OP-13. PROCEDURES FOR DESIGN OF EMBANKMENT

Similar documents
INTI COLLEGE MALAYSIA

PRINCIPLES OF GEOTECHNICAL ENGINEERING

TABLE OF CONTENTS CHAPTER TITLE PAGE TITLE PAGE DECLARATION DEDIDATION ACKNOWLEDGEMENTS ABSTRACT ABSTRAK

Embankment over Soft Clay Design and Construction Control

Reinforced Soil Structures Reinforced Soil Walls. Prof K. Rajagopal Department of Civil Engineering IIT Madras, Chennai

SOME GEOTECHNICAL PROPERTIES OF KLANG CLAY

Chapter 17 EMBANKMENTS

OP-023. INTERPRETATION OF INSTRUMENTED TEST PILE RESULT

EN Eurocode 7. Section 3 Geotechnical Data Section 6 Spread Foundations. Trevor L.L. Orr Trinity College Dublin Ireland.

Calculation of 1-D Consolidation Settlement

SOIL INVESTIGATION REPORT. PROPOSED HOUSING DEVELOPMENT PROJECT Coral Spring, Trelawny, Jamaica.

Table of Contents Chapter 1 Introduction to Geotechnical Engineering 1.1 Geotechnical Engineering 1.2 The Unique Nature of Soil and Rock Materials

SOIL MECHANICS: palgrave. Principles and Practice. Graham Barnes. macmiiian THIRD EDITION

Analysis of Load-Settlement Relationship for Unpaved Road Reinforced with Geogrid

Expressway Embankment Landslide Treatment Technology for Peat Subgrade

Chapter (5) Allowable Bearing Capacity and Settlement

1.8 Unconfined Compression Test

FUNDAMENTALS SOIL MECHANICS. Isao Ishibashi Hemanta Hazarika. >C\ CRC Press J Taylor & Francis Group. Taylor & Francis Group, an Informa business

Compressibility & Consolidation

Bearing Capacity Of Shallow Foundation

SHEET PILE WALLS. Mehdi Mokhberi Islamic Azad University

Introduction to Soil Mechanics

vulcanhammer.net This document downloaded from

Field and Laboratory Testing of Soil for Surcharge Design

INTRODUCTION TO STATIC ANALYSIS PDPI 2013

Chapter (11) Pile Foundations

Engineeringmanuals. Part2

GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE

HKIE-GD Workshop on Foundation Engineering 7 May Shallow Foundations. Dr Limin Zhang Hong Kong University of Science and Technology

Chapter (12) Instructor : Dr. Jehad Hamad

CHARACTERIZATION OF SOFT CLAY- A CASE STUDY AT CRANEY ISLAND

Boreholes. Implementation. Boring. Boreholes may be excavated by one of these methods: 1. Auger Boring 2. Wash Boring 3.

Chapter 7 GEOMECHANICS

GROUND IMPROVEMENT WORKSHOP JUNE 2010 PERTH, AUSTRALIA. CHAIRMAN OF T.C. Ground Improvement

INVESTIGATION OF SATURATED, SOFT CLAYS UNDER EMBANKMENTS. Zsolt Rémai Budapest University of Technology and Economics Department of Geotechnics

23.1 Effective Stress 23.2 Settlement of Foundations Time-Dependent Settlement Magnitude of Acceptable Settlement

REGRESSION ANALYSIS OF SHORT TERM TIME-SETTLEMENT RESPONSE OF SOFT CLAYEY SOIL AT CONSTANT LOADING CONDITION

Advanced model for soft soils. Modified Cam-Clay (MCC)

Dynamic Response of EPS Blocks /soil Sandwiched Wall/embankment

The process of consolidation and settlement

BRASIL MAY 2010

BEARING CAPACITY SHALLOW AND DEEP FOUNDATIONS

Study on Settlement Prediction Model of High-Speed Railway Bridge Pile Foundation

Supplementary Problems for Chapter 7

8.1. What is meant by the shear strength of soils? Solution 8.1 Shear strength of a soil is its internal resistance to shearing stresses.

Geotechnical Properties of Soil

IAEA SAFETY STANDARDS Geotechnical Aspects of Site Evaluation and Foundations in NPPs, NS-G-3.6

Deep Foundations 2. Load Capacity of a Single Pile

Predicting Settlement and Stability of Wet Coal Ash Impoundments using Dilatometer Tests

Theory of Shear Strength

Computers and Geotechnics

STUDY ON CONSOLIDATION OF ALLUVIAL CLAY IN NORTHERN QUEENSLAND

Settlement prediction for soft ground improved by columns

Examples to verify and illustrate ELPLA

Compression and swelling. Mechanisms of compression. Mechanisms Common cases Isotropic One-dimensional Wet and dry states

Geotechnical Indications Of Eastern Bypass Area In Port Harcourt, Niger Delta

Ch 4a Stress, Strain and Shearing

GEOTECHNICAL ENGINEERING UNSATURATED AND SATURATED SOILS

Laboratory Testing Total & Effective Stress Analysis

Planning of Subsurface Investigation and Interpretation of Test Results for Geotechnical Design

The Bearing Capacity of Soils. Dr Omar Al Hattamleh

SOIL MODELS: SAFETY FACTORS AND SETTLEMENTS

SETTLEMENT OF AN EMBANKMENT TREATED WITH PRELOADING AND PREFABRICATED VERTICAL DRAIN OF EAST-COAST HIGHWAY PHASE 2 (A CASE STUDY)

(C) Global Journal of Engineering Science and Research Management

Soil strength. the strength depends on the applied stress. water pressures are required

SEM-2016(01HI CIVIL ENGINEERING. Paper Answer all questions. Question No. 1 does not have internal choice,

CPT Guide 5 th Edition. CPT Applications - Deep Foundations. Gregg Drilling & Testing, Inc. Dr. Peter K. Robertson Webinar # /2/2013

A Thesis presented to the Faculty of the Graduate School at the University of Missouri-Columbia

SI Planning & Laboratory Testing for Hill-Site Development

A Comparative Study on Bearing Capacity of Shallow Foundations in Sand from N and /

water proofing will relatively long time fully completed) be provided 10 storey building (15x25m) original GWT position 1 sat = 20 kn/m 3

THE PREDICTION OF FINAL SETTLEMENT FROM 1D-CONSOLIDATION TEST: A CASE STUDY


Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

TIME-DEPENDENT BEHAVIOR OF PILE UNDER LATERAL LOAD USING THE BOUNDING SURFACE MODEL

2017 Soil Mechanics II and Exercises Final Exam. 2017/7/26 (Wed) 10:00-12:00 Kyotsu 4 Lecture room

Cone Penetration Test Design Guide for State Geotechnical Engineers

Foundation Engineering Prof. Dr N.K. Samadhiya Department of Civil Engineering Indian Institute of Technology Roorkee

Liquefaction and Foundations

Surcharge Loading On Reduction of Secondary Compression

Geotechnical Investigation and Monitoring Results of a Landslide Failure at Southern Peninsular Malaysia (Part 1: Investigating Causes of Failure)

Pilot Implementation Using Geofoam for Repair of Bridge Approach Slabs

Class Principles of Foundation Engineering CEE430/530

Central Queensland Coal Project Appendix 4b Geotechnical Assessment. Environmental Impact Statement

Theory of Shear Strength

GEOTECHNICAL ENGINEERING ECG 503 LECTURE NOTE ANALYSIS AND DESIGN OF RETAINING STRUCTURES

Pit Slope Optimization Based on Hydrogeologic Inputs

SETTLEMENT CHARACTERISTICS OF COODE ISLAND SILT

SOIL SHEAR STRENGTH. Prepared by: Dr. Hetty Muhammad Azril Fauziah Kassim Norafida

ULTIMATE BEARING CAPACITY OF ECCENTRICALLY LOADED STRIP FOUNDATION ON SAND REINFORCED WITH GEOGRIDS

3D FEM investigation on bending failure mechanism of column inclusion under embankment load

APPENDIX F CORRELATION EQUATIONS. F 1 In-Situ Tests

3-BEARING CAPACITY OF SOILS

H.1 SUMMARY OF SUBSURFACE STRATIGRAPHY AND MATERIAL PROPERTIES (DATA PACKAGE)

D1. A normally consolidated clay has the following void ratio e versus effective stress σ relationship obtained in an oedometer test.

SITE INVESTIGATION 1

MODELLING OF PRIMARY CONSOLIDATION

Introduction to Geotechnical Engineering. ground

The San Jacinto Monument Case History

OVERVIEW REVIEW OF FOUNDATIONS & SOILS ENG.

Transcription:

Page 1 of 8 WORK INSTRUCTIONS FOR ENGINEERS TYC Compiled by : LSS Checked by : GSS Approved by : OP-13. PROCEDURES FOR DESIGN OF EMBANKMENT

Page of 8 13.0 13.1. OVERALL PROCEDURES This section will briefly list down the overall procedures necessary for the design of the embankment over soft clay. The procedures are as follows : 1) Determine the Embankment Fill Height (EFH). (Section 13.) ) Settlement Analysis (Section 13.3) 3) Design of Surcharge Height (Section 13.4) 4) Stability Analysis of the Embankment (Section 13.5) 13.. DETERMINATION OF THE EMBANKMENT FILL HEIGHT (EFH) 1) Determine the Net Fill Height (NFH) of the embankment. Net Fill Height (NFH) is the finished road level (FRL) minus the existing ground level (EGL). NFH = FRL EGL (m) ) First preliminary estimation of the Total Settlement ( ρ T ). As a crude guide, the following percentage can be used : Subsoil Soft Clay Thickness Total Settlement as Percentage of NFH (%) < 5m 15% - 0% 5m to 10m 0% - 30% 10m to 15m 5% - 35% > 15m 30% - 40% 3) Estimation of the Embankment Fill Height (EFH) which is the total of Net Fill Height (NFH) and the Total Settlement ( ρ T ). EFH = NFH + ρ T 4) Carry out Settlement Analysis (Section 9.3 for details) to obtain the representative total settlement which includes Immediate Settlement ( ρ i ) + Primary Consolidation Settlement ( ρ c ) +Secondary Consolidation Settlement ( ρ s ). The embankment pressure shall be based on the Embankment Fill Height (EFH) times the bulk unit weight of the fill materials ( γ ). bulk( fill) Embankment Pressure (kpa) = EFH x γ bulk( fill) ρ T = ρ + ρ + ρ i c s Note : In most cases, the Secondary Consolidation Settlement ( ρ s ) can be ignored in the calculation of the EFH. This is because ρ cannot be totally removed during construction. s 5) After obtaining the Total Settlement from Steps 4 above, CORRECT the Embankment Fill Height as in Steps 3. Steps 3 to 5 shall be repeated until the error of Embankment Fill Height is less than 5%. (EFH i+1 EFH i ) < (5% of EFH i )

Page 3 of 8 6) Obtain the correct Embankment Fill Height (EFH). It is important to calculate the EFH so that the stability analysis can take into consideration the loading from the fill to compensate settlement. 13.3. SETTLEMENT ANALYSIS Settlement can be conveniently divided into three stages :- (A) (B) (C) Initial Settlement (also called immediate or undrained or shear settlement), ρ i Primary Consolidation Settlement, ρ c Secondary Compression, ρ s Total settlement (long term), ( ρ T ) is the sum of initial + primary consolidation + secondary compression settlements. ρ T = ρ + ρ + ρ i c s For details of the equations to be used, please refer to Tan & Gue (000) titled Embankment over Soft Clay Design and Construction Control. 13.3.1. Selection of Parameters 1) Plot all the boreholes results (subsoil cross-section). ) Obtain correct existing groundwater level (install standpipes to monitor because water in borehole after drilling can be misleading). 3) Compile all consolidation parameters into following plots for all boreholes or in zones:- C c /1+e c C r /1+e o C α /1+ e p γ (so that correct initial effective overburden pressure, bulk( fill) σ ' can be calculated) vo OCR c v m v k v (as obtained from m v.c v. γ w ) 4) Select the design lines for Consolidation Parameters. (Need to be reviewed) 5) Obtain the Undrained Young s Modulus (E u ) of the subsoil to estimate immediate settlement based on :- SPT N values Correlation, E u = 000 to 3000 SPT N (kpa) (crude guide) Undrained Shear Strength Correlation, E u = 00s u to 600s u (kpa) [Can start with 400s u ] 6) The correct E u can be obtained from CIU tests.

Page 4 of 8 13.3.. Immediate Settlement Immediate settlement can be estimated using elastic displacement theory as : 1 ρ I = ( I q) dh Where q = Applied Stress / Pressure on the subsoil (kpa). dh = thickness of each layer (m). = Undrained Young s Modulus of the subsoil (kpa) E u I = Influence factor E U A useful chart is given by Osterberg (1957) and shown in Figure 1. The chart allows estimation of the initial settlement of the embankment. For embankment on very soft clay, it is advisable to include the immediate settlement of the soft clay in the calculation of the Embankment Fill Height (EFH). 13.3.3. Consolidation Settlement 1) It is acceptable to use 1-D primary consolidation settlement for embankment. ) The loading of the embankment shall be based on EFH (no surcharging) or GFH (with surcharging, see Section9.4) 3) One dimensional primary consolidation settlement can be estimated using the expression : ρ c = C σ ' n r vc C vf [ log + log i= 1 1+ eo σ ' vo 1+ eo σ ' vc C σ ' ] H i

Page 5 of 8 where ρ c = Consolidation Settlement Magnitude (m) σ vo = Initial vertical effective stress σ vf = Final vertical effective stress = σ vo + Δ σ v σ vc σ vc = Preconsolidation Pressure / Yield Stress H i = Initial thickness of incremental soil layer, e o = Initial voids ratio C C = Compression Index C r = Recompression Index 4.5 4.0 3.5 Settlement Net Fill Actual Fill Thickness (m) 3.0.5.0 1.5 Actual Fill Thickness 1.0 0.5 Settleme Net Fill 4) The degree of consolidation, U v is a function of the time factor, T v where : Where 0.0 0.0 0.5 1.0 1.5.0.5 Settlement/ Net Fill (m) Settlement / Net Fill T v = c v t / H D c v = Coefficient of consolidation (m /year) t = Time following application of loading (year) H D = Drainage path length (m) (e.g. for soft clay of 0m, two way drainages [up and down], the H D is 10m) 5) The average degree of consolidation as a function of time factor for Terzaghi s theory of consolidation by vertical flow can be expressed as : U v = 4TV π

Page 6 of 8 for T v = c v t / H D < 0. U v 8 π T = 1 exp π 4 V for T v = c v t / H D 0. 6) In order to calculate actual fill height properly (EFH or GFH), different pressure can be applied to obtain different settlement for each borehole or zone. The results are used to plot the Settlement/Net Fill vs Actual Fill Thickness. The total settlement in this plot shall include Immediate settlement + Consolidation settlement. From the plot, from the net fill, the total settlement and actual fill thickness can be obtained. 13.3.4. Secondary Compression ρ S C n α = [ i= 1 1+ ep log( t)] H i where ρ s = Secondary Compression Magnitude (m) H i = Initial thickness of incremental soil layer, i of n. e p = Voids ratio at the end of primary consolidation C α = Secondary Compression Index. t = Time for calculation. 13.4. DESIGN OF SURCHARGE Surcharging is to subject the ground to higher pressure than that during the service life in order to achieve a higher initial rate of settlement thus reducing long term settlements. When designing surcharge, three major issues need to be addressed : Duration required for surcharging. Height of extra fill on top of the embankment required for surcharging. Bearing capacity check for the embankment at the edge with surcharged fill. The gross thickness of the fill which include Embankment Fill Height (EFH) and Surcharge Fill (SF) is termed Gross Fill Height (GFH). GFH = EFH + SF (m) Total Pressure Action, PGFH = EFH x γ bulk(fill) + SF x γ bulk(surcharge) The design process can be summarised as follows : 1) Determine the long term total settlement, (ρ T ) [Section 9.3] of the embankment under loading from Embankment Fill Height (EFH) [Section 9.]. ) Determine the duration allowed (T -surcharge ) for surcharging. This will depend on the project development schedule. 3) Obtain the total settlement vs time plot for different gross fill height (GFH) as follows:

Page 7 of 8 4) Based on the figure below, using the Total Settlement (ρ T ) from the EFH and the Allowed Surcharge Duration, T-surcharge, the Gross Fill Height (GFH) required to achieve the total settlement in the allowable time frame can be determined. 5) If vertical drains are used, this method can also be used with minor adjustment for vertical spacing, and more rapid rate of settlement. Months Time (year) 0 5 10 15 0 0 0 50 50 Settlement (mm) 500 750 1000 150 1500 500 750 1000 150 1500 Long Term Total Settlement of EFH, ρ T 1750 000 50 1750 000 50 LEGEND Fill = 1.0m Fill =.0m Fill = 3.0m Fill = 4.0m Fill = 5.0m 500 500 0 5 10 15 0 Allowed Surcharge Duration, T -surcharge 13.5. STABILITY ANALYSIS 1) For stability analysis, at least two stages shall be checked : (a) Short Term (Total Stress) using Undrained Shear Strength (s u ). (b) Long Term (Effective Stress) using Drained Strength Parameters (c -φ ). ) The required factor of safety (FOS) are as follows : (a) Short Term, FOS = 1. to 1.3 (if confidence on strength, use 1.) (b) Long Term, FOS = 1.4 to 1.5 (1.4 can be used in Geoguide) 3) At least two types of potential failure plane shall be checked : (a) Circular (Modified Bishop) (b) Non-Circular or Wedge Method (Modified Janbu or Morgenstern & Price or Sarma) Note : (1) Normally Wedge Method will produce lower FOS compared to Circular Method. () Should select proper boundary (boxes) for the Wedge analysis, if possible should start with circular method first to determine potential failure zones. 4) In stability analysis the following dimension shall be used : (a) The height of the embankment shall be : Embankment Fill Height (EFH), if no surcharging.(section 9.) Gross Fill Height (GFH), if surcharging. (Section 9.4) (b) At least 10kPa surcharge loading (traffic, machineries, etc.) on top of the embankment (acting pressure) (c) The magnitude of immediate settlement (both in the Soft Clay and Sand Layers) should be included in the Embankment Fill Height (EFH) to simulate settlement during Note : (1) For embankment construction, normally surcharging with or without vertical drains are required.

Page 8 of 8 () The magnitude of immediate settlement (both in the Soft Clay and Sand Layers) should be included in the EFH or GFH to simulate settlement during construction so that the stability analysis do not under estimate the weight of the embankment. 5) General guidelines for the strength parameters of the well-compacted predominantly granular fill materials is c = 0 to 5kPa, φ =8 to 30. It is recommended to carry out shear box test on the well-compacted fill materials to obtain representative parameters. 13.6. Selection of Ground Treatment for Stability of the Embankment Preliminary selection of the ground treatment method to satisfy stability requirements for construction of the embankment listed in priority are as follows : 13.6.1. Priority 1 : 1) Counterweight Berms (should have sufficient ROW and fill materials are sufficient at site) ) Partial Soft Soil Replacement (should be limited to not more than 4m deep if possible) 3) Combination of (a) and (b) 13.6.. Priority : 1) Staged Construction (With or Without Vertical Drains) (Note : need to validate gain in strength for each stage of filling) ) Geosynthetics reinforcement (high strength geotextile). 3) Combination of Priority 1 with (d) or (e). 13.6.3. Priority 3 : 1) Piled Embankment using slab system (require transition piles between piled and unpiled embankment) ) EPS 3) Stone Columns 4) Dynamic Replacement (only if soft clay is shallow) Note : Refer to : Gue, S.S. and Tan, Y.C. (001) Geotechnical Solutions for High Speed Track Embankment A Brief Overview Technical Seminar Permanent Way Institution Annual Convention 001, Kuantan. 8-9 September 001.