SUPPLEMENTAL LEVEE FAILURE ANALYSIS USING NWS BREACH AND HEC-RAS EXISTING RD 799 LEVEE AT SANDMOUND SLOUGH

Size: px
Start display at page:

Download "SUPPLEMENTAL LEVEE FAILURE ANALYSIS USING NWS BREACH AND HEC-RAS EXISTING RD 799 LEVEE AT SANDMOUND SLOUGH"

Transcription

1 SUPPLEMENTAL LEVEE FAILURE ANALYSIS USING NWS BREACH AND HEC-RAS EXISTING RD 799 LEVEE AT SANDMOUND SLOUGH FOR THE CYPRESS LAKES PROJECT CONTRA COSTA COUNTY, CALIFORNIA September 2, 2003 Prepared By: CIVIL SOLUTIONS 1325 Howe Avenue Suite 202 Sacramento, CA (916) JOB # This document prepared under the supervision of: Signature dated : The status of this report is PRELIMINARY unless the appropriate signature is provided to the left. Signature will not be provided until review is complete Civil Solutions

2 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough -i- TABLE OF CONTENTS 1 SUMMARY AND CONCLUSIONS INTRODUCTION PURPOSE OF THE STUDY SITE DESCRIPTION Location Existing Conditions Proposed Cypress Lakes Project STUDY APPROACH FLOOD HAZARD ASSUMPTIONS Model Datum Tide Hydrograph TWELVE BREACH SCENARIOS LEVEE FAILURE COMPUTER MODELS THE BREACH MODEL Input Data Description Levee Geometry and Soils Reservoir Variables Calculation of Breach Geometry and Dynamics Breach Model Results HEC-RAS Input Data Description River Reaches Cross-sections Inline and Lateral Structures Flow Data and Boundary Conditions HEC-RAS Geospatial Referencing MODELING THE LEVEE BREACH IN HEC-RAS RESULTS TIME-TO-FILL MAXIMUM FLOW VELOCITY Average Channel Velocity Velocity Distribution RECOMMENDATIONS REPAIR THE LEVEE BREACH AS QUICKLY AS POSSIBLE INTERIOR LEVEE DESIGN...29

3 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough -ii- 7.3 GOLF COURSE CONSTRUCTION...29

4 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough -iii- LIST OF TABLES Table 1 - Breach Location and Development Scenario Matrix Table 2 - Breach Model Input Summary Table 3 - Breach Model Output Data Summary Table 4 - Downstream Boundary Hydrograph Computation Rule Table 5 - Summary of Breach Data Used in Hec-ras Table 6 - Time-to-fill Summary

5 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough -iv- LIST OF FIGURES Figure 1- Vicinity Map Figure 2 - Site and Levee Boring Location Map Figure 3 - Typical Levee Cross-section Figure 4 - Breach Locations Figure 5- Comparison of 100-year High Tide Elevations and BREACH Model Reservoir Stage Figure 6 - Typical HEC-RAS With-Project Stream System Schematic Figure 7 - Typical HEC-RAS Cross-section Figure 8 - Lateral Diversion Rating Curve Figure 9 - Typical HEC-RAS Lateral Structure Figure 10a, 10b - Levee Failure Geometry and Flow Progression from BREACH Model Figure 11 - HEC-RAS Levee Breach Progression Curve Figure 12 - Typical HEC-RAS Inline Structure and Breach Figure 13 - Breach 1: Rate of Fill Analysis Figure 14 - Breach 2: Rate of Fill Analysis Figure 15 - Breach 3: Rate of Fill Analysis Figure 16 - Breach 1: Velocity Profiles Figure 17 - Breach 2: Velocity Profiles Figure 18 - Breach 3: Velocity Profiles Figure 19 - Figure 20 - Figure 21 - Figure 22 -

6 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough -v- LIST OF APPENDICES APPENDIX A YEAR TIDE DATA APPENDIX B - BREACH INPUT AND OUTPUT FILES APPENDIX C - HEC-RAS VELOCITY PLOTS APPENDIX D - OVERSIZED EXHIBITS APPENDIX E - CD

7 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough -vi- FIGURE 1 VICINITY MAP

8 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page -1-1 SUMMARY AND CONCLUSIONS This report presents the results of a study of potential flooding of the Hotchkiss Tract. The study uses two computer models (BREACH and HEC-RAS) to simulate a breach in the Sandmound Slough Levee, and to compute hydraulic and hydrologic conditions of the resulting flood. The study was undertaken to determine: Would the construction of an interior levee by the Cypress Lakes Project have a significant effect on flooding conditions, and if so, Can those changes in conditions be associated with differences in the risks to life and property created by the flooding. We identified two conditions that we believe can be related to the relative risks associated with flooding; maximum flow velocity and time-to-fill. The study evaluates these conditions for 4 levels of development; Existing conditions, Phase 1 development, Ultimate level of development and Ultimate development with golf course plus 3 potential breach locations, resulting in 12 modeling scenarios. The results of the model study indicate that, while the overall magnitude of the changes are modest, there are local increases in maximum flow velocity due to construction of the Cypress Lakes levee. This occurs mostly in the zone between the existing and proposed levees. The timeto-fill is reduced from approximately 60 hours to 57.5 hours, or by less than 5%.

9 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page -2-1 INTRODUCTION 1.1 PURPOSE OF THE STUDY This study analyzes the hydraulic and hydrologic conditions on the Hotchkiss Tract that could result from the failure of the levee on Sandmound Slough, in the vicinity of the proposed Cypress Lakes Project. It focuses on two conditions that can be associated with the risks to life and property as a consequence of such a failure. These are maximum flow velocity and time-tofill. Maximum flow velocity is directly related to the forces that endanger life and damage structures, cause erosion, etc. Time-to-fill is an indicator of the available emergency response time. The study considers three potential levee breach locations and four development scenarios, resulting in 12 site conditions with differing physical characteristics. The study is designed to allow the investigators to evaluate the effect these physical differences may have on the resulting hydraulic and hydrologic conditions of the site, and therefore the associated relative risks. 1.2 STUDY LIMITATIONS AND DISCLAIMER The study is designed to establish a basis for comparing the relative risk to life and property from an assumed levee failure. We made no attempt to determine the probability of a levee failure, and the levee failure is assumed to be equally likely at any location. The 3 failure locations were chosen to be representative of the northerly, central and southerly regions of the site, not for any conditions specific to that location. The direct impacts of the levee failure on structures within the failure zone itself was not a factor in the choice of breach locations. Due to limited data and limited model sophistication, the study is only intended as a comparison of the relative risks, not as an absolute or objective establishment of the magnitude of these risks. No attempt is made to quantify the magnitude of the losses, in lives or dollars, that would result from a levee failure. The time-to-fill factor is a relative measure of the duration of the initial flood event. It is defined as the time when the interior water surface elevation reaches the exterior tide elevation, so the initial flow of water into the site from Sandmound Slough ceases. It does not consider the elevation of existing roadways or structures, does not imply or assume an elevation below which there is no risk to life or damage to property, etc., and is not to be taken as an indication of the time available for evacuation or emergency response. It is simply a relative measure of the effect that changes in site volume due to variation in levee geometry could have on the rate at which the water surface within the Hotchkiss tract would rise in response to the driving tidal elevation. 1.3 SITE DESCRIPTION Location The study site is located on the Hotchkiss Tract, Contra Costa County, California (Figure 1). It occupies approximately 3,230 acres between Dutch Slough on the North, Sandmound Slough on the East, Rock Slough on the South, the Contra Costa Canal and Little Dutch Slough on the West

10 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page -3- (Figure 2) Existing Conditions Most of the site is below the diurnal tidal elevation in the adjacent sloughs of the Sacramento/San Joaquin Delta. Elevations range from -9 ft NGVD to over 15 ft NGVD, with most of the land surface between 0.0 and 1.0 ft Levees along Dutch Slough and Sandmound Slough protect the Hotchkiss Tract from flooding. A typical levee cross-section is shown in Figure 3. Several residences occupy the area along Sandmound Slough, including several that are on the levee interior bank Proposed Cypress Lakes Project The Cypress Lakes Project proposes to develop approximately 681 acres of the site with residential development. Current development proposal includes constructing a levee approximately 400 feet inboard of the existing Sandmound Slough Levee (RD 799 Levee). There are three potential levee configurations; Phase 1", Ultimate Development without golf course fill between the levees, and Ultimate Development with golf course fill between the levees. These levee configurations are shown on Figures A, B and C.

11 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page -4- FIGURE 2 SITE LEVE BORI LOCA MAP AND E NG TION

12 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page -5-2 STUDY APPROACH The study was developed to evaluate the hydraulic and hydrologic conditions on the Hotchkiss Tract at the location of the Cypress Lakes Development in the event of a breach in the Sandmound Slough levee. Two computer models were required for this study. The National Weather Service BREACH model, and the U.S. Army Corps of Engineers, Hydrologic Engineering Center s River Analysis System (HEC-RAS v Unsteady State). The BREACH model was used to determine the geometry of the levee breach, and HEC-RAS was used to model unsteady flow hydraulics. More details on the models is provided below. 2.1 FLOOD HAZARD ASSUMPTIONS Model Datum The BREACH model cannot work with negative elevations. The model datum was adjusted to ft NGVD for this analysis. For example, the elevation of the typical levee toe on the inboard side is -4.0 ft NGVD, represented as 96.0 ft in BREACH. All elevations were adjusted back to NGVD for the HEC-RAS modeling Tide Hydrograph The BREACH model study assumes the levee failure occurs at the 100-year high tide elevation of 7.0 ft NGVD at the beginning of a 10-day period of high tides and high river flows. This is considered to be the worst case condition for flood hazards. The tidal elevations were proportionately adjusted from the February 21, 1986 to March 3, 1986 Rock Slough gage records to correspond to the 100-year high tide elevation 1. The tide vs time hydrograph is presented in Appendix A, Table A-1 and Figure A TWELVE BREACH SCENARIOS There are 12 levee breach scenarios resulting from 3 assumed breach locations and 4 levels of development. Breach 1 is near the northern end and opposite of the proposed Phase 1 Cypress Lakes Levee. Breach 2 is centrally located, directly across from the area of the widest setback between the existing and proposed levees, and the Breach 3 is at the southern end of the Cypress Lakes project. The 3 levee breach locations are shown on Figure 4. The 4 development scenarios are: 1. Existing Conditions - no Cypress Lakes Project and no new levee construction. 2. Phase 1 - Includes the Phase 1 Cypress Lakes Levee, approximately 400 feet inboard of the existing levee. 1 The measured high tide was 9.28 ft Mean Lower Low Water (MLLW). This value was adjusted to NGVD by subtracting 3.0 ft. All values in the hydrograph were then adjusted by the ratio 7/6.28.

13 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page Ultimate Development - No Golf Course - This levee encloses the Cypress Lakes project at build-out, but without the proposed golf course fill between the levees. 4. Ultimate Development - With Golf Course. The Ultimate Cypress Lakes Levee with golf course fill between the levees. For the purpose of this study, the modeling of the development scenarios focuses on the geometry of the Cypress Lakes Levee, and how it effects the hydraulics of the flow pathway(s) downstream of the breach sites, and the total available volume of storage as it relates to the timeto-fill. The 12 scenarios are shown as a matrix in Table 1. TABLE 1 BREACH LOCATION AND DEVELOPMENT SCENARIO MATRIX Breach Location Development Scenario Breach 1 - North Breach 2 - Central Breach 3 - South Existing Conditions B1EX B2EX B3EX Phase 1 B1P1 B2P1 B3P1 Ultimate Development: No Golf Course Ultimate Development: With Golf Course B1NG B2NG B3NG B1WG B2WG B3WG 3.3 LEVEE FAILURE The study assumes the same levee failure conditions for all 12 scenarios. Typical conditions representative of the entire levee were used in the BREACH model, and the results of the BREACH model were used in all subsequent HEC-RAS model runs.

14 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page -7-

15 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page -8-4 COMPUTER MODELS The study required two computer models, BREACH and HEC-RAS The BREACH model is deterministic with regard to the levee failure. It uses the laws of physics applied to the processes of erosion and sediment transport mechanics to compute the dynamics of the levee failure, that is, how the breach geometry develops and changes over time. The model calculates flow through the breach based on a weir flow equation. It is limited to calculating flow in one direction (through the breach from the reservoir ), and does not have the ability to calculate complex hydraulics of flow in the channel downstream of the levee failure. HEC-RAS is a one-dimensional hydraulic model with recently added capabilities to calculate unsteady flow and mixed flow conditions. However, the solution procedure can become unstable and fail to converge on a rational solution when flow is near critical depth, the channel is dry, or the rate of change of flow or hydraulic properties of the channel is too rapid. HEC-RAS also calculates flow through the breach as weir flow and channel flow when the weir is submerged. It can calculate flow in both directions, depending upon the hydraulic conditions, and reports flow from the downstream side of the levee back through the breach as negative values. The levee failure routine in HEC-RAS is parametric. It does not calculate breach geometry or breach dynamics in the same manner as the BREACH model. HEC-RAS applies simple algebraic algorithms to data, supplied by the modeler, that defines the breach geometry and the breach progression. So despite more sophisticated hydraulic computation capabilities, HEC- RAS requires the modeler to specify the initial and final breach geometry, the timeline and pathway of the breach dynamics. Therefore, the results of the BREACH model analysis were used to specify the properties of the levee failure, and HEC-RAS was used to model the hydraulic conditions downstream of the failure. 4.1 THE BREACH MODEL Input Data Description Input to the BREACH model includes data describing: The levee (or dam) geometry, engineering properties of the levee soils and the grass cover, if it exists; The reservoir surface area/volume relationship, and the magnitude and timing of inflow to the reservoir; Whether the failure begins as an overtopping or piping failure, and the elevation at which the failure begins; Data to define a single tailwater cross-section and downstream channel slope; Some information on initial conditions and constraints on the breach. BREACH model input data is summarized in Table 2. The complete BREACH model input file,

16 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page -9- output file, and variable definitions can be found in Appendix B. TABLE 2 BREACH MODEL INPUT SUMMARY Variable Description Value HI Initial Tide elevation (ft) HU Elevation of top of levee HL Elevation of the bottom of the levee on the inboard side 96.0 HPI Elevation at which piping failure begins ZU Slope of the outboard face of the levee 2.25 ZD Slope of the inboard face of the levee 2.50 GL Average length of grass on the levee (inches) 2.0 GS Condition of the grass on the levee (poor) 0.0 VMP Maximum permissible velocity for grass lined channel before grass is eroded away (fps) D50S D50 (mm) of outer material on the levee.20 PORS Porosity ratio of the outer material.38 UWS Unit weight (lbs/cu ft) of outer material AFRS Internal friction angle (degrees) of outer material 31.0 COHS Cohesive strength of outer material (lb/sq ft) 6.6 UNFCC Ratio of D90 to D30 grain size of outer material Levee Geometry and Soils The typical levee cross-section in Figure 3 was provided by Barbara Burns, KSN, Inc. Soils data on grain size is taken from boring logs and analysis by Klienfelder (1999), and other soils properties are from data provided by Foott (1994). Soil cohesion was adjusted upward in response to comments in a memo from Kevin Coulton (HDR, 3/17/2003) to account for reported pore pressure cohesion in otherwise cohesionless soils.

17 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page -10- FIGURE 3 TYPICAL LEVEE CROSS-SECTION

18 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page Reservoir Variables The BREACH model uses reservoir stage as the upstream hydraulic grade line for calculating flow through the levee breach. So for this analysis, the 100-year tide cycle would have to be represented in the BREACH model as a varying water level in the reservoir. However, reservoir stage is not a direct input variable. It is calculated in the model from input variables that define the reservoir stage/volume relationship, a time series of reservoir inflows, and computed outflow through the breach. Since only 8 pairs of values can be specified for the time and magnitude of reservoir inflow, and 8 pairs of values define the reservoir stage-volume relationship, the modeler does not have sufficient control of the reservoir stage to completely model the tidal regime for the 10-day study period. However, after a number of iterations, we were able to create a time series of reservoir water surface elevations that envelope the daily maximum tide elevations for the ten day study period. The resulting reservoir stage is generally higher than the tide elevations over the study period. This should somewhat compensate for the inability of the BREACH model to account for the erosive forces of the ebb tide on breach formation and expansion. We believe this is the best that can be done given the limitations of the BREACH model. The reservoir stage is plotted with the maximum daily tide elevations in Figure 5.

19 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page Calculation of Breach Geometry and Dynamics The BREACH model calculates failures that initiate in piping mode or overtopping mode. Piping mode was chosen for this study. The BREACH model calculates orifice flow and erosion of the failure pipe until the pipe collapses, and then converts to weir flow calculations. The expansion and collapse of the pipe, and the expansion of the resulting trapezoidal breach are based on calculations of erosion rates, sediment transport capacity of the flow, and the strength of the soil and grass cover given the engineering properties of the soils specified in the input data. The elevation at which the failure pipe initiates was originally set to ft (model datum). This elevation was chosen as representative of elevations related to rodent damage, and piping failures on similar levees in the region. In response to comments from reviewers, we changed this elevation to determine the effect this variable has on the failure geometry and dynamics. The results demonstrate that if the initial pipe elevation is too high, above the phreatic zone, the pipe does not collapse during the simulation. If the pipe initiates too low, the collapse occurs within the first time step, provides no information on the flow transition from piping to weir flow, and does not result in a significantly different final weir geometry Breach Model Results The BREACH Model provides detailed output at each time step on flow conditions, reservoir state, erosion of the levee face, breach geometry, and weir hydraulics, etc. A summary of the BREACH model results is presented in Table 3, and output variable definitions and the complete output table are presented in Appendix B. TABLE 3 BREACH MODEL OUTPUT DATA SUMMARY Variable Description Value QBP MAX OUTFLOW THRU BREACH (CFS) TP TIME AT WHICH PEAK OUTFLOW OCCURS (HR) TRS DURATION OF RISING LIMB OF HYDROGRAPH (HR) TB TIME AT WHICH SIGNIFICANT RISE IN OUTFLOW STARTS (HR) 0.0 BRD FINAL DEPTH OF BREACH (FT) 13.0 BRW TOP WIDTH OF BREACH AT PEAK BREACH FLOW (FT) 188 HU ELEVATION OF TOP OF DAM (FT) HC FINAL ELEVATION OF BOTTOM OF BREACH (FT) 96.0 Z SIDE SLOPE OF BREACH AT PEAK BREACH FLOW (FT/FT) 1.26 BO BOTTOM WIDTH OF BREACH AT PEAK BREACH FLOW (FT) 155

20 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page HEC-RAS Input Data Description Input to the HEC-RAS model includes data describing the stream system layout, the channel cross-sections, bridges, culverts, levees and other hydraulic structures, and the flow conditions River Reaches HEC-RAS is organized by River and Stream Reaches. For all runs, the river is identified as Cypress Lakes. For the three Existing Conditions runs, there is only one stream reach ( Cypress Lakes ) perpendicular to the levee. For the 9 runs of the 3 with-project conditions, there are two stream reaches, Breach X North and Breach X South, where X represents the number assigned to the breach location (See Table 1). A typical stream system layout for the with-project conditions is shown in Figure 6. FIGURE 6 TYPICAL HEC-RAS STREAM SYSTEM LAYOUT

21 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page Cross-sections Channel cross-sections are identified by River Station, numbered from downstream to upstream. The cross-section name typically corresponds to the River Station of its location (the cumulative distance upstream from the beginning of the stream reach, in hundreds of feet or in miles), but not necessarily. The program assigns cross-section order based on the numeric order of the cross-section names, so no matter how they are identified, the names must increase in numeric value from downstream to upstream. Channel cross-sections are described by channel station/elevation pairs, from left to right, looking downstream. Channel station is the horizontal distance along the line of the crosssection. Channel stations can be negative, but must increase from left to right. We have defined the channel stations so that the channel center is at 0.0, and channel stations become more negative to the left and positive to the right. A typical cross-section is presented in Figure 7. FIGURE 7 TYPICAL HEC-RAS CROSS-SECTION

22 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page -15- HEC-RAS is a one-dimensional flow model, while flow through the levee breach expanding into the interior zone is clearly a two-dimensional flow condition. We made an adjustment in our modeling approach to try to account for this. For the Existing Conditions model, elliptical cross-sections were drawn out from the assumed breach centerline to the interior of the site. For the developed condition runs, the section immediately downstream of the breach were also elliptical in shape. The elliptical shape was chosen so that the expanding flow lines will be more nearly perpendicular to the cross-sections. Cross-section locations as shown on the oversize exhibits attached to this report. The detailed information for each cross-section is available in the accompanying HEC-RAS files on CD in APPENDIX E Inline and Lateral Structures Flow through a levee in HEC-RAS can be modeled as a breach in an inline structure or in a lateral structure. Inline structures are parallel to the bounding cross-sections, and lateral structures run between cross-sections, connecting them at the corresponding bank stations or overbank areas. Both are described by weir/embankment data that defines the levee profile, weir crest width, weir coefficient, upstream and downstream embankment sideslopes, weir shape, etc. Outflow from a breached lateral structure becomes lateral inflow between two specified crosssections of an adjacent stream reach. Outflow from a breached inline structure continues downstream to the next cross-section of the same reach. While the Sandmound Slough levee is a lateral structure relative to the project site, we found that it was more appropriate, for the purposes of this analysis, to model it as an inline structure. HEC-RAS requires 2 cross-sections upstream of the inline structure. These cross-sections were constructed to minimize unintended effects on the breach hydraulics, and are not intended to be accurate representations of Sandmound Slough. The cross-section immediately downstream of the inline structure is the inboard face of the levee. For the 9 With Project models, the levee breach is on the Breach X North stream reach. For the 9 with project scenarios, the connection between the North and South stream reaches is defined by a lateral structure. A weir section is specified in the lateral structure. Flow across the weir is controlled by a rating curve, and is independent of the upstream and downstream water surface elevations, weir hydraulics, etc. The rating curve assures that at any flow, one half of the flow upstream of the weir continues downstream in the North reach, and one half of the flow is over the weir into the South reach. The rating curve is presented in Figure 8. Outflow across the lateral weir from the North reach is specified to occur between the left bank stations of the bounding cross-sections, and inflow to the South reach is between the right bank stations of the bounding cross-sections. The upstream section of the South reach was duplicated to create the upstream inflow section. Without this additional cross-section, the upstream cross-section on the South reach only saw the specified upstream boundary condition inflow. With the added crosssection, the hydraulics of the upstream section of the South reach shown on the maps and graphics, and included in the output tables more accurately represents the flow conditions at the

23 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page -16- upstream boundary of the reach. A typical lateral structure is shown in Figure 9.

24 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page -17- FIGURE 8 LATERAL DIVERSION RATING CURVE TY PI CA L HE C- RA S LA TE RA L ST RU CT UR E FIGURE 9

25 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page Flow Data and Boundary Conditions The data entry interval can be specified from 1 minute to 1 year. We chose an interval of 0.25 hours (15 minutes) in an attempt to obtain sufficient data to describe the hydraulic characteristics of the levee failure as it transitions from piping failure to weir flow, and to model the initial breach flood wave. The 240 hour duration at 4 time steps per hour yields 960 time steps. Both upstream and downstream boundary conditions must be specified for each data input interval. Boundary conditions are typically specified as a flow hydrograph, stage hydrograph, stage/flow hydrograph, lateral inflow hydrograph, rating curve, or normal depth. An initial flow is also required at the upstream boundary for each stream reach. The upstream boundary condition of the North reach for all model runs is a stage hydrograph of the tidal regime for the 10-day, 100-year event. Upstream boundary condition on the South reach for all runs is a flow hydrograph of a constant 2 cfs. The downstream boundary condition is a stage hydrograph of the water surface elevation on the study site. It represents the state-of-fill of the site. That is, as flooding from the levee breach progresses, the rising water surface elevation in the study area should appear in the model as an increase in the elevation of the downstream boundary stage hydrograph. At some time - the time-to-fill - the interior water surface and the tide elevation in Sandmound Slough are equalized, and flow into the site ceases. As the tide elevation drops below the interior flood stage, flow would occur across the levee breach from the study site to Sandmound Slough and the interior flood stage would drop. Again, this drop in interior water surface elevation would be represented in the model as a drop in the downstream boundary stage hydrograph. Flow would shift from a positive value, flow from Sandmound Slough into the site, to negative, flow from the site back to Sandmound Slough, several times during the model simulation. Ideally, the stage at each time step would be computed by HEC-RAS from stage/volume data describing the site as a reservoir, a reservoir routing routine, and flow data computed during the model run. Unfortunately, HEC-RAS does not have this capability, and the downstream boundary condition stage hydrograph must be specified in the input data. Civil Solutions devised a spreadsheet program to estimate the reservoir routing computations outside of the HEC-RAS model. The initial stage hydrograph was computed from the flow data obtained from the BREACH model. The spreadsheet program computes the stage at each time step and compares it the with the tide elevation at that time step, until the computed interior stage exceeds the tide elevation. At this point the BREACH model flow data is no longer relevant, as the model can only calculate flow one way. The spreadsheet converts to a simple routine that reduces the interior stage at each time step by an amount that approximates the rate of change associated with the approximate average flow rate. The spreadsheet compares this adjusted interior stage to the tide stage, and when the next rising tide again exceeds the interior stage, the spreadsheet increases the interior stage by the same amount, etc. This produced a useable downstream stage hydrograph for the initial HEC-RAS run. We revised the spreadsheet program to do iterative runs with HEC-RAS, making use of the flow data reported by HEC-RAS at each time step, and the ability of HEC-RAS to report outflows as

26 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page -19- negative values. As before, the spreadsheet program compares the computed interior stage with the tide elevation. If the interior stage equals or exceeds the tide stage, and the next timestep flow is negative (indicating outflow), a new stage is computed and used. However, if the next timestep flow is still positive, the new stage is computed using ½ the reported inflow as outflow. In the same way, if the computed interior stage is less than the tide stage, and the reported next timestep flow is negative, ½ the reported outflow is used as inflow to compute the next timestep stage. While this is an arbitrary adjustment for the unpredictable change in flow direction, it does provide a reasonable level of convergence in 3 to 5 iterations. The computation rule is summarized in Table 4. The modeling results indicate that the unsteady flow routine is extremely sensitive to the downstream stage at the initial time steps. For some runs, the difference in a stable and an unstable model run was as little as 0.01 ft for the first value in the time series. This appears to be associated with problems the HEC-RAS solution procedure has with flows near critical depth. Therefore, the initial value in the downstream boundary stage hydrograph was chosen to achieve a stable model run, and the hydrograph was adjusted to smooth the transition using an internal interpretive routine in HEC-RAS. We attempted to maintain a similar initial boundary condition value for all runs to adhere to the comparative nature of the study. One additional adjustment was made to achieve stable model runs. A pilot channel was included in the model cross-sections to smooth out the apparent channel bed slope. Adverse channel slope, rapid changes in channel slope, and extremely steep channel slopes all tested the HEC- RAS model s computational limits HEC-RAS Geospatial Referencing HEC-RAS stream system geometry can be referenced to a coordinate system using geographic information system (GIS) technology. By overlaying the stream lines and cross-sections on a known coordinate grid, the model results can also be referenced to the same grid. The model output includes velocity and flow distribution information that Civil Solutions was able to assign to points on the model grid, creating a two dimensional picture of conditions on the site at any point in the simulation time. By stringing these images together, Civil Solutions created a video presentation of the velocity field on the site as it progressed through the 10-day simulation period. This presentation can be viewed at the website. Tom - Reference website. 5 MODELING THE LEVEE BREACH IN HEC-RAS HEC-RAS can model a breach in either a lateral structure or an inline structure. The breach can be specified to initiate as a piping failure or an overtopping failure. As indicated earlier, HEC- RAS relies on final breach geometry and a breach progression relationship provided by the modeler. The breach input data includes final bottom width, final bottom elevation, final side slopes for the left and right side of the breach and the time for full breach formation. The Breach Progression is defined by a table of Time Fraction vs Breach Fraction values.

27 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page -20- As noted above, the BREACH model and HEC-RAS approach the levee breach analysis in very different way. This led to significant differences in the flow rates across the breach that each program calculated during the crucial initial stages of the levee failure. Specifically: The BREACH model calculates the initial piping failure will expand and collapse by the end of the first hour. When the same piping failure initial conditions were used in HEC- RAS, it took several hours for the pipe to collapse. It is not clear exactly what criteria HEC-RAS uses to determine when the pipe collapses, but it appears to occur as soon as the water surface elevation touches the pipe soffit. Therefore in HEC-RAS the collapse is dependent upon the tide elevation, not the strength of the levee soils. The BREACH model calculates the levee failure will rapidly incise to its final bottom elevation, while the bottom width and top width remain relatively constant. The top width then increases rapidly while the bottom width increases slowly, and finally the bottom width increases until the side slopes achieve their final angle. So in the BREACH model, the shape of the breach that effects how it behaves as a weir varies throughout the simulation. The change in levee failure geometry and flow over time calculated by the BREACH model are graphed in Figures 10a and 10b. In HEC-RAS, the breach fraction appears to be applied uniformly to the breach geometry so that the breach reaches its final bottom elevation, final bottom width and final top width (based on the fixed side slopes provided) at the same time. This is clearly quite different from the breach progression calculated by the BREACH model, and results in much smaller initial flows through the failed levee than the BREACH model calculates. We varied the breach characteristics used in HEC-RAS to achieve initial flow rates that were consistent with those calculated by the BREACH model. These adjustments include: Changing the failure mechanism from piping mode to overtopping mode, Reducing the initial breach elevation from 4.0 ft to 1.0 ft by specifying a notch in the levee that extends to this elevation (See Figure 12), and Calculate the breach progression fraction based on the change in breach top width. The breach geometry used in HEC-RAS is summarized in Table 5, the breach progression relationship is in Figure 11, and a typical inline structure is shown in Figure 12.

28 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page -21- TABLE 5 SUMMARY OF BREACH DATA USED IN HEC-RAS Variable Value Center Station 0 Final Bottom Width 152 ft Final Bottom Elevation -4.0 ft Left Side Slope 1.25 h:v Right Side Slope 1.25 h:v Full Formation Time (hours) 240 Failure Mode Overtopping Trigger Failure at Water Surface Elevation Starting Water Surface Elevation 6.5 Ft

29 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page -22- FIGURES 10-A, 10-B LEVEE FAILURE GEOMETRY AND FLOW PROGRESSION FROM BREACH MODEL

30 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page -23- FIGURE 11 BREACH PROGRESSION FOR HEC-RAS TYPICAL HEC- RAS INLINE STRUCTURE AND BREACH FIGURE 12

31 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page RESULTS 6.1 TIME-TO-FILL The time-to-fill is the time required for the water surface elevation within the Hotchkiss Tract to equalize with the tide elevation in Sandmound Slough. Again, this is not an absolute measure of the flooding conditions or risks, and is very dependent upon the timing of the breach and the tides, etc. Table 6 presents the time-to-fill, water surface elevation at the time-to-fill and the volume of water on the Hotchkiss Tract at the time-to-fill. Figures 13, 14 and 15 show the rate of filling with the tide elevation curve for each breach location. The time-to-fill varies no more than 2¾ hours, or less than 5 percent. The differing water surface elevations is a reflection of the influence the tidal cycle has on this indicator. The water surface is higher when the time-to-fill is shorter because the tide is falling during this time interval. TABLE 6 Time-to-Fill Comparison Breach 1 Breach 2 Breach 3 Time Stage Volume Time Stage Volume Time Stage Volume Scenario (Hours) (ft) (ac-ft) (Hours) (ft) (ac-ft) (Hours) (ft) (ac-ft) Existing Conditions Phase I Ultimate: No Golf Ultimate: W/ Golf MAXIMUM FLOW VELOCITY Average Channel Velocity Figures 16, 17 and 18 show the average channel velocity at the levee breach face for the 4 levels of development at the 3 breach locations. These figure indicate that breach location has far more influence on the maximum flow velocity - at the breach - than does the differences in levee development. The figures also show that the time of the initial breach may not be the time of highest velocity. The high flow velocities toward the end of the simulation are a consequence of the greater difference in high tide and low tide elevations, combined with the large breach opening (see figure A-1), resulting in greater differences in hydraulic head across the breach, and therefore flow rates and velocities.

32 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page -25-

33 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page -26-

34 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page -27-

35 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page Velocity Distribution As noted above in the HEC-RAS model description, it was necessary to adjust the model geometry to achieve successful model runs, as recommended by the HEC-RAS User s Manual. While these adjustments would not likely influence the average channel velocity data, they do appear in the velocity distribution results. Figures 21 through 24 show typical profiles and crosssections for the 3 developed condition scenarios. These figures compare the elevations on the ground with those used in the HEC-RAS model. The pilot channel shown on the model crosssections increases the apparent depth and width of the channel along the proposed levee toe, and significantly reduces the abruptness and steepness of local changes in the channel bed profile. During low flows, when the hydraulics properties of the channel near the bed are dominant, these two conditions will have opposite effects. That is, the smoother profile will tend to reduce the flow velocity - locally - and the greater capacity of the pilot channel will tend to increase the local flow velocity, as well as the time over which the hydraulic of the small channel dominates. When the flow exceeds the capacity of the pilot channel, the capacity of the channel crossincreases dramatically, and flow velocity is reduced accordingly. As this analysis is intended to be comparative and not absolute, the velocity distribution data does provide some insight into potential issues resulting from construction of the Cypress Lakes levee. The Velocity Distribution figures in Appendix C are composite snapshots of instantaneous maximum velocity by spacial location for each of the 12 modeling scenarios. That is, for each model run, the highest velocity for each point on the spacial grid during the simulation was extracted and included in the plot. These plots are absolute worst case conditions (for the modeled scenario), since the maximum velocities shown at various grid points may have occurred hours or days apart. There are 3 plots for each of the 12 scenarios, the maximum velocity for the first 12 hour period (at the time of the breach), the maximum ebb tide velocity - that is maximum velocity of flow leaving the site, and maximum flood tide velocity - maximum velocity of flow entering the site during the entire 10-day simulation period. These velocity distribution plots indicate that the area between sections J and G in the southern reach, and between sections S and U to the north, consistently experience the highest flow velocities outside of the immediate breach location. Between Sections J and G the construction of the proposed levee would leave a small channel along the outboard toe. Between Sections J and G, the channel is narrower, and the golf course development reduces flow area even further, leading to higher velocities in this reach.

36 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page RECOMMENDATIONS Based on the analysis conducted for this study, Civil Solutions presents the following recommendations: 7.1 REPAIR THE LEVEE BREACH AS QUICKLY AS POSSIBLE This study assumed the breach would occur during a period when the daily low tides remained abnormally high. The modeling indicates that the velocities are generally highest on the ebb tide, when the tide elevations in Sandmound Slough are low and the water surface in Sandmound Slough is high. This occurred toward the end of the modeling period in this study. High velocities in the study occurred in the first two days as the breach formed, but the highest velocities occurred near the end of the 10-day model when the breach was at it s maximum size, and tidal fluctuations were returning to normal values. Therefore, the longer the breach remains open, the greater the potential for the breach to increase in size, and for erosive velocities to occur in the study area. 7.2 INTERIOR LEVEE DESIGN The design and construction of the interior levee should address the potential for erosion of the outboard toe. The creation of a channel along the toe due to the existing site topography interface with the levee fill, creation of a borrow pit for levee fill, or to promote drainage of the region between the levees should be avoided. If a channel is created by or results from levee construction, the levee toe along the channel should be armored. 7.3 GOLF COURSE CONSTRUCTION The construction of portions of the golf course between the levees reduces the cross-sectional area, and increases local flow velocity for the areas between the two levees near the proposed golf course. This may result in a sufficient change in flow regime such that structures and land which may not have been damaged (as a result of flow velocities)in the Post-project without golf scenario, may realize velocities of damaging potential in the post-project with golf scenario (i.e. velocities may exceed the 3 to 6 fps threshold where erosion and structural damage may occur).

37 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page -30-

38 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page -31-

39 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page -32-

40 Cypress Lakes - Levee Failure and Hydraulic Analysis - Sandmound Slough Page -33-

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

Summary of Hydraulic and Sediment-transport. Analysis of Residual Sediment: Alternatives for the San Clemente Dam Removal/Retrofit Project,

Summary of Hydraulic and Sediment-transport. Analysis of Residual Sediment: Alternatives for the San Clemente Dam Removal/Retrofit Project, Appendix N SUMMARY OF HYDRAULIC AND SEDIMENT-TRANSPORT ANALYSIS OF RESIDUAL SEDIMENT: ALTERNATIVES FOR THE SAN CLEMENTE DAM REMOVAL/RETROFIT PROJECT, CALIFORNIA the San Clemente Dam Removal/Retrofit Project,

More information

UPPER COSUMNES RIVER FLOOD MAPPING

UPPER COSUMNES RIVER FLOOD MAPPING UPPER COSUMNES RIVER FLOOD MAPPING DRAFT BASIC DATA NARRATIVE FLOOD INSURANCE STUDY SACRAMENTO COUTY, CALIFORNIA Community No. 060262 November 2008 Prepared By: CIVIL ENGINEERING SOLUTIONS, INC. 1325 Howe

More information

YELLOWSTONE RIVER FLOOD STUDY REPORT TEXT

YELLOWSTONE RIVER FLOOD STUDY REPORT TEXT YELLOWSTONE RIVER FLOOD STUDY REPORT TEXT TECHNICAL REPORT Prepared for: City of Livingston 411 East Callender Livingston, MT 59047 Prepared by: Clear Creek Hydrology, Inc. 1627 West Main Street, #294

More information

PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0

PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0 PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0 LYCOMING COUNTY S.R.15, SECTION C41 FINAL HYDROLOGIC AND HYDRAULIC REPORT STEAM VALLEY RUN STREAM RELOCATION DATE: June, 2006 REVISED:

More information

WP2.1 BREACH FORMATION LARGE SCALE EMBANKMENT FAILURE

WP2.1 BREACH FORMATION LARGE SCALE EMBANKMENT FAILURE WP2. BREACH FORMATION LARGE SCALE EMBANKMENT FAILURE Kjetil Arne Vaskinn, Sweco Gröner Norway Aslak Løvoll, Norconsult AS Norway Kaare Höeg, Norwegian Geotechnical Institute (NGI), Norway WP2. BREACH FORMATION

More information

Technical Memorandum No Sediment Model

Technical Memorandum No Sediment Model Pajaro River Watershed Study in association with Technical Memorandum No. 1.2.9 Sediment Model Task: Development of Sediment Model To: PRWFPA Staff Working Group Prepared by: Gregory Morris and Elsie Parrilla

More information

LOMR SUBMITTAL LOWER NEHALEM RIVER TILLAMOOK COUNTY, OREGON

LOMR SUBMITTAL LOWER NEHALEM RIVER TILLAMOOK COUNTY, OREGON LOMR SUBMITTAL LOWER NEHALEM RIVER TILLAMOOK COUNTY, OREGON Prepared for: TILLAMOOK COUNTY DEPARTMENT OF COMMUNITY DEVELOPMENT 1510-B THIRD STREET TILLAMOOK, OR 97141 Prepared by: 10300 SW GREENBURG ROAD,

More information

LAR BPWG. DWR Erosion Screening Process Application to LAR. May 17, water resource specialists

LAR BPWG. DWR Erosion Screening Process Application to LAR. May 17, water resource specialists LAR BPWG DWR Erosion Screening Process Application to LAR May 17, 2016 Presentation Outline Review of Erosion Screening Process Modifications for LAR Application ESP LAR Results Recommendations ESP Background

More information

Section 4: Model Development and Application

Section 4: Model Development and Application Section 4: Model Development and Application The hydrologic model for the Wissahickon Act 167 study was built using GIS layers of land use, hydrologic soil groups, terrain and orthophotography. Within

More information

ARTICLE 5 (PART 2) DETENTION VOLUME EXAMPLE PROBLEMS

ARTICLE 5 (PART 2) DETENTION VOLUME EXAMPLE PROBLEMS ARTICLE 5 (PART 2) DETENTION VOLUME EXAMPLE PROBLEMS Example 5.7 Simple (Detention Nomograph) Example 5.8 Offsite and Unrestricted Areas (HEC-HMS) Example 5.9 Ponds in Series w/ Tailwater (HEC-HMS) Example

More information

LOMR SUBMITTAL LOWER NESTUCCA RIVER TILLAMOOK COUNTY, OREGON

LOMR SUBMITTAL LOWER NESTUCCA RIVER TILLAMOOK COUNTY, OREGON LOMR SUBMITTAL LOWER NESTUCCA RIVER TILLAMOOK COUNTY, OREGON Prepared for: TILLAMOOK COUNTY DEPARTMENT OF COMMUNITY DEVELOPMENT 1510-B THIRD STREET TILLAMOOK, OR 97141 Prepared by: 10300 SW GREENBURG ROAD,

More information

L OWER N OOKSACK R IVER P ROJECT: A LTERNATIVES A NALYSIS A PPENDIX A: H YDRAULIC M ODELING. PREPARED BY: LandC, etc, LLC

L OWER N OOKSACK R IVER P ROJECT: A LTERNATIVES A NALYSIS A PPENDIX A: H YDRAULIC M ODELING. PREPARED BY: LandC, etc, LLC L OWER N OOKSACK R IVER P ROJECT: A LTERNATIVES A NALYSIS A PPENDIX A: H YDRAULIC M ODELING PREPARED BY: LandC, etc, LLC TABLE OF CONTENTS 1 Introduction... 1 2 Methods... 1 2.1 Hydraulic Model... 1 2.2

More information

Technical Memorandum No

Technical Memorandum No Pajaro River Watershed Study in association with Technical Memorandum No. 1.2.10 Task: Evaluation of Four Watershed Conditions - Sediment To: PRWFPA Staff Working Group Prepared by: Gregory Morris and

More information

Chapter 5 CALIBRATION AND VERIFICATION

Chapter 5 CALIBRATION AND VERIFICATION Chapter 5 CALIBRATION AND VERIFICATION This chapter contains the calibration procedure and data used for the LSC existing conditions model. The goal of the calibration effort was to develop a hydraulic

More information

Appendix E Guidance for Shallow Flooding Analyses and Mapping

Appendix E Guidance for Shallow Flooding Analyses and Mapping Appendix E Guidance for Shallow Flooding Analyses and Mapping E.1 Introduction Different types of shallow flooding commonly occur throughout the United States. Types of flows that result in shallow flooding

More information

APPENDIX B HYDROLOGY

APPENDIX B HYDROLOGY APPENDIX B HYDROLOGY TABLE OF CONTENTS 1.0 INTRODUCTION... 1 2.0 PROBABLE MAXIMUM PRECIPITATION (PMP)... 1 3.0 DESIGN FLOW CALCULATION... 1 4.0 DIVERSION CHANNEL SIZING... 2 5.0 REFERENCES... 4 LIST OF

More information

Standards for Soil Erosion and Sediment Control in New Jersey May 2012

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SEDIMENT BASIN Definition A barrier, dam, excavated pit, or dugout constructed across a waterway or at other suitable locations to intercept and retain sediment. Basins created by construction

More information

WATER MANAGEMENT REPORT FOR PAGE ESTATES

WATER MANAGEMENT REPORT FOR PAGE ESTATES WATER MANAGEMENT REPORT FOR PAGE ESTATES SLB Consulting of SW Florida, LLC PO Box 2826 Bonita Springs, FL. 34133 Phone: 239-948-9566 sandra@slbconsult.com C.O.A. # 25395 September 1, 2014 Sandra L. Bottcher

More information

ENGINEERING HYDROLOGY

ENGINEERING HYDROLOGY ENGINEERING HYDROLOGY Prof. Rajesh Bhagat Asst. Professor Civil Engineering Department Yeshwantrao Chavan College Of Engineering Nagpur B. E. (Civil Engg.) M. Tech. (Enviro. Engg.) GCOE, Amravati VNIT,

More information

STRUCTURAL STABILITY ASSESSMENT

STRUCTURAL STABILITY ASSESSMENT STRUCTURAL STABILITY ASSESSMENT CFR 257.73(d) Bottom Ash Pond Complex Cardinal Plant Brilliant, Ohio October, 2016 Prepared for: Cardinal Operating Company Cardinal Plant Brilliant, Ohio Prepared by: Geotechnical

More information

Technical Memorandum. To: From: Copies: Date: 10/19/2017. Subject: Project No.: Greg Laird, Courtney Moore. Kevin Pilgrim and Travis Stroth

Technical Memorandum. To: From: Copies: Date: 10/19/2017. Subject: Project No.: Greg Laird, Courtney Moore. Kevin Pilgrim and Travis Stroth Technical Memorandum To: From: Greg Laird, Courtney Moore Kevin Pilgrim and Travis Stroth 5777 Central Avenue Suite 228 Boulder, CO 80301 www.otak.com Copies: [Electronic submittal] Date: 10/19/2017 Subject:

More information

STREAM RESTORATION AWRA Summer Specialty Conference, GIS and Water Resources IX

STREAM RESTORATION AWRA Summer Specialty Conference, GIS and Water Resources IX STREAM RESTORATION 2016 AWRA Summer Specialty Conference, GIS and Water Resources IX Innovative Use of 2D Hydraulic Modeling in Stream Restoration Design Presented by: Li Gao, PE and Robert Scrafford,

More information

Sediment and Water Quality in HEC-RAS. Mark Jensen

Sediment and Water Quality in HEC-RAS. Mark Jensen Sediment and Water Quality in HEC-RAS Mark Jensen The HEC-RAS Modeling System 1D River Hydraulics Graphical User Interface Steady & Unsteady Flow Bridges, Culverts, Dams, weirs, gates, etc Data storage/management

More information

TSEGI WASH 50% DESIGN REPORT

TSEGI WASH 50% DESIGN REPORT TSEGI WASH 50% DESIGN REPORT 2/28/2014 Daniel Larson, Leticia Delgado, Jessica Carnes I Table of Contents Acknowledgements... IV 1.0 Project Description... 1 1.1 Purpose... 1 Figure 1. Erosion of a Headcut...

More information

Limited Visual Dam Safety Inspections OA Oahu Reservoir No Oahu, Hawaii

Limited Visual Dam Safety Inspections OA Oahu Reservoir No Oahu, Hawaii Limited Visual Dam Safety Inspections OA00137 Oahu Reservoir No. 155 Oahu, Hawaii Prepared by: U.S. ARMY CORPS OF ENGINEERS HONOLULU DISTRICT STATE OF HAWAII DEPARTMENT OF LAND AND NATURAL RESOURCES May

More information

PRELIMINARY DRAFT FOR DISCUSSION PURPOSES

PRELIMINARY DRAFT FOR DISCUSSION PURPOSES Memorandum To: David Thompson From: John Haapala CC: Dan McDonald Bob Montgomery Date: February 24, 2003 File #: 1003551 Re: Lake Wenatchee Historic Water Levels, Operation Model, and Flood Operation This

More information

Rock Sizing for Batter Chutes

Rock Sizing for Batter Chutes Rock Sizing for Batter Chutes STORMWATER MANAGEMENT PRACTICES Photo 1 Rock-lined batter chute Photo 2 Rock-lined batter chute 1. Introduction In the stormwater industry a chute is a steep drainage channel,

More information

ERDC/LAB TR-0X-X 100. Figure 7-3 Maximum velocity magnitudes for existing conditions for 100-year flood event

ERDC/LAB TR-0X-X 100. Figure 7-3 Maximum velocity magnitudes for existing conditions for 100-year flood event ERDC/LAB TR-0X-X 100 Figure 7-3 Maximum velocity magnitudes for existing conditions for 100-year flood event ERDC/LAB TR-0X-X 101 Figure 7-4 Model schematization of Option 1 Figure 7-5 Bed displacement

More information

Leveraging new models and data to improve flood stage forecast. Improving Flood Stage Forecasting in the Feather River Watershed. September 11 th 2015

Leveraging new models and data to improve flood stage forecast. Improving Flood Stage Forecasting in the Feather River Watershed. September 11 th 2015 Leveraging new models and data to improve flood stage forecast Improving Flood Stage Forecasting in the Feather River Watershed September 11 th 2015 Mitch Russo, P.E. (DWR) Ashok Bathulla, P.E., CFM (GEI)

More information

Evaluation of Scour Depth around Bridge Piers with Various Geometrical Shapes

Evaluation of Scour Depth around Bridge Piers with Various Geometrical Shapes Evaluation of Scour Depth around Bridge Piers with Various Geometrical Shapes Dr. P. D. Dahe * Department of Civil Engineering, SGGSIE&T, Vishnupuri, Nanded (Maharashtra) S. B. Kharode Department of Civil

More information

Continuing Education Course #101 Drainage Design with WinTR-55

Continuing Education Course #101 Drainage Design with WinTR-55 1 of 5 Continuing Education Course #101 Drainage Design with WinTR-55 1. WinTR-55 uses the Kinematic Wave method for calculating storm runoff rates and volumes. 2. According to the Velocity Method, the

More information

Appendix 15 Computational Methodology

Appendix 15 Computational Methodology Appendix 15 Computational Methodology Introduction This Appendix describes the process used by the risk team to determine the final loss exceedence values in the risk analysis. The process involved the

More information

U.S. ARMY CORPS OF ENGINEERS

U.S. ARMY CORPS OF ENGINEERS CORPS FACTS Regulating Mississippi River Navigation Pools U.S. ARMY CORPS OF ENGINEERS BUILDING STRONG Historical Background Federal improvements in the interest of navigation on the Mississippi River

More information

Semester Project Final Report. Logan River Flood Plain Analysis Using ArcGIS, HEC-GeoRAS, and HEC-RAS

Semester Project Final Report. Logan River Flood Plain Analysis Using ArcGIS, HEC-GeoRAS, and HEC-RAS Semester Project Final Report Logan River Flood Plain Analysis Using ArcGIS, HEC-GeoRAS, and HEC-RAS Kedric Curtis, Josh Hogge, Jordan Jarrett, Jared Justensen May 6, 2016 CEE 6190 GIS for Civil Engineers

More information

Rock Sizing for Waterway & Gully Chutes

Rock Sizing for Waterway & Gully Chutes Rock Sizing for Waterway & Gully Chutes WATERWAY MANAGEMENT PRACTICES Photo 1 Rock-lined waterway chute Photo 2 Rock-lined gully chute 1. Introduction A waterway chute is a stabilised section of channel

More information

Chapter 10 - Sacramento Method Examples

Chapter 10 - Sacramento Method Examples Chapter 10 Sacramento Method Examples Introduction Overview This chapter presents two example problems to demonstrate the use of the Sacramento method. These example problems use the SACPRE and HEC-1 computer

More information

MODELING OF LOCAL SCOUR AROUND AL-KUFA BRIDGE PIERS Saleh I. Khassaf, Saja Sadeq Shakir

MODELING OF LOCAL SCOUR AROUND AL-KUFA BRIDGE PIERS Saleh I. Khassaf, Saja Sadeq Shakir ISSN 2320-9100 11 International Journal of Advance Research, IJOAR.org Volume 1, Issue 8,August 2013, Online: ISSN 2320-9100 MODELING OF LOCAL SCOUR AROUND AL-KUFA BRIDGE PIERS Saleh I. Khassaf, Saja Sadeq

More information

MEMORANDUM. Situation. David Ford Consulting Engineers, Inc J Street, Suite 200 Sacramento, CA Ph Fx

MEMORANDUM. Situation. David Ford Consulting Engineers, Inc J Street, Suite 200 Sacramento, CA Ph Fx David Ford Consulting Engineers, Inc. 2015 J Street, Suite 200 Sacramento, CA 95811 Ph. 916.447.8779 Fx. 916.447.8780 MEMORANDUM To: Brad Moore, PE, USACE From: Nathan Pingel, PE (Lic # CA 63242), and

More information

BREACH: AN EROSION MODEL FOR EARTHEN DAM FAILURES. by D.L. Fread 1. July 1988 (Revision 1, August 1991)

BREACH: AN EROSION MODEL FOR EARTHEN DAM FAILURES. by D.L. Fread 1. July 1988 (Revision 1, August 1991) BREACH: AN EROSION MODEL FOR EARTHEN DAM FAILURES by D.L. Fread 1 July 1988 (Revision 1, August 1991) ABSTRACT. A physically based mathematical model (BREACH) to predict the breach characteristics (size,

More information

Hydraulics of bendway weirs

Hydraulics of bendway weirs River Basin Management IV 389 Hydraulics of bendway weirs C. Thornton 1, S. Abt 1, D. Baird 2 & R. Padilla 3 1 Colorado State University, Fort Collins, CO, USA 2 U.S. Bureau of Reclamation, Denver, CO,

More information

Hydraulic and Sediment Transport Modeling Strategy

Hydraulic and Sediment Transport Modeling Strategy Appendix B Hydraulic and Sediment Transport Modeling Strategy May 2014 Technical Memorandum Channel Capacity Report January 2015 San Joaquin River Restoration Program Hydraulic and Sediment Transport Modeling

More information

Probabilistic Evaluation of a Meandering Low-Flow Channel. February 24 th, UMSRS

Probabilistic Evaluation of a Meandering Low-Flow Channel. February 24 th, UMSRS Probabilistic Evaluation of a Meandering Low-Flow Channel February 24 th, 2014 2014 UMSRS 1 2 acknowledgments Low- Flow Channel (LFC) overview Proposed Diversion Channel collects runoff from: The Rush

More information

THE NEED FOR AN ADDITIONAL SPILLWAY AT THE SANFORD DAM BOILING SPRING LAKES, NC. Presentation for The Brunswick County Commissioners April 20, 2015

THE NEED FOR AN ADDITIONAL SPILLWAY AT THE SANFORD DAM BOILING SPRING LAKES, NC. Presentation for The Brunswick County Commissioners April 20, 2015 THE NEED FOR AN ADDITIONAL SPILLWAY AT THE SANFORD DAM BOILING SPRING LAKES, NC Presentation for The Brunswick County Commissioners April 20, 2015 The Sanford Dam Earth Dam constructed in 1961 Drainage

More information

Modelling Breach Formation through Embankments

Modelling Breach Formation through Embankments Modelling Breach Formation through Embankments Mohamed A. A. Mohamed, Paul G. Samuels, Mark W. Morris, Gurmel S. Ghataora 2 HR Wallingford Howbery Park, Wallingford, Oxon, OX 8BA, UK 2 School of Civil

More information

Open Channel Flow Part 2. Ch 10 Young, notes, handouts

Open Channel Flow Part 2. Ch 10 Young, notes, handouts Open Channel Flow Part 2 Ch 10 Young, notes, handouts Uniform Channel Flow Many situations have a good approximation d(v,y,q)/dx=0 Uniform flow Look at extended Bernoulli equation Friction slope exactly

More information

A STUDY OF LOCAL SCOUR AT BRIDGE PIERS OF EL-MINIA

A STUDY OF LOCAL SCOUR AT BRIDGE PIERS OF EL-MINIA A STUDY OF LOCAL SCOUR AT BRIDGE PIERS OF EL-MINIA Dr. Gamal A. Sallam 1 and Dr. Medhat Aziz 2 ABSTRACT Bridges are critical structures that require a substantial investment to construct and serve an important

More information

Chapter 7 Mudflow Analysis

Chapter 7 Mudflow Analysis Chapter 7 Mudflow Analysis 7.0 Introduction This chapter provides information on the potential and magnitude of mud floods and mudflows that may develop in Aspen due to rainfall events, snowmelt, or rain

More information

INTRODUCTION TO HYDROLOGIC MODELING USING HEC-HMS

INTRODUCTION TO HYDROLOGIC MODELING USING HEC-HMS INTRODUCTION TO HYDROLOGIC MODELING USING HEC-HMS By Thomas T. Burke, Jr., PhD, PE Luke J. Sherry, PE, CFM Christopher B. Burke Engineering, Ltd. October 8, 2014 1 SEMINAR OUTLINE Overview of hydrologic

More information

Solutions to Flooding on Pescadero Creek Road

Solutions to Flooding on Pescadero Creek Road Hydrology Hydraulics Geomorphology Design Field Services Photo courtesy Half Moon Bay Review Solutions to Flooding on Pescadero Creek Road Prepared for: San Mateo County Resource Conservation District

More information

CASE STUDIES. Introduction

CASE STUDIES. Introduction Introduction The City of Winston-Salem faces the challenge of maintaining public infrastructure (e.g., water and sewer lines, storm drains, roads, culverts and bridges) while minimizing the potential impacts

More information

Tarbela Dam in Pakistan. Case study of reservoir sedimentation

Tarbela Dam in Pakistan. Case study of reservoir sedimentation Tarbela Dam in Pakistan. HR Wallingford, Wallingford, UK Published in the proceedings of River Flow 2012, 5-7 September 2012 Abstract Reservoir sedimentation is a main concern in the Tarbela reservoir

More information

HYDROLOGIC AND HYDRAULIC REPORT FOR SR. 0522, SECTION 5BN ALONG BLACKLOG CREEK CROMWELL TOWNSHIP HUNTINGDON COUNTY. Prepared for:

HYDROLOGIC AND HYDRAULIC REPORT FOR SR. 0522, SECTION 5BN ALONG BLACKLOG CREEK CROMWELL TOWNSHIP HUNTINGDON COUNTY. Prepared for: HYDROLOGIC AND HYDRAULIC REPORT FOR SR. 0522, SECTION 5BN ALONG BLACKLOG CREEK CROMWELL TOWNSHIP Prepared for: KCI Technologies, Inc. Mechanicsburg, PA and Pennsylvania Department of Transportation Engineering

More information

A Simple Procedure for Estimating Loss of Life from Dam Failure. Wayne J. Graham, P.E. 1

A Simple Procedure for Estimating Loss of Life from Dam Failure. Wayne J. Graham, P.E. 1 A Simple Procedure for Estimating Loss of Life from Dam Failure Wayne J. Graham, P.E. 1 INTRODUCTION Evaluating the consequences resulting from a dam failure is an important and integral part of any dam

More information

The last three sections of the main body of this report consist of:

The last three sections of the main body of this report consist of: Threatened and Endangered Species Geological Hazards Floodplains Cultural Resources Hazardous Materials A Cost Analysis section that provides comparative conceptual-level costs follows the Environmental

More information

6.4 Sensitivity Tests

6.4 Sensitivity Tests 6.4 Sensitivity Tests 6.4.1 Sensitivity of Floodplain Inundation to Width of Dry Culvert The preliminary design for the Expressway based on consideration of possible future climate effects to 2090 assumed

More information

Appendix I. Dredged Volume Estimates. Draft Contractor Document: Subject to Continuing Agency Review

Appendix I. Dredged Volume Estimates. Draft Contractor Document: Subject to Continuing Agency Review Appendix I Dredged Volume Estimates Draft Contractor Document: Subject to Continuing Agency Review Interoffice Correspondence Date: April 6, 2007 To: L. Bossi (WHI) Copy: S. Thompson (WHI), B. Fidler (NNJ)

More information

STABILIZATION OF THE H&CT RAILWAY STONE DAM WALTER E. SKIPWITH, PE, JOYCE CRUM, AIA AND JOHN BAUMGARTNER, PE. Introduction.

STABILIZATION OF THE H&CT RAILWAY STONE DAM WALTER E. SKIPWITH, PE, JOYCE CRUM, AIA AND JOHN BAUMGARTNER, PE. Introduction. STABILIZATION OF THE H&CT RAILWAY STONE DAM WALTER E. SKIPWITH, PE, JOYCE CRUM, AIA AND JOHN BAUMGARTNER, PE I. A. Introduction General The Old Stone Dam is located in the upper reach of Cottonwood Creek

More information

The Use of Synthetic Floods for Defining the Regulated Volume Duration Frequency Curves for the Red River at Fargo, ND

The Use of Synthetic Floods for Defining the Regulated Volume Duration Frequency Curves for the Red River at Fargo, ND The Use of Synthetic Floods for Defining the Regulated Volume Duration Frequency Curves for the Red River at Fargo, ND Prepared by the USACE - St. Paul District Hydrology & Water Management Section June

More information

Appendix O. Sediment Transport Modelling Technical Memorandum

Appendix O. Sediment Transport Modelling Technical Memorandum Appendix O Sediment Transport Modelling Technical Memorandum w w w. b a i r d. c o m Baird o c e a n s engineering l a k e s design r i v e r s science w a t e r s h e d s construction Final Report Don

More information

Kaskaskia Morphology Study Headwaters to Lake Shelbyville

Kaskaskia Morphology Study Headwaters to Lake Shelbyville Kaskaskia Morphology Study Headwaters to Lake Shelbyville KWA Mini Summit 5 March 2012 1 Kaskaskia Morphology Study Headwaters to Lake Shelbyville Conducted by U.S. Army Corps of Engineers, St. Louis District

More information

Advanced /Surface Hydrology Dr. Jagadish Torlapati Fall 2017 MODULE 2 - ROUTING METHODS

Advanced /Surface Hydrology Dr. Jagadish Torlapati Fall 2017 MODULE 2 - ROUTING METHODS Routing MODULE - ROUTING METHODS Routing is the process of find the distribution of flow rate and depth in space and time along a river or storm sewer. Routing is also called Flow routing or flood routing.

More information

Rucker Pond. Background

Rucker Pond. Background Rucker Pond Background The Rucker Basin consists of two subbasins (East and West) that drain to a single area known as Rucker Pond. Both subbasins have the same hydraulic parameters, but have different

More information

Pompton Lakes Dam Downstream Effects of the Floodgate Facility. Joseph Ruggeri Brian Cahill Michael Mak Andy Bonner

Pompton Lakes Dam Downstream Effects of the Floodgate Facility. Joseph Ruggeri Brian Cahill Michael Mak Andy Bonner Pompton Lakes Dam Downstream Effects of the Joseph Ruggeri Brian Cahill Michael Mak Andy Bonner ASFPM 2013: Overview Page 2 Overview Page 3 Overview Page 4 Overview Page 5 Overview - Historical Pompton

More information

Chapter 7 Mudflow Analysis

Chapter 7 Mudflow Analysis Chapter 7 Mudflow Analysis 7.0 Introduction This chapter provides information on the potential and magnitude of mud floods and mudflows that may develop in Aspen due to rainfall events, snowmelt, or rain

More information

Open Channel Hydraulics III - Sharpcrested

Open Channel Hydraulics III - Sharpcrested PDHonline Course H140 (2 PDH) Open Channel Hydraulics III - Sharpcrested Weirs Instructor: Harlan H. Bengtson, Ph.D., PE 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone

More information

CCR Rule Annual Inspection Report (cont.) 2

CCR Rule Annual Inspection Report (cont.) 2 The inspection findings consisted of maintenance items and items that were not observed to be signs or potential signs of significant structural weakness. No deficiencies or disrupting conditions that

More information

3301 East 120 th Avenue Assited Living & Memory Care

3301 East 120 th Avenue Assited Living & Memory Care UTILITY REPORT FOR 3301 East 120 th Avenue Assited Living & Memory Care 1 st Submittal January 23, 2016 2 nd Submittal March 04, 2016 Prepared for: 3301 E. 120 th Ave, LLC. 8200 E. Maplewood Ave., Suite

More information

H4: Steady Flow through a Channel Network

H4: Steady Flow through a Channel Network August 9, Chapter 7 H4: Steady Flow through a Channel Network Contents 7. Problem Specification............................. 7-7. Background................................... 7-3 7.3 Contra Costa Water

More information

Flow estimations through spillways under submerged tidal conditions

Flow estimations through spillways under submerged tidal conditions Computational Methods and Experimental Measurements XIII 137 Flow estimations through spillways under submerged tidal conditions P. D. Scarlatos 1, M. Ansar 2 & Z. Chen 2 1 Department of Civil Engineering

More information

Applying GIS to Hydraulic Analysis

Applying GIS to Hydraulic Analysis Texas A&M University Department of Civil Engineering CVEN689 Applications of GIS to Civil Engineering Instructor: Francisco Olivera, Ph.D., P.E. Applying GIS to Hydraulic Analysis Lim, Chae Kwan April

More information

Rock Sizing for Small Dam Spillways

Rock Sizing for Small Dam Spillways Rock Sizing for Small Dam Spillways STORMWATER MANAGEMENT PRACTICES Photo 1 Rock-lined spillway on a construction site sediment basin Photo 2 Rock-lined spillway on a small farm dam 1. Introduction A chute

More information

DRAFT Design Hydraulic Study. Bridge 04C-0055, Mattole Road Bridge over Mattole River at Honeydew. Humboldt County. Prepared for:

DRAFT Design Hydraulic Study. Bridge 04C-0055, Mattole Road Bridge over Mattole River at Honeydew. Humboldt County. Prepared for: DRAFT Design Hydraulic Study Bridge 04C-0055, Mattole Road Bridge over Mattole River at Honeydew Humboldt County Prepared for: Morrison Structures Incorporated 1890 Park Marina Drive, Suite 104 Redding,

More information

Analysis of Hydraulic Impacts on the Schuylkill River

Analysis of Hydraulic Impacts on the Schuylkill River Analysis of Hydraulic Impacts on the Schuylkill River Manayunk Sewer Basin Construction Project and the Venice Island Recreation Center Reconstruction Project Venice Island, Manayunk, Philadelphia, PA

More information

Results of the Sava River Model

Results of the Sava River Model Results of the Sava River Model Jamie G. James, P.E. Nashville District September 2010 US Army Corps of Engineers BUILDING STRONG Discussion Outline Study Goals Model Limitations HEC-RAS Model Results

More information

USGS Flood Inundation Mapping of the Suncook River in Chichester, Epsom, Pembroke and Allenstown, New Hampshire

USGS Flood Inundation Mapping of the Suncook River in Chichester, Epsom, Pembroke and Allenstown, New Hampshire USGS Flood Inundation Mapping of the Suncook River in Chichester, Epsom, Pembroke and Allenstown, New Hampshire NH Water & Watershed Conference Robert Flynn, USGS NH-VT Water Science Center March 23, 2012

More information

Birecik Dam & HEPP Downstream River Arrangement R. Naderer, G. Scharler Verbundplan GmbH, 5021 Salzburg, Austria

Birecik Dam & HEPP Downstream River Arrangement R. Naderer, G. Scharler Verbundplan GmbH, 5021 Salzburg, Austria Birecik Dam & HEPP Downstream River Arrangement R. Naderer, G. Scharler Verbundplan GmbH, 5021 Salzburg, Austria e-mail: scharlerg@verbund.co.at Abstract Birecik Dam & HEPP on the Euphrates river in Turkey

More information

Villages at Riverdale Thornton, CO

Villages at Riverdale Thornton, CO FINAL UTILITY REPORT Villages at Riverdale Thornton, CO October 14, 216 Revised: March 29, 217 JN: 1539 Prepared for: PCS Group, Inc. 11 16 th Street #3 B-18 Denver, CO 8265 P: 33.531.495 Prepared by:

More information

Eastlake Assited Living & Memory Care

Eastlake Assited Living & Memory Care UTILITY REPORT FOR Eastlake Assited Living & Memory Care 1 st Submittal January 23, 2016 2 nd Submittal March 04, 2016 June 7, 2016 Final Submittal August 08, 2016 Prepared for: 3301 E. 120 th Ave, LLC.

More information

Stage Discharge Tabulation for Only Orifice Flow

Stage Discharge Tabulation for Only Orifice Flow Stage Discharge Tabulation for Only Orifice Flow DEPTH STAGE DISCHARGE (meters) (feet) (meters) (feet) (m 3 /s) (ft 3 /s) 0 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 2.00 0.7 1.3 2.0 2.6 3.3 3.9 4.6

More information

design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards.

design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards. design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards. In addition to the field inspection, Associated Engineers, Inc.

More information

B-1. Attachment B-1. Evaluation of AdH Model Simplifications in Conowingo Reservoir Sediment Transport Modeling

B-1. Attachment B-1. Evaluation of AdH Model Simplifications in Conowingo Reservoir Sediment Transport Modeling Attachment B-1 Evaluation of AdH Model Simplifications in Conowingo Reservoir Sediment Transport Modeling 1 October 2012 Lower Susquehanna River Watershed Assessment Evaluation of AdH Model Simplifications

More information

7.3 Sediment Delivery Analysis

7.3 Sediment Delivery Analysis 7.3 Sediment Delivery Analysis In order to evaluate potential changes in sedimentation patterns that could occur due to impacts from the FCP and LPP alignments, sediment assessment models were constructed

More information

3.0 TECHNICAL FEASIBILITY

3.0 TECHNICAL FEASIBILITY 3.0 TECHNICAL FEASIBILITY 3.1 INTRODUCTION To enable seasonal storage and release of water from Lake Wenatchee, an impoundment structure would need to be constructed on the lake outlet channel. The structure

More information

Project (Project No. US-CA-62-2) Maintenance Inspection and Reports (Subtask 14.1) Inspection Report No.2

Project (Project No. US-CA-62-2) Maintenance Inspection and Reports (Subtask 14.1) Inspection Report No.2 MEMORANDUM TO: FROM: Jim Well, Ducks Unlimited Mike Harvey, PhD, PG SUBJECT: M&T/ Llano Seco Fish Screen Project (Project No. US-CA-62-2) Maintenance Inspection and Reports (Subtask 14.1) Inspection Report

More information

4.17 Spain. Catalonia

4.17 Spain. Catalonia 4.17 Spain Catalonia In Spain, inundation studies are the responsibility of the respective Hydrographic Confederations of each river basin (River Basin Authorities). The actual status of inundation studies

More information

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area.

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area. Sediment Trench SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils [1] Performance of

More information

Dam Break Analysis Using HEC-RAS and HEC-GeoRAS A Case Study of Ajwa Reservoir

Dam Break Analysis Using HEC-RAS and HEC-GeoRAS A Case Study of Ajwa Reservoir Journal of Water Resources and Ocean Science 2016; 5(6): 108-113 http://www.sciencepublishinggroup.com/j/wros doi: 10.11648/j.wros.20160506.15 ISSN: 2328-7969 (Print); ISSN: 2328-7993 (Online) Case Report

More information

Lecture Note for Open Channel Hydraulics

Lecture Note for Open Channel Hydraulics Chapter -one Introduction to Open Channel Hydraulics 1.1 Definitions Simply stated, Open channel flow is a flow of liquid in a conduit with free space. Open channel flow is particularly applied to understand

More information

Pequabuck River Flooding Study and Flood Mitigation Plan The City of Bristol and Towns of Plainville and Plymouth, CT

Pequabuck River Flooding Study and Flood Mitigation Plan The City of Bristol and Towns of Plainville and Plymouth, CT Pequabuck River Flooding Study and Flood Mitigation Plan The City of Bristol and Towns of Plainville and Plymouth, CT Raymond Rogozinski and Maged Aboelata The City of Bristol and Towns of Plainville and

More information

Saganashkee Slough - McMahon Woods Section 506 Great Lakes Fishery & Ecosystem Restoration Study

Saganashkee Slough - McMahon Woods Section 506 Great Lakes Fishery & Ecosystem Restoration Study 2015 Saganashkee Slough - McMahon Woods Section 506 Great Lakes Fishery & Ecosystem Restoration Study Appendix B Civil Design USACE Chicago District August 2015 TABLE OF CONTENTS INTRODUCTION... 3 General...

More information

Coarse Sediment Traps

Coarse Sediment Traps Coarse Sediment Traps SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils [2] Type 3 System Supplementary Trap Dispersive Soils [1] Though primarily

More information

Rock & Aggregate Drop Inlet Protection

Rock & Aggregate Drop Inlet Protection Rock & Aggregate Drop Inlet Protection SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System Supplementary Trap Dispersive Soils

More information

How Do Human Impacts and Geomorphological Responses Vary with Spatial Scale in the Streams and Rivers of the Illinois Basin?

How Do Human Impacts and Geomorphological Responses Vary with Spatial Scale in the Streams and Rivers of the Illinois Basin? How Do Human Impacts and Geomorphological Responses Vary with Spatial Scale in the Streams and Rivers of the Illinois Basin? Bruce Rhoads Department of Geography University of Illinois at Urbana-Champaign

More information

Two-Dimensional Simulation of Truckee River Hydrodynamics

Two-Dimensional Simulation of Truckee River Hydrodynamics Two-Dimensional Simulation of Truckee River Hydrodynamics by Stephen H. Scott PURPOSE: The purpose of this Coastal and Hydraulics Engineering Technical Note (CHETN) is to demonstrate the use of multidimensional

More information

Running Water Earth - Chapter 16 Stan Hatfield Southwestern Illinois College

Running Water Earth - Chapter 16 Stan Hatfield Southwestern Illinois College Running Water Earth - Chapter 16 Stan Hatfield Southwestern Illinois College Hydrologic Cycle The hydrologic cycle is a summary of the circulation of Earth s water supply. Processes involved in the hydrologic

More information

June 9, R. D. Cook, P.Eng. Soils Engineer Special Services Western Region PUBLIC WORKS CANADA WESTERN REGION REPORT ON

June 9, R. D. Cook, P.Eng. Soils Engineer Special Services Western Region PUBLIC WORKS CANADA WESTERN REGION REPORT ON PUBLIC WORKS CANADA WESTERN REGION REPORT ON GEOTECHNICAL INVESTIGATION PROPOSED MARTIN RIVER BRIDGE MILE 306.7 MACKENZIE HIGHWAY Submitted by : R. D. Cook, P.Eng. Soils Engineer Special Services Western

More information

Modeling Great Britain s Flood Defenses. Flood Defense in Great Britain. By Dr. Yizhong Qu

Modeling Great Britain s Flood Defenses. Flood Defense in Great Britain. By Dr. Yizhong Qu Modeling Great Britain s Flood Defenses AIRCurrents Editor s note: AIR launched its Inland Flood Model for Great Britain in December 2008. The hazard module captures the physical processes of rainfall-runoff

More information

Sediment Trap. A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff through a stabilized spillway.

Sediment Trap. A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff through a stabilized spillway. Sediment Trap SC-15 Source: Caltrans Construction Site Best Management Practices Manual, 2003. Description A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff

More information

Big Rivers Electric Corporation Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Impoundment Liner Assessment Report

Big Rivers Electric Corporation Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Impoundment Liner Assessment Report Big Rivers Electric Corporation Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Impoundment Liner Assessment Report CCR Surface Impoundment Information Name: Operator:

More information