STATUS REPORT FOR MAY JULY Spartan IR Camera for the SOAR Telescope. Edwin D. Loh

Size: px
Start display at page:

Download "STATUS REPORT FOR MAY JULY Spartan IR Camera for the SOAR Telescope. Edwin D. Loh"

Transcription

1 STATUS REPORT FOR MAY JULY 2003 Spartan IR Camera for the SOAR Telescope Edwin D. Loh Department of Physics & Astronomy Michigan State University, East Lansing, MI ext August 2003 During this reporting period, we (1) finished the metrology of the cryo-optical box, (2) began the cold test of the cryo-optical box, and (3) resumed work on the software. We have completed 80% of the milestones of the project. We have scaled back the instrument to have only J, H, and K filters. The budget is $57 k under the baseline: $44k for filters has been removed, but costs increased by $22 k since 30 April. Delivery of the instrument is delayed for 8 months until February mm D Figure 1 Left: The cryo-optical box suspended above the bathtub of the vacuum enclosure in the semi-clean foyer of the clean room. Center: First cool-down of the instrument without optics. Right: Errors, magnified by 10,000, of the locating pins on the top plate of the cryo-optical box.

2 2 Figure 2 Optical schematic. The red ray is the principal ray for the high-resolution, f/21 channel; the cyan ray, the wide-field, f/12 channel. 1 Project Status 1.1 Summary Problems with the mirrors, now expected in early October and 17 months late, will delay completion of the instrument to the end of February Axsys uses a computergenerated hologram (CGH) to produce a beam that is a spherical wave upon reflection off of the aspheric mirror (Figure 3). In addition the CGH produces two separate Figure 3 The computer-generated hologram (CGH) converts a plane wave entering from the interferometer at the left to a spherical wave if the mirror shape is correct. Picture is from Diffraction International, Minnetonka, MN,

3 3 beams to align itself to the interferometer and to the master plate, which holds the mirror. Axsys has had problems locating the beam that aligns the master plate. After attempting a mechanical alignment procedure for 8 months and failing, they have finally located the missing alignment beam. With metrology secured, they expect to polish one mirror a week. The Advanced Technologies and Instrumentation Program of the NSF funded the Widefield Upgrade for the Spartan IR Camera, for the installation of the third and fourth detectors. The Fundacao de Apoio a Universidade de São Paulo (FUSP) funded the third detector with a grant to Beatriz Barbuy of the Instituto de Astronomia, Geofisica e Ciências Atmosféricas (IAG) da Universidade de São Paulo. The Fundacao de Amparo a Pesquisa do Estado de São Paulo (FAPESP) funded the fourth detector with a grant to Sueli Viegas of the IAG. These detectors will be added approximately a year after commissioning. We have scaled back the project by eliminating the narrow-band filters; they can be added after delivery of the instrument if funds become available. The labor resources are tight. If any additional open-ended problems arise, additional resources will be needed. See 1.4. The project summary is in Table 1, and earned value analysis, percent complete, and work summaries by WBS are in Table 2. Changes since 30 April 2003, the date covered in the last report, are also in Table 2. More details are in Tables 3 4.

4 4 Table 1 Project Summary Status date 7/31/2003 Dates Start: Tue 9/4/01 Finish: 2/20/2004 Baseline Start: Mon 9/3/01 Baseline Finish: Tue 6/10/03 Actual Start: Tue 9/4/01 Actual Finish: NA Start Variance: 0 d Finish Variance: 183d Duration Scheduled: 644 d Remaining: 112 d Baseline: 461 d Actual: 532 d Variance: 183 d Percent Complete: 83% Work Scheduled: 16,550 h Remaining: 1,947 h Baseline: 8,733 h Actual: 14,603 h Variance: 7,817 h Percent Complete: 88% Costs Scheduled: $1,073,549 Remaining: $53,399 Baseline: $1,131,372 Actual: $1,0,150 Variance: ($57,823) Task Status Resource Status Tasks not yet started: 129 Work Resources: 0 Tasks in progress: 56 Overallocated Work Resources: 7 Tasks completed: 519 Material Resources: 0 Total Tasks: 704 Total Resources: Earned-value Analysis The schedule variance (SV) worsened by $12k since the last report 1. The schedule variance is due to delays in the fabrication of the mirrors (WBS and ) by Axsys Technologies and delayed installation of the instrument (WBS 1.7.5). The schedule variance in procurements is not real: inexplicably, some completed tasks show a schedule variance. The variance at completion (VAC) improved by $24k since the last report, primarily for three reasons. (1) We removed the narrow-band filters. (2) The bills for work by mechanical fabrication by vendors and for materials, which were paid in this reporting period, had not been entered accurately in the project file. (3) We damaged two rotation stages by allowing moisture to condense on the bearings; repair is costly. 1 Earned value analysis does not apply here to work charged under Fixed Costs, WBS 1.1.7, (Biel, Chen, Davis, Laporte, Lien, and Loh); therefore it cannot show problems in work done by them. It can show problems with purchased parts and labor that is charged by the hour.

5 5 Table 2 Earned value analysis, % complete, and work. A positive schedule variance, SV, indicates the project is ahead of schedule. A positive cost variance, CV, or variance at completion, VAC, indicate the project is less costly than budgeted. WBS Task BCWP[$] SV [$] CV [$] EAC [$] BAC [$] VAC [$] %WC %C W [hr] RW[hr] 1 Spartan IR Camera 1,065,1 (66,352) 44,871 1,073,549 1,131,372 57,824 88% 83% 16,550 1, Project Management 156,619 (5,000) 2, , ,619 (14,939) 96% 97% 1, System Engineering (1,996) 2, (2,056) 100% 100% 1, Mechanical 338,979 (29,081) 43, , ,060 63,370 94% 85% 8, Electronics 10,105 (2,600) ,426 12,705 2,279 89% 88% 2, Software 10,000 (800) 3,860 7,722 10,800 3,078 89% 54% 1, Integration 2,200 (1,600) 2,018 2,445 3,800 1,355 36% 40% 1, Deliverables 2,600 (18,200) ,956 20,800 5,844 46% 50% Procurement 111,417 (9,131) (6,000) 121, ,548 (801) 98% 99% Preplan Spending 432,321 0 (307) 432, ,321 (307) 100% 100% 0 0 Change from 04/30/03 1 Spartan IR Camera 17,924 (11,804) (21,829) (24,168) 0 24,168 6% 1% 1,536 (755) 1.1 Project Management 6,364 (6,364) (5,513) (1,932) 0 1,932 5% 0% 182 (60) 1.2 System Engineering % 1% 47 (11) 1.3 Mechanical 8,560 8,560 (15,824) (22,044) 0 22,044 7% 4% 929 (426) 1.4 Electronics 0 0 (520) (726) % 1% 303 (107) 1.5 Software 0 0 (1,140) (418) % -32% 8 (70) 1.6 Integration (672) 2% 1% (52) (55) 1.7 Deliverables 1,000 (16,000) (552) % 22% 33 (82) 1.8 Procurement 2,000 2,000 1, (280) 0% 0% Preplan Spending % 0% 0 0 BCWS Budgeted cost of work scheduled BAC Budget at completion BCWP Budgeted cost of work performed VAC Variance at completion; VAC=BAC-EAC ACWP Actual cost of work performed %WC Work completed SV Schedule variance; SV=BCWP-BCWS %C Percent completed; (duration of the task) / (total duration) CV Cost variance; CV=BCWP-ACWP W Work EAC Estimate at completion RW Remaining work

6 6 Table 3 Details on earned value, % completion, and work for WBS The change since 30 April 2003 is in the last three columns. WBS Task EAC [$] BAC [$] VAC [$] %WC %C W[hr] RW[hr]dW drw dvac 1.1 Project Management 176, ,619 (14,939) 96% 97% 1, (60) 1, Schedule & Budget 5,728 6, % 98% (2) Weekly Meetings % 84% (7) Reviews % 0% (38) (38) Monthly & Quarterly Reports % 94% (17) Manage % 100% Consultants 0 10,000 10, % 100% Fixed Cost 167, ,008 (27,685) 100% 96% (0) 1, Travel 1,000 5,000 4,000 0% 67% Move Laboratory (136) 100% 100% Training (645) 100% 100% Hire Engineer/Designer 1,356 0 (1,356) 100% 100% Maintain Laboratory % 100% System Engineering 2, (2,056) 100% 100% 1, (11) Optics % 100% Analysis % 100% Plans % 100% Requirements/ICDs/Review D (192) 100% 100% (3) Software Requirements % 100% Master Layout 2, (1,864) 100% 100% Mechanical 304, ,060 63,370 94% 85% 8, (426) 22, Cryo-Optical Box 31,514 41,188 9,674 98% 97% 2, (78) (5,107) Thermal Reflector 3,518 3, % 100% (108) Vacuum Enclosure 17,373 27,380 10, % 100% (1,721) Filter Wheel 6,607 12,400 5,793 81% 91% (43) Rotational Stage 52,496 44,450 (8,046) 97% 89% (10,000) Mirrors & Mounts 96,188 98,575 2,387 90% 56% (1,206) Mirrors 81,435 95,975 14,540 88% 13% Mounts for Mechanisms 8,113 1,800 (6,313) 100% 100% (624) Mounts for Mirrors 6, (5,839) 83% 93% (582) Filters 6,650 51,000 44, % 100% , Upgrades 82,714 84,186 1,472 93% 75% 1, (94) (813) nd Channel Mirrors & Moun 78,816 80,055 1,239 86% 68% (24) (258) Mask Wheel Upgrade 1,468 4,131 2,663 63% 84% (9) (26) Eyed Focal Plane Assembly 2,430 0 (2,430) 100% 100% (39) (1,035) Eyed Focal Plane Mechanis % 100% (8) (7) Metrology & Acceptance Test 2,743 0 (2,743) 96% 97% (77) (1,511) Fixtures 4,887 0 (4,887) 81% 85% (161) (1,623) 1.4 Electronics 10,426 12,705 2,279 89% 88% 2, (107) Detector Assembly 4,200 6,920 2,720 86% 85% 1, (109) Electronic Hardware 6,226 5,785 (441) 100% 100% Software 7,722 10,800 3,078 89% 54% 1, (70) Select Vendor for Software % 100% Write Minimal Software 5,000 10,000 5, % 100% Write Baseline Software 1,140 0 (1,140) 100% 100% (13) (92) Write Operating Software 1,582 0 (1,582) 8% 1% (3)

7 7 Table 4 Details on earned value, % completion, and work for WBS The change since 30 April 2003 is in the last three columns. WBS Task EAC [$] BAC [$] VAC [$] %WC %C W[hr] RW[hr] dw drw dvac 1.6 Integration 2,445 3,800 1,355 36% 40% 1, (52) (55) (672) Telescope Simulator 1,773 3,800 2,7 78% 77% (2) Integration (672) 0% 0% (52) (52) (672) Install optics (160) 0% 0% (20) (20) (160) Optical Alignment (512) 0% 0% (512) Flexure Test % 0% Cold Tests % 0% (32) (32) Acceptance Tests % 0% Project Complete % 0% Deliverables 14,956 20,800 5,844 46% 50% (82) Manuals % 59% (39) Acceptance Test % 0% Pack & Ship 4,476 4, % 51% (45) Documentation 480 1, % 48% (1) Installation 10,000 15,000 5,000 0% 0% Procurement 121, ,548 (801) 98% 99% (280) Procure Computers for Labora 2,552 2,400 (152) 100% 100% Procure Solidworks License 4,643 1,645 (2,998) 100% 100% Procure Dust-free Hood 0 3,000 3, % 100% Procure Parts for Test Dewar 0 2,000 2, % 100% Procure Field-flattening Lens 6,280 2,000 (4,280) 100% 100% (280) Procure Vacuum Bulkhead 2,605 4,300 1, % 100% Procure 4 Additional Rotation 61,968 67,040 5, % 100% Procure Parts for Vacuum Enc 7,949 7,163 (786) 100% 100% Procure Parts for Telescope Si % 100% Procure Window 6,617 8,000 1, % 100% Procure Coordinate Measuring 23,212 22,500 (712) 100% 100% Procure Mask % 67% Misc Supplies 3,932 5,000 1,068 0% 0% Procure Instrument Computer 1,091 0 (1,091) 100% 100% Preplan Spending 432, ,321 (307) 100% 100% Schedule The remaining tasks are to finish fabrication and to test the mechanical parts (WBS 1.3), to accept delivery of the mirrors (WBS & ), testing the electronics (WBS 1.4.1), finish the software (WBS 1.5) and integration (WBS 1.6). The Gantt chart (Figure 4.) shows the tasks on the critical path, which contains Mirrors and Integration. The critical path means this: delay in any of these tasks causes a delay in the completion of the project. Installation of the optics is scheduled to start in late October 11.

8 Figure 4 Gantt chart of incomplete summary tasks and incomplete tasks on the critical path. The text to the right of the bar line is the percent of the work completed for summary tasks and the completion date for other tasks. 8

9 9 1.4 Work Summary From 1 May to 31 July, we worked 2,254 hours and the remaining work decreased by 681 hours. The work efficiency, defined to be the ratio of the change in the remaining work to the change in the actual work, is 30%, which is about the same as that of the last reporting period. The project will need more resources in all likelihood. If all of the labor is expended at the end of the project, then the work efficiency must rise to 70% during the remaining time. Such high efficiency is not possible if problems arise as they have done in the past. There are several key milestones where time-consuming problems may arise. (1) Milestone 88: Detector Tested in Lab, (2) Milestone 111: Cryo-Optical Box Thermal Test Finished, (3) Milestone 132: Instrument Assembled & Aligned at Room Temperature, (4) Milestone 133: Flexure Tested, (5) Milestone 136: Cold Test #1 [of Entire Instrument] Finished. The other milestones, which involve fabrication, writing documentation, and writing software, are not expected to cause open-ended problems. Hours Actual Remaining Variance Jul-01 Feb- Sep- Mar-03 Oct-03 Date dremaining / dactual 120% 100% 80% 60% 40% 20% 0% Jul-01-20% Feb- Sep- Mar-03 Oct-03-40% -60% Date Figure 5 Work summary (top) and work efficiency (bottom). "Actual" is the number of hours expended. "Remaining" is the estimated hours to complete the project. Variance = Actual + Remaining Baseline. 1.5 Milestones The time-phased completion of the milestones is in Figure 6, and a complete list of milestones is in the Appendix. We have finished 80% of the 147 milestones.

10 10 Figure 6 Cumulative number of milestones completed (blue) and not completed (magenta) vs. date. 160 Milestones S O N D- 01 J- F M A- M- J- J A S- O- N- D- J- 03 F- 03 M- 03 A- 03 M- 03 J- 03 J- 03 A- 03 S Personnel Jianjun Chen finished his master s project, Control Software for the Motors, Spartan IR Camera, in May, and left the project. Nate Verhanovtiz, a graduate student in mechanical engineering, joined the project in May. His responsibility is software. 2 Task Details Refer to Table Project Management (WBS 1.1) The cost of labor for the extension in the schedule is included. 2.2 System Engineering (WBS 1.2) There is nothing to report.

11 11 Table 5 Cost and work by WBS WBS Task Work [hr] Cost [$] dwork May03 EAC Variance Remainin EAC VAC RemainingdEAC dremainin 1 Spartan IR Camera 16,678 7,945 2,095 1,073,901 57,472 53, Project Management 1, ,558 (14,939) 22, System Engineering 1, ,776 (2,056) Mechanical 8,233 4, ,2 62,858 9, Cryo-Optical Box 2, ,514 9, MLI Blanket 60 (11) 0 2,533 1, CryoBox 1, ,822 (1,942) Mask Plate , A-Frame 52 (220) , N2 Can 225 (196) 0 4,654 5, Thermal Reflector , Vacuum Enclosure ,373 10, Filter Wheel ,607 5,793 2, Rotational Stage ,496 (8,046) 5, Mirrors & Mounts ,188 2, Mirrors ,435 14, Mounts for Mechanisms ,113 (6,313) Mounts for Mirrors ,639 (5,839) Filters ,650 44, Upgrades 1, ,842 1, nd Channel Mirrors & Mounts [Upg 589 (179) 94 78,944 1, Mask Wheel Upgrade 134 (121) 60 1,468 2, Eyed Focal Plane Assembly ,430 (2,430) Eyed Focal Plane Mechanism Metrology & Acceptance Tests ,839 (2,839) Fixtures ,175 (5,175) 1, Electronics 2,347 1, ,426 2, Software 1,120 1, ,722 3,078 1, Integration 1,097 (161) 721 2,285 1,515 2, Deliverables ,956 5,844 13, Procurement ,349 (801) 3, Preplan Spending ,628 (307) Mechanical Cryogenic Optical Box (WBS ) The two major tasks are measuring the cryo-optial box (COB) and the thermal test Measure Cryo-Optical Box (WBS ) Since the cryo-optical box (COB) supports the optics, the positions of the locating pins and the locating pads must be accurate to 0.1 mm at the tightest, and the relative locations of pairs of pins that locate mirrors must be accurate to 0.01 mm. The accuracy is beyond the capability of machining and requires metrology and shims. See the shim assembly for the filter wheels and fold mirrors (Figure 11). Here we report the metrology of the two large plates, called the top and bottom, to which the optics mount. Directions are defined in Figure 7.

12 12 Figure 7 The cryo-optical box. The edges of the walls define the vertical position of the optics; the plates conform to the walls. The measurement of the bottom edge of the walls deviates by up to 0.12 mm 800 back back inside wall from a plane. See figure 8. The deviation is mainly a twist: the right side of the back wall is down by 0.12 mm and the 600 left side is up by 0.08 mm. 400 inside wall The errors of the locating pins are quite small and well within the range of adjustment of the shim plates. The errors left and right halves are different (Figure 9). Apparently, the machining occurred on two days, and the temperature was 2.2 C cooler when the right half was machined. We have devised a procedure for assembling the COB reproducibly. With the bolts snug but not tight, we measure front front F R Figure 8 Deviation, magnified by 2000, of the bottom edge of the walls from a plane. The right edge of the back wall is low (shifted away from the top) by 0.12 mm.

13 13 and adjust the twist. Then we tighten the bolts. The twist, 0.3 mrad/m, is reproducible to 0.03 mrad/m, which translates to a maximum error of 0. mm in height Cl 12Cl' 12Cm 12Cm' Cl 12Cl' 12Cm 12Cm' refa 21Cm 21 refa 21Cm Cl 21Cl' Cl 21Cl' 600 ff refc 600 ff refc 400 af 400 af 200 m m' refb ff' da' da 200 m m' refb ff' da' da Figure 9 Errors (magnified by 10,000) of the pin holes in the top (left panel) and bottom (right panel) plates. Points with errors less than 0.005mm are shown as dots. The points are shifted so that refa has zero error and rotated so that refb has minimal error. The largest errors are 0.041mm [1.6mil] and 0.047mm [1.9mil] for the top and bottom respectively. The labels are m for mask, ff for filter-fold mirror assembly, 21Cl and 12Cl for f/21 and f/12 collimators, 12Cl and 21Cm for f/12 and f/21 collimators, da for detector assembly, and refa, refb, and refc for reference holes Cryo-Optical Box Thermal Test (WBS ) The thermal and vacuum design, though tested with a small dewar, is theoretical; now we test the design for the first time. With the COB in the vacuum enclosure and cooled, the questions are Is the pressure low enough (0.03 mtorr) that heat loss by molecular conduction is lower than that by radiation? Does a test load, here a cradle for a rotation stage, cool at the same rate are the COB? If so, the thermal conductance of the bolted joints is sufficiently high. What is the cooling time of the COB? What is the heat load? This is measured by the rate of nitrogen boil-off.

14 14 We have assembled the COB in the vacuum enclosure (Figure 10). The results of the first run are The e-fold time for cooling a dummy load is 3.4 hr. To cool within 1K of equilibrium requires 17 hr. The heat load is a factor of 3 higher than expected, primarily because the gas pressure, 0.1 mtorr, is too high. We plan to determine the composition of the residual gas in order to reduce the pressure. Figure 10 The cryo-optical box, which is wrapped in the aluminized mylar blanket, is suspended over the bathtub of the vacuum enclosure in the foyer of the clean room Eyed Focal-Plane Assembly (WBS ) The 2-eyed focal-plane assembly, which holds two detectors, is done. See Figure Fixtures (WBS ) The Lifting Jig for the COB (WBS ) is finished. It is in use in Figure 10. The Test Stand for Flexure Test (WBS ) is being fabricated. The Nitrogen Fill & Flush System (WBS ) has been designed.

15 15 Pin Figure 11 Left: Filter-fold assembly for the two filter wheels and their rotation stages and the two fold mirrors. Note the hole for one of two pins that locate the assembly accurately in the cryo-optical box. Right: 2-eyed focal-plane assembly without the detector cards and detectors.

16 16 The Clean Area for Assembly (WBS ), which consists of a clean bench, a clean room, and a clean hood for the coordinate-measuring machine, is finished. The clean room is in use in Figure 10. The racks for the computer, motor controller, and electronics (WBS ) are being designed. 2.4 Electronics (WBS 1.4) MUX Test at Cold Temperature (WBS ) We discovered a problem with the test of the multiplerer. (A multiplexer is a detector without the HgCdTe sensing layer.) The multiplexer does not accumulate more photoelectrons with a longer exposure time, even though it can produce an image. 2 Since Rockwell has not tried it, we have abandoned this test Cold Lab Test of Engineering-grade Detector (WBS ) We have installed the engineering-grade detector. Testing is in progress. 2.5 Software (WBS 1.5) We have reorganized the software tasks. The engineering software (WBS 1.5.3) is used during testing, and the operating software is used for observing. The engineering software has all of the functions for operating the instrument and many diagnostics. It does not have links to the telescope control system or to the data control system. The operating software (WBS 1.5.4) does have links to the rest of the observatory. Furthermore, it must be transparent so that a novice such as the PI can change the operation of the detector as needed. The engineering software is done. In the process of testing the multiplexer, we discovered timing problems with the old software, the engineering software was rewritten from scratch. We have used this software extensively. The observing software communicates with other parts of the observatory through these packages. (1) A sequencer controls it and the telescope. (2) A FITS server formats pictures. (3) A data system 2 Loh, 2003, Status Report for October 20 April 2003, Spartan IR Camera.

17 17 saves data and displays pictures. (4) An event logger saves instrumental events and observing events. In addition, the observing software has a graphical user interface (GUI) for the astronomer. We are working on the observing software. We will add links to the packages as they become available. 2.6 Integration (WBS 1.6) There is nothing to report. 2.7 Deliverables (WBS 1.7) Maintenance Manual (WBS ) We have sent a draft of the maintenance manual to S. Heathcote for review. Included is the procedure for installing the mask wheel. That procedure with modifications for each case will be used for installing all of the optics Design and Fabricate Shipping Container (WBS ) The design is complete. Shock absorbers will transfer a 3-g acceleration to the instrument if the shipping container is dropped 15-cm. 2.8 Procurement (WBS 1.8) Procure Field-flattening Lens (WBS 1.8.5) The lenses have been delivered Procure 4 Additional Rotation Stages [Upgrade] (WBS 1.8.7) We damaged two rotation stages by allowing moisture to condense on the bearings. For testing, we now cool the surrounding air to dry it before cooling the rotation stage. We designed a mechanism with a spring to remove the backlash. 2.9 Preplan Spending (WBS 1.9) There is nothing to report.

18 18 3 Appendix Table 6 Milestones Milestone Completed 117 of 147 (79.6%) Date Baseline Completed Scheduled Variance 1 Requisition for Flexible Cable Issued 4-Sep-01 1-Oct d 2 Requisition for Rotation Stage Issued 6-Sep-01 6-Sep-01 0 d 3 Optical Design Finished 7-Sep-01 7-Sep-01 0 d 4 N2 Can Engineered 7-Sep-01 7-Sep-01 0 d 5 A-Frame Strut Engineered 17-Sep Nov d 6 Requisition for Vacuum Blukhead Issued 17-Sep-01 7-Sep-01-6 d 7 Requirements for Optical Alignment Written 17-Sep Sep-01 0 d 8 Vacuum Enclosure & Cryo Box ICD Written 18-Sep Sep-01 9 d 9 Controller Card SCA Tested (Existing Computer 21-Sep Dec d 10 Detector Physical Dimensions Measured 24-Sep Sep-01-2 d 11 Requisition for Mirrors Issued 28-Sep Feb- 104 d 12 Requisition for Detector PCB Issued 28-Sep Nov d 13 Software Requirements Written 28-Sep Sep-01 0 d 14 Method for Optical Alignment Created 1-Oct-01 3-Jan- 68 d 15 Specifications for Telescope Simulator Written 3-Oct-01 3-Oct-01 0 d 16 Requisition for Coordinate-Measuring Machine I 5-Oct Nov d 17 Detector Assembly Concept Developed 8-Oct-01 3-Dec d 18 Solidworks License Delivered 11-Oct-01 9-Oct-01-2 d 19 Mechanism Mounting Blocks Engineered 12-Oct Sep d 20 Select SW Vendor 12-Oct Oct-01 1 d 21 Test-Dewar Concept Sketch Finished 15-Oct Oct-01 4 d 22 Vacuum Bulkhead Delivered 15-Oct Feb- 97 d 23 N2 Can Designed 18-Oct Jan- 60 d 24 Requisitions for Computer for Laboratory Issued 19-Oct Oct-01-2 d 25 Detector Holder Prototype Designed 25-Oct-01 4-Feb- 72 d 26 Mechanism Mounting Blocks Designed 29-Oct-01 8-Mar- 95 d 27 Rotation Stage Test Fixture Engineered 31-Oct Dec d 28 Coordinate-Measuring Machine Delivered 2-Nov Feb- 73 d 29 Rotation Stage Test Fixture Designed 7-Nov-01 7-Jan- 43 d 30 Flex Cable Finished 9-Nov-01 8-Nov-01-1 d 31 Computers for Laboratory Delivered 9-Nov Dec d 32 Project Plan Finished 16-Nov Dec d 33 Cryo-Optical Box Engineering Finished 16-Nov Nov-01 8 d 34 Detector Holder Prototype Fabricated 19-Nov Jun- 157 d 35 Test-Dewar Fabricated 19-Nov Apr- 113 d 36 Detector PCB Finished 21-Nov-01 4-Mar- 73 d 37 Master Layout Designed 26-Nov Nov-01-1 d 38 Rotation Stage Delivered 29-Nov-01 6-Feb- 50 d 39 A-Frame Strut 3D Designed 30-Nov Nov-01 0 d 40 Specifications for Vacuum Enclosure Written 6-Dec Oct d 41 Rotation Stage Test Fixture Fabricated 7-Dec-01 8-Feb- 45 d 42 Requisition for Field-flattening Lenses Issued 7-Dec Oct- 225 d 43 Mask Plate Engineering Finished 7-Dec Feb- 56 d

19 44 Requisition for Window Issued 10-Dec-01 8-Feb- 44 d 45 MLI Requisition Issued 10-Dec-01 3-Dec- 256 d 46 Flex Cable/Bulkhead Assembly Finished 11-Dec Feb- 56 d 47 Specification for Filter Wheels Written 14-Dec Dec-01-4 d 48 Rotation Stage Tested 14-Dec-01 4-Apr- 79 d 49 Mechanism Mounting Blocks Fabricated 14-Dec-01 4-Dec- 254 d 50 Joined Filter Consortium 14-Dec May- 112 d 51 Requisitions for Vacuum Parts Initiated 20-Dec Apr- 86 d 52 Requisition for Rotation Stage Controller & 2nd 25-Dec-01 1-Mar- 48 d 53 Cable for Motors Analyzed 28-Dec-01 8-Feb- 30 d 54 Mask Plate Designed 28-Dec May- 97 d 55 Detector Holder Prototype Thermal Test Finishe 1-Jan- 19-Sep- 187 d 56 Vacuum Enclosure Engineered 3-Jan- 31-Oct d 57 MLI Designed 8-Jan- 12-Feb- 25 d 58 Thermal Reflector Engineered 9-Jan- 17-May- 92 d 59 Deliver Communications Test Software 14-Jan- 30-Jan- 12 d 60 Requirements for Window Written 15-Jan- 18-Jan- 3 d 61 Requirements for Field-Flattening Lens Written 15-Jan- 8-Feb- 18 d 62 Requirements for Telescope Simulator Modified 15-Jan- 10-Dec d 63 Requirements for Pyramidal MirrorWritten 15-Jan- 8-Feb- 18 d 64 Motor PCB Designed 18-Jan- 24-Jun- 110 d 65 Filter Wheel Mounting Block Specified 21-Jan- 21-Sep d 66 MUX Tested at Room Temperature 22-Jan- 8-May d 67 Parts for Test Dewar Assembled 25-Jan- 8-Feb- 10 d 68 Cryo-Optical Box Drawings Finished 30-Jan- 18-Oct- 188 d 69 Vacuum Parts Delivered 31-Jan- 15-Jul- 117 d 70 Telescope Simulator Engineered 31-Jan- 3-Jul- 109 d 71 MUX Tested at Cold Temperature 1-Feb- 5-Aug d 72 Requistions for Parts for Telescope Simulator Iss 8-Feb- 26-Sep- 164 d 73 Motor PCB Fabricated 8-Feb- 10-Jul- 108 d 74 Communications with NI6533 Card Tested 20-Feb- 20-Feb- 0 d 75 Vacuum Enclosure Designed 22-Feb- 13-Nov- 189 d 76 Upgrade Decision for 2nd Channel Made 28-Feb- 10-Jun- 72 d 77 Web Site Created 28-Feb- 8-Mar- 6 d 78 MLI Blanket Delivered 7-Mar- 31-Jan d 79 Thermal Reflector Concept Analyzed 8-Mar- 1-Mar- -6 d 80 Telescope Simulator Designed 11-Mar- 25-Feb d 81 Parts for Telescope Simulator Delivered 13-Mar- 26-Sep- 141 d 82 A-Frame Strut Fabricated 15-Mar- 14-Dec d 83 Software Drives Detector Controller 20-Mar- 14-Mar- -4 d 84 Mask Plate Finished 22-Mar- 5-Jun- 53 d 85 Thermal Reflector Designed 22-Mar- 30-May- 49 d 86 Vendor for Thermal Reflector Selected 22-Mar- 29-Oct- 157 d 87 N2 Can Fabricated 28-Mar- 10-Apr d 88 Detector Tested in Lab 2-Apr- 3-Sep ArcView Drives Detector Controller 3-Apr- 28-Jun- 62 d 90 Rotation Stage Controller & 2nd Stage Delivered 8-Apr- 15-Oct- 137 d 91 Cryo-Optical Box Fabricated 9-Apr- 30-Apr d 92 Detector Tested with Sky 10-Apr- 11-Sep Software Drives Filter Wheels 10-Apr- 20-Sep- 116 d 94 Filter Wheel Designed 12-Apr- 26-Apr- 10 d 95 Minimal Software Complete 24-Apr- 20-Sep- 106 d 19

20 96 Detector Assembly Designed 30-Apr- 17-Mar d 97 Reworked Electronics Finished 1-May- 1-Oct GUI Complete 1-May- 25-Jul d 99 Mirrors Delivered 6-May- 6-Oct Window Delivered 9-May- 2-May- -5 d 101 Baseline Software Complete 14-May- 25-Jul d 1 Thermal Reflector Fabricated 15-May- 15-Nov- 132 d 103 Telescope Simulator Fabricated 17-May- 7-Jul Mirrors Installed in Mounts 20-May- 20-Oct Mask Wheel Engineered 21-May- 25-Feb- -61 d 106 Vacuum Enclosure Finished 24-May- 13-Mar d 107 Mirror Mounts Engineered 31-May- 15-Jul- 31 d 108 Mirror Mounts Detailed 12-Jun- 8-Aug- 41 d 109 Collimator and Camera Mirror Mount Designed 14-Jun- 14-Mar d 110 Mask Wheel Designed 18-Jun- 15-May- -24 d 111 Cryo-Optical Box Thermal Test Finished 21-Jun- 8-Sep Operating Software Complete 25-Jun- 26-Sep Mirror Mounts Fabricated 10-Jul- 13-Jan d 114 Filter Wheels Fabricated 12-Jul- 4-Dec- 103 d 115 Field-Flattening Lenses Delivered 12-Jul- 18-Aug d 116 Test Plan for Filter Wheel Written 12-Jul- 13-May- -45 d 117 Detector Assembly Fabricated 15-Jul- 16-Jun Detector Assembly Finished 22-Jul- 15-Oct Focal-Plane Assembly Designed 23-Jul- 19-Apr d 120 Mask Wheel Fabricated 31-Jul- 21-May d 121 Filter Wheel #1 Tested Warm 7-Aug- 10-Dec- 89 d 122 Focal-plane Assembly Fabricated 13-Aug- 27-Jun d 123 Filter Wheel #1 Tested Cold 15-Aug- 15-Aug- 124 Filter Wheel #2 Tested 22-Aug- 10-Dec- 79 d 125 Mask Wheel Tested 3-Sep- 24-Jun F/21 Collimator & Camera Mirrors Delivered [U 13-Sep- 6-Oct nd Collimator and Mirror Mount Fabricated 13-Sep- 6-Jun d 128 Telescope Simulator Finished 7-Oct- 23-Jul nd Collimator and Mirror Mount Tested 17-Oct- 1-Jul Basic Filters Delivered 13-Dec- 3-Jan d 131 All Filters Delivered 13-Dec- 3-Jan d 132 Instrument Assembled & Aligned at Room Temp 21-Jan Nov Flexure Tested 28-Jan Nov Draft Maintenance Manual Written 14-Feb-03 6-Aug d 135 Draft Software Manual Written 14-Feb-03 9-May Cold Test #1 Finished 18-Feb-03 8-Dec As-Built Drawing Package Assembled 28-Feb Feb Draft Operating Manual Written 14-Mar Mar Maintenance Manual Finished 31-Mar Sep Software Manual Finished 31-Mar Jun Draft Acceptance Test Written 31-Mar Aug Shipping Container Finished 31-Mar Jun Cold Tests Finished 11-Apr Jan Operating Manual Finished 30-Apr Apr Acceptance Test Written 7-May Sep Pre-Ship Acceptance Test Finished, Integration C 14-May-03 5-Feb Project Complete 10-Jun Feb-04 20

November 3, 2014 Eric P. Smith JWST Program Office

November 3, 2014 Eric P. Smith JWST Program Office November 3, 014 Eric P. Smith JWST Program Office 1 SINCE LAST CAA MEETING... Completed of 3 recommended GAO schedule risk analyses for this year. Mutually agreed to drop 3 rd. Will perform cost-risk study

More information

PS2 Status Report. Nick Kaiser Pan-STARRS, Institute for Astronomy, U. Hawaii. Durham Workshop 2013/01/08. Monday, January 7, 13

PS2 Status Report. Nick Kaiser Pan-STARRS, Institute for Astronomy, U. Hawaii. Durham Workshop 2013/01/08. Monday, January 7, 13 PS2 Status Report Nick Kaiser Pan-STARRS, Institute for Astronomy, U. Hawaii Durham Workshop 2013/01/08 The near term future for Pan-STARRS: PS1+2 PS1 survey mission to end 12/2013 PS2 telescope delivery

More information

LIGO workshop What Comes Next for LIGO May 7-8, 2015, Silver Spring, MD KAGRA KAGRA. Takaaki Kajita, ICRR, Univ. of Tokyo for the KAGRA collaboration

LIGO workshop What Comes Next for LIGO May 7-8, 2015, Silver Spring, MD KAGRA KAGRA. Takaaki Kajita, ICRR, Univ. of Tokyo for the KAGRA collaboration LIGO workshop What Comes Next for LIGO May 7-8, 2015, Silver Spring, MD KAGRA KAGRA Takaaki Kajita, ICRR, Univ. of Tokyo for the KAGRA collaboration Outline Introduction: Overview of KAGRA Status of the

More information

A PRELIMINARY ALIGNMENT PLAN FOR RIA AT MSU

A PRELIMINARY ALIGNMENT PLAN FOR RIA AT MSU IWAA2004, CERN, Geneva, 4-7 October 2004 A PRELIMINARY ALIGNMENT PLAN FOR RIA AT MSU D. P. Sanderson, NSCL-MSU, 1 Cyclotron Lab, East Lansing, MI 48824, USA 1. INTRODUCTION The Rare Isotope Accelerator

More information

SYSTEM BRIEF DAILY SUMMARY

SYSTEM BRIEF DAILY SUMMARY SYSTEM BRIEF DAILY SUMMARY * ANNUAL MaxTemp NEL (MWH) Hr Ending Hr Ending LOAD (PEAK HOURS 7:00 AM TO 10:00 PM MON-SAT) ENERGY (MWH) INCREMENTAL COST DAY DATE Civic TOTAL MAXIMUM @Max MINIMUM @Min FACTOR

More information

Next Generation SOFIA Science Instrument Call for Proposals

Next Generation SOFIA Science Instrument Call for Proposals Next Generation SOFIA Science Instrument Call for Proposals Kimberly Ennico-Smith NASA SOFIA Project Scientist Alan Rhodes NASA SOFIA Science Instrument Development Manager NASA Ames Research Center Outline

More information

SPICA/SAFARI (SPace Infrared telescope for Cosmology and Astrophysics)

SPICA/SAFARI (SPace Infrared telescope for Cosmology and Astrophysics) SPICA/SAFARI (SPace Infrared telescope for Cosmology and Astrophysics) 1 SPICA/SAFARI (SPace Infrared telescope for Cosmology and Astrophysics) Summary SAFARI (SPICA far-infrared instrument) is an imaging

More information

GAMINGRE 8/1/ of 7

GAMINGRE 8/1/ of 7 FYE 09/30/92 JULY 92 0.00 254,550.00 0.00 0 0 0 0 0 0 0 0 0 254,550.00 0.00 0.00 0.00 0.00 254,550.00 AUG 10,616,710.31 5,299.95 845,656.83 84,565.68 61,084.86 23,480.82 339,734.73 135,893.89 67,946.95

More information

March 4, 2013 Eric P. Smith JWST Program Office

March 4, 2013 Eric P. Smith JWST Program Office March 4, 2013 Eric P. Smith JWST Program Office 1 SIMPLIFIED SCHEDULE OTE = Optical Telescope Element OTIS = Optical Telescope + ISIM k months of project funded critical path (mission pacing) schedule

More information

Nanostructured alumina materials characterization study

Nanostructured alumina materials characterization study I-3. Development of mini-focus SANS Main collaborator: Abdul Aziz Mohammed Malaysian Nuclear Agency (Nuclear Malaysia) Kompleks PUSPATI, Bangi 43000 Kajang Selangor MALAYSIA Tel #: 603-89250510; Fax #:

More information

James Webb Space Telescope (JWST) Program Status. Mark Clampin JWST Observatory Project Scientist NASA/Goddard Space Flight Center

James Webb Space Telescope (JWST) Program Status. Mark Clampin JWST Observatory Project Scientist NASA/Goddard Space Flight Center James Webb Space Telescope (JWST) Program Status Mark Clampin JWST Observatory Project Scientist NASA/Goddard Space Flight Center James Webb Space Telescope (JWST) Organization Mission Lead: Goddard Space

More information

How to buy a telescope for your institution

How to buy a telescope for your institution How to buy a telescope for your institution by Dr. Frank Melsheimer DFM Engineering, Inc. 1035 Delaware Avenue, Unit D Longmont, Colorado 80501 phone 303-678-8143 fax 303-772-9411 www.dfmengineering.com

More information

Wind Resource Data Summary Cotal Area, Guam Data Summary and Transmittal for December 2011

Wind Resource Data Summary Cotal Area, Guam Data Summary and Transmittal for December 2011 Wind Resource Data Summary Cotal Area, Guam Data Summary and Transmittal for December 2011 Prepared for: GHD Inc. 194 Hernan Cortez Avenue 2nd Floor, Ste. 203 Hagatna, Guam 96910 January 2012 DNV Renewables

More information

Shipyard Work Center Performance Analysis

Shipyard Work Center Performance Analysis Shipyard Work Center Performance Analysis PERCEPTION Helping The Shipyard Improve Productivity A Training Tutorial 1 PERCEPTION compiles shipyard production information and generates concise reports on

More information

Sales Analysis User Manual

Sales Analysis User Manual Sales Analysis User Manual Confidential Information This document contains proprietary and valuable, confidential trade secret information of APPX Software, Inc., Richmond, Virginia Notice of Authorship

More information

Technical note on seasonal adjustment for M0

Technical note on seasonal adjustment for M0 Technical note on seasonal adjustment for M0 July 1, 2013 Contents 1 M0 2 2 Steps in the seasonal adjustment procedure 3 2.1 Pre-adjustment analysis............................... 3 2.2 Seasonal adjustment.................................

More information

Galileo Telescope Solar Viewer Joseph Hora, Elizabeth Hora 2017/09/18

Galileo Telescope Solar Viewer Joseph Hora, Elizabeth Hora 2017/09/18 Galileo Telescope Solar Viewer Joseph Hora, Elizabeth Hora 2017/09/18 17 7.75 5 2 1.5 3 2 1.5 Materials: (all dimensions in inches) 3x plywood sheet 17 x 7.75 x ½ 3x wood block cut from 2x4: 5 x 2 x 1.5

More information

SYSTEM BRIEF DAILY SUMMARY

SYSTEM BRIEF DAILY SUMMARY SYSTEM BRIEF DAILY SUMMARY * ANNUAL MaxTemp NEL (MWH) Hr Ending Hr Ending LOAD (PEAK HOURS 7:00 AM TO 10:00 PM MON-SAT) ENERGY (MWH) INCREMENTAL COST DAY DATE Civic TOTAL MAXIMUM @Max MINIMUM @Min FACTOR

More information

ENGINE SERIAL NUMBERS

ENGINE SERIAL NUMBERS ENGINE SERIAL NUMBERS The engine number was also the serial number of the car. Engines were numbered when they were completed, and for the most part went into a chassis within a day or so. However, some

More information

HMS-5000 Manual. Product Name: HMS-5000 Hall Effect Measurement System with variable temperature from 80K to 350K. - Manual version: ver 5.

HMS-5000 Manual. Product Name: HMS-5000 Hall Effect Measurement System with variable temperature from 80K to 350K. - Manual version: ver 5. HMS-5000 Manual Product Name: HMS-5000 Hall Effect Measurement System with variable temperature from 80K to 350K - Manual version: ver 5.01- www.ecopia21.co.kr - Table of contents - 1. Hardware Installation

More information

Champaign-Urbana 2001 Annual Weather Summary

Champaign-Urbana 2001 Annual Weather Summary Champaign-Urbana 2001 Annual Weather Summary ILLINOIS STATE WATER SURVEY 2204 Griffith Dr. Champaign, IL 61820 wxobsrvr@sws.uiuc.edu Maria Peters, Weather Observer January: After a cold and snowy December,

More information

LHC Commissioning in 2008

LHC Commissioning in 2008 LHC Commissioning in 2008 Mike Lamont AB/OP Schedule slides c/o Lyn Evans (MAC 14/6/07) Status: Installation & equipment commissioning LHC commissioning - CMS June 07 2 Procurement problems of remaining

More information

Hard and Soft X-ray Mirror System Design Status

Hard and Soft X-ray Mirror System Design Status Hard and Soft X-ray Mirror System Design Status From FEL Gas Attenuator & Diagnostics HOMS/SOMS Mirror System To Experiment Stations This work performed under the auspices of the U.S. Department of Energy

More information

SPARC4 Simultaneous Polarimeter and Rapid Camera in 4 bands

SPARC4 Simultaneous Polarimeter and Rapid Camera in 4 bands SPARC4 Simultaneous Polarimeter and Rapid Camera in 4 bands Claudia Vilega Rodrigues claudia.rodrigues@inpe.br Astrophysics Division Instituto Nacional de Pesquisas Espaciais WORKSHOP ON SOAR SCIENCE 2020

More information

Monthly Magnetic Bulletin

Monthly Magnetic Bulletin BRITISH GEOLOGICAL SURVEY Jim Carrigan Observatory Prudhoe Bay Monthly Magnetic Bulletin May 2014 14/05/JC JIM CARRIGAN OBSERVATORY MAGNETIC DATA 1. Introduction Jim Carrigan observatory is the fourth

More information

Jan. 5, 2006 Development of a Helical Undulator for ILC Positron Source

Jan. 5, 2006 Development of a Helical Undulator for ILC Positron Source Jan. 5, 2006 Development of a Helical Undulator for ILC Positron Source Abstract. The long-term goal of this research is the development of a polarized positron source able to satisfy the demands of the

More information

Syllabus: UHH ASTR 450 (F18): Astronomical Instrumentation

Syllabus: UHH ASTR 450 (F18): Astronomical Instrumentation Syllabus: UHH ASTR 450 (F18): Astronomical Instrumentation Prof. Klaus W. Hodapp This course is the final course in the 3-course series on optics and astronomical instrumentation offered at UHH. We will

More information

Outage Coordination and Business Practices

Outage Coordination and Business Practices Outage Coordination and Business Practices 1 2007 Objectives What drove the need for developing a planning/coordination process. Why outage planning/coordination is crucial and important. Determining what

More information

Blanco Primary Mirror Radial Support Repair

Blanco Primary Mirror Radial Support Repair Blanco Primary Mirror Radial Support Repair ACTR Project #450 Project description. Project Manager: Tim Abbott Project Engineer: Andres Montane Date:5 Feb 2008 Note: this document was abstracted from section

More information

Update on Development of High Current Bunched Electron Beam from Magnetized DC Photogun

Update on Development of High Current Bunched Electron Beam from Magnetized DC Photogun Update on Development of High Current Bunched Electron Beam from Magnetized DC Photogun JLEIC Collaboration Meeting October 6, 2016 Riad Suleiman and Matt Poelker Magnetized Cooling JLEIC bunched magnetized

More information

CRaTER Project Monthly Technical Progress and Schedule Status Report (NNG05EB92C DRD 20 & 21) April 2005

CRaTER Project Monthly Technical Progress and Schedule Status Report (NNG05EB92C DRD 20 & 21) April 2005 CRaTER Project Monthly Technical Progress and Schedule Status Report (NNG05EB92C DRD 20 & 21) April 2005 Page 1 of 6 Table of Contents Project Scientist s Report... 3 Project Engineer s Report... 3 Mission

More information

arxiv: v1 [astro-ph.im] 10 Oct 2016

arxiv: v1 [astro-ph.im] 10 Oct 2016 Building Medium Size Telescope Structures for the Cherenkov Telescope Array arxiv:1610.02913v1 [astro-ph.im] 10 Oct 2016 A. Schulz 1,a), M. Garczarczyk 1, L. Oakes 2, S. Schlenstedt 1, U. Schwanke 2 and

More information

EBS IT Meeting July 2016

EBS IT Meeting July 2016 EBS IT Meeting 18 19 July 2016 Conference Call Details Conference call: UK Numbers Tel: 0808 238 9819 or Tel: 0207 950 1251 Participant code: 4834 7876... Join online meeting https://meet.nationalgrid.com/antonio.delcastillozas/hq507d31

More information

HMS-5000 Manual. Product Name: HMS-5000 Hall Effect Measurement System with variable temperature from 80K to 350K. - Manual version: ver 5.

HMS-5000 Manual. Product Name: HMS-5000 Hall Effect Measurement System with variable temperature from 80K to 350K. - Manual version: ver 5. HMS-5000 Manual Product Name: HMS-5000 Hall Effect Measurement System with variable temperature from 80K to 350K - Manual version: ver 5.01- www.ecopia21.co.kr - Table of contents - 1. Hardware Installation

More information

TILT, DAYLIGHT AND SEASONS WORKSHEET

TILT, DAYLIGHT AND SEASONS WORKSHEET TILT, DAYLIGHT AND SEASONS WORKSHEET Activity Description: Students will use a data table to make a graph for the length of day and average high temperature in Utah. They will then answer questions based

More information

ALMA/ASTE/Mopra Report

ALMA/ASTE/Mopra Report 1 ALMA/ASTE/Mopra Report Daisuke Iono (NAOJ) NRO UM 2014/7/24 2 ALMA Telescope 21 countries and regions (Japan, Taiwan, Korea, U.S., Canada, 15 European nations, and Chile) 4 regions East Asia: NAOJ North

More information

Investigating Factors that Influence Climate

Investigating Factors that Influence Climate Investigating Factors that Influence Climate Description In this lesson* students investigate the climate of a particular latitude and longitude in North America by collecting real data from My NASA Data

More information

Distortion mapping correction in aspheric null testing

Distortion mapping correction in aspheric null testing Distortion mapping correction in aspheric null testing M. Novak, C. Zhao, J. H. Burge College of Optical Sciences, 1630 East University Boulevard, Tucson, AZ, 85721 ABSTRACT We describe methods to correct

More information

Jackson County 2013 Weather Data

Jackson County 2013 Weather Data Jackson County 2013 Weather Data 61 Years of Weather Data Recorded at the UF/IFAS Marianna North Florida Research and Education Center Doug Mayo Jackson County Extension Director 1952-2008 Rainfall Data

More information

SOT-363 Q 1 Q 2 TOP VIEW. Characteristic Symbol Value Unit I D. Characteristic Symbol Value Unit Drain Source Voltage V DSS -20 V

SOT-363 Q 1 Q 2 TOP VIEW. Characteristic Symbol Value Unit I D. Characteristic Symbol Value Unit Drain Source Voltage V DSS -20 V COMPLEMENTARY PAIR ENHANCEMENT MODE FIELD EFFECT TRANSISTOR Features Low On-Resistance Low Gate Threshold Voltage V GS(th) < 1V Low Input Capacitance Fast Switching Speed Low Input/Output Leakage Complementary

More information

GLAST Large Area Telescope Monthly Mission Review

GLAST Large Area Telescope Monthly Mission Review GLAST Large Area Telescope Monthly Mission Review Gamma-ray Large Area Space Telescope LAT Flight Software Status May 2, 2007 Jana Thayer Stanford Linear Accelerator Center 1 FSW Status B0-10-1 available

More information

Champaign-Urbana 1998 Annual Weather Summary

Champaign-Urbana 1998 Annual Weather Summary Champaign-Urbana 1998 Annual Weather Summary ILLINOIS STATE WATER SURVEY Audrey Bryan, Weather Observer 2204 Griffith Dr. Champaign, IL 61820 wxobsrvr@sparc.sws.uiuc.edu The development of the El Nìno

More information

Financial Review. No member of the Board of Directors has reported accepting any gifts or incentive from any vendor contracted by the association.

Financial Review. No member of the Board of Directors has reported accepting any gifts or incentive from any vendor contracted by the association. Financial Review In accordance with NRS 116.31083, the financial statements for La Jolla Classic HOA for the month ending March 31st, 2015 have been provided to the Board of Directors by Mesa Management,

More information

Computing & Telecommunications Services Monthly Report January CaTS Help Desk. Wright State University (937)

Computing & Telecommunications Services Monthly Report January CaTS Help Desk. Wright State University (937) January 215 Monthly Report Computing & Telecommunications Services Monthly Report January 215 CaTS Help Desk (937) 775-4827 1-888-775-4827 25 Library Annex helpdesk@wright.edu www.wright.edu/cats/ Last

More information

Monthly Magnetic Bulletin

Monthly Magnetic Bulletin BRITISH GEOLOGICAL SURVEY Ascension Island Observatory Monthly Magnetic Bulletin December 2008 08/12/AS Crown copyright; Ordnance Survey ASCENSION ISLAND OBSERVATORY MAGNETIC DATA 1. Introduction Ascension

More information

Physics 476LW Advanced Physics Laboratory Michelson Interferometer

Physics 476LW Advanced Physics Laboratory Michelson Interferometer Physics 476LW Advanced Physics Laboratory Michelson Interferometer Introduction An optical interferometer is an instrument which splits a beam of light into two beams, each beam follows a different path

More information

Report on PIAVE G. Bisoffi

Report on PIAVE G. Bisoffi Report on PIAVE G. Bisoffi International Scientific Committee, Legnaro February 10th, 2005 Context: Upgrade of the LNL Nuclear Physics Facility 3. CRYOGENIC SYSTEM UPGRADE 5. ALPI Energy Upgrade 4 3 4.

More information

Computing & Telecommunications Services

Computing & Telecommunications Services Computing & Telecommunications Services Monthly Report September 214 CaTS Help Desk (937) 775-4827 1-888-775-4827 25 Library Annex helpdesk@wright.edu www.wright.edu/cats/ Table of Contents HEAT Ticket

More information

Cryostat Assembly. 17 September Martin Nordby, Rafe Schindler, Gary Guiffre, Rick Van Berg

Cryostat Assembly. 17 September Martin Nordby, Rafe Schindler, Gary Guiffre, Rick Van Berg Cryostat Assembly 17 September 2008 Martin Nordby, Rafe Schindler, Gary Guiffre, Rick Van Berg General Cryostat section views Contents Raft Tower load transfer process Integration fixturing Back end cable

More information

Champaign-Urbana 1999 Annual Weather Summary

Champaign-Urbana 1999 Annual Weather Summary Champaign-Urbana 1999 Annual Weather Summary ILLINOIS STATE WATER SURVEY 2204 Griffith Dr. Champaign, IL 61820 wxobsrvr@sws.uiuc.edu Maria Peters, Weather Observer A major snowstorm kicked off the new

More information

STS41-D Solar Array Flight Experiment

STS41-D Solar Array Flight Experiment The Space Congress Proceedings 1984 (21st) New Opportunities In Space Apr 1st, 8:00 AM STS41-D Solar Array Flight Experiment Gary F. Turner Manager, Solar Array Programs Lockheed Missiles & Space Co.,

More information

PAIRITEL's Telescopes and Cameras: A History...

PAIRITEL's Telescopes and Cameras: A History... PAIRITEL's Telescopes and Cameras: A History... Design, development, and operation of 2MASS The 2MASS Clearance Sale: Trash or Treasure? The Future The Telescope that Almost Wasn't: Part I 2MASS had to

More information

WIND DATA REPORT. Vinalhaven

WIND DATA REPORT. Vinalhaven WIND DATA REPORT Vinalhaven July 1, 2004 September 30, 2004 Prepared for Fox Islands Electric Cooperative By Melissa L. Ray Anthony L. Rogers April 4, 2005 Renewable Energy Research Laboratory 160 Governors

More information

Climatography of the United States No

Climatography of the United States No Climate Division: AK 5 NWS Call Sign: ANC Month (1) Min (2) Month(1) Extremes Lowest (2) Temperature ( F) Lowest Month(1) Degree s (1) Base Temp 65 Heating Cooling 90 Number of s (3) Jan 22.2 9.3 15.8

More information

Status and Calibration of the erosita X ray Telescope

Status and Calibration of the erosita X ray Telescope Status and Calibration of the erosita X ray Telescope Vadim Burwitz Max Planck Institut für extraterrestrische Physik on behalf of the erosita Team IACHEC, Lake Arrowhead, USA, 29 Mar 2017 Spektr Rentgen

More information

LNER Class L1. By Peter Sheppard

LNER Class L1. By Peter Sheppard LNER Class L1 By Peter Sheppard BR Nos. 67701 to 67800 Hornby have recently produced models of the LNER class L1 2 6 4 tank locomotives. Four models in different liveries have already been issued and a

More information

REPORT ON LABOUR FORECASTING FOR CONSTRUCTION

REPORT ON LABOUR FORECASTING FOR CONSTRUCTION REPORT ON LABOUR FORECASTING FOR CONSTRUCTION For: Project: XYZ Local Authority New Sample Project Contact us: Construction Skills & Whole Life Consultants Limited Dundee University Incubator James Lindsay

More information

Climatography of the United States No

Climatography of the United States No Month (1) Min (2) Month(1) Extremes Lowest (2) Temperature ( F) Lowest Month(1) Degree s (1) Base Temp 65 Heating Cooling 100 Number of s (3) Jan 63.9 39.3 51.6 86 1976 16 56.6 1986 20 1976 2 47.5 1973

More information

Climatography of the United States No

Climatography of the United States No Temperature ( F) Month (1) Min (2) Month(1) Extremes Lowest (2) Lowest Month(1) Degree s (1) Base Temp 65 Heating Cooling 100 Number of s (3) Jan 32.8 21.7 27.3 62 1918 1 35.8 1983-24 1950 29 10.5 1979

More information

Fine Alignment of the ATF Damping Ring

Fine Alignment of the ATF Damping Ring Fine Alignment of the ATF Damping Ring M. Takano, S. Araki (a), Y. Funahashi (a), H. Hayano (a), T. Matsui (b), J. Urakawa (a) Toho University 2 2 1 Miyama, Funabashi, Chiba 275, Japan (a) KEK, High Energy

More information

5mm Silicon PIN Photodiode, T-1 3/4 PD333-3B/H0/L2

5mm Silicon PIN Photodiode, T-1 3/4 PD333-3B/H0/L2 Features Fast response time High photo sensitivity Small junction capacitance Pb free This product itself will remain within RoHS compliant version. Description is a high speed and high sensitive PIN photodiode

More information

KING EDWARD POINT OBSERVATORY MAGNETIC DATA

KING EDWARD POINT OBSERVATORY MAGNETIC DATA BRITISH GEOLOGICAL SURVEY King Edward d Point Observatory Monthly Magnetic Bulletin October 2018 18/10/KE King Edward Point (UK) Maps British Antarctic Survey KING EDWARD POINT OBSERVATORY MAGNETIC DATA

More information

PICTURE sounding rocket telescope

PICTURE sounding rocket telescope PICTURE sounding rocket telescope D. Content, S. Antonille, D. Rabin, T. Wallace NASA GSFC 1 Overview of talk Two {ambitious} sounding rocket concepts sharing a telescope OTA overview PM development program

More information

Development of surface metrology for the Giant Magellan Telescope primary mirror

Development of surface metrology for the Giant Magellan Telescope primary mirror Development of surface metrology for the Giant Magellan Telescope primary mirror J. H. Burge a,b, W. Davison a, H. M. Martin a, C. Zhao b a Steward Observatory, University of Arizona, Tucson, AZ 85721,

More information

Climatography of the United States No

Climatography of the United States No Climate Division: CA 4 NWS Call Sign: Month (1) Min (2) Month(1) Extremes Lowest (2) Temperature ( F) Lowest Month(1) Degree s (1) Base Temp 65 Heating Cooling 100 Number of s (3) Jan 55.6 39.3 47.5 77

More information

Climatography of the United States No

Climatography of the United States No Climate Division: CA 5 NWS Call Sign: Month (1) Min (2) Month(1) Extremes Lowest (2) Temperature ( F) Lowest Month(1) Degree s (1) Base Temp 65 Heating Cooling 100 Number of s (3) Jan 56.6 36.5 46.6 81

More information

Climatography of the United States No

Climatography of the United States No Climate Division: CA 1 NWS Call Sign: Month (1) Min (2) Month(1) Extremes Lowest (2) Temperature ( F) Lowest Month(1) Degree s (1) Base Temp 65 Heating Cooling 100 Number of s (3) Jan 57.9 38.9 48.4 85

More information

Climatography of the United States No

Climatography of the United States No Climate Division: CA 5 NWS Call Sign: Month (1) Min (2) Month(1) Extremes Lowest (2) Temperature ( F) Lowest Month(1) Degree s (1) Base Temp 65 Heating Cooling 100 Number of s (3) Jan 44.8 25.4 35.1 72

More information

Climatography of the United States No

Climatography of the United States No Climate Division: CA 4 NWS Call Sign: Month (1) Min (2) Month(1) Extremes Lowest (2) Temperature ( F) Lowest Month(1) Degree s (1) Base Temp 65 Heating Cooling 100 Number of s (3) Jan 49.4 37.5 43.5 73

More information

Improve Forecasts: Use Defect Signals

Improve Forecasts: Use Defect Signals Improve Forecasts: Use Defect Signals Paul Below paul.below@qsm.com Quantitative Software Management, Inc. Introduction Large development and integration project testing phases can extend over many months

More information

Climatography of the United States No

Climatography of the United States No Climate Division: CA 6 NWS Call Sign: Month (1) Min (2) Month(1) Extremes Lowest (2) Temperature ( F) Lowest Month(1) Degree s (1) Base Temp 65 Heating Cooling 100 Number of s (3) Jan 69.4 46.6 58.0 92

More information

Climatography of the United States No

Climatography of the United States No Climate Division: CA 4 NWS Call Sign: Month (1) Min (2) Month(1) Extremes Lowest (2) Temperature ( F) Lowest Month(1) Degree s (1) Base Temp 65 Heating Cooling 1 Number of s (3) Jan 58.5 38.8 48.7 79 1962

More information

Climatography of the United States No

Climatography of the United States No Climate Division: CA 6 NWS Call Sign: Month (1) Min (2) Month(1) Extremes Lowest (2) Temperature ( F) Lowest Month(1) Degree s (1) Base Temp 65 Heating Cooling 1 Number of s (3) Jan 67.5 42. 54.8 92 1971

More information

Climatography of the United States No

Climatography of the United States No Climate Division: CA 1 NWS Call Sign: Month (1) Min (2) Month(1) Extremes Lowest (2) Temperature ( F) Lowest Month(1) Degree s (1) Base Temp 65 Heating Cooling 1 Number of s (3) Jan 57.8 39.5 48.7 85 1962

More information

Monthly Magnetic Bulletin

Monthly Magnetic Bulletin BRITISH GEOLOGICAL SURVEY Ascension Island Observatory Monthly Magnetic Bulletin March 2017 17/03/AS Crown copyright; Ordnance Survey ASCENSION ISLAND OBSERVATORY MAGNETIC DATA 1. Introduction Ascension

More information

Champaign-Urbana 2000 Annual Weather Summary

Champaign-Urbana 2000 Annual Weather Summary Champaign-Urbana 2000 Annual Weather Summary ILLINOIS STATE WATER SURVEY 2204 Griffith Dr. Champaign, IL 61820 wxobsrvr@sws.uiuc.edu Maria Peters, Weather Observer January: January started on a mild note,

More information

HaloSat Overview. Philip Kaaret August 17, 2016

HaloSat Overview. Philip Kaaret August 17, 2016 HaloSat Overview Philip Kaaret (philip-kaaret@uiowa.edu) August 17, 2016 Outline Scientific Motivation Missing Baryon Problem Mission Goal and Science Requirements Impediments Mission Level 1 Requirements

More information

WIND DATA REPORT. Vinalhaven

WIND DATA REPORT. Vinalhaven WIND DATA REPORT Vinalhaven April 1, 2004 June 30, 2004 Prepared for Fox Islands Electric Cooperative By Melissa L. Ray Anthony L. Rogers April 4, 2005 Renewable Energy Research Laboratory 160 Governors

More information

Status of the PRad Experiment (E )

Status of the PRad Experiment (E ) Status of the PRad Experiment (E12-11-106) NC A&T State University for the PRad collaboration Outline PRad Physics goals ep-scattering and the proton radius PRad experiment experimental setup development

More information

Multivariate Regression Model Results

Multivariate Regression Model Results Updated: August, 0 Page of Multivariate Regression Model Results 4 5 6 7 8 This exhibit provides the results of the load model forecast discussed in Schedule. Included is the forecast of short term system

More information

WYANDOTTE MUNICIPAL SERVICES COMMUNITY WIND ENERGY PROJECT WIND RESOUCE SUMMARY

WYANDOTTE MUNICIPAL SERVICES COMMUNITY WIND ENERGY PROJECT WIND RESOUCE SUMMARY WYANDOTTE MUNICIPAL SERVICES COMMUNITY WIND ENERGY PROJECT WIND RESOUCE SUMMARY MONTHLY REPORT October 15, 2007 Black & Veatch Project: 144374 Prepared by: Black & Veatch Corporation 6300 S. Syracuse Way

More information

Record date Payment date PID element Non-PID element. 08 Sep Oct p p. 01 Dec Jan p 9.85p

Record date Payment date PID element Non-PID element. 08 Sep Oct p p. 01 Dec Jan p 9.85p 2017/18 Record date Payment date PID element Non-PID element 08 Sep 17 06 Oct 17 9.85p - 9.85p 01 Dec 17 05 Jan 18-9.85p 9.85p 09 Mar 18 06 Apr 18 9.85p - 9.85p Final 22 Jun 18 27 Jul 18 14.65p - 14.65p

More information

PROCESS CONTROL BASIS FOR A COST-EFFECTIVE SELECTIVE SOLDERING PROCESS

PROCESS CONTROL BASIS FOR A COST-EFFECTIVE SELECTIVE SOLDERING PROCESS PROCESS CONTROL BASIS FOR A COST-EFFECTIVE SELECTIVE SOLDERING PROCESS Christian Ott Kreuzwertheim, Germany christian.ott@seho.de Heike Schlessmann heike.schlessmann@seho.de Reiner Zoch reiner.zoch@seho.de

More information

SOT-563 Q 1 Q 2 BOTTOM VIEW. Characteristic Symbol Value Unit Drain Source Voltage V DSS 20 V Gate-Source Voltage V GSS ±8 V T A = 25 C T A = 85 C

SOT-563 Q 1 Q 2 BOTTOM VIEW. Characteristic Symbol Value Unit Drain Source Voltage V DSS 20 V Gate-Source Voltage V GSS ±8 V T A = 25 C T A = 85 C COMPLEMENTARY PAIR ENHANCEMENT MODE FIELD EFFECT TRANSISTOR Features Mechanical Data Low On-Resistance Low Gate Threshold Voltage V GS(th)

More information

Climatography of the United States No

Climatography of the United States No Climate Division: ND 8 NWS Call Sign: BIS Month (1) Min (2) Month(1) Extremes Lowest (2) Temperature ( F) Lowest Month(1) Degree s (1) Base Temp 65 Heating Cooling 100 Number of s (3) Jan 21.1 -.6 10.2

More information

Distributed by: www.jameco.com 1-8-831-4242 The content and copyrights of the attached material are the property of its owner. BT52C2V - BT52C39 SURFACE MOUNT ENER DIODE Features Planar Die Construction

More information

Climatography of the United States No

Climatography of the United States No Climate Division: TN 1 NWS Call Sign: Month (1) Min (2) Month(1) Extremes Lowest (2) Temperature ( F) Lowest Month(1) Degree s (1) Base Temp 65 Heating Cooling 100 Number of s (3) Jan 47.6 24.9 36.3 81

More information

GERDA TG4 Cryogenic Vessel Status Report

GERDA TG4 Cryogenic Vessel Status Report GERDA TG4 Cryogenic Vessel Status Report K.T.Knöpfle MPI Kernphysik, Heidelberg ktkno@mpi-hd.mpg.de GERDA Collaboration Meeting at LNGS 26 28 June 2006 Outline Baseline Design: Copper cryostat for LN2

More information

Climatography of the United States No

Climatography of the United States No Climate Division: CA 5 NWS Call Sign: FAT Month (1) Min (2) Month(1) Extremes Lowest (2) Temperature ( F) Lowest Month(1) Degree s (1) Base Temp 65 Heating Cooling 1 Number of s (3) Jan 53.6 38.4 46. 78

More information

Climatography of the United States No

Climatography of the United States No Climate Division: CA 6 NWS Call Sign: 1L2 N Lon: 118 3W Month (1) Min (2) Month(1) Extremes Lowest (2) Temperature ( F) Lowest Month(1) Degree s (1) Base Temp 65 Heating Cooling 1 Number of s (3) Jan 63.7

More information

Implementation Status & Results Burkina Faso TRANSPORT SECTOR PROJECT (P074030)

Implementation Status & Results Burkina Faso TRANSPORT SECTOR PROJECT (P074030) losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Implementation Status & Results Burkina Faso TRANSPORT SECTOR PROJECT (P074030) Operation Name:

More information

The Cassegrain ADC for Keck I Preliminary Design Review Process and Charter September 15, 2003 By Sean Adkins

The Cassegrain ADC for Keck I Preliminary Design Review Process and Charter September 15, 2003 By Sean Adkins CALIFORNIA ASSOCIATION FOR RESEARCH IN ASTRONOMY By Sean Adkins INTRODUCTION The Technical Facilities group of the UCO/Lick Observatory located on the Santa Cruz campus of the University of California

More information

INTERNATIONAL. Member Observatory. The Boquete Optical SETI Observatory. (11/5/15)

INTERNATIONAL. Member Observatory. The Boquete Optical SETI Observatory. (11/5/15) INTERNATIONAL Member Observatory The Boquete Optical SETI Observatory. (11/5/15) Boquete, Panama is located about 25 miles south of the Panama/Costa Rica Border on the slopes of Vulcan Baru, the tallest

More information

Climatography of the United States No

Climatography of the United States No Climate Division: CA 5 NWS Call Sign: BFL Month (1) Min (2) Month(1) Extremes Lowest (2) Temperature ( F) Lowest Month(1) Degree s (1) Base Temp 65 Heating Cooling 1 Number of s (3) Jan 56.3 39.3 47.8

More information

Development Status of the DOTIFS Project: a new multi-ifu optical spectrograph for the 3.6m Devasthal Optical Telescope

Development Status of the DOTIFS Project: a new multi-ifu optical spectrograph for the 3.6m Devasthal Optical Telescope ARIES Development Status of the DOTIFS Project: a new multi-ifu optical spectrograph for the 3.6m Devasthal Optical Telescope 2015 Survey Science Group Meeting January, 27, High 1 Speaker: Haeun Chung

More information

Sun Shield. Solar Paddle

Sun Shield. Solar Paddle The Institute of Space and Astronautical Science Report SP No.14, December 2000 Current Status of ASTRO-F By Hiroshi Murakami Λ (November 1, 2000) Abstract: The ASTRO-F is the second infrared astronomy

More information

Structure of MLL Tandem operation Experiments

Structure of MLL Tandem operation Experiments Maier-Leibnitz-Laboratorium Tandem Operation and Experiments Structure of MLL Tandem operation Experiments Dr. L. Beck 1 Maier-Leibnitz-Laboratorium MP 8-1970 Am Coulombwall 6 85748 Garching Germany Tel.

More information

WIND DATA REPORT FOR THE YAKUTAT JULY 2004 APRIL 2005

WIND DATA REPORT FOR THE YAKUTAT JULY 2004 APRIL 2005 WIND DATA REPORT FOR THE YAKUTAT JULY 2004 APRIL 2005 Prepared on July 12, 2005 For Bob Lynette 212 Jamestown Beach Lane Sequim WA 98382 By John Wade Wind Consultant LLC 2575 NE 32 nd Ave Portland OR 97212

More information

Telescope. 1. Read these instructions carefully and familiarise yourself with the procedure before assembling the unit.

Telescope. 1. Read these instructions carefully and familiarise yourself with the procedure before assembling the unit. Telescope a Simple assembly instructions- Please keep for future reference IMPORTANT 1. Read these instructions carefully and familiarise yourself with the procedure before assembling the unit. 2. Check

More information

Climatography of the United States No

Climatography of the United States No Climate Division: TN 3 NWS Call Sign: BNA Month (1) Min (2) Month(1) Extremes Lowest (2) Temperature ( F) Lowest Month(1) Degree s (1) Base Temp 65 Heating Cooling 100 Number of s (3) Jan 45.6 27.9 36.8

More information