Implementation Status & Results Mozambique Mozambique Mining and Gas Technical Assistance Project (P129847)

Similar documents
Implementation Status & Results Mozambique Cities and Climate Change (P123201)

Implementation Status & Results Congo, Republic of Rep. of Congo - Water, Electricity & Urban Development SIL (LEN) (P106975)

Implementation Status & Results Jamaica Rural Economic Development Initiative (P105122)

Implementation Status & Results Burkina Faso Local Government Support Project (P120517)

Implementation Status & Results Burkina Faso TRANSPORT SECTOR PROJECT (P074030)

Implementation Status & Results Chad Urban Development Project (P072030)

Implementation Status & Results China CN Integrated Economic Development of Small Towns (P118597)

Public Disclosure Copy

Implementation Status & Results Benin BN-National Community Driven Development Project (P081484)

Implementation Status & Results Burundi Burundi - Emergency Energy Project from IDA CRW (P122217)

Implementation Status & Results Africa RCIP3 - Regional Communications Infrastructure Program - Phase 3 (P111432)

Implementation Status & Results Congo, Democratic Republic of Democratic Republic of Congo Emergency Social Action Project (P086874)

Public Disclosure Copy. Implementation Status & Results Report Strengthening Institutional Capacity for Government Effectiveness Project (P149176)

Implementation Status & Results Central African Republic CAR - Emergency Urban Infrastructure Rehabilitation & Maintenance (P104595)

Implementation Status & Results Angola Local Development Project (P105101)

Implementation Status & Results Central African Republic CF-Support to Vulnerable Groups Community Development Project (P111679)

Implementation Status & Results Benin Agricultural Productivity and Diversification (P115886)

Implementation Status & Results Mozambique MZ - Spatial Development Planning Technical Assistance Project (P121398)

Implementation Status & Results Belize Municipal Development (P111928)

Cities and Climate Change (P123201)

Implementation Status & Results Niger Niger - Competitiveness & Growth Support (P127204)

Implementation Status & Results Chad Urban Development Project (P072030)

The World Bank. Key Dates. Project Development Objectives. Component(s) Overall Ratings. Public Disclosure Copy

Implementation Status & Results Iraq Iraq Third Emergency Education Project (P096234)

The World Bank Cities and Climate Change (P123201)

Implementation Status & Results Indonesia Improving Governance for Sustainable Indigenous Community Livelihoods in Forested Areas (P130632)

The World Bank Zambia Water Resources Development Project (P114949)

Implementation Status & Results Ghana GH:Sustainable Rural Water & Sanit Serv (P120026)

Implementation Status & Results Central African Republic CF-Support to Vulnerable Groups Community Development Project (P111679)

Implementation Status & Results Ethiopia Electricity Network Reinforcement and Expansion Project (ENREP) (P119893)

Public Disclosure Copy

Implementation Status & Results Djibouti Djibouti Power Access and Diversification Project (P086379)

Implementation Status & Results Morocco Strengthening micro-entrepreneurship for disadvantaged youth (P144134)

Implementation Status & Results Azerbaijan Third Highway Project (P118023)

Zambia - Mining and Environmental Remediation and Improvement Project (P154683)

The World Bank Haiti Business Development and Investment Project (P123974)

The World Bank OECS Regional Tourism Competitiveness (P152117)

Implementation Status & Results Vietnam Danang Sustainable City Development Project (SCDP) (P123384)

Implementation Status & Results Benin BJ-Youth Employment (FY14) (P132667)

Implementation Status & Results Indonesia Third National Program for Community Empowerment in Rural Areas - Disaster Management Support (P125600)

Implementation Status & Results Africa West and Central Africa Air Transport Safety & Security Project (P083751)

Urban Water Supply Project (P156739)

Public Disclosure Copy. AFCC2/RI-The Eastern Electricity Highway Project under the First Phase of the Eastern Africa Power

Implementation Status & Results Cameroon CAMEROON--Equity and Quality for Improved Learning Project (P133338)

Public Disclosure Copy

Public Disclosure Copy. Implementation Status & Results Report Somali Core Economic Institutions and Opportunities Program (SCORE) (P152241)

The World Bank Mali Reconstruction and Economic Recovery (P144442)

Public Disclosure Copy

The World Bank Cusco Regional Development (P117318)

The World Bank Mali Reconstruction and Economic Recovery (P144442)

Public Disclosure Copy

Public Disclosure Copy. Implementation Status & Results Report UGANDA North Eastern Road-corridor Asset Management Project (NERAMP) (P125590)

Implementation Status & Results Brazil BR APL Integrated Water Management In Metropolitan Sao Paulo (P006553)

The World Bank Haiti Business Development and Investment Project (P123974)

Implementation Status & Results Niger Niger - Competitiveness & Growth Support (P127204)

Implementation Status & Results Argentina AR RENEW.ENERGY R.MKTS (P006043)

Implementation Status & Results Ethiopia Tana & Beles Integrated Water Resources Development (P096323)

Implementation Status & Results Indonesia Strategic Roads Infrastructure Project (P079906)

Implementation Status & Results Mekong Mekong Integrated Water Resources Management (P104806)

Implementation Status & Results Vietnam Distribution Efficiency Project (P125996)

Implementation Status & Results Indonesia Third National Program for Community Empowerment in Rural Areas - Disaster Management Support (P125600)

The World Bank. Key Dates. Project Development Objectives. Components. Implementation Status & Results Report. Key Project Dates

The World Bank. Key Dates. Project Development Objectives. Components. Implementation Status & Results Report. Key Project Dates

The World Bank Sri Lanka Agriculture Sector Modernization Project (P156019)

Implementation Status & Results Brazil BR APL Integrated Water Management In Metropolitan Sao Paulo (P006553)

Public Disclosure Copy

Public Disclosure Copy

The World Bank Greater Maputo Water Supply Expansion Project (P125120)

Implementation Status & Results Indonesia Water Resources and Irrigation Sector Management Program 2 (P114348)

Relaunching Agriculture: Strengthening Agriculture Public Services II Project (GAFSP - IDA) (P126744)

The World Bank Ethiopia: Transport Systems Improvement Project (TRANSIP) (P151819)

The World Bank Zambia Water Resources Development Project (P114949)

Implementation Status & Results Brazil BR Sao Paulo Water Recovery Project - REAGUA (P106703)

Implementation Status & Results Mekong Mekong Integrated Water Resources Management (P104806)

Implementation Status & Results Peru PE Optimization of Lima Water and Sewerage Systems (P117293)

Sierra Leone Energy Access Project - Sierra Leone Infrastructure Development Fund (P126180)

Implementation Status & Results Morocco MA-Rural Water Supply (P145529)

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank Indonesia National Slum Upgrading Project (P154782)

Public Disclosure Copy

Implementation Status & Results Ghana Ghana Commercial Agriculture (P114264)

Punjab Cities Program (P156972)

The World Bank Sri Lanka Agriculture Sector Modernization Project (P156019)

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

Public Disclosure Copy

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank Ethiopia: National Quality Infrastructure Development Project (P160279)

Implementation Status & Results Vietnam Second Northern Mountains Poverty Reduction Project (P113493)

Public Disclosure Copy

The World Bank Community Development Program Support Project-Phase III (P144637)

The World Bank CG Rep. LISUNGI Safety Nets System Project (P145263)

The World Bank Heilongjiang Cold Weather Smart Public Transportation System (P133114)

Public Disclosure Copy

The World Bank Caribbean Regional Communications Infrastructure Program (P114963)

The World Bank. Key Dates. Project Development Objectives. Components. Overall Ratings. Public Disclosure Authorized

The World Bank Livestock Sector Development Support Project (P159476)

Public Disclosure Copy

Public Disclosure Copy

The World Bank Third National Urban Water Sector Reform Project (P123513)

Public Disclosure Copy. Implementation Status & Results Report Emergency Agricultural Livelihoods and Climate Resilience Project (P166328)

Transcription:

Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Mozambique Mozambique Mining and Gas Technical Assistance Project (P129847) Operation Name: Mozambique Mining and Gas Technical Assistance Project Project Stage: Implementation Seq.No: 3 Status: ARCHIVED Archive Date: 02-Dec-2014 (P129847) Country: Mozambique Approval FY: 2013 Product Line: IBRD/IDA Region: AFRICA Lending Instrument: Technical Assistance Loan Implementing Agency(ies): Ministry of MIneral Resources Key Dates Board Approval Date 28-Mar-2013 Original Closing Date Planned Mid Term Review Date Last Archived ISR Date 03-May-2014 Effectiveness Date 22-Aug-2013 Revised Closing Date Actual Mid Term Review Date Project Development Objectives Project Development Objective (from Project Appraisal Document) The proposed project development objective is to strengthen the capacity and governance systems of key institutions to manage the mining and hydrocarbon sectors in Mozambique. Has the Project Development Objective been changed since Board Approval of the Project? Yes No losure Authorized Public Disclosure Authorized Component(s) Component Name Component Cost Component A: Mining Governance Capacity Building and Reform 17.65 Component B: Natural Gas Capacity Building and Governance Reform 11.05 Component C: Cross-cutting Mining/ Natural Gas Capacity Building and Reforms 9.95 Component D: Cross-Sectoral Reforms 0.80 Component E: Project Management and Coordination 4.90 PPA Refinancing 3.00 Contingencies 2.65 Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Substantial Substantial Page 1 of 8

Implementation Status Overview The mining and gas industry in Mozambique has seen some important developments over recent months. New mining and petroleum sector laws and new mining and petroleum fiscal laws were passed by the Parliament in July and August 2014, respectively. With adoption of the laws, Ministry of Mineral Resources is proceeding with supporting regulations including an update of mining licensing and cadastre procedures (with support of MAGTAP). Negotiations for major LNG projects continue after the passage of the Enabling Law. The mining sector, in particular coal, has seen a negative impact with low prices, compounded by infrastructure challenges. Mozambique remains EITI compliant and is on schedule to produce its 5th reconciliation report by December, 2014. The new report will be in line with the new EITI standard; 150 companies are expected to be covered and the EITI Secretariat will be issuing an implementation report by the end of the year reporting on achievement of various milestones including public engagement outreach and follow up to recommendations. MAGTAP implementation continues in accordance with the planned project and with procurement progressing in all major components. Several major activities are under implementation, including transaction advisory support for the LNG project, geophysical surveying, financial and marketing advisory services to ENH, review of a tantalum project and mining and gas communications strategy preparation for the Ministry of Mineral Resources (MIREM). Preparation of a Strategic Environmental and Social Assessment for mining and gas is starting with a delay but is expected to proceed from this point forward as planned. While it is early to report on results, the assessment of the project impact remains positive with strong commitment on behalf of key counterparts and dedication of the MIREM and its project management unit. The project coordinates across existing technical assistance projects for mining and gas governance in Mozambique and benefits from available analytical work supported by other development partners as well as by other World Bank programs. The disbursement rate for the IDA part of the project as of October 2014 is 9% (US$4.1 million). An additional $6.7 million is committed under signed contracts and procurement has started for an additional $9.0 million worth of contracts. The total signed, committed and ongoing procurements amounts to about 40% of the total amount, including the project's DfID co-financing. Locations Country First Administrative Division Location Planned Actual Mozambique Not Entered Província de Zambézia Mozambique Not Entered Tete Mozambique Not Entered Sofala Province Mozambique Not Entered Niassa Province Mozambique Not Entered Nampula Mozambique Not Entered Maputo Province Mozambique Not Entered Manica Province Mozambique Not Entered Inhambane Province Mozambique Not Entered Gaza Province Mozambique Not Entered Cabo Delgado Province Mozambique Not Entered Cidade de Maputo Results Page 2 of 8

Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Mining Cadastral database and GIS system Yes/No Value No Yes Yes integrated with the land-use databases & accessible on-line for public level information Mining cadastre became online accessible in 2013. The Mining Law was approved Jul 2014. DNM is proceeding with update of cadastre regulations. Mines and gas construction projects subject to Number Value 0.00 7.00 annual technical inspections in line with established standards. Mine and gas inspectors positions in place since Jul 2014. Inspectors of all Provinces benefited from training in Health and Safetyin Mining Best-Practices 2014 in south Africa. The procurement of equipments and vehicles is done. Mines and gas operations subject to fiscal Number Value 0.00 0.00 5.00 controls per year in line with established standards Currently not done. Program to establish these functions not yet prepared. Regular health and safety and environmental Number Value 0.00 0.00 50.00 monitoring visits and inspections to mines and gas exploration/production sites in linewith standards for supervision of compliance & baseline at ad hoc basis No regular environmental monitoring of safety audits taking place. Regulations of mining and oil operations are under review by task force. New mining/gas/infrastructure related contracts negotiated, benefitting from the developed frameworks and procedures Number Value 0.00 1.00 11.00 Date 01-May-2013 First contract for transaction advice on Mining signed and executed. TORs are under preparation to cover future Page 3 of 8

requests and establish coal price benchmarking. Direct project beneficiaries Number Value 0.00 2390.00 Date 01-May-2013 will be updated as part of annual report. Beneficiaries are people trained. Female beneficiaries Percentage Sub Type Supplemental Value 0.00 35.00 Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Mining Cadastre procedures updated The Mining Law approved in July 2014. DNM is proceeding with regulations and update of the mining cadastre. Mineral Information System upgraded with new geodata for strategic areas Not yet started Number of ASM associations/cooperatives Number Value 63.00 63.00 89.00 Date 05-Nov-2012 No update as yet. Component not started Procedures of tendering and evaluation of mineral assets developed No update as yet Number of ASMs who have received targeted Number Value 0.00 0.00 2000.00 training (of which female %) Not yet started Health and safety and environmental regulations, including standards and monitoring procedures updated Regulations under preparation. Page 4 of 8

Local law enforcement and judicial personnel trained on mining law and regulations under the project Number of studies assessing economic and financial feasibility for development of gas infrastructure carried out Staff of gas sector management institutions trained through MAGTAP to manage, regulate and monitor gas sector Tools and mechanisms to attract financing for the State participation are in place Pemba Regional Office equipped and operational to undertake health and safety, and environmental inspections of gas field operations Computerized Environmental Management Information System developed Results of Strategic Environmental and Social Assessment publicly disclosed by GoM in papers and through workshops and public outreach Number Value 0.00 0.00 200.00 Date 01-May-2013 No training delivered as yet Number Value 0.00 0.00 5.00 First study supported by Project (for Gas Transportation Feasibility Study) under procurement. Number Value 0.00 0.00 140.00 6 staff of ENH will be trained in Dubai in structuring, pricing and negotiating of LNG. Number to be updated during annual review. EMEM business plan preparation in procurement; development of a Strategic Business Plan for ENH- Logistics is in the pipeline of planned activities. Construction is being completed by govt; equipment procurement will proceed next with deliver of vehicles in November, 2014. Not yet developed Preparation of the SESA by the National Directorate of Mines will commence soon Page 5 of 8

Annual disclosure of reports on extractive industries revenues and revenue allocation at national level Provincial Directorates of Mineral Resources equipped & capable to monitor and inspect mining & exploration operations in their jurisdictions Number of CSO/CBOs trained on transparency monitoring across the extractive sector value chain Strategies and policies for strengthening linkages of mines and gas production with national economy developed Number of bankable business plans developed under the project related to local industry participation in provision of local goods and services to extractive industry Standards & procedures for oil & gas contingency planning & emergency preparations developed Number Value 0.00 4.00 5.00 Date 01-May-2013 5th report to be issued by the end of 2014 (for 2012 accounts). Number Value 1.00 1.00 10.00 MAGTAP acquired vehicles for Provincial Directorates and Equipment (computers, GPS, Printers) is under procurement. Is anticipated the DIPREMEs will be equipped by end 2014. Number Value 0.00 0.00 50.00 Terms of reference are under preparation. Training provided as part of EITI CSO support in Cabo Delgado, Tete and Nampula. Numberto be updated as part of annual review One project submitted by IPEME is under procurement. Number Value 0.00 0.00 2.00 One EOI has been disclosed by IPEME. National Congress on Oil Spill Prevention scheduled for November 2015. TOR for procedures for oil and gas contingency plan evaluation under preparation. Page 6 of 8

Data on Financial Performance (as of 22-Oct-2014) Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P129847 IDA-51990 Effective 28-Mar-2013 19-Apr-2013 22-Aug-2013 P129847 IDA-Q8120 Effective 11-Apr-2012 09-May-2012 09-May-2012 30-Apr-2013 30-Apr-2013 P129847 TF-16113 Effective 27-Jan-2014 27-Jan-2014 27-Jan-2014 30-Nov-2018 30-Nov-2018 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P129847 IDA-51990 Effective USD 50.00 50.00 0.00 8.14 40.55 16.00 P129847 IDA-Q8120 Effective USD 3.00 3.00 0.00 0.00 3.00 0.00 P129847 TF-16113 Effective USD 8.43 8.43 0.00 0.32 8.11 4.00 Disbursement Graph Key Decisions Regarding Implementation Since effectiveness, the project is on track to achieve its development objective and is rated as Satisfactory. There are no specific issues to be raised at this stage. Restructuring History There has been no restructuring to date. Page 7 of 8

Related Projects There are no related projects. Page 8 of 8