The World Bank Ho Chi Minh City Green Transport Development (P126507)

Similar documents
The World Bank Can Tho Urban Development and Resilience (P152851)

Public Disclosure Copy

Public Disclosure Copy

The World Bank China: Qinghai Xining Urban Transport Project (P127867)

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

Public Disclosure Copy. Implementation Status & Results Report UGANDA North Eastern Road-corridor Asset Management Project (NERAMP) (P125590)

Public Disclosure Copy

Public Disclosure Copy. Implementation Status & Results Report CN Yunnan Honghe Prefecture Diannan Center Urban Transport (P101525)

The World Bank Heilongjiang Cold Weather Smart Public Transportation System (P133114)

The World Bank Regional Infrastructure Development Fund (P154947)

The World Bank Zambia Water Resources Development Project (P114949)

The World Bank. Kenya: Off-grid Solar Access Project for Underserved Counties (P160009) Key Dates. Project Development Objectives.

SÃO PAULO METRO LINE 4 (PHASE 2) (P106390)

Public Disclosure Copy

The World Bank Sri Lanka Agriculture Sector Modernization Project (P156019)

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy

The World Bank Second Ho Chi Minh City Environmental Sanitation Project (P127978)

The World Bank Guilin Integrated Environment Management (P133017)

The World Bank Uganda Energy for Rural Transformation III (P133312)

Public Disclosure Copy

Public Disclosure Copy

The World Bank Ethiopia: Transport Systems Improvement Project (TRANSIP) (P151819)

The World Bank Sri Lanka Agriculture Sector Modernization Project (P156019)

Public Disclosure Copy

The World Bank Earthquake Housing Reconstruction Project (P155969)

The World Bank Zambia Water Resources Development Project (P114949)

Public Disclosure Copy

The World Bank Transport Connectivity and Asset Management Project (P132833)

Sri Lanka Strategic Cities Development Project (P130548)

SUSTAINABLE CITIES (P128605)

Public Disclosure Copy

Key Dates. Project Development Objectives. Components. Overall Ratings

The World Bank Greater Maputo Water Supply Expansion Project (P125120)

The World Bank Local and Regional Competitiveness Project (P154263)

Public Disclosure Copy

EC Ibarra Transport Infrastructure Improvement Project (P147280)

Public Disclosure Copy

Public Disclosure Copy

Urban Water Supply Project (P156739)

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy

The World Bank Cusco Regional Development (P117318)

The World Bank BiH Floods Emergency Recovery Project (P151157)

Public Disclosure Copy

Public Disclosure Copy

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

Public Disclosure Copy. Implementation Status & Results Report Vietnam: Project for Improved Land Governance and Databases (VILG) (P154387)

The World Bank MA- Noor Ouarzazate Concentrated Solar Power Project (P131256)

Public Disclosure Copy

Key Dates. Project Development Objectives. Components. Overall Ratings

Public Disclosure Copy

Public Disclosure Copy. Implementation Status & Results Report Upper Cisokan Pumped Storage Hydro-Electrical Power (1040 MW) Project (P112158)

The World Bank Ethiopia Geothermal Sector Development Project (P133613)

The World Bank Ethiopia: National Quality Infrastructure Development Project (P160279)

Public Disclosure Copy. Implementation Status & Results Report Cambodia Global Partnership for Education Second Education Support Project (P144715)

Public Disclosure Copy

The World Bank Indonesia: Geothermal Energy Upstream Development Project (P155047)

Public Disclosure Copy. Implementation Status & Results Report DJ-Rural Community Development and Water Mobilization Project (PRODERMO) (P117355)

Public Disclosure Copy

The World Bank Dam Operational Improvement and Safety (P096532)

PAMSIMAS Support Trust Fund (P116236)

The World Bank China Wuhan Second Urban Transport (P112838)

Public Disclosure Copy. Implementation Status & Results Report KH - Livelihood Enhancement and Association of the Poor Project (LEAP) (P153591)

Public Disclosure Copy. AFCC2/RI-The Eastern Electricity Highway Project under the First Phase of the Eastern Africa Power

Key Dates. Project Development Objectives. Components. Overall Ratings

The World Bank Bangladesh Modern Food Storage Facilities Project (P120583)

NI - INTEGRATED PUBLIC PROVISION OF HEALTH CARE SERVICES (P164452)

The World Bank Local and Regional Competitiveness Project (P154263)

Public Disclosure Copy

Public Disclosure Copy

The World Bank Third National Urban Water Sector Reform Project (P123513)

Name Previous Rating Current Rating

SUSTAINABLE CITIES (P128605)

Public Disclosure Copy. Implementation Status & Results Report Small Town Water Supply and Urban Septage Management Project (P156738)

The World Bank OECS Regional Tourism Competitiveness (P152117)

The World Bank Georgia National Innovation Ecosystem (GENIE) Project (P152441)

Public Disclosure Copy

The World Bank Indonesia National Slum Upgrading Project (P154782)

The World Bank Earthquake Housing Reconstruction Project (P155969)

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy

The World Bank Senegal Tourism and Enterprise Development Project (P146469)

Public Disclosure Copy

The World Bank Mali Reconstruction and Economic Recovery (P144442)

The Project s Development Objective (PDO) is to promote environmentally sustainable urban transport in India and to improve the usage of

Sierra Leone Energy Access Project - Sierra Leone Infrastructure Development Fund (P126180)

Public Disclosure Copy

The World Bank Indonesia National Slum Upgrading Project (P154782)

Public Disclosure Copy

Public Disclosure Copy. Implementation Status & Results Report Pacific Islands Regional Oceanscape Program - Solomon Islands (P151777)

The World Bank Swaziland Health, HIV/AIDS and TB Project (P110156)

Ethiopia: Transport Systems Improvement Project (TRANSIP) (P151819)

Public Disclosure Copy

Public Disclosure Copy

West Bank and Gaza: Finance for Jobs (P151089)

The World Bank Ecuador - Sustainable Family Farming Modernization Project (P151963)

Transcription:

Public Disclosure Authorized EAST ASIA AND PACIFIC Vietnam Transport & ICT Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 6 ARCHIVED on 25-Dec-2017 ISR31002 Implementing Agencies: Ho Chi Minh City People's Committee, Urban-Civil works construction investment management authority, Socialist Republic of Vietnam, Ho Chi Minh City People's Committee, Urban-Civil works construction management authority, HCM GT PMU Public Disclosure Authorized Key Dates Key Project Dates Bank Approval Date:29-May-2015 Planned Mid Term Review Date:12-Nov-2018 Original Closing Date:31-Dec-2020 Project Development Objectives Effectiveness Date:09-Oct-2015 Actual Mid-Term Review Date:-- Revised Closing Date:31-Dec-2020 Public Disclosure Authorized Project Development Objective (from Project Appraisal Document) The project development objective is to improve the performance and efficiency of public transport along a high priority corridor in Ho Chi Minh City. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Bus Rapid Transit Corridor Development:(Cost $122.80 M) Public Disclosure Authorized Institutional Strengthening:(Cost $5.00 M) Contingency:(Cost $9.65 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Unsatisfactory Moderately Unsatisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions 12/25/2017 Page 1 of 8

After a review process that lasted over a year, the HCMC People's Committee has approved the report that re-confirmed the project feasibility and proposed cost-efficient design options in November 2017, after studying in detail the lessons from Hanoi BRT. Implementation of the project is expected to resume in January, and be followed by the completion of the Detailed Design and start of tender process in late 2018. The next implementation support mission by the World Bank is scheduled for May 2018. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Substantial Substantial Substantial Macroeconomic Moderate Moderate Moderate Sector Strategies and Policies Substantial Substantial Substantial Technical Design of Project or Program Moderate Moderate Moderate Institutional Capacity for Implementation and Sustainability Substantial Substantial Substantial Fiduciary Substantial Substantial Substantial Environment and Social Moderate Moderate Moderate Stakeholders Moderate Moderate Moderate Other -- -- -- Overall Substantial Substantial Substantial Results Project Development Objective Indicators Number of passengers per day using the BRT system (Number, Custom) Value 0.00 0.00 0.00 28,300.00 Date 01-Jan-2019 20-Jun-2017 20-Dec-2017 31-Dec-2020 People satisfied with the service provided by Public Transport (Percentage, Custom) 12/25/2017 Page 2 of 8

Value 33.00 0.00 0.00 50.00 Date 01-Jan-2019 23-May-2016 20-Dec-2017 31-Dec-2020 Women satisfied with the service provided by Public Transport (Sub-Indicator) (Percentage, Custom Breakdown) Value 40.00 0.00 0.00 60.00 Date 01-Jan-2019 20-Jun-2017 20-Dec-2017 31-Dec-2020 Low income riders satisfied with the service provided by Public Transport (Sub-Indicator) (Percentage, Custom Breakdown) Value 25.00 0.00 0.00 50.00 Date 01-Jan-2019 20-Jun-2017 20-Dec-2017 31-Dec-2020 Travel time by public transport along the project corridor, measured as in-vehicle time from An Lac to Ky Con (14.1 km) (Minutes, Custom) Value 60.00 -- 60.00 37.00 Date 01-Jan-2019 -- 20-Dec-2017 31-Dec-2020 Number of workers and students accessing Thu Thiem Development within 45 minutes (Number, Custom) 12/25/2017 Page 3 of 8

Value 1,122,000.00 -- 1,122,000.00 1,290,000.00 Date 01-Jan-2019 -- 20-Dec-2017 31-Dec-2020 Number of residents accessing Thu Thiem Development within 45 minutes. (Sub-Indicator) (Number, Custom Supplement) Value 1,050,000.00 1,050,000.00 1,050,000.00 1,208,000.00 Difference in GHG emissions compared to BAU case (Tones/year, Custom) Value 0.00 -- 0.00-23,000.00 Date 01-Jan-2019 -- 20-Dec-2017 31-Dec-2020 Overall Comments Intermediate Results Indicators Percentage of physical work completed as part of the civil works for the BRT transitway (Percentage, Custom) Value 0.00 0.00 0.00 100.00 Date 01-Mar-2016 20-Jun-2017 20-Dec-2017 30-Jun-2019 12/25/2017 Page 4 of 8

Percentage of physical work completed as part of the civil works for BRT stations (Percentage, Custom) Value 0.00 0.00 0.00 100.00 Date 01-Mar-2016 20-Jun-2017 20-Dec-2017 30-Jun-2019 Percentage of physical work completed as part of the civil works for constructing the Terminal at Rach Chiec (Percentage, Custom) Value 0.00 0.00 0.00 100.00 Date 01-Mar-2016 20-Jun-2017 20-Dec-2017 30-Jun-2019 Percentage of physical work completed as part of the civil works for constructing the Thu Thiem technical facility (Percentage, Custom) Date 01-Mar-2016 -- 20-Dec-2017 31-Dec-2020 Number of buses acquired for the BRT system (Number, Custom) Value 0.00 -- 0.00 28.00 Date 01-Mar-2016 -- 20-Dec-2017 15-Feb-2019 12/25/2017 Page 5 of 8

Percentage of intersections with improved traffic and safety control (Percentage, Custom) Date 01-Mar-2016 -- 20-Dec-2017 31-Dec-2020 Percentage of sidewalk improvements completed along the BRT route (Percentage, Custom) Value 0.00 0.00 0.00 100.00 Date 01-Mar-2016 20-Jun-2017 20-Dec-2017 31-Dec-2020 Percentage of improvements to station access within a 400-meter radius completed (Percentage, Custom) Date 01-Mar-2016 -- 20-Dec-2017 31-Dec-2020 Percentage of planned greening and landscaping activities along the corridor completed (Percentage, Custom) Date 01-Mar-2016 -- 20-Dec-2017 31-Dec-2020 12/25/2017 Page 6 of 8

Percentage of training courses delivered to the HCMC PC and its agencies (Percentage, Custom) Date 01-Sep-2015 -- 20-Dec-2017 31-Dec-2020 Number of studies completed under Component 2 of the project (Number, Custom) Value 0.00 -- 0.00 3.00 Date 01-Sep-2015 -- 20-Dec-2017 31-Dec-2020 Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P126507 IDA-56540 Effective USD 124.00 124.00 0.00 0.07 119.12 0% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P126507 IDA-56540 Effective 29-May-2015 09-Jul-2015 09-Oct-2015 31-Dec-2020 31-Dec-2020 Cumulative Disbursements 12/25/2017 Page 7 of 8

Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 12/25/2017 Page 8 of 8