The MD was done at 450GeV using beam 2 only. An MD focussing on injection of bunches with nominal emittance was done in parallel on beam 1.
|
|
- Franklin Carroll
- 5 years ago
- Views:
Transcription
1 CERN-ATS-Note MD MKI UFOs at Injection Tobias BAER, Mike BARNES, Wolfgang BARTMANN, Chiara BRACCO, Etienne CARLIER, Christophe CHANAVAT, Lene Norderhaug DROSDAL, Noel GARREL, Brennan GODDARD, Verena KAIN, Volker MERTENS, Jan UYTHOVEN, Jorg WENNINGER, Markus ZERLAUTH Keywords: UFO, dust particle, macro particle, MKI, injection kicker magnet Summary During the MD, the production mechanism of UFOs at the injection kicker magnets (MKIs) was studied. This was done by pulsing the MKIs on a gap in the circulating beam, which led to an increased number of UFOs. In total 43 UFO type beam loss patterns at the MKIs were observed during the MD. The MD showed that pulsing the MKIs directly induces UFO type beam loss patterns. From the temporal characteristics of the loss profile, estimations about the dynamics of the UFOs are made. 1. Introduction An important limitation for the performance of the Large Hadron Collider are so called UFOs ( Unidentified Falling Objects ). UFOs were first observed in July 2010 and caused numerous protection beam dumps since then. They are presumably micrometer sized dust particles that lead to fast beam losses with a duration of about 10 turns when they interact with the beam. Exceptionally many UFOs occur around the injection kicker magnets MKI (cf. Fig. 1). The Aim of the MD was to study the production mechanism of the UFOs at the MKIs. For this, the MKIs were pulsed without injection of beam on a gap in the partly filled machine (1236 circulating bunches). Tests were done with all four MKIs pulsing at the same time and pulsing of individual MKIs only. The MD was done at 450GeV using beam 2 only. An MD focussing on injection of bunches with nominal emittance was done in parallel on beam Machine Protection verification In order to pulse a single MKI individually, the fine delay of the other MKIs was increased beyond the delay of the kicker dump switch. Because this implicates significant changes of the behaviour of the equipment, while operating with high intensity beam (1236 nominal bunches), the MD was classified as MPS class C. Thus, a procedure to guarantee
2 machine protection was put in place for this MD [1]. A key aspect to ensure machine protection was a test with pilot bunches distributed around the machine. This test showed the feasibility of the procedure for individual MKI pulsing and that the individual MKI pulses in a gap of the partly filled machine do not affect the circulating beam. Figure 1: Layout of the MKI for beam 2. Mobile BLMs (red) have been installed in addition to the existing BLMs (blue). 3. Observations and Results During the MD, the MKIs were pulsed in total 21 times (cf. Table 1). 14 times all MKIs were pulsed together, 3 times only MKI.D was pulsed and 4 times only MKI.A was pulsed. In total 43 UFO type loss pattern at the MKIs were identified during the MD (cf. Table 2). Figure 2 gives an overview of the kicker pulses and the observed beam losses. Figure 2: Overview of the MKI pulses and the beam losses at the MKIs with 1236 bunches circulating beam. Most of the loss spikes are UFO type losses
3 UFOs between MKI pulses Especially in the beginning of the MD, several UFO type loss pattern were observed between the kicker pulses (8 UFOs within 20 minutes after the last injection). Towards the end of the MD, the MKIs were pulsed more frequently, but particularly in the hour after the last MKI pulse only 4 UFO type loss pattern were observed. Figure 3 illustrates the number of UFO type loss pattern between the kicker pulses and the number of kicker pulses for certain time intervals. Figure 3: The number of UFO type loss pattern between the kicker pulses and the number of kicker pulses for different time intervals during the MD. Especially after the last injection, many UFO type loss patterns were observed. UFOs directly after MKI pulses 17 of the identified UFO type loss patterns where observed within the second of the pulsing of the MKIs. Table 1 summarizes the MKI pulses and the detected UFO type loss patterns. A UFO type loss pattern was always observed when all four magnets were pulsed or only MKI.D was pulsed. In the four cases where MKI.A was pulsed, no UFO type loss was observed. The kicker pulses are generally accompanied by a small loss signal with a typical duration of 40 80µs (cf. Fig. 4 and Fig. 5), which is recorded by the BLM injection capture buffer (512 40µs). The amplitude of this loss signal is given in Table 1. In all but the highlighted case, the loss signal in the moment of the kicker pulse is smaller than the peak loss of the UFO type loss pattern and cannot explain it 1. It is concluded that in these cases an UFO is directly following the MKI pulses. In two cases the UFO is even recorded by the BLM injection capture buffer (cf. Fig. 4 and Fig. 5). 1 For the UFO type loss pattern after the injection at :30: (highlighted in Table 1), the signal in RS01 and RS02 corresponds to the signal while pulsing the MKIs. The losses in the higher running sums cannot be explained from the beam losses recorded in the injection capture buffer. Especially the loss in RS05 exceeds with 1.44E-04 Gy/s the usual noise level (cf. Appendix A.1). Possibly, a UFO with lower magnitude than the losses while pulsing the MKIs occurred after the injection capture buffer ended
4 Assuming that a macro particle is released in the moment of the kicker pulse and assuming a constant acceleration a of the particle until it interacts with the beam, for these cases, the acceleration can be calculated from the time difference t between MKI pulse and UFO occurrence by a = 2 s t2, with s = 19mm being the half-aperture of the MKI. The resulting acceleration is 658 m for the case depicted in Fig. 4 and 2055 m s 2 s2 for the case depicted in Fig. 5. The resulting particle velocity v p in the moment of the interaction with the beam would be 5.0 m and 8.8 m respectively. In the limit that the macro particle size is much small than the s s beam size, and assuming a constant particle velocity while interacting with the beam 2, the particle velocity can also be calculated from the temporal width σ t of the loss profile by v p = σ b, with σ σ b being the beam size [3]. With a normalized emittance of ε n = 2.5μm rad t and a beta function of β = 43m it is obtained that v p = 2.96 m, respectively v s p = 2.17 m. s The inconsistency of the calculated particle velocities implicates that the simple model of the macro particle dynamics is not sufficient and that the motion is more complex (cf. e.g. [2]). An increased statistics is needed to draw more specific conclusions about the macro particle dynamics. Figure 4: (left) Spatial beam loss pattern of the UFO directly after the injection at 01:29: The loss pattern downstream of the TDI is due to uncaptured beam lost on the TDI. (right) The temporal distribution of the loss. From Gaussian fit: Amplitude: 0.018Gy/s, temporal width: 160µs, delay to kicker pulse: 7.6ms. 2 This is assumed to be a major simplification. The macro particle dynamics is expected to be much more complex due to ionization processes [2]
5 Figure 5: (left) Spatial beam loss pattern of the UFO directly after the injection at 23:54: The loss pattern downstream of the TDI is due to uncaptured beam, lost on the TDI. (right) The temporal distribution of the loss. From Gaussian fit: Amplitude: Gy/s, temporal width: 218µs, delay to kicker pulse: 4.3ms. Timestamp (local time) MKI pulsing UFO detected (BLM) UFO Peak loss RS01 [Gy/s] Peak loss at pulse RS01 [Gy/s] :38: A, B, C, D BLMEI.05R8.B2E10_MKI.D5R8.B2 3.95E E :54: A, B, C, D BLMEI.05R8.B2E10_MKI.D5R8.B2 5.25E E :56: A, B, C, D BLMEI.05R8.B2E20_MKI.C5R8.B2 6.34E E :15: D BLMEI.05R8.B2E10_MKI.D5R8.B2 3.17E E :22: D BLMEI.05R8.B2E10_MKI.D5R8.B2 8.60E E :29: D BLMEI.05R8.B2E10_MKI.D5R8.B2 1.27E E :35: A, B, C, D BLMMI.05R8.B2E30_MKI.B5R8.B2 2.12E E :40: A None N/A 0.0 (MKI.D) :48: A None N/A 0.0 (MKI.D) :56: A None N/A 0.0 (MKI.D) :02: A None N/A 0.0 (MKI.D) :07: A, B, C, D BLMMI.05R8.B2E31_MKI.A5R8.B2 7.96E E :18: A, B, C, D BLMEI.05R8.B2E10_MKI.D5R8.B2 7.78E E :29: A, B, C, D BLMEI.05R8.B2E10_MKI.D5R8.B2 1.38E E :29: A, B, C, D BLMEI.05R8.B2E10_MKI.D5R8.B2 2.05E E :30: A, B, C, D BLMEI.05R8.B2E10_MKI.D5R8.B2 1.36E E :32: A, B, C, D BLMMI.05R8.B2E30_MKI.B5R8.B2 2.05E E :35: A, B, C, D BLMMI.05R8.B2E30_MKI.B5R8.B2 7.02E E :35: A, B, C, D BLMMI.05R8.B2E30_MKI.B5R8.B2 1.18E E :37: A, B, C, D BLMMI.05R8.B2E31_MKI.A5R8.B2 1.18E E :38: A, B, C, D BLMEI.05R8.B2E10_MKI.D5R8.B2 1.81E E-03 Table 1: Overview of MKI pulses and detected UFO type loss patterns in the second of the MKI pulse
6 Timestamp (local time) UFO BLM Peak loss RS01 Peak loss RS05 [Gy/s] [Gy/s] :01:31 BLMMI.05R8.B2E31_MKI.A5R8.B2 7.42E E :05:22 BLMEI.05R8.B2E20_MKI.C5R8.B2 1.73E E :05:29 BLMEI.05R8.B2E20_MKI.C5R8.B2 1.36E E :05:30 BLMEI.05R8.B2E20_MKI.C5R8.B2 3.26E E :09:37 BLMMI.05R8.B2E30_MKI.B5R8.B2 3.62E E :15:26 BLMMI.05R8.B2E31_MKI.A5R8.B2 1.65E E :16:38 BLMMI.05R8.B2E30_MKI.B5R8.B2 2.44E E :21:20 BLMMI.05R8.B2E31_MKI.A5R8.B2 2.72E E :38:06 BLMEI.05R8.B2E10_MKI.D5R8.B2 3.95E E :38:17 BLMMI.05R8.B2E30_MKI.B5R8.B2 5.43E E :39:03 BLMEI.05R8.B2E10_MKI.D5R8.B2 8.15E E :39:09 BLMEI.05R8.B2E20_MKI.C5R8.B2 1.54E E :54:49 BLMEI.05R8.B2E10_MKI.D5R8.B2 5.25E E :55:17 BLMEI.05R8.B2E20_MKI.C5R8.B2 5.43E E :56:20 BLMEI.05R8.B2E20_MKI.C5R8.B2 6.34E E :03:13 BLMEI.05R8.B2E10_MKI.D5R8.B2 1.18E E :15:20 BLMEI.05R8.B2E10_MKI.D5R8.B2 3.17E E :21:31 BLMMI.05R8.B2E31_MKI.A5R8.B2 1.27E E :22:10 BLMEI.05R8.B2E10_MKI.D5R8.B2 8.60E E :29:01 BLMEI.05R8.B2E10_MKI.D5R8.B2 1.27E E :35:06 BLMMI.05R8.B2E30_MKI.B5R8.B2 2.12E E :37:21 BLMMI.05R8.B2E30_MKI.B5R8.B2 9.96E E :45:51 BLMMI.05R8.B2E30_MKI.B5R8.B2 8.24E E :48:26 BLMMI.05R8.B2E30_MKI.B5R8.B2 2.90E E :05:05 BLMMI.05R8.B2E31_MKI.A5R8.B2 3.62E E :07:46 BLMMI.05R8.B2E31_MKI.A5R8.B2 7.96E E :18:25 BLMEI.05R8.B2E10_MKI.D5R8.B2 7.78E E :19:16 BLMEI.05R8.B2E10_MKI.D5R8.B2 3.89E E :19:19 BLMEI.05R8.B2E10_MKI.D5R8.B2 3.80E E :19:40 BLMEI.05R8.B2E20_MKI.C5R8.B2 1.27E E :20:50 BLMEI.05R8.B2E10_MKI.D5R8.B2 1.63E E :21:26 BLMEI.05R8.B2E10_MKI.D5R8.B2 2.08E E :29:03 BLMEI.05R8.B2E10_MKI.D5R8.B2 1.38E E :29:49 BLMEI.05R8.B2E10_MKI.D5R8.B2 2.05E E :30:34 BLMEI.05R8.B2E10_MKI.D5R8.B2 1.36E E :30:46 BLMEI.05R8.B2E10_MKI.D5R8.B2 1.29E E :32:07 BLMMI.05R8.B2E30_MKI.B5R8.B2 2.05E E :35:08 BLMMI.05R8.B2E30_MKI.B5R8.B2 7.02E E :35:23 BLMEI.05R8.B2E20_MKI.C5R8.B2 8.15E E :35:54 BLMMI.05R8.B2E30_MKI.B5R8.B2 1.18E E :37:25 BLMMI.05R8.B2E31_MKI.A5R8.B2 1.18E E :38:10 BLMEI.05R8.B2E10_MKI.D5R8.B2 1.81E E :38:36 BLMEI.05R8.B2E10_MKI.D5R8.B2 1.63E E :06:12 BLMMI.05R8.B2E30_MKI.B5R8.B2 4.53E E :17:51 BLMMI.05R8.B2E30_MKI.B5R8.B2 4.53E E :18:47 BLMMI.05R8.B2E30_MKI.B5R8.B2 3.62E E-05 Table 2: Beam losses at the MKIs with UFO type loss patterns, which were identified during the MD. The highlighted events occurred within the second of the pulsing of the MKIs
7 4. Conclusions and Follow-up The MD showed that pulsing the MKIs directly induces UFO type loss patterns. A post-analysis of injections for normal physics fills revealed several additional cases where a UFO type loss pattern is occurring a few ms after an injection. From the observed loss patterns, it is calculated that the acceleration of macro particle released in the moment of the MKI pulse can exceed the gravitational acceleration by orders of magnitude. A possible explanation could be initially charged dust particles. Following these observations, the triggering of the BLM injection capture buffer was adjusted for nominal operation to increase the detection efficiency of UFOs occurring directly after an injection. The previously observed asymmetry between the four MKI magnets [4] was confirmed by the MD: Whereas there was always observed an UFO type loss pattern after pulsing all four MKIs or MKI.D only, no UFOs were observed directly after pulsing MKI.A. The observations indicate that the UFO rate between the MKI pulses is higher after the last injection with beam and is only secondarily determined by the pulsing of the MKIs. The MD showed that by pulsing the MKIs a sufficient number of UFOs can be produced to study the effect and especially the dynamics of the macro particles. A dedicated UFO MD focusing on comprehensive studies of the production mechanism of UFOs at the MKIs and the MKQA is planned. The use of a dedicated BLM buffer will significantly improve the diagnostics for UFOs which follow directly the kicker pulses. References [1] C. Bracco et al., MD2-2011: Injection studies and MKI UFOs, CERN EDMS Document No , Geneva, June [2] F. Zimmermann, Interaction of macro-particles with the LHC proton beam, IPAC 10, Kyoto, May [3] J. Wenninger, Analysis attempt of dump UFOs, LHC Machine Protection Panel, Geneva, March [4] T. Baer, UFO Update, Mini-Chamonix Workshop, Crozet, July
8 Appendix BLM Noise Appendix A.1: Typical BLM noise of BLMEI.05R8.B2E10_MKI.D5R8.B2 for two minutes stating at :24:00. The spikes are typical noise spikes. Appendix A.2: Typical BLM noise for the mobile monitors 5R8 for two minutes starting at :24:00. The noise is much less than for the permanent monitors 5R8, which can be explained by cabling and acquisition card specific differences
Tobias Baer February, 9 th 2012
UFOs Will they take over? Chamonix Workshop 2012 Tobias Baer February, 9 th 2012 Acknowledgements: W. Bartmann, M. Barnes, C. Bracco, F. Cerutti, B. Dehning, L. Ducimetière, A. Ferrari, N. Fuster Martinez,
More informationLHC commissioning. 22nd June Mike Lamont LHC commissioning - CMS 1
LHC commissioning Mike Lamont AB-OP nd June 005.06.05 LHC commissioning - CMS 1 Detailed planning for 7-87 8 and 8-18 005 006 Short Circuit Tests CNGS/TI8/IT1 HWC LSS.L8.06.05 LHC commissioning - CMS Sector
More informationResults of UFO dynamics studies with beam in the LHC
Journal of Physics: Conference Series PAPER OPEN ACCESS Results of UFO dynamics studies with beam in the LHC To cite this article: B Lindstrom et al 2018 J. Phys.: Conf. Ser. 1067 022001 View the article
More informationLHC operation in 2015 and prospects for the future
LHC operation in 2015 and prospects for the future Moriond Workshop La Thuile March 2016 Jörg Wenninger CERN Beams Department Operation group / LHC For the LHC commissioning and operation teams 1 Moriond
More informationTRANSVERSE DAMPER. W. Höfle, CERN, Geneva, Switzerland. Abstract INTRODUCTION AND HIGHLIGHTS IN Controlled Transverse Blow-up
TRANSVERSE DAMPER W. Höfle, CERN, Geneva, Switzerland Abstract Plans for the operation of the transverse damper in 2012 at bunch spacings of 50 ns and 25 ns and at increased collision energy will be reviewed.
More informationBeam Optics & Dynamics Studies for LHC
Beam Optics & Dynamics Studies for LHC Alexander Koschik ETH Zurich, Integrated Systems Laboratory (Swiss Federal Institute of Technology Zurich) SLAC, Aug. 2010 0 Background Information Master s degree
More informationCommissioning of the LHC collimation system S. Redaelli, R. Assmann, C. Bracco, M. Jonker and G. Robert-Demolaize CERN, AB department
39 th ICFA Advance Beam dynamics Workshop High Intensity High Brightness Hadron Beams - HB 2006 Tsukuba, May 29 th - June 2 nd, 2006 Commissioning of the LHC collimation system S. Redaelli, R. Assmann,
More informationINJECTION AND DUMP CONSIDERATIONS FOR A 16.5 TEV HE-LHC
INJECTION AND DUMP CONSIDERATIONS FOR A 16.5 TEV HE-LHC B. Goddard, M. Barnes, W. Bartmann, J. Borburgh, C. Bracco, L. Ducimetière, V. Kain, M. Meddahi, V. Mertens, V. Senaj, J. Uythoven, CERN, Geneva,
More informationBEAM TESTS OF THE LHC TRANSVERSE FEEDBACK SYSTEM
JINR BEAM TESTS OF THE LHC TRANSVERSE FEEDBACK SYSTEM W.Höfle, G.Kotzian, E.Montesinos, M.Schokker, D.Valuch (CERN) V.M. Zhabitsky (JINR) XXII Russian Particle Accelerator Conference 27.9-1.1. 21, Protvino
More informationOTHER MEANS TO INCREASE THE SPS 25 ns PERFORMANCE TRANSVERSE PLANE
OTHER MEANS TO INCREASE THE SPS 25 ns PERFORMANCE TRANSVERSE PLANE H. Bartosik, G. Arduini, A. Blas, C. Bracco, T. Bohl, K. Cornelis, H. Damerau, S. Gilardoni, S. Hancock, B. Goddard, W. Höfle, G. Iadarola,
More informationEmittance blow-up and loss maps in LHC using the transverse damper as exciter
CERN-ATS-Note-2012-034 MD (LHC) September 5, 2014 Wolfgang.Hofle@cern.ch Emittance blow-up and loss maps in LHC using the transverse damper as exciter W. Hofle, D. Valuch, R. Assmann, S. Redaelli, R. Schmidt,
More informationMain aim: Preparation for high bunch intensity operation with β*=3.5 m and crossing angle (-100 µrad in IR1 and +100 µrad in IR5)
Week 24 Main aim: Preparation for high bunch intensity operation with β*=3.5 m and crossing angle (-100 µrad in IR1 and +100 µrad in IR5) Commission systems required for guaranteeing beam stability as
More informationInjection: Hadron Beams
Proceedings of the CAS CERN Accelerator School: Beam Injection, Extraction and Transfer, Erice, Italy, 10-19 March 2017, edited by B. Holzer, CERN Yellow Reports: School Proceedings, Vol. 5/2018, CERN-2018-008-SP
More informationLHC Run 2: Results and Challenges. Roderik Bruce on behalf of the CERN teams
LHC Run 2: Results and Challenges Roderik Bruce on behalf of the CERN teams Acknowledgements A big thanks to all colleagues involved across various teams! Special thanks for material and discussions G.
More informationStatus and Outlook of the LHC
Status and Outlook of the LHC Enrico Bravin - CERN BE-BI J-PARC visit seminar 6 July 2017 Outlook Overview of LHC Objectives for run2 Parameters for 2016/2017 and differences w.r.t. 2015 Summary of commissioning
More informationLHC Injection Kicker Magnets - An Overview of heating and beam screen changes in LHC-MKI8d
LHC Injection Kicker Magnets - An Overview of heating and beam screen changes in LHC-MKI8d H. Day, M. Barnes, B. Salvant, F. Caspers, E. Metral October 9, 2012 Contents Introduction Contents Background
More informationAccuracy of LHC proton loss rate determination by the BLM system
Accuracy of LHC loss rate determination by the BLM system Eva Barbara Holzer, Bernd Dehning, Christian W. Fabjan, Daniel Kramer, Mariusz Sapinski, and Markus Stockner Abstract Most of the monitors of the
More informationAnomaly Detection for the CERN Large Hadron Collider injection magnets
Anomaly Detection for the CERN Large Hadron Collider injection magnets Armin Halilovic KU Leuven - Department of Computer Science In cooperation with CERN 2018-07-27 0 Outline 1 Context 2 Data 3 Preprocessing
More informationLHC Studies Working Group Notes from the meeting held on 13th September 2011
LHC Studies Working Group Notes from the meeting held on 13th September 2011 The meeting was dedicated to the results of LHC MD#3, which took place from August 24th to 29th. The slides can be found at
More informationOVERVIEW OF THE LHEC DESIGN STUDY AT CERN
OVERVIEW OF THE LHEC DESIGN STUDY AT CERN 1 CERN CH-1211 Geneve 23, Switzerland E-mail: Oliver.bruning@cern.ch Abstract The Large Hadron electron Collider (LHeC) offers the unique possibility of exploring
More informationPlans for 2016 and Run 2
Plans for 2016 and Run 2 Mike Lamont An attempt at synthesis Acknowledgements all round After LS1 It s going to be like after a war Serge Claudet Evian 2012 Where are we? 1/2 6.5 TeV, 2*80 cm, 2*levelled
More informationCOLLECTIVE EFFECTS IN THE LHC AND ITS INJECTORS
COLLECTIVE EFFECTS IN THE LHC AND ITS INJECTORS E. Métral, G. Arduini, R. Assmann, H. Bartosik, P. Baudrenghien, T. Bohl, O. Bruning, X. Buffat, H. Damerau, S. Fartoukh, S. Gilardoni, B. Goddard, S. Hancock,
More informationMACHINE PROTECTION ISSUES AND STRATEGIES FOR THE LHC
MACHINE PROTECTION ISSUES AND STRATEGIES FOR THE LHC R. Schmidt and J. Wenninger for the Working Group on Machine Protection, CERN, Geneva, Switzerland Abstract For nominal beam parameters at 7 TeV/c,
More informationMD Landau Damping: Beam Transfer Functions and diffusion mechanisms
CERN-ACC-NOTE-2017-0026 25-04-2017 claudia.tambasco@cern.ch MD 1407 - Landau Damping: Beam Transfer Functions and diffusion mechanisms C. Tambasco, J. Barranco *, A. Boccardi, X. Buffat, M. Crouch, M.
More informationMachine Protection Systems
Machine Protection Systems Jörg Wenninger CERN Beams Department Operations group Special CERN CAS, Feb. 2009 Introduction Beam induced damage CERN accelerators risks Beam dumps Passive protection Failure
More informationLHC Collimation and Loss Locations
BLM Audit p. 1/22 LHC Collimation and Loss Locations BLM Audit Th. Weiler, R. Assmann, C. Bracco, V. Previtali, S Redaelli Accelerator and Beam Department, CERN BLM Audit p. 2/22 Outline Introduction /
More informationLUMINOSITY LEVELLING TECHNIQUES FOR THE LHC
Published by CERN in the Proceedings of the ICFA Mini-Workshop on Beam Beam Effects in Hadron Colliders, CERN, Geneva, Switzerland, 18 22 March 2013, edited by W. Herr and G. Papotti, CERN 2014 004 (CERN,
More informationINJECTION PAINTING AND ASSOCIATED HW FOR 160 MeV PSB H
Proceedings of HB, Morschach, Switzerland TUOB INJECTION PAINTING AND ASSOCIATED HW FOR 6 MeV PSB H C. Bracco, B. Balhan, J. Borburgh, C. Carli, E. Carlier, R. Chamizo, M. Chanel, T. Fowler, B. Goddard,
More informationFLUKA studies on the radiation in the Point 5 Q6-Q7 area: Roman Pots, TCL6 and RR
FLUKA studies on the radiation in the Point 5 Q6-Q7 area: Roman Pots, TCL6 and RR M. Brugger, F. Cerutti, L.S. Esposito, EN-STI-EET, CERN on behalf of the FLUKA team!! Acknowledgement for the valuable
More informationElectron cloud observation in the LHC
Electron cloud observation in the LHC Giovanni Rumolo IPAC 11, San Sebastian (Spain), 8 September 2011 On behalf of the large team of experimenters and simulators G. Arduini, V. Baglin, H. Bartosik, N.
More informationWill LHCb be running during the HL-LHC era? Burkhard Schmidt for the LHCb Collaboration
Will LHCb be running during the HL-LHC era? Burkhard Schmidt for the LHCb Collaboration Helpful discussions with L. Rossi and several other colleagues from the machine acknowledged Outline: Introduction
More informationCNGS proton beam. Malika Meddahi for SL/BT group CERN
CNGS proton beam Malika Meddahi for SL/BT group CERN CNGS proton beam Layout of the proton line Beam parameters Extraction channel New magnets Intensity limitations Requirements for beam instrumentation
More informationAperture Measurements and Implications
Aperture Measurements and Implications H. Burkhardt, SL Division, CERN, Geneva, Switzerland Abstract Within short time, the 2/90 optics allowed to reach similar luminosity performance as the 90/60 optics,
More informationResults of UFO dynamics studies with beam in the LHC
Results of UFO dynamics studies with beam in the LHC B. Lindstrom, A. Apollonio, P. Bélanger, A. Gorzawski, L. Grob, E.B. Holzer, A. Lechner, R. Schmidt, M. Valette, D. Valuch, D. Wollmann 9 th International
More informationLHC accelerator status and prospects. Frédérick Bordry Higgs Hunting nd September Paris
LHC accelerator status and prospects 2 nd September 2016 - Paris LHC (Large Hadron Collider) 14 TeV proton-proton accelerator-collider built in the LEP tunnel Lead-Lead (Lead-proton) collisions 1983 :
More informationBeam Loss Monitors, Specification
H.Burkhardt, BI Review, Mon. 19/11/2001 Beam Loss Monitors, Specification BLM main scope and challenges types of BLM Collimation, Special, Arc Sensitivity and Time Resolution Summary largely based on work
More informationCollimators and Cleaning, Could this Limit the LHC Performance?
Collimators and Cleaning, Could this Limit the LHC Performance? R. Assmann, CERN-AB/ABP Chamonix XII March 2003 Answer is easy: You bet, collimation and cleaning can limit us! The question we are considering:
More informationarxiv: v2 [physics.acc-ph] 26 Jun 2015
Testing Beam-Induced Quench Levels of LHC Superconducting Magnets in Run 1 B. Auchmann, T. Baer, M. Bednarek, G. Bellodi, C. Bracco, R. Bruce, F. Cerutti, V. Chetvertkova, B. Dehning, P. P. Granieri, W.
More informationRaising intensity of the LHC beam in the SPS - longitudinal plane
SL-Note-- MD Raising intensity of the LHC beam in the SPS - longitudinal plane Ph. Baudrenghien, T. Bohl, T. Linnecar, E. Shaposhnikova Abstract Different aspects of the LHC type beam capture and acceleration
More informationDaniel Wollmann, CERN
LHC parameters for Machine Protection Failure time scales and Machine Protection Systems LHC Operation a machine protection view Machine Protection studies for the future Cold diode qualification Sc. strand
More informationarxiv: v1 [physics.acc-ph] 10 Aug 2016
Machine Protection and Operation for LHC J. Wenninger CERN, Geneva, Switzerland arxiv:1608.03113v1 [physics.acc-ph] 10 Aug 2016 1 Introduction Abstract Since 2010 the Large Hadron Collider (LHC) is the
More informationLHC Commissioning in 2008
LHC Commissioning in 2008 Mike Lamont AB/OP Schedule slides c/o Lyn Evans (MAC 14/6/07) Status: Installation & equipment commissioning LHC commissioning - CMS June 07 2 Procurement problems of remaining
More informationLHC Studies Working Group Notes from the meeting held on 8 December 2011
LHC Studies Working Group Notes from the meeting held on 8 December 2011 The meeting was dedicated to the results of LHC MD#4 and floating MDs, and a first outlook to the requests for 2012. The agenda
More informationInterface with Experimental Detector in the High Luminosity Run
Chapter 5 Interface with Experimental Detector in the High Luminosity Run H. Burkhardt CERN, BE Department, Genève 23, CH-1211, Switzerland This chapter describes the upgrade of the interaction regions
More informationWhy are particle accelerators so inefficient?
Why are particle accelerators so inefficient? Philippe Lebrun CERN, Geneva, Switzerland Workshop on Compact and Low-Consumption Magnet Design for Future Linear and Circular Colliders CERN, 9-12 October
More informationMEASUREMENT AND SIMULATION OF LUMINOSITY LEVELING IN LHC VIA BEAM SEPARATION
MEASUREMENT AND SIMULATION OF LUMINOSITY LEVELING IN LHC VIA BEAM SEPARATION Stefan Paret, Ji Qiang, LBNL, Berkeley, USA Reyes Alemany-Fernandez, Rama Calaga, Rossano Giachino, Werner Herr, Delphine Jacquet,
More informationDYNAMIC APERTURE STUDIES FOR HL-LHC V1.0 *
SLAC PUB 17366 December 2018 DYNAMIC APERTURE STUDIES FOR HL-LHC V1.0 * Y. Cai, R. De Maria, M. Giovannozzi, Y. Nosochkov, F.F. Van der Veken ;1 CERN, CH-1211 Geneva 23, Switzerland SLAC National Accelerator
More informationChallenges and Plans for the Proton Injectors *
Chapter 16 Challenges and Plans for the Proton Injectors * R. Garoby CERN, BE Department, Genève 23, CH-12, Switzerland The flexibility of the LHC injectors combined with multiple longitudinal beam gymnastics
More informationTurn-around improvements
LHC Performance Workshop - Chamonix 2012 Hotel Les Aiglons, Chamonix, France February 6 th -10 th, 2012 Turn-around improvements S. Redaelli, BE-ABP (formerly BE-OP) and W. Venturini Delsolaro, BE-RF (formerly
More informationThe FLUKA study of the secondary particles fluence in the AD-Antiproton Decelerator target area.
2014-01-09 marco.calviani@cern.ch elzbieta.nowak@cern.ch The FLUKA study of the secondary particles fluence in the AD-Antiproton Decelerator target area. M. Calviani and E. Nowak EN/STI CERN, Geneva, Switzerland
More informationThe TESLA Dogbone Damping Ring
The TESLA Dogbone Damping Ring Winfried Decking for the TESLA Collaboration April 6 th 2004 Outline The Dogbone Issues: Kicker Design Dynamic Aperture Emittance Dilution due to Stray-Fields Collective
More informationLHC Beam Operations: Past, Present and Future
LHC Beam Operations: Past, Present and Future Maria Kuhn CERN, Geneva, Switzerland Abstract A brief overview of LHC operations over the last 3 years is provided. Luminosity performance has been satisfactory
More informationHL-LHC OPERATIONAL SCENARIOS
CERN-ACC-NOTE-2015-0009 2015-05-19 Elias.Metral@cern.ch HL-LHC OPERATIONAL SCENARIOS G. Arduini, N. Biancacci, O. Brüning, R. De Maria, M. Giovannozzi, W. Höfle, K. Li, E. Métral, J.E. Muller, Y. Papaphilippou,
More informationBEAM DYNAMICS ISSUES IN THE SNS LINAC
BEAM DYNAMICS ISSUES IN THE SNS LINAC A. Shishlo # on behalf of the SNS Accelerator Group, ORNL, Oak Ridge, TN 37831, U.S.A. Abstract A review of the Spallation Neutron Source (SNS) linac beam dynamics
More informationCOMBINER RING LATTICE
CTFF3 TECHNICAL NOTE INFN - LNF, Accelerator Division Frascati, April 4, 21 Note: CTFF3-2 COMBINER RING LATTICE C. Biscari 1. Introduction The 3 rd CLIC test facility, CTF3, is foreseen to check the feasibility
More informationConceptual design of an accumulator ring for the Diamond II upgrade
Journal of Physics: Conference Series PAPER OPEN ACCESS Conceptual design of an accumulator ring for the Diamond II upgrade To cite this article: I P S Martin and R Bartolini 218 J. Phys.: Conf. Ser. 167
More informationShort Introduction to CLIC and CTF3, Technologies for Future Linear Colliders
Short Introduction to CLIC and CTF3, Technologies for Future Linear Colliders Explanation of the Basic Principles and Goals Visit to the CTF3 Installation Roger Ruber Collider History p p hadron collider
More informationMachine Protection. Lars Fröhlich DESY. CERN Accelerator School on FELs and ERLs June 9, 2016
Machine Protection Lars Fröhlich DESY CERN Accelerator School on FELs and ERLs June 9, 2016 Overview What & Why? Interaction of Beams with Matter Damage to Permanent Magnets Photo: Wikimedia Commons, CC
More informationThe LHC: the energy, cooling, and operation. Susmita Jyotishmati
The LHC: the energy, cooling, and operation Susmita Jyotishmati LHC design parameters Nominal LHC parameters Beam injection energy (TeV) 0.45 Beam energy (TeV) 7.0 Number of particles per bunch 1.15
More informationLuminosity Goals, Critical Parameters
CAS Zürich 22 nd February 2018 Luminosity Goals, Critical Parameters Bruno Muratori, STFC Daresbury Laboratory & Cockcroft Institute Werner Herr, CERN Goals At the end of this lecture you should be able
More informationOpen Issues from the SPS Long-Range Experiments
Open Issues from the SPS Long-Range Experiments Frank Zimmermann US-LARP Beam-Beam Workshop SLAC, 2007 Gerard Burtin, Ulrich Dorda, Gijs de Rijk, Jean-Pierre Koutchouk, Yannis Papaphilippou, Tannaji Sen,
More informationMeasurement and Compensation of Betatron Resonances at the CERN PS Booster Synchrotron
Measurement and Compensation of Betatron Resonances at the CERN PS Booster Synchrotron Urschütz Peter (AB/ABP) CLIC meeting, 29.10.2004 1 Overview General Information on the PS Booster Synchrotron Motivation
More informationD. Brandt, CERN. CAS Frascati 2008 Accelerators for Newcomers D. Brandt 1
Accelerators for Newcomers D. Brandt, CERN D. Brandt 1 Why this Introduction? During this school, you will learn about beam dynamics in a rigorous way but some of you are completely new to the field of
More informationPoS(EPS-HEP2017)533. First Physics Results of AWAKE, a Plasma Wakefield Acceleration Experiment at CERN. Patric Muggli, Allen Caldwell
First Physics Results of AWAKE, a Plasma Wakefield Acceleration Experiment at CERN Patric Muggli, Max Planck Institute for Physics E-mail: muggli@mpp.mpg.de AWAKE is a plasma wakefield acceleration experiment
More informationEuCARD-2 Enhanced European Coordination for Accelerator Research & Development. Conference/Workshop Paper
CERN-ACC-2017-0020 EuCARD-2 Enhanced European Coordination for Accelerator Research & Development Conference/Workshop Paper Upgrade of the CERN SPS Extraction Protection Elements TPS Borburgh, Jan (CERN)
More informationSTATUS OF LHC COMMISSIONING
Proceedings of PAC9, Vancouver, BC, Canada MO1BCI3 STATUS OF LHC COMMISSIONING J. Wenninger, CERN, Geneva Abstract Beam commissioning of the LHC started with injection tests in August 28, and a circulating
More informationLHC Luminosity and Energy Upgrade
LHC Luminosity and Energy Upgrade Walter Scandale CERN Accelerator Technology department EPAC 06 27 June 2006 We acknowledge the support of the European Community-Research Infrastructure Activity under
More informationStatus of the LHC Beam Cleaning Study Group
Status of the LHC Beam Cleaning Study Group R. Assmann, SL BI Review 19.11.2001 BI Review 19.11.01, R. Assmann 1 LHC Beam Cleaning Study Group: Mandate: Study beam dynamics and operational issues for the
More informationLHC APERTURE AND COMMISSIONING OF THE COLLIMATION SYSTEM
LHC APERTURE AND COMMISSIONING OF THE COLLIMATION SYSTEM S. Redaelli, R. Aßmann, G. Robert-Demolaize, CERN, Geneva, Switzerland Abstract The design LHC aperture and its dependence on various optics imperfections
More informationThe Luminosity Upgrade at RHIC. G. Robert-Demolaize, Brookhaven National Laboratory
The Luminosity Upgrade at RHIC G. Robert-Demolaize, Brookhaven National Laboratory RHIC accelerator complex: IPAC'15 - May 3-8, 2015 - Richmond, VA, USA 2 The Relativistic Heavy Ion Collider (RHIC) aims
More informationOn-axis injection into small dynamic aperture
On-axis injection into small dynamic aperture L. Emery Accelerator Systems Division Argonne National Laboratory Future Light Source Workshop 2010 Tuesday March 2nd, 2010 On-Axis (Swap-Out) injection for
More informationCHALLENGES IN BEAM INSTRUMENTATION AND DIAGNOSTICS FOR LARGE RING COLLIDERS BASED ON THE LHC EXPERIENCE
CHALLENGES IN BEAM INSTRUMENTATION AND DIAGNOSTICS FOR LARGE RING COLLIDERS BASED ON THE LHC EXPERIENCE R. Jones, M. Wendt #, J. Wenninger, CERN, Geneva, Switzerland Abstract An overview on some of the
More information(Lead) Ions in the LHC
(Lead) Ions in the LHC Large Hadrons in the Large Hadron Collider John Jowett BE-ABP J.M. Jowett, LHC Performance Workshop, Chamonix, 6/2/2009 1 Plan of talk n Simplified survey of parameter space Energy,
More informationFACET-II Design Update
FACET-II Design Update October 17-19, 2016, SLAC National Accelerator Laboratory Glen White FACET-II CD-2/3A Director s Review, August 9, 2016 Planning for FACET-II as a Community Resource FACET-II Photo
More informationBetatron Matching and Dispersion Matching
Betatron Matching and Dispersion Matching K. Hanke, CERN, Geneva, Switzerland Abstract The TT2-TT10 transfer line optics has been modeled and optimized in order to minimize blow-up at injection into the
More informationLinac4: From Initial Design to Final Commissioning
Linac4: From Initial Design to Final Commissioning Alessandra M Lombardi for the LINAC4 Team 1 Oliver.Abevrle,Davide.Aguglia,Luca.Arnaudon,Philippe.Baudrenghien, Giulia.Bellodi Caterina.Bertone,Yannic.Body,Jan.Borburgh,Enrico.Bravin,Olivier.Brunner,Jean-
More informationPractical Lattice Design
Practical Lattice Design Dario Pellegrini (CERN) dario.pellegrini@cern.ch USPAS January, 15-19, 2018 1/17 D. Pellegrini - Practical Lattice Design Lecture 5. Low Beta Insertions 2/17 D. Pellegrini - Practical
More informationMULTITURN EXTRACTION BASED ON TRAPPING IN STABLE ISLANDS AT CERN PS: RECENT MEASUREMENT ADVANCES
MULTITURN EXTRACTION BASED ON TRAPPING IN STABLE ISLANDS AT CERN PS: RECENT MEASUREMENT ADVANCES M. Giovannozzi and R. Cappi, S. Gilardoni, M. Martini, E. Métral, M A. Sakumi, R. Steerenberg, CERN A.-S.
More informationBeam. RF antenna. RF cable
Status of LEP2 J. Wenninger, SL Operation for the SL division LEPC September 1998 Outline Optics and RF for 1998 Beam current limitations Injection and ramp Performance at high energy Conclusions LEPC/15-09-98
More informationLOLA: Past, present and future operation
LOLA: Past, present and future operation FLASH Seminar 1/2/29 Christopher Gerth, DESY 8/5/29 FLASH Seminar Christopher Gerth 1 Outline Past Present Future 8/5/29 FLASH Seminar Christopher Gerth 2 Past
More informationBeam Cleaning and Collimation Systems
Published by CERN in the Proceedings of the Joint International Accelerator School: Beam Loss and Accelerator Protection, Newport Beach, US, 5 14 November 2014, edited by R. Schmidt, CERN-2016-002 (CERN,
More informationFrequency and time domain analysis of trapped modes in the CERN Proton Synchrotron
Frequency and time domain analysis of trapped modes in the CERN Proton Synchrotron Serena Persichelli CERN Impedance and collective effects BE-ABP-ICE Abstract The term trapped mode refers to a resonance
More informationA multi-physics approach to simulate the RF-heating 3D power map induced by the proton beam in a beam intercepting device
Journal of Physics: Conference Series PAPER OPEN ACCESS A multi-physics approach to simulate the RF-heating 3D power map induced by the proton beam in a beam intercepting device To cite this article: L
More informationRadiation damage in diamond sensors at the CMS experiment of the LHC
Radiation damage in diamond sensors at the CMS experiment of the LHC Moritz Guthoff on behalf of the CMS beam monitoring group ADAMAS Workshop 2012, GSI, Germany IEKP-KIT / CERN KIT University of the State
More informationThe Beam Instrumentation and Diagnostic Challenges for LHC Operation at High Energy
IBIC14 Monterey, California, USA. The Beam Instrumentation and Diagnostic Challenges for LHC Operation at High Energy Rhodri Jones (CERN Beam Instrumentation Group) Outline LHC Performance during Run I
More informationLHC RUN 2: RESULTS AND CHALLENGES
LHC RUN 2: RESULTS AND CHALLENGES R. Bruce, G. Arduini, H. Bartosik, R. de Maria, M. Giovannozzi, G. Iadarola, J.M. Jowett, K. Li, M. Lamont, A. Lechner, E. Metral, D. Mirarchi, T. Pieloni, S. Redaelli,
More informationLattice Design and Performance for PEP-X Light Source
Lattice Design and Performance for PEP-X Light Source Yuri Nosochkov SLAC National Accelerator Laboratory With contributions by M-H. Wang, Y. Cai, X. Huang, K. Bane 48th ICFA Advanced Beam Dynamics Workshop
More informationNOVEL METHOD FOR MULTI-TURN EXTRACTION: TRAPPING CHARGED PARTICLES IN ISLANDS OF PHASE SPACE
EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH CERN - PS DIVISION CERN/PS 200-05 (AE) NOVEL METHOD FOR MULTI-TURN EXTRACTION: TRAPPING CHARGED PARTICLES IN ISLANDS OF PHASE SPACE R. Cappi and M. Giovannozzi
More informationSIMULATION STUDY FOR MEIC ELECTRON COOLING*
SIMULATION STUDY FOR MEIC ELECTRON COOLING* He Zhang #, Yuhong Zhang, JLab, Newport News, VA 23606, USA Abstract Electron cooling of the ion beams is one critical R&D to achieve high luminosities in JLab
More informationarxiv: v1 [physics.acc-ph] 10 Aug 2016
Machine Protection and Interlock Systems for Circular Machines Example for LHC R. Schmidt CERN, Geneva, Switzerland arxiv:1608.03087v1 [physics.acc-ph] 10 Aug 2016 Abstract This paper introduces the protection
More informationBeam Diagnostics Lecture 3. Measuring Complex Accelerator Parameters Uli Raich CERN AB-BI
Beam Diagnostics Lecture 3 Measuring Complex Accelerator Parameters Uli Raich CERN AB-BI Contents of lecture 3 Some examples of measurements done with the instruments explained during the last 2 lectures
More informationACHIEVABLE SPACE-CHARGE TUNE SHIFT WITH LONG LIFETIME IN THE CERN PS & SPS
Contributed talk (15 + 5 min, 30 slides) ACHIEVABLE SPACE-CHARGE TUNE SHIFT WITH LONG LIFETIME IN THE CERN PS & SPS Elias Métral Elias Métral, HB2008 workshop, Nashville, Tennessee, USA, August 25-29,
More informationLHC Commissioning The good, the bad the ugly
LHC Commissioning The good, the bad the ugly eefact2018 Hong-Kong, 25-28 September 2018 J. Wenninger / R. Giachino CERN Beams Department Operation Group / LHC On behalf of the LHC operation & commissioning
More informationAre we ready for the 2009 beam operation?
LHC Performance Workshop - Chamonix 2009 Centre de Congrès Le Majestic, Chamonix, France 2 nd -6 th February 2008 Are we ready for the 2009 beam operation? S. Redaelli, R. Alemany, R. Bailey, V. Kain,
More informationSimulations and measurements of collimation cleaning with 100MJ beams in the LHC
The 4th International Particle Accelerator Conference, IPAC13 May 13 th -17 th, 2013 Shanghai, China Simulations and measurements of collimation cleaning with 100MJ beams in the LHC R. Bruce, R.W. Assmann,
More informationBETATRON SQUEEZE: STATUS, STRATEGY AND ISSUES
BETATRON SQUEEZE: STATUS, STRATEGY AND ISSUES M. Lamont, G. Müller, S. Redaelli, M. Strzelczyk CERN, Geneva, Switzerland Abstract The betatron squeeze will be one of the most critical manipulation of the
More informationStatus and Results of the UA9 Crystal Collimation Experiment at the CERN-SPS
HB2012 - Beijing - 18 September 2012 Status and Results of the UA9 Crystal Collimation Experiment at the CERN-SPS Simone Montesano (CERN) for the UA9 collaboration Silicon strip crystal Outline Crystal
More informationHiLumi LHC FP7 High Luminosity Large Hadron Collider Design Study. Deliverable Report SIMULATION MODELS FOR ENERGY DEPOSITION
CERN-ACC-2013-011 HiLumi LHC FP7 High Luminosity Large Hadron Collider Design Study Deliverable Report SIMULATION MODELS FOR ENERGY Redaelli, Stefano (CERN) 20 November 2012 The HiLumi LHC Design Study
More informationCompressor Lattice Design for SPL Beam
EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH CERN A&B DIVISION AB-Note-27-34 BI CERN-NUFACT-Note-153 Compressor Lattice Design for SPL Beam M. Aiba Abstract A compressor ring providing very short proton
More informationTransverse dynamics Selected topics. Erik Adli, University of Oslo, August 2016, v2.21
Transverse dynamics Selected topics Erik Adli, University of Oslo, August 2016, Erik.Adli@fys.uio.no, v2.21 Dispersion So far, we have studied particles with reference momentum p = p 0. A dipole field
More information