The Quail Creek Dike Failure

Size: px
Start display at page:

Download "The Quail Creek Dike Failure"

Transcription

1 The Quail Creek Dike Failure (Lessons Not Learned) AEG Shlemon Specialty Conference Dam Foundation Failures and Incidents Denver, CO May 2013 Douglas D. Boyer, PE, CEG US Army Corps of Engineers Risk Management Center

2 Acknowledgement Mr. Larry Von Thun Retired Bureau of Reclamation Served as a member of the independent panel for the failure of the dike

3 Before The Quail Creek Reservoir was formed by Quail Creek Dam and Quail Creek Dike near the town of Saint George in South Western Utah near the Nevada border. This picturesque, arid, country basked in the beauty of this reservoir that stored water from Quail Creek just before it flowed into the Virgin River.

4 and After But on New Years Eve 1988 that beauty became a beast as the dike began to fail and the resulting breach outflow striped the ground bare for miles causing millions of dollars in damage. The failure date is given as Jan 1, 1989 as the breach occurred just after midnight on New Years Eve. The estimates were that the breach effects extended 89 miles downstream and that there was over $12 million in damages 1.

5 LESSONS not LEARNED This presentation is titled Lessons not Learned - in order to highlight the proximity of this Dike s design and construction in terms of both time and location to Teton Dam. The design and construction of this dike took place in the period 7-9 years after the failure of Teton Dam. The lessons relative to internal erosion, foundation preparation and foundation inspection garnered from the Teton Dam failure were well known by that time. Utah is a neighboring state to Idaho and the failure of Teton Dam and the lessons from its failure should have been ever present in their minds. But these basic lessons were not learned and failure occurred because they were not heeded. The good news was that there was no life loss, despite the complications to warning resulting from the New Year being rung in juxtaposed with sirens and other warnings going out. The other fortunate thing from a technical evaluation standpoint was that unlike so many dam failures all the evidence was not washed away with the breach. This is not because the breach was partial. As can be seen here the breach area was stripped bare to the foundation.

6 Dike Cross Section However, the failure mechanism development process was being replicated and was preserved in the adjoining potions of the dam. Further the instrumentation at the site recorded the hydrogeologic process going on in the dam and foundation during the grouting remediation and provided the necessary information to gain insight on the failure causes.

7 First Filling The potential for trouble at the site was evident upon the first filling of the reservoir. Water came pouring from the foundation as can be seen here. In a unwitting and unintentional manner, as we shall see later, the efforts to reduce this flow ultimately contributed to the failure of the dike. But we will start at the beginning with the design, move into construction and then finally into the performance, watching along the way for the lessons from Teton Dam that were not heeded.

8 St. George, Utah

9 Quail Creek Reservoir

10 Geology Sandstone with interbedded gypsiferous siltstones, gypsum, and dolomite (Moenkopi Fm) Bedding dips 5 to 25 degrees (into left abutment) Highly fractured with some open joints Soft to hard beds results in hogback appearance As indicated on this slide the rock at the foundation level at this site was primarily sandstone with interbedded gypsiferous siltstones, gypsum, and dolomite. The bedding dipped 5 to 25 degrees (into the left abutment). The rock was quite weathered and highly fractured with some very open joints. This description is a great simplification of the complexity of the geology on both the regional scale and the local scale.

11

12

13

14 Bedrock Characteristics This slide of the upper portion of the foundation within the breach erosion zone gives insight as to the condition of the weathered bedrock that formed the dam foundation.

15 Dike Statistics Height = 78 ft Crest length = 1,980 ft Crest width = 20 ft Approximately 40,000 acre-ft of storage Constructed 1984 Reservoir began filling in 1985 The dike was almost 80 feet high at its maximum section and nearly 2000 feet long. In retrospect calling this structure a dike was not appropriate, as that designation may have resulted in the designer, the inspectors, the regulators, and the contractor considering it less important and thus apply less in the way of defensive design, give less attention to the inspection and take shortcuts or make allowances that made the dam less safe. When the structure was rebuilt it was called Quail Creek South Dam.

16 Cross section This slide shows the design cross section for the dike. (go over each of the zones) The failure mechanism of piping by internal erosion was definitely recognized and understood by the time of the failure of Teton Dam in However, the means to recognize when a piping and seepage erosion failure may be possible and how to defend against its occurrence was not everywhere understood and recognized by practicing engineers and dam regulators. That situation changed considerably after the failure of Teton Dam. The lesson from that failure resulted in: Piping becoming a commonly recognized threat to dam safety by all. Greater attention to filters. The recognition of, importance of, need for and use of filters to protect the impervious core of dams became the practice. Foundation treatment to ensure that material could not be piped through joints or other discontinuities in the foundation and foundation inspections and approval for placement by a geologist and the design engine became the norm. Further, the piping mechanism, although previously understood and discussed in theory by educators and leading geotechnical engineering consultants it now became de-mystified and was able to be described recognized - understood and defended against in very practical terms. For piping by backward erosion leading to dam failure / loss of reservoir to occur, the following three simply stated conditions had to exist: There had to be a flow path from the reservoir to an unfiltered free exit. The erodibility of the material at that free exit point of the flow path combined with the seepage force (gradient) of the flow emerging at that exit point had to be great enough to remove and carry away a soil particle in order to begin the process of backward erosion. The soil being piped (or something directly above the soil) had to support a pipe or opening in the soil so that the erosion could progress back to the reservoir. Although these steps have now been extended and developed in piping / seepage erosion event tress to cover a number of subtleties and variations in piping / seepage erosion mechanisms the basic piping process described above, after the Teton Dam failure should have been commonly understood by dam designers and to allow piping to be defended against in one or more ways. This design cross section illustrates that right from the get go in design these piping lessons while generally recognized were not fully understood and defended against. So although the potential failure mode of piping through the dam was protected against, the failure mode of piping at the dam foundation contact through the cutoff trench was not. This latter potential piping failure mode is evident in the desig cross section. The Zone I (Sandy Silt and Silty Sand) was erodible and could support a pipe. The foundation key trench extended through open, highly permeable highly weathered rock. The trench was protecte on the bottom with a layer of Zone II which was a very good, plastic, non-erodible, quite impermeable clay. This clay was called the purple clay. However, the sides of the cutoff trench were neither filtered nor protected with the clay. Thus, a flow path from the reservoir into the Zone III, into the weathered rock and then through the key trench (Zone 1) with a free exit for Zone I into the weathered rock and / or into the Zone III. This would allow for tunnel formation at the dam foundation contact leading to seepage erosion, expansion of the tunnel and collapse of the dam. This mode was very similar to the actual failure mode f the dam and had other causative actions not taken place, which will be explained in detail in this presentation, this design flaw could have ultimately resulted in the failure of the dike. Now let s move to the geology of the foundation for the dam and its preparation.

17 Foundation Preparation Provisions 1-foot of foundation stripping 10-foot-deep cutoff trench through weathered rock 200-foot-long triple-line grout curtain through left abutment sandstone No dental concrete or slush grouting required except for sandstone area This slide lists the work called for relative to foundation preparation: 1-foot of foundation stripping (indicative of this arid environment and lack of vegetation and soil development) A 10-foot-deep cutoff trench through the weathered rock (the intent was not to reach un-weathered rock) just to get down a ways to what might be considered better un-weathered rock on which to place the fill. Provide a 200-foot-long triple-line grout curtain through left abutment sandstone (thought to have more open jointing based on observation of the sandstone outcrops) No dental concrete or slush grouting required except for sandstone area

18 Dam Excavation This slide shows how the foundation looked when excavation was completed. The foundation either had been approved for fill placement or was ready for approval and then fill placement. The foundation rock was not washed off and cleaned for inspection. It is reasonable to consider that the weathered rock (as seen in the previous picture) had been broken, consolidated and filled in to form an acceptable looking base on which to place earthfill. When in reality a geologic Pandora s box that had never been examined by trenching lay under the surface (it was revealed to a degree upon first filling). The lesson not well followed at Quail Creek Dike that was widely adopted after Teton Dam Failure of performing foundation approvals before fill placement, had been given short shrift here by virtue of inadequate foundation preparation and cleanup for proper inspection. Likely the consideration that this was just a dike played a role in the apparent nonchalance in the lack of serious investigation of the foundation and in the lack of preparations for approving the foundation.

19 This schematic shows what the 10 foot of excavation requirement may have actually looked like when it was carried out. The contractor, concerned about the rolling topography in profile would have tended to cut out less in the valleys with rock more susceptible to weathering and relatively more in the more erosion resistant bedrock highs in order to smooth the bedrock profile. Although this portrayal of the probable excavation as well as the above discussions on foundation cleanup and approval was not documented via measurements or records, this characterization described was made by the Investigation Board 3 after discussions with representatives of the dam owner, the dam designer and construction inspector and the contractor.

20 Now we come to the most astonishing aspect of this project with regard to the lack of understanding and guarding against piping and internal erosion. What was allowed as a convenience to the contractor during construction actually invited a piping failure to occur. The gross error in judgment made can only indirectly be called a lesson not learned from the Teton Dam failure because what was done here was not done at Teton nor anywhere else to my knowledge. As we have just seen the topographic profile consisted of a series of small hills and valleys rather than a relatively uniform decent to the valley floor that is commonly experienced. Because of these elevation irregularities along the profile, the contractor requested permission to fill the local valleys in the right side and central portion of the dam with the Zone 1 material in order to create a smoother foundation profile on which to begin placement of the various material zones in a continuous manner - cross valley as is the general practice. This slide shows this fill being placed in the intermediate valleys. The left abutment can be seen in the background. The leveling course as placed created an artificial foundation as shown in the next slide.

21 The dam design cross section in these intermediate valley sections now contained an: unprotected, unfiltered Zone 1 layer extending from upstream to downstream consisting of erodible sandy silt and silty sand with enough plasticity to hold a pipe.

22 Dike Remnant Investigations The evidence of the vulnerability of this zone to piping was readily exposed when the remaining dam on either side of the breach was excavated and trenched, as shown in this shot. The zones of the dam can readily be made out. The trenches in the slide running both parallel and transverse to the axis were within the artificial foundation and were replete with piping channels, as shown in the next photo.

23 Piping Channel in Zone 1 FOUNDATION? This oval shaped opening about 10 inches long and 2-3 inches high in the bottom portion of the picture is a shot of a typical piping channel. Some were large and some were smaller. The forensic excavation was made on either side of the breach. When the downstream face of the remnant on the left side was peeled back and exposed the face of the Zone 1 foundation there were several dozen of these channels visible all at once. Getting to see these pipes and make a close examination of them was an incredible experience after having studied, discussed and preached on their potential for development on a number of dams for several years. It is safe to say that what we were able to witness in the Quail Creek Dike forensic investigation was remarkable and instructive. It allowed strong visual verification and unequivocal documentation of the backward erosion piping process that we formulate in failure mode descriptions. Further, it allowed a definitive finding on the failure mechanism at Quail Creek Dike as opposed to the multiple failure mode scenarios and theories where the direct evidence is often washed away. Multiple theories on failure often result from the forensic evaluation of a dam failure, the evidence we saw plus the instrumentation results that we will now discuss allowed a very solid case to be made on all aspects of the failure mode.

24 Dam Performance Seepage, Piezometric Response, and Remediation Activities The performance of the dam is best evaluated by examining the interrelationship of the leakage through the dam s foundation, the attempts to reduce or shut that leakage off by grouting and the resulting response in the piezometers in the dam and foundation. It may be noted that avoidance of water loss was important for Washington County who were the dam owners.

25

26 About 5 cfs Leakage as noted previously, foundation leakage commenced during first filling with a large portion of the captured portion of the leakage emerging from the sandstone foundation of the left abutment. The foundation was in general quite porous as we saw in the earlier photograph and thus a considerable amount of water could have been entering the foundation rock, drop in elevation and flow downstream without being visible at the surface (not emerging until it reached the Virgin River).

27

28

29

30 This graph shows the measured seepage versus reservoir level during the first season of filling ( ). By the time the reservoir level had reached about 80-85% of normal maximum the dike seepage had reached 7cfs, which was excessive, well beyond expectations. Reservoir filling stopped (probably mid April 1986 and drawdown and foundation grouting commenced around mid May 1986). In addition to the seepage flowing out of the sandstone there were a few localized gusher locations just beyond the downstream toe. Due to this toe seepage two actions were taken both in direct conflict with piping lessons learned following the Teton Dam failure. The first was that a trench about 5 feet deep was dug along the toe and filled with sewer rock. This rock was clean (no fines) sized from about 1 ½ inches to 3 inches in diameter points, This trench drained to the valley thalweg. This trench provided a free exit for material to be piped into and not only that, the flow into the exit was hidden from view. It was ultimately dirty water bubbling out of the top of the sewer rock that alerted the Washington County Director that a failure was underway. Also, horizontal drains were installed at the toe of the dam towards the upstream to capture and control the foundation seepage. These drains were 4 ½ inch diameter pipes and were not filtered in any way.

31

32

33

34

35

36 The time line plot showing reservoir level and grouting period shows that most of the grouting took place with a nearly full reservoir and the evidence of grout in the rock well downstream showed up in the path scoured by the breach flow as shown in this slide. This was to be expected. What was feared but not necessarily expected was the evidence of grout throughout the dam remnant. The foundation grouting that had been done by drilling through the dam had found pathways back into the dam, fractured the dam and filled seams in the dam with grout nearly to the crest of the dam.

37 Grout in the Rock Downstream and in the Dam The time line plot showing reservoir level and grouting period shows that most of the grouting took place with a nearly full reservoir and the evidence of grout in the rock well downstream showed up in the path scoured by the breach flow as shown in this slide. Grout travel in the foundation towards the downstream would be expected as it would be pushed downstream by the seepage water. What might have been feared but not necessarily expected was the evidence of grout throughout the dam remnant. The foundation grouting that had been done by drilling through the dam had found pathways back into the dam, fractured the dam and filled seams in the dam with grout nearly to the crest of the dam.

38 Throughout this entire time period of filling and refilling and then reservoir held nearly full, the dam itself except for the upstream shell apparently remained high and dry. The 10 foot thick purple clay layer was quite impervious, tight enough such that there was probably little progression of the phreatic surface through it in the two years that the reservoir was held up. Remnant excavation showed no sign that any water ever entered the dam itself. All the seepage was through the foundation until the grouting in the foundation forced the phreatic surface in the foundation up into the artificial zone 1 foundation. The higher pressures in this material created gradients which allowed piping initiation. This process is illustrated in the following slides of the piezometric response in the foundation.

39 One piezometer (Piez. 18) was about 15 feet into the foundation rock at the toe and another (Piez. 16) was at the same elevation (2900 ft) and located about 40 feet downstream of the axis. A third (Piez. 17) was also located 40 feet downstream of the axis but at an elevation about 5 feet above the cutoff trench. The pressures in Piezometer 17, although it may have been located in just a bit of foundation bedrock rock at station 7+50 can be considered representative of the pressures (at elevation 2925 ft.) that would have been at the contact of the artificial Zone 1 and would likely have penetrated several feet within it.

40 This is illustrated in the typical cross section through the area of breach. Note the location of elevation 2925 with respect to the Zone 1 leveling fill.

41 This slide clearly shows the pattern of the development and change of pressures in the foundation rock and the artificial foundation zone as a function of the foundation grouting and the onset piping. Because of local variations in foundation conditions, amount of leakage and grouting effects and due to timing pressures could have been higher or lower in adjacent areas, however th general pattern captured by these piezometers illustrates a response that makes sense. The timing of the effects also likely varied as different areas were grouted at different times. The 2 nd grouting began to take effect in this reach in October of 1987 and the pressures in the foundation rock near the axis (Piez. 16) gradually rose for a year due to the grouting, gaining about 40 feet in head a substantial amount. The pressures at or in the Zone 1 at the foundation contact also rose but to a somewhat lesser degree because of its higher elevation (gaining 20 feet in head between June and August once the actual water level had reached elevation 2925 ). This increase in head obviously established a high gradient between this piezometric location and the toe. This is directly demonstrated by the response of piezometer 18 at the toe (recall it is under 15 feet of rock ) which shows a continual rise in pressure during the entire period up to the point of failure with the gradient between Piezometer 16 and 18 reaching a maximum of over 40 feet of head loss over a distance of 100 feet in July of The gradient between Piezometer 17 and the toe (elevation 2913 with 0 pressure head) would also have been comparably high. The head in Piez. 17 reaching a high of 2942 feet in July gives head differential of 29 feet over a distance of about 120 feet. Considering that there is a free exit in the 5 foot deep toe trench results in another 5 feet of head differential. A gradient / head lo of 34 feet over 120 feet in this silty sand, sandy silt material certainly seems great enough to initiate piping and of course we know it did. The piezometric response in the piezometers also illustrates a commonly preached insight. That is the potential development of and the initiation of piping may be indicated by either rising piezometric levels or falling levels. The response of Piezometers 16, 17 and 18 show that piping channels had probably developed in earnest back to near the axis by August of At that time the pipes provided pressure relief and the pressures at the axis began to drop while increase flow cause the pressures at Piez 18. to continue to rise. To me this was an remarkable instrumentation portrayal and documentation of a concept that is discussed in principal but rarely able to be seen.

42 This slide shows this gradient change with time in cross section. Another lesson not learned at Quail Creek Dike was that instrumentation can tell us what is going on and for an embankment dam it needs to be actively read and interpreted by personnel familiar with piping and seepage dam failure mode mechanisms.

43 December 30, 1988 Seepage measurements taken Visual observations made All is well

44 December 31, 1988

45 December 31, :00 am observation all is well

46 December 31, :00 am observation all is well 10:00 am observation all is well

47 December 31, :00 am observation all is well 10:00 am observation all is well 10:30 am observation New seepage area 200 to 300 gpm Brown-reddish coloring in water

48 Decisions Made Build a graded filter over the seepage area Channelize seepage into downstream flume for monitoring Monitor seepage Call design engineer

49 12:00 pm Seepage steady Beginning to move small amount of sand and some gravel

50 1:30 pm Filter constructed Seepage still about gpm No movement of materials through filter Slight discoloration of seepage Monitor for changes

51 4:30 pm Slight increase in seepage Extend filter to capture growing/migrating seepage area Continue monitoring

52 8:20 pm Seepage increasing significantly Not enough material on-site Sound of concern

53 Decisions Made Call design engineer Attempted to contact state personnel Contact County Emergency Management Contact contractor and material supplier

54 8:30 pm More and larger equipment on-site More material delivered to site

55 10:00 pm Equipment and materials not making progress Seepage continues to increase significantly

56 10:30 pm Equipment and personnel removed from area due to concern for safety and impending failure

57 Decisions Made Contact County Emergency Management Contact state personnel Contact police Close downstream highway Begin downstream evacuation in inundation area

58 11:00 pm Embankment starts to fail

59 Midnight Embankment breaches

60 Damage No loss of life Significant damage to property and livestock Roads and bridges washed out Some homes with minimal inundation Utility lines washed out

61 Quail Creek Dike Piping Failure Around mid-day on Dec. 31 reddish brown seepage water could be seen in and then began emerging from the toe trench and at new seepage locations. Although attempts to control and contain the increasing seepage with filter material were made, by 8:30 dam failure appeared imminent and warnings went out. As water emerged and erosion of the toe occurred the shell of the dam began collapsing into the eroded area and that material was carried away by the ever increasing discharge from the tunnel under the dam.

62 What Happened?

63 Failure Mode Based on the evidence gathered and the witnessing of the failure development this failure mode was formulated. High leakage / seepage flow occurred through the foundation of the dam. This flow entered upstream and dropped in elevation as it proceeded under the da leaving the dam cross section above the cutoff essentially unaffected. (It is conceivable that this leakage could have stabilized with time but it is also possible th it could have eroded out a high capacity tunnel through the foundation that would resulted in loss of the reservoir.) A free exit toe trench was dug at the toe of the dam and filled with coarse rock, increasing the gradient and providing a free exit for escape of soil material. This toe trench exacerbated the free exit condition that already existed. The potential failure mode existed without it and it is likely that failure would have resulted even if the toe trench had not been built. However, the likelihood of intervention and avoidance of failure would have increased without it. Grouting the foundation forced the water level up to the Zone 1 leveling material and the resulting high pressures provided a gradient through this mate that was great enough to initiate backward erosion piping in the Zone 1. Backward erosion piping continued through the Zone 1leveling material until it reached the reservoir. It appears that it took on the order of 6-9 months for pipes to go from the toe to the reservoir through this material. Seepage erosion along the pipe in the Zone 1 leveling material once it reached the reservoir rapidly expanded the tunnel and increased the discharge. upstream downstream continuity of this fill material and its relative erodibility allowed this development to occur very rapidly and preclude intervention. The dam collapsed into the eroded toe and the high discharge was able to carry away the collapsing material until a through breach occurred.

64 Lessons Not Learned Need to understand the concepts behind and piping and seepage erosion failure modes Need for appreciation of geologic conditions and their impact on the seepage design features Need for good Foundation cleanup prior to foundation approval Need for foundation filters or other foundation treatment at critical contacts of embankment and foundation Lessons not learned -- Need to understand the concepts behind and piping and seepage erosion failure modes Need for appreciation of geologic conditions and their impact on the seepage design features Need for good Foundation cleanup prior to foundation approval Need for foundation filters or other foundation treatment at critical contacts of embankment and foundation

65 Remnant cross section for illustration purposes if needed while discussing lessons

66 Lessons Not Learned Do not use grout to treat a potential piping problem Do not use drain trenches at the toe of the dam without providing appropriate filtering capacity Read, Review and Interpret Instrumentation Need to not relax criteria and diligence on the design and construction of a structure on the basis of designation (dike versus dam) Lessons not learned Do not use grout to treat a potential piping problem Do not use drain trenches at the toe of the dam without providing appropriate filtering capacity Read, Review and Interpret Instrumentation Need to not relax criteria and diligence on the design and construction of a structure on the basis of its designation (dike versus dam)

67 References Carlson, D.D. and Meyer, D.F., Flood on the Virgin River, January 1989, in Utah, Arizona, and Nevada Von Thun, J.L., The Quail Creek Dike Failure, Annual Lecture Series No 10 Foundations of Dams, New Orleans, LA, 1990 Investigation of the Cause of the Failure of Quail Creek Dike, Report of Independent Review Team (Robert James, J. Lawrence Von Thun, Alan O Neil, Richard Catanach), 1989 Final Design Report Quail Creek Dam and Dike; Rollins, Brown and Gunnell, Inc; August, 1983

68 Thank You

A Simple Procedure for Estimating Loss of Life from Dam Failure. Wayne J. Graham, P.E. 1

A Simple Procedure for Estimating Loss of Life from Dam Failure. Wayne J. Graham, P.E. 1 A Simple Procedure for Estimating Loss of Life from Dam Failure Wayne J. Graham, P.E. 1 INTRODUCTION Evaluating the consequences resulting from a dam failure is an important and integral part of any dam

More information

FRED BURR DAM FEASIBILITY STUDY

FRED BURR DAM FEASIBILITY STUDY FRED BURR DAM FEASIBILITY STUDY Fred Burr Dam Feasibility Study Purpose: Develop pre-feasibility risk reduction alternatives and recommendations for short-term operations and long-term rehabilitation.

More information

STRUCTURAL STABILITY ASSESSMENT

STRUCTURAL STABILITY ASSESSMENT STRUCTURAL STABILITY ASSESSMENT CFR 257.73(d) Bottom Ash Pond Complex Cardinal Plant Brilliant, Ohio October, 2016 Prepared for: Cardinal Operating Company Cardinal Plant Brilliant, Ohio Prepared by: Geotechnical

More information

Teton Dam Failure A Review of the Technical Factors Contributing to the Failure

Teton Dam Failure A Review of the Technical Factors Contributing to the Failure Teton Dam Failure A Review of the Technical Factors Contributing to the Failure Outline of Presentation Location, Background and Project Statistics Technical Causes of Failure to be Discussed Geology

More information

PROBLEMS AND SOLUTIONS THAT MAY EMERGE IN THE FOUNDATION AND BODY OF A HOMOGENEOUS FILL DAM ON A WEAK CLAYEY-SILTY-SANDY FORMATION ÇIKRIKÇI DAM

PROBLEMS AND SOLUTIONS THAT MAY EMERGE IN THE FOUNDATION AND BODY OF A HOMOGENEOUS FILL DAM ON A WEAK CLAYEY-SILTY-SANDY FORMATION ÇIKRIKÇI DAM PROBLEMS AND SOLUTIONS THAT MAY EMERGE IN THE FOUNDATION AND BODY OF A HOMOGENEOUS FILL DAM ON A WEAK CLAYEY-SILTY-SANDY FORMATION ÇIKRIKÇI DAM Esen Yalım KARADUMAN BAR-SU Eng. & Conc. Inc. Ankara Turkey

More information

Geosynthetics Applications and Performance Reviews Select Case Histories

Geosynthetics Applications and Performance Reviews Select Case Histories Geosynthetics Applications and Performance Reviews Select Case Histories Debora J. Miller, Ph.D., P.E.; Dean B. Durkee,, Ph.D., P.E.; Michael A. Morrison, P.E., David B. Wilson, P.E., and Kevin Smith,

More information

CCR Rule Annual Inspection Report (cont.) 2

CCR Rule Annual Inspection Report (cont.) 2 The inspection findings consisted of maintenance items and items that were not observed to be signs or potential signs of significant structural weakness. No deficiencies or disrupting conditions that

More information

International Journal of Scientific & Engineering Research, Volume 8, Issue 2, February ISSN

International Journal of Scientific & Engineering Research, Volume 8, Issue 2, February ISSN P P International Journal of Scientific & Engineering Research, Volume 8, Issue 2, February-2017 1053 Effect of Impervious Core on Seepage through Zoned Earth Dam (Case Study: Khassa Chai Dam) Abstract

More information

This report was prepared by Klohn Crippen Consultants Ltd. for Alberta Transportation Central Region under Contract No. CE053/2000.

This report was prepared by Klohn Crippen Consultants Ltd. for Alberta Transportation Central Region under Contract No. CE053/2000. Alberta Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 June 7, 2002 Mr. Melvin Mayfield, P.Eng. Project Engineer Dear Mr. Mayfield: Central Region Landslide Assessment Site

More information

HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR (c)(1)(i) (xii)

HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR (c)(1)(i) (xii) HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR 257.73(c)(1)(i) (xii) (i) Site Name and Ownership Information: Site Name: E.C. Gaston Steam Plant Site Location:

More information

HOOVER DAM: Grout Curtain Failure and Lessons Learned in Site Characterization

HOOVER DAM: Grout Curtain Failure and Lessons Learned in Site Characterization HOOVER DAM: Grout Curtain Failure and Lessons Learned in Site Characterization J. David Rogers Dams Symposium Association of Engineering Geologists Annual Meeting Las Vegas, Nevada September 22, 2005 The

More information

Rock Sizing for Waterway & Gully Chutes

Rock Sizing for Waterway & Gully Chutes Rock Sizing for Waterway & Gully Chutes WATERWAY MANAGEMENT PRACTICES Photo 1 Rock-lined waterway chute Photo 2 Rock-lined gully chute 1. Introduction A waterway chute is a stabilised section of channel

More information

Module 9 : Foundation on rocks. Content

Module 9 : Foundation on rocks. Content FOUNDATION ON ROCKS Content 9.1 INTRODUCTION 9.2 FOUNDATION TYPES ON ROCKS 9.3 BEARING CAPCITY- SHALLOW FOUNDATION 9.3.1 Ultimate bearing capacity 9.3.2 Safe bearing pressure 9.3.3 Estimation of bearing

More information

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area.

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area. Sediment Trench SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils [1] Performance of

More information

Practical aspects of dam break analysis

Practical aspects of dam break analysis Practical aspects of dam break analysis Louis C Hattingh Hattingh Anderson Associates CC Dam break analysis It is a model You need to understand what you model & have an idea of the answers that you expect

More information

PREDICTING UNDERSEEPAGE OF MASONRY DAMS Published in Proceedings of 29 th ASDSO Conference, Hollywood, FL, Sept Oct. 1, 2009.

PREDICTING UNDERSEEPAGE OF MASONRY DAMS Published in Proceedings of 29 th ASDSO Conference, Hollywood, FL, Sept Oct. 1, 2009. PREDICTING UNDERSEEPAGE OF MASONRY DAMS Published in Proceedings of 29 th ASDSO Conference, Hollywood, FL, Sept. 27 - Oct. 1, 29. Joshua M. Hendrix, EIT, US Army Corps of Engineers, Rock Island, IL Timothy

More information

CHAPTER FIVE: THE LOWER MISSISSIPPI REGION AND PLAQUEMINES PARISH

CHAPTER FIVE: THE LOWER MISSISSIPPI REGION AND PLAQUEMINES PARISH CHAPTER FIVE: THE LOWER MISSISSIPPI REGION AND PLAQUEMINES PARISH 5.1 Overview Plaquemines Parish is the area where the last portion of the Mississippi River flows out into the Gulf of Mexico (see Figures

More information

Seepage Analysis for Shurijeh Reservoir Dam Using Finite Element Method. S. Soleymani 1, A. Akhtarpur 2

Seepage Analysis for Shurijeh Reservoir Dam Using Finite Element Method. S. Soleymani 1, A. Akhtarpur 2 Seepage Analysis for Shurijeh Reservoir Dam Using Finite Element Method S. Soleymani 1, A. Akhtarpur 2 1 Group of Dam Construction, Toossab Company, P.O. Box 917751569, Mashhad City, Iran, PH (+98) 511-7684091;

More information

Amistad Dam Investigation and Oversight: Karst- Founded Dam on the USA-Mexico Border

Amistad Dam Investigation and Oversight: Karst- Founded Dam on the USA-Mexico Border Amistad Dam Investigation and Oversight: Karst- Founded Dam on the USA-Mexico Border Brook Brosi, CPG, PG USACE Lisa Nowicki Perks, PG USACE Kimberly Heenan, PE AECOM US Army Corps of Engineers BUILDING

More information

Instructor : Dr. Jehad Hamad. Chapter (7)

Instructor : Dr. Jehad Hamad. Chapter (7) Instructor : Dr. Jehad Hamad Chapter (7) 2017-2016 Soil Properties Physical Properties Mechanical Properties Gradation and Structure Compressibility Soil-Water Relationships Shear Strength Bearing Capacity

More information

Todd N. Loar, PG, CEG

Todd N. Loar, PG, CEG 1 USACE DAM RISK ASSESSMENT PROGRAM OVERVIEW AND HOW ENGINEERING GEOLOGY CONTRIBUTES TO THE LEVEL OF CONFIDENCE AND RESULTS 255 255 255 237 237 237 217 217 217 200 200 200 0 0 0 163 163 163 131 132 122

More information

TAKING THE MYSTERY OUT OF USACE S ER DRILLING IN EARTH EMBANKMENT DAMS AND LEVEES

TAKING THE MYSTERY OUT OF USACE S ER DRILLING IN EARTH EMBANKMENT DAMS AND LEVEES TAKING THE MYSTERY OUT OF USACE S ER 1110-1-1807 DRILLING IN EARTH EMBANKMENT DAMS AND LEVEES 237 237 237 217 217 217 200 200 200 80 119 27 252 174.59 1 255 255 255 0 0 0 163 163 163 131 132 122 239 65

More information

Big Rivers Electric Corporation Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Impoundment Liner Assessment Report

Big Rivers Electric Corporation Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Impoundment Liner Assessment Report Big Rivers Electric Corporation Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Impoundment Liner Assessment Report CCR Surface Impoundment Information Name: Operator:

More information

Bedrock Dewatering for Construction of Marmet and Soo Lock Projects

Bedrock Dewatering for Construction of Marmet and Soo Lock Projects Bedrock Dewatering for Construction of Marmet and Soo Lock Projects Michael Nield Engineering Geologist Dam Safety Production Center, Huntington, WV August 2012 US Army Corps of Engineers BEDROCK DEWATERING

More information

IMPORTANCE OF GEOLOGIC CHARACTERIZATION FOR LEVEE FOUNDATION AND BORROW MATERIALS AS STUDIED AT THE INDIAN GRAVES LEVEE DISTRICT, ADAMS COUNTY, IL

IMPORTANCE OF GEOLOGIC CHARACTERIZATION FOR LEVEE FOUNDATION AND BORROW MATERIALS AS STUDIED AT THE INDIAN GRAVES LEVEE DISTRICT, ADAMS COUNTY, IL IMPORTANCE OF GEOLOGIC CHARACTERIZATION FOR LEVEE FOUNDATION AND BORROW MATERIALS AS STUDIED AT THE INDIAN GRAVES LEVEE DISTRICT, ADAMS COUNTY, IL Conor Watkins Missouri University of Science and Technology

More information

R.M.HARW & ASSOCIATES LTD. GEOTECHNICAL INVESTIGATION PROPOSED BRIDGE SITE. HELAVA CREEKl MILE MACKENZIE HIGHWAY E-2510 OCTOBER 16, 1973

R.M.HARW & ASSOCIATES LTD. GEOTECHNICAL INVESTIGATION PROPOSED BRIDGE SITE. HELAVA CREEKl MILE MACKENZIE HIGHWAY E-2510 OCTOBER 16, 1973 El R.M.HARW & ASSOCIATES LTD. GEOTECHNICAL INVESTIGATION PROPOSED BRIDGE SITE HELAVA CREEKl MILE 616.4 MACKENZIE HIGHWAY E-2510 OCTOBER 16, 1973 R,M,HARDV & ASSOCIATES LTD. CONSULTING ENGINEERING & TESTING

More information

November 20, 2003 Project

November 20, 2003 Project November 20, 2003 Project 032810 1021 Main Street Winchester, MA 01890-1970 781.721.4000 781.721.4073 fax Mr. Bobby Van Cleave Geotechnical Engineer Little Rock District Federal Building, 7th Floor 700

More information

WP2.1 BREACH FORMATION LARGE SCALE EMBANKMENT FAILURE

WP2.1 BREACH FORMATION LARGE SCALE EMBANKMENT FAILURE WP2. BREACH FORMATION LARGE SCALE EMBANKMENT FAILURE Kjetil Arne Vaskinn, Sweco Gröner Norway Aslak Løvoll, Norconsult AS Norway Kaare Höeg, Norwegian Geotechnical Institute (NGI), Norway WP2. BREACH FORMATION

More information

mountain rivers fixed channel boundaries (bedrock banks and bed) high transport capacity low storage input output

mountain rivers fixed channel boundaries (bedrock banks and bed) high transport capacity low storage input output mountain rivers fixed channel boundaries (bedrock banks and bed) high transport capacity low storage input output strong interaction between streams & hillslopes Sediment Budgets for Mountain Rivers Little

More information

Slope Stability Evaluation Ground Anchor Construction Area White Point Landslide San Pedro District Los Angeles, California.

Slope Stability Evaluation Ground Anchor Construction Area White Point Landslide San Pedro District Los Angeles, California. Slope Stability Evaluation Ground Anchor Construction Area White Point Landslide San Pedro District Los Angeles, California Submitted To: Mr. Gene Edwards City of Los Angeles Department of Public Works

More information

RESERVOIR DRAWDOWN RATES/RESERVOIR DRAWDOWN TEST Iron Gate, Copco (I & II), and JC Boyle Dams

RESERVOIR DRAWDOWN RATES/RESERVOIR DRAWDOWN TEST Iron Gate, Copco (I & II), and JC Boyle Dams TECHNICAL MEMORANDUM No. 1 TO: Michael Bowen California Coastal Conservancy Geotechnical & Earthquake Engineering Consultants CC: Eric Ginney Philip Williams & Associates PREPARED BY: Paul Grant SUBJECT:

More information

MAPPING BEDROCK: Verifying Depth to Bedrock in Calumet County using Seismic Refraction

MAPPING BEDROCK: Verifying Depth to Bedrock in Calumet County using Seismic Refraction MAPPING BEDROCK: Verifying Depth to Bedrock in Calumet County using Seismic Refraction Revised December 13, 2011 Dave Hart Wisconsin Geological and Natural History Survey INTRODUCTION Seismic refraction

More information

ENGINEER S CERTIFICATION OF FAULT AREA DEMONSTRATION (40 CFR )

ENGINEER S CERTIFICATION OF FAULT AREA DEMONSTRATION (40 CFR ) PLATTE RIVER POWER AUTHORITY RAWHIDE ENERGY STATION BOTTOM ASH TRANSFER (BAT) IMPOUNDMENTS LARIMER COUNTY, CO ENGINEER S CERTIFICATION OF FAULT AREA DEMONSTRATION (40 CFR 257.62) FOR COAL COMBUSTION RESIDUALS

More information

Chapter 3 Erosion in the Las Vegas Wash

Chapter 3 Erosion in the Las Vegas Wash Chapter 3 Erosion in the Las Vegas Wash Introduction As described in Chapter 1, the Las Vegas Wash (Wash) has experienced considerable change as a result of development of the Las Vegas Valley (Valley).

More information

Yoshinori KAWAMURA, Oriental Consultants Global Co., Ltd.

Yoshinori KAWAMURA, Oriental Consultants Global Co., Ltd. Landslides along National Roads in Central Highland in Sri Lanka: Review on Current Situation and Suggestion for Further Development of Landslide Mitigation along Highways in Sri Lanka Yoshinori KAWAMURA,

More information

MONITORING SEEPAGE FLOW THROUGH CARUACHI LEFT EMBANKMENT DAM DURING INITIAL RESERVOIR FILLING

MONITORING SEEPAGE FLOW THROUGH CARUACHI LEFT EMBANKMENT DAM DURING INITIAL RESERVOIR FILLING MONITORING SEEPAGE FLOW THROUGH CARUACHI LEFT EMBANKMENT DAM DURING INITIAL RESERVOIR FILLING EMILIO MARTINEZ Senior Hydraulic Engineer, Department of Hydraulic, CVG EDELCA Hid. Macagua I, Apartado 28

More information

Construction Exits Rock pads

Construction Exits Rock pads Construction Exits Rock pads SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow [1] Clayey Soils Type 3 System Supplementary Trap Dispersive Soils [1] Minor

More information

Rock & Aggregate Drop Inlet Protection

Rock & Aggregate Drop Inlet Protection Rock & Aggregate Drop Inlet Protection SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System Supplementary Trap Dispersive Soils

More information

*** ***! " " ) * % )!( & ' % # $. 0 1 %./ +, - 7 : %8% 9 ) 7 / ( * 7 : %8% 9 < ;14. " > /' ;-,=. / ١

*** ***!   ) * % )!( & ' % # $. 0 1 %./ +, - 7 : %8% 9 ) 7 / ( * 7 : %8% 9 < ;14.  > /' ;-,=. / ١ ١ ******!" #$ % & '!( ) % * ") +,-./ % 01. 3 ( 4 56 7/4 ) 8%9 % : 7 ;14 < 8%9 % : *7./ = ;-, >/'." Soil Permeability & Seepage ٢ Soil Permeability- Definition ٣ What is Permeability? Permeability is the

More information

Monitoring Scour Critical Bridges During Floods For Local Bridge Owners. Presented by

Monitoring Scour Critical Bridges During Floods For Local Bridge Owners. Presented by Monitoring Scour Critical Bridges During Floods For Local Bridge Owners Presented by SAFETY FIRST DO NOT ENDANGER YOURSELF OR OTHERS WHILE MONITORING BRIDGES DO NOT ENTER FLOOD WATERS FLOOD WATERS INCLUDE

More information

Cattaraugus Creek: A Story of Flowing Water and the Geology of the Channel It Flows Through Presentation to West Valley Citizen Task Force 4/27/16

Cattaraugus Creek: A Story of Flowing Water and the Geology of the Channel It Flows Through Presentation to West Valley Citizen Task Force 4/27/16 Cattaraugus Creek: A Story of Flowing Water and the Geology of the Channel It Flows Through Presentation to West Valley Citizen Task Force 4/27/16 Raymond C. Vaughan, Ph.D. What happens if you drop a

More information

Modeling Great Britain s Flood Defenses. Flood Defense in Great Britain. By Dr. Yizhong Qu

Modeling Great Britain s Flood Defenses. Flood Defense in Great Britain. By Dr. Yizhong Qu Modeling Great Britain s Flood Defenses AIRCurrents Editor s note: AIR launched its Inland Flood Model for Great Britain in December 2008. The hazard module captures the physical processes of rainfall-runoff

More information

ICOLD TCDS - Technical Committe on Dam Surveillance

ICOLD TCDS - Technical Committe on Dam Surveillance Click to edit Master title ICOLD TCDS - Technical Committe on Dam Surveillance Sam Johansson TCDS Foundation SwedCold, 2017-10-09 1 Click TCDS to - edit Master title Technical Committe on Dam Surveillance

More information

UPPER COSUMNES RIVER FLOOD MAPPING

UPPER COSUMNES RIVER FLOOD MAPPING UPPER COSUMNES RIVER FLOOD MAPPING DRAFT BASIC DATA NARRATIVE FLOOD INSURANCE STUDY SACRAMENTO COUTY, CALIFORNIA Community No. 060262 November 2008 Prepared By: CIVIL ENGINEERING SOLUTIONS, INC. 1325 Howe

More information

design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards.

design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards. design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards. In addition to the field inspection, Associated Engineers, Inc.

More information

1 PROJECT BACKGROUND. August 14, Alberta Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8

1 PROJECT BACKGROUND. August 14, Alberta Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8 August 14, 2013 Alberta Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 Mr. Dennis Grace, P.Eng. Construction Engineer Dear Mr. Grace: Central Region Geohazard Assessment 2013

More information

Summary of Hydraulic and Sediment-transport. Analysis of Residual Sediment: Alternatives for the San Clemente Dam Removal/Retrofit Project,

Summary of Hydraulic and Sediment-transport. Analysis of Residual Sediment: Alternatives for the San Clemente Dam Removal/Retrofit Project, Appendix N SUMMARY OF HYDRAULIC AND SEDIMENT-TRANSPORT ANALYSIS OF RESIDUAL SEDIMENT: ALTERNATIVES FOR THE SAN CLEMENTE DAM REMOVAL/RETROFIT PROJECT, CALIFORNIA the San Clemente Dam Removal/Retrofit Project,

More information

SLOPE STABILITY EVALUATION AND ACCEPTANCE STANDARDS

SLOPE STABILITY EVALUATION AND ACCEPTANCE STANDARDS INFORMATION BULLETIN / PUBLIC - BUILDING CODE REFERENCE NO.: LABC 7006.3, 7014.1 Effective: 01-01-2017 DOCUMENT NO.: P/BC 2017-049 Revised: 12-21-2016 Previously Issued As: P/BC 2014-049 SLOPE STABILITY

More information

THE NEED FOR AN ADDITIONAL SPILLWAY AT THE SANFORD DAM BOILING SPRING LAKES, NC. Presentation for The Brunswick County Commissioners April 20, 2015

THE NEED FOR AN ADDITIONAL SPILLWAY AT THE SANFORD DAM BOILING SPRING LAKES, NC. Presentation for The Brunswick County Commissioners April 20, 2015 THE NEED FOR AN ADDITIONAL SPILLWAY AT THE SANFORD DAM BOILING SPRING LAKES, NC Presentation for The Brunswick County Commissioners April 20, 2015 The Sanford Dam Earth Dam constructed in 1961 Drainage

More information

b) EFFECTIVE STRESS (c) SEEPAGE

b) EFFECTIVE STRESS (c) SEEPAGE b) EFFECTIVE STRESS B1. A fine sand layer of 5 m thickness lies on a 5 m clay deposit. The water table is at the ground surface. Below the clay is a rock formation. Piezometers installed in the rock show

More information

Attachment B to Technical Memorandum No.2. Operations Plan of Ross Valley Detention Basins

Attachment B to Technical Memorandum No.2. Operations Plan of Ross Valley Detention Basins Attachment B to Technical Memorandum No.2 Operations Plan of Ross Valley Detention Basins Operations Plan of Ross Valley Detention Basins Stetson Engineers Inc. January 26, 2011 1.0 Introduction Achieving

More information

Central Queensland Coal Project Appendix 4b Geotechnical Assessment. Environmental Impact Statement

Central Queensland Coal Project Appendix 4b Geotechnical Assessment. Environmental Impact Statement Central Queensland Coal Project Appendix 4b Geotechnical Assessment Environmental Impact Statement GEOTECHNICAL ASSESSMENT OF OPEN CUT MINING ADJACENT TO THE BRUCE HIGHWAY, CENTRAL QUEENSLAND COAL PROJECT

More information

MINISTRY OF ENERGY AND MINES Mines and Mineral Resources. REPORT OF GEOTECHNICAL INSPECTOR (Issued pursuant to Section 15 of the Mines Act)

MINISTRY OF ENERGY AND MINES Mines and Mineral Resources. REPORT OF GEOTECHNICAL INSPECTOR (Issued pursuant to Section 15 of the Mines Act) MINISTRY OF ENERGY AND MINES Mines and Mineral Resources REPORT OF GEOTECHNICAL INSPECTOR (Issued pursuant to Section 15 of the Mines Act) Name of Property: Permit No.: M-203 General Manager: Company:

More information

Gotechnical Investigations and Sampling

Gotechnical Investigations and Sampling Gotechnical Investigations and Sampling Amit Prashant Indian Institute of Technology Gandhinagar Short Course on Geotechnical Investigations for Structural Engineering 12 14 October, 2017 1 Purpose of

More information

Lecture 14: Floods. Key Questions

Lecture 14: Floods. Key Questions Lecture 14: Floods Key Questions 1. What is an upstream flood? 2. What is a downstream flood? 3. What were the setup conditions that cause floods? 4. What is a 100-year flood? 5. How are 100-year flood

More information

CASE STUDY #9 - Brushy Fork Dam, Sugar Grove, West Virginia

CASE STUDY #9 - Brushy Fork Dam, Sugar Grove, West Virginia CASE STUDY #9 - Brushy Fork Dam, Sugar Grove, West Virginia Brushy Fork Dam is a flood control structure built by the Soil Conservation Service southeast of the city of Franklin in Pendleton County, West

More information

An Evaluation of Pavement Drainage Interstate 64, Rowan-Carter Counties

An Evaluation of Pavement Drainage Interstate 64, Rowan-Carter Counties Transportation Kentucky Transportation Center Research Report University of Kentucky Year 1984 An Evaluation of Pavement Drainage Interstate 64, Rowan-Carter Counties David L. Allen Herbert F. Southgate

More information

(Refer Slide Time: 02:10)

(Refer Slide Time: 02:10) Soil Mechanics Prof. B.V.S. Viswanathan Department of Civil Engineering Indian Institute of Technology, Bombay Lecture 24 Flow of water through soils-v Welcome to lecture five of flow of water through

More information

Floods Lecture #21 20

Floods Lecture #21 20 Floods 20 Lecture #21 What Is a Flood? Def: high discharge event along a river! Due to heavy rain or snow-melt During a flood, a river:! Erodes channel o Deeper & wider! Overflows channel o Deposits sediment

More information

APPENDIX A M&T/Llano Seco Long-Term Water Reliability Study These photos are examples of rock spurs in use throughout the United States

APPENDIX A M&T/Llano Seco Long-Term Water Reliability Study These photos are examples of rock spurs in use throughout the United States APPENDIX A M&T/Llano Seco Long-Term Water Reliability Study These photos are examples of rock spurs in use throughout the United States Glenn Colusa Irrigation District completed a Sacramento River project

More information

A.V. Watkins Dam Failure Incident November 2006 Forensic Investigations and Repair

A.V. Watkins Dam Failure Incident November 2006 Forensic Investigations and Repair A.V. Watkins Dam Failure Incident November 2006 Forensic Investigations and Repair Mark Bliss, P.E. Geotechnical Engineering Group 3 Shlemon Specialty Conference May 17, 2013 Purpose of This Presentation

More information

HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GADSDEN ASH POND 40 CFR (c)(1)(i)-(xii)

HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GADSDEN ASH POND 40 CFR (c)(1)(i)-(xii) HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GADSDEN ASH POND 40 CFR 257.73(c)(1)(i)-(xii) (i) Site Name and Ownership Information: Site Name: Site Location: Site Address: Gadsden

More information

FAMOUS FAILURES: REVISITING MAJOR DAM CATASTROPHES

FAMOUS FAILURES: REVISITING MAJOR DAM CATASTROPHES FAMOUS FAILURES: REVISITING MAJOR DAM CATASTROPHES Marla J. Barnes Editor, Hydro Review Magazine Failure of a dam is something we hope never happens. But if a failure occurs, it s important to study the

More information

FORENSIC GEOLOGY A CIVIL ACTION

FORENSIC GEOLOGY A CIVIL ACTION NAME 89.215 - FORENSIC GEOLOGY A CIVIL ACTION I. Introduction In 1982 a lawsuit was filed on behalf of eight Woburn families by Jan Schlictmann. The suit alleged that serious health effects (childhood

More information

Land subsidence due to groundwater withdrawal in Hanoi, Vietnam

Land subsidence due to groundwater withdrawal in Hanoi, Vietnam Land Subsidence (Proceedings of the Fifth International Symposium on Land Subsidence, The Hague, October 1995). 1AHS Publ. no. 234, 1995. 55 Land subsidence due to groundwater withdrawal in Hanoi, Vietnam

More information

PERENNIAL PROBLEM OF EARTHEN BUND OF WELLINGDON RESERVOIR. ANALYSIS OF CAUSES AND REMEDIAL MEASURES A CASE STUDY.

PERENNIAL PROBLEM OF EARTHEN BUND OF WELLINGDON RESERVOIR. ANALYSIS OF CAUSES AND REMEDIAL MEASURES A CASE STUDY. PERENNIAL PROBLEM OF EARTHEN BUND OF WELLINGDON RESERVOIR. ANALYSIS OF CAUSES AND REMEDIAL MEASURES A CASE STUDY. By Er. S. Muthu Parvatha Vardhini, Asst. Executive Engineer, (Designs) Water Resources

More information

Standards for Soil Erosion and Sediment Control in New Jersey May 2012

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SEDIMENT BASIN Definition A barrier, dam, excavated pit, or dugout constructed across a waterway or at other suitable locations to intercept and retain sediment. Basins created by construction

More information

Construction Exits Vibration grids

Construction Exits Vibration grids Construction Exits Vibration grids SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils [1] Type 3 System Supplementary Trap Dispersive Soils [1]

More information

Why Geomorphology for Fish Passage

Why Geomorphology for Fish Passage Channel Morphology - Stream Crossing Interactions An Overview Michael Love Michael Love & Associates mlove@h2odesigns.com (707) 476-8938 Why Geomorphology for Fish Passage 1. Understand the Scale of the

More information

NORTHUMBERLAND COUNTY, PA

NORTHUMBERLAND COUNTY, PA QUAKER RUN Stream and Wetland Restoration As-Built Completion Report and First Year Monitoring Data Coal Township NORTHUMBERLAND COUNTY, PA Upstream Before Upstream After Prepared for: COAL TOWNSHIP 805

More information

U-Shaped Sediment Traps

U-Shaped Sediment Traps U-Shaped Sediment Traps SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils [1] Type 3 System Supplementary Trap Dispersive Soils [1] Generally

More information

CASE STUDIES. Introduction

CASE STUDIES. Introduction Introduction The City of Winston-Salem faces the challenge of maintaining public infrastructure (e.g., water and sewer lines, storm drains, roads, culverts and bridges) while minimizing the potential impacts

More information

3.12 Geology and Topography Affected Environment

3.12 Geology and Topography Affected Environment 3 Affected Environment and Environmental Consequences 3.12 Geology and Topography 3.12.1 Affected Environment 3.12.1.1 Earthquakes Sterling Highway MP 45 60 Project Draft SEIS The Kenai Peninsula is predisposed

More information

Sacramento River Bank Protection Project

Sacramento River Bank Protection Project 2005 - FIELD RECONNAISSANCE REPORT OF BANK EROSION SITES - SACRAMENTO RIVER FLOOD CONTROL LEVEES AND TRIBUTARIES Sacramento River Bank Protection Project Project No. 32-0530.10, Task 3 Prepared for: U.S.

More information

3/8/17. #20 - Landslides: Mitigation and Case Histories. Questions for Thought. Questions for Thought

3/8/17. #20 - Landslides: Mitigation and Case Histories. Questions for Thought. Questions for Thought #20 - Landslides: Mitigation and Case Histories Web Exercise #3 (Volcanoes) Due Wednesday There is a 2-point penalty for every day the assignment is late. Exam 1 Scores Scores and exam key are posted Vaiont

More information

B-1. Attachment B-1. Evaluation of AdH Model Simplifications in Conowingo Reservoir Sediment Transport Modeling

B-1. Attachment B-1. Evaluation of AdH Model Simplifications in Conowingo Reservoir Sediment Transport Modeling Attachment B-1 Evaluation of AdH Model Simplifications in Conowingo Reservoir Sediment Transport Modeling 1 October 2012 Lower Susquehanna River Watershed Assessment Evaluation of AdH Model Simplifications

More information

Learning Objectives. Your goals for studying this chapter are: Understand where landslides occur. Understand the warning signs of landslides.

Learning Objectives. Your goals for studying this chapter are: Understand where landslides occur. Understand the warning signs of landslides. Learning Objectives Landslides are common problems across the country and in many parts of the world. Next to flooding, they are the most likely natural hazard you may have to deal with in your lifetime.

More information

Engineer. Engineering. Engineering. (in-ja-neer ) A person trained and skilled in any of the various branches of engineering: a civil engineer

Engineer. Engineering. Engineering. (in-ja-neer ) A person trained and skilled in any of the various branches of engineering: a civil engineer Engineer (in-ja-neer ) A person trained and skilled in any of the various branches of engineering: a civil engineer (Random House Webster s College Dictionary, 1991) CE100 Introduction to Civil Geotechnical

More information

HAW CREEK, PIKE COUNTY, MISSOURI-TRIB TO SALT RIVER ERODING STREAM THREATHENING COUNTY ROAD #107, FOURTEEN FT TALL ERODING BANK WITHIN 4 FT OF THE

HAW CREEK, PIKE COUNTY, MISSOURI-TRIB TO SALT RIVER ERODING STREAM THREATHENING COUNTY ROAD #107, FOURTEEN FT TALL ERODING BANK WITHIN 4 FT OF THE HAW CREEK, PIKE COUNTY, MISSOURI-TRIB TO SALT RIVER ERODING STREAM THREATHENING COUNTY ROAD #107, FOURTEEN FT TALL ERODING BANK WITHIN 4 FT OF THE ROAD, PROJECT CONSTRUCTED IN 1 DAY, MARCH 10, 2009 BY

More information

Advanced Hydraulics Prof. Dr. Suresh A Kartha Department of Civil Engineering Indian Institute of Technology, Guwahati

Advanced Hydraulics Prof. Dr. Suresh A Kartha Department of Civil Engineering Indian Institute of Technology, Guwahati Advanced Hydraulics Prof. Dr. Suresh A Kartha Department of Civil Engineering Indian Institute of Technology, Guwahati Module - 2 Uniform Flows Lecture - 6 Design of Channels for Uniform Flow (Refer Slide

More information

Rock Scaling Recommendations Logan Creek Drive Cut Slope

Rock Scaling Recommendations Logan Creek Drive Cut Slope Rock Scaling Recommendations Logan Creek Drive Cut Slope US 50, Milepost DO 8.47 to DO 8.61 Douglas County, Nevada January 2008 MATERIALS DIVISION STATE OF NEVADA DEPARTMENT OF TRANSPORTATION MATERIALS

More information

1. PROJECT BACKGROUND. July 18, Alberta Infrastructure & Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8

1. PROJECT BACKGROUND. July 18, Alberta Infrastructure & Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8 July 18, 2005 Alberta Infrastructure & Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 Mr. Alain Momedi, P.Eng. Project Engineer Dear Mr. Momedi: H11:04 km 11.1 Erosion along

More information

Project (Project No. US-CA-62-2) Maintenance Inspection and Reports (Subtask 14.1) Inspection Report No.2

Project (Project No. US-CA-62-2) Maintenance Inspection and Reports (Subtask 14.1) Inspection Report No.2 MEMORANDUM TO: FROM: Jim Well, Ducks Unlimited Mike Harvey, PhD, PG SUBJECT: M&T/ Llano Seco Fish Screen Project (Project No. US-CA-62-2) Maintenance Inspection and Reports (Subtask 14.1) Inspection Report

More information

See discussions, stats, and author profiles for this publication at:

See discussions, stats, and author profiles for this publication at: See discussions, stats, and author profiles for this publication at: http://www.researchgate.net/publication/261179220 Analysis of Seepage Problem effects underneath Diyala Weir using 2-D model for the

More information

Assessment of heterogeneity of an internal structure of an earth-fill embankment with 2-D resistivity survey

Assessment of heterogeneity of an internal structure of an earth-fill embankment with 2-D resistivity survey Assessment of heterogeneity of an internal structure of an earth-fill embankment with 2-D resistivity survey Peangta Satarugsa, Praiwan Uphatum, Manatchanok Buanark and Sakorn Sangchupoo Department of

More information

ENGINEERING EVALUATION OF THE STANLEY MINE ADVENTURE PARK AREA CLEAR CREEK COUNTY, COLORADO. Prepared for:

ENGINEERING EVALUATION OF THE STANLEY MINE ADVENTURE PARK AREA CLEAR CREEK COUNTY, COLORADO. Prepared for: braun Braun Consulting Engineers ENGINEERING EVALUATION OF THE STANLEY MINE ADVENTURE PARK AREA CLEAR CREEK COUNTY, COLORADO Prepared for: STANLEY MINES ADENTURE PARK 3375 W. POWERS CIRCLE LITTLETON, COLORADO

More information

Materials. Use materials meeting the following.

Materials. Use materials meeting the following. 208.01 Section 208. SOIL EROSION AND SEDIMENTATION CONTROL 208.01 Description. Install and maintain erosion and sedimentation controls to minimize soil erosion and to control sedimentation from affecting

More information

North Carolina Simplified Inundation Maps For Emergency Action Plans December 2010; revised September 2014; revised April 2015

North Carolina Simplified Inundation Maps For Emergency Action Plans December 2010; revised September 2014; revised April 2015 North Carolina Simplified Inundation Maps For Emergency Action Plans December 2010; revised September 2014; revised April 2015 INTRODUCTION Emergency Action Plans (EAPs) are critical to reducing the risks

More information

A BOOKLET ON. T Rangasamy, A R Leach and A P Cook. Facilitating safety and health research in the South African mining industry

A BOOKLET ON. T Rangasamy, A R Leach and A P Cook. Facilitating safety and health research in the South African mining industry A BOOKLET ON THE HYDRAULIC DESIGN OF COAL BARRIER PILLARS T Rangasamy, A R Leach and A P Cook Facilitating safety and health research in the South African mining industry A BOOKLET ON THE HYDRAULIC DESIGN

More information

Limited Visual Dam Safety Inspections OA Oahu Reservoir No Oahu, Hawaii

Limited Visual Dam Safety Inspections OA Oahu Reservoir No Oahu, Hawaii Limited Visual Dam Safety Inspections OA00137 Oahu Reservoir No. 155 Oahu, Hawaii Prepared by: U.S. ARMY CORPS OF ENGINEERS HONOLULU DISTRICT STATE OF HAWAII DEPARTMENT OF LAND AND NATURAL RESOURCES May

More information

December 11, 2006 File:

December 11, 2006 File: December 11, 2006 File: 15-85-38 Alberta Infrastructure and Transportation Room 301, Provincial Building 9621-96 Avenue Peace River, Alberta T8S 1T4 Attention: Mr. Ed Szmata PEACE REGION (SWAN HILLS AREA)

More information

Agenda. INDOT Office of Environmental Services. Describe Results of FHWA QAR. Landscape and Waterway Permitting Unit. Interviews Site Inspections

Agenda. INDOT Office of Environmental Services. Describe Results of FHWA QAR. Landscape and Waterway Permitting Unit. Interviews Site Inspections Nathan Saxe Administrator, Ecology and Waterway Permitting Section Back to Basics: Erosion and Sediment Control FHWA INDOT Quality Assurance Review (QAR) Results 1 Agenda INDOT Office of Environmental

More information

U.S. ARMY CORPS OF ENGINEERS

U.S. ARMY CORPS OF ENGINEERS CORPS FACTS Regulating Mississippi River Navigation Pools U.S. ARMY CORPS OF ENGINEERS BUILDING STRONG Historical Background Federal improvements in the interest of navigation on the Mississippi River

More information

Rebuilding Flood-Conscious Society

Rebuilding Flood-Conscious Society A zone where strong flood flow or river bank erosion by levee breach are anticipated, which likely to occur collapsing/washing away of house. Set up the joint councils by relative stakeholders(river managers,

More information

Advanced Geologic Exploration, Inc.

Advanced Geologic Exploration, Inc. Advanced Geologic Exploration, Inc. Scientists of the Earth PO Box 1956, Chester, CA 96020 Voice: (530) 258-4228 Fax (530) 258-4339 www.advancedgeologic.com January 23, 2009 Job No. G-081201 Terri Barber,

More information

ADDENDA #1 CONTRACT # C May 3, 2013 Page 1 of 1

ADDENDA #1 CONTRACT # C May 3, 2013 Page 1 of 1 State of California Natural Resources Agency Edmund G. Brown Jr., Governor DEPARTMENT OF PARKS AND RECREATION Major General Anthony L. Jackson, USMC (Ret), Director ADDENDA #1 CONTRACT # C1247040 May 3,

More information

Fletcher Junction Project Technical Update December 18, 2008

Fletcher Junction Project Technical Update December 18, 2008 Fletcher Junction Project Technical Update December 18, 2008 Disclaimer Warning! The business of Gold Exploration can be FUN, but it can also be hazardous to your physical, emotional, spiritual and financial

More information

KRIS wsbssm. IBHiiilll

KRIS wsbssm. IBHiiilll KRIS wsbssm IBHiiilll Digitized by the Internet Archive in 2012 with funding from University of Illinois Urbana-Champaign http://archive.org/details/engineeringaspec34ekbl STATE OF ILLINOIS HENRY HORNER,

More information

Starting at Rock Bottom

Starting at Rock Bottom Starting at Rock Bottom At rock bottom of the Brushy Creek site s geological column lies the first clue to human habitation: A smelting and heattreating furnace, and mold, carved into Bed Ked: Figure 15

More information

Emergency Action Plan (EAP) Tata Pond Dam

Emergency Action Plan (EAP) Tata Pond Dam For Official Use Only Not for Public Distribution 02/03/16 Emergency Action Plan (EAP) Tata Pond Dam State of Connecticut Dam ID: 0000 Town or City, County, Connecticut Name of Dam Owner Dam Hazard Classification

More information