An environmentally sensitive erosion control technique in the Mekong River Delta: 10 years on
|
|
- Daniel McGee
- 6 years ago
- Views:
Transcription
1 7 th Australian Stream Management Conference - Full Paper An environmentally sensitive erosion control technique in the Mekong River Delta: 10 years on John Tilleard 1, Tony Ladson 2 1 Moroka Pty Ltd, PO Box 67C, Somers, Vic, john.tilleard@moroka.com.au 2 Moroka Pty Ltd. P.O. Box 1245, Fitzroy North, Vic tony.ladson@moroka.com.au Key Points Bank retreat of 6-35 m/yr threatened the stability of the My Thuan bridge site in the Mekong delta Bank revetment was expensive, damaged the land-water interface and was unsuited to dominant channel migration processes. Submerged permeable groynes were proposed as an alternative. Physical modelling was used to optimize the configuration of 12x100 m groynes for bed stability. 3 years of post-construction monitoring confirmed velocity reduction achieved by the groynes. Recent observation, 10 years after construction, suggests the works are performing well. Formal monitoring is now needed to ratify the performance and confirm applicability to other sites. Keywords Mekong, permeable structures, bank erosion, channel migration, pile fields, bridge protection, groynes, erosion control, monitoring, My Thuan, Vietnam Introduction In 2002, to minimize erosion and scour threats to a major new bridge (Figure 1) in the Mekong Delta, AusAID funded works to reduce the rate of channel migration over more than 2 km of river upstream of the bridge. Figure 1. AusAID built the My Thuan Bridge in the Mekong delta in 2002 Instead of locally standard techniques involving bank battering and shaping followed by some form of rock or concrete revetment, highly permeable lines of submerged piles extending 100m out from the bank were used to disturb the formation of secondary currents, reduce water velocities and boundary shear stress and reduce the scour of sediment from the bed and banks. There was minimal interference with the river bank itself, and its existing form and vegetative cover was maintained. Intensive monitoring of velocities and bed and bank profiles for several years after construction provided reassurance that the technique would be successful. 10 years on, during a visit to the area, the bank was observed to have retained its largely natural character but bank migration appears to have been arrested. If this could be confirmed by a new round of monitoring, then the technique would offer an effective approach to managing erosion which is less intrusive and has less impact than standard revetment techniques, even on a large mobile bed river. and Hughes, R. (editors), Proceedings of the 7th Australian Stream Management Conference. Townsville, Queensland, Pages
2 History of channel migration upstream of the My Thuan bridge In the Mekong Delta channel migration over many kilometres of river is associated with rapid bank retreat (Figure 2). The retreat is the result of the combined effects of natural river and tidal processes, impacts of land use in the catchments, floodplain and riparian zone, use of the river for gravel and sand extraction, navigation, irrigation and hydropower and impacts of climate change. The typical response by local agencies and international aid organisations is to form and shape the river bank and protect it from erosion using concrete revetment (Figure 3). Figure 2. There are many kilometres of eroding bank in the Mekong Delta Figure 3. Concrete revetment is the standard approach to erosion control Channel migration upstream of the My Thuan Bridge threatened long term bridge security (as well as ongoing social dislocation and reduced food production). Figure 4 is a satellite image of the locality with river flow from left to right. The bank where the groyne field annotation is shown exhibited the greatest rate of bank retreat. Continued downstream migration of this bend would eventually impinge on the stability of bridge approaches. There was also a 40m deep scour hole in the river bend associated with the bend. Downstream migration of this would threaten the stability of bridge foundations. Prior to works, rates of channel migration were extreme (Figure 5) with rates of bank retreat over 20 m per year. As well as the new bridge, roads and houses were regularly threatened by river bank erosion (figure 6). Design principles and process Revetment acts to stop erosion by providing a physical barrier to protect bank material from removal by the flowing water. This has profound environmental impact at the land-water interface and does nothing to dissipate flow energy. It treats effect not cause. The use of revetment assumes that the primary mechanism of erosion is removal of material from the face of the bank rather than progressive undermining of the toe of the bank by migration of the channel thalweg which is the implied dominant erosion mode at least at this site. AusAID recognized the limitations of standard revetment treatments and supported an alternative approach using permeable groynes. and Hughes, R. (editors), Proceedings of the 7th Australian Stream Management Conference. Townsville, Queensland, Pages
3 Groyne Field Scour hole Figure 4. Satellite image showing location of My Thuan bridge, scour hole and groyne field. Flow is left to right. Figure 5. Between 1958 and 1992, historical rates of bank retreat were between 6 and 35 m/year at 5 transects along the left bank upstream of the scour hole Figure 6. Erosion damaging roadway and threatening houses in 1996 Intensive physical modelling was undertaken at the Vietnamese Institute for Water Resources Research (Figure 7). The aim of the modelling was to test the velocity reductions that could be achieved with different groyne configurations and to develop optimum configurations to meet velocity reduction criteria based on the mobility characteristics of bed and bank sediments. and Hughes, R. (editors), Proceedings of the 7th Australian Stream Management Conference. Townsville, Queensland, Pages
4 Modelled velocities guided optimization of: Groyne locations Groyne length Groyne spacing Groyne orientation Size of piles Permeability Height of groynes above the bed Need for scour protection around groynes The groyne layout was configured to reduce velocities in the near bank zone to below the threshold of motion of the bed material. The eventual design provided for 12 lines of 100 submerged piles extending 100m out from the river bank (Figure 8). 450 mm square concrete piles were driven into the river bed from a floating barge. The piles were spaced at 1125 mm and they were driven so that their tops were up to 15 m below water level. Rock was placed via a chute from a barge to limit bed scour around and through the groynes. Figure 7. Model groynes to test velocity reduction Figure 8. Example of design profile of two groynes (groynes 3 and 4) Figure 8. Example of design profile of two groynes (Groynes 3 and 4) and Hughes, R. (editors), Proceedings of the 7th Australian Stream Management Conference. Townsville, Queensland, Pages
5 Monitoring Extensive monitoring was undertaken during construction and then for 3 years. Monitoring included bed level surveys using side scan sonar, pile integrity surveys using divers and velocity monitoring throughout the groyne field using an Acoustic Doppler Current Profiler (ADCP). Figure 9 demonstrates the velocity reductions achieved in the groyne field. Figure 9. Measured velocity profile along a vertical 60 m out from river bank after construction of groynes. Flow is left to right. X axis is distance (m) along the river. Approach velocity > 1m/sec is slowed to around 0.5 m/s within the groyne field. Observations 10 years on Monitoring ceased in 2004 and the author is aware of no formal evaluations of the performance of the works since then. However during a visit to the area in May 2013, it was possible to make some brief observations of the location and condition of the bank upstream of the bridge and through the groyne field. No sign of active erosion was observed and the bank appears to have stabilized in its 2003 location. Figure 10 (May 2013) indicates that the bank retreat shown in Figure 6 has stabilized. Figure 10 shows a stable bank in the vicinity of the upstream groynes. No formal measurements or monitoring were undertaken during this visit. Figure 10. May Erosion shown in Figure 6 appears to have stabilised. and Hughes, R. (editors), Proceedings of the 7th Australian Stream Management Conference. Townsville, Queensland, Pages
6 Conclusions Submerged permeable groynes appear to offer an alternative to bank revetment for managing bank erosion on a large river such as the Mekong in the Mekong delta. Submerged permeable groynes can disturb secondary currents and dissipate energy, reducing the water velocities that cause bank retreat by scour of the river bed at the toe of the river bank. Compared to bank revetment, submerged permeable groynes have limited environmental and visual impact. They need not interfere with shipping or other uses of the river and its environs. A new tranche of monitoring involving ADCP measurements, pile integrity surveys and satellite comparisons could ratify the effectiveness of the submerged permeable groyne approach and confirm its suitability for further development and application. Acknowledgments AusAID are gratefully acknowledged for their willingness to back an innovative approach to protecting their substantial asset. The investigation and design was undertaken by Ian Drummond and Associates Pty Ltd for Maunsell Pty Ltd. Lindsay White and Bob Keller were instrumental in developing the approach. Dr Thai at the Water Resources Research Institute in Hanoi supervised the modelling. Ben de Witt oversaw structural aspects of design, looked after the project during construction and managed the monitoring program. References Maunsell Pty Ltd (1996a). My Thuan Bridge Project Vietnam. Phase 3 Detailed Design and Documentation. Final Report on River Studies. Prepared for Australian Agency for International Development and Ministry of Transport and Communications, Vietnam. October 1996 Maunsell Pty Ltd (1996b). My Thuan Bridge Project Vietnam. Phase 3 Detailed Design and Documentation. Report on River Bank Protection Works. Prepared for Australian Agency for International Development and Ministry of Transport and Communications, Vietnam. November 1996 Maunsell Pty Ltd (1996c). My Thuan Bridge Project Vietnam. Phase 3 Detailed Design and Documentation. Final Bridge Design Report. Prepared for Australian Agency for International Development and Ministry of Transport and Communications, Vietnam. November 1996 and Hughes, R. (editors), Proceedings of the 7th Australian Stream Management Conference. Townsville, Queensland, Pages
Project (Project No. US-CA-62-2) Maintenance Inspection and Reports (Subtask 14.1) Inspection Report No.2
MEMORANDUM TO: FROM: Jim Well, Ducks Unlimited Mike Harvey, PhD, PG SUBJECT: M&T/ Llano Seco Fish Screen Project (Project No. US-CA-62-2) Maintenance Inspection and Reports (Subtask 14.1) Inspection Report
More information6.11 Naas River Management Unit
6.11 Naas River Management Unit 6.11.1 Site 41 Issue: Bed and bank erosion Location: E 0685848 N 6058358 Waterway: Naas River Management Unit: Naas River Facing downstream from Bobeyan Rd bridge Facing
More informationCountermeasure Calculations and Design
Countermeasure Calculations and Design Summarized from Bridge Scour and Stream Instability Countermeasures, Experience, Selection, and Design Guidance, Second Edition, Publication No. FHWA NHI 01-003,
More informationVetiver System for Stream Bank Stabilisation. Paul Truong
Vetiver System for Stream Bank Stabilisation (With special references to the river and canal bank stabilisation in Australia and Vietnam) Paul Truong Director, The Vetiver Network International, Veticon
More informationHAW CREEK, PIKE COUNTY, MISSOURI-TRIB TO SALT RIVER ERODING STREAM THREATHENING COUNTY ROAD #107, FOURTEEN FT TALL ERODING BANK WITHIN 4 FT OF THE
HAW CREEK, PIKE COUNTY, MISSOURI-TRIB TO SALT RIVER ERODING STREAM THREATHENING COUNTY ROAD #107, FOURTEEN FT TALL ERODING BANK WITHIN 4 FT OF THE ROAD, PROJECT CONSTRUCTED IN 1 DAY, MARCH 10, 2009 BY
More informationSCOUR AND EROSION ALONGSIDE BANK PROTECTION WORK: CASE STUDIES FROM BANGLADESH
SCOUR AND EROSION ALONGSIDE BANK PROTECTION WORK: CASE STUDIES FROM BANGLADESH KNUT OBERHAGEMANN Northwest Hydraulic Consultants Lt. 4823 99 th Street Edmonton, Alberta T6E 4Y1, Canada ABDUN NOOR Bangladesh
More informationInstream Erosion Control General
Instream Erosion Control General EROSION CONTROL TECHNIQUES Revegetation Temperate Climates Short-Term Non Vegetation Wet Tropics Long-Term Weed Control [1] Semi-Arid Zones Permanent [1] Weed control attributes
More informationUpper Mississippi River Basin Environmental Management Program Workshop
Presentation to the Upper Mississippi River Basin Environmental Management Program Workshop by Michael Rodgers River Engineer US Army Corps of Engineers, St. Louis District August 17, 2007 Engineering
More informationJ-river engineering for Vietnam
J-river engineering for Vietnam Workshop on erosion control in the Mekong Delta Soc Trang, June 2015 Onga river, Japan Dr. MATSUKI Trung: JICA Expert 1 Project for Building Disaster Resilient Society in
More informationCarmel River Bank Stabilization at Rancho San Carlos Road Project Description and Work Plan March 2018
Carmel River Bank Stabilization at Rancho San Carlos Road Project Description and Work Plan March 2018 EXISTING CONDITION The proposed Carmel River Bank Stabilization at Rancho San Carlos Road Project
More informationAnnual transport rates at two locations on the fore-slope.
Sediment Transport by Currents Fore-slope Sediment transport rates and sediment concentrations were computed from the hydrodynamic model runs as well as from direct measurements of current velocities at
More informationStream Geomorphology. Leslie A. Morrissey UVM July 25, 2012
Stream Geomorphology Leslie A. Morrissey UVM July 25, 2012 What Functions do Healthy Streams Provide? Flood mitigation Water supply Water quality Sediment storage and transport Habitat Recreation Transportation
More informationRock Sizing for Waterway & Gully Chutes
Rock Sizing for Waterway & Gully Chutes WATERWAY MANAGEMENT PRACTICES Photo 1 Rock-lined waterway chute Photo 2 Rock-lined gully chute 1. Introduction A waterway chute is a stabilised section of channel
More informationA STUDY OF LOCAL SCOUR AT BRIDGE PIERS OF EL-MINIA
A STUDY OF LOCAL SCOUR AT BRIDGE PIERS OF EL-MINIA Dr. Gamal A. Sallam 1 and Dr. Medhat Aziz 2 ABSTRACT Bridges are critical structures that require a substantial investment to construct and serve an important
More informationRock Sizing for Multi-Pipe & Culvert Outlets
Rock Sizing for Multi-Pipe & Culvert Outlets STORMWATER AND WATERWAY MANAGEMENT PRACTICES Photo 1 Rock pad outlet structure at end of a duel stormwater pipe outlet Photo 2 Rock pad outlet structure at
More informationDevelopment and application of demonstration MIKE 21C morphological model for a bend in Mekong River
Development and application of demonstration MIKE 21C morphological model for a bend in Mekong River September 2015 0 Table of Contents 1. Introduction... 2 2. Data collection... 3 2.1 Additional data...
More informationIsland 32 Erosion. prepared for Ministry of Environment, Lands and Parks A Street Surrey, British Columbia, V3R 7P8. and
Island 32 Erosion prepared for Ministry of Environment, Lands and Parks 10334 152A Street Surrey, British Columbia, V3R 7P8 and District of Chilliwack 8550 Young Road Chilliwack, British Columbia, V2P
More informationRock Sizing for Small Dam Spillways
Rock Sizing for Small Dam Spillways STORMWATER MANAGEMENT PRACTICES Photo 1 Rock-lined spillway on a construction site sediment basin Photo 2 Rock-lined spillway on a small farm dam 1. Introduction A chute
More informationNATURE OF RIVERS B-1. Channel Function... ALLUVIAL FEATURES. ... to successfully carry sediment and water from the watershed. ...dissipate energy.
1 2 Function... Sevier River... to successfully carry sediment and water from the watershed....dissipate energy. 3 ALLUVIAL FEATURES 4 CHANNEL DIMENSION The purpose of a stream is to carry water and sediment
More informationCASE STUDIES. Introduction
Introduction The City of Winston-Salem faces the challenge of maintaining public infrastructure (e.g., water and sewer lines, storm drains, roads, culverts and bridges) while minimizing the potential impacts
More information24.0 Mineral Extraction
Chapter 24 - Mineral Extraction 24.0 Mineral Extraction 24.1 Introduction Apart from gravel, sand, rock, limestone and salt extraction in relatively small quantities mineral extraction is not a strong
More informationRock Sizing for Batter Chutes
Rock Sizing for Batter Chutes STORMWATER MANAGEMENT PRACTICES Photo 1 Rock-lined batter chute Photo 2 Rock-lined batter chute 1. Introduction In the stormwater industry a chute is a steep drainage channel,
More informationConnecticut Coastal Management Program
Connecticut Coastal Management Program Fact Sheet for SHORELINE FLOOD AND EROSION CONTROL STRUCTURES What are Shoreline Flood and Erosion Control Structures? The Connecticut General Statutes (CGS) define
More informationJune 2018 Sediments and Dredging at GBR Ports
June 2018 Sediments and Dredging at GBR Ports Reef 2050 Long Term Sustainability Plan The Great Barrier Reef is over 2000 km long and covers an area of approximately 350,000 square kilometres. It is a
More informationWhy Geomorphology for Fish Passage
Channel Morphology - Stream Crossing Interactions An Overview Michael Love Michael Love & Associates mlove@h2odesigns.com (707) 476-8938 Why Geomorphology for Fish Passage 1. Understand the Scale of the
More information3/3/2013. The hydro cycle water returns from the sea. All "toilet to tap." Introduction to Environmental Geology, 5e
Introduction to Environmental Geology, 5e Running Water: summary in haiku form Edward A. Keller Chapter 9 Rivers and Flooding Lecture Presentation prepared by X. Mara Chen, Salisbury University The hydro
More informationDomino Effect of River Training in Large Sand-Bed Braiding Rivers
6 th International Conference on Structural Engineering and Construction Management 2015, Kandy, Sri Lanka, 11 th -13 th December 2015 SECM/15/176 Domino Effect of River Training in Large Sand-Bed Braiding
More informationBest Management Practices for Coldwater Fisheries Enhancement and Restoration
Best Management Practices for Coldwater Fisheries Enhancement and Restoration MACC Annual Environmental Conference 2017 March 3, 2017 Tim Dexter, MassDOT Highway Division 1 Leading the Nation in Transportation
More informationFlooding in Dolgellau
Flooding in Dolgellau Graham Hall MMath, PhD University of Wales, Bangor Background Flooding has historically been a cause for concern in Dolgellau. Following a serious flood in December 1964 when shops
More informationUGRC 144 Science and Technology in Our Lives/Geohazards
UGRC 144 Science and Technology in Our Lives/Geohazards Flood and Flood Hazards Dr. Patrick Asamoah Sakyi Department of Earth Science, UG, Legon College of Education School of Continuing and Distance Education
More informationConsequences of river regulation works: altered fluvial processes + increasing flood hazard
Consequences of river regulation works: altered fluvial processes + increasing flood hazard Dr. Tímea Kiss assistant professor Department of Physical Geography and Geoinformatics, University of Szeged,
More informationUpper Drac River restoration project
Upper Drac River restoration project Restoration of a braided river bed incised in clay substratum through sediment reloading and bed widening SHF Conference, Nantes, 6 & 7 october 2014 Small scale morphological
More informationRAILWAYS AND FISH: HOW TO PROTECT AND ENHANCE FISH HABITAT VALUES AT STREAM CROSSINGS THROUGH PROJECT DESIGN AND CONSTRUCTION
RAILWAYS AND FISH: HOW TO PROTECT AND ENHANCE FISH HABITAT VALUES AT STREAM CROSSINGS THROUGH PROJECT DESIGN AND CONSTRUCTION Rail Environment Conference November 2016 AGENDA Objective Background Benefits
More informationCentral Queensland Coal Project Appendix 4b Geotechnical Assessment. Environmental Impact Statement
Central Queensland Coal Project Appendix 4b Geotechnical Assessment Environmental Impact Statement GEOTECHNICAL ASSESSMENT OF OPEN CUT MINING ADJACENT TO THE BRUCE HIGHWAY, CENTRAL QUEENSLAND COAL PROJECT
More informationChutes Part 5: Rock linings
Chutes Part 5: Rock linings DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent [2] [1] Chutes
More informationRock Sizing for Bank Stabilisation
Rock Sizing for Bank Stabilisation WATERWAY MANAGEMENT PRACTICES Photo 1 Lower bank rock stabilisation with voids filled with small rocks Photo 2 Rock stabilisation with plants introduced at time of rock
More informationAnalysis of Cost-Effective Rehabilitation: Principles and Tools for Reducing Uncertainty in Design
Analysis of Cost-Effective Rehabilitation: Principles and Tools for Reducing Uncertainty in Design Natasha Bankhead and Andrew Simon Cardno ENTRIX, Oxford, MS natasha.bankhead@cardno.com Often the Questions
More informationGEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE
GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE Prof. J. N. Mandal Department of civil engineering, IIT Bombay, Powai, Mumbai 400076, India. Tel.022-25767328 email: cejnm@civil.iitb.ac.in Module - 4
More informationSeaton to Seaton Hole SUMMARY OF PREFERRED PLAN RECOMMENDATIONS AND JUSTIFICATION
Location reference: Policy Unit reference: Plan: Seaton to Seaton Hole 6a29 and 6a30 SUMMARY OF PREFERRED PLAN RECOMMENDATIONS AND JUSTIFICATION The large number of properties and assets at risk in the
More informationEFFECT OF SAND MINING ACTIVITY ON THE SEDIMENT CONTROL SYSTEM (A CASE STUDY OF SOMBE-LEWARA RIVER, DONGGALA, INDONESIA)
Civil Engineering Forum Volume XXI/1 - January 01 EFFECT OF SAND MINING ACTIVITY ON THE SEDIMENT CONTROL SYSTEM (A CASE STUDY OF SOMBE-LEWARA RIVER, DONGGALA, INDONESIA) Y. A. Bawias Agency of Public Works,
More informationHydraulics of bendway weirs
River Basin Management IV 389 Hydraulics of bendway weirs C. Thornton 1, S. Abt 1, D. Baird 2 & R. Padilla 3 1 Colorado State University, Fort Collins, CO, USA 2 U.S. Bureau of Reclamation, Denver, CO,
More informationAppendix F Channel Grade Control Structures
Stream Simulation Appendix F Channel Grade Control Structures This appendix briefly describes permanent grade control structures that are sometimes needed in the upstream and/or downstream reaches adjacent
More informationErosion Surface Water. moving, transporting, and depositing sediment.
+ Erosion Surface Water moving, transporting, and depositing sediment. + Surface Water 2 Water from rainfall can hit Earth s surface and do a number of things: Slowly soak into the ground: Infiltration
More informationDegradation Concerns related to Bridge Structures in Alberta
Degradation Concerns related to Bridge Structures in Alberta Introduction There has been recent discussion regarding the identification and assessment of stream degradation in terms of how it relates to
More informationHabitat Assessment. Peggy Compton UW-Extension Water Action Volunteers Program Coordinator
Habitat Assessment Peggy Compton UW-Extension Water Action Volunteers Program Coordinator Adapted from a presentation by Jean Unmuth, Water Quality Biologist, WI DNR dnr.wi.gov www.uwex.edu erc.cals.wisc.edu
More informationPhysical landscapes River landscapes in the UK
Physical landscapes River landscapes in the UK The shape of river valleys change s as rivers flow downstream - PROCESSES Erosion Abrasion or corrasion Attrition Hydraulic Action Solution or corrosion Deposition
More informationVietnam Coastal Erosion - Cause and Challenges -
Administration of Sea and Islands Center for Oceanography University of Transport and Communications, Hanoi Vietnam Vietnam Coastal Erosion - Cause and Challenges - Presenters: Pham Hoang KIEN Le Van CONG
More informationAvoiding Geohazards in the Mid-Atlantic Highlands by Using Natural Stream Principles
Avoiding Geohazards in the Mid-Atlantic Highlands by Using Natural Stream Principles J. Steven Kite, WVU Neal Carte, WVDOT Will Harman, Michael Baker Corp. Donald D. Gray, WVU Photo: W. Gillespie North
More informationPirai river (Bolivia)
Pirai river (Bolivia) Confluent of the Amazon river which average discharge is only 6 m3/s, but with peak discharge over 5000 m3/s, a challenge for river basin management and for flood control HYDROEUROPE
More informationGrant 0299-NEP: Water Resources Project Preparatory Facility
Document Produced under Grant Project Number: 45206 May 2016 Grant 0299-NEP: Water Resources Project Preparatory Facility Final Report Volume 3 East Rapti (1 of 9) Prepared by Pvt. Ltd. For Ministry of
More informationStream Restoration and Environmental River Mechanics. Objectives. Pierre Y. Julien. 1. Peligre Dam in Haiti (deforestation)
Stream Restoration and Environmental River Mechanics Pierre Y. Julien Malaysia 2004 Objectives Brief overview of environmental river mechanics and stream restoration: 1. Typical problems in environmental
More informationEROSION CONTROL FIELD GUIDE By Craig Sponholtz & Avery C. Anderson
WORKING WITH NATURE TO HEAL EROSION Soil loss caused by flowing water diminishes the fertility, productivity and healing capacity of the land. This guide was created to empower landowners and managers
More informationStep 5: Channel Bed and Planform Changes
Step 5: Channel Bed and Planform Changes When disturbed, streams go through a series of adjustments to regain equilibrium with the flow and sediment supply of their watersheds. These adjustments often
More informationmountain rivers fixed channel boundaries (bedrock banks and bed) high transport capacity low storage input output
mountain rivers fixed channel boundaries (bedrock banks and bed) high transport capacity low storage input output strong interaction between streams & hillslopes Sediment Budgets for Mountain Rivers Little
More informationSteven Noble MDEQ - WRD Enbridge Response Unit
EPA situation report, October 19, 2012 Steven Noble MDEQ - WRD Enbridge Response Unit Brief history of the spill Monitoring Monitoring the impacts Follow the oil The Current Situation A Look at the Future
More informationWhite River Update. Jeanne Stypula, Supervising Engineer. Advisory Committee Meeting April 26, 2016
White River Update Jeanne Stypula, Supervising Engineer Advisory Committee Meeting April 26, 2016 Department of Natural Resources and Parks Water and Land Resources Division River and Floodplain Management
More informationFUTURE MEANDER BEND MIGRATION AND FLOODPLAIN DEVELOPMENT PATTERNS NEAR RIVER MILES 200 TO 191 OF THE SACRAMENTO RIVER PHASE III REPORT
FUTURE MEANDER BEND MIGRATION AND FLOODPLAIN DEVELOPMENT PATTERNS NEAR RIVER MILES 200 TO 191 OF THE SACRAMENTO RIVER PHASE III REPORT Eric W. Larsen REPORT FOR DUCKS UNLIMITED March 31, 2006-1 - Contents
More informationWithin-event spatially distributed bedload: linking fluvial sediment transport to morphological change
Within-event spatially distributed bedload: linking fluvial sediment transport to morphological change C.D. Rennie 1, R. Williams 2, J. Brasington 3, D. Vericat 4, and M. Hicks 5 1 Department of Civil
More informationErosion and Deposition
CHAPTER 3 LESSON 2 Erosion and Deposition Landforms Shaped by Water and Wind Key Concepts What are the stages of stream development? How do water erosion and deposition change Earth s surface? How do wind
More informationThe last three sections of the main body of this report consist of:
Threatened and Endangered Species Geological Hazards Floodplains Cultural Resources Hazardous Materials A Cost Analysis section that provides comparative conceptual-level costs follows the Environmental
More informationA Quantitative Assessment of Human Interventions and Climate Change on the West African sediment budget
Public Disclosure Authorized Public Disclosure Authorized A Quantitative Assessment of Human Interventions and Climate Change on the West African sediment budget Public Disclosure Authorized The West African
More informationMATHEMATICAL MODELING OF FLUVIAL SEDIMENT DELIVERY, NEKA RIVER, IRAN. S.E. Kermani H. Golmaee M.Z. Ahmadi
JOURNAL OF ENVIRONMENTAL HYDROLOGY The Electronic Journal of the International Association for Environmental Hydrology On the World Wide Web at http://www.hydroweb.com VOLUME 16 2008 MATHEMATICAL MODELING
More informationLong Valley Meadow Restoration Project
Long Valley Meadow Restoration Project USDA Forest Service Mogollon Rim Ranger District Coconino National Forest Coconino County, Arizona T13N, R9E, Section 12 and T13N, R10E, Sections 6 and 7 Gila and
More informationLearning Objectives: I can identify and interpret river flows and directions.
Learning Objectives: I can identify and interpret river flows and directions. Bellringer Review: Check for Understanding Questions: 1 2 What Are The Key Parts Of A River s Anatomy? In your data notebooks
More informationNORTHUMBERLAND COUNTY, PA
QUAKER RUN Stream and Wetland Restoration As-Built Completion Report and First Year Monitoring Data Coal Township NORTHUMBERLAND COUNTY, PA Upstream Before Upstream After Prepared for: COAL TOWNSHIP 805
More informationGully Erosion Part 1 GULLY EROSION AND ITS CAUSES. Introduction. The mechanics of gully erosion
Gully Erosion Part 1 GULLY EROSION AND ITS CAUSES Gully erosion A complex of processes whereby the removal of soil is characterised by incised channels in the landscape. NSW Soil Conservation Service,
More informationGEOMORPHIC CHANGES IN LOWER CACHE CREEK 2012
GEOMORPHIC CHANGES IN LOWER CACHE CREEK 2012 Eric W. Larsen Technical Memorandum Prepared for Cache Creek Technical Advisory Committee Natural Resources Program Yolo County Board of Supervisors 2012 Prepared
More informationDecline of Lake Michigan-Huron Levels Caused by Erosion of the St. Clair River
Decline of Lake Michigan-Huron Levels Caused by Erosion of the St. Clair River W.F. & Associates Coastal Engineers (in association with Frank Quinn) April 13, 2005 Outline Problem Definition Understanding
More informationThe River Restoration Centre therrc.co.uk. Understanding Fluvial Processes: supporting River Restoration. Dr Jenny Mant
The River Restoration Centre therrc.co.uk Understanding Fluvial Processes: supporting River Restoration Dr Jenny Mant Jenny@therrc.co.uk Understanding your catchment Hydrology Energy associated with the
More informationThe Effects of Flooding on Structures. Or What to Expect when the Drought Ends Violently
The Effects of Flooding on Structures Or What to Expect when the Drought Ends Violently Let s Define Flood Increase in discharge compared to normal level Direct runoff of rainfall (we re talking about
More informationField Trip Number One. By: Pat Dryer. Geography 360
Field Trip Number One By: Pat Dryer Geography 360 Table of Contents Introduction. Page 1 Stop One... Page 2 Stop Two... Page 4 Stop Three... Page 5 Stop Four... Page 7 Bibliography Page 8 Campus Map Source:
More informationDolores River Watershed Study
CHAPTER 4: RIVER AND FLOODPLAIN ISSUES The Dolores River falls into a category of streams in Colorado that share some unique characteristics. Like some other mountain streams in the state, it has a steep
More informationIndigenous technical knowledge for bank erosion and flood management
2017 APEC Typhoon Symposium, May 2 4, 2017, GIS NTU Convention Center, Taipei Indigenous technical knowledge for bank erosion and flood management Hao Zhang 1) and Hajime Nakagawa 2) 1) Associate Professor,
More informationAnabranch management on a regulated reach of the Murray River
Anabranch management on a regulated reach of the Murray River Julian Martin 1 and Dean Judd 2 1 Earth Tech Pty Ltd, PO Box 165, Wangaratta, Victoria, 3676. Web: www.earthtech.com.au, Email: julian.martin@earthtech.com.au
More informationWORKSHOP #2 [Modeling and Sediment Transfers Review of alternative solutions] Bucharest 07 October 2015
STUDIU DE FEZABILITATE PENTRU SOLUŢII TEHNICE ALTERNATIVE/COMPLEMENTARE PRIVIND LUCRĂRILE CE SE VOR EXECUTA ÎN PUNCTUL CRITIC 01 BALA DIN CADRUL PROIECTULUI ÎMBUNĂTĂŢIREA CONDIŢIILOR DE NAVIGAŢIE PE DUNĂRE
More informationFluvial Processes in River Engineering
Fluvial Processes in River Engineering Howard H. Chang San Diego State University... A WILEY-INTERSCIENCE PUBLTCATION John Wiley & Sons New York Chicbester Brisbane Toronto Singapore CONTENTS PARTI FLUVIAL
More informationAppendix A Flood Damages in 2013
Appendix A Flood Damages in 2013 RPT2-2014-07-09-App_A_Highwood_River_Flood_Damage_In_2013.Docx Table of Contents page Sign-Off 1. Flood Damage in 2013... 1 1.1 Background... 1 1.2 Town of High River...
More informationRIVER BANK EROSION AND SUSTAINABLE PROTECTION STRATEGIES
B-11 Fourth International Conference on Scour and Erosion 2008 RIVER BANK EROSION AND SUSTAINABLE PROTECTION STRATEGIES Md.. Shofiul Islam 1 1 Scientific Officer, River Research Institute (RRI) (Faridpur
More informationMODELING OF LOCAL SCOUR AROUND AL-KUFA BRIDGE PIERS Saleh I. Khassaf, Saja Sadeq Shakir
ISSN 2320-9100 11 International Journal of Advance Research, IJOAR.org Volume 1, Issue 8,August 2013, Online: ISSN 2320-9100 MODELING OF LOCAL SCOUR AROUND AL-KUFA BRIDGE PIERS Saleh I. Khassaf, Saja Sadeq
More informationMORPHOLOGICAL PROCESSES AND EFFECTIVE RIVER EROSION MANAGEMENT: A CASE STUDY OF THE ARIAL KHAN RIVER IN BANGLADESH
MORPHOLOGICAL PROCESSES AND EFFECTIVE RIVER EROSION MANAGEMENT: A CASE STUDY OF THE ARIAL KHAN RIVER IN BANGLADESH Jakia Akter* 1, Maminul Haque Sarker, Preetha Haque 1 Center for environmental and Geographic
More information27. Running Water I (p ; )
27. Running Water I (p. 424-436; 440-444) Hydrosphere How much of the Earth s surface is covered by water? Earth's water is collectively called the and is stored in a number of so-called as follows: 1.
More informationSTABILITY OF OLD STONE GROINS IN THE KATSURA RIVER DURING FLOODS
B-10 Fourth International Conference on Scour and Erosion 008 STABILITY OF OLD STONE GROINS IN THE KATSURA RIVER DURING FLOODS Taisuke ISHIGAKI 1, Takahiro ASANO and Ryuji KAWANAKA 3 1 Member of JSCE,
More informationBowen Collinsville Enterprise Don River Sand and Flooding Briefing Report Prepared and presented by John Finlay April 9 th 2013
Bowen Collinsville Enterprise Don River Sand and Flooding Briefing Report Prepared and presented by John Finlay April 9 th 2013 1 Bowen Collinsville Enterprise Briefing Report on Don River 1. The Don River
More informationCurrent Status of Vietnam Coastal Erosion and Major Measures for Mitigation
Vietnam Administration of Sea and Islands Center for Oceanography University of Transport and Communications Current Status of Vietnam Coastal Erosion and Major Measures for Mitigation Case Study: Thanh
More informationLaboratory Investigation of Submerged Vane Shapes Effect on River Banks Protection
Australian Journal of Basic and Applied Sciences, 5(12): 1402-1407, 2011 ISSN 1991-8178 Laboratory Investigation of Submerged Vane Shapes Effect on River Banks Protection Touraj Samimi Behbahan Department
More informationDETAILED DESCRIPTION OF STREAM CONDITIONS AND HABITAT TYPES IN REACH 4, REACH 5 AND REACH 6.
DETAILED DESCRIPTION OF STREAM CONDITIONS AND HABITAT TYPES IN REACH 4, REACH 5 AND REACH 6. The Eklutna River was divided into study reaches (figure 1) prior to this site visit. Prominent geologic or
More informationScheepvaart en ecologische doelstellingen
Scheepvaart en ecologische doelstellingen Margriet Schoor 25 April 2008 The Rhine Delta Rotterdam 2/3 1/3 Scheepvaart en ecologische doelstellingen 2 Germany Navigation on the Rhine Busiest river in Europe
More informationIMPACTS OF SECONDARY FLOOD EMBANKMENTS ON THE WAIMAKARIRI FLOODPLAIN, NEW ZEALAND
IMPACTS OF SECONDARY FLOOD EMBANKMENTS ON THE WAIMAKARIRI FLOODPLAIN, NEW ZEALAND Terry van Kalken (1), Tony Oliver (2), Ian Heslop (2), Tony Boyle (2) (1) DHI Water & Environment, e-centre, Oaklands Road,
More informationOperative Chapter 13 Natural Hazards 31 January 2015 NATURAL HAZARDS
CHAPTER 13: NATURAL HAZARDS 13.0 INTRODUCTION Natural hazards have the potential to damage property, infrastructure and ecosystems, and threaten health and safety. Remedying the damage can cost individuals
More informationSTREAM RESTORATION AWRA Summer Specialty Conference, GIS and Water Resources IX
STREAM RESTORATION 2016 AWRA Summer Specialty Conference, GIS and Water Resources IX Innovative Use of 2D Hydraulic Modeling in Stream Restoration Design Presented by: Li Gao, PE and Robert Scrafford,
More informationNEWS RELEASE UNDER SECTION 404 OF THE CLEAN WATER ACT (33 USC 1344) ACTION NUMBER SPA ABQ
PUBLIC NOTICE Public Notice Issue Date: //6/07 Albuquerque District Comments due: /6/08 NEWS RELEASE UNDER SECTION 0 OF THE CLEAN WATER ACT ( USC ) ACTION NUMBER SPA-06-00-ABQ BANK STABILIZATION ALONG
More informationFinal Exam. Running Water Erosion and Deposition. Willamette Discharge. Running Water
Final Exam Running Water Erosion and Deposition Earth Science Chapter 5 Pages 120-135 Scheduled for 8 AM, March 21, 2006 Bring A scantron form A calculator Your 3 x 5 paper card of formulas Review questions
More informationCFD Modeling for Structure Designs in Environmental Impacts Mitigation
CFD Modeling for Structure Designs in Environmental Impacts Mitigation June 05 Navid Nekouee, Hugo Rodriguez and Steven Davie Environmental Impact Mitigation Design Savannah Harbor Expansion Project (SHEP)
More informationTechnical Memorandum. To: From: Copies: Date: 10/19/2017. Subject: Project No.: Greg Laird, Courtney Moore. Kevin Pilgrim and Travis Stroth
Technical Memorandum To: From: Greg Laird, Courtney Moore Kevin Pilgrim and Travis Stroth 5777 Central Avenue Suite 228 Boulder, CO 80301 www.otak.com Copies: [Electronic submittal] Date: 10/19/2017 Subject:
More informationEvaluation of Scour Depth around Bridge Piers with Various Geometrical Shapes
Evaluation of Scour Depth around Bridge Piers with Various Geometrical Shapes Dr. P. D. Dahe * Department of Civil Engineering, SGGSIE&T, Vishnupuri, Nanded (Maharashtra) S. B. Kharode Department of Civil
More informationCoastal erosion and coastal protection near the bridge across Jökulsá river, Breiðamerkursandur, Iceland
Coastal erosion and coastal protection near the bridge across Jökulsá river, Breiðamerkursandur, Iceland Helgi Jóhannesson 1 and Sigurður Sigurðarson 2 1 Public Roads Administration, Borgartún 7, IS-105
More informationRiver Processes. A) Write definitions for the terms erosion, transportation & deposition.
River Processes Lesson Aims To learn what is erosion, transportation and deposition. To learn which processes carry out erosion, transportation and deposition in river systems. Within rivers a number of
More information3.12 Geology and Topography Affected Environment
3 Affected Environment and Environmental Consequences 3.12 Geology and Topography 3.12.1 Affected Environment 3.12.1.1 Earthquakes Sterling Highway MP 45 60 Project Draft SEIS The Kenai Peninsula is predisposed
More informationControlling Processes That Change Land
1 Name Date Controlling Processes That Change Land People try to control some of the processes that change land. To do this, people apply technology- the use of science to solve problems in everyday life.
More informationGeo 302D: Age of Dinosaurs. LAB 2: Sedimentary rocks and processes
Geo 302D: Age of Dinosaurs LAB 2: Sedimentary rocks and processes Last week we covered the basic types of rocks and the rock cycle. This lab concentrates on sedimentary rocks. Sedimentary rocks have special
More information