Analysis and Comparison of Risk and Load Point Indices of Power System Model HLI and HLII

Size: px
Start display at page:

Download "Analysis and Comparison of Risk and Load Point Indices of Power System Model HLI and HLII"

Transcription

1 Analysis and Comparison of Risk and Load Point Indices of Power System Model HLI and HLII L.B. Rana and N.Karki Abstract Aim of this work is to evaluate risk analysis of the Electrical Power Network with Discrete generation, load Model and transmission line constraints. The system under considered is analyzed using conditional probability approach and discrete Markov model. The generation load model and transmission model are convolved to form the appropriate risk model. Load point indices LOLP, LOLE, Expected Energy Not served EENS or Loss of Energy Expectation are computed with and without transmission facilities constraints. Also effect of transmission capacity and peak load are investigated. The basic generation model is capacity outage probability table(copt) and load model is daily peak load variation curve (DPLVC) or hourly variation of load (LDC).The calculated indices do not normally include transmission constraints. Basic modeling approach for HLI is shown in Fig.No.2. Keywords LOLP, LOLE EENS HLI and HLII S I. INTRODUCTION INCE the modern power system is composed by three subsystems Generation, Transmission and Distribution. Reliability and risk evaluation of the whole network is complex so it is divided in different hierarchical levels (HL) as shown in Fig.No.1. The concept of hierarchical levels (HL) has been developed in order to establish a consistent means of identifying and grouping these functional zones [1]. HLI represents generation and Load Model only. Whereas HLII includes transmission facilities also. And HLIII represents whole network. In this analysis first of all HLI is only considered. The generation and load models are convolved to compute probabilistic risks and adequacy indices [1]. Fig..2 Modeling approach for HLI [1] Then transmissions facilities constrain are imposed to form HLII. Then conditional probability approach is implied to get load point or delivery point indices seen by each individual network node. Scheme for calculation of reliability indices for HLII is shown in flow chart of Fig.3. The system is initializing with initial outage and line flow limit is imposed. Fig. 1 HL of Electrical Power Network [1] Lalit. Rana is PhD Scholar in Lappeernrata University of Technology, Lappeenranata Finland. rana.lalit@gmail.com N.Karki is Lecturer in Electrical Engineering Department, Institute of Engineering Thribhuvan University Nepal Fig. 3 Scheme for Reliability indices Computation 83

2 If there is no line flow limit then generation is reschedule and again same line flow limit is imposed to obtain the minimum load point power curtailment, otherwise it gives reliability index of load point without rescheduling. The steady state value of the availability and unavailability for any system is obtained from equation (1) when time approaches to infinity. μ λ -(λ + µ)t Availability, A(t) = + e (1.a) λ + μ λ + μ λ λ -(λ + µ)t Unavailability, U(t) = + e (1.b) λ + μ λ + μ μ λ Hence Availability, A= Unavailability, U= λ + μ λ + μ Also the when the system fulfill requirements needed for binominal distribution i.e. trails are independent and probability of failure and success for each trail are constant can be applied.generalized expression is given in equation (2). (p + q) n = p n + n p n-1 n(n 1) q + p n-2 q 2 n(n 1)(n - 2) + 2! 3! p n-3 q 3 n(n 1)..[n - (r -1)] p n-r q r +. + r! q n..(2) n(n 1)..[n - (r -1)] n! Where p n-r q r = = ncr r! r!(n - r)! II. LOAD POINT INDICES Departure Rate is defined as the rate by which system n departed from state j to all other states ν = a kj k = 1, j Frequency of occurrence/ annum is defined as summation of the product of departure rate from j state to all other state and probability of system being in state j. Frequency of n occurrence/ annum f = P * a j kj k = 1, j Loss of load probability (LOLP) is defined as the probability of the generating capacity is less than daily peak load over a space of time usually one year n LOLP = P( C ). P( L > C ) i i i i = 1, Where P (Ci) is individual probability of the state i which is obtained from the capacity outage probability table. Where P(Li>Ci) is percentage of time for which outage capacity will cause loss of loads The Loss of Load Expectance (LOLE) is risk index and the most widely accepted and used probabilistic method in system reliability evaluation for generating systems. Two models are required and employed. One is the previously 84 studied Load Duration Curve (LDC), and the other is the COPT. These two models are convolved in the process. The units of the LOLE are in days per year (d/y). The LOLE evaluation method is expressed in the following mathematical formula. LOLE = P. t. Hence LOLE is k k. defined as summation of the product of probability of outage and the percentage of time that cause load loss Expected Energy Not supplied (EENS) or Loss of Energy Expectance (LOEE), EENS or LOEE in load point in per unit is computed t j P D j j j 100 EENS = where. D = L. dt., and, D = ( L C ). dt D j j 0 0 Where Dj is energy curtailed due to capacity outage Qk, Pj is probability of capacity outage Qk. Where D is total energy under load curve.eens is computed from DLPVC as shown in Fig.4 shaded area represents EENS. III. SYSTEM DESCRIPTION The single line diagram of the system under consideration is shown Fig. 5. It consist six generators of equal capacity connected in common bus, two parallel transmission line and load model. TABLE I SYSTEM DATA [1] Generator data 6 x 40 MW units λ=0.01 f/day = 3.65 f/yr µ = 0.49 r/day = r/yr Dj Load Capacity outage 27.77% ti % % of Time Fig. 4 DLPVC Transmission elements Individual line-cap. =160 MW 2 lines λ= 0.5 f/yr r=7.5 hours/repair Load Peak load = 180MW load-duration curve varies from the 100% to the 60% Load (MW) %of Time Generating System Transmission System Daily Load Curve Fig. 5 System considered P0 240 P1 200 P Max 180 P2 160 P3 120 P4 80

3 IV. MODEL FOR STATISTICAL ANALYSIS 4.1. Generation Model The Discrete Markov model for the system is developed as shown in Fig.6 assuming there is no common cause failure and all failure is independent. Also repair actions are carried out independent of each other (i.e. maintenance crew is thus not a limiting factor). The system consist seven dependent equations hence the steady state probability of system being in any state can be obtained from any of six dependent and another equation i.e. is sum of probabilities of being all possible states is equal to 1 [1-2]. Hence limiting state probability of the generating station computed from equation (1) of appendix I which is illustrated in Table II. TABLE II STEADY STATE PROBABILITY OF THE GENERATION SYSTEM P0 P1 P2 P P4 P5 P All Six Up 4.2. Transmission Line Model For this analysis two parallel TL is considered each of capacity 160MW. Failure rate and repair rate of TL is shown in table I. Fig.No.7 represents Discrete Markov model of TL. The steady state Markov Model of TL comprises three dependent equations and solved by considering another equation which gives sum of being any states is equal to unity [1-2] as shown in Appendix I. Both Up 2λt µt 6λ µ One Up 5 Up 1DN Fig. 6 Generation Markov Model Since the Generation and the transmission outage are independent and no common cause failure, so the two independent models is merged and load model is imposed to obtain load point indices. λt 2µt Fig. 7 TL Markov Model λ 6µ All Six down Both down Probability of failure failure k K V. ANALYSIS Q = P. P and Frequency of k F = F. P, Where, P I, F and P K are Outage condition of the Network, Probability of existence of outage, Frequency of occurrence of outage and probability of the load at bus exceeding the I K maximum load that can be supplied at that bus during the outage respectively Expected number of load curtailments n =. F x Where j belongs to number of states which includes all contingencies resulting in line overloads which are alleviated by load curtailment at bus K. Expected load curtailed= F. x = L Where L is the load not supplied at an load point due all contingencies to alleviate overloading and F is state frequency Expected Load Curtailed = Load Curtailed x frequency by which that amount of load is curtailed. Expected energy not supplied EENS = F. L D x Where Dj is duration in hours of the load curtailment arising due to the outage j. EENS = ELL x hours associated to that ELL 5.1 Load Point Indices with and without TL The system is analyzed with and without transmission line is computed and result are compared and illustrated in Table IV and Fig.No.8. It is observed that system indices are affected with TL constraints and performance becomes poorer. Here eighteen possible states are obtained after merging two models. Indices for each state are computed as below. Let consider the system is in state 2 i.e. All Generators are functioning and but only one line is functioning capacity Available = 160 MW State Probability =Probability of all Gen. functioning x Probability of one TL functioning Total frequency occurrence per year =Prob. of being that state x depart rate from the state = P(0G1L)x(6λ+λt+µt) Similarly state probability and frequency per annum is computed and listed in table P kj = probability of load at bus K exceeding the maximum load that can be supplied at that bus without failure. It s computed as shown For state 2 when capacity available is 160 MW 85

4 P = = k =,Failure Probability = x0.2777= and Failure Frequency = x0.2777= The result for all possible states without and with TL are shown Appendix II and III TABLE.III TRANSMISSION LINE OUTAGE Outage TLin Prob Depart Rate Freq. Occ/year 0 2X 0, , X 0, ,5 1, ,89E , MW. The results are presented in Table VI and Fig.No 10. TABLE V INDICES WITH DIFFERENT TL CAPACITY Indices TL of 170MW T.L of 160 MW TL of 150 MW Failure Probability days per year Failure Fequency EENS(MWhr) per Year Expected Load Curtailed MW TABLE IV LOAD POINT INDICES WITH AND WITHOUT TL Indices Failure Probability days per year Failure Fequency EENS(MWhr) per Year Expected Load Curtailed (MW) Without TL constraints With T.L constraints Fig. 9 Indices with different TL Capacity TABLE VI Fig. 8 Indices with and without TL 5.2. Load Point Indices with different TL capacity Here two cases are considered one is when Transmission Capacity is increased to 170 MW and other is decreased to 150 MW. The Results are compared in Table V and Fig. No Indices for Different System Peak To perform this analysis transmission capacity per line is considered as 160MW and the Load Model is also constant ie Linear variation from 100% to 60%,only the Peak varies. Here again two situations are considered one is Peak load increased to 200MW and other is decreased to INDICES WITH DIFFERENT PEAK Indices 200MW Peak 180 MW Peak 160 MW Peak Failure Probability days per year Failure Frequency EENS(MWhr) per Year Expected Load Curtailed CONCLUSION Fig. 10 Indices with different System Peak 86

5 It is observed that the risk will be more when the TL constraints will imposed and it will be increased with increase the value of peak load of system.also it will affected the Transmission line capacity for the given load model i.e. decreases with increases the TL capacity for given load model and same failure and repair rate.also it is further influenced from the size of the generators. REFERENCE [1] Reliability Evaluation of Power Systems Second Edition by Roy Billinton University of Saskatchewan College of Engineering Saskatoon, Saskatchewan, Canada and Ronald N. Allan University of Manchester Institute of Science and Technology Manchester, England [2] System Reliability Theory: Models, Statistical Methods, and Applications, Second Edition by Marvin Rausand and Arnljot Høyland [3] Introduction to Reliability Engineering Second edition by E. E. Lewis Department of Mechanical Engineering, Northwestern University, Euanston, Illinois uiy, 1994 Appendix I Steady state Equation for the Generation Steady state Equation for the Transmission Appendix II Pin A 0.98 U 0.02 F R Indi. Cum Dept % Load En Pout Prob Prob Rate F/year time LOLP Curt Curt E E E E E E E E E-05 LOLE ELL

6 Appendix III Cond. Cap (Avai) State State Probabilities and Frequencies and other indices Failure Prob. Frequency Pij Prob Freq Hrs Outage Load Curt ELL EENS 0G0L G1L G2L E E G0L G1L E E G2L E E E E G0L G1L E E G2L E E E E E E-05 3G0L G1L E E G2L E E E E E E-05 4G0L E E G1L E E E E G2L E E E E E E-07 5G0L E E E E G1L E E E E E-06 2E-05 5G2L E E E E E E-09 6G0L E E E E E G1L E E E E E E-08 6G2L E E E E E E

A PROBABILISTIC MODEL FOR POWER GENERATION ADEQUACY EVALUATION

A PROBABILISTIC MODEL FOR POWER GENERATION ADEQUACY EVALUATION A PROBABILISTIC MODEL FOR POWER GENERATION ADEQUACY EVALUATION CIPRIAN NEMEŞ, FLORIN MUNTEANU Key words: Power generating system, Interference model, Monte Carlo simulation. The basic function of a modern

More information

Chapter 2. Planning Criteria. Turaj Amraee. Fall 2012 K.N.Toosi University of Technology

Chapter 2. Planning Criteria. Turaj Amraee. Fall 2012 K.N.Toosi University of Technology Chapter 2 Planning Criteria By Turaj Amraee Fall 2012 K.N.Toosi University of Technology Outline 1- Introduction 2- System Adequacy and Security 3- Planning Purposes 4- Planning Standards 5- Reliability

More information

Power System Research Group Electrical Engineering Dept., University of Saskatchewan Saskatoon, Canada

Power System Research Group Electrical Engineering Dept., University of Saskatchewan Saskatoon, Canada Abstract Failure Bunching Phenomena in Electric Power Transmission Systems Roy Billinton Gagan Singh Janak Acharya Power System Research Group Electrical Engineering Dept., University of Saskatchewan Saskatoon,

More information

EVALUATION OF WIND ENERGY SOURCES INFLUENCE ON COMPOSITE GENERATION AND TRANSMISSION SYSTEMS RELIABILITY

EVALUATION OF WIND ENERGY SOURCES INFLUENCE ON COMPOSITE GENERATION AND TRANSMISSION SYSTEMS RELIABILITY EVALUATION OF WIND ENERGY SOURCES INFLUENCE ON COMPOSITE GENERATION AND TRANSMISSION SYSTEMS RELIABILITY Carmen Lucia Tancredo Borges João Paulo Galvão carmen@dee.ufrj.br joaopaulo@mercados.com.br Federal

More information

The annual peak load for the test system is 2850 MW. Table A1.1 gives data on weekly peak loads in percent

The annual peak load for the test system is 2850 MW. Table A1.1 gives data on weekly peak loads in percent APPENDIX 1 IEEE RELIABILITY TEST SYSTEM INTRODUCTION The IEEE Reliability Test System (RTS) was developed in order to provide a common test system which could be used for comparing the results obtained

More information

2 Theory. 2.1 State Space Representation S 2 S 1 S 3

2 Theory. 2.1 State Space Representation S 2 S 1 S 3 In the following sections we develop the theory, illustrate the technique by applying it to a sample system, and validate the results using the method of enumeration. Notations: A-state functional (acceptable)

More information

RTO Winter Resource Adequacy Assessment Status Report

RTO Winter Resource Adequacy Assessment Status Report RTO Winter Resource Adequacy Assessment Status Report RAAS 03/31/2017 Background Analysis performed in response to Winter Season Resource Adequacy and Capacity Requirements problem statement. Per CP rules,

More information

A possible notion of short-term value-based reliability

A possible notion of short-term value-based reliability Energy Laboratory MIT EL 1-13 WP Massachusetts Institute of Technology A possible notion of short-term value-based reliability August 21 A possible notion of short-term value-based reliability Yong TYoon,

More information

RELIABILITY MODELING AND EVALUATION IN AGING POWER SYSTEMS. A Thesis HAG-KWEN KIM

RELIABILITY MODELING AND EVALUATION IN AGING POWER SYSTEMS. A Thesis HAG-KWEN KIM RELIABILITY MODELING AND EVALUATION IN AGING POWER SYSTEMS A Thesis by HAG-KWEN KIM Submitted to the Office of Graduate Studies of Texas A&M University in partial fulfillment of the requirements for the

More information

Probabilistic production cost simulation. EG2200 Lectures 12 14, autumn 2015 Mikael Amelin

Probabilistic production cost simulation. EG2200 Lectures 12 14, autumn 2015 Mikael Amelin Probabilistic production cost simulation EG2200 Lectures 12 14, autumn 2015 Mikael Amelin 1 Course objectives Apply probabilistic production cost simulation to calculate the expected operation cost and

More information

Research on the Effect of Substation Main Wiring on the Power System Reliability Yuxin Zhao 1, a, Tao Liu 2,b and Yanxin Shi 3,c

Research on the Effect of Substation Main Wiring on the Power System Reliability Yuxin Zhao 1, a, Tao Liu 2,b and Yanxin Shi 3,c International Power, Electronics and aterials Engineering Conference (IPEEC 2015) esearch on the Effect of ubstation ain Wiring on the Power ystem eliability Yuxin Zhao 1, a, Tao Liu 2,b and Yanxin hi

More information

Net Export Rule 1 : Deriving the generation value of storage device G(t)

Net Export Rule 1 : Deriving the generation value of storage device G(t) Net Export Rule 1 : Deriving the generation value of storage device G(t) G(t) nx = n i=1 G(i, t) min{0, N(i, t)} Where, i = 1,2, n location G(i, t) storage device generation metered output at location

More information

Mathematics - Course 121 THE BINOMIAL DISTRIBUTION AND POWER SYSTEM RELIABILITY

Mathematics - Course 121 THE BINOMIAL DISTRIBUTION AND POWER SYSTEM RELIABILITY Mathematics - Course 121 THE BINOMIAL DISTRIBUTION AND POWER SYSTEM RELIABILITY I THE BINOMIAL DISTRIBUTION Recall (from 121.00-3) that the number of different combinations of r objects which can be formed

More information

Composite System Reliability Evaluation using State Space Pruning

Composite System Reliability Evaluation using State Space Pruning Composite System Reliability Evaluation using State Space Pruning C. Singh, Fellow, IEEE J. Mitra, Student Member, IEEE Department of Electrical Engineering Texas A & M University College Station, Texas

More information

EE 445 / 850: Final Examination

EE 445 / 850: Final Examination EE 445 / 850: Final Examination Date and Time: 3 Dec 0, PM Room: HLTH B6 Exam Duration: 3 hours One formula sheet permitted. - Covers chapters - 5 problems each carrying 0 marks - Must show all calculations

More information

ADEQUACY ASSESSMENT IN POWER SYSTEMS USING GENETIC ALGORITHM AND DYNAMIC PROGRAMMING. A Thesis DONGBO ZHAO

ADEQUACY ASSESSMENT IN POWER SYSTEMS USING GENETIC ALGORITHM AND DYNAMIC PROGRAMMING. A Thesis DONGBO ZHAO ADEQUACY ASSESSMENT IN POWER SYSTEMS USING GENETIC ALGORITHM AND DYNAMIC PROGRAMMING A Thesis by DONGBO ZHAO Submitted to the Office of Graduate Studies of Texas A&M University in partial fulfillment of

More information

Reliability Evaluation of Engineering Systems:

Reliability Evaluation of Engineering Systems: Reliability Evaluation of Engineering Systems: Concepts and Techniques Roy Billinton PhD, DSc, FEIC, FRSC, FIEEE, PE c. J. MacKenzie Professor of Electrical Engineering University of Saskatchewan and Ronald

More information

Prediction of Power System Balancing Requirements and Tail Events

Prediction of Power System Balancing Requirements and Tail Events Prediction of Power System Balancing Requirements and Tail Events PNNL: Shuai Lu, Yuri Makarov, Alan Brothers, Craig McKinstry, Shuangshuang Jin BPA: John Pease INFORMS Annual Meeting 2012 Phoenix, AZ

More information

Winter Season Resource Adequacy Analysis Status Report

Winter Season Resource Adequacy Analysis Status Report Winter Season Resource Adequacy Analysis Status Report Tom Falin Director Resource Adequacy Planning Markets & Reliability Committee October 26, 2017 Winter Risk Winter Season Resource Adequacy and Capacity

More information

Module 4-2 Methods of Quantitative Reliability Analysis

Module 4-2 Methods of Quantitative Reliability Analysis Module 4-2 Methods of Quantitative Reliability Analysis Chanan Singh Texas A&M University METHODS OF QUANTITATIVE RELIABILITY ANALYSIS ANALYTICAL METHODS - STATE SPACE USING MARKOV PROCESSES - NETWORK

More information

Monte Carlo Simulation for Reliability Analysis of Emergency and Standby Power Systems

Monte Carlo Simulation for Reliability Analysis of Emergency and Standby Power Systems Monte Carlo Simulation for Reliability Analysis of Emergency and Standby Power Systems Chanan Singh, Fellow, IEEE Joydeep Mitra, Student Member, IEEE Department of Electrical Engineering Texas A & M University

More information

Cyber Physical Power Systems Power in Communications

Cyber Physical Power Systems Power in Communications 1 Cyber Physical Power Systems Power in Communications Information and Communications Tech. Power Supply 2 ICT systems represent a noticeable (about 5 % of total t demand d in U.S.) fast increasing load.

More information

A Unified Framework for Defining and Measuring Flexibility in Power System

A Unified Framework for Defining and Measuring Flexibility in Power System J A N 1 1, 2 0 1 6, A Unified Framework for Defining and Measuring Flexibility in Power System Optimization and Equilibrium in Energy Economics Workshop Jinye Zhao, Tongxin Zheng, Eugene Litvinov Outline

More information

Note. Design via State Space

Note. Design via State Space Note Design via State Space Reference: Norman S. Nise, Sections 3.5, 3.6, 7.8, 12.1, 12.2, and 12.8 of Control Systems Engineering, 7 th Edition, John Wiley & Sons, INC., 2014 Department of Mechanical

More information

9. Reliability theory

9. Reliability theory Material based on original slides by Tuomas Tirronen ELEC-C720 Modeling and analysis of communication networks Contents Introduction Structural system models Reliability of structures of independent repairable

More information

Power System Security. S. Chakrabarti

Power System Security. S. Chakrabarti Power System Security S. Chakrabarti Outline Introduction Major components of security assessment On-line security assessment Tools for contingency analysis DC power flow Linear sensitivity factors Line

More information

Chapter 9 Part II Maintainability

Chapter 9 Part II Maintainability Chapter 9 Part II Maintainability 9.4 System Repair Time 9.5 Reliability Under Preventive Maintenance 9.6 State-Dependent Systems with Repair C. Ebeling, Intro to Reliability & Maintainability Chapter

More information

Reliability Modeling of Dynamic Thermal Rating

Reliability Modeling of Dynamic Thermal Rating 1 Reliability Modeling of Dynamic Thermal Rating Hamid Shaker, Student Member, IEEE, Hamidreza Zareipour, Senior Member, IEEE, and Mahmud Fotuhi-Firuzabad, Senior Member, IEEE Abstract In this paper, a

More information

A Model for a Zonal Operating Reserve Demand Curve

A Model for a Zonal Operating Reserve Demand Curve A Model for a Zonal Operating Reserve Demand Curve Yen-Yu Lee Electrical and Computer Engineering University of Texas at Austin March 5, Outline What is operating reserves? Why do we need elastic reserves

More information

Module 6 : Preventive, Emergency and Restorative Control. Lecture 27 : Normal and Alert State in a Power System. Objectives

Module 6 : Preventive, Emergency and Restorative Control. Lecture 27 : Normal and Alert State in a Power System. Objectives Module 6 : Preventive, Emergency and Restorative Control Lecture 27 : Normal and Alert State in a Power System Objectives In this lecture you will learn the following Different states in a power system

More information

Module 7-2 Decomposition Approach

Module 7-2 Decomposition Approach Module 7-2 Decomposition Approach Chanan Singh Texas A&M University Decomposition Approach l Now we will describe a method of decomposing the state space into subsets for the purpose of calculating the

More information

Module PE.PAS.U19.5. U19.1 Introduction

Module PE.PAS.U19.5. U19.1 Introduction Module PE.PAS.U19.5 Generation adequacy evaluation 1 Module PE.PAS.U19.5 Generation adequacy evaluation U19.1 Introduction Probabilistic evaluation o generation adequacy is traditionally perormed or one

More information

SINGLE OBJECTIVE RISK- BASED TRANSMISSION EXPANSION

SINGLE OBJECTIVE RISK- BASED TRANSMISSION EXPANSION Vol.2, Issue.1, Jan-Feb 2012 pp-424-430 ISSN: 2249-6645 SINGLE OBJECTIVE RISK- BASED TRANSMISSION EXPANSION V.Sumadeepthi 1, K.Sarada 2 1 (Student, Department of Electrical and Electronics Engineering,

More information

Risk-Based Composite Power System Vulnerability Evaluation to Cascading Failures Using Importance Sampling

Risk-Based Composite Power System Vulnerability Evaluation to Cascading Failures Using Importance Sampling 1 Risk-Based Composite Power System Vulnerability Evaluation to Cascading Failures Using Importance Sampling Quan Chen, Student Member, IEEE and Lamine Mili, Senior Member, IEEE Abstract Large-scale blackouts

More information

An Integral Measure of Aging/Rejuvenation for Repairable and Non-repairable Systems

An Integral Measure of Aging/Rejuvenation for Repairable and Non-repairable Systems An Integral Measure of Aging/Rejuvenation for Repairable and Non-repairable Systems M.P. Kaminskiy and V.V. Krivtsov Abstract This paper introduces a simple index that helps to assess the degree of aging

More information

Pb1 y13 =-j10 Pb5. Pb4. y34 =-j10

Pb1 y13 =-j10 Pb5. Pb4. y34 =-j10 EE 55, Exam, ake-home. Due Monday, April, 06, 5:00pm. You may use class notes or any reference materials (e.g., books, etc.) that you like; however, you must work alone, i.e., you should not be communicating

More information

Branch Outage Simulation for Contingency Studies

Branch Outage Simulation for Contingency Studies Branch Outage Simulation for Contingency Studies Dr.Aydogan OZDEMIR, Visiting Associate Professor Department of Electrical Engineering, exas A&M University, College Station X 77843 el : (979) 862 88 97,

More information

Software Tools: Congestion Management

Software Tools: Congestion Management Software Tools: Congestion Management Tom Qi Zhang, PhD CompuSharp Inc. (408) 910-3698 Email: zhangqi@ieee.org October 16, 2004 IEEE PES-SF Workshop on Congestion Management Contents Congestion Management

More information

Fault-Tolerant Computing

Fault-Tolerant Computing Fault-Tolerant Computing Motivation, Background, and Tools Slide 1 About This Presentation This presentation has been prepared for the graduate course ECE 257A (Fault-Tolerant Computing) by Behrooz Parhami,

More information

Reliability Assessment of Radial distribution system incorporating weather effects

Reliability Assessment of Radial distribution system incorporating weather effects International Journal of Engineering Research and Development e-issn: 2278-067X, p-issn: 2278-800X, www.ijerd.com Volume 6, Issue 7 (pril 2013), PP. 45-51 Reliability ssessment of Radial distribution system

More information

Meshed power system reliability estimation techniques

Meshed power system reliability estimation techniques Energy Production and Management in the 21st Century, Vol. 1 235 Meshed power system reliability estimation techniques S. A. Gusev, O. M. Kotov & V. P. Oboskalov Ural Federal University, Russia Abstract

More information

Other Continuous Probability Distributions

Other Continuous Probability Distributions CHAPTER Probability, Statistics, and Reliability for Engineers and Scientists Second Edition PROBABILITY DISTRIBUTION FOR CONTINUOUS RANDOM VARIABLES A. J. Clar School of Engineering Department of Civil

More information

Winter Season Resource Adequacy Analysis

Winter Season Resource Adequacy Analysis Winter Season Resource Adequacy Analysis Patricio Rocha-Garrido Sr. Engineer Resource Adequacy Planning RAAS August 4, 2017 Introduction Reliability requirements for the RTO and LDAs are calculated based

More information

Research Article RELIABILITY ASSESSMENT OF RADIAL NETWORKS VIA MODIFIED RBD ANALYTICAL TECHNIQUE

Research Article RELIABILITY ASSESSMENT OF RADIAL NETWORKS VIA MODIFIED RBD ANALYTICAL TECHNIQUE Sigma J Eng & Nat Sci 35 (4), 2017, 717-726 Sigma Journal of Engineering and Natural Sciences Sigma Mühendislik ve Fen Bilimleri Dergisi Research Article RELIABILITY ASSESSMENT OF RADIAL NETWORKS VIA MODIFIED

More information

Application of Monte Carlo Simulation to Multi-Area Reliability Calculations. The NARP Model

Application of Monte Carlo Simulation to Multi-Area Reliability Calculations. The NARP Model Application of Monte Carlo Simulation to Multi-Area Reliability Calculations The NARP Model Any power system reliability model using Monte Carlo simulation consists of at least the following steps: 1.

More information

c 2017 Mariola Ndrio

c 2017 Mariola Ndrio c 2017 Mariola Ndrio RESOURCE ADEQUACY IN GRIDS WITH INTEGRATED RENEWABLE RESOURCES BY MARIOLA NDRIO THESIS Submitted in partial fulfillment of the requirements for the degree of Master of Science in Electrical

More information

Modelling wind power in unit commitment models

Modelling wind power in unit commitment models Modelling wind power in unit commitment models Grid integration session IEA Wind Task 25 Methodologies to estimate wind power impacts to power systems Juha Kiviluoma, Hannele Holttinen, VTT Technical Research

More information

The influence of the unit commitment plan on the variance of electric power. production cost. Jinchi Li

The influence of the unit commitment plan on the variance of electric power. production cost. Jinchi Li The influence of the unit commitment plan on the variance of electric power production cost by Jinchi Li A Creative Component paper submitted to the graduate faculty in partial fulfillment of the requirements

More information

Outage Coordination and Business Practices

Outage Coordination and Business Practices Outage Coordination and Business Practices 1 2007 Objectives What drove the need for developing a planning/coordination process. Why outage planning/coordination is crucial and important. Determining what

More information

Availability Analysis of Refining System of a Sugar Plant Using Markov Process

Availability Analysis of Refining System of a Sugar Plant Using Markov Process Availability Analysis of Refining System of a Sugar Plant Using Markov Process Er. Aman 1, Dr. V.K. Mahna 2, Dr. Rajiv Khanduja 3 1 Research Scholar, Dept. of Mechanical Engineering, M.R.I.U., Faridabad,Haryana,

More information

LECTURE #6 BIRTH-DEATH PROCESS

LECTURE #6 BIRTH-DEATH PROCESS LECTURE #6 BIRTH-DEATH PROCESS 204528 Queueing Theory and Applications in Networks Assoc. Prof., Ph.D. (รศ.ดร. อน นต ผลเพ ม) Computer Engineering Department, Kasetsart University Outline 2 Birth-Death

More information

Failure modeling and maintenance optimization for a railway line

Failure modeling and maintenance optimization for a railway line Failure modeling and maintenance optimization for a railway line Per Hokstad *, Helge Langseth SINTEF Technology and Society, Department of Safety and Reliability, N-7465 Trondheim, Norway Bo H. Lindqvist,

More information

Estimation of Current Transformer Insulation Life with an Effect of Environmental Variables

Estimation of Current Transformer Insulation Life with an Effect of Environmental Variables Estimation of Current Transformer Insulation Life with an Effect of Environmental Variables Priti N. Bawankule 1, Dr. A. G. Thosar 2, P. S. Swami 3 PG Student [EPS], Dept. of EE, Government College of

More information

Base Cases for Assessing Risk in Transmission System Planning

Base Cases for Assessing Risk in Transmission System Planning Conference on Probabilistic Methods Applied to Power Systems June 218, Boise, ID PMAPS 218 Base Cases for Assessing Risk in Transmission System Planning Dimitry Gorinevsky Mitek Analytics LLC Palo Alto,

More information

New Formulations of the Optimal Power Flow Problem

New Formulations of the Optimal Power Flow Problem New Formulations of the Optimal Power Flow Problem Prof. Daniel Kirschen The University of Manchester 2010 D. Kirschen and The University of Manchester 1 2010 D. Kirschen and The University of Manchester

More information

Monte Carlo Simulation

Monte Carlo Simulation Monte Carlo Simulation 198 Introduction Reliability indices of an actual physical system could be estimated by collecting data on the occurrence of failures and durations of repair. The Monte Carlo method

More information

Markov Model. Model representing the different resident states of a system, and the transitions between the different states

Markov Model. Model representing the different resident states of a system, and the transitions between the different states Markov Model Model representing the different resident states of a system, and the transitions between the different states (applicable to repairable, as well as non-repairable systems) System behavior

More information

Bayesian Networks 2:

Bayesian Networks 2: 1/27 PhD seminar series Probabilistics in Engineering : Bayesian networks and Bayesian hierarchical analysis in engineering Conducted by Prof. Dr. Maes, Prof. Dr. Faber and Dr. Nishijima Bayesian Networks

More information

AN INTEGRAL MEASURE OF AGING/REJUVENATION FOR REPAIRABLE AND NON REPAIRABLE SYSTEMS

AN INTEGRAL MEASURE OF AGING/REJUVENATION FOR REPAIRABLE AND NON REPAIRABLE SYSTEMS R&RAA # 1 (Vol.1) 8, March AN INEGRAL MEASURE OF AGING/REJUVENAION FOR REPAIRABLE AND NON REPAIRABLE SYSEMS M.P. Kaminskiy and V.V. Krivtsov Abstract his paper introduces a simple index that helps to assess

More information

Security Monitoring and Assessment of an Electric Power System

Security Monitoring and Assessment of an Electric Power System International Journal of Performability Engineering Vol. 10, No. 3, May, 2014, pp. 273-280. RAMS Consultants Printed in India Security Monitoring and Assessment of an Electric Power System PUROBI PATOWARY

More information

Applications of the Particle Swarm Optimization in Composite Power System Reliability Evaluation

Applications of the Particle Swarm Optimization in Composite Power System Reliability Evaluation Applications of the Particle Swarm Optimization in Composite Power System Reliability Evaluation Mohammed Benidris Salem Elsaiah Joydeep Mitra Michigan State University, USA ABSTRACT This chapter introduces

More information

Bulk Power System Reliability Assessment Considering Protection System Hidden Failures

Bulk Power System Reliability Assessment Considering Protection System Hidden Failures 2007 irep Symposium- Bulk Power System Dynamics and Control - V, Revitalizing Operational Reliability August 19-24, 2007, Charleston, SC, USA Bulk Power System Reliability Assessment Considering Protection

More information

The Impact of Distributed Generation on Power Transmission Grid Dynamics

The Impact of Distributed Generation on Power Transmission Grid Dynamics The Impact of Distributed Generation on Power Transmission Grid Dynamics D. E. Newman B. A. Carreras M. Kirchner I. Dobson Physics Dept. University of Alaska Fairbanks AK 99775 Depart. Fisica Universidad

More information

A Simplified Model to Predict Frost Penetration for Manitoba Soils

A Simplified Model to Predict Frost Penetration for Manitoba Soils A Simplified Model to Predict Frost Penetration for Manitoba Soils Haithem Soliman, M.Sc. PHD Student Department of Civil Engineering University of Manitoba Email: umsolimh@cc.umanitoba.ca Said Kass, P.Eng.

More information

Wenhui Hou* Department of Mechanical Engineering, Tangshan Polytechnic College, Tangshan , China *Corresponding author(

Wenhui Hou* Department of Mechanical Engineering, Tangshan Polytechnic College, Tangshan , China *Corresponding author( Rev. Téc. Ing. Univ. Zulia. Vol. 39, Nº 3, 238-245, 216 doi:1.21311/1.39.3.31 Reliability Assessment Algorithm of Rural Power Network Based on Bayesian Network Yunfang Xie College of Mechanical and Electrical

More information

Reactive Power Compensation for Reliability Improvement of Power Systems

Reactive Power Compensation for Reliability Improvement of Power Systems for Reliability Improvement of Power Systems Mohammed Benidris, Member, IEEE, Samer Sulaeman, Student Member, IEEE, Yuting Tian, Student Member, IEEE and Joydeep Mitra, Senior Member, IEEE Department of

More information

Theoretical Probability Models

Theoretical Probability Models CHAPTER Duxbury Thomson Learning Maing Hard Decision Third Edition Theoretical Probability Models A. J. Clar School of Engineering Department of Civil and Environmental Engineering 9 FALL 003 By Dr. Ibrahim.

More information

Business Case: UV Facility Backup Generator

Business Case: UV Facility Backup Generator Business Case: UV Facility Backup Generator Eric Brainich December 13, 2010 Background The Portland Water Bureau is currently working on the design for a new Ultra Violet (UV) Treatment Facility and the

More information

Probabilistic Evaluation of the Effect of Maintenance Parameters on Reliability and Cost

Probabilistic Evaluation of the Effect of Maintenance Parameters on Reliability and Cost Probabilistic Evaluation of the Effect of Maintenance Parameters on Reliability and Cost Mohsen Ghavami Electrical and Computer Engineering Department Texas A&M University College Station, TX 77843-3128,

More information

A Nodal Capacity Market to Assure Resource Adequacy

A Nodal Capacity Market to Assure Resource Adequacy 212 45th Hawaii International Conference on System Sciences A odal Capacity Market to Assure Resource Adequacy Aleksandr M. Rudkevich Charles River Associates arudkevich@crai.com Anatoly I. Lazebnik CJSC

More information

Steady-State and Transient Probabilities Calculation for Engineering Models

Steady-State and Transient Probabilities Calculation for Engineering Models International Journal of Engineering Science Invention ISSN (Online): 2319 6734, ISSN (Print): 2319 6726 Volume 5 Issue 8 August 2016 PP. 54-64 Steady-State and Transient Probabilities Calculation for

More information

Availability Optimization for Coal Handling System using Genetic Algorithm

Availability Optimization for Coal Handling System using Genetic Algorithm International Journal of Performability Engineering Vol. 9, o. 1, January 21, pp. 19-1. RAMS Consultants Printed in India Availability Optimization for Coal Handling System using Genetic Algorithm SAJAY

More information

Integrating Reliability into the Design of Power Electronics Systems

Integrating Reliability into the Design of Power Electronics Systems Integrating Reliability into the Design of Power Electronics Systems Alejandro D. Domínguez-García Grainger Center for Electric Machinery and Electromechanics Department of Electrical and Computer Engineering

More information

A Comprehensive Approach for Bulk Power System Reliability Assessment

A Comprehensive Approach for Bulk Power System Reliability Assessment PAPER D: #44 1 A Comprehensive Approach for Bulk Power System Reliability Assessment Fang Yang, Student Member, EEE, A. P. Sakis Meliopoulos, Fellow, EEE, George J. Cokkinides, Member, EEE, and George

More information

Probabilistic Reliability Management Approach and Criteria for Power System Short-term Operational Planning

Probabilistic Reliability Management Approach and Criteria for Power System Short-term Operational Planning Probabilistic Reliability Management Approach and Criteria for Power System Short-term Operational Planning Efthymios Karangelos and Louis Wehenkel Department of Electrical Engineering & Computer Science

More information

Transmission congestion tracing technique and its application to recognize weak parts of bulk power systems

Transmission congestion tracing technique and its application to recognize weak parts of bulk power systems J. Mod. Power Syst. Clean Energy DOI 10.1007/s40565-016-0230-7 Transmission congestion tracing technique and its application to recognize weak parts of bulk power systems Ming GAN 1,2, Kaigui XIE 1, Chunyan

More information

Quantitative evaluation of Dependability

Quantitative evaluation of Dependability Quantitative evaluation of Dependability 1 Quantitative evaluation of Dependability Faults are the cause of errors and failures. Does the arrival time of faults fit a probability distribution? If so, what

More information

Reliable Computing I

Reliable Computing I Instructor: Mehdi Tahoori Reliable Computing I Lecture 5: Reliability Evaluation INSTITUTE OF COMPUTER ENGINEERING (ITEC) CHAIR FOR DEPENDABLE NANO COMPUTING (CDNC) National Research Center of the Helmholtz

More information

A Markov model for estimating the remaining life of electrical insulation in distribution transformer

A Markov model for estimating the remaining life of electrical insulation in distribution transformer AMERICAN JOURNAL OF SCIENTIFIC AND INDUSTRIAL RESEARCH 2010, Science Huβ, http://www.scihub.org/ajsir ISSN: 2153-649X doi:10.5251/ajsir.2010.1.3.539.548 A Markov model for estimating the remaining life

More information

Risk and Safety in Civil, Surveying and Environmental Engineering

Risk and Safety in Civil, Surveying and Environmental Engineering Risk and Safety in Civil, Surveying and Environmental Engineering Prof. Dr. Michael Havbro Faber ETH Zurich, Switzerland Contents of Today's Lecture Introduction to structural systems reliability General

More information

ABSTRACT I. INTRODUCTION II. FUZZY MODEL SRUCTURE

ABSTRACT I. INTRODUCTION II. FUZZY MODEL SRUCTURE International Journal of Scientific Research in Computer Science, Engineering and Information Technology 2018 IJSRCSEIT Volume 3 Issue 6 ISSN : 2456-3307 Temperature Sensitive Short Term Load Forecasting:

More information

Aviation Infrastructure Economics

Aviation Infrastructure Economics Aviation Short Course Aviation Infrastructure Economics October 14-15, 15, 2004 The Aerospace Center Building 901 D St. SW, Suite 850 Washington, DC 20024 Lecture BWI/Andrews Conference Rooms Instructor:

More information

MISO September 15 Maximum Generation Event Overview. October 11, 2018

MISO September 15 Maximum Generation Event Overview. October 11, 2018 MISO September 15 Maximum Generation Event Overview October 11, 2018 Purpose & Key Takeaways Purpose: Summarize operations during the September 15 South Region Maximum Generation Event Key Takeaways: MISO

More information

Estimating Failure Propagation in Models of Cascading Blackouts

Estimating Failure Propagation in Models of Cascading Blackouts 8th International Conference on Probability Methods Applied to Power Systems, Ames Iowa, September 2004 Estimating Failure Propagation in Models of Cascading Blackouts Ian Dobson Benjamin A. Carreras Vickie

More information

International Studies about the Grid Integration of Wind Generation

International Studies about the Grid Integration of Wind Generation International Studies about the Grid Integration of Wind Generation Dr.-Ing. Markus Pöller/DIgSILENT GmbH Internation Studies About Grid Integration of Wind Generation Grid Integration of Wind Generationin

More information

Peterborough Distribution Inc Ashburnham Drive, PO Box 4125, Station Main Peterborough ON K9J 6Z5

Peterborough Distribution Inc Ashburnham Drive, PO Box 4125, Station Main Peterborough ON K9J 6Z5 Peterborough Distribution Inc. 1867 Ashburnham Drive, PO Box 4125, Station Main Peterborough ON K9J 6Z5 November 15, 2017 Ontario Energy Board PO Box 2319 27 th Floor, 2300 Yonge St Toronto ON M4P 1E4

More information

Link Models for Packet Switching

Link Models for Packet Switching Link Models for Packet Switching To begin our study of the performance of communications networks, we will study a model of a single link in a message switched network. The important feature of this model

More information

Peak Shifting Discussion and Forecast Sensitivities

Peak Shifting Discussion and Forecast Sensitivities Peak Shifting Discussion and Forecast Sensitivities SODRSTF February 2, 2018 Andrew Gledhill Resource Adequacy Planning Objectives Peak shaving forecast sensitivities Using 5/10 CP method as was previously

More information

Batch Arrival Queuing Models with Periodic Review

Batch Arrival Queuing Models with Periodic Review Batch Arrival Queuing Models with Periodic Review R. Sivaraman Ph.D. Research Scholar in Mathematics Sri Satya Sai University of Technology and Medical Sciences Bhopal, Madhya Pradesh National Awardee

More information

Markov Reliability and Availability Analysis. Markov Processes

Markov Reliability and Availability Analysis. Markov Processes Markov Reliability and Availability Analysis Firma convenzione Politecnico Part II: Continuous di Milano e Time Veneranda Discrete Fabbrica State del Duomo di Milano Markov Processes Aula Magna Rettorato

More information

Optimal Capacitor Placement in Distribution System with Random Variations in Load

Optimal Capacitor Placement in Distribution System with Random Variations in Load I J C T A, 10(5) 2017, pp. 651-657 International Science Press Optimal Capacitor Placement in Distribution System with Random Variations in Load Ajay Babu B *, M. Ramalinga Raju ** and K.V.S.R. Murthy

More information

Norm Hann Performance Manager, Performance Management Department Hydro One Networks Inc.

Norm Hann Performance Manager, Performance Management Department Hydro One Networks Inc. Norm Hann Performance Manager, Performance Management Department Hydro One Networks Inc. Phone: (416)-345-5407 Email: Norm.Hann@HydroOne.com Closing the Crevice Achieving A Process For Asset Performance

More information

Probabilistic Analysis of a Desalination Plant with Major and Minor Failures and Shutdown During Winter Season

Probabilistic Analysis of a Desalination Plant with Major and Minor Failures and Shutdown During Winter Season Probabilistic Analysis of a Desalination Plant with Major and Minor Failures and Shutdown During Winter Season Padmavathi N Department of Mathematics & Statistics Caledonian college of Engineering Muscat,

More information

Minimization of load shedding by sequential use of linear programming and particle swarm optimization

Minimization of load shedding by sequential use of linear programming and particle swarm optimization Turk J Elec Eng & Comp Sci, Vol.19, No.4, 2011, c TÜBİTAK doi:10.3906/elk-1003-31 Minimization of load shedding by sequential use of linear programming and particle swarm optimization Mehrdad TARAFDAR

More information

Importance Sampling Stratified Sampling. Lecture 6, autumn 2015 Mikael Amelin

Importance Sampling Stratified Sampling. Lecture 6, autumn 2015 Mikael Amelin Importance Sampling Stratified Sampling Lecture 6, autumn 2015 Mikael Amelin 1 Introduction All samples are treated equally in simple sampling. Sometimes it is possible to increase the accuracy by focusing

More information

Availability and Reliability Analysis for Dependent System with Load-Sharing and Degradation Facility

Availability and Reliability Analysis for Dependent System with Load-Sharing and Degradation Facility International Journal of Systems Science and Applied Mathematics 2018; 3(1): 10-15 http://www.sciencepublishinggroup.com/j/ijssam doi: 10.11648/j.ijssam.20180301.12 ISSN: 2575-5838 (Print); ISSN: 2575-5803

More information

Reliability Evaluation in Transmission Systems

Reliability Evaluation in Transmission Systems Reliability Evaluation in Transmission Systems Chanan Singh 1 and Joydeep Mitra 2 1 Texas A&M University, College Station, TX, USA 2 Michigan State University, East Lansing, MI, USA 1 Introduction In reliability

More information

XLVI Pesquisa Operacional na Gestão da Segurança Pública

XLVI Pesquisa Operacional na Gestão da Segurança Pública A strong mixed integer formulation for a switch allocation problem Fábio Luiz Usberti 1, Celso Cavellucci 2 and Christiano Lyra Filho 2 1 Institute of Computing, 2 School of Electrical and Computer Engineering

More information

International Journal of Mechatronics, Electrical and Computer Technology

International Journal of Mechatronics, Electrical and Computer Technology A Hybrid Algorithm for Optimal Location and Sizing of Capacitors in the presence of Different Load Models in Distribution Network Reza Baghipour* and Seyyed Mehdi Hosseini Department of Electrical Engineering,

More information

Chapter 8. Calculation of PFD using Markov

Chapter 8. Calculation of PFD using Markov Chapter 8. Calculation of PFD using Markov Mary Ann Lundteigen Marvin Rausand RAMS Group Department of Mechanical and Industrial Engineering NTNU (Version 0.1) Lundteigen& Rausand Chapter 8.Calculation

More information