1 Minnesota Department of Transportation Memo Geotechnical Engineering Section Office of Materials (MS 64) Office Tel: (61) Gervais Avenue, Maplewood, MN 9 Office Fax: (61) Date: January 26, 07 To: From: Concur: Subject: N. Rosen, Final Design Project Manager Metro Design, Waters Edge R. Lamb, Foundations Project Engineer Foundations Unit G. Person, Foudations Engineer Foundations Unit SP TH 169 MSE Wall N169RW2 Located at the NE quadrant of proposed TH 169 and CSAH 81 Foundation Investigation and Recommendations Subsurface Investigation Information The foundation soils for the wall consist of an upper -0 ft. layer of medium dense to dense sands with some gravel followed by stiff semicohesive soils (Sandy Loam). These soils are underlain by more medium dense to very dense sands. Water was encountered approximately 2 ft. below the existing ground surface. Please refer to the attached boring logs for a more complete description of the foundation soils. Foundation Analysis Wall Loading: 2 ft. Live Load Surcharge Wall Type: MSE Wall The mechanically stabilized earth wall (MSE wall) is assumed to vary in height from -34 ft. Allowable Bearing capacities for the foundation soils were calculated assuming a footing width equal to 0.7H (wall height), a unit weight of fill of 12 pcf and a safety factor of 2.. Based on our analysis, the foundation soils (compacted granular fill) have adequate bearing capacities to support this MSE wall. No subcut is necessary. Estimated Settlement Wall settlements were estimated based on the overall embankment construction settlements assuming fill heights of -34 ft. Our analysis was based on a Boussinesq stress distribution. This settlement analysis considered both lateral settlement and transverse settlement. Based on our analysis, we estimate that the wall will settle 2- in. with a maximum differential settlement of less than 1 in. per ft, as specified by code. The majority of this settlement should occur during construction and backfilling operations, however, up to 1 in. of settlement within the clayey sand layers is anticipated to take up to one month to dissipate. Foundation Recommendations Wall Station Foundation Type Entire Wall Spread Footing *Proposed Subcut Subcut *Subcut depth measure from top of leveling pad Backfill Material Allowable Soil Bearing Capacity Estimated Settlement n/a n/a 4-12 ksf 2- in. Additional Recommendations: 1. Topsoil and other organic material should be removed from areas where fill is to be placed. 2. The walls should be backfilled according to the attached Diagram MSEW-1 3. The leveling pad should be buried a minimum of 2.0 ft. below the final ground line. 4. The MSE wall should be supported with a spread footing foundation placed on compacted granular embankment fill. Attachments: Borings: T, T26 CPT Soundings: C119, C121, C0, C021, C02, C038, C039 Diagram MSEW-1, Boring Index, Cpt Index, Boring Plan, Boring Profile cc: G. Engstrom, D. Van Deusen, File R.Lamb SP N169RW2.xls Page 1 of 1

2 MSE RETAINING WALL with a Segmental Precast Concrete Panel Facing SEE MN/DOT TECH. MEMO NO MRR-06 FOR DESIGN DETAILS MINNESOTA DEPARTMENT OF TRANSPORTATION NOT TO SCALE MOMENT SLAB, TRAFFIC AND SOUND BARRIER IMPERVIOUS LAYER (GEOMEMBRANE) -0" Facing Panel 4" PERF. PIPE. COMBINED GEOMEMBRANE AND PAVEMENT EDGE DRAIN 1 3 H 2-0" MIN. EMBED. 2:1 (V:H) 2:1 (V:H) SELECT GRANULAR FILL MNDOT SPEC B2 MODIFIED TO % PASSING THE NO. 0 SIEVE COMPACTION EQUAL TO 2.3F1 LEVELING PAD CONTRACTOR S OPTION TO USE DETAIL A OR B EXCAVATION LIMITS SOIL REINFORCEMENT (TYP.) 2:1 (V:H) INSITU SOILS 4" PERF. PIPE. 1 2 BACK DRAINTILE RETAINED BACKFILL PER ROADWAY TYPICAL MINIMUM LIMITS OF WEDGE OF SPECIFIED BACKFILL MATERIAL. ACTUAL EXCAVATION LIMITS BASED UPON OSHA REQUIREMENTS AND INSITU SOILS. INLET INSITU SOILS ANY SUITABLE BACKFILL MATERIAL 2 4" NON-PERF. PIPE DRAINAGE SYSTEM NOTES: ALL PIPE SHALL BE AS PER MnDOT SPEC STORM SEWER DETAIL A L 0.7H (8 FT. MIN.) " THERMOPLASTIC PERFORATED PIPE, SPEC. 324, WRAP WITH TYPE I GEOTEXTILE. ATTACH TO PIPE AS PER MNDOT SPEC. 2. NON-PERFORATED PIPE TO CONNECT TO INPLACE OR PROPOSED DRAINAGE SYSTEM AT 400 MAX. SPACING ALONG LENGTH OF DRAINTILE. CONNECT TO INPLACE OR PROPOSED PAVEMENT EDGE DRAIN AT ENDS OF MSE WALL. 6" LEAN MIX BACKFILL, SPEC. 2 (MIN.) 4-0" 1-6" 4" THERMOPLASTIC PERFORATED PIPE 1 DETAIL B TOP OF CONCRETE (MIX. NO. 1A43) ELEVATION TO MATCH OTHER TYPE(S) OF LEVELING PAD TYPE i GEOTEXTILE FABRIC (OVERLAP ENDS OF FABRIC BENEATH LEAN MIX BACKFILL (MIN.) COARSE FILTER AGGREGATE SPEC H (MIN. WIDTH OF 18") CENTER PANELS ON PAD CONCRETE LEVELING PAD 4-0" CONCRETE PAD (MIN. WIDTH OF 18") CENTER PANELS ON PAD 2-0" (MIN.) NOT TO SCALE CONCRETE PAD WITHOUT DRAIN NOT TO SCALE Structural Backfill, Leveling Pad Details and Drainage System Treatment (MSE Walls with Precast Concrete Facia - Level Backfill) State of Minnesota - Department of Transportation Office of Materials Revised September 0 Diagram No. MSEW-1

3 4 41 CONC. C113 T D 412 C117 T T T18 { SERRW2 T18 70 C C119 C118 C119 C118 C { SWRRW1 { SB169 6 { SERRW C034 C034 C0 C c014 C028 C021 CONC. { S169RW2 C { INB81 C { NB C121 C03 CONC. CONC. P P P T24 0 C124 2 C036 P 2 { N169RW2 PARKING LOT C0 7 { ISB169 { SWRAMP C031 c C032 C038 c038 T2 C12 c039 { INB c02 T33 C033 { SERAMP { BRAID { BRAIDRW { IWB9 { IEB9 T26 T26 { EB9 BIT. 3.6

4 STA EL STA EL STA EL T - # TH 169 NB, , 2.7 Rt Coh SPT slorg slpl SL w/ a few C119 - #663 TH 169 NB, , 76.4 Rt PWP Tip Stress FR C0 - #66480 TH 169 NB, , 39.6 Rt PWP Tip Stress FR 890 C021 - #66481 TH 169 NB, , 38.8 Rt C121 - #6636 TH 169 NB, , 0.9 Lt PWP Tip Stress FR INPLA seams S, dk brn w/ brn, 880 moist 880 PWP Tip Stress FR 8 S to FS, brn, damp to 870 moist S w/ a few thin seams slpl SL, gray-brns & 860 moist S, gray-brn & sat 42 S & G, brn & sat slpl SL w/ a few pebbles, brn & Vmoist mixed S & CrS, brn & sat 4 69 FS, brn & sat S w/ a few seams CrS, brn & sat 6 37 Bottom of Hole Water measured at 27.2 while sampling and/or drilling

5 RETAINING WALL N169RW2 PROFILE TOP OF RAIL TOP OF BARRIER SLAB STA EL STA EL C121 - #6636 FINISHED GROUNDLINE TH 169 NB, , 0.9 Lt (EAST SIDE OF WALL) INPLACE GROUNDLINE c038 - # PWP Tip Stress FR PWP Tip Stress FR

6 E 2 STA EL STA EL STA EL STA EL BELOW FINISHED GROUNDLINE (FOR ESTIMATED WALL AREA) c038 - # c02 - # PWP Tip Stress FR c039 - # PWP Tip Stress FR PWP Tip Stress FR 880 T26 - #67262 TH 169 NB, , 63.6 Rt Coh SPT S, loamy on top; brn & damp CrS, brn & wet S w/ G, gray-brn to brn, 12 wet to sat 14 S, brn & sat CrS & FG, brn & sat mixed pl SL & SCL w/ pebbles, gray & Vmoist 99 S w/ some G, gray-brn & sat LS w/ a little G, brn & 0/. wet 40 0/.3 Bottom of Hole Water measured at 1.0 while sampling and/or drilling

7 Minnesota Department of Transportation Geotechnical Section Boring Log Descriptive Terminology (English Units) USER NOTES, ABBREVIATIONS AND DEFINITIONS - Additional information available in Geotechnical Manual. This boring was made by ordinary and conventional methods and with care deemed adequate for the Department's design purposes. Since this boring was not taken to gather information relating to the construction of the project, the data noted in the field and recorded may not necessarily be the same as WH... Weight of Hammer WR... Weight of Rod Mud... Drilling Fluids in Sample CS... Continuous Sample very loose loose...- medium dense dense very dense...>0 that which a contractor would desire. While the Consistency - Cohesive Soils BPF Department believes that the information as to the conditions and materials reported is accurate, it does not warrant that the information is necessarily complete. This information has been edited or abridged and may not reveal all the information which might be useful or of interest to the contractor. Consequently, the Department will make available very soft soft firm...-8 stiff very stiff hard very hard...> 60 at its offices, the field logs relating to this boring. Since subsurface conditions outside each borehole are unknown, and soil, rock and water conditions cannot be relied upon to be consistent or uniform, no warrant is made that conditions adjacent to this boring will necessarily be the same as or similar to those shown on this log. Furthermore, the Department will not be responsible for any interpretations, assumptions, projections or interpolations made by contractors, or other users of this log. Water levels recorded on this log should be used with discretion since the use of drilling fluids in borings may seriously distort the true field conditions. Also, water levels in cohesive soils often take extended periods of time to reach equilibrium and thus reflect their true field level. Water levels can be expected to vary both seasonally and yearly. The absence of notations on this log regarding water does not necessarily mean that this boring was dry or that the contractor will not encounter subsurface water during the course of construction. WATER MEASUREMENT AB... After Bailing AC... After Completion AF... After Flushing w/c... with Casing w/m... with Mud WSD... While Sampling/Drilling w/aug... with Hollow Stem Auger MISCELLANEOUS NA... Not Applicable w/... with w/o... with out sat... saturated SOIL/CORE TESTS SPT N ASTM D186 Modified Blows per foot with 140 lb. hammer and a standard energy of 2 ft-lbs. This energy represents 60% of the potential energy of the system and is the average energy provided by a Rope & Cathead system. MC... Moisture Content COH... Cohesion γ... Sample Density LL... Liquid Limit PI... Plasticity Index Φ... Phi Angle REC... Percent Core Recovered RQD... Rock Quality Description (Percent of total core interval consisting of unbroken pieces 4 inches or longer) ACL... Average Core Length (Average length of core that is greater than 4 inches long) Core Breaks... Number of natural core breaks per 2-foot interval. DISCONTINUITY SPACING Fractures Distance Bedding Very Close... <2 inches...very Thin Close inches...thin Mod. Close inches...medium Wide... >36 inches...thick WS PD DRILLING SYMBOLS Vane Shear Test Washed Sample (Collected during plug drilling) Augered Plug Drilled Split Tube Sample (SPT N60 2 in. spilt tube with liners) Thin Wall Sample (3 in. Shelby Tube) % Sand Core Drilled 70 DRILLING OPERATIONS (NV Core Barrel unless otherwise noted) 80 AUG... Augered CS Continuous Soil 90 CD... Core Drilled Sample LS DBD... Disturbed by Drilling A/J 0% S Augered & Jetted DBJ... Disturbed by Jetting Jet Jetted PD... Plug Drilled A/P ST... Split Tube (SPT test) Augered & Plug Drilled TW... Thinwall (Shelby Tube) WS... Wash Sample RELATIVE DENSITY NSR... No Sample Retrieved Compactness - Granular Soils Index Sheet No. 3.0 March 03 G:\geotech\Public\Forms\INDEX.doc BPF 60 0 COLOR blk... Black wht...white grn... Green brn...brown orng... Orange yel...yellow dk... Dark lt...light IOS... Iron Oxide Stained GRAIN SIZE /PLASTICITY VF... Very Fine pl...plastic F... Fine slpl...slightly Cr... Coarse Plastic SOIL/ROCK TERMS C... Clay Lmst...Limestone L... Loam Sst...Sandstone S... Sand Dolo...Dolostone Si... Silt wx...weathered G... Gravel (No. Sieve to 3 inches) Bldr... Boulder (over 3 inches) T... till (unsorted, nonstratified glacial deposits) Mn/DOT Triangular Textural Soil Classification System 40 SC SCL (plastic) SL (slightly plastic) C CL L 0 % % Silt Si SiCL SiL % Clay Si 90 0%

8 MINNESOTA DEPARTMENT OF TRANSPORTATION - GEOTECHNICAL SECTION LABORATORY LOG & TEST RESULTS - SUBSURFACE EXPLORATION UNIQUE NUMBER State Project Location 28R19 TH 169 NB, , 2.7'Rt Hennepin Co. Coordinate: X=4976 Y=21488 Latitude (North)=4 06'22." DEPTH Elev. Lithology US Highway 169 Longitude (West)=93 23'34.07" Classification (ft.) Drill Machine Boring No. 927 Failing 100 4x4 Hammer Mobile Auto Calibrated Drilling Operation SPT N60 REC MC RQD T COH (psf) (pcf) ACL Core (ft) Breaks Soil Rock (Survey) SHEET 1 of 3 Drilling Completed 3/27/06 Other Tests Or Remarks Formation or Member 14 slorg slpl SL w/ a few seams S, dk brn w/ brn, moist S to FS, brn, damp to moist S w/ a few thin seams slpl SL, gray-brns & moist Index Sheet Code 3.0 (Continued Next Page) Soil Class:DSB Rock Class: Edit: DMS Date: 1/23/07 G:\GINT\PROJECTS-ACTIVE\270-7.GPJ

9 MINNESOTA DEPARTMENT OF TRANSPORTATION - GEOTECHNICAL SECTION LABORATORY LOG & TEST RESULTS - SUBSURFACE EXPLORATION UNIQUE NUMBER Mn/DOT GEOTECHNICAL SECTION - LOG & TEST RESULTS SHEET 2 of 3 State Project R19 US Highway 169 Boring No. T (Survey) DEPTH Elev Lithology Classification Drilling Operation SPT N60 REC MC RQD COH (psf) (ft) (pcf) ACL Core Breaks Soil Rock Other Tests Or Remarks Formation or Member S, gray-brn & sat heave to 33.0' 3 S & G, brn & sat 42 N/A slpl SL w/ a few pebbles, brn & Vmoist mixed S & CrS, brn & sat (Continued Next Page) Soil Class:DSB Rock Class: Edit: DMS Date: 1/23/07 G:\GINT\PROJECTS-ACTIVE\270-7.GPJ

10 MINNESOTA DEPARTMENT OF TRANSPORTATION - GEOTECHNICAL SECTION LABORATORY LOG & TEST RESULTS - SUBSURFACE EXPLORATION UNIQUE NUMBER Mn/DOT GEOTECHNICAL SECTION - LOG & TEST RESULTS SHEET 3 of 3 State Project R19 US Highway 169 Boring No. T (Survey) DEPTH Elev. 8.8 Lithology Classification Drilling Operation SPT N60 REC MC RQD COH (psf) ACL (ft) (pcf) Core Breaks Soil Rock Other Tests Or Remarks Formation or Member FS, brn & sat S w/ a few seams CrS, brn & sat Bottom of Hole ' Water measured at 27.2' while sampling and/or drilling Soil Class:DSB Rock Class: Edit: DMS Date: 1/23/07 G:\GINT\PROJECTS-ACTIVE\270-7.GPJ

11 MINNESOTA DEPARTMENT OF TRANSPORTATION - GEOTECHNICAL SECTION LABORATORY LOG & TEST RESULTS - SUBSURFACE EXPLORATION UNIQUE NUMBER State Project Location TH 169 NB, , 63.6'Rt Hennepin Co. Coordinate: X=49792 Y=21780 Latitude (North)=4 06'31.14" DEPTH Elev. Lithology 27R21 US Highway 169 Longitude (West)=93 23'28." Classification (ft.) Drill Machine 927 Failing 100 4x4 Hammer Mobile Auto Calibrated Drilling Operation SPT N 60 REC SHEET 1 of 3 Drilling Completed MC COH Other Tests (psf) (pcf) Or Remarks RQD Boring No. T26 ACL Core (ft) Breaks Soil Rock (from Plan) Formation or Member 4/13/ S, loamy on top; brn & damp CrS, brn & wet 17 1 S w/ G, gray-brn to brn, wet to sat 12 N/A S, brn & sat CrS & FG, brn & sat Index Sheet Code 3.0 (Continued Next Page) Soil Class:DSB Rock Class: Edit: DMS Date: 1/23/07 G:\GINT\PROJECTS-ACTIVE\270-7.GPJ

12 MINNESOTA DEPARTMENT OF TRANSPORTATION - GEOTECHNICAL SECTION LABORATORY LOG & TEST RESULTS - SUBSURFACE EXPLORATION UNIQUE NUMBER Mn/DOT GEOTECHNICAL SECTION - LOG & TEST RESULTS SHEET 2 of 3 State Project R21 US Highway 169 Boring No. T (from Plan) DEPTH Elev. Lithology Classification Drilling Operation SPT N60 REC MC RQD COH (psf) (pcf) ACL Core (ft) Breaks Soil Rock Other Tests Or Remarks Formation or Member CrS & FG, brn & sat (continued) mixed pl SL & SCL w/ pebbles, gray & Vmoist S w/ some G, gray-brn & sat LS w/ a little G, brn & wet (Continued Next Page) hard 49.0' - boulder Soil Class:DSB Rock Class: Edit: DMS Date: 1/23/07 G:\GINT\PROJECTS-ACTIVE\270-7.GPJ

13 MINNESOTA DEPARTMENT OF TRANSPORTATION - GEOTECHNICAL SECTION LABORATORY LOG & TEST RESULTS - SUBSURFACE EXPLORATION UNIQUE NUMBER Mn/DOT GEOTECHNICAL SECTION - LOG & TEST RESULTS SHEET 3 of 3 State Project R21 US Highway 169 Boring No. T (from Plan) DEPTH Elev. Lithology Classification Drilling Operation SPT N60 REC MC RQD COH (psf) (ft) (pcf) ACL Core Breaks Soil Rock Other Tests Or Remarks Formation or Member LS w/ a little G, brn & wet (continued) 0/ Bottom of Hole ' Water measured at 1.0' while sampling and/or drilling 40/. 0/.3 9 Soil Class:DSB Rock Class: Edit: DMS Date: 1/23/07 G:\GINT\PROJECTS-ACTIVE\270-7.GPJ

14 This Cone Penetration Test (CPT) Sounding follows ASTM D 778 and was made by ordinary and conventional methods and with care deemed adequate for the Department's design purposes. Since this sounding was not taken to gather information relating to the construction of the project, the data noted in the field and recorded may not necessarily be the same as that which a contractor would desire. While the Department believes that the information as to the conditions and materials reported is accurate, it does not warrant that the information is necessarily complete. This information has been edited or abridged and may not reveal all the information which might be useful or of interest to the contractor. Consequently, the Department will make available at its offices, the field logs relating to this sounding. Minnesota Department of Transportation Geotechnical Section Cone Penetration Test Index Sheet 1.0 (CPT 1.0) USER NOTES, ABBREVIATIONS AND DEFINITIONS This Index sheet accompanies Cone Penetration Test Ratio of sleeve friction over corrected tip Data. Please refer to the Boring Log Descriptive resistance. Terminology Sheet for information relevant to FR = fs/qt conventional boring logs. Vs Shear Wave Velocity A measure of the speed at which a siesmic wave travels through soil/rock. PORE WATER MEASUREMENTS Pore water measurements reported on CPT Log are representative of water pressures measured at the U2 location, just behind the cone tip, prior to the sleeve, as shown in the figure below. These measurements are considered to be dynamic water pressures due to the local disturbance caused by the cone tip. Dynamic water pressure decay and Static water pressure measurements are reported on a Pore Water Pressure Dissipation Graph. Since subsurface conditions outside each CPT Sounding are unknown, and soil, rock and water conditions cannot be relied upon to be consistent or uniform, no warrant is made that conditions adjacent to this sounding will necessarily be the same as or similar to those shown on this log. Furthermore, the Department will not be responsible for any interpretations, assumptions, projections or interpolations made by contractors, or other users of this log. U2 Robertson CPTU 1990 Soil Behavior type based on pore pressure Water pressure measurements and subsequent interpreted water levels shown on this log should be used with discretion since they represent dynamic conditions. Dynamic Pore water pressure measurements may deviate substantially from hydrostatic conditions, especially in cohesive soils. In cohesive soils, water pressures often take extended periods of time to reach equilibrium and thus reflect their true field level. Water levels can be expected to vary both seasonally and yearly. The absence of notations on this log regarding water does not necessarily mean that this boring was dry or that the contractor will not encounter subsurface water during the course of construction. CPT Terminology CPT...Cone Penetration Test CPTU...Cone Penetration Test with Pore Pressure measurements SCPTU...Cone Penetration Test with Pore Pressure and Seismic measurements Piezocone...Common name for CPTU test (Note: This test is not related to the Dynamic Cone Penetrometer DCP) qt TIP RESISTANCE The resistance at the cone corrected for water pressure. Data is from cone with 60 degree apex angle and a cm 2 end area. fs SLEEVE FRICTION RESISTANCE The resistance along the sleeve of the penetrometer. FR Friction Ratio SBT SOIL BEHAVIOR TYPE Soil Classification methods for the Cone Penetration Test are based on correlation charts developed from observations of CPT data and conventional borings. Please note that these classification charts are meant to provide a guide to Soil Behavior Type and should not be used to infer a soil classification based on grain size distribution. The numbers corresponding to different regions on the charts represent the following soil behavior types: 1. Sensitive, Fine Grained 2. Organic Soils - Peats 3. Clays - Clay to Silty Clay 4. Silt Mixtures - Clayey Silt to Silty Clay. Sand Mixtures - Silty Sand to Sandy Silt 6. Sands - Clean Sand to Silty Sand 7. Gravelly Sand to Sand 8. Very Stiff Sand to Clayey Sand 9. Very Stiff, Fine Grained Note that engineering judgment, and comparison with conventional borings is especially important in the proper interpretation of CPT data in certain geomaterials. The following charts are used to provide a Soil Behavior Type for the CPT Data. Robertson CPT 1990 Soil Behavior type based on friction ratio where... QT... normalized cone resistance BBq... pore pressure ratio Fr... Normalized friction ratio σvo... overburden pressure σ vo... effective over burden pressure u 2... measured pore pressure u0... equilibrium pore pressure G:\GEOTECH\PUBLIC\FORMS\CPTINDEX.DOC January, 02

15 State Project Location MINNESOTA DEPARTMENT OF TRANSPORTATION - GEOTECHNICAL SECTION Ret Wall TH 169 NB, , 39.6'Rt CPT Machine 94 CPT Truck (from Plan) SHEET 1 of 1 Hennepin Co. Coordinate: X=49764 Y=21013 (ft.) CPT Operator D Brady Date Completed Latitude (North)=4 06'23.6" Longitude (West)=93 23'32.84" Hole Type undesignated 11// Interpreted Soil Behavior Type UBC 1990 FR CONE PENETRATION TEST RESULTS UNIQUE NUMBER Sleeve Friction Tip Resistance Sounding No. C0 Friction Ratio Pore Pressure End of Data Bottom of Hole Index Sheet Code 3.0 BN0404C Soil Class: Rock Class: Edit: DMS Date: 1/23/07 G:\GINT\PROJECTS-ACTIVE\270-7.GPJ

16 State Project Location Hennepin Co. Coordinate: X= Y= MINNESOTA DEPARTMENT OF TRANSPORTATION - GEOTECHNICAL SECTION Latitude (North)=4 06'24.42" CONE PENETRATION TEST RESULTS UNIQUE NUMBER Ret Wall 169 C (from Plan) TH 169 NB, , 38.8'Rt Interpreted Soil Behavior Type UBC 1990 FR Longitude (West)=93 23'32.23" Sleeve Friction (ft.) Tip Resistance CPT Machine CPT Operator Hole Type undesignated Sounding No. 94 CPT Truck D Brady Friction Ratio SHEET 1 of 1 Date Completed 11//04 Pore Pressure End of Data Bottom of Hole Index Sheet Code 3.0 BN0403C Soil Class: Rock Class: Edit: DMS Date: 1/23/07 G:\GINT\PROJECTS-ACTIVE\270-7.GPJ

17 State Project Location Hennepin Co. Coordinate: X= Y=2169 Latitude (North)=4 06'29.94" MINNESOTA DEPARTMENT OF TRANSPORTATION - GEOTECHNICAL SECTION,, ft. LT Ret Wall Interpreted Soil Behavior Type UBC 1990 FR CONE PENETRATION TEST RESULTS UNIQUE NUMBER Longitude (West)=93 23'29.29" Sleeve Friction (ft.) Tip Resistance CPT Machine CPT Operator Hole Type undesignated Sounding No CPT Track lueck c02 Friction Ratio (from Plan) SHEET 1 of 2 Date Completed /18/06 Pore Pressure Index Sheet Code 3.0 (Continued Next Page) A18Y060C.DAT Soil Class: Rock Class: Edit: Date: 1/23/07 G:\GINT\PROJECTS-ACTIVE\270-7.GPJ

18 MINNESOTA DEPARTMENT OF TRANSPORTATION - GEOTECHNICAL SECTION CONE PENETRATION TEST RESULTS UNIQUE NUMBER State Project Ret Wall 169 Sounding No. c (from Plan) Mn/DOT GEOTECHNICAL SECTION - CONE PENETRATION TEST RESULTS SHEET 2 of Interpreted Soil Behavior Type UBC 1990 FR End of Data Sleeve Friction Tip Resistance Friction Ratio Pore Pressure Bottom of Hole.89 A18Y060C.DAT Soil Class: Rock Class: Edit: Date: 1/23/07 G:\GINT\PROJECTS-ACTIVE\270-7.GPJ

19 State Project Location,, ft. LT Hennepin Co. Coordinate: X= Y=2100 Latitude (North)=4 06'28.37" MINNESOTA DEPARTMENT OF TRANSPORTATION - GEOTECHNICAL SECTION CONE PENETRATION TEST RESULTS UNIQUE NUMBER Ret Wall 169 c (from Plan) Interpreted Soil Behavior Type UBC 1990 FR Sleeve Friction Longitude (West)=93 23'29.36" (ft.) Tip Resistance CPT Machine CPT Operator Hole Type undesignated CPT Track lueck Sounding No. Friction Ratio SHEET 1 of 1 Date Completed /18/06 Pore Pressure End of Data Bottom of Hole Index Sheet Code 3.0 A18Y0603C.DAT Soil Class: Rock Class: Edit: Date: 1/23/07 G:\GINT\PROJECTS-ACTIVE\270-7.GPJ

20 State Project Location,, ft. LT CPT Machine CPT Track Hennepin Co. Coordinate: X=49791 Y=2196 Latitude (North)=4 06'29.32" MINNESOTA DEPARTMENT OF TRANSPORTATION - GEOTECHNICAL SECTION Ret Wall Interpreted Soil Behavior Type UBC 1990 FR CONE PENETRATION TEST RESULTS UNIQUE NUMBER Longitude (West)=93 23'29.07" Sleeve Friction (ft.) Tip Resistance CPT Operator lueck Hole Type undesignated Sounding No. c039 Friction Ratio (from Plan) SHEET 1 of 1 Date Completed /18/06 Pore Pressure End of Data Bottom of Hole Index Sheet Code 3.0 A18Y0604C.DAT Soil Class: Rock Class: Edit: Date: 1/23/07 G:\GINT\PROJECTS-ACTIVE\270-7.GPJ

21 State Project Ret Wall Location TH 169 NB, , 76.4'Rt CPT Machine 94 CPT Truck Latitude (North)=4 06'22.78" Interpreted Soil Behavior Type Sleeve Friction 169 Hennepin Co. Coordinate: X= Y= MINNESOTA DEPARTMENT OF TRANSPORTATION - GEOTECHNICAL SECTION UBC 1990 FR CONE PENETRATION TEST RESULTS UNIQUE NUMBER 663 Longitude (West)=93 23'32.86" (ft.) Tip Resistance CPT Operator Sounding No. C119 D Brady SHEET 1 of 1 Date Completed Hole Type undesignated 11//04 Friction Ratio 88.8 (from Plan) Pore Pressure End of Data Bottom of Hole Index Sheet Code 3.0 BN040C Soil Class: Rock Class: Edit: DMS Date: 1/23/07 G:\GINT\PROJECTS-ACTIVE\270-7.GPJ

22 State Project Location TH 169 NB, , 0.9'Lt Hennepin Co. Coordinate: X= Y=21189 Latitude (North)=4 06'2." MINNESOTA DEPARTMENT OF TRANSPORTATION - GEOTECHNICAL SECTION Ret Wall Interpreted Soil Behavior Type UBC 1990 FR CONE PENETRATION TEST RESULTS UNIQUE NUMBER Longitude (West)=93 23'32.2" Sleeve Friction (ft.) Tip Resistance CPT Machine CPT Operator Hole Type undesignated Sounding No. C CPT Truck D Brady Friction Ratio (from Plan) SHEET 1 of 1 Date Completed 11//04 Pore Pressure End of Data Bottom of Hole Index Sheet Code 3.0 BN0402C Soil Class: Rock Class: Edit: DMS Date: 1/23/07 G:\GINT\PROJECTS-ACTIVE\270-7.GPJ

23 State Project Location TH 169 NB, , 2.7'Rt CPT Machine 927 Failing 100 4x4 SHEET 1 of 3 Hennepin Co. Coordinate: X=4976 Y=21488 (ft.) CPT Operator J. Hasselquist Date Completed Latitude (North)=4 06'22." Longitude (West)=93 23'34.07" Hole Type BORING 3/27/ MINNESOTA DEPARTMENT OF TRANSPORTATION - GEOTECHNICAL SECTION 28R19 Interpreted Soil Behavior Type UBC 1983 FR CONE PENETRATION TEST RESULTS UNIQUE NUMBER Sleeve Friction Tip Resistance Sounding No. T Friction Ratio (Survey) Pore Pressure Index Sheet Code 3.0 (Continued Next Page) Soil Class:DSB Rock Class: Edit: DMS Date: 1/23/07 G:\GINT\PROJECTS-ACTIVE\270-7.GPJ

24 MINNESOTA DEPARTMENT OF TRANSPORTATION - GEOTECHNICAL SECTION CONE PENETRATION TEST RESULTS UNIQUE NUMBER State Project R Sounding No. T (Survey) Mn/DOT GEOTECHNICAL SECTION - CONE PENETRATION TEST RESULTS SHEET 2 of 3 Interpreted Soil Behavior Type UBC 1983 FR Sleeve Friction Tip Resistance Friction Ratio Pore Pressure (Continued Next Page) Soil Class:DSB Rock Class: Edit: DMS Date: 1/23/07 G:\GINT\PROJECTS-ACTIVE\270-7.GPJ

25 MINNESOTA DEPARTMENT OF TRANSPORTATION - GEOTECHNICAL SECTION CONE PENETRATION TEST RESULTS UNIQUE NUMBER State Project R Sounding No. T (Survey) Mn/DOT GEOTECHNICAL SECTION - CONE PENETRATION TEST RESULTS SHEET 3 of 3 Interpreted Soil Behavior Type UBC 1983 FR Sleeve Friction Tip Resistance Friction Ratio Pore Pressure Soil Class:DSB Rock Class: Edit: DMS Date: 1/23/07 G:\GINT\PROJECTS-ACTIVE\270-7.GPJ

26 State Project R Location TH 169 NB, , 63.6'Rt CPT Machine 927 Failing 100 4x MINNESOTA DEPARTMENT OF TRANSPORTATION - GEOTECHNICAL SECTION Hennepin Co. Coordinate: X=49792 Y=21780 Latitude (North)=4 06'31.14" Interpreted Soil Behavior Type UBC 1983 FR CONE PENETRATION TEST RESULTS UNIQUE NUMBER Longitude (West)=93 23'28." Sleeve Friction (ft.) Tip Resistance CPT Operator Hole Type BORING Sounding No. T26 J. Hasselquist Friction Ratio (from Plan) SHEET 1 of 3 Date Completed 4/13/0 Pore Pressure Index Sheet Code 3.0 (Continued Next Page) Soil Class:DSB Rock Class: Edit: DMS Date: 1/23/07 G:\GINT\PROJECTS-ACTIVE\270-7.GPJ

27 MINNESOTA DEPARTMENT OF TRANSPORTATION - GEOTECHNICAL SECTION CONE PENETRATION TEST RESULTS UNIQUE NUMBER State Project R Sounding No. T (from Plan) Mn/DOT GEOTECHNICAL SECTION - CONE PENETRATION TEST RESULTS SHEET 2 of Interpreted Soil Behavior Type UBC 1983 FR Sleeve Friction Tip Resistance Friction Ratio Pore Pressure (Continued Next Page) Soil Class:DSB Rock Class: Edit: DMS Date: 1/23/07 G:\GINT\PROJECTS-ACTIVE\270-7.GPJ

28 MINNESOTA DEPARTMENT OF TRANSPORTATION - GEOTECHNICAL SECTION CONE PENETRATION TEST RESULTS UNIQUE NUMBER State Project R Sounding No. T (from Plan) Mn/DOT GEOTECHNICAL SECTION - CONE PENETRATION TEST RESULTS SHEET 3 of Interpreted Soil Behavior Type UBC 1983 FR Sleeve Friction Tip Resistance Friction Ratio Pore Pressure Soil Class:DSB Rock Class: Edit: DMS Date: 1/23/07 G:\GINT\PROJECTS-ACTIVE\270-7.GPJ

SP TH 169 MSE Wall N169RW1 Located at the SW quadrant of proposed TH 169 and CSAH 81 Foundation Investigation and Recommendations

SP TH 169 MSE Wall N169RW1 Located at the SW quadrant of proposed TH 169 and CSAH 81 Foundation Investigation and Recommendations Minnesota Department of Transportation Memo Geotechnical Engineering Section Office of Materials (MS 64) Office Tel: (61) 366-98 1400 Gervais Avenue, Maplewood, MN 9 Office Fax: (61) 366-616 Date: January,

More information

Minnesota Department of Transportation MEMO Office of Materials Mailstop Gervais Avenue Maplewood, MN 55109

Minnesota Department of Transportation MEMO Office of Materials Mailstop Gervais Avenue Maplewood, MN 55109 Minnesota Department of Transportation MEMO Office of Materials Mailstop 4 1400 Gervais Avenue Maplewood, MN 9 DATE: April 2, 09 TO: FROM: D. J. Sosa, Final Design Project Manager Metro Waters Edge Gary

More information

From R. Lamb, Foundations Project Engineer Concurred By G. Person,Foundations Engineer

From R. Lamb, Foundations Project Engineer Concurred By G. Person,Foundations Engineer Minnesota Department of Transportation Memo Geotechnical Engineering Section Office of Materials (MS 64) Office Tel: (61) 366-98 1400 Gervais Avenue, Maplewood, MN 9 Office Fax: (61) 779-616 Date: October

More information

Minnesota Department of Transportation Geotechnical Section Cone Penetration Test Index Sheet 1.0 (CPT 1.0)

Minnesota Department of Transportation Geotechnical Section Cone Penetration Test Index Sheet 1.0 (CPT 1.0) This Cone Penetration Test (CPT) Sounding follows ASTM D 5778 and was made by ordinary and conventional methods and with care deemed adequate for the Department's design purposes. Since this sounding was

More information

Minnesota Department of Transportation Geotechnical Section Cone Penetration Test Index Sheet 1.0 (CPT 1.0)

Minnesota Department of Transportation Geotechnical Section Cone Penetration Test Index Sheet 1.0 (CPT 1.0) This Cone Penetration Test (CPT) Sounding follows ASTM D 778 and was made by ordinary and conventional methods and with care deemed adequate for the Department's design purposes. Since this sounding was

More information

Subcut Elevation. Proposed Subcut N/A

Subcut Elevation. Proposed Subcut N/A Minnesota Department of Transportation Memo Geotechnical Engineering Section Office of Materials (MS 64) Office Tel: (61) 366-98 1400 Gervais Avenue, Maplewood, MN 9 Office Fax: (61) 779-616 Date: November

More information

Existing Bridge Proposed Bridge 66003

Existing Bridge Proposed Bridge 66003 922 335 9 T2 X 924 919 9 T4 923 T3 919 922 9 T1 925 919 Existing Bridge 6842 919 9 Proposed Bridge 66003 Minnesota Department of Transportation Geotechnical Section Boring Log Descriptive Terminology (English

More information

Rich Lamb, Foundations Design/Build Engineer

Rich Lamb, Foundations Design/Build Engineer Minnesota Department of Transportation MEMO Mailstop 64 14 Gervais Avenue Maplewood, MN 9 DATE: November 17, 16 TO: FROM: CONCUR: Andrew Lutaya, Final Design Project Manager Metro District Paul Martin,

More information

Minnesota Department of Transportation MEMO Office of Materials Mailstop Gervais Avenue Maplewood, MN 55109

Minnesota Department of Transportation MEMO Office of Materials Mailstop Gervais Avenue Maplewood, MN 55109 Minnesota Department of Transportation MEMO Office of Materials Mailstop 64 1400 Gervais Avenue Maplewood, MN 9 DATE: May 1, 09 TO: FROM: Dale Gade, Final Design Project Manager Metro Waters Edge Gary

More information

An Equal Opportunity Employer. Date: December 17, To: Dan Prather, Preliminary Bridge Engineer Office of Bridges & Structures.

An Equal Opportunity Employer. Date: December 17, To: Dan Prather, Preliminary Bridge Engineer Office of Bridges & Structures. Minnesota Department of Transportation Office of Materials & Road Research 1400 Gervais Avenue, Maplewood, MN 9 Memo Date: December 17, 14 To: From: Dan Prather, Preliminary Bridge Engineer Office of Bridges

More information

B-1 BORE LOCATION PLAN. EXHIBIT Drawn By: 115G BROOKS VETERINARY CLINIC CITY BASE LANDING AND GOLIAD ROAD SAN ANTONIO, TEXAS.

B-1 BORE LOCATION PLAN. EXHIBIT Drawn By: 115G BROOKS VETERINARY CLINIC CITY BASE LANDING AND GOLIAD ROAD SAN ANTONIO, TEXAS. N B-1 SYMBOLS: Exploratory Boring Location Project Mngr: BORE LOCATION PLAN Project No. GK EXHIBIT Drawn By: 115G1063.02 GK Scale: Checked By: 1045 Central Parkway North, Suite 103 San Antonio, Texas 78232

More information

Project: ITHACA-TOMPKINS REGIONAL AIRPORT EXPANSION Project Location: ITHACA, NY Project Number: 218-34 Key to Soil Symbols and Terms TERMS DESCRIBING CONSISTENCY OR CONDITION COARSE-GRAINED SOILS (major

More information

Chapter 12 Subsurface Exploration

Chapter 12 Subsurface Exploration Page 12 1 Chapter 12 Subsurface Exploration 1. The process of identifying the layers of deposits that underlie a proposed structure and their physical characteristics is generally referred to as (a) subsurface

More information

ATTACHMENT A PRELIMINARY GEOTECHNICAL SUMMARY

ATTACHMENT A PRELIMINARY GEOTECHNICAL SUMMARY ATTACHMENT A PRELIMINARY GEOTECHNICAL SUMMARY Kevin M. Martin, P.E. KMM Geotechnical Consultants, LLC 7 Marshall Road Hampstead, NH 0384 603-489-6 (p)/ 603-489-8 (f)/78-78-4084(m) kevinmartinpe@aol.com

More information

Boreholes. Implementation. Boring. Boreholes may be excavated by one of these methods: 1. Auger Boring 2. Wash Boring 3.

Boreholes. Implementation. Boring. Boreholes may be excavated by one of these methods: 1. Auger Boring 2. Wash Boring 3. Implementation Boreholes 1. Auger Boring 2. Wash Boring 3. Rotary Drilling Boring Boreholes may be excavated by one of these methods: 4. Percussion Drilling The right choice of method depends on: Ground

More information

Photo 1 - Southerly view across 2700 parking lot toward existing building. Multi-residential building borders western side of property in upper right of view. Photo 2 - Southerly view across 2750 parking

More information

Geotechnical Recommendations for Proposed Additions to the Three Mile Creek Severe Weather Attenuation Tank Project

Geotechnical Recommendations for Proposed Additions to the Three Mile Creek Severe Weather Attenuation Tank Project TECHNICAL MEMORANDUM Geotechnical Recommendations for Proposed Additions to the Three Mile Creek Severe Weather Attenuation Tank Project PREPARED FOR: PREPARED BY: DATE: June 28, 218 PROJECT NUMBER: 697482

More information

Civil Engineering, Surveying and Environmental Consulting WASP0059.ltr.JLS.Mich Ave Bridge Geotech.docx

Civil Engineering, Surveying and Environmental Consulting WASP0059.ltr.JLS.Mich Ave Bridge Geotech.docx 2365 Haggerty Road South * Canton, Michigan 48188 P: 734-397-3100 * F: 734-397-3131 * www.manniksmithgroup.com August 29, 2012 Mr. Richard Kent Washtenaw County Parks and Recreation Commission 2330 Platt

More information

ENCE 3610 Soil Mechanics. Site Exploration and Characterisation Field Exploration Methods

ENCE 3610 Soil Mechanics. Site Exploration and Characterisation Field Exploration Methods ENCE 3610 Soil Mechanics Site Exploration and Characterisation Field Exploration Methods Geotechnical Involvement in Project Phases Planning Design Alternatives Preparation of Detailed Plans Final Design

More information

Pierce County Department of Planning and Land Services Development Engineering Section

Pierce County Department of Planning and Land Services Development Engineering Section Page 1 of 7 Pierce County Department of Planning and Land Services Development Engineering Section PROJECT NAME: DATE: APPLICATION NO.: PCDE NO.: LANDSLIDE HAZARD AREA (LHA) GEOLOGICAL ASSESSMENT REPORT

More information

Depth (ft) USCS Soil Description TOPSOIL & FOREST DUFF

Depth (ft) USCS Soil Description TOPSOIL & FOREST DUFF Test Pit No. TP-6 Location: Latitude 47.543003, Longitude -121.980441 Approximate Ground Surface Elevation: 1,132 feet Depth (ft) USCS Soil Description 0 1.5 1.5 5.0 SM 5.0 8.0 SM Loose to medium dense,

More information

SOIL CLASSIFICATION CHART COARSE-GRAINED SOILS MORE THAN 50% RETAINED ON NO.200 SIEVE FINE-GRAINED SOILS 50% OR MORE PASSES THE NO.200 SIEVE PRIMARY DIVISIONS GRAVELS MORE THAN 50% OF COARSE FRACTION RETAINED

More information

GEOTECHNICAL REPORT. Matanuska-Susitna Borough. Parks Highway Connections Museum Drive. Matanuska-Susitna Borough, Alaska.

GEOTECHNICAL REPORT. Matanuska-Susitna Borough. Parks Highway Connections Museum Drive. Matanuska-Susitna Borough, Alaska. Matanuska-Susitna Borough GEOTECHNICAL REPORT Parks Highway Connections Museum Drive Matanuska-Susitna Borough, Alaska March 2, 20 Prepared By: John Thornley, PE Geotechnical Engineer 333 Arctic Blvd.,

More information

B-1 SURFACE ELEVATION

B-1 SURFACE ELEVATION 5A 5B LOGGED BY El. S. Bhangoo DRILLING CONTRACTOR Pitcher Drilling DRILLING METHOD Rotary Wash BEGIN DATE 12-14-12 SAMPLER TYPE(S) AND SIZE(S) (ID) SPT, MC BOREHOLE BACKFILL AND COMPLETION COMPLETION

More information

Report of Preliminary Geotechnical Exploration. CSO-012 Sewer Separation Cincinnati, Hamilton County, Ohio. February, 2011

Report of Preliminary Geotechnical Exploration. CSO-012 Sewer Separation Cincinnati, Hamilton County, Ohio. February, 2011 11242843_GeoTech_Preliminary - Feburary 2011_1/40 Report of Preliminary Geotechnical Exploration CSO-012 Sewer Separation Cincinnati, Hamilton County, Ohio February, 2011 11242843_GeoTech_Preliminary -

More information

APPENDIX C HYDROGEOLOGIC INVESTIGATION

APPENDIX C HYDROGEOLOGIC INVESTIGATION Figure B-5.7 Figure B-5.8 Preliminary Geotechnical and Environmental Report Appendix C Hydrogeologic Investigation APPENDIX C HYDROGEOLOGIC INVESTIGATION December 21, 2011 WESTSIDE SUBWAY EXTENSION PROJECT

More information

Geotechnical Engineering Report

Geotechnical Engineering Report Geotechnical Engineering Report Turner Turnpike Widening Bridge B Bridge Crossing: South 257 th West Avenue Creek County, Oklahoma June 1, 2016 Terracon Project No. 04155197 Prepared for: Garver, LLC Tulsa,

More information

Geotechnical Data Report

Geotechnical Data Report Geotechnical Data Report Downtown Greenville Future Conveyance Study December 1, 2015 Terracon Project No. 86155032 Prepared for: Prepared by: Terracon Consultants, Inc. December 1, 2015 561 Mauldin Road

More information

The process of determining the layers of natural soil deposits that will underlie a proposed structure and their physical properties is generally

The process of determining the layers of natural soil deposits that will underlie a proposed structure and their physical properties is generally The process of determining the layers of natural soil deposits that will underlie a proposed structure and their physical properties is generally referred to as sub surface investigation 2 1 For proper

More information

APPENDIX E SOILS TEST REPORTS

APPENDIX E SOILS TEST REPORTS Otsego County, NY Site Work Specifications APPENDIX E SOILS TEST REPORTS Blue Wing Services, Inc. July 1, 2010 Blue Wing Services May 20, 2010 Page 2 the site, was not made available to Empire at this

More information

AN EMPLOYEE OWNED COMPANY

AN EMPLOYEE OWNED COMPANY CTL Engineering, Inc. 2860 Fisher Road, P.O. Box 4448, Columbus, Ohio 43204338 Phone: 614/2768123 Fax: 614/2766377 Email: ctl@ctleng.com AN EMPLOYEE OWNED COMPANY Consulting Engineers Testing Inspection

More information

PRELIMINARY GEOTECHNICAL EXPLORATION Additional MeadWestvaco Ridgeville Property 331 acres Dorchester County, South Carolina S&ME Project No. 1131-09-259A Prepared For: BP Barber & Associates Post Office

More information

Geotechnical Engineering Report

Geotechnical Engineering Report Geotechnical Engineering Report Turner Turnpike Widening Bridge D Bridge Crossing: South 209 th West Avenue Creek County, Oklahoma June 1, 2016 Terracon Project No. 04155197 Prepared for: Garver, LLC Tulsa,

More information

Geotechnical Engineering Report

Geotechnical Engineering Report Geotechnical Engineering Report Turner Turnpike Widening Polecat Creek Bridge (Bridge A) June 1, 2016 Terracon Project No. 04155197 Prepared for: Garver, LLC Prepared by: Terracon Consultants, Inc. TABLE

More information

DATA REPORT GEOTECHNICAL INVESTIGATION GALVESTON CRUISE TERMINAL 2 GALVESTON, TEXAS

DATA REPORT GEOTECHNICAL INVESTIGATION GALVESTON CRUISE TERMINAL 2 GALVESTON, TEXAS DATA REPORT GEOTECHNICAL INVESTIGATION GALVESTON CRUISE TERMINAL 2 GALVESTON, TEXAS SUBMITTED TO PORT OF GALVESTON 123 ROSENBERG AVENUE, 8TH FLOOR GALVESTON, TEXAS 77553 BY HVJ ASSOCIATES, INC. HOUSTON,

More information

Technical Memorandum. Soil Borings

Technical Memorandum. Soil Borings Technical Memorandum To: Project File and Appendix F to Sediment Remedial Investigation Report From: Sara L. Leow, PE Subject: Geotechnical Investigation and Results Summary Date: February 213 Project:

More information

CPT Data Interpretation Theory Manual

CPT Data Interpretation Theory Manual CPT Data Interpretation Theory Manual 2016 Rocscience Inc. Table of Contents 1 Introduction... 3 2 Soil Parameter Interpretation... 5 3 Soil Profiling... 11 3.1 Non-Normalized SBT Charts... 11 3.2 Normalized

More information

APPENDIX A. Borehole Logs Explanation of Terms and Symbols

APPENDIX A. Borehole Logs Explanation of Terms and Symbols APPENDIX A Borehole Logs Explanation of Terms and Symbols Page 153 of 168 EXPLANATION OF TERMS AND SYMBOLS The terms and symbols used on the borehole logs to summarize the results of field investigation

More information

SITE INVESTIGATION 1

SITE INVESTIGATION 1 SITE INVESTIGATION 1 Definition The process of determining the layers of natural soil deposits that will underlie a proposed structure and their physical properties is generally referred to as site investigation.

More information

GEOTECHNICAL INVESTIGATION REPORT

GEOTECHNICAL INVESTIGATION REPORT GEOTECHNICAL INVESTIGATION REPORT SOIL INVESTIGATION REPORT FOR STATIC TEST FACILITY FOR PROPELLANTS AT BDL, IBRAHIMPATNAM. Graphics Designers, M/s Architecture & Engineering 859, Banjara Avenue, Consultancy

More information

ADDENDUM 1 FISHER SLOUGH RESTORATION PROJECT SKAGIT COUNTY, WASHINGTON

ADDENDUM 1 FISHER SLOUGH RESTORATION PROJECT SKAGIT COUNTY, WASHINGTON F I N A L A D D E N D U M 1 R E P O R T ADDENDUM 1 FISHER SLOUGH RESTORATION PROJECT SKAGIT COUNTY, WASHINGTON REPORT OF GEOTECHNICAL INVESTIGATION URS JOB NO. 3376186 Prepared for Tetra Tech Inc. 142

More information

Conventional Field Testing & Issues (SPT, CPT, DCPT, Geophysical methods)

Conventional Field Testing & Issues (SPT, CPT, DCPT, Geophysical methods) Conventional Field Testing & Issues (SPT, CPT, DCPT, Geophysical methods) Ajanta Sachan Assistant Professor Civil Engineering IIT Gandhinagar Conventional Field Testing 1 Field Test: In-situ shear strength

More information

REPORT OF SUBSURFACE EXPLORATION

REPORT OF SUBSURFACE EXPLORATION REPORT OF SUBSURFACE EXPLORATION GRAND RIVER DAM AUTHORITY HULBERT 69 KV SWITCHING STATION S. 440 Road Hulbert, Cherokee County, Oklahoma ENERCON PROJECT NO. GRDA006 MARCH 7, 2012 PREPARED FOR: C/O ENERCON

More information

APPENDIX A GEOTECHNICAL REPORT

APPENDIX A GEOTECHNICAL REPORT The City of Winnipeg Bid Opportunity No. 529-2017 Template Version: C420170317 - RW APPENDIX A GEOTECHNICAL REPORT Quality Engineering Valued Relationships KGS Group 2017 Industrial Street Rehabilitation

More information

Northern Colorado Geotech

Northern Colorado Geotech PRELIMINARY GEOTECHNICAL ENGINEERING REPORT PROPOSED CECIL FARMS DEVELOPMENT WELD COUNTY ROAD 7, BETWEEN ROADS 7 AND 7 SEVERANCE, COLORADO NORTHERN COLORADO GEOTECH PROJECT NO. 0-6 APRIL 0, 06 Prepared

More information

(THIS IS ONLY A SAMPLE REPORT OR APPENDIX OFFERED TO THE USERS OF THE COMPUTER PROGRAM

(THIS IS ONLY A SAMPLE REPORT OR APPENDIX OFFERED TO THE USERS OF THE COMPUTER PROGRAM C A U T I O N!! (THIS IS ONLY A SAMPLE REPORT OR APPENDIX OFFERED TO THE USERS OF THE COMPUTER PROGRAM EQLique&Settle2. THE AUTHOR IS HEREBY RELEASED OF ANY LIABILITY FOR ANY INCORRECT USE OF THIS SAMPLE

More information

APPENDIX C. Borehole Data

APPENDIX C. Borehole Data APPENDIX C Borehole Data MAJOR DIVISIONS SOIL CLASSIFICATION CHART SYMBOLS GRAPH LETTER TYPICAL DESCRIPTIONS ADDITIONAL MATERIAL

More information

Geotechnical Investigation

Geotechnical Investigation Geotechnical Investigation Veterans Parkway Bridge Approaches Investigation Savannah, Georgia July 20, 2015 Terracon Project No. ES155020 Prepared for: Chatham County Engineering Department Savannah, Georgia

More information

Field Exploration. March 31, J-U-B ENGINEERS, Inc. 115 Northstar Avenue Twin Falls, Idaho Attn: Mr. Tracy Ahrens, P. E. E:

Field Exploration. March 31, J-U-B ENGINEERS, Inc. 115 Northstar Avenue Twin Falls, Idaho Attn: Mr. Tracy Ahrens, P. E. E: March 31, 201 11 Northstar Avenue 83301 Attn: Mr. Tracy Ahrens, P. E. E: taa@jub.com Re: Geotechnical Data Report Preliminary Phase 1 Field Exploration Revision No. 1 Proposed Rapid Infiltration Basin

More information

Table of Contents. Description

Table of Contents. Description Table of Contents Description Page A. Introduction... 1 A.1. Project Description... 1 A.2. Site Conditions and History... 2 A.3. Purpose... 3 A.4. Background Information and Reference Documents... 4 A.5.

More information

Soil Mechanics Brief Review. Presented by: Gary L. Seider, P.E.

Soil Mechanics Brief Review. Presented by: Gary L. Seider, P.E. Soil Mechanics Brief Review Presented by: Gary L. Seider, P.E. 1 BASIC ROCK TYPES Igneous Rock (e.g. granite, basalt) Rock formed in place by cooling from magma Generally very stiff/strong and often abrasive

More information

REPORT OF PRELIMINARY GEOTECHNICAL EXPLORATION. Marion County Industrial Park Lot 4. Marion County, South Carolina S&ME Project No.

REPORT OF PRELIMINARY GEOTECHNICAL EXPLORATION. Marion County Industrial Park Lot 4. Marion County, South Carolina S&ME Project No. REPORT OF PRELIMINARY GEOTECHNICAL EXPLORATION Marion County Industrial Park Lot 4 Marion County, South Carolina S&ME Project No. 1633-12-332 Prepared By: 133 Highway 1 Business Conway, South Carolina

More information

General. DATE December 10, 2013 PROJECT No TO Mary Jarvis Urbandale/Riverside South Development Corporation

General. DATE December 10, 2013 PROJECT No TO Mary Jarvis Urbandale/Riverside South Development Corporation DATE December 10, 201 PROJECT No. 10-1121-0260- TO Mary Jarvis Urbandale/Riverside South Development Corporation CC Justin Robitaille, Urbandale Jonathan Párraga, J.L. Richards & Associates Limited FROM

More information

Soils. Technical English - I 10 th week

Soils. Technical English - I 10 th week Technical English - I 10 th week Soils Soil Mechanics is defined as the branch of engineering science which enables an engineer to know theoretically or experimentally the behavior of soil under the action

More information

Geotechnical Investigation Juneau Seawalk - Taku Fisheries to Miner s Wharf Juneau, Alaska DM&A Job No

Geotechnical Investigation Juneau Seawalk - Taku Fisheries to Miner s Wharf Juneau, Alaska DM&A Job No Duane Miller & Associates 5821 Arctic Boulevard, Suite A Anchorage, AK 99518-1654 (907) 644-3200 Fax 644-0507 Arctic & Geotechnical Engineering May 4, 2006 Tetra Tech/KCM, Inc. 1971 First Avenue Seattle,

More information

Preliminary Geotechnical Investigation Cadiz / Trigg County I-24 Business Park. Cadiz, Kentucky

Preliminary Geotechnical Investigation Cadiz / Trigg County I-24 Business Park. Cadiz, Kentucky Environmental & Geoscience, LLC 834 Madisonville Road Hopkinsville, KY 440 70.44.000 FAX 70.44.8300 www.wedrill.com A member of Trinity Energy & Infrastructure Group, LLC Preliminary Geotechnical Investigation

More information

Appendix G GEOLOGICAL INVESTIGATION

Appendix G GEOLOGICAL INVESTIGATION Appendix G GEOLOGICAL INVESTIGATION JOB NUMBER: 3268.001 DATE: 10-14-13 BY: CC SITE 0 2000 1"=2000' VICINITY MAP CARGILL PARCEL HICKORY STREET AND ENTERPRISE DRIVE NEWARK, CALIFORNIA FOR

More information

Limited Geotechnical Engineering Evaluation Classroom Additions Albany County Campus Laramie, Wyoming

Limited Geotechnical Engineering Evaluation Classroom Additions Albany County Campus Laramie, Wyoming Limited Geotechnical Engineering Evaluation Classroom Additions Albany County Campus 2300 Missile Drive, Cheyenne, Wyoming 82001 Phone 307-635-0222 www.stratageotech.com Limited Geotechnical Engineering

More information

APPENDIX F CORRELATION EQUATIONS. F 1 In-Situ Tests

APPENDIX F CORRELATION EQUATIONS. F 1 In-Situ Tests APPENDIX F 1 APPENDIX F CORRELATION EQUATIONS F 1 In-Situ Tests 1. SPT (1) Sand (Hatanaka and Uchida, 1996), = effective vertical stress = effective friction angle = atmosphere pressure (Shmertmann, 1975)

More information

PRELIMINARY GEOTECHNICAL ENGINEERING REPORT. Proposed Re-Development 44 Old Worcester Road Charlton, Massachusetts. Prepared For:

PRELIMINARY GEOTECHNICAL ENGINEERING REPORT. Proposed Re-Development 44 Old Worcester Road Charlton, Massachusetts. Prepared For: PRELIMINARY GEOTECHNICAL ENGINEERING REPORT Proposed Re-Development 44 Old Worcester Road Charlton, Massachusetts Prepared For: Meridian Associates, Inc. 500 Cummings Center, Suite 5950 Beverly, Massachusetts

More information

Liquefaction and Foundations

Liquefaction and Foundations Liquefaction and Foundations Amit Prashant Indian Institute of Technology Gandhinagar Short Course on Seismic Design of Reinforced Concrete Buildings 26 30 November, 2012 What is Liquefaction? Liquefaction

More information

Geotechnical Engineering Study, Conifer Senior High School Football Field Improvements, Conifer, Colorado

Geotechnical Engineering Study, Conifer Senior High School Football Field Improvements, Conifer, Colorado 2390 South Lipan Street Denver, CO 80223 phone: (303) 742-9700 fax: (303) 742-9666 email: kadenver@kumarusa.com www.kumarusa.com Office Locations: Denver (HQ), Colorado Springs, Fort Collins, and Frisco,

More information

REPORT OF PRELIMINARY GEOTECHNICAL EXPLORATION. Marion County Industrial Park. Marion County, South Carolina S&ME Project No.

REPORT OF PRELIMINARY GEOTECHNICAL EXPLORATION. Marion County Industrial Park. Marion County, South Carolina S&ME Project No. REPORT OF PRELIMINARY GEOTECHNICAL EXPLORATION Marion County Industrial Park Marion County, South Carolina S&ME Project No. 1633-12-186 Prepared By: 133 Highway 1 Business Conway, South Carolina 2926 August

More information

Geotechnical Engineering Report

Geotechnical Engineering Report Geotechnical Engineering Report Richland Creek Trunk Sewer Greenville, South Carolina March 31, 2014 Terracon Project No. 86145008 Prepared for: Renewable Water Resources Greenville, South Carolina Prepared

More information

ENGINEERING ASSOCIATES

ENGINEERING ASSOCIATES July 16, 211 Vista Design, Inc. 11634 Worcester Highway Showell, Maryland 21862 Attention: Reference: Dear Mr. Polk: Mr. Richard F. Polk, P.E. Geotechnical Engineering Report Charles County RFP No. 11-9

More information

IN SITU SPECIFIC GRAVITY VS GRAIN SIZE: A BETTER METHOD TO ESTIMATE NEW WORK DREDGING PRODUCTION

IN SITU SPECIFIC GRAVITY VS GRAIN SIZE: A BETTER METHOD TO ESTIMATE NEW WORK DREDGING PRODUCTION IN SITU SPECIFIC GRAVITY VS GRAIN SIZE: A BETTER METHOD TO ESTIMATE NEW WORK DREDGING PRODUCTION Nancy Case O Bourke, PE 1, Gregory L. Hartman, PE 2 and Paul Fuglevand, PE 3 ABSTRACT In-situ specific gravity

More information

Ardaman & Associates, Inc. Geotechnical, Environmental and Materials Consultants

Ardaman & Associates, Inc. Geotechnical, Environmental and Materials Consultants SUBSURFACE SOIL EXPLORATION DRAINAGE IMPROVEMENTS TO THE HENDRY COUNTY, FLORIDA Ardaman & Associates, Inc. Geotechnical, Environmental and Materials Consultants OFFICES Orlando, 88 S. Orange Avenue, Orlando,

More information

GEOTECHNICAL SITE CHARACTERIZATION

GEOTECHNICAL SITE CHARACTERIZATION GEOTECHNICAL SITE CHARACTERIZATION Neil Anderson, Ph.D. Professor of Geology and Geophysics Richard W. Stephenson, P.E., Ph.D. Professor of Civil, Architectural and Environmental Engineering University

More information

TP-1 N61E 0 DARK BROWN SANDY SILT (ML) stiff, wet with roots (Disturbed Surficial Soil) DEPTH (FEET) 5 REDDISH BROWN SANDSTONE intensely fractured, weak to friable, deeply weathered, tight (Franciscan

More information

Appendix A. Producer Statement Advisory Note

Appendix A. Producer Statement Advisory Note Appendix A Producer Statement Advisory Note Ref. No. 17095 26 May 2017 PRODUCER STATEMENT CONSTRUCTION REVIEW (PS4) IMPORTANT ADVISORY NOTE The Building Consent Authority (BCA) frequently requires Producer

More information

SOIL MECHANICS Assignment #5: Stresses in a Soil Mass.

SOIL MECHANICS Assignment #5: Stresses in a Soil Mass. Geotechnical Engineering Research Laboratory One University Avenue Lowell, Massachusetts 01854 Edward L. Hajduk, D.Eng, PE Lecturer PA105D Tel: (978) 934 2621 Fax: (978) 934 3052 e mail: Edward_Hajduk@uml.edu

More information

Reinforced Soil Structures Reinforced Soil Walls. Prof K. Rajagopal Department of Civil Engineering IIT Madras, Chennai

Reinforced Soil Structures Reinforced Soil Walls. Prof K. Rajagopal Department of Civil Engineering IIT Madras, Chennai Geosynthetics and Reinforced Soil Structures Reinforced Soil Walls continued Prof K. Rajagopal Department of Civil Engineering IIT Madras, Chennai e-mail: gopalkr@iitm.ac.inac in Outline of the Lecture

More information

patersongroup Design for Earthquakes Consulting Engineers May 19, 2016 File: PG3733-LET.01

patersongroup Design for Earthquakes Consulting Engineers May 19, 2016 File: PG3733-LET.01 patersongroup May 19, 2016 File: PG3733-LET.01 Hydro Ottawa Limited c/o Cresa Toronto 170 University Avenue, Suite 1 Toronto, Ontario M5H 3B3 Attention: Ms. Barbara Wright Consulting Engineers 154 Colonnade

More information

Geotechnical Data Report

Geotechnical Data Report Geotechnical Data Report ReWa Solar Farm at Durbin Creek Fountain Inn, South Carolina September 1, 2017 Terracon Project No. 86165043 Prepared for: Renewable Water Resources Greenville, South Carolina

More information

Geotechnical Engineering Report

Geotechnical Engineering Report Geotechnical Engineering Report Single-Span Bridge North Western Road & Hall of Fame Avenue August 25, 2015 Terracon Project No. 03155156 Prepared for: Olsson Associates Prepared by: Terracon Consultants,

More information

Gotechnical Investigations and Sampling

Gotechnical Investigations and Sampling Gotechnical Investigations and Sampling Amit Prashant Indian Institute of Technology Gandhinagar Short Course on Geotechnical Investigations for Structural Engineering 12 14 October, 2017 1 Purpose of

More information

Town of Amenia Dutchess County New York

Town of Amenia Dutchess County New York Appendix 9.14.2 Preliminary Geotechnical Investigation 2/2007 Preliminary Geotechnical Interpretive Report for Silo Ridge Golf Resort Community Town of Amenia Dutchess County New York February 16, 2007

More information

Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay 13 Permeability and Seepage -2 Conditions favourable for the formation quick sand Quick sand is not a type of sand but a flow condition occurring within a cohesion-less soil when its effective stress is

More information

Design of RC Retaining Walls

Design of RC Retaining Walls Lecture - 09 Design of RC Retaining Walls By: Prof Dr. Qaisar Ali Civil Engineering Department UET Peshawar www.drqaisarali.com 1 Topics Retaining Walls Terms Related to Retaining Walls Types of Retaining

More information

Geotechnical Subsurface Exploration and Laboratory Testing Data Report

Geotechnical Subsurface Exploration and Laboratory Testing Data Report Geotechnical Subsurface Exploration and Laboratory Testing Data Report 2016 1A Emergency Bridge Replacement Package SCDOT PIN P031819 S 19 (Highway 19 East) Bridge over Bug Swamp Horry County, South Carolina

More information

KDOT Geotechnical Manual Edition. Table of Contents

KDOT Geotechnical Manual Edition. Table of Contents KDOT Geotechnical Manual 2007 Edition The KDOT Geotechnical Manual is available two volumes. Both volumes are very large electronic (pdf) files which may take several minutes to download. The table of

More information

The CPT in unsaturated soils

The CPT in unsaturated soils The CPT in unsaturated soils Associate Professor Adrian Russell (UNSW) Mr David Reid (Golder Associates) Prof Nasser Khalili (UNSW) Dr Mohammad Pournaghiazar (UNSW) Dr Hongwei Yang (Uni of Hong Kong) Outline

More information

ABSTRACT. Use and Application of Piezocone Penetration Testing in Presumpscot Formation

ABSTRACT. Use and Application of Piezocone Penetration Testing in Presumpscot Formation ABSTRACT Use and Application of Piezocone Penetration Testing in Presumpscot Formation Presumpscot Formation is commonly referred to as glacial marine clay found along the coastline of eastern New England.

More information

FOUNDATION ANALYSIS AND DESIGN REPORT. Mark Bishop, PE, Kimley-Hom and Associates, Inc. Jeffery K. Voyen, PE, American Engineering Testing, Inc.

FOUNDATION ANALYSIS AND DESIGN REPORT. Mark Bishop, PE, Kimley-Hom and Associates, Inc. Jeffery K. Voyen, PE, American Engineering Testing, Inc. FOUNDATION ANALYSIS AND DESIGN REPORT TO: FROM: Mark Bishop, PE, Kimley-Hom and Associates, Inc. Jeffery K. Voyen, PE, American Engineering Testing, Inc. DATE: June 25, 2014 SUBJECT: LRT Bridge over Excelsior

More information

CITY OF VALDEZ Project Title: East Pioneer Reconstruction Project No.: Contract No.: TO: All Recipients Date: April 14, 2014

CITY OF VALDEZ Project Title: East Pioneer Reconstruction Project No.: Contract No.: TO: All Recipients Date: April 14, 2014 CITY OF VALDEZ Project Title: East Pioneer Reconstruction Project No.: 13-3-1.32 Contract No.: 11 TO: All Recipients Date: April 14, 214 SUBJECT: Addendum No.1 This seventeen (17) page Addendum forms a

More information

Soil type identification and fines content estimation using the Screw Driving Sounding (SDS) data

Soil type identification and fines content estimation using the Screw Driving Sounding (SDS) data Mirjafari, S.Y. & Orense, R.P. & Suemasa, N. () Proc. th NZGS Geotechnical Symposium. Eds. GJ Alexander & CY Chin, Napier Soil type identification and fines content estimation using the Screw Driving Sounding

More information

pcf REQUIRED: Determine the shear strength parameters for use in a preliminary shallow foundation design. SOLUTION:

pcf REQUIRED: Determine the shear strength parameters for use in a preliminary shallow foundation design. SOLUTION: 14.330 SOIL MECHANICS Assignment #8: Shear Strength Solution. PROBLEM #1: GIVEN: A regional residential building contractor is planning on building a custom 4,100 ft² home on Martha s Vineyard, MA. The

More information

(C) Global Journal of Engineering Science and Research Management

(C) Global Journal of Engineering Science and Research Management GEOTECHNCIAL ASSESSMENT OF PART OF PORT HARCOURT, NIGER DELTA FOR STRUCTURAL ANALYSIS Warmate Tamunonengiyeofori Geostrat International Services Limited, www.geostratinternational.com. *Correspondence

More information

June 9, R. D. Cook, P.Eng. Soils Engineer Special Services Western Region PUBLIC WORKS CANADA WESTERN REGION REPORT ON

June 9, R. D. Cook, P.Eng. Soils Engineer Special Services Western Region PUBLIC WORKS CANADA WESTERN REGION REPORT ON PUBLIC WORKS CANADA WESTERN REGION REPORT ON GEOTECHNICAL INVESTIGATION PROPOSED MARTIN RIVER BRIDGE MILE 306.7 MACKENZIE HIGHWAY Submitted by : R. D. Cook, P.Eng. Soils Engineer Special Services Western

More information

Chapter 7 GEOMECHANICS

Chapter 7 GEOMECHANICS Chapter 7 Final SCDOT GEOTECHNICAL DESIGN MANUAL August 2008 Table of Contents Section Page 7.1 Introduction...7-1 7.2 Geotechnical Design Approach...7-1 7.3 Geotechnical Engineering Quality Assurance...7-2

More information

PLATE 6 FEB G r o v e l a n d F l o o d w a l l - B o r e h o l e M a p. Legend. Groveland Floodwall Boreholes. Contour Lines.

PLATE 6 FEB G r o v e l a n d F l o o d w a l l - B o r e h o l e M a p. Legend. Groveland Floodwall Boreholes. Contour Lines. 611 6 Defau FALS conto Conto DPLV lt Eurs20 01_to 3po Defau FALS conto Conto DPLV lt Eurs20 01_to 4po 612 Conto DPLV conto Defau FALS 01_to urs20 Elt po 5 Conto DPLV conto Defau FALS 01_to urs15 Elt po

More information

Class Principles of Foundation Engineering CEE430/530

Class Principles of Foundation Engineering CEE430/530 Class Principles of Foundation Engineering CEE430/530 1-1 General Information Lecturer: Scott A. Barnhill, P.E. Lecture Time: Thursday, 7:10 pm to 9:50 pm Classroom: Kaufmann, Room 224 Office Hour: I have

More information

NEW DOWN-HOLE PENETROMETER (DHP-CIGMAT) FOR CONSTRUCTION APPLICATIONS

NEW DOWN-HOLE PENETROMETER (DHP-CIGMAT) FOR CONSTRUCTION APPLICATIONS NEW DOWN-HOLE PENETROMETER (DHP-CIGMAT) FOR CONSTRUCTION APPLICATIONS 1 2 C. Vipulanandan 1, Ph.D., M. ASCE and Omer F. Usluogullari 2 Chairman, Professor, Director of Center for Innovative Grouting Materials

More information

Date: April 2, 2014 Project No.: Prepared For: Mr. Adam Kates CLASSIC COMMUNITIES 1068 E. Meadow Circle Palo Alto, California 94303

Date: April 2, 2014 Project No.: Prepared For: Mr. Adam Kates CLASSIC COMMUNITIES 1068 E. Meadow Circle Palo Alto, California 94303 City of Newark - 36120 Ruschin Drive Project Draft Initial Study/Mitigated Negative Declaration Appendix C: Geologic Information FirstCarbon Solutions H:\Client (PN-JN)\4554\45540001\ISMND\45540001 36120

More information

Drilled Shaft Foundations in Limestone. Dan Brown, P.E., Ph.D. Dan Brown and Associates

Drilled Shaft Foundations in Limestone. Dan Brown, P.E., Ph.D. Dan Brown and Associates Drilled Shaft Foundations in Limestone Dan Brown, P.E., Ph.D. Dan Brown and Associates Foundation Engineering How we teach our students Fundamental understanding of soil and rock behavior (good!) Focus

More information

December 5, Junction Gateway, LLC 7551 W. Sunset Boulevard #203 Los Angeles, CA Mr. James Frost P: Dear Mr.

December 5, Junction Gateway, LLC 7551 W. Sunset Boulevard #203 Los Angeles, CA Mr. James Frost P: Dear Mr. December 5, 2014 Junction Gateway, LLC 7551 W. Sunset Boulevard #203 90046 Attn: Re: Mr. James Frost P: 323.883.1800 Geotechnical Update Letter Sunset & Effie Mixed Use Development 4301 to 4311 Sunset

More information

M E M O R A N D U M. Mr. Jonathan K. Thrasher, P.E., Mr. Ian Kinnear, P.E. (FL) PSI

M E M O R A N D U M. Mr. Jonathan K. Thrasher, P.E., Mr. Ian Kinnear, P.E. (FL) PSI M E M O R A N D U M TO: FROM: Mr. Mark Schilling Gulf Interstate Engineering Mr. Jonathan K. Thrasher, P.E., Mr. Ian Kinnear, P.E. (FL) PSI DATE: November 11, 2014 RE: Summary of Findings Geotechnical

More information

SOIL MECHANICS AND APPLIED FOUNDATION ENGINEERING FUNDAMENTAL FACTS OF SOIL BEHAVIOR

SOIL MECHANICS AND APPLIED FOUNDATION ENGINEERING FUNDAMENTAL FACTS OF SOIL BEHAVIOR SOIL MECHANICS AND APPLIED FOUNDATION ENGINEERING The Subsurface is Unknown to many and Blind Guesswork cannot be used to Determine the Character and Behavior of the Underlying Soil Conditions. FUNDAMENTAL

More information

Terraprobe Consulting Geotechnical & Environmental Engineering Construction Materials Inspection & Testing

Terraprobe Consulting Geotechnical & Environmental Engineering Construction Materials Inspection & Testing Terraprobe Consulting Geotechnical & Environmental Engineering Construction Materials Inspection & Testing GEOTECHNICAL INVESTIGATION BLOCKS TO PIER HAMILTON, ONTARIO PREPARED FOR: City of Hamilton Waterfront

More information

SUBSURFACE EXPLORATION REPORT FOR THE MARITIME INFRACTURE REHABILITATION AT WHISKEY ISLAND BULK TERMINAL CLEVELAND, OHIO PGI PROJECT NO.

SUBSURFACE EXPLORATION REPORT FOR THE MARITIME INFRACTURE REHABILITATION AT WHISKEY ISLAND BULK TERMINAL CLEVELAND, OHIO PGI PROJECT NO. SUBSURFACE EXPLORATION REPORT FOR THE MARITIME INFRACTURE REHABILITATION AT WHISKEY ISLAND BULK TERMINAL CLEVELAND, OHIO PGI PROJECT NO. G1G PREPARED FOR KS ASSOCIATES, INC. PREPARED BY PRO GEOTECH, INC.

More information