+LJK7HPSHUDWXUH 6XSHUFRQGXFWLQJ&DEOH

Similar documents
Hydra Fault Current Limiting HTS Cable to be Installed in the Consolidated Edison Grid

TYPE TESTING OF A 13.2 KV, 69 MVA TRIAX HTS CABLE

Superconducting cables Development status at Ultera

Status and Progress of a Fault Current Limiting HTS Cable To Be Installed In The Consolidated Edison Grid

INSTALLATION AND COMMISSIONING OF TRIAX HTS CABLE

Commissioning testing of a 1 MVA Superconducting transformer featuring 2G HTS Roebel cable

Progress in Scale-up of 2G HTS Wire at SuperPower Part III

Cryogenic and Electrical Test Results of a 30 M HTS Power Cable

The development of a Roebel cable based 1 MVA HTS transformer

Testing of Single Phase Short Sample Cable Core Made with YBCO Conductors

Latest Status of High Temperature Superconducting Cable Projects

R&D of 22.9kV/50MVA HTS Transmission Power Cable in Korea

Fault Current Limiter Based on Coated Conductor

Applications Using SuperPower 2G HTS Conductor

High-Performance 2G HTS Wire for an Efficient and Reliable Electricity Supply

Critical Current Properties of HTS Twisted Stacked-Tape Cable in Subcooled- and Pressurized-Liquid Nitrogen

Conductor Requirements for Superconducting Fault Current Limiters

Superconducting Cables

Fault Current Limiters

Experiences with Superconducting Cable & Fault Current Limiter in a German City Center Mark Stemmle

Feasibility of HTS DC Cables on Board a Ship

Superconductivity for Electric Systems DOE 2006 Wire Development Workshop

Superconducting Fault Current Limiters

The Present Status and Prospective of the power transmission by Superconductors in China

Risk mitigation in the development of a Roebel cable based 1 MVA HTS transformer

Transmission Level HTS Fault Current Limiter

TRANSMISSION LINES. All aluminum alloy conductor (AAAC) Aluminum conductor alloy reinforced (ACAR)

SPECIFICATION SS 51/9 400KV COUPLING CAPACITORS FOR POWER LINE CARRIER SYSTEM

EPRI Technology Watch 2010 Superconducting Cables Fault Current Limiters

Fatima Michael College of Engineering & Technology

Current Lead Optimization for Cryogenic Operation at Intermediate Temperatures. L. Bromberg, P.C. Michael, J.V. Minervini and C.

O Plus Dry Bushing 69 kv system, 350 kv BIL, 3000 A. Table of contents

For the electronic measurement of current: DC, AC, pulsed..., with galvanic separation between the primary and the secondary circuit.

Second Generation HTS Wire for Electric Power Applications

2 nd Generation High-Temperature Superconducting Wires for Fault Current Limiter Applications

TRANSFORMERS. Pascal Tixador. Grenoble INP - Institut Néel / G2Elab. Introduction

HiLumi LHC FP7 High Luminosity Large Hadron Collider Design Study. Milestone Report. Cryogenic Scenarios for the Cold Powering System

Status of HTS Projects at SuperPower: 2G HTS Wire and Cable

New Generation of DC Power Transmission Technology Using HTS Cables

Impedance relay and protection assemblies

Superconductivity for Electric Systems 2006 Annual DOE Peer Review

Superconducting Fault Current Limiters

Short-circuit protection to a fault: Superconducting fault current limiters

Progress Towards A High-field HTS Solenoid

Varistor Voltage. D: Disk, S: Square S:Straight, C:Crimped, I:Inner, Y:Y kink Size(mm) B: Bulk (Standard lead 20mm min.)

Magnetic Property Measurement System

New Transmission Options Case Study Superconductor Cables. Transmission Policy Institute Sheraton Downtown Denver, Colorado April 20-21, 2011

MASSACHUSETTS INSTITUTE OF TECHNOLOGY DEPARTMENT OF MECHANICAL ENGINEERING DEPARTMENT OF NUCLEAR ENGINEERING 2.64J/22.68J , : & HTS

Grounding and Shielding

Russian Development Program on HTS Power Cables

Railway Research. Study of Superconducting Fault Current Limiter Device in a AC Railway System. 1. Introduction. International Journal of

Gesellschaft für Schwerionenforschung mbh (GSI), Planckstrasse 1, D Darmstadt, Germany

Development of 2 MVA Class Superconducting Fault Current Limiting Transformer (SFCLT) with YBCO Coated Conductors

2G HTS Wire and High Field Magnet Demonstration

DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING QUESTION BANK

An Investigation of the Current Distribution in an HTS Triaxial Power Cable and its Operational Impacts on a Power System

For the electronic measurement of current: DC, AC, pulsed..., with galvanic separation between the primary and the secondary circuit.

For the electronic measurement of current: DC, AC, pulsed..., with galvanic separation between the primary and the secondary circuit.

URD Cable Fault Prediction Model

Inductively Coupled Pulsed Energy Extraction System for 2G Wire-Based Magnets

Digital Current Transducer HO-SW series I P N = A. Ref: HO 100-SW; HO 150-SW; HO 200-SW; HO 250-SW

2G HTS Wire Status in the USA

Request Ensure that this Instruction Manual is delivered to the end users and the maintenance manager.

RESULTS OF ON-GRID OPERATION OF SUPERCONDUCTOR DYNAMIC SYNCHRONOUS CONDENSER

INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad

SSC-JE EE POWER SYSTEMS: GENERATION, TRANSMISSION & DISTRIBUTION SSC-JE STAFF SELECTION COMMISSION ELECTRICAL ENGINEERING STUDY MATERIAL

O Plus Dry Bushing 25 kv system, 150 kv BIL, 3000 A

THE CERN CRYOGENIC TEST FACILITY FOR THE ATLAS BARREL TOROID MAGNETS

Overhead lines. 110 kv wood tower with guy wires

Grid Issues and Challenges Addressed by High Temperature Superconductor (HTS) Technology

Instruction. Vacuum Circuit Breaker Operator Module. Type 3AH 4.16kV to 38kV. Power Transmission & Distribution

Report on PIAVE G. Bisoffi

KIT-ENERGY CENTRE. KIT The research University in the Helmholtz Association

Gas Discharge Tube (GDT) Data Sheet

HIGH ENERGY DENSITY CAPACITOR CHARACTERIZATION

Design and preliminary results of a prototype HTS SMES device

Model M3484 Industrial Line Noise Filter Module Customer Reference Manual


Keywords: Superconducting Fault Current Limiter (SFCL), Resistive Type SFCL, MATLAB/SIMULINK. Introductions A rapid growth in the power generation

Alternating Current (AC): Alternating Current is electric current that reverses directions at regular intervals.

Status and Future Direction of HTS Power Application in KEPCO

Ref: HLSR 16-PW; HLSR 32-PW; HLSR 40-PW-000; HLSR 50-PW-000,

Thermal and temperature cycling tests on solid dielectric switches, interrupters, and reclosers

For the electronic measurement of current: DC, AC, pulsed..., with galvanic separation between the primary and the secondary circuit.

Independent, accredited testing station Member laboratory of STL and LOVAG TEST CONFIRMATION. on the given range of performed tests

Opus: University of Bath Online Publication Store

3/31/2006 9:36:15 AM RECENT DEVELOPMENT SUPERCONDUCTIVITY: THE FUTURE OF POWER TRANSMISSION

Development of superconducting undulators at the Advanced Photon Source

INSTITUTE OF AERONAUTICAL ENGINERING DUNDIGAL ELECTRICAL AND ELECTRONICS ENGINEERING

Power Engineering Institute Warsaw University of Technology

CURRENT LEADS FOR THE LHC MAGNET SYSTEM

STUDIES ON LIGHTNING CHARACTERISTICS

Analysis of Very Fast Transients in EHV Gas Insulated Substations

RECENT DEVELOPMENT OF HIGH-TEMPERATURE SUPERCONDUCTING (HTS) CABLE IN SUMITOMO ELECTRIC INDUSTRIES, LTD.

Experimental Investigation of High-Temperature Superconducting Magnet for Maglev

EasyDry transformer bushing Better performance made easy. Power and productivity for a better world TM ABB

THE DIMENSIONING OF ELECTRICAL CONDUCTORS FOR USE IN "PANEL BOARDS" ADDRESSED TO HAZARDOUS AREAS - PART THREE

UNIT I - INTRODUCTION SYLLABUS

DATA SHEET General Purpose Thick Film Chip Resistor CR Series

Thermal analysis of superconducting undulator cryomodules

Transcription:

+LJK7HPSHUDWXUH 6XSHUFRQGXFWLQJ&DEOH 2000 Annual Peer Review Superconductivity Program for Electric Systems U.S. Department of Energy July 17-19, 2000 Washington, DC World s First Industrial Field Test of HTS Cable Delivers Power To Industrial Customer 2 1

Presentation Outline Southwire Activities (David Lindsay, Southwire) Introduction 30-m Cable Installation 30-m Cable Operation FY 2000 Results 30-m Cable Off-Line Testing (Mike Gouge, ORNL) 5-m Cable Research Component Development Cryogenic Dielectrics Research (John Stovall, ORNL) FY 2000 Performance / FY 2001 Plans Technology Integration Summary 3 Project Participants at Southwire and ORNL Southwire John Armstrong Zack Butterworth Hugh Butler Randy Denmon Dwain Gosdin R. L. Hughey Gary Hyatt Donnie Kittle Kim Knuckles David Lindsay Steve Owens Ron Martin Sammy Pollard David Reece Mark Roden Uday Sinha Jerry Tolbert Lewis Waters Nick Ware Oak Ridge National Laboratory Glenn Barber Larry Baylor Bob Benson Jonathan Demko Alvin Ellis Paul Fisher Chris Foster Mike Gouge Robert Hawsey Randy James Winston Lue Patrick Martin Marshall Pace Vaughn Patania Isidor Sauers Bill Schwenterly Dennis Sparks John Stovall 4 2

Other Project Participants Argonne National Laboratory EURUS - Plastronic Georgia Transmission IGC Superpower Southern Cal Edison Southern Company Subcontractors and Consultants 5 SPI Project Goal (February 1997) First U.S. Industrial SPI Cable Installation At the end of the three year project, a high temperature superconducting (HTS) cable will be providing electric service to a large industrial customer at 12.4-kV and 1.25-kA. Operation of 30-meter three-phase cable in FY 2000 at Southwire Headquarters in Carrollton, Georgia. 6 3

Cable Cross Sectional View Features Magnetic field shielded. Both conductor and dielectric are wrapped from tapes. Cryogenic dielectric reduces size and increases current carrying capacity. Flexible cable to allow reeling 7 Southwire Project Status FY 2000 goals have been completed. Cables installed Aug 99 Cryogenic system delivered Sept. 99 Cable terminations assembled Sept. 99 Cryogenic system tested Oct. 99 Off-line electrical testing Nov/Dec 99 Cables energized Jan. 5, 2000 Dedication ceremony Feb. 18, 2000 Continuous operation started Feb. 21, 2000 Off-line research June 7-30, 2000 8 4

HTS Cable Site Progress Under construction, as shown last year In operation this year 9 Cables Installed - 8/24/99 Site ready for cable installation Phase 3 set in place 10 5

Cryogenic System Delivered - 9/2/99 PHPK, Inc. As delivered Installed and operational 11 Termination Assembly - 9/23/99 Assembly in progress Assembly completed 12 6

System Testing Oct. - Dec. 1999 Cryogenic system acceptance and testing Off-line electrical testing of superconducting cables Circuit breakers and protection system 13 Cables First Energized on January 5, 2000 Phase 3 Phase 2 Phase 1 Electrical Control and Protection Panel for HTS Cables 14 7

Computer (PLC) Controlled Cryogenic System 15 Dedication Ceremony - Feb. 18, 2000 Georgia Governor and Energy Secretary 16 8

Electrical Block Diagram of SW HTS Cable Transmission Distribution Customer Loads 115 kv HTS Cable Three Manufacturing Plants Substation 40 MVA Existing Overhead Lines 12.4 kv Switching Configurations 1. Overhead only 2. HTS Cable only 3. Both Copper Rod Mill 17 Substation Two way transmission feed one from Yates Power Plant one from Bremen switchyard 40 MVA Two 20 MVA matched unit, non regulating, transformers 115 kv high side / 12.4 kv low side Two 12.4 kv feeders out Switchyard is part of Integrated Transmission System and provided by Georgia Power 18 9

Two 12.4 kv Feeders Exiting Substation Southwire feeder (left) HTS cable on SW feeder Copper Division Southwire feeder (right) Both 1033.5 ACSR (aluminum conductor steel reinforced) 12.4 kv protection on Southwire feeder is a vacuum breaker with a reclosing relay set for three shot before lock out. Symmetrical 3 phase fault current is around 14,000 amps at 12.4 kv 19 HTS May Phase 2000 - HTS 1 Phase Current 1 for (1 hour May data) 2000 1400 1200 30 days of continuous operation 1000 Current, amps rms 800 600 400 200 Plant shutdown for maintenance Phase 1 2 3 Amps Amps Amps Average 853 863 845 Std Dev 119 116 118 Min 219 244 218 Max 1,084 1,088 1,073 0 4/30/2000 5/7/2000 5/14/2000 5/21/2000 5/28/2000 20 10

HTS Phase 1 Return Temperature for May 2000 81 80 79 Temperature, K 78 77 76 75 1 K 74 4/30/2000 5/7/2000 5/14/2000 5/21/2000 5/28/2000 21 70 HTS Phase 1 Return Pressure for May 2000 66 Pressure,psia 62 58 4 psia 54 50 4/30/2000 5/7/2000 5/14/2000 5/21/2000 5/28/2000 22 11

HTS Phase 1 Current for May 9, 2000 1200 1100 Current, amps rms 1000 900 800 700 600 12:00 AM 6:00 AM 12:00 PM 6:00 PM 12:00 AM 23 HTS Phase 1 Return Temperature for May 9, 2000 81 80 79 Temperature, K 78 77 76 75 1 K 74 12:00 AM 6:00 AM 12:00 PM 6:00 PM 12:00 AM 24 12

HTS Phase 1 Return Pressure for May 9, 2000 70 66 Pressure, psia 62 58 4 psia 54 50 12:00 AM 6:00 AM 12:00 PM 6:00 PM 12:00 AM 25 This field demonstration has successfully shown the utility application of superconducting cables at distribution voltages and high currents. Potential utility applications Substation to customer Substation to substation Extended substation bus Substation express feeder Generating unit to step-up transformer 26 13

Presentation Outline Southwire Activities (David Lindsay, Southwire) Introduction 30-m Cable Installation 30-m Cable Operation FY 2000 Results 30-m Cable Off-Line Testing (Mike Gouge, ORNL) 5-m Cable Research Component Development Cryogenic Dielectrics Research (John Stovall, ORNL) FY 2000 Performance / FY 2001 Plans Technology Integration Summary 27 FY 2000 Objectives for ORNL (from FY 1999 Peer Review) Conduct cable bending and short circuit tests on the 5-m cables. Continue cryogenic dielectric aging tests. Assist Southwire with the final construction, installation, checkout, testing, and operation of the SPI 30-m, 3-phase HTS cable. Extend HTS cable capability in partnership with Southwire researchers by: developing a cable splice, improving the cable cryostat cryogenic insulation, design a cable termination for higher operating voltages, and examine cryogenic dielectric system requirements for higher voltage HTS cables. 28 14

FY 2000 Results 30-m Cable Demonstration (Southwire lead) Assisted Southwire with assembly of 3-phase, 30-m cable (Aug- Oct 99) Joint Southwire/ORNL effort in commissioning cable and cryogenics system (Sep-Dec 99) Joint Southwire/ORNL effort in 30-m cable demonstration and tests (dc V-I, ac withstand, temperature and flow scans, etc.) 5-m Cable Research (ORNL lead) successful over-current tests (~10 x) on 5-m cable impulse tested cable #2 and the terminations to ~ 90 kv (recoverable breakdown above 90 kv) bent 5-m cable and tested 29 FY 2000 Results (continued) HTS Cable Component Development design improvements to pressurized termination: heat loss reduced more robust to ambient conditions collaboration with NASA Kennedy Space Center Cryogenics Test Bed on low thermal loss, flexible cryostats. have designed and fabricated a 5-m cable with a splice developed and successfully tested model dielectric tape splice will test cold dielectric cable splice next month at ORNL cryogenic dielectric aging tests underway YBCO quench and stability studies 30 15

ORNL supported the 30-m, 3-phase, HTS cable demonstration at Southwire First use of HTS cables in an industrial application 31 ORNL assisted Southwire with the assembly of 30-m HTS cable terminations in Sept. 1999 32 16

Commissioning the 30-m cryogenic system Sept. - Oct. 1999 acceptance testing at Southwire in September 1999. commissioning in Oct-Nov 1999 support of software development for manual and automatic control functions system is quite reliable: minor equipment problems with some components: cryogenic valve actuator, control air compressor 33 Off-line testing of 30-m cables High voltage withstand DC voltage/current tests Nov. 1999 DC current load test DC voltage/current tests June 2000 to determine cable performance after 6 months of operation, after 4 to 6 cooldown and warm-up cycles, and under variable loading 34 17

High Voltage Withstand Test - 11/19/99 Voltage held for 30 minutes on each phase to test cable dielectric system. Phases 1 and 2 maintained at 166% of rated voltage without breakdown. Phase 3 maintained at 230% of rated voltage without breakdown. 35 Measured and Calculated Capacitance Capacitance- nf / m Phase 1 Phase 2 Phase 3 Measured 1.815 1.739 1.265 Calculated 1.778 1.778 1.207 Difference 2.1% -2.2% 4.8% Inductance - nh / m Phase 1 Phase 2 Phase 3 Calculated 31.4 31.4 38.2 Above values result in surge impedance for 30-m cable of about 4 ohms. 36 18

V-I curve & DC current load tests Nov./Dec. 1999 and June 2000 Voltage versus current (VI curve) was measured to determine the resistance of the superconducting cables and terminations. DC load current tests simulated average, rated, and emergency loading of superconducting cables. 37 Off-line average, rated, and emergency dc load current tests were conducted in Dec. 1999 1600 Phases 3 & 2 Phases 1 & 2 (6 to 8 hours at each dc current) 1400 1200 Current, dc amps 1000 800 600 400 Phases 1 & 2 52 hours 200 0 11/30/99 12/1/99 12/2/99 12/3/99 12/4/99 12/5/99 12/6/99 38 19

DC V-I curves in Nov. 1999 and June 2000 indicate no change in 30-m cable performance 0.6 0.5 0.4 Volts 0.3 0.2 0.1 Phase 3 (Nov 1999) Phase 2 (Nov 1999) Phase 3 (June 2000) Phase 2 (June 2000) linear fit 0 0 500 1000 1500 2000 2500 Current (A) 39 Testing of 30-m HTS Cables at Carrollton 3.5 5-m and 30-m Cable V-I Curves @ 77K 3 2.5 2 First 5-m cable First phase of 30-m cable 1.5 1 I c = 1090 A n = 3 I c = 2980 A n = 9 0.5 0-0.5 0 500 1000 1500 2000 2500 3000 3500 Testing was performed on the power and shield conductors in the cable cryostat with boiling liquid nitrogen cooling. Performance was as expected from the individual tape properties. 40 20

End-to-end cable dc resistance has been measured Fixed Resistance Variable dc Resistance with distance Fixed Resistance 3 Supply Terminations 3 Phase HTS Cable 3 Return Terminations 67 µ ohms per phase At 1250 amps No dc resistance At 2500 amps and 0.25 µv / cm 0.01 µ ohms per meter per phase 67 µ ohms per phase 41 5-m cable research facility at ORNL 42 21

5-m High Temperature Superconducting Cable Research Facility Status: July 2000 Facility upgrades complete impulse power supply upgraded from 100 to 200 kv (BIL tests) 25,000 A pulsed dc power supply commissioned (short circuit tests) pressurized terminations: improved cryogenic performance Adjacent test stands used for development of HTS tapes (BSCCO and YBCO) large capacity cryocooler with power supplies and data acquisition for ac loss, stability and quench testing ~ 20 cm warm bore, 6 T magnet (cooled by pulse-tube cryocooler) for quench and stability studies of HTS conductors 43 Facility upgrade - 200 kv impulse generator 44 22

5-m HTS cable #2 and terminations were impulse tested to ~90 kv Requirement is 110 kv for distribution-class cable Breakdown above 90 kv does no insulation damage Cable can recover if test voltage reduced to < 90 kv Tests indicative of transient breakdown in long liquid nitrogen path No damage evident in system when disassembled Will next test with different cable 45 Facility upgrade - 25,000 A, pulsed dc power supply for short circuit testing 46 23

Over-current testing of single HTS tapes A fault current simulation test was performed on a single HTS tape wound on a rigid former. Tape was cooled in an open liquid nitrogen bath. Pulsed currents of up to 10 x the critical current applied for up to 3 seconds. At 10 times the design current (each tape @ ~ 120 A), the data showed that the HTS still carries a significant fraction of the total current R/L (mohm/cm) 1 0.1 0.01 0.001 0.0001 10-5 HTS Tape Resistance at Current pulses R/L @ Critical current 0 50 100 150 200 250 300 I (A) R/L @300 K R/L @ 130 K 47 14000 Successful short circuit (10x) test of 5-m HTS cable I (A) HTSC000018 Vcb Vjt 6000 12000 5000 10000 4000 I (A) 8000 6000 3000 2000 V (mv) 4000 1000 2000 0 0-1000 0 2 4 6 8 10 Time (s) Figure shows HTS cable and joint voltage in response to a 12.8- ka, 2 sec over-current pulse to simulate a short to ground. Cable survived with no performance degradation over-currents up to 15 ka. Design current is 1.25 ka. 48 24

5-m HTS cable bending to simulate storage and shipment after manufacture Bent 5-m cable #2 in both directions Tested cable after bending to determine dielectric system integrity ac withstand test successful 49 Second generation pressurized termination (T2) developed An innovative new termination has been developed and refined the design uses liquid / gaseous nitrogen at few to 10 bar pressure the inner and shield conductor cold bushings are eliminated the vacuum pumping system, system pump-down and leak checking from the previous vacuum design T1 are eliminated simple flange and bus arrangement the concept is reliable and uses pressure rated components familiar to the utility industry heat losses have been reduced about a factor of 2 from the 6/99 T2 prototype 50 25

T2 (pressure termination) is more compact than T1 (vacuum termination) T1: T2: Neutral bushing Phase bushing 51 Testing of T2 (pressure termination) T2 terminations have been through many cooldown cycles both at ORNL and Southwire. Cooldown is efficient with no component being stressed by the rate of cooldown. High current runs: dc current scans to about 2500 amp on the center conductor. 10 x overcurrent to 13 ka for 2 s Performed an ac withstand test at 18 kv ac for 30 minutes. Impulse tested to ~90 kv. Measured heat loads and LN pressure drops. 52 26

Heat load of terminations has been reduced 500 Each termination has two leads - phase and neutral 400 Heat Load (watt) 300 200 100 0 T2 (1999), I=1250 A, 5-m T2 (2000), I=1000 A, 5-m T2 (2000), I=600 A, 30-m T2 (1999), I=0 A, 5-m T2 (2000), I=0 A, 5-m 53 Cable system heat loss has been measured Fixed Heat Loss Variable Heat Loss with distance and current Fixed Heat Loss 3 Supply Terminations 3 Phase HTS Cable, 3 cryostats 3 Return Terminations Cable cryostat - 1 W / m / phase 230 W / termination Conductor and Shield 230 W / termination 0.2 W / m / phase 690 W 110 W 690 W Heat loss (all 3 phases) for 30.5 meter cable and terminations at 600 amps is 1490 W. 54 27

Simulated flexible cryostat testing is being conducted with NASA Kennedy Space Center Testing in progress on simulated flexible cryostat geometry. Goal is to design flexible thermal insulation with heat loads approaching rigid cryostat values. 55 Presentation Outline Southwire Activities (David Lindsay, Southwire) Introduction 30-m Cable Installation 30-m Cable Operation FY 2000 Results 30-m Cable Off-Line Testing (Mike Gouge, ORNL) 5-m Cable Research Component Development Cryogenic Dielectrics Research (John Stovall, ORNL) FY 2000 Performance / FY 2001 Plans Technology Integration Summary 56 28

Splice Development and Testing A cable splice design has been developed. A model cable has successfully tested the dielectric splice design. A 5-m splice cable is being manufactured by Southwire for testing at ORNL. Future plans include testing a splice on the 30- m cable at Southwire. Future location of splice at 30-m test site. 57 A model cable successfully tested the dielectric splice design 30 min. ac withstand at 2.5 x operating voltage (18 kv) Partial discharge level less than 1 pc at 18 kv Passed ac voltage breakdown test (10 times rated) Passed 110 kv BIL impulse test (1.2 x 50 µs ) Conductor Ground Shield Semicon Shield Cryoflex Dielectric Stress Cone Field enhancement HTS Cable Splice 58 29

A small model cable dewar has been set up for and aging studies and partial discharge (PD) Dedicated system for aging studies and PD. Automated high pressure LN2 fill system installed An innovative partial discharge system has been developed for model cable aging studies Used to isolate PD signals from cable test region and stress cones Conventional PD detectors connected to HV bus have difficulty locating the source of PD 59 Cryogenic dielectric model cable aging studies are determining cable lifetime E, ac Electric Field Strength Aging relationship, t E n = Constant 0.2 h 2.4 h 24 h 30 years Data Needed Extrapolated to 30 years Operating stress of Southwire 30-m cable 10-4 10-3 10-2 10-1 10 0 10 1 10 2 10 3 10 4 t, Time to Breakdown (days) 60 30

ORNL FY 2000 Performance FY 2000 Plan Assist Southwire with the final construction, installation, checkout, testing, and operation of the SPI 30-m, 3- phase HTS cable. FY 2000 Performance 30-m Cable Demonstration New cable termination design improved performance Heat load of HTS cable system estimated during operation Voltage withstand test verified cable dielectric system and cable capacitance was measured Dc load current tests tested conductors and cryogenic system operation off-line Dc V-I testing verified health of main and shield cable conductors and measured endto-end resistances (11/99 & 6/00) Review of operational data has shown ways to improve system performance. 61 ORNL FY 2000 Performance FY 2000 Plan Conduct cable bending and short circuit tests on the 5-m cables. Continue cryogenic dielectric aging tests. FY 2000 Performance Bent 5-m cable and tested dielectric - passed Successful short-circuit tests of 5-m cable, no degradation at 15 ka Impulse tested cable #2 and the terminations Measurements suggest dielectric n value is in acceptable range 30-m cable operating electric stress is very conservative 62 31

ORNL FY 2000 Performance FY 2000 Plan Extend HTS cable capability in partnership with Southwire researchers by: developing a cable splice, improving the cable cryostat cryogenic insulation FY 2000 Performance HTS Cable Component Development have designed and fabricated a 5-m cable with a splice developed and successfully tested model dielectric tape splice will test 5-m dielectric cable splice next month at ORNL design improvements to pressurized termination: heat loss reduced more robust to ambient conditions initiated collaboration with NASA Kennedy Space Center Cryogenics Test Bed on low thermal loss, flexible cryostat 63 Change in Plans During FY 2000 FY 2000 Plan FY 2000 Performance Deferred due to utility interest in applications at distribution voltages and high currents. design a cable termination for higher operating voltages, and examine cryogenic dielectric system requirements for higher voltage HTS cables Added YBCO quench and stability studies were initiated 64 32

ORNL FY 2001 Plans Oct. 1, 2000 to Sept. 30, 2001 ORNL will work with Southwire to improve the overall design and capabilities of the HTS cable system. Specific activities include: evaluation of 30-m cable operation and performance, research and development and testing of cable splices, continue development of the pressurized termination, continued research on cryogenic dielectric materials, and research improving cryogenic system. In addition, ORNL will assist Southwire with the design and analysis of an HTS cable system for siting in a large urban area with a utility partner. 65 Technology Integration - Partnerships Partners with expertise and funding. Project is being conducted as a DOE SPI with equal cost sharing by Southwire and DOE. Southwire expertise includes: Wire and cable manufacturing, Established utility customer base, Design and installation of turn-key systems for utilities, Design and construction of copper rod mills world-wide, Design and construction of manufacturing plants, and now Design and installation of superconducting cables for utility customers. FY 2000 progress is evidence of well functioning team. 5-m cable research at ORNL. 30-m cable installation at Southwire 30-m cable testing and operation at Southwire 66 33

Technology Integration - Expertise and Facilities Efficient use of equipment and personnel between ORNL/Southwire. Assembly of 30-m cables has involved a team of ORNL, Southwire and subcontracted technicians. Shared use of SW ac power supply, ORNL dc power supply, SW PD detector. Technical capability is being established in industry by subcontracting for subsystems and components. Cryogenic system was competitively bid and awarded to U.S. industry. Components for terminations are being manufactured by U.S. industry resulting from competitive request for quotations. Several key consultants have provided technical expertise and analysis. 67 Technology Integration - Publications Two papers were presented at 1999 Cryogenic Engineering and International Cryogenic Materials Conference, July 12-16, 1999, Montréal, Québec, Canada 5-m Single-Phase HTS Transmission Cable Tests Cryogenic System For A High Temperature Superconducting Power Transmission Cable Four technical presentations/papers will be presented at the Applied Superconductivity Conference, ASC 2000, in September 2000 Development and Testing of HTS Cables and Terminations at ORNL Fault Current Tests of HTS Cable and Tape Installation And Operation Of The Southwire 30-Meter High-Temperature Superconducting Power Cable (Invited Paper) Practical AC Loss and Thermal Considerations for HTS Power Transmission Cable System ORNL Annual Report is available on the web www.ornl.gov/htsc/htspc-11.pdf 68 34

Summary FY 2000 goals have been achieved 30-m HTS cable has been installed 30-m HTS cable is in operation ORNL has provided a breadth of expertise to Southwire 4 ORNL research division s have contributed this year Have experimented with BSCCO tapes, 1-m, 5-m, 30-m cables, dielectric model cables, splice cables, cable joints, cryogenic systems Have conducted a variety of tests: critical current, ac losses, ac withstand, voltage breakdown, impulse strength, partial discharge, short-circuit, dielectric aging, cryogenic heat loads The difficult transition from laboratory testing to a practical field application has been completed. 69 World s First Industrial Field Test of HTS Cable Delivers Power To Industrial Customer 70 35