, 2015, 5:30 PM Dr. Doug Sears Learning Center, Room 1 (Posted January 21, 2015) 1. Call to Order 2. Roll Call

More information

DRAFT. PRELIMINARY LANDSLIDE MODELING for KRAMER AVENUE LANDSLIDE SITKA, ALASKA. Prepared for: Andrew Friske 210 Kramer Ave. Sitka, Alaska 99835

DRAFT. PRELIMINARY LANDSLIDE MODELING for KRAMER AVENUE LANDSLIDE SITKA, ALASKA. Prepared for: Andrew Friske 210 Kramer Ave. Sitka, Alaska 99835 PRELIMINARY LANDSLIDE MODELING for KRAMER AVENUE LANDSLIDE SITKA, ALASKA Prepared for: Andrew Friske 210 Kramer Ave. Sitka, Alaska 99835 Prepared by: Northern Geotechnical Engineering, Inc. d.b.a. Terra

More information

Request for Empanelment

Request for Empanelment Request for Empanelment (Empanelment is method/procedure/way to seek technical & financial or financial quotation from eligible firm/organization/academic institute to short list eligible contender for

More information

AQUATIC RESOURCES DELINEATION REFRESHER

AQUATIC RESOURCES DELINEATION REFRESHER AQUATIC RESOURCES DELINEATION REFRESHER James Jamie Robb Wetland Specialist, Office of the Chief 12 October 2016 US Army Corps of Engineers Ordinary High Water Mark (OHWM) How is the OHWM characterized

More information

Edward R. Sajecki Commissioner of Planning and Building. Conservation Authority Regulations and Mapping

Edward R. Sajecki Commissioner of Planning and Building. Conservation Authority Regulations and Mapping Corporate Report Clerk s Files Originator s Files EC.19.CON DATE: TO: FROM: SUBJECT: Chair and Members of Planning and Development Committee Meeting Date: April 3, 2006 Edward R. Sajecki Commissioner of

More information

DE PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE

DE PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE DE 05-142 PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE Petition for License to Construct and Maintain Electric Lines Over and Across the Public Waters of the Nashua River in the City of Nashua, New Hampshire

More information

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers This form should be completed by following the instructions provided in Section IV of the JD Form Instructional Guidebook. SECTION

More information

UPPER COSUMNES RIVER FLOOD MAPPING

UPPER COSUMNES RIVER FLOOD MAPPING UPPER COSUMNES RIVER FLOOD MAPPING DRAFT BASIC DATA NARRATIVE FLOOD INSURANCE STUDY SACRAMENTO COUTY, CALIFORNIA Community No. 060262 November 2008 Prepared By: CIVIL ENGINEERING SOLUTIONS, INC. 1325 Howe

More information

CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 01/08/18 HIGHWAY: COUNTY: 10/25/2015 ESTIMATE PAID: AWARD DATE: 11/01/2015 ESTIMATE PERIOD:

CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 01/08/18 HIGHWAY: COUNTY: 10/25/2015 ESTIMATE PAID: AWARD DATE: 11/01/2015 ESTIMATE PERIOD: 1,554,603.20 CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 01/08/18 792 73 CONTRACT ID: 629050001 PROJECT: SUP - 629050001 CONTRACT: 10154031 AWARD AMOUNT: $1,697,780.64 PROJECTED AMOUNT: $1,697,780.64 ADJ.

More information

HILLSIDE DEVELOPMENT APPLICATION CHECKLIST C (Proposal to create lots as of 9/12/2007)

HILLSIDE DEVELOPMENT APPLICATION CHECKLIST C (Proposal to create lots as of 9/12/2007) HILLSIDE DEVELOPMENT APPLICATION CHECKLIST C (Proposal to create lots as of 9/12/2007) Applicability for lands to be partitioned and/or divided, without ultimate building construction proposed. Submittal

More information

Table 1 - Infiltration Rates

Table 1 - Infiltration Rates Stantec Consulting Ltd. 100-300 Hagey Boulevard, Waterloo ON N2L 0A4 November 14, 2017 File: 161413228/10 Attention: Mr. Michael Witmer, BES, MPA, MCIP, RPP City of Guelph 1 Carden Street Guelph ON N1H

More information

New Service Provided by State Agency in Oregon: Base Flood Elevation Determinations

New Service Provided by State Agency in Oregon: Base Flood Elevation Determinations New Service Provided by State Agency in Oregon: Base Flood Elevation Determinations Jed Roberts, MS, CFM Flood Mapping Coordinator Oregon Department of Geology and Mineral Industries (DOGAMI) About DOGAMI

More information

BACKGROUND AND PROJECT DESCRIPTION

BACKGROUND AND PROJECT DESCRIPTION June 7, 2017 Applicant: Murdock Builders Location: Approximately 600 West 1200 North Prepared by: Brian Tucker Public Hearing Item: Yes Zone: A-2, RA-2 ATTACHMENTS 1. Findings for Decision. 2. Resolution

More information

THE LAW OF THE REPUBLIC OF TAJIKISTAN ON GEODESY AND CARTOGRAPHY

THE LAW OF THE REPUBLIC OF TAJIKISTAN ON GEODESY AND CARTOGRAPHY THE LAW OF THE REPUBLIC OF TAJIKISTAN ON GEODESY AND CARTOGRAPHY The given Law determines the legal basics of the activity in the sphere of geodesy and cartography, and it is aimed at creation of conditions

More information

SECTION DESCRIPTION PAGE I. BUDGET INTRODUCTION... 1 II. FISCAL YEAR 2017 BUDGET ANALYSIS... 2 III. PROPOSED OPERATING BUDGET... 3

SECTION DESCRIPTION PAGE I. BUDGET INTRODUCTION... 1 II. FISCAL YEAR 2017 BUDGET ANALYSIS... 2 III. PROPOSED OPERATING BUDGET... 3 2018 SECTION DESCRIPTION PAGE I. BUDGET INTRODUCTION... 1 II. FISCAL YEAR 2017 BUDGET ANALYSIS... 2 III. PROPOSED OPERATING BUDGET... 3 IV. GENERAL FUND 001 DESCRIPTIONS... 4 V. DEBT SERVICE FUNDS... 6

More information

DESIGN BULLETIN No. 39/2006 (Revised June 2007) June 2007 Amendment to Design Bulletin #39/2006

DESIGN BULLETIN No. 39/2006 (Revised June 2007) June 2007 Amendment to Design Bulletin #39/2006 Design Bulletin 39 - Revised Tender Submission Requirements DESIGN BULLETIN No. 39/2006 (Revised June 2007) TENDER SUBMISSION REQUIREMENTS June 2007 Amendment to Design Bulletin #39/2006 This amendment

More information

Identifying Trends in Exclusions and Feature Revisions to Promote Better Recon. Surface Water Status Monitoring Network

Identifying Trends in Exclusions and Feature Revisions to Promote Better Recon. Surface Water Status Monitoring Network Identifying Trends in Exclusions and Feature Revisions to Promote Better Recon Surface Water Status Monitoring Network Andy Woeber GIS Analyst Watershed Monitoring Section FDEP Tallahassee Surface water

More information

Sacramento River Bank Protection Project

Sacramento River Bank Protection Project 2005 - FIELD RECONNAISSANCE REPORT OF BANK EROSION SITES - SACRAMENTO RIVER FLOOD CONTROL LEVEES AND TRIBUTARIES Sacramento River Bank Protection Project Project No. 32-0530.10, Task 3 Prepared for: U.S.

More information

GIS TECHNICIAN I GIS TECHNICIAN II

GIS TECHNICIAN I GIS TECHNICIAN II GIS TECHNICIAN I GIS TECHNICIAN II CITY OF ROSEVILLE DEFINITION To perform a variety of technical office and field work duties related to the creation and maintenance of maps, tables, graphs and other

More information

DRY LAND APPROVED JURISDICTIONAL DETERMINATION FORM 1 U.S.

DRY LAND APPROVED JURISDICTIONAL DETERMINATION FORM 1 U.S. DRY LAND APPROVED JURISDICTIONAL DETERMINATION FORM 1 U.S. Army Corps of Engineers This form should be completed by following the instructions provided in Section IV of the JD Form Instructional Guidebook.

More information

Town of Taos Request for Proposal Historic Preservation GIS Geodatabase Project April 2007

Town of Taos Request for Proposal Historic Preservation GIS Geodatabase Project April 2007 Town of Taos Request for Proposal Historic Preservation GIS Geodatabase Project April 2007 1. Background The Town of Taos is requesting proposals from qualified firms or a team of firms who can develop

More information

NODE. Reconnaissance Inventory of Wetland and Sedimentation Basin Sites New and Alamo Rivers Volume lof2

NODE. Reconnaissance Inventory of Wetland and Sedimentation Basin Sites New and Alamo Rivers Volume lof2 Reconnaissance Inventory of Wetland and Sedimentation Basin Sites New and Alamo Rivers Volume lof2 Prepared for The Citizen's Congressional Task Force on the New River May 2002 NODE '(YO N D ( N CI N (

More information

Big Rivers Electric Corporation Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Impoundment Liner Assessment Report

Big Rivers Electric Corporation Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Impoundment Liner Assessment Report Big Rivers Electric Corporation Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Impoundment Liner Assessment Report CCR Surface Impoundment Information Name: Operator:

More information