FLOOD RISK ASSESSMENT 11-4

Size: px
Start display at page:

Download "FLOOD RISK ASSESSMENT 11-4"

Transcription

1 FLOOD RISK ASSESSMENT 11-4

2 Strathy Wood Wind Farm - Flood Risk Assessment Final Report January 2012 Atmos Consulting Ltd Rosebery House 9 Haymarket Terrace Edinburgh EH12 5EZ

3 JBA Office JBA Consulting Port Neuk 1 Longcraig Road South Queensferry EH30 9TD Revision History Revision Ref / Date Issued Amendments Issued to Site Visit Report - Draft / - Lucy Parker 14 October 2011 Site Visit Report - Draft v2 / Amendments following Lucy Parker 31 October 2011 review - s of 17 Oct & 26 Oct 2011 Flood Risk Assessment - Draft / Addition of hydraulic Lucy Parker 21 December 2011 modelling and conclusions Flood Risk Assessment - Final / 10 January 2012 Amendments following comments on Draft Report Lucy Parker Flood Risk Assessment - Final / 16 January 2012 Contract Minor amendments following comments Lucy Parker This report describes work commissioned by Atmos, on behalf of E.ON, through Purchase Order No. POR Atmos representative for the contract was Lucy Parker. Caroline Anderton, Angus Clark and Nicola Buckley of JBA Consulting carried out this work. Prepared by... Nicola Buckley BSc MSc Analyst Reviewed by... Caroline Anderton BSc MSc CEnv CSci MCIWEM C.WEM Principal Analyst Purpose This document has been prepared as a final report for Atmos Consulting Ltd. JBA Consulting accepts no responsibility or liability for any use that is made of this document other than by the Client for the purposes for which it was originally commissioned and prepared. JBA Consulting has no liability regarding the use of this report except to Atmos Consulting Ltd. 2011s Strathy Wood FRA - Final Report.doc

4 Acknowledgements JBA would like to thank Andy Low of SEPA for supplying gauge data. Copyright Jeremy Benn Associates Limited 2012 Carbon Footprint 239g A printed copy of the main text in this document will result in a carbon footprint of 239g if 100% post-consumer recycled paper is used and 304g if primary-source paper is used. These figures assume the report is printed in black and white on A4 paper and in duplex. JBA is aiming to achieve carbon neutrality. 2011s Strathy Wood FRA - Final Report.doc

5 1 Introduction Terms of Reference Reporting Guidelines Flood Risk Assessment Site Description and Details Historical Flooding SEPA Flood Map Existing Flood Alleviation Measures Hydrology Hydraulic Modelling Watercourse Crossings Flood Risk Outwith the Site Impact of the Development on Fluvial Morphology Changes in Surface Runoff Access and Egress Conclusions and Recommendations Appendices A Photographs s Strathy Wood FRA - Final Report.doc

6 List of Figures Figure 2-1: Site Location Plan... 2 Figure 2-2: Plan of the River Strathy Catchments... 3 Figure 2-3: Plan of the Sub-catchments... 4 Figure 2-4: Hydraulic Model Geometries... 8 Figure 2-5: Long Section of The Uair Showing Different Downstream Boundary Conditions... 9 Figure 2-6: Modelled 200 Year Plus Climate Change Flood Outlines Figure 2-7: Watercourse Crossings within Site Boundary Figure 2-8: Photograph of the Existing Bridge on The Uair Figure 2-9: Model Cross Section of the Existing Bridge on The Uair Figure 2-10: Model Cross Section of Proposed Bridge on The Uair (Option a) Figure 2-11: Model Cross Section of Proposed Bridge on The Uair (Option b) Figure 2-12: Model Long Section on The Uair Showing Different Bridge Options Figure 2-13: New Crossing of the Strathy Option Locations Figure 2-14: Model Cross Section of Proposed Bridge over the River Strathy (Location 1 on Embankment) Figure 2-15: Model Cross Section of Proposed Bridge over the River Strathy (Location 1 on Piers) Figure 2-16: Model Long Section on the River Strathy Showing Bridge Options (Location 1) Figure 2-17: Model Cross Section of Proposed Bridge over the River Strathy (Location 2 on Embankment) Figure 2-18: Model Cross Section of Proposed Bridge over the River Strathy (Location 2 on Piers) Figure 2-19: Model Long Section on the River Strathy Showing Bridge Options (Location 2) Figure 2-20: Model Cross Section of Proposed Bridge over the River Strathy (Location 3 on Embankment) Figure 2-21: Model Cross Section of Proposed Bridge over the River Strathy (Location 3 on Piers) Figure 2-22: Model Long Section on the River Strathy Showing Bridge Options (Location 3) Figure 2-23: Model Cross Section of Proposed Bridge over the River Strathy (Location 4 on Embankment) Figure 2-24: Model Cross Section of Proposed Bridge over the River Strathy (Location 4 on Piers) Figure 2-25: Model Long Section on the River Strathy Showing Bridge Options (Location 4) Figure 2-26: Model Cross Section of Proposed Bridge over Tributary Figure 2-27: Model Cross Section of Proposed Bridge over Tributary Figure 2-28: Watercourse Crossings Outwith the Site Boundary Figure 2-29: Flood Risk Receptor Locations s Strathy Wood FRA - Final Report.doc

7 Photograph 1: River Strathy Looking Upstream from Section Photograph 2: River Strathy Looking Downstream from Section Photograph 3: River Strathy Looking Downstream from Section Photograph 4: River Strathy Looking Downstream from Section Photograph 5: River Strathy Looking Upstream from Section Photograph 6: River Strathy Looking Upstream from Section Photograph 7: River Strathy Looking Downstream from Section Photograph 8: River Strathy Looking Across from Right Bank at Section Photograph 9: River Strathy Looking Downstream from Right Bank at Section Photograph 10: River Strathy Looking Upstream from Section Photograph 11: River Strathy Looking Downstream from Section Photograph 12: River Strathy Looking Downstream from Left Bank at Section Photograph 13: River Strathy Looking Downstream from Right Bank at Section Photograph 14: River Strathy Looking Across from Right Bank at Section Photograph 15: River Strathy Looking Downstream from Section Photograph 16: River Strathy Looking Across from Left Bank to Uair Confluence Photograph 17: River Strathy Looking Downstream from Section Photograph 18: River Strathy Looking Downstream from Section Photograph 19: River Strathy Looking Downstream from Section Photograph 20: River Strathy Looking Downstream from Section Photograph 21: The Uair Looking Downstream from Section Photograph 22: Upstream Face of Existing Bridge over The Uair at Section Photograph 23: Looking Downstream to the Existing Bridge over The Uair at Section Photograph 24: The Uair Looking Downstream to its Confluence with the River Strathy Photograph 25: Tributary 1 Looking Downstream from Section Photograph 26: Tributary 1 Looking Downstream from Section Photograph 27: Tributary 1 Looking Downstream from Section Photograph 28: Tributary 2 at Section Photograph 29: Tributary 2 Looking Downstream from Section Photograph 30: Tributary 2 Looking Upstream from Section Photograph 31: Tributary 2 Looking Downstream from Section Photograph 32: Tributary 2 Looking Downstream from Section List of Tables Table 2-1: Catchment Descriptors for the River Strathy at Strathy Bridge... 5 Table 2-2: Gauge Information - River Strathy at Strathy Bridge (96003)... 5 Table 2-3: Parameters of QMED Adjustment for River Strathy Flow Estimations... 6 Table 2-4: Flood Growth Factors... 6 Table 2-5: Peak Flow Estimates for the River Strathy... 6 Table 2-6: Peak Flow Estimates for the Sub-catchments s Strathy Wood FRA - Final Report.doc

8 Table 2-7: Sensitivity Analysis Results... 8 Table 2-8: Existing and Proposed Watercourse Crossings within Site Boundary Table 2-9: Existing Watercourse Crossings within Site Boundary Table 2-10: Modelled Water Levels on The Uair for Different Bridge Options Table 2-11: New Crossing of the Strathy Option Locations Table 2-12: Modelled Water Levels on the River Strathy for Different Bridge Options (Location 1) Table 2-13: Modelled Water Levels on the River Strathy for Different Bridge Options (Location 2) Table 2-14: Modelled Water Levels on the River Strathy for Different Bridge Options (Location 3) Table 2-15: Modelled Water Levels on the River Strathy for Different Bridge Options (Location 4) Table 2-16: New Crossing Over the River Strathy Optioneering Table 2-17: Watercourse Crossings Outwith the Site Boundary - Photographs Table 2-18: Main Flood Risk Receptors Abbreviations ALTBAR... Mean catchment altitude (m above sea level) AMAX... Annual Maximum BFIHOST... Base Flow Index estimated from soil type BHS... British Hydrological Society DPLBAR... Index describing catchment size and drainage path configuration DPSBAR... FEH index of mean drainage path slope FARL... FEH index of flood attenuation due to reservoirs and lakes FEH... Flood Estimation Handbook HEC-RAS... Hydrologic Engineering Center River Analysis System (developed by the US Army) JBA... JBA Consulting Engineers & Scientists maod... metres Above Ordnance Datum NGR... National Grid Reference NRFA... National River Flow Archive OS... Ordnance Survey PROPWET... FEH index of proportion of time that soil is wet QMED... Median Annual Flood (with return period 2 years) SAAR... Standard Average Annual Rainfall (mm) SEPA... Scottish Environment Protection Agency SPRHOST... Standard percentage runoff derived using the HOST classification URBEXT... FEH index of fractional urban extent 2011s Strathy Wood FRA - Final Report.doc

9 1 Introduction 1.1 Terms of Reference E.ON Climate and Renewables Developments Ltd (E.ON) propose to develop land to the south of Strathy in Caithness and Sutherland. The development will require the construction of new river crossings and part of the site lies within SEPA's Indicative River and Coastal Flood Map (Scotland); as such a more detailed assessment of flood risk, specific to the site, is required. The study is necessary to meet the requirements of Scottish Planning Policy, February 2010 (SPP) 1 and SEPA Policy The study comprised the following: Site walkover survey Consultation with SEPA and Highland Council The derivation of peak flows for several local watercourses The construction of hydraulic models on the River Strathy, The Uair and two unnamed tributaries of The Uair The modelling of potential bridge options over the River Strathy, The Uair and two unnamed tributaries of The Uair Advise on watercourse buffer zones Determine pre- and post-development runoff rates and SUDs volumes The consideration of option feasibility for the mitigation of flood risk The analysis of results and preparation of a report to meet the requirements of Scottish Planning Policy (SPP) and SEPA protocol. 1.2 Reporting Guidelines This Flood Risk Assessment is consistent with the reporting requirements detailed within SEPA s Technical Flood Risk Guidance for Stakeholders 3 which supersedes Annex B of SEPA Policy The aim of this document is to ensure that relevant information is presented in a clear format that can be reviewed by the Planning Authority and SEPA and is consistent with SPP 2. 1 Scottish Planning Policy, February Scottish Executive. 2 Scottish Environment Protection Agency Policy No. 41: A SEPA-Planning Authority Protocol, Development at Risk of flooding: Advice and Consultation, Version 1.0. September SEPA Technical Flood Risk Guidance for Stakeholders, Version 6, August flooding.aspx 2011s Strathy Wood FRA - Final Report.doc 1

10 2 Flood Risk Assessment 2.1 Site Description and Details E.ON Climate and Renewables Developments Ltd (E.ON) are proposing the development of an onshore wind farm within an area to the south of Strathy in Caithness and Sutherland. The indicative site boundary is shown within Figure 2-1, with the site referred to herein as 'Strathy Wood'. Figure 2-1: Site Location Plan The main watercourse passing through the site is the River Strathy, which passes through the site from the west to the north. The Uair converges with the River Strathy towards the downstream extent, and a number of additional small tributaries are also present within the area. 2.2 Historical Flooding A review of the BHS Chronology of Historical events, the Internet and the National Library of Scotland (NLS) Licence Digital Collections Archive of the Scotsman Newspaper ( ) did not result in any records of flooding in the vicinity of the site. 2.3 SEPA Flood Map SEPA s flood map is a strategic broad scale tool developed by SEPA for use in assessing flood risk. The River Strathy and Uair are covered by SEPA s Indicative River and Coastal Flood Map (Scotland). Several unnamed watercourses are however too small (catchment areas less than 3km 2 ) to have been covered during SEPA s flood mapping study. Within the study boundary this includes the two unnamed tributaries of the Uair, the Alltan na' Main and the unnamed tributary of the River Strathy (located to the south of the site). 2011s Strathy Wood FRA - Final Report.doc 2

11 2.4 Existing Flood Alleviation Measures There are no formal flood prevention or protection measures present in the immediate vicinity of the site. 2.5 Hydrology Flow estimates were undertaken at eight different locations within the catchment to inform the flood risk assessment. The flow estimation locations are detailed below and their catchments are shown graphically within Figure 2-2 and Figure 2-3. River Strathy Catchments: Catchment 1 (C1) - River Strathy at Strathy Bridge Catchment 2 (C2) - River Strathy downstream of The Uair confluence Catchment 3 (C3) - River Strathy upstream of The Uair confluence Sub-catchments: Catchment 4 (C4) - The Uair Catchment 5 (C5) - The Uair Sub-Catchment A Catchment 6 (C6) - The Uair Sub-catchment B Catchment 7 (C7) - Altan na' Main (to culvert beneath track) Catchment 8 (C8) - Unnamed Upper Catchment (to culvert beneath track) Figure 2-2: Plan of the River Strathy Catchments 2011s Strathy Wood FRA - Final Report.doc 3

12 Figure 2-3: Plan of the Sub-catchments Catchment Characteristics The hydrological catchment of the River Strathy at Strathy Bridge has an area of approximately 121 km 2. The catchment is orientated south to north and drains a remote area of northern Scotland. Land use within the catchment is dominated by heath and moorland, with sheep farming and forestry the predominant land uses. The area is designated a special area of conservation (SAC) for peat. Since the 1970s there has been extensive afforestation within the catchment and forest plantations now represent a significant area (c.25%). There are numerous small lochs within the catchment, which are likely to have an attenuation effect. The FEH CD ROM has a FARL value of for the catchment, which is representative of the storage effect that these lochans may have. The main tributary of the River Strathy is 'The Uair', which converges with the River Strathy to the northeast of Braerathy Lodge. The Uair is fed by numerous small tributaries and hill lochs that flow over open heathland. The catchment has a low percentage of forestry, with the predominant land use being open moorland/heath. The Uair has its source on the northeastern flanks of Cnoc nan Tri-chlach, which flows in to Loch Crocach approximately 15 km upstream of the confluence of The Uair with the River Strathy. A small percentage of flow from the upper portion of The Uair is thought to leave the catchment and flow into the Halladale catchment. Ordnance Survey mapping shows this occurs in two places in the vicinity of Loch nam Breac; at a sluice at the southern end of the loch, and where a stream bifurcates approximately 800 m upstream of the loch. Flow lost from the catchment is not thought be significant enough to affect the hydrological estimates. Geologically the River Strathy catchment predominantly consists of metamorphic migmatitic rocks from the moine supergroup; these represent approximately 80%. A fault runs north to south through the catchment which the River Strathy follows for its last 10 km before flowing into the North Sea. At the northern end of the catchment on the western side of the fault there is an area of Proterozoic Gneiss which represents approximately 10% of the catchment geology. To the east of the fault there is an area of Old Red Sandstone from the mid Devonian period of geological time; there are also small outcrops of this in the south of the catchment. These bedrock formations are overlain (c. 95%) with superficial deposits of till, alluvium and peat. 2011s Strathy Wood FRA - Final Report.doc 4

13 The catchment descriptors for the River Strathy at Strathy Bridge are summarised within Table 2-1. Table 2-1: Catchment Descriptors for the River Strathy at Strathy Bridge AREA (km 2 ) SAAR (mm) 1090 FARL SAAR (mm) 1110 PROPWET 0.60 URBEXT ALTBAR (m above sea level) 161 URBEXT BFIHOST FPEXT DPLBAR (km) FPDBAR DPSBAR (m/km) 58.1 FPLOC SPRHOST (%) Hydrometric Data Gauged data is collected on the River Strathy at Strathy Bridge (station number 96003); located within the study reach at OS NGR NC This gauge is present within the HiFlows-UK database 4. There are 25 years of data available for the gauge, with the most up to date AMAX series for the gauge obtained from SEPA 5 for the purpose of this study; this included data up to 2 November It was noted that the AMAX records received from SEPA were identical to those available on the HiFlows-UK website 6 ; although an additional four years of data were provided within the SEPA dataset. The most up to date SEPA AMAX series was therefore used within the analysis undertaken. However, it was noted by SEPA that there is only confidence in the gauge data up to a flow of approximately QMED; as such the gauge data has only been used in the adjustment of QMED. Additional background information on the gauge at Strathy Bridge was obtained from the National River Flow Archive (NRFA) website 7, and is summarised within Table 2-2. Table 2-2: Gauge Information - River Strathy at Strathy Bridge (96003) Grid Reference NC Station Elevation (maod) 4.5 Mean Flow (m3/s) % Exceedence (m3/s) % Exceedence Average Annual Rainfall (mm) Peak Flow Estimation Peak flow estimations were undertaken for a range of annual probabilities or design events at the flow estimation locations detailed within Section 2.5. Flood estimates for catchments of the size and nature such as these watercourses are frequently undertaken using the Flood Estimation Handbook (FEH). The Flood Estimation Handbook suggests that flow estimates for catchments with a FARL of less than 0.95 should be calculated using the rainfall runoff method. However, in this instance, as gauged data is available on the River Strathy a combination of the statistical and rainfall runoff methods have been utilised. Estimation of QMED An estimation of QMED can be undertaken in one of two ways; (a) using gauged flow data, or (b) using an equation to derive a value from catchment descriptors. A combination of these two methods can also be undertaken, whereby the estimations of QMED from flow data and catchment descriptors at a gauged site are compared to give an adjustment factor which can then be applied to a subject site where the hydrological characteristics are deemed similar. For this purpose the gauged site(s) are termed 'donor sites'. Flow estimations on the River Strathy utilised the Strathy Bridge gauge as a donor for the estimation of QMED, whereas estimations for the sub-catchments derived QMED from catchment descriptors correspondence, Andy Low, SEPA, 18 August s Strathy Wood FRA - Final Report.doc 5

14 The details of the QMED adjustments made for the River Strathy flow estimations can be viewed in Table 2-3. Table 2-3: Parameters of QMED Adjustment for River Strathy Flow Estimations Subject Site River Strathy Bridge River Strathy d/s of The Uair River Strathy u/s of The Uair Donor Site River Strathy Bridge River Strathy Bridge River Strathy Bridge Distance Between Centroids, dij (km) Power Term, a Adjustment Factor QMED from Catchment Descriptors (m3/s) Final Adjusted QMED (m3/s) Flood Growth Curves Due to the low FARL value of the catchment, the flood growth curves have been derived using the rainfall runoff methodology. The growth factors for each catchment are details within Table 2-4. It can be seen that the 1% AP (100 year) growth factors are all within the normal range of 2.1 to 4.0. Table 2-4: Flood Growth Factors Return C1 C2 C3 C4 C5 C6 C7 C8 Period (years) Peak Flows The final peak flows for a range of return periods are displayed in Table 2-5 for the River Strathy and Table 2-6 for the sub-catchments. Table 2-5: Peak Flow Estimates for the River Strathy Return Period (years) Annual Probability [AP] (%) C1 - River Strathy at Strathy Bridge C2 - River Strathy d/s of The Uair C3 - River Strathy u/s of The Uair cc 0.5+cc s Strathy Wood FRA - Final Report.doc 6

15 Table 2-6: Peak Flow Estimates for the Sub-catchments Return Period (years) Annual Probability [AP] (%) C4 - The Uair C5 - Uair Subcatchment A C6 - Uair Subcatchment B C7 - Altan na' Main C8 - Unnamed Upper Catchment cc 0.5+cc The potential effects of climate change were also considered and the design flow for the 0.5% AP (200 year) plus climate change event determined by up scaling by a factor of 20%, as recommended within SEPA s most recent guidance 8. The resulting flow values are also displayed in tables above. 2.6 Hydraulic Modelling Hydraulic modelling was initially undertaken of the existing situation and termed the 'baseline' scenario, and this was then progressed into the modelling of different options for watercourse crossings. The baseline model is detailed below, with the bridge option modelling presented within Section HEC-RAS Models Hydraulic modelling was undertaken within HEC-RAS (Hydraulic Engineering Center-River Analysis System), a one dimensional model software package developed by the US Army Corps of Engineers. Four separate models were constructed to represent the River Strathy, The Uair and two unnamed tributaries; the interaction of the Strathy with the Uair was also investigated. The model locations and geometries are presented within Figure 2-4, with the model extents detailed below: River Strathy: upstream extent NC downstream extent NC The Uair: upstream extent NC downstream extent NC Tributary 1: upstream extent NC downstream extent NC Tributary 2: upstream extent NC downstream extent NC Expansion and contraction coefficients were entered into the model as per the HEC-RAS user manual, and Manning s n values assigned to sections according to observations from the site inspection and the tabulated values in the HEC-RAS manual. The Manning s n values used in the models are typically between and for the channel and to 0.1 for the banks and floodplain areas. The downstream boundary conditions were based on a normal depth relationship for each watercourse, and the effect that water levels in the River Strathy have on levels in The Uair were investigated. 8 SEPA Technical Flood Risk Guidance for Stakeholders, Version 6, August s Strathy Wood FRA - Final Report.doc 7

16 Figure 2-4: Hydraulic Model Geometries Calibration and Sensitivity Analysis Calibration is necessary to develop confidence in the hydraulic model s predictions of flood depths and extents and to test levels of uncertainty and confidence in the parameters used. Calibration is achieved through the use of historic flood data. Ideally, this information is primarily in the form of peak water levels at specific locations, which correspond to peak recorded river flows. Unfortunately no data is available to allow calibration of the models, and sensitivity analysis has therefore been undertaken so as to determine the effect of uncertainty of the different parameters used. The parameters considered are flows (±20%), the downstream boundary condition (±10% of depth) and Manning s n (global ±10%). The analysis was undertaken based on the 0.5% AP (200 year) flow. The results of the sensitivity analysis are displayed within Table 2-7. Table 2-7: Sensitivity Analysis Results Scenario River Strathy The Uair Average Difference (m) Max/ Min Difference (m) Average Difference (m) Max/ Min Difference (m) Flow +20% Flow -20% Manning s +10% Manning s -10% Downstream Boundary +10% Downstream Boundary -10% Downstream Boundary as Level in Strathy n/a n/a s Strathy Wood FRA - Final Report.doc 8

17 Scenario Tributary 1 Tributary 2 Average Difference (m) Max/ Min Difference (m) Average Difference (m) Max/ Min Difference (m) Flow +20% Flow -20% Manning s +10% Manning s -10% Downstream Boundary +10% Downstream Boundary -10% It can be seen that all the models are most sensitive to the flow used. The River Strathy and Uair are relatively sensitive to Manning's 'n', but none of the modelled reaches are particularly sensitive to the downstream boundary due to the steep gradient of the catchments. This is exemplified by Figure 2-5 which shows the 0.5% AP (200 year) modelled levels along The Uair with a normal depth boundary and with the downstream boundary set at the 0.5% AP (200 year) water level in the River Strathy; it can be seen that due to the steep gradient of the channel, changes in the downstream boundary do not propagate far upstream. Figure 2-5: Long Section of The Uair Showing Different Downstream Boundary Conditions Stream_UAIR Reach_200 Uair Legend WS 200yr - ds bdy strathy WS 200yr - final baseline Ground 77 Elevation (m) Main Channel Distance (m) Flood Outlines The 0.5% AP (200 year) plus climate change flood outlines for each of the watercourses modelled are presented in Figure 2-6. It can be seen that all the proposed turbines are located outwith the defined flood zone, and this area should remain undeveloped. 2011s Strathy Wood FRA - Final Report.doc 9

18 Figure 2-6: Modelled 200 Year Plus Climate Change Flood Outlines 2.7 Watercourse Crossings Watercourse crossing optioneering has been undertaken and recommendations provided in line with SEPA s River Crossing Guidance 9. Figure 2-7 shows the existing crossings within the vicinity of the site, along with options for new crossings; further details are provided within Table 2-8. Photographs of the existing crossings on the Uair and Alltan na' Main are shown in Table 2-9. Table 2-8: Existing and Proposed Watercourse Crossings within Site Boundary Crossing A B C & D Details Existing culvert over the Altan na' Main Existing crossing over The Uair - requires upgrading New crossings to be constructed over minor watercourses 1, 2, 3 & 4 Options for new crossing over the River Strathy 9 SEPA (2010) Engineering in the water environment: good practice guide. River crossings, Second Edition, November s Strathy Wood FRA - Final Report.doc 10

19 Figure 2-7: Watercourse Crossings within Site Boundary 2011s Strathy Wood FRA - Final Report.doc 11

20 Table 2-9: Existing Watercourse Crossings within Site Boundary ID Photograph Comments A Iron pipe. c. 0.50m in dia. OS NGR NC B c. 12m in width OS NGR NC E Corrugated Metal Pipe c. 0.50m in dia. OS NGR NC The baseline hydraulic model, as detailed within Section 2.6.1, was used to investigate the effect the proposed changes and new crossings could have on water levels. The modelling considered the following scenarios, with the results for each presented and discussed within the following sections: Upgrade of the existing crossing over The Uair with (a) bridge deck on piers, and (b) bridge deck on a solid abutment across right floodplain. New crossing over the River Strathy at the four potential locations identified (a) with bridge on embankment across floodplains, and (b) with bridge deck raised on piers. New crossings over each of the two unnamed tributaries. 2011s Strathy Wood FRA - Final Report.doc 12

21 A number of assumptions were made during the modelling of the bridges, and these are summarised below: Where the bridge deck has been raised on piers, these have been placed at a spacing of approximately 15 m and set at 2 m in width. Bridge widths were all set at 5 m. Soffit levels were set 600 mm (freeboard) above the 0.5% AP (200 year) plus climate change water level immediately upstream of the structure. Ineffective flow areas were set up and downstream of any abutments, embankments and piers. Freeboard is required to allow for any uncertainty within the calculations and modelling undertaking. In addition, it should help reduce the potential for bridge blockage. This includes the potential for ice blocks within the watercourses to hit the structures; these are anecdotally known to flow down the watercourses during periods of snow melt Crossing Over The Uair There is an existing crossing over The Uair consisting of metal lattice work on a wooden deck. This bridge is located approximately 60 m upstream of the River Strathy Uair confluence. Water levels are anecdotally known to reach the soffit of the bridge during spate conditions, and as such it is likely that there will be a requirement to replace this bridge crossing. The current deck is located at the relief level at which water will flow out of the Uair and across the floodplain. The Uair and floodplain are at a reasonable gradient at this location and therefore any water currently flowing out of bank will simply flow immediately into the River Strathy; there is therefore likely to be limited headloss across the existing structure. Any new structure will need to be situated outwith the main channel, with a deck level set above the 0.5% AP (200 year) with an allowance for climate change and freeboard of 600 mm. The existing bridge is shown within Figure 2-8, with the model cross section presented in Figure 2-9. Figure 2-8: Photograph of the Existing Bridge on The Uair 2011s Strathy Wood FRA - Final Report.doc 13

22 Figure 2-9: Model Cross Section of the Existing Bridge on The Uair 79 Uair RS = BR Legend Elevation (m) WS 200cc WS 50yr WS 2yr Ground Ineff Bank Sta Station (m) Two options were considered for the upgrading of the existing bridge; (a) with the deck raised and connected to high ground and one support pier within the right bank floodplain (Figure 2-10), and (b) with the deck raised, connected to high ground on the left bank and supported on a large abutment on the right bank floodplain (Figure 2-11). The Figures below show the 0.5% AP (200 year) and 50% AP (2 year) modelled flood levels within the proposed bridge structures in place. Figure 2-12 shows a long section of the model reach with the modelled water levels for the 0.5% AP (200 year) plus climate change event during each scenario; these levels are presented in tabular form within Table Figure 2-10: Model Cross Section of Proposed Bridge on The Uair (Option a) 79 Uair RS = BR Legend Elevation (m) WS 200cc WS 50yr WS 2yr Ground Ineff Bank Sta Station (m) Figure 2-11: Model Cross Section of Proposed Bridge on The Uair (Option b) 79 Uair RS = BR Legend Elevation (m) WS 200cc WS 50yr WS 2yr Ground Ineff Bank Sta Station (m) 2011s Strathy Wood FRA - Final Report.doc 14

23 Figure 2-12: Model Long Section on The Uair Showing Different Bridge Options Stream_UAIR Reach_200 Uair Legend WS 200cc - final baseline WS 200cc - br raised piers WS 200cc - br rasied abut Ground Elevation (m) * * * Main Channel Distance (m) Table 2-10: Modelled Water Levels on The Uair for Different Bridge Options Section Baseline (maod).1295* Bridge on Abutment (maod).15625* Difference (m) Bridge on Piers (maod) Difference (m) * * * or * * Notes: * denotes interpolated cross section. Red bold text denotes an increase in water levels. Blue bold text denotes a decrease in water levels. It can be seen that both options reduce the flood water levels in the vicinity of the bridge. This is due to the fact that the current deck is at a relatively low level and therefore acts to significantly raise water levels at the bridge. The proposals for the replacement structure raise the deck above the water levels and therefore increase the flow capacity of the watercourse at the bridge New Crossing Over the River Strathy The current proposal is to provide access over the River Strathy for four turbines to be located on the left bank of the river. During and following the site visit four possible locations for bridge crossings were identified by JBA, and these are presented within Figure s Strathy Wood FRA - Final Report.doc 15

24 Figure 2-13: New Crossing of the Strathy Option Locations Location no. 1 (OS NGR NC ) is located downstream of the Strathy-Uair confluence. This location has been chosen as it would give the greatest ability for the new road to follow the existing contours on the left bank of the river. Location no. 2 (OS NGR NC ) was a site chosen prior to the site visit. This site was chosen due to the SEPA flood map being at its narrowest. Location no. 3 (OS NGR NC ) was suggested by the land owner as this is the location of an existing ford. Location no. 4 (OS NGR NC ) suggested post site visit. Photographs taken at each of these locations are shown within Table s Strathy Wood FRA - Final Report.doc 16

25 Table 2-11: New Crossing of the Strathy Option Locations ID s Strathy Wood FRA - Final Report.doc 17

26 Modelling was undertaken to investigate the effect of constructing a new bridge crossing at each of the four possible locations. Two options were considered at each location; with the bridge raised up on an embankment across the floodplain, and with the bridge deck raised up on piers. Model cross sections and long sections at each location are presented below, along with tables showing the effect the different options have on water levels. Details of the different options are summarised within Table Bridge Location 1 Figure 2-14: Model Cross Section of Proposed Bridge over the River Strathy (Location 1 on Embankment) Strathy RS = BR Legend WS 200cc WS 50yr Elevation (m) WS 2yr Ground Ineff Bank Sta Station (m) Figure 2-15: Model Cross Section of Proposed Bridge over the River Strathy (Location 1 on Piers) Strathy RS = BR Legend WS 200cc WS 50yr Elevation (m) WS 2yr Ground Ineff Bank Sta Station (m) Figure 2-16: Model Long Section on the River Strathy Showing Bridge Options (Location 1) Strathy R_Strathy Reach_100 Legend WS 200cc - baseline WS 200cc - br 1 piers WS 200cc - br 1 embank v2 Ground Elevation (m) Main Channel Distance (m) 2011s Strathy Wood FRA - Final Report.doc 18

27 Table 2-12: Modelled Water Levels on the River Strathy for Different Bridge Options (Location 1) Section Baseline (maod) Bridge on Embankment (maod) Difference (m) Bridge on Piers (maod) Difference (m) Weir New Bridge Notes: * denotes interpolated cross section. Red bold text denotes an increase in water levels. Blue bold text denotes a decrease in water levels. Bridge Location 2 Figure 2-17: Model Cross Section of Proposed Bridge over the River Strathy (Location 2 on Embankment) 88 Strathy RS = BR Legend Elevation (m) WS 200cc WS 50yr WS 2yr Ground Ineff Bank Sta Station (m) Figure 2-18: Model Cross Section of Proposed Bridge over the River Strathy (Location 2 on Piers) 88 Strathy RS = BR Legend Elevation (m) WS 200cc WS 50yr WS 2yr Ground Ineff Bank Sta Station (m) 2011s Strathy Wood FRA - Final Report.doc 19

28 Figure 2-19: Model Long Section on the River Strathy Showing Bridge Options (Location 2) R_Strathy Reach_100 Strathy Legend WS 200cc - baseline WS 200cc - br 2 piers WS 200cc - br 2 embank v2 Ground Elevation (m) Main Channel Distance (m) Table 2-13: Modelled Water Levels on the River Strathy for Different Bridge Options (Location 2) Section Baseline (maod) Bridge on Embankment (maod) Difference (m) Bridge on Piers (maod) Difference (m) Weir * New Bridge Notes: * denotes interpolated cross section. Red bold text denotes an increase in water levels. Blue bold text denotes a decrease in water levels. Bridge Location 3 Figure 2-20: Model Cross Section of Proposed Bridge over the River Strathy (Location 3 on Embankment) 90 Strathy RS = BR Legend Elevation (m) WS 200cc WS 50yr WS 2yr Ground Ineff Bank Sta Station (m) 2011s Strathy Wood FRA - Final Report.doc 20

29 Figure 2-21: Model Cross Section of Proposed Bridge over the River Strathy (Location 3 on Piers) 90 Strathy RS = BR Legend Elevation (m) WS 200cc WS 50yr WS 2yr Ground Ineff Bank Sta Station (m) Figure 2-22: Model Long Section on the River Strathy Showing Bridge Options (Location 3) R_Strathy Reach_100 Strathy Legend WS 200cc - baseline WS 200cc - br 3 piers WS 200cc - br 3 embank v2 Ground Elevation (m) * Main Channel Distance (m) Table 2-14: Modelled Water Levels on the River Strathy for Different Bridge Options (Location 3) Section Baseline (maod) Bridge on Embankment (maod) Difference (m) Bridge on Piers (maod) Difference (m) * New Bridge Weir Notes: * denotes interpolated cross section. Red bold text denotes an increase in water levels. Blue bold text denotes a decrease in water levels. 2011s Strathy Wood FRA - Final Report.doc 21

30 Bridge Location 4 Figure 2-23: Model Cross Section of Proposed Bridge over the River Strathy (Location 4 on Embankment) Strathy RS = BR Legend 92 WS 200cc 90 WS 50yr Elevation (m) WS 2yr Ground Ineff Bank Sta Station (m) Figure 2-24: Model Cross Section of Proposed Bridge over the River Strathy (Location 4 on Piers) Strathy RS = BR Legend 92 WS 200cc 90 WS 50yr Elevation (m) WS 2yr Ground Ineff Bank Sta Station (m) Figure 2-25: Model Long Section on the River Strathy Showing Bridge Options (Location 4) Strathy R_Strathy Reach_100 Legend WS 200cc - baseline WS 200cc - br 4 piers WS 200cc - br 4 embank v2 Ground Elevation (m) Main Channel Distance (m) 2011s Strathy Wood FRA - Final Report.doc 22

31 Table 2-15: Modelled Water Levels on the River Strathy for Different Bridge Options (Location 4) Section Baseline (maod) Bridge on Embankment (maod) Difference (m) Bridge on Piers (maod) Difference (m) New Bridge Weir Notes: * denotes interpolated cross section. Red bold text denotes an increase in water levels. Blue bold text denotes a decrease in water levels. 2011s Strathy Wood FRA - Final Report.doc 23

32 Table 2-16: New Crossing Over the River Strathy Optioneering Location ID Location 1 Location 2 Location 3 Location 4 Bridge Type Bridge Width Across Floodplain (m) Soffit Elevation (maod) Maximum Change in Upstream Water Level (m) Embankment Greatest ability to contour around existing Piers topography. Pros Cons Smallest effect on water levels if constructed on embankment. Long bridge crossing required - floodplain relatively narrow but crossing wide due to freeboard required on deck level. Embankment Shortest crossing option. Erosion to left bank immediately upstream could Piers impact on structure in the future or construction could destabilise this area further. Topography over left bank is steep and could be difficult for access track. Embankment Along line of existing track to ford. Long bridge crossing across wide floodplain. Piers Greatest increase in local water levels Embankment Space to contour round to gain access. Right bank is higher than left. Piers Smallest effect on water levels if constructed on Wide floodplain on left bank. piers. In all locations, the watercourse is modelled as coming out of bank on one side or the other during the 50% AP (2 year) event; there is therefore no preferred location in this respect. 2011s Strathy Wood FRA - Final Report.doc 24

33 It can be seen that each of the proposed options has pros and cons for and against; however, based on the criteria considered within this report, the bridge locations are ranked below in order of preference with regard to flood risk: Option 4 - preferred location. Placing the crossing at this location has the smallest effect on flood water levels (when constructed on piers) and there is scope to contour the access tracks to the bridge with the existing topography. Option 1 - Long bridge crossing but has smallest effect on local water levels if constructed on an embankment. Option 2 - Is the shortest crossing but the area of current erosion upstream would need to be considered carefully. Left bank is also steep and could prove difficult for the construction of access track. Option 3 - Long bridge crossing and has greatest effect on local water levels. However, it should be noted that this analysis does not include all potential parameters, for example, geomorphology and sediment transfer. In general terms, construction on an embankment as opposed to piers would have a greater effect on water levels during flood conditions. Embankments would also have more of an effect on floodplain flow patterns and would increase the time taken for the floodplain to drain after an event; however, this could be taken into consideration during the design phase and it ensured that adequate drainage is provided through the embankments. Construction on piers would have less of an impact on local flow patterns and flood levels, but is likely to be more expensive. Indicative costs for the construction of a crossing at location 4 would be 450,000 with the deck raised up on embankments, and 900,000 with the deck raised on piers New Crossings over Unnamed Tributaries New crossings are proposed over two unnamed tributaries. Both of the tributaries are small watercourses located within narrow, steep valleys. As such, as long as the proposed structures are located above the current flood levels, there would be no effect on water levels within the burns. Modelled cross sections and proposed structure dimensions are presented for each tributary below. Tributary 1 Figure 2-26: Model Cross Section of Proposed Bridge over Tributary Trib_1 RS = BR Legend Elevation (m) WS 200cc WS 50yr WS 2yr Ground Bank Sta Station (m) Deck soffit level = maod Bridge span = 10.9 m 2011s Strathy Wood FRA - Final Report.doc 25

34 Tributary 2 Figure 2-27: Model Cross Section of Proposed Bridge over Tributary 2 Trib_2 RS = BR Legend WS 200cc Elevation (m) WS 50yr WS 2yr Ground Bank Sta Station (m) Deck soffit level = maod Bridge span = 8.3 m Watercourse Crossings Outwith the Site Boundary There are a number of crossings that are located outwith the site boundary, but which convey watercourses beneath the access road to the site; these are likely to require widening. The location of the structures is presented within Figure 2-28, with photographs of each shown in Table Figure 2-28: Watercourse Crossings Outwith the Site Boundary 2011s Strathy Wood FRA - Final Report.doc 26

35 Table 2-17: Watercourse Crossings Outwith the Site Boundary - Photographs Structure Photograph Comments ID 4 Twin rectangular masonry black culvert. c. 1m in height and 0.5m in width. OS NGR NC Concrete pipe culvert. c. 0.75m in dia. OS NGR NC Masonry rectangular block culvert. C. 1.5m in height and 0.5m in width. OS NGR NC s Strathy Wood FRA - Final Report.doc 27

36 7 Twin corrugated iron culverts. Each c. 0.50m dia. OS NGR NC c. 1.5m wide and high OS NGR NC Twin concrete pipes, each c. 0.40m in dia. OS NGR NC c. Corrugated Iron culvert, c. 1m dia. within barrel although inlet collapsed. OS NGR NC s Strathy Wood FRA - Final Report.doc 28

37 11 c. 4 m arch. OS NGR NC Concrete road bridge. Opening c. 0.40m in height, 3 m wide. OS NGR NC CAR Licensing Regulation for the design and construction of the crossing points comes under the Water Environment (Controlled Activities) (Scotland) Regulations 2011 (CAR), with respect to water crossings. The authorisation process operates at three levels to allow for proportionate and risk-based regulation; these are: General Binding Rules Registration Licence - Simple or Complex These levels cover activities with increasing levels of potential impact upon the environment. In the case of the crossing over the River Strathy and The Uair, a simple licence is likely to be required, but the crossings over the two unnamed tributaries are likely to come under the general binding rules as the channel widths are less than 5 m (refer to GBR6). 2.8 Flood Risk Outwith the Site Flood Risk Receptors The site is located in a remote area of Northern Scotland. However, there are several properties downstream of the study area. These are shown graphically in Figure 2-29, with further details provided within Table s Strathy Wood FRA - Final Report.doc 29

38 Figure 2-29: Flood Risk Receptor Locations Table 2-18: Main Flood Risk Receptors Receptor ID Photograph Comments 1 Braerathy Braerathy With site boundary. Set well above floodplain - outside SEPA flood map of the Strathy. OS NGR NC Dallangwell House Downstream of site boundary. Set well above floodplain on paleo terracing - outside SEPA flood map of the Strathy. Access crosses the Strathy. OS NGR NC s Strathy Wood FRA - Final Report.doc 30

39 3 Bowside Cottage Strathy Cottage Downstream of site boundary. Set well above floodplain outside SEPA flood map of the Strathy. OS NGR NC Bowside Lodge Downstream of site boundary. Set well above floodplain outside SEPA flood map of the Strathy. OS NGR NC Strathy Village Hall Downstream of site boundary. Set above floodplain - outside SEPA flood map of the Strathy. OS NGR Wind Turbines It is recommended that no turbines are constructed within the 0.5% AP (200 year) plus climate change flood outline as defined by this study. 2011s Strathy Wood FRA - Final Report.doc 31

40 2.9 Impact of the Development on Fluvial Morphology Designed appropriately the new crossing of the Strathy should not impact of fluvial morphology. Current areas of bank and terracing erosion should be acknowledged and incorporated into the design Changes in Surface Runoff The development of areas of hardstanding at the base of each wind turbine as well as the widening of the existing track and construction of new sections of track will result in localised increases in runoff. In addition, during the construction phase there is also likely to be increases in erosion and sediment transport. Due to the disparate nature of the wind turbines and access tracks, the construction of traditional style SUDs ponds is not appropriate. It is therefore recommended that a system of clean water diversion trenches are constructed upslope of the access tracks and areas of hardstanding, with runoff from the areas of development collected by small drainage channels. Flows from both the clean water diversion channels and development drainage channels should subsequently be directed to a suitable surface water level spreader for overland dispersal. These methods should be implemented both during and post construction. Appropriate pre-discharge treatment of the runoff would be via a gravel filter trench. The treatment volume required for the 50 by 50 m area of hardstanding at the base of each turbine would be 37.5 m Access and Egress The current access track generally lies outwith the 0.5% AP (200 year) plus climate change flood outline as defined within this study. However, the track does cross a number of watercourses between the site and the town of Strathy to the north. The nature of these structures is such that during high flows water is likely to build up on the upstream side and weir over the access track and then flow downslope in to the main valley of the River Strathy. This is exemplified by the crossing over The Uair, where water is shown to overtop the track during the 50% AP (2 year) event and above. Any works required to the existing structures located outwith the site would be assumed to either match the existing capacity of the structures or to exceed them. Due to the nature of the surrounding topography and gradient on the road, flooding from these small watercourses would not be expected to reach extreme depths and should not prevent vehicular access. 2011s Strathy Wood FRA - Final Report.doc 32

41 3 Conclusions and Recommendations E.ON Climate and Renewables Developments Ltd (E.ON) are proposing the development of an onshore wind farm within an area to the south of Strathy in Caithness and Sutherland. The development will require the construction of new river crossings and part of the site lies within SEPA's fluvial Indicative River and Coastal Flood Map (Scotland). As such a more detailed assessment of flood risk, which is specific to the site is required, and this is undertaken herein. The main watercourse passing through the area is the River Strathy, which passes through the west of the site. The Uair converges with the River Strathy towards the downstream extent, and a number of additional small tributaries are also present within the area. Within the development proposal there is a requirement to construct new crossings over the River Strathy as well as over two small tributaries, and to upgrade an existing crossing over The Uair. A baseline hydraulic model was initially developed and was used to investigate the effect the proposed changes and new crossings could have on water levels. The modelling considered the following scenarios: New crossing over the River Strathy at four potential locations with (a) bridge on embankment across floodplains, and (b) bridge deck raised on piers. Upgrade of the existing crossing over The Uair with (a) bridge deck on piers, and (b) bridge deck on a solid abutment across right floodplain. New crossings over two unnamed tributaries. The pros and cons of each potential crossing location over the River Strathy are outlined within the report, with the recommended order of preference summarised below. However, it should be noted that this analysis is only based on the parameters considered within this report, i.e. with regard to flood risk. A plan showing the potential bridge locations can be found within the main body of the report. Option 4 - preferred location. Placing the crossing at this location has the smallest effect on flood water levels (when constructed on piers) and there is scope to contour the access tracks to the bridge with the existing topography. Option 1 - Long bridge crossing but has smallest effect on local water levels if constructed on an embankment. Option 2 - Is the shortest crossing but the area of current erosion upstream would need to be considered carefully. Left bank is also steep and could prove difficult for the construction of access track. Option 3 - Long bridge crossing and has greatest effect on local water levels. Water levels reach the soffit of the existing crossing over The Uair during the 50% AP (2 year) event, with water building up to the upstream of the structure and weiring over the road. Two options are presented for the upgrade of this structure, and both have the effect of reducing the flood water levels in the vicinity of the bridge. The proposals for crossings over the two unnamed tributaries would have no effect on the burns or existing water levels. Access and egress to the site is via an existing track which runs south from the town of Strathy. The track lies outwith SEPA's fluvial Indicative River and Coastal Flood Map (Scotland); however, it does cross a number of watercourses between the site and the town of Strathy to the north. The nature of these structures is such that during high flows water is likely to build up on the upstream side and weir over the access track and then flow downslope in to the main valley of the River Strathy. Any works required to the existing structures located outwith the site would be assumed to either match the existing capacity of the structures or to exceed them. Regulation for the design and construction of the crossing points comes under the Water Environment (Controlled Activities) (Scotland) Regulations 2011 (CAR), with respect to water crossings. The authorisation process operates at three levels to allow for proportionate and risk-based regulation. In the case of the crossing over the River Strathy and The Uair, a 2011s Strathy Wood FRA - Final Report.doc 33

42 simple licence is likely to be required, but the crossings over the two unnamed tributaries are likely to come under the general binding rules. 2011s Strathy Wood FRA - Final Report.doc 34

43 Appendices A Photographs Photograph 1: River Strathy Looking Upstream from Section 1867 Photograph 2: River Strathy Looking Downstream from Section s Strathy Wood FRA - Final Report.doc 35

44 Photograph 3: River Strathy Looking Downstream from Section 1736 Photograph 4: River Strathy Looking Downstream from Section s Strathy Wood FRA - Final Report.doc 36

45 Photograph 5: River Strathy Looking Upstream from Section 1404 Photograph 6: River Strathy Looking Upstream from Section s Strathy Wood FRA - Final Report.doc 37

46 Photograph 7: River Strathy Looking Downstream from Section 1166 Photograph 8: River Strathy Looking Across from Right Bank at Section s Strathy Wood FRA - Final Report.doc 38

47 Photograph 9: River Strathy Looking Downstream from Right Bank at Section 1166 Photograph 10: River Strathy Looking Upstream from Section s Strathy Wood FRA - Final Report.doc 39

48 Photograph 11: River Strathy Looking Downstream from Section 968 Photograph 12: River Strathy Looking Downstream from Left Bank at Section s Strathy Wood FRA - Final Report.doc 40

49 Photograph 13: River Strathy Looking Downstream from Right Bank at Section 968 Photograph 14: River Strathy Looking Across from Right Bank at Section s Strathy Wood FRA - Final Report.doc 41

50 Photograph 15: River Strathy Looking Downstream from Section 778 Photograph 16: River Strathy Looking Across from Left Bank to Uair Confluence 2011s Strathy Wood FRA - Final Report.doc 42

51 Photograph 17: River Strathy Looking Downstream from Section 585 Photograph 18: River Strathy Looking Downstream from Section s Strathy Wood FRA - Final Report.doc 43

52 Photograph 19: River Strathy Looking Downstream from Section 226 Photograph 20: River Strathy Looking Downstream from Section s Strathy Wood FRA - Final Report.doc 44

53 Photograph 21: The Uair Looking Downstream from Section 183 Photograph 22: Upstream Face of Existing Bridge over The Uair at Section s Strathy Wood FRA - Final Report.doc 45

54 Photograph 23: Looking Downstream to the Existing Bridge over The Uair at Section 76 Photograph 24: The Uair Looking Downstream to its Confluence with the River Strathy 2011s Strathy Wood FRA - Final Report.doc 46

55 Photograph 25: Tributary 1 Looking Downstream from Section 251 Photograph 26: Tributary 1 Looking Downstream from Section s Strathy Wood FRA - Final Report.doc 47

56 Photograph 27: Tributary 1 Looking Downstream from Section 135 Photograph 28: Tributary 2 at Section s Strathy Wood FRA - Final Report.doc 48

57 Photograph 29: Tributary 2 Looking Downstream from Section 291 Photograph 30: Tributary 2 Looking Upstream from Section s Strathy Wood FRA - Final Report.doc 49

58 Photograph 31: Tributary 2 Looking Downstream from Section 238 Photograph 32: Tributary 2 Looking Downstream from Section s Strathy Wood FRA - Final Report.doc 50

59 Offices at Atherstone Doncaster Edinburgh Haywards Heath Limerick Newcastle upon Tyne Newport Northallerton Saltaire Skipton Tadcaster Wallingford Warrington Registered Office South Barn Broughton Hall SKIPTON North Yorkshire BD23 3AE t:+44(0) Jeremy Benn Associates Ltd Registered in England Visit our website

Flood and runoff estimation on small catchments. Duncan Faulkner

Flood and runoff estimation on small catchments. Duncan Faulkner Flood and runoff estimation on small catchments Duncan Faulkner Flood and runoff estimation on small catchments Duncan Faulkner and Oliver Francis, Rob Lamb (JBA) Thomas Kjeldsen, Lisa Stewart, John Packman

More information

WINFAP 4 QMED Linking equation

WINFAP 4 QMED Linking equation WINFAP 4 QMED Linking equation WINFAP 4 QMED Linking equation Wallingford HydroSolutions Ltd 2016. All rights reserved. This report has been produced in accordance with the WHS Quality & Environmental

More information

Identification of Rapid Response

Identification of Rapid Response Flood Forecasting for Rapid Response Catchments A meeting of the British Hydrological Society South West Section Bi Bristol, 20 th October 2010 Identification of Rapid Response Catchments Oliver Francis

More information

UPPER COSUMNES RIVER FLOOD MAPPING

UPPER COSUMNES RIVER FLOOD MAPPING UPPER COSUMNES RIVER FLOOD MAPPING DRAFT BASIC DATA NARRATIVE FLOOD INSURANCE STUDY SACRAMENTO COUTY, CALIFORNIA Community No. 060262 November 2008 Prepared By: CIVIL ENGINEERING SOLUTIONS, INC. 1325 Howe

More information

Presented at WaPUG Spring Meeting 1 st May 2001

Presented at WaPUG Spring Meeting 1 st May 2001 Presented at WaPUG Spring Meeting 1 st May 21 Author: Richard Allitt Richard Allitt Associates Ltd 111 Beech Hill Haywards Heath West Sussex RH16 3TS Tel & Fax (1444) 451552 1. INTRODUCTION The Flood Estimation

More information

LOMR SUBMITTAL LOWER NEHALEM RIVER TILLAMOOK COUNTY, OREGON

LOMR SUBMITTAL LOWER NEHALEM RIVER TILLAMOOK COUNTY, OREGON LOMR SUBMITTAL LOWER NEHALEM RIVER TILLAMOOK COUNTY, OREGON Prepared for: TILLAMOOK COUNTY DEPARTMENT OF COMMUNITY DEVELOPMENT 1510-B THIRD STREET TILLAMOOK, OR 97141 Prepared by: 10300 SW GREENBURG ROAD,

More information

Flood Map. National Dataset User Guide

Flood Map. National Dataset User Guide Flood Map National Dataset User Guide Version 1.1.5 20 th April 2006 Copyright Environment Agency 1 Contents 1.0 Record of amendment... 3 2.0 Introduction... 4 2.1 Description of the Flood Map datasets...4

More information

PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0

PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0 PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0 LYCOMING COUNTY S.R.15, SECTION C41 FINAL HYDROLOGIC AND HYDRAULIC REPORT STEAM VALLEY RUN STREAM RELOCATION DATE: June, 2006 REVISED:

More information

Grant 0299-NEP: Water Resources Project Preparatory Facility

Grant 0299-NEP: Water Resources Project Preparatory Facility Document Produced under Grant Project Number: 45206 May 2016 Grant 0299-NEP: Water Resources Project Preparatory Facility Final Report Volume 3 East Rapti (1 of 9) Prepared by Pvt. Ltd. For Ministry of

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

Natural Susceptibility to Coastal Erosion: Methodology and Mapping Summary

Natural Susceptibility to Coastal Erosion: Methodology and Mapping Summary Natural Susceptibility to Coastal Erosion: Methodology and Mapping Summary. Introduction The Flood Risk Management (Scotland) Act 2009 (FRM Act) introduced a coordinated and partnership approach to how

More information

Initial OPW Designation APSR AFRR IRR Co-ordinates Easting: Northing: River / Catchment / Sub-catchment Type of Flooding / Flood Risk

Initial OPW Designation APSR AFRR IRR Co-ordinates Easting: Northing: River / Catchment / Sub-catchment Type of Flooding / Flood Risk Location: Shannon International Airport Radar Station, Co. Clare Unique ID: 275485 (from PFRA database) Initial OPW Designation APSR AFRR IRR Co-ordinates Easting: 137684 Northing: 160636 River / Catchment

More information

Technical Memorandum No Sediment Model

Technical Memorandum No Sediment Model Pajaro River Watershed Study in association with Technical Memorandum No. 1.2.9 Sediment Model Task: Development of Sediment Model To: PRWFPA Staff Working Group Prepared by: Gregory Morris and Elsie Parrilla

More information

Appendix O. Sediment Transport Modelling Technical Memorandum

Appendix O. Sediment Transport Modelling Technical Memorandum Appendix O Sediment Transport Modelling Technical Memorandum w w w. b a i r d. c o m Baird o c e a n s engineering l a k e s design r i v e r s science w a t e r s h e d s construction Final Report Don

More information

Chapter 7 Mudflow Analysis

Chapter 7 Mudflow Analysis Chapter 7 Mudflow Analysis 7.0 Introduction This chapter provides information on the potential and magnitude of mud floods and mudflows that may develop in Aspen due to rainfall events, snowmelt, or rain

More information

PRELIMINARY DRAFT FOR DISCUSSION PURPOSES

PRELIMINARY DRAFT FOR DISCUSSION PURPOSES Memorandum To: David Thompson From: John Haapala CC: Dan McDonald Bob Montgomery Date: February 24, 2003 File #: 1003551 Re: Lake Wenatchee Historic Water Levels, Operation Model, and Flood Operation This

More information

Chelmsford Borough Council LDF: Level 1 SFRA

Chelmsford Borough Council LDF: Level 1 SFRA Chelmsford Borough Council LDF: Level 1 SFRA Urban Capacity Study Sites PPS25 Flood Zones 2007 Figure B20-1 Preliminary Core Strategy Assessment Flood Zone Potential Housing Potential Employment 1, 2 &

More information

ReFH2 Technical Note: Applying ReFH2 FEH13 in small clay catchments

ReFH2 Technical Note: Applying ReFH2 FEH13 in small clay catchments ReFH2 Technical Note: Applying ReFH2 FEH13 in small clay catchments Contents 1 The issue 2 Identifying problem clay catchments and correcting BFIHOST Appendix 1 What is an appropriate value of BFI for

More information

D. MATHEMATICAL MODEL AND SIMULATION

D. MATHEMATICAL MODEL AND SIMULATION D. MATHEMATICAL MODEL AND SIMULATION D - i TABLE OF CONTENTS D.1 Objective of Model Development... D - 1 D.2 Selection of Software... D - 1 D.3 General Steps of Simulation by MOUSE... D - 1 D.4 Cases of

More information

Tool 2.1.4: Inundation modelling of present day and future floods

Tool 2.1.4: Inundation modelling of present day and future floods Impacts of Climate Change on Urban Infrastructure & the Built Environment A Toolbox Tool 2.1.4: Inundation modelling of present day and future floods Authors M. Duncan 1 and G. Smart 1 Affiliation 1 NIWA,

More information

Chapter 7 Mudflow Analysis

Chapter 7 Mudflow Analysis Chapter 7 Mudflow Analysis 7.0 Introduction This chapter provides information on the potential and magnitude of mud floods and mudflows that may develop in Aspen due to rainfall events, snowmelt, or rain

More information

Natural flood management summary: Methodology and mapping

Natural flood management summary: Methodology and mapping Natural flood management summary: Methodology and mapping 1. Introduction The Flood Risk Management (Scotland) Act (FRM Act) introduced a co-ordinated and partnership approach to how we tackle flood risk

More information

Modeling Great Britain s Flood Defenses. Flood Defense in Great Britain. By Dr. Yizhong Qu

Modeling Great Britain s Flood Defenses. Flood Defense in Great Britain. By Dr. Yizhong Qu Modeling Great Britain s Flood Defenses AIRCurrents Editor s note: AIR launched its Inland Flood Model for Great Britain in December 2008. The hazard module captures the physical processes of rainfall-runoff

More information

Extreme rainfall in Cumbria, November 2009 an assessment of storm rarity

Extreme rainfall in Cumbria, November 2009 an assessment of storm rarity Extreme rainfall in Cumbria, November 2009 an assessment of storm rarity Lisa Stewart 1, Dave Morris 1, David Jones 1 and Peter Spencer 2 1 Centre for Ecology and Hydrology, Wallingford, UK; 2 Environment

More information

Karamea floodplain investigation

Karamea floodplain investigation Karamea floodplain investigation NIWA Client Report: CHC2010-107 October 2010 NIWA Project: ELF 10234/1 Karamea floodplain investigation Graeme Smart Jo Bind NIWA contact/corresponding author Graeme Smart

More information

AGENDA ITEM 6 APPENDIX /0151/DET GROUND WATER & SURFACE WATER MANAGEMENT PLAN

AGENDA ITEM 6 APPENDIX /0151/DET GROUND WATER & SURFACE WATER MANAGEMENT PLAN CAIRNGORMS NATIONAL PARK AUTHORITY Planning Committee Agenda Item 6 Appendix 18 12/10/2018 AGENDA ITEM 6 APPENDIX 18 2018/0151/DET GROUND WATER & SURFACE WATER MANAGEMENT PLAN Dalwhinnie Quarry Ground

More information

A SIMPLE GIS METHOD FOR OBTAINING FLOODED AREAS

A SIMPLE GIS METHOD FOR OBTAINING FLOODED AREAS A SIMPLE GIS METHOD FOR OBTAINING FLOODED AREAS ROMAN P., I. 1, OROS C., R. 2 ABSTRACT. A simple GIS method for obtaining flooded areas. This paper presents a method for obtaining flooded areas near to

More information

CONCEPTUAL AND TECHNICAL CHALLENGES IN DEFINING FLOOD PLANNING AREAS IN URBAN CATCHMENTS

CONCEPTUAL AND TECHNICAL CHALLENGES IN DEFINING FLOOD PLANNING AREAS IN URBAN CATCHMENTS CONCEPTUAL AND TECHNICAL CHALLENGES IN DEFINING FLOOD PLANNING AREAS IN URBAN CATCHMENTS C Ryan 1, D Tetley 2, C Kinsey 3 1 & 2 Catchment Simulation Solutions, NSW 3 Co-ordinator Stormwater and Structural

More information

Degradation Concerns related to Bridge Structures in Alberta

Degradation Concerns related to Bridge Structures in Alberta Degradation Concerns related to Bridge Structures in Alberta Introduction There has been recent discussion regarding the identification and assessment of stream degradation in terms of how it relates to

More information

The UK Benchmark Network (UKBN2) User Guide. A network of near-natural catchments

The UK Benchmark Network (UKBN2) User Guide. A network of near-natural catchments The UK Benchmark Network (UKBN2) A network of near-natural catchments Last modified: 30/04/2018 The UK Benchmark Network The UK Benchmark Network (UKBN) comprises a subset of gauging stations from the

More information

LOMR SUBMITTAL LOWER NESTUCCA RIVER TILLAMOOK COUNTY, OREGON

LOMR SUBMITTAL LOWER NESTUCCA RIVER TILLAMOOK COUNTY, OREGON LOMR SUBMITTAL LOWER NESTUCCA RIVER TILLAMOOK COUNTY, OREGON Prepared for: TILLAMOOK COUNTY DEPARTMENT OF COMMUNITY DEVELOPMENT 1510-B THIRD STREET TILLAMOOK, OR 97141 Prepared by: 10300 SW GREENBURG ROAD,

More information

Technical Memorandum No

Technical Memorandum No Pajaro River Watershed Study in association with Technical Memorandum No. 1.2.10 Task: Evaluation of Four Watershed Conditions - Sediment To: PRWFPA Staff Working Group Prepared by: Gregory Morris and

More information

MEMORANDUM. Situation. David Ford Consulting Engineers, Inc J Street, Suite 200 Sacramento, CA Ph Fx

MEMORANDUM. Situation. David Ford Consulting Engineers, Inc J Street, Suite 200 Sacramento, CA Ph Fx David Ford Consulting Engineers, Inc. 2015 J Street, Suite 200 Sacramento, CA 95811 Ph. 916.447.8779 Fx. 916.447.8780 MEMORANDUM To: Brad Moore, PE, USACE From: Nathan Pingel, PE (Lic # CA 63242), and

More information

FLOOD HAZARD AND RISK ASSESSMENT IN MID- EASTERN PART OF DHAKA, BANGLADESH

FLOOD HAZARD AND RISK ASSESSMENT IN MID- EASTERN PART OF DHAKA, BANGLADESH FLOOD HAZARD AND RISK ASSESSMENT IN MID- EASTERN PART OF DHAKA, BANGLADESH Muhammad MASOOD MEE07180 Supervisor: Prof. Kuniyoshi TAKEUCHI ABSTRACT An inundation simulation has been done for the mid-eastern

More information

FLOOD RISK MAPPING AND ANALYSIS OF THE M ZAB VALLEY, ALGERIA

FLOOD RISK MAPPING AND ANALYSIS OF THE M ZAB VALLEY, ALGERIA River Basin Management IX 69 FLOOD RISK MAPPING AND ANALYSIS OF THE M ZAB VALLEY, ALGERIA AMEL OUCHERIF & SAADIA BENMAMAR National Polytechnic School of Algiers, Algeria ABSTRACT To contribute to flood

More information

Hydrological Survey of Black Hill, Bedminnie Moss, and Tappethill Moss

Hydrological Survey of Black Hill, Bedminnie Moss, and Tappethill Moss Hydrological Survey of Black Hill, Bedminnie Moss, and Tappethill Moss East Ayrshire Report: Tappethill Hydrological Report r2.docx August 2015 Prepared for: Daisy Whytock, Project Manager, East Ayrshire

More information

The Revitalised Flood Hydrograph Model ReFH 2.2: Technical Guidance

The Revitalised Flood Hydrograph Model ReFH 2.2: Technical Guidance The Revitalised Flood Hydrograph Model ReFH 2.2: Technical Guidance The Revitalised Flood Hydrograph Model ReFH 2.2: Technical Guidance Wallingford HydroSolutions Ltd 2016. All rights reserved. This report

More information

via via CCTA File /6 Train Avenue West and 70 Yonge Street South, Springwater Natural Hazard Study

via via  CCTA File /6 Train Avenue West and 70 Yonge Street South, Springwater Natural Hazard Study January 16, 217 via via email (vsimpson@ipsconsulting.com) CCTA File 416428 Vanessa Simpson, B.ID, M.PL. Junior Planner/ Planning Technician Innovative Planning Solutions 1 Dunlop Street East, Suite 21

More information

Appendix E Guidance for Shallow Flooding Analyses and Mapping

Appendix E Guidance for Shallow Flooding Analyses and Mapping Appendix E Guidance for Shallow Flooding Analyses and Mapping E.1 Introduction Different types of shallow flooding commonly occur throughout the United States. Types of flows that result in shallow flooding

More information

APPLICATION OF HEC-RAS MODEL FOR ESTIMATING CHANGES IN WATERCOURSE GEOMETRY DURING FLOODS

APPLICATION OF HEC-RAS MODEL FOR ESTIMATING CHANGES IN WATERCOURSE GEOMETRY DURING FLOODS Studia Geotechnica et Mechanica, Vol. XXXIV, No. 2, 2012 DOI: 105277/sgm021206 APPLICATION OF HEC-RAS MODEL FOR ESTIMATING CHANGES IN WATERCOURSE GEOMETRY DURING FLOODS JOANNA MARKOWSKA Department of Environmental

More information

6.4 Sensitivity Tests

6.4 Sensitivity Tests 6.4 Sensitivity Tests 6.4.1 Sensitivity of Floodplain Inundation to Width of Dry Culvert The preliminary design for the Expressway based on consideration of possible future climate effects to 2090 assumed

More information

The last three sections of the main body of this report consist of:

The last three sections of the main body of this report consist of: Threatened and Endangered Species Geological Hazards Floodplains Cultural Resources Hazardous Materials A Cost Analysis section that provides comparative conceptual-level costs follows the Environmental

More information

Lecture 10: River Channels

Lecture 10: River Channels GEOG415 Lecture 10: River Channels 10-1 Importance of channel characteristics Prediction of flow was the sole purpose of hydrology, and still is a very important aspect of hydrology. - Water balance gives

More information

Four Mile Run Levee Corridor Stream Restoration

Four Mile Run Levee Corridor Stream Restoration Four Mile Run Levee Corridor Stream Restoration 30% Design Summary U.S. Army Corps of Engineers, Baltimore District Presentation Outline Four Mile Run 1.) Historic Perspective 2.) Existing Conditions 3.)

More information

Stream Geomorphology. Leslie A. Morrissey UVM July 25, 2012

Stream Geomorphology. Leslie A. Morrissey UVM July 25, 2012 Stream Geomorphology Leslie A. Morrissey UVM July 25, 2012 What Functions do Healthy Streams Provide? Flood mitigation Water supply Water quality Sediment storage and transport Habitat Recreation Transportation

More information

Great Lakes Update. Volume 194: 2015 Annual Summary

Great Lakes Update. Volume 194: 2015 Annual Summary Great Lakes Update Volume 194: 2015 Annual Summary Background The U.S. Army Corps of Engineers (USACE) tracks and forecasts the water levels of each of the Great Lakes. This report summarizes the hydrologic

More information

DREDGING A land manager s guide to the rules

DREDGING A land manager s guide to the rules DREDGING A land manager s guide to the rules Introduction Farmers have long practised sediment management, commonly referred to as dredging. The introduction of controls on these activities in 2006 was

More information

Flooding in Dolgellau

Flooding in Dolgellau Flooding in Dolgellau Graham Hall MMath, PhD University of Wales, Bangor Background Flooding has historically been a cause for concern in Dolgellau. Following a serious flood in December 1964 when shops

More information

Vermont Stream Geomorphic Assessment. Appendix E. River Corridor Delineation Process. VT Agency of Natural Resources. April, E0 - April, 2004

Vermont Stream Geomorphic Assessment. Appendix E. River Corridor Delineation Process. VT Agency of Natural Resources. April, E0 - April, 2004 Vermont Stream Geomorphic Assessment Appendix E River Corridor Delineation Process Vermont Agency of Natural Resources - E0 - River Corridor Delineation Process Purpose A stream and river corridor delineation

More information

YELLOWSTONE RIVER FLOOD STUDY REPORT TEXT

YELLOWSTONE RIVER FLOOD STUDY REPORT TEXT YELLOWSTONE RIVER FLOOD STUDY REPORT TEXT TECHNICAL REPORT Prepared for: City of Livingston 411 East Callender Livingston, MT 59047 Prepared by: Clear Creek Hydrology, Inc. 1627 West Main Street, #294

More information

Terrestrial Flood Risk and Climate Change in the Yallahs River, Jamaica. An assessment of future flood risk. projections of future climate

Terrestrial Flood Risk and Climate Change in the Yallahs River, Jamaica. An assessment of future flood risk. projections of future climate Terrestrial Flood Risk and Climate Change in the Yallahs River, Jamaica An assessment of future flood risk using hydrodynamic models driven by projections of future climate Matthew Wilson1, Arpita Mandal2,

More information

Tidal flood outline (No changes proposed)

Tidal flood outline (No changes proposed) Tidal flood outline (No changes proposed) SWRBD CFRAM Study Flood Risk Review Site Inspection Report Name: Schull Hydrometric Area: 20 County: Cork Unique OPW ID: 200303 Site Type: CAR Source of Flooding:

More information

Natural hazards in Glenorchy Summary Report May 2010

Natural hazards in Glenorchy Summary Report May 2010 Natural hazards in Glenorchy Summary Report May 2010 Contents Glenorchy s hazardscape Environment setting Flood hazard Earthquakes and seismic hazards Hazards Mass movement Summary Glossary Introduction

More information

Pressure Head: Pressure head is the height of a column of water that would exert a unit pressure equal to the pressure of the water.

Pressure Head: Pressure head is the height of a column of water that would exert a unit pressure equal to the pressure of the water. Design Manual Chapter - Stormwater D - Storm Sewer Design D- Storm Sewer Sizing A. Introduction The purpose of this section is to outline the basic hydraulic principles in order to determine the storm

More information

Report for Area Drainage Studies for 1320 MW (2x660 MW) THERMAL POWER PROJECT AT MIRZAPUR, U.P.

Report for Area Drainage Studies for 1320 MW (2x660 MW) THERMAL POWER PROJECT AT MIRZAPUR, U.P. Report for Area Drainage Studies for 1320 MW (2x660 MW) THERMAL POWER PROJECT AT MIRZAPUR, U.P. 1. Introduction M/s Welspun Energy Uttar Pradesh Ltd. (WEUPL) is putting up 1320 MW (2 x 660 MW) coal fired

More information

3.0 TECHNICAL FEASIBILITY

3.0 TECHNICAL FEASIBILITY 3.0 TECHNICAL FEASIBILITY 3.1 INTRODUCTION To enable seasonal storage and release of water from Lake Wenatchee, an impoundment structure would need to be constructed on the lake outlet channel. The structure

More information

Floodplain modeling. Ovidius University of Constanta (P4) Romania & Technological Educational Institute of Serres, Greece

Floodplain modeling. Ovidius University of Constanta (P4) Romania & Technological Educational Institute of Serres, Greece Floodplain modeling Ovidius University of Constanta (P4) Romania & Technological Educational Institute of Serres, Greece Scientific Staff: Dr Carmen Maftei, Professor, Civil Engineering Dept. Dr Konstantinos

More information

The Soils and Land Capability for Agriculture. Land North of Aberdeen, Aberdeenshire

The Soils and Land Capability for Agriculture. Land North of Aberdeen, Aberdeenshire The Soils and Land Capability for Agriculture Of Land North of Aberdeen, Aberdeenshire Report prepared for Peter Radmall Associates May 2012 Reading Agricultural Consultants Ltd Beechwood Court, Long Toll,

More information

Hydrologic Forecast Centre Manitoba Infrastructure, Winnipeg, Manitoba. FEBRUARY OUTLOOK REPORT FOR MANITOBA February 23, 2018

Hydrologic Forecast Centre Manitoba Infrastructure, Winnipeg, Manitoba. FEBRUARY OUTLOOK REPORT FOR MANITOBA February 23, 2018 Page 1 of 17 Hydrologic Forecast Centre Manitoba Infrastructure, Winnipeg, Manitoba FEBRUARY OUTLOOK REPORT FOR MANITOBA February 23, 2018 Overview The February Outlook Report prepared by the Hydrologic

More information

Hydrologic Forecast Centre Manitoba Infrastructure, Winnipeg, Manitoba. MARCH OUTLOOK REPORT FOR MANITOBA March 23, 2018

Hydrologic Forecast Centre Manitoba Infrastructure, Winnipeg, Manitoba. MARCH OUTLOOK REPORT FOR MANITOBA March 23, 2018 Page 1 of 21 Hydrologic Forecast Centre Manitoba Infrastructure, Winnipeg, Manitoba MARCH OUTLOOK REPORT FOR MANITOBA March 23, 2018 Overview The March Outlook Report prepared by the Hydrologic Forecast

More information

STATEMENT OF EVIDENCE OF SHANE LANDER (GEOTECHNICAL - QD2) ON BEHALF OF MURPHYS DEVELOPMENTS LIMITED

STATEMENT OF EVIDENCE OF SHANE LANDER (GEOTECHNICAL - QD2) ON BEHALF OF MURPHYS DEVELOPMENTS LIMITED IN THE MATTER of the Housing Accords and Special Housing Areas Act 2013 ("HASHAA") AND IN THE MATTER of Proposed Qualifying Development Application ("QD2") for 125 Murphys Road, Flat Bush BETWEEN Murphys

More information

JUNE 2004 Flood hydrology of the Waiwhetu Stream

JUNE 2004 Flood hydrology of the Waiwhetu Stream JUNE 2004 Flood hydrology of the Waiwhetu Stream Laura Watts Resource Investigations Contents 1. Introduction 1 2. Catchment description 2 3. Data availability and quality 3 3.1 Rainfall data 3 3.2 Water

More information

STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1. DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT

STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1. DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1 DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT Prepared by: PAULUS, SOKOLOWSKI & SARTOR STORMWATER MANAGEMENT 1. Methodology

More information

Pequabuck River Flooding Study and Flood Mitigation Plan The City of Bristol and Towns of Plainville and Plymouth, CT

Pequabuck River Flooding Study and Flood Mitigation Plan The City of Bristol and Towns of Plainville and Plymouth, CT Pequabuck River Flooding Study and Flood Mitigation Plan The City of Bristol and Towns of Plainville and Plymouth, CT Raymond Rogozinski and Maged Aboelata The City of Bristol and Towns of Plainville and

More information

Roger Andy Gaines, Research Civil Engineer, PhD, P.E.

Roger Andy Gaines, Research Civil Engineer, PhD, P.E. Roger Andy Gaines, Research Civil Engineer, PhD, P.E. Research Civil Engineer/Regional Technical Specialist Memphis District August 24, 2010 Objectives Where we have been (recap of situation and what s

More information

APPENDIX E. GEOMORPHOLOGICAL MONTORING REPORT Prepared by Steve Vrooman, Keystone Restoration Ecology September 2013

APPENDIX E. GEOMORPHOLOGICAL MONTORING REPORT Prepared by Steve Vrooman, Keystone Restoration Ecology September 2013 APPENDIX E GEOMORPHOLOGICAL MONTORING REPORT Prepared by Steve Vrooman, Keystone Restoration Ecology September 2 Introduction Keystone Restoration Ecology (KRE) conducted geomorphological monitoring in

More information

HYDROLOGY AND HYDRAULICS MUSKEG RIVER BRIDGE

HYDROLOGY AND HYDRAULICS MUSKEG RIVER BRIDGE PUBLIC WORKS CANADA HYDROLOGY AND HYDRAULICS MUSKEG RIVER BRIDGE KILOMETRE 207.9, LIARD HIGKWAY December 1978 I I f I I I I # Bolter Parish Trimble Ltd. ONLIULTINO Public Works, Canada, 9925-109 Street,

More information

IMPROVING ACCURACY, LEAD TIME AND CONTINGENCY IN FLUVIAL FLOOD FORECASTS TO ENHANCE EMERGENCY MANAGEMENT

IMPROVING ACCURACY, LEAD TIME AND CONTINGENCY IN FLUVIAL FLOOD FORECASTS TO ENHANCE EMERGENCY MANAGEMENT IMPROVING ACCURACY, LEAD TIME AND CONTINGENCY IN FLUVIAL FLOOD FORECASTS TO ENHANCE EMERGENCY MANAGEMENT Federico Groppa 1, Jon Wicks 2, Andy Barnes 3 1 Halcrow Group, Brisbane, QLD, groppaf@halcrow.com

More information

PEAT SLIDE RISK ASSESSMENT 11-5

PEAT SLIDE RISK ASSESSMENT 11-5 PEAT SLIDE RISK ASSESSMENT 11-5 - Strathy Wood Wind Farm Peat Assessment: Peat Slide Risk and Peat Waste Final Report Atmos Consulting Ltd. Moray House 16-18 Bank Street INVERNESS IV1 1QY JBA Project Manager

More information

9. PROBABLE MAXIMUM PRECIPITATION AND PROBABLE MAXIMUM FLOOD

9. PROBABLE MAXIMUM PRECIPITATION AND PROBABLE MAXIMUM FLOOD 9. PROBABLE MAXIMUM PRECIPITATION AND PROBABLE MAXIMUM FLOOD 9.1. Introduction Due to the size of Watana Dam and the economic importance of the Project to the Railbelt, the Probable Maximum Flood (PMF)

More information

WINFAP 4 Urban Adjustment Procedures

WINFAP 4 Urban Adjustment Procedures WINFAP 4 Urban Adjustment Procedures WINFAP 4 Urban adjustment procedures Wallingford HydroSolutions Ltd 2016. All rights reserved. This report has been produced in accordance with the WHS Quality & Environmental

More information

The Assessment of Flood Risk for Proposed Development Sites at Holyport

The Assessment of Flood Risk for Proposed Development Sites at Holyport The Assessment of Flood Risk for Proposed Development Sites at Holyport Dr Harvey J.E. Rodda FRGS March 2014 Contents Summary... 3 Background... 3 Disclaimer... 3 Location... 4 Topography... 4 Geology...

More information

Tarbela Dam in Pakistan. Case study of reservoir sedimentation

Tarbela Dam in Pakistan. Case study of reservoir sedimentation Tarbela Dam in Pakistan. HR Wallingford, Wallingford, UK Published in the proceedings of River Flow 2012, 5-7 September 2012 Abstract Reservoir sedimentation is a main concern in the Tarbela reservoir

More information

GEOL 1121 Earth Processes and Environments

GEOL 1121 Earth Processes and Environments GEOL 1121 Earth Processes and Environments Wondwosen Seyoum Department of Geology University of Georgia e-mail: seyoum@uga.edu G/G Bldg., Rm. No. 122 Seyoum, 2015 Chapter 6 Streams and Flooding Seyoum,

More information

Section 4: Model Development and Application

Section 4: Model Development and Application Section 4: Model Development and Application The hydrologic model for the Wissahickon Act 167 study was built using GIS layers of land use, hydrologic soil groups, terrain and orthophotography. Within

More information

REDWOOD VALLEY SUBAREA

REDWOOD VALLEY SUBAREA Independent Science Review Panel Conceptual Model of Watershed Hydrology, Surface Water and Groundwater Interactions and Stream Ecology for the Russian River Watershed Appendices A-1 APPENDIX A A-2 REDWOOD

More information

Vegetation effects on river hydraulics. Johannes J. (Joe) DeVries David Ford Consulting Engineers, Inc. Sacramento, CA

Vegetation effects on river hydraulics. Johannes J. (Joe) DeVries David Ford Consulting Engineers, Inc. Sacramento, CA Vegetation effects on river hydraulics Johannes J. (Joe) DeVries David Ford Consulting Engineers, Inc. Sacramento, CA jjdevries@ford-consulting.com SAC05 D2P31 RM 99.0L VIEW UPSTREAM AT UPSTREAM END DWR

More information

Transactions on Information and Communications Technologies vol 18, 1998 WIT Press, ISSN

Transactions on Information and Communications Technologies vol 18, 1998 WIT Press,   ISSN STREAM, spatial tools for river basins, environment and analysis of management options Menno Schepel Resource Analysis, Zuiderstraat 110, 2611 SJDelft, the Netherlands; e-mail: menno.schepel@resource.nl

More information

Floodplain Risk Management in Dungog after the April 2015 Super Storm. Presentation Outline

Floodplain Risk Management in Dungog after the April 2015 Super Storm. Presentation Outline Presentation Outline Floodplain Risk Management in after the April 2015 Super Storm Rohan Hudson, Royal HaskoningDHV FMA 2017 Preparing for the Next Great Flood 17th May 2017 Background and Flood Mechanisms

More information

ESTIMATING JOINT FLOW PROBABILITIES AT STREAM CONFLUENCES USING COPULAS

ESTIMATING JOINT FLOW PROBABILITIES AT STREAM CONFLUENCES USING COPULAS ESTIMATING JOINT FLOW PROBABILITIES AT STREAM CONFLUENCES USING COPULAS Roger T. Kilgore, P.E., D. WRE* Principal Kilgore Consulting and Management 2963 Ash Street Denver, CO 80207 303-333-1408 David B.

More information

LOCATED IN INDIAN RIVER COUNTY PREPARED FOR S.J.R.W.M.D. AND F.W.C.D. DECEMBER, 2003 Updated 2007 Updated May 2014 PREPARED BY

LOCATED IN INDIAN RIVER COUNTY PREPARED FOR S.J.R.W.M.D. AND F.W.C.D. DECEMBER, 2003 Updated 2007 Updated May 2014 PREPARED BY FELLSMERE WATER CONTROL DISTRICT EAST MASTER DRAINAGE PLAN AND STORMWATER HYDROLOGIC ANALYSIS OF THE GRAVITY DRAINAGE SYSTEM LOCATED BETWEEN THE EAST BOUNDARY, LATERAL U, THE MAIN CANAL, AND DITCH 24 LOCATED

More information

Ground Water Protection Council 2017 Annual Forum Boston, Massachusetts. Ben Binder (303)

Ground Water Protection Council 2017 Annual Forum Boston, Massachusetts. Ben Binder (303) Ground Water Protection Council 2017 Annual Forum Boston, Massachusetts Protecting Groundwater Sources from Flood Borne Contamination Ben Binder (303) 860-0600 Digital Design Group, Inc. The Problem Houston

More information

Summary of the 2017 Spring Flood

Summary of the 2017 Spring Flood Ottawa River Regulation Planning Board Commission de planification de la régularisation de la rivière des Outaouais The main cause of the exceptional 2017 spring flooding can be described easily in just

More information

Stormwater Capacity Analysis for Westover Branch Watershed

Stormwater Capacity Analysis for Westover Branch Watershed Stormwater Capacity Analysis for Westover Branch Watershed Pimmit Run Little Pimmit Run, Mainstem Stohman's Run Gulf Branch Pimmit Run Tributary Little Pimmit Run, W. Branch Little Pimmit Run, E. Branch

More information

Edexcel GCSE Geography Controlled Assessment Exemplar 2014 Example Task Question: The channel characteristics of a river change along its course.

Edexcel GCSE Geography Controlled Assessment Exemplar 2014 Example Task Question: The channel characteristics of a river change along its course. Example Task Question: The channel characteristics of a river change along its course. Purpose Focus on velocity Sub- focus questions: 1. To what extent is there a regular /even change in velocity downstream?

More information

Flood hydrology of the Mangaroa River MARCH 2005

Flood hydrology of the Mangaroa River MARCH 2005 Flood hydrology of the Mangaroa River MARCH 2005 MARCH 2005 Flood hydrology of the Mangaroa River Laura Watts Contents Summary 1 1. Introduction 2 2. Catchment description 3 3. Data availability and quality

More information

Surface Water and Stream Development

Surface Water and Stream Development Surface Water and Stream Development Surface Water The moment a raindrop falls to earth it begins its return to the sea. Once water reaches Earth s surface it may evaporate back into the atmosphere, soak

More information

Archaeological Evaluation of Land off Hubbards Lane, Boughton Monchelsea, Kent

Archaeological Evaluation of Land off Hubbards Lane, Boughton Monchelsea, Kent Archaeological Evaluation of Land off Hubbards Lane, Boughton Monchelsea, Kent NGR: 576190 151300 Site Code: HUB/EV/16 (Planning Application: 16/500014/OUT/MA) SWAT Archaeology The Office, School Farm

More information

Waipatiki Catchment Flood Hazard Analysis. June 2008 AM 08/04 HBRC Plan Number 4029

Waipatiki Catchment Flood Hazard Analysis. June 2008 AM 08/04 HBRC Plan Number 4029 Waipatiki Catchment Flood Hazard Analysis June 2008 AM 08/04 HBRC Plan Number 4029 Asset Management Group Technical Report ISSN 1174 3085 Engineering Section Waipatiki Catchment: Flood Hazard Analysis

More information

CASE STUDY NATHPA JHAKRI, INDIA

CASE STUDY NATHPA JHAKRI, INDIA SEDIMENT MANAGEMENT CASE STUDY NATHPA JHAKRI, INDIA Key project features Name: Nathpa Jhakri Country: India Category: reduce sediment production (watershed management); upstream sediment trapping; bypass

More information

Hydrometric Data Management a National Perspective. Matt Fry, National River Flow Archive. CEH Wallingford

Hydrometric Data Management a National Perspective. Matt Fry, National River Flow Archive. CEH Wallingford Hydrometric Data Management a National Perspective Matt Fry National River Flow Archive CEH Wallingford National River Flow Archive - Objectives UK focal point for hydrometric data Long term data management

More information

ENGINEERING HYDROLOGY

ENGINEERING HYDROLOGY ENGINEERING HYDROLOGY Prof. Rajesh Bhagat Asst. Professor Civil Engineering Department Yeshwantrao Chavan College Of Engineering Nagpur B. E. (Civil Engg.) M. Tech. (Enviro. Engg.) GCOE, Amravati VNIT,

More information

How Do Human Impacts and Geomorphological Responses Vary with Spatial Scale in the Streams and Rivers of the Illinois Basin?

How Do Human Impacts and Geomorphological Responses Vary with Spatial Scale in the Streams and Rivers of the Illinois Basin? How Do Human Impacts and Geomorphological Responses Vary with Spatial Scale in the Streams and Rivers of the Illinois Basin? Bruce Rhoads Department of Geography University of Illinois at Urbana-Champaign

More information

Rock & Aggregate Drop Inlet Protection

Rock & Aggregate Drop Inlet Protection Rock & Aggregate Drop Inlet Protection SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System Supplementary Trap Dispersive Soils

More information

3.12 Geology and Topography Affected Environment

3.12 Geology and Topography Affected Environment 3 Affected Environment and Environmental Consequences 3.12 Geology and Topography 3.12.1 Affected Environment 3.12.1.1 Earthquakes Sterling Highway MP 45 60 Project Draft SEIS The Kenai Peninsula is predisposed

More information

Each basin is surrounded & defined by a drainage divide (high point from which water flows away) Channel initiation

Each basin is surrounded & defined by a drainage divide (high point from which water flows away) Channel initiation DRAINAGE BASINS A drainage basin or watershed is defined from a downstream point, working upstream, to include all of the hillslope & channel areas which drain to that point Each basin is surrounded &

More information

Flood Hazard Inundation Mapping. Presentation. Flood Hazard Mapping

Flood Hazard Inundation Mapping. Presentation. Flood Hazard Mapping Flood Hazard Inundation Mapping Verne Schneider, James Verdin, and JeradBales U.S. Geological Survey Reston, VA Presentation Flood Hazard Mapping Requirements Practice in the United States Real Time Inundation

More information

MODELING OF LOCAL SCOUR AROUND AL-KUFA BRIDGE PIERS Saleh I. Khassaf, Saja Sadeq Shakir

MODELING OF LOCAL SCOUR AROUND AL-KUFA BRIDGE PIERS Saleh I. Khassaf, Saja Sadeq Shakir ISSN 2320-9100 11 International Journal of Advance Research, IJOAR.org Volume 1, Issue 8,August 2013, Online: ISSN 2320-9100 MODELING OF LOCAL SCOUR AROUND AL-KUFA BRIDGE PIERS Saleh I. Khassaf, Saja Sadeq

More information

Hydrologic Forecast Centre. Manitoba Infrastructure. Winnipeg, Manitoba FEBRUARY FLOOD OUTLOOK REPORT FOR MANITOBA.

Hydrologic Forecast Centre. Manitoba Infrastructure. Winnipeg, Manitoba FEBRUARY FLOOD OUTLOOK REPORT FOR MANITOBA. Page 1 of 20 Hydrologic Forecast Centre Manitoba Infrastructure Winnipeg, Manitoba FEBRUARY FLOOD OUTLOOK REPORT FOR MANITOBA February 28, 2019 Overview The February Outlook Report prepared by the Hydrologic

More information

Dealing with Zone A Flood Zones. Topics of Discussion. What is a Zone A Floodplain?

Dealing with Zone A Flood Zones. Topics of Discussion. What is a Zone A Floodplain? Dealing with Zone A Flood Zones Topics of Discussion Overview of Zone A Floodplains Permitting Development in Zone A Floodplains Estimating Flood Elevations in Zone A Flood Insurance Implications Letters

More information