The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

Similar documents
The World Bank Ho Chi Minh City Green Transport Development (P126507)

The World Bank China: Qinghai Xining Urban Transport Project (P127867)

Public Disclosure Copy. Implementation Status & Results Report CN Yunnan Honghe Prefecture Diannan Center Urban Transport (P101525)

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

Public Disclosure Copy

The World Bank Uganda Energy for Rural Transformation III (P133312)

Public Disclosure Copy

Public Disclosure Copy

Name Previous Rating Current Rating

The World Bank Transport Connectivity and Asset Management Project (P132833)

The Project s Development Objective (PDO) is to promote environmentally sustainable urban transport in India and to improve the usage of

The World Bank Local and Regional Competitiveness Project (P154263)

Public Disclosure Copy

Public Disclosure Copy. Implementation Status & Results Report UGANDA North Eastern Road-corridor Asset Management Project (NERAMP) (P125590)

Sri Lanka Strategic Cities Development Project (P130548)

SÃO PAULO METRO LINE 4 (PHASE 2) (P106390)

The World Bank Indonesia: Geothermal Energy Upstream Development Project (P155047)

Public Disclosure Copy

The World Bank China Wuhan Second Urban Transport (P112838)

The World Bank. Kenya: Off-grid Solar Access Project for Underserved Counties (P160009) Key Dates. Project Development Objectives.

Public Disclosure Copy

Public Disclosure Copy. AFCC2/RI-The Eastern Electricity Highway Project under the First Phase of the Eastern Africa Power

EC Ibarra Transport Infrastructure Improvement Project (P147280)

Public Disclosure Copy

West Bank and Gaza: Finance for Jobs (P151089)

The World Bank Can Tho Urban Development and Resilience (P152851)

The World Bank Zambia Water Resources Development Project (P114949)

The World Bank Guilin Integrated Environment Management (P133017)

The World Bank Regional Infrastructure Development Fund (P154947)

Public Disclosure Copy

The World Bank Sri Lanka Agriculture Sector Modernization Project (P156019)

The World Bank Integrated Forest Ecosystem Management (P151102)

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy

The World Bank Second Rural Transport Improvement Project (P123828)

The World Bank Sri Lanka Agriculture Sector Modernization Project (P156019)

The World Bank Heilongjiang Cold Weather Smart Public Transportation System (P133114)

Public Disclosure Copy

Urban Water Supply Project (P156739)

The World Bank Zambia Water Resources Development Project (P114949)

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy

The World Bank Bangladesh Modern Food Storage Facilities Project (P120583)

Public Disclosure Copy. Implementation Status & Results Report KH - Livelihood Enhancement and Association of the Poor Project (LEAP) (P153591)

Public Disclosure Copy

Public Disclosure Copy

The World Bank Local and Regional Competitiveness Project (P154263)

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank Ethiopia: Transport Systems Improvement Project (TRANSIP) (P151819)

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy

Key Dates. Global Development Objectives. Components. Overall Ratings. Implementation Status and Key Decisions

The World Bank Georgia National Innovation Ecosystem (GENIE) Project (P152441)

Public Disclosure Copy. Implementation Status & Results Report Vietnam: Project for Improved Land Governance and Databases (VILG) (P154387)

PAMSIMAS Support Trust Fund (P116236)

The World Bank Cusco Regional Development (P117318)

The World Bank Ethiopia: National Quality Infrastructure Development Project (P160279)

Public Disclosure Copy. Implementation Status & Results Report DJ-Rural Community Development and Water Mobilization Project (PRODERMO) (P117355)

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

Public Disclosure Copy

The World Bank Second Ho Chi Minh City Environmental Sanitation Project (P127978)

Public Disclosure Copy

Ethiopia: Transport Systems Improvement Project (TRANSIP) (P151819)

The World Bank. Key Dates. Project Development Objectives. Components. Overall Ratings. Public Disclosure Authorized

Public Disclosure Copy

Public Disclosure Copy

The World Bank Bangladesh Weather and Climate Services Regional Project (P150220)

Public Disclosure Copy

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

Relaunching Agriculture: Strengthening Agriculture Public Services II Project (GAFSP - IDA) (P126744)

Public Disclosure Copy. Implementation Status & Results Report Cambodia Global Partnership for Education Second Education Support Project (P144715)

Public Disclosure Copy. Implementation Status & Results Report Girls Education and Womens Empowerment and Livelihood Project (P151451)

Public Disclosure Copy

The World Bank OECS Regional Tourism Competitiveness (P152117)

The World Bank Tamil Nadu Sustainable Urban Development Program (P150395)

The World Bank. Key Dates. Project Development Objectives. Components. Implementation Status & Results Report. Key Project Dates

Public Disclosure Copy

The World Bank JM Youth Employment in Digital and Animation Industries (P148013)

Public Disclosure Copy

The World Bank MA- Noor Ouarzazate Concentrated Solar Power Project (P131256)

The World Bank Earthquake Housing Reconstruction Project (P155969)

Second Tamil Nadu Road Sector Project (P143751)

The World Bank Ghana - Maternal, Child Health and Nutrition Project (P145792)

The World Bank. DRC Electricity Access & Services Expansion (EASE) (P156208) Key Dates. Project Development Objectives. Components.

Sierra Leone Energy Access Project - Sierra Leone Infrastructure Development Fund (P126180)

The World Bank Livestock Sector Development Support Project (P159476)

The World Bank. Key Dates. Project Development Objectives. Components. Implementation Status & Results Report. Key Project Dates

The World Bank Swaziland Health, HIV/AIDS and TB Project (P110156)

Public Disclosure Copy

The World Bank Dam Operational Improvement and Safety (P096532)

Public Disclosure Copy

The World Bank Pakistan: Third Punjab Education Sector Project (P154524)

Key Dates. Project Development Objectives. Components. Overall Ratings

Public Disclosure Copy

The World Bank BiH Floods Emergency Recovery Project (P151157)

Transcription:

Public Disclosure Authorized EAST ASIA AND PACIFIC Vietnam Transport & ICT Global Practice IBRD/IDA Specific Investment Loan FY 2008 Seq No: 16 ARCHIVED on 28-Dec-2016 ISR26429 Implementing Agencies: Hanoi Urban Transport Development Project Management Unit Public Disclosure Authorized Key Dates Key Project Dates Bank Approval Date:03-Jul-2007 Planned Mid Term Review Date:15-Nov-2011 Original Closing Date:31-Dec-2013 Project Development Objectives Effectiveness Date:22-Apr-2008 Actual Mid-Term Review Date:07-Jun-2012 Revised Closing Date:31-Dec-2016 Public Disclosure Authorized Public Disclosure Authorized Project Development Objective (from Project Appraisal Document) The development objective of the IDA Credit is to increase urban mobility in targeted areas in Hanoi by (i) increasing the use ofpublic transport in two existing and one new corridors; and (ii) reducing travel times by all modes between the city center and thewest and northwest sections of the city (west of West Lake). Has the Project Development Objective been changed since Board Approval of the Project Objective? No Hanoi Urban Transport Development Project GEF component (P085393) Global Environmental Objective (from Project Appraisal Document) GEF strategic objectives are to promote a shift to more environmentally-sustainable transport modes and urban development plans, and to promote the replication of these approaches in the country and region. Its global environment objective is to lower Hanoi's transport-related greenhouse gas emissions, relative to a business-as-usual scenario. Has the Global Environmental Objective been changed since Board Approval of the Project Objective? No Components Name Bus Rapid Transit:(Cost $99.88 M) Road Infrastructure and Sustainable Urban Planning:(Cost $194.33 M) Page 1 of 8

Institutional Development Component:(Cost $10.49 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions Following the Bank s last mission to Hanoi in May 2016, there have been several developments towards eventual achievement of the PDO and GEO: 1. For the Road component, the Ring Road 2 has been open to traffic since January 18, 2016, and the travel time has significantly reduced in the north-west area of the city, meeting one of the key outcome indicators. The road also contributes to the reduction of travel time from the city center to the airport. 2. For the BRT component, civil work contracts for 21 stations and 2 terminals (Kim Ma and Yen Nghia), as well as strengthening of Lang Ha flyover, have been completed. BRT vehicles have been delivered and BRT drivers have been trained by the vehicle supplier. Traffic Management Plan and BRT Service Plan have been approved by the DOT and PC, and based on these plans, TRAMOC (Public Transport Management & Operation Centre), TRANSERCO (BRT operator under contract with TRAMOC), and the Traffic Police are preparing for the launch of service in January, 2017. Technical testing for BRT (operation of vehicles without passengers) has been conducted since 15 December 2016. The BRT system is planned to put into operation on 1st January 2017 with the frequency of 5 minutes during rush hour. The Credit has disbursed approximately US$ 90.52 million to date (or 58% of the amount in USD or 63% of the amount in SDR due to changes in SDR:USD exchange rate). The Grant has disbursed approximately US$ 5.95 million to date (or 61% of the amount). There is an amount of US$12m un-used IDA fund under the project will be cancelled. The Department of Transport and WB task team co-chaired a press meeting on December 19, 2016 on BRT operation and received positive/constructive comments/questions from public. A conference on urban public transport under the GEF component, focusing on BRT, was organized by the Ministry of Construction of Vietnam, on October 21, 2016. The conference discussed the lessons learned from ongoing BRT projects financed by the Bank in Vietnam (Hanoi, Ho Chi Minh City, and Da Nang) and other countries (China, Korea, and India), and how Vietnamese cities can succeed in developing public transport systems. International experiences, both successes and failures, were also presented and discussed. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Substantial Substantial Macroeconomic -- Moderate Moderate Sector Strategies and Policies -- Moderate Moderate Technical Design of Project or Program -- Substantial Substantial Institutional Capacity for Implementation and Sustainability -- Substantial Substantial Fiduciary -- Moderate Moderate Environment and Social -- Substantial Substantial Stakeholders -- Substantial Substantial Other -- -- -- Page 2 of 8

Overall -- Substantial Substantial Results Project Development Objective Indicators PHINDPDOTBL Increase in the use of public transport in two exisiting and one new corridor: Number of daily BRT/bus boardings. (Text, Custom) Value Kim Ma - Khuat Duy Tien: 30,000; Khuat Duy Tien - Yen Nghia: 50,000; Dong Anh - West of West Lake: 25,000 Kim Ma - Khuat Duy Tien: 32.730; Khuat Duy Tien - Yen Nghia: 64.970; Dong Anh - West of West Lake: 19,380 Kim Ma - Khuat Duy Tien: 32.038; Khuat Duy Tien - Yen Nghia: 63.598; Dong Anh - West of West Lake: 27,518 Kim Ma - Khuat Duy Tien: 37,000; Khuat Duy Tien - Yen Nghia: 61,000; Dong Anh - West of West Lake: 28,000 Date 22-Oct-2013 30-Dec-2015 02-Nov-2016 31-Dec-2016 PHINDPDOTBL Number of BRT riders whose alternate mode would have been a private motorized vehicle/taxi (Text, Custom) Value 0.00 0.00 0.00 10% Date 22-Oct-2013 19-May-2016 02-Nov-2016 31-Dec-2016 PHINDPDOTBL User satisfaction on BRT system (all persons) (Percentage, Custom Supplement) Value 0.00 0.00 0.00 55.00 PHINDPDOTBL User satisfaction on BRT System for women (Percentage, Custom Supplement) Page 3 of 8

PHINDGEOTBL Value 0.00 0.00 0.00 60.00 Overall Comments The BRT is now under technical testing (operation without passengers) and will be put into full operation in early 2017. The indicators on user satisfaction will be made in ICR Global Environmental Objective Indicators Hanoi GHG emissions saved through 2025 (project corridor) (Text, Custom) Value 1.5m tons 1.62 tons 1.62 tons 1.5m tons Date 01-May-2008 15-Apr-2015 15-Apr-2015 31-Dec-2016 Overall CommentsPHGEOCMTS Intermediate Results Indicators Travel time by bus from Kim Ma to Khuat Duy Tien (Text, Custom) Value 50 min 32 min 30 min 30 min Date 22-Oct-2013 09-May-2016 02-Nov-2016 31-Dec-2016 Page 4 of 8

Travel time by bus from Khuat Duy Tien to Yen nghia (Text, Custom) Value 45 min 34 min 33 min 35 min Date 22-Oct-2013 09-May-2016 02-Nov-2016 31-Dec-2016 Travel time by bus Cau Giay to Dyke Road at Nhat Tran (Minutes, Custom) Value 28.00 21.00 21.00 22.00 Date 22-Oct-2013 09-May-2016 02-Nov-2016 31-Dec-2016 Travel time by motor cycle Nhat tan to Cau Giay (PM peak) (Minutes, Custom) Value 21.00 18.00 11.00 15.00 Date 22-Oct-2013 15-Dec-2015 02-Nov-2016 31-Dec-2016 Adoption of land use TA- Draft Final Report developed - Final Report approved (Number, Custom) Value 0.00 0.00 1.00 1.00 Date 22-Oct-2013 22-Sep-2015 30-Jun-2016 30-Jun-2016 Page 5 of 8

Strengthened capacity for planning multi-modal public transport system (Number, Custom) Value 0.00 0.00 1.00 1.00 Date 22-Nov-2007 09-May-2016 02-Nov-2016 31-Dec-2016 Step 1: establishment of Multi-Modal Public Transport Committee (Number, Custom Breakdown) Value 0.00 1.00 1.00 1.00 Date 22-Oct-2013 31-Jul-2013 31-Dec-2013 31-Dec-2016 Step 2: Draft final report on establishment of PTA developed. (Number, Custom Breakdown) Value 0.00 1.00 1.00 1.00 Date 22-Oct-2013 30-Jun-2015 30-Jun-2015 31-Dec-2016 Number of DAPM staff trained (Number, Custom) Value 0.00 61.00 61.00 60.00 Date 22-Oct-2013 09-May-2016 02-Nov-2016 31-Dec-2016 Page 6 of 8

Coordinated institutional system for AQM policy making in place based on monitoring system and emission data (Number, Custom) Value 0.00 0.00 1.00 1.00 Date 22-Nov-2007 09-May-2016 02-Nov-2016 31-Dec-2016 Number of staff trained, skills assessment (Number, Custom Breakdown) Value 0.00 128.00 128.00 85.00 Date 22-Nov-2007 09-May-2016 02-Nov-2016 31-Dec-2016 Number of replication activities (workshop, studies in other Vietnam cities, study tours) (Number, Custom Breakdown) Value 0.00 5.00 6.00 6.00 Date 22-Nov-2007 09-May-2016 21-Oct-2016 31-Dec-2016 Overall Comments Indicators will be updated during ICR period. Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P083581 IDA-43470 Effective USD 155.21 155.21 0.00 90.52 55.88 58% P085393 TF-58293 Effective USD 9.80 9.80 0.00 5.95 3.85 61% Key Dates (by loan) Page 7 of 8

Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P083581 IDA-43470 Effective 03-Jul-2007 22-Nov-2007 22-Apr-2008 31-Dec-2013 31-Dec-2016 P085393 TF-58293 Effective 22-Nov-2007 22-Nov-2007 22-Nov-2007 31-Dec-2013 31-Dec-2016 Cumulative Disbursements Restructuring History Level Approved on 11-Feb-2014,Level 2 Approved on 11-Jun-2015 Related Project(s) P085393-Hanoi Urban Transport Development Project GEF component Page 8 of 8