Managing an Extreme Weather Event of Prolonged Duration May 22, 2013

Similar documents
Hurricane Preparation and Recovery. October 11, 2011 Jon Nance, Chief Engineer, NCDOT

Aid to Critical Infrastructure and Key Resources During a Disaster. Pete Grandgeorge MidAmerican Energy Company

New Jersey Department of Transportation Extreme Weather Asset Management Pilot Study

Doug Kluck NOAA Kansas City, MO National Center for Environmental Information (NCEI) National Integrated Drought Information System (NIDIS)

3Chapter Three: Rescue and Response

Missouri River Basin Water Management

Superstorm Sandy What Risk Managers and Underwriters Learned

City of Madison Flooding Event AUGUST 20 TH, 2018-PRESENT

Plow Camera and Location Sharing Practices. National Rural ITS Conference October 23, 2018

United States Multi-Hazard Early Warning System

President s Day Weekend Storm Community Meeting and Workshop April 17, 2017

Monitoring Scour Critical Bridges During Floods For Local Bridge Owners. Presented by

2018 NASCIO Award Submission Category: Cross-Boundary Collaboration and Partnerships. Project Title: Tennessee Wildfires: A Coordinated GIS Response

Extreme Weather Events

OC Public Works El Niño Storm Preparation 2015

IH 35 at Blanco River May 2015

2012 FLOODS AND DEBRIS REMOVAL

UDOT Weather Program Traffic Operations Center

Active Traffic & Safety Management System for Interstate 77 in Virginia. Chris McDonald, PE VDOT Southwest Regional Operations Director

Storm Surge Analysis Update Meeting Cross City, Florida June 17, 2014

Guide to Hydrologic Information on the Web

2014 Annual Mitigation Plan Review Meeting

Construction complete on all HSDRRS projects across storm evacuation routes

FLOOD/SCS EVENT, APRIL 28 MAY 4

THE 3D SIMULATION INFORMATION SYSTEM FOR ASSESSING THE FLOODING LOST IN KEELUNG RIVER BASIN

Fast and Furious Rebuilding and Widening the I-90 West Corridor

TRAFFIC ALERT FOR WEEK OF February 4 8, 2008

WHAT HAPPENS WHEN A TORNADO STRIKES THE COMMUNITY? Carroll County Sheriff s Office Emergency Management

Upper Missouri River Basin December 2017 Calendar Year Runoff Forecast December 5, 2017

MUNICIPALITY OF ANCHORAGE PUBLIC TRANSPORTATION DEPARTMENT AnchorRIDES TRANSPORTATION SYSTEM

Background on the March 13-14, 2007 Flooding in Browns Valley (Traverse County), Minnesota

THE NEED FOR AN ADDITIONAL SPILLWAY AT THE SANFORD DAM BOILING SPRING LAKES, NC. Presentation for The Brunswick County Commissioners April 20, 2015

Transportation Management Center s Mission

AASHTO Committee on Maintenance 2018 Annual Meeting July 25, Hurricane Irma- Preparation and Response

Transportation Management Center s Mission

VISIT MISSISSIPPI GULF COAST CRISIS COMMUNICATION MANUAL 2016

HURRICANE MATTHEW A GIS PERSPECTIVE GLYNN COUNTY GIS

The Sunland Park flyover ramp is set to close the week of March 19 until early summer

NGIAs' roles in successful disaster response

SHORT NIGHTTIME WATER SHUTDOWN TO OCCUR IN EARLY HOURS OF MAY 29

Miami-Dade County Overview

Weather Information for Road Managers

Quick Response Report #126 Hurricane Floyd Flood Mapping Integrating Landsat 7 TM Satellite Imagery and DEM Data

Indiana GIS Resources

Technical Memorandum #2 Future Conditions

TRB First International Conference on Surface Transportation Resilience

GIS and Remote Sensing Support for Evacuation Analysis

September 20, 2012 TFMA 2012 Fall Conference, Rockwall, Texas

CHAPTER FIVE: THE LOWER MISSISSIPPI REGION AND PLAQUEMINES PARISH

Red River Levee Panel

City of Punta Gorda Community Emergency Management Plan 2013

Floodplain Mapping & Flood Warning Applications in North Carolina

Extreme Weather and Climate Change Vulnerability Assessment of Central Texas Transportation Infrastructure

Flood Scenario Worksheet

Temporary College Closure Due to Inclement Weather or Other Adverse Conditions.

Interpretive Map Series 24

COMMUNITY EMERGENCY RESPONSE TEAM FLOODS INTRODUCTION

Innovated Technological Trends in Highways. Flood Modelling & Evaluation of Impacts on Infrastructure

The Great USA Flood of 1993

2016 HURRICANE SEASON PREPARATION. March 30, 2016

Welcome to the Business Owner Task Force. Selma Stockstill SouthGate Constructors Public Information Manager

Deploying the Winter Maintenance Support System (MDSS) in Iowa

ICE STORM! a mini tabletop exercise for home care agencies

Septem ber 28, 2016 EL PASO, Texas

Community Discovery Data Questionnaire

The last three sections of the main body of this report consist of:

Timeframe. Crow Wing County, Baxter, Brainerd, Breezy Point, Crosby, Crosslake, Cuyuna, Deerwood, Emily, Fifty

Information. Information Technology. Geographic. Services (GIS) 119 W Indiana Ave Deland, FL 32720

MUNICIPALITY OF ANCHORAGE PUBLIC TRANSPORTATION DEPARTMENT AnchorRIDES PARATRANSIT SYSTEM

Significant Events: A Multi-Level Approach to Significant Event Response

4.1 Hazard Identification: Natural Hazards

4-3-1 Earthquake and Tsunami Countermeasures of Tokyo s

Suwannee Satilla Basins Flood Control Issues, Opportunities and Assistance

Continental Divide National Scenic Trail GIS Program

Hurricane Florence Recovery Report 4:00 PM October 17, 2018

Lessons Learned and Shared

Approved by: A. Cherrie Epps, Ph.D., President and Chief Executive Officer

West Tennessee Construction June 14-21, 2017

How Can DOT Operations and Maintenance Prepare for Extreme Weather Events?

DEPARTMENT OF GEOLOGY AND MINERAL INDUSTRIES WAYS & MEANS SUBCOMMITTEE ON NATURAL RESOURCES MARCH 2, 2017

STEUBEN COUNTY, NEW YORK. Hazard Analysis Report

Page G Crow Wing County Multi-Hazard Mitigation Plan, 2017

Press Release. March 12, 2018

Sunday, March 24, :30 a.m. EDT

2016 APWA Snow Conference. Web-based GIS for Municipal Snow Operations

Seasonal Hazard Outlook

Topographic Strategy National Topographic Office March 2015

Acquisition of Multi-Function Equipment at DIA: Conditions, Factors, Considerations & Integration. Presented by Mike Carlson September 20, 2012

WINTER STORM Annex II

Daily Operations Briefing Tuesday, January 24, :30 a.m. EST

Massachusetts Department of Public Health Emergency Preparedness Bureau. August 27, hrs

Real-Time Flood Forecasting Modeling in Nashville, TN utilizing HEC-RTS

2006 & 2007 Pre-Hurricane Scenario Analyses

FOR PROJECTS INITIATED AFTER NOVEMBER 1, 2008 ITEM 716 EMBANKMENT EARTH OUTLET SEDIMENT TRAP

New Pig Corporation newpig.com HOT-HOGS Page 1 of 10

National Situation Report As of 5:00 a.m. EDT Tuesday, April 4, 2017

Midwest/Great Plains Climate-Drought Outlook September 20, 2018

Daily Operations Briefing. Friday, June 20, :30 a.m. EDT

TABLE OF CONTENTS LIST OF TABLES. Page

Hurricane KATRINA Lessons Learned for Managing Risk

Transcription:

Managing an Extreme Weather Event of Prolonged Duration May 22, 2013 MISSOURI RIVER FLOOD OF 2011 M I C H A E L J. K E N N E R L Y P. E. D I R E C T O R O F T H E O F F I C E O F D E S I G N I O W A D E P A R T M E N T O F T R A N S P O R T A T I O N

Missouri River Basin

Overview of the Event Snowpack in Northern Rockies was 212% above normal. One year s worth of rain fell in the Upper Missouri Basin the last two weeks of May. Water released from Gavins Point Dam June 25 exceeded twice the previous record and did not decrease until July 31. The Missouri River in Sioux City was above flood stage from June 5 to August 26 (82 days). Longest duration flood event in U.S. history.

Impact of the Flooding Timeline of the Event

Insert Timeline Impact of the Flooding Timeline of the Event

Impact of the Flooding

Impact of the Flooding Over 60 miles of Iowa s Primary Highway System, including 50 miles of Interstate Highways I-29, and I-680 were close for nearly 5 months. Three of the 11 Western Iowa Missouri River crossings were closed (I-680, IA 2, and IA 175) There were no open river crossing along a 75 mile stretch between St Joseph, Missouri and Pacific Junction, Iowa which is approximately 20 miles south of Omaha\Council Bluffs. Decreased mobility impacted the flow of goods and services and resulted in economic displacement in affected communities. Each of the 3 closed river crossings were part major commuter route. The detour for the closure of I-29 in southwest Iowa resulted in an additional 150 miles for the trip from Kansas City to Sioux Falls, SD

Impact of the Flooding I-29 Multi-State Detour Multi-state Global Detour June 13 June 17 I-29 in Iowa 152 Miles I-29 Detour 150 Extra Miles (Kansas City Sioux Falls)

Impact of the Flooding I-29 in Fremont County approximately 15 miles north of Missouri Border I-29 looking north.

Impact of the Flooding I-29 near Hamburg in Southwest Iowa

Impact of the Flooding Rail line damage: The line is just east of I-29 north of IA 2 in Fremont County

Impact of the Flooding This photo was taken two months into the event on I-29 in Southwest Iowa 12

Impact of the Flooding I-680

Impact of the Flooding I-680

Impact of the Flooding I-680

Impact of the Flooding I-680

Impact of the Flooding I-680

Impact of the Flooding I-680

Impact of the Flooding Mitigation Sites There were 5 sites where mitigation measures were taken to insure that travel was maintained on those roadways. US 30: A portion of the 9 mile section between I-29 and Blair, Nebraska was maintained through the use of TrapBags placed along the south shoulder. I-29 MP 107 to 109: TrapBags were placed along both shoulders of the southbound lanes of I-29 from MP 107 to MP 109. I-29 Hamilton Blvd. in Sioux City: A temporary ramp to the Wesley Parkway interchange was placed to provide access across the Veterans Memorial Bridge, as well as patching to repair a damaged storm sewer. I-29 MP 103 to 104: We placed a 12 inch HMA overlay in the southbound lanes to raise the elevation of the roadway above the anticipated peak elevation. I-29/I-680 north interchange near Loveland: Crews installed a new pipe, sandbags and pumps to prevent the water from closing the road. IA 175 near Onawa, Iowa: Contractor was hired to replace shoulders damages by floodwaters along IA 175, and place material along the embankment to the approach to the Missouri River bridge. However the bridge was closed due to concerns resulting from a significant scour hole that developed near the embankment.

Mitigation Strategies TrapBags on the south side of US 30 West of Missouri Valley

Mitigation Strategies TrapBags on the south side of US 30 West of Missouri Valley

Mitigation Strategies HESCO Barriers Near Hamburg on I-29

Communication and Coordination Incident Management Initial coordination between 6 states (South Dakota, Minnesota, Nebraska, Iowa, Missouri and Kansas) Iowa DOT hosted a daily partner conference call / webinar starting in June, became weekly in August and lasted into October. Included neighboring states, Iowa state agencies, Federal officials and facilitated key decision-making discussions. Heavy use of GIS provided partners a common operating picture. Used Google Earth with custom layers (inundation levels, LIDAR, historical imagery, etc ) The Air Wing of The Iowa State Patrol provided weekly updates of areas that were inaccessible.

Communication and Coordination Informing The Public Iowa DOT opened a flood call center for the public Open from June 9 - July 12. Anywhere from 2-8 operators at any one time, close to 50,000 calls were received from the public. A Missouri River Flood Website was hosted by Iowa DOT. It contained press releases, detour maps and other information resources. We had 2.7 million visitors to that site. The Iowa 511 site had approximately 650,000 visits during peak flooding in June and July. Changeable Message Signs

Communication and Coordination Web Page and Detour Information familiar Google-maps interface with colorcoding for the global detour

Communication and Coordination Web Page and Detour Information Iowa DOT Website: Site specific updates June 17 October 8

Communication and Coordination Utilization of Information from Resource Agencies US Army Corps flood inundation data 27

Communication and Coordination Information gathering and Monitoring Techniques (LiDAR) LiDAR Imagery of IA 175 near Decatur

Communication and Coordination Information gathering and Monitoring Techniques (LiDAR) Aerial Photography of IA 175 near Decatur

Communication and Coordination Information gathering and Monitoring Techniques (LiDAR) LiDAR Imagery of IA 175 near Decatur

Communication and Coordination Photos and Video from Field Personnel Video of I-29: Photos and video taken by field personnel was an extremely valuable tool in both response and recovery.

Flood Recovery Repair\Relink\Recover Designated two people to coordinate the flood recovery efforts: Damage Assessment and Plan Development was Coordinated by Michael J. Kennerly PE Director of the Office of Design Project Administration was coordinated by Robert A. Younie PE, Director of the Office of Maintenance.

Flood Recovery Repair\Relink\Recover We hired a consultant to do the damage assessment, and we put them on an accelerated schedule. We gave them 15 calendar days to complete the DDIR s. (22 covering 59 mi) We utilized an existing contract to dispose of hazardous material. Pavement cleaning and debris removal contract Limited Design Concept to rebuild I-680 Utilized consultant services to supplement on contract administration staff.

Flood Recovery Repair\Relink\Recover Basic Requirement to Re-opening to traffic Debris removal Checking for voids Inspecting roadway Inspecting culverts Inspecting bridges Full recovery Reestablishment of Roadside Vegetation Lighting Other traffic services

Flood Recovery Repair\Relink\Recover 35

Flood Recovery Repair\Relink\Recover First road closed June 4 th (I-29 SB Hamilton Blvd exit in Sioux City) opened September 1 st I-29 in Council Bluffs opened September 23 rd I-29 in Southern Iowa opened October 8 th I-680 and IA-175 opened November 2 nd Last road opened November 11 th (IA-333) A total of 42 projects were awarded. Total Projects Awarded $42.2 million

Lessons Learned/Future Considerations Understanding and tracking the timing of a presidential Disaster Proclamation. 180 Day clock starts immediately Communication is Key; Engage the resource agencies, CORP and FHWA early and throughout the event. Utilize as many media outlets as possible to keep the public informed, including social media. Ensuring that the information is 100 percent accurate 100 percent of the time is key to helping the public, emergency responders, and business make key decisions. Begin planning your recovery effort at the onset of the event: Understanding what you need, where to acquire it, and who is responsible for it is key to rapid response. Keep the teams managing the various aspects, flood management,and recovery small. Early coordination with emergency responders and keeping them updated on closures and openings throughout the event is extremely important. Innovative Contracting: Limited Design Concept

Lessons Learned/Future Considerations Keep the team managing the event small Development of an Electronic Detailed Damage Inspection Report (DDIR) after the floods of 2008 Decision making structure needs to be clearly defined and communicated from the onset, simple, and adhered to throughout the process. Keep solutions simple, but encourage innovation and taking risks. Be aggressive. Improve the way information is stored and can be displayed geospatially. Electronic As-Builts that utilize survey grade accuracy LiDAR to expedite future plan development (we lost all of our survey control points on I-680 in the flood)

Lessons Learned/Future Considerations Consider the use of airborne LiDAR to create the digital terrain models (DTM) used in design. An understanding of the levee system, including the heights of the levees, and their location is essential in managing an event of this magnitude. Evacuation procedures Temporary housing assistance. Evacuation of care facilities Establishment of evacuation routes Prevention of looting when homes are vacated for a substantial amount of time. Establish designated detour routes and where possible have the signing already in place.

Questions?