Status and Outlook of the LHC
|
|
- Barry Miles
- 5 years ago
- Views:
Transcription
1
2 Status and Outlook of the LHC Enrico Bravin - CERN BE-BI J-PARC visit seminar 6 July 2017
3 Outlook Overview of LHC Objectives for run2 Parameters for 2016/2017 and differences w.r.t Summary of commissioning and operation Performance and achievements of 2016 and 2017 Peek at 2018 and beyond 3
4 The Large Hadron Collider Double ring of 27 km circumference Twin aperture superconducting magnets Designed to collide protons (and heavy ions) at high energy (7 TeV) and high luminosity (10 34 cm -2 s -1 ) 4 interaction points LHC energy limited to 6.5 TeV by the need to retrain the magnets 200 quenches were needed to reach 6.5 TeV 300 more will be needed to reach 7 TeV (postponed 2020) 4
5 LHC and injectors Protons Linac-2 50 MeV Booster 1.4 GeV PS 25 GeV SPS 450 GeV LHC 7 TeV 208 Pb 82+ Linac MeV/u LEIR 72 MeV/u PS 5.9 GeV/u SPS 177 GeV/u LHC 2.76 TeV/u 5
6 Beam parameters L = N 2 b f revk b 4 " 1 q 1+( xing s ) 2 2 xing Run 1 Run Design Energy [TeV] Ibunch 1.7E E E E E E+11 Bunch spacing [ns] / Beta* [m] *33 55 Crossing angle [urad] / / # of bunches Emittance [mm mrad] Peak Luminosity [cm -2 s -1 ] 7.7E+33 5E E+34 *1.7E34 *1.9E34 1E+34 Integrated Luminosity [fb-1] *45 *45 6
7 Objectives for Run 2 Run 2 main objective: 100 fb -1 p-p for ATLAS and CMS at E cm 13TeV 2015: Recommission the machine after LS1 at E beam = 6.5TeV Target 5 fb : p-p production + Pb-p run Target p-p 25 fb : p-p (+ Pb-Pb in 2018) Target p-p 45 fb -1 /y 7
8 Changes Smaller beta* from 80cm to 40cm higher luminosity New combined ramp & squeeze (3m) shorter cycle Better handling of e-cloud effects mitigate transients, reduced movement of triplet in IR8 Changed BLM thresholds minimise dumps due to UFOs BCMS beams smaller transverse emittances higher luminosity 8
9 Changes Replaced one superconducting dipole, thermal cycle of sector 12, potential e-cloud and UFO surge New optics (Achromatic Telescopic Squeeze) potential for beta* < 40 cm (HL-LHC baseline optics) Dynamic crossing angle during the fill 300 to 240 urad higher luminosity Improved combined ramp & squeeze (1m) shorter cycle Fixed limitations with SPS and injection kicker vacuum longer bunch trains (144 bpi, more bunches) and higher bunch intensity, higher L 9
10 Beam commissioning 3 phases 1. Low intensity single bunch (8E9 protons) 2. Nominal intensity single bunch (1.2E11 protons) 3. Gradual increase of number of bunches (1-2500) 10
11 Commissioning milestones 2017 EYETS - Many interventions warm-up of S12 Ended on April 14 Nominal intensity Injection Started operation with nominals May 4 Powering tests Start March 31 End April 26 Combined ramp and squeeze CR&S on May 12 HW check out BIS loop closed April 28 Squeeze First collisions First collisions May 12 Low intensity injection Low intensity combined ramp and squeeze First beam April 29 First CR&S to 1m April 30 Collimators setup First stable beams Bunch trains injection May 23 3b+3b May 24 12b+12b 72b May 26 Low intensity squeeze First squeeze to 40cm May 1 Physics Intensity ramp-up 2029b June 20 Corrections of Optics, Q, Q`, C - 11
12 Combined Ramp & Squeeze CR&S Squeeze 11m 10m ALICE 6m Beta* [dm] m m LHCb 40cm ATLAS & CMS 12
13 Possible performance limitations Unidentified laying object (ULO) Reduces available aperture Unidentified falling objects (UFO) Trigger beam dumps and magnet quenches Electron cloud Limits number of bunches (vacuum, thermal load) Instabilities: losses, degraded beam quality Hardware faults rate Fault tracking tools (identify critical systems) Consolidations (using fault tracking as input) R2E project (SEU almost gone) 13
14 UFOs Small particles (~10μm) falling onto the beam generating showers Source and mechanism not fully understood yet 2015: 21 UFO-related dumps, including 3 quenches (ULO events not included) In 2016 increased threshold of BLMs Expected increase of UFO-induced quenches (~+1) Expected decrease of UFO-induced dumps(~-10) 2016: 21 UFO-related dumps including 3 quenches 14
15 Evolution of UFOs There is a clear conditioning effect Not known if conditioning will be lost after venting At the present rate UFOs are under control Time 15
16 Electron cloud Electron liberated on the vacuum chamber are accelerated by the p+ beam Accelerated electrons impact on the vacuum chamber liberating more electrons If the SEY is high, and the bunch spacing short, it turns into an avalanche producing heat load on the cold beam screens and trigger beam instabilities electron bombardment reduces the SEY (scrubbing) 16
17 e-cloud in 2016 Modest effects of e-cloud during 2016 due to the limitation in bunch current and short batches Cryo limit 160 w/hc Courtesy G. Iadarola 17
18 e-cloud in 2017 Scrubbing run 18
19 Sector 1-2 back where it was in 2016 Friday Sunday 19
20 Availability 6 June 18 September Excellent availability! Almost 50% of fills dumped by OP Courtesy B. Todd 20
21 Fault analysis 21 Courtesy B. Todd
22 Other limitations in 2016 Start of the run affected by few important faults Some generated long downtimes 66kV transformer IP8, POPS, PS MPS, water flooding Pt.3 Some imposed limitations throughout the year LHC dump B1 N2 leak (in the shadow of other limitations) SPS internal dump (TIDVG) (no 144b/288b trains) Bad vacuum around injection kicker of B2 max total current for B2 limited to ~2.4E14p (e-cloud) 14 April - LHC dump B1 25 April - SPS dump 27 April POPS down 29 April marteen 20 May - PS MPS 21 June - Water Pt. 3 22
23 Standard vs BCMS beams in the PS Standard 72b batch εxy~2.5μm Ibunch < 1.3E11 BCMS 48b batch εxy~1.5μm Ibunch < 1.3E11 23
24 Beam structure The LHC injection gap is ~900ns while the SPS injection gap is ~200ns The maximum number of bunches in the LHC depends on the number of batches per SPS injection 72b / inj. max 2040b (2 x 48b) / inj. max 2220b (2076b) (4 x 72b) / inj. max 2800b PS batch 72b SPS batch 288b SPS batch 144b 3μs Abort gap 26.7km, 89μs, ns slots, max 2800 bunches 24
25 LHC performance MJ/beam Steady production from beginning of June From end of June LHC operated consistently above design peak luminosity 25
26 Production 2016 Astonishing integrated luminosity achievement Fast ramp-up after each configuration change Steady peace through the year 26
27 Operation cycle Turnaround 3h is technically the shortest value Almost half of the fills ended by operators We can finally decide the length of fills! Courtesy B. Todd 27
28 Heavy ion run 2016 summary p - 5 tev c.m. for ALICE Very long fills at levelled luminosity Record fill of 37 hours in stable beams p - Pb and Pb - 8 TeV c.m. Increased bunch intensity of ions and protons Peak luminosity of 8E29 cm -2 s -1, a factor 7.8 better than design 28
29 HI run 2016 goals and results 29
30 LHC as tide and earth quake monitor LHC orbit 13: CET The long and fills at 4 TeV provided a unique opportunity to monitor the earth tides with the LHC during a week around full moon. The model scale is defined by LEP data scaled to LHC. New Zealand 7.8 MW earthquake of 11: UTC clearly visible 30
31 Special operation Van der Meer scans for luminosity calibration Full VdM scans on 17, 18, 27 May for all experiments Partial scans and studies here and there Large beta* run for forward physics (ALFA and TOTEM) September, very successful Plus many ad hoc cycles during the 20 days of MDs Partially with HL-LHC in view, partially to test improvement already applied 31
32 ~ Same days of p-p physics
33 Status of 2017 run Max 1.58 E34 cm -2 s -1 ~6.5 fb -1 33
34 Long term LHC plan 34
35 Conclusions Despite some troublesome events 2016 has been a wonderful year at the LHC Excellent machine availability/reliability as never before UFO, e-cloud, faults under control Despite not pushing parameters too hard due to limitations delivered more than 40fb-1 to ATLAS and CMS Big progress in understanding and controlling the machine Fast start-up in 2017 shows that the machine, the people and the tools are mature Peak luminosity of 2016 already surpassed after only few weeks of physics in 2017 Established a solid base for the coming years 35
36 The End
37 Commissioning milestones 2016 YETS - Many interventions on many systems Ended on March 4 Nominal intensity Injection Started operation with nominals March 29 Powering tests HW check out Low intensity injection Low intensity combined ramp and squeeze Low intensity squeeze Corrections of Optics, Q, Q`, C - Start March 4 End March 21 BIS loop closed March 23 First beam March 25 First CR&S March 26 First squeeze March 26 Combined ramp and squeeze Squeeze First collisions Collimators setup First stable beams Bunch trains injection Physics Intensity ramp-up CR&S on April 6 First collisions April 8 April 23 3b+3b April 24 12b+12b 72b April b June 1 Included special bump in IP5 to increase dispersion in TOTEM 37
38 e-cloud studies Several fills with same conditions during the year to quantify conditioning (modest) 3 fills with 72bpi and increasing bunch intensity Large differences between sectors not understood 38
39 Radiation effects Beam Losses Distance from IP1 (cw) [m] Courtesy S. Danzeca 39
40 Not only ATLAS and CMS ALICE ~13.5 nb -1 LHCb ~1.9 fb -1 Both profit from the long fills 40
41 Luminosity lifetime h turnaround ATLAS 72b 3.0μm 185μrad 96b 2.5μm 185μrad 96b 2.5μm 140μrad CMS Courtesy F.Antoniou, G. Iadarola, Y.Papaphilippou 41
42 Losses in collisions May October 140 μrad During the first few hours in collisions losses well in excess of the burn-off After ~3h losses become dominated by luminosity burn-off Situation improved during the year (BCMS) Courtesy F.Antoniou, G. Iadarola, Y.Papaphilippou Reduction of crossing angle has no effect 42
LHC operation in 2015 and prospects for the future
LHC operation in 2015 and prospects for the future Moriond Workshop La Thuile March 2016 Jörg Wenninger CERN Beams Department Operation group / LHC For the LHC commissioning and operation teams 1 Moriond
More informationPlans for 2016 and Run 2
Plans for 2016 and Run 2 Mike Lamont An attempt at synthesis Acknowledgements all round After LS1 It s going to be like after a war Serge Claudet Evian 2012 Where are we? 1/2 6.5 TeV, 2*80 cm, 2*levelled
More informationLHC accelerator status and prospects. Frédérick Bordry Higgs Hunting nd September Paris
LHC accelerator status and prospects 2 nd September 2016 - Paris LHC (Large Hadron Collider) 14 TeV proton-proton accelerator-collider built in the LEP tunnel Lead-Lead (Lead-proton) collisions 1983 :
More informationLHC Run 2: Results and Challenges. Roderik Bruce on behalf of the CERN teams
LHC Run 2: Results and Challenges Roderik Bruce on behalf of the CERN teams Acknowledgements A big thanks to all colleagues involved across various teams! Special thanks for material and discussions G.
More informationLHC commissioning. 22nd June Mike Lamont LHC commissioning - CMS 1
LHC commissioning Mike Lamont AB-OP nd June 005.06.05 LHC commissioning - CMS 1 Detailed planning for 7-87 8 and 8-18 005 006 Short Circuit Tests CNGS/TI8/IT1 HWC LSS.L8.06.05 LHC commissioning - CMS Sector
More informationLHC Commissioning The good, the bad the ugly
LHC Commissioning The good, the bad the ugly eefact2018 Hong-Kong, 25-28 September 2018 J. Wenninger / R. Giachino CERN Beams Department Operation Group / LHC On behalf of the LHC operation & commissioning
More informationLHC Beam Operations: Past, Present and Future
LHC Beam Operations: Past, Present and Future Maria Kuhn CERN, Geneva, Switzerland Abstract A brief overview of LHC operations over the last 3 years is provided. Luminosity performance has been satisfactory
More informationLHC Luminosity and Energy Upgrade
LHC Luminosity and Energy Upgrade Walter Scandale CERN Accelerator Technology department EPAC 06 27 June 2006 We acknowledge the support of the European Community-Research Infrastructure Activity under
More informationThanks to all Contributors
Thanks to all Contributors High Gradient versus High Field Dr. José Miguel Jiménez CERN Technology Department Head CERN-Spain Liaison Officer 2 Main topics A worldwide success? Full exploitation of the
More informationBeam Loss Monitors, Specification
H.Burkhardt, BI Review, Mon. 19/11/2001 Beam Loss Monitors, Specification BLM main scope and challenges types of BLM Collimation, Special, Arc Sensitivity and Time Resolution Summary largely based on work
More informationGianluigi Arduini CERN - Beams Dept. - Accelerator & Beam Physics Group
Gianluigi Arduini CERN - Beams Dept. - Accelerator & Beam Physics Group Acknowledgements: O. Brüning, S. Fartoukh, M. Giovannozzi, G. Iadarola, M. Lamont, E. Métral, N. Mounet, G. Papotti, T. Pieloni,
More informationMain aim: Preparation for high bunch intensity operation with β*=3.5 m and crossing angle (-100 µrad in IR1 and +100 µrad in IR5)
Week 24 Main aim: Preparation for high bunch intensity operation with β*=3.5 m and crossing angle (-100 µrad in IR1 and +100 µrad in IR5) Commission systems required for guaranteeing beam stability as
More informationLHC status & 2009/2010 operations. Mike Lamont
LHC status & 2009/2010 operations Mike Lamont Contents 7-9-09 LHC status - CMS week 2 Consolidation brief recall Splices Operational energies Potential performance Present status Plans for 2009-2010 Consolidation
More informationLHC. Construction Understanding first the commissioning. Prospects for
LHC Overview The problem what and is fixing LHC it? Construction Understanding first the commissioning problem Making Beam sure commissioning there no Titanic II Prospects for 2009 2010 LHC is a superconducting
More informationLHC Upgrade Plan and Ideas - scenarios & constraints from the machine side
LHC Upgrade Plan and Ideas - scenarios & constraints from the machine side Frank Zimmermann LHCb Upgrade Workshop Edinburgh, 11 January 2007 Frank Zimmermann, LHCb Upgrade Workshop time scale of LHC upgrade
More informationLHC Commissioning in 2008
LHC Commissioning in 2008 Mike Lamont AB/OP Schedule slides c/o Lyn Evans (MAC 14/6/07) Status: Installation & equipment commissioning LHC commissioning - CMS June 07 2 Procurement problems of remaining
More informationLHC RUN 2: RESULTS AND CHALLENGES
LHC RUN 2: RESULTS AND CHALLENGES R. Bruce, G. Arduini, H. Bartosik, R. de Maria, M. Giovannozzi, G. Iadarola, J.M. Jowett, K. Li, M. Lamont, A. Lechner, E. Metral, D. Mirarchi, T. Pieloni, S. Redaelli,
More informationLHC RunII Commissioning and HL-LHC Status
LHC RunII Commissioning and HL-LHC Status The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme 7 Capacities
More informationTransverse dynamics Selected topics. Erik Adli, University of Oslo, August 2016, v2.21
Transverse dynamics Selected topics Erik Adli, University of Oslo, August 2016, Erik.Adli@fys.uio.no, v2.21 Dispersion So far, we have studied particles with reference momentum p = p 0. A dipole field
More informationLarge Hadron Collider at CERN
Large Hadron Collider at CERN Steve Playfer 27km circumference depth 70-140m University of Edinburgh 15th Novemebr 2008 17.03.2010 Status of the LHC - Steve Playfer 1 17.03.2010 Status of the LHC - Steve
More informationLHC Commissioning and First Operation
LHC Commissioning and First Operation PPC 2010, July 12, 2010, Turin, Italy Steve Myers Director for Accelerators and Technology, CERN Geneva (On behalf of the LHC team and international collaborators)
More informationOPERATIONAL BEAMS FOR THE LHC
OPERATIONAL BEAMS FOR THE LHC Y. Papaphilippou, H. Bartosik, G. Rumolo, D. Manglunki, CERN, Geneva, Switzerland Abstract The variety of beams, needed to set-up in the injectors as requested in the LHC,
More informationLHC Collimation and Loss Locations
BLM Audit p. 1/22 LHC Collimation and Loss Locations BLM Audit Th. Weiler, R. Assmann, C. Bracco, V. Previtali, S Redaelli Accelerator and Beam Department, CERN BLM Audit p. 2/22 Outline Introduction /
More informationBeam-Beam DA Simulations for HL-LHC
Beam-Beam DA Simulations for HL-LHC N. Karastathis G. Arduini, X. Buffat, S. Fartoukh, R. de Maria, Y. Papaphilippou on behalf of the HiLumi LHC WP2 Outline: Brief recap of baseline scenario at collisions
More informationThe Luminosity Upgrade at RHIC. G. Robert-Demolaize, Brookhaven National Laboratory
The Luminosity Upgrade at RHIC G. Robert-Demolaize, Brookhaven National Laboratory RHIC accelerator complex: IPAC'15 - May 3-8, 2015 - Richmond, VA, USA 2 The Relativistic Heavy Ion Collider (RHIC) aims
More informationPoS(EPS-HEP 2013)149. LHC, HL-LHC and beyond. M. Lamont.
E-mail: Mike.Lamont@cern.ch A brief overview of LHC operations over the last 3 years is given. Luminosity performance has been satisfactory and the factors that have been exploited are outlined. Availability
More informationMachine Protection Basics of Accelerator Science and Technology at CERN
a) b) c) Machine Protection Basics of Accelerator Science and Technology at CERN Markus Zerlauth with acknowledgements to M.Lamont, R.Schmidt, J. Wenninger and many other CERN colleagues Outline Introduction
More informationChallenges and Plans for the Proton Injectors *
Chapter 16 Challenges and Plans for the Proton Injectors * R. Garoby CERN, BE Department, Genève 23, CH-12, Switzerland The flexibility of the LHC injectors combined with multiple longitudinal beam gymnastics
More information2008 JINST 3 S Main machine layout and performance. Chapter Performance goals
Chapter 2 Main machine layout and performance 2.1 Performance goals The aim of the LHC is to reveal the physics beyond the Standard Model with centre of mass collision energies of up to 14 TeV. The number
More informationLHC Upgrade (accelerator)
LHC Upgrade (accelerator) Time scale of LHC luminosity upgrade Machine performance limitations Scenarios for the LHC upgrade Phase 0: no hardware modifications Phase 1: Interaction Region upgrade Phase
More informationThe TESLA Dogbone Damping Ring
The TESLA Dogbone Damping Ring Winfried Decking for the TESLA Collaboration April 6 th 2004 Outline The Dogbone Issues: Kicker Design Dynamic Aperture Emittance Dilution due to Stray-Fields Collective
More informationThe Beam Instrumentation and Diagnostic Challenges for LHC Operation at High Energy
IBIC14 Monterey, California, USA. The Beam Instrumentation and Diagnostic Challenges for LHC Operation at High Energy Rhodri Jones (CERN Beam Instrumentation Group) Outline LHC Performance during Run I
More informationBeam. RF antenna. RF cable
Status of LEP2 J. Wenninger, SL Operation for the SL division LEPC September 1998 Outline Optics and RF for 1998 Beam current limitations Injection and ramp Performance at high energy Conclusions LEPC/15-09-98
More informationSPPC Study and R&D Planning. Jingyu Tang for the SPPC study group IAS Program for High Energy Physics January 18-21, 2016, HKUST
SPPC Study and R&D Planning Jingyu Tang for the SPPC study group IAS Program for High Energy Physics January 18-21, 2016, HKUST Main topics Pre-conceptual design study Studies on key technical issues R&D
More informationStatus of the LIU project and progress on space charge studies
Status of the LIU project and progress on space charge studies S. Gilardoni CERN BE/ABP In collaboration with: J. Coupard, H. Damerau, A. Funken, B. Goddard, K. Hanke, A. Lombardi, D. Manglunki, M. Meddahi,
More informationBEAM TESTS OF THE LHC TRANSVERSE FEEDBACK SYSTEM
JINR BEAM TESTS OF THE LHC TRANSVERSE FEEDBACK SYSTEM W.Höfle, G.Kotzian, E.Montesinos, M.Schokker, D.Valuch (CERN) V.M. Zhabitsky (JINR) XXII Russian Particle Accelerator Conference 27.9-1.1. 21, Protvino
More informationStatus of the LHC Beam Cleaning Study Group
Status of the LHC Beam Cleaning Study Group R. Assmann, SL BI Review 19.11.2001 BI Review 19.11.01, R. Assmann 1 LHC Beam Cleaning Study Group: Mandate: Study beam dynamics and operational issues for the
More information1.1 Electron-Cloud Effects in the LHC
11 1.1 Electron-Cloud Effects in the LHC F. Zimmermann, E. Benedetto 1 mail to: frank.zimmermann@cern.ch CERN, AB Department, ABP Group 1211 Geneva 23, Switzerland 1.1.1 Introduction The LHC is the first
More informationOverview of LHC Accelerator
Overview of LHC Accelerator Mike Syphers UT-Austin 1/31/2007 Large Hadron Collider ( LHC ) Outline of Presentation Brief history... Luminosity Magnets Accelerator Layout Major Accelerator Issues U.S. Participation
More informationThe LHC: the energy, cooling, and operation. Susmita Jyotishmati
The LHC: the energy, cooling, and operation Susmita Jyotishmati LHC design parameters Nominal LHC parameters Beam injection energy (TeV) 0.45 Beam energy (TeV) 7.0 Number of particles per bunch 1.15
More informationDaniel Wollmann, CERN
LHC parameters for Machine Protection Failure time scales and Machine Protection Systems LHC Operation a machine protection view Machine Protection studies for the future Cold diode qualification Sc. strand
More informationFY04 Luminosity Plan. SAG Meeting September 22, 2003 Dave McGinnis
FY04 Luminosity Plan SAG Meeting September 22, 2003 Dave McGinnis FY03 Performance Accelerator Issues TEV Pbar Main Injector Reliability Operations Study Strategy Shot Strategy Outline FY04 Luminosity
More informationMD Landau Damping: Beam Transfer Functions and diffusion mechanisms
CERN-ACC-NOTE-2017-0026 25-04-2017 claudia.tambasco@cern.ch MD 1407 - Landau Damping: Beam Transfer Functions and diffusion mechanisms C. Tambasco, J. Barranco *, A. Boccardi, X. Buffat, M. Crouch, M.
More informationThe LHC. Part 1. Corsi di Dottorato Corso di Fisica delle Alte Energie Maggio 2014 Per Grafstrom CERN and University of Bologna
The LHC Part 1 Corsi di Dottorato Corso di Fisica delle Alte Energie Maggio 2014 Per Grafstrom CERN and University of Bologna Organizzazione Part 1 Part 2 Part 3 Introduction Energy challenge Luminosity
More informationHL-LHC OPERATIONAL SCENARIOS
CERN-ACC-NOTE-2015-0009 2015-05-19 Elias.Metral@cern.ch HL-LHC OPERATIONAL SCENARIOS G. Arduini, N. Biancacci, O. Brüning, R. De Maria, M. Giovannozzi, W. Höfle, K. Li, E. Métral, J.E. Muller, Y. Papaphilippou,
More informationCommissioning of the LHC collimation system S. Redaelli, R. Assmann, C. Bracco, M. Jonker and G. Robert-Demolaize CERN, AB department
39 th ICFA Advance Beam dynamics Workshop High Intensity High Brightness Hadron Beams - HB 2006 Tsukuba, May 29 th - June 2 nd, 2006 Commissioning of the LHC collimation system S. Redaelli, R. Assmann,
More informationInterface with Experimental Detector in the High Luminosity Run
Chapter 5 Interface with Experimental Detector in the High Luminosity Run H. Burkhardt CERN, BE Department, Genève 23, CH-1211, Switzerland This chapter describes the upgrade of the interaction regions
More informationOperational Experience with HERA
PAC 07, Albuquerque, NM, June 27, 2007 Operational Experience with HERA Joachim Keil / DESY On behalf of the HERA team Contents Introduction HERA II Luminosity Production Experiences with HERA Persistent
More informationRun2 Problem List (Bold-faced items are those the BP Department can work on) October 4, 2002
Run2 Problem List (Bold-faced items are those the BP Department can work on) October 4, 2002 Linac Booster o 4.5-4.8e12 ppp at 0.5 Hz o Space charge (30% loss in the first 5 ms) o Main magnet field quality
More informationOTHER MEANS TO INCREASE THE SPS 25 ns PERFORMANCE TRANSVERSE PLANE
OTHER MEANS TO INCREASE THE SPS 25 ns PERFORMANCE TRANSVERSE PLANE H. Bartosik, G. Arduini, A. Blas, C. Bracco, T. Bohl, K. Cornelis, H. Damerau, S. Gilardoni, S. Hancock, B. Goddard, W. Höfle, G. Iadarola,
More informationWill LHCb be running during the HL-LHC era? Burkhard Schmidt for the LHCb Collaboration
Will LHCb be running during the HL-LHC era? Burkhard Schmidt for the LHCb Collaboration Helpful discussions with L. Rossi and several other colleagues from the machine acknowledged Outline: Introduction
More informationMachine Protection Systems
Machine Protection Systems Jörg Wenninger CERN Beams Department Operations group Special CERN CAS, Feb. 2009 Introduction Beam induced damage CERN accelerators risks Beam dumps Passive protection Failure
More informationTools of Particle Physics I Accelerators
Tools of Particle Physics I Accelerators W.S. Graves July, 2011 MIT W.S. Graves July, 2011 1.Introduction to Accelerator Physics 2.Three Big Machines Large Hadron Collider (LHC) International Linear Collider
More informationPractical Lattice Design
Practical Lattice Design Dario Pellegrini (CERN) dario.pellegrini@cern.ch USPAS January, 15-19, 2018 1/17 D. Pellegrini - Practical Lattice Design Lecture 5. Low Beta Insertions 2/17 D. Pellegrini - Practical
More informationMuch of this material comes from lectures given by Philippe Lebrun (head of CERN's Accelerator Technology Department), at SUSSP, Aug
! " # # $ ' ( # # $ %& ) Much of this material comes from lectures given by Philippe Lebrun (head of CERN's Accelerator Technology Department), at SUSSP, Aug. 2009. http://www.ippp.dur.ac.uk/workshops/09/sussp65/programme/
More informationLHC Status and CERN s future plans. Lyn Evans
LHC Status and CERN s future plans Lyn Evans Machine layout L. Evans EDMS document no. 859415 2 Cryodipole overview 1250 1000 Equivalent dipoles 750 500 250 0 01-Jan-01 01-Jan-02 01-Jan-03 01-Jan-04 01-Jan-05
More informationOn-axis injection into small dynamic aperture
On-axis injection into small dynamic aperture L. Emery Accelerator Systems Division Argonne National Laboratory Future Light Source Workshop 2010 Tuesday March 2nd, 2010 On-Axis (Swap-Out) injection for
More informationPlans for ions in the injector complex D.Manglunki with the help of I-LHC and LIU-PT teams
Plans for ions in the injector complex D.Manglunki with the help of I-LHC and LIU-PT teams Special acknowledgements to T.Bohl, C.Carli, E.Carlier, H.Damerau, L.Ducimetière, R.Garoby, S.Gilardoni, S.Hancock,
More informationCERN Accelerator School Budapest, Hungary 7 October Giulia Papotti (CERN, BE-OP-LHC) acknowledgements to: W. Herr, W. Kozanecki, J.
CERN Accelerator School Budapest, Hungary 7 October 016 Giulia Papotti (CERN, BE-OP-LHC) acknowledgements to: W. Herr, W. Kozanecki, J. Wenninger and with material by: X. Buffat, F. Follin, M. Hostettler
More informationSC magnets for Future HEHIHB Colliders
SC magnets for Future HEHIHB Colliders presented by L. Bottura WAMS, Archamps, March 22-23,2004 Overview Few selected examples of drivers for R&D in the next 10 years LHC upgrades scenarios (why? how?)
More informationShort Introduction to CLIC and CTF3, Technologies for Future Linear Colliders
Short Introduction to CLIC and CTF3, Technologies for Future Linear Colliders Explanation of the Basic Principles and Goals Visit to the CTF3 Installation Roger Ruber Collider History p p hadron collider
More informationThe achievements of the CERN proton antiproton collider
The achievements of the CERN proton antiproton collider Luigi DiLella Scuola Normale Superiore, Pisa, Italy Motivation of the project The proton antiproton collider UA1 and UA2 detectors Discovery of the
More informationUPGRADE ISSUES FOR THE CERN ACCELERATOR COMPLEX
EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics Large Hadron Collider Project LHC Project Report 1110 UPGRADE ISSUES FOR THE CERN ACCELERATOR COMPLEX R. Garoby CERN,
More informationTurn-around improvements
LHC Performance Workshop - Chamonix 2012 Hotel Les Aiglons, Chamonix, France February 6 th -10 th, 2012 Turn-around improvements S. Redaelli, BE-ABP (formerly BE-OP) and W. Venturini Delsolaro, BE-RF (formerly
More informationLHC upgrade based on a high intensity high energy injector chain
LHC upgrade based on a high intensity high energy injector chain Walter Scandale CERN AT department PAF n. 6 CERN, 15 September 2005 luminosity and energy upgrade Phase 2: steps to reach maximum performance
More informationLuminosity for the 100 TeV collider
Luminosity for the 100 TeV collider M.L.Mangano, contribution to the Luminosity discussion session, Jan 15 2015 IAS programme on The Future of High Energy Physics Critical parameter to determine the physics
More informationResults of UFO dynamics studies with beam in the LHC
Journal of Physics: Conference Series PAPER OPEN ACCESS Results of UFO dynamics studies with beam in the LHC To cite this article: B Lindstrom et al 2018 J. Phys.: Conf. Ser. 1067 022001 View the article
More informationPlans for the LHC Luminosity Upgrade Summary of the CARE-HHHAPD-LUMI-05 workshop
Plans for the LHC Luminosity Upgrade Summary of the APD-LUMI-05 workshop Walter Scandale CERN AT department LHC project seminar Geneva, 10 November 2005 We acknowledge the support of the European Community-Research
More informationThe Large Hadron Collider Lyndon Evans CERN
The Large Hadron Collider Lyndon Evans CERN 1.9 K 2.728 K T The coldest ring in the universe! L.R. Evans 1 The Large Hadron Collider This lecture. LHC Technologies Magnets Cryogenics Radiofrequency Vacuum
More informationThe LHC for Dummies. Jamie Boyd (CERN) acknowledgments to many colleagues!
The LHC for Dummies Jamie Boyd (CERN) acknowledgments to many colleagues! 1 The LHC high energy, high luminosity Physics goals of the LHC dictate High energy (design 14 TeV), to maximize sensijvity to
More informationChamonix XII: LHC Performance Workshop. Requirements from the experiments in Year 1*
Chamonix XII: LHC Performance Workshop Requirements from the experiments in Year 1* 3-8 March, 2003 Experiments: Foreseen Status in April 2007 Physics Reach in the First Year Requirements from the Experiments
More informationWe acknowledge the support of the European Community-Research Infrastructure Activity under the FP6 "Structuring the European Research Area"
Scenarios for the LHC Upgrade Walter Scandale & Frank Zimmermann BEAM 2007 CERN We acknowledge the support of the European Community-Research Infrastructure Activity under the FP6 "Structuring the European
More informationFLUKA studies on the radiation in the Point 5 Q6-Q7 area: Roman Pots, TCL6 and RR
FLUKA studies on the radiation in the Point 5 Q6-Q7 area: Roman Pots, TCL6 and RR M. Brugger, F. Cerutti, L.S. Esposito, EN-STI-EET, CERN on behalf of the FLUKA team!! Acknowledgement for the valuable
More informationAccelerators. Lecture V. Oliver Brüning. school/lecture5
Accelerators Lecture V Oliver Brüning AB/ABP http://bruening.home.cern.ch/bruening/summer school/lecture5 V) LEP, LHC + more LEP LHC Other HEP Projects Future Projects What else? LEP Precision Experiment:
More informationBeam losses versus BLM locations at the LHC
Geneva, 12 April 25 LHC Machine Protection Review Beam losses versus BLM locations at the LHC R. Assmann, S. Redaelli, G. Robert-Demolaize AB - ABP Acknowledgements: B. Dehning Motivation - Are the proposed
More informationCERN & the High Energy Frontier
CERN & the High Energy Frontier Emmanuel Tsesmelis CERN Directorate Office Corfu Summer Institute 13th Hellenic School & Workshop on Elementary Particle Physics & Gravity Corfu, Greece 1 September 2013
More informationLHC State of the Art and News
LHC State of the Art and News ATL-GEN-SLIDE-2010-139 16 June 2010 Arno Straessner TU Dresden on behalf of the ATLAS Collaboration FSP 101 ATLAS Vulcano Workshop 2010 Frontier Objects in Astrophysics and
More information8 lectures on accelerator physics
8 lectures on accelerator physics Lectures can be found at Lecture 1 and 2: Introduction Why do we accelerate? What are the important parameters for characterizing accelerators Lecture 3 and 4: Examples
More informationEarly Physics with the CMS detector at LHC
Early Physics with the CMS detector at LHC HLPW2008 6. 8. March 2008 Spa, Belgium Andre Holzner CERN/CMS Outline Status and schedule CMS LHC Early data analyses: The roadmap to discovering new physics
More informationThe LHC Collider. STOA lecture, Brussels, 27 th November 2012 Steve Myers Director of Accelerators and Technology, CERN
The LHC Collider STOA lecture, Brussels, 27 th November 2012 Steve Myers Director of Accelerators and Technology, CERN Outline of Talk The LHC Stored energy and protection systems 2008 start-up 2008 accident
More informationResults of UFO dynamics studies with beam in the LHC
Results of UFO dynamics studies with beam in the LHC B. Lindstrom, A. Apollonio, P. Bélanger, A. Gorzawski, L. Grob, E.B. Holzer, A. Lechner, R. Schmidt, M. Valette, D. Valuch, D. Wollmann 9 th International
More informationOPERATION OF THE LARGE HADRON COLLIDER WITH HEAVY IONS
OPERATION OF THE LARGE HADRON COLLIDER WITH HEAVY IONS R. Bruce CERN - AB/ABP, Geneva, Switzerland also at MAX-lab, Lund University, Sweden Outline Introduction: CERN and the LHC, physics motivation, injector
More informationIMPLEMENTATION AND EXPERIENCE WITH LUMINOSITY LEVELLING WITH OFFSET BEAM
IMPLEMENTATION AND EXPERIENCE WITH LUMINOSITY LEVELLING WITH OFFSET BEAM F. Follin, D. Jacquet, CERN, Geneva, Switzerland Abstract The practice of luminosity levelling with an offset beam has been used
More informationSLS at the Paul Scherrer Institute (PSI), Villigen, Switzerland
SLS at the Paul Scherrer Institute (PSI), Villigen, Switzerland Michael Böge 1 SLS Team at PSI Michael Böge 2 Layout of the SLS Linac, Transferlines Booster Storage Ring (SR) Beamlines and Insertion Devices
More informationBeam Optics & Dynamics Studies for LHC
Beam Optics & Dynamics Studies for LHC Alexander Koschik ETH Zurich, Integrated Systems Laboratory (Swiss Federal Institute of Technology Zurich) SLAC, Aug. 2010 0 Background Information Master s degree
More informationLHC ORBIT SYSTEM, PERFORMANCE AND STABILITY
LHC ORBIT SYSTEM, PERFORMANCE AND STABILITY Kajetan Fuchsberger Abstract During the LHC run period in 2009 the Orbit system proved to be very reliable. In the following the analysis results of the first
More informationELIC: A High Luminosity And Efficient Spin Manipulation Electron-Light Ion Collider Based At CEBAF
ELIC: A High Luminosity And Efficient Spin Manipulation Electron-Light Ion Collider Based At CEBAF Lia Merminga and Yaroslav Derbenev Center for Advanced Studies of Accelerators, Jefferson Laboratory,
More informationICFA Beam-Beam Workshop, March 2013 R. Jacobsson 1
Input from all experiments and machine, thanks to G. Arduini, O. Bruning, T. Camporesi, M. Chamizo, M. Deile, A. Di Mauro, W. Herr, G. Papotti,T. Pauly, T. Pieloni, G. Rakness, T. Sako, S. Zimmermann 1
More informationTransverse beam stability and Landau damping in hadron colliders
Work supported by the Swiss State Secretariat for Educa6on, Research and Innova6on SERI Transverse beam stability and Landau damping in hadron colliders C. Tambasco J. Barranco, X. Buffat, T. Pieloni Acknowledgements:
More informationLecture 1 and 2: Introduction Why do we accelerate? What are the important parameters for characterizing accelerators Lecture 3 and 4: Examples
5 lectures on accelerator physics + 3 invited lectures Lectures can be found at Lecture 1 and 2: Introduction Why do we accelerate? What are the important parameters for characterizing accelerators Lecture
More informationWhy are particle accelerators so inefficient?
Why are particle accelerators so inefficient? Philippe Lebrun CERN, Geneva, Switzerland Workshop on Compact and Low-Consumption Magnet Design for Future Linear and Circular Colliders CERN, 9-12 October
More informationElectron Cloud Studies made at CERN in the SPS
Electron Cloud Studies made at CERN in the SPS J.M. Jimenez On behalf of the Electron Cloud Study Team, a Collaboration between AT and AB Departments Main Topics Introduction LHC Injectors SPS Running
More informationFCC-hh Final-Focus for Flat-Beams: Parameters and Energy Deposition Studies
FCC-hh Final-Focus for Flat-Beams: Parameters and Energy Deposition Studies Jose L. Abelleira, Leon Van Riesen Haupt, Andrei Seryi, Emilia Cruz Alaniz (JAI-FCC team) Thanks to the CERN FLUKA team 10 th
More informationEmittance blow-up and loss maps in LHC using the transverse damper as exciter
CERN-ATS-Note-2012-034 MD (LHC) September 5, 2014 Wolfgang.Hofle@cern.ch Emittance blow-up and loss maps in LHC using the transverse damper as exciter W. Hofle, D. Valuch, R. Assmann, S. Redaelli, R. Schmidt,
More informationHiLumi LHC FP7 High Luminosity Large Hadron Collider Design Study. Deliverable Report SIMULATION MODELS FOR ENERGY DEPOSITION
CERN-ACC-2013-011 HiLumi LHC FP7 High Luminosity Large Hadron Collider Design Study Deliverable Report SIMULATION MODELS FOR ENERGY Redaelli, Stefano (CERN) 20 November 2012 The HiLumi LHC Design Study
More informationTobias Baer February, 9 th 2012
UFOs Will they take over? Chamonix Workshop 2012 Tobias Baer February, 9 th 2012 Acknowledgements: W. Bartmann, M. Barnes, C. Bracco, F. Cerutti, B. Dehning, L. Ducimetière, A. Ferrari, N. Fuster Martinez,
More informationRun II Status and Prospects
Run II Status and Prospects Jeff Spalding Fermilab June 14, 2004 Run II Status and Prospects - Spalding 1 Contents Introduction Major elements of the Run II campaign Present performance Status of the upgrade
More information(4) vacuum pressure & gas desorption in the IRs ( A.
Electron Cloud Effects in the LHC Frank Zimmermann,, SL/AP (1) heat load on the beam screen inside the s.c. magnets (4 20 K) (2) heat load on the cold bore (1.9 K) (3) beam instability at injection (4)
More informationR&D ON FUTURE CIRCULAR COLLIDERS
R&D ON FUTURE CIRCULAR COLLIDERS Double Chooz ALICE Edelweiss HESS Herschel CMS Detecting radiations from the Universe. Conseil Scientifique de l Institut 2015 Antoine Chance and Maria Durante MOTIVATIONS
More informationAccelerators for Beginners and the CERN Complex
Accelerators for Beginners and the CERN Complex Rende Steerenberg CERN, BE/OP 2 Contents Why Accelerators and Colliders? The CERN Accelerator Complex Cycling the Accelerators & Satisfying Users The Main
More information