SWAN LAKE FIRST NATION MATRIX SOLUTIONS INC. PARTNERSHIP INDIGENOUS CONSTRUCTION MONITORING

Similar documents
SWAN LAKE FIRST NATION MATRIX SOLUTIONS INC. PARTNERSHIP INDIGENOUS CONSTRUCTION MONITORING

SPREAD 7 AUGUST 13 TH TO AUGUST 18 T

SOLUT TO AUGUST 25 T SPREAD 7 AUGUST 20 TH

MANITOBA METIS FEDERATION MATRIX SOLUTIONS INC. PARTNERSHIP INDIGENOUS CONSTRUCTION MONITORING

SAMSON CREE NATION MATRIX SOLUTIONS INC. PARTNERSHIP ABORIGINAL CONSTRUCTION MONITORING

SPREAD 9 AUGUST 13 TH TO AUGUST 18 T

SWAN LAKE FIRST NATION MATRIX SOLUTIONS INC. PARTNERSHIP INDIGENOUS CONSTRUCTION MONITORING

SGS MUSCOWPETUNG ABORIGINAL CONSTRUCTION MONITORING

Exploring Habitats. Study Habitat Drawings to Identify Living Things & Nonliving Conditions. Safety Precautions

East Branch Grand Calumet River Great Lakes Legacy Act Sediment Remediation and Restoration Project

RISK RATING SAFE WORK METHOD STATEMENT 1 HIGH 2 MEDIUM 3LOW. I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager

2.8-1 SCIENCE EXPERIMENTS ON FILE Revised Edition. Dew Formation

Kindergarten Reading Street/Science Correlation (PreK-2 Science Curriculum Frameworks) Scott Foresman Reading Street Unit 1, Week 2 Fix-it Duck

Snow Cover. Snow Plowing and Removal Services Best Practices Guide. l

General. High Winds. High winds are a common hazard in the UAE.

Actions SLT Staff Students, Parents/Carers Ensure all. with caution in all. gritted.

2010 Winter Weather Advisory

The mowed firebreaks are at least 10 wide and are usually 20. A rotary hay rake is used to clear larger firebreaks.

Bipole III Transmission Project Construction Environmental Protection Plan Construction Section N2 Environmentally Sensitive Site Locations Map 81

Extending Learning Beyond the Classroom

Ecosystems Chapter 4. What is an Ecosystem? Section 4-1

Whether you are driving or walking, if you come to a flooded road, Turn Around Don't Drown

Hurricanes form over warm ocean water.

Snow Plow Safety Quick Reference Guide

Construction Exits Vibration grids

Weather in Saskatchewan. John Paul Cragg Warning Preparedness Meteorologist Environment and Climate Change Canada

Witless Bay Ecological Reserve

Weather and Climate 1. Elements of the weather

Watching the Weather

Plant Indicators for Acids and Bases

Severe Weather Policy (Snow & Ice) Seek Ye First the Kingdom of God...

Materials. Use materials meeting the following.

Learning Objectives: I can identify and interpret river flows and directions.

Winter guide for HGV drivers

Grade K, Unit C, Physical. this chapter students discover: - different kinds of objects - some properties of matter

Organism Interactions in Ecosystems

Winter Weather Get It Together. Infographic Social Media Campaign Transcomm 2018 Awards - 8a: Logo, Illustration and Infographic

FOUR-ON-THE SNOW Newsletter

1,836 people die and 136,309 people are injured every year from icy roads in the US.

3 Weather and Climate

4th Grade Social Studies First Nine Weeks

Review for Earth and Space and Energy Types Test

Construction Exits Rock pads

FOREST FIRE News July 29, :30

Counselor s Name: Counselor s Ph #: 1) Define meteorology. Explain how the weather affects farmers, sailors, aviators,

Tom Blackman Project Lead. Mékell Mikell Communications Representative

Hurricanes. Where's the Really Bad Weather 1. What: Rotating wind/rain storm Winds from 75 to 200 mph As big as 600 miles wide

WATER OBSTACLE COURSE

Thank you for choosing AIMS!

Bipole III Transmission Project Construction Environmental Protection Plan Construction Section N1 Environmentally Sensitive Site Locations Map 25

Wind. Rain PAGE 01 CHAPTER 07 WEATHER CONDITIONS AND DRIVING

Avon Community School Corporation

Frequently Used R Words

Weather. science centers. created by: The Curriculum Corner.

Grade 6 Nature Walk: Volunteer Guide

CITY OF BEAVER DAM SNOW & ICE REMOVAL POLICY

Trainee Manual C02 CITY OF SASKATOON. Water and Sewer Section. Severe Storm Response Trainee Manual. Version # 1-0-3

Guided Reading Chapter 18: Weather Patterns

Greenwich Public Schools Science Curriculum Objectives

SNOW CONTROL OPERATIONS

Weather and climate. reflect. what do you think? look out!

BAD WEATHER DOESN T CAUSE ACCIDENTS

Contents. Chapter 1 Introduction Chapter 2 Cyclones Chapter 3 Hurricanes Chapter 4 Tornadoes... 36

Safe Driving in Bad Weather Conditions

Wildfire Preparedness

1. Major streets, Central Business District (CBD) and school bus routes. 2. Local streets 3. Downtown parking lots

While all thunderstorms are dangerous, the National Weather Service (NWS) defines a severe thunderstorm as one that:

THE MINISTRY OF ENERGY AND ENERGY INDUSTRIES MINERALS DIVISION MINE DESIGN TEMPLATE OPERATOR NAME: OPERATOR ADDRESS: PHONE NUMBER: FACSIMILE:

Page 1 of 6 SWCC MORNING INTELLIGENCE BRIEFING. June 1, Daily Summary

Agenda. INDOT Office of Environmental Services. Describe Results of FHWA QAR. Landscape and Waterway Permitting Unit. Interviews Site Inspections

1.0 INSPECTION ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER PROJECT, CARMACKS, YUKON. Dear Mr. West-Sells,

ICE STORM! a mini tabletop exercise for home care agencies

WINTER MAINTENANCE TRAINING VINCE LOMBARDI

November 2012 Climate Summary

Al-Omam International School

4th Grade. Earth Systems.

SAFETY. Always be aware of your surroundings

Climate Change: How it impacts Canadians and what we can do to slow it down.

John A. Carlson Snow and Ice Removal

Signs in the Sky. by Michelle August

4th Grade. Slide 1 / 101. Slide 2 / 101. Slide 3 / 101. Earth Systems. Earth Systems Earth's Systems. Mechanical Weathering

PLEASE SAVE 1 SET OF BATTERIES FOR THE FINAL CHALLENGE.

Keeping well and healthy when it is really cold

WHAT S CIVIL DEFENCE?

FINAL STREAM. Prepared For: Discharge. Draft Stream. Level Hay Street, Subiaco WA Indiana Street. Golden, CO USA

IN VEHICLES: Do not try to outrun a tornado. Abandon your vehicle and hide in a nearby ditch or depression and cover your head.

Cub Scout and Webelos Nova Award Down and Dirty

CHAPTER 7 GEOLOGY AND SOILS

My Community vs. Nunavut Weather and Climate

Scout s Address: City State Zip:

Land and Water Study Guide

Coconino County Common Snow Plow Questions/Concerns

WILDLIFE ROAD MITIGATION PLAN FOR THE JAY PROJECT DRAFT. Dominion Diamond Ekati Corporation

Regulations concerning protection of Bjørnøya Nature Reserve in Svalbard

CLEARING THE WAY CAUTION. brampton.ca/snow

The Dust Bowl By Jessica McBirney 2018

Today s Airtime: 4.6 Total PIC Time: Total Logged Time:

Completion Match each each piece of equipment with its description. Please only put one number in the blank.

AVALANCHE ACTIVITY ON US HIGHWAY 12. Mick Riffie Idaho Transportation Department Lowman, ID

Changes in Texas Ecoregions Copy the questions and answers

Transcription:

SWAN LAKE FIRST NATION MATRIX SOLUTIONS INC. PARTNERSHIP INDIGENOUS CONSTRUCTION MONITORING WEEKLY REPORT SPREAD 9 NOVEMBER 13 TH TO NOVEMBER 17 TH Suite 600, 214-11 Ave. SW Calgary, AB, Canada T2R 0K1 T 403.237.0606 F 403.263.2493 www.matrix-solutions.com

1. PURPOSE OF THIS REPORT The report is a weekly summary of the daily reports submitted by the Indigenous Construction Monitors that are working on spread nine. The social and cultural findings have been tabulated with locations and mitigation measures below. A summary of the construction activities has been summarized for the weeks of November 13 th to November 17 th, 2018. 2 Matrix Solutions Inc.

Field Observation Traditional Use Area (hunting, fishing, gathering, trapping) Rock Formations (rocks of significance, tipi rings, etc.) Artifacts Social and Cultural Features # of occurrences Description and Mitigation Measures Mitigation Status Further Action Required (Yes/No) Bones Potential Gravesites Field Observation Medicinal or Cultural Plants Environmental Features # of occurrences Description and Mitigation Measures Mitigation Status Further Action Required (Yes/No) Aquatic Life Animal Observations or Burrows Bird Nests Trees (Red Willow) Wetlands Watercourse Crossing 3 Matrix Solutions Inc.

Additional Observations and Summary of Activities or Concerns Weekly activity included attending daily tailgate meetings and continue to check access points on the ROW and monitor Spread 9. November 14, 2018 - Safety included: Vehicle: check vehicle tires, fluids, keep clean. Weather: Drive to the conditions. Slips, trips, falls: Make sure shoe lace are tied, hatch footing ice, wet conditions. Confined space: stay out of congested areas. Weather: Dress for the weather Dry dusty road conditions. Show caution remain wary on right of way dangers or potential problems. A lot of heavy trucks hauling water for pipe test. Being attentive when on land, watching for wildlife. Communication is important to touch base to ensure all personal are safe. Being aware of muster points at field office but out in the field with other crews. Ensure P.P.E. is worn at all time in the field. Weather forecast/environment: Patches of clouds, -9.5 degrees C Monitored to make sure the soils were not mixed. The areas were clean from any garbage and on the ROW. Ensured all spill kits were on machines and in the trucks that were on the ROW. Continue to keep waste out of pipeline area. Being careful as to ignitions sources. Being aware of weather conditions. General: Attended safety meeting with our senior monitor and was given direction to travel to sskp 1071.71-1071.71. arrived and monitored an excavator back filling the clay back on to the pipe and spreading it at the same time. The clean-up crew on site picking up ties and any garbage that was laying around and put it in the back of truck. The crew were piling the ties on a trailer that was pulled in on the ROW for the morning and part of the afternoon. We travelled to sskp 1095+173 and monitored tie-ins as we travelled to sskp 1095+780 monitoring tie-ins there as well and moving east to Rd# 60 1096+100 where they were demobilizing bore. SSKP 1064.800 Crew in the area are removing bridge and cleaning up ROW. It is here where there is interim clean up and final reclamation. Remove mats, matting, geotextiles and ramps from locations indicated on the Line List if necessary. Further on down the R.O.W. SSKP 1096.200 MB-WC82. Three excavators digging and demobilizing. Excavating tie in ditch Rd 59a heading east. Monitored here close to END-OF-THE-LINE activities here where other tie in crews are close by with side booms digging trench for tie ins and installing tie ins. SSKP 1071 once again here tie in crew are back filling pipe. MB-WC-80. Returned to Morden field office to complete daily report. Work Forecast: To continue monitoring spread 9. November 15, 2018 - Safety included: Vehicle: Check vehicle tires, fluids, keep clean. Weather: Drive to the conditions. Slips, trips, falls: make sure shoe lace are tied, hatch footing ice and wet conditions. Confined space: stay out of congested areas. Dry dusty road conditions. Show caution remain wary on right of way dangers or potential problems. Being attentive when on land, watching for wildlife. Communication is important to touch base to ensure all personal are safe. Incorporate buddy system. Being aware of muster points at field office but out in the field with other crews. Ensure P.P.E. is worn at all time in the field. 4 Matrix Solutions Inc.

Weather forecast/environment: Patches of clouds, -2.5 degrees C. Being careful as to ignition sources. Being aware of weather conditions. Continue to keep waste out of pipeline area. Be aware of extreme windy conditions General: attended safety meeting with our senior monitor and discussed the weather as it was cold and windy dress warm. We travelled to sskp 1074+300, met and observed Elden Pagee and Morris Scott (cleaning crew) as they were cleaning the ROW as we were doing our sweeps from 1071+100 leading up to 1074+300.We had kept travelling along the ROW as we came up to sskp 1074+400 Rd 46 heading east and monitored the back filling with the clay. We had moved along to Rd 47 sskp 1075+100 as they were back filling there with clay as well as they were doing a good job and keeping the soils separated as they just used the clay at both sites. Travelled to sskp 1058+100 as they were getting ready for pressure testing so we had to leave the area. SSKP 1093.130 Restoring MB-WC80 Seven earth moving machines. 5 excavators and 2 rock trucks SSKP 1064.800 SSKP 1058.04 Crews in the area are removing bridges road approaches and cleaning up ROW. It is here where there is interim clean up and final reclamation. installing mats, matting, geotextiles in order for farmers to have access to cultivated areas. Crew is headed eastward working on deficiencies. SSKP 1071 back filling removing trench boxes in area. Removing rubbish. Returned to Morden field office to complete daily report. Work Forecast: To continue monitoring spread 9 November 16, 2018 - Safety included: Slips, trips, falls: watch your footing Wild-life: scan the ditches practice defensive driving. Proper disposal of cigarettes butts. Vehicle: Keep clean at all time inside and out. Show caution remain wary on right of way dangers or potential problems. Being attentive when on land, watching for wildlife. Communication is important to touch base to ensure all personal are safe. Incorporate buddy system. Being aware of muster points at field office and to sign on with other crews when available. Ensure P.P.E. and worn at all times Ensure cold weather safety kits are available. Weather forecast/environment: Patches of clouds, -9degrees. Continue to keep waste out of pipeline area. Being careful as to ignitions sources. Being aware of weather conditions. Be aware of extreme windy conditions. General: Today was given direction by our senior monitor tailgate meeting and weather conditions dress for it as we head out to Rd58+Rd59 kkps 1093.426-1095.173. Monitored the crew that was doing tie-in ditch and back filling with clay as they were using an excavator to fill in the ditch and the dozer spread it out. We also met a grader levelling off the ROW going west from 1095.173 to 1093.426. Travelled to sskp 1071.49-1071.71(Her-176) Grass Dancers going north west to Rd 43-1070.639 as they were taken out the bridge/approach removal as we monitored and finished up for the day. SSKP 1093.130 Restoring MB-WC80 Tie in ditch and back fill. SSKP 1070.639 SSKP removing bridges road approaches and cleaning up ROW. It is here where there is interim clean up and final reclamation. installing mats, matting, geotextiles for farmers to have access to cultivated areas. Crew is headed eastward 5 Matrix Solutions Inc.

working on deficiencies. SSKP 1058.078 Installing hoarding for hydro test and disassemble bridges at PJ trailers. Returned to Morden field office to complete daily report. Work Forecast: To continue monitoring spread 9. November 17, 2018 - Safety included: Slips, trips, falls: watch your footing. Dangers: Today wet conditions and raining. Wild-life: Scan the ditches practice defensive driving. Proper disposal of cigarettes butts. Show caution remain wary on right of way dangers or potential problems. Being attentive when on land, watching for wildlife. Communication is important to touch base to ensure all personal are safe. Incorporate buddy system. Being aware of muster points at field office and to sign on with other crews when available. Ensure P.P.E. is worn at all times. Ensure cold weather safety kits are available. Weather forecast/environment: Patches of clouds, -12 degrees. Continue to keep waste out of pipeline area. Being careful as to ignitions sources. Being aware of weather conditions. Be aware of extreme windy conditions General: Given direction by our senior monitor this morning the tailgate meeting. Travelled to sskp 1070.639 Rd 43 to monitor the removing of the bridges and the ramps and road approaches heading east. We monitored the removal of the ramps with an excavator and began to pile the mats. As they had finished doing the mats they began to move the bridge, there was three excavators working as that site and three ground spotters. Spent all morning there and most of the afternoon before going to sskp 1096.816 where it was too congested with equipment. SSKP 1096 Hydro acing Enbridge crossing in preparation for back filling. SSKP 1095.024 Restoring MB-WC81 Tie in ditch and back fill restoration. SSKP 1071 (HER-176) here crews are removing bridge and preparing and crushing frozen soil with dozer and rock truck. SSKP 1070.639 SSKP Quiet here Crew is headed eastward working on deficiencies. Returned to Morden field office to complete daily report. Work Forecast: To continue monitoring spread 9. 6 Matrix Solutions Inc.

s of Sites Visited & Topics Discussed This Week November 14, 2018 SSKP1074+100 PICTURE WAS TAKEN FACING EAST 1073+400 CLEAN UP GUYS PICTURE WAS TAKEN FACING EAST Road 39 facing east excavators SSKP 1096.200 facing west SSKP 1096.33 facing west SSKP 1071 facing west 7 Matrix Solutions Inc.

November 15, 2018 SSKP 1074+400 RD46 PICTURE WAS TAKEN FACING WEST SSKP 1093.13 PICTURE WAS TAKEN FACING EAST SSKP 1073-74-75 men and equipment working facing East excavators SSKP 1093.130 facing north SSKP 1074 facing west SSKP 1058 facing south 8 Matrix Solutions Inc.

November 16, 3018 SSKP 1093+100 AS PICTURE WAS TAKEN FACING EAST SSKP 1095.173 Rd picture was taken facing east SSKP 1085 facing north excavators SSKP 1058.078 facing east SSKP 1093 facing east 9 Matrix Solutions Inc.

November 17, 2018 sskp1070.639 Rd 43 picture was taken facing east sskp 1096.816 picture was taken facing east Road 16 excavator digging EAST SIDE ROAD 16 LOWERING PIPE 10 Matrix Solutions Inc.

SSKP 1091.782 facing south excavators SSKP 1071 facing east SSKP 1096 facing west SSKP 1096 facing south 11 Matrix Solutions Inc.

APPROVALS Grant Manningway Construction Monitor December 18, 2018 Date Daniel Tober Senior Environmental Scientist December 18, 2018 Date 12 Matrix Solutions Inc.