Integrating Wind Resources Into the Transmission Grid

Size: px
Start display at page:

Download "Integrating Wind Resources Into the Transmission Grid"

Transcription

1 Integrating Wind Resources Into the Transmission Grid Gary D. Bachman Wisconsin Public Utility Institute May 26, 2010

2 Introduction Statement of FERC Chairman Jon Wellinghoff on Efficient Integration of Renewables into the Grid, January 21, 2010: Approximately 9,000 MW of variable energy resources went into commercial operation in the U.S. during 2009 and a similar number in Currently, there are thousands of MW of VERs, particularly wind, in the process of interconnection to the electric grid. These new resources offer low operating costs and low greenhouse gas emissions, which can benefit consumers VERs also have some operational characteristics which present challenges to system operators. Therefore, it is important that the Commission examine the most efficient ways to effectively integrate these resources into the electric grid, while maintaining reliability and operational stability. 2

3 Introduction Wind and Natural Gas are the leading sources of new generation capacity in the United States, collectively totaling roughly 80% of new installed capacity in New growth driven in large part by state renewable portfolio standards, production tax credits, and in some cases, favorable economics. Here in the Midwest, the Midwest Governors Association has established a goal of 30 percent renewable energy consumption by

4 Introduction The rapid development of wind generation presents challenges for transmission system operators 4

5 What s the Problem? Balancing Area operators ( BAs ) are responsible for continuously balancing generating resources with load and must maintain adequate generating reserves that are quickly available to accomplish this task. NERC measures a BA s compliance with this requirement through its Control Performance Standard 2 ( CPS-2 ), which measures the balance over 10-minute periods of each month. 5

6 What s the Problem? CPS-2 sets a limit on the maximum permitted Area Control Error ( ACE ). ACE is the instantaneous difference between actual and scheduled flow on tie lines between a balancing area and surrounding balancing areas. In order to be in compliance with CPS-2, a BA must pass this measurement in at least 90 percent of the 10-minute periods in each one month period. 6

7 What s the Problem? The output from dispatchable (fossil-based, nuclear, hydro) generation is typically set at a certain level, and can be maintained so long as the unit is performing properly. Dispatchable generation typically does not vary much from its scheduled output, barring an unforeseen outage. A BA s intrahour role has therefore traditionally focused on managing the moment-to-moment deviations in loads using online generating capacity that can respond instantaneously in a process known as regulation. 7

8 What s the Problem? Wind generation introduces a new source of variability that the BA must manage to meet its CPS-2 requirements. The output from a wind generator can increase or decrease in response to changes in wind speed and direction, and is also susceptible to a phenomenon known as high speed cutout which can occur during high wind conditions when governors on the generators shut them down as a protective mechanism. 8

9 What s the Problem? Insert Hopkins Telemetry Ridge: 0 MW Example to 134 MW from in 7 minutes PSE Wind Generation (MW) Wild Horse: 0 MW to 129 MW in 11 minutes 0 20:00 20:30 21:00 21:30 22:00 22:30 23:00 23:30 0:00 0:30 1:00 1:30 2:00 2:30 3:00 June 4-5, 2009 Wild Horse Hopkins Ridge HR Schedule: HE 2100 = 15, HE 2200 = 130, HE 2300 = 140, HE 2400 = 100, HE 01 = 5 9

10 What s the Problem? Wind generators underperform relative to their schedules when the wind blows less than expected. During times of low load levels, wind projects may produce energy that is not needed, which requires other generation to back down to preserve balance on the system. Example of Extreme Wind Variability: On November 27, 2009, one wind facility in the Pacific Northwest recorded an output of 0 MW halfway through the 0:300 scheduling hour, 175 MW halfway through the 0:400 hour, and 26 MW halfway through the 0:500 hour. A 175 positive ramping event, followed by a 149 MW negative ramping event, in two hours. 10

11 What s the Problem? Offsetting Load Variability? When wind generators in a balancing area experience a ramping event in the same direction of load movement, the variability of wind and load offset to reduce the BA s within hour fluctuations. Of course, when wind and load vary in the opposite direction, there is an additive effect on net variability. Analysis of some western systems has shown that the beneficial effects of offsetting load variability dissipate as more wind is added because the first few large wind projects absorb the available offsetting load variability. 11

12 What s the Problem? Wind Diversity? Different wind sheds may experience ramping events at different times, such that a wind resource in one geographical corner of a balancing area may ramp up while another resource ramps downward. This offsetting wind variability reduces the within-hour burden on the BA. However, a concentration of wind farms around a single geographic resource (i.e., single windshed) can have an additive effect and increase the burden on the BA. 12

13 What s the Problem? BAs must have sufficient flexible capacity available that can be ramped up or down to balance wind ramping events in order to meet CPS-2 standard and keep the system balanced. Current tariff provisions and market protocols were largely developed prior to the recent increase in wind development and were designed with dispatchable not variable generation in mind. 13

14 What s the Problem? For example, it is generally not efficient or appropriate to balance wind generation using the same regulation products used to balance load variation because of the magnitude and duration of wind ramping events. The most appropriate products are similar to the Spinning Reserve Service and Supplemental Reserve Service, which reserve products are defined as ancillary services under the pro forma OATT. However, they are only available during contingencies. Most wind ramping events do not qualify as contingencies as defined in the pro forma OATT and thus the ancillary service products are not available for use by BAs for that purpose. 14

15 What s the Problem? Moreover, FERC s restrictions on the sale of ancillary services at market-based rates have limited the development of a market for products that are like spinning and supplemental reserves but are not contingency products. Absent a market for reserve products, BAs are often forced to balance wind resources using facilities or resources on their system that are not well suited to the task and/or would otherwise be dedicated to optimizing cost of service to native load. The pro forma OATT does not recover the costs of providing the integration service or such resources. 15

16 What s the Problem? Wind developers are concerned that BAs may try to shift the costs of wind integration to wind developers in a way that is inconsistent among BAs, unduly discriminatory, or punitive. Wind developers fear that if the cost of integrating wind generation becomes unduly high, the growth of the industry will be stunted. Wind developers also fear discriminatory curtailment practices by BAs that could limit the amount of wind energy that reaches the market and limit RECs. 16

17 What s the solution? FERC-approved tariff amendments allow BAs to recover costs of following wind generation: Entergy Services, Inc., 120 FERC 61,042 (2007): Commission approved amendment to Entergy OATT that allowed for separate recovery of the costs of holding additional reserves for meeting generation imbalances. 17

18 What s the solution? FERC-approved tariff amendments allow BAs to recover costs of following wind generation: Westar Energy, Inc., 130 FERC 61,215 (2010) Westar sought and obtained FERC approval to implement new OATT Schedule 3A, Generator Regulation and Frequency Response Service Westar observed wind generators in Kansas from Dec to Nov to determine the deviation from schedule over 10-minute intervals. Westar allowed load variations and other wind variations in the BA to offset a generator s deviations where applicable the portfolio-wide approach to measuring wind variability. The data collected demonstrated that wind generators deviations from deployment signal are more than three times greater than those of dispatchable generators. Westar claimed that as a result, wind generators placed a heavier burden on its system than dispatchable generation. 18

19 What s the solution? FERC-approved tariff amendments allow BAs to recover costs of following wind generation: Westar Energy, Inc., 130 FERC 61,215 (2010) (cont d) Westar therefore proposed to charge under Schedule 3A intermittent generators a higher generator regulation charge than dispatchable units a regulation requirement of 7.8 percent of nameplate capacity (Westar s Schedule 3 charges dispatchable units a regulation requirement of 1.35 percent of nameplate capacity). The Commission s approved Westar s proposal, finding that it reasonably assesses intermittent generation a higher regulation requirement consistent with cost causation principles. Id. at P

20 What s the solution? FERC Rejects Tariff Amendments That Shift Burden of Providing Following Services to Generators: NorthWestern Corporation, 129 FERC 61,116 (2009) Northwestern proposed an amendment that would have required intermittent renewable generators to supply or otherwise provider their own generation following capability for both capacity and energy. The Commission held that Northwestern could not shift its responsibility to provide generator imbalance service under Schedule 9 of the pro forma OATT to intermittent generators. Opinion advised Northwestern to file tariff revisions that would allow it to recover costs of providing regulation services to intermittent generators if those costs were not already being recovered under the utility s OATT. 20

21 What s the solution? Curtailment? Generally, transmission providers are allowed to curtail generation on a pro rate basis to reduce transmission congestion. But: some wind generation cannot reduce output without shutting down completely, presenting an all or nothing decision for BAs. Some transmission providers have developed different curtailment practices for wind generation to accommodate ramping events: BPA agreed in a settlement with its customers to sell flexible capacity to wind generators under its OATT at a discounted rate of $1.29 to $1.58 per kw-month. In exchange, BPA obtained the right to curtail wind generators when 90% of its balancing reserves are deployed. 21

22 What s the solution? Voluntary Regional Efforts: Various regions have formed working groups to develop solutions to wind integration. Example: Northwest Wind Integration Action Plan ( NWIAP ). Identifies 16 action plan items that would help facilitate the reliable and efficient interconnection of large amounts of wind in the region. Example: Joint Initiative Voluntary effort by ColumbiaGrid, Northern Tier Transmission group, and WestConnect to develop products and services to aid wind integration. Have developed a standard intrahour scheduling product and business practice. 22

23 What s the solution? Different regions have taken different approaches depending on the quantity and characteristics of wind resources interconnected to the grid in those regions. Wind generators are concerned that this ad hoc approach may lead to a lack of consistency across regions, a lack of transparency, and potentially discriminatory treatment of wind resources. 23

24 FERC s Notice of Inquiry On January 21, 2010, FERC issued a Notice of Inquiry ( NOI ) seeking comments on whether reforms of existing policies are needed to better integrate wind generation into the transmission grid. The NOI welcomed general comments, and also sought comments on seven particular subject areas. 24

25 FERC s Notice of Inquiry 1. Data and Reporting Requirements: Development of state-of-the art forecasting techniques could take some of the uncertainty out of a BA s job when it comes to integrating wind resources. BAs will have a better idea of the quantity of reserves they need to have available if they can better predict large scale ramping events. Wind generators will be able to schedule more accurately and hence avoid scheduling penalties for over/under generation if they can better predict output. 25

26 FERC s Notice of Inquiry 1. Data and Reporting Requirements: Questions Raised: Sharing of data collected by a generator at the site of wind turbines with BAs Centralized forecasting by BA? Cost recovery? Even with a perfect forecast the variability must still be smoothed. 26

27 FERC s Notice of Inquiry 2. Scheduling Practices and Incentives/Penalties: FERC primarily sought comments on two areas of inquiry: Whether there should be a move to intrahour scheduling Whether the current exemption from third tier scheduling penalties for wind generation should be continued and/or creating proper incentives to schedule accurately. Intrahour Scheduling: A move to intrahour scheduling would wind generators to schedule more accurately in response to changing weather conditions, and allow BAs to more frequently and efficiently adjust the amount of reserves they need to have available to balance wind. Tariff provisions and operational protocols would need to be revised to accommodate intrahour scheduling. 27

28 FERC s Notice of Inquiry 2. Scheduling Practices and Incentives/Penalties: Scheduling Penalties: Currently, intermittent generators are exempt from 25% scheduling penalty for third tier scheduling errors (>7.5%), which requires wind generators to purchase imbalance energy at 125% of the energy s incremental cost. Instead, wind generators must only pay 110% of the incremental cost of replacement energy for even the largest of generation imbalances. FERC solicited comments on whether this 10% penalty is an adequate incentive for wind generators to schedule accurately, or whether it is not harsh enough (or too harsh). 28

29 FERC s Notice of Inquiry 3. Day-Ahead Market Participation Currently, participating in day-ahead markets (in regions where they are available) is generally considered too risky for wind generation because of the uncertain output and risk of underperformance. Wind generators without a full contract offtaker generally participate only in the real time energy market. The Commission is considering ways of encouraging participation by wind resources in day-ahead markets. 29

30 FERC s Notice of Inquiry 4. Balancing Area coordination and/or consolidation: In some cases, wind integration costs can be reduced by increasing the size of a balancing area to encompass more (hopefully) offsetting load and wind variations. If there is little wind or load diversity in the region, consolidating balancing areas may not have significant benefits. Some western utilities have discussed the formation of a wind only balancing area across the interconnection, though significant transmission issues would need to be resolved. 30

31 FERC s Notice of Inquiry 4. Balancing Area coordination and/or consolidation: BA coordination activities that can facilitate integration by shifting BA responsibilities and burdens: Dynamic transfers Dynamic schedules Pseudo-ties ACE Diversity Interchange ( ADI ) developed in Pacific Northwest; voluntary frequency sharing program that has allowed some BAs to better meet their CPS-2 requirements. 31

32 FERC s Notice of Inquiry 5. Reserve Products and Ancillary Services: As discussed previously, spinning reserves and supplemental reserves contingency products that could otherwise be used to balance wind ramping events. The lack of a market for suitable wind following reserve products means that transmission providers often rely on more expensive regulation reserves or, outside of RTO/ISO areas, are required to balance wind ramping events using resources that were acquired to serve to native load. The Commission thus sought comments on whether the definitions of these ancillary services should be revised to make them applicable to wind ramping events; and otherwise how a market for such products and services should be fostered. 32

33 FERC s Notice of Inquiry 5. Reserve Products and Ancillary Services: Key Questions: Type of product flexible, can be ramped up or down (spinning?) on short notice Technology Natural gas, peaking unit? Who should be responsible under the tariff for providing wind following service? BA? Wind generator? Cost allocation if BA provides service Based on historical scheduling imbalances of wind generators? Portfolio-wide approach, taking into account offsetting load and wind variations 33

34 FERC s Notice of Inquiry 6. Wind participation in capacity markets In areas with organized capacity markets, Commission has inquired, among other topics, whether: Uniform capacity rating for wind resources should be developed Wind resources are prohibited from participating in forward capacity markets 34

35 FERC s Notice of Inquiry 7. Real-time Adjustments Redispatch there is some uncertainty concerning redispatch practices when a wind ramping event results in a reserve shortage, and who is to bear the costs associated with the event. Inability of to reduce output when a wind generator cannot reduce output through blade feathering or a governor in response to BA dispatch instructions, should they be ordered to shut down completely? 35

36 FERC s Notice of Inquiry The Commission received over 100 sets of comments on these topics. Trends: BAs and transmission providers generally favor: Flexibility to develop regional/ba-specific solutions. Shifting of responsibility to balance wind generation to wind generators curtailment in extreme ramping events. Full cost recovery Wind developers generally favor: Consistent application of policies through a FERC rulemaking. BAs retain responsibility for balancing system with reserves, even during ramping events. Policies which place wind generators on equal footing with dispatchable generation. 36

37 QUESTIONS? 37

38 For more information Gary D. Bachman Wisconsin Public Utility Institute May 26, 2010

CAISO Participating Intermittent Resource Program for Wind Generation

CAISO Participating Intermittent Resource Program for Wind Generation CAISO Participating Intermittent Resource Program for Wind Generation Jim Blatchford CAISO Account Manager Agenda CAISO Market Concepts Wind Availability in California How State Supports Intermittent Resources

More information

Colorado PUC E-Filings System

Colorado PUC E-Filings System Page 1 of 10 30-Minute Flex Reserve on the Public Service Company of Colorado System Colorado PUC E-Filings System Prepared by: Xcel Energy Services, Inc. 1800 Larimer St. Denver, Colorado 80202 May 13,

More information

Bringing Renewables to the Grid. John Dumas Director Wholesale Market Operations ERCOT

Bringing Renewables to the Grid. John Dumas Director Wholesale Market Operations ERCOT Bringing Renewables to the Grid John Dumas Director Wholesale Market Operations ERCOT 2011 Summer Seminar August 2, 2011 Quick Overview of ERCOT The ERCOT Market covers ~85% of Texas overall power usage

More information

Wind Rules and Forecasting Project Update Market Issues Working Group 12/14/2007

Wind Rules and Forecasting Project Update Market Issues Working Group 12/14/2007 Wind Rules and Forecasting Project Update Market Issues Working Group 12/14/2007 Background Over the past 3 MIWG meetings, NYISO has discussed a methodology for forecasting wind generation in the NYCA

More information

DEMAND FORECASTING PROTOCOL

DEMAND FORECASTING PROTOCOL FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 443 DEMAND FORECASTING PROTOCOL FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 444 DEMAND FORECASTING PROTOCOL Table of Contents DFP 1 OBJECTIVES,

More information

Prediction of Power System Balancing Requirements and Tail Events

Prediction of Power System Balancing Requirements and Tail Events Prediction of Power System Balancing Requirements and Tail Events PNNL: Shuai Lu, Yuri Makarov, Alan Brothers, Craig McKinstry, Shuangshuang Jin BPA: John Pease INFORMS Annual Meeting 2012 Phoenix, AZ

More information

International Workshop on Wind Energy Development Cairo, Egypt. ERCOT Wind Experience

International Workshop on Wind Energy Development Cairo, Egypt. ERCOT Wind Experience International Workshop on Wind Energy Development Cairo, Egypt ERCOT Wind Experience March 22, 21 Joel Mickey Direcr of Grid Operations Electric Reliability Council of Texas jmickey@ercot.com ERCOT 2 2

More information

A Unified Framework for Defining and Measuring Flexibility in Power System

A Unified Framework for Defining and Measuring Flexibility in Power System J A N 1 1, 2 0 1 6, A Unified Framework for Defining and Measuring Flexibility in Power System Optimization and Equilibrium in Energy Economics Workshop Jinye Zhao, Tongxin Zheng, Eugene Litvinov Outline

More information

Systems Operations. PRAMOD JAIN, Ph.D. Consultant, USAID Power the Future. Astana, September, /6/2018

Systems Operations. PRAMOD JAIN, Ph.D. Consultant, USAID Power the Future. Astana, September, /6/2018 Systems Operations PRAMOD JAIN, Ph.D. Consultant, USAID Power the Future Astana, September, 26 2018 7/6/2018 Economics of Grid Integration of Variable Power FOOTER GOES HERE 2 Net Load = Load Wind Production

More information

Derogation Criteria for the Requirements for Generators Network Code

Derogation Criteria for the Requirements for Generators Network Code Derogation Criteria for the Requirements for Generators Network Code Decision Paper Reference: CER/17/084 Date Published: 13/04/2017 Closing Date: 0 Executive Summary Commission Regulation (EU) 2016/631

More information

Pursuant to Section 205 of the Federal Power Act ( FPA ) 1 and the Commission s

Pursuant to Section 205 of the Federal Power Act ( FPA ) 1 and the Commission s PJM Interconnection 2750 Monroe Boulevard Norristown, PA 19403-2497 Steven R. Pincus Associate General Counsel 610.666.4370 fax 610.666.8211 steven.pincus@pjm.com July 31, 2017 Honorable Kimberly D. Bose

More information

Battery Energy Storage

Battery Energy Storage Battery Energy Storage Implications for Load Shapes and Forecasting April 28, 2017 TOPICS» What is Energy Storage» Storage Market, Costs, Regulatory Background» Behind the Meter (BTM) Battery Storage Where

More information

Recent US Wind Integration Experience

Recent US Wind Integration Experience Wind Energy and Grid Integration Recent US Wind Integration Experience J. Charles Smith Nexgen Energy LLC Utility Wind Integration Group January 24-25, 2006 Madrid, Spain Outline of Topics Building and

More information

Operations Report. Tag B. Short, Director South Region Operations. Entergy Regional State Committee (ERSC) February 14, 2018

Operations Report. Tag B. Short, Director South Region Operations. Entergy Regional State Committee (ERSC) February 14, 2018 Operations Report Tag B. Short, Director South Region Operations Entergy Regional State Committee (ERSC) February 14, 2018 1 Winter Operations Highlights South Region Max Gen Event Regional Dispatch Transfer

More information

Wind power and management of the electric system. EWEA Wind Power Forecasting 2015 Leuven, BELGIUM - 02/10/2015

Wind power and management of the electric system. EWEA Wind Power Forecasting 2015 Leuven, BELGIUM - 02/10/2015 Wind power and management of the electric system EWEA Wind Power Forecasting 2015 Leuven, BELGIUM - 02/10/2015 HOW WIND ENERGY IS TAKEN INTO ACCOUNT WHEN MANAGING ELECTRICITY TRANSMISSION SYSTEM IN FRANCE?

More information

APPENDIX 7.4 Capacity Value of Wind Resources

APPENDIX 7.4 Capacity Value of Wind Resources APPENDIX 7.4 Capacity Value of Wind Resources This page is intentionally left blank. Capacity Value of Wind Resources In analyzing wind resources, it is important to distinguish the difference between

More information

Outage Coordination and Business Practices

Outage Coordination and Business Practices Outage Coordination and Business Practices 1 2007 Objectives What drove the need for developing a planning/coordination process. Why outage planning/coordination is crucial and important. Determining what

More information

2018 Annual Review of Availability Assessment Hours

2018 Annual Review of Availability Assessment Hours 2018 Annual Review of Availability Assessment Hours Amber Motley Manager, Short Term Forecasting Clyde Loutan Principal, Renewable Energy Integration Karl Meeusen Senior Advisor, Infrastructure & Regulatory

More information

Economic Evaluation of Short- Term Wind Power Forecasts in ERCOT: Preliminary Results

Economic Evaluation of Short- Term Wind Power Forecasts in ERCOT: Preliminary Results Economic Evaluation of Short- Term Wind Power Forecasts in ERCOT: Preliminary Results Preprint K. Orwig, B.-M. Hodge, G. Brinkman, E. Ela, and M. Milligan National Renewable Energy Laboratory V. Banunarayanan

More information

Deep Thunder. Local Area Precision Forecasting for Weather-Sensitive Business Operations (e.g. Electric Utility)

Deep Thunder. Local Area Precision Forecasting for Weather-Sensitive Business Operations (e.g. Electric Utility) 1 Deep Thunder Local Area Precision Forecasting for Weather-Sensitive Business Operations (e.g. Electric Utility) Dipl. Ing. Helmut Ludwar Chief Technologist Wien, im Oktober 2010 Forecasts for Weather-Sensitive

More information

SHORT TERM LOAD FORECASTING

SHORT TERM LOAD FORECASTING Indian Institute of Technology Kanpur (IITK) and Indian Energy Exchange (IEX) are delighted to announce Training Program on "Power Procurement Strategy and Power Exchanges" 28-30 July, 2014 SHORT TERM

More information

The North American Electric Reliability Corporation hereby submits Informational Filing of the North American Electric Reliability Corporation.

The North American Electric Reliability Corporation hereby submits Informational Filing of the North American Electric Reliability Corporation. !! January 19, 2016 VIA ELECTRONIC FILING Jim Crone Director, Energy Division Manitoba Innovation, Energy and Mines 1200-155 Carlton Street Winnipeg MB R3C 3H8 Re: North American Electric Reliability Corporation

More information

Power System Seminar Presentation Wind Forecasting and Dispatch 7 th July, Wind Power Forecasting tools and methodologies

Power System Seminar Presentation Wind Forecasting and Dispatch 7 th July, Wind Power Forecasting tools and methodologies Power System Seminar Presentation Wind Forecasting and Dispatch 7 th July, 2011 Wind Power Forecasting tools and methodologies Amanda Kelly Principal Engineer Power System Operational Planning Operations

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Interconnection for Wind Energy ) Docket No. RM

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Interconnection for Wind Energy ) Docket No. RM UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Interconnection for Wind Energy ) Docket No. RM05-4-000 REQUEST FOR REHEARING OF THE NORTH AMERICAN ELECTRIC RELIABILITY COUNCIL

More information

Information Document Calculation of Pool Price and Transmission Constraint Rebalancing Costs During a Constraint Event ID # R

Information Document Calculation of Pool Price and Transmission Constraint Rebalancing Costs During a Constraint Event ID # R Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between an Information Document

More information

Report on Phase 2: System Performance Evaluation. Prepared for:

Report on Phase 2: System Performance Evaluation. Prepared for: THE EFFECTS OF INTEGRATING WIND POWER ON TRANSMISSION SYSTEM PLANNING, RELIABILITY, AND OPERATIONS Report on Phase 2: System Performance Evaluation Prepared for: THE NEW YORK STATE ENERGY RESEARCH AND

More information

CARLOS F. M. COIMBRA (PI) HUGO T. C. PEDRO (CO-PI)

CARLOS F. M. COIMBRA (PI) HUGO T. C. PEDRO (CO-PI) HIGH-FIDELITY SOLAR POWER FORECASTING SYSTEMS FOR THE 392 MW IVANPAH SOLAR PLANT (CSP) AND THE 250 MW CALIFORNIA VALLEY SOLAR RANCH (PV) PROJECT CEC EPC-14-008 CARLOS F. M. COIMBRA (PI) HUGO T. C. PEDRO

More information

REVISED UPDATED PREPARED DIRECT SAFETY ENHANCEMENT COST ALLOCATION TESTIMONY OF GARY LENART SAN DIEGO GAS & ELECTRIC COMPANY AND

REVISED UPDATED PREPARED DIRECT SAFETY ENHANCEMENT COST ALLOCATION TESTIMONY OF GARY LENART SAN DIEGO GAS & ELECTRIC COMPANY AND Application No: Exhibit No.: Witness: A.--00 ) In the Matter of the Application of San Diego Gas & ) Electric Company (U 0 G) and Southern California ) Gas Company (U 0 G) for Authority to Revise ) Their

More information

APPENDIX H WIND INTEGRATION STUDY

APPENDIX H WIND INTEGRATION STUDY STUDY Introduction This wind integration study (WIS) estimates the operating reserves required to both maintain PacifiCorp s system reliability and comply with North American Electric Reliability Corporation

More information

Stochastic Unit Commitment with Topology Control Recourse for Renewables Integration

Stochastic Unit Commitment with Topology Control Recourse for Renewables Integration 1 Stochastic Unit Commitment with Topology Control Recourse for Renewables Integration Jiaying Shi and Shmuel Oren University of California, Berkeley IPAM, January 2016 33% RPS - Cumulative expected VERs

More information

Joint procurement of natural gas for grid operation

Joint procurement of natural gas for grid operation Joint procurement of natural gas for grid operation Slide www.aggm.at 1 Joint procurement of natural gas for grid operation AGGM 19. November 2014 1. General information 2. Procurement Slide 2 Joint procurement

More information

NSP Electric - Minnesota Annual Report Peak Demand and Annual Electric Consumption Forecast

NSP Electric - Minnesota Annual Report Peak Demand and Annual Electric Consumption Forecast Page 1 of 5 7610.0320 - Forecast Methodology NSP Electric - Minnesota Annual Report Peak Demand and Annual Electric Consumption Forecast OVERALL METHODOLOGICAL FRAMEWORK Xcel Energy prepared its forecast

More information

California Independent System Operator (CAISO) Challenges and Solutions

California Independent System Operator (CAISO) Challenges and Solutions California Independent System Operator (CAISO) Challenges and Solutions Presented by Brian Cummins Manager, Energy Management Systems - CAISO California ISO by the numbers 65,225 MW of power plant capacity

More information

Cost of Inflow Forecast Uncertainty for Day Ahead Hydropower Production Scheduling

Cost of Inflow Forecast Uncertainty for Day Ahead Hydropower Production Scheduling Cost of Inflow Forecast Uncertainty for Day Ahead Hydropower Production Scheduling HEPEX 10 th University Workshop June 25 th, 2014 NOAA Center for Weather and Climate Thomas D. Veselka and Les Poch Argonne

More information

Renewables and the Smart Grid. Trip Doggett President & CEO Electric Reliability Council of Texas

Renewables and the Smart Grid. Trip Doggett President & CEO Electric Reliability Council of Texas Renewables and the Smart Grid Trip Doggett President & CEO Electric Reliability Council of Texas North American Interconnected Grids The ERCOT Region is one of 3 North American grid interconnections. The

More information

4/26/94 Revised 12/26/96 5/9/99 7/30/01 WSCC UNSCHEDULED FLOW MITIGATION PLAN

4/26/94 Revised 12/26/96 5/9/99 7/30/01 WSCC UNSCHEDULED FLOW MITIGATION PLAN 4/26/94 Revised 12/26/96 5/9/99 7/30/01 WSCC UNSCHEDULED FLOW MITIGATION PLAN WSCC UNSCHEDULED FLOW MITIGATION PLAN TABLE OF CONTENTS SECTION PAGE 1 PARTIES... 1 2 RECITALS...1 3 TERM... 3 4 DEFINITIONS...

More information

EUROPEAN EXPERIENCE: Large-scale cross-country forecasting with the help of Ensemble Forecasts

EUROPEAN EXPERIENCE: Large-scale cross-country forecasting with the help of Ensemble Forecasts WEPROG Weather & wind Energy PROGnoses EUROPEAN EXPERIENCE: Large-scale cross-country forecasting with the help of Ensemble Forecasts Session 6: Integrating forecasting into market operation, the EMS and

More information

Content Area: Social Studies Standard: 1. History Prepared Graduates: Develop an understanding of how people view, construct, and interpret history

Content Area: Social Studies Standard: 1. History Prepared Graduates: Develop an understanding of how people view, construct, and interpret history Standard: 1. History Develop an understanding of how people view, construct, and interpret history 1. Organize and sequence events to understand the concepts of chronology and cause and effect in the history

More information

Solar Eclipse March 20 th WG System Operation

Solar Eclipse March 20 th WG System Operation Solar Eclipse March 20 th 2015 WG System Operation 6-03-2015 Solar Eclipse 20 March 2015 A solar eclipse will pass through the European power system Between 07:40 and 11:50 UCT (08:40-12:50 CET) The reduction

More information

1 Descriptions of Function

1 Descriptions of Function Wide-Area Wind Generation Forecasting 1 Descriptions of Function All prior work (intellectual property of the company or individual) or proprietary (non-publicly available) work should be so noted. 1.1

More information

Report on System-Level Estimation of Demand Response Program Impact

Report on System-Level Estimation of Demand Response Program Impact Report on System-Level Estimation of Demand Response Program Impact System & Resource Planning Department New York Independent System Operator April 2012 1 2 Introduction This report provides the details

More information

Energy Forecasting Customers: Analysing end users requirements Dec 3rd, 2013 Carlos Alberto Castaño, PhD Head of R&D

Energy Forecasting Customers: Analysing end users requirements Dec 3rd, 2013 Carlos Alberto Castaño, PhD Head of R&D IT Solutions for Renewables Energy Forecasting Customers: Analysing end users requirements Dec 3rd, 2013 Carlos Alberto Castaño, PhD Head of R&D carlos.castano@gnarum.com I. Who we are II. Customers Profiles

More information

Analysis and the methods of forecasting of the intra-hour system imbalance

Analysis and the methods of forecasting of the intra-hour system imbalance POSTER 2016, PRAGUE MAY 24 1 Analysis and the methods of forecasting of the intra-hour system imbalance Štěpán KRATOCHVÍL 1, Jan BEJBL 2 1,2 Dept. of Economy, management and humanities, Czech Technical

More information

FORECASTING OF WIND GENERATION The wind power of tomorrow on your screen today!

FORECASTING OF WIND GENERATION The wind power of tomorrow on your screen today! FORECASTING OF WIND GENERATION The wind power of tomorrow on your screen today! Pierre Pinson 1, Gregor Giebel 2 and Henrik Madsen 1 1 Technical University of Denmark, Denmark Dpt. of Informatics and Mathematical

More information

Optimal Demand Response

Optimal Demand Response Optimal Demand Response Libin Jiang Steven Low Computing + Math Sciences Electrical Engineering Caltech Oct 2011 Outline Caltech smart grid research Optimal demand response Global trends 1 Exploding renewables

More information

WIND INTEGRATION IN ELECTRICITY GRIDS WORK PACKAGE 3: SIMULATION USING HISTORICAL WIND DATA

WIND INTEGRATION IN ELECTRICITY GRIDS WORK PACKAGE 3: SIMULATION USING HISTORICAL WIND DATA WIND INTEGRATION IN ELECTRICITY GRIDS WORK PACKAGE 3: SIMULATION USING PREPARED BY: Strategy and Economics DATE: 18 January 2012 FINAL Australian Energy Market Operator Ltd ABN 94 072 010 327 www.aemo.com.au

More information

Declaration Population and culture

Declaration Population and culture Declaration Population and culture The ministers of the parties to the Alpine Convention regard the socio-economic and socio-cultural aspects mentioned in Article 2, Paragraph 2, Item a., as being central

More information

Improving Forecasting Through Accurate Data. Jim Blatchford Sr. Policy Issues Representative. Rizwaan Sahib Telemetry Engineer CAISO.

Improving Forecasting Through Accurate Data. Jim Blatchford Sr. Policy Issues Representative. Rizwaan Sahib Telemetry Engineer CAISO. Improving Forecasting Through Accurate Data By Jim Blatchford Sr. Policy Issues Representative Rizwaan Sahib Telemetry Engineer Abstract Poor meteorological and production data quality can raise significant

More information

Economic Operation of Power Systems

Economic Operation of Power Systems Economic Operation of Power Systems Section I: Economic Operation Of Power System Economic Distribution of Loads between the Units of a Plant Generating Limits Economic Sharing of Loads between Different

More information

Proper Security Criteria Determination in a Power System with High Penetration of Renewable Resources

Proper Security Criteria Determination in a Power System with High Penetration of Renewable Resources Proper Security Criteria Determination in a Power System with High Penetration of Renewable Resources Mojgan Hedayati, Kory Hedman, and Junshan Zhang School of Electrical, Computer, and Energy Engineering

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * *

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * * BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * * IN THE MATTER OF THE APPLICATION OF PUBLIC SERVICE COMPANY OF COLORADO FOR APPROVAL OF ITS 01 RENEWABLE ENERGY STANDARD COMPLIANCE

More information

Colorado PUC E-Filings System

Colorado PUC E-Filings System Attachment A.1 RES Summary Colorado PUC E-Filings System Total RECs Acquired Non-Distributed Generation Distributed Generation Retail Distributed Generation Carry Forward Previous Carry Forward Total Carry

More information

Multi-Area Stochastic Unit Commitment for High Wind Penetration in a Transmission Constrained Network

Multi-Area Stochastic Unit Commitment for High Wind Penetration in a Transmission Constrained Network Multi-Area Stochastic Unit Commitment for High Wind Penetration in a Transmission Constrained Network Anthony Papavasiliou Center for Operations Research and Econometrics Université catholique de Louvain,

More information

UPDATE ELECTRICITY STATEMENT OF OPPORTUNITIES FOR THE NATIONAL ELECTRICITY MARKET

UPDATE ELECTRICITY STATEMENT OF OPPORTUNITIES FOR THE NATIONAL ELECTRICITY MARKET UPDATE ELECTRICITY STATEMENT OF OPPORTUNITIES FOR THE NATIONAL ELECTRICITY MARKET Published: 26 October 2015 ELECTRICITY STATEMENT OF OPPORTUNITIES IMPORTANT NOTICE Purpose AEMO publishes the Electricity

More information

Page No. (and line no. if applicable):

Page No. (and line no. if applicable): COALITION/IEC (DAYMARK LOAD) - 1 COALITION/IEC (DAYMARK LOAD) 1 Tab and Daymark Load Forecast Page No. Page 3 Appendix: Review (and line no. if applicable): Topic: Price elasticity Sub Topic: Issue: Accuracy

More information

Reducing Contingency-based Windfarm Curtailments through use of Transmission Capacity Forecasting

Reducing Contingency-based Windfarm Curtailments through use of Transmission Capacity Forecasting Reducing Contingency-based Windfarm Curtailments through use of Transmission Capacity Forecasting Doug Bowman Southwest Power Pool Jack McCall Lindsey Manufacturing Co. CIGRE US National Committee 2017

More information

Ms. Cheryl Blundon Director Corporate Services & Board Secretary

Ms. Cheryl Blundon Director Corporate Services & Board Secretary Ai\I or newfoundland!abrader k hydro a nalcor energy company Hydro Place. 500 Columbus Drive. P.O. Box 12400. St. John's. NI. Canada Al 4K7 t. 709.737.1400 f. 709.737.1800 www.n1h.nl.ca May 13, 2015 The

More information

A new stochastic program to facilitate intermittent renewable generation

A new stochastic program to facilitate intermittent renewable generation A new stochastic program to facilitate intermittent renewable generation Golbon Zakeri Geoff Pritchard, Mette Bjorndal, Endre Bjorndal EPOC UoA and Bergen, IPAM 2016 Premise for our model Growing need

More information

Colorado PUC E-Filings System

Colorado PUC E-Filings System Colorado PUC E-Filings System Attachment A.1 RES Summary Total Acquired Non-Distributed Generation Distributed Generation Retail Distributed Generation Carry Forward Previous Carry Forward Total Carry

More information

Space-Time Wind Speed Forecasting for Improved Power System Dispatch

Space-Time Wind Speed Forecasting for Improved Power System Dispatch Space-Time Wind Speed Forecasting for Improved Power System Dispatch Xinxin Zhu 1, Marc G. Genton 1, Yingzhong Gu 2 and Le Xie 2 January 16, 2012 Abstract In order to support large scale integration of

More information

CP:

CP: Adeng Pustikaningsih, M.Si. Dosen Jurusan Pendidikan Akuntansi Fakultas Ekonomi Universitas Negeri Yogyakarta CP: 08 222 180 1695 Email : adengpustikaningsih@uny.ac.id Operations Management Forecasting

More information

Integration of WindSim s Forecasting Module into an Existing Multi-Asset Forecasting Framework

Integration of WindSim s Forecasting Module into an Existing Multi-Asset Forecasting Framework Chad Ringley Manager of Atmospheric Modeling Integration of WindSim s Forecasting Module into an Existing Multi-Asset Forecasting Framework 26 JUNE 2014 2014 WINDSIM USER S MEETING TONSBERG, NORWAY SAFE

More information

RTO Winter Resource Adequacy Assessment Status Report

RTO Winter Resource Adequacy Assessment Status Report RTO Winter Resource Adequacy Assessment Status Report RAAS 03/31/2017 Background Analysis performed in response to Winter Season Resource Adequacy and Capacity Requirements problem statement. Per CP rules,

More information

NATIONAL ELECTRICITY FORECASTING REPORT UPDATE FOR THE NATIONAL ELECTRICITY MARKET

NATIONAL ELECTRICITY FORECASTING REPORT UPDATE FOR THE NATIONAL ELECTRICITY MARKET NATIONAL ELECTRICITY FORECASTING REPORT UPDATE FOR THE NATIONAL ELECTRICITY MARKET Published: December 2014 IMPORTANT NOTICE Purpose The purpose of this publication is to report on the accuracy of the

More information

The Value of (Improved) Renewable Energy Forecasts to Operational and Market Stakeholders. Justin Sharp, Ph.D.

The Value of (Improved) Renewable Energy Forecasts to Operational and Market Stakeholders. Justin Sharp, Ph.D. The Value of (Improved) Renewable Energy Forecasts to Operational and Market Stakeholders Justin Sharp, Ph.D. As yet the wind is an untamed and un-harnessed force; And quite possibly one of the greatest

More information

PROJECT ECONOMIC ANALYSIS

PROJECT ECONOMIC ANALYSIS Electricity Transmission Expansion and Supply Improvement Project (RRP NEP 41155) PROJECT ECONOMIC ANALYSIS A. Overview 1. The economic analysis undertaken for the Electricity Transmission and Supply Improvement

More information

LEGAL DISCLAIMER. APG Coin (APG) White Paper (hereinafter 'the White Paper', 'the Document') is presented for informational purposes only

LEGAL DISCLAIMER. APG Coin (APG) White Paper (hereinafter 'the White Paper', 'the Document') is presented for informational purposes only LEGAL DISCLAIMER THIS DOCUMENT DOES NOT GIVE PERSONAL LEGAL OR FINANCIAL ADVICE. YOU ARE STRONGLY ENCOURAGED TO SEEK YOUR OWN PROFESSIONAL LEGAL AND FINANCIAL ADVICE. APG Coin (APG) White Paper (hereinafter

More information

Responses to Questions Related to the October 10, 2012, Partners in Business Meeting

Responses to Questions Related to the October 10, 2012, Partners in Business Meeting Responses to Questions Related to the October 10, 2012, Partners in Business Meeting Question 1: Regarding the update on the ITC-Entergy transaction, what is the expected impact to ITC Midwest rates and

More information

Wind Integration Study for Public Service of Colorado Addendum Detailed Analysis of 20% Wind Penetration

Wind Integration Study for Public Service of Colorado Addendum Detailed Analysis of 20% Wind Penetration Final Report: Wind Integration Study for Public Service of Colorado Addendum Detailed Analysis of 2% Wind Penetration Prepared for Xcel Energy 55 15th Street Denver, Colorado 822 c/o Mr. Tom Ferguson thomas.f.ferguson@xcelenergy.com

More information

Capacity Scarcity Condition Monday, September 3, 2018 Two primary factors led to the implementation of OP 4 event Significant generation outages and r

Capacity Scarcity Condition Monday, September 3, 2018 Two primary factors led to the implementation of OP 4 event Significant generation outages and r S E P T E M B E R 1 2, 2 0 1 8 September 3 OP-4 Event and Capacity Scarcity Condition Vamsi Chadalavada E X E C U T I V E V I C E P R E S I D E N T A N D C H I E F O P E R A T I N G O F F I C E R Capacity

More information

Business Case: UV Facility Backup Generator

Business Case: UV Facility Backup Generator Business Case: UV Facility Backup Generator Eric Brainich December 13, 2010 Background The Portland Water Bureau is currently working on the design for a new Ultra Violet (UV) Treatment Facility and the

More information

T E S L A T O A C Q U I R E S O L A R C I T Y

T E S L A T O A C Q U I R E S O L A R C I T Y T E S L A T O A C Q U I R E S O L A R C I T Y C R E A T I N G T H E W O R L D S L E A D I N G S U S T A I N A B L E E N E R G Y C O M P A N Y I N V E S T O R P R E S E N T A T I O N A u g u s t 1, 2 0

More information

Contents Economic dispatch of thermal units

Contents Economic dispatch of thermal units Contents 2 Economic dispatch of thermal units 2 2.1 Introduction................................... 2 2.2 Economic dispatch problem (neglecting transmission losses)......... 3 2.2.1 Fuel cost characteristics........................

More information

About Nnergix +2, More than 2,5 GW forecasted. Forecasting in 5 countries. 4 predictive technologies. More than power facilities

About Nnergix +2, More than 2,5 GW forecasted. Forecasting in 5 countries. 4 predictive technologies. More than power facilities About Nnergix +2,5 5 4 +20.000 More than 2,5 GW forecasted Forecasting in 5 countries 4 predictive technologies More than 20.000 power facilities Nnergix s Timeline 2012 First Solar Photovoltaic energy

More information

OFFSHORE INTEGRATION STUDY. Analysis, benchmark and mitigation of storm and ramping risks from offshore wind power in Belgium 05/02/2018

OFFSHORE INTEGRATION STUDY. Analysis, benchmark and mitigation of storm and ramping risks from offshore wind power in Belgium 05/02/2018 OFFSHORE INTEGRATION STUDY Analysis, benchmark and mitigation of storm and ramping risks from offshore wind power in Belgium 05/02/2018 This study has been developed in close collaboration with 1 TABLE

More information

System Impact Assessment Addendum #2 Greenfield & St. Clair Energy Centres

System Impact Assessment Addendum #2 Greenfield & St. Clair Energy Centres IESO_REP_0292 System Impact Assessment Addendum #2 Greenfield & St. lair Energy entres onnection Assessment & Approval Process Issue 3.0 Greenfield Energy entre AA I 2004-167 Applicant: Greenfield Energy

More information

FORECASTING: A REVIEW OF STATUS AND CHALLENGES. Eric Grimit and Kristin Larson 3TIER, Inc. Pacific Northwest Weather Workshop March 5-6, 2010

FORECASTING: A REVIEW OF STATUS AND CHALLENGES. Eric Grimit and Kristin Larson 3TIER, Inc. Pacific Northwest Weather Workshop March 5-6, 2010 SHORT-TERM TERM WIND POWER FORECASTING: A REVIEW OF STATUS AND CHALLENGES Eric Grimit and Kristin Larson 3TIER, Inc. Pacific Northwest Weather Workshop March 5-6, 2010 Integrating Renewable Energy» Variable

More information

Modelling wind power in unit commitment models

Modelling wind power in unit commitment models Modelling wind power in unit commitment models Grid integration session IEA Wind Task 25 Methodologies to estimate wind power impacts to power systems Juha Kiviluoma, Hannele Holttinen, VTT Technical Research

More information

Committee Meeting November 6, 2018

Committee Meeting November 6, 2018 Committee Meeting November 6, 2018 Agenda Where we are in the process Land Use Plan Transportation Element Housing & Neighborhoods Elements Next Steps Schedule November 6: Plan Elements December: Plan

More information

EIA411 May 1, A Report to the Office of Energy Emergency Operations Department of Energy Under EIA-411

EIA411 May 1, A Report to the Office of Energy Emergency Operations Department of Energy Under EIA-411 EIA411 May 1, 2006 A Report to the Office of Energy Emergency Operations Department of Energy Under EIA-411 All questions concerning this data should be directed to: Jason Speer Southwest Power Pool 415

More information

Planning a 100 percent renewable electricity system

Planning a 100 percent renewable electricity system Planning a 100 percent renewable electricity system Andy Philpott Electric Power Optimization Centre University of Auckland www.epoc.org.nz (Joint work with Michael Ferris) INI Open for Business Meeting,

More information

Anemos.Rulez: Extreme Event Prediction and Alarming to Support Stability of Energy Grids

Anemos.Rulez: Extreme Event Prediction and Alarming to Support Stability of Energy Grids Anemos.Rulez: Extreme Event Prediction and Alarming to Support Stability of Energy Grids Hans-Peter (Igor) Waldl, Philipp Brandt Overspeed GmbH & Co. KG, Marie-Curie-Straße 1, 26129 Oldenburg, Germany,

More information

Expedited Filing Draft August 22, 2017

Expedited Filing Draft August 22, 2017 Applicability 1 Section 304.9 applies to: (a) (b) Requirements Expedited Filing Draft August 22, 2017 the legal owner of a wind or solar aggregated generating facility connected to the interconnected electric

More information

Centralized Forecasting Registration and Communication Requirements for Distribution Connected Variable Generators. IESO Training

Centralized Forecasting Registration and Communication Requirements for Distribution Connected Variable Generators. IESO Training Centralized Forecasting Registration and Communication Requirements for Distribution Connected Variable Generators IESO Training May 2017 Centralized Forecasting - Registration and Communication Requirements

More information

Chapter 2. Planning Criteria. Turaj Amraee. Fall 2012 K.N.Toosi University of Technology

Chapter 2. Planning Criteria. Turaj Amraee. Fall 2012 K.N.Toosi University of Technology Chapter 2 Planning Criteria By Turaj Amraee Fall 2012 K.N.Toosi University of Technology Outline 1- Introduction 2- System Adequacy and Security 3- Planning Purposes 4- Planning Standards 5- Reliability

More information

Value of Forecasts in Unit Commitment Problems

Value of Forecasts in Unit Commitment Problems Tim Schulze, Andreas Grothery and School of Mathematics Agenda Motivation Unit Commitemnt Problem British Test System Forecasts and Scenarios Rolling Horizon Evaluation Comparisons Conclusion Our Motivation

More information

POWER SYSTEM OPERATING PROCEDURE LOAD FORECASTING

POWER SYSTEM OPERATING PROCEDURE LOAD FORECASTING POWER SYSTEM OPERATING PROCEDURE LOAD FORECASTING PREPARED BY: PROCEDURE TYPE: DOCUMENT REFERENCE: FINAL APPROVER: Systems Capability System Operating Procedure SO_OP_3710 Christian Schaefer DOC. VERSION:

More information

ISO Smart Grid Use Case

ISO Smart Grid Use Case SMART GRID ROADMAP PROJECT IC3 Non-dispatchable Distributed Energy Resources (DER) changes ISO Forecast IC-3 Non-dispatchable Distributed Energy Resources (DER) Changes ISO Forecast and Unit Commitment

More information

Director Corporate Services & Board Secretary

Director Corporate Services & Board Secretary March, The Board of Commissioners of Public Utilities Prince Charles Building Torbay Road, P.O. Box 0 St. John s, NL AA B Attention: Ms. Cheryl Blundon Director Corporate Services & Board Secretary Dear

More information

Technical Requirements. Version No. 1.0 Effective Date 10/1/2008

Technical Requirements. Version No. 1.0 Effective Date 10/1/2008 PURPOSE This document applies to wind Generators and describes technical standards that such wind Generators must satisfy to be qualified as a Participating Intermittent Resource (PIR) under the CAISO

More information

Software Tools: Congestion Management

Software Tools: Congestion Management Software Tools: Congestion Management Tom Qi Zhang, PhD CompuSharp Inc. (408) 910-3698 Email: zhangqi@ieee.org October 16, 2004 IEEE PES-SF Workshop on Congestion Management Contents Congestion Management

More information

COORDINATING CONGESTION RELIEF ACROSS MULTIPLE REGIONS

COORDINATING CONGESTION RELIEF ACROSS MULTIPLE REGIONS COORDINATING CONGESTION RELIEF ACROSS MULTILE REGIONS MICHAEL D. CADWALADER* SCOTT M. HARVEY** WILLIAM W. HOGAN*** SUSAN L. OE** *HB Hagler Bailly, Inc., Cambridge, MA 02142 **Navigant Consulting, Inc.,

More information

EVALUATION OF WIND ENERGY SOURCES INFLUENCE ON COMPOSITE GENERATION AND TRANSMISSION SYSTEMS RELIABILITY

EVALUATION OF WIND ENERGY SOURCES INFLUENCE ON COMPOSITE GENERATION AND TRANSMISSION SYSTEMS RELIABILITY EVALUATION OF WIND ENERGY SOURCES INFLUENCE ON COMPOSITE GENERATION AND TRANSMISSION SYSTEMS RELIABILITY Carmen Lucia Tancredo Borges João Paulo Galvão carmen@dee.ufrj.br joaopaulo@mercados.com.br Federal

More information

The World Bank Zambia Water Resources Development Project (P114949)

The World Bank Zambia Water Resources Development Project (P114949) Public Disclosure Authorized AFRICA Zambia Water Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 8 ARCHIVED on 13-Jan-2018 ISR28939 Implementing Agencies: Republic of Zambia, Ministry

More information

Duration and deadline differentiated demand: a model of flexible demand

Duration and deadline differentiated demand: a model of flexible demand Duration and deadline differentiated demand: a model of flexible demand A. Nayyar, M. Negrete-Pincetić, K. Poolla, W. Chen, Y.Mo, L. Qiu, P. Varaiya May, 2016 1 / 21 Outline Duration-differentiated (DD)

More information

elgian energ imports are managed using forecasting software to increase overall network e 칁 cienc.

elgian energ imports are managed using forecasting software to increase overall network e 칁 cienc. Elia linemen install Ampacimon real time sensors that will communicate with the dynamic thermal ratings software to control energy import levels over this transmission line. OV RH AD TRAN MI ION D namic

More information

POWER SYSTEM OPERATING PROCEDURE LOAD FORECASTING

POWER SYSTEM OPERATING PROCEDURE LOAD FORECASTING POWER SYSTEM OPERATING PROCEDURE LOAD FORECASTING PREPARED BY: PROCEDURE TYPE: DOCUMENT REFERENCE: FINAL APPROVER: Systems Capability System Operating Procedure SO_OP_3710 Mark Stedwell DOC. VERSION: 19

More information

The Study of Overhead Line Fault Probability Model Based on Fuzzy Theory

The Study of Overhead Line Fault Probability Model Based on Fuzzy Theory Energy and Power Engineering, 2013, 5, 625-629 doi:10.4236/epe.2013.54b121 Published Online July 2013 (http://www.scirp.org/journal/epe) The Study of Overhead Line Fault Probability Model Based on Fuzzy

More information

FORECAST ACCURACY REPORT 2017 FOR THE 2016 NATIONAL ELECTRICITY FORECASTING REPORT

FORECAST ACCURACY REPORT 2017 FOR THE 2016 NATIONAL ELECTRICITY FORECASTING REPORT FORECAST ACCURACY REPORT 2017 FOR THE 2016 NATIONAL ELECTRICITY FORECASTING REPORT Published: November 2017 Purpose The National Electricity Rules (Rules) require AEMO to report to the Reliability Panel

More information

The Group of Representative Bodies (GRB) Position Paper on the EC Expert Group on the Technical Pillar of the 4th Railway Package Topics

The Group of Representative Bodies (GRB) Position Paper on the EC Expert Group on the Technical Pillar of the 4th Railway Package Topics The Group of Representative Bodies (GRB) Position Paper on the EC Expert Group on the Technical Pillar of the 4th Railway Package Topics Brussels, 15.03.2017 1 P a g e Scope of this GRB position paper

More information