MAJOR REHABILITATION REPORT: BASELINE COST ESTIMATE FOR RECOMMENDED PLAN

Size: px
Start display at page:

Download "MAJOR REHABILITATION REPORT: BASELINE COST ESTIMATE FOR RECOMMENDED PLAN"

Transcription

1 MAJOR REHABILITATION REPORT: BASELINE COST ESTIMATE FOR RECOMMENDED PLAN BOLIVAR DAM SANDY CREEK OF THE TUSCARAWAS RIVER, OHIO PREPARED BY: COST ENGINEERING SECTION, USACE, HUNTINGTON DISTRICT AUGUST 2008

2 MAJOR REHABILITATION REPORT: BASELINE COST ESTIMATE FOR RECOMMENDED PLAN BOLIVAR DAM SANDY CREEK OF THE TUSCARAWAS RIVER, OHIO AUGUST 2008

3 Bolivar Dam Major Rehabilitation Report August 2008 TABLE OF CONTENTS 1 INTRODUCTION PROJECT DESCRIPTION METHODOLOGY Cost Methodology General Direct Costs Labor-Wage Determination Equipment Rates Overtime Vendor Quotes Sales Tax Crews Quantities Indirect Costs Construction Contractor Field Strategy Prime Contractor Subcontractors Escalation Contingency PROJECT FEATURE ACCOUNTS (01) Lands and Damages (04) Dams (18) Cultural Resources (19) Buildings, Grounds, and Utilities (22) Feasibility Studies (30) Planning, Engineering, And Design (31) Supervision And Administration COST ESTIMATE REPORTS MII Cost Estimate Reports Direct Cost Cost to Prime Project Cost TAB A MII Report Appendix D: Baseline Cost Estimate for Recommended Plan i

4 Bolivar Dam Major Rehabilitation Report August 2008 LIST OF TABLES Table 1. Contractor Markups... 3 Table 2. OMB Factors... 5 Table 3. Base Year Contingencies... 6 Table 4. Non-Fully Funded & Fully Funded Project Costs... 9 Appendix D: Baseline Cost Estimate for Recommended Plan ii

5 Bolivar Dam Major Rehabilitation Report August INTRODUCTION The Bolivar Dam Major Rehabilitation project is proposed to be implemented by the Huntington District. This report describes in detail fully-funded project costs and schedule execution for all appropriate feature accounts. 2 PROJECT DESCRIPTION Bolivar Dam is located on Sandy Creek of the Tuscarawas River, miles above the mouth of the Muskingum River, located in Stark and Tuscarawas Counties of Ohio. The Dam has an impervious core with a cut-off trench and is flanked by pervious zones. The embankment has a maximum height of 87 feet, a crest length of 6300 feet, and a crest width of 25 feet. Constructed primarily for flood control, the maximum flood control pool level of elevation feet would encompass 6500 surface acres. 3 METHODOLOGY 3.1 COST METHODOLOGY General The feasibility cost estimate has been prepared to an equivalent FY08 price level. The preparation of this cost estimate is in accordance with guidelines and policies included in ER Cost Engineering Policy and General Requirements, (26 March 1993) and ER Civil Works Cost Engineering, (31 March 1994). The estimate was completed using the latest guidance from OCE concerning implementation of the Civil Works Breakdown Structure (CWBS) and Chart of Accounts. The estimate was prepared using the MCACES 2nd Generation MII Version 2.3 cost estimating software developed by Project Time and Cost, Atlanta, Georgia. The MII estimating software was used to develop the estimate by developing a construction sequence for each item of work and applying detailed line items and crews to perform the work. Crews were developed that correspond to the work being performed. Material prices were obtained through telephone solicitations with vendors, Internet suppliers, MII Cost Book, recent similar projects, and R.S. Means Cost data references Direct Costs Direct costs are based on anticipated equipment, labor, and materials necessary to construct the project as scoped. Local material quotes were obtained for most of the material items. Direct costs were calculated independent of the contractor assigned to perform the tasks. Following formulation of the direct cost, a determination was made as to whether the work would be performed by the prime contractor or a subcontractor. Appendix D: Baseline Cost Estimate for Recommended Plan Page 1

6 Bolivar Dam Major Rehabilitation Report August Labor-Wage Determination Current Tuscarawas County, Ohio, Davis-Bacon wage rates (General Decision Number: OH /04/2008 OH2) as provided by the Department of Labor, were used for all craft labor. The total labor rate was developed using the base wage, fringe benefits, FICA, FUTA, and Workman s Compensation rates for each craft. The base wage rate and fringe were entered into MII and applied accordingly. Additional labor burdens are computed by MII based on the state, which in this case is Ohio Equipment Rates The 2007 Equipment database, based on EP , Construction Equipment Ownership and Operation Expense Schedule, Region II, was used and adjusted for current fuel costs Overtime The estimator assumed that the contractor would work various overtime shifts dependent on the season and type of work being performed Vendor Quotes Vendor quotes have been acquired and documented for the material prices associated with significant features of work Sales Tax Ohio sales tax was included at a rate of 7% on material Crews Project specific crews have been developed for use in estimating the direct costs of construction for those items not estimated using quotes or historical cost information. Crew members consist of selected complements of labor classifications and equipment pieces assembled to perform specific tasks. Productivity has been assigned to each crew reflective of the expected output per unit of measure for the specific activities listed in the cost estimate Quantities The quantity takeoffs were developed and provided by the Project Development Team (PDT) members. Other associated sub-quantities were developed by the estimator. Appendix D: Baseline Cost Estimate for Recommended Plan Page 2

7 Bolivar Dam Major Rehabilitation Report August Indirect Costs Construction Contractor Field Strategy The contractor field strategy assumed that one prime contractor would perform most of the work associated with the concrete cutoff wall, impervious blanket, and downstream seepage blanket. Estimator assumed that this prime contractor would subcontract out various earthwork items, clearing and grubbing, seeding, paving, mechanical/electrical work, radial grouting, and work associated with the relief wells and instrumentation. A separate prime contractor was assumed to construct the RE office and subcontract out the fencing and paving construction. Table 1. Contractor Markups Contractor Prime Contractor Clearing/seeding subcontractor Paving subcontractor Mechanical/electrical subcontractor Radial grouting subcontractor Relief well/instrumentation subcontractor Drilling subcontractor Building Contractor Fencing subcontractor Paving subcontractor Items of Work Concrete cutoff wall, impervious blanket, downstream seepage blanket All work associated with seeding and clearing/grubbing Demolition/construction of paved roadway Gate work and hoisting equipment Radial grouting Relief wells and instrumentation Radial grouting Construction of RE office Installation of fence/swing gate Pavement of parking lot Prime Contractor Field Office Overhead (FOOH) The indirect costs for Field Office Overhead (FOOH) are included as a percentage of the direct costs. For this project, 15% has been used for FOOH on both the prime and subcontracted work. This value represents the anticipated prime contractor field overhead costs for such items as project supervision, contractor quality control, contractor field office supplies, personal protective equipment, field engineering, and other incidental field overhead costs. Appendix D: Baseline Cost Estimate for Recommended Plan Page 3

8 Bolivar Dam Major Rehabilitation Report August Home Office Overhead (HOOH) For Home Office Overhead (HOOH) expense, the cost estimate includes an allowance applied as percentage of direct cost plus field overhead. HOOH includes items such as office rental/ownership costs, utilities, office equipment ownership/maintenance, office staff (managers, accountants, clerical, etc.), insurance, and miscellaneous. In reality, the range of home office overhead can be quite broad and depends largely on the contractor s annual volume of work and the type of work that is generally performed by the contractor. In this case, a value of 6% has been used for HOOH on both the prime and subcontracted work Profit Profit has been calculated using the profit weighted guidelines as described in ER (31 March 1994) Bond Bond was included as a running percentage of 1% (own work and subcontracted work) B&O Tax B&O tax was not included Subcontractors Field Office Overhead (FOOH) All subcontractor overhead costs are set to 15% (own work and subcontracted work) of direct cost to account for such items as project supervision, contractor quality control, contractor field office supplies, personal protective equipment, field engineering, and other incidental field overhead costs. The exception is where the subcontractor has provided a quoted price including overhead. In that case, no additional markups have been included for subcontractor s overhead. Appendix D: Baseline Cost Estimate for Recommended Plan Page 4

9 Bolivar Dam Major Rehabilitation Report August Home Office Overhead (HOOH) The cost estimate includes an allowance applied as percentage of direct cost plus field overhead for HOOH. HOOH includes such items as office rental/ownership costs, utilities, office equipment ownership/maintenance, office staff (managers, accountants, clerical, etc.), insurance, and miscellaneous. In reality, the range of HOOH can be quite broad and depends largely on the contractor s annual volume of work and the type of work that is generally performed by the contractor. In this case, a value of 6% was assumed for the subcontractor (own work and subcontracted work) Profit Profit has been included as a percentage. In this case, a value of 10% was assumed for the subcontractor (own work and subcontracted work) Bond Bond was included as a running percentage of 1% (own work and subcontracted work) B&O Tax B&O tax was not included Escalation Escalation has not been included in the MII cost estimate. It is included in the Fully Funded Cost Estimate in Appendix G. The fully funded table distributes the base level cost estimate across the appropriate years according to the schedule. The yearly totals are inflated by OMB cost factors as shown in Table 2, which vary by feature account. These inflated yearly totals are summed to yield a total fully funded project cost. Table 2. OMB Factors OMB PRIOR FY 08 FY 09 FY 10 FY 11 FY 12 FY 13 FY 14 FY 15 Class I Class II Appendix D: Baseline Cost Estimate for Recommended Plan Page 5

10 Bolivar Dam Major Rehabilitation Report August Contingency A Cost and Schedule Risk Analysis (CSRA) was performed on this project to identify the 80% confidence level project cost and contingencies. A summary of these contingencies be feature account can be found in Table 3 below. Additional information concerning the risk analysis can be found in Appendix G. The CSRA identified the following factors as major impacts for both the cost and schedule: Funding The current fully-funded cost requires approximately $39M for FY12, $53M for FY13, and $59M for FY 14. If funding is capped and the project schedule is pushed out, costs will increase due to the longer construction schedule, escalation, and additional E&D & S&A. Contract Acquisition Currently only a handful of contractors are capable of performing this type of construction in the United States. If the project is not competitively bid, or if there are not many bidders, project costs will increase due to a non-competitive market. Scope Growth The current cost estimate is based on the current known conditions and quantities. Further engineering analysis may result in additional scope and increase costs. Table 3. Base Year Contingencies Feature Account % Contingency 01 Lands & Damages 12.8% 04 Dams 32.4% 18 Cultural Resource Preservation 161.1% 19 Buildings, Grounds, & Utilities 24.1% 22 Feasibility Studies 0.0% 30 Planning, Engineering, & Design 41.6% 31 Supervision & Administration 36.4% Total Project Contingency 33.0% Appendix D: Baseline Cost Estimate for Recommended Plan Page 6

11 Bolivar Dam Major Rehabilitation Report August PROJECT FEATURE ACCOUNTS 4.1 (01) LANDS AND DAMAGES The land and damages feature account includes costs for both permanent and temporary acquisitions. The Government owns all the land and no acquisitions are anticipated for this project. Only administrative costs have been included in this account for investigations. 4.2 (04) DAMS This cost account includes the construction of the Bolivar DSA measures, which includes the following: Impervious blanket, Partial cutoff wall along the upstream toe, Abutment cutoff wall, Downstream seepage blanket, Rehabilitation of relief wells, Instrumentation, and Mechanical/electrical upgrades. 4.3 (18) CULTURAL RESOURCES This cost account includes costs for archaeological investigations. 4.4 (19) BUILDINGS, GROUNDS, AND UTILITIES This cost account includes the construction of the resident engineer s building that would be required as part of the implementation of this project. 4.5 (22) FEASIBILITY STUDIES This cost account includes all costs expended for the purpose of preparing the feasibility report. 4.6 (30) PLANNING, ENGINEERING, AND DESIGN The work covered under this account includes project management, project planning, preliminary design, final design, geotechnical and HTRW investigations, hydraulic modeling, preparation of plans, preparation of specifications, engineering during construction, contract advertisement, opening of bids, and contract award. The cost for this account was estimated by the PDT and is included for each major project feature. Appendix D: Baseline Cost Estimate for Recommended Plan Page 7

12 Bolivar Dam Major Rehabilitation Report August (31) SUPERVISION AND ADMINISTRATION The work covered under this account includes contract supervision, contract administration, construction administration, technical management activities, and District office supervision and administration costs. The cost for this account has been estimated based on a historical factor of 7.5% of the total construction cost accounts. Appendix D: Baseline Cost Estimate for Recommended Plan Page 8

13 Bolivar Dam Major Rehabilitation Report August COST ESTIMATE REPORTS 5.1 MII COST ESTIMATE REPORTS Total project cost prior to fully-funding is $138,437,000 at FY08 price level. The total fully-funded project cost is $165,006,000. Table 4 below summarizes these costs broken out by feature account. Table 4. Non-Fully Funded & Fully Funded Project Costs Direct Cost Direct costs are defined as bare costs that are marked up for productivity adjustments, overtime, taxes, and/or other miscellaneous adjustments Cost to Prime Cost to prime is defined as direct costs with markups applied for PTI and any allowances such as small tools for the subcontractor work. The subcontractor markup for job office overhead (JOOH), home office overhead (HOOH), profit, bond, and excise tax and/or any miscellaneous adjustment is also included. This is in effect the cost to the performing contractor. Appendix D: Baseline Cost Estimate for Recommended Plan Page 9

14 Bolivar Dam Major Rehabilitation Report August Project Cost The project cost takes the cost to owner and then adds any escalation, contingencies, SIOH (supervision, inspection, and overhead), and/or any miscellaneous owner costs. It should be noted that escalation factors are applied in the fully funded spreadsheet calculations and not using escalation functions in the MII cost estimating software. Appendix D: Baseline Cost Estimate for Recommended Plan Page 10

15 Bolivar Dam Major Rehabilitation Report August 2008 TAB A MII REPORT Appendix D: Baseline Cost Estimate for Recommended Plan Page 11

16 MII Independent Government Estimate Title Page Estimated by CELRH-EC-TC Designed by U.S. Army Corps of Engineers Prepared by Dustin Sawyers Preparation Date 8/29/2008 Effective Date of Pricing 10/1/2007 Estimated Construction Time Days This report is not copyrighted, but the information contained herein is For Official Use Only.

17 MII Independent Government Estimate Table of Contents Library Properties... i Project Notes... ii Markup Properties...iii Direct Costs...1 Construction Costs...1 Associated Costs...17 Indirect Costs...19 Construction Costs...19 Associated Costs...19 Owner Costs...20 Construction Costs...20 Associated Costs...20 Crew Summary...21 Labor Rates...28 Equipment Rates...29

18 MII Independent Government Estimate Library Properties Page i Library Properties Designed by Design Document U.S. Army Corps of Engineers Document Date 8/29/2008 Estimated by District Huntington District CELRH-EC-TC Contact Dustin L. (304) Prepared by Budget Year 2008 Dustin Sawyers UOM System Original Direct Costs Timeline/Currency LaborCost Preparation Date 8/29/2008 EQCost Escalation Date 8/29/2008 MatlCost Eff. Pricing Date 10/1/2007 SubBidCost Estimated Duration 0 Day(s) Allowance Currency US dollars Exchange Rate Costbook CB04aEB: MII English Cost Book 2004b Final Labor Rates LaborCost1 LaborCost2 LaborCost3 LaborCost4 Labor LB04NatFD: Bolivar Dam Labor Rates Note: Davis-Bacon General Decision Number: OH /01/2006 OH2 Equipment EP07R02: MII Equipment Region 2r 2007 Note: Fuel prices updated on August 17, 2008 from for the state of Ohio. Electricity rates updated from 02 MIDEAST Fuel Shipping Rates Sales Tax 7.00 Electricity Over 0 CWT 7.31 Working Hours per Year 1,450 Gas Over 240 CWT 7.32 Labor Adjustment Factor 1.07 Diesel Off-Road Over 300 CWT 6.32 Cost of Money 5.25 Diesel On-Road Over 400 CWT 5.97 Cost of Money Discount Over 500 CWT 3.56 Tire Recap Cost Factor 1.50 Over 700 CWT 3.56 Tire Recap Wear Factor 1.80 Over 800 CWT 4.88 Tire Repair Factor 0.15 Equipment Cost Factor 1.00 Standby Depreciation Factor 0.50

19 Project Notes Print Date Wed 27 August 2008 U.S. Army Corps of Engineers Time 16:10:47 MII Independent Government Estimate Project Notes Page ii Date Author Note

20 MII Independent Government Estimate Markup Properties Page iii Markup Properties Direct Cost Markups Category Method Productivity Productivity Productivity Overtime 6-12s Overtime Overtime Days/Week Hours/Shift Shifts/Day 1st Shift 2nd Shift 3rd Shift Standard Actual Day OT Factor Working OT Percent FCCM Percent Monday 1.50 Yes (44.44) Tuesday 1.50 Yes Wednesday 1.50 Yes Thursday 1.50 Yes Friday 1.50 Yes Saturday 1.50 Yes Sunday 2.00 No Overtime 2-shifts Overtime Overtime Days/Week Hours/Shift Shifts/Day 1st Shift 2nd Shift 3rd Shift Standard Actual Day OT Factor Working OT Percent FCCM Percent Monday 1.50 Yes (69.70) Tuesday 1.50 Yes Wednesday 1.50 Yes Thursday 1.50 Yes Friday 1.50 Yes Saturday 1.50 Yes Sunday 2.00 No Supervision/Foreman TaxAdj Running % on Selected Costs LaborCost Show up time MiscDirect Running % on Selected Costs LaborCost Small Tools TaxAdj Running % on Selected Costs LaborCost Sales Tax TaxAdj Running % on Selected Costs MatlCost Contractor Markups Category Method JOOH JOOH Running % HOOH HOOH Running % Prime's Profit Profit Profit Weighted Guidelines Guideline Value Weight Percentage Risk Difficulty Size Period Invest (Contractor's) Assist (Assistance by) SubContracting Total Sub's Profit Allowance Running % B&O Tax Allowance Running % Bond Bond Running % Weather Delays Allowance Running % Contract Mods/Claims Allowance Running %

21 MII Independent Government Estimate Markup Properties Page iv Owner Markups Category Method Contingency Contingency Running %

22 MII Independent Government Estimate Direct Costs Page 1 Description Quantity UOM CrewTag Duration DirectLabor DirectEQ DirectMatl DirectSubBid DirectCost Direct Costs 58, ,549,619 18,340,613 16,890,068 9,696,743 76,407,145 58, ,549, ,340, ,890, ,696, ,137, Construction Costs 1.00 EA 58, ,549,619 18,340,613 16,890,068 9,696,743 58,137,043 58, ,542, ,338, ,871, ,444, ,756, Dams , ,542,182 18,338,078 16,871,210 9,444,743 57,756, , , Mobilization/Demobilization , ,000 USR Mob/demob 1.00 LS , ,000 (Note: Allow $800k based upon recent budgetary quote received from Inquip Associates for mob/demob at Mohawk Dam for same type of work.) Impervious Blanket 128, CY 1, , ,351 3,207, ,349, Impervious Material Fill 128, ECY 1, , ,926 3,181, ,075, USR Placement of impervious fill 188, LCY CREW-37 1, , , ,711 (Note: Assume 1.47 LCY/ECY.) USR Impervious fill, material only 276, TON ,181, ,181,536 (Note: Assume 1.4 TON/LCY (CAT Handbook Ed.31, page 28-4 for natural bed clay), 1.47 LCY/ECY, and 5% waste. Quote on 3/12/2008 by Keith B. Kimble of Kimble Clay & (330) for $10.75/TON.) USR Testing 1.00 LS ,000 (Note: Allow $50k.) ' Stripping 33, BCY ,872 52, , USR Strip topsoil & stockpile on site 33, BCY CREW ,872 52, ,722 (Note: Assumed material would be stripped and stockpiled nearby (no hauling required).) ' Topsoil 33, ECY ,476 74, , USR Spread & compact topsoil from stockpile 33, BCY CREW ,476 74, ,698 (Note: Assumed stripped material would be placed over blanket.) , , Seeding ACR ,704 13,353 25, , , , USR Seeding ACR CREW ,704 13,353 25, ,959 (Note: Referenced 2008 RS Means Heavy Construction, page 282, ) Partial Cuttoff Wall 620, SF 53, ,402,191 17,001,905 7,498,412 4,158,980 40,561,488 (Note: 141' Deep (135' deep + 5' impervious fill + 1' above impervious fill) x 4400 LF = 620,400 SF) Upstream Toe Cuttoff Wall 620, SF 53, ,402,191 17,001,905 7,498,412 4,158,980 40,561,

23 MII Independent Government Estimate Direct Costs Page 2 Description Quantity UOM CrewTag Duration DirectLabor DirectEQ DirectMatl DirectSubBid DirectCost 3.2 Excavation for 3' Wide Cuttoff Wall, Earth 68, BCY 35, ,958,219 14,598,001 1,891,024 4,036,500 27,483, Guidewall Excavation 620, SF 7, ,849 1,063, ,846, USR Excavation of guidewall 7, HR CREW-17 7, ,849 1,063, ,846,500 (Note: Hydromill excavation duration is 14,046 HR (see folder below) with two 12-HR shifts. Assumming excavation of guidewall takes place only during one 12-HR shift results in a duration of 7023 HR.) Hydromill Excavation 620, SF 14, ,236, , ,645,000 6,169, , , USR Setup time EA CREW-22 3, ,904 88, ,716 (Note: Referencing Mississinewa Final Report dated June 13, 2007, allow 10' panels with 1' of the secondary panels notching into the primary panels on each side. This results in 28' of wall for 3 panels; 4400 LF / 28' = 157 sections of 3 panels. 157 sections x 3 panels/section equals 471 panels.) USR Soil excavation w/ hydromill 620, SF CREW-22 8, ,348, , ,548,079 (Note: Referencing Mississinewa Final Report dated June 13, 2007, soil Excavation productivity is SF/HR.) USR Maintenance and repairs 620, SF CREW-23 1, , ,384 (Note: Referencing Mississinewa Final Report dated June 13, 2007, maintenance and repairs is 2,788 HR. Assume ¾ of time was due to rock and ¼ time was for soil since rock is more difficult to excavate. 2,788 HR x 25% = 697 HR; 330,806 SF of Mississinewa overburden/ 697 HR maintenance & repairs in overburden = 474 SF/HR for maintenance & repairs.) USR Standby 620, SF CREW , ,528 (Note: Referencing Mississinewa Final Report dated June 13, 2007, standby time is 1,065 HR. Assume ¾ of time was due to rock and ¼ time was for soil since rock is more difficult to excavate. 1,065 HR x 25% = 266 HR; 330,806 SF of Mississinewa overburden/ 266 HR standby in overburden = 1,242 SF/HR for standby.) , , USR Bauer BC32 hydromill with cutter and operator, rental per month MO ,645,000 3,645,000 (Note: Rental rate is $135,000/MO. Assume WK/MO x 6 DAY/WK x 10 HR/DAY = 260 HR/MO per shift; 14,046 HR / (260 HR/MO x 2 shifts) = 27 MO.) Bentonite Slurry 620, SF ,557, ,557,077 (Note: Referencing Wolf Creek Dam, the slurry mix weighs 70 LB/CF and takes approximately 22.6 LB of bentonite per CF of slurry. There is 22.6 LB/CF = LB of bentonite per CY. Assume bentonite can be recycled three times, therefore 610.2/3 = lbs of bentonite required per CY of excavation.) USR Bentonite, material only 154, CWT ,557, ,557,077 (Note: Referenced Wolf Creek estimate received in January 2007 for $8.40/CWT. Allow $10/CWT due to inflation. No quotes were obtained in time for completion of the baseline cost estimate.) Desanding Plant 68, SF , ,500 (Note: Treatment plant consists of two BE 250 and one GS 500 complete with fitting material. Total capacity is 132,000 gallon per hour. Installed power 190 HP. Voltage, Option 1 is 3 phase, 220V/60 Hz and Option 2 is 3 phase, 380V/50Hz. Weight is 14,500 kg. Rental rate is $14,500/MO. Consumption is 75 gallons per hour.) , , USR Desanding plant, rental per month MO , ,500 (Note: Rental rate is $14,500/MO. Assume WK/MO x 6 DAY/WK x 10 HR/DAY = 260 HR/MO per shift; 14,046 HR / (260 HR/MO x 2 shifts) = 27 MO.) Support Crew 68, SF 14, ,010,271 13,245,910 66, ,322, , , USR Support crew 12, HR CREW-20 12, ,622,575 13,153, ,776,112 (Note: This crew will support the desanding plant and pumping of material during the excavation operation. Hydromill excavation duration is 14,046 HR with 12,237 HR operating and 1,809 HR on standby for maintenance, repairs, and standby time.) USR Support crew (equipment on standby) 1, HR CREW-21 1, ,696 92, ,068 (Note: This crew will support the desanding plant and pumping of material during the excavation operation. Hydromill excavation duration is 14,046 HR with 12,237 HR operating and 1,809 HR on standby for maintenance, repairs, and standby time.)

24 MII Independent Government Estimate Direct Costs Page 3 Description Quantity UOM CrewTag Duration DirectLabor DirectEQ DirectMatl DirectSubBid DirectCost USR 6" perforated pipe, material only 9, LF , ,447 (Note: Estimator assumed one line would be used for bringing in the bentonite slurry and another line would be used for removing the excavated material (pump is included in support crew). Referenced 2008 RS Means Heavy Construction, page 316, for material cost. Total lenght of wall is 4400 LF x 2 lines = 8800 LF; use 9,000 LF. Setup and moving of pipe will be performed by the support crew as needed. This quantity was assumed to cover costs for broken/damaged lines that may occur during construction.) Repairs/Down-Time to Hydromill 1.00 LS , ,500 USR Material allowance for repairs 1.00 LS , ,500 (Note: Upon discussions with Bob Bowles, Nashville District, repairs to the hydromill teeth can occur often during project construction and be costly ($250,000 for Mississinewa). Allow $250,000 for repairs.) Geologist 1.00 LS , , USR Geologist 14, HR , ,832 (Note: Due to the complexity of the excavation process, estimator assumed a geologist would be on-site full-time for monitoring. Hourly rate used from Contract W D-0011, Bid Item #7, as obtained from EC-GG.) Concrete for 3' Wide Cuttoff Wall 69, CY 7, ,078,101 1,104,182 5,607, ,789, USR Concrete, material only 80, CY ,607, ,607,388 (Note: Assume 5% waste and 11.11% for extra material when the secondary panels are notched into the primary panels.) USR Tremie placement 7, HR CREW-39 7, ,078,101 1,104, ,182,284 (Note: Hydromill excavation duration is 14,046 HR with two 12-HR shifts. Assumming excavation of guidewall takes place only during one 12-HR shift results in a duration of 7,023 HR.) Excavation Spoil (Swell Factor = 1.2) 82, LCY 11, ,365,871 1,299, ,665,592 (Note: Currently, SF/HR x 3 FT wide x 24 HR/DAY results in 196 CY of material being excavated per day. These crews are assumed to work only 10 hours per day and not be on-site during the 2nd shift of work. The duration for the cutoff wall is 14,046 HR working 24-hour shifts or 7,023 HR for a 12-hour shift. Converting this to 10-hour shift results in 5,852.5 hours (7,023/12 * 10). Loading will be performed by the FE loader with the hydromill support crew. Hauling crew Dump truck w/ driver Spreading & compaction crew at spoil area (½ working/ ½ standby) Dozer w/ operator Roller w/ operator Water truck w/ driver Oiler (assist with loading/hauling and spreading/compaction)) USR Haul cuttings to spoil area 5, HR CREW-18 5, , , ,578 (Note: Loading is being performed by FE loader on hydromill support crew. Excavated material will be transported to the spoil area (remains of old quarry) located below the downstream right abutment.) USR Spread and compact cuttings at spoil area 5, HR CREW-35 5, ,110, , ,027, Verification Drilling LF , , , , USR Mob and Demob (Confined Space) 1.00 EA ,300 2,300 (Note: Referenced from drilling contract W D-0011, Bid Item #36, as obtained from EC-GG.) USR 4" Core Drilling, 4" wireline LF ,450 86,450 (Note: Referenced from drilling contract W D-0011, Bid Item #26, as obtained from EC-GG.) USR Hydraulic Pressure Testing EA ,480 25,480 (Note: Referenced from drilling contract W D-0011, Bid Item #28, as obtained from EC-GG. Cost includes pressure testing, grout, and placement of grout.) USR Inspector DAY ,250 8,250 (Note: Referenced from drilling contract W D-0011, Bid Item #9, as obtained from EC-GG. Each hole is about 50' in depth, therefore 906.4/50 = 19 holes. Assuming two holes can be completed in a 10-HR day, this equates to 19 holes / 2 holes per day = say 10 days.) * Test Section 1.00 LS ,000

25 MII Independent Government Estimate Direct Costs Page 4 Description Quantity UOM CrewTag Duration DirectLabor DirectEQ DirectMatl DirectSubBid DirectCost USR Test section allowance 1.00 LS ,000 (Note: Allow $500k. Test section will become part of permanent wall therefore labor/equipment/materials are included in folders above. This allowance is for the testing/waiting/approval by and for the contractor's work. Assume 1-month additional time required on project schedule.) Abutment Cutoff Wall 48, SF ,007 24,176 99,619 1,670,020 1,844, , , , , Clearing/Grubbing 0.50 ACR ,910 2, , , , , USR Clearing & Grubbing 0.50 ACR CREW ,910 2, , , , USR Tree allowance 0.50 ACR (Note: Allow $1,000/ACR for the cost of trees reimbursable to the Government.) Abutment Cuttoff Wall 48, SF ,440,000 1,440, USR Construction of cement/bentontite slurry wall 48, SF ,440,000 1,440,000 (Note: No details are available at this stage as to what the cement/bentonite mixture is, only that it will not be a full concrete cutoff wall. Cost referenced from drilling data received from Jim Rose on April 22, 2008 for similar contract currently being performed in Jacksonville District. Cost is $27.40/SF which includes excavation into earth/rock, cement/bentonite material and placement, and spoil of material. Use $30/SF.) , , , , Seeding 0.50 ACR ,391 1, , , , , , USR Seeding 0.50 ACR CREW ,391 1, ,469 (Note: Referenced 2008 RS Means Heavy Construction, page 282, ) Remove and Replace Culvert, 12" CMP LF , USR Trench excavation with backhoe 6.00 BCY CREW USR Demo 12" CMP pipe LF CREW USR Bank run sand, material only 2.20 TON (Note: Quote on 3/12/2008 by Keith B. Kimble of Kimble Clay & (330) for $9.00/TON.) USR Place & compact sand 1.50 ECY CREW USR 12" BCCMP pipe LF CREW ,166 (Note: Referenced 2008 RS Means Heavy Construction, page 310, ) USR Backfill & compaction 4.10 LCY CREW USR Haul material to spoil, 12 CY truck, 2 mile round trip 3.20 LCY CREW , , , Remove and Replace Flag Pole 1.00 EA , , ,

26 MII Independent Government Estimate Direct Costs Page 5 Description Quantity UOM CrewTag Duration DirectLabor DirectEQ DirectMatl DirectSubBid DirectCost USR Demo flagpole 1.00 EA CREW , , USR Flagpole foundation, 40' to 50' high, includes excavation & concrete 1.00 EA CREW , ,562 (Note: Referenced 2008 RS Means Building Construction, page 334, ) , , USR Flagpoles, steel, direct imbedded installation, 50' high 1.00 EA CREW , ,225 (Note: Referenced 2008 RS Means Building Construction, page 334, ) , Remove and Replace Monument ,000 USR Remove and replace monuments 1.00 LS ,000 (Note: Allow $10k.) Remove and Replace Chain Link Fence LF , , , USR Remove existing fence, includes hauling LF CREW USR Chain link fence, industrial, aluminized steel, in concrete, 6 ga. wire, 2-1/2" 10' OC, 8' high, includes excavation (Note: Referenced 2008 RS Means Heavy Construction, page 269, ) LF CREW , , , , , Remove and Replace Light Pole 1.00 EA , , , USR Demo lightpole 1.00 EA CREW , , USR Light pole, aluminum, 40' high w/ 1 bracket arm 1.00 EA CREW , ,502 (Note: Referenced 2008 RS Means Heavy Construction, page 197, /3800.) , , USR Lightpole foundation, 40' to 50' high, includes excavation & concrete 1.00 EA CREW , ,562 (Note: Referenced 2008 RS Means Building Construction, page 334, ) Demolish Roadway 1, SY ,076 9,651 18, , USR Demo bituminous pavement, 4" to 6" thick (includes loading and hauling) 1, SY CREW ,076 9, ,727 (Note: Referenced 2008 RS Means Heavy Construction, page 23, Allow 40 hours.) USR Disposal fees TON , ,864 (Note: Quote on 4/8/08 from Countywide Recycling and Disposal Facility for Construction & Demolition material (C&D) material is $30/TON with an additional $1.06/TON for EPA fees. Assume 6" thick asphalt and 110 LB/SY per inch thickness.) Roadway Replacement 1, SY ,453 8,743 64,780 8,600 95, Prepare & Roll Subbase 1, SY ,505 1, , USR Prepare and roll sub-base 1, SY CREW ,505 1, ,595 (Note: Allow 10 HR.) Filter Fabric 1, SY , , ,368

27 MII Independent Government Estimate Direct Costs Page 6 Description Quantity UOM CrewTag Duration DirectLabor DirectEQ DirectMatl DirectSubBid DirectCost USR Filter fabric installation 1, SY CREW , ,667 (Note: Allow 10 HR.) USR Filter fabric, Mirafi HP 665, material only 1, SY , ,701 (Note: Quote referenced from recent project at Minersville, OH. Quote on 12/14/2006 by Glenn Dupilka of JMD (412) for $2.95/SY. Assume 5% overlap.) " Aggregate Class I ECY ,482 3,364 11, , USR 8" aggregate, Class I, material only TON , ,714 (Note: Assume 1.5 TON/LCY and 1.14 LCY/ECY. Quote on 3/12/2008 by Keith B. Kimble of Kimble Clay & (330) for $16.75/TON.) USR Placement of aggregate CY CREW ,482 3, ,846 (Note: Allow 10 HR.) /2" Intermediate Course CY ,820 1,618 13, , USR Asphaltic concrete pavement, 2-1/2" intermediate course TON CREW ,820 1,618 13, ,730 (Note: Cost referenced from 2008 RS Means Heavy Construction, page 261, Assume 2 TON/CY. Allow 5 HR.) /2" Top Course CY ,820 1,618 14, , USR Asphaltic concrete pavement, 2-1/2" top course TON CREW ,820 1,618 14, ,497 (Note: Cost referenced from 2008 RS Means Heavy Construction, page 261, Assume 2 TON/CY. Allow 5 HR.) Tack Coat 1, SY , , USR Tack coat, 0.10 gal per SY 1, SY CREW , ,945 (Note: Cost referenced from 2008 RS Means Heavy Construction, page 254, ) Prime Coat 1, SY , , USR Prime coat, 4 oz per SY 1, SY CREW , ,930 (Note: Cost referenced from 2008 RS Means Heavy Construction, page 254, ) Guardrail (remove and replace) LF , ,162 8,600 27, USR Remove Guardrail LF ,600 8, USR Install guardrail LF CREW , , ,351 (Note: Referenced 2008 RS Means Heavy Construction, page 340, Allow 10 HR.) Storm Drain, 4" PVC LF

28 MII Independent Government Estimate Direct Costs Page 7 Description Quantity UOM CrewTag Duration DirectLabor DirectEQ DirectMatl DirectSubBid DirectCost USR Trench excavation with backhoe 3.00 BCY CREW USR Place & compact sand 1.00 ECY CREW USR Bank run sand, material only 1.10 TON (Note: Quote on 3/12/2008 by Keith B. Kimble of Kimble Clay & (330) for $9.00/TON.) USR 4" SDR 35 PVC Pipe LF CREW (Note: Referenced 2008 RS Means Heavy Construction, page 308, ) USR Backfill & compaction 3.00 LCY CREW USR Haul material to spoil, 12 CY truck, 2 mile round trip 1.00 LCY CREW Temporary Relocate/ Replace Sewer Line, 4" PVC LF , , Remove Existing Sewer Line, 4" PVC LF USR Trench excavation with backhoe 3.00 BCY CREW USR Demo and remove existing pipe LF CREW USR Backfill & compaction 4.00 LCY CREW Install Temporary Sewer Line, 4" PVC LF USR Trench excavation with backhoe 3.00 BCY CREW USR Place & compact sand 1.00 ECY CREW USR Bank run sand, material only 1.10 TON (Note: Quote on 3/12/2008 by Keith B. Kimble of Kimble Clay & (330) for $9.00/TON.) USR 4" SDR 35 PVC Pipe LF CREW (Note: Referenced 2008 RS Means Heavy Construction, page 308, ) USR Backfill & compaction 3.00 LCY CREW USR Haul material to spoil, 12 CY truck, 2 mile round trip 1.00 LCY CREW Remove Temporary Sewer Line, 4" PVC LF USR Trench excavation with backhoe 3.00 BCY CREW USR Demo and remove existing pipe LF CREW

29 MII Independent Government Estimate Direct Costs Page 8 Description Quantity UOM CrewTag Duration DirectLabor DirectEQ DirectMatl DirectSubBid DirectCost USR Backfill & compaction 4.00 LCY CREW Install Permanent Sewer Line, 4" PVC LF USR Trench excavation with backhoe 3.00 BCY CREW USR Place & compact sand 1.00 ECY CREW USR Bank run sand, material only 1.10 TON (Note: Quote on 3/12/2008 by Keith B. Kimble of Kimble Clay & (330) for $9.00/TON.) USR 4" SDR 35 PVC Pipe LF CREW (Note: Referenced 2008 RS Means Heavy Construction, page 308, ) USR Backfill & compaction 3.00 LCY CREW USR Haul material to spoil, 12 CY truck, 2 mile round trip 1.00 LCY CREW Temporary Relocate/ Replace Water Line, 1" PE LF , , Remove Existing Water Line, 1" PE LF USR Trench excavation with backhoe, expose pipe 3.00 BCY CREW USR Demo and remove existing pipe LF CREW USR Backfill & compaction 4.00 LCY CREW Install Temporary Water Line, 1" PE LF USR Trench excavation with backhoe, expose pipe 3.00 BCY CREW USR Place & compact sand 1.00 ECY CREW USR Bank run sand, material only 1.10 TON (Note: Quote on 3/12/2008 by Keith B. Kimble of Kimble Clay & (330) for $9.00/TON.) USR 1" polyethylene pipe, C901, 160 PSI LF CREW (Note: Referenced 2008 RS Means Heavy Construction, page 298, ) USR Haul material to spoil, 12 CY truck, 2 mile round trip 1.00 LCY CREW USR Backfill & compaction 3.00 LCY CREW

30 MII Independent Government Estimate Direct Costs Page 9 Description Quantity UOM CrewTag Duration DirectLabor DirectEQ DirectMatl DirectSubBid DirectCost Remove Temporary Water Line, 1" PE LF USR Trench excavation with backhoe, expose pipe 3.00 BCY CREW USR Demo and remove existing pipe LF CREW USR Backfill & compaction 4.00 LCY CREW Install Permanent Water Line, 1" PE LF USR Trench excavation with backhoe 3.00 BCY CREW USR Place & compact sand 1.00 ECY CREW USR Bank run sand, material only 1.10 TON (Note: Quote on 3/12/2008 by Keith B. Kimble of Kimble Clay & (330) for $9.00/TON.) USR 1" polyethylene pipe, C901, 160 PSI LF CREW (Note: Referenced 2008 RS Means Heavy Construction, page 298, ) USR Backfill & compaction 3.00 LCY CREW USR Haul material to spoil, 12 CY truck, 2 mile round trip 1.00 LCY CREW Temporary Relocate/ Replace UG Electric to Office LF , , Remove Existing UG Electric to Office LF USR Trench excavation with backhoe 3.00 BCY CREW USR Backfill & compaction 4.00 LCY CREW USR Demo and remove existing pipe LF CREW USR Removal current connections 1.00 HR CREW (Note: Allow 1 hour.) Install Temporary UG Electric to Office LF USR Trench excavation with backhoe 3.00 BCY CREW USR Place & compact sand 1.00 ECY CREW USR Bank run sand, material only 1.10 TON (Note: Quote on 3/12/2008 by Keith B. Kimble of Kimble Clay & (330) for $9.00/TON.)

31 MII Independent Government Estimate Direct Costs Page 10 Description Quantity UOM CrewTag Duration DirectLabor DirectEQ DirectMatl DirectSubBid DirectCost USR 2" PVC Conduit, 2" diameter LF CREW (Note: Referenced 2008 RS Means Heavy Construction, page 329, ) USR Underground cable, #6, type USE LF CREW (Note: Referenced 2006 MII English Cost Book, Source Tag ) USR Backfill & compaction 3.00 LCY CREW USR Testing 1.00 HR CREW (Note: Allow 1 hour.) Remove Temporary UG Electric to Office LF USR Trench excavation with backhoe 3.00 BCY CREW USR Backfill & compaction 4.00 LCY CREW USR Demo and remove existing pipe LF CREW USR Removal current connections 1.00 HR CREW (Note: Allow 1 hour.) Install Permanent UG Electric to Office LF USR Trench excavation with backhoe 3.00 BCY CREW USR Place & compact sand 1.00 ECY CREW USR Bank run sand, material only 1.10 TON (Note: Quote on 3/12/2008 by Keith B. Kimble of Kimble Clay & (330) for $9.00/TON.) USR 2" RGS Conduit, 2" diameter LF CREW (Note: Referenced 2008 RS Means Heavy Construction, page 329, ) USR Backfill & compaction 3.00 LCY CREW USR Underground cable, #6, type USE LF CREW (Note: Referenced 2006 MII English Cost Book, Source Tag ) USR Testing 1.00 HR CREW (Note: Allow 1 hour.) Temporary Relocate/ Replace UG Telephone to Intake LF , , Remove Existing UG Telephone to Intake LF

Print Date Wed 16 January 2013 U.S. Army Corps of Engineers Time 07:48:43. Cost Estimate Report

Print Date Wed 16 January 2013 U.S. Army Corps of Engineers Time 07:48:43. Cost Estimate Report Cost Estimate Report Title Page Plan J. without trails Springfield, Missouri Flood Risk Management Feasibility Study Class 4 Cost Estimate P2 Number 354082 Estimated by Designed by Prepared by Cost Engineering

More information

APPENDIX C COST ENGINEERING REPORT DETROIT BEACH, SECTION 205 FRENCHTOWN, MICHIGAN

APPENDIX C COST ENGINEERING REPORT DETROIT BEACH, SECTION 205 FRENCHTOWN, MICHIGAN APPENDIX C COST ENGINEERING REPORT DETROIT BEACH, SECTION 205 FRENCHTOWN, MICHIGAN C-1 APPENDIX C COST ENGINEERING REPORT DETROIT BEACH, SECTION 205 FRENCHTOWN, MICHIGAN TABLE OF CONTENTS 1. Introduction

More information

U.S. Army Corps of Engineers - Buffalo District Project : Blanchard River Flood Control Project Cost Estimate

U.S. Army Corps of Engineers - Buffalo District Project : Blanchard River Flood Control Project Cost Estimate Print Date Tue 29 December 2015 Eff. Date 10/1/2015 U.S. Army Corps of Engineers - Buffalo District Project : Blanchard River Flood Control Project Cost Estimate Time 13:18:11 Title Page Estimated by AECOM

More information

Appendix C Benchmarking Cost Estimates

Appendix C Benchmarking Cost Estimates REPORT Appendix C Benchmarking Cost Estimates C-1 Table C-1 Permits, Notifications & Location Services Notes: Costs associated with delays in construction have not been included in this estimate OneCall

More information

Materials. Use materials meeting the following.

Materials. Use materials meeting the following. 208.01 Section 208. SOIL EROSION AND SEDIMENTATION CONTROL 208.01 Description. Install and maintain erosion and sedimentation controls to minimize soil erosion and to control sedimentation from affecting

More information

Designed by. Preparation Date 6/22/2018 Effective Date of Pricing 3/1/2019 Estimated Construction Time 400 Days

Designed by. Preparation Date 6/22/2018 Effective Date of Pricing 3/1/2019 Estimated Construction Time 400 Days Independent Government Estimate Updated 6/22/18 Title Page Estimated by NAVFAC Cost Designed by Prepared by NAVFAC Cost Preparation Date 6/22/2018 Effective Date of Pricing 3/1/2019 Estimated Construction

More information

DESIGN BULLETIN No. 39/2006 (Revised June 2007) June 2007 Amendment to Design Bulletin #39/2006

DESIGN BULLETIN No. 39/2006 (Revised June 2007) June 2007 Amendment to Design Bulletin #39/2006 Design Bulletin 39 - Revised Tender Submission Requirements DESIGN BULLETIN No. 39/2006 (Revised June 2007) TENDER SUBMISSION REQUIREMENTS June 2007 Amendment to Design Bulletin #39/2006 This amendment

More information

20217 CLEAR STONE TON $14.20 $5, $ $ $ %

20217 CLEAR STONE TON $14.20 $5, $ $ $ % ACCOUNT NO: 10332-84-174-84300: 54250(91223) ACCOUNT NO: 10529-403-172: 54440 (91226) ACCOUNT NO: 10463-51-130: 54250 (91223) ACCOUNT NO: 10332-84-174-84300: 54250 (91223) 20217 CLEAR STONE 375.00 TON

More information

TAKING THE MYSTERY OUT OF USACE S ER DRILLING IN EARTH EMBANKMENT DAMS AND LEVEES

TAKING THE MYSTERY OUT OF USACE S ER DRILLING IN EARTH EMBANKMENT DAMS AND LEVEES TAKING THE MYSTERY OUT OF USACE S ER 1110-1-1807 DRILLING IN EARTH EMBANKMENT DAMS AND LEVEES 237 237 237 217 217 217 200 200 200 80 119 27 252 174.59 1 255 255 255 0 0 0 163 163 163 131 132 122 239 65

More information

2015 Costs and Returns Estimate Eastern Idaho: Alfalfa Hay Establishment in Grain Stubble Paul E. Patterson Background and Assumptions

2015 Costs and Returns Estimate Eastern Idaho: Alfalfa Hay Establishment in Grain Stubble Paul E. Patterson Background and Assumptions 2015 Costs and Returns Estimate Eastern Idaho: Alfalfa Hay Establishment in Grain Stubble Paul E. Patterson Background and Assumptions Eastern Idaho The University of Idaho s costs and returns estimates

More information

Bob Rettig Construction and Consulting

Bob Rettig Construction and Consulting 1 Client: Sample A, Code Home: (714) 345-4265 Property: Main St. Anytown, Ca. 90000 Operator Info: Operator: JOE Estimator: 2 Company: Bob Rettig Construction Consulting Business: 30262 Crown Valley Parkway,

More information

Background and Assumptions

Background and Assumptions 2017 Costs and Returns Estimate Southcentral Idaho: Magic Valley Alfalfa Hay Establishment with Oats Ben Eborn Magic Valley Background and Assumptions The University of Idaho s costs and returns estimates

More information

20217 CLEAR STONE TON $14.20 $5, $ $ $ %

20217 CLEAR STONE TON $14.20 $5, $ $ $ % ACCOUNT NO: 10332-84-174-84300: 54250(91223) ACCOUNT NO: 10529-403-172: 54440 (91226) ACCOUNT NO: 10463-51-130: 54250 (91223) ACCOUNT NO: 10332-84-174-84300: 54250 (91223) 20217 CLEAR STONE 375.00 TON

More information

Franklin County Engineer's Office - Highway Design Dublin Road And Fishinger Road Improvements Rebid Bid Tabulation

Franklin County Engineer's Office - Highway Design Dublin Road And Fishinger Road Improvements Rebid Bid Tabulation 2/20/2015 Page 1 of 16 Strawser Paving Co., Inc. Double Z Construction Co Decker Construction Company Shelly & Sands, Inc. 1595 Frank Road 2550 Harrison Road 3040 McKinley Avenue P.O.Box 2469 Columbus,

More information

Paul Patterson Background and Assumptions

Paul Patterson Background and Assumptions 2015 Costs and Returns Estimate Southcentral Idaho: Magic Valley Alfalfa Hay Production Paul Patterson Background and Assumptions Magic Valley The University of Idaho s costs and returns estimates are

More information

Background and Assumptions

Background and Assumptions 2017 Costs and Returns Estimate Southcentral Idaho: Magic Valley Alfalfa Hay Production Ben Eborn Magic Valley Background and Assumptions The University of Idaho s costs and returns estimates are based

More information

FOR PROJECTS INITIATED AFTER NOVEMBER 1, 2008 ITEM 716 EMBANKMENT EARTH OUTLET SEDIMENT TRAP

FOR PROJECTS INITIATED AFTER NOVEMBER 1, 2008 ITEM 716 EMBANKMENT EARTH OUTLET SEDIMENT TRAP AFTER NOVEMBER 1, 2008 ITEM 716 EMBANKMENT EARTH OUTLET SEDIMENT TRAP 716.1 Description. This work shall consist of furnishing, installing, maintaining, and removing temporary erosion protection and sediment

More information

Average Bid Prices for Awarded Contracts Page 1 State Aid Projects Not Included 1/1/2016 to 12/31/2016

Average Bid Prices for Awarded Contracts Page 1 State Aid Projects Not Included 1/1/2016 to 12/31/2016 Average Bid Prices for Awarded s Page 1 Number Description Units Quantity Dollars (000S) Average Price 2011 2011601/00003 CONSTRUCTION SURVEYING LS 28.00 1241.85 $44,351.96 28 2011 2011601/00010 VIBRATION

More information

Saganashkee Slough - McMahon Woods Section 506 Great Lakes Fishery & Ecosystem Restoration Study

Saganashkee Slough - McMahon Woods Section 506 Great Lakes Fishery & Ecosystem Restoration Study 2015 Saganashkee Slough - McMahon Woods Section 506 Great Lakes Fishery & Ecosystem Restoration Study Appendix B Civil Design USACE Chicago District August 2015 TABLE OF CONTENTS INTRODUCTION... 3 General...

More information

Background and Assumptions

Background and Assumptions 2017 Costs and Returns Estimate Eastern Idaho: Lower Rainfall Dryland Feed Barley Ben Eborn and Terrell Sorensen Eastern Idaho Background and Assumptions The University of Idaho s costs and returns estimates

More information

DOCUMENTATION WORKBOOK FY 2018

DOCUMENTATION WORKBOOK FY 2018 DOCUMENTATION WORKBOOK SPECIFIC TASK TRAINING PROGRAM Conducted by the ILLINOIS CENTER FOR TRANSPORTATION (ICT) AND IDOT BUREAU OF CONSTRUCTION FY 2018 WORKBOOK TABLE OF CONTENTS Workbook Page 1... Maximum

More information

Amistad Dam Investigation and Oversight: Karst- Founded Dam on the USA-Mexico Border

Amistad Dam Investigation and Oversight: Karst- Founded Dam on the USA-Mexico Border Amistad Dam Investigation and Oversight: Karst- Founded Dam on the USA-Mexico Border Brook Brosi, CPG, PG USACE Lisa Nowicki Perks, PG USACE Kimberly Heenan, PE AECOM US Army Corps of Engineers BUILDING

More information

Rock & Aggregate Drop Inlet Protection

Rock & Aggregate Drop Inlet Protection Rock & Aggregate Drop Inlet Protection SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System Supplementary Trap Dispersive Soils

More information

12"CMP DIA. ELEV. PVC CI DI CMP VCP RCP RCAP LRCP LCPP STA. LA LB BM-2 ROW PI POT LF TH PVC

12CMP DIA. ELEV. PVC CI DI CMP VCP RCP RCAP LRCP LCPP STA. LA LB BM-2 ROW PI POT LF TH PVC PLANS FOR X-REFS: FILE PATH: Z:\WEST BRANCH 3682 MAIN STREET SIDEWALK IMPROVEMENTS - PHASE 3\DRAWINGS\_PRODUCTION DRAWINGS\TITLE & INDEX PLOTTED: Thursday, May 26, 216 4:7:42 PM MAIN STREET SIDEWALK PHASE

More information

Delaware Bay Dikes Repair and Prevention Project Preliminary Design for New Castle Dikes

Delaware Bay Dikes Repair and Prevention Project Preliminary Design for New Castle Dikes City of New Castle Presentation Delaware Bay Dikes Repair and Prevention Project Preliminary Design for New Castle Dikes New Castle Conservation District DNREC August 22, 2012 Agenda Project Background

More information

SECTION DESCRIPTION PAGE I. BUDGET INTRODUCTION... 1 II. FISCAL YEAR 2017 BUDGET ANALYSIS... 2 III. PROPOSED OPERATING BUDGET... 4

SECTION DESCRIPTION PAGE I. BUDGET INTRODUCTION... 1 II. FISCAL YEAR 2017 BUDGET ANALYSIS... 2 III. PROPOSED OPERATING BUDGET... 4 2018 SECTION DESCRIPTION PAGE I. BUDGET INTRODUCTION... 1 II. FISCAL YEAR 2017 BUDGET ANALYSIS... 2 III. PROPOSED OPERATING BUDGET... 4 IV. GENERAL FUND 001 DESCRIPTIONS... 6 V. DEBT SERVICE FUNDS... 9

More information

CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 10/10/18 HIGHWAY: FM 373 COUNTY: 05/02/2018 ESTIMATE PAID: AWARD DATE: 05/24/2018 ESTIMATE PERIOD:

CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 10/10/18 HIGHWAY: FM 373 COUNTY: 05/02/2018 ESTIMATE PAID: AWARD DATE: 05/24/2018 ESTIMATE PERIOD: CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 10/10/18 22 CONTRACT ID: 082301029 PROJECT: STP 2018(824) CONTRACT: 05183218 AWARD : $2,899,372.26 PROJECTED : $2,911,372.26 ADJ. PROJECTED : $2,911,372.26 CONTRACT:

More information

Summary of All Units Change In Net Position For the Four Months Ending Tuesday, July 31, Annual Budget

Summary of All Units Change In Net Position For the Four Months Ending Tuesday, July 31, Annual Budget Summary of All Units Customer Billings 4001 Customer Billings $19,603,438.00 $6,675,236.00 $6,812,439.85 $137,203.85 4004 Dark Fiber Billings 122,480.00 40,828.00 21,720.00 (19,108.00) 4005 Capital Billings

More information

Crop Enterprise Budget Sugar Beets, Thick-Planted, Wheatland Area

Crop Enterprise Budget Sugar Beets, Thick-Planted, Wheatland Area Crop Enterprise Budget Sugar Beets, Thick-Planted, Wheatland Area John P. Hewlett, Farm/Ranch Management Extension Specialist Chris Bastian, Research Associate MP-72.3 University of Wyoming - August, 1994

More information

SECTION DESCRIPTION PAGE I. BUDGET INTRODUCTION... 1 II. FISCAL YEAR 2017 BUDGET ANALYSIS... 2 III. FINAL OPERATING BUDGET... 3

SECTION DESCRIPTION PAGE I. BUDGET INTRODUCTION... 1 II. FISCAL YEAR 2017 BUDGET ANALYSIS... 2 III. FINAL OPERATING BUDGET... 3 2018 SECTION DESCRIPTION PAGE I. BUDGET INTRODUCTION... 1 II. FISCAL YEAR 2017 BUDGET ANALYSIS... 2 III. FINAL OPERATING BUDGET... 3 IV. GENERAL FUND 001 DESCRIPTIONS... 4 Background Information The Four

More information

Paul Patterson, Steven Hines and Juliet Marshall. Background and Assumptions

Paul Patterson, Steven Hines and Juliet Marshall. Background and Assumptions 2015 Costs and Returns Estimate Southcentral Idaho: Magic Valley Spring Malting Barley Paul Patterson, Steven Hines and Juliet Marshall. Background and Assumptions Magic Valley The University of Idaho

More information

DRAFT. Fort Worth Central City Preliminary Design. Current Working Estimate. Appendix E. January 2005 Updated April 2005

DRAFT. Fort Worth Central City Preliminary Design. Current Working Estimate. Appendix E. January 2005 Updated April 2005 Fort Worth Central City Preliminary Design Current Working Estimate Appendix E January 2005 Updated April 2005 DRAFT Images courtesy of CDM, Gideon Toal, and Bing Thom Architects TARRANT WATER REGINAL

More information

Town of Barnstable. Department of Public Work. Snow and Ice Control Operations Plan

Town of Barnstable. Department of Public Work. Snow and Ice Control Operations Plan Town of Barnstable Department of Public Work Snow and Ice Control Operations Plan I. Mission: The mission of the Department of Public Works is to remove accumulations of snow and ice from town, county

More information

Plows Truck Drivers. tations. Winter Maintenance Report. 30,546 Lane Miles 87% 174,000 40,000. Total Cost of Winter $ Million

Plows Truck Drivers. tations. Winter Maintenance Report. 30,546 Lane Miles 87% 174,000 40,000. Total Cost of Winter $ Million 2014-15 Winter Maintenance Report 30,546 Lane Miles At A Glance Total Cost of Winter $ 87.9 Million 87% Frequency Achieving Bare Lanes 1,514 Full-time 327 Backup Drivers 839 Plows 39.4 Statewide Snowfall

More information

SNOW REMOVAL - REQUEST FOR PROPOSAL. Snow Removal/Clearing and Sanding/Salting for Winter Fundy Ocean Research Center for Energy

SNOW REMOVAL - REQUEST FOR PROPOSAL. Snow Removal/Clearing and Sanding/Salting for Winter Fundy Ocean Research Center for Energy Fundy Ocean Research Center for Energy SNOW REMOVAL - REQUEST FOR PROPOSAL Snow Removal/Clearing and Sanding/Salting for Winter 2016-17 Sites 1. FORCE Sub-Station Driveway (portion of Old Black Rock Road),

More information

Background and Assumptions

Background and Assumptions 2017 Costs and Returns Estimate Southcentral Idaho: Magic Valley Soft White Spring Wheat Ben Eborn, Steven Hines and Juliet Marshall. Magic Valley Background and Assumptions The University of Idaho s costs

More information

10701 TRAFFIC CONTROL 1.00 LUMP SUM $4, $4, $ $4, $4, %

10701 TRAFFIC CONTROL 1.00 LUMP SUM $4, $4, $ $4, $4, % ACCOUNT NO. 10154-403-172 ACCOUNT NO. 10154-403-174 ACCOUNT NO. 11712-84-174-84600 ACCOUNT NO. 10154-403-172 10701 TRAFFIC CONTROL 1.00 LUMP SUM $4,000.00 $4,000.00 0.00 $0.00 1.00 $4,000.00 1.00 $4,000.00

More information

THE NEED FOR AN ADDITIONAL SPILLWAY AT THE SANFORD DAM BOILING SPRING LAKES, NC. Presentation for The Brunswick County Commissioners April 20, 2015

THE NEED FOR AN ADDITIONAL SPILLWAY AT THE SANFORD DAM BOILING SPRING LAKES, NC. Presentation for The Brunswick County Commissioners April 20, 2015 THE NEED FOR AN ADDITIONAL SPILLWAY AT THE SANFORD DAM BOILING SPRING LAKES, NC Presentation for The Brunswick County Commissioners April 20, 2015 The Sanford Dam Earth Dam constructed in 1961 Drainage

More information

Background and Assumptions

Background and Assumptions 2017 Costs and Returns Estimate Southcentral Idaho: Magic Valley Hard Red Spring Wheat Ben Eborn, Steven Hines and Juliet Marshall. Magic Valley Background and Assumptions The University of Idaho s costs

More information

ADDENDA #1 CONTRACT # C May 3, 2013 Page 1 of 1

ADDENDA #1 CONTRACT # C May 3, 2013 Page 1 of 1 State of California Natural Resources Agency Edmund G. Brown Jr., Governor DEPARTMENT OF PARKS AND RECREATION Major General Anthony L. Jackson, USMC (Ret), Director ADDENDA #1 CONTRACT # C1247040 May 3,

More information

Background and Assumptions

Background and Assumptions 2017 Costs and Returns Estimate Eastern Idaho Spring Malting Barley Ben Eborn, Terrell Sorensen and Jon Hogge Eastern Idaho Background and Assumptions The University of Idaho s costs and returns estimates

More information

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area.

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area. Sediment Trench SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils [1] Performance of

More information

Paul Patterson and Steven Hines Background and Assumptions

Paul Patterson and Steven Hines Background and Assumptions 2015 Costs and Returns Estimate Southcentral Idaho: Magic Valley Commercial Dry Beans Paul Patterson and Steven Hines Background and Assumptions Magic Valley The University of Idaho s costs and returns

More information

U-Shaped Sediment Traps

U-Shaped Sediment Traps U-Shaped Sediment Traps SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils [1] Type 3 System Supplementary Trap Dispersive Soils [1] Generally

More information

Prime6400 Software. Furnish and Install: Architectural Metalwork. SS Counter Tops Metal Brackets Metal Tops Metal Wall Panels

Prime6400 Software. Furnish and Install: Architectural Metalwork. SS Counter Tops Metal Brackets Metal Tops Metal Wall Panels To: Prime Estimating & Software Services, LLC 4248 Kensington High Street Naples, Florida, U.S.A. 3405 Att: Doug Baxter Phone: (239) 213-1237 Fax: (239) 213-1237 Project: Mock Metalwork Project Address:

More information

White River Update. Jeanne Stypula, Supervising Engineer. Advisory Committee Meeting April 26, 2016

White River Update. Jeanne Stypula, Supervising Engineer. Advisory Committee Meeting April 26, 2016 White River Update Jeanne Stypula, Supervising Engineer Advisory Committee Meeting April 26, 2016 Department of Natural Resources and Parks Water and Land Resources Division River and Floodplain Management

More information

ROCK EXCAVATION (GRADING) OPSS 206 INDEX

ROCK EXCAVATION (GRADING) OPSS 206 INDEX 206-2 - OPSS 206 INDEX 206-2.1 GENERAL 206-2.1.1 Classification of Rock Materials 206-2.1.2 Tender Items 206-2.1.3 Other Excavation Tender Items 206-2.1.4 Specifications 206-2.1.5 Special Provisions 206-2.1.6

More information

Lake Sedimentation Survey of Siloam Springs State Park Lake, Adams County, Illinois

Lake Sedimentation Survey of Siloam Springs State Park Lake, Adams County, Illinois Contract Report 567 Lake Sedimentation Survey of Siloam Springs State Park Lake, Adams County, Illinois by Richard L. Allgire Office of Sediment & Wetland Studies Prepared for the Illinois Department of

More information

MICROCOMPUTER CROP COST AND RETURN GENERATOR

MICROCOMPUTER CROP COST AND RETURN GENERATOR MICROCOMPUTER CROP AND RETURN GENERATOR BUDGET AREA... VALENCIA AND SOUTHERN BERNALILLO COUNT FARM SIZE.... 30.00 ACRES IRRIGATION TYPE FLOOD NUMBER OF CROPS 5 VERSION 1.0 COPYRIGHT (C) 1984 by NEW MEXICO

More information

That Council give first three readings to District of Squamish Cemetery Bylaw No , Amendment Bylaw No. 1931, 2006

That Council give first three readings to District of Squamish Cemetery Bylaw No , Amendment Bylaw No. 1931, 2006 REPORT TO: Council FOR: Regular PRESENTED: October 3, 2006 FILE: FROM: Department of Recreation, Parks and Tourism SUBJECT: Amendment to Cemetery Bylaw No. 1532, 1998 Recommendation: That Council give

More information

Background and Assumptions

Background and Assumptions EBB4-SU-17 2017 Costs and Returns Estimate Eastern Idaho: Bingham and Power Counties Sugarbeets Ben Eborn Eastern Idaho Background and Assumptions The University of Idaho s costs and returns estimates

More information

STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1. DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT

STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1. DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1 DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT Prepared by: PAULUS, SOKOLOWSKI & SARTOR STORMWATER MANAGEMENT 1. Methodology

More information

10. GEOTECHNICAL EXPLORATION PROGRAM

10. GEOTECHNICAL EXPLORATION PROGRAM Geotechnical site investigations should be conducted in multiple phases to obtain data for use during the planning and design of the tunnel system. Geotechnical investigations typically are performed in

More information

Coarse Sediment Traps

Coarse Sediment Traps Coarse Sediment Traps SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils [2] Type 3 System Supplementary Trap Dispersive Soils [1] Though primarily

More information

Eastern Idaho. Paul E. Patterson and Juliet M. Marshall Background and Assumptions

Eastern Idaho. Paul E. Patterson and Juliet M. Marshall Background and Assumptions 2015 Costs and Returns Estimate Eastern Idaho: Soft White Spring Wheat Paul E. Patterson and Juliet M. Marshall Background and Assumptions Eastern Idaho The University of Idaho s costs and returns estimates

More information

Limited Visual Dam Safety Inspections OA Oahu Reservoir No Oahu, Hawaii

Limited Visual Dam Safety Inspections OA Oahu Reservoir No Oahu, Hawaii Limited Visual Dam Safety Inspections OA00137 Oahu Reservoir No. 155 Oahu, Hawaii Prepared by: U.S. ARMY CORPS OF ENGINEERS HONOLULU DISTRICT STATE OF HAWAII DEPARTMENT OF LAND AND NATURAL RESOURCES May

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS 10782 Wattsburg Road Erie, PA 16509 The WATTSBURG AREA SCHOOL DISTRICT invites qualified vendors to submit proposals for CONTRACTED SNOW REMOVAL MANDATORY PRE-SUBMISSION MEETING All

More information

Paul Patterson Background and Assumptions

Paul Patterson Background and Assumptions 2015 Costs and Returns Estimate Southcentral Idaho: Magic Valley Corn Silage: Grown Using Genetically Modified Seed Paul Patterson Background and Assumptions Magic Valley The University of Idaho s costs

More information

Unit 2: Debris Quantity Forecasting and Estimating. December 2007 E/G/L202 Debris Management Planning 1

Unit 2: Debris Quantity Forecasting and Estimating. December 2007 E/G/L202 Debris Management Planning 1 Unit 2: Debris Quantity Forecasting and Estimating December 2007 E/G/L202 Debris Management Planning 1 Objectives 2.1 Discuss the importance and differences between debris forecasting and estimating 2.2

More information

Background and Assumptions

Background and Assumptions 2013 Costs and Returns Estimate Southwest Idaho: Treasure valley Commercial Dry Beans Kathleen Painter Background and Assumptions Southwestern Idaho The University of Idaho s costs and returns estimates

More information

Crop Enterprise Budget Dry Beans, Powell Area

Crop Enterprise Budget Dry Beans, Powell Area Crop Enterprise Budget Dry Beans, Powell Area John P. Hewlett, Farm/Ranch Management Extension Specialist Jay Jenkins, Extension Educator Paul A. Burgener, Former Graduate Assistant Jim J. Jacobs, Professor,

More information

B805 TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES - OPSS 805

B805 TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES - OPSS 805 B805 MEASURES - OPSS 805 805.1 GENERAL Construction activities frequently remove protective cover and expose soil to accelerated rates of erosion. Sediments generated thereby can be conveyed via runoff

More information

CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 09/08/17 HIGHWAY: RM 2721 COUNTY: 09/07/2012 ESTIMATE PAID: AWARD DATE: 09/27/2012 ESTIMATE PERIOD:

CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 09/08/17 HIGHWAY: RM 2721 COUNTY: 09/07/2012 ESTIMATE PAID: AWARD DATE: 09/27/2012 ESTIMATE PERIOD: -58,265.40 CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 09/08/17 517-7.00 8 CONTRACT ID: 271901008 PROJECT: STP 2013(029)HES CONTRACT: 09123212 AWARD AMOUNT: $2,899,581.31 PROJECTED AMOUNT: $2,928,572.31

More information

CITY OF NEW LONDON WINTER ROAD & SIDEWALK MAINTENANCE POLICY

CITY OF NEW LONDON WINTER ROAD & SIDEWALK MAINTENANCE POLICY CITY OF NEW LONDON WINTER ROAD & SIDEWALK MAINTENANCE POLICY GENERAL The purpose of this policy is to set up acceptable procedures and policies for the winter maintenance of public areas in the City of

More information

3. If a forecast is too high when compared to an actual outcome, will that forecast error be positive or negative?

3. If a forecast is too high when compared to an actual outcome, will that forecast error be positive or negative? 1. Does a moving average forecast become more or less responsive to changes in a data series when more data points are included in the average? 2. Does an exponential smoothing forecast become more or

More information

Horizontal Directional Drilling: An Approach to Design and Construction. Presenter: John Briand, PE Co-Author: Danielle Neamtu, PE

Horizontal Directional Drilling: An Approach to Design and Construction. Presenter: John Briand, PE Co-Author: Danielle Neamtu, PE Horizontal Directional Drilling: An Approach to Design and Construction Presenter: John Briand, PE Co-Author: Danielle Neamtu, PE Presentation Outline General HDD overview Conceptual-level evaluation Detailed

More information

0.00 2,420, ,420, ,512, , , , Property Taxes - Prior

0.00 2,420, ,420, ,512, , , , Property Taxes - Prior General Ledger Budget Analysis User: Printed: Fiscal Year: vnoel 04/23/2018-2:03PM 2019 2016 2017 2018 2018 2510 Klamath Cty Library Serv Dist 5010 Library Service District R10 Property Taxes 2,400,758.62

More information

GASB 34. Basic Financial Statements M D & A

GASB 34. Basic Financial Statements M D & A GASB 34 Basic Financial Statements M D & A In June 1999, the Governmental Accounting Standards Board issued Statement No. 34 (GASB 34) which fundamentally changed the financial reporting model for state

More information

Exhibit "A" Date: 1/27/2011

Exhibit A Date: 1/27/2011 Exhibit "A" Date: 1/27/2011 To: Bentley Communities Contact: Doug Knox Address: 1595 Paoli Pike Phone: 610-430-3700 West Chester, PA 19380 Fax: 610-430-3228 Project Name: Culbertson Village (Eastern Quadrent)(Phase

More information

Sediment Trap. At multiple locations within the project site where sediment control is needed.

Sediment Trap. At multiple locations within the project site where sediment control is needed. Sediment Trap SE-3 Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control

More information

Drivers % Winter Maintenance Report 30,517 46, , Statewide Snowfall Average. Truck Stations. Full-time Backup.

Drivers % Winter Maintenance Report 30,517 46, , Statewide Snowfall Average. Truck Stations. Full-time Backup. 2016-17 Winter Maintenance Report At A Glance 30,517 Snow and Ice Lane Miles 54 Statewide Snowfall Average 150 Truck Stations Total Cost of Winter $ 97 Million 87% Frequency Achieving Bare Lanes 1,779

More information

CITY OF CAPE CORAL STORMWATER MASTER PLAN PHASE II - PART 1 BASINS 4, 10, & 14 SUB-BASIN DRAINAGE IMPROVEMENTS HYDRAULIC ANALYSIS SUMMARY

CITY OF CAPE CORAL STORMWATER MASTER PLAN PHASE II - PART 1 BASINS 4, 10, & 14 SUB-BASIN DRAINAGE IMPROVEMENTS HYDRAULIC ANALYSIS SUMMARY CITY OF CAPE CORAL STORMWATER MASTER PLAN PHASE II - PART 1 BASINS 4, 10, & 14 SUB-BASIN DRAINAGE IMPROVEMENTS HYDRAULIC ANALYSIS SUMMARY Cape Coral, FL Prepared for: The City of Cape Coral Public Works

More information

Countermeasure Calculations and Design

Countermeasure Calculations and Design Countermeasure Calculations and Design Summarized from Bridge Scour and Stream Instability Countermeasures, Experience, Selection, and Design Guidance, Second Edition, Publication No. FHWA NHI 01-003,

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

Orica Australia Pty Ltd Ammonium Nitrate Facility Upgrade

Orica Australia Pty Ltd Ammonium Nitrate Facility Upgrade Orica Australia Pty Ltd Ammonium Nitrate Facility Upgrade January 2010 Revision 0 Contents 1. Introduction 1 1.1 Purpose 1 1.2 Objectives 1 1.3 Relevant Environmental Legislation, Guidelines and Policies

More information

TOWN OF JAMESTOWN TOWN COUNCIL RECOMMENDED BUDGET 2014/2015

TOWN OF JAMESTOWN TOWN COUNCIL RECOMMENDED BUDGET 2014/2015 70001.000 COUNCIL GENERAL GOVERNMENT.101 Salaries (5) 10,455.62 11,300.00 11,300.00 11,300.00 11,300.00.302 Fees & Supplies 632.78 1,500.00 1,500.00 1,500.00 1,500.00.305 Advertising 0.00 2,500.00 2,500.00

More information

New Jersey Department of Transportation DATE : 04/10/12 PAGE : TABULATION OF BIDS

New Jersey Department of Transportation DATE : 04/10/12 PAGE : TABULATION OF BIDS PAGE : 421-1 CONTRACT TIME : 12/15/12 COMPLETION DATE CONTRACT DESCRIPTION : PROJECT(S) : 100% STATE MAINTENANCE ROADWAY REPAIR CONTRACT CENTRAL, CONTRACT NO. C204, DP 11421 ROUTES US 1 NB & SB, 18 NB

More information

Specifications Whitcomb Elementary School Demolition January 15, 2016

Specifications Whitcomb Elementary School Demolition January 15, 2016 SECTION 31 2500 - EROSION CONTROL PART 1 - GENERAL 1.1 RELATED DOCUMENTS: A. The provisions of the Contract Documents apply to the work of this Section. B. The Virginia Erosion and Sediment Control Handbook,

More information

EAGLES NEST AND PIASA ISLANDS

EAGLES NEST AND PIASA ISLANDS EAGLES NEST AND PIASA ISLANDS HABITAT REHABILITATION AND ENHANCEMENT PROJECT MADISON AND JERSEY COUNTIES, ILLINOIS ENVIRONMENTAL MANAGEMENT PROGRAM ST. LOUIS DISTRICT FACT SHEET I. LOCATION The proposed

More information

Stone Outlet Sediment Trap

Stone Outlet Sediment Trap 3.12 Sediment Control Description: A stone outlet sediment trap is a small detention area formed by placing a stone embankment with an integral stone filter outlet across a drainage swale for the purpose

More information

Insured: Ana Cid Home: (714) Property: Vista View Lake Elsinore, CA 92530

Insured: Ana Cid Home: (714) Property: Vista View Lake Elsinore, CA 92530 1 Insured: Ana Cid Home: (714) 515-9871 Property: 15002 Vista View Lake Elsinore, CA 92530 Claim Rep.: Doug Felberg Business: (916) 694-8006 E-mail: d.felberg@pacificspecialty.com Estimator: Bryan Reece

More information

Woodford County Erosion Prevention Plan and Permit. Application #

Woodford County Erosion Prevention Plan and Permit. Application # Woodford County Erosion Prevention Plan and Permit Application # Date Instructions: Applicant will complete Parts A and B, and attach a proposed site diagram. This diagram must be completed in accordance

More information

Department Mission: Mandated Services: Department Overview: Successes and Challenges:

Department Mission: Mandated Services: Department Overview: Successes and Challenges: Department: Law Library FY 2016 Proposed Budget Department Mission: The Lloyd De Lap Klamath County Law Library is dedicated to providing legal research material to members of the bar and the community

More information

OVERVIEW OF ER DRILLING IN EARTH EMBANKMENT DAMS AND

OVERVIEW OF ER DRILLING IN EARTH EMBANKMENT DAMS AND OVERVIEW OF ER 1110-1-1807 DRILLING IN EARTH EMBANKMENT DAMS AND 255 255 255 237 237 237 0 0 0 217 217 217 LEVEES 163 163 163 200 200 200 131 132 122 239 65 53 80 119 27 110 135 120 Requirements and Processes

More information

City of Eagleville Budget Presentation Fiscal Year 2018

City of Eagleville Budget Presentation Fiscal Year 2018 City of Eagleville Budget Presentation Fiscal Year 2018 Work Sessions: March 9, 2017: March 23, 2017: April 13, 2017: General Fund Revenue Estimates Parks & Recreation State Street Aid Revenue and Expenses

More information

City of Forest Hills Profit & Loss for the month and Fiscal Year October 2015

City of Forest Hills Profit & Loss for the month and Fiscal Year October 2015 Profit & Loss for the month and Fiscal Year Oct 15 Jul - Oct 15 Ordinary Income/Expense Income 31900- Other Taxes 31910- Franchise Taxes 6,407.61 21,517.61 Total 31900- Other Taxes 6,407.61 21,517.61 31600

More information

Systems. Department Mission: Mandated Services: Department Overview: Successes and Challenges:

Systems. Department Mission: Mandated Services: Department Overview: Successes and Challenges: Department: Geographic Information Systems FY 2018 Proposed Budget Department Mission: The mission of the Klamath County Geographic Information Systems (GIS) department is to provide maintenance of and

More information

SEXTANT & SEXTANT PE frequently asked questions

SEXTANT & SEXTANT PE frequently asked questions SEXTANT & SEXTANT PE frequently asked questions What is SEXTANT? SEXTANT is a software application that helps Financial Executives and Estimators determine their costing and budgeting standards also known

More information

Insured: Ana Cid Home: (714) Property: Vista View Lake Elsinore, CA 92530

Insured: Ana Cid Home: (714) Property: Vista View Lake Elsinore, CA 92530 1 Insured: Ana Cid Home: (714) 515-9871 Property: 15002 Vista View Lake Elsinore, CA 92530 Claim Rep.: Doug Felberg Business: (916) 694-8006 E-mail: d.felberg@pacificspecialty.com Estimator: Bryan Reece

More information

TOWN OF THORNTON, NEW HAMPSHIRE WINTER AND INCLEMENT WEATHER POLICY AND PRIORITIES

TOWN OF THORNTON, NEW HAMPSHIRE WINTER AND INCLEMENT WEATHER POLICY AND PRIORITIES TOWN OF THORNTON, NEW HAMPSHIRE WINTER AND INCLEMENT WEATHER POLICY AND PRIORITIES Pursuant to RSA 231:92 a, the Thornton Board of Selectmen hereby establishes the following policy and procedure for winter

More information

Community Erosion Assessment Napakiak, Alaska 15 January 2008

Community Erosion Assessment Napakiak, Alaska 15 January 2008 1. Community: Napakiak, Alaska Community Erosion Assessment Napakiak, Alaska 15 January 2008 Figure 1: Napakiak Location & Vicinity Map 2. Community Profile Summary: Napakiak is a 2 nd class city of 378

More information

Geosynthetics Applications and Performance Reviews Select Case Histories

Geosynthetics Applications and Performance Reviews Select Case Histories Geosynthetics Applications and Performance Reviews Select Case Histories Debora J. Miller, Ph.D., P.E.; Dean B. Durkee,, Ph.D., P.E.; Michael A. Morrison, P.E., David B. Wilson, P.E., and Kevin Smith,

More information

FRED BURR DAM FEASIBILITY STUDY

FRED BURR DAM FEASIBILITY STUDY FRED BURR DAM FEASIBILITY STUDY Fred Burr Dam Feasibility Study Purpose: Develop pre-feasibility risk reduction alternatives and recommendations for short-term operations and long-term rehabilitation.

More information

Department Mission: Mandated Services: Department Overview: Successes and Challenges:

Department Mission: Mandated Services: Department Overview: Successes and Challenges: Department: Information Technology FY 2019 Proposed Budget Department Mission: Klamath County Information Technology delivers business services that empower, support and serve all county departments in

More information

CHAPTER FIVE: THE LOWER MISSISSIPPI REGION AND PLAQUEMINES PARISH

CHAPTER FIVE: THE LOWER MISSISSIPPI REGION AND PLAQUEMINES PARISH CHAPTER FIVE: THE LOWER MISSISSIPPI REGION AND PLAQUEMINES PARISH 5.1 Overview Plaquemines Parish is the area where the last portion of the Mississippi River flows out into the Gulf of Mexico (see Figures

More information

Snow Removal Winchester Department of Public Works

Snow Removal Winchester Department of Public Works Snow Removal Winchester Department of Public Works Town of Winchester Board of Selectmen Meeting Neil H. Amwake, P.E. November 4, 2013 Presentation Outline Goals and Objectives 1. Connecticut snowfall

More information

Town of Southwest Ranches Statement of Revenues and Expenditures From 10/1/2011 Through 12/31/2011. Current Period Actual

Town of Southwest Ranches Statement of Revenues and Expenditures From 10/1/2011 Through 12/31/2011. Current Period Actual 01 - General Fund Revenue Ad Valorem Taxes 311000 3,007,200.12 4,102,334.00 (1,095,133.88) Franchise Fee-Electric 313100 56,486.83 490,000.00 (433,513.17) Solid Waste Franchise Fee 313700 0.00 35,000.00

More information

City of Forest Hills Profit & Loss for the month and Fiscal Year May 2016

City of Forest Hills Profit & Loss for the month and Fiscal Year May 2016 Profit & Loss for the month and Fiscal Year May 16 Jul '15 - May 16 Ordinary Income/Expense Income 31900- Other Taxes 31910- Franchise Taxes 18,106.78 121,422.86 Total 31900- Other Taxes 18,106.78 121,422.86

More information

Background. Valley fills Sites in the Area. Construction over Mine Spoil Fills

Background. Valley fills Sites in the Area. Construction over Mine Spoil Fills Construction over Mine Spoil Fills Wayne A. Karem, PhD, PE, PG, D.GE 2014 KSPE Annual Conference Background Strip mining; mountaintop and contour mining Creates huge quantities of mine spoil The mine spoil

More information

Department: County Counsel FY Proposed Budget

Department: County Counsel FY Proposed Budget Department: County Counsel FY 2018-2019 Proposed Budget Department Mission: The mission of the Klamath County Counsel s office is to provide Klamath County with the best legal support possible to achieve

More information