Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Azerbaijan Third Highway Project (P118023) Operation Name: Third Highway Project (P118023) Project Stage: Implementation Seq.No: 9 Status: ARCHIVED Archive : 28-Apr-2014 Country: Azerbaijan Approval FY: 2010 Product Line: IBRD/IDA Region: EUROPE AND CENTRAL ASIA Lending Instrument: Specific Investment Loan Implementing Agency(ies): Azeryolservis JSC Key s Board Approval Original Closing 31-Mar-2015 Planned Mid Term Review 01-Oct-2012 Last Archived ISR 26-Sep-2013 Effectiveness 08-Nov-2010 Revised Closing Actual Mid Term Review 06-Nov-2013 Project Development Objectives Project Development Objective (from Project Appraisal Document) To contribute to a more efficient and safer Baku-Shamakhi and Yenikend-Shorsulu roads and higher quality road services as part of the general network upgrading to motorway standard, and to improve the management of the nascent motorway network. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) losure Authorized Public Disclosure Authorized Component Name Component 1: Upgrading a 77 km section of M4 Baku-Shamakhi and 48 km section of M3 Yenikend- Shorsulu roads into a four-lane motorwa y. Component 2: Institutional development (management and financing Azerbaijan Motorways; institutional development of the ARS) Component 3: Project Management including technical assistance and financing additional costs for project implementation. Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Moderate Moderate Component Cost 316.00 Implementation Status Overview The World Bank has finalized a comprehensive restructuring of the Project. The restructuring provides opportunities for more strategic and efficient use of existing resources including the financing of remaining works on upgrading Yenikend-Shorsulu section of M3 Highway, originally financed under the Second Highway Project. 5.00 1.00 Page 1 of 5
Locations Country First Administrative Division Location Planned Actual Azerbaijan Salyan Salyan Rayon Azerbaijan Baku Alyaty Azerbaijan Samaxi Rayonu Samaxi Rayonu Azerbaijan Samaxi Rayonu Samaxi Azerbaijan Baku Baku Azerbaijan Baku Baku Azerbaijan Abseron Rayonu Abseron Rayonu Azerbaijan Qobustan Rayonu Qobustan Rayonu Results Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Efficiency: Reduction in road user costs from Percentage Value 100.00 100.00 80.00 Baku to Shamakhi Civil works are Efficiency: Reduction in road user costs from Percentage Value 100.00 100.00 80.00 Yenikend to Shorsulu procurement of civil works is Safety: Reduction of personal injury per 100- Percentage Value 100.00 100.00 70.00 million vehicle-km along the Baku-Shamkhi road. Civil works are Safety: Reduction of personal injury per 100- Percentage Value 100.00 100.00 70.00 million vehicle-km along the Yenikend-Shorsulu road. procurement of civil works is Page 2 of 5
Quality:Percentage of M roads in good and fair condition as a share of total M roads of the network Intermediate Results Indicators Percentage Value 55.00 61.00 70.00 15-Jan-2014 Rehabilitation and upgrading of a number of M roads is Indicator Name Core Unit of Measure Baseline Current End Target Number of km upgraded for Baku-Shamakhi Kilometers Value 0.00 10.00 77.00 road civil works are Number of km upgraded for Yenikend-Shorsulu Kilometers Value 0.00 0.00 48.00 road procurement of civil works contracts is Roads constructed, non-rural Kilometers Value 0.00 10.00 125.00 civil works are Percentage of safety audits conducted on road Percentage Value 0.00 80.00 80.00 accidents recorded during construction stage of Baku-Shamakhi. Civil works started. Supervising Engineers were instructed to report and carry out audits Safety audits on detailed design. Text Value No Yes Yes Audits have been completed for the sections 1,2&3 of M4 Baku - Shamakhi road Safety audits on construction completion. Text Value No No Yes No sections completed yet Design of a Motorway Guidelines. Text Value No under preparation Yes 25-May-2010 Page 3 of 5
Development of motorways management and maintenance strategy Development of a pilot Motorway Management Unit. Data on Financial Performance (as of 21-Jan-2014) Financial Agreement(s) Key s Text Value No No Yes 15-Jan-2014 Preparation is progressing Text Value No yes Yes completed Project Ln/Cr/Tf Status Approval Signing Effectiveness Original Closing Revised Closing P118023 IBRD-78890 Effective 25-May-2010 11-Aug-2010 08-Nov-2010 31-Mar-2015 P118023 IDA-47230 Effective 25-May-2010 11-Aug-2010 08-Nov-2010 31-Mar-2015 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P118023 IBRD-78890 Effective USD 171.60 171.60 0.00 33.82 137.78 20.00 P118023 IDA-47230 Effective USD 70.00 70.00 0.00 0.00 70.67 0.00 Disbursement Graph Page 4 of 5
Key Decisions Regarding Implementation The restructuring and recent progress in implementation open good prospects for the satisfactory implementation of the Project. As the performance of the project shows steady signs of improvements, the implementing agency needs to focus on maintaining the positive momentum in implementation of the Project and inform the World Bank about any deviation from the plan of actions agreed during the restructuring. Restructuring History Level 1 Board/AOB Decision on 04-Dec-2013 Related Projects There are no related projects. Page 5 of 5