IE652 - Chapter 10. Assumptions. Single Machine Scheduling
|
|
- Thomasine Wheeler
- 6 years ago
- Views:
Transcription
1 IE652 - Chapter 10 Single Machine Scheduling 1 Assumptions All jobs are processed on a single machine Release time of each job is 0 Processing times are known with certainty Scheduling Sequencing in this case 2
2 Performance Measures for Single Machine Scheduling C max is not the measure of performance, because all sequences of jobs gives the same result for this criterion. Common measures for single machine problems: Minimizing the mean flow time ( F ), the maximum tardiness (T max ), the number of tardy jobs (n T ) 3 Minimizing The Mean Flowtime To minimize the mean flow time place the job with the shortest processing time in the first position, because it is counted n times in the calculation of total flow time (P ) + (P1 + P2 ) + (P1 + P2 + P3 ) (P1 + P2 + P F = n Therefore; SPT (shortest processing time) rule gives the best sequence for the minimum mean flow time 1 + P n 4 )
3 SPT (shortest processing time) 5 SPT - Example Consider the following 7 jobs and their processing times. J i P i a) Evaluate the sequence of J1, J2, J3, J4, J5, J6, J7. b) Use SPT rule. Discuss which measures will be affected by the change in the sequence. 6
4 Sequence : J1(6), J2(4), J3(8), J4(3), J5(2), J6(7), J7(1) J1 J2 J3 J4 J5 J6 J F = = = SPT Sequence : J7(1), J5(2), J4(3), J2(4), J1(6), J6(7), J3(8) J7 J5 J4 J2 J1 J6 J F = = =
5 Minimizing The Mean Weighted Flow Time In many situations, all jobs are not equally important. WIP inventory values may be different, when jobs have different importance (value). Then, we can assign importance weight or value to each job. 9 Minimizing The Mean Weighted Flow Time Sequence the jobs so as to minimize WSPT (Weighted Shortest Processing Time) rule can establish this objective n 1 Fv = vi F i(k) n k = 1 F v 10
6 WSPT (Weighted Shortest Processing Time) 11 WSPT Example A company has a production line that can produce six parts (coded as JAxx). The time required to produce each part, and their per unit material costs are given in the following table. How would you schedule these parts through the line to minimize the inventory cost of work-inprocess? Assume inventory holding cost is 40% per year, and each week contains 40 hours. Part, i JA01 JA02 JA03 JA04 JA05 JA06 P i (minutes) Q i (units) c i,unit cost ($)
7 WSPT Example Part, i JA01 JA02 JA03 JA04 JA05 JA06 P i (minutes) Q i (units) c i,unit cost ($) ratio P i / c i Sequence: JA05 JA04 JA02 JA01 JA06 JA03 F5[1] = 7 F4[2] = = 11 F2[3] = = 16 F v = F1[4] = = 18.5 F6[5] = = 21.5 F3[6] = = 24.7 (not real C max ) 13 Minimizing The Maximum Tardiness 14
8 EDD (Earliest Due Date) 15 EDD Example F F Job, i P i d i
9 SPT sequence (solution to a) Job, i P i d i C i L i T i E i EDD sequence (solution to b) Job, i P i d i C i L i T i E i
10 Minimizing The Number of Tardy Jobs 19 Moore Hodgson Algorithm 20
11 Moore Hodgson Algorithm 21 Moore Hodgson Algorithm Example Consider the following jobs, and find a sequence to minimize the number of tardy jobs. Job, i P i d i
12 EDD sequence: Ji Pi di Ci Li Ti Moore Hodgson Algorithm Step 1: Ji Pi di Ci Li Ti Tardiness occurs 24
13 Moore Hodgson Algorithm Step 2: Ji Pi di Ci Li Ti Moore Hodgson Algorithm Step 3: Ji Pi di Ci Li Ti Remove job 1 from the sequence 26
14 Moore Hodgson Algorithm Step 1: Ji Pi di Ci Li Ti Tardiness occurs 27 Moore Hodgson Algorithm Step 2: Ji Pi di Ci Li Ti
15 Moore Hodgson Algorithm Step 3: Ji Pi di Ci Li Ti Remove job 5 from the sequence 29 Moore Hodgson Algorithm Step 1: Ji Pi di Ci Li Ti NO Tardiness occurs 30
16 Moore Hodgson Algorithm Step 4: Ji Pi di Ci Li Ti Sequence Dependent Setup Times If the setup times are sequence independent, then they are included in P i (processing time). Example for dependent setup time: Color changes in glass industry: Normal colored changeover (setup time) is short, Colored normal changeover (setup time) is long, This is known as the problem of sequence dependent setup times. 32
17 Sequence Dependent Setup Times Performance measure: C max C max is a function of the order in which jobs are processed. C max = F max = F n [ n] = S[ k-1],[ k] + Pi [ k] i k = 1 n k = 1 Where; S [k-1],[k] = The time to changeover from the job in position [k-1] to the job in position [k]. 33 Regret based algorithm Step 1: Reduce the matrix by row: minimum element in each row is subtracted from every element of that row Step 2: Reduce the matrix by column: minimum element in each column is subtracted from every element of that column Step 3: Calculate the regret value for every zero element in the matrix: the smallest elements in the column and row corresponding to the zero element are summed Step 4: Choose the zero element with largest regret: Select i*, j* with R i*j* = max{r ij }, i=1..n ; j=1..n Assign job pair in sequence as i* j* Step 5: Prohibit a subtour by setting p j*k* =, (k* is the first job of the subtour) remove row i* and column j* from the matrix, go to step 1 34
18 Regret based algorithm- Example 35 Steps 1 and 2: Matrix reduction C max = 19 36
19 Steps 3 and 4: Calculate regret values and assign job pair in sequence as i*,j* with largest regret value Subtours after iteration 1 = (5,2) 37 Step 5: set p 2,5 =, remove the row 5 and column 2 from the matrix Go to step 1 38
20 Steps 1 and 2: Matrix reduction C max = 19+5 = Steps 3 and 4: Calculate regret values and assign job pair in sequence as i*,j* with largest regret value Subtours after iteration 2 = (5,2), (3,1) 40
21 Step 5: set p 1,3 =, remove the row 3 and column 1 from the matrix, go to step 1 for the third iteration as follows: C max = 24 Subtours after iteration 3 = (5,2), (3,1,4) 41 set p 4,3 =, remove the row 1 and column 4 from the matrix, go to step 1 for the next iteration as follows: C max = 24 Complete tour after iteration 4 = (5,2,3,1,4,5) 42
SINGLE MACHINE SEQUENCING Part 2. ISE480 Sequencing and Scheduling Fall semestre
SINGLE MACHINE SEQUENCING Part 2 2011 2012 Fall semestre Minimizing Total Weighted Flowtime In a common variation of the F-problem, obs do not have equal importance. One way of distinguishing the obs is
More informationSingle Machine Problems Polynomial Cases
DM204, 2011 SCHEDULING, TIMETABLING AND ROUTING Lecture 2 Single Machine Problems Polynomial Cases Marco Chiarandini Department of Mathematics & Computer Science University of Southern Denmark Outline
More informationRCPSP Single Machine Problems
DM204 Spring 2011 Scheduling, Timetabling and Routing Lecture 3 Single Machine Problems Marco Chiarandini Department of Mathematics & Computer Science University of Southern Denmark Outline 1. Resource
More informationCHAPTER 16: SCHEDULING
CHAPTER 16: SCHEDULING Solutions: 1. Job A B C A B C 1 5 8 6 row 1 0 3 1 Worker 2 6 7 9 reduction 2 0 1 3 3 4 5 3 3 1 2 0 column reduction A B C 1 0 2 1 Optimum: 2 0 0 3 Worker 1, Job A 3 1 1 0 2 B 3 C
More informationLecture 4 Scheduling 1
Lecture 4 Scheduling 1 Single machine models: Number of Tardy Jobs -1- Problem 1 U j : Structure of an optimal schedule: set S 1 of jobs meeting their due dates set S 2 of jobs being late jobs of S 1 are
More informationSimple Dispatch Rules
Simple Dispatch Rules We will first look at some simple dispatch rules: algorithms for which the decision about which job to run next is made based on the jobs and the time (but not on the history of jobs
More informationSingle Machine Models
Outline DM87 SCHEDULING, TIMETABLING AND ROUTING Lecture 8 Single Machine Models 1. Dispatching Rules 2. Single Machine Models Marco Chiarandini DM87 Scheduling, Timetabling and Routing 2 Outline Dispatching
More informationBi-criteria Scheduling Problems on Parallel Machines
Bi-criteria Scheduling Problems on Parallel Machines by Divya Prakash Thesis submitted to the Faculty of the Virginia Polytechnic Institute and State University in partial fulfillment of the requirements
More informationMINIMIZING TOTAL TARDINESS FOR SINGLE MACHINE SEQUENCING
Journal of the Operations Research Society of Japan Vol. 39, No. 3, September 1996 1996 The Operations Research Society of Japan MINIMIZING TOTAL TARDINESS FOR SINGLE MACHINE SEQUENCING Tsung-Chyan Lai
More informationRecoverable Robustness in Scheduling Problems
Master Thesis Computing Science Recoverable Robustness in Scheduling Problems Author: J.M.J. Stoef (3470997) J.M.J.Stoef@uu.nl Supervisors: dr. J.A. Hoogeveen J.A.Hoogeveen@uu.nl dr. ir. J.M. van den Akker
More informationDynamic Scheduling with Genetic Programming
Dynamic Scheduling with Genetic Programming Domago Jakobović, Leo Budin domago.akobovic@fer.hr Faculty of electrical engineering and computing University of Zagreb Introduction most scheduling problems
More informationSimulation. Stochastic scheduling example: Can we get the work done in time?
Simulation Stochastic scheduling example: Can we get the work done in time? Example of decision making under uncertainty, combination of algorithms and probability distributions 1 Example study planning
More informationScheduling Lecture 1: Scheduling on One Machine
Scheduling Lecture 1: Scheduling on One Machine Loris Marchal October 16, 2012 1 Generalities 1.1 Definition of scheduling allocation of limited resources to activities over time activities: tasks in computer
More informationBatch delivery scheduling with simple linear deterioration on a single machine 1
Acta Technica 61, No. 4A/2016, 281 290 c 2017 Institute of Thermomechanics CAS, v.v.i. Batch delivery scheduling with simple linear deterioration on a single machine 1 Juan Zou 2,3 Abstract. Several single
More informationEcon 172A, Fall 2012: Final Examination Solutions (I) 1. The entries in the table below describe the costs associated with an assignment
Econ 172A, Fall 2012: Final Examination Solutions (I) 1. The entries in the table below describe the costs associated with an assignment problem. There are four people (1, 2, 3, 4) and four jobs (A, B,
More informationParallel machine scheduling with batch delivery costs
Int. J. Production Economics 68 (2000) 177}183 Parallel machine scheduling with batch delivery costs Guoqing Wang*, T.C. Edwin Cheng Department of Business Administration, Jinan University, Guangzhou,
More informationCombinatorial Structure of Single machine rescheduling problem
Workshop on Combinatorics and Optimization Combinatorial Structure of Single machine rescheduling problem Yuan Jinjiang Department of mathematics, Zhengzhou University Zhengzhou, Henan 450052 Page 1 of
More informationarxiv: v2 [cs.ds] 27 Nov 2014
Single machine scheduling problems with uncertain parameters and the OWA criterion arxiv:1405.5371v2 [cs.ds] 27 Nov 2014 Adam Kasperski Institute of Industrial Engineering and Management, Wroc law University
More informationEcon 172A, Fall 2012: Final Examination Solutions (II) 1. The entries in the table below describe the costs associated with an assignment
Econ 172A, Fall 2012: Final Examination Solutions (II) 1. The entries in the table below describe the costs associated with an assignment problem. There are four people (1, 2, 3, 4) and four jobs (A, B,
More informationSingle Machine Scheduling: Comparison of MIP Formulations and Heuristics for. Interfering Job Sets. Ketan Khowala
Single Machine Scheduling: Comparison of MIP Formulations and Heuristics for Interfering Job Sets by Ketan Khowala A Dissertation Presented in Partial Fulfillment of the Requirements for the Degree Doctor
More informationPart III: Traveling salesman problems
Transportation Logistics Part III: Traveling salesman problems c R.F. Hartl, S.N. Parragh 1/282 Motivation Motivation Why do we study the TSP? c R.F. Hartl, S.N. Parragh 2/282 Motivation Motivation Why
More informationTechniques for Proving Approximation Ratios in Scheduling
Techniques for Proving Approximation Ratios in Scheduling by Peruvemba Sundaram Ravi A thesis presented to the University of Waterloo in fulfillment of the thesis requirement for the degree of Master of
More informationMulti-Objective Scheduling Using Rule Based Approach
Multi-Objective Scheduling Using Rule Based Approach Mohammad Komaki, Shaya Sheikh, Behnam Malakooti Case Western Reserve University Systems Engineering Email: komakighorban@gmail.com Abstract Scheduling
More informationMVE165/MMG630, Applied Optimization Lecture 6 Integer linear programming: models and applications; complexity. Ann-Brith Strömberg
MVE165/MMG630, Integer linear programming: models and applications; complexity Ann-Brith Strömberg 2011 04 01 Modelling with integer variables (Ch. 13.1) Variables Linear programming (LP) uses continuous
More informationIntroduction into Vehicle Routing Problems and other basic mixed-integer problems
Introduction into Vehicle Routing Problems and other basic mixed-integer problems Martin Branda Charles University in Prague Faculty of Mathematics and Physics Department of Probability and Mathematical
More informationOnline Appendix for Coordination of Outsourced Operations at a Third-Party Facility Subject to Booking, Overtime, and Tardiness Costs
Submitted to Operations Research manuscript OPRE-2009-04-180 Online Appendix for Coordination of Outsourced Operations at a Third-Party Facility Subject to Booking, Overtime, and Tardiness Costs Xiaoqiang
More informationPart III: Traveling salesman problems
Transportation Logistics Part III: Traveling salesman problems c R.F. Hartl, S.N. Parragh 1/74 Motivation Motivation Why do we study the TSP? it easy to formulate it is a difficult problem many significant
More informationCoin Changing: Give change using the least number of coins. Greedy Method (Chapter 10.1) Attempt to construct an optimal solution in stages.
IV-0 Definitions Optimization Problem: Given an Optimization Function and a set of constraints, find an optimal solution. Optimal Solution: A feasible solution for which the optimization function has the
More informationScheduling Lecture 1: Scheduling on One Machine
Scheduling Lecture 1: Scheduling on One Machine Loris Marchal 1 Generalities 1.1 Definition of scheduling allocation of limited resources to activities over time activities: tasks in computer environment,
More informationChapter 3: Discrete Optimization Integer Programming
Chapter 3: Discrete Optimization Integer Programming Edoardo Amaldi DEIB Politecnico di Milano edoardo.amaldi@polimi.it Sito web: http://home.deib.polimi.it/amaldi/ott-13-14.shtml A.A. 2013-14 Edoardo
More informationMinimizing Mean Flowtime and Makespan on Master-Slave Systems
Minimizing Mean Flowtime and Makespan on Master-Slave Systems Joseph Y-T. Leung,1 and Hairong Zhao 2 Department of Computer Science New Jersey Institute of Technology Newark, NJ 07102, USA Abstract The
More informationScheduling with Advanced Process Control Constraints
Scheduling with Advanced Process Control Constraints Yiwei Cai, Erhan Kutanoglu, John Hasenbein, Joe Qin July 2, 2009 Abstract With increasing worldwide competition, high technology manufacturing companies
More informationExample: 1. In this chapter we will discuss the transportation and assignment problems which are two special kinds of linear programming.
Ch. 4 THE TRANSPORTATION AND ASSIGNMENT PROBLEMS In this chapter we will discuss the transportation and assignment problems which are two special kinds of linear programming. deals with transporting goods
More informationAlgorithm Design Strategies V
Algorithm Design Strategies V Joaquim Madeira Version 0.0 October 2016 U. Aveiro, October 2016 1 Overview The 0-1 Knapsack Problem Revisited The Fractional Knapsack Problem Greedy Algorithms Example Coin
More informationMODELING (Integer Programming Examples)
MODELING (Integer Programming Eamples) IE 400 Principles of Engineering Management Integer Programming: Set 5 Integer Programming: So far, we have considered problems under the following assumptions:
More informationBounds for the Permutation Flowshop Scheduling Problem with Exact Time Lags while Minimizing the Total Earliness and Tardiness
Bounds for the Permutation Flowshop Scheduling Problem with Exact Time Lags while Minimizing the Total Earliness and Tardiness Imen Hamdi, Taïcir Loukil Abstract- We consider the problem of n-jobs scheduling
More informationProofs for all the results presented in the body of the article are presented below: ProofofLemma1:Consider a Nash schedule S where x O i > P i
ONLINE SUPPLEMENT FOR Non-Cooperative Games for Subcontracting Operations by George L. Vairaktarakis Weatherhead School of Management Department of Operations Case Western Reserve University 10900 Euclid
More informationIntegrated Production Scheduling and Preventive Maintenance Planning for a Single Machine Under a Cumulative Damage Failure Process
Integrated Production Scheduling and Preventive Maintenance Planning for a Single Machine Under a Cumulative Damage Failure Process Yarlin Kuo, Zi-Ann Chang Department of Industrial Engineering and Management,
More informationFH2(P 2,P2) hybrid flow shop scheduling with recirculation of jobs
FH2(P 2,P2) hybrid flow shop scheduling with recirculation of jobs Nadjat Meziani 1 and Mourad Boudhar 2 1 University of Abderrahmane Mira Bejaia, Algeria 2 USTHB University Algiers, Algeria ro nadjet07@yahoo.fr
More informationFlow Shop and Job Shop Models
Outline DM87 SCHEDULING, TIMETABLING AND ROUTING Lecture 11 Flow Shop and Job Shop Models 1. Flow Shop 2. Job Shop Marco Chiarandini DM87 Scheduling, Timetabling and Routing 2 Outline Resume Permutation
More informationThe Traveling Salesman Problem: An Overview. David P. Williamson, Cornell University Ebay Research January 21, 2014
The Traveling Salesman Problem: An Overview David P. Williamson, Cornell University Ebay Research January 21, 2014 (Cook 2012) A highly readable introduction Some terminology (imprecise) Problem Traditional
More informationMinimizing the Number of Tardy Jobs
Minimizing the Number of Tardy Jobs 1 U j Example j p j d j 1 10 10 2 2 11 3 7 13 4 4 15 5 8 20 Ideas: Need to choose a subset of jobs S that meet their deadlines. Schedule the jobs that meet their deadlines
More informationAdvanced Modified Time Deviation Method for Job Sequencing
ABSTRACT 2018 IJSRST Volume 4 Issue 10 Print ISSN : 2395-6011 Online ISSN : 2395-602X Themed Section: Science and Technology Advanced Modified Time Deviation Method for Sequencing R Rajalakshmi 1, S Rekha
More informationSTABILITY OF JOHNSON S SCHEDULE WITH LIMITED MACHINE AVAILABILITY
MOSIM 01 du 25 au 27 avril 2001 Troyes (France) STABILITY OF JOHNSON S SCHEDULE WITH LIMITED MACHINE AVAILABILITY Oliver BRAUN, Günter SCHMIDT Department of Information and Technology Management Saarland
More informationLower Bounds for Parallel Machine Scheduling Problems
Lower Bounds for Parallel Machine Scheduling Problems Philippe Baptiste 1, Antoine Jouglet 2, David Savourey 2 1 Ecole Polytechnique, UMR 7161 CNRS LIX, 91128 Palaiseau, France philippe.baptiste@polytechnique.fr
More informationAlgorithm Design. Scheduling Algorithms. Part 2. Parallel machines. Open-shop Scheduling. Job-shop Scheduling.
Algorithm Design Scheduling Algorithms Part 2 Parallel machines. Open-shop Scheduling. Job-shop Scheduling. 1 Parallel Machines n jobs need to be scheduled on m machines, M 1,M 2,,M m. Each machine can
More informationOutline. Relaxation. Outline DMP204 SCHEDULING, TIMETABLING AND ROUTING. 1. Lagrangian Relaxation. Lecture 12 Single Machine Models, Column Generation
Outline DMP204 SCHEDULING, TIMETABLING AND ROUTING 1. Lagrangian Relaxation Lecture 12 Single Machine Models, Column Generation 2. Dantzig-Wolfe Decomposition Dantzig-Wolfe Decomposition Delayed Column
More informationScheduling Online Algorithms. Tim Nieberg
Scheduling Online Algorithms Tim Nieberg General Introduction on-line scheduling can be seen as scheduling with incomplete information at certain points, decisions have to be made without knowing the complete
More informationUsing column generation to solve parallel machine scheduling problems with minmax objective functions
Using column generation to solve parallel machine scheduling problems with minmax objective functions J.M. van den Akker J.A. Hoogeveen Department of Information and Computing Sciences Utrecht University
More informationLPT rule: Whenever a machine becomes free for assignment, assign that job whose. processing time is the largest among those jobs not yet assigned.
LPT rule Whenever a machine becomes free for assignment, assign that job whose processing time is the largest among those jobs not yet assigned. Example m1 m2 m3 J3 Ji J1 J2 J3 J4 J5 J6 6 5 3 3 2 1 3 5
More informationChapter 3: Discrete Optimization Integer Programming
Chapter 3: Discrete Optimization Integer Programming Edoardo Amaldi DEIB Politecnico di Milano edoardo.amaldi@polimi.it Website: http://home.deib.polimi.it/amaldi/opt-16-17.shtml Academic year 2016-17
More informationMarjan van den Akker. Han Hoogeveen Jules van Kempen
Parallel machine scheduling through column generation: minimax objective functions, release dates, deadlines, and/or generalized precedence constraints Marjan van den Akker Han Hoogeveen Jules van Kempen
More informationTask Models and Scheduling
Task Models and Scheduling Jan Reineke Saarland University June 27 th, 2013 With thanks to Jian-Jia Chen at KIT! Jan Reineke Task Models and Scheduling June 27 th, 2013 1 / 36 Task Models and Scheduling
More informationScheduling jobs with agreeable processing times and due dates on a single batch processing machine
Theoretical Computer Science 374 007 159 169 www.elsevier.com/locate/tcs Scheduling jobs with agreeable processing times and due dates on a single batch processing machine L.L. Liu, C.T. Ng, T.C.E. Cheng
More informationResearch Article Minimizing the Number of Tardy Jobs on a Single Machine with an Availability Constraint
Journal of Industrial Engineering, Article ID 568317, 13 pages http://dx.doi.org/10.1155/2014/568317 Research Article Minimizing the Number of Tardy Jobs on a Single Machine with an Availability Constraint
More information2WB05 Simulation Lecture 7: Output analysis
2WB05 Simulation Lecture 7: Output analysis Marko Boon http://www.win.tue.nl/courses/2wb05 December 17, 2012 Outline 2/33 Output analysis of a simulation Confidence intervals Warm-up interval Common random
More informationDeterministic Scheduling. Dr inż. Krzysztof Giaro Gdańsk University of Technology
Deterministic Scheduling Dr inż. Krzysztof Giaro Gdańsk University of Technology Lecture Plan Introduction to deterministic scheduling Critical path metod Some discrete optimization problems Scheduling
More informationCourse 495: Advanced Statistical Machine Learning/Pattern Recognition
Course 495: Advanced Statistical Machine Learning/Pattern Recognition Lecturer: Stefanos Zafeiriou Goal (Lectures): To present discrete and continuous valued probabilistic linear dynamical systems (HMMs
More informationInternational Journal of Industrial Engineering Computations
International Journal of Industrial Engineering Computations 3 (202) 32 336 Contents lists available at GrowingScience International Journal of Industrial Engineering Computations homepage: www.growingscience.com/iec
More informationRobust optimization for resource-constrained project scheduling with uncertain activity durations
Robust optimization for resource-constrained project scheduling with uncertain activity durations Christian Artigues 1, Roel Leus 2 and Fabrice Talla Nobibon 2 1 LAAS-CNRS, Université de Toulouse, France
More informationExtended Job Shop Scheduling by Object-Oriented. Optimization Technology
Extended Job Shop Scheduling by Object-Oriented Optimization Technology Minoru Kobayashi, Kenji Muramatsu Tokai University Address: 1117 Kitakaname, Hiratsuka, Kanagawa, 259-1292, Japan Telephone: +81-463-58-1211
More informationMTHSC 4420 Advanced Mathematical Programming Homework 2
MTHSC 4420 Advanced Mathematical Programming Homework 2 Megan Bryant October 30, 2013 1. Use Dijkstra s algorithm to solve the shortest path problem depicted below. For each iteration, list the node you
More informationSlides 12: Output Analysis for a Single Model
Slides 12: Output Analysis for a Single Model Objective: Estimate system performance via simulation. If θ is the system performance, the precision of the estimator ˆθ can be measured by: The standard error
More informationOn bilevel machine scheduling problems
Noname manuscript No. (will be inserted by the editor) On bilevel machine scheduling problems Tamás Kis András Kovács Abstract Bilevel scheduling problems constitute a hardly studied area of scheduling
More informationUsing column generation to solve parallel machine scheduling problems with minmax objective functions
J Sched (2012) 15:801 810 DOI 10.1007/s10951-010-0191-z Using column generation to solve parallel machine scheduling problems with minmax objective functions J.M. van den Akker J.A. Hoogeveen J.W. van
More informationPolynomial time solutions for scheduling problems on a proportionate flowshop with two competing agents
Journal of the Operational Research Society (2014) 65, 151 157 2014 Operational Research Society Ltd All rights reserved 0160-5682/14 wwwpalgrave-journalscom/jors/ Polynomial time solutions for scheduling
More informationLinear Equations and Matrix
1/60 Chia-Ping Chen Professor Department of Computer Science and Engineering National Sun Yat-sen University Linear Algebra Gaussian Elimination 2/60 Alpha Go Linear algebra begins with a system of linear
More informationMatrix Arithmetic. j=1
An m n matrix is an array A = Matrix Arithmetic a 11 a 12 a 1n a 21 a 22 a 2n a m1 a m2 a mn of real numbers a ij An m n matrix has m rows and n columns a ij is the entry in the i-th row and j-th column
More informationOn the exact solution of a large class of parallel machine scheduling problems
1 / 23 On the exact solution of a large class of parallel machine scheduling problems Teobaldo Bulhões 2 Ruslan Sadykov 1 Eduardo Uchoa 2 Anand Subramanian 3 1 Inria Bordeaux and Univ. Bordeaux, France
More informationComputers and Mathematics with Applications
Computers and Mathematics with Applications 60 (2010) 1374 1384 Contents lists available at ScienceDirect Computers and Mathematics with Applications journal homepage: www.elsevier.com/locate/camwa Heuristics
More informationDeterministic Operations Research, ME 366Q and ORI 391 Chapter 2: Homework #2 Solutions
Deterministic Operations Research, ME 366Q and ORI 391 Chapter 2: Homework #2 Solutions 11. Consider the following linear program. Maximize z = 6x 1 + 3x 2 subject to x 1 + 2x 2 2x 1 + x 2 20 x 1 x 2 x
More informationColumn Generation. ORLAB - Operations Research Laboratory. Stefano Gualandi. June 14, Politecnico di Milano, Italy
ORLAB - Operations Research Laboratory Politecnico di Milano, Italy June 14, 2011 Cutting Stock Problem (from wikipedia) Imagine that you work in a paper mill and you have a number of rolls of paper of
More informationIntroduction to integer programming III:
Introduction to integer programming III: Network Flow, Interval Scheduling, and Vehicle Routing Problems Martin Branda Charles University in Prague Faculty of Mathematics and Physics Department of Probability
More informationNeville s Method. MATH 375 Numerical Analysis. J. Robert Buchanan. Fall Department of Mathematics. J. Robert Buchanan Neville s Method
Neville s Method MATH 375 Numerical Analysis J. Robert Buchanan Department of Mathematics Fall 2013 Motivation We have learned how to approximate a function using Lagrange polynomials and how to estimate
More informationAsymmetric Traveling Salesman Problem (ATSP): Models
Asymmetric Traveling Salesman Problem (ATSP): Models Given a DIRECTED GRAPH G = (V,A) with V = {,, n} verte set A = {(i, j) : i V, j V} arc set (complete digraph) c ij = cost associated with arc (i, j)
More informationSolving Linear Systems Using Gaussian Elimination. How can we solve
Solving Linear Systems Using Gaussian Elimination How can we solve? 1 Gaussian elimination Consider the general augmented system: Gaussian elimination Step 1: Eliminate first column below the main diagonal.
More informationMATH 445/545 Test 1 Spring 2016
MATH 445/545 Test Spring 06 Note the problems are separated into two sections a set for all students and an additional set for those taking the course at the 545 level. Please read and follow all of these
More informationMATH 56A: STOCHASTIC PROCESSES CHAPTER 1
MATH 56A: STOCHASTIC PROCESSES CHAPTER. Finite Markov chains For the sake of completeness of these notes I decided to write a summary of the basic concepts of finite Markov chains. The topics in this chapter
More informationarxiv: v1 [cs.ds] 11 Dec 2013
WORST-CASE PERFORMANCE ANALYSIS OF SOME APPROXIMATION ALGORITHMS FOR MINIMIZING MAKESPAN AND FLOW-TIME PERUVEMBA SUNDARAM RAVI, LEVENT TUNÇEL, MICHAEL HUANG arxiv:1312.3345v1 [cs.ds] 11 Dec 2013 Abstract.
More informationAn exact approach to early/tardy scheduling with release dates
Computers & Operations Research 32 (2005) 2905 2917 www.elsevier.com/locate/dsw An exact approach to early/tardy scheduling with release dates Jorge M.S. Valente, Rui A.F.S. Alves Faculdade de Economia,
More informationSolving a Production Scheduling Problem as a Time-Dependent Traveling Salesman Problem
Solving a Production Scheduling Problem as a Time-Dependent Traveling Salesman Problem GABRIELLA STECCO Department of Applied Mathematics, University Ca Foscari of Venice, Dorsoduro n. 3825/E, 30123 Venice,
More informationTotally unimodular matrices. Introduction to integer programming III: Network Flow, Interval Scheduling, and Vehicle Routing Problems
Totally unimodular matrices Introduction to integer programming III: Network Flow, Interval Scheduling, and Vehicle Routing Problems Martin Branda Charles University in Prague Faculty of Mathematics and
More informationWelcome to CPSC 4850/ OR Algorithms
Welcome to CPSC 4850/5850 - OR Algorithms 1 Course Outline 2 Operations Research definition 3 Modeling Problems Product mix Transportation 4 Using mathematical programming Course Outline Instructor: Robert
More informationThe polynomial solvability of selected bicriteria scheduling problems on parallel machines with equal length jobs and release dates
The polynomial solvability of selected bicriteria scheduling problems on parallel machines with equal length jobs and release dates Hari Balasubramanian 1, John Fowler 2, and Ahmet Keha 2 1: Department
More informationMinimizing the weighted completion time on a single machine with periodic maintenance
Minimizing the weighted completion time on a single machine with periodic maintenance KRIM Hanane University of Valenciennes and Hainaut-Cambrésis LAMIH UMR CNRS 8201 1st year Phd Student February 12,
More informationOmega 38 (2010) Contents lists available at ScienceDirect. Omega. journal homepage:
Omega 38 (2010) 3 -- 11 Contents lists available at ScienceDirect Omega journal homepage: www.elsevier.com/locate/omega A single-machine learning effect scheduling problem with release times Wen-Chiung
More informationSingle machine scheduling with forbidden start times
4OR manuscript No. (will be inserted by the editor) Single machine scheduling with forbidden start times Jean-Charles Billaut 1 and Francis Sourd 2 1 Laboratoire d Informatique Université François-Rabelais
More informationInternational Journal of Industrial Engineering Computations
International Journal of Industrial Engineering Computations 2 (20) 49 498 Contents lists available at GrowingScience International Journal of Industrial Engineering Computations homepage: www.growingscience.com/iec
More informationLecture #8: We now take up the concept of dynamic programming again using examples.
Lecture #8: 0.0.1 Dynamic Programming:(Chapter 15) We now take up the concept of dynamic programming again using examples. Example 1 (Chapter 15.2) Matrix Chain Multiplication INPUT: An Ordered set of
More informationComputer Science, Informatik 4 Communication and Distributed Systems. Simulation. Discrete-Event System Simulation. Dr.
Simulation Discrete-Event System Simulation Chapter 0 Output Analysis for a Single Model Purpose Objective: Estimate system performance via simulation If θ is the system performance, the precision of the
More informationThe Assignment Problem
CHAPTER 12 The Assignment Problem Basic Concepts Assignment Algorithm The Assignment Problem is another special case of LPP. It occurs when m jobs are to be assigned to n facilities on a one-to-one basis
More informationScheduling with Constraint Programming. Job Shop Cumulative Job Shop
Scheduling with Constraint Programming Job Shop Cumulative Job Shop CP vs MIP: Task Sequencing We need to sequence a set of tasks on a machine Each task i has a specific fixed processing time p i Each
More informationOn-Line Algorithms for Due Date Quotation with Lateness Penalties
Principal Investigator/Project Director: Philip Kaminsky Institution: University of California, Berkeley. Award Number: DMI-0092854 Program: DMII OR/SEE Project Title: CAREER: Scheduling of Large Scale
More information1 Multiply Eq. E i by λ 0: (λe i ) (E i ) 2 Multiply Eq. E j by λ and add to Eq. E i : (E i + λe j ) (E i )
Direct Methods for Linear Systems Chapter Direct Methods for Solving Linear Systems Per-Olof Persson persson@berkeleyedu Department of Mathematics University of California, Berkeley Math 18A Numerical
More informationDesign of Manufacturing Systems Manufacturing Cells
Design of Manufacturing Systems Manufacturing Cells Outline General features Examples Strengths and weaknesses Group technology steps System design Virtual cellular manufacturing 2 Manufacturing cells
More informationLower Bounds for Parallel Machine Scheduling Problems
Lower Bounds for Parallel Machine Scheduling Problems Philippe Baptiste 1, Antoine Jouglet 2,, David Savourey 2 1 Ecole Polytechnique, UMR 7161 CNRS LIX, 91128 Palaiseau, France philippe.baptiste@polytechnique.fr
More informationA comparison of sequencing formulations in a constraint generation procedure for avionics scheduling
A comparison of sequencing formulations in a constraint generation procedure for avionics scheduling Department of Mathematics, Linköping University Jessika Boberg LiTH-MAT-EX 2017/18 SE Credits: Level:
More informationDefinition. A matrix is a rectangular array of numbers enclosed by brackets (plural: matrices).
Matrices (general theory). Definition. A matrix is a rectangular array of numbers enclosed by brackets (plural: matrices). Examples. 1 2 1 1 0 2 A= 0 0 7 B= 0 1 3 4 5 0 Terminology and Notations. Each
More informationA new ILS algorithm for parallel machine scheduling problems
J Intell Manuf (2006) 17:609 619 DOI 10.1007/s10845-006-0032-2 A new ILS algorithm for parallel machine scheduling problems Lixin Tang Jiaxiang Luo Received: April 2005 / Accepted: January 2006 Springer
More informationThe CON Job Scheduling Problem on a Single and Parallel Machines
The CON Job Scheduling Problem on a Single and Parallel Machines Huajun Zhou A Thesis Submitted to the University of North Carolina at Wilmington in Partial Fulfillment Of the Requirements for the Degree
More information